HomeMy WebLinkAboutKingcove Oldharbor Hydro 2 of 13 1982Volume A
FINAL SUMMARY REPORT
Feasibility Studies for
KING COVE HYDROELECTRIC PROJECT
OLD HARBOR HYDROELECTRIC PROJECT
LARSEN BAY HYDROELECTRIC PROJECT
Reconnaissance Study for
TOGIAK HYDROELECTRIC PROJECT
Submitted by
DOWL ENGINEERS
ANCHORAGE, ALASKA
In Association with
TUDOR ENGINEERING COMPANY
SAN FRANCISCO, CALIFORNIA
DRYDEN & LARUE
ANCHORAGE, ALASKA
AUGUST 1982
ALASKA POWER AUTHORITY
SUMMARY VOLUME
CONTENTS
Section
Page
FOREWORD
I.
INTRODUCTION
I-1
II.
KING COVE SUMMARY
II-1
III.
OLD HARBOR SUMMARY
III-1
IV.
LARSEN BAY SUMMARY
IV-1
V.
TOGIAK SUMMARY
V-1
NBI-432-9526-SC i
FOREWORD
This volume, Volume A, is a summary report incorporating
the findings, conclusions, and recommendations of the feasibil-
ity studies for King Cove (Volume B), Old Harbor (Volume C),
and Larsen Bay (Volume D) and the reconnaissance study for
Togiak (Volume E). Volumes B through E are comprehensive
individual project reports that present the findings and recom-
mendations of studies to assess the economic, technical,
environmental, and social feasibilities of hydroelectric
projects for these four villages.
Each of the volumes for the individual project reports
consists of 12 sections and six appendices. The first section
of each report is a concise summary of all activities conducted
for the particular project. Following a brief introduction,
Section I, these summaries from each volume are reproduced here
as Sections II, III, IV and V and some similarity in format and
narrataive will be noted. Selected photographs, figures and
drawings have also been included with each summary section as
appropriate.
NBI-432-9526-SF ii
TOGIA
KING COV
Ci 0
oQ oD LARSEN BAY
LOCATION MAP FIGURE
1-1
SECTION I
INTRODUCTION
A. GENERAL
This summary report presents the overall results of studies
conducted to appraise proposed hydroelectric projects at King
Cove, Larsen Bay, Old Harbor and Togiak. With the exception of
Togiak, all studies were at the feasibility level and included
the optimal sizing of all project features. The studies for
Togiak were at a reconnaissance level since the prior studies
were not as extensive and since the proposed project involves a
small dam and is more complex.
The studies were authorized by the Alaska Power Authority
as a result of numerous prior studies of energy alternatives
that had recommended hydroelectric projects as the best source
of future electric energy for the four villages. In addition
to the hydropower alternative, the continued use of diesel
generators, the installation of waste heat recovery equipment,
and the installation of wind powered generators were all
considered as possible future energy sources.
The overall results of these studies indicate that feasible
hydroelectric projects can be constructed at King Cove, Old
Harbor and Larsen Bay. The study for Togiak indicates that a
hydroelectric project of sufficient size to satisfy the overall
electric demands is marginal at best and then only if 7.0 miles
of the required 11.6-mile access road to the site is con-
structed by the Alaska Department of Transportation. It may,
however, be possible to construct a much smaller hydropower
site near Togiak which would satisfy at least a portion of the
electrical needs of the village. This site is currently being
assessed at a preliminary level and will be addressed in a
later report.
NBI-432-9526-SI I-1
Any or all projects studied could be constructed and on-
line by January 1985 if a decision to proceed is made by
December 1982.
B. PURPOSE AND SCOPE OF STUDIES
The primary purposes of the studies for King Cove, Larsen
Bay and Old Harbor were to prepare recommendations of the best
configurations for developing dependable sources of hydro-
electric energy supplies for the villages and to determine the
engineering, environmental, and economic feasibilities of the
projects. For Togiak the primary purpose was to determine if
any feasible project could be constructed with the intent to
optimize the project features in the next phase if overall
feasibility was demonstrated.
The general scope of the studies consisted of first
projecting the future electrical energy needs of the villages
over a 20-year planning period and developing alternative
diesel and hydroelectric project scenarios to meet those
projections. Increases in demand for energy and the cost of
petroleum products were recognized for a 20-year planning
period extending from 1982 through 2001. The demands and costs
were assumed to be constant after the 20-year planning period.
The period for economic evaluation extended 50 years past the
on-line date for the hydroelectric alternative. Economic
comparisons were then made between these alternatives, the
environmental effects were assessed, and conclusions and
recommendations were formulated.
NBI-432-9526-SI I-2
The diesel alternative for each village was know❑ as the
"base case" plan and was essentially a continuation of the
present diesel generating plants, enlarged as necessary to
accommodate future growth. Heat recovery, to be used for local
space heating, was incorporated with the base case plans to the
maximum extent that is economically feasible. Wind generation
was also considered as part of the base case plan and was found
to be economically feasible, although of limited value, at all
four sites.
Some hydroelectric energy was also used for space heating.
I❑ assessing power and energy priorities for the hydroelectric
energy for each village, the first priority was given to the
direct electrical demand for the village. The second priority,
when excess energy was available, was the cannery demand (King
Cove only) and the third priority was the village space heating
demand.
C. OVERALL STUDY RESULTS
A table presenting the size, average annual energy
generated, the estimated cost (in 1982 dollars), the fuel oil
displaced by the hydroelectric energy, and the benefit/cost
ratio (B/C) for each project is presented below. The B/C
ratios shown reflect the benefits from waste heat recovery, and
wind generation and the utilization of excess electrical energy
for space heating (and the cannery at King Cove). A more
detailed summary is contained in the following sections of this
volume: King Cove, Section II; Old Harbor, Sect -ion III; Larsen
Bay, Section IV; and Togiak, Section V.
NBI-432-9526-SI I-3
Average
Annual 1982 Fuel Oil
Project Size Energy Cost Displaced/Yr. B/C
(kW) ^\J kWh $ (Gal. )
King Cove 575 \ _.2,280,0001. 3,744,90010Yr143,700 2.011
054
Larsen Bay 270 " , 1, 090, 00e, 2, 8;1, 400 °ii0Ap 85,700 1.237
yd
Old Harbor 340 0�'L--1,310,000,4`11=3,082,300 �; N' 1039300 1.403
Togiak 432 6iV 2,660,00041119 7,047,200 189,800 1.024
(lid 'CA. i C..'•. 5� 92n°fin
The values given above for fuel oil displacement are for a
combination of diesel fuel used for diesel generators and space
heating.
As the B/C values in the above table indicate, the projects
for King Cove, Larsen Bay, and Old Harbor are feasible. The
Togiak project is marginal.
As is presented in the following more detailed summaries
for each project, it is possible to derive several different
B/C ratios for each of the projects. This is because the
calculated B/C ratio for a given project depends on which
combination of assumptions concerning waste heat recovery (from
the diesel generator), space heating (from the hydroelectric
energy in excess of the villages electrical demands) and
supplemental wind generators are utilized. For example, the
B/C ratios presented above are somewhat lower when the benefit
of space heating with excess hydroelectric energy is not
included.
D. STUDY PARTICIPANTS
DOWL Engineers, of Anchorage, Alaska, was the primary con-
tractor for the study. DOWL was assisted by two subcontractors-
-Tudor Engineering Company of San Francisco, California, and
Dryden & LaRue of Anchorage, Alaska. DOWL performed the project
management functions and provided all geological, geotechnical,
NBI-432-9526-SI I-4
and environmental information. Tudor, as principal subcontrac-
tor, supplied all hydroelectric expertise for the project and
compiled the project report. Dryden and LaRue formulated the
demand projections and supplied all diesel generating and
transmission line information.
E. ACKNOWLEDGEMENTS
The cooperation of the many federal, state, and local
agencies and local residents contacted during the course of the
study is gratefully acknowledged. This list includes, but is
not limited to, the Alaska Power Administration, the Alaska
Department of Fish and Game, the Alaska Department of Trans-
portation, the U.S. Army Corps of Engineers, the U.S. Geologi-
cal Survey, and the U.S. Fish and Wildlife Service. The assis-
tance of the Rockford Corporation and the Locher Construction
Company, a subsidiary of Anglo Energy Company, is also acknow-
ledged. We especially wish to thank the Alaska Power Authority
and their program manager for the project, Mr. Don Baxter.
NBI-432-9526-SI I-5
SECTION II
KING COVE
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume B--
Feasibility Study for King Cove Hydroelectric Project. Included
for general background information are several items from that
report: Exhibit VI-1, Photographs of the Project Area; Figure
VII-39 Projected Monthly Generation, Demand, and Usage; and
selected project drawings which include Plate I, the General
Plan, Plate III, the Penstock Plan, Profile and Details, and
Plate VI, the Powerhouse Plans and Sections. References to
figures, exhibits, and plates in the summary presented here
refer to items in Volume B, the full feasibility report for the
King Cove Hydroelectric Project.
NBI-432-9526-SKC II-1
KING COVE
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying
King Cove with electrical energy had recommended a hydro-
electric project as the best source. As a direct result of
these prior studies and recommendations, the Alaska Power
Authority authorized a feasibility study to investigate in
detail the hydropower potential in the vicinity of King Cove.
This report summarizes the activities conducted for the
feasibility study. These activities included projections of
energy needs, formulation of a hydroelectric project plan and
an alternative base case plan to meet the electrical energy
needs of King Cove, detailed analyses of economic feasibility
of each option, and preparation of an environmental assessment
of the effects of the project.
The results of the study indicate that a 575 kilowatt (kW)
hydroelectric project can be constructed at King Cove, that the
project is considerably more economical than the base case
alternative, and that the environmental effects of the project
are minor.
The estimated total construction cost of the proposed King
Cove hydroelectric project is $3,743,900 i❑ January 1982
dollars. The project could be implemented and on-line by
January 1, 1985, if a decision to proceed with the project is
made by December 1982. During an average water year, the
proposed project would be capable of supplying more than 90
percent of the electrical needs and some of the space heating
needs in the project area. The equivalent savings in diesel
fuel in the year 2001 would be about 120,000 gallons for direct
electrical demand and 23,000 gallons for space heating.
NBI-432-9526-SKC II-2
B. AREA DESCRIPTION
King Cove is located on the western end of the Alaskan
Peninsula near the beginning of the Aleutian Island chain.
With the exception of Cold Bay/Fort Randall 18 miles to the
northwest, the nearest major towns are Dillingham, King Salmon,
and Kodiak, 300 to 400 miles to the northeast. The selected
hydropower site is located on Delta Creek about five miles
north of town. The project area and the proposed site are
shown on Plate I of Appendix A.
C. POWER PLANNING
Power planning for the King Cove Project was conducted
using standards set forth by the Alaska Power Authority.
Previously recommended potential hydroelectric sites were
investigated and the project area was surveyed to evaluate
potential new sites. After detailed study, a project was
selected and then compared with a base case plan. The base
case plan consisted of a continuation of the present diesel
generation system, enlarged as necessary to meet future
growth. The base case also included the installation of waste
heat recovery and wind generation. These were both found to be
viable for installation.
Present energy demands for King Cove for direct electrical
uses, cannery use, and space heating were estimated and future
uses in these same categories were projected. The projections
were based on forecasts of increases in the number of customers
and increased usage rates. Population growth and employment,
legislation and other political influences, life style changes,
and other factors can influence future energy demands but they
were not explicitly treated.
NBI-432-9526-SKC II-3
The period of economic evaluation used was 53 years, which
starts in January 1982 and extends for the 50-year life of the
hydroelectric project after the estimated on-line date of
January 1985. The energy demands for King Cove were increased
for 20 years starting i❑ January 1982 and extending through
December 2001. The demands were then held level over the
remainder of the economic evaluation period. The cannery
demand was assumed to remain constant over the entire period.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be the
direct electrical needs of King Cove, second priority would be
for the cannery requirements, and remaining energy would be
used for space heating to as great an extent as possible.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine -
generator system to produce electric power. In the case of the
recommended King Cove Hydroelectric Project, a low weir will
act as a dam to divert water from Delta Creek through an inlet
structure and into a penstock (conveyance pipe). The penstock
will be 36 inches in diameter and it will carry the water about
5300 feet to the powerhouse, where it will be passed through
the turbine -generator system to produce electric energy. The
project will incorporate a sediment basin near the diversion
weir to trap and remove sediment from, the water before it
enters the penstock; otherwise, coarse sediment might damage
the turbine.
The powerhouse will have the capacity to produce 595 kw of
electrical power. A transmission line will be constructed to
transmit the power generated at the plant to King Cove. Access
NBI-432-9526-SKC II-4
to the powerhouse facilities will be provided by building a new
road to link up with the existing road at the King Cove
Airport. The transmission line will follow the alignment of
the new access road and the existing road from the airport to
King Cove. The general plan and features of the proposed
project are presented on Plates I through VIII of Appendix A.
Photographs of the project area are presented in Exhibits VI-1
and VI-2 at the end of Section VI and in the Environmental
Report, Appendix E.
Under the recommended plan, energy generated by the hydro-
electric plant will have to be supplemented by diesel genera-
tion. The entire existing diesel capacity will be required as
standby and backup power. The hydroelectric generation will be
adequate to meet the direct electrical needs of King Cove (not
including the cannery) during most of the year; however, from
December through March diesel will be necessary to supplement
the hydrogeneration. Diesel will also be needed at times to
meet the needs of the cannery located in King Cove.
In all, during an average water year the proposed hydro-
electric project will be capable of supplying more than 90
percent of the electrical needs of King Cove and approximately
one-third of the cannery needs.
Average annual energy production from the hydroelectric
plant will be 2.28 million kilowatt-hours (kWh) and the average
annual plant factor will be about 45 percent, which means that
the plant is expected to generate about 45 percent of the
energy that it could produce if the turbine -generator unit was
operated continuously at full capacity.
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of King Cove assumed that the existing diesel system
NBI-432-9526-SKC II-5
u
would continue to be used as the sole source of electric power,
excluding the cannery. Because of apparent economic benefits,
it was assumed that the system would incorporate waste beat
recovery that would be used for space heating. The
installation of wind generation equipment was also considered
and was found to be economically viable. The existing diesel
plant's capacity was judged to be adequate to meet peak demands
on the King Cove system throughout the period of study.
The diesel system at King Cove now uses about 70,000 gal-
lons of fuel oil per year; this rate was expected to increase
over the next 20 years to more than 128,000 gallons per year.
Waste heat recovery was expected to displace the use of 17,000
gallons of fuel oil per year by the year 2001.
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
base case costs to the net present worth of the proposed hydro-
electric project costs using specified real price escalation
and discount rates. Net present worth is the present value of
the costs that would be incurred over a comparable economic
evaluation period of 53 years for both the base case and the
hydroelectric project.
The net present worth of the total cost of the base case
plan is $9,287,000. This net present worth is $8,790,000 after
adjustment for waste heat recovery; $8,170,800 after adjustment
for wind energy; and $12,983,900 after adjustment for the can- .
nery credit. In order to compare all alternatives to the
hydroelectric project, all costs other than the cost of the
hydroelectric project and its diesel supplement were applied as
adjustments to the base case. The net present worth of the
base case, after all adjustments, including the space heating
credit associated with the hydro project, is $14,203,900.
NBI-432-9526-SKC II-6
For the proposed hydroelectric project, the present worth
of the costs is $7,053,100. A comparison of these net present
costs with the base case net present costs indicates that the
recommended hydroelectric project is considerably more
economical than the alternative base case.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For this project the calculated B/C ratio is
1.317 when the hydro project is compared to the base case only,
1.246 when the base case is adjusted for waste heat recovery,
1.158 when the wind energy credit is also considered, 1.841
when the cannery credit is added, and 2.011 when all adjust-
ments have been made.
The annual unit costs of energy production for the base
case and recommended hydroelectric alternatives were calculated
for each year of the economic analysis in order to determine
the optimum timing for development of the hydroelectric proj-
ect. This analysis indicates that the hydroelectric project is
viable for immediate development.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The environmental study results indicate that the effects
of the project will be minor due to the limited scope of the
project activities, the lack of major fish or wildlife
resources in the immediate area, and the availability of
measures to mitigate potential effects from the construction
and operation of the facilities. Minor socioeconomic benefits
will occur as a result of project construction and maintenance
and cheaper electric rates made possible by the project.
Additional environmental studies do not appear to be warranted
NBI-432-9526-SKC II-7
unless regulatory agencies or local residents express addi-
tional concerns.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that the
proposed 575 kW project is feasible and that the energy demands
of King Cove are sufficient to utilize the hydroelectric
plant's planned capacity. The proposed project is a more
economic means of meeting the area's future electric needs than
the base case diesel alternative. Environmental effects of the
proposed project are minor.
In view of these findings, it is recommended that actions
be initiated to implement the project.
NBI-432-9526-SKC II-8