Loading...
HomeMy WebLinkAboutASRC-PHO-RSA PHO Public works USDW 2012-EERichard S. Armstrong, PE, LLC Comprehensive, Investment Grade Energy Audit Point Hope USDW Building (aka Public Works or DMS Building) Project The North Slope Borough Department of Public Works Richard S. Armstrong, PE, LLC 2321 Merrill Field Drive, C Co Richard S. Armstrong, PE, LLC Mechanical/Electrical Engineer Comprehensive, Investment Grade Energy Audit of USDW Building (aka Public Works or DMS Building) Project # ASRC-PHO-RSA-01 Prepared for: The North Slope Borough Department of Public Works April 6, 2012 Prepared by: Richard S. Armstrong, PE, LLC 2321 Merrill Field Drive, C-6 Anchorage, Ak 99501 Co-Preparer: WHPacific, Inc. 1728 Ahkovak Barrow, AK 99723 Point Hope Old USDW Building Point Hope Old USDW Building Comprehensive Energy Audit 3 REPORT DISCLAIMERS The information contained in this report, including any attachments, is intended solely for use by the building owner and the AHFC. No others are authorized to disclose, copy, distribute or retain this report, in whole or part, without written authorization from Richard S. Armstrong, PE, LLC, 2321 Merrill Field Drive, C-6, Anchorage, Ak 99501. Additionally, this report contains recommendations that, in the opinion of the auditor, will cause the owner to realize energy savings over time. All recommendations must be designed by a registered engineer, licensed in the State of Alaska, in the appropriate discipline. Lighting recommendations should all be first reviewed by running a lighting analysis to assure that the recommended lighting upgrades will comply with State of Alaska Statue as well as IES recommendations. Payback periods may well vary from those forecast due to the uncertainty of the final installed design, configuration, equipment selected, and installation costs of recommended Energy Efficiency Measures (EEMs), or the operating schedules and maintenance provided by the owner. Furthermore, EEMs are typically interactive, so implementation of one EEM may impact the cost savings from another EEM. Neither the auditor, Richard S. Armstrong, PE, LLC, AHFC, or others involved in preparation of this report will accept liability for financial loss due to EEMs that fail to meet the forecasted payback periods. This audit meets the criteria of an Investment Grade Audit (IGA) per the Association of Energy Engineers definition, and is valid for one year. The life of the IGA may be extended on a case-by-case basis, at the discretion of the AHFC. IGSs are the property of the State, and may be incorporated into AkWarm- C, the Alaska Energy Data Inventory (ARIS), or other state and/or public information system Point Hope Old USDW Building Comprehensive Energy Audit 4 Investment Grade Energy Audit Point Hope Old USDW Building 1. Executive Summary: The Point Hope Old USDW building, now known as Public Works or DMS, was constructed in 1983 and has seen no major remodels since then. Table 1 2010 2011 Utility Consumption Cost/Year Consumption Cost/Year Electricity-kWh 122,840 $29,482 120,580 $28,939 Fuel Oil - Gallons Not available 21,999 $139,694 Total Energy Costs $29,482* $168,633 *NOTE: assuming similar fuel oil use for 2010, the utility cost for 2010 was $169,176 A benchmark measure of energy use relative to other similar function buildings in the area is the Energy Use Index (EUI), which takes the total annual energy used by the facility divided by the square footage area of the building, for a value expressed in terms of kBTU/SF. This number can then be compared to other buildings to see if it is about average, higher or lower than similar buildings in the area. Likewise, the Energy Cost Index (ECI) is the cost of all energy used by the building expressed in $/SF of building area. The comparative values for the subject building are listed in Table 2 below: Table 2 USDW Building PHO Average Warm Storage Energy Use Index (EUI) kBTU/SF Avg 2009, 2010 32 41 34 Energy Cost Index (ECI) Average 2009, 2010 $2.79 $3.54 $3.10 Various Energy Efficiency Measures (EEMs) have been analyzed for this building to determine if they would be applicable for energy savings with reasonably good payback periods. Those EEMs that have a payback period or those that are recommended for code compliance, life cycle replacement, or other reasons are also included. Also, where a lighting upgrade is recommended from T-12 lamps with magnetic ballasts to T-8 lamps with electronic ballasts, then the entire facility should be re-lamped and re-ballasted to Point Hope Old USDW Building Comprehensive Energy Audit 5 maintain a standard lighting parts inventory, regardless of the payback. For example, a storage room that is infrequently used may not show a very good payback for a lighting upgrade, but consistency dictates a total upgrade. Specific EEMs recommended for this facility are summarized below, and are detailed in the attached AkWarm Energy Audit Report along with specific payback times, as well as estimated installation costs and estimated energy savings. Several of the EEMs are not modeled in the AkWarm-C program because they will require engineering to determine costs and payback once the technical savings are estimated. The higher priority items are summarized below: a. Air Infiltration: In mixed use, vehicle maintenance and storage facilities such as the subject building, it is typical that the overhead doors are opened and left open for long periods of time, even during the winter months. A single overhead door left open will cause a vehicle bay’s heaters to run at full capacity in an attempt to maintain temperature. All this heat is lost to the outside as long as the door is open. This is an effective loss of half a gallon of fuel oil per hour per unit heater or H&V (Heating and Ventilation) unit. It is recommended to add automatic door closers with integral personnel safety sensors, set to close the overhead door 1-3 minutes after opening. This increased frequency of door opening and closings will increase energy usage by the door openers, and this offset is considered in the AkWarm-C Report in Appendix B. b. Thermostat Setbacks: With a few exceptions, all rooms in this building have thermostats which control room and/or zone temperatures. It is recommended that setback thermostats be installed and programmed to reduce room temperatures to 55 °F during unoccupied periods. c. Fluorescent Lighting Upgrades: The offices and other low spaces have a mixture of T12 and T8 lamps with mostly magnetic ballasts. The AkWarm-C program models these lamps and shows the payback period if all lamps are changed to T8s with electronic programmable ballasts. It is Point Hope Old USDW Building Comprehensive Energy Audit 6 recommended that all T12 lamps be retrofitted to T8 with electronic ballasts for lamp and ballast standardization regardless of the payback period. Typical savings in power consumption varies 10-30% with this upgrade. d. Lighting Control Upgrades: During the audit, almost all of the building’s lights were found to be left on with nobody in the space. Occupant controls sense the presence of occupants, turn the lights on at a pre-determined level, and then turn the lights off after a programmed time period of no occupancy. It is recommended that motion-sensing occupancy sensors be installed in the existing duplex switch boxes for all offices, corridors, and stairwells, and that ceiling-mounted dual- technology sensors be installed where obstacles may interfere with line-of-sight sensors, such as in lavatories, corridors, vehicle bays, and storage areas. The second technology in these sensors activates lighting based on sound. These controls can reduce total kWh consumption for the lighting in the order of 30-90%, depending on the amount of time the lights are manually left on. e. High-Bay Lighting: The vehicle bays are illuminated with 250- Watt HPS fixtures, which take several minutes to restrike. This means they are typically left on at all times, which wastes a large amount of electrical energy. It is recommended that these HPS lamps be replaced with 5-tube HO (High-Output) T5 fixtures with fixture-mounted, dual-technology occupancy sensors. There is a negligible energy savings resulting directly from the fixture/lamp change, but because T5 lamps have no warm-up time, they allow the use of occupancy sensors which can result in up to 80-90% reduction in on-time and energy use. Multiple “night lights” could also be wired to be on continuously if desired. f. Exterior Lighting Upgrades: The exterior high pressure sodium lights operate during periods of darkness, which is about half of the year. It is estimated that the use of LED exterior lights can reduce the power consumption by 60% and extend bulb replacement frequency to 5-10 years, yielding an even better payback by reducing maintenance costs. Point Hope Old USDW Building Comprehensive Energy Audit 7 g. Headbolt Heater Controls: Studies have shown that leaving a vehicle plugged in for more than four hours is an unnecessary waste of energy regardless of outside temperature, as the engine’s temperature typically stabilizes after that. Leaving block, oil pan, and battery heaters energized when not needed may waste up to $300 per year per car in electricity costs. To reduce this cost, microprocessor-controlled duplex receptacles have been developed that cycle power to the heaters based on outside temperature. It is recommended that the existing headbolt heater receptacles be replaced with these temperature-controlled receptacles at a cost of $200 each. h. Refrigerator: Newer Energy Star refrigerators use about 411 watts, compared to 1990 versions that used 1,044 watts. It is recommended that, at EOL (End Of Life), the existing refrigerators be replaced with an Energy Star equivalent unit. The cost difference is about $75 per unit, which will be realized in energy savings in less than two years. In addition to EEMs, various Energy Conservation Measures (ECMs) are recommended since they are policies or procedures that are followed by management and employees that require no capital outlay. Examples of recommended ECMs for this facility include: • Turn off lights when leaving a room that is not controlled by an occupancy sensor that automatically turns off lights. • Turn off computers, monitors, printers, faxes, coffee makers, etc when leaving the office for the day. • Keep overhead doors closed except when they are required to be open for movement of vehicles. The 21 priority recommendations in the detailed report estimate to save $38,197/year, with an installed cost of $55,687. This does not include design or CA services, but overall it does indicate a cost effective energy savings program. Point Hope Old USDW Building Comprehensive Energy Audit 8 2. Audit and Analysis Background: a. Program Description: This audit included services to identify, develop, and evaluate energy efficiency measures at the subject building. The scope of this project included evaluating the building shell, lighting, other electrical systems, and heating, ventilating, and air conditioning (HVAC) equipment. Measures were selected such that an overall simple payback period of 8 years or less could be achieved. b. Audit Description and Methodology: Preliminary audit information was gathered in preparation for the site survey, including benchmark utility consumption data, floor and lighting plans, and equipment schedules where available. A site visit is then performed to inventory and evaluate the actual building condition, including: i. Building envelope (roof, windows, etc) ii. Heating, ventilating, and air conditioning iii. Lighting systems and controls iv. Building specific equipment v. Plumbing systems c. Method of Analysis: The information gathered prior to the site visit and at the site visit is entered into AkWarm-C, an energy modeling developed for Alaska Housing Finance Corporation (AHFC) specifically to identify forecasted energy consumption which can be compared to actual energy consumption. AkWarm-C also has some pre-programmed EEM retrofit options that can be analyzed with energy savings forecasted based on occupancy schedules, utility rates, building construction type, building function, existing conditions, and climatic data that is already uploaded to the program based on the zip code of the building. When new equipment is proposed, energy consumption is calculated based on manufacturer’s cataloged information. Cost savings are calculated based on the historical energy costs for the building. Installation costs include labor and equipment to estimate the full up-front investment required to implement a change, but design and construction management Point Hope Old USDW Building Comprehensive Energy Audit 9 costs are excluded. Costs are derived from Means Cost Data, industry publications, experience of the auditor, local contractors and equipment suppliers. Maintenance savings are calculated were applicable and are added to the energy savings for each EEM. The cost and savings are applied and a simple payback and simple return on investment (ROI) is calculated. The simple payback is based on the number of years that it takes for the savings to pay back the net installation cost (Net Installation divided by Net Savings.) A simple life-time calculation is shown for each EEM. The life- time for each EEM is estimated based on the typical life of the equipment being replaced or altered. The energy savings is extrapolated throughout the life-time of the EEM. The total energy savings is calculated as the total life-time multiplied by the yearly savings. d. Limitations of the Study: All results are dependent on the quality of input data provided, and can only act as an approximation. In some instances, several methods may achieve the identified savings. This report is not intended as a final design document. A design professional, licensed to practice in Alaska and in the appropriate discipline, who is following the recommendations, shall accept full responsibility and liability for the results. Budgetary estimates for engineering and design of these projects in not included in the cost estimate for each measure, but these costs generally run around 15% of the cost of the work. 3. Acknowledgements: We wish to acknowledge the help of numerous individuals who have contributed information that was used to prepare this report, including: a. Alaska Housing Finance Corporation (Grantor): AHFC provided the grant funds, contracting agreements, guidelines, and technical direction for providing the audits. AHFC reviewed and approved the final short list of buildings to be audited Point Hope Old USDW Building Comprehensive Energy Audit 10 based on the recommendation of the Technical Service Provider (TSP). b. North Slope Borough (Owner): The NSB provided building sizing information, two years energy billing data, building schedules and functions, as well as building age. Price Brower, manager of the facility, was very helpful in offering any assistance requested during the audit. c. Nortech Engineering (Benchmark TSP): Nortech Engineering compiled the data received from the NSB and entered that data into the statewide building database, called the Alaska Retrofit Information System (ARIS). d. Richard S. Armstrong, PE, LLC (Audit TSP): This is the TSP who was awarded the projects in the Arctic Slope Regional Corporation, Bering Straits area, and the Nana area. The firm gathered all relevant benchmark information provided to them by Nortech, cataloged which buildings would have the greatest potential payback, and prioritized buildings to be audited based on numerous factors, including the Energy Use Index (EUI), the Energy Cost Index (ECI), the age of the building, the size of the building, the location of the building, the function of the building, and the availability of plans for the building. They also trained their selected sub-contracted auditors, assigned auditors to the selected buildings, and performed quality control reviews of the resulting audits. They prepared a listing of potential EEMs that each auditor must consider, as well as the potential EEMs that the individual auditor may notice in the course of his audit. Richard S. Armstrong, PE, LLC also performed some of the audits to assure current knowledge of existing conditions. e. WHPacific, Inc (Audit Preparer): This firm specializes in mechanical, electrical, and civil design, and has a mechanical EIT who is a Certified Energy Auditor in Training. This CEIT has received additional training from Richard S. Armstrong, PE, LLC to acquire further specific information regarding audit requirements and potential EEM applications. WHPacific Point Hope Old USDW Building Comprehensive Energy Audit 11 prepared this audit and submitted it for review by Richard S. Armstrong, PE, LLC. 4. Building Description and Function: The subject structure is called the Point Hope Public Works Building, and was formerly known as the Point Hope USDW building. It was constructed in 1983 and has seen no major remodels since then. The building is a mixture of one story high-bay spaces and two story office/storage areas. This building serves as a shop and storage space for the North Slope Borough School District, the NSB Roads division, the NSB power and Light Division, and the NSB Water and Sewer Division. It also provides office space for the Point Hope public works office. a. Heating System: The building heating system consists of two Burnham 1,552 MBH cast iron boilers. The boilers provide heat to the make-up air system, offices, shops, and storage areas. The boilers were installed after 2001. Hot glycol is circulated in three loops using six pumps. Pumps 1, 3, and 5 are Grundfos UPS50-160F circ pumps, and the three old B&G pumps (CP-2, 4, and 6) are inoperative or missing. Because of this, there is no redundancy in the circulation system, and if one of the pumps fails, a portion of the building or heat trace will lose heat. These pumps should be replaced with the new models as soon as possible to avoid such failure. b. Ventilation System: There are 10 H&V (Heating and Ventilation) units and 10 exhaust fans in this building. All together, the exhaust fans can draw over 7500 cfm of conditioned air from the building. Careful attention should be paid to the control system governing these fans. Since there are typically only 3 or 4 occupants in this building, very little air exchanges are needed in a building this size, and the ventilation system can potentially waste a great deal of heat. c. Plumbing System: Toilets with lavs, showers, and clothes washing facilities are provided for the workers, in addition to a break sink. Each bay is equipped with a drain system to a sump which pumps the graywater into the sewage system. Point Hope Old USDW Building Comprehensive Energy Audit 12 d. Domestic Hot Water: Hot water is generated using a sidearm water heater that draws heat from the boilers. A 4.5 kW electric water heater is also installed, but this was not energized during the audit, and it is unknown how much it is used. e. Lighting: Lighting throughout the building is comprised of a mixture of T12 and T8 fixtures with mostly magnetic ballasts in the offices and low spaces. The hangar area is lit using 250 watt HPS lighting fixtures, and exterior lights are typically 250 watt HPS wall packs. 5. Historic Energy Consumption: Energy consumption is modeled within the AkWarm-C program. The program only analyzes 12 months of data, so where 24 months of data are available, the data is averaged and input to AkWarm-C to provide more accuracy. The energy consumption data is presented and graphed in the attached AkWarm-C program results. The average electric consumption for the building is 121,710 kWh/year at an average cost of $29,210/year. The average #2 fuel oil consumption was 21,999/year, at an average annual cost of $139,693/year. 6. Energy Efficiency Measures considered or recommended: The building was examined for application of a multitude of potential EEMs. Those EEMs that appear to have an application for the subject building are further analyzed for estimated payback periods, either within the AkWarm-C program or separately within this report. General EEM categories were discussed in this report’s executive summary. Each specific EEM is detailed in the attached AkWarm-C report that comprises Appendix B. The accuracy of the cost estimates and paybacks varies significantly due to a multitude of conditions, but is estimated to be approximately +/- 25%. Assumptions made regarding energy costs and the life of the EEM, noting that post-construction measurement and verification are based on energy savings, not energy cost savings. Many of the selected EEMs are analyzed within the Point Hope Old USDW Building Comprehensive Energy Audit 13 AkWarm-C program using the schedules and estimated costs input into the model. 7. Interactive Effects of Projects: The AkWarm-C program calculates savings assuming that all recommended EEM are implemented. If some EEMs are not implemented, savings for the remaining EEMs will be affected, in some cases positively, and in others, negatively. For example, if the fan motors are not replaced with premium efficiency motors, then the savings for the project to install variable speed drives (VFDs) on the fans will be increased. In general, all projects were evaluated sequentially so that energy savings associated with one EEM would not be attributed to another EEM as well. For example, the night setback EEM was analyzed using the fan and heating load profile that will be achieved after installation of the VFD project is completed. By modeling the recommended projects sequentially, the analysis accounts for interactive effects between the EEMs and does not “double count” savings. Interior lighting, plug loads, facility equipment, and occupants generate heat within the building. When the building is in cooling mode, these contribute to the overall cooling demands of the building; therefore lighting efficiency improvements will reduce cooling requirements on air conditioned buildings. Conversely, lighting efficiency improvements are anticipated to increase heating requirements slightly. Heating penalties are included in the lighting project analysis that is performed by AkWarm-C. 8. Loan Program: The Alaska Housing Finance Corporation (AHFC) Alaska Energy Efficiency Revolving Loan Fund (AEERLF) is a State of Alaska program enacted by the Alaska Sustainable Energy Act (senate Bill 220, A.S. 18.56.855, “Energy Efficiency Revolving Loan Fund). The AEERLF will provide loans for energy efficiency retrofits to public facilities via the Retrofit Energy Assessment for Loan System (REAL). As defined in 15 AAC 155.605, the program may finance energy efficiency improvements to buildings owned by: a. Regional educational attendance areas; Point Hope Old USDW Building Comprehensive Energy Audit 14 b. Municipal governments, including political subdivisions of municipal governments; c. The University of Alaska; d. Political subdivisions of the State of Alaska, or e. The State of Alaska Native corporations, tribal entities, and subsidiaries of the federal government are not eligible for loans under this program. Appendix A: Photos The Public Works/Old USDW Building as seen from the southeast. Looking from the southwest. Appendix A: Photos In the 2nd floor boiler room. The burner on boiler #2 was being repaired during the audit. Glycol circ pumps #1-6. Each loop has only one operable pump. Appendix A: Photos New building compressor waiting to be installed in the 2nd floor boiler room. Backup genset in the 1st floor mechanical room. Tested weekly. Appendix A: Photos Most thermostat controls are inoperable and have been hard wired for full heating capacity. Inoperable used oil burner. This is a good source of “free” heat if it is repaired. Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 1 ENERGY AUDIT REPORT – PROJECT SUMMARY – Created 4/9/2012 4:29 AM General Project Information PROJECT INFORMATION AUDITOR INFORMATION Building: USDW Building (Public Works Building) Auditor Company: Richard S. Armstrong, PE, LLC Address: 901 Ippiq St Auditor Name: Richard S. Armstrong, David Robbins City: Point Hope Auditor Address: 2321 Merrill Field Drive C-6 Anchorage, Ak 99501 Client Name: John Long Client Address: PO Box 129 901 Ippiq St Point Hope, AK 99766 Atqasuk, AK 99791 Auditor Phone: (907) 229-0331 Auditor FAX: Client Phone: (907) 368-2613 Auditor Comment: Client FAX: Design Data Building Area: 13,850 square feet Design Heating Load: Design Loss at Space: 1,993,807 Btu/hour with Distribution Losses: 2,190,996 Btu/hour Plant Input Rating assuming 82.0% Plant Efficiency and 25% Safety Margin: 3,339,933 Btu/hour Note: Additional Capacity should be added for DHW load, if served. Typical Occupancy: 8 people Design Indoor Temperature: 70 deg F (building average) Actual City: Point Hope Design Outdoor Temperature: -39.7 deg F Weather/Fuel City: Point Hope Heating Degree Days: 16,501 deg F-days Utility Information Electric Utility: North Slope Borough Utilities - Commercial - Lg Natural Gas Provider: None Average Annual Cost/kWh: $0.296/kWh Average Annual Cost/ccf: $0.000/ccf Annual Energy Cost Estimate Description Space Heating Space Cooling Water Heating Lighting Refrige ration Other Electric al Cooking Clothes Drying Ventilatio n Fans Service Fees Total Cost Existing Building $154,25 0 $0 $923 $14,730 $0 $5,073 $0 $245 $1,314 $180 $176,715 With Proposed Retrofits $125,78 1 $0 $2,800 $4,103 $0 $4,231 $0 $240 $1,283 $180 $138,617 SAVINGS $28,469 $0 -$1,877 $10,628 $0 $842 $0 $6 $31 $0 $38,098 Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 2 $0 $50,000 $100,000 $150,000 $200,000 Existing Retrofit Service Fees Ventilation and Fans Space Heating Other Electrical Lighting Domestic Hot Water Clothes Drying Annual Energy Costs by End Use $0 $50,000 $100,000 $150,000 $200,000 Existing Retrofit #2 Oil Electricity Annual Energy Costs by Fuel Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 3 PRIORITY LIST – RECOMMENDED ENERGY EFFICIENCY MEASURES Rank Feature Recommendation Annual Energy Savings Installed Cost SIR Payback (Years) 1 Setback Thermostat: Equipment bays Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Equipment bays space. $13,868 $600 313.79 0 2 Setback Thermostat: Storage and warehouse Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Storage and warehouse space. $12,291 $1,200 139.05 0.1 3 Setback Thermostat: Overnight residences Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Overnight residences space. $2,516 $600 56.93 0.2 4 Setback Thermostat: Offices, corridors, stairwells Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Offices, corridors, stairwells space. $3,363 $1,200 38.05 0.4 5 Other Electrical: Pump 10 - sewage ejector Remove Manual Switching and Add new Clock Timer or Other Scheduling Control $162 $100 9.24 0.6 6 Lighting: T12-1 lamp interior lighting - bathrooms Remove Manual Switching and Add new Occupancy Sensor $240 $150 9.16 0.6 7 Other Electrical: Refrigerators Replace with standard sized refrigerator $38 $75 2.87 2 8 Lighting: Exterior lighting - 250W HPS door lights Replace with 5 LED 100W Module StdElectronic $784 $3,000 2.45 3.8 9 Other Electrical: Head bolt heaters - 4 of 7 typically in use Remove Manual Switching and Add new Other Controls $531 $1,400 2.35 2.6 10 Lighting: T12-4 lamp Interior lighting; add OS Replace with 17 FLUOR (4) T8 4' F32T8 28W Energy- Saver Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi- Level Switch $947 $2,700 1.99 2.9 11 Lighting: Exterior lighting - 150W HPS wall packs Replace with LED 34W Module StdElectronic $124 $800 1.90 6.4 Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 4 PRIORITY LIST – RECOMMENDED ENERGY EFFICIENCY MEASURES Rank Feature Recommendation Annual Energy Savings Installed Cost SIR Payback (Years) 12 Lighting: T12-2 lamp Interior lighting - vestibules, offices, storage areas, etc; add OS Replace with 126 FLUOR (2) T8 4' F32T8 28W Energy-Saver Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi-Level Switch $2,108 $18,950 1.55 9 13 Lighting: Interior lighting - incandescent bulbs Replace with FLUOR CFL, A Lamp 20W $2 $10 1.36 4.2 14 Lighting: T12-1 lamp Interior lighting - vestibules, offices, storage areas, etc; add OS Replace with 31 FLUOR T8 4' F32T8 28W Energy- Saver Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi- Level Switch $188 $8,550 1.14 45.5 15 Lighting: Interior lighting - high bay Public Works bay - 250W HPS fixtures Replace with 13 FLUOR (4) T5 45.2" F54W/T5 HO Energy-Saver HighLight StdElectronic and Remove Manual Switching and Add new Occupancy Sensor $611 $7,501 1.04 12.3 16 Lighting: T8-4 lamp Interior lighting; add OS Replace with 2 FLUOR (4) T8 4' F32T8 32W Standard Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor $62 $450 0.77 7.3 17 Lighting: Exterior lighting - 250W HPS wall packs Replace with 5 LED 48W Module StdElectronic $268 $6,000 0.59 22.4 18 Lighting: T12-1 lamp interior lighting - bathrooms Replace with 2 FLUOR T8 4' F32T8 32W Standard Instant StdElectronic $16 $200 0.44 12.7 19 Lighting: T8-1 lamp Interior lighting; add OS Replace with FLUOR T8 4' F32T8 32W Standard Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi-Level Switch $12 $450 0.14 39 Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 5 PRIORITY LIST – RECOMMENDED ENERGY EFFICIENCY MEASURES Rank Feature Recommendation Annual Energy Savings Installed Cost SIR Payback (Years) 20 Lighting: T8-2 lamp Interior lighting; add OS Replace with FLUOR (2) T8 4' F32T8 32W Standard Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor $17 $1,750 0.05 102.6 21 Other Electrical: Overhead door openers Improve Manual Switching -$50 $1 -282.63 0 TOTAL $38,098 $55,687 9.08 1.5 ENERGY AUDIT REPORT – ENERGY EFFICIENT RECOMMENDATIONS 1. Building Envelope Insulation Rank Location Existing Type/R-Value Recommendation Type/R- Value Installed Cost Annual Energy Savings Exterior Doors – Replacement Rank Location Size/Type/Condition Recommendation Installed Cost Annual Energy Savings Windows and Glass Doors – Replacement Rank Location Size/Type/Condition Recommendation Installed Cost Annual Energy Savings Air Leakage Rank Location Estimated Air Leakage Recommended Air Leakage Target Installed Cost Annual Energy Savings 2. Mechanical Equipment Mechanical Rank Recommendation Installed Cost Annual Energy Savings Setback Thermostat Rank Location Size/Type/Condition Recommendation Installed Cost Annual Energy Savings Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 6 1 Equipment bays Existing Unoccupied Heating Setpoint: 70.0 deg F Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Equipment bays space. $600 $13,868 2 Storage and warehouse Existing Unoccupied Heating Setpoint: 70.0 deg F Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Storage and warehouse space. $1,200 $12,291 3 Overnight residences Existing Unoccupied Heating Setpoint: 70.0 deg F Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Overnight residences space. $600 $2,516 4 Offices, corridors, stairwells Existing Unoccupied Heating Setpoint: 70.0 deg F Implement a Heating Temperature Unoccupied Setback to 55.0 deg F for the Offices, corridors, stairwells space. $1,200 $3,363 Ventilation Rank Recommendation Cost Annual Energy Savings 3. Appliances and Lighting Lighting Fixtures and Controls Rank Location Existing Recommended Installed Cost Annual Energy Savings 6 T12-1 lamp interior lighting - bathrooms 2 FLUOR T12 6' F72T12/HO 85W Standard Magnetic with Manual Switching Remove Manual Switching and Add new Occupancy Sensor $150 $240 8 Exterior lighting - 250W HPS door lights 5 HPS 250 Watt Magnetic with Manual Switching Replace with 5 LED 100W Module StdElectronic $3,000 $784 10 T12-4 lamp Interior lighting; add OS 17 FLUOR (4) T12 4' F40T12 40W Standard Magnetic with Manual Switching Replace with 17 FLUOR (4) T8 4' F32T8 28W Energy- Saver Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi- Level Switch $2,700 $947 11 Exterior lighting - 150W HPS wall packs HPS 150 Watt Magnetic with Daylight Sensor Replace with LED 34W Module StdElectronic $800 $124 Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 7 12 T12-2 lamp Interior lighting - vestibules, offices, storage areas, etc; add OS 126 FLUOR (2) T12 4' F40T12 40W Standard Magnetic with Manual Switching Replace with 126 FLUOR (2) T8 4' F32T8 28W Energy- Saver Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi- Level Switch $18,950 $2,108 13 Interior lighting - incandescent bulbs INCAN A Lamp, Std 60W with Manual Switching Replace with FLUOR CFL, A Lamp 20W $10 $2 14 T12-1 lamp Interior lighting - vestibules, offices, storage areas, etc; add OS 31 FLUOR T12 4' F40T12 40W Standard Magnetic with Manual Switching Replace with 31 FLUOR T8 4' F32T8 28W Energy-Saver Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi-Level Switch $8,550 $188 15 Interior lighting - high bay Public Works bay - 250W HPS fixtures 13 HPS 250 Watt Magnetic with Manual Switching Replace with 13 FLUOR (4) T5 45.2" F54W/T5 HO Energy-Saver HighLight StdElectronic and Remove Manual Switching and Add new Occupancy Sensor $7,501 $611 16 T8-4 lamp Interior lighting; add OS 2 FLUOR (4) T8 4' F32T8 32W Standard Instant StdElectronic with Manual Switching Replace with 2 FLUOR (4) T8 4' F32T8 32W Standard Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor $450 $62 17 Exterior lighting - 250W HPS wall packs 5 HPS 100 Watt Magnetic with Daylight Sensor Replace with 5 LED 48W Module StdElectronic $6,000 $268 18 T12-1 lamp interior lighting - bathrooms 2 FLUOR T12 6' F72T12/HO 85W Standard Magnetic with Manual Switching Replace with 2 FLUOR T8 4' F32T8 32W Standard Instant StdElectronic $200 $16 19 T8-1 lamp Interior lighting; add OS FLUOR T8 4' F32T8 32W Standard Instant StdElectronic with Manual Switching Replace with FLUOR T8 4' F32T8 32W Standard Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor, Multi-Level Switch $450 $12 20 T8-2 lamp Interior lighting; add OS FLUOR (2) T8 4' F32T8 32W Standard Instant StdElectronic with Manual Switching Replace with FLUOR (2) T8 4' F32T8 32W Standard Instant StdElectronic and Remove Manual Switching and Add new Occupancy Sensor $1,750 $17 Refrigeration Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 8 Rank Location Existing Recommended Installed Cost Annual Energy Savings Other Electrical Equipment Rank Location Existing Recommended Installed Cost Annual Energy Savings 5 Pump 10 - sewage ejector Dayton .5/120/1 motor with Manual Switching Remove Manual Switching and Add new Clock Timer or Other Scheduling Control $100 $162 7 Refrigerators standard sized refrigerator with Manual Switching Replace with standard sized refrigerator $75 $38 9 Head bolt heaters - 4 of 7 typically in use 4 Duplex receptacle head bolt heaters with Manual Switching Remove Manual Switching and Add new Other Controls $1,400 $531 21 Overhead door openers 7 PowerMaster openers, 3/4 HP, 115V single phase motors with Manual Switching Improve Manual Switching $1 -$50 Cooking/Clothes Drying Rank Recommended Installed Cost Annual Energy Savings Fire tube for boiler #2 (burner down for maintenance) New air compressor in 2nd floor mech room. Awaiting installation. Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 9 Generator room on first floor. Fire sprinkler system zone assembly Cast iron Burnham Boilers #1 and #2 Circ pumps on the three glycol loops. Three have been replaced with new grundfos pumps. The other three are inoperable. View of the building from the east side (main entrance). Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 10 View of the building from the northeast corner (school district bays) View of the building from the northwest corner. School Dist bays and lineman bay visible. view of the building from the southeast corner. lineman bay and DMS bays visible. thermister reading access panel. hardwired temp control. Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 11 programmable building controls not in use/inoperable H&V unit #2 Black Gold used oil burner inoperable. South-facing bay door. Showing air infiltration at base and sides. Close-up on bay door showing infiltration of -15F air. Appendix B Energy Audit – Energy Analysis and Cost Comparison AkWarm Commercial Audit Software USDW Building (Public Works Building) Page 12 H&V unit #1 showing heating of incoming air at coil after mixing. IR view of glycol pumps showing inoperative pumps. ------------------------------------------ AkWarmCalc Ver 2.1.4.2, Energy Lib 3/1/2012 Appendix C: Equipment Schedules - Mechanical Appendix C: Equipment Schedules - Mechanical Appendix D: Building Plan Appendix E: Lighting Plan Appendix E: Lighting Plan Appendix F: Mechanical Schematics Appendix F: Mechanical Schematics Appendix F: Mechanical Schematics