HomeMy WebLinkAboutSEA-AEE-Kake Schools 2012-EE
Kake Schools
Kake City School District
Funded by:
Final Report
February 2012
Prepared by:
Energy Audit
Table of Contents
Section 1: Executive Summary 2
Section 2: Introduction 9
Section 3: Energy Efficiency Measures 12
Section 4: Description of Systems 24
Section 5: Methodology 29
Appendix A: Energy and Life Cycle Cost Analysis 32
Appendix B: Energy and Utility Data 42
Appendix C: Equipment Data 47
Appendix D: Abbreviations 52
Audit Team
The energy audit is performed by Alaska Energy Engineering LLC of Juneau, Alaska. The audit team
consists of:
Jim Rehfeldt, P.E., Energy Engineer
Jack Christiansen, Energy Consultant
Brad Campbell, Energy Auditor
Loras O’Toole P.E., Mechanical Engineer
Will Van Dyken P.E., Electrical Engineer
Curt Smit, P.E., Mechanical Engineer
Philip Iverson, Construction Estimator
Karla Hart, Technical Publications Specialist
Jill Carlile, Data Analyst
Grayson Carlile, Energy Modeler
Kake Schools 1 Energy Audit (February 2012)
Section 1
Executive Summary
An energy audit of the Kake K-12 Schools was performed by Alaska Energy Engineering LLC. The
investment grade audit was funded by Alaska Housing Finance Corporation (AHFC) to identify
opportunities to improve the energy performance of public buildings throughout Alaska.
Four buildings on the Kake K-12 Schools campus were audited: the high school, the elementary
school, the library building, and the vocational education building. These four buildings, with a
combined area of 80,900 square feet, contain commons, classrooms, offices, a gym, locker rooms, a
kitchen and cafeteria, a library, storage, and mechanical support spaces. Heat is supplied to each of
these four buildings by a boiler plant located in high school building that connects to the other
buildings via a set of utilidors and above ground piping.
Building Assessments
The following summarizes our assessment of the buildings.
Envelope
All buildings on the school campus have exterior doors that are not thermally broken. Future exterior
door replacement selection should include this feature.
High School: The high school envelope is in good repair. With the exception of some door weather
stripping, the exterior appeared to be well maintained. Envelope issues with the exterior of the
building were limited to design issues that are not easily corrected. An arctic entryway was not
included on the main entrance and the unnecessarily high ceiling with upper windows further reduces
the efficiency of this space. The entryway window curtain assembly utilized single pane window
glazing, further adding to the poor energy efficiency of this space. Several doors also have single
pane glazing.
Elementary School: Issues with the elementary school building envelope are minor in significance.
With the exception of missing and damaged gutter downspouts along the east walls and some
moisture damage to the foundation skirting, the exterior envelope is well preserved. Problems
identified by the audit team were limited to the interior of the building envelope. Contractors
installing the ductwork for the new air handling unit AHU-2 cut open an access space approximately
2 ½’x3’ to access the attic and did not repair the opening. This is a 7 ½ square foot opening for
outside air to flow directly into the conditioned space of the building. Energy will be saved if this
section is filled in and insulated. In this same attic space there are approximately 48 square feet of
duct insulation and 40 square feet of ceiling insulation missing that should be replaced. While the
elementary school design did incorporate an arctic entry, the interior arctic entry door was observed
wedged open during both days of the audit, thereby defeating any opportunity to improve building
energy efficiency with this feature.
Kake Schools 2 Energy Audit (February 2012)
Vocational Education: The vocational education building is in poor condition. Siding has been
damaged and the interior insulation is exposed to the elements. The overhead door in the wood shop
is uninsulated and in poor condition. The walls and ceiling are very poorly insulated. Although an R-
11 batt has been applied to all exterior surfaces, the building is a metal-framed structure and the
framing is not thermally broken. Because these metal framing members are in direct contact with the
exterior shell and the interior space, they thermally bridge the already poor insulation value of the
building. An optimal insulation package in this climate would include R-26 for the walls and R-46 for
the ceiling. We estimate that the vocational education building envelope is R-8 on all exterior
surfaces. To compound this problem, there are several places in the attic space where a significant
amount of insulation has pulled away from the roof and the exterior metal roofing is exposed to the
interior conditioned space.
Library: The library building exterior appears to be well maintained. A new roof was installed in
2000 and the paint is in good condition. Issues with the building envelope are due to design and
construction and they are fairly significant. Despite a reasonably sized perimeter hydronic heating
system, staff has had a difficult time keeping the building warm enough. Three Toyostove heaters
have recently been installed to provide additional heat to the library, the daycare classroom, and the
PTA office. The energy audit revealed a very poorly insulated floor system that is losing heat due to
the elevated exposure the piling construction provides. The audit team found the floor was only
insulated with 2” of rigid foam, providing an insulation package of approximately R-10. A large
portion of this insulation was missing just inside the crawlspace access. Optimal floor insulation
packages for this type of construction are R-30. Skirting has been added to the building, which most
likely improves the thermal performance. Recommendations for adding insulation to the skirting
package, installing a vapor barrier on the ground under the building, and putting fill against the
skirting base are outlined in Section 3, Energy Efficiency Measures.
Kake Schools 3 Energy Audit (February 2012)
Heating System
The school buildings are heated by two fuel oil boilers that provide heat to air handling units, unit
heaters, and perimeter hydronic systems within the audited buildings, as well as most of the campus
domestic hot water needs. The boiler plant is connected to the Vocational Building via an
aboveground utilidor with insulated piping. Recommendations for eliminating the below ground
connections and adding an additional thermal blanket to this system are outlined in Section 3, Energy
Efficiency Measures.
An issue with the heating system is the high number of pumps utilized to supply heating water to the
buildings. Because the Kake School campus was constructed and renovated in several phases, the
boiler system utilizes 18 pumps rated at a total 15.3 HP to circulate water for heating purposes
throughout the four buildings. This system could be consolidated into a primary/secondary pumping
system with a variable speed pumping capability that would deliver better performance with less
pumps and an associated reduction in horsepower, thereby providing both operational and
maintenance savings.
At the time of the audit Boiler #1 was running and Boiler #2 was on-line and not isolated. Circulating
heating water through a non-necessary boiler results in a significant amount of heat losses. This is
covered with recommendations in the report. The temperature band for boiler operation could be
optimized as well. A lead/lag operating sequence with 30 degree delta T should be utilized to
optimize boiler efficiency, i.e. lead boiler operates from 150°F – 180°F and lag boiler operates from
140°F to 170°F. Utilizing a lead/lag operating sequence when both boilers must be operated will also
increase the efficiency of the boiler system.
The remainder of the fuel oil boiler heating system appears to be in good condition; however fairly
simple improvements can be made to improve its effectiveness and efficiency. These are outlined in
Section 3, Energy Efficiency Measures.
Domestic Hot Water System
The domestic hot water system consists of two indirect hot water heaters that supply the buildings.
The showers are served by a tempering valve that controls the temperature of the domestic hot water.
The valve needs to be recalibrated as outlet temperature, which should be constant, varies with flow
rate.
Kake Schools 4 Energy Audit (February 2012)
Ventilation System
Air handling systems, ventilation fans, and exhaust fans provide air heating and cooling and maintain
indoor air quality. While the maintenance manager has already made significant improvements to the
operation and efficiency of this equipment, the overall condition of the ventilation systems was only
fair. Opportunities to reduce heating costs through right-sizing building space air exchange rates and
improving control sequences have been identified in this report.
Air quality due to lack of ventilation in the portions of the elementary school and library buildings is
the biggest audit concern.
Library: Fresh air for the library building was originally provided by the unit ventilators; however,
they have all failed and are currently not used. The addition of the Toyostove heaters in the building
have helped maintain a comfortable temperature level but they do not provide any fresh air to the
spaces. Staff is strongly encouraged to repair these units in an effort to improve air quality within the
building.
Elementary School: The original heat recovery ventilator for the original wing of the elementary
school is not being operated. This provided a source of fresh air and exhaust for the two bathrooms,
the two offices, and the janitor’s closet in the middle of the building. As a result, fumes from the toilet
rooms and janitor’s closet, including a strong odor of cleaning chemicals, can be smelled throughout
the wing of the building. It is imperative that these spaces are properly ventilated for the health of the
occupants. Fortunately the recently installed air handling unit is capable of providing a ventilation
source for these spaces as well. An exhaust fan is needed for the toilets and janitor’s closet. Until
these modifications can be made, it is recommended that less toxic cleaning agents are utilized and
stored in these spaces.
High School: Within the high school a large amount of heat is generated in the kitchen space by the
freezer, the refrigerator, the dishwasher, and cooking equipment. Because these additional heat
sources have made the kitchen space too warm, staff keeps the kitchen exhaust hood operating
throughout the day to help cool the space. Although this does help cool the room, it puts a very large
energy load on the high school to do so. When the kitchen hood is operating, it removes 3,000 cfm of
conditioned air from the school. This air must be made up and heated. To do so, 3,000 cfm of outside
air must be passed through the gym and the school air handler units to be heated and delivered to the
interior spaces, only to be removed from the school through the kitchen ventilation fan. Energy will
be saved if heat is removed from the kitchen and utilized within the building envelope. Operation of
the kitchen make-up air fan can supply makeup air at lower temperatures, which reduces heating
energy, cools the kitchen, and could further reduce energy consumption.
Additional opportunities to improve ventilation quality and efficiency, such as utilizing heat recovery
methods in the high school boiler room and the elementary school pump room are outlined Section
3, Energy Efficiency Measures.
Kake Schools 5 Energy Audit (February 2012)
Lighting
The current Kake Schools maintenance manager has been very focused on saving energy through
lighting modifications. These efforts will provide a significant reduction in electrical consumption for
the campus. Interior lighting now consists primarily of T8 and compact fluorescent fixtures. Exterior
lighting consists primarily of compact fluorescent lighting, LED lighting, and several remaining metal
halide fixtures.
The audit team understands that lighting upgrades will continue in the coming months. Replacement
of the remaining existing fixtures with more energy efficient units, increased efforts to only use half
of the gym lighting when possible, and the addition of occupancy sensors are solutions for further
reductions in operational costs.
High School: The gym lighting in the high school is the largest lighting load in the building. There
are two individual light switches that each control 50% of the gym lighting. Under most
circumstances, half the lighting provides sufficient light levels; however, both banks of lights are
typically used. Each hour that only half of the lighting is used saves 4.2 kWh power. Energy will be
saved if a lockable cover is placed over one of the switches so that full gym lighting is used only
when authorized by staff.
Elementary School: An unnecessarily large number of lights in the elementary school are powered
continuously so that they can operate as ‘stumble’ lighting. This is a lighting circuit that provides
occupants illumination at all times regardless of the status of the light switch position. Reducing the
number of lights connected to stumble lighting circuits, while still maintaining sufficient illumination
levels for proper egress, will reduce the after-hours electrical consumption of this building.
Summary
It is the assessment of the energy audit team that the majority of the campus energy losses are due to
the need to optimize heating and ventilation systems in accordance with occupancy, insufficient
insulation issues in the vocational education and library buildings, and the inefficient design of the
campus heating and distribution system. The level of effort and enthusiasm expressed by the
maintenance manager to implement energy efficiency measures on the Kake School campus is
commendable, and the results of his efforts can already be seen in the energy use data covered in this
report.
The development of an energy policy for the school campus could provide additional energy savings
while serving as a tool for the education of staff and supervisors. We recommend that an energy
policy includes guidelines for:
hours of operations of the buildings;
thermostat setpoints for daytime and night setback modes of the individual spaces;
instructions and reminders about the use of lights within the building;
an organized process for making any changes to the guidelines; and,
a requirement to replace existing appliances and equipment with Energy Star rated units.
Kake Schools 6 Energy Audit (February 2012)
Energy Efficiency Measures (EEMs)
All buildings have opportunities to improve their energy efficiency. The energy audit revealed
numerous opportunities in which an efficiency investment will result in a net reduction in long-term
operating costs. EEMs addressing specific buildings are identified as follows: High School (HS);
Elementary School (Elem); Library (Lib); and Vocational Education (Voc).
Behavioral and Operational EEMs
The following EEMs require behavioral and operational changes in the building use. The savings are
not readily quantifiable but these EEMs are highly recommended as low-cost opportunities that are a
standard of high performance buildings.
EEM-1: Weather-strip Doors
EEM-2: Lower Entrance Temperature Setpoints
EEM-3: (Elem) Ventilate Bathrooms & Janitor Closet
EEM-4: (Lib) Install UPS for Toyostove Heaters
EEM-5: (Elem) Repair Access to Attic Space
EEM-6: (HS) Seal Roof Penetrations
EEM-7: (Voc) Install Programmable Thermostat
EEM-8: (Elem) Repair Attic Insulation
EEM-9: Install Fuel Tank Level Monitor
EEM-10: (Voc) Repair Insulation
EEM-11: (HS) Close Fume Hood Sashes
EEM-12: (Lib) Repair Ventilation Systems
Kake Schools 7 Energy Audit (February 2012)
High and Medium Priority EEMs
The following EEMs are recommended for investment. They are ranked by life cycle savings to
investment ratio (SIR). This ranking method places a priority on low cost EEMs which can be
immediately funded, generating energy savings to fund higher cost EEMs in the following years.
Negative values, in parenthesis, represent savings.
25-Year Life Cycle Cost Analysis
Investment Operating Energy Total SIR
High Priority EEM-
13: Install Pipe Insulation $800 $0 ($135,400) ($134,600) 169.3
14: (Lib) Turn Off Computers $200 $0 ($17,800) ($17,600) 89.0
15: (HS) Isolate Standby Boiler $500 $3,400 ($45,000) ($41,100) 83.2
16: Replace Lavatory Aerators $200 $0 ($12,500) ($12,300) 62.5
17: Perform Boiler Combustion Test $700 $16,300 ($55,700) ($38,700) 56.3
18: (HS) Install Gym Light Switch Cover $500 $0 ($27,700) ($27,200) 55.4
19: Convert to Propane Heat $104,800 $0 ($1,496,500) ($1,391,700) 14.3
20: (Elem) Pump Room Heat Recovery $6,200 $0 ($70,500) ($64,300) 11.4
21: (Voc) Reroute Heating Mains $5,500 $0 ($55,700) ($50,200) 10.1
22: (HS) Install Gym Light Fixtures $4,200 $0 ($30,000) ($25,800) 7.1
23: (Voc) Increase Utilidor Pipe Insulation $1,900 $0 ($13,300) ($11,400) 7.0
24: Optimize Ventilation Systems $27,500 $0 ($186,300) ($158,800) 6.8
25: Upgrade Transformer $11,500 $0 ($64,300) ($52,800) 5.6
26: (HS) Server Room Heat Recovery $8,000 $0 ($36,100) ($28,100) 4.5
27: (Voc) Replace Shop Door $15,300 $0 ($62,500) ($47,200) 4.1
28: Upgrade Motors $9,300 $0 ($32,400) ($23,100) 3.5
Medium Priority EEM-
29: (HS) Operate Kitchen Make-up Air Fan $6,700 $17,000 ($32,300) ($8,600) 2.3
30: (HS) Replace Single Pane Glazing $11,500 $0 ($21,700) ($10,200) 1.9
31: (HS) Boiler Room Heat Recovery $69,300 $4,300 ($128,400) ($54,800) 1.8
32: (Lib) Increase Building Floor Insulation $34,200 $0 ($54,500) ($20,300) 1.6
33: Convert to Variable Speed Pumping $186,500 ($20,400) ($184,800) ($18,700) 1.1
Totals* $505,300 $20,600 ($2,763,400) ($2,237,500) 5.4
*The analysis is based on each EEM being independent of the others. While it is likely that some
EEMs are interrelated, an isolated analysis is used to demonstrate the economics because the audit
team is not able to predict which EEMs an Owner may choose to implement. If several EEMs are
implemented, the resulting energy savings is likely to differ from the sum of each EEM projection.
Summary
The energy audit revealed numerous opportunities for improving the energy performance of the
building. It is recommended that the behavioral and high priority EEMs be implemented now to
generate energy savings from which to fund the medium priority EEMs.
Another avenue to consider is to borrow money from AHFCs revolving loan fund for public
buildings. AHFC will loan money for energy improvements under terms that allow for paying back
the money from the energy savings. More information on this option can be found online at
http://www.ahfc.us/loans/akeerlf_loan.cfm.
Kake Schools 8 Energy Audit (February 2012)
Section 2
Introduction
This report presents the findings of an energy audit of four buildings1 on the Kake School Campus
located in Kake, Alaska. The purpose of this investment grade energy audit is to evaluate the
infrastructure and its subsequent energy performance to identify applicable energy efficiencies
measures (EEMs).
The energy audit report contains the following sections:
Introduction: Building use and energy consumption.
Energy Efficiency Measures: Priority ranking of the EEMs with a description, energy
analysis, and life cycle cost analysis.
Description of Systems: Background description of the building energy systems.
Methodology: Basis for how construction and maintenance cost estimates are derived and the
economic and energy factors used for the analysis.
BUILDING USE
The Kake Schools is an 80,900 square foot campus comprised of the high school building, elementary
school building, library building, and the vocational building. These four buildings contain commons,
classrooms, offices, a gym, locker rooms, a kitchen and cafeteria, a library, storage, and mechanical
support spaces. Heat is supplied to each of these four buildings by a boiler system located in high
school building that connects to the other buildings via buried and aboveground piping. The school is
operated by 32 staff and attended by 95 students. There are 65 students in the elementary school, and
30 students in the junior and senior high school. In addition, the Head Start program has 16 children
enrolled and 3 teachers.
The campus is occupied in the following manner:
School Buildings 7:30 am – 4:30 pm (M-F) Staff
8:30 am – 4:30 pm (M-F) Students
Gym 10:00 am – 11:00 am (M-F) Head Start Programs
12:30 am – 4:30 pm (M-F) School Activities
4:30 am – 5:30 pm (M-F) Sports Practice
7:30 pm – 9:00 pm (MWF) Open Gym
1 A fifth building, used by the IT department, was not included in the audit. This building is heated by a Toyo stove
and not connected to the main heating plant.
Kake Schools 9 Energy Audit (February 2012)
Campus Building History
1971 – Kake High School Original Construction
1977 – Kake Vocational Education Building Construction
1994 – Kake Elementary School Construction
1999 – Kake High School Renovation
2001 – Kake Elementary School Addition
2012 – Kake Elementary School Heating and Ventilation Improvements
Energy Consumption
The building energy sources include an electric service, #2 fuel oil for the heating plant, #1 diesel for
Toyostove Stoves in the library building, and propane for cooking. The following table shows annual
energy use and cost.
Annual Energy Consumption and Cost
Source Consumption Cost Energy, MMBtu
Electricity 289,688 kWh $117,800 1,000 17%
Propane 300 Gallons $1,100 30 1%
#1 Fuel Oil 971 Gallons $5,400 130 2%
#2 Fuel Oil 33,827 Gallons $185,400 4,700 80%
Totals $309,700 5,860 100%
Electricity
This chart shows electrical energy use
from 2008 to 2011. The effective cost—
energy costs plus demand charges—is
40.7¢ per kWh. Electrical consumption
rose in 2010 due to increased community
use. The reduction in electrical
consumption during 2011 is a direct
reflection of the maintenance manager’s
efforts, which have included the
replacement of a significant number of
light fixtures with more efficient models
and close monitoring of the use and
performance of equipment.
Kake Schools 10 Energy Audit (February 2012)
Fuel Oil
This chart shows heating energy use
from 2008 to 2011. The chart compares
annual use with the heating degree
days, which is a measurement of the
demand for energy to heat a building. A
year with a higher number of degree
days reflects colder outside
temperatures and a higher heating
requirement.
The reason for higher fuel oil consumption in 2008 and 2009 could not be determined. The lower
consumption in 2010 cannot be explained. The reduced fuel consumption in 2011 is considered to
reflect current consumption rates since the maintenance manager has implemented energy savings
measures.
The maintenance manager was interested in methods to more accurately monitor and report boiler
fuel use. Energy is typically saved when fuel consumption is tracked closely. Veeder Root is a
company that manufactures a tank level monitor that would integrate well with the existing building
DDC system.
Cost of Heat Comparison
This chart shows a comparison of the current
cost of fuel oil heat and electric heat. The
comparison is based on a #2 fuel oil
conversion efficiency of 70%, #1 fuel oil
conversion efficiency of 84%, propane
efficiency of 78%, and electric boiler
conversion efficiency of 95%. Propane heat is
currently less expensive than fuel oil or
electric heat.
Kake Schools 11 Energy Audit (February 2012)
Section 3
Energy Efficiency Measures
The following energy efficiency measures (EEMs) were identified during the energy audit. The
EEMs are priority ranked and, where applicable, subjected to energy and life cycle cost analysis.
EEMs addressing specific buildings are identified as follows: High School (HS); Elementary School
(Elem); Library (Lib); and Vocational Education (Voc). Appendix A contains the energy and life
cycle cost analysis spreadsheets.
The EEMs are grouped into the following prioritized categories:
Behavioral or Operational: EEMs that require minimal capital investment but require
operational or behavioral changes. The EEMs provide a life cycle savings but an analysis is not
performed because the guaranteed energy savings is difficult quantify.
High Priority: EEMs that require a small capital investment and offer a life cycle savings.
Also included in this category are higher cost EEMs that offer significant life cycle savings.
Medium Priority: EEMs that require a significant capital investment to provide a life cycle
savings. Many medium priority EEMs provide a high life cycle savings and offer substantial
incentive to increase investment in building energy efficiency.
Low Priority: EEMs that will save energy but do not provide a life cycle savings.
BEHAVIORAL OR OPERATIONAL
The following EEMs are recommended for implementation. They require behavioral or operational
changes that can occur with minimal investment to achieve immediate savings. These EEMs are not
easily quantified by analysis because they cannot be accurately predicted. They are recommended
because they offer a life cycle savings, represent good practice, and are accepted features of high
performance buildings.
EEM-1: Weather-strip Doors
Purpose: Several exterior steel doors do not seal and are missing weather stripping. Energy will be
saved if doors are properly weather-stripped to reduce infiltration.
Scope: Replace weather stripping on exterior doors.
EEM-2: Lower Entrance Temperature Setpoints
Purpose: Energy will be saved if the entryway thermostat setpoints were lowered to 55°F in all
entrances. A higher temperature may be required so the entry dries in an appropriate
amount of time.
Scope: Lower entryway thermostat setpoints to 55°F.
Kake Schools 12 Energy Audit (February 2012)
EEM-3: (Elem) Ventilate Bathrooms & Janitor Closet
Purpose: The heat recovery unit that supplies administrative spaces and exhausts the toilet rooms
and janitors closet in the old section of the elementary wing is no longer working. As a
result, the air quality in this portion of the building is poor and the odor of cleaning
chemicals is very strong. The recently installed air handling unit that services the
remaining portion of the original elementary wing is capable of supplying the ventilation
requirements of the administrative spaces. This will significantly improve air quality in
these spaces with minimal capital investment. An exhaust fan is also needed to remove
odors from the toilet rooms and janitor closet.
Scope: Install ducting to ventilate the admin spaces with AHU-2. Install an exhaust fan to
exhaust odors from the toilet rooms and janitors closet. Less toxic cleaning chemicals
should be considered to minimize the exhaust requirements of the janitor’s closet.
EEM-4: (Lib) Install UPS for Toyostove Heaters
Purpose: Frequent power interruptions to the school campus result in losing the programmed night
setback modes on the Toyostove heaters in the library building. This results in the heaters
maintaining daytime temperatures throughout the entire 24-hour period until the
programming is reset. Energy will be saved if a UPS is used to protect the heaters from
power surges and to retain the programming during outages.
Scope: Install a UPS power supply for each of the Toyostove heaters in the library building.
EEM-5: (Elem) Repair Access to Attic Space
Purpose: Contractors installing the ductwork for the new AHU in the original elementary wing cut
an opening of approximately 2 ½’x3’ to access the attic and did not repair it. This is a 7 ½
square foot opening for outside air to flow directly into the conditioned space of the
building. Energy will be saved if this section is filled in and insulated.
Scope: Properly fill and insulate the access opening from the fan room to the attic above the old
elementary wing.
EEM-6: (HS) Seal Roof Penetrations
Purpose: The original kitchen ventilation roof penetration is no longer used but still provides a path
for air flow from interior conditioned spaces. Energy will be saved if this penetration is
properly filled and insulated.
Scope: Properly fill and insulate the abandoned kitchen ventilation ducting on the high school
roof.
EEM-7: (Voc) Install Programmable Thermostat
Purpose: The vocational education building temperature setpoint is kept at 70°F. Energy will be
saved by installing a programmable thermostat with night setback mode. The occupied
setpoint should be reduced to 68°F and unoccupied setpoint should be set to 62°F.
Scope: Install programmable thermostats in the vocational education building.
Kake Schools 13 Energy Audit (February 2012)
EEM-8: (Elem) Repair Attic Insulation
Purpose: A 48 square foot section of ductwork is missing insulation and a 40 square foot section of
attic insulation is missing in the attic space above the old elementary school wing. Energy
would be saved if these sections of insulation were properly repaired.
Scope: Replace ductwork and attic insulation above the original elementary school wing.
EEM-9: Install Fuel Tank Level Monitor
Purpose: Maintenance staff is interested in a method to more accurately monitor and report boiler
fuel use. Energy is typically saved when fuel consumption is tracked closely. Veeder-
Root is a company that manufactures a tank level monitor that would integrate well with
the existing building DDC system.
Scope: Install a Veeder-Root fuel level monitor and connect it to the DDC system.
EEM-10: (Voc) Repair Insulation
Purpose: Approximately 60 square feet of insulation have pulled away from the ceiling in the attic
space of the vocational education building. Energy will be saved if this insulation is
repaired.
Scope: Repair insulation that has pulled away from the ceiling in the attic space of the vocational
education building.
EEM-11: (HS) Close Fume Hood Sashes
Purpose: During the audit it was noted that the fume hood in the science room was left fully open.
This results in unnecessary loss of conditioned air through the fume hood exhaust system.
Energy will be saved if the fume hood sash is kept fully closed when not in use and the
fan shut off when not needed.
Scope: Ensure the fume hood sash is fully closed and the fume hood fan is off when not in use.
EEM-12: (Lib) Repair Ventilation Systems
Purpose: The library building has cabinet unit ventilators that are designed to supply heat and
ventilation air. The units are not operating properly. Toyostove stoves have been added to
heat the building. However, there is no ventilation now that the units are not working.
Scope: Perform repairs to the cabinet unit ventilators and return them to service properly
ventilating the building.
Kake Schools 14 Energy Audit (February 2012)
HIGH PRIORITY
The following EEMs are recommended for implementation because they are low cost measures that
have a high savings to investment ratio. The EEMs are listed from highest to lowest priority. Negative
values, in parenthesis, represent savings.
EEM-13: Install Pipe Insulation
Purpose: Several sections of heating pipe are uninsulated. Energy will be saved if these sections of
piping are optimally insulated.
Scope: Install pipe insulation in the following locations:
- 36’ of ¾” pipe at the ceiling of the library/Head Start storage room
- 40’ of ¾” pipe in the elementary school new fan room
- 3’ of 1” pipe in the attic space of the vocational education building
- 10’ of 1” pipe in the elementary school pump room
- 20’ of ¾” pipe in the elementary school pump room
- 6’ of 2 ½’ pipe in the elementary school pump room
- 15’ of ¾” pipe in the elementary school heat exchanger room
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($4,780) ($4,780) $800 $0 ($135,400) ($134,600) 169.3
EEM-14: (Lib) Turn Off Computers
Purpose: The 15 computers in the library are currently left on continuously. Even though they
automatically enter a more efficient sleep mode, energy will be saved if the computers
are shut off when not in use.
Scope: Establish and post a computer policy to turn off the machines when not in use.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($630) ($630) $200 $0 ($17,800) ($17,600) 89.0
Kake Schools 15 Energy Audit (February 2012)
EEM-15: (HS) Isolate Standby Boiler
Purpose: Only one of the high school boilers is needed to supply the heating load. Circulating hot
water through a standby boiler can result in a 3% efficiency loss of the operable boiler
due to the standby boiler acting as a heat sink. Energy will be saved by closing the return
valve to isolate the boiler.
Scope: Isolate the standby boiler by closing the return valve when only a single boiler is required
to meet the heating load and outside temperatures are moderate. If leaking is a concern, a
successful strategy is to keep a minimal flow through the boiler so it remains at 100-
120°F.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$200 ($1,590) ($1,390) $500 $3,400 ($45,000) ($41,100) 83.2
EEM-16: Replace Lavatory Aerators
Purpose: Energy and water will be saved by replacing the lavatory aerators with low-flow models.
Scope: Replace lavatory aerators with water-conserving fixtures.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($440) ($440) $200 $0 ($12,500) ($12,300) 62.5
EEM-17: Perform a Boiler Combustion Test
Purpose: Operating the boiler with an optimum amount of excess air will improve combustion
efficiency. Annual cleaning followed by a combustion test is recommended.
Scope: Annually clean and perform a combustion test on the boiler.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$960 ($1,960) ($1,000) $700 $16,300 ($55,700) ($38,700) 56.3
EEM-18: (HS) Install Gym Light Switch Cover
Purpose: There are two individual light switches that each control power to 50% of the gym
lighting. Under most circumstances only one switch is needed because 50% of the
lighting in the gym space is adequate, however both banks of lights are usually used.
Reducing the gym lighting to 50% for 3 hours each day will save $5 per day in lighting
energy.
Scope: Install a lockable cover over one of the gym lighting switches and educate staff about the
benefit of proper gym lighting use.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($980) ($980) $500 $0 ($27,700) ($27,200) 55.4
Kake Schools 16 Energy Audit (February 2012)
EEM-19: Convert to Propane Heating
Purpose: The propane distributor in Kake reports that the current bulk cost of propane is $2.90 per
gallon. Heating with propane at this price would reduce the cost of heating the school
complex by 25%. Energy costs will be less if the high school boilers are converted to
propane heat.
Scope: Install a propane tank and replace the burners with dual-fuel oil/gas burners. This will
provide the campus with dual-fuel capability to utilize the least expensive energy source.
Before doing the conversion, perform an analysis of the long-term cost of propane to gain
assurance that propane will retain its price advantage in future years.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($52,800) ($52,800) $104,800 $0 ($1,496,500) ($1,391,700) 14.3
EEM-20: (Elem) Pump Room Heat Recovery
Purpose: A significant amount of heat loss from the equipment operating in the elementary school
pump room could be captured and utilized within the elementary school building instead
of being exhausted outside. This includes ambient heat losses from the pumps, piping,
and domestic hot water heating components. Energy will be saved if the heat generated in
this space is delivered to the new air handling unit for redistribution throughout the
building.
Scope: Install ducting to supply air to the pump room and return heated air to AHU-2 for
redistribution throughout the old elementary classroom wing. Install a jacket on the
domestic hot water tank to reduce heat loss of the unit.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($2,490) ($2,490) $6,200 $0 ($70,500) ($64,300) 11.4
EEM-21: (Voc) Reroute Heating Mains
Purpose: The heating piping between the high school boiler room and the vocational education
building is routed under each building foundation. In the high school building, this causes
the piping to be submerged in a pool of water. The pipe insulation has deteriorated at
both locations. Energy will be saved if the underground portion of each end of the piping
is abandoned and the piping is routed directly through the buildings walls.
Scope: Eliminate the piping under the foundation of the boiler room and the vocational education
building and run it through the walls.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($1,970) ($1,970) $5,500 $0 ($55,700) ($50,200) 10.1
Kake Schools 17 Energy Audit (February 2012)
EEM-22: (HS) Install Gym Light Fixtures
Purpose: The kitchen staff makes frequent trips each day through the gym, which is between the
kitchen and the pantry. The gym pendant lights are the only existing lighting between
these spaces. Energy will be saved if two sconce light fixtures are installed so that the
gym pendant lights can remain off.
Scope: Install sconce light fixtures between the kitchen and the pantry.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($1,060) ($1,060) $4,200 $0 ($30,000) ($25,800) 7.1
EEM-23: (Voc) Increase Utilidor Pipe Insulation
Purpose: The heating piping serving the vocational education building is installed in an above-
ground utilidor. The piping is under-insulated. Energy will be saved if the piping is
wrapped with an insulating blanket to reduce heat loss.
Scope: Install an insulating blanket around the heating mains inside the utilidor.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($470) ($470) $1,900 $0 ($13,300) ($11,400) 7.0
Kake Schools 18 Energy Audit (February 2012)
EEM-24: Optimize Ventilation Systems
Purpose: The school campus buildings utilize fixed-flow heating and ventilation system units to
provide conditioned air to interior spaces during school hours and as needed on evenings
and weekends. Under most conditions the space occupancy throughout the majority of
these operational hours is well below the setpoint of the air handling systems. This results
in an unnecessarily high fuel and electric demand to support school operations. Energy
will be saved if modifications are made to the respective air handling systems to improve
performance and to reduce air flow when not needed.
The following modifications are recommended to improve the indoor air quality and
thermal comfort within the buildings:
High School Gym (VU-1): To reduce temperature stratification across the gym, extend
the return ducts across the gym and preferably down to the floor level to draw the heated
air downward.
Elementary School Original Building (AHU-2 Classroom Ventilation): The system was
recently installed and has not been commissioned. The following deficiencies are noted:
- The heating coil automatic valve is open when fan is off.
- The minimum outside air setpoint is not overriding the mixed air temperature control.
- The exhaust air flow rates can be reduced.
- The EAD can be controlled with building pressure.
Vocational Building (VU-1a and VU-2a): The unit heaters in the shop spaces are
manually operated to provide supplemental heat when the outside temperature drops
below 20°F. The systems should be operated whenever the building is occupied to
provide adequate ventilation and exhaust make-up. The controls are not working properly
and must be recalibrated.
Scope: Perform the following modifications and commission each HVAC system to perform as a
properly integrated system when completed:
High School Locker Room (EF-3)
- Remove the CUH fans so transfer air from the gym can flow to the locker rooms
without operating the fans. (CHU-1 is 1/3 HP, CHU-2 is ¾ HP). Cabinet unit heaters
would be operated simply as transfer air heaters after this modification.
- Locker Exhaust fan EF-3 is currently controlled from a light switch in either locker
room. During the audit, this fan was operating continuously despite occasional use of
the room. Install occupancy and humidity sensors to control the operation of EF-3.
Elementary School New Addition (AHU-1)
- Reduce exhaust air flow rates in the art/science and gym storage spaces.
- Disable the heating coil when fan is off, except during freezing weather.
- Control the EAD from building pressure.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($6,570) ($6,570) $27,500 $0 ($186,300) ($158,800) 6.8
Kake Schools 19 Energy Audit (February 2012)
EEM-25: Upgrade Transformer
Purpose: The existing 37.5 kVA transformer in the boiler room is not TP-1 rated. Energy will be
saved if this less-efficient transformer is replaced with an energy efficient model that
complies with NEMA Standard TP 1-2001.
Scope: Replace the boiler room transformer with a NEMA Standard TP 1-2001compliant model.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($2,270) ($2,270) $11,500 $0 ($64,300) ($52,800) 5.6
EEM-26: (HS) Server Room Heat Recovery
Purpose: The high school server room is insufficiently cooled and the heat generated from this
space is not optimally utilized within the building envelope. Energy will be saved and the
server room will operate at a cooler temperature if outside air is ducted through the
crawlspace into the server room and the heated air transferred to the adjacent science
room.
Scope: Install ducting to supply outside air through the crawlspace to the server room and
exhaust the warmed air into the science room.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($1,270) ($1,270) $8,000 $0 ($36,100) ($28,100) 4.5
EEM-27: (Voc) Replace Shop Door
Purpose: The 12’ x 12’ overhead door for the wood shop is uninsulated and has poor weather
stripping. Energy will be saved if this door is replaced with a high efficiency insulated
overhead door.
Scope: Replace overhead door with high efficiency insulated overhead door.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($2,200) ($2,200) $15,300 $0 ($62,500) ($47,200) 4.1
Kake Schools 20 Energy Audit (February 2012)
EEM-28: Upgrade Motors to Premium Efficiency
Purpose: The equipment inspection identified eight motors that could be upgraded with premium
efficiency models to save energy. They are:
- P-1 (Elementary) 1 ½ HP
- P-2 (Elementary) 1 ½ HP
- EF-1 (Elementary) 1 HP
- VU-1 (High School) 5 HP
- VU-2 (High School) 3 HP
- EF-1 (High School) 2 HP
- EF-2 (High School) 2 HP
- EF-5 (High School) 1 ½ HP
Scope: Replace identified motors with premium efficiency motors.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($1,140) ($1,140) $9,300 $0 ($32,400) ($23,100) 3.5
MEDIUM PRIORITY
Medium priority EEMs will require planning and a higher level of investment. They are
recommended because they offer a life cycle savings. The EEMs are listed from highest to lowest
priority. Negative values, in parenthesis, represent savings.
EEM-29: (HS) Operate Kitchen Make-up Air Fan
Purpose: A large amount of heat is generated in the kitchen space by the freezer, the refrigerator,
the dishwasher, and cooking equipment. Because these additional heat sources have made
the kitchen space too warm, the door to the gym is kept open and the kitchen ventilation
hood is operated continuously to cool the kitchen. Although this does help cool the room,
the outside makeup air puts a very large energy load on the high school.
When the kitchen hood is operating, it removes 3,000 cfm of conditioned air from the
school. Kitchen staff should be instructed on the energy load associated with operating
the hood so it is only operated while cooking. Energy will be saved if the hood make-up
air fan is returned to service. The fan will supply tempered air that is only heated enough
to cool the kitchen while providing make-up for the hood.
Scope: Return the make-up air fan to operation. Modify controls so the supply air temperature
modulates to maintain room temperature.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$1,000 ($1,140) ($140) $6,700 $17,000 ($32,300) ($8,600) 2.3
Kake Schools 21 Energy Audit (February 2012)
EEM-30: (HS) Replace Single-Pane Glazing
Purpose: Single pane glazing is installed in three doors and nine windows in the high school.
Energy will be saved if the glazing is replaced with high efficiency double pane glazing.
Scope: Replace single pane glazing with energy efficient double pane glazing units.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($770) ($770) $11,500 $0 ($21,700) ($10,200) 1.9
EEM-31: (HS) Boiler Room Heat Recovery
Purpose: A significant amount of heat loss from the high school heating plant can be captured and
utilized within the building instead of being exhausted outside. This includes ambient
heat losses from the boilers, piping, and boiler system components such as the expansion
tank and de-aerator. Energy will be saved if an air-to-water heat pump is installed in the
boiler to transfer heat to a fan coil unit in the gym. The combustion efficiency of the
boilers will increase and additional energy will be available for heat recovery efforts if
the thermostat for VF-1 is increased from 70°F to 85°F.
Scope: Install a fan coil unit in the boiler and gym to capture the available heat from the boiler
room and deliver it to the adjacent gym.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$250 ($4,530) ($4,280) $69,300 $4,300 ($128,400) ($54,800) 1.8
EEM-32: (Lib) Increase Floor Insulation
Purpose: The floor of the library building is minimally insulated with 2” of rigid insulation applied
to the underside of the subfloor. The floor assembly provides an R-12 insulating level.
An optimal insulation level for the building is R-30. In addition to the poor insulation
value, a 3’x12’ section of insulation below the Head Start room has been removed,
leaving 36 square feet uninsulated. The poor insulation value of the building floor has
contributed to the need to add Toyostove heaters in several spaces to assist in keeping
interior spaces warm. Energy will be saved by increasing the floor insulation.
Scope: Install an additional 4” of rigid insulation under the entire library building floor. Install 2”
of rigid insulation to the inside of the building skirting. Install a vapor barrier directly on
the ground under the building and seal it to the perimeter skirting. Apply fill material to
the outside base of the skirting to help seal the crawlspace and prevent air flow.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
$0 ($1,920) ($1,920) $34,200 $0 ($54,500) ($20,300) 1.6
Kake Schools 22 Energy Audit (February 2012)
EEM-33: Convert to Variable Speed Pumping
Purpose: Because the Kake school campus was constructed and renovated in a series of individual,
non-integrated construction projects, the boiler system utilizes 18 pumps to circulate
water for heating purposes through the four buildings covered in this audit. This system
could be consolidated into a primary/secondary pumping system with variable speed
pumping capability that would deliver better performance with a fraction of the
horsepower and a greatly reduced number of pumps, thereby providing both operational
and maintenance savings.
Scope: Consolidated hydronic heating system into a primary/secondary pumping system with
variable speed pumping for the entire campus.
Annual Costs Life Cycle Costs
Operating Energy Total Investment Operating Energy Total SIR
($1,200) ($6,520) ($7,720) $186,500 ($20,400) ($184,800) ($18,700) 1.1
LOW PRIORITY
Low priority EEMs do not offer a life cycle energy savings and are not recommended.
EEM-34: (Voc) Increase Building Insulation
Purpose: Insulation is installed only between the metal purlins of the vocational education
building. The metal building components act as thermal bridges between the interior and
exterior of the building. The estimated R-value of the building walls and ceiling is R-8.
An optimal R-value by current construction standards is R-26 for the wall and R-46 for
the roof. Energy will be saved if the insulation level of the walls and ceiling is increased.
Scope: Increase the insulating value of the building envelope.
This EEM is not recommended because the high cost of adding insulation to the existing
envelope will not be offset by energy savings.
EEM-35: (HS) Install Locker Room Hot Water Return Loop
Purpose: The locker room hot water supply does not have a recirculating loop. As a result it takes
approximately 10-15 minutes for hot water to reach the showers. Energy will be saved if
a domestic hot water return line and recirculation pump were installed.
Scope: Install a domestic hot water return line and recirculation pump.
This EEM is not recommended because the hot water recirculation system will increase
heat loss and pump energy consumption. Since the showers are used so infrequently,
there is less heat loss associated with occasionally dumping water to the drain until hot
water reaches the fixtures.
Kake Schools 23 Energy Audit (February 2012)
Section 4
Description of Systems
ENERGY SYSTEMS
This section provides a general description of the building systems. Energy conservation
opportunities are addressed in the Energy Efficiency Measure section of the report.
Kake Schools 24 Energy Audit (February 2012)
Building Envelope
R-value
Component Description (inside to outside) Existing Optimal
High School
Exterior Wall 5/8” Gyp. bd, 2”x6” stud walls w/average R-21 batt, siding R-21 R-32
Roof 24” o.c. trusses w/ average R-30 all roof sections R-30 R-56
Floor Slab 4” Concrete slab-on-grade R-10 R-10
Foundation 8” concrete - uninsulated R-5 R-20
Windows Vinyl, double pane R-1.5 R-5
Doors Steel doors w/ non-thermally broken frames R-1.5 R-5
Elementary School (Original Portion)
Exterior Wall 5/8” Gyp. Bd, 2”x6” stud walls w/average R-21 batt, siding R-21 R-32
Roof 24” o.c. trusses w/ R-38 batt R-38 R-56
Floor (Vented) Uninsulated floor joists, 50% insulated perimeter rim joists 6” batt R-10 R-40
Foundation 8” concrete – 2” rigid insulation R-10 R-20
Windows Vinyl, double pane R-1.25 R-5
Doors Steel doors w/ non-thermally broken frames R-1.5 R-5
Elementary School (New Addition)
Exterior Wall 5/8” Gyp. Bd, 2”x12” stud walls w/average R-21 batt, siding R-21 R-32
Roof average 7 ½” rigid foam EPDM build up – R35 R-35 R-56
Floor (Vented) 4” concrete slab on grade R-10 R-40
Foundation 8” concrete – 2” rigid insulation R-10 R-20
Windows Vinyl, double pane R-1.25 R-5
Doors Steel doors w/ non-thermally broken frames R-1.5 R-5
Library Building
Exterior Wall 5/8” Gyp. Bd, 2”x6” stud walls w/average R-19 batt, siding R-19 R-32
Roof Rigid foam EPDM build up – R-30 average R-30 R-56
Floor (on pilings) 2” foam insulation, skirting is uninsulated R-10 R-40
Windows Aluminum, double pane R-1.5 R-5
Doors Steel doors w/ non-thermally broken frames R-1.5 R-5
Vocational Building
Exterior Wall 3 ½” batt insulation applied between purlins R-8 R-32
Roof 3 ½” batt insulation applied between purlins R-8 R-56
Floor Slab 4” Concrete slab-on-grade R-10 R-10
Foundation 8” thickened slab R-5 R-20
Windows None - R-5
Doors Non-insulated steel roll-up doors and entry doors R-1.25 R-5
Kake Schools 25 Energy Audit (February 2012)
Heating System
The Kake school buildings are heated by two fuel oil boilers. The heating system has the following
pumps:
High School
CP-1supplies the indirect domestic hot water heaters
CP-2 is a back-up pump for CP-1
CP-3 supplies the high school hydronic heating system
CP-4 is a back-up pump for CP-3 and CP-5
CP-5 supplies the library hydronic heating system
CP-6 supplies high school VU-1 and VU-2
CP-7 is the back-up pump for CP-6 and CP-8
CP-8 supplies the Vocational building hydronic heating system
CP-9 is the boiler B-1 recirculation pump
CP-10 is the boiler B-2 recirculation pump
CP-11 is the domestic hot water recirculation pump
CP-12 is the glycol side supply pump for the heat exchanger
Elementary School
P-1/P-2 are lead/standby pumps for the building hydronic heating loop
P-3/P-4 are lead/standby pumps for the original wing perimeter heating units
P-5 supplies the indirect domestic hot water heater
P-6 is the heat recovery coil pump
P-7/P-8 are lead/standby pumps for the new wing perimeter heating units
P-9 supplies the new wing ventilation units
P-10 supplies AHU-2
HWRP-1 is the domestic hot water recirculation pump
HWRP-2 is the domestic hot water recirculation pump
Library Building
None
Vocational Building
P-1 is the VU-1a heating coil pump
P-2 is the VU-2a heating coil pump
Kake Schools 26 Energy Audit (February 2012)
Ventilation Systems
Area Fan System Description
High School
Gym VU-1 7,500 cfm 5 HP constant volume air handling unit consisting of
a heating coil, mixing box, filter section, and supply fan
School VU-2 6,350 cfm 3 HP constant volume air handling unit consisting of
a heating coil, mixing box, filter section, and supply fan
Boys Locker Room CHU-1 1/3 HP constant volume air handling unit consisting of a heating
coil, filter section, and supply fan
Girls Locker Room CHU-2 ¾ HP constant volume air handling unit consisting of a heating
coil, filter section, and supply fan
Boiler Room VF-1 2,100 cfm ½ HP constant volume ventilation fan
Green House VF-2 1,200 cfm 1/3 HP constant volume ventilation fan
Entry VF-3 1,700 cfm ½ HP constant volume ventilation fan
Gym EF-1 6,400 cfm 2 HP constant volume exhaust fan supplying air to
VU-1
School EF-2 5,700 cfm 2 HP constant volume exhaust fan supplying air to
VU-2
Locker EF-3 1,200 cfm 1/3 HP constant volume exhaust fan
Bathroom EF-4 650 cfm constant volume exhaust fan
Kitchen EF-5 3,000 cfm 1 ½ HP constant volume exhaust fan
Bathroom EF-6 130 cfm constant volume exhaust fan
Elementary School
New Addition AHU-1 7,800 cfm 7 ½ HP constant volume air handling unit consisting
of a heating coil, mixing box, filter section, and supply fan
Original Building
(6 rooms)
AHU-2 5,600 cfm 5 HP constant volume air handling unit consisting of
a heating coil, mixing box, filter section, and supply fan
Original Building
(5 rooms)
HRV 3 HP constant volume air handling unit consisting of a heating
coil, heat recovery coil, filter section, and supply fan (Not Used)
New Addition RF-1 4,800 cfm 2 HP constant volume fan supplying return air to
AHU-1
New Addition EF-1 2,500 cfm 1 HP constant volume exhaust fan
Original Building
(6 rooms)
RF-2 Constant volume fan supplying return air to AHU-2
Library/Head Start Building
Boys Restroom EF-1 110 cfm constant volume exhaust fan
Girls Restroom EF-2 110 cfm constant volume exhaust fan
Head Start Restroom EF-3 110 cfm constant volume exhaust fan
Kake Schools 27 Energy Audit (February 2012)
Ventilation Systems, continued.
Area
Fan
System Description
Vocational Building
Wood /Auto Shop VU-1a Constant volume air handling unit consisting of a heating coil, filter
section, and supply fan
Office/Classroom VU-2a Constant volume air handling unit consisting of a heating coil, filter
section, and supply fan
Auto Shop HX-1 Constant volume exhaust fan with outside make up air heat exchanger
(Not Used)
Auto Shop EF-4a Constant volume exhaust fan (Not Used)
Domestic Hot Water System
The boiler system in the high school provides the heat source for the indirect hot water heaters in the
high school and the elementary school. The high school has two indirect hot water heating units that
are located in the high school boiler room. These appear to be properly sized and in good condition.
The elementary school has a single indirect hot water heater that is poorly insulated and losing a
significant amount of heat to the pump room space. We recommend that the elementary school unit
be replaced with a unit similar to the model used to service the high school.
A 50-gallon electric direct hot water heater is used in the vocational building. This unit is oversized
for the needs of that space. Energy consumption will be reduced if it is replaced with a smaller
indirect hot water heating unit that is supplied from the boilers, since fuel oil heat is less expensive
than electrical heat in Kake.
Automatic Control System
The school facility has a DDC system located in the high school to control the operation of the
heating and ventilation systems. Energy will be saved through further optimization of fan system
scheduling combined with a retro-commissioning of the air handler systems.
Lighting
The maintenance manager at the Kake schools has been very focused on saving energy through
lighting modifications. These efforts will provide a significant reduction in electrical consumption
and cost for the facility. Interior lighting now consists primarily of T8 and compact fluorescent
fixtures. Exterior lighting consists primarily of compact fluorescent lighting, LED lighting, and
several remaining metal halide fixtures. The audit team understands that there will be a continued
effort to complete the lighting conversions in the coming months. Replacement of the remaining
existing fixtures with more efficient units, increased efforts to only use half of the gym lighting when
possible, and the addition of occupancy sensors are solutions for further reductions in operational
costs.
Electric Equipment
Commercial equipment for food preparation was located in the kitchen and surrounding spaces.
Kake Schools 28 Energy Audit (February 2012)
Section 5
Methodology
Information for the energy audit was gathered through on-site observations, review of construction
documents, and interviews with operation and maintenance personnel. The EEMs are evaluated using
energy and life cycle cost analyses and are priority ranked for implementation.
Energy Efficiency Measures
Energy efficiency measures are identified by evaluating the building’s energy systems and comparing
them to systems in modern, high performance buildings. The process for identifying the EEMs
acknowledges the realities of an existing building that was constructed when energy costs were much
lower. Many of the opportunities used in modern high performance buildings—highly insulated
envelopes, variable capacity mechanical systems, heat pumps, daylighting, lighting controls, etc.—
simply cannot be economically incorporated into an existing building.
The EEMs represent practical measures to improve the energy efficiency of the buildings, taking into
account the realities of limited budgets. If a future major renovation project occurs, additional EEMs
common to high performance buildings should be incorporated.
Life Cycle Cost Analysis
The EEMs are evaluated using life cycle cost analysis which determines if an energy efficiency
investment will provide a savings over a 25-year life. The analysis incorporates construction,
replacement, maintenance, repair, and energy costs to determine the total cost over the life of the
EEM. Future maintenance and energy cash flows are discounted to present worth using escalation
factors for general inflation, energy inflation, and the value of money. The methodology is based on
the National Institute of Standards and Technology (NIST) Handbook 135 – Life Cycle Cost
Analysis.
Life cycle cost analysis is preferred to simple payback for facilities that have long—often perpetual—
service lives. Simple payback, which compares construction cost and present energy cost, is
reasonable for short time periods of 2-4 years, but yields below optimal results over longer periods
because it does not properly account for the time value of money or inflationary effects on operating
budgets. Accounting for energy inflation and the time value of money properly sums the true cost of
facility ownership and seeks to minimize the life cycle cost.
Construction Costs
The cost estimates are derived based on a preliminary understanding of the scope of each EEM as
gathered during the walk-through audit. The construction costs for in-house labor are $60 per hour for
work typically performed by maintenance staff and $110 per hour for contract labor.
The cost estimate assumes the work will be performed as part of a larger renovation or energy
efficiency upgrade project. When implementing EEMs, the cost estimate should be revisited once the
scope and preferred method of performing the work has been determined. It is possible some EEMs
will not provide a life cycle savings when the scope is finalized.
Kake Schools 29 Energy Audit (February 2012)
Maintenance Costs
Maintenance costs are based on in-house or contract labor using historical maintenance efforts and
industry standards. Maintenance costs over the 25-year life of each EEM are included in the life cycle
cost calculation spreadsheets and represent the level of effort to maintain the systems.
Energy Analysis
The energy performance of an EEM is evaluated within the operating parameters of the building. A
comprehensive energy audit would rely on a computer model of the building to integrate building
energy systems and evaluate the energy savings of each EEM. This investment grade audit does not
utilize a computer model, so energy savings are calculated with factors that account for the dynamic
operation of the building. Energy savings and costs are estimated for the 25-year life of the EEM
using appropriate factors for energy inflation.
Prioritization
Each EEM is prioritized based on the life cycle savings to investment ratio (SIR) using the following
formula:
Prioritization Factor = Life Cycle Savings / Capital Costs
This approach factor puts significant weight on the capital cost of an EEM, making lower cost EEMs
more favorable.
Kake Schools 30 Energy Audit (February 2012)
Economic Factors
The following economic factors are significant to the findings.
Nominal Interest Rate: This is the nominal rate of return on an investment without regard to
inflation. The analysis uses a rate of 5%.
Inflation Rate: This is the average inflationary change in prices over time. The analysis uses an
inflation rate of 2%.
Economic Period: The analysis is based on a 25-year economic period with construction
beginning in 2010.
Fuel Oil
Fuel oil currently costs $5.48 per gallon for a seasonally adjusted blend of #1 and #2 fuel oil. The
analysis is based on 6% fuel oil inflation which has been the average for the past 20-years.
Electricity
Electricity is supplied by Inside Passage Electrical Cooperative. The building is billed for electricity
under the Large Power Interruptible rate. This rate charges for both electrical consumption (kWh) and
peak electric demand (kW). Electrical consumption is the amount of energy consumed and electric
demand is the rate of consumption.
Large Power Interruptible
Electricity ($ / kWh )
1-60,000 kWh $0.4000
60,000-240,000 kWh $0.3784
>240,000 kWh $0.3679
Customer Charge $160.00
Summary
The following table summarizes the energy and economic factors used in the analysis.
Summary of Economic and Energy Factors
Factor Rate or Cost Factor Rate or Cost
Nominal Discount Rate 5% Electricity (2013) $0.431/kwh
General Inflation Rate 2% Electricity Inflation 6%
Fuel Oil Cost (2013) $5.81/gal Fuel Oil Inflation 6%
Kake Schools 31 Energy Audit (February 2012)
Appendix A
Energy and Life Cycle Cost Analysis
Kake Schools 32 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
Basis
Economic
Study Period (years) 25 Nominal Discount Rate 5%General Inflation 2%
Energy
2012 $/gal Fuel Inflation 2012 $/gal
Fuel Oil $5.48 6% $5.81
Electricity $/kWh (2011)$/kW (2011)Inflation $/kWh (2012)$/kW (2012)
w/ Demand Charges $0.407 $0.00 6% $0.431 $0.00
w/o Demand Charges $0.407 -6% $0.431 -
EEM-13: Install Pipe Insulation
Energy Analysis
Service Size Length Bare BTUH Insul BTUH Factor kBtu η boiler Gallons
Heating 0.75 111 74 11 100% -61,259 68%-650
Heating 1.00 13 90 12 100% -8,883 68%-94
Heating 2.50 6 154 15 100% -7,306 68%-78
-822
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Pipe Insulation 3/4"0 111 lnft $5 $555
1"0 13 lnft $6 $78
2.5"0 6 lnft $9 $54
Estimating contingency 0 15%$103
Energy Costs
Fuel Oil 1 - 25 -822 gal $5.81 ($135,395)
Net Present Worth ($134,600)
EEM-14: (Lib) Turn Off Computers
Energy Analysis
Equipment Number Watts Hours kWh
Workstation 15 -20 4,860 -1,458
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Establish and post computer policy 0 4 hr $60 $240
Energy Costs
Electric Energy 1 - 25 -1,458 kWh $0.431 ($17,829)
Net Present Worth ($17,600)
Kake Schools 33 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-15: (HS) Isolate Standby Boiler
Energy Analysis
Input MBH Loss %Loss MBH Hours, exist Hours, new kBtu η boiler Gallons
1,789 1.0% 18 2,880 1,440 -25,766 68% -274
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Turn off boiler and isolate it 0 1 ea $500 $500
Annual Costs
Alternate lead/standby boilers 1 - 25 2 ea $100.00 $3,405
Energy Costs
Fuel Oil 1 - 25 -274 gal $5.81 ($45,044)
Net Present Worth ($41,100)
EEM-16: Replace Lavatory Aerators
Energy Analysis
η boiler 68%
Fixture Existing Proposed Uses/day Days Water,Gals % HW kBTU Gallons
Lavatories 0.3 0.2 375 198 -13,365 80% -7,134 -76
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Replace lavatory aerators 0 4 ea $35 $140
Replace showerhead 0 1 ea $35 $35
Energy Costs
Fuel Oil 1 - 25 -76 gal $5.81 ($12,471)
Net Present Worth ($12,300)
EEM-17: Perform Boiler Combustion Test
Energy Analysis
Annual Gal % Savings Savings, Gal
33,800 -1.0% -338
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Purchase combustion analyzer 0 1 LS $700 $700
Annual Costs
Clean boielr and perform combustion test 1 - 25 16 hrs $60.00 $16,346
Energy Costs
Fuel Oil 1 - 25 -338 gal $5.81 ($55,651)
Net Present Worth ($38,600)
Gallons per Use
Kake Schools 34 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-18: (HS) Install Gym Light Switch Cover
Energy Analysis
Watts Hours kWh
-4,200 540 -2,268
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Install lockable switch cover 0 1 LS $500 $500
Energy Costs
Electric Energy 1 - 25 -2,268 kWh $0.431 ($27,734)
Net Present Worth ($27,200)
EEM-19: Convert to Propane Heat
Energy Analysis
#2 Fuel Oil
Annual Gal η, boiler Heat kBtu
-33,827 72% -3,373,228
Propane
Heat kBtu η, boiler Gallons
3,373,228 80% 46,747
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Install propane tank and piping 0 1 ea $15,000 $15,000
Repalce boiler burner 0 2 ea $22,000 $44,000
Estimating contingency 0 15%$8,850
Overhead & profit 0 30% $20,355
Design fees 0 10%$8,821
Project management 0 8%$7,762
Energy Costs
Propane 1 - 25 46,747 gal $3.07 $4,073,076
Fuel Oil 1 - 25 -33,827 gal $5.81 ($5,569,540)
Net Present Worth ($1,391,700)
EEM-20: (Elem) Pump Room Heat Recovery
Energy Analysis
Heat Recovery
MBH Hours Loss, kBtu Factor Recovery, kBtu η boiler Gallons
-10 6,480 -64,800 75% -48,600 82% -428
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Supply and return ductwork 0 1 LS $2,500 $2,500
Hot water tank insulating blanket 0 1 LS $500 $500
Balancing 0 1 LS $500 $500
Estimating contingency 0 15%$525
Overhead & profit 0 30%$1,208
Design fees 0 10%$523
Project management 0 8%$460
Energy Costs
Fuel Oil 1 - 25 -428 gal $5.81 ($70,458)
Net Present Worth ($64,200)
Kake Schools 35 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-21: (Voc) Reroute Heating Mains
Energy Analysis
Service Size Length Bare BTUH Insul BTUH Factor kBtu η boiler Gallons
Heating 1.50 28 145 15 100% -31,886 68%-339
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Reroute piping through the exterior wall 0 8 lnft $200 $1,600
Pipe insulation 1-1/2"0 8 lnft $8 $64
Repair wall penetrations 0 1 LS $2,000 $2,000
Estimating contingency 0 15%$550
Overhead & profit 0 30%$1,264
Energy Costs
Fuel Oil 1 - 25 -339 gal $5.81 ($55,745)
Net Present Worth ($50,300)
EEM-22: (HS) Install Gym Light Fixtures
Energy Analysis
Lighting
Room # Fixtures Lamp Lamp, watts Fixture Watts Hours, exist Hours, new Savings, kWh
Gym 25 CFL 168 193 -1,620 1,080 -2,608
Gym 2 CFL 64 74 0 1,080 159
-2,449
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Install wall pak light fixtures 0 2 LS $1,500 $3,000
Overhead & profit 0 30%$900
Project management 0 8%$312
Energy Costs
Electric Energy 1 - 25 -2,449 kWh $0.431 ($29,950)
Net Present Worth ($25,700)
EEM-23: (Voc) Increase Utilidor Pipe Insulation
Energy Analysis
Service Size Length Exist BTUH Insul BTUH Factor kBtu η boiler Gallons
Supply 1.50 111 18 11 100% -6,807 68%-72
Return 1.50 13 18 11 100% -797 68%-8
-81
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Remove and reinstall access covers 0 8 hrs $60 $480
Insulating blanket 0 78 lnft $15 $1,170
Estimating contingency 0 15%$248
Energy Costs
Fuel Oil 1 - 25 -81 gal $5.81 ($13,293)
Net Present Worth ($11,400)
Kake Schools 36 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-24: Optimize Ventilation Systems
Energy Analysis
Fan Case CFM ΔP η, fan BHP η, motor kW Hours kWh
CUH-1 Existing -600 0.50 55% -0.1 70%0 1,800 -165
CUH-3 Existing -600 0.50 55% -0.1 70%0 1,800 -165
EF-3 Existing -1,200 0.50 55% -0.2 70%0 1,800 -329
Optimized 1,200 0.50 55% 0.2 70%0 540 99
EF-1 Existing -2,500 0.88 60% -0.6 85%-1 1,800 -906
Optimized 1,430 0.88 60% 0.3 85%0 1,800 518
0 -948
Ventilation SA CFM MAT T,room MBH Hours kBtu η boiler Gallons
EF-3 Existing -1,200 40 65 -32 1,800 -58,320 68%-619
Optimized 1,200 40 65 32 540 17,496 68%186
AHU-1 Existing -7,600 58 70 -98 1,800 -177,293 68%-1,882
Optimized 7,600 62 70 66 1,800 118,195 68%1,255
-99,922 -1,061
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Remove cabinet unit heater fans 0 2 ea $500 $1,000
Install occupancy sensor and humidity sensor fan controls 0 2 ea $2,500 $5,000
Convert science and storage exhaust to return grilles 0 2 ea $250 $500
Rebalance AHU-1 and EF-1 0 1 LS $6,000 $6,000
Control modifications 0 1 LS $3,000 $3,000
Estimating contingency 0 15%$2,325
Overhead & profit 0 30%$5,348
Design fees 0 10%$2,317
Project management 0 8%$2,039
Energy Costs
Electric Energy 1 - 25 -948 kWh $0.431 ($11,587)
Fuel Oil 1 - 25 -1,061 gal $5.81 ($174,685)
Net Present Worth ($158,700)
EEM-25: Upgrade Transformer
Energy Analysis
Number kVA ηold ηnew KW kWh
1 37.5 96.8% 98.4% -0.6 -5,256
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Replace transformer, kVA 37.5 0 1 LS $6,500 $6,500
Estimating contingency 0 15%$975
Overhead & profit 0 30%$2,243
Design fees 0 10%$972
Project management 0 8%$855
Energy Costs
Electric Energy 1 - 25 -5,256 kWh $0.431 ($64,272)
Electric Demand 1 - 25 -7 kW $0.00 $0
Net Present Worth ($52,700)
Kake Schools 37 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-26: (HS) Server Room Heat Recovery
Energy Analysis
Heat Recovery
MBH Hours Loss, kBtu Factor Recovery, kBtu η boiler Gallons
-5 6,480 -33,165 75% -24,873 82% -219
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Outside air duct through crawlspace to server room 0 1 LS $2,000 $2,000
Exhaust fan discharging to adjacent science room 0 1 LS $2,000 $2,000
Thermostat control 0 1 LS $500 $500
Estimating contingency 0 15%$675
Overhead & profit 0 30%$1,553
Design fees 0 10%$673
Project management 0 8%$592
Energy Costs
Fuel Oil 1 - 25 -219 gal $5.81 ($36,060)
Net Present Worth ($28,100)
EEM-27: (Voc) Replace Shop Door
Energy Analysis
Component Area R,exist R,new ΔT MBH kBtu η boiler Gallons
Overhead Door 144 0.75 5 25 -4.1 -35,741 68%-379
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Replace overhead door 0 144 sqft $60 $8,640
Estimating contingency 0 15%$1,296
Overhead & profit 0 30%$2,981
Design fees 0 10%$1,292
Project management 0 8%$1,137
Energy Costs
Fuel Oil 1 - 25 -379 gal $5.81 ($62,483)
Net Present Worth ($47,100)
Kake Schools 38 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-28: Upgrade Motors
Energy Analysis
Equip Number HP ηold ηnew kW Hours kWh
EF-1 1 1 78.5% 85.5% -0.05 6,480 -338
P-1 1 1.5 78.5% 86.5% -0.09 3,240 -290
P-2 1 1.5 78.5% 86.5% -0.09 3,240 -290
EF-5 1 1.5 78.5% 86.5% -0.09 1,800 -161
EF-1 1 2 80.8% 86.5% -0.09 1,800 -153
EF-2 1 2 80.8% 86.5% -0.09 1,800 -153
VU-2 1 3 84.0% 89.5% -0.12 1,800 -222
VU-1 1 5 74.0% 89.5% -0.58 1,800 -1,041
-1.2 -2,648
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs HP
Replace motor 1 0 1 LS 940 $940
Replace motor 1.5 0 3 LS 955 $2,865
Replace motor 2 0 2 LS 970 $1,940
Replace motor 3 0 1 LS 1,080 $1,080
Replace motor 5 0 1 LS 1,290 $1,290
Estimating contingency 0 15%$1,217
Energy Costs
Electric Energy 1 - 25 -2,648 kWh $0.431 ($32,381)
Net Present Worth ($23,000)
EEM-29: (HS) Operate Kitchen Make-up Air Fan
Energy Analysis
Fan Case CFM ΔP η, fan BHP η, motor kW Hours kWh
MAF Proposed 2,400 1.00 55%1 89%1 1,200 691
Ventilation SA CFM MAT T,room MBH Hours kBtu η boiler Gallons
Infiltration Existing -2,400 40 70 -78 1,800 -139,968 68%-1,486
MAU-1 Optimized 2,400 40 65 65 1,800 116,640 68%1,238
-23,328 -248
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Return MAU-1 to service 0 1 ea $2,500 $2,500
Recalibrate controls 0 1 ea $2,000 $2,000
Estimating contingency 0 15%$675
Overhead & profit 0 30%$1,553
Annual Costs
DDC Maintenance 1 - 25 1 LS $1,000.00 $17,027
Energy Costs
Electric Energy 1 - 25 691 kWh $0.431 $8,444
Fuel Oil 1 - 25 -248 gal $5.81 ($40,783)
Net Present Worth ($8,600)
Kake Schools 39 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-30: (HS) Replace Single Pane Glazing
Energy Analysis
Component Area R,exist R,new ΔT MBH kBtu η boiler Gallons
Windows 67 0.75 2.5 20 -1.3 -10,956 68%-116
Door 9 0.75 2.5 20 -0.2 -1,472 68%-16
-1.4 -12,428 -132
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Replace window glazing unit 0 67 sqft $85 $5,695
Replace door glazing unit 0 9 sqft $85 $765
Estimating contingency 0 15%$969
Overhead & profit 0 30%$2,229
Design fees 0 10%$966
Project management 0 8%$850
Energy Costs
Fuel Oil 1 - 25 -132 gal $5.81 ($21,726)
Net Present Worth ($10,300)
EEM-31: (HS) Boiler Room Heat Recovery
Energy Analysis
Heat Recovery
Input, MBH Jacket Loss MBH Hours Loss, kBtu Factor Recovery, kBtu η boiler Gallons
3,579 -1.0% -36 6,480 -231,891 75% -173,919 82%-1,531
Heat Pump Energy
Recovery, kBtu COP kWh HP Heat, kBtu η boiler Gallons
-173,919 3 16,991 57,973 82% -510
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Boiler room heat pump 0 1 LS $15,000 $15,000
Gym fan coil unit 0 1 LS $6,000 $6,000
Piping between heat pump and fan coil 0 1 LS $12,000 $12,000
Controls 0 1 LS $6,000 $6,000
Estimating contingency 0 15%$5,850
Overhead & profit 0 30% $13,455
Design fees 0 10%$5,831
Project management 0 8%$5,131
Annual Costs
Heat pump maintenance 1 - 25 1 LS $250.00 $4,257
Energy Costs
Electric Energy 1 - 25 16,991 kWh $0.431 $207,771
Electric Demand 1 - 25 60.0 kW $0.00 $0
Fuel Oil 1 - 25 -2,042 gal $5.81 ($336,184)
Net Present Worth ($54,900)
Kake Schools 40 Energy Audit (February 2012)
Alaska Energy Engineering LLC Energy and Life Cycle Cost Analysis
25200 Amalga Harbor Road Tel/Fax: 907.789.1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
EEM-32: (Lib) Increase Building Floor Insulation
Energy Analysis
Component Area R,exist R,new ΔT MBH kBtu η boiler Gallons
Floor 3,850 12 30 25 -4.8 -31,185 68%-331
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Insulate crawlspace floor and perimeter 0 3,850 sqft $5 $19,250
Estimating contingency 0 15%$2,888
Overhead & profit 0 30%$6,641
Design fees 0 10%$2,878
Project management 0 8%$2,533
Energy Costs
Fuel Oil 1 - 25 -331 gal $5.81 ($54,518)
Net Present Worth ($20,300)
EEM-33: Convert to Variable Speed Pumping
Energy Analysis
Pump GMP Head η pump BHP η motor kW Hours kWh
High School
CP-1/CP-2 -10 22 50% -0.1 70% -0.2 6,480 -1,028
CP-3 -56 45 60% -1.4 89% -1.2 6,480 -7,717
CP-5 -18 44 50% -0.5 89% -0.4 6,480 -2,911
CP-6 -131 25 75% -1.5 89% -1.2 6,480 -8,024
CP-8 -20 38 60% -0.4 89% -0.4 6,480 -2,327
Elementary School
P-1/P-2 -110 24 65% -1.4 89% -1.2 6,480 -7,463
Primary/Secondary
Design
P-1/P-2 150 15 65% 1.2
P-3A/P-3B 300 30 65% 4.7
Average Flow
P-1/P-2 150 15 65% 1.2 92% 0.9 6,480 6,153
P-1/P-2 150 20 65% 1.6 92% 1.3 6,480 8,204
-15,113
Life Cycle Cost Analysis Year Qty Unit Base Cost Year 0 Cost
Construction Costs
Demo boiler room pumps and piping 0 1 LS $5,000 $5,000
Primary pumps, 1,5 HP 0 2 LS $5,000 $10,000
Secondary pumps, 5 HP with VFD 0 2 LS $10,000 $20,000
Piping and appurtenances 0 1 LS $50,000 $50,000
Controls 0 1 LS $20,000 $20,000
Estimating contingency 0 15% $15,750
Overhead & profit 0 30% $36,225
Design fees 0 10% $15,698
Project management 0 8% $13,814
Annual Costs
Pump maintenance 1 - 25 -6 ea $200.00 ($20,432)
Energy Costs
Electric Energy (Effective Cost)1 - 25 -15,113 kWh $0.431 ($184,804)
Net Present Worth ($18,800)
Kake Schools 41 Energy Audit (February 2012)
Appendix B
Energy and Utility Data
Kake Schools 42 Energy Audit (February 2012)
Alaska Energy Engineering LLC Billing Data
25200 Amalga Harbor Road Tel/Fax: 907-789-1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
ELECTRIC RATE
Electricity ($ / kWh )
1-60,000 kWh $0.4000
60,000-240,000 kWh $0.3784
>240,000 kWh $0.3679
Customer Charge $160.00
ELECTRICAL CONSUMPTION AND DEMAND
2008 2009 2010 2011
kWh kWh kWh kWh
Jan 22,800 22,080 30,240 28,800 25,980
Feb 26,160 27,840 33,840 29,760 29,400
Mar 23,760 24,960 25,440 27,600 25,440
Apr 24,480 24,960 32,880 25,920 27,060
May 21,360 24,960 28,800 23,040 24,540
Jun 19,200 15,120 22,320 15,120 17,940
Jul 12,720 15,120 19,200 14,540 15,395
Aug 11,520 11,760 24,000 16,997 16,069
Sep 21,360 20,400 31,920 24,075 24,439
Oct 26,640 23,520 30,240 24,410 26,203
Nov 20,400 30,720 32,160 27,807 27,772
Dec 27,360 31,680 32,160 26,604 29,451
Total 257,760 273,120 343,200 284,673 289,688
Average 21,480 22,760 28,600 23,723 24,141
ELECTRIC BILLING DETAILS
Month Energy Total Energy Total % Change
Jan $12,096 $12,256 $11,520 $11,680 -4.7%
Feb $13,536 $13,696 $11,904 $12,064 -11.9%
Mar $10,176 $10,336 $11,040 $11,200 8.4%
Apr $13,152 $13,312 $10,368 $10,528 -20.9%
May $11,520 $11,680 $9,216 $9,376 -19.7%
Jun $8,928 $9,088 $6,048 $6,208 -31.7%
Jul $7,680 $7,840 $5,816 $5,976 -23.8%
Aug $9,600 $9,760 $6,799 $6,959 -28.7%
Sep $12,768 $12,928 $9,630 $9,790 -24.3%
Oct $12,096 $12,256 $9,764 $9,924 -19.0%
Nov $12,864 $13,024 $11,123 $11,283 -13.4%
Dec $12,864 $13,024 $10,642 $10,802 -17.1%
Total $ 137,280 $ 139,200 $ 113,869 $ 115,789 -16.8%
Average $ 11,440 $ 11,600 $ 9,489 $ 9,649 -16.8%
Cost ($/kWh) $0.406 $0.407 0.3%
2010 2011
Electrical costs are based on the current electric rates.
Large Power Interruptible
Month Average
Kake Schools 43 Energy Audit (February 2012)
Alaska Energy Engineering LLC Annual Electric Consumption
25200 Amalga Harbor Road Tel/Fax: 907-789-1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecElectric Use (kWh)Month of the Year
Electric Use History
2008 2009
2010 2011
$ 0
$ 2,000
$ 4,000
$ 6,000
$ 8,000
$ 10,000
$ 12,000
$ 14,000
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecElectric Cost (USD)Month of the Year
Electric Cost Breakdown
2010
Kake Schools 44 Energy Audit (February 2012)
Alaska Energy Engineering LLC Annual Fuel Consumption
25200 Amalga Harbor Road Tel/Fax: 907-789-1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Kake Schools
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
Year #2 Fuel Oil #1 Fuel Oil Propane Degree Days Total
2,008 31,863 985 300 9,093 32,163
2,009 42,560 1,004 300 9,284 42,860
2,010 31,348 970 300 9,013 31,648
2,011 29,536 925 300 8,729 29,836
Average 33,827 971 300
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
50,000
2008 2009 2010 2011 Degree DaysGallonsYear
Annual Fuel Use
#2 Fuel Oil #1 Fuel Oil
Propane Degree Days
Kake Schools 45 Energy Audit (February 2012)
Alaska Energy Engineering LLC
25200 Amalga Harbor Road Tel/Fax: 907-789-1226
Juneau, Alaska 99801 jim@alaskaenergy.us
Annual Energy Consumption and Cost
Energy Cost $/MMBtu Area ECI EUI
#2 Fuel Oil $5.48 $56.52 80,900 $3.83 72
#1 Fuel Oil $5.61 $52.33
Electricity $0.407 $125.48
Propane $3.66 $50.72
Source Cost
Electricity 289,688 kWh $117,800 1,000 17%
Propane 300 Gallons $1,100 30 1%
#1 Fuel Oil 971 Gallons $5,400 130 2%
#2 Fuel Oil 33,827 Gallons $185,400 4,700 80%
Totals $309,700 5,860 100%
Annual Energy Consumption and Cost
Consumption Energy, MMBtu
$0
$20
$40
$60
$80
$100
$120
$140
#2 Fuel Oil #1 Fuel Oil Electricity PropaneCost $ / MMBtuCost of Heat Comparison
Kake Schools 46 Energy Audit (February 2012)
Appendix C
Equipment Data
Kake Schools 47 Energy Audit (February 2012)
MotorHP / Volts / RPM / EfficEF-1 Men's Room Exhaust FanBroan 676F-B 110 CFM 115 VInterlocked with lightEF-2Women's RoomExhaust FanBroan 676F-B 110 CFM 115 VInterlocked with lightEF-3 Headstart Restroom Exhaust Panasonic110 CFM 115 VInterlocked with lightT-1 Library HeaterToyo Laser 73 40 MBHT-2 PAT Office HeaterToyo Laser 30 15 MBHT-3 Headstart HeaterToyo Laser 73 40 MBHF-1Outside High SchoolWalk-In Freezer HeatKraft ELC096BJ208 V - (2) 1/20 HPVU-1AWood/Auto Shops Pace B-11F1.5 HP/ 208 V/ 1750 RPMVU-2AOffice/Classroom Pace A-8Fno nameplate dataP-1 Attic VU-1A Fan Coil B&G 60451/4 HP/ 115 V/ 1715 RPM/47%P-2 Attic VU-2A Fan Coil B&G 189105no name plateDHWHElectric Hot Water Heater AO Smith Energy Saver 50 Gallon 4500 Watts upper 4500 Watts lowerHX-1 Auto Shop Supply FanPace1.5 HP/ 208 V/ 1725 RPM/ 78.5% Not usedExhaust FanPaceno dataNot usedEF-4A Auto Shop Exhaust FanPacenot usedLibrary / Headstart BuildingVocational BuildingKake K-12 Schools - Major Equipment InventoryCapacityNotesUnit IDLocation Function Make Model
Kake Schools 48 Energy Audit (February 2012)
MotorHP / Volts / RPM / EfficKake K-12 Schools - Major Equipment InventoryCapacityNotesUnit IDLocation Function Make ModelP-1 Pump Room Building Heating Taco 1639C3E2-6.191.5 HP/ 208 V/ 1725 RPM/78.5%P-2 Pump Room Building Heating Taco 1635C3E3-6.191.5 HP/ 208 V/ 1725 RPM/78.5%P-3 Pump Room Elementary Radiation Taco 1615C3N31/3 HP/ 115 V/ 1725 RPM/60P-4 Pump Room Elementary Radiation Taco1/3 HP/ 115 V/ 1725 RPM/60%P-5 Pump Room Hot Water TankTaco 121A3N14.31/4 HP/ 115 V/ 1725 RPM/47%P-6 Pump Room HRV CoilTaco 11181/8 HP/ 115 V/ 1750 RPMP-7New Radiation System Taco 1615C3N11/2 HP/ 115 V/ 1750 RPM/62%P-8New Radiation System1615C3N11/2 HP/ 115 V/ 1750 RPM/62%P-9AHU-1 Fan Coil Taco 1615C3N23/4 HP/ 208 V/ 1725 RPM/76%HW RP-1 Pump Room Hot Water Return Pump Taco115 VHW RP-2 Pump Room Hot Water Return Pump Taco 005-BF21/35 HP/ 115 VDHWH-1 Pump Room Indirect Hot Water Heater Ajax VG3004MW 190 GallonAHU-1 New Addition New Addition Vent LogicAir CSU-6K-H-8 7800 CFM 7.5 HP/ 208 V/ 1760 RPM/ 91% offRF-1 New Addition New Addition RF LogicAir CSU-6K 4800 CFM 2 HP/ 208 V/ 1725 RPM/ 86.5% offEF-1 New Addition New AdditionCook 180 CPS 2500 CFM 1 HP/ 208 V/ 1725 RPM/ 78.5%AHU-2 Elementary Old ClassroomsHaakon Airpak5600 CFM 5 HP/ 208 V/ 1750 RPM/ 89.5% Supply fan5200 CFM 1.5 HP/ 208 V/ 1750 RPM/78.5% Return fanP-10Boiler Loop Pump Taco 0011F4 5200 CFM 1/8 HP/ 3250 RPM/ 115 VHRV Old Fan Room Ventilation and Exhaust DLI MicroZ3 HP/ 208 V/ 1750 RPM/81.4%3 HP/ 208 V/ 1750 RPM/81.4%Elementary School BuildingKake Schools 49 Energy Audit (February 2012)
MotorHP / Volts / RPM / EfficKake K-12 Schools - Major Equipment InventoryCapacityNotesUnit IDLocation Function Make ModelB-1 Boiler Room BoilerBurnham V11091503 MBH 2 HP/ 120 V/86.5%B-2 Boiler Room BoilerBurnham V11091503 MBH 2 HP/ 120 V/80.8%HWG-1 Boiler Room Domestic Hot Water Heater Amtrol WHS-120ZC-DW 119 Gallon indirect hot water heaterHWG-2 Boiler Room Domestic Hot Water Heater Amtrol WHS-120ZC-DW 119 Gallon indirect hot water heaterCP-1 Boiler Room Hot Water Circulation Grundfos UP 43-75F 10 gpm 1/6 HP/ 120 VCP-2 Boiler Room Back Up for CP-1 Grundfos UP 43-75F 10 gpm 1/6 HP/ 120 VCP-3 Boiler Room Building HeatGrundfos UPS 50-160 56 gpm 1.5 HP/ 208 V/ speed 3/81.4%CP-4 Boiler Room Backup for CP-3 & CP-4 Grundfos UPS 50-160 56 gpm 1.5 HP/ 208 V/ speed 3/81.4%CP-5 Boiler Room Library HeatGrundfos UPS 50-160 18 gpm 1.5 HP/ 208 V/ speed 3/81.4%CP-6 Boiler Room VU-1 and VU-2Grundfos UPS 50-160 131 gpm 1.5 HP/ 120 V/ speed 3/81.4%CP-7 Boiler Room Back Up CP-6 and CP-8 Grundfos UPS 50-160 56 gpm 1.5 HP/ 208 V/ speed 3/81.4%CP-8 Boiler Room Shop BuildingGrundfos UPS 50-160 20 gpm 1.5 HP/ 208 V/ speed 1/81.4%CP-9 Boiler Room B-1 Boiler Shock Grundfos UP 26-99F 30 gpm 1/6 HP/ 120 VInterlock w/boiler enableCP-10 Boiler Room B-2 Boiler Shock Grundfos UP 26-99F 30 gpm 1/6 HP/ 120 VInterlock w/boiler enableCP-11 Boiler Room Domestic HWCGrundfos UPS 15-42F 2 gpm 1/25 HP/ 120 V/ speed 1CP-12 Boiler Room HX, Glycol Side Grundfos UP 26-99F 20 gpm 1/6 HP/ 120 VSP-1 Boiler Room Sump PumpGrundfos KP1503 gpm 1/4HP/ 120 V/47%MUA-1Kitchen Make Up Air Gaylord MCF-2300A 2400 CFM 3/4 HP/ 208 V/76%T-1 Boiler Room TransformerTierney A01137-3T131115 37.5 KVANon TPI rated 115° FVU-1 Fan Room 1 Gym SupplyPace A-20F7500 CFM 5 HP/ 208 V/ 1725 RPM/ 74%Outside air damper brokenVU-2 Fan Room 2 School SupplyPace A-18F6350 CFM 3 HP/ 208 V/ 1755 RPM/81.4%EF-1 Fan Room 1 Gym ReturnPace A-20F6400 CFM 2 HP/ 208 V/ 1750 RPM/80.8%EF-2 Fan Room 2 School ReturnPace A-20F5700 CFM 2 HP/ 1208 V/ 1725 RPM/80.8%High School BuildingKake Schools 50 Energy Audit (February 2012)
MotorHP / Volts / RPM / EfficKake K-12 Schools - Major Equipment InventoryCapacityNotesUnit IDLocation Function Make ModelEF-3 Roof Locker ExhaustCook1200 CFM 1/8 HP/ 120 VEF-4 Bathrooms Bathroom Exhaust Cook650 CFM 1/3 HP/ 120 V/60%EF-5 Roof Kitchen Grease Hood Cook 180V8B 3000 CFM 1.5 HP/ 208 V/ 1725 RPM/ 84%EF-6 Bathrooms Bathroom Cabinet Exhaust Penn ZIV130 CFM 125 W/ 120 VVF-1 Boiler Room Ventilation FanLoren Cook 108510DF 2100 CFM 1/2HP/ 120 V/62%Thermostat @ 70°FVF-2 Roof Green House Vent Fan Cook1200 CFM 1/3 HP/ 120 V/60%VF-3 Entry Entry Vent FanPenn1700 CFM 1/2 HP/ 120 V/62%RH-1Home EconomicsRange Hood Fan Nutone RL6300 190 CFM 120 VCHU-1Above Locker RoomsBoys Locker Room Pace A-8F1/3 HP/ 115 V/ 1725 RPM/60% Running - belt brokenAC-1 Book Room Air ConditionerAir Technology not usedCHU-2Above Locker RoomsGirls Locker Room Pace A-8F3/4 HP/ 115 V/76%2 Kitchen Convection Oven2.16 KW 120 V/ 18 Amps3 Kitchen Tilting Kettle120 V/ 10 Amps5 Kitchen Range120 V7 Kitchen Serving Counter120 V/ 20 Amps9 Kitchen Hot Food Wells2.6 KW 208 V/ 12.3 Amps10 Kitchen Cold Food Unit1/5 HP/ 120 V/ 2.3 Amps16 Kitchen Refrigerator1/3 HP/ 120 V/ 9.6 Amps/60%17 Kitchen Freezer3/4 HP/ 120 V/ 11 Amps/76%18 Kitchen Preparation Table120 V/ 15 Amps27 Kitchen Dishwasher208 V/ 43.6 Amps30 Kitchen Mixer1/2 HP/ 120 V/62%31 Kitchen Disposer208 V/ 3 phase/ 3.3 AmpsHigh School Building, continuedKake Schools 51 Energy Audit (February 2012)
Appendix D
Abbreviations
AHU Air handling unit
BTU British thermal unit
BTUH BTU per hour
CBJ City and Borough of Juneau
CMU Concrete masonry unit
CO2 Carbon dioxide
CUH Cabinet unit heater
DDC Direct digital controls
DHW Domestic hot water
EAD Exhaust air damper
EEM Energy efficiency measure
EF Exhaust fan
Gyp Bd Gypsum board
HVAC Heating, Ventilating, Air-
conditioning
HW Hot water
HWRP Hot water recirculating pump
KVA Kilovolt-amps
kW Kilowatt
kWh Kilowatt-hour
LED Light emitting diode
MBH 1,000 Btu per hour
MMBH 1,000,000 Btu per hour
OAD Outside air damper
PSI Per square inch
PSIG Per square inch gage
RAD Return air damper
RF Return fan
SIR Savings to investment ratio
SF Supply fan
UV Unit ventilator
VAV Variable air volume
VFD Variable frequency drive
Kake Schools 52 Energy Audit (February 2012)