HomeMy WebLinkAboutKingcove Oldharbor Hydro 10 of 13 1982SECTION V
TOGIAK
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume E--
Reconnaissance Study for Togiak Hydroelectric Project. Included
for general background information are several items from that
report: Exhibit VI-1, Photographs of the Project Area; Figure
VII-4, Projected Monthly Generation, Demand, and Usage; and
selected project drawings which include Plate I, the General
Plan, and Plate II, Alternative A - Plans and Sections.
References to figures, exhibits, and plates in the summary
presented here refer to items in Volume E, the full feasibility
report for the Togiak Hydroelectric Project'.
NBI-432-9526-ST V-1
TOGIAK
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying the
Togiak area with electrical energy had recommended a hydroelec-
tric project as the best source. As a direct result of these
prior studies and recommendations, the Alaska Power Authority
authorized a reconnaissance -level feasibility study to investi-
gate in detail the hydropower potential in the vicinity of
Togiak.
This report summarizes the activities conducted for the
reconnaissance study. These activities included projections of
energy needs, formulation of alternative hydroelectric projects
and a hypothetical base case to meet the electrical energy
needs of Togiak, detailed analyses of economic feasibility, and
preparation of an environmental assessment of the effects of
the project.
The results of the technical studies conducted indicate
that a 432 kilowatt (kW) hydroelectric project utilizing a 38-
foot-high concrete dam could be constructed on the Quigmy River
to meet the electric demands of Togiak. However, the results
of the economic analyses indicate that the hydroelectric
project would have only marginal feasibility. An additional
project on the Kurtluk River is currently under investigation.
The results of this investigtion will be presented in a
subsequent report.
The total cost of the proposed Togiak hydroelectric project
is $7,047,200 with the 4.6-mile road option and $8,169,600 with
the 11.6-mile road in January 1982 dollars. The project could
be implemented and on-line by January 1, 1985, if a decisio❑ to
NBI-432-9526-ST V-2
proceed with the project is made by December 1982. During an
average water year, the proposed project would be capable of
supplying about 99 percent of the electrical needs and about 30
percent of the space heating needs in the project area. The
equivalent savings in diesel fuel in the year 2001 would be
144,000 gallons for direct electrical demand and 44,000 gallons
for space heating.
B. AREA DESCRIPTION
Togiak is a small village located on Bristol Bay about 70
miles west of Dillingham and 400 miles southwest of
Anchorage. The hydroelectric site selected for detailed study
is on the Quigmy River about 12 miles west of Togiak. The
smaller village of Twin Hills, four miles east of Togiak, was
included i❑ the assessment of the future power needs of the
area.
C. POWER PLANNING
Power planning for the Togiak Project was conducted using
standards set forth by the Alaska Power Authority. Previously
recommended potential hydroelectric sites were investigated and
the project area was surveyed to evaluate potential new
sites. After detailed study, a project was selected and then
compared with a base case plan. The base case pla❑ consisted
of a continuation of the present diesel generatio❑ system,
enlarged as necessary to meet future growth. The installation
of waste heat recovery equipment and wind generators was also
considered as part of the base case plan.
Present energy demands for Togiak for direct electrical
uses and space heating were estimated and future uses in these
same categories were projected. The projections were based on
forecasts of increases i❑ the number of customers and increased
usage rates. Population growth and employment, legislation and
NBI-432-9526-ST V-3
other political influences, life style changes, and other
factors can influence future energy demands but were not
explicitly treated.
The period of economic evaluation used was 53 years, which
starts in January 1982 and extends for the 50-year life of the
hydroelectric project after the estimated on-line date of
January 1985. The energy demands for Togiak were increased for
20 years starting in 1982 and extending through December
2001. The demands were then held level over the remainder of
the economic evaluation period. As stated, the neighboring
community of Twin Hills was included in estimating future
energy demands.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be for
the direct electrical needs of the Togiak area, and any remain-
ing energy would be used for space heating.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine -
generator system to produce electric power. In the case of the
alternative projects considered to bring hydroelectric power to
Togiak, three dam configurations and two access road options
were evaluated. These are described below. All three of the
dams considered would divert water from the Quigmy River
through an intake structure and pass the water through a tur-
bine -generator system to produce electric energy. An access
road would be constructed from Togiak to the project facilities
and a transmission line would be constructed along the access
road alignment to transmit the power generated at the plant to
Togiak.
NBI-432-9526-ST V-4
The general plan and features of the recommended hydroelec-
tric project are presented in the plates of Appendix A. Photo-
graphs of the project area are presented in Exhibits VI-1
through VI-3 of Section VI and in pages 2, 10, and 15 of
Appendix E.
The site selected for investigation was a narrow canyon
suitable for either a concrete or rockfill dam. Since both
types were apparently technically feasible, two concrete dams
(38 and 28 feet high) and one rockfill dam were investigated to
evaluate their economic feasibility and confirm their technical
feasibility. Although the Quigmy River above the proposed dam
site locations might not be a major spawning area, the
preliminary designs for all three dam alternatives incorporated
fish ladders to allow for fish passage.
An 11.6-mile road would be required to provide access from
Togiak to the proposed facilities. The Alaska State Department
of Transportation and Public Facilities, Division of Aviation,
is investigating the possibility of building a road along the
first seven miles of the proposed access road alignment in
order to reach a gravel source needed to construct an airport
to serve Togiak. Two possibilities exist for obtaining an
access road for the proposed hydroelectric project:
1. The entire 11.6-mile road would be built as part of
the hydroelectric project.
2. The Alaska Department of Transportation would build
the first seven miles of the road and the hydroelec-
tric project would build the remaining 4.6 miles.
The investigations conducted during this study indicate
that the most favorable combination, and indeed the only one
that could be economically feasible, is the 38-foot-high
concrete dam with only 4.6 miles of the access road being
funded by the project.
NBI-432-9526-ST V-5
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of Togiak assumed that the existing diesel system would
continue to be used as the sole source of electric power. It
was also assumed that the system would be modified to incorpor-
ate waste heat recovery that would be used for space heating.
Wind generation would also be installed as part of this plan.
The existing diesel plant's capacity was judged to be adequate
to meet peak demands on the Togiak system throughout the period
of study. The forecasted energy demands for the base case
included the requirements for Twin Hills.
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
base case costs to the net present worth of the alternative
proposed hydroelectric project costs using specified real price
escalation and discount rates. Net present worth is the
present value of the costs that would be incurred over a
comparable economic evaluation period of 53 years for both
projects.
The net present worths of the base case are as follows:
Base Case Only
Waste Heat Credit
Subtotal
Wind Energy Credit
Subtotal
Space Heating Credit
Total
Alternatives A & C
$11,027,600
999,400
10,028,200
540,700
9,487,500
2,463,000
$11,950,500
NBI-432-9526-ST V-6
Alternative B
-.$111027,600
999,400
10,028,200
540,700
9,4879500
1 234,800
17221,300
I
The space heating credit was shown as an increase in cost
to the base case so that all present worths could be compared
to the hydroelectric project standing alone.
For the three alternative hydroelectric projects studied,
the present worth of the costs is as follows:
Alternative A
Alternative B
Alternative C
W/11.6-Mile ,Road
$12,758,400
13,037,400
13,257,700
W/4.6-Mile Road
$11,668,600
11,947,600
12,167,900
As can be noted from the table, the only hydroelectric
alternative with a lower present worth cost than the base case
is alternative A, and then only if the 4.6-mile roadway can be
constructed.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For the alternative studies for this project,
the calculated B/C ratios were as follows:
B/C Ratio B/C Ratio
W/11,6-Mile Road W/4.6-Mile Road
Alternative
A
0.937
1.024
Alternative
B
0.822
0.897
Alternative
C
0.982
_. 0.901
NBI-432-9526-ST V-7
These results indicate that Alternative A, the 38-foot-high
concrete dam with 432 kW installed capacity, is marginally
feasibile only if the Alaska Department of Transportation con-
structs the first 7.0 miles of the required 11.6-mile access
road. If the entire 11.6-mile road must be constructed, the
project is a break-even proposition.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The study results indicate that a hydroelectric project at
the Quigmy site could have potentially serious environmental
impacts, but measures such as fish ladders could likely miti-
gate the most serious effects. Additional studies are recom-
mended to answer questions related to the downstream effects of
the dam impoundment on salmon spawning; coho (silver) salmon
runs; minimum water requirements for fish below the proposed
dam; selection of a suitable access route; and methods to
ensure safe passage of out -migrating young salmon. Additional
study of fish passage facilities is also recommended.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that a
marginally feasible project consisting of a 38-foot-high
concrete dam with 432 kW installed capacity could be con-
structed at the Quigmy River site. The next step in project
implementation, the preparation of a Definitive Project Report
to optimize the project features, should be pursued only if the
Alaska Department of Transportation constructs the initial 7.0
miles of the necessary 11.6-mile-long access road.
A more detailed investigation of a much smaller hydroelec-
tric site on the Kurtluk River three miles from Togiak could be
pursued, but the project would meet only a small portion of the
Togiak electric demands. The site is currently being investi-
gated at a preliminary level and will be addressed in a
subsequent letter report.
NBI-432-9526-ST V-8