HomeMy WebLinkAboutKingcove Oldharbor Hydro 4 of 13 1982SECTION III
OLD HARBOR
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume C--
Feasibility Study for Old Harbor Hydroelectric Project.
Included for general background information are several items
from that report: Exhibit VI-2, Photographs of the Project
Area; Figure VII-3, Projected Monthly Generation, Demand, and
Usage; and selected project drawings which include Plate I, the
General Plan, Plate III, the Penstock Plan, Profile, and
Details, and Plate V, the Powerhouse Plans and Sections.
References to figures, exhibits, and plates in the summary
presented here refer to items in Volume C, the full feasibility
report for the Old Harbor Hydroelectric Project.
NBI-432-9526-SOH III-1
OLD HARBOR
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying Old
Harbor with electrical energy recommended a hydroelectric
project as the best alternative. As a direct result of these
prior studies and recommendations, the Alaska Power Authority
authorized a feasibility study to investigate in detail the
hydropower potential in the vicinity of Old Harbor.
This report summarizes the activities conducted for the
feasibility study. These activities included projections of
energy needs, formulation of a hydroelectric project plan and
an alternative base case plan to meet the electrical energy
needs of Old Harbor, detailed analyses of economic feasibility,
and preparation of an environmental assessment of the effects
of the proposed hydroelectric project.
The results of the study indicate that a 340 kilowatt (kW)
hydroelectric project can be constructed at Old Harbor, that
the project is considerably more economical than the base case
alternative, and that the environmental effects of the project
are minor.
The estimated total construction cost of the proposed Old
Harbor hydroelectric project is $3,082,300 in January 1982
dollars. The project could be implemented and on-line by
January 1, 19859 if a decision to proceed with the project is
made by December 1982. During an average water year, the
proposed project would be capable of supplying more than 85
percent of the electrical needs and about it percent of the
space heating needs in the project area. The equivalent
savings in diesel fuel in the year 2001 would be more than
83,000 gallons for direct electrical demand and more than
19,000 gallons for space heating.
NBI-432-9526-SOH III-2
B. AREA DESCRIPTION
Old Harbor is a small village located on the southeast
coast of Kodiak Island, 50 miles southwest of the city of
Kodiak. The selected hydroelectric development site for Old
Harbor is located on Midway Creek across Midway Bay from the
village.
C. POWER PLANNING
Power planning for the Old Harbor Project was conducted
using standards set forth by the Alaska Power Authority.
Previously recommended potential hydroelectric sites were
investigated and the project area was surveyed to evaluate
potential new sites. After detailed study, a project was
selected and then compared with a base case plan. The base
case plan consisted of a continuation of the present diesel
generation system, enlarged as necessary to meet future
growth. Wind generation was also considered as part of the
base case. Wind generation was found to be a viable means
supplemental generation.
Present energy demands for Old Harbor for direct electrical
uses and space heating were estimated and future uses in these
categories were projected. The projections were based on
forecasts of increases in the number of customers and increased
usage rates. Population growth and employment, legislation and
other political influences, life style changes, and other
factors can influence future energy demands, but were not
explicitly treated.
The period of economic evaluation used was 53 years,
beginning in January 1982 and extending for the 50-year life of
the hydroelectric project beyond the estimated on-line date of
January 1985. The energy demands for Old Harbor were increased
NBI-432-9526-SOH III-3
for 20 years starting in January 1982 and extending through
December 2001. The demands were then held level over the
remainder of the economic evaluation period.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be for
the direct electrical needs of Old Harbor, and remaining energy
would be used for space heating to as great an extent as
possible.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine -
generator system to produce electric power. In the case of the
recommended Old Harbor Hydroelectric Project, a low weir will
act as a dam to divert water from Midway Creek through an inlet
structure and into a penstock (conveyance pipe). The penstock
will be 24 inches in diameter and will carry the water about
2200 feet to the powerhouse, where it will be passed through
the turbine -generator system to produce electric energy.
The powerhouse will have the capacity to produce 340 kw of
electrical power. A transmission line will be constructed to
transmit the power generated at the plant to Old Harbor.
Access to the powerhouse facilities will be provided by
building a new road from Midway Bay to the facilities and by
building a dock at the bay. The dock will be reached by boat
from Old Harbor. The transmission line will be constructed
from the powerhouse across the upper end of Midway Bay to Old
Harbor. The general plan and features of the proposed project
are presented on Plates I through VI of Appendix A. Photo-
graphs of the project area appear in Exhibits VI-1 through VI-4
at the end of Section VI and in the Environmental Report,
AppPridix E.
NBI-432-9526-SOH III-4
Under the recommended plan, energy generated by the hydro-
electric plant will have to be supplemented by diesel genera-
tion. The entire existing diesel capacity will be required as
standby and backup power. The hydroelectric generation will be
adequate to meet the direct electrical needs of Old Harbor
during most of the year; however, during periods from the end
of November to the first of April it will be necessary to
supplement the hydroelectric generation with diesel power.
In all, during an average water year the proposed hydro-
electric project will be capable over the project life of
supplying an average of more than 90 percent of the electrical
needs of Old Harbor and approximately 15 percent of the space
heating requirements.
Average annual energy production from the hydroelectric
plant will be 1.31 millioā¯‘ kilowatt-hours (kWh) and the average
annual plant factor will be about 44 percent, which means that
the plant is expected to generate about 44 percent of the
energy that it could produce if the turbine -generator unit was
operated continuously at full capacity.
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of Old Harbor assumed that the existing diesel system
would continue to be used as the sole source of electric
power. Because there are no significant heating loads near the
plant, it was assumed that the system would not incorporate
waste heat recovery that would be used for space heating, since
it probably would not be economical to relocate the plant
nearer a heating load. The existing diesel plant's capacity
was judged to be adequate to meet peak demands on the Old
Harbor system throughout the period of study.
NBI-432-9526-SOH III-5
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
base case costs to the net present worth of the proposed hydro-
electric project costs using specified real price escalation
and discount rates. Net present worth is the present value of
the costs that would be incurred over a comparable economic
evaluation period of 53 years for both projects. All costs
other than the cost of the hydroelectric project and diesel
supplement were considered as adjustments to the base case
cost.
The present worth of the total costs of the base case plan
is $8,182,800. If this cost is reduced by the wind energy
credit of $330,400, the net present worth is $7,852,400.
Adding the space heating credit at $1,234,600 results in a
final net present worth of $9,087,000.
For the proposed hydroelectric project, the present worth
of the costs is $6,475,000. A comparison of this net present
cost with the base case net present costs indicates that the
recommended hydroelectric project is considerably more
economical than the alternative base case.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For this project, the calculated B/C ratio is
1.264 when the hydroelectric energy used only for the direct
electrical needs of Old Harbor is compared to the base case
only and 1.213 when the wind energy credit is included.
Inclusion of the space heating credit results in a final B/C
ratio of 1.403. These B/C ratios indicate that the proposed
hydroelectricproject is highly feasible.
NBI-432-9526-SOH III-6
The unit costs for each year of operation for both the base
case and the hydroelectric alternative were calculated and
compared in order to determine the optimum timing for project
development. This analysis indicates that the project is
viable for immediate development.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The study results indicate that the adverse environmental
effects of the project will be minor due to the limited scope
of project activities, the limited nature of the fishery
resources in Midway Creek, and the availability of measures to
mitigate the potential effects from the construction and
operation of the facilities. Implementation of the project
should bring some socioeconomic benefits to Old Harbor. The
local payroll will be expanded during construction and some
employment should be provided for local residents both for
construction and maintenance of the facilities. The project
should also bring a dependable and cheaper supply of electric
power to the local residents.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that the
proposed 340 kW hydroelectric project is feasible and that the
energy demands of Old Harbor are sufficient to utilize the
hydroelectric plant's planned capacity. The proposed project
is a more economic means of meeting the area's future electric
needs than the base case diesel alternative. - Environmental
effects of the proposed project are minor.
In view of these findings, it is recommended that actions
be initiated to implement the project.
NBI-432-9526-SOH III-7