HomeMy WebLinkAboutENN Nenana City Hall 2012-EEManaging Office
2400 College Road 3105 Lakeshore Dr. Suite 106A 4402 Thane Road
Fairbanks, Alaska 99709 Anchorage, Alaska 99517 Juneau, Alaska 99801
p. 907.452.5688 p. 907.222.2445 p: 907.586.6813
f. 907.452.5694 f. 907.222.0915 f: 907.586.6819
www.nortechengr.com
ENERGY AUDIT – FINAL REPORT
Nenana City Office
307 East 2nd Street
Nenana, Alaska
Prepared for:
Mr. Jayson Mayrand
City of Nenana
307 East 2nd Street
Nenana, Alaska
Prepared by:
David C. Lanning PE, CEA
Stephanie Young EIT, CEAIT
July 13, 2012
Acknowledgment: "This material is based upon work supported by the Department of
Energy under Award Number DE-EE0000095.”
ENVIRONMENTAL ENGINEERING, HEALTH & SAFETY
Anch: 3105 Lakeshore Dr. Ste 106A, 99517 907.222.2445 Fax: 222.0915
Fairbanks: 2400 College Road, 99709 907.452.5688 Fax: 452.5694
Juneau: 4402 Thane Road, 99801 907.586.6813 Fax: 586.6819
info@nortechengr.com www.nortechengr.com
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
i
TABLE OF CONTENTS
1.0 EXECUTIVE SUMMARY ................................................................................................. 1
2.0 INTRODUCTION ............................................................................................................. 5
2.1 Building Use ......................................................................................................... 5
2.2 Building Occupancy and Schedules ..................................................................... 5
2.3 Building Description ............................................................................................. 6
3.0 BENCHMARKING 2010 UTILITY DATA ......................................................................... 8
3.1 Total Energy Use and Cost of 2010 ..................................................................... 9
3.2 Energy Utilization Index of 2010 ......................................................................... 10
3.3 Cost Utilization Index of 2010............................................................................. 11
3.4 Seasonal Energy Use Patterns .......................................................................... 12
3.5 Future Energy Monitoring ................................................................................... 13
4.0 MODELING ENERGY CONSUMPTION ........................................................................ 14
4.1 Understanding How AkWarm Models Energy Consumption ............................... 15
4.2 AkWarm Calculated Savings for the Nenana City Office .................................... 16
4.3 Additional Modeling Methods ............................................................................. 17
5.0 BUILDING OPERATION AND MAINTENANCE (O & M) .............................................. 18
5.1 Operations and Maintenance ............................................................................. 18
5.2 Commissioning .................................................................................................. 18
5.3 Building Specific Recommendations .................................................................. 19
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
ii
APPENDICES
Appendix A Recommended Energy Efficiency Measures .......................................... 21
Appendix B Energy Efficiency Measures that are NOT Recommended ..................... 27
Appendix C Significant Equipment List ...................................................................... 28
Appendix D Local Utility Rate Structure ..................................................................... 29
Appendix E Analysis Methodology ............................................................................ 31
Appendix F Audit Limitations ..................................................................................... 32
Appendix G References ............................................................................................. 33
Appendix H Typical Energy Use and Cost – Fairbanks and Anchorage ..................... 34
Appendix I Typical Energy Use and Cost – Continental U.S. ................................... 35
Appendix J List of Conversion Factors and Energy Units .......................................... 36
Appendix K List of Acronyms, Abbreviations, and Definitions .................................... 37
Appendix L Building Floor Plan ................................................................................. 38
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
1
1.0 EXECUTIVE SUMMARY
NORTECH has completed an ASHRAE Level II Energy Audit of the Nenana City Office, a 3,680
square foot facility in the City of Nenana. The audit began with benchmarking which resulted in
a calculation of the energy consumption per square foot. A site inspection was completed on
August 24, 2011 to obtain information about the lighting, heating, ventilation, cooling and other
building energy uses. The existing usage data and current systems were then used to develop
a building energy consumption model using AkWarm.
Once the model was calibrated, a number of Energy Efficiency Measures (EEMs) were
developed from review of the data and observations. EEMs were evaluated and ranked on the
basis of both energy savings and cost using a Savings/Investment Ratio (SIR). While these
modeling techniques were successful in verifying that many of the EEMs would save energy,
not all of the identified EEMs were considered cost effective based on the hardware, installation,
and energy costs at the time of this audit.
While the need for a major retrofit can typically be identified by an energy audit, upgrading
specific systems often requires collecting additional data and engineering and design efforts that
are beyond the scope of the Level II energy audit. The necessity and amount of design effort
and cost will vary depending on the scope of the specific EEMs planned and the sophistication
and capability of the entire design team, including the building owners and operators. During
the budgeting process for any major retrofit identified in this report, the building owner should
add administrative and supplemental design costs to cover the individual needs of their own
organization and the overall retrofit project.
The following table, from AkWarm, is a summary of the recommended EEMs for the Nenana
City Office. Additional discussion of the modeling process can be found in Section 3. Details of
each individual EEM can be found in Appendix A of this report. A summary of EEMs that were
evaluated but are not currently recommended is located in Appendix B.
PRIORITY LIST – ENERGY EFFICIENCY MEASURES (EEMs)
Rank Feature/
Location Improvement Description
Estimated
Annual
Energy
Savings
Estimated
Installed
Cost
Savings to
Investment
Ratio, SIR
Simple
Payback
(Years)
1
Setback
Thermostat:
Heated Space
from Furnace 2
Implement a Heating
Temperature Unoccupied
Setback to 62.0 deg F for the
Heated Space from Furnace 2
$1,319 $150 120 0.1
2
Setback
Thermostat:
Heated Space
from Furnace 1
Implement a Heating
Temperature Unoccupied
Setback to 62.0 deg F for the
Heated Space from Furnace 1
$588 $150 53 0.3
3 Refrigeration:
Lobby
Add a timer to Soda Machine
to reduce on-time. $27 $26 5.8 0.9
4
Exterior Door:
Storage- 15, 16,
17
Remove existing door and
install standard pre-hung U-
0.16 insulated door, including
hardware.
$91 $534 4.0 5.9
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
2
PRIORITY LIST – ENERGY EFFICIENCY MEASURES (EEMs)
Rank Feature/
Location Improvement Description
Estimated
Annual
Energy
Savings
Estimated
Installed
Cost
Savings to
Investment
Ratio, SIR
Simple
Payback
(Years)
5 HVAC And DHW Replace furnaces with new
efficient furnaces $3,804 $18,000 3.6 4.7
6
On- or Below-
Grade Floor,
Perimeter: House
Install 4' of R-30 rigid board
insulation on Perimeter of
Crawl Space Floor.
$751 $5,667 3.1 7.5
7 Other Electrical:
Copy Room
Program Energy Saver Mode
for the Copier $10 $25 2.2 2.6
8 Lighting: Janitor
Closet
Replace with FLUOR (2) CFL,
Spiral 13 W $1 $4 2.2 2.8
9 Lighting: Outdoor
Lighting
Replace with 5 LED 12W
Module StdElectronic $244 $1,000 2.1 4.1
10 Exterior Door:
File Room
Remove existing door and
install standard pre-hung U-
0.16 insulated door, including
hardware.
$47 $558 2.0 12
11 Exterior Door:
Office- 3
Remove existing door and
install standard pre-hung U-
0.16 insulated door, including
hardware.
$45 $534 2.0 12
12
Below- (part or
all) Grade Wall:
Crawl Space
Walls
Install R-10 rigid foam board to
interior or exterior side of wall.
Does not include cost of
coverings.
$214 $2,729 1.9 13
13
(8) Windows: File
Room, offices,
hallway,
conference, and
entry
Replace existing windows with
U-0.22 vinyl window $953 $10,919 1.5 12
14 Nenana City
Office Roof
Replace Roofing with a built up
roof composed of at least 12-
inches rigid foam insulation
and a vapor barrier and ensure
that proper roof drainage is
maintained.
$3,563 $59,493 1.4 17
15 (6) Windows:
Front Lobby- 8
Replace existing windows with
U-0.22 vinyl window $661 $8,416 1.4 13
16 Lighting: Storage
Room- 20
Replace with FLUOR CFL, A
Lamp 15W $1 $4 1.2 4.8
17
Lighting:
Combined T12
Lighting
Replace with 31 FLUOR (2) T8
4' F32T8 25W Energy-Saver
Instant HighEfficElectronic
$289 $2,170 1.0 7.5
TOTAL, cost-effective measures $12,608 $110,378 2.1 8.8
The Nenana City Office structure is nearing the end of its design life at 57 years old with an
estimated cost of replacement at $400,000-500,000. Bringing the existing building up to current
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
3
energy standards requires retrofits to almost every part of the building envelope and will cost
about $110,000, about a quarter of the cost to replace the building.
Replacing the building is a viable option. Calculations show that a new, more efficient building
could provide approximately $200,000 in energy savings over a 40 year life. Looking for funding
to replace the building is recommended.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
4
Modeled Building Energy Cost Breakdown
The above charts are a graphical representation of the modeled energy usage for the Nenana
City Office. The greatest portion of energy cost for the building is the ceiling envelope losses
followed by the envelope floor, wall, air and window losses. This indicates that the greatest
savings can be found by upgrading the envelope. Detailed improvements for the envelope and
other cost effective measures can be found in Appendix A.
The energy cost by end use breakdown was provided by AkWarm based on the field inspection
and does not indicate that all individual fixtures and appliances were directly measured. The
current energy costs are shown above on the left hand pie graph and the projected energy
costs, assuming use of the recommended EEMs, are shown on the right.
The chart breaks down energy usage by cost into the following categories:
• Envelope Air Losses—the cost to provide heated fresh air to occupants, air leakage, heat lost in
air through the chimneys and exhaust fans, heat lost to wind and other similar losses.
• Envelope
o Ceiling—quantified heat loss transferred through the ceiling portion of the envelope.
o Window—quantified heat loss through the window portion of the envelope.
o Wall/Door—quantified heat loss through the wall and door portions of the envelope.
o Floor—quantified heat loss through the floor portion of the envelope.
• Water Heating—energy cost to provide domestic hot water.
• Fans—energy cost to run ventilation, and exhaust fans.
• Lighting—energy cost to light the building.
• Refrigeration—energy costs to provide refrigerated goods for the occupants.
• Other Electrical—includes energy costs not listed above including cooking loads, laundry loads,
other plug loads and electronics.
Envelope
Air Losses
$3,280
14%
Ceiling
$6,150
27% Window
$2,255
10%
Wall/Door
$3,690
16%
Floor
$4,100
18%
Water
Heating
$350
2%
Lighting
$2,149
9%
Refriger-
ation
$327
1%
Other
Electrical
$620
3%
Existing Building Energy Cost
$22,919
Envelope
Air Losses
$2,193
9%
Ceiling
$835
4%
Window
$209
1%
Wall/Door
$2,245
10%
Floor
$2,193
9%
Water
Heating
$366
2% Lighting
$1,421
6%
Refriger-
ation
$247
1%
Other
Electrical
$602
3%
EEM
Savings
$12,591
55%
Retrofit Building Energy Cost
$10,311
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
5
2.0 INTRODUCTION
The Alaska Housing Finance Corporation contracted with NORTECH to perform ASHRAE
Level II Energy Audits for publically owned buildings in Alaska. This report presents the findings
of the utility benchmarking, modeling analysis, and the recommended building modifications,
and building use changes that are expected to save energy and money.
The report is organized into sections covering:
• description of the facility,
• the building’s historic energy usage (benchmarking),
• estimating energy use through energy use modeling,
• evaluation of potential energy efficiency or efficiency improvements, and
• recommendations for energy efficiency with estimates of the costs and savings.
2.1 Building Use
The building serves as the City office for the City of Nenana and a commercial rental space. All
City business is conducted here and city documents are stored here. The building houses the
Fire Chief’s office, the Mayor’s office, the City Clerk’s office and the Nenana Court.
2.2 Building Occupancy and Schedules
The building is occupied from 8:00 am to 5:00 pm, Monday through Friday, year round.
Approximately 20 full and part time employees work in the Nenana City Office.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
6
2.3 Building Description
The original single-story, wood-framed building was constructed in 1955. The building has a flat
built-up-roof and post and a pad foundation. An above ground crawlspace was created by
framing and insulating around the perimeter beams. A small, wood-framed addition with a cold
roof was added later.
Building Envelope
Building Envelope: Walls
Wall Type Description Insulation Notes
Above-grade walls Wood-framed with 2x6 studs
spaced 16-inches on center. R-19 fiberglass batt. ---
Below-grade walls:
North Wall 2x6 Wood Framing
R-19 fiberglass batt
insulation plus ¼ of the
exterior has 1-inch
foam board insulation
Water damage from
flooding approximately
25% has been
removed.
Building Envelope: Floors
Floor Type Description Insulation Notes
Crawlspace Floor
Compacted soil floor with a
damaged and poorly installed
vapor barrier
None ----
Building Envelope: Roof
Roof Type Description Insulation Notes
Main Roof
Hot roof, built-up construction,
ceiling has 3-inch tongue-in-
groove wood decking
Less than R-20, 4-
inches fiber board
insulation
Roof exhibits drainage
problems including
ponding.
Addition Roof Cold roof with wood-framed
trusses
R-38 fiberglass batt
insulation ---
Building Envelope: Doors and Windows
Door and Window
Type Description Estimated
R-Value Notes
All Doors Residential style metal doors 3.0 ---
All Windows Double-paned, wood-framed
windows 1.3
Window edges show
signs of damage and
poor sealing.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
7
Heating and Ventilation Systems
Two old, residential size furnaces provide heat to the building. Heat is distributed through un-
insulated and assumed leaky ducts in the crawlspace. These ducts provide heat for the
crawlspace. Two, non-programmable thermostats regulate heat supply to the building.
Air Conditioning System
No air conditioning system is installed in the building.
Energy Management
No air conditioning system is installed in the building.
Lighting Systems
Lighting in the building is mainly fluorescent ceiling-mounted fixtures with T12 (1 ½-inch
diameter, 4-foot long) or T8 (1-inch diameter, 4-foot long) bulbs. Lighting in low use storage and
mechanical rooms is composed of incandescent ceiling mounted fixtures. The exterior has
metal halide wall-mounted fixtures with 100 W bulbs.
Domestic Hot Water
Domestic Hot Water is provided by an electric water heater with a 50 gallon storage tank. Hot
water does not re-circulate.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
8
3.0 BENCHMARKING 2010 UTILITY DATA
Benchmarking building energy use consists of obtaining and then analyzing two years of energy
bills. The original utility bills are necessary to determine the raw usage, and charges as well as
to evaluate the utility’s rate structure. The metered usage of electrical and natural gas
consumption is measured monthly, but heating oil, propane, wood, and other energy sources
are normally billed upon delivery and provide similar information. During benchmarking,
information is compiled in a way that standardizes the units of energy and creates energy use
and billing rate information statistics for the building on a square foot basis. The objectives of
benchmarking are:
• to understand patterns of use,
• to understand building operational characteristics,
• for comparison with other similar facilities in Alaska and across the country, and
• to offer insight in to potential energy savings.
The results of the benchmarking, including the energy use statistics and comparisons to other
areas, are discussed in the following sections.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
9
3.1 Total Energy Use and Cost of 2010
The energy use profiles below show the energy and cost breakdowns for the Nenana City
Office. The total 2010 energy use was 705 mmBTU and the total energy cost for the building
was $15,930. These charts show the portion of use for a fuel type and the portion of its cost.
The above charts indicate that the highest portion of energy use is for fuel oil and the highest
portion of cost is for fuel oil. Fuel oil consumption correlates directly to space heating and
domestic hot water while electrical use can correlate to lighting systems, plug loads, and HVAC
equipment. The energy type with the highest cost often provides the most opportunity for
savings.
Electric
54
8%
Oil
651
92%
Energy Use Total (mmBTU)
Electric
$3,058
19%
Oil
$12,871
81%
Energy Cost Total ($)
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
10
3.2 Energy Utilization Index of 2010
The primary benchmarking statistic is the Energy Utilization Index (EUI). The EUI is calculated
from the utility bills and provides a simple snapshot of the quantity of energy actually used by
the building on a square foot and annual basis. The calculation converts the total energy use
for the year from all sources in the building, such as heating fuel and electrical usage, into
British Thermal Units (BTUs). This total annual usage is then divided by the number of square
feet of the building. The EUI units are BTUs per square foot per year.
The benchmark analysis found that the Nenana City Office has an EUI of 192,000 BTUs per
square foot per year.
The EUI is useful in comparing this building’s energy use to that of other similar buildings in
Alaska and in the Continental United States. The EUI can be compared to average energy use
in 2003 found in a study by the U.S. Energy Information Administration of commercial buildings
(abbreviated CBECS, 2006). That report found an overall average energy use of about 90,000
BTUs per square foot per year while studying about 6,000 commercial buildings of all sizes,
types, and uses that were located all over the Continental U.S. (see Table C3 in Appendix I).
In a recent and unpublished state-wide benchmarking study sponsored by the Alaska Housing
Finance Corporation, schools in Fairbanks averaged 62,000 BTUs per square foot and schools
in Anchorage averaged 123,000 BTUs per square foot annual energy use. The chart below
shows the Nenana City Office relative to these values. These findings are discussed further in
Appendix H.
192,000
62,000
123,000
0
50,000
100,000
150,000
200,000
250,000
Btu/ Sq. Ft Annual Energy Use Index (Total Energy/ SF)
Nenana City Office Fairbanks Schools Anchorage Schools
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
11
3.3 Cost Utilization Index of 2010
Another useful benchmarking statistic is the Cost Utilization Index (CUI), which is the cost for
energy used in the building on a square foot basis per year. The CUI is calculated from the cost
for utilities for a year period. The CUI permits comparison of buildings on total energy cost even
though they may be located in areas with differing energy costs and differing heating and/or
cooling climates. The cost of energy, including heating oil, natural gas, and electricity, can vary
greatly over time and geographic location and can be higher in Alaska than other parts of the
country.
The CUI for Nenana City Office is about $4.33 per square foot per year. This is based on utility
costs from 2010 and the following rates:
Electricity at $ 0.19 / kWh ($ 5.57 / Therm)
# 2 Fuel Oil at $ 2.75 / gallon ($ 1.96 / Therm)
The Department of Energy Administration study, mentioned in the previous section (CBECS,
2006) found an average cost of $2.52 per square foot in 2003 for 4,400 buildings in the
Continental U.S (Tables C4 and C13 of CBDES, 2006). Schools in Fairbanks have an average
cost for energy of $2.42 per square foot while Anchorage schools average $2.11 per square
foot. The chart below shows the Nenana City Office relative to these values. More details are
included in Appendix H.
$4.33
$2.42
$2.11
$0.00
$0.50
$1.00
$1.50
$2.00
$2.50
$3.00
$3.50
$4.00
$4.50
$5.00
$/Sq. Ft Annual Energy Cost Index (Total Cost/ SF)
Nenana City Office Fairbanks Schools Anchorage Schools
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
12
3.4 Seasonal Energy Use Patterns
Energy consumption is often highly correlated with seasonal climate and usage variations. The
graphs below show the electric and fuel consumption of this building over the course of two
years. The lowest monthly use is called the baseline use. The electric baseline often reflects
year round lighting consumption while the heating fuel baseline often reflects year round hot
water usage. The clear relation of increased energy usage during periods of cold weather can
be seen in the months with higher usage.
Fuel data was unavailable before November 2009.
0
500
1000
1500
2000
2500
Apr-09Jun-09Aug-09Oct-09Dec-09Feb-10Apr-10Jun-10Aug-10Oct-10Dec-10Feb-11KWH Electrical Consumption
0
200
400
600
800
1,000
1,200
Apr-09Jun-09Aug-09Oct-09Dec-09Feb-10Apr-10Jun-10Aug-10Oct-10Dec-10Feb-11Gallons Fuel Oil Deliveries
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
13
3.5 Future Energy Monitoring
Energy accounting is the process of tracking energy consumption and costs. It is important for
the building owner or manager to monitor and record both the energy usage and cost each
month. Comparing trends over time can assist in pinpointing major sources of energy usage and
aid in finding effective energy efficiency measures. There are two basic methods of energy
accounting: manual and automatic. Manual tracking of energy usage may already be performed
by an administrative assistant: however if the records are not scrutinized for energy use, then
the data is merely a financial accounting. Digital energy tracking systems can be installed. They
display and record real-time energy usage and accumulated energy use and cost. There are
several types which have all of the information accessible via Ethernet browser.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
14
4.0 MODELING ENERGY CONSUMPTION
After benchmarking of a building is complete and the site visit has identified the specific systems
in the building, a number of different methods are available for quantifying the overall energy
consumption and to model the energy use. These range from relatively simple spreadsheets to
commercially available modeling software capable of handling complex building systems.
NORTECH has used several of these programs and uses the worksheets and software that
best matches the complexity of the building and specific energy use that is being evaluated.
Modeling of an energy efficiency measure (EEM) requires an estimate of the current energy
used by the specific feature, the estimated energy use of the proposed EEM and its installed
cost. EEMs can range from a single simple upgrade, such as light bulb type or type of motor, to
reprogramming of the controls on more complex systems. While the need for a major retrofit
can typically be identified by an energy audit, the specific system upgrades often require
collecting additional data and engineering and design efforts that are beyond the scope of the
Level II energy audit.
Based on the field inspection results and discussions with the building owners/operators,
auditors developed potential EEMs for the facility. Common EEMs that could apply to almost
every older building include:
• Reduce the envelope heat losses through:
o increased building insulation, and
o better windows and doors
• Reduce temperature difference between inside and outside using setback thermostats
• Upgrade inefficient:
o lights,
o motors,
o refrigeration units, and
o other appliances
• Reduce running time of lights/appliances through:
o motion sensors,
o on/off timers,
o light sensors, and
o other automatic/programmable systems
The objective of the following sections is to describe how the overall energy use of the building
was modeled and the potential for energy savings. The specific EEMs that provide these overall
energy savings are detailed in Appendix A of this report. While the energy savings of an EEM is
unlikely to change significantly over time, the cost savings of an EEM is highly dependent on the
current energy price and can vary significantly over time. An EEM that is not currently
recommended based on price may be more attractive at a later date or with higher energy
prices.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
15
4.1 Understanding How AkWarm Models Energy Consumption
NORTECH used the AkWarm model for evaluating the overall energy consumption at Nenana
City Office. The AkWarm program was developed by the Alaska Housing Finance Corporation
(AHFC) to model residential energy use. The original AkWarm is the modeling engine behind
the successful residential energy upgrade program that AHFC has operated for a number of
years. In the past few years, AHFC has developed a version of this model for commercial
buildings.
Energy use in buildings is modeled by calculating energy losses and consumption, such as:
• Heat lost through the building envelope components, including windows, doors,
walls, ceilings, crawlspaces, and foundations. These heat losses are computed for
each component based on the area, heat resistance (R-value), and the difference
between the inside temperature and the outside temperature. AkWarm has a library
of temperature profiles for villages and cities in Alaska.
• Window orientation, such as the fact that south facing windows can add heat in the
winter but north-facing windows do not.
• Inefficiencies of the heating system, including the imperfect conversion of fuel oil or
natural gas due to heat loss in exhaust gases, incomplete combustion, excess air,
etc. Some electricity is also consumed in moving the heat around a building through
pumping.
• Inefficiencies of the cooling system, if one exists, due to various imperfections in a
mechanical system and the required energy to move the heat around.
• Lighting requirements and inefficiencies in the conversion of electricity to light;
ultimately all of the power used for lighting is converted to heat. While the heat may
be useful in the winter, it often isn’t useful in the summer when cooling may be
required to remove the excess heat. Lights are modeled by wattage and operational
hours.
• Use and inefficiencies in refrigeration, compressor cooling, and heat pumps. Some
units are more efficient than others. Electricity is required to move the heat from
inside a compartment to outside it. Again, this is a function of the R-Value and the
temperature difference between the inside and outside of the unit.
• Plug loads such as computers, printers, mini-fridges, microwaves, portable heaters,
monitors, etc. These can be a significant part of the overall electricity consumption
of the building, as well as contributing to heat production.
• The schedule of operation for lights, plug loads, motors, etc. is a critical component
of how much energy is used.
AkWarm adds up these heat losses and the internal heat gains based on individual unit usage
schedules. These estimated heat and electrical usages are compared to actual use on both a
yearly and seasonal basis. If the AkWarm model is within 5 % to 10% of the most recent 12
months usage identified during benchmarking, the model is considered accurate enough to
make predictions of energy savings for possible EEMs.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
16
4.2 AkWarm Calculated Savings for the Nenana City Office
Based on the field inspection results and discussions with the building owners/operators,
auditors developed potential EEMs for the facility. These EEMs are then entered into AkWarm
to determine if the EEM saves energy and is cost effective (i.e. will pay for itself). AkWarm
calculates the energy and money saved by each EEM and calculates the length of time for the
savings in reduced energy consumption to pay for the installation of the EEM. AkWarm makes
recommendations based on the Savings/Investment Ratio (SIR), which is defined as ratio of the
savings generated over the life of the EEM divided by the installed cost. Higher SIR values are
better and any SIR above one is considered acceptable. If the SIR of an EEM is below one, the
energy savings will not pay for the cost of the EEM and the EEM is not recommended.
Preferred EEMs are listed by AkWarm in order of the highest SIR.
A summary of the savings from the recommended EEMs are listed in this table.
Description Space
Heating
Water
Heating Lighting Refrigeration Other
Electrical
Service
Fees Total
Existing
Building $19,474 $350 $2,149 $327 $410 $210 $22,919
With All
Proposed
Retrofits
$7,675 $366 $1,421 $247 $392 $210 $10,311
Savings $11,799 -$16 $728 $80 $18 $0 $12,608
Savings in these categories represent the overall savings for the building, and reflect any added
cost that might occur because of a retrofit. For example, installing more efficient lights will
increase the heating load and creating or lowering an unoccupied setback temperature will
increase hot water heat losses and cost.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
17
4.3 Additional Modeling Methods
The AkWarm program effectively models wood-framed and other buildings with standard
heating systems and relatively simple HVAC systems. AkWarm models of more complicated
mechanical systems are sometimes poor due to a number of simplifying assumptions and
limited input of some variables. Furthermore, AKWarm is unable to model complex HVAC
systems such as variable frequency motors, variable air volume (VAV) systems, those with
significant digital or pneumatic controls or significant heat recovery capacity. In addition, some
other building methods and occupancies are outside AkWarm capabilities.
This report section is included in order to identify benefits from modifications to those more
complex systems or changes in occupant behavior that cannot be addressed in AkWarm.
The Nenana City Office was calibrated within NORTECH standards in AKWarm. Retrofits for the
HVAC system were adequately modeled in AkWarm and did not require additional outside
calculations.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
18
5.0 BUILDING OPERATION AND MAINTENANCE (O & M)
5.1 Operations and Maintenance
A well-implemented operation and maintenance (O & M) plan is often the driving force behind
energy savings. Such a plan includes preserving institutional knowledge, directing preventative
maintenance, and scheduling regular inspections of each piece of HVAC equipment within the
building. Routine maintenance includes the timely replacement of filters, belts and pulleys, the
proper greasing of bearings and other details such as topping off the glycol tanks. Additional
benefits to a maintenance plan are decreased down time for malfunctioning equipment, early
indications of problems, prevention of exacerbated maintenance issues, and early detection of
overloading/overheating issues. A good maintenance person knows the building’s equipment
well enough to spot and repair minor malfunctions before they become major retrofits.
Operations and Maintenance staff implementing a properly designed O & M plan will:
• Track and document
o Renovations and repairs,
o Utility bills and fuel consumption, and
o System performance.
• Keep available for reference
o A current Building Operating Plan including an inventory of installed systems,
o The most recent available as-built drawings,
o Reference manuals for all installed parts and systems, and
o An up-to-date inventory of on-hand replacement parts.
• Provide training and continuing education for maintenance personnel.
• Plan for commissioning and re-commissioning at appropriate intervals.
5.2 Commissioning
Commissioning of a building is the verification that the HVAC systems perform within the design
or usage ranges of the Building Operating Plan. This process ideally, though seldom, occurs as
the last phase in construction. HVAC system operation parameters degrade from ideal over time
due to incorrect maintenance, improper replacement pumps, changes in facility tenants or
usage, changes in schedules, and changes in energy costs or loads. Ideally, re-commissioning
of a building should occur every five to ten years. This ensures that the HVAC system meets
the potentially variable use with the most efficient means.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
19
5.3 Building Specific Recommendations
The Nenana City Office is approximately 57 years old and while the structural portions of the
building are still usable, it was constructed in an era when energy was less costly than today.
The amount of effort to renovate the facility could be better spent in building a new one that can
serve Nenana for the next 50 years in an economical manner. The energy savings alone
between this building and a new, efficient building will pay for almost half the cost of a new
building.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
20
APPENDICES
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
21
Appendix A Recommended Energy Efficiency Measures
A number of Energy Efficiency Measures (EEMs) are available to reduce the energy use and
overall operating cost for the facility. The EEMs listed below are those recommended by
AkWarm based on the calculated savings/investment ration (SIR) as described in Appendix E.
AkWarm also provides a breakeven cost, which is the maximum initial cost of the EEM that will
still return a SIR of one or greater.
This section describes each recommended EEM and identifies the potential energy savings and
installation costs. This also details the calculation of breakeven costs, simple payback, and the
SIR for each recommendation. The recommended EEMs are grouped together generally by the
overall end use that will be impacted.
A.1 Temperature Control
Programmable thermostats should be installed and programmed in the entire building
Programmable thermostats allow for automatic temperature setback, which reduce usage more
reliably than manual setbacks. Reduction of the nighttime temperature set points will decrease
the energy usage.
Rank Building Space Recommendation
1 Heated Space from Furnace 2
Implement a Heating Temperature
Unoccupied Setback to 62.0 deg F for the
Heated Space from Furnace 2 space.
Installation Cost $150 Estimated Life of Measure (yr.) 15 Energy Savings (/yr.) $1,319
Breakeven Cost $17,804 Savings-to-Investment Ratio 120 Simple Payback (yr.) 0
Rank Building Space Recommendation
2 Heated Space from Furnace 1
Implement a Heating Temperature
Unoccupied Setback to 62.0 deg F for the
Heated Space from Furnace 1 space.
Installation Cost $150 Estimated Life of Measure (yr.) 15 Energy Savings (/yr.) $588
Breakeven Cost $7,936 Savings-to-Investment Ratio 53 Simple Payback (yr.) 0
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
22
A.2 Electrical Loads
A.2.1 Lighting
The electricity used by lighting eventually ends up as heat in the building. In areas where
electricity is more expensive than other forms of energy, or in areas where the summer
temperatures require cooling; this additional heat can be both wasteful and costly. Converting
to more efficient lighting reduces cooling loads in the summer and allows the user to control
heat input in the winter. The conversion from T12 (one and a half inch fluorescent bulbs) to T8
(one inch), T5 (5/8 inch), Compact Fluorescent Lights (CFL), or LED bulbs provides a significant
increase in efficiency. LED bulbs can be directly placed in existing fixtures. The LED bulb
bypasses the ballast altogether, which removes the often irritating, “buzzing” noise that
magnetic ballasts tend to make.
Rank Location Existing Condition Recommendation
8 Janitor Closet INCAN (2) A Lamp, Std 75W with Manual
Switching
Replace with FLUOR (2) CFL,
Spiral 13 W
Installation Cost $4 Estimated Life of Measure (yr.) 7 Energy Savings (/yr.) $1
Breakeven Cost $9 Savings-to-Investment Ratio 2.2 Simple Payback (yr.) 3
Rank Location Existing Condition Recommendation
9 Outdoor Lighting 5 MH 100 Watt StdElectronic with Manual
Switching
Replace with 5 LED 12W
Module StdElectronic
Installation Cost $1,000 Estimated Life of Measure (yr.) 10 Energy Savings (/yr.) $244
Breakeven Cost $2,056 Savings-to-Investment Ratio 2.1 Simple Payback (yr.) 4
Rank Location Existing Condition Recommendation
16 Storage Room- 20 INCAN A Lamp, Std 75W with Manual
Switching
Replace with FLUOR CFL, A
Lamp 15W
Installation Cost $4 Estimated Life of Measure (yr.) 7 Energy Savings (/yr.) $1
Breakeven Cost $5 Savings-to-Investment Ratio 1.2 Simple Payback (yr.) 5
Rank Location Existing Condition Recommendation
17 Combined T12
Lighting
31 FLUOR (2) T12 4' F40T12 40W
Standard Magnetic with Manual Switching
Replace with 31 FLUOR (2) T8
4' F32T8 25W Energy-Saver
Instant HighEfficElectronic
Installation Cost $2,170 Estimated Life of Measure (yr.) 10 Energy Savings (/yr.) $289
Breakeven Cost $2,267 Savings-to-Investment Ratio 1.0 Simple Payback (yr.) 8
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
23
A.2.2 Other Electrical Loads
The soda machine in the lobby does not need to be on during the night and unoccupied hours
as there are not perishable items within it. Installing a timing device to reduce on time to
business hours will save energy.
The large copier in the office does not go to standby mode when not in use, though the function
is an option. Resetting the controls to allow the copier to utilize the standby mode will save
energy.
A.3 Building Envelope: Recommendations for change
A.3.1 Exterior Walls
The exterior walls do not provide an effective thermal protection when compared to current
Interior building standards however adding insulation to the walls is not cost-effective at this
time.
Rank Location Existing Condition Recommendation
3 Lobby Soda Vending Machine
Put soda machine on a timing
device to reduce run time to
business hours only.
Installation Cost $26 Estimated Life of Measure (yr.) 7 Energy Savings (/yr.) $27
Breakeven Cost $150 Savings-to-Investment Ratio 5.8 Simple Payback (yr.) 1
Rank Location Existing Condition Recommendation
7 Copy Room CSPro Copier with Manual Switching Reset controls to allow the
copier to go to standby mode
when not in use.
Installation Cost $25 Estimated Life of Measure (yr.) 7 Energy Savings (/yr.) $10
Breakeven Cost $56 Savings-to-Investment Ratio 2.2 Simple Payback (yr.) 3
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
24
A.3.2 Foundation and/or Crawlspace
The floor and footings have no insulation protection and very little soil cover. Adding rigid foam
insulation flat along the footprint of the building and adding extra soil cover will protect the
footings.
The exterior of the crawlspace is only insulated on the north wall. Adding rigid foam insulation to
the exterior of the rest of crawlspace will reduce heat losses.
A.3.3 Roofing and Ceiling
The existing built-up, flat roof has insufficient insulation and poor drainage. Replacing the
roofing with at least R-60 insulation and providing proper roof drainage will reduce envelope
energy losses.
Rank Location Existing Condition Recommendation
6
On- or Below-Grade
Floor, Perimeter:
House
Insulation for 0' to 2' Perimeter: None
Insulation for 2' to 4' Perimeter: None
Insulation Quality: Damaged
Modeled R-Value: 6.7
Install 4' of R-30 rigid board
insulation on Perimeter of Crawl
Space Floor.
Installation Cost $5,667 Estimated Life of Measure (yr.) 30 Energy Savings (/yr.) $751
Breakeven Cost $17,745 Savings-to-Investment Ratio 3.1 Simple Payback (yr.) 8
Rank Location Existing Condition Recommendation
12
Below- (part) Grade
Wall: Exterior Crawl
Space Walls
Wall Type: All Weather Wood
Insul. Sheathing: None
Framed Wall: 2 x 6, 16" on center
R-13 Batt: FG or RW, 3.63 inches
Insulation Quality: Damaged
Modeled R-Value: 14.3
Install R-10 rigid foam board to
interior or exterior side of wall.
Does not include cost of
coverings.
Installation Cost $2,729 Estimated Life of Measure (yr.) 30 Energy Savings (/yr.) $214
Breakeven Cost $5,050 Savings-to-Investment Ratio 1.9 Simple Payback (yr.) 13
Rank Location Existing Condition Recommendation
14
Cathedral Ceiling:
Nenana City Hall
Roof
Framing Type: Standard
Framing Spacing: 16 inches
Insulated Sheathing: XPS (Blue/Pink
Foam), 1.25 inches
Bottom Insulation Layer: None
Top Insulation Layer: None
Modeled R-Value: 9.4
Remove existing roofing and
replace with a built up roof
system including at least 12-
inches of rigid foam board
insulation. Ensure proper roof
drainage.
Installation Cost $59,493 Estimated Life of Measure (yr.) 30 Energy Savings (/yr.) $3,563
Breakeven Cost $84,182 Savings-to-Investment Ratio 1.4 Simple Payback (yr.) 17
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
25
A.3.4 Windows
The existing windows are in poor condition and contribute to envelope heat losses. The
windows should be replaced by a professional window installer to reduce heat loss.
A.3.5 Doors
The existing doors are old, residential style doors. The doors and weather stripping should be
replaced by a professional installer.
Rank Location Existing Condition Recommendation
13
Windows: File
Room, offices,
hallway, conference,
and entry
Glass: Double, glass
Certified U-Value: 0.80
Solar Heat Gain Coefficient: 0.46
Replace existing window with U-
0.22 vinyl window
Installation Cost $10,919 Estimated Life of Measure (yr.) 20 Energy Savings (/yr.) $953
Breakeven Cost $16,553 Savings-to-Investment Ratio 1.5 Simple Payback (yr.) 11
Rank Location Existing Condition Recommendation
15 Window/Skylight:
Front Lobby- 8
Glass: Double, glass
Certified U-Value: 0.80
Solar Heat Gain Coefficient: 0.46
Replace existing window with U-
0.22 vinyl window
Installation Cost $8,416 Estimated Life of Measure (yr.) 20 Energy Savings (/yr.) $661
Breakeven Cost $11,475 Savings-to-Investment Ratio 1.4 Simple Payback (yr.) 13
Rank Location Existing Condition Recommendation
4 Exterior Door:
Storage- 15, 16, 17
Door Type: Entrance, Metal, polyurethane
core, metal edge
Modeled R-Value: 2.5
Remove existing door and install
pre-hung U-0.16 insulated door,
including hardware.
Installation Cost $534 Estimated Life of Measure (yr.) 30 Energy Savings (/yr.) $91
Breakeven Cost $2,140 Savings-to-Investment Ratio 4.0 Simple Payback (yr.) 6
Rank Location Existing Condition Recommendation
10 Exterior Door: File
Room
Door Type: Entrance, Metal, polyurethane
core, metal edge
Modeled R-Value: 2.5
Remove existing door and install
pre-hung U-0.16 insulated door,
including hardware.
Installation Cost $558 Estimated Life of Measure (yr.) 30 Energy Savings (/yr.) $47
Breakeven Cost $1,102 Savings-to-Investment Ratio 2.0 Simple Payback (yr.) 12
Rank Location Existing Condition Recommendation
11 Exterior Door:
Office- 3
Door Type: Entrance, Metal, polyurethane
core, metal edge
Modeled R-Value: 2.5
Remove existing door and install
pre-hung U-0.16 insulated door,
including hardware.
Installation Cost $534 Estimated Life of Measure (yr.) 30 Energy Savings (/yr.) $45
Breakeven Cost $1,055 Savings-to-Investment Ratio 2.0 Simple Payback (yr.) 12
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
26
A.4 Building Heating System / Air Conditioning
A.4.1 Heating and Heat Distribution
The existing furnaces are old and in very poor condition. Both units should be replaced with the
most energy efficient replacement alternatives.
The crawlspace is heated by the un-insulated furnace ducts, however once the crawlspace and
footings are fully insulated, the ducts can be sealed and insulated in small portions so long as
the crawlspace temperature is monitored in the cold months. The crawlspace should be kept
warm enough to ensure that the water and sewer lines do not freeze. The ducts should be
insulated until the crawlspace temperature is maintained in the coldest months.
A.4.2 Air Conditioning
No air conditioning system is installed in the building, therefore no recommendations are made
in this category.
A.4.3 Ventilation
No air conditioning system is installed in the building, therefore no recommendations are made
in this category.
A.4.4 Air Changes and Air Tightening
Air losses through the doors and windows were high in the building however the door and
window replacements will provide the necessary air tightening. No additional air
recommendations are suggested.
Rank Recommendation
5 Replace existing furnaces with new, energy efficient models, apply mastic to ductwork in crawlspace.
Installation Cost $18,000 Estimated Life of Measure (yr.) 20 Energy Savings (/yr.) $3,804
Breakeven Cost $64,869 Savings-to-Investment Ratio 3.6 Simple Payback (yr.) 5
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
27
Appendix B Energy Efficiency Measures that are NOT Recommended
As indicated in other sections of the report, a number of potential EEMs were identified that
were determined to be NOT cost effective by the AkWarm model. These EEMs are not
currently recommended on the basis of energy savings alone because each may only save a
small amount of energy, have a high capital cost, or be expensive to install. While each of
these EEMs is not cost effective at this time, future changes in building use such as longer
operating hours, higher energy prices, new fixtures or hardware on the market, and decreases
in installation effort may make any of these EEMs cost effective in the future. These potential
EEMs should be reviewed periodically to identify any changes to these factors that would
warrant re-evaluation.
Although these upgrades are not currently cost effective on an energy cost basis, the fixtures,
hardware, controls, or operational changes described in these EEMs should be considered
when replacing an existing fixture or unit for other reasons. For example, replacing an existing
window with a triple-pane window may not be cost effective based only on energy use, but if a
window is going to be replaced for some other reason, then the basis for a decision is only the
incremental cost of upgrading from a less efficient replacement window to a more efficient
replacement window. That incremental cost difference will have a significantly shorter payback,
especially since the installation costs are likely to be the same for both units.
The following measures were not found to be cost-effective:
Rank Feature/Location Improvement Description
Annual
Energy
Savings
Installed
Cost
Savings to
Investment
Ratio, SIR
Simple
Payback
(Years)
17 Lighting: Combined
T12 Lighting
Replace with 31 FLUOR (2)
T8 4' F32T8 25W Energy-
Saver Instant
HighEfficElectronic
$266 $2,170 0.94 8.2
18 Above-Grade Wall:
City Hall Walls
Install R-25 rigid foam board
to exterior and cover with T1-
11 siding or equivalent.
$977 $29,230 0.79 30
19 Lighting: Storage- 18 Replace with 2 FLUOR CFL,
Spiral 13 W $1 $5 0.72 8.2
20 Lighting: Boiler
Rooms
Replace with FLUOR CFL,
Spiral 15 W $0 $5 0.59 13
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
28
Appendix C Significant Equipment List
HVAC Equipment
Equipment Manufacturer Model No. Fuel Type Estimated
Efficiency Notes
Furnace Dornback --- #2 Fuel Oil 68% Two Units, old, no recent
maintenance
Fans Dornback --- Electric --- Two units
Lighting
Location Lighting Type Bulb Type Quantity KWH/YR Cost/YR
Office/Hall Fluorescent T8 61 4,579 $ 962
Office/Hall Fluorescent T12 31 3,954 830
Outdoors Metal Halide 100-W 5 1,298 273
Janitor Closet,
Storage, Boiler
Rooms
Incandescent A bulb 6 29 6
Energy Consumption calculated by AkWarm based on wattage, schedule and an electric rate of $ 0.21kWh.
Plug Loads
Equipment Location Manufacturer KWH/YR Cost/YR
Computers Offices Varies 1,341 $ 282
Soda Machine Lobby Dixie Narco 1,100 231
Refrigerator File Room E Wave 400 84
Assorted Office Extras Offices Varies 341 72
Copy/Print Offices Varies 198 42
Energy Consumption calculated by AkWarm based on wattage, schedule and an electric rate of $ 0.21kWh.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
29
Appendix D Local Utility Rate Structure
The information in this section was provided directly from the local utility or gathered from the
local utility’s publicly available information at the time of the audit. All language used in this
section was provided by the local utility and believed to be current at the time of the audit.
Energy use terms, specific fees, and other specific information are subject to change. Updated
rate structure information should be gathered from the utility during future discussion of rates,
rate structures and utility pricing agreements.
Golden Valley Electric Association Rate Structure:
GS-1 General Service Effective Rates***
Customer Charge $20.00
Utility Charge $0.08712 / kWh $0.19655 / kWh
***The effective rate is all of the charges totaled together and divided by the kilowatt hour used.
GVEA offers five different rates to its members, depending on the classification of the service
provided. The rates are divided into two categories: Residential and General Service (GS).
Eighty-five percent of the electric services on GVEA's system are single-family dwellings,
classified under the Residential rate. The four General Service rates apply to small and large
power users that do not qualify for the Residential rate.
The General Service rates break down as follows:
GS-1 General Service Services under 50 kilowatts (kW) of demand per billing cycle
GS-2(S) Large General Service
Secondary Services 50 kW and higher of demand per billing cycle
GS-2(P) Large General Service
Primary Services at primary voltage
GS-3 Industrial Service Services at transmission voltage
Customer Charge
A flat fee that covers costs for meter reading, billing and customer service.
Utility Charge (kWh charge)
This charge is multiplied by the number of kilowatt-hours (kWh) used in a monthly billing period.
It covers the costs to maintain power plants and substations, interest on loans as well as wires,
power poles and transformers.
Fuel and Purchased Power
This charge is based on a combination of forecasted and actual power costs. The monthly
charge allows Golden Valley to pass on increases and decreases in fuel and energy purchases
to our members. It is calculated quarterly and multiplied by the kilowatt-hours used each month.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
30
Regulatory Charge
This charge of .000492 per kWh is set by the Regulatory Commission of Alaska (RCA). Since
November 1, 1992, the Regulatory Commission of Alaska has been funded by a Regulatory
Charge to the utilities it regulates rather than through the State general fund. The charge,
labeled "Regulatory Cost Charge." on your bill, is set by the RCA, and applies to all retail
kilowatt-hours sold by regulated electric utilities in Alaska.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
31
Appendix E Analysis Methodology
Data collected was processed using AkWarm energy use software to estimate current energy
consumption by end usage and calculate energy savings for each of the proposed energy
efficiency measures (EEMs). In addition, separate analysis may have been conducted to
evaluate EEMs that AkWarm cannot effectively model to evaluate potential reductions in annual
energy consumption. Analyses were conducted under the direct supervision of a Certified
Energy Auditor, Certified Energy Manager, or a Professional Engineer.
EEMs are evaluated based on building use, maintenance and processes, local climate
conditions, building construction type, function, operational schedule and existing conditions.
Energy savings are calculated based on industry standard methods and engineering
estimations. Each model created in AkWarm is carefully compared to existing utility usage
obtained from utility bills. The AkWarm analysis provides a number of tools for assessing the
cost effectiveness of various improvement options. The primary assessment value used in this
audit report is the Savings/Investment Ratio (SIR). The SIR is a method of cost analysis that
compares the total cost savings through reduced energy consumption to the total cost of a
project over its assumed lifespan, including both the construction cost and ongoing maintenance
and operating costs. Other measurement methods include Simple Payback, which is defined as
the length of time it takes for the savings to equal the total installed cost and Breakeven Cost,
which is defined as the highest cost that would yield a Savings/Investment Ratio of one.
EEMs are recommended by AkWarm in order of cost-effectiveness. AkWarm first calculates
individual SIRs for each EEM, and then ranks the EEMs by SIR, with higher SIRs at the top of
the list. An individual EEM must have a SIR greater than or equal to one in order to be
recommended by AkWarm . Next AkWarm modifies the building model to include the installation
of the first EEM and then re-simulates the energy use. Then the remaining EEMs are re-
evaluated and ranked again. AkWarm goes through this iterative process until all suggested
EEMs have been evaluated.
Under this iterative review process, the savings for each recommended EEM is calculated
based on the implementation of the other, more cost effective EEMs first. Therefore, the
implementation of one EEM affects the savings of other EEMs that are recommended later.
The savings from any one individual EEM may be relatively higher if the individual EEM is
implemented without the other recommended EEMs. For example, implementing a reduced
operating schedule for inefficient lighting may result in relatively higher savings than
implementing the same reduced operating schedule for newly installed lighting that is more
efficient. If multiple EEMs are recommended, AkWarm calculates a combined savings.
Inclusion of recommendations for energy savings outside the capability of AkWarm will impact
the actual savings from the AkWarm projections. This will almost certainly result in lower
energy savings and monetary savings from AkWarm recommendations. The reality is that only
so much energy is consumed in a building. Energy savings from one EEM reduces the amount
of energy that can be saved from additional EEMs. For example, installation of a lower wattage
light bulb does not save energy or money if the bulb is never turned on because of a schedule
or operational change at the facility.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
32
Appendix F Audit Limitations
The results of this audit are dependent on the input data provided and can only act as an
approximation. In some instances, several EEMs or installation methods may achieve the
identified potential savings. Actual savings will depend on the EEM selected, the price of
energy, and the final installation and implementation methodology. Competent tradesmen and
professional engineers may be required to design, install, or otherwise implement some of the
recommended EEMs. This document is an energy use audit report and is not intended as a
final design document, operation, and maintenance manual, or to take the place of any
document provided by a manufacturer or installer of any device described in this report.
Cost savings are calculated based on estimated initial costs for each EEM. Estimated costs
include labor and equipment for the full up-front investment required to implement the EEM.
The listed installation costs within the report are conceptual budgetary estimates and should not
be used as design estimates. The estimated costs are derived from Means Cost Data, industry
publications, local contractors and equipment suppliers, and the professional judgment of the
CEA writing the report and based on the conditions at the time of the audit.
Cost and energy savings are approximations and are not guaranteed.
Additional significant energy savings can usually be found with more detailed auditing
techniques that include actual measurements of electrical use, temperatures in the building and
HVAC ductwork, intake and exhaust temperatures, motor runtime and scheduling, and infrared,
air leakage to name just a few. Implementation of these techniques is the difference between a
Level III Energy Audit and the Level II Audit that has been conducted.
Disclaimer: "This report was prepared as an account of work sponsored by an agency of the
United States Government. Neither the United States Government nor any agency thereof, nor
any of their employees, makes any warranty, express or implied, or assumes any legal liability
or responsibility for the accuracy, completeness, or usefulness of any information, apparatus,
product, or process disclosed, or represents that its use would not infringe privately owned
rights. Reference herein to any specific commercial product, process, or service by trade name,
trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement,
recommendation, or favoring by the United States Government or any agency thereof. The
views and opinions of authors expressed herein do not necessarily state or reflect those of the
United States Government or any agency thereof."
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
33
Appendix G References
Although not all documents listed below are specifically referenced in this report, each contains
information and insights considered valuable to most buildings.
Alaska Department of Education and Early Development; Education Support Services/Facilities.
(1999). Alaska School Facilities Preventative Maintenance Handbook. Juneau, AK:
Alaska Department of Education and Early Development.
Alaska Housing Finance Corportation. (2010). Retrofit Energy Assessment for Loans. AHFC.
ASHRAE. (1997). 1997 ASHRAE Handbook: Fundamentals. Atlanta, GA: ASHRAE.
ASHRAE. (2007). ASHRAE Standard 105-2007 Expressing and Comparing Building Energy
Performance. Retrieved from ASHRAE: www.ashrae.org
ASHRAE. (2007). ASHRAE Standard 90.1-2007 Energy Standards for buildings Except Low-
Rise Residential Buildings. Retrieved from ASHRAE: www.ashrae.org
ASHRAE. (2010). ASHRAE Standard 62.1-2010 Ventilaton for Acceptable Indoor Air Quality.
Retrieved from ASHRAE: www.ashrae.org
ASHRAE. (2010). ASHRAE Standard 62.2-2010 Ventilation and Acceptable Indoor Air Quality in
Low Rise Residential Buildings. Retrieved from ASHRAE: www.ashrae.org
ASHRAE RP-669 and SP-56. (2004). Procedures for Commercial Building Energy Audits.
Atlanta, GA: ASHRAE.
Coad, W. J. (1982). Energy Engineering and Management for Building Systems. Scarborough,
Ontario, Canada: Van Nostrand Reinhold Company.
Daley, D. T. (2008). The Little Black Book of Reliability Management. New York, NY: Industrial
Press, Inc.
Federal Energy Management Program. (2004, March 3). Demand Controlled Ventilation Using
CO2 Sensors. Retrieved 2011, from US DOE Energy Efficiency and Renewable Energy:
http://www.eere.energy.gov/femp/pdfs/fta_co2.pdf
Federal Energy Management Program. (2006, April 26). Low-Energy Building Design
Guidelines. Retrieved 2011, from Department of Energy; Federal Energy Management
Program: http://www.eren.doe.gov/femp/
Institute, E. a. (2004). Variable Speed Pumping: A Guide to Successful Applications. Oxford,
UK: Elsevier Advanced Technology.
International Code Council. (2009). International Energy Conservation Code. Country Club Hills,
IL: International Code Council, Inc.
Leach, M., Lobato, C., Hirsch, A., Pless, S., & Torcellini, P. (2010, September). Technical
Support Document: Strategies for 50% Energy Savings in Large Office Buildings.
Retrieved 2011, from National Renewable Energy Laboratory:
http://www.nrel.gov/docs/fy10osti/49213.pdf
Thumann, P.E., C.E.M., A., Younger, C.E.M., W. J., & Niehus, P.E., C.E.M., T. (2010).
Handbook of Energy Audits Eighth Edition. Lilburn, GA: The Fairmont Press, Inc.
U.S. Energy Information Administration. (2006). Commercial Building Energy Consumption
Survey (CBECS). Retrieved 2011, from Energy Information Administration:
http://www.eia.gov/emeu/cbecs/
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
34
Appendix H Typical Energy Use and Cost – Fairbanks and Anchorage
This report provides data on typical energy costs and use on selected building in Fairbanks and
Anchorage, Alaska for comparative purposes only. The values provided by the US Energy
Information Administration CBECS study included a broader range of building types for the
Continental U.S. are not necessarily good comparatives for buildings and conditions in Alaska.
An assortment of values from CBECS may be found in Appendix I.
The Alaska data described in this report came from a benchmarking study NORTECH and other
Technical Services Providers (TSPs) completed on publicly owned buildings in Alaska under
contract with AHFC. This study acquired actual utility data for municipal buildings and schools
in Alaska for the two recent full years. The utility data included costs and quantities including
fuel oil, electricity, propane, wood, steam, and all other energy source usage. This resulted in a
database of approximately 900 buildings. During the course of the benchmarking study, the
comparisons made to the CBECS data appeared to be inappropriate for various reasons.
Therefore, this energy use audit report references the average energy use and energy cost of
Anchorage and Fairbanks buildings as described below.
The Alaska benchmarking data was evaluated in order to find valid comparison data. Buildings
with major energy use information missing were eliminated from the data pool. After detailed
scrutiny of the data, the most complete information was provided to NORTECH by the
Fairbanks North Star Borough School District (FNSBSD) and the Anchorage School District
(ASD). The data sets from these two sources included both the actual educational facilities as
well as the district administrative buildings and these are grouped together in this report as
Fairbanks and Anchorage schools. These two sources of information, being the most complete
and reasonable in-state information, have been used to identify an average annual energy
usage for Fairbanks and for Anchorage in order to provide a comparison for other facilities in
Alaska.
Several factors may limit the comparison of a specific facility to these regional indicators. In
Fairbanks, the FNSBSD generally uses number two fuel oil for heating needs and electricity is
provided by Golden Valley Electric Association (GVEA). GVEA produces electricity from a coal
fired generation plant with additional oil generation upon demand. A few of the FNSBSD
buildings in this selection utilize district steam and hot water. The FNSBSD has recently (the
last ten years) invested significantly in envelope and other efficiency upgrades to reduce their
operating costs. Therefore a reader should be aware that this selection of Fairbanks buildings
has energy use at or below average for the entire Alaska benchmarking database.
Heating in Anchorage is through natural gas from the nearby natural gas fields. Electricity is
also provided using natural gas. As the source is nearby and the infrastructure for delivery is in
place, energy costs are relatively low in the area. As a result, the ASD buildings have lower
energy costs, but higher energy use, than the average for the entire benchmarking database.
These special circumstances should be considered when comparing the typical annual energy
use for particular buildings.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
35
Appendix I Typical Energy Use and Cost – Continental U.S.
Released: Dec 2006
Next CBECS will be conducted in 2007
Table C3. Consumption and Gross Energy Intensity for Sum of Major Fuels for Non-Mall Buildings, 2003
All Buildings* Sum of Major Fuel Consumption
Number of
Buildings
(thousand)
Floor
space
(million
square
feet)
Floor space
per Building
(thousand
square feet)
Total
(trillion
BTU)
per
Building
(million
BTU)
per
Square Foot
(thousand
BTU)
per
Worker
(million
BTU)
All Buildings* 4,645 64,783 13.9 5,820 1,253 89.8 79.9
Building Floor space (Square Feet)
1,001 to 5,000 2,552 6,789 2.7 672 263 98.9 67.6
5,001 to 10,000 889 6,585 7.4 516 580 78.3 68.7
10,001 to 25,000 738 11,535 15.6 776 1,052 67.3 72.0
25,001 to 50,000 241 8,668 35.9 673 2,790 77.6 75.8
50,001 to 100,000 129 9,057 70.4 759 5,901 83.8 90.0
100,001 to 200,000 65 9,064 138.8 934 14,300 103.0 80.3
200,001 to 500,000 25 7,176 289.0 725 29,189 101.0 105.3
Over 500,000 7 5,908 896.1 766 116,216 129.7 87.6
Principal Building Activity
Education 386 9,874 25.6 820 2,125 83.1 65.7
Food Sales 226 1,255 5.6 251 1,110 199.7 175.2
Food Service 297 1,654 5.6 427 1,436 258.3 136.5
Health Care 129 3,163 24.6 594 4,612 187.7 94.0
Inpatient 8 1,905 241.4 475 60,152 249.2 127.7
Outpatient 121 1,258 10.4 119 985 94.6 45.8
Lodging 142 5,096 35.8 510 3,578 100.0 207.5
Retail (Other Than Mall) 443 4,317 9.7 319 720 73.9 92.1
Office 824 12,208 14.8 1,134 1,376 92.9 40.3
Public Assembly 277 3,939 14.2 370 1,338 93.9 154.5
Public Order and Safety 71 1,090 15.5 126 1,791 115.8 93.7
Religious Worship 370 3,754 10.1 163 440 43.5 95.6
Service 622 4,050 6.5 312 501 77.0 85.0
Warehouse and Storage 597 10,078 16.9 456 764 45.2 104.3
Other 79 1,738 21.9 286 3,600 164.4 157.1
Vacant 182 2,567 14.1 54 294 20.9 832.1
This report references the Commercial Buildings Energy Consumption Survey (CBECS), published by the U.S.
Energy Information Administration in 2006. Initially this report was expected to compare the annual energy
consumption of the building to average national energy usage as documented below. However, a direct comparison
between one specific building and the groups of buildings outlined below yielded confusing results. Instead, this
report uses a comparative analysis on Fairbanks and Anchorage data as described in Appendix F. An abbreviated
excerpt from CBECS on commercial buildings in the Continental U.S. is below.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
36
Appendix J List of Conversion Factors and Energy Units
1 British Thermal Unit is the energy required to raise one pound of water one degree F°
1 Watt is approximately 3.412 BTU/hr.
1 horsepower is approximately 2,544 BTU/hr.
1 horsepower is approximately 746 Watts
1 "ton of cooling” is approximately 12,000 BTU/hr., the amount of power required
to melt one short ton of ice in 24 hours
1 Therm = 100,000 BTU
1 KBTU = 1,000 BTU
1 KWH = 3413 BTU
1 KW = 3413 BTU/Hr
1 Boiler HP = 33,400 BTU/Hr
1 Pound Steam = approximately 1000 BTU
1 CCF of natural gas = approximately 1 Therm
1 inch H2O = 250 Pascal (Pa) = 0.443 pounds/square inch (psi)
1 atmosphere (atm) = 10,1000 Pascal (Pa)
BTU British Thermal Unit
CCF 100 Cubic Feet
CFM Cubic Feet per Minute
GPM Gallons per minute
HP Horsepower
Hz Hertz
kg Kilogram (1,000 grams)
kV Kilovolt (1,000 volts)
kVA Kilovolt-Amp
kVAR Kilovolt-Amp Reactive
KW Kilowatt (1,000 watts)
KWH Kilowatt Hour
V Volt
W Watt
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
37
Appendix K List of Acronyms, Abbreviations, and Definitions
ACH Air Changes per Hour
AFUE Annual Fuel Utilization Efficiency
Air Economizer A duct, damper, and automatic control system that
allows a cooling system to supply outside air to reduce
or eliminate the need for mechanical cooling.
Ambient Temperature Average temperature of the surrounding air
Ballast A device used with an electric discharge lamp to cause
the lamp to start and operate under the proper circuit
conditions of voltage, current, electrode heat, etc.
CO2 Carbon Dioxide
CUI Cost Utilization Index
CDD Cooling Degree Days
DDC Direct Digital Control
EEM Energy Efficiency Measure
EER Energy Efficient Ratio
EUI Energy Utilization Index
FLUOR Fluorescent
Grade The finished ground level adjoining a building at the
exterior walls
HDD Heating Degree Days
HVAC Heating, Ventilation, and Air-Conditioning
INCAN Incandescent
NPV Net Present Value
R-value Thermal resistance measured in BTU/Hr-SF-̊F (Higher
value means better insulation)
SCFM Standard Cubic Feet per Minute
Savings to Investment Ratio (SIR) Savings over the life of the EEM divided by Investment
capital cost. Savings includes the total discounted dollar
savings considered over the life of the improvement.
Investment in the SIR calculation includes the labor and
materials required to install the measure.
Set Point Target temperature that a control system operates the
heating and cooling system
Simple payback A cost analysis method whereby the investment cost of
an EEM is divided by the first year’s savings of the EEM
to give the number of years required to recover the cost
of the investment.
Energy Audit – Final Report
Nenana City Office
Nenana, Alaska
F:\00-Jobs\2011\2602 F - AHFC Grade Audits\50-300 Doyon Other Region\50-420 Nenana\50-421 City Hall\Reports\Final\2012.07.12 Final AHFC Report ENN
Nenana City Hall.Docx
38
Appendix L Building Floor Plan
Floor plan adapted from a previous NORTECH project floor plan drawing.
1-Office
2-Office
3-Office
4-Bathroom
5-Storage
6-Entry
7-Entry
8-Front Lobby
9-Office
10-Storage
11-Copy Room
12-File Room
12B-Boiler Room
13-Office
14-Office
15-Storage
16-Storage
17-Storage
18-Storage
19-Bathroom
20-Conference Room
21-Fire Chief
22-Storage
23-Entry
24-Hallway
25-Janitor Closet
26-Bathroom
27-Hallway
28-Office
29-Office
30-Boiler Room