Loading...
HomeMy WebLinkAboutASRC-BRW-RSA Barrow FS 1 2012-EE Richard S. Armstrong, PE, LLC Mechanical/Electrical Engineer Comprehensive Energy Audit of Barrow Fire Station #1 1040 Kiogak, Barrow Project # ASRC%BRW%RSA%07 Prepared for: The North Slope Borough Department of Public Works August 8, 2011 Prepared by: Richard S. Armstrong, PE, LLC 2321 Merrill Field Drive, C%6 Anchorage, Ak 99501 Barrow Fire Station #1 Comprehensive Energy Audit 2 TABLE OF CONTENTS 1. Executive Summary 4 2. Audit and Analysis Background 7 3. Acknowledgements 8 4. Building Description & Function 10 5. Historic Energy Consumption 10 6. Energy Efficiency Measures Considered 11 7. Interactive Effects of Projects 11 8. Loan Program 12 Appendix A: Photos Appendix B: AkWarm5C Report Appendix C: Equipment Schedules Appendix D: Building Plan Appendix E: Lighting Plan Appendix F: Mechanical Schematic Submitted by: _______________________________ Richard S. Armstrong, PE, CEM, CEA Date:__________________________ Barrow Fire Station #1 Comprehensive Energy Audit 3 REPORT DISCLAIMERS The information contained in this report, including any attachments, is intended solely for use by the building owner and the AHFC. No others are authorized to disclose, copy, distribute or retain this report, in whole or part, without written authorization from Richard S. Armstrong, PE, LLC, 2321 Merrill Field Drive, C*6, Anchorage, Ak 99501. Additionally, this report contains recommendations that, in the opinion of the auditor, will cause the owner to realize energy savings over time. All recommendations must be designed by a registered engineer, licensed in the State of Alaska, in the appropriate discipline. Lighting recommendations should all be first reviewed by running a lighting analysis to assure that the recommended lighting upgrades will comply with State of Alaska Statue as well as IES recommendations. Payback periods may well vary from those forecast due to the uncertainty of the final installed design, configuration, equipment selected, and installation costs of recommended Energy Efficiency Measures (EEMs), or the operating schedules and maintenance provided by the owner. Furthermore, EEMs are typically interactive, so implementation of one EEM may impact the cost savings from another EEM. Neither the auditor, Richard S. Armstrong, PE, LLC, AHFC, or others involved in preparation of this report will accept liability for financial loss due to EEMs that fail to meet the forecasted payback periods. This audit meets the criteria of an Investment Grade Audit (IGA) per the Association of Energy Engineers definition, and is valid for one year. The life of the IGA may be extended on a case*by*case basis, at the discretion of the AHFC. IGSs are the property of the State, and may be incorporated into AkWarm* C, the Alaska Energy Data Inventory (ARIS), or other state and/or public information system Barrow Fire Station #1 Comprehensive Energy Audit 4 Investment Grade Energy Audit Barrow Fire Station #1 1. Executive Summary: The Barrow Fire Station #1 is estimated to have been originally constructed in 1979, but it underwent a significant addition and upgrade in 1990 based on plans for the remodel/addition project. The facility contains four apparatus bays, as well as an office, training room, and break room. The building is in generally good condition. The 2009 and 2010 annual utility energy consumption reported by BUECI and collected as benchmark data by Nortec Engineering is displayed in Table 1 below: Table 1 2009 2009 2010 2010 Utility Consumption Cost/Year Consumption Cost/Year Electricity*kWh 2,729 $8,580 3,156 $9,898 Natural Gas*CCF 11,484 $3,549 9,404 $2,915 Ttl Energy Costs $12,129 $12,813 A benchmark measure of energy use relative to other similar function buildings in the area is the Energy Use Index (EUI), which takes the total annual energy used by the facility divided by the square footage area of the building, for a value expressed in terms of kBTU/SF. This number can then be compared to other buildings to see if it is about average, higher or lower than similar buildings in the area. Likewise, the Energy Cost Index (ECI) is the cost of all energy used by the building expressed in $/SF of building area. The comparative values for the subject building are listed in Table 2 below: Table 2 Fire Station #1 Barrow Avg Fire Station #2 Energy Use Index (EUI) kBTU/SF 207 211 175 Energy Cost Index (ECI) $/SF $1.92 $1.68 $1.51 Various Energy Efficiency Measures (EEMs) have been analyzed for this building to determine if they would be applicable for energy savings with reasonably good payback periods. Those EEMs that have a payback period of less than 8 years, or those that are Barrow Fire Station #1 Comprehensive Energy Audit 5 recommended for code compliance, life cycle replacement, or other reasons are also included. Also, where a lighting upgrade is recommended from T*12 lamps with magnetic ballasts to T*8 lamps with electronic ballasts, then the entire facility should be relamped and reballasted to maintain a standard lighting parts inventory, regardless of the payback. For example, a storage room that is infrequently used may not show a very good payback for a lighting upgrade, but consistency dictates a total upgrade. Specific EEMs recommended for this facility are detailed in the attached AkWarm Energy Audit Report along with specific payback times, as well as estimated installation costs and estimated energy savings. The higher priority items are summarized below: a. Lighting Upgrades: In general, all of the T*12 flourescent lamps, and all of the magnetic ballasts should be replaced with new T*8 lamps with electronic ballasts. Typical savings in power consumption varies 10*30% with this upgrade. b. Lighting Control Upgrades: Many lights were found to be left on with nobody in the space. Occupant controls can sense the presence of workers, and turn the lights on. The controller can then turn the lights off after a programmed time period of no occupancy. These controls can reduce total kWh consumption for the lighting in the order of 30* 90%, depending on the amount of time the lights are manually left on. c. Exterior Lighting Upgrades: The exterior high pressure sodium lights operate during periods of darkness, which is about half of a year. It is estimated that the use of LED exterior lights can reduce the power consumption by 60%. d. Air Handler Unit Cycling: The AHU*1 presently operates 24/7. The purpose of the AHU*1 is primarily to ventilate the training area, as well as the adjoining break room and office. The new Fire Station 2 has a larger training area, and has generally replaced the function of this space. The intent of this EEM is to only start the AHU*1 when persons are occupying the training room. The smaller adjacent break room can cause the AHU*1 to start with proper placement and selection of the occupancy sensor. The Barrow Fire Station #1 Comprehensive Energy Audit 6 office has an operable window, so it should not need additional ventilation given the size of the space. e. Setback Thermostats in Office and Appartus Room: The thermostats were found to be set to 75 degrees F, 24/7. It is recommended that lockable setback thermostats be installed and programmed for occupied temperatures of 72 deg F, and unoccupied temperatures of 55 deg F. This has an estimated payback of 0.8 years for the apparatus room, and 2.1 years for the office. f. Headbolt Heater Controls: There are retrofit headbolt heater receptacles that have microprocessors to cycle the power on and off in response to the outside air temperature. This is estimated to have a payback of 2.8 years. g. Air Tightening: The last major upgrade to the building was in 1990, 21 years ago. It is recommended that all of the doors be tightened with new weather stripping to reduce infiltration. This EEM is estimated to have a payback of 9.9 years. h. Refrigerator: Newer Energy Star refrigerators use about 411 watts, compared to 1990 versions that used 1,044 watts. While this would have a 15 year payback, it is still recommended due to the relatively low cost and quick payback. In addition to EEMs, various Energy Conservation Measures (ECMs) are recommended since they are policies or procedures that are followed by management and employees that require no capital outlay. Examples of recommended ECMs for this facility include: • Turn off lights when leaving a room that is not controlled by an occupancy sensor that automatically turns off lights. • Turn off computers, monitors, printers, faxes, coffee makers, etc when leaving the office for the day. • Keep overhead doors closed except when they are required to be open for movement of vehicles. The 29 priority recommendations in the detailed report estimate to save $6,327/year, with an installed cost of $31,811. This does not include design or CA services, but overall it does indicate a cost effective energy savings program. Barrow Fire Station #1 Comprehensive Energy Audit 7 2. Audit and Analysis Background: a. Program Description: This audit included services to identify, develop, and evaluate energy efficiency measures at the subject building. The scope of this project included evaluating the building shell, lighting, other electrical systems, and heating, ventilating, and air conditioning (HVAC) equipment. Measures were selected such that an overall simple payback period of 8 years or less could be achieved. b. Audit Description and Methodology: Preliminary audit information was gathered in preparation for the site survey, including benchmark utility consumption data, floor and lighting plans, and equipment schedules where available. A site visit is then performed to inventory and evaluate the actual building condition, including: i. Building envelope (roof, windows, etc) ii. Heating, ventilating, and air conditioning iii. Lighting systems and controls iv. Building specific equipment v. Plumbing systems c. Method of Analysis: The information gathered prior to the site visit and at the site visit is entered into AkWarm*C, an energy modeling developed for Alaska Housing Finance Corporation (AHFC) specifically to identify forecasted energy consumption which can be compared to actual energy consumption. AkWarm*C also has some pre*programmed EEM retrofit options that can be analyzed with energy savings forecasted based on occupancy schedules, utility rates, building construction type, building function, existing conditions, and climatic data that is already uploaded to the program based on the zip code of the building. When new equipment is proposed, energy consumption is calculated based on manufacturer’s cataloged information. Cost savings are calculated based on the historical energy costs for the building. Installation costs include labor and equipment to estimate the full up*front investment required to implement a change, but design and construction management Barrow Fire Station #1 Comprehensive Energy Audit 8 costs are excluded. Costs are derived from Means Cost Data, industry publications, experience of the auditor, local contractors and equipment suppliers. Haakensen Electric was consulted for some of the lighting retrofit costs. Maintenance savings are calculated were applicable and are added to the energy savings for each EEM. The cost and savings are applied and a simple payback and simple return on investment (ROI) is calculated. The simple payback is based on the number of years that it takes for the savings to pay back the net installation cost (Net Installation divided by Net Savings.) A simple life*time calculation is shown for each EEM. The life* time for each EEM is estimated based on the typical life of the equipment being replaced or altered. The energy savings is extrapolated throughout the life*time of the EEM. The total energy savings is calculated as the total life*time multiplied by the yearly savings. d. Limitations of the Study: All results are dependent on the quality of input data provided, and can only act as an approximation. In some instances, several methods may achieve the identified savings. This report is not intended as a final design document. A design professional, licensed to practice in Alaska and in the appropriate discipline, who is following the recommendations, shall accept full responsibility and liability for the results. Budgetary estimates for engineering and design of these projects in not included in the cost estimate for each measure, but these costs generally run around 15% of the cost of the work. 3. Acknowledgements: We wish to acknowledge the help of numerous individuals who have contributed information that was used to prepare this report, including: a. Alaska Housing Finance Corporation (Grantor): AHFC provided the grant funds, contracting agreements, guidelines, and technical direction for providing the audits. AHFC reviewed and approved the final short list of buildings to be Barrow Fire Station #1 Comprehensive Energy Audit 9 audited based on the recommendation of the Technical Service Provider (TSP). b. North Slope Borough (Owner): The NSB provided building sizing information, two years energy billing data, building schedules and functions, as well as building age. c. Nortech Engineering (Benchmark TSP): Nortech Engineering compiled the data received from the NSB and entered that data into the statewide building database, called the Alaska Retrofit Information System (ARIS). d. Richard S. Armstrong, PE, LLC (Audit TSP): This is the TSP who was awarded the projects in the Arctic Slope Regional Corporation, Bering Straits area, and the Nana area. The firm gathered all relevant benchmark information provided to them by Nortech, cataloged which buildings would have the greatest potential payback, and prioritized buildings to be audited based on numerous factors, including the Energy Use Index (EUI), the Energy Cost Index (ECI), the age of the building, the size of the building, the location of the building, the function of the building, and the availability of plans for the building. They also trained their selected sub*contracted auditors, assigned auditors to the selected buildings, and performed quality control reviews of the resulting audits. They prepared a listing of potential EEMs that each auditor must consider, as well as the potential EEMs that the individual auditor may notice in the course of his audit. Richard S. Armstrong, PE, LLC also performed some of the audits to assure current knowledge of existing conditions. e. RSA Engineering, Inc (Energy Auditor): This firm specializes in mechanical and electrical design, and has trained three of its mechanical engineers to perform specific energy audits. All three are Certified Energy Auditors, and have received additional training from Richard S. Armstrong, PE, LLC to acquire further specific information regarding audit requirements and potential EEM applications. Barrow Fire Station #1 Comprehensive Energy Audit 10 f. Energy Audits of Alaska: This firm has been selected to provide audits under this contract in addition to RSA Engineering. The firm has two mechanical engineers, certified as energy auditors or professional engineers. 4. Building Description and Function: The subject building is called the Barrow Fire Station #1. It was originally constructed in 1979, and had a substantial addition constructed in 1990. The new addition housed the apparatus room, and the original part of the building became an office and training center, with toilet and shower rooms. The total size of the building, including the addition is 6,480 SF. The building has one story. a. Heating System: The building heating system consists of four Weil McLain cast iron “Gold” boilers, fired sequentially. Hot glycol is distributed to terminal units, unit heaters, and the air handler coil through copper pipe. b. Ventilation System: The office/training side of the building is ventilated with an 1100 CFM air handler unit located above the toilet room. The Apparatus room equipment is exhausted with a single wall outlet exhaust fan rated at 2,952 CFM, connected to exhaust tailpipe adaptors. The toilet room and shower areas are each exhausted with individual 88 CFM exhaust fans. c. Plumbing System: There is one toilet and one steam style shower along with one lav for hand washing. d. Domestic Hot: How water is generated using an electric hot water heater, located in the mechanical room. e. Lighting: Typical lighting throughout the building is comprised of T*12 fluorescent fixtures, using magnetic ballasts. Exterior lighting utilizes 250 watt high pressure sodium (HPS) wall packs, in addition to existing lighting on the older section. 5. Historic Energy Consumption: Energy consumption is modeled within the AkWarm*C program. The program only analyzes 12 months of data, so where 24 months of data are available, the data is averaged to provide more accuracy. The energy consumption Barrow Fire Station #1 Comprehensive Energy Audit 11 data is presented and graphed in the attached AkWarm*C program results. Energy consumption was analyzed using two factors: the Energy Cost Index (ECI) and the Energy Use Index (ECU). The energy cost index takes the average cost of gas and electrical energy over the surveyed period of time (typically 2 years) and averages the cost, divided by the square footage of the building. The ECI for this building is $ 1.92, and the average ECI for all buildings in Barrow that were surveyed is $ 1.68/SF. Fire Station #2, a newer facility in adjacent Browerville has an ECI of $1.51. The energy use index (ECU) is the total average electrical and heating energy consumption per year expressed in thousands of BTUs/SF. The average ECU for all buildings in Barrow that were surveyed is 211 kbtu/sf, and the EUI for this building is 207 kbtu/sf, compared to 175 for Fire Station #2. 6. Energy Efficiency Measures considered or recommended: The building was examined for application of a multitude of potential EEMs that are discussed below. Those EEMs that appear to have an application for the subject building are further analyzed for estimated payback periods, either within the AkWarm*C program or separately within this report. The accuracy of the cost estimates and paybacks varies significantly due to a multitude of conditions, but is estimated to be approximately +/* 25%. Assumptions made regarding energy costs and the life of the EEM, noting that post* construction measurement and verification are based on energy savings, not energy cost savings. Many of the selected EEMs are analyzed within the AkWarm*C program using the schedules and estimated costs input into the model. Some of the other EEMs are not modeled within AkWarm*C, and are individually discussed within this report. 7. Interactive Effects of Projects: The AkWarm*C program calculates savings assuming that all recommended EEM are implemented. If some EEMs are not implemented, savings for the remaining EEMs will be affected, in some cases positively, and in others, negatively. For example, if the fan motors are not replaced Barrow Fire Station #1 Comprehensive Energy Audit 12 with premium efficiency motors, then the savings for the project to install variable speed drives (VFDs) on the fans will be increased. In general, all projects were evaluated sequentially so that energy savings associated with one EEM would not be attributed to another EEM as well. For example, the night setback EEM was analyzed using the fan and heating load profile that will be achieved after installation of the VFD project is completed. By modeling the recommended projects sequentially, the analysis accounts for interactive effects between the EEMs and does not “double count” savings. Interior lighting, plug loads, facility equipment, and occupants generate heat within the building. When the building is in cooling mode, these contribute to the overall cooling demands of the building; therefore lighting efficiency improvements will reduce cooling requirements on air conditioned buildings. Conversely, lighting efficiency improvements are anticipated to increase heating requirements slightly. Heating penalties are included in the lighting project analysis that is performed by AkWarm*C. 8. Loan Program: The Alaska Housing Finance Corporation (AHFC) Alaska Energy Efficiency Revolving Loan Fund (AEERLF) is a State of Alaska program enacted by the Alaska Sustainable Energy Act (senate Bill 220, A.S. 18.56.855, “Energy Efficiency Revolving Loan Fund). The AEERLF will provide loans for energy efficiency retrofits to public facilities via the Retrofit Energy Assessment for Loan System (REAL). As defined in 15 AAC 155.605, the program may finance energy efficiency improvements to buildings owned by: a. Regional educational attendance areas; b. Municipal governments, including political subdivisions of municipal governments; c. The University of Alaska; d. Political subdivisions of the State of Alaska, or e. The State of Alaska Native corporations, tribal entities, and subsidiaries of the federal government are not eligible for loans under this program. Barrow Fire Station #1 Comprehensive Energy Audit 13 Appendix A: Photos Appendix B: AkWarm5C Report Appendix C: Equipment Schedule Appendix D: Building Plan Appendix E: Lighting Plan Appendix F: Mechanical Schedule Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 1 ENERGY AUDIT REPORT – PROJECT SUMMARY General Project Information PROJECT INFORMATION AUDITOR INFORMATION Building: Barrow Fire Department Auditor Company: Richard S. Armstrong, PE, LLC Address: 1040 Koigak Auditor Name: Richard S. Armstrong City: Barrow Auditor Address: 2321 Merrill Field Drive C-6 Anchorage, Ak 99501 Client Name: Harold Snowball Client Address: PO Box 69 Barrow, Alaska 99723 Auditor Phone: (907) 229-0331 Auditor FAX: Client Phone: (907) 852-0213 Auditor Comment: Client FAX: Design Data Building Area: 6,848 square feet Design Heating Load: Design Loss at Space: 206,247 Btu/hour with Distribution Losses: 206,247 Btu/hour Plant Input Rating assuming 82.0% Plant Efficiency and 25% Safety Margin: 314,401 Btu/hour Note: Additional Capacity should be added for DHW load, if served. Typical Occupancy: 2 people Design Indoor Temperature: 75 deg F (building average) Actual City: Barrow Design Outdoor Temperature: -41 deg F Weather/Fuel City: Barrow Heating Degree Days: 20,370 deg F-days Utility Information Electric Utility: Barrow Utilities - elec - Commercial - Sm Natural Gas Provider: Barrow Utilities & Electric-gas - Commercial - Sm Average Annual Cost/kWh: $0.098/kWh Average Annual Cost/ccf: $0.291/ccf Annual Energy Cost Estimate Description Space Heating Space Cooling Water Heating Lighting Other Electrical Cooking Clothes Drying Ventilation Fans Service Fees Total Cost Existing Building $3,080 $0 $17 $5,463 $3,631 $0 $0 $314 $391 $12,997 With Proposed Retrofits $1,958 $0 $18 $2,630 $1,616 $0 $0 $17 $391 $6,669 SAVINGS $1,122 $0 -$1 $2,832 $2,015 $0 $0 $297 $0 $6,327 Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 2 $0 $2,000 $4,000 $6,000 $8,000 $10,000 $12,000 $14,000 Existing Retrofit Service Fees Ventilation and Fans Space Heating Space Cooling Refrigeration Other Electrical Lighting Domestic Hot Water Cooking Clothes Drying Annual Energy Costs by End Use $0 $2,000 $4,000 $6,000 $8,000 $10,000 $12,000 $14,000 Existing Retrofit Natural Gas Electricity Annual Energy Costs by Fuel $0 $500 $1,000 $1,500 $2,000 Floor WallDoor Window Ceiling Air Existing Retrofit Annual Space Heating Cost by Component Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 3 PRIORITY LIST – RECOMMENDED ENERGY EFFICIENCY MEASURES Rank Feature Recommendation Annual Energy Savings Installed Cost SIR Payback (Years) 1 Other Electrical: Computers, monitors, printers Improve Manual Switching $447 $10 284.53 0 2 Ventilation Cycle fan to only operate when occupancy sensor in training room occupancy sensor should be installed that detects occupant and starts AHU-1 and turns on lights since space is rarely used. $1,248 $500 31.50 0.4 3 Setback Thermostat: Equipment Storage Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Equipment Storage space. $249 $200 15.84 0.8 4 Setback Thermostat: Office Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Office space. $93 $200 5.92 2.1 5 Other Electrical: AHU Fan Remove Manual Switching and Add new Other Controls $240 $350 4.36 1.5 6 Other Electrical: Building hydronic Circulator Improve Manual Switching $151 $350 2.75 2.3 7 Lighting: Equipment Storage Replace with 35 FLUOR (2) T8 8' F96T8/HO 86W Standard Program StdElectronic and Remove Manual Switching and Add new Multi-Level Switch $1,118 $5,786 2.36 5.2 8 Other Electrical: Head Bolt Heaters Remove Manual Switching and Add new Other Controls $1,074 $3,000 2.29 2.8 9 Lighting: Office 107 Replace with 4 FLUOR (4) T8 4' F32T8 32W Standard (2) Program HighEfficElectronic and Remove Manual Switching and Add new Occupancy Sensor, Manual Dimmer $102 $750 1.47 7.4 Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 4 PRIORITY LIST – RECOMMENDED ENERGY EFFICIENCY MEASURES Rank Feature Recommendation Annual Energy Savings Installed Cost SIR Payback (Years) 10 Lighting: Equipment Storage - Night Lights Replace with 5 FLUOR (2) T8 8' F96T8/HO 86W Standard Program StdElectronic $76 $630 1.47 8.3 11 Lighting: Mechanical Room Lighting Room 112 Remove Manual Switching and Add new Occupancy Sensor $41 $350 1.42 8.6 12 Lighting: Exterior Lights Replace with 6 LED 100W Module StdElectronic $825 $8,000 1.27 9.7 13 Lighting: Office/Reception #114-115 Fluorescent Remove Manual Switching and Add new Occupancy Sensor, Multi-Level Switch $31 $350 1.07 11.5 14 Lighting: Corridor # 108 Replace with 4 FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic and Remove Manual Switching and Add new Occupancy Sensor $64 $850 0.92 13.3 15 Air Tightening Perform air sealing to reduce air leakage by 20%. $148 $1,500 0.89 10.2 16 Lighting: Training Room 113 Replace with 17 FLUOR (4) T8 4' F32T8 32W Standard (2) Program StdElectronic and Remove Manual Switching and Add new Occupancy Sensor and Improve Multi-Level Switch $361 $3,350 0.69 9.3 17 Lighting: Projector room #115 - Incandescent Replace with 2 FLUOR CFL, A Lamp 15W $3 $50 0.65 18.9 18 Refrigeration: Household refrigerator Replace with Energy Star Reefer $54 $800 0.43 14.9 19 Lighting: Mechanical Room Lighting Room 112 Replace with 2 FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic $3 $250 0.15 83.9 20 Lighting: Office/Reception #114-115 Fluorescent Replace with 2 FLUOR (4) T8 4' F32T8 32W Standard (2) Program HighEfficElectronic $4 $450 0.11 112.5 Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 5 PRIORITY LIST – RECOMMENDED ENERGY EFFICIENCY MEASURES Rank Feature Recommendation Annual Energy Savings Installed Cost SIR Payback (Years) 21 Lighting: Storage 101, 102 Remove Manual Switching and Add new Occupancy Sensor $2 $350 0.04 157.1 22 Lighting: Dressing/ Shower # 110, 111 Replace with 2 FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic $1 $250 0.03 352.6 23 Lighting: Bathroom #109 Replace with FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic $0 $125 0.02 701.4 24 Lighting: Storage 101, 102 Replace with 4 FLUOR (3) T8 4' F32T8 32W Standard Program HighEfficElectronic $0 $450 0.00 4114.3 25 HVAC And DHW VFD on pumps, electronic ignition on boilers, turn boilers off June & July. Provide OSA reset schedule on boilers $0 $250 0.00 Infinity 26 Other Electrical: Building hydronic Circulator Replace with 3/4 HP circulator for hydronic heat $0 $2,000 0.00 Infinity 27 Other Electrical: Computers, monitors, printers Replace with 2 Computer and monitor $0 $10 0.00 Infinity 28 Lighting: Bathroom #109 Remove Manual Switching and Add new Occupancy Sensor -$2 $300 -0.07 -185.4 29 Lighting: Dressing/ Shower # 110, 111 Remove Manual Switching and Add new Occupancy Sensor -$3 $350 -0.10 -122.6 TOTAL $6,327 $31,811 2.01 5 ENERGY AUDIT REPORT – ENERGY EFFICIENT RECOMMENDATIONS 1. Building Envelope Insulation Rank Location Existing Type/R8Value Recommendation Type/R8 Value Installed Cost Annual Energy Savings Exterior Doors – Replacement Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 6 Rank Location Size/Type/Condition Recommendation Installed Cost Annual Energy Savings Windows and Glass Doors – Replacement Rank Location Size/Type/Condition Recommendation Installed Cost Annual Energy Savings Air Leakage Rank Location Estimated Air Leakage Recommended Air Leakage Target Installed Cost Annual Energy Savings 15 Air Tightness estimated as: 5000 cfm at 50 Pascals Perform air sealing to reduce air leakage by 20%. $1,500 $148 2. Mechanical Equipment Mechanical Rank Recommendation Installed Cost Annual Energy Savings 25 VFD on pumps, electronic ignition on boilers, turn boilers off June & July. Provide OSA reset schedule on boilers $250 $0 Setback Thermostat Rank Location Size/Type/Condition Recommendation Installed Cost Annual Energy Savings 3 Equipment Storage Existing Unoccupied Heating Setpoint: 75.0 deg F Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Equipment Storage space. $200 $249 4 Office Existing Unoccupied Heating Setpoint: 75.0 deg F Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Office space. $200 $93 Ventilation Rank Recommendation Cost Annual Energy Savings 2 Cycle fan to only operate when occupancy sensor in training room occupancy sensor should be installed that detects occupant and starts AHU-1 and turns on lights since space is rarely used. $500 $1,248 3. Appliances and Lighting Lighting Fixtures and Controls Rank Location Existing Recommended Installed Cost Annual Energy Savings Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 7 7 Equipment Storage 35 FLUOR (2) T12 8' F96T12/HO 95W Energy-Saver EfficMagnetic with Manual Switching Replace with 35 FLUOR (2) T8 8' F96T8/HO 86W Standard Program StdElectronic and Remove Manual Switching and Add new Multi-Level Switch $5,786 $1,118 9 Office 107 4 FLUOR (4) T12 4' F40T12 34W Energy-Saver (2) EfficMagnetic with Manual Switching Replace with 4 FLUOR (4) T8 4' F32T8 32W Standard (2) Program HighEfficElectronic and Remove Manual Switching and Add new Occupancy Sensor, Manual Dimmer $750 $102 10 Equipment Storage - Night Lights 5 FLUOR (2) T12 8' F96T12/HO 95W Energy-Saver EfficMagnetic Replace with 5 FLUOR (2) T8 8' F96T8/HO 86W Standard Program StdElectronic $630 $76 11 Mechanical Room Lighting Room 112 2 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Remove Manual Switching and Add new Occupancy Sensor $350 $41 12 Exterior Lights 6 HPS 250 Watt Magnetic with On/Off Photoswitch Replace with 6 LED 100W Module StdElectronic $8,000 $825 13 Office/Reception #114-115 Fluorescent 2 FLUOR (4) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Remove Manual Switching and Add new Occupancy Sensor, Multi-Level Switch $350 $31 14 Corridor # 108 4 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Replace with 4 FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic and Remove Manual Switching and Add new Occupancy Sensor $850 $64 16 Training Room 113 17 FLUOR (4) T12 4' F40T12 34W Energy-Saver (2) EfficMagnetic with Manual Switching Replace with 17 FLUOR (4) T8 4' F32T8 32W Standard (2) Program StdElectronic and Remove Manual Switching and Add new Occupancy Sensor and Improve Multi-Level Switch $3,350 $361 17 Projector room #115 - Incandescent 2 INCAN Reflector, Std 75W PAR38 with Manual Switching Replace with 2 FLUOR CFL, A Lamp 15W $50 $3 19 Mechanical Room Lighting Room 112 2 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Replace with 2 FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic $250 $3 Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 8 20 Office/Reception #114-115 Fluorescent 2 FLUOR (4) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Replace with 2 FLUOR (4) T8 4' F32T8 32W Standard (2) Program HighEfficElectronic $450 $4 21 Storage 101, 102 4 FLUOR (3) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Remove Manual Switching and Add new Occupancy Sensor $350 $2 22 Dressing/ Shower # 110, 111 2 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Replace with 2 FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic $250 $1 23 Bathroom #109 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Replace with FLUOR (2) T8 4' F32T8 32W Standard Program HighEfficElectronic $125 $0 24 Storage 101, 102 4 FLUOR (3) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Replace with 4 FLUOR (3) T8 4' F32T8 32W Standard Program HighEfficElectronic $450 $0 28 Bathroom #109 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Remove Manual Switching and Add new Occupancy Sensor $300 -$2 29 Dressing/ Shower # 110, 111 2 FLUOR (2) T12 4' F40T12 34W Energy-Saver EfficMagnetic with Manual Switching Remove Manual Switching and Add new Occupancy Sensor $350 -$3 Refrigeration Rank Location Existing Recommended Installed Cost Annual Energy Savings 18 Household refrigerator Standard reefer Replace with Energy Star Reefer $800 $54 Other Electrical Equipment Rank Location Existing Recommended Installed Cost Annual Energy Savings 1 Computers, monitors, printers 2 Computer and monitor with Manual Switching Improve Manual Switching $10 $447 5 AHU Fan Air Handler with Manual Switching Remove Manual Switching and Add new Other Controls $350 $240 6 Building hydronic Circulator 3/4 HP circulator for hydronic heat with Manual Switching Improve Manual Switching $350 $151 8 Head Bolt Heaters 3 Head bolt heaters on equipment with Manual Switching Remove Manual Switching and Add new Other Controls $3,000 $1,074 26 Building hydronic Circulator 3/4 HP circulator for hydronic heat with Manual Switching Replace with 3/4 HP circulator for hydronic heat $2,000 $0 Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 9 27 Computers, monitors, printers 2 Computer and monitor with Manual Switching Replace with 2 Computer and monitor $10 $0 Cooking/Clothes Drying Rank Recommended Installed Cost Annual Energy Savings Boiler Room - Weil McLain Gold Gas Boilers Building Exterior Appartus room with lights on Mezzanine storage with no lighting switchleg Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software Barrow Fire Department Page 10 Unoccupied break room with lights on Corridor with lights on Shop Bay with Lights On