HomeMy WebLinkAboutTazimia Hydro Project Reoconn Design and Constructibility Feasibility Study 1994TAZIMINA HYDROELECI'RIC PROJECI'
RECONNAISSANCE DESIGN AND CONSTRUCTmiLITY
FEASIBILITY STUDY
Pn:pared for
ILIAMNA-NEWBALEN-NONDALTON ELECTIUC COOPERATIVE
Pn:pared by
BDR ENGINEERING, INC.
2525 ·c· street
Suite JSO
ADcborage, AK 99SOJ
September 1994
TABLE OF CONTENTS
Section
1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1
2. Proposed Project Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
Access Road . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
Stream Channel Control Sill . . . . . . . . . . . . . . . . . . . . . . . . . . 2-1
Intake Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2
Penstock . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3
Fish Screen Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3
Elevator Access Shaft . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4
Powerhouse . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-4
Switchyard and Transmission Line . . . . . . . . . . . . . . . . . . . . . . 2-5
3. Construction Cost Estimates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-1
4. Project Energy Production . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-1
5. Project Economics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-1
6. Development Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-1
APPENDIX A: SUPPORTING DATA FOR COST ESTIMATES
APPENDIX B: PRELIMINARY DESIGN CRITERIA
September 1994 i Tazimina Hydroelectric Project
SECTION 1
1. INTRODUCTION
HDR Engineering was retained by Diamna-Newhalen-Nondalton Electric Cooperative
(INNEC) to conduct an engineering review and constructibility study of the Tazimina
Hydroelectric Project. The purpose of this work was to review the project configuration
previously developed for the project, develop alternative layouts for the project, to improve
constructibility and increase the level of detail in the proposed project configuration, and
fmally, to update construction cost estimates for the project based on the selected
development plan.
The review of the project configuration previously developed for the project was completed
in June, 1994 and is discussed in a letter report to INNEC dated June 23, 1994. In this
report, the project configuration selected in the June 23, 1994 report is developed in more
detail in order to provide enough detail to allow construction cost estimates to be prepared.
The design criteria and the conceptual designs presented in this report should provide a flrm
foundation upon which the preliminary and final designs for the project can be based.
Energy output for the selected development plan is predicted, and a simple economic analysis
is also included to provide an estimate of fmt year energy costs from the project.
September 1994 1-1 Tazimina Hydroelectric Project
C'll
z
0
F= u w
tn
2. PROPOSED PROJECT DESCRIPTION
GENERAL
In the past, there have been many conceptual designs considered for the Tazimina River
Hydroelectric Project, each varying in magnitude and complexity. A conclusion derived
from the previous studies is that the configuration of the project must be relatively simple
to construct using conventional equipment and construction techniques, and that project
operation be practical with a minimum of complexity. The project description described in
this section has been developed based on these conclusions.
Main features of the proposed project include an access road, stream channel control sill,
gated intake structure, buried steel penstock, fish screen structure, elevator access shaft,
semi-underground powerhouse, switchyard and underground transmission line. Plan and
section drawings of these features are shown at the end of this section.
ACCESS ROAD
Access to the project site will be via a new 6. 7 mile gravel surfaced road. The access road
will extend from the Newhalen-Nondalton Road, around the north end of Alexcy Lake and
on to the project site along the left bank of the Tazimina River looking downstream. The
road will be a limited access road of single lane construction, 16' wide with turnouts
constructed at strategic locations. Drainage culverts will be installed along the 6. 7 mile
length to safely pass runoff where the road crosses natural drainage courses. The project's
transmission cable and a communications (telephone) cable will be buried along the edge of
the road, in the road prism. The access road grade will be raised slightly above the
surrounding area for drainage and to help it blow clear of snow in winter.
Road construction material will consist of coarse pit run material for road ballast, where
needed, and smaller (2-inch minus) rock for use as the top course. Geotextile fabric may
be required in some areas to add additional stability to the road base. Cost of construction
of this road will depend on the location and frequency of material borrow sites along the
route. Frequent borrow sites will reduce haul times. Borrow sites in the road right-of-way
will reduce costs for imported materials. For this study, we are assuming about 1/2 of the
material will come from the right-of-way and the other half from new or existing borrow
pits.
STREAM CHANNEL CONTROL Sll..L
A linear concrete sill will be constructed across the right side of the river, opposite the intake
structure. Purpose of the sill will be to prevent degradation of the streambed, and to help
divert streamflow to the intake during periods of low flow. The sill will be about 80 feet
in length and be constructed of pre-cast concrete blocks. The blocks will be trapezoidal in
section to provide stability against flowing water. Block dimensions will be 2' high by 4'
long, with a 1' top width and 3' bottom width. The blocks will be fastened to the rock
Sf!ptember 1994 2-1 Tazimina Hydroelectric Project
streambed with steel anchors. They will be installed during the low flow period, and some
temporary sandbagging may be required during installation. Streambed elevation at the sill
is about El. 574.5. The top of the sill will be visible above the water at low flows, but it
will be totally submerged during spring and summer at higher flow periods.
In addition to the sill, a rock trap will be excavated in the stream channel between the
channel control sill and intake to help guide stream bedload material downstream and away
from the intake.
INTAKE STRUCTURE
A key function of the intake is to withdraw 110 cfs from the river, the hydraulic capacity
of the units, during the low flow period between January and April. The problem of
diverting 110 cfs to the intake presents a design challenge because no dam will be
constructed to aid in diverting flow, and the 170 foot wide river channel makes it difficult
to attract a large percentage of the streamflow to the intake during low flow periods.
Compounding the problem is the potential of ice blocking the intake during the low flow
period.
The proposed design addresses these challenges. The intake structure will be located on the
left bank approximately 300 feet upstream of the top of the falls. The axis of the channel
control sill will be located about 50 feet upstream of the intake on the opposite bank. Future
model studies of the sill, rock trap and intake structure will help to refme the proposed plan,
location, dimensions and elevations of these features.
Excavation for intake construction will be completed in "the dry". The intake is setback into
the left bank far enough to allow the natural rock to form a cofferdam. On completion of
the intake and downstream facilities, the rock cofferdam will be excavated and connection
to the river will be made.
The concrete intake structure will be constructed in sound rock and will include a trashrack,
intake gate and sluice gate. A concrete headwall will be constructed in the same plane as
the trashrack structure to provide protection from floating debris and to provide a cutoff to
possible seepage along the penstock trench. The trashrack will be designed for a maximum
of 1.5 feet per second approach velocity. If the capacity of the power plant is eventually
doubled in size, the increased flow will result in an approach velocity of 3 fps without
increasing the trashrack size. This is the recommended maximum velocity for manual
cleaning. The trashrack will be set 2 feet below minimum water surface elevation to prevent
ice formation and clogging of the rack. Sensors will be installed to detect differential
pressures across the trashrack. A 6-foot square electrically operated vertical slide gate will
be installed in the intake. Penstock invert elevation at the intake is preliminarily set at El.
568, though it may need to be deeper pending results of hydraulic model tests. The intake
sill will be elevated above the trench to keep bedload in the river and out of the intake.
Minimum water surface elevation in the intake will be about El. 575.
September 1994 2-2 Tazimina Hydroelectric Project
A gated intake to an 18-inch sluice pipe will be installed in the intake. The sluice pipe will
help keep the front of the intake clear of bedload deposits. The sluice pipe invert will be set
about 2 feet below the penstock intake invert.
PENSTOCK
From the intake, flow to the turbines will be conveyed via a 60" buried welded steel
penstock. The penstock diameter is sized to convey 220 cfs, or double the proposed initial
hydraulic capacity of the power plant. Although the initial design plant flow is only 110 cfs,
future plant design flow of up to 220 cfs can be accommodated with this design without field
construction by simply installing a 60-inch pipe now instead of a 48-inch pipe. The cost of
this larger pipe installation is minimal, consisting of material cost only to go from 48-inch
to 60-inch pipe. The penstock will be divided into two sections, separated by a fish screen
structure described below. The upper section of penstock is 120 feet long and the lower
section is 310 feet long. Constructing the penstock will require deep open-cut excavation
of the native rock. The cut will generally range between 30 and 40 feet deep, and will be
360 feet long. Blasting will be required to loosen material before excavating. Construction
of the trench will be in two 20-foot lifts after drilling and shooting of the rock. Rock
between the trench and river will remain intact to a minimum elevation of El. 585, or about
10 to 15 feet above the streambed. Following excavation, the pipe and fish screen structure
will be installed and backfilled. The trench will be backfilled sufficiently to form a sloping
bench along the left bank of the river. Snowmelt and runoff will drain toward the river from
the sloping bench.
The penstock section downstream of the fish screen structure will also be 60" diameter
welded steel pipe. The initial180 feet of the lower penstock section will experience internal
pressures of less than 10 psi. The downstream 130 feet of the lower section will be installed
in a rock notch excavated in the cliff downstream and to the left of Tazimina Falls. A rough
19-foot wide by 1 0-foot deep slot will be blasted from the top of the cliff to the powerhouse.
Blasting will be accomplished by the drill and shoot technique with some scaling probably
required. Blasted rock will not be executed, but instead will be left as part of the talus file
at the base of the cliff. The slot will provide initial access for excavating the powerhouse
cavern. The 60" diameter penstock, a 96" diameter permanent elevator shaft, 30" vent shaft,.
and two 12" diameter power and communication conduits will be installed within the slot and
encased with concrete from the top of the cliff to the powerhouse to protect them from
winter icing conditions.
FISH SCREEN STRUCTURE
At this time it is uncertain whether or not a fish screen structure will be required for the
project. If a fish screen structure is eventually required, it will need to be designed to
reduce the velocity of penstock flow to 0.5 fps approach velocity at the screen sutface. The
proposed fish screen structure is designed to provide gradual deceleration of flow to the
screens and gradual flow acceleration downstream of the screens. The total screen size will
be 8 feet high by 30 feet wide, consisting of a series of ten 3-foot wide screens set side by
side. Screens will be fully submerged to help prevent plugging from floating ice. The
September 1994 2-3 Tazimina Hydroelectric Project
screen structure must be designed with the flexibility to be able to revise its design in the
future depending on final screening requirements.
The structure will have a concrete roof deck, with removable panels to provide access for
cleaning the screens, cleaning out sediments that may have deposited on the floor of the
structure, or to petform other maintenance on the structure. A hoist and frame will be
constructed above the screens to pull them for maintenance.
At the downstream end of the screens, a ramp will be constructed in the bottom of the
structure leading to a fish bypass pipe. The bypass pipe will be routed back to the river to
keep fish from becoming trapped in the ftsh screen structure.
A second sluice gate and sluice pipe will be installed in the fish screen structure. The sluice
pipe will connect with the sluice pipe from the intake, and all sediment will be carried in a
single 18-inch pipe to a discharge point on the face of the cliff near the powerhouse. Slope
on all sluice pipes will be about 2 to 3%, which should provide sufficient sweeping velocities
for all sizes of rock that could enter the sluice pipe system.
ELEVATOR ACCESS SHAFT
Permanent access to the powerhouse will be provided via an enclosed elevator shaft installed
in the rock notch previously described. The shaft will be formed by 96" diameter steel cans
encased in reinforced concrete. The shaft will be inclined at an approximate slope of 1H:2V
and extend from El. 590 at the sutface to the powerhouse at El. 480. At the top, a small
concrete enclosed elevator landing will be constructed where passengers and equipment can
be loaded and unloaded. Design lifting capacity of the elevator will be determined during
final design.
POWERHOUSE
The powerhouse will be a semi-underground structure, excavated into the cliff at the left of
the falls. The powerhouse will be 40 by 50 feet in plan view and 18 feet high. The
generator floor will be set at El 484.5; about 15 feet above the streambed. Construction
above the streambed offers significant advantages over the alternative of construction at or
below streambed, including less dewatering problems and better operation under heavy
winter icing conditions.
The powerhouse will contain two 350-kW horizontal Francis turbines, generators, switchgear
and auxiliary equipment. Design flow and head on each unit will be 55 cfs and 85 feet,
respectively. A single 6-foot wide draft tube pit serving both units would be excavated
below the cavern floor. Tailwater level would be controlled by a concrete control sill
constructed above the normal high water level of the river. A concrete floor will be
constructed within the cavern and over the 6-foot wide draft tube pit and tailrace channel.
Cavern walls will be shotcrete lined and rock bolted if needed. The exterior wall facing the
river will be cast concrete and inclined at the same angle as the elevator.
September 1994 2-4 Tazimina Hydroelectric Project
The powerhouse will be sized and configured to accommodate doubling the plant capacity,
to 1400 kW, in the future. New turbines and generators would replace the units initially
installed.
SWITCHYARD AND TRANSMISSION LINE
The transmission line will be 6. 7 miles long and operated at 7200 volts. The line will be
buried and follow the new access road alignment. The new transmission line will be buried
25 kV 260 mil EPR insulated cable with concentric neutral, to match the cable used
throughout the INNEC system. A transformer at the powerhouse end would be necessary
to step up the 480V generation voltage to 7200V. Tap changers would be provided to allow
some adjustment in transmission voltage to best match the system at the tie-in point. Other
types of insulation systems could also be used, including cable-in-conduit. Final decisions
on cable type will be made during final design. A multi-pair communications cable will also
be installed along with the transmission line to provide voice and control circuits for the
plant.
September 1994 2-5 Tazimina Hydroelectric Project
l
I
i
l . I
I
TAZIMINA HYDROELECTRIC PROJECT
Project Number f
-------------
OVERALL PROJECT PLAN
A
c
D
TAZIMINA RIVER
40 F"EET
I
TAZIMINA
HYDROELECTRIC PROJECT
PRELIMINARY SITE PLAN /r------------l
HDR Engineering, Inc.
SCALE: 1"•20'-0"
·~DESIGNED ----
DRAWN ___ _
CHK:
APPROVED BY:
DWG. NO
c
H
~
~ >
UJ
...)
IV
~00
5Ba
se;,o
I
0
---r--
\ 4~
(!(..,584
HEADWP-..LL
EL 5(.:.7
---'", ., ,;--···
' "
I
I t:_ PtN $1 oc.t;:
I zo
1_..-/:
I
I I
/ ~-,
"
INTAKE:" HEADWALL
ORIGINAL
"' "
" '\.
s'x. tS'
I
40
<
6ROUND
' '---
Tf!!AS ~ RA C 1'.
___s_
-----
I
bO
TA~A H~DROELECTRIC;;;JECT·-, .. ~Number ·--
lo ... ?>j,?fN
INTAKE HEADWALL IP•oiKtM .......
------~
.• ,':
......:, .... ·. ' ' H"
.. ~.. .
<. 580 ~\ ' <:) ~\ ' ~ ... , " I ~ \ ' v \ ' tJJ ~ bo'' ~N5TDC~ '-
..J -y ··-----
lu EL.S~~-\.:: I~ /L---tf IB '' s Lu, c:.e
I I tL 5bS"
SbO
I I
0 2o 40 bo
A·A
I Protect Title TA:zJMI..tA HYDROELECTRIC PROJECT
I Protect Numbtw
~-T~
SECTION A-A I Protect Mana.-
---
I
0
-----
_,,~L FW oF Ftt..t...
-~··~ ...... ·-·-
20
B·B
<f. 18" 5<-UIC£
I
4o
I
6o
I Proleet Tldtt TAZIIWNA HYDROELECTRIC PROJECT
Tldtt
SECT10N B-B
v
----------
I
8o
I Proleet--Nu-mbeo ______ _
I o ... ') / 'i /l'f
r Proleet M•n•e-
--------
FILL -·-
£L5fo7
5be>.
0
-___ .J
I
I
I..-;
I 1 I
~G~J
lEV"/~'
C-c_
.'----
£(.. 5b2.5
8o
~Project Number
SECTION c-c
---
II' ,, <f ~o PE.NSTo c.lc ---··
I
0
----/-· ORI61NAL-uRVUNO
+j
I I
; 'J" i t 1 ) L>-./ --·~---.---·
I
2.o
·-<t_ 18'' SLUIC.E R<oM. INiA.~
6o
D-D
r-P_rofec_t T-ltle------~------------
@'1 ,--TAZ~A HYDROELECTRIC PROJECT
SECTION D-D
Bo
---
I
0
---r----·-
1 -----
\
EL SGo3 \I 6
\~_ __
zo
E-E
" -----"
I
4o
~
\
\
\ ? ..._ ---
I
{:,a
TAZ~A HYDROELECTRIC PROJECT
lo ... '"'( __ 117 .
D P' r +
SECllON E-E I Project Meneger
SbO
--
I
0
------
\
I
Zo
F-F
-~ . --
I
4o
ORI~JNAL
-
/8" SLVfCE
I
60
TAZIMINA HYDROELECTRIC PROJECT
SEC110N F-F
\
\
\
\
\ _....;"/,__
\ -
·"----
I
&J
I Project Number
--_1 :_-OfCIGINAL.. GR.OUNO --·----;-ICf> a:: r ,~.. 1.. --/ -1!.. -------.. ---~
~ ,,
' " (
I \
4~ I \
t
I \
~~ ~o" f'ENSroCJ<.. .~~ \
\ ~· /\II \ ii;
..J \ \U
\
l s, s l I.) I <.C. \
\
\ -~ ~ 5W -~vd \.
I I ' r
0 z..o 40 6o Bo
SECTJON Q-Q
I Protect Tide
1-il{ ~--TAZMiA HYDROELECTRIC PROJECT
i:!LeVAlOR
j__
coNDUIT
H-t-i
5Ec-nor,l TH~OU6H NcrrcH
I Prot-ct Title TAZ~A HYDROELECTRIC PROJEC~-I Pr<>t-ct Nu...a-
ID•ta , (~ /1) /1'1
SECTION H-H fProiKfM-.....
,...-
I
0
n
I
I
..___j
/
II
' 7
I'
'
I
I
I
! I
/
J . k TAILetJ...c.E (BE Low)
\ I
........ _/
/
/
/
/
/
/
/
/
/
/
/
/ /
/ //
~/ -'<
/
/
/
I
/
~-ill. ':: TAZMNA HYDROELECTRIC PRO.ECT
. .. I POWERHOUSE PLAN
s~o
0 Z.o
_:-::: O~IG.tl-.lA'-6_,2Qu~...J!) --·-------------~····~ --------------------~~t---.--~·-------------------------------------
/--
//
/
//
I (,
( C:L.~B4 Er_ . .S95 f ---------------~==-----,-.7.~.~ .. -.·-----------~~========~
·'.·"'~:: · Flt..l _.-+ D
i
\__ 5, '" 0' Of'el..l&t-J e:. w I '"f12ASH (2J\QC..
I
bo
I
80 (00
"o" 4> PENSTOC.IC.
/2.0
I
!4o
c::,
I
ll::JO
I
lfb
I
2oo
E:L. Sf,Z
I
22o
I I
I . I i ~ • I ~ I ~ '...tl ,..t.
lOOO
.sea
,,, .
ll· !:> . ...
~ ~.
,,
bO
Cot-JCRETt ENCASEMENT
O(?t" la-.&A:'-6f:?..otJN[:) ---a..\
( Ff.i..L..L.S ScDt oF NoTC.-t) \
520
soo
E.t, 497
4 /l.UNNER EL.486.o
EL. 464,0
480
I
0
\
PoWER HO\J~E
''f'"''f'"''t __ 2 ___ _,
2-350 kW
f ' I I I
I ' I I
\ L--_l •---...!
'---( TAI:AA-: ~H:N:£=
z.o
I
40
y---ORIGINAL c:E,ROlJND
\ ~ ftNS.TOCK
\
\
I
too
\
\
\
'\.
""
Ac.c.Ess
~ !
I
I I i
f j I
000
540
52D
50cJ
4Bo
' " .
I
0
H
EL 582
I
2.D
ELEVATOR SHAFr
El.E VA TOR
...._,
~\\
/-;1,
..::._,
I
40
-:,\ ' \ '
\
EltVATOR SHAFT SEC.iiON
ORIGINAL, 6KolJND
ACC£SSWA.'{
I
bO
8
c
D
E
G
H
r----~
I
I
I
I
I
I
I
I
I
Sl.C
120 KW TYPE •GP·
LOAD CONTROL
GOVERNOR UNIT
2
DISCONNECT
SYI110t
1SI<V
100A
I
MAIN POWER
TRANSFORMER
7.2KV-480V
1000 KVA
L_
------~~----~ I) 200A
120KW LOAD OUt.IP TANK
(COUlD BE LOCATED
IN N£WHAlEN)
I
IL CONTROL SIGNAL
--TO GO'vERNOR
REGULATOR/
EXOlER
3
-l
4
7.'JJ<V BURIED TRANSMISSION
UNE -6. 7 YII.ES TO NE'IIHAlEN/
NONDALTON T-UNE
I AUXIUARY 301<W GENERA TOR
' 7 9
L------------------------------------------, r '
\ EXOTER
10
NEW 151<'1 FUSED
DISCONNECT CABINET
I
I
I
11
NEW ..
---------------------------
1Z
•j• EXIS11HG .. §
~
!
I
I
J ----...-
z
~
> ~ ,..;
13 14
NO. DATE REVISION
~
~f-1'0'110 'IIWISF'OAMDt
-3E-PO'I'EM'M&.~
i CUI!MMT 1'ltNfSF'OIIIol
1 ClMIIOfT 'IIINSF'ORWOt.
8tJSHIIC T'IP£
l GDolltA TCR Fll.J) lliNI:lHi
A OO.TA
K 1M
~ OPEN 1M
+ 1M IQIIT
~n-f UCH'IMNC N!II!S1at
-{[])-FUSE
EJ II£SJS'Dt
ICJICA'IIIG IJQfT {W • ~
15 16
BY CHK APPROV.
t:4 DIOC)[
* CONTACT. ~y a.osm
-if-CN>AaltiR
_--:.,_ SPUCE _........_
SW1'04
-~ II\I5IED s-ltH
~ Sti10t (Y -'tG. NE'IIllt)
0 ltCMCA'IINC IIEmt
·6) GDolltAltiR
G P<MEJt CIRCUT ~
LOW IICilfAGE
liiEDIUio1l IQ.TAGE:
IN1!J1I..OCX
~
I r--------------)¥......._,..-BREAKER
I SHUT-DOWN : r-------------86E ---SOLENOID
l&
480V, ~.
----------------r-------------
' r----------
I I ,..-----------./ I I 1 I
1 I 1 I
I I 1 I
I I 1 I
I I 1 I
I I 1 I
I I 1 I
I I 1 I
I I 1 I
I I 1 I
I I 1 I
I I I I
I I r-------------.J I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I I I
I
I
I
I
---------\
------------i I I -----------1-.J ' I ------------------~---r---------1 I I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
G£NERATOR 11 r----.----t
~W I I I o.~.F. 0
1 -e-1 -e' F'.L. AMPS ~2
-------38 -49G -12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I I I
1 I I l ____ j __________ j
(REL..4Y5/CONTROI..S Slt.IILAR TO UNIT fl)
I
1/0
INTAKE
REMOTE 1/0 BASE
...... ______ ........ __ .. ------
EXIS]NG NEWHALEN QIESf1 POWER PUNT
CONJ'R(J. SCHEMADC
500
FEET
1/0
(IF NEEDED)
1/0
PI.AHT
OPERATOR
INTERFACE
TEIMNAL
POWERHOUSE
(t.IAS1ER)
TEl.£PHONE
CABliNG
APPROX. 20.7
MILES
1/0
OPERATOR
INTERF"ACE
l£RWINAL
DIESEL
GENERA nNe
PI.JINT
IN N£WH~
12 CJiiERSIIED SWI10f
'" UllllOISI'IED s-lOt
%5 S"nnCC44IttSM CHEOc DE't1CE
25A JAJRJMliC $YNCHIIOHilllt
rr UIICEJMli.TAGE: II£U. y
32 ~ POilti£R II£U.Y
3-J MASlUt SEQIUENC:E DE't1CE
lll II£AIIING 'l!lllflfltAl\111£ ll£u. 't
a ~ UONI'ICIIING DEw:E
40 F1ELO RliLAY
41 F1ELO CIRCUIT IIR£AIIOt
u IUIIIUoM. 'lltANSI"t:Jt 011' SELEC'Itllt !X';II(Z
.S IIEWJISI:...f~NASE Qlt --~ CUIW:NT RElAY
ofl 'IDIPI:ItA1UIIt: RliLAY (G • ClOVATOR. T • lit~
511N AC 'lilliE OV£JICIJRROIT REI.AT (1M • 'lltMSf'QIMER M£U'IIUI.)
51Y AC liiC OIOICWI1IEHT MLio T (V • 'tG. TAG£ IIESTIIAIN1)
52 AC CIIIIC\AT BN:NC£11
" ~TAGE: IIQ.A'I'
""/Z7 10CI!l $TAltiR 01101.11) 11£\..\'1'
10 'tG.fAG£ IUUHCE
u PIII$$UIIIC s-ltH
W F1ELO GR01.11D PROltClM III:LAT
71 C.. 1£1111. SW10t LOW
81 fiM'.IMNCT. IIQ.AY (0/11 -CM!t/UNO(lt)
Ill L..Ot'QtG-QIT IIIELAY (I • EMPGOIC:'I', N • NOAUAI.)
17 OIF'l'UI!N1Ltl. PR01EClM 11£\.1. T (G • GDolltA TCR.
T • 1R.INSIIallotEJ)
" AMIIE'IEit AS ~-lOt
AID Nil' TRAH!iDI.Jeat
r I"'I£C::UUiNCT w:mt
"' Pa.a FAC'ItiR WETER
sc S'fNCHIOIISiol attac
SLC SHUNT LOAD CONlRQJ.Dt
Sl S1MC'H $C(lll£ Qlt Sll.ECltiR $YIIltH
'I YCLNETER
VM YCLT MftllrS ltEI.ClM WID
VM'ID VM 11tAHSilUCDt
VS YCLNETER SWiltH
VII) YCLT 'I'RAHSDUCEit
w •1TWETER
.. •JtHC:Ut loiE1Eif
IW1D ..... ,. 'I'RAHSDUCEit
I.N.N. ELECTRIC COOPERA 11VE
TAZIMINA
HYDROELECTRIC PROJECT
PRELIMINARY
ELECTRICAL
ONE LINE DIAGRAM
HDR Engineering, Inc.
OA'IE: 8-4-94
OWG. NO.
01<: J. SNYDER SK-EE-1
F1l(: 6012!10t.DW:P PlOT SCAlE! 1•1 0.\lE: 08/08/94 nWE: 2:: 10pm PAnt H: \TAZIWINA\
G
SECTION3
3. CONSTRUCTION COST ESTIMATE
An estimate of probable construction cost was prepared for the project configuration
described in Section 2. The estimated Direct Construction Cost of the project is $6,887,000.
Total Project Development Cost, including engineering services, owner costs, contingencies
and escalation is estimated to be $10,359,000.
The Direct Construction Cost is the cost a reasonable contractor would be expected to bid
for the work if it were bid in 1995. Construction quantities were estimated for the major
project features based on preliminary sketches. Unit and lump sum prices were estimated
based on experience data and contractor quotes for the turbine/generator equipment and
penstock trench excavation. The estimates reflect local conditions, remoteness of the project
site and Alaska wage rates. Some costs were also included for related work, such as heating
equipment changes at the school which are necessary because of the new project. Cost for
land use has been included as an annual expense in the economic analysis.
Turbine and generator quotes were obtained from three potential vendors; Bouvier
Hydropower, Inc., Sulzer, and Hydro West Group, Inc. Quotations ranged from $887,000
to $1,200,000 for two 350-kW horizontal Francis turbines, generators, switchgear and
auxiliary equipment. Copies of their quotations are provided in Appendix A.
A preliminary estimate of penstock trench excavation costs was obtained from Wilder
Construction Company in Anchorage. A copy of their estimate is also included in Appendix
A. These costs were adjusted based on recent construction bid prices in the area.
Unit prices for reinforced concrete are based on based on recent experience data in Alaska.
Actual contractor bid prices are expected to vary considerably depending on the bidders'
assumptions and strategy in formulating its bid. Access road construction costs were based
on having to import about 50% of the material for the road bed from 4 or 5 borrow sits near
the road alignment, and obtaining the rest from cut slopes within the right-of-way.
Contingencies were added to direct construction costs in varying percentages to account for
a degree of uncertainty in the fmal cost of each major project feature. Based on the level
of study conducted for this report, a contingency of 15% was added to the turbine/generator
and other equipment, and 20% to all other work. This results in a contingency fund for this
project of about $1,270,000.
Costs for engineering, geotechnical investigations, topographic surveying, hydraulic
modelling, permitting and construction management are estimated to total $1,512,00. This
aggregate amount is based on HDR's experience costs with hydroelectric project design and
construction management services, as well as estimates from frrrns specializing in
geotechnical, surveying and hydraulic modelling services. When performing construction
in remote areas, the expense of performing detailed engineering design and effective
construction management normally pays back big dividends in the form of reduced
September 1994 3-1 Tazimina Hydroelectric Project
construction bids and fewer changes in the field. We have found this approach to be key to
the success of projects we have completed in the past.
September 1994 3-2 Tazimina Hydroelectric Project
TABLE 3-1
TAZIMINARIVER HYDROELECfRIC PROJECT
PRELIMINARY ESTIMATE OF PROBABLE CONSTRUCTION COST
FERC
AlxNo Description Quantity Unit
330 LAND AND LAND RIGHTS
.1 Land RighWEasements (handled as annual expense) 1 LS
Total -Alx No. 330-Land and Land Ri11hts
331 STRUCTURES AND IMPROVEMENTS
.1 ACCESS ROAD
.1 Construct Acce>s Road 6.7 MI
.2 Gravel Purchases from Bristol Bay Native Corp. 15000 CY
.2 POWERHOUSE
.1 Rock Face Excavation 660 CY
.2 Powerhouse Cavern Excavation 1260 CY
.3 Tailrace Excavation 90 CY
.4 Reinf<rced Concrete in Notch 550 CY
.5 Generator Floor Concrete 150 CY
.6 Tailwater Control Wier 2 CY
.7 Rock Bolts 500 LF
.8 Shotaete and Mesh 60 CY
9 Miscellaneous Metals 15,(XX) LB
.3 SITE WORK
.1 Parking-Grading'Surfucing 1 LS
.2 Storage Shed 1 LS
.3 Fencing'Safety Barriers 1 LS
Subtotal
. Mobilization (10%)
Total -Alx No. 331 -Stuctures and Imorovements
332 RESERVOIRS, DAMS, AND WATERWAYS
.1 CHANNEL CON1ROL SILL
.1 Streambed Preparatioo 1 LS
.2 Pre-cast Concrete Blocks (2x2x4) 20 EA
.3 Block Transport and Installation 1 LS
.4 Excavatbn of Rock Trap 30 CY
.2 INTAKE STRUCTURE
.1 Dewatering'Care ofWater 1 LS
.2 Rock Excavation 300 CY
.3 Backfill 80 CY
.4 Reinf<rced Concrete 40 CY
.5 Trashrack 1 LS
.6 66" Intake Gate and Electric Operator 1 EA
.7 24" Sluice Gate and Electric Operator 1 EA
.8 Water Level Instrumentation 1 LS
.9 Miscellaneous Metals (Grating, Handrails, etc.) 3000 LBS
.10 Electrical Conduit and Wiring 1 LS
.3 FISH SCREEN STRUCI1JRE
.1 Dewatering'Care of Water 1 LS
.2 Rock Excavation 2400 CY
.3 Backfill 500 CY
.4 Reinf<rced Concrete 260 CY
.5 Fish Screens 240 SF
.6 Miscellaneous Metals 10000 LBS
p:\hyd\tazimina\feasib\cost -estwk3
16-Sep-94
Unit Amount
Price ($)
$0 $0
$0
$150,(XX) $1,005,(XX)
$3 $45,000
$125 $82,500
$150 $189,000
$100 $9,(XX)
$1,(XX) S550,(XX)
$800 $120,(XX)
$800 $1,600
$25 $12,500
$700 $42,(XX)
$7 $105,000
$15,(XX) $15,000
$25,000 $2S,(XX)
S15,(XX) $15,(XX)
$221,660
$2438.260
$20,(XX) $20,(XX)
$500 $10,(XX)
$25,000 $25,000
$200 $6,(XX)
$5,000 $5,000
$40 $12,000
$12 $960
$1,000 $40,000
$14,000 $14,000
$35,(XX) $35,(XX)
$18,000 $18,000
$4,000 $4,000
$7 $21,000
$15,000 $15,(XX)
$5,000 $5,000
$40 $96,000
$12 $6,000
$1,000 $260,000
$250 $60,000
$7 $70,000
TABLE 3-1
TAZIMINA RIVER HYDROFLECTRIC PROJECf
PRELIMINARY ESTIMATE OF PROBABLE CONSTRUCTION COST
PERC
Ace No Descriotion buantitv Unit
.7 24" Sluice Gate and Electric Operator 1 EA
.4 WA1ER CONVEYANCE
.1 Rode Excavation ( excl. intake, screen structure, ootch) 8600 CY
2 (IJ' Steel Penstock 430 LF
.3 30" Steel Penstock 20 LF
.4 18" Steel Sluice Pipe 405 1F
.5 Pipe Bedding 115 CY
.6 Select BackfiH 660 CY
.7 Native Backfill 5200 CY
.8 Pipe Installation 1 LS
Mobilization (10%)
Total -Ace No. 332 -Reservoi" Dams & Waterwavs
333 TURBINES AND GENERATORS (incl. governor & excite )
.1 350kW Hc:rimntal Francis Turbines 2 EA
2 · 400 kV A Synclirooous Generators 2 EA
.3 Goveroor and Process Control Cabinets 2 EA
.4 Flywheels 2 EA
.5 Install Units and B:juipment 1 LS
.6 30" Isolation Valves 2 EA
Total -Ace No. 333 -Turbines and Generators
334 ACCESSORY ELECTRICAL EQUIPMENT
.1 Switchgear 1 LS
2 Statbn Service 1 LS
3 Control Panel 1 LS
.4 Conduit/Wire/Cables 1 LS
.5 Lighting 1 LS
.6 Grounding 1 LS
.7 30-kW Emergency Generator and Fuel Tank 1 LS
.8 Battery Bank and Olarger 1 LS
.9 Invener and Transfer Switch 1 LS
.10 Power and O:lmmunication Lines to Intake 1 LS
.11 New Heating Equipment at School 1 LS
Total -Ace No. 334 -Ace. Electrical Equipment
335 MffiCELLANEOUSMECHANICALEQUIPMENT
.1 Ventilation Equipment and Shaft 1 LS
.2 Unit Heaters 1 LS
.3 Sump Pump 1 LS
.4 Portable 8-Ton Hoist 1 LS
.5 Elevator, Rails and Shaft Liner 1 LS
.6 Project Truck: and Backhoe 1 LS
Total -A£c No. 335-Misc. Mechanical E.Quioment
352 STRUCfURES AND IMPROVEMENTS (T-Iine)
(TRANSMISSION FACILITY)
.1 Switchyard E.xcavaticn and Grading 30 CY
.2 Switchyard Fill 30 CY
.3 Equipment Foundations and Oil Spill Containment 1 LS
.4 Grounding 1 LS
p:\byd\tazimina\feasib\cost -est.wk:3
16-Sep-94
Unit Amount
Price ($)
$18,000 $18,000
$40 $344,000
$275 $118,250
$150 $3,000
$80 $32,400
$30 $3,450
$20 $13,200
$12 $62,400
$25,000 $25,000
$134,266
$1476926
$298,000 $596,000
$51,000 $102,000
$46,500 $93,000
$15,000 . $30,000
$75,000 $75,000
$25,000 $50,000
$946000
$225,000 $225,000
$70,000 $70,000
$150,000 $150,000
$150,000 $150,000
$60,000 $60,000
$10,000 $10,000
$25,000 $25,000
$15,000 $15,000
$20,000 $20,000
$10,000 $10,000
$50,000 $50,000
$785000
$90,000 $90,000
$5,000 $5,000
$4,000 $4,000
$12,000 $12,000
$180,000 $180,000
$90,000 $90,000
$381000
$20 $600
$20 $600
$8,000 $8,000
$5,000 $5,000
PERC
Are No
353
356
331
332
333
334
335
352
353
356
.5
.6
.1
2
.1
2
.3
.4
.5
.6
TABLE 3-1
TAZIMINARIVER HYDROELECIRIC PROJECT
PRELIMINARY ESTIMA1E OF PROBABLE CONSfRUCTION COST
Description Quantity Unit
FencingfGate 1 LS
Lighting 1 LS
Mobilization (10%)
Total -Are No. 352 -Structures & Imrrovements
SWITCHY ARD EQUIPMENT & STRUCTURES
Main Transfooner 480/7200 V, 850 KV A 1 LS
Disconnect Switch 1 LS
Total -Are No. 353 -Suh!ltation EQuipment & Structures
FIXTIJRES, CONDUCTORS & DEVICES
Transmission Line, 7 2 k V, Buried Construction 6.7 !MILES
Transmission Line Cable Material, 3 conductor 35376 FT
Interconnection 1 LS
Changes to INNEC System 1 LS
Telepoone Line to Newbalen, Cable 10.7 MI
Telepoone Line to Newhalen, imtall 4 miles 4 MI
Total -Ace No. 356 -Fixtures Conductors & Devices .. (Total mobiliZation cost mcluded m above -$357,946)
SUMMARY
SfRUCTURES AND IMPROVEMENTS
RESERVOIRS, DAMS, AND WATERWAYS
TURBINES AND GENERATORS (incl. governor & exciter)
ACCESSORY ELECIRICAL EQUIPMENT
MmC~OUSME~CALEQUIPMENT
SfRUCTURES AND IMPROVEMENTS (T -line)
SWITCHY ARD EQUIPMENT & STRUCTURES
FIXTIJRES, CONDUCTORS & DEVICES
Total Direct Coostruction Costs (rouooed)
Design Engineering@ 9%
Geotechnical, Borings & Test Pits
Topographic Surveying
Hydraulic Modelling
PERC Approval and Other Permits
Construction Mgmt. @ 7%
Subtotal (rounded)
Contingency (15% on turbine/generator & other equipment)
Contingency (20% on remaining accounts)
Total Project Construction Cost (1994)
Escalation to 1995 (3%)
Total Project Comtruction Cost (1995)
INDIRECT COSTS:
INNEC Administrative Costs
INNEC Legal Costs
p:\hyd\tazimina\feasib\cost-estwk3
19-Sep-94
Unit
Price
$3,(XX)
$3,(XX)
$40,(XX)
$10,(XX)
$60,000
$6
$10,(XX)
$50,(XX)
$5,000
$15,000
Amount
($)
$3,(XX)
$3,(XX)
$2,020
$22,220
$40,(XX)
$10,(XX)
$50 (XX)
$402,(XX)
$212,256
$10,(XX)
$50,(XX)
$53,500
$60,(XX)
$7ffl756
2,438,260
1,476,926
946,(XX)
785,(XX)
381,000
22,220
50,000
787,756
$6,887 ,(XX)
619,830
160,(XX)
100,(XX)
75,(XX)
75,000
482,090
$8,399,(XX)
316,800
955,032
$9,670,832
290,125
$9,960,957
Financing Costs and Underwriting Fees
Interest During Constructioo (9 mos. on 1/2 balance over $5M@ 6.25%, grant spent first)
lOO,(XX)
100,(XX)
75,(XX)
122,718
Estimated Total Project Development Cost (1995 $),with iOOirects $10,358,675
SECTION4 ']
4. PROJECT ENERGY PRODUCTION
The full load output from the project will be approximately 700 kW. Current peak load in
the INNEC system is about 480 kW. About 110 cubic feet per second of water is required
to produce full turbine output with our proposed arrangement. There are about 5 112 years
of daily flow records on the Tazimina River at the falls (see attached table). During this
periodt the lowest recorded river flow was 140 cfs. Although it is likely that flows may
occasionally drop below 140 cfs, it is reasonable to assume that 110 cfs is available at most
times for diversion except during short periods in the late winter months. If this is the case,
full load output should be available at most times from the units, if necessary. In reality,
the units will be operated to follow the INNEC system load. It appears that at least in the
near term, sufficient energy would be generated by the hydro facility to carry 100% of the
INNEC load, except during very low river flow periods or during hydro plant outages.
Using the project configuration developed as part of this study, an estimate of the maximum
theoretical energy generation from the project was made. To perform this analysis, a
computer based model called "HEP" (Hydropower Evaluation Program) was used. HEP is
a computer model for computing average and annual power generation for a run-of-river
hydropower project, developed and hand verified by HDR Engineering, Inc. The daily flows
at the diversion site for the five years of record, and project development information (such
as pipe length, diameter, diversion and powerhouse elevation, turbine and generator
efficiency curves, and other system losses) are input into the model and it calculates energy
production for each day of the period of record.
For each daily flow in the period of record, HEP first subtracts any required instream flow
release for that day (zero in this case). The remaining flow is used to decide how many
turbines can operate and their percent of full load. Based on the percent load, efficiency of
the turbine and generator are obtained from look-up tables that ·are input by the user. Head
loss in the pipeline is calculated using Manning's Equation and by then adding intake and
other miscellaneous losses. Finally, daily energy is calculated using the net head, available
flow, and appropriate efficiencies. Daily energy is reduced to account for losses such as
transmission line losses, station service use, and downtime. This process is repeated for
every day of the period of record. The output table shows the monthly average energy
production (obtained by averaging daily generation) for each month of the period of record.
The HEP model was run for two cases; a) using the proposed project arrangement with two,
350 kW units with a total diversion of 110 cfs, and; b) the same arrangement using two 700
kW units and a total diverted flow of 220 cfs (future case). Output from the two cases is
attached.
Results show that the maximum theoretical generation from the proposed arrangement is
about 6,030,000 kWh per year. In the future, increasing diversion to 220 cfs and replacing
the turbines with two 700 kW units could provide up to 10t800,000 kWh per year. Current
INNEC system load is approximately 1,800,000 kWh per year. The two unit, 350 kW each
arrangement proposed is projected to be able to carry the entire 1994 electrical load of the
Sepumber 1994 4-1 Tazimina Hydroelectric Project
INNEC system except for unplanned outages, and has enough capacity to accommodate
considerable load growth in the future. If system demands expand significantly or additional
interties are constructed to other load centers, turbine upgrading could clearly provide
significantly more energy in the future.
September 1994 4-2 Tazimina Hydroelectric Project
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
install gage
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
DAILY AVERAGE FLOWS-TAZIMINA RIVER ATTAZIMINA FALLS
(Format is wat« yNif (Oct-Sept.), linJt number is month number (Oct•1), followed by daitvflowsfor each day of month)
1981
1
0
2
0
3
0
4
0
5
0
6
0
7
0
8
0
9
0
10
3000
11
3020
12
809
1982
1
606
2
590
3
320
4
250
5
250
6
185
7
146
8
435
9
1980
10
1700
11
1460
12
3760
1983
1
932
2
425
3
232
4
140
5
140
6
140
7
180
8
630
9
1800
10
1410
11
1150
12
704
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
3050
2990
2050
2840
1260
781
624
636
880
570
470
320
260
250
330
240
200
185
175
146
180
445
1090
1860
2540
1780
2380
1420
1240
4760
2100
940
558
410
310
228
330
140
140
140
140
140
140
185
300
670
1790
1780
1880
1400
858
1090
624
684
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2170
2930
2880
2690
2680
1240
767
594
636
840
560
450
320
260
250
350
235
200
185
175
144
179
460
1240
1820
2300
1840
2200
1390
1280.
4800
2030
893
570
400
310
219
321
140
140
140
140
140
140
190
320
710
1940
1760
1870
1370
851
1020
612
672
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2310
2740
2800
3180
2470
1200
746
588
618
810
550
440
320
260
250
360
235
200
185
175
141
160
460
1390
1850
2100
1800
2030
1340
1270
4490
1930
916
552
390
300
217
300
140
140
140
140
140
140
195
330
750
2020
1800
1880
1320
830
879
624
660
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2520
2570
2690
3190
2330
1200
753
582
612
800
540
420
320
260
250
370
250
200
185
175
141
162
460
1500
1900
1910
1740
1880
1280
1230
4080
1810
900
516
375
300
213
290
140
140
140
140
140
145
200
340
790
2070
1850
1800
1260
830
888
648
672
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2740
2400
2590
3020
2170
1160
767
570
690
800
530
410
300
260
250
370
245
200
185
185
140
189
470
1710
1970
1140
1720
1720
1230
1300
3790
1700
637
495
386
290
213
270
140
140
140
140
140
145
210
360
850
2040
1880
1730
1190
900
872
654
690
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2880
2290
2460
2810
2000
1150
739
546
760
790
520
400
300
250
250
370
217
190
185
185
140
211
495
2620
1980
1630
1780
1800
1170
1730
3860
1580
746
480
350
290
215
240
140
140
140
140
140
150
220
380
900
1990
1840
1870
1130
924
858
648
725
0
0
0
0
0
0
0
0
0
255
0
0
0
0
0
0
0
2780
2240
2380
2620
1820
1110
711
522
830
780
520
390
300
250
250
360
203
190
185
185
143
242
516
3160
1930
1550
1850
1510
1120
2160
3640
1470
594
475
362
280
210
220
140
140
140
140
140
150
225
400
950
1990
1820
1650
1080
940
823
636
748
0
0
0
0
0
0
0
0
0
0
0
0
224
0
c
0
0
2690
2190
2380
2430
1700
1070
711
500
893
780
520
380
300
250
250
350
200
190
185
185
151
275
528
2880
1920
1630
2080
1440
1100
2350
3250
1370
570
485
362
280
210
200
140
140
140
140
140
150
230
420
1000
2040
1870
1640
1020
1080
802
618
746
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2620
2240
2400
2350
1620
1040
704
485
972
740
520
380
300
250
250
350
200
190
185
185
158
358
546
2720
1980
1730
2350
1370
1070
2410
2680
1280
570
470
350
270
210
180
140
140
140
140
140
155
240
440
1050
2080
1920
1600
988
1280
767
606
725
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2530
2480
2400
2390
1570
'1020
690
465
1020
120
520
350
280
250
280
330
200
190
185
155
162
415
582
2720
2100
1780
2780
1320
1070
2380
2620
1190
570
450
336
270
210
170
140
140
140
140
140
155
250
460
1150
2060
2020
1540
972
1410
725
594
718
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2460
2840
2320
2380
1530
982
684
500
1030
100
520
350
280
250
260
320
200
190
185
155
186
420
648
2790
2230
1820
2840
1460
1030
2280
2450
1120
570
480
330
280
207
180
140
140
140
140
140
160
280
480
1200
2010
1980
1480
948
1450
697
570
718
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2390
3000
2190
2480
1500
958
678
546
1020
680
520
350
280
250
280
300
200
190
177
154
171
425
739
2730
2490
1870
2780
1540
988
2160
2270
1080
564
455
324
280
223
150
140
140
140
140
140
185
270
510
1300
1920
1980
1420
908
1430
672
552
711
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2380
2980
2130
2560
1450
950
660
564
988
860
510
350
280
250
260
290
190
175
152
175
410
788
2580
2840
1840
2620
1530
996
2210
2210
1010
558
485
318
250
292
150
140
140
140
140
170
280
540
1350
1850
1920
1360
879
1380
642
594
746
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2800
2820
2080
2800
1390
894
642
564
950
630
490
350
280
250
280
280
190
175
150
179
410
637
2350
2760
1780
2600
1490
1040
2180
2190
964
558
470
318
245
334
145
140
140
140
140
170
290
570
1450
1800
1900
1370
858
1320
638
672
885
0
0
0
0
0
0
0
0
0
0
0
0
0
0
2840
1980
3080
1350
846
570
900
610
350
280
250
310
260
190
175
148
420
948
2150
1710
2540
1480
1170
2370
932
552
445
242
334
140
140
140
140
140
115
600
1520
1790
1410
851
1240
630
704
1984
Oct 1 1000 1180 1260 1270 1260 1310 1310 1270 1350 1710 2630 3340 3490 3270 2950
2630 2350 2100 1890 1740 1600 1470 1360 1260 1140 1040 981 917 859 816 n4
Nov 2 726 711 711 678 631 600 636 876 947 924 886 851 809 754 714
704 690 666 624 606 624 618 594 547 528 522 505 557 793 1060
Dec 3 1270 1350 1340 1310 1250 1170 1090 1000 909 652 809 756 712 680 630
597 584 534 505 500 505 475 450 430 410 390 380 360 340 328 309
Jan 4 300 290 280 280 270 260 260 250 250 240 240 240 240 230 230
230 230 230 220 220 220 220 220 220 220 210 210 210 210 210 210
Feb 5 210 210 210 210 210 210 210 210 210 210 210 210 210 210 210
210 210 210 210 210 210 210 210 210 210 210 210 210 210
Mar 6 210 210 210 .250 330 390 400 410 410 400 360 380 340 327 300
290 288 283 275 270 268 265 280 255 250 250 263 285 263 280 258
Apr 7 255 255 250 245 245 245 240 238 228 221 215 215 211 211 209
207 203 203 195 195 201 207 203 201 195 197 221 279 290 303
May 8 327 338 334 327 321 321 324 330 334 346 358 386 374 386 398
425 450 470 490 522 564 612 660 710 759 802 637 858 879 886 893
Jun 9 893 900 940 1020 1120 1250 1380 154C 1650 1740 1790 1790 1810 1900 1970
2050 2230 2420 2450 2370 2300 2250 2210 2250 2390 2570 2610 2520 2440 2420
Jut 10 2370 2270 2150 1980 1930 1910 1920 1930 1920 1860 1800 1720 1630 1590 1520
1440 1370 1370 1370 1370 1340 1280 1250 1210 1180 1130 1100 1060 1060 1040 1020
Aug 11 1020 1000 988 980 964 972 964 948 932 908 971 980 940 900 865
830 795 816 864 886 900 1020 1180 1410 2130 3180 3370 3120 2790 2420 2110
Sep 12 1880 1660 1500 1380 1240 1140 1060 997 941 880 837 795 768 767 746
725 704 697 690 690 886 648 642 846 846 830 824 836 886 668
1985
Oct 1 672 736 781 795 809 809 802 781 760 739 718 890 886 638 600
588 564 540 516 485 470 485 480 455 430 398 378 358 346 346 346
Nov 2 346 324 300 288 293 303 303 288 273 265 255 245 240 238 245
253 250 243 235 240 248 243 235 225 215 207 207 203 205 199
Dec 3 195 195 197 195 201 199 195 195 193 191 189 190 190 185 185
185 180 180 180 180 180 180 180 175 175 175 175 175 175 170 170
Jan 4 170 170 170 170 170 165 185 185 185 185 185 185 185 185 165
180 160 160 180 180 180 180 180 160 160 155 155 155 155 155 155
Feb 5 155 155 155 155 155 155 155 155 155 155 155 155 155 155 155
155 155 155 155 155 150 150 150 150 150 150 150 150
Mar 8 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150
150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150
Apr 7 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150
150 150 150 150 188 150 147 147 151 147 133 133 130 128 128
May 8 130 133 135 139 141 150 163 189 175 180 180 182 185 193 209
243 305 369 439 460 485 557 847 773 899 1080 1270 1590 1960 2270 2540
Jun 9 2550 2480 2380 2510 2700 2760 2700 2630 2550 2460 2370 2340 2440 2490 2490
2450 2390 2310 2250 2250 2240 2160 2160 2200 2250 2450 2750 3010 3330 3640
Jul 10 3800 4000 4100 4100 3900 3700 3500 3300 3100 3000 2900 2900 2800 2800 2700
2500 2400 2300 2300 2300 2200 2200 2100 2000 1900 1900 1900 1600 1700 1710 1640
Aug 11 1540 1470 1410 1380 1340 1350 1440 1550 1690 1920 2180 2810 3380 3690 3610
4150 4250 3930 3520 3240 3010 2820 2580 2370 2200 2030 1880 1740 1730 1670 1620
Sep 12 1600 1580 1580 1540 1480 1410 1340 1300 1290 1300 1280 1270 1220 1270 1480
1860 2140 2240 2480 2490 2320 2180 2100 2060 1990 1940 2160 3670 4690 5390
1986
Oct 1 5390 4870 4220 3870 3150 2750 2460 2420 2800 2550 2380 2200 2030 1860 1800
1790 1670 1520 1370 1300 1230 1140 1070 997 941 880 831 782 719 678 654
Nov 2 630 606 588 570 552 516 480 460 440 425 410 400 390 380 370
360 350 342 338 334 330 327 318 312 306 298 285 280 275 270
Dec 3 265 260 255 250 250 245 240 240 235 235 230 230 225 225 220
220 210 210 210 210 200 200 200 200 200 200 200 190 190 190 190
Jan 4 190 180 180 180 180 180 180 180 180 180 180 180 180 180 180
170 170 170 170 170 170 170 170 170 170 170 170 170 170 170 170
Feb 5 170 170 170 170 170 160 160 160 160 160 160 160 160 180 160
160 160 160 160 160 160 160 160 160 160 160 160 160
Mar 6 160 160 160 160 160 160 180 160 160 160 160 160 160 160 160
160 160 180 160 160 160 160 160 160 160 160 160 160 160 160 160
Apr 7 160 160 160 180 160 160 160 180 160 160 160 160 160 160 180
160 160 160 160 160 160 160 160 160 160 170 170 170 170 170
May 8 180 180 180 180 180 190 190 190 190 190 200 210 220 230 250
270 290 320 350 380 420 460 500 580 620 700 800 900 1000 1100 1160
Jun 9 1230 1270 1270 1280 1300 1330 1340 1350 1360 1390 1380 1380 1350 1340 1380
1540 1840 2160 2350 2350 2310 2180 2050 1900 1760 1830 1540 1480 1480 1530
Jul 10 1610 1710 1870 1980 2020 2010 1980 1900 1790 1670 1590 1580 1520 1460 1410
1410 1370 1320 1280 1370 1520 1610 1730 1960 2050 2030 1920 1790 1660 1530 1480
Aug 11 1390 1320 1280 1380 1450 1470 1440 1430 1410 1410 1390 1380 1380 1490 1880
2140 2150 2150 2080 1970 1840 1730 1780 1940 2030 2020 2100 2100 2050 1980 1680
Sep 12 1780 1690 1560 1470 1380 1300 1420 1910 2340 2380 2280 2150 2010 1860 1740
1730 1710 1670 1640 1940 2310 2490 2540 2420 2270 2080 1960 1800 1690 1610
Tazimina P~ER GENERATION
----------------------------------------------------------------------------------------------------------------------------
DATA FILE USED: TAZIMIN2.QCH
MODEL DESCRIPTION
PIPE #
1
LENGTH
450
HEADWATER ELEV: 575
TAILWATER ELEV: 482
GROSS HEAD: 93
DIAMETER
60
NET HEAD i FULL LOAD: 91.9
MANNING'S n
.011
MINOR LOSSES
2
NAMEPLATE CAPACITY (kW): 747.9 @ 1 ~ER FACTOR
STATION SERVICE LOSS:
TRANSFORMER LOSS: 1
TRANSMISSION LOSS: 3
SCHEDULED D~N TIME: 3
TURBINE SELECTED: 2 -FRAN-SUL
GENERATOR SELECTED: BURKE
MINIMUM INSTREAM FL~S
OCT NOV DEC JAN FEB
0 0 0 0 0
MAR
0
SIMULATED PRODUCTION IN MEGAWATT-HOURS
YEAR OCT NOV DEC JAN FEB MAR
1982 511.9 495.4 511.9 511.9 462.4 511.9
1983 511.9 495.4 511.9 511.9 462.4 511.9
1984 511.9 495.4 511.9 511.9 478.9 511.9
1985 511.9 495.4 511.9 511.9 462.4 511.9
1986 511.9 495.4 511.9 511.9 462.4 511.9
AVERAGE 511.9 495.4 511.9 511.9 465.7 511.9
AVERAGE PLANT FACTOR: 0.92
AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 0
THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES
X LOAD TURBINE GENERATOR COMBINED
----------------------------------------
0 0.0 o.o 0.0
10 o.o 90.0 0.0
20 0.0 93.0 o.o
30 0.0 94.6 0.0
40 74.0 95.4 70.6
50 81.0 96.0 77.8
60 85.0 96.4 81.9
70 87.3 96.5 84.2
80 90.0 96.5 86.8
90 91.1 96.5 87.9
100 90.5 96.5 87.3
APR MAY JUN JUL AUG SEP
0 0 0 0 0 0
APR MAY JUN JUL AUG SEP TOTAL
495.4 511.9 495.4 511.9 511.9 495.4 6027.3
495.4 511.9 495.4 511.9 511.9 495.4 6027.3
495.4 511.9 495.4 511.9 511.9 495.4 6043.8
495.4 511.9 495.4 511.9 511.9 495.4 6027.3
495.4 511.9 495.4 511.9 511.9 495.4 6027.3
495.4 511.9 495.4 511.9 511.9 495.4 6030.6
----------------------------------------------------------------------------------------------------------------------------
Tazimina POWER GENERATION
--------------------------------------------------------------.--------------------------------------------------------------
DATA FILE USED: TAZIMIN2.QCH
MODEL DESCRIPTION
PIPE #
1
LENGTH
450
HEADWATER ELEV: 575
TAILWATER ELEV: 482
GROSS HEAD: 93
DIAMETER
60
NET HEAD ~ FULL LOAD: 88.8
MANNING'S n
.011
MINOR LOSSES
2
NAMEPLATE CAPACITY CkW): 1444.1 ~ 1 POWER FACTOR
STATION SERVICE LOSS:
TRANSFORMER LOSS: 1
TRANSMISSION LOSS: 3
SCHEDULED DOWN TIME: 3
TURBINE SELECTED: 2 -FRAN-SUL
GENERATOR SELECTED: BURKE
MINIMUM INSTREAM FLOWS
OCT NOV DEC JAN FEB
0 0 0 0 0
MAR
0
SIMULATED PRODUCTION IN MEGAWATT-HOURS
YEAR OCT NOV DEC JAN FEB MAR
1982 988.4 956.5 988.4 988.4 8n.9 855.2
1983 988.4 956.5 9.79.1 n6.5 553.8 613.1
1984 988.4 956.5 988.4 981.1 889.0 984.8
1985 988.4 946.2 841.1 n7.o 615.6 663.4
1986 988.4 956.5 950.3 794.0 654.3 715.0
AVERAGE 988.4 954.5 949.5 843.4 718.1 766.3
AVERAGE PLANT FACTOR: 0.85
AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 0
THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES
X LOAD TURBINE GENERATOR COMBINED
-------------------·--------------------
0 0.0 0.0 0.0
10 0.0 90.0 0.0
20 0.0 93.0 0.0
30 o.o 94.6 0.0
40 74.0 95.4 70.6
so 81.0 96.0 n.8
60 85.0 96.4 81.9
70 87.3 96.5 84.2
80 90.0 96.5 86.8
90 91.1 96.5 87.9
100 90.5 96.5 87.3
APR MAY JUN JUL AUG SEP
0 0 0 0 0 0
APR MAY JUN JUL AUG SEP TOTAL
683.0 961.5 956.5 988.4 988.4 956.5 11189.5
788.5 988.4 956.5 988.4 988.4 956.5 10484.4
925.1 988.4 956.5 988.4 988.4 956.5 11591.8
627.4 866.3 956.5 988.4 988.4 956.5 10165.4
700.5 937.6 956.5 988.4 988.4 956.5 10586.7
744.9 948.5 956.5 988.4 988.4 956.5 10803.5
5. PROJECT ECONOMICS
A simple economic analysis was performed to estimate the first year cost of energy produced
from the hydroelectric project. A spreadsheet was developed that calculates first year energy
costs based on input values for assumed project capital cost, interest rate, discount rate,
O&M cost and system load growth. A copy of the spreadsheet output is attached for a base
case scenario. The spreadsheet also contains assumptions for cost to maintain the diesel
system on standby and costs for diesel fuel during periods the hydroelectric plant is
shutdown. Diesel fuel is estimated to cost $1.15 per gallon in 1994.
Assuming a total plant capital cost of $9,961,000, a $5 million grant from the State of
Alaska, a $3.4 million grant from the federal government, and the other assumptions shown
on the spreadsheet (base case 5% interest), the fust year energy costs will be approximately
$0.10 per kilowatt hour with a bond interest of 5%. If bond interest is 7% or 9%, instead
of 5%, first year energy cost increases to $0.111 and $0.120 per kilowatt hour respectively.
Spreadsheets showing these analyses follow. Power price is very sensitive to overall system
demand. Increasing load has a dramatic effect on lowering energy price, because the fixed
costs are relatively high, and the incremental cost of additional generation is extremely low.
For example, increasing system load from 1,775,000 (actual 1993-94 production) to
2,300,000 reduces first year energy price from $0.10 to $0.078 per kWh. A copy of this
spreadsheet example (Increased Load Case) is also attached. This spreadsheet model is
available to check the impact of varying assumptions and sensitivity of power price to
changes in fmancing, O&M costs and/or project cost in the future. Under base case
assumptions, some negative cash flow results in the early years of the project. Increasing
first year energy cost from $0.10 to $0.123 would avoid any negative cash flow.
Allowance for a savings (a benefit) in the expense of rebuilding the diesel fuel storage depot
is included in the annual costs analysis, since constructing the hydroelectric project will
indefmitely defer the need to rebuild the fuel facilities. Assuming 20 year bonds (7%) are
sold to fmance an estimated $400,000 in repairs, an annual savings of approximately $38,000
per year results from the deferred work.
September 1994 5-1 Tazimina Hydroelectric Project
HYDROELECTRIC PROJECT ECONOtvflCS
TAZIMINA HYDROELECTRIC PROJECT
Assumptions: BASE CASE 5%
Construction interest rate:
Bond Interest Rate:
Percent financed:
Kilowatt hOW"S prod./year:
Total Capital Cost:
Number years ofloan
YEAR ••••••••••••••••••••••••••••••••••••••••••••••• •••••••••
Operating Revenues:
Power Price (price escalated@ 5% to represent 5% load growth)
Sale of Electricity Revenues
Total Revenues:
1996
Operating Expenses (annual assumed escalation shown in parentheses)
Operating Labor ( 4%)
Maintenance Expenses (5%)
Land Use Payments (0%)
Insurance (4o/o)
Permit Fees (2%)
Maintaining Diesel Plant On Stand-by (4%)
Diesel Fuel For 3% of Load (4% fuel, 5% load growth)
Savings From Deferred Fuel Tankage Rehabilitation (0%)
Administrative Fees (5%)
Total Expenses:
Debt Service
Interest Expense
Principal Repayment
Total Debt Service
Operating Cash Flow
EQUITY Contribution
Total Capital Expeditures
8400012
9961000
0.03
(program updated 10/21/94)
0.050
0.05000
15.671
(These are global variables)
1775641 (July to June 1994 actual)
9961000 (Not including indirc.cts)
30
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 ........... ....... ....... ....... ....... ....... ....... ....... ....... ........ ........ ........ ........ ....... ....... ....... . ..... .
0.103 0.108 O.ll3 0.119 0.125 0.131 0.138 0.145 0.152 0.159 0.167 0.176 0.184 0.194 0.203 0.214 0.224
182358 191476 201050 211103 221658 232741 244378 256596 269426 282898 297043 311895 327489 343864 361057 379110 398065
182358 191476 201050 211103 221658 232741 244378 256596 269426 282898 297043 311895 327489 343864 361057 379110 398065
70000
15000
20000
10000
3000
20000
4368
-35000
15000
72!!00
15750
20000
10400
3060
20800
4770
-35000
15750
75712
16538
20000
10816
3121
21632
5209
-35000
16538
78740
17364
20000
11249
3184
22497
5688
-35000
17364
81890
18233
20000
11699
3247
23397
6211
-35000
18233
85166
19144
20000
12167
3312
24333
6783
-35000
19144
88572
20101
20000
12653
3378
25306
7407
-35000
20101
92115
21107
20000
13159
3446
26319
8088
-35000
21107
95800
22162
20000
13686
3515
27371
8832
-35000
22162
99632
23270
20000
14233
3585
28466
9645
-35000
23270
103617
24433
20000
14802
3657
29605
10532
-35000
24433
107762
25655
20000
15395
3730
30789
11501
-35000
25655
112072
26938
20000
16010
3805
32021
12559
-35000
26938
116555
28285
20000
16651
3881
33301
13715
-35000
28285
121217
29699
20000
17317
3958
34634
14976
-35000
29699
126066
31184
20000
18009
4038
36019
16354
-35000
31184
131109
32743
20000
18730
4118
37460
17859
-35000
32743
122368 128330 134565 141087 147910 155049 162520 170340 178528 187101 196080 205487 215343 225672 236500 247854 259762
78049
23495
76875
24670
75641
25903
74346
27199
72986
28558
71558
29986
70059
31486
68485
33060
66832
34713
65096
36449
63273
38271
61360
40185
59351
42194
57241
44304
55026
46519
52700
48845
50258
51287
101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545
-41554 -38398 -35059 -31529 ·27796 -23853 -19687 -15288 -10646 -5748 -582 4863 10602 16647 23012 29711 36759
Real Discount Rate For Economic Analysis ....................................... ........... ......... ....... ....... ....... ....... ....... ....... ....... ....... ........ ........ ........ ........ ....... ....... ....... . ....... .
PV of Operating Cash Flow
(Adjust power price until sum approximates zero)
Debt Principal=
Annual Loan Payments~
Annual interest
Annual principal
6166
(sum)
-40344
0.971
-36194
0.943
-32084
0.915
-28013
0.888
-23977
0.863
-19976
0.837
-16007 -12069
0.813 0.789
-8159
0.766
-4277
0.744
-421
0.722
3411
0.701
7219
0.681
11006
0.661
14771
0.642
18515
0.623
22240
0.605
1560988 ••••••• ••••••• ••••••• ••••••• ••••••• ••••••• ••••• •• ••••••• ••••••• ••••••• ••••••• ••••••• •••• •• • ••••••• ••• ... ••• • ••••••
101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545
78049
23495
76875
24670
75641
25903
74346
27199
72986
28558
71558
29986
70059
31486
68485
33060
66832
34713
65096
36449
63273
38271
61360
40185
59351
42194
57241
44304
55026
46519
52700
48845
50258
51287
2014 2015 2016 2017 2018
•••••••••••••••••••••••••••••••••••
0.235 0.247 0.260 0.272 0.286
417969 438867 460810 483851 508043
417969 438867 460810 483851 508043
136353 141807 147479 153379 159514
34380 36099 37904 39799 41789
20000 20000 20000 0 0
19479 20258 21068 21911 22788
4201 4285 4370 4458 4547
38958 40516 42137 43822 45575
19502 21296 23255 25395 27731
-35000 -35000 -35000
34380 36099 37904 39799 41789
272253 285361 299119 328564 343734
47693 45001 42174 39205 36088
53851 56544 59371 62340 65457
101545 101545 101545 101545 101545
44171 51962 60147 53743 62765
•••••••••••••• ••••••• ••••••••••••••
25946 29633 33302 28889 32757
0.587 0.570 0.554 0.538 0.522
953866 900015 843471 784100 721760
101545 101545 101545 101545 101545
47693 45001 42174 39205 36088
53851 56544 59371 62340 65457
NOTES: I. Power Price is shown here escalating at 5% per year for calculation purposes. In reality, we are asswning power price is comtant in the future at the 1997 rate and the load is growing at 5%. Results are the same.
2. To model different load growth projections, change power price escalation to match desired load growth rate.
3. To model impact of other financing methods or grants, change percent financed so "equity contribution" equals the grant amounts. Then adj1«t "power price" in the first year until the PV of operating cash flow approximates zero.
4. Only first 20 years of operation are shown and only 20 years included in the PV calculations for simplicity.
5. Land use payments are to pay for $400,000 in land use charges over 20 yean at no interest.
6. Tank farm rehabilitation savings based on avoiding $400,000 in rehab. costs financed w/20 year 6% bonds.
HYDROELECTRIC PROJECT ECONO~!JCS (program updated 10121194)
T AZIMINA HYDROELECTRIC PROJECT
Assumptions: BASE CASE 7%
Construction interest rate: 0.070 (These are global variables)
Bond Interest Rate: 0.070
Pen:cnt financed: 15.671
Kilowatt hours prod.lyear: 1775641 (July to June 1994 actual)
Total Capital Cost: 9961000 (Not including indirects)
Number yean of loan 30
YF.AR 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 •••••••••••••••••••••••••••••••••••••••••••••••• ••••••••• ••••••••• •••••••• ••••••••••••••••••••••••••••••• ••••••• ••••••• • •••••• • •••••• ••••••• ••••••• ••••••• ...•.......•....
Operating Revenues:
Power Price (price escalated@ 5% to represent 5% load growth) 0.1108 O.ll6 0.122 0.128 0.135 0.141 0.149 0.156 0.164 0.172 0.181 0.190 0.199 0.209 0.219
Sale of Electricity Revenues 196812 206653 216985 227835 239226 251188 263747 276934 290781 305320 320586 336615 353446 371118 389674
Total Revenues: 196812 206653 216985 227835 239226 251188 263747 276934 290781 305320 320586 336615 353446 371118 389674
Operating Expenses (annual assumed escalation shown in parentheses)
Operating Labor (4%) 70000 72800 75712 78740 81890 85166 88572 92115 95800 99632 103617 107762 112072 116555 121217
Maintenance Expenses (5%) 15000 15750 16538 17364 18233 19144 20101 21107 22162 23270 24433 25655 26938 28285 29699
Land Use Payments (0%) 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000
Insurance ( 4%) 10000 10400 10816 11249 11699 12167 12653 13159 13686 14233 14802 15395 16010 16651 17317
Pennit Fees (2%) 3000 3060 3121 3184 3247 3312 3378 3446 3515 3585 3657 3730 3805 3881 3958
MainWtining Dies~! Plant On Stand-by (4%) 20000 20800 21632 22497 23397 24333 25306 26319 27371 28466 29605 30789 32021 33301 34634
Diesel Fuel For 3% of Load (4% fuel, 5% load growth) 4368 4770 5209 5688 6211 6783 7407 8088 8832 9645 10532 11501 12559 13715 14976
Savings From Deferred Fuel Tankage Rehabilitation (0~'<>) -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000
Administrative Fees (5%) 15000 15750 16538 17364 18233 19144 20101 21107 22162 23270 24433 25655 26938 28285 29699
ToWll Expenses: 122368 128330 134565 141087 147910 155049 162520 170340 178528 187101 196080 205487 215343 225672 236500
Debt Service
Interest Exp1:11Se 109269 108112 106875 105550 104133 102617 100994 99258 97401 95413 93287 91011 88576 85971 83184
Principal Repayment !6525 17682 18920 20244 21661 23178 24800 26536 28393 30381 32508 34783 37218 39823 42611
Total Debt Service 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794
Operating Cash Flow -51350 -47472 -43374 -39047 -34478 -29656 -24567 -19201 -13541 -7575 -1289 5334 12309 19652 27380
EQUITY Contribution 8400012
Total Capital Expeditures 9961000
Real Discount Rate For Economic Analysis O.G3 ....................................... • •••••••••• •••••••••••••••••••••••••••••••••••••••••••••••• • •••••• ••••••• ........ • •••••• ••••••• ++++otr•• • ••••••••••••••••••••••
PV of Operating Cash Flow 316 -49855 -44747 -39693 -34692 -29741 -24836 -19976 -15157 -10378 -5637 -931 3741 8382 12992 17574
(Adjust power price until sum approximates zero) (sum) 0.971 0.943 0.915 0.888 0.863 0.837 0.813 0.789 0.766 0.744 0.722 0.701 0.681 0.661 0.642
Debt Principal~ 1560988 ••••••• ••••••• • •••••• ••••••• ••••••• • •••••• • •••••• ••••••• . ....... • •••••• ••••••• ••••••• ....... ........
Annual Loan Payments~ 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794 125794
Annual interest 109269 108112 106875 105550 104133 102617 100994 99258 97401 95413 93287 91011 88576 85971 83184
Annual principa I 16525 17682 18920 20244 21661 23178 24800 26536 28393 30381 32508 34783 37218 39823 42611
2012 2013 2014 2015 2016 2017 2018 ....... ......... ....... ......... ....... . ............... .
0.230 0.242 0.254 0.267 0.280 0.294 0.309
409158 429616 451097 473652 497334 522201 548311
409158 429616 451097 473652 497334 522201 548311
126066 131109 136353 141807 147479 153379 159514
31184 32743 34380 36099 37904 39799 41789
20000 20000 20000 20000 20000 0 0
18009 18730 19479 20258 21068 21911 22788
4038 4118 4201 4285 4370 4458 4547
36019 37460 38958 40516 42137 43822 45575
16354 17859 19502 21296 23255 25395 27731
-35000 -35000 -35000 -35000 -35000
31184 32743 34380 36099 37904 39799 41789
247854 259762 272253 285361 299119 328564 343734
80201 77009 73594 69940 66030 61847 57371
45594 48785 52200 55854 59764 63948 68424
125794 125794 125794 125794 125794 125794 125794
35510 44060 53049 62496 72421 67843 78783
••••••• ••••••••••••••••••••• • •••••••••••••••••••••••••
22128 26657 31161 35641 40098 36469 41 I 16
0.623 0.605 0.587 0.570 0.554 0.538 0.522
••••••• ••••••• ••••••• 999146 943291 883527 819580
125794 125794 125794 125794 125794 125794 125794
80201 77009 73594 69940 66030 61847 57371
45594 48785 52200 55854 59764 63948 68424
NOTES: L Pow<..-r Price is sho\01'1 here escalating at 5% per year for calculation pwposes. In reality, we are assuming
power price is constant in the future at the 1997 rate and the load is growing at 5%. Results are the same.
2. To model different load growth projections, change power price: escalation t.o match desired load growth rate:.
3. To model impact of other fmancing methods or grants, change: percent financed so "equity contribution" equals
the grant amounts. Then adjust "power price" in the ftrllt year until the PV of operating cash flow approximates zero.
4. Only fint 20 years of operation are shown and only 20 yean included in the PV calculations for simplicity.
S. Land use payments are t.o pay for $400,000 in land use charges over 20 years at no interest.
6. Tank farm rehabilitation savings based on avoiding $400,000 in rehab. costs fmanced w/20 year 6% bonds.
HYDROELEC1RIC PROJECT ECONOI\1ICS (program updated 10/21194)
T AZIMINA HYDROELEC1RIC PROJECT
Assumptions: BASE CASE 9%
Construction interest rate: 0.090 (These are global variables)
Bond Interest Rate: 0.090
Percent financed: 15.671
Kilowatt hours prodJycar: 1775641 (July to June 1994 actual)
Total Capital Cost: 9961000 (Not including indirects)
Number years ofloan 30
YEAR 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
•••••••••••••••••••••••••••••••••••••••••••••••• ••••••••• •••••••••••••••••••••••••••••••••••••••••••••••• • •••••• . ...... ••••••• • •••••• ....... ....... ....... ........ ..........
Operating Revenues:
Power Price (price escalated @ 5% to represent 5% load growth) 0.1198 0.126 0.132 0.139 0.146 0.153 0.160 0.169 0.177 0.186 0.195 0.205 0.215 0.226 0.237
Sale of Electricity Revenues 212633 223265 234428 246149 258457 271380 284949 299196 314156 329864 346357 363675 381858 400951 420999
Total Revenues: 212633 223265 234428 246149 258457 271380 284949 299196 314156 329864 346357 363675 381858 400951 420999
Operating Expenses (annual assumed escalation shown in parentheses)
Operating Labor (4%) 70000 72800 75712 78740 81890 85166 88572 92115 95800 99632 103617 107762 112072 116555 121217
Maintenance Expenses (5%) 15000 15750 16538 17364 18233 19144 20101 21107 22162 23270 24433 25655 26938 28285 29699
Land Use Payments (0%) 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000 20000
Insurance (4%) 10000 10400 10816 11249 11699 12167 12653 13159 13686 14233 14802 !5395 16010 16651 17317
Pennit Fees (2%) 3000 3060 3121 3184 3247 3312 3378 3446 3515 3585 3657 3730 3805 3881 3958
Maintaining Diesel Plant On Stand-by (4%) 20000 20800 21632 22497 23397 24333 25306 26319 27371 28466 29605 30789 32021 33301 34634
Diesel Fuel For 3% of Load (4% fuel, 5% load growth) 4368 4770 5209 5688 6211 6783 7407 8088 8832 9645 10532 11501 12559 13715 14976
Savings From Deferred Fuel Tankage Rehabilitation (0%) -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000 -35000
Administrative Fees (5%) 15000 15750 16538 17364 18233 19144 20101 21107 22162 23270 24433 25655 26938 28285 29699
Total Expenses: 122368 128330 134565 141087 147910 155049 162520 170340 178528 187101 196080 205487 215343 225672 236500
Debt Service
Interest Expense 140489 139458 138335 137110 135776 134321 132735 131006 129122 127068 124830 122390 119730 116831 113672
Principal Repayment 11452 12483 13606 14831 16165 17620 19206 20935 22819 24872 27111 29551 32211 35109 38269
Total Debt Service 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941
Operating Cash Flow -61676 -57006 -52078 -46878 -41394 -35610 -29512 -23085 -16313 -9178 -1665 6247 14575 23338 32557
EQUfi'Y Contribution 8400012
Total Capital Expeditures 9961000
Real DiscoWtt Rate For Economic Analysis 0.03 ......................................... ..•........ •••••••••••••••••••••••••••••••••••••••••••••••• • ••••••••••••• • •••••• ••••••• ••••••• • •••••• ••••••• . ...................
PV of Operating Cash Flow 244 -59880 -53734 -47659 -41651 -35707 -29823 -23996 -18224 -12502 -6830 -1202 4381 9925 15429 20~97
(Adjust power price until sum approximates zero) (sum) 0.971 0.943 0.9IS 0.888 0.863 0.837 0.813 0.789 0.766 0.744 0.722 0.701 0.681 0.661 0.642
Debt Principal= 1560988 ••••••• ••••••• ••••••• ••••••• ••••••• ••••••• • •••••• • •••••• ••••••• • •••••• ••••••• ••••••• • •••••• • ••••••
Annual Loan Payments= 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941 151941
Annual interest 140489 139458 138335 137ll0 135776 134321 132735 131006 129122 127068 124830 122390 119730 116831 113672
Annual principal 11452 12483 13606 14831 16165 17620 19206 20935 22819 24872 27111 29551 32211 35109 38269
2012 2013 2014 2015 2016 2017 2018 ....... ....... ......... ....... ....... . ............... .
0.249 0.261 0.274 0.288 0.303 0.318 0.334
442049 464151 487359 511727 537313 564179 592388
442049 464151 487359 511727 537313 564179 592388
126066 131109 136353 141807 147479 153379 159514
31184 32743 34380 36099 37904 39799 41789
20000 20000 20000 20000 20000 0 0
18009 18730 19479 20258 21068 21911 22788
4038 4118 4201 4285 4370 4458 4547
36019 37460 38958 40516 42137 43822 45575
16354 17859 19502 21296 23255 25395 27131
-35000 -35000 -35000 -35000 -35000
31184 32743 34380 36099 37904 39799 41789
247854 259762 272253 285361 299i19 328564 343734
110227 106473 102381 97921 93059 87759 81983
41714 45468 49560 54020 58882 64181 69958
151941 151941 151941 151941 151941 151941 151941
42254 52449 63165 74425 86253 83674 96713
••••••• ....... ....... ....... ....... ········ ...............
26331 31732 37103 42443 47756 44979 50474
0.623 0.605 0.587 0.570 0.554 0.538 0.522
••••••• ••••••• . ........ ••••••• ••••••• 975105 910923
151941 151941 151941 151941 151941 151941 151941
110227 106473 102381 97921 93059 87759 81983
41714 45468 49560 54020 58882 64181 69958
NOTES: I. Power Price is shown here escalating at 5% per year for calculation purposes. In reality, we are assuming
power price is constant in the future at the 1997 rate and the load is growing at 5%. Results are the same.
2. To model different load growth projections, change power price escalation to match desired load growth rate.
3. To model impact of other financing methods or grants, change percent financed so "equity contribution" equals
the grant amounts. Then adjust "power price" in the fmt year until the PV of operating cash flow approximates zero.
4. Only first 20 years of operation are shown and only 20 yean included in the PV calculations for simplicity.
5. Land use payments are to pay for $400,000 in land use charges over 20 years at no interest.
6. Tank farm rehabilitation savings based on avoiding $400,000 in rehab. costs fmanced w/ 20 year 6% bonds.
HYDROELECTRIC PROJECT ECONOMICS
T AZIMINA HYDROELECTRIC PROJECT
Assumptions: INCREASED LOAD CASE
(program updated I 0121194)
Construction interest rate:
Bond Interest Rate:
Percent financed:
Kilowatt holltll prod.!year:
Total Capital Cost:
Number yean of loan
YEAR 1996
0.050
0.05000
15.671
(These are global variable.•)
2300000 (load increase )
9961000 (Not including indirects)
30
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 ................................................... ••••••• ........... ••••••• ••••••• ••••••• •••••••• •••••••• •••••••• •••••••• •••••••• ••••••• +~te••••• ••••••• ••••••• ••••••• ••••••• ••••••• • •••••••
Operating Revenues:
Power Price (price escalated @ 5% to represent 5% load growth)
Sale of Electricity Revenues
Total Revenues:
Operating Expenses (annual assumed escalation shown in parentheses)
Operating Labor (4%)
M:aintcnanee Expenses (5%)
Land Use Payments (0%)
Insurance ( 4%)
Pennit Fees (2%)
M:aintaining Diesel Plant On Stand-by ( 4%)
Diesel Fuel For 3% of Load ( 4% fuel, 5o/oload growth)
Savings From Deferred Fuel Tankage Rehabilitation (0%)
Administrative Fees (5%)
Total Expenses:
Debt Service
Interest Expense
Principal Repayment
Total Debt Service
Operating Cash Flow
EQUITY Contribution
Total Capital Expeditures
•••••••
•••••••
0.03
0.080 0.084 0.088 0.093 0.097 0.102 0.107 0.113 0.118 0.124 0.130 0.137 0.144 0.151 0.159 0.167 0.175
184230 193442 203114 213269 223933 235129 246886 259230 272192 285801 300091 315096 330851 347393 364763 383001 402151
184230 193442 203114 213269 223933 235129 246886 259230 272192 285801 300091 315096 330851 347393 364763 383001 402151
70000
15000
20000
10000
3000
20000
5658
-35000
15000
72800
15750
20000
10400
3060
20800
6179
-35000
15750
75712
16538
20000
10816
3121
21632
6747
-35000
16538
78740
17364
20000
11249
3184
22497
7368
-35000
17364
81890
18233
20000
11699
3247
23397
8046
-35000
18233
85166
19144
20000
12167
3312
24333
8786
-35000
19144
88572
20101
20000
12653
3378
25306
9594
-35000
20101
92115
21107
20000
13159
3446
26319
10477
-35000
21107
95800
22162
20000
13686
3515
27371
11440
-35000
22162
99632
23270
20000
14233
3585
28466
12493
-35000
23270
103617
24433
20000
14802
3657
29605
13642
-35000
24433
107762
25655
20000
15395
3730
30789
14897
-35000
25655
112072
26938
20000
16010
3805
32021
16268
-35000
26938
116555
28285
20000
16651
3881
33301
17765
-35000
28285
121217
29699
20000
17317
3958
34634
19399
-35000
29699
126066
31184
20000
18009
4038
36019
21184
-35000
31184
131109
32743
20000
18730
4118
37460
23133
-35000
32743
123658 129739 136103 142766 149744 157052 164707 172729 181136 189949 199191 208883 219052 229722 240923 252684 265035
78049
23495
76875
24670
75641
25903
74346
27199
72986
28558
71558
29986
70059
31486
68485
33060
66832
34713
65096
36449
63273
38271
61360
40185
59351
42194
57241
44304
55026
46519
52700
48845
50258
51287
101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545
-40973 -37842 -34534 -31042 -27356 -23467 -19366 -15043 -10489 -5693 -644 4668 10254 16126 22295 28773 35571
Real Discount Rate For Economic Analysis ••••••••••••••••••••••••••••••••••••• ......... ......... ....... ....... ....... ........ ........ ........ ........ ........ ....... ....... ....... ....... ....... ······· ....... . ........ .
PV of Operating Cash Flow
(Adjust power price until sum approximates zero)
Debt Principal~
Annual Loan Payments~
Annual interest
Annual principal
984
(sum)
-39179
0.971
-35669
0.943
-31604
0.915
-27580
0.888
-23597
0.863
-19653
0.837
-15746
0.813
-11875
0.789
-8039
0.766
-4236
0.744
-465
0.722
3274
0.701
6983
0.681
10661
0.661
14310
0.642
17930
0.623
21521
0.605
1560988 ••••••• ••••••• ......... ......... ••••••• ......... ••••••• ••••••• ••••••• ••••••• ••••••• ••••••• ••••••• ........... ••••••• • ••••••
101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545 101545
78049
23495
76875
24670
75641
25903
74346
27199
72986
28558
71558
29986
70059
31486
68485
33060
66832
34713
65096
36449
63273
38271
61360
40185
59351
42194
57241
44304
55026
46519
52700
48845
50258
51287
NOTES: 1. Power Price is shown here escalating at 5% per year for calculation pwposes. In reality, we are assuming power price is constant in tbe future at the 1997 rate and tbe load is growing at 5%. Results are tbe same.
2014 2015 2016 2017 ..............................
0.184 0.193 0.202 0.213
422259 443371 465540 488817
422259 443371 465540 488817
136353 141807 147479 153379
34380 36099 37904 39799
20000 20000 20000 0
19479 20258 21068 21911
4201 4285 4370 4458
38958 40516 42137 43822
25261 27585 30123 32894
-35000 -35000 -35000
34380 36099 37904 39799
278012 291650 305986 336063
47693 45001 42174 39205
53851 56544 59371 62340
101545 101545 101545 101545
42702 50177 58009 51209
......... ••••••• ••••••••••••••
25083 28615 32118 27528
0.587 0.570 O.S54 0.538
953866 900015 843471 784100
101545 101545 101545 101545
47693 45001 42174 39205
53851 56544 59371 62340
2. To model different load growth projections, change power price escalation to match desired load growth rate.
3. To model impact of other financing methods or grants, change percent financed so "e<juity contribution" e<juals the grant amounts. 'Then adjust "power price" in the first year until the PV of operating cash flow approximates zero.
4. Only flfSt 20 years of operation are shown and only 20 years included in the PV calculations for simplicity.
5. Land use payments are to pay for $400,000 in land use charges over 20 years at no interest.
6. Tank fann rehabilitation savings based on avoiding $400,000 in rehab. costs financed w/ 20 year 6% bonds.
SECTION 6 -----:----------=----=-----------:-.......... ----
6.DEVELOPMENTSCHEDULE
A project development schedule was assembled that shows the timing of the major tasks and
their relationships through the end of 1995. The schedule is shown on the attached Figure
1.
The major assumptions that control the development schedule include:
• Construction work will be divided into three main contracts, an access road
construction and transmission line installation contract; a turbine/ generator
equipment supply contract; and a general construction contract to construct the
balance of the plant, install equipment and start-up and test the completed
plant.
• Construction should begin in the spring of 1995 and project completion should
be as early as possible in 1996.
• Construction work is likely to be suspended on the jobsite during the winter
(mid-November until April).
• The access road contract would be necessary first in order to provide site
access to construct the rest of the project.
To meet these goals and constraints, there are a variety of tasks that must be completed
before construction can proceed. Concerns about river hydraulics and their effect on intake
design dictate the need to model the intake structure. Geotechnical infonnation necessary
for fmal design of project features will have to be collected before snowfall in 1994. FERC
approval and other state pennits must be applied for in time to have all necessary approvals
in-hand by spring of 1995.
These tasks are all shown on the attached schedule with projected timeframes to complete
each task. It is clear that to meet a start of construction date of late spring, 1995, there are
several tasks that need to get underway in the near future. The critical path on the
development schedule passes through the following tasks:
• Complete Fisheries Studies
• Agency Consultation
• Complete FERC Application and File with FERC
• FERC Processing of Application
These four tasks must be completed generally as shown in order to allow construction on-site
to begin as planned. Other tasks, such as surveying, geotechnical studies, intake modelling
and fmal engineering design, are also closely scheduled and interdependent, so that they
could move onto the critical path if only small schedule slips or "float" occurs on the current
critical path items. The FERC application processing time assumed in this schedule, about
September 1994 6-1 Tazimina Hydroelectric Project
6 months, is a major assumption. Although FERC staff .have suggested 6 months as a
reasonable processing time, everything possible should be done to try to expedite PERC
processing. Failure to get this approval by spring or early summer 1995 could jeopardize
the 1995 construction season.
September 1994 6-2 Tazimina Hydroelectric Project
Prepared 8/94 FIGURE 1 TAZIMINAHYDROBLECTRICPROJECf
PROPOSED PROJECT DBVELOPMBNTSCHIDULB lHROUGH 1995
IWS 1~
Sent Oct. Nov Dec Jan Feb Mar AOr Mav Jun Jul Au_g s~~~ Oct Nov Dec Jan
ITEM 1 2 3 4 s ' 7 8 9 0 1U213 14 IS 16 17 I z 3 4 s 6 1. 8 9 011121314 5 16 .. 1718 9 211 2122 23 lt425 26 Z1 28• 29 J<l·· 31 Z. 33'.:!4 35 IJ,Ii.l'73$ l9 ~41 ~.43 44~ 40 41 11$49 sli H s2 1 l 3
Road and River BedSurvejing *;~;::~f:~~t'~~~: ~~i;!~~~~w.
Geotecbnical Exploralons M
Intake Physical Modd ~t
Compete Fisheries Studies
AgencyO>nwltalion
Finalize & File FERC Applicaion t~lli®
FERC Processing ~
Obtain OlherPennits & ROW's -~_&~
Design Access Road& Trans.Une w
Purchase & Deliver T -line Material
Final EnrjneeringDesign, Rest of Plan :~m~JJ•~-::::::· "'> •••• .. ~~~ .. ··.·:
Bid and Award Turbine,Gen. Contract
Manufacture Tu rtine,Generator
.. delkery-tiwl1
Bid aad Award Road l'.ontract
Road Contractor Mobilize
Construct Access Roadff -line
._, ..... ~~
Bid and AwardGen.Constr. Contract ®1 ~--:.··
Consuuclion ContractorMol:ilizes ~'!&'£~ ....... @
Jifllm oare low)
Consuuct Control Sill in River
Begin Intake & Powemouse Constr. ·-·-·"" . , WO<treSI.IIles5 96
Winter 1995 Job ShutdoMI ••
Work lM:>Uid resume May, 1!196 and start up would occur Nov.l 996.
H:\hyd\!azimina\sd:iedule.\W 3
APPENDIX
APPENDIX A
FROM IWILDER-~lN-OFFICe TO
WILDD. CONSTB.tJcriON COMJ"ANY
M 19839
Mr. Dan Thampson, p .:s.
BDR&gineerlng..Jnc.
SOO 108th Ave.nue Suite 1200
Bdlevue, WMlrington980Q4..S538
RE: Tamnma Hydroelectric Project
Dear Don.
<206 4537112:17 1994.12:17-28
In rc:tireo.ce to the letter sent to me on July 21, 1994, my .6ndiDgs are as follows:
1. I do see some problems with e:ava.tinga.40-foot deep treacb for a 42-incb peast
inc-Jude, but are not limited to:
• A high watertablema.y~ with~
• Prom tho 60il inCormsiiou &Wea. blasting will be required to l
exca.vatioD.
• Deep exca.vation in roek ma.y be daz:!Fous to wotkl:rs.
• Tbn::e ezcavators will he required to re:m.ovc mavated matJ:riai ft.
2. I om:aot fairly c:ompare the cost of tumlcU:ng/drilliog vs. c:xca.vatiD& bceau&e we do
work. The known cons of driiiiD& are as follows.
• DriDiag is cxpea.sivc compared to ~on.
• Drilled. pipdines are typic:a1fy off'ths m.nrlt by 10%. 'Illi& means that
feet ot a drllled 4&-iDcb. hole for a 4~ pemtook, the
approximately 3S-fcet from the proper dMfinatiou
3. The cost for =ca.vati.ng the 3SO.foot lang trench 40-foot deep with 114 ;1
approximately $22. 76/CY. I c:stimam that 9333 CY 'Vrill be c:rc:avated at a total
This cost does not include arry other work not specific:aily ~ 'IJ:u: total
include my COlt for mobilization to the aik:, supervisioa, boDdiug. iasurcmcc, etc.
&lopes wiJl Ot
of $212450.00.
also does not
4. I have no recomm.enda:tious far the~ needed. I am not fim1iliar v.dth this type rwort.
S. This project satmds very irJterestirl& aQd 'We do haw a sta1f ofpc:cple who~ filmiliar· · this type of
work.
I hope tbat these answers are hdpful to the design of :your project. Par further um · about clriiiing,
CODtac:;t .Atlas Drilling Company, Denali Drilling Company. of Alaska Road Borings. Tbank you for
contacting me 8lld if you ever have any :firture proj~ for whidt you would lila; to w some local
=:perieD.oe, plcue don"t hesitate to can me.
7£-
1etfezy s. Detmis,
Project Engineer
Wilder Coiistrw::tion Company
FROH : WIL.DER-HI=liN-OFFICE TO
O .. G.
'
ExeavCl~~ w'il\ kA\IC.. +o in l 2.o
' ct~+er dr:U i'!j E; ~e>o+~'0
,..~
=koo bctek ho>e.~ / br&., • .fw~ w~ll be.
C4~f t"oc..k Ot..o\ f J. #e. +r&\ch.
'h>r ~so" ct Trenc.\-J~
ctrr•ox-i ~"+f!.. ~..f <.cJdl
~ &.c.k t: H J e
. be, ~ 2.12. qso c.
-·
UNIT DESCRIPTION LABOR Ut"t:HA fiNG IIJVVNt:11::lHiP I HAUL MATERIAL SUBS TOTAL
fx7oo _,~~--
18'\0o 60
... -J2.ZS"Ooo
tJ)
'l .
~
I
Ill
(I)
...
1\1 " .. 0111 ...
212.qso 01
M r------~o~----------~------r-------7-----~r-----~r-------~------~----~-d~------~
rr;c.e, I~'( Y22 7' ~
r-----~------------1-------r--------r----~r-------l--------~------1--------1---------'
_____ c~ _________ .___ __ --ll..----~l-----L------'---__j-___ _,. ____ 1 ______ j ~
Telephone Conversation
Record
--6 8.b
!L.:..:.:Pro=iect:,__-+T.5oa~~:.r:lo!:· ~· _,.. __________ IProjet:tNo. 072SD-OO 3'1<fJ
I Time I Date 7/2.( /<;y
I Call to ~ F? Mk,
1 1
! L..::.::Ca~llfr=om_--!::Q:;.._,~~~~c:n.--~-----=----:c----
~~-.' 'Dr~ t/ -:..! . p;:; I s" "2. -z 3/2 Phone No.
I Discussion, Agreement and/or Action
ITEM
NO. DESCRIPTION QlY UNIT
1 Moblllzatlon and Damobili2ation 1LS
2 Clear Creek Diversion 1LS
3Giacler CraekOillerslon 1LS
4 k:cass Roads 1LS
5 32-inch pipeline CC to Bif 1 LS
' 8 32-inch plpeline GC to Bit 1 LS
7 32-lnch pipeline Bit to PH 1 LS
8 Constn.ct Powerhouse 1LS
9 lns1all Turbine/Generator 1 LS
10 Constn.ct Trans. Line 1LS
11 Environmental Pro111Ction 1lS
TOTALS 0
1 hermy certlftthatltleabovel$ a true andcorra::t sumrr
Prqa::t
Manager
Engineers Doyle
TOTAL TOTAL
$640,000 $330,000
$503,354 $319,000
$583,228 $374,000
$451,055 $316,000
$35,755 $23,000
$60,370 $51,000
$440,250 $3)1,000
$!:00,000 $450,000
$58,750 $224,000
$303,740 $358,000
$23,500 $3:1,000
$3,600,000 $2,854,000
BID DATE
OPENIIGTIME
LOCATION
SWMARY OF PACPOSALS RECEI\IED
FCA KIIG COw'E HYORCIB...EClRIC
Tango Glco
TOTAL TOTAL
$222,227 S3JO,OOO
$318,217 $458,568
$380,167 $411,572
$471,394 $518,760
$68,009 $100,314
$86,411 $62,1:20
$574,092 $383,418
$541,158 $509,648
$64,721 $50,000
$245,115 $483,575
$12,448 $3),000
$3,074,017 $3,315,975
February 24, 11114
11:00.00
HDR Engineering
Bra:: han
TOTAL
$624,000
$354,000
$381,000
$714,150
$23,100
$33,000
$325,000
$429,000
$57,000
$515,000
$81,000
$3,516,250
Wilder
TOTAL
$6)0,000
$400,000
$400,000
$846,000
$40,000
$60,000
$:1;0,000
$700,000
$70,000
$!i50,000
$12,000
$3,828,000
CCMPUTED BV:Bd> Butera
ITEM Engineers Doyle
NO. DESCRIPTION QlY UNITUNITPRICE UNIT PRO:
1 ClasS I Concrete, Inc I R, F. P Cf EA $1,000.00 $950.00
2 Clan II Concrete, Ce$t-ln -Place Cf EA $350.00 $450.00
3 steal Relnfo«: amant Bars LB EA $5.00 $1.50
4 Common E>eaw.tion Cf EA $4.00 $4.00
5 Rock E:cavatlal Cf EA $50.00 $10.00
6 F II Back!lll, Bedding Cf EA $3).00 $10.00
7 F/IBack!lll, Cia$$ B Cf EA $8.00 $7.00
8 F /I Backfill, Class C Cf EA $8.00 $5.00
9 F/1 Back!lll, ClasS D Cf EA $50.00 $10.00
10 F/1 Back!lll, ClasS E Cf EA $3:1.00 $8.00
11 F /IBack!lll, Sand Cf EA $:10.00 $12.00
12 F/118' Layer Riprap Cf EA $50.00 $:'0.00
13 F/124' Layer Alprap Cf EA $50.00 $3).00
14 Reyegetation AC EA $1,000.00 $11)0.00
15 tns1all24" CMP Culverts LF EA $60.00 $00.00
161nstell& FllletWeld 1-32' Pipa..blnt EA EA $!:00.00 $1,200.00
17 Fumlsh/lnstall Geolai<Uie Fllletr Fabric SY EA $:15.00 S4.00
18 Fumlsh Miscellaneous Metals LB EA $5.00 $4.00
19 Fumlsh/lnstell12' Cable Tray LF EA $15.00 $100.00
SWMARY OF PRCPOSALS RECEI\IED
FCA KIIG Co.IE H'I'DRCIELEClRIC
Tango Gllco Brechan Wilder
UNIT PRICE UNIT PRO: UNIT PRO: UNIT PRO:
$680.00 $775.00 $8.50 $1,000.00
$480.00 $725.00 $450.00 $6)0.00
$0.47 $0.70 $0.75 $0.90
$9.50 $15.50 $7.00 $10.00
$32.00 $132.15 $40.00 $al.OO
$18.75 $41.60 $18.00 $18.00
$16.00 $31.10 $12.00 $18.00
$15.00 $25.00 $10.00 $18.00
$21.25 $30.00 $24.00 $18.00
$18.75 $40.00 $:15.00 $18.00
$16.75 $43.40 $14.00 $al.OO
$47.50 $76.:20 $30.00 $30.00
$47.50 $72.50 $34.00 $30.00
$7,000.00 $1,000.00 $2,100.00 $5,000.00
$32.00 $34.50 $40.00 $50.00
$550.00 $8)4.30 $81!0.00 $:00.00
$U!5 $5.75 $1.80 $2.00
$2.50 $2.10 $1.50 $2.00
$30.00 $44.00 $35.00 $10.00
Southec-t Haskell Thompson-Mt Brice l<lewtttPacifld>K ConllaC'tlr! TIC
TOTAL TOTAL TOTAL TOTAL TOTAL TOTAL TOTAL AVERitGE
$400,000 $335,000 $11)0,000 $337,330 $847,000 $791,255 $632,357 $530,764
$:1;0,000 $387,448 saso.ooo $563,310 $400,000 $590,000 $624,735 $462,107
$400,000 $366,536 saso.ooo $559,148 $400,000 $620,000 $640,()44 $464,372
$:00,000 $826,560 saso,ooo $700,364 $400,000 $460,000 $6)0,620 $al6,969
$100,000 $152,320 $60,000 $511,873 $125,000 $:15,000 $45,704 $1'9,115
$100,000 $178,080 $60,000 $95,290 $125,000 $35,000 $74,773 $81,723
$580,000 $728,320 $450,000 $818,323 $!:00,000 $380,000 $380,869 $460,919
$:00,000 $424,882 $:00,000 $840,668 $:00,000 $6)0,000 $688,370 $540,311
$300,000 $143,536 $150,000 $111,255 $!:00,000 $:15,000 $138,577 $154,507
$630,000 $543,001 $150,000 $452,680 $:00,000 $900,000 $649,327 $506,225
$90,000 $62,640 $40,000 $62,764 $50,000 $10,000 $286,863 $64,811
$3,950,000 $4,118,323 $4,180,000 $4,280,045 $4,347,000 $4,416,255 $4,942,239 $3,901,842
Southec-t Haskell Thompson-Mt Brice Klawltt Pacifld>K ConllaC'tlrl TIC
UNIT PRICE UNIT PRO: UNIT PRO: UNIT PRICE UNIT PRO: UNIT PRO: UNIT PRICE AVERitGE
$6)0.00 $795.00 $11)0.00 $700.00 $700.00 $700.00 $1,428.00 $783.04
saso.oo $485.00 $400.00 $625.00 $200.00 saso.oo $813.00 $519.00
$3.00 $1.00 $0.80 $0.50 $1.00 $1.00 $1.21 $1.07
$4.00 $8.00 $5.00 $7.50 $3.00 $10.00 $8.95 $7.54
$15.00 $22.00 $18.00 $al.OO $5.00 $$.00 $25.00 $32.85
$:15.00 $22.00 $33.00 $18.00 $:15.00 $19.40 $14.25 $21.92
$12.00 $17.00 $11.00 $12.00 $18.00 $15.00 $17.00 $15.51
$10.00 $11.00 $11.00 $10.00 $12.00 $11.:20 $8.02 $12.19
$14.00 s:s.oo $13.00 $18.00 $21.00 $17.45 $18.40 $:10.34
$22.00 $33.00 $15.00 $16.00 $3).00 $14.50 $14.50 $21.40
$25.00 $33.00 $9.00 $18.00 $50.00 $22.00 $18.75 $23.66
$:15.00 $55.00 $45.00 $40.00 $3).00 $:15.00 $14.60 $37.38
$:15.00 $55.00 $50.00 $50.00 $35.00 $25.00 $14.60 $:S.88
$2,000.00 $$.00 $2,700.00 $1,500.00 $!:00.00 $5,000.00 $3,250.00 $2,575.42
$40.00 $88.00 $20.00 $100.00 $40.00 $51.00 $60.00 $49.46
$200.00 $6)0.00 $1,200.00 $3,400.00 $!:00.00 $:00.00 $166.00 $1'99.19
$3.50 $4.00 $1.00 $1.50 $1.00 $5.00 $2.33 $2.76
$3.00 $3.00 $2.00 $2.50 $3.00 $2.50 $3.25 $2.61
$40.00 $22.00 $125.00 $60.00 $20.00 $35.00 $62.00 $47.75
Item
No.
l
2A
2B
3A
ALT
3B
ALT
King Cove Hydroelectric Project
City of King Cove
Pricing Proposal
Unit
Description Est. Qty. Units Cost
Main Transmission Cable 90,000 LF $1740M
600 V Power Cable 4/0 A WG 8,000 LF 395M
600 V Power Cable 350 KCM 16.000 656M
Intake Structure Communications Cable 2,000 LF 2683M
6 pair 976M
Intake Structure Communications Cable 6,000 LF 3799M
12 pair 1846M
BID TOTAL (Items 1-4) ALT
Total Cost
$ 156,600.00
3,160.00
10,496.00
5,366.00
~;"0(7
22,794.00
11,076.00
$ 198,416.00
H¥.3. 284.00
. UNl:. HU~DRED NlNETY-l:.lGI:iT THOUSAND FOUR HUNVKEV SlXTl:.l:.N !JL!L
BID TOTAL (tn words) ONE HUNDRED EIGHTY-THREE THOUSAND TWO HUNDRED EIGHT-FOUR ~
Guaranteed number of days to complete delivery to City of King Cove dock of all materials
under this Contract Agreement is 84 calendar days from the date of Notice to
Proceed.
Exceptions to Specifications
LARS
OLLARS
Items 1,2A,2B meet specifications as required. Item 3A has a 60 Mil Hypalon
Jacket in lieu of 63 Mil. Item 3A-ALT has a PVC/Nylon Jacket. Item 3B has a
80 Mil Hypalon Jacket in lieu of 85 Mil. Item 3B-ALT has a PVC/Nylon Jacket.
Western States Electric will accept Items 2A,2B,3A,3A-ALT,3B,3B-ALT incre-
mentally with Item 1.
King Cove Hydro Supply of Cable
1422 130th Avenue NE
Bellevue. WA 98005
(206) 455-0234
July 27, 1994
John J. Snyder, PE
Senior Project Manager
HDR Engineering, Inc.
500 1 08th Ave. NE, Suite 1200
Bellevue, Washington 98004-5538
Subject: Tazimina Hydroelectric Project
1"""\ ..
( c 1"f.<~-lltZ.tM• 101... B. c
WEST
J,S~~·
D ~ .. ?'~
GROUP, INC.
Budgetary Price Quotations for Turbine-Generator Equipment
Dear Jack:
In response to your July 8 letter to Bill Holveck, I am pleased to provide the following
estimate.
Two -Horizontal shaft, Francis hydraulic turbines, each rated 350 kW at 900
RPM, with a net head of 85 feet, and 55 cts flow. These units would be
complete with synchronous generators, exciters, governors, stop valves,
switchgear, protection and control.
Lot net estimating price for two units $1,200,000
This price estimate assumes the buyers acceptance of t~e Terms and Conditions of
sale printed on the reverse side of this page.
Shipment would be FOB factory, with freight allowed to the port nearest the job site. It
is estimated that shipment could be made within 12 months of the date of an order
with approval to proceed with design and manufacture.
Expected turbine-generator performance curves are attached. This is a very small
machine, with a runner diameter of just 15 inches, and we dor:'t have a representative
outline to send you at this time.
Please let me know if you need any additional information or data.
Sincerely,
HYDRO WEST GROUP, INC.
I
~ct-Y~
Howard D. Sorensen, PE
Sales Manager
>-u m 75°/o
u
Ll..
TAZIMINA RIVER HYDRO, ILIAMNA, AK
TURBINE-GENERATOR PERFORMANCE
lli 7 Q 0/o +----'--'--
65%
25 30 35 40 45 50 55
TURBINE DISCHARGE (CFS)
60 65 70
400
350
300
250 5
n..
1:-
:J
200 °
150
100
-EFFICIENCY --...;-POWER HYDRO WEST GROUP, INC.
BOUVIER HYDRO NJ lt.L NO.
BOUVIER HYDROPOWER, INC.
1 OS Old Matawan Road • P.O. Box 997 • Old Bridge, New Jersey 08857 -· ... -.. . ··--. .. , _ _.;;...;...._ _ ___;:._ __
Tel: 908·390-1 ZJ4 • Fax: 90H-39Q-7790
July 12, 1994
HDR Engineering, Inc.
Suite 1200
500 lOBth Ave., N.£.
Bellevue, Washinqton 98004-5538
Attention: Mr. J. snyder
subject: Tazimina Hydroelectric Project
Dear Mr. snyder:
Hydro turbines & equipment
~-T;t:A,tMcNJf-B ~
,J ·~~
]_Tl--r--
p"' ~/,;~~
Thank you tor your recent inquiry requesting budgetary price and
technical information on hydroturbine equipment for the subject
application. Based on the site net head ana flow data submitted
with your FAX of June 14, 1994, we propose two horizontal Francis
type turbines each including a synchronous generator, and
hydraulic pressure unit (HPU) for actuation of the turbine wicxet
gates. Also proposed is a controls/switchgear package including
battery system and governor.
The turbine configuration proposed has the turbine runner mounted
onto a turbine shaft supported by two anti-friction bearings. A
flywheel can be mounted between the governor and draft tube
shafts. Alternative arrangements are also possible if such
better suit the site conditions.
The following data is submitted:
Turbine Type
Runner Diameter
Speed
Max. Turbine output
(@ 90 tt Net Head)
Runner Material
Wicket Gate Material
-
-
Horizontal Francis
450 1DJil
900 RPM
365 KW (55 cfs) each
Aluminum Bronze
Aluminum Bronze
THf VOfSt·ALPitH M.LI. GROUP
aouVIER HYDRO NJ TEL No.
Mr. J. Snyder
CL Runner to Tailwatar
Intake Type
Draft Tube Type
Turbine Performance at 90
output CKW) Efficiency
365
357
334
315
298
248
210
177
Generator Type
Generator Rating
89.0
90.0
92.0
92.8
92.0
88.0
85.0
82.0
-
Speed
Voltc.9e -
Temperature Rise
Power Factor
Excitation
ft
(%)
JuJ.y 12, 1994
4' above T.w.
Spiral Case
Elbow
Net Head:
Flgw (cfsl
55,.0
53.3
48.7
45.5
43.4
37.8
33.2
29.0
Horizontal Synchronous
350 KW (Nominal)
900 RPM
480 v
80° c over 4oo c Ambient
0.90
Brush less
our budgetary price tor the above equipment is as follows:
Turbines, HPus, Generators,
Governors, and Controlsfswitchqear -US$ 887,000
Prices are F.O.B. Jobsite and include any applicable import
duties. we have included for your refarance a preliminary
turbine outline drawinq. Delivery time tor the proposed
equipment is approximately 12 months after contract award.
R.QUVIER HYDRO NJ fi:.L NO. ';)UO ..);)U I I ;;)V ..... u. ...... _,I.,...._,
Mr. J. Snyder -3-July 12, 1994
The controls/switchgear will have full manual and
operation capability. Automatic restart after utility
included. Station service equipment, SCADA system,
power transformer are not included.
automatic
outage is
and main
The unit inertia requirements are dependent upon the expected
load changes and allowable frequency fluctuations. Because this
data was not submitted with your inquiry, no estimation of the
necessary flywheel effect could be made. Any needed inertia over
that inherent in the turbine runner and generator rotor would be
an additional cost.
Should you have any questions, please contact us.
Very truly yours,
BOUVIER HYDROPOWER, INC.
Wolf J. Kramer
enc.
cc Mr. R. Gore; Gore Electric Compnay
'ROUVIER HYDRO NJ f£L NO.
..
·' ~ -~
r--.-----· .~ ~t~ ~:,f ----J i
~ ~~~---1.
f·~. . .t•' r-----~--~·~· ~~· ~·;
CC-~ ~Z.Il"it;J.4-t-3. <...-
,J -c:;; N r~/1-., SULZER
BY OVERNIGHT COURIER
August 1, 1994
SED/sch
D_ ~~ ... -
HDR Engineering, Inc.
500 108th Ave. N.E.
BELLEVUE, WA 98004-5538
Attn: Mr. J. J. Snyder
Re: Request for Budgetary Price Quotations for
Hydroelectric Turbines and Generator Equipment
Tazimina Hydroelectric Project
Dear Jack:
Sulzer USA Inc.
~ 255 Pas: S:ree:. SCJ.:e SO
San Franc;sc.:;. CA_ g..:: C9
Fax ~~15l ~4~·886E
Pursuant to your fax inquiry of July 8, 1994 we are pleased to pro-
vide you with the requested information as follows:
2 Francis turbines, 2 x 350 kW, 27 m
2 Synchronous generators, 2 x 350 kW
2 Governor and process control cabinets
2 Low voltage switchgears with 1600 A breaker
2 Butterfly valves {ON 400)
Mechanical erection & commissioning
TOTAL
$ 595,000.-
$ 102,000.-
$ 93,000.-
$ 108,000.-
$ 30,000.-
$ 38,000.-
$ 966,000.------------
Above prices are for equipment delivered fob project site.
They do not include any local sales & use tax.
Electrical installation work as described on page 7 of 7 under
Section 4 is not included in our proposal.
The delivery time is about 13 to 16 months after order award
and clarification of all technical details.
-page 2 -SULZER
We shall be happy to provide you with any additional information
which you may require.
Yours sincerely,
~~S,_IN_C_·-------4 /
Edy o. Sennhauser
Enclosure
Proposal by SEWR/Compact Hydro
(415) 441-8868 (fax)
SULZERj
HYDRO
COMPACT HYDRO
CONTENTS:
Tazimina Project
Alaska
2*Francis Turbines, 2* 350 KW
Synchronous generator
1 -budget offer with separated prices
2 -turbine describtion & drawings
3 -electrical equipment & drawings
4 -prospects I photos
COMPACT HYDRO
SEWR, Bellut
-
Synchronous generator I....._.-_.-.--_,.........,..
COMPACT HYDRO
CONTENTS:
DESCRIPTION OF THE TURBINE
1 • Horizontal Francis turbine
1 . 1 Spiral casing and stay ring
1 .2 Base frame
1 . 3 Draft tube
1 .4 Wicket gate with adjusting mechanism
1 .4. 1 Generator side cover
1 .4.2 Draft tube side cover
1 .4.3 Stationary labyrinths
1 .4.4 Guide vanes
1 .4.5 Levers
1 .4.6 Oscillating regulating ring
1 .4. 7 Servo motor
1 . 5 Francis runner
1. 6 Shaft sealing (labyrinth)
1 . 7 Tools and special tools
COMPACT HYDRO
Bellut
Page 1 of 6
Synchronous generator
Compact . turbine
"FRANCIS"
i . Horizontal . Francis turbine
I HY 1J1{U
COMPACT HYDRO
The horizontal Francis turbine consists of the following main parts:
1 . 1 Spiral casing and stay ring
mainly consisting of:
-welded spiral casing plates
-parallel plates
-stay vanes
-support/suspension with connecting elements
-discharge with hand-operated shutoff valve
-pressure measuring connections
The spiral casing consists of several spiral plates, which are adapted to the pa-
rallel plates of the stay ring and then welded. On the upstream side, one wel-
ded-on flange provides the connection with the inlet pipe and/or the dismant·
ling piece to the shutoff valve.
Depending on its size, the stay ring is of welded or cast design and stress anne-
aled, whereby the generator side side plate forms an integral part with the cor-
responding turbine cover.
In individual cases the one-part spiral casing incl. stay ring can also be comple-
tely cast design.
The total turbine casing is firmly attached to the base frame by a shell-shaped
supporting arm and supported on it. The supporting arm is welded or screwed to
the generator sided parallel plate.
1 . 2 Base frame
The base frame is designed in steel welding construction and supports both the
turbine casing and the generator. Moreover the servomotor pressure oil supply is
flanged to the base frame.
COMPACI' HYDRO
Bellut
Page 2 of 6
~,··rl41iH .... l..:> 1 utuun ... u,-..)-IV J.\,. rv
Synchronous generator lH~U1<U
COMPACT HYDRO
The required anchoring material is included in our scope of supply.
The complete generator /turbine unit is preassembled in the workshop, fitted
onto the base frame, aligned and transported onto site. This reduces the site er-
ection time considerably and minimizes the border lines to other suppliers.
1 . 3 Draft tube
mainly consisting of:
-conical pieces
-bended pieces
-anchoring material (if required)
The draft tube is flanged to the downstreamsided cover and is assembled of co-
nical pieces and a bended pipe, which are screwed to flanges. .
Assembly and disassembly operations are reduced and faciliated considerably by
the easily detachable flange connections. According to local conditions, the
draft tube leds into the downstream channel.
1 .4 Wicket gate with operating mechanism
The wicket gate with operating mechanism consists mainly of:
1 . 4. 1 Generator side cover
The solid cover plate together with the generator side parallel plate of the stay
ring is made of one piece. It accommodates the guide vane bearings, the laby-
rinth rings and the shaft sealing casing.
1 .4.2 Draft tube side cover
The one-part, solid cover plate is attached to the stay ring and accommodates
the suction side guide vane bearings and the labyrinth rings.
1.4.3 Stationary labyrinths
The labyrinth rings are of one-stage and one part, and firmly attached to the co-
vers. The material selected guarantees a large hardness difference between the
stationary and rotating labyrinth rings.
COMPAcr HYDRO
Bellut
Page 3 of 6
Synchronous generator IHIUJ.<U .
COMPACT HYDRO
1.4.4 Guide vanes
The guide vanes with trunnions are cast of one piece or forged. All guide vane
bearin.gs, both radially and axially, are designed maintenance-free. Sealing to
the water channel is secured by 0-ring sealings.
1.4.5 Levers
The guide vane levers designed as shackles, are clamped onto the guide vane
trunnions and fixed into position during assembly. A disc screwed onto the trun-
nion prevents the lever from axial displacement.
The frictional connection is a safety coupling and prevents possible damage to
the guide vanes in the case of jammed foreign material. All guide vane levers
are connected by bolts with the oscillating regulating ring.
1.4.6 Oscillating regulating ring
The oscillating regulating ring is connected by bolts, which are run in mainte-
nance-free bushes, with the individual guide vane levers and simultaneously
supported on them.
1.4. 7 Servomotor
The wicket gate servo motor is double acting, controlled with oil pressure and
attached on the generator side cover. The piston rod is directly connected with
the oscillating regulating ring and operates the wicket gate via the lever posi-
tion. A feedback signal device is integrated into the servomotor.
1 . 5 Francis runner
The runner is welded or cast of one piece. The labyrinths are an integrated part
of the rim and crown. The Francis runner is statically balanced in the workshop.
The hydraulic thrust is relieved through boreholes in the runner hub. A form-fit
connection with feather transmits the torque directly onto the generator shaft
trunnion, which supports the turbine runner. The generator bearings are dimen-
sioned accordingly. The runner is fixed axially onto the shaft trunnion by means
of the screwed-on hood.
COMPACI' HYDRO
Bellut
Page 4 of 6
-J.J.W.l~J,...) .&.U.&.I.,n.U""',.J'-..,.1-..IU£'*"''
Synchronous generator I .til Ul<U
COMPACT HYDRO
1 .6 Shaft sealing
A labyrinth sealing prevents the operating water emerging from the shaft and
the generator side cover. The small leakage cools the labyrinth. The leakage
quantity is centrifuged into the sealing housing by a slinger ring and flows off
naturally through an adequately dimensioned pipe. Supply of sealing water is not
necessary.
1 . 7 Tools and special tools
The delivery comprises general tools for maintenance and special tools for
assembly and disassembly of the parts supplied.
COMPACI' HYDRO
Bellut
Page 5 of 6
Tazimina 2 horizontal Francis turbines
Prototype efficiency versa output at net head H = 25,91 m
Tailwater: 146.61 m Turbine shaft: approx. 149.1 m
Prototype-Data
D2 =518 mrn
Dd =600mrn
Dz =621 mrn
n =900/min
efficiency 11 [%] discharge Q [m3/s)
92~----~------.-----~------.-----~------.------.------.------r------r------r------rl.S
90
82
78
76
I
I --------r---------,....1
1.6
0.8
0.4
74+-----~--~~r-----~------r-~--~----~r-----~~--~r-~~~----~------~-----+O
0.10 0.15 0.20 0.25 0.30 0.35 0.40
output P [MW]
Sulzer Escher Wyss Ravensburg HT817 K.Sclunid 2Q-JUL-1994 8212 200
-.& """""'•""'.a.w _., ~" v•••wv,-_._.v """" • •
Synchronous generator
Inlet Valves
I HYDRO
COMPACT HYDRO
The Francis Turbine will be equipped with an Inlet Valve.
The turbine inlet valve (600 rnm butterfly valve) will be designed to
close safely and reliably under all normal and emergency conditions,
including closure against maximum runaway discharge.
The turbine inlet valve will be operated by an oilhydraulic servomotor.
Oil supply unit is integrated part of valve drive. Closing action will
be effected by a weight.
Upstreamsided the valves will be connected to the penstock by a flange
connection.
Downstreamsided a dismanteling piece will be provided for erection and
dismanteling purposes.
Please find a typical design of valves in the annexed brochure.
COMPACf HYDRO
Bellut
Page 6 of 6
c
0
. . . .
" 'i a "' <
~
" < , ::
L
c
':'
~ . , . . -:; , • L
.0 .
"
i ..,
c , .. c
;!
' < I : < •: . .. .
• §
' : . ., .. c , ...
l:
! : ... • • ' . ,. . J-;
' 0
I o
• .-g
; ~
; !
< .
1
"' c ,
::
' !
c .
0
Q.
L . .,
0 ....
c • ..,
' • .: .
L • .
"' .
..:
0 • ' • c . .,
0
L
rX·
~
c
!
.c;
!
;;:
" L . >
c • "' c
~ :;;
c .
~ ., . ,
N
c 0 -r-A
~~ I f " (\J
.r---1 fij
_J 0 .. ~ .LA I
I
f r-~"1 ~ ~~~~~~ I , I r0~ ~ co
" I~ \ ,.!1.-,~!llll""'; !)
!"'f'
i ) --; ~ ~ ~ I
t: ~ ...-f--I''· .J I • r--. ~ *.
I t ?-~ w I ~ I~ ~I I F
I
1 ..
I
-I 0 5 =1 , 9•02 FAKTORS F~~ TURBINE-DIMENSIONS BASED
ON RUNNER-02 (APPROXIMATELY)
FAKTOREN FUER TURBINENABMESSUNGEN E
1: ., BEZOGEN AUF LAUFRAO-¢ D2 {ALLES CA . MASSE)
c 0 ., .. ., SERIE A B c 0 E F G
1 3, 7•02 4,2•02 0:!•2+2,5· 2. 5•02 5•02+3,5. 4•02 2.5•0~
~~ c I 2 3,4•02 4•02 02•2+3111 2. 5•02 5•D2+3m 4•02 2.5•02 fF rrnrn a~ 11J,;JI-~~ ~'-I no 1{,.. I'\ 3 3.2•02 3,9•02 02•2+3m 2,4•02 5•02+3m 4•02 2,0•02
I 'r :lm 4 3•02 3,6•02 02•2+3,511 2. 5•02 5•02+2,511 I 4•02 2 .5•02 I ,.L I ~ ':! '\,,J I ~ ,... lm'1r l A
OUt: - -
Eml
T I
• ~ ./ SCHMID 29.06.9t MASSE MEKO 3 NACH AUSLEGUNG KORRIGIERT -----,
Au•ru•hrvno li>do· -O.tuo Vt.,. {)-Ut•t•U• ~I~ ~b.,.~tn I No•• O~tu• a•n•h•tot ! SPENGLER 30.11.9 p3.12.93!_ I I ! Seh••t ••-
BUEREN
t•chn lach ~ C.tatdnet O.tuo Gootuoft I o.•uo L c. ........ I Oatuo I Vts. ()-motell• I Dot"' i
l<on•trvktt<~ S.,. St~tl•1• I ntht f()-tg,Moso••ci> 1:50 e ·i' I
CDMPUTERZEICHNUNG c:::JM···· ••nd ... , •·•r•""'"" M ..... rt---.. J~N ~SNSNW~ u-...-. z.,~ I
•rfo••uno•b\att nl.'lleh2v••l••n ~ Aulf~ , ......... ~"lm''" ........... ~ ........... -........ 8::..-.:;.-:: _ 1 o9o3s3 HA P AB SU N ~.;, ~ I
l
uobor 1°·5 "1 3 30 1120 1400 1000 200~C:WO• 000• ~.t:;:. ••• !'.'!::.:.:.:.:;;;• • COMPACT FRANCIS COMPACT -FRANCIS (r.ou r_. j
••• 3 6 20 400 1000 2000 4000 000 2000 6000 ...... ~:;·,::::·. ....... I I I· ...... "*i""".,;.l Zul~ Ab•. t0,1 t0.1 tO.:? tO~J t:0.5 t0~8 t1.2 t2 tJ t4 t5 t6 AU••••t'"to(.,..,.n .. r~.~.,.
1 J F'-Jer NennMdst:e <0.5 vnd > .. 000 •tnd •ntapraehend& Grent .. o••• nteht ~~~:"'••'••.,-•'""lrttto"•" ... e-., ~ ~ W'Y!illl 0 3 88 8211 058
In OIN ISO 2766 T•fl 1 f'•stnalet~t. DJNe70f11f3Kt .. u8F' I I
..111111.... ~~~ -~~~~~ ~~82.11 058 I :?5. . . PLOT AN I BUEHREN HT81 3
I ·" 1. 1':_ JUL 1994 09: ,,.16 .. -··--
2*Francis Turbines, 2 * 350 KW
Synchronous generator
1 n 1. .u .1'-v
COMPACT HYDRO
Description of the Complete
Electrical Equipment
To supplement the mechanical equipment Sulzer-Escher Wyss
Ravensburg also provides to the customer the complete electrical
equipment to operate the powerstation savely.
This offer includes following electrical equipment:
1. 0-Generator
2. 0-Turbine control cabinet
3. 0-24 V DC supply
4. 0-Generator control and
protection cabinet
5 . 0-Motor control center
6. 0-Installation, errection and commissioning
The turbine and unit control system each unit is independent from
the funktion of the other stations .Necessary communication between
the stations will be handle by wired signals.
All delivered mechanical and electrical components are
dimensioned, organized, tested and commissioned by Sulzer Hydro.
COWACf HYDRO
Bellut
Page 1 of 7
2*Francis Turbmes, 2 "'_;;,o K w
Synchronous generator I HYDRO
COMPACT HYDRO
1 I 0 Generators
This tender includes a power generating system which is based on a
syncronous generator.The generator is a low voltage generator
(400 V,50 Hz) with roller bearing. The manufacturer is
Co I Hit zinger Power, Austria, a very expirienced generator manufacturer
with an extensive reference list.
1.1 generator data sheet :
rated output
class of rating
power factor
rated voltage
winding connection
voltage variation
frequency
speed
over speed ( 5 min.)
class of insulation
protection
cooling
forme
bearing
437 KVA I 350 KW
s 1
0,8 I lagging
480 v
star-to 4 terminals
+1-10 %
60 Hz
900 RPM
1784 RPM
class F -
IP 23
IC 01
IM-B3
roller bearing
efficiency at rated voltage and cos
phi 0.80
414
314
112
standards
95,3
95,4
94,8
IEC 34-1 I VDE 0530
1.0
96,2
96,3
96,0
COMPAcr HYDRO
Bellut
Page 2 of 7
2*Francis Turbines, 2 * 350 KW
Synchronous generator IHYDkO
COMPACT HYDRO
Turbine Control System
2 , 0 Turbine control Cabinet (lay out see annex No. 2-1)
Turbine Governor system DTL 95
The digital control system DTL 95 allows a reliable control of the
turbine,to main the operation constant at the preset setpoint. The
system incorporates the experience gained in many descades of designing
and manufacturing governors for hydroelectric turbines, and is a mature
high-quality turbine governor system providing a maximum ease of
operation to the user.
Detailed information to the system hard-and software are given in the
enclosure prospects:
1.-DTL 525 CONTROL AND GOVERNING
CONCEPT FOR DOUBLE REGULATED TURBINES
2.-APPLICATION-WATER TURBINES CONTROLLED AND
REGULATED BY DTL 5 25
3.-DTL 515 -FEATURES-USER CONFIGURABLE DIGITAL
TURBINE CONTROL SYSTEM
4.-DTL 525 -USER CONFIGURABLE DIGITAL
TURBINE CONTROL SYSTEM
The governor voltage signals are defined between 0-10 d.c., the
current signals between 0 and 20 rnA. A reliable governor power supply,
if required battery backed for continuity, is essential for a proper
governor performance.
The governor is programmable via software modules which are entered in
SPL (Sulzer Programming Language) .
COMPACf HYDRO
Bellut
Page 3 of 7
2*Francis Turbines, 2 * 350 KW
Synchronous generator I HYDRO
COMPACT HYDRO
The basic functions among others include applications for the following:
opening limiting
level control
speed control
load control
discharge flow control
startup slope
joint control
The PID characteristic is individually programable.
Our tender covers 4 of the aforementioned basic functions.
Process control
The unit process control, automatic start up and shut down program,
temperature monitoring, interlocking, fault indication and monitoring
will be treated also by the Sulzer DTL control sytem.
All turbine values (speed and guide vane position are processed by
digital working transducer and transmitted in separate shielded cables.
Binary signals like limit switches,position switches,pressure and level
switches will be processed via a 2 cable bus system from turbine
location to the process system DTL 95.
Turbine o.perating panel WI:
The turbine control system will be operated over micro soft key
contacts and a menue leaded monitor system.
All turbine values (turbine speed,water level,guide vane position,
temperatures etc.) will be indicated on several pictures on the
monitor screen .Also feedback signals as well as fault alarms will be
indicated on this scre~n.A printer is installed to record fault
situations.
CO:MPACf HYDRO
Bellut
Paqe 4 of 7
2*Francis Turbines, 2 * 350 KW
Synchronous generator
..., '-'.L.I~.L.J ...... I HYDRO
COMPACT HYDRO
Speed Measuring and Monitoring System
The toothed rim provided on the turbine shaft allows measurement of the
impulses recurring at a frequency governed by the shaft speed which are
transmitted direct digital to the process system DTL 95.Speed limited
contacts for the process control will be set by the DTL,speed indication
be shown on the MMI monitor screen picture.
Headrace Water Level Controller
To allow for its long actingtimes the headrace water level controller
is made as a PI controller. Proportional amplification and integration
time constant are functions of the dynamic action of the headrace.
Trip Action
In response to a trip action the setpoints of the position control
circuits independent from the gate limiter position are reset to zero,
and the turbine closes. The trip action can be initiated locally on the
turbine control .panel by pressing the red EMERGENCY BUTTON.
Operatin2 Mode Selector Switch ;
A key-locked switch with 4 control positions will be provided.
Position A -automatic control operation
Position B -manual control operation
Position 0 -safety OFF position
Position F -spare
COMPACI' HYDRO
Bellut
Page 5 of 7
2*Francis Turbines, 2 * 350 KW
Synchronous generator
3.0 ·· 24 V-DC-Power Supply
IHYUl{U
COMPACT HYDRO
The D. C. power supply is designed for feeding the turbine control-,
generator protection systems and measurements devises. The nominal
voltage is 24 volt and is backed by batteries with 2*120 Ah capacity.
In addition it concludes per unit:
.-1 battery charger-AC-DC converter; 21 A,24 V -DC
-1 DC voltage instruments
-1 DC current instruments
-1 terminal block for 220 V input voltage
-terminal block for 24 V output voltage
-24 V fuse double pole fuse distribution
-1 monitoring module with alarm contacts
-1 battery frame
This DC system is not designed to feed other auxiliaries like
DC pumps or other DC power equipment.Each unit is provide with an own
DC system.
4. 0 Generator control Cabinet
The generator control cabinet contains all generator instrumentation,
the generator voltage.controler,the cos phi controler,the synchronizing
devise and the generator protection relais.
This offer includes. the generator protection relais:
1 Over/undervoltage relay
1 Over/underfrequency relay
1 Asymetrical relay
1 power reverse protection
1 Grid identification relay
1 overcurrent-time relay
1 short circuit protection
COMPACT HYDRO
BeUut
Page 6 of 7
2*Francis Turbines, 2 * 350 KW
Synchronous generator
ltl}:UKU
COMPACT HYDRO
Following electrical values of the generator are indicated by
instruments :
-active power
-3* generator current instruments
- 1 generator voltage,selectable by switch
cos phi indication
- 3 double indication instruments for synchronization
5. 0 Motor control center-MCC
The motor control center (MCC) for the station auxiliary control
is placed in the generator control cabinet.
480 V, three-phase A.C. and 280 V A.C. outgoing branch circuit for:
-Governor oil pump 1 , 3 ph, 50 Hz, 20 A
-feeder for upstream butterfly valve,3 ph,20 A
-generator stand still heater
-DC supply
-feeder for powerhouse sub distribution,63 A
-spare feeder 1, 3 ph, 25 A
-spare feeder 2, 3 ph, 25 A
-spare feeder 3, 3 ph, 25 A
6. 0 Electricaly installation, errection and commissioning:
The cableing and installation of all control and power cable is not
included in this offer.
The internal earting system of the electrical installation as well
as the earthing of all metall installed part inside the power house
is not includet in this offer.
The installation of powerhouse ligthing system is also not in the scope
of Sulzer Hydro supply.
This works can be offer optionaly by SEW based as a supervisor job or
exclusive done including material delivering by SEW-staff.
. COIVIPACT HYDRO
Bellut
Page 7 of 7
layout of turbine control cabinet· front side
o·
MMI
DO DO
DO
"'-----"'j D D
00000 D D
[Q] 0
emergency operation mode
off key switch
/
600
...._ _____ ..,/
..,__ ____ 800
~--------------~ Annex 2-1
Rv, 19.7.1994
HP 811, Bellut
HA2211
Layout of the turbine control cabinet-inside
onnlgg inggming
nluas;
1· guide vane feed-
back
· 2 • turbine speed -n-
4. temperatur measu-
rement
anolog out; going VA-
l.uu.o.
~. guide vane con-
trol
digital I/0
1. 48 digital inputs
2. 4 8 diqi tal outputs
I
DC-cabinet light
:ITB modules
for transmition of non time
criticalyanalog und binary
feedback signals via bus
system.
door contact control
800
Annex 2-1
heater
thennomete:r
SULZER
turbine control system
DTL X -95
digital contro~ system
~
l.water level control
2.speed control
3.position control
4. emergency stop funk-
tion
S.compl.au~omatc control
6.temp monitoring
7.interlocking
Rv, 19.7.1994
HP 811, Bel-
lut HA 2211
Layout or turbine control cabinet, generator protection and generator breaker cabinet
1~1 ~ § § 18][8(8la
••••••
[!] [2] ~
, ... , , ... , , ... , , ... , , ... ,, ... ,
generator protection
excitation
synchronizing
MCC
.. 800nun .. .. 800nun .. -4 800nun ..
2400nun
mrbine-comrol generator-conlrol generator
cabinet cabinet breaker cabinet
DC rectifier 600A
SULZEJRIHYDJRO
C.II.Bellut
19. Juli 199
preliminary sinele line diaeramm for erid parallel operation
I Tazimina, Alaska
I grid-3/N/PEN/480 v /60 lli
U<
I>, I»
-=----
®-----
440KVA
900RPM Jl
synchronouse ~
lli:i l.·ie;p:···;::~?;i:;············· ·.·.·.· .·.··············[~!i~Ji\li:ll:!ji
tl •• 2 x generator bearing temperaturs :::
·. 3 x generator stator temperaturs ;;:
i.ndication, alarms, shutdown-contacts I
·F
1\120 Ah
governor oil
pump drive
m
..I.. .,.
-F l , -F i
~,dzeriHydro
Compact Hydro, BELLUT, HA 22 l 1
19.7.1994
24V,21A=
-F -F ,
220V
20A
220V
20A
Nr. 1 Nr. 10
220 V and light distribution
·F
i ,
APPENDIXB
I.N .N. Electric Cooperative
Newhalen, Alaska
PRELIMINARY
TAZIMINA HYDROELECTRIC PROJECT
DESIGN CRITERIA
HDR ENGINEERING, INC.
Revision Pages
No. Date Prepared By Reviewed By Ap_proved By Affected
Draft 8/8/94
TAZIMINA HYDROELECTRIC PROJECT
DESIGN CRITERIA
TABLE OF CONTENTS
SECTION I-GENERAL DESIGN CRITERIA
1.0 INTRODUCTION .................................. I-1
2.0 REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-1
3.0 GENERAL DESCRIPTION OF FACll.lTIES . . . . . . . . . . . . . . . . . . I-2
4.0 MATERIALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-3
4.1 Unit Weights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-3
4.2 Concrete . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-3
4.3 Reinforcement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-4
4. 4 E.arth and Rock . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I -4
4.5 Steel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-4
4.6 Timber . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I-4
SECTION ll -DIVERSION AND INTAKE
1.0 INTRODUCTION .................................. ll-1
2.0 REFERENCES .................................... ll-1
3.0 DESCRIPTION OF FACIUTIES ......................... ll-1
4.0 HYDRAUUC DESIGN CRITERIA ........................ ll-2
4.1 General Project Operation ....................... n-2
4.2 Design Maximum Water Sm:face Elevation ............ ll-2
4.3 Nonnal Maximum Water Surface Elevation ............ ll-3
4.4 Minimum Operating Water Surface Elevation ........... ll-3
4.5 Design Flow ............................... ll-3
4.6 Intake Submergence .......................... ll-3
4. 7 Minimum Instream Flow ....................... ll-3
4. 8 Fish Screen and Trashrack Velocity . . . . . . . . . . . . . . . . . ll -4
TABLE OF CONTENTS CONTINUED
~
5.0 STRUCTURAL DESIGN CRITERIA ....................... ll-4
5.1 Crest Elevation of Diversion/Intake Structure ........... ll-4
5 . 2 Design 'Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . n -4
5.3 Foundation Bearing Pressures ................... , ll-5
5.4 Stability ................................. ll-5
SECTION m -PENSTOCK
1.0 INTRODUCTION ill-1
2.0 REFER.ENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ill-1
3.0 PENSTOCK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ill-1
3.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ill-1
3.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m-1
3.3 Design 'Loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m-2
4.0 THRUST BLOCKS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ill-4
5.0 ELBOWS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m-5
6.0 PENSTOCK APPURTENANCES . . . . . . . . . . . . . . . . . . . . . . . ill-5
6.1 Manholes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . m-5
6.2 Air Release and Vacuum Release Equipment ill-5
6.3 Leak Detection Stem . . . . . . . . . . . . . . . . . . . . . . . . . ill-6
1.0 TR.EN'CIDNG ....................... , ............ m-6
SECTION IV-ROADS AND SITE DRAINAGE
1.0 INTRODUCTION ................................. IV-1
2.0 REFER.ENCES ................................... IV-1
3. 0 ACCESS ROADS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV -1
4.0 SITE DRAINAGE ................................. IV-2
. TABLE OF CONTENTS CONTINUED
SECTION V -POWERHOUSE
1.0 INTRODUCTION .................................. V -1
2.0 REFERBN'CES .................................... V-1
3.0 GENERAL DESCRIPTION OF FACIUTIES .................. V-1
4.0 TURBINE/GENERATOR .............................. V-1
5.0 PLANT CONTROI..S ................................. V-1
5 .1 l.oad Controls . . . . . . . . . . . . . . . . . . . . . . . . . . . . . V -1
5.2 Back-up Power ............................. V-2
5.3 Other Powerhouse Equipment .................... V-2
6.0 POWERHOUSE STRUCTURE .......................... V-3
SECTION VI-TRANSMISSION LINE .......................... VI-1
1.0 INTRODUCTION ................................. VI-1
2.0 REFERBN'CES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . VI-1
3.0 GENERAL DESCRIPTION OF FACILITIES . . . . . . . . . . . . . . VI-1
GENERAL DESIGN CRITERIA
SECTION I
1.0 INTRODUCTION
This document presents the genentl design criteria to be used in preparing preliminary and
fmal designs of the diversion/intake structures, penstock, powerhouse, transmission line and
access roads. Section I presents genentl design criteria to be used for these project facilities.
Sections ll, m and IV present specific design criteria for the diversion and intake, penstock,
and roads and site drainage respectively, and should be worked in conjunction with the genentl
criteria in this section. Design criteria for the powerhouse, powerhouse equipment,
switchyard and transmission line are covered in Sections V and VI.
These design criteria are to be qsed as the basis for preparing detailed design drawings,
calculations, and specifications. Layouts and designs developed with this criteria will be used
by HDR to prepare construction cost estimates.
2.0 REFERENCES
Design engineers should also refer to applicable information contained in the following
documents:
1. Feasibility Report: Tazimina River Hydroelectric Project, Stone and Webster
Engineering Co. for Alaska Power Authority, 1987.
2. Tazimina River Hydroelectric Project Feasibility Study, HDR Engineering, Inc.
for INNEC, May, 1991.
3. Bristol Bay Regional Power Plan Detailed Feasibility Analysis, Interim
Feasibility Assessment, Stone and Webster Engineering Co, July, 1982.
4. Site contour mapping developed by HDR and Stone and Webster Engineering
Co.
5. FERC's "Engineering Guidelines for the Evaluation of Hydropower Projects."
6. Considerations in the design and operation of Hydro Power Intakes, C o I d
Regions Hydrology and Hydraulics, 1990.
7. " Design and Operation of Shallow River Diversions in Cold Regions",
Engineering and Research Center, U.S. Bureau of Reclamation, Sept., 1974.
8. U.S. Geological Survey, Stream flow data for Tazimina River, gage
#15299900.
1-1
3.0 GENERAL DESCRIPTION OF FACILITIES
The proposed powerhouse site is located near El. 485 on the left bank of Tazimina Falls about
6.7 miles from the Newhalen-Nondalton Road and about 20 miles from the village of
Newhalen. A new transmission line would be buried along a new 6. 7 mile access road to the
tie-in point to an existing 7.2 kV transmission line that runs along the Newhalen-Nondalton
Road.
The new facility will generally consist of an intake on the river about 350 feet upstream of
the falls, a penstock to carry the diverted water to the powerhouse, and a semi-underground
powerhouse constructed in the cliff near the base of the falls, housing two 350 kW francis
type turbines and synchronous generators.
The intake structure will be constructed along the river bank to divert 110 cfs from the river.
The design will allow future expansion, if desired, for up to a diversion flow of 220 cfs
without modifications. A short (2 to 3 foot high) channel control sill will be installed in the
river to help prevent any future erosion of the river bed and also to help move the water
channel over near the intake during low flow periods. The intake structure will include
provisions for a trash rack, shut-off valve, sediment flushing and exclusion of floating ice
from the intake. From the intake, flow will be conveyed in a 60-inch pipe to a fish screen
structure. The fish screen structure will be designed to lower flow velocities to about 0.5 fps
to prevent impingement of fry against the screen, and to divert (bypass) fish back to the river.
Rocks and sediment carried into the screen structure will be sluiced through a sluice pipe and
discharged back to river downstream of the falls. Negotiations with resource agencies are
ongoing that might eliminate or reduce the need for fish screening, and if so, the screen
requirement could be dropped later. Screen design should provide flexibility to easily address
future design changes. Because of cost considerations, the intake and pipeline are designed
to allow future flow increases to 220 cfs without modification. The fish screen structure,
however, is designed for only 110 cfs and would have to be enlarged to accommodate higher
flows in the future.
From the fish screen structure, water will follow a conveyance pipeline (penstock) following
a slope sufficient to maintain hydraulic flow to the powerhouse. The pipeline will be buried,
and has capacity built in to allow a future design flow of 220 cfs.
The penstock will be installed in a "slot" cut into the face of the steep cliffside leading down
to the base of the falls. This slot will also be cut large enough to accommodate transmission
lines and communications cables, as well as a large capacity elevator that will provide
operations and maintenance access to the powerhouse.
The powerhouse will consist of a cavern cut into the cliff face large enough to house the
turbines, generators and control equipment. The room shall be made large enough to
accommodate larger units up to 1.4 MW total capacity in the future (two 350 kW units
replaced with two 700 kW units). The open end of this room facing downriver will be closed
. in with cast-in-place concrete. Water will exit the powerhouse through a tailrace opening over
a tailrace wall that will hold minimum tailwater elevation at about 15 feet above the normal
falls tailwater level.
I-2
The generating units will be designed for fully automatic shutdown and for one-button start-
up. The plant shall also be designed with a SCADA system that will allow remote monitoring
of the plant from the village over telephone lines. An 8 ton crane will be provided for
maintenance use and to help move equipment to the elevator for removal. Enough floor space
will be provided inside the powerhouse to allow disassembly of the turbine.
The transmission line will be buried along the gravel access road to the Newhalen-Nondalton
Road. The line will be three phase 260 mil 25 kV EPR insulated concentric neutral cable
direct buried along the new access road, a minimum of 4 feet deep. The line will be operated
at 7.2 kV, 3 phase, 60 Hz. kWh metering will be provided at the powerhouse. Splices will
be in sectionalizer vaults. A multi-pair shielded telephone type communications cable will
be buried along with the transmission line to provide voice and SCADA communications. An
additional 4 miles of this telephone cable will need to be installed along the Newhalen-
Nondalton Road to reach a tie-in point to existing cables (total telephone cable length 10.7
miles).
4.0 MATERIALS
4.1 Unit Weights
The following standard unit weights shall be used, where applicable.
4.2 Concrete
Water
Steel
Concrete
Wood
Ice
Snow
Backfill
62.4 pcf
490 pcf
150 pcf
45 pcf
5 kips per linear foot
20 pcf
120 pcf, internal angle = 36 degrees (prelim.)
The analysis and design of new reinforced concrete structures shall follow the latest revision
of ACI Code 318 and applicable sections of ACI 350. Reinforced concrete structures shall
be analyzed on the basis of the theory of elastic frames, but design of a section shall be
carried out using the ultimate strength design method.
Concrete used for the project shall achieve a minimum compressive strength of 3000 psi at
28 days. Lean concrete for pipe slurry bedding (if used) will have a minimum l 000 psi
compressive strength.
Cement used for the project shall be Type I or II confonning to ASTM C 150.
1-3
4.3 Reinforcement
Reinforcement detailing will be perfonned in accordance with the ACI Manual of Standard
Practice for Detailing Reinforced Concrete Structures. Reinforcement shall confonn to the
requirements of AST.M A 706, Grade 60.
4.4 Earth and Rock
Engineering properties for earth and rock, including allowable temporary and pennanent
excavated slopes, will be detennined by the geotechnical consultant. Reference should be
made to their fmal report when it becomes available.
4.5 Steel
Steel members shall be designed in accordance with the Specification for the Design,
Fabrication, and Erection of Structural Steel for Buildings, and the Manual of Steel
Construction published by the AISC. Structural steel and miscellaneous steel will comply with
the following AST.M requirements:
Structural Steel Shapes, Plates and Bars
Structural Steel Tubing
Aluminum Members
Bolts
Grating
Checkered Plate
Handrail
Stainless Steel
A36
A500 Grade B
B209
A193, Grade B8 or better
A36 or Aluminum
A108 Grade 1016, 1018, 1019
AI 20 Std. Wt.
A304 (ANSI 18 Cr 8 Ni)
Exposed metal surfaces will be hot dip galvanized or stainless, except for gates and valves.
All exterior stairs, and checkered plate will be hot dip galvanized in accordance with AST.M
A123. All exposed bolts, nuts, and washers will be type 304 stainless. Gates and valves will
be painted with zinc chromate and a corrosion resistant paint. ·
4.6 Timber
Timber used for structural purposes shall be treated West Coast Douglas Fir, designed in
accordance with the UBC and American Institute of Timber Construction (AITC).
1-4
1.0 INTRODUCTION
DIVERSION AND INTAKE
SECTIONll
This section presents the hydrnulic, structural, and mechanical design criteria for the diversion
and intake structures.
2.0 REFERENCES
. 1. U.S. Army Corps of Engineers. "Hydrnulic Design Criteria".
2. U.S. Department of Interior. "Guidelines for Determining Flood Flow
Frequency.,. Bulletin #17B. September 1981.
3.0 DESCRIPTION OF FACll..ITIES
The diversion/intake structure will be a cast-in-place concrete gravity structure approximately
18 feet high by 12 feet long. River bed elevation at the intake is approximately 574ft. msl.
Normal water surface elevation is approximately el. 575. Maximum use of local materials
should be made to minimize concrete volumes. The intake will divert up to a maximum of
110 cfs with the capability to increase diverted flows to 220 cfs for future increased
hydroelectric power generation without modification.
The intake will include provisions for sluicing bedload, preventing debris and ice from
entering the penstock with a trashrack and shutting off the entire flow with a slide gate type
valve. The crest elevation of the river bed erosion control sill will be approximately El. 576.
Electrical power and control signal cables will be run from the powerhouse to the intake.
Design snow depth at the intake is six feet.
A fish screen structure will be located downstream of the intake to provide fish screening and
sediment sluicing capability.
Basic requirements of the intake and fish screen structure are as follows:
1. The diversion and intake will be concrete gravity structures.
2. Bedload is expected to accumulate in the basin in front of the intake structure
and occasionally may enter the intake and fish screen structures. The intake
will need to be kept clear of obstructions to maintain the designed hydraulic
capacity. To help keep the intake free of obstruction, an uncontrolled
sluiceway slot will be cut into the bedrock front of the intake. A sluicing pipe
arrangement will also be included.
Il-l
3. A steel trashrack with 1 1/2-inch vertical bar spacings will be installed to keep
floating debris from entering the intake. Provision will be made for installation
of pressure differential measuring instruments.
4. A small (approximately 20' x 24') utility building with power and small shop
facilities will be included near the intake to provide a maintenance and storage
area.
5. A slide gate will be installed to shut off flow to the penstock and allow the
penstock to be dewatered. The gate will be capable of operating remotely and
manually. Gate guides and stems, and other exposed hardware shall be
stainless steel. An air vent will be designed downstream of the shut-off gate.
Gate operators will have metal security enclosures.
6. The diversion and intake facilities will be designed with future maintenance in
mind. Principal maintenance tasks are expected to be:
Lubrication of the intake gate stem and guides.
Lubrication of motor operators.
Removal of sediment deposits in intake box.
Removal of sediment deposits in front of intake structure to maintain
unrestricted flow to the intake.
Removal of floating debris against trashracks.
7. Mounting pads and other provisions shall be provided for future addition of
trash rack automatic cleaning equipment if necessary.
8. Project facilities shall be designed against potential vandalism. For example,
hinges shall be concealed, bolts tacked down and solid covers provided over
openings in the intake deck. OSHA standards shall apply. Fencing will not
be installed entirely around the diversion/intake, but a safety fencing and
handrails, etc. will be provided as necessary.
4.0 HYDRAULIC DESIGN CRITERIA
4.1 General Project Operation
The project will be operated in a run-of-river mode. Fluctuation of the water levels in the
river are beyond the control of the plant, and all expected water levels must be accommodated
in the design. ·
4.2 Design Maximum Water Surface Elevation
The intake will be designed to be stable for factors of safety presented later in this document.
The design maximum water surface elevation will be based on the 100-year instantaneous
flood of----cfs as determined by HDR. The height of the operating deck will be set at the
11-2
design maximum water surface elevation plus 2 feet. (Note: blank data to be developed and
filled in during fmal design)
4.3 Average Annual Maximum Water Surface Elevation
Average Annual Maximum Water Surface Elevation at the intake structure will be determined
based on available stream flow data and hydrologic analysis. For design, this elevation is -
----msl.
4.4 Minimum Operating Water Surface Elevation
Flow from the intake will be controlled by the wicket gates on the turbines. Water surface
at the intake will be monitored by a level sensing device that sends a signal to the powerhouse
turbine. The device will be programmed to send an alarm when the water surface is about
to drop below the minimum n~sary to insure enough water to operate the turbines. The
powerplant will be shut down when the water surface elevation drops below the Minimum
Operating Water Surface Elevation. The minimum operating water surface elevation will be
elevation -
4.5 Design Flow
The penstock will be sized to convey a maximum flow of 110 cfs to the turbines, with
provisions to increase that flow to 220 cfs in the future.
4.6 Intake Submergence
The intake invert will be set based on an article by J.L.Gordon (Water Power, Aprill970).
The equation is:
s = CVD0·5
Where, S = Elevation difference between minimum operating elevation
and crown of intake, FT
C = 0.4 (for lateral approach flow)
V = Velocity of flow in pipeline, FPS
D = Diameter of pipeline, FT
4. 7 Minimum Instream Flow
No minimum instream flow releases at the diversion/intake structure will be necessary. For
a major percentage of the time, river flows greatly exceed the flow amount being diverted for
power generation. Provisions will be made to measure penstock flow rates at the powerhouse.
IT-3
4.8 Fish Screen and Trashrack Velocity
Maximum flow velocity through the trashrack shall not exceed 3 fps at 220 cfs. The trashrack
will be designed to withstand full differential pressure across the rack. Fish screens will be
designed for 0.5 foot per second approach velocity based on net flow area for a flow of 110
cfs.
5.0 STRUCTURAL DESIGN CRITERIA
5 .I Crest Elevation of Diversion/Intake Structure
The crest elevation of the channel control sill will be 576.0
The penstock invert elevation at the intake will be 567.0
5.2 Design Loads
The diversion and intake structures shall be designed to resist overturning and sliding in
accordance with PERC's "Engineering Guidelines ... ", including references. The diversion
structure shall be analyzed for four loading cases, 1) Nonnal operating, 2) Flood, 3) Nonnal
operating with earthquake, and 4) Construction.
5.2.1 Hydrostatic Pressure
Hydrostatic levels shall be as detennined by the hydraulic design criteria.
5.2.2 Uplift Pressure
Uplift will be assumed to act over 100 percent of the area and to vary as a straight line from
the maximum differential between headwater and tailwater.
5.2.3 ~quake
:Equivalent static earthquake inertia forces will be computed using a horizontal acceleration
in accordance with the UBC for Zone 4. Vertical seismic loads are assumed to be zero.
Importance factors for the intake and powerhouse structures shall be 1.25, all other structures
1.0
5.2.4 Ice and Snow
The magnitude of pressure exerted by ice sheets against the dam and intake structure shall be
assumed to be 5 kips per linear foot. Snow loads shall be detennined in accordance with
Section 2347 of the UBC.
ll-4
5.2.5 Silt
For detennining the pressure against structures caused by silt, the unit weight of silt shall be
85 pcf for computing horizontal pressures and 120 pcf for computation of vertical pressures.
5.2.6 ~ FTessures
Lateral earth pressures on retaining walls and other backfilled structures shall be detennined
from the fonnula:
Where, F = Horizontal earth pressure
K = Coefficient of earth pressure
K.clivc= (to be detennined)
K.t .-= (to be determined)
~ivc= (to be detennined)
w= Unit weight of soil plus groundwater, pcf
H = Height of soil, ft.
5.2.7 Wind Load-per UBC, Basic wind speed 110 mph, exposure D
5. 3 Foundation Bearing Pressure
Design bearing pressures will be detennined by the geotechnical consultant.
5.4 Stability
Structures will be designed to meet PERC-specified factors of safety as shown below for each
of the following load cases:
Case I-
Case ll-
Case m-
Case IV-
Nonnal Operating Condition
*Water elevation nonnal maximum
* Silt loading
Flooding Condition
* lOD-year flood level
Earthquake Condition
* Same loads as Case I plus earthquake loads using static seismic
coefficients.
Construction Condition
* Construction completed with no water behind diversion structure
* ~quake forces appli~ as in Case ill
ll-5
5.4.1 ()verturning
The stability of a structure against overturning will be governed by the location of the
resultant of all loads acting on the structure. The location of the resultant must fall within the
diamond-shaped "kern" defmed by the equation:
S = 0.5-Y/L + 0.5-XIW
Where,
5.4.2 Sliding
S = Parameter defming kern boundaries. When S = 116, the entire base
is in compression.
Y = Distance from either side to location of resultant.
L = Length of base.
X = Distance from toe to location of resultant.
W = Width of base.
For structures on rock, stability against sliding will be determined by the shear-friction factor.
Q = CA + (W-U) tan ci>
H
Where, Q = Shear friction factor
C = Cohesion value of concrete on rock, psf
A = Area of base considered, sf
W = Sum of vertical forces (except uplift), lb
U = Uplift forces, lb
tan ci> = coefficient of internal friction
H = Sum of horizontal forces, lb
Minimum factors of safety will be 2.0 for Case I, 1.25 for Case IT, and 1.1 for Cases m and
IV.
For structures on soil, the sliding coefficient "f' is defmed as follows:
f = H/V
Where, H = Summation of all horizontal forces
V = Summation of all vertical forces
"r' should not exceed the following values for normal loading conditions:
On Gravel 0.50
On Sand 0.40
IT-6
5.4.3 Flotation
Vertical forces shall exceed the following values:
1.5 times the uplift forces for Case I.
1.25 times the uplift forces for Case ll.
1.1 times the uplift forces for Cases m and IV.
ll-7
1.0 INTRODUCTION
PENSTOCK
SECTIONm
This section presents the design criteria to be used as the basis for preparing detailed design
drawings, calculations, and specifications for the penstock and thrust blocks.
2.0 REFERENCES
1. American Institute of Steel Construction. AISC Manual of Steel Construction,
8th Edition.
2. American Association of State Highway and Transportation Officials
(AASHTO). Standard Specification for Highway Bridges.
3. American Water Works Association. Steel Pipe Design and Installation ·M-11.
4. American Iron and Steel Institute. 1983. Welded Steel Pipe, Steel Plate
Engineering Data Volume 3.
5. American Iron and Steel Institute. 1984. Steel Penstocks and Tunnel Liners,
Steel Plate Engineering Data Volume 4.
6. American Iron and Steel Institute. Steel Plate Engineering Data Volume 4.
1992. Buried Steel Penstocks.
3.0 PENSTOCK
3.1 General
The penstock will extend from the intake to the powerhouse and will be about 450 feet long
total length. The penstock will be of steel construction and will be buried. Other possible
materials for the penstock will be evaluated during final design. The size of the penstock
shall be 60 inches in diameter. The penstock will be equipped with manholes, air release
valves, air and vacuum valves, and thrust blocks as necessary. Exterior penstock surfaces
will be protected by a polyethylene tape coating system in accordance with AWWA C214,
similar to the Polyken 80 mil system. Interior penstock surfaces will be protected by a 16 mil
DFf coating of coal tar epoxy in accordance with AWWA C210. Installation of cathodic
protection will be decided by the geotechnical consultant and HDR later.
3.2 Materials
Penstock steel shall confonn to ASTM A139C, D, orE having minimum yield strength of
42 ksi, 46 ksi and 52 ksi, respectively. The potential use of galvanized corrugated metal pipe
shall also be investigated for portions of the penstock. The penstock will have lap welded slip
ill-1
joints for its entire length. The penstock will be specified to include in the scope of supply
all appurtenances and bulkheads required for field hydrotesting of the completed penstock.
3.3 Design Loads
The penstock will be designed to resist internal, external, flotation, one half vacuum, and
water hammer loads, and hydrostatic testing to 125 percent of static head.
3.3.1 Shell Stress Due to Internal Pressure
S = PD/2t
Where: p
D
s
t
=
3.3 .2 External Loads
Internal pressure = -rwh/144 in psi
1'w = Unit weight of water, 62.4 pcf
h = Static head of water in feet
Penstock diameter; inches
Stress in the pipe wall psi
Shell thickness; inches
Steel pipe wall thickness shall be determined by the Spangler deflection formula. Deflection is
calculated using the following equation:
Where:
4,. = D1 (kW r)/(EI + 0.061 E' r)
A,.
Dt
K
w
r
E
I
E'
-
-
-
-
-
-
-
-
Maximum allowable horizontal deflection of pipe
Deflection lag factor = 1.0
Bedding constant = 0.10
Soil load on pipe, lb/lineal inch of pipe
Radius of pipe, inch
Modulus of elasticity for pipe = 30,000,000 psi
Moment of inertia of cross section of pipe wall, inch4/lineal inch of pipe
wall = tl/12 (t=wall thickness,in.)
Modulus of soil = 1,500 psi (or as determined by geotechnical
consultant)
Maximum allowable deflection shall be limited to 2 percent of penstock diameter.
3.3.3 Soil Load Determination
Soil load on the pipe shall be determined by the soil prism theory using the formula:
W = -yHD/12
m-2
Where: w
"'(
H
D
--
-
-
Vertical soil load on pipe, lbs/inch
Soil unit weight, pcf
Height of fill over pipe, feet
Outside diameter of pipe, feet
3.3.4 Live Load Detennination
Live load on pipe shall be checked for two cases:
1. AASHTO HS20-44 truckload as specified in AASHTO HB-12 "Standard Specification
for Highway Bridges" on minimum earth cover with the pipe empty.
2. A 15-ton wheel load (front end loader) on minimum earth cover with the pipe empty.
Assume the wheel footprint is 10 inches by 20 inches. Maximum bearing pressures
for a track-mounted hoe will also be investigated.
3.3.5 Minimum Handling Thickness
D+20 t---
400
Where: D
t
3.3.6 Buckling
Penstock inside diameter inches
Shell thickness; inches
Buckling shall be calculated in accordance with ANSIIAWWA C950-81.
Allowable buckling pressure = qa
qa•(_!_) X (3~ B1E 1 EI )liZ
FS D3
The summation of external loads will be less than or equal to the allowable buckling pressure:
We qa >y jl.., + Rw D + P,
m-3
Where: FS = 3.0
D = Diameter of pipe (in)
Rw -Water buoyancy factor = 1 -.33 <hw/h)
h -Height of ground surface above pipe (in)
B' -1/1 +4e(-0.65H)
H -Height of fill above pipe (ft)
B -30 x 1<1 psi
I -w/64 (D0
4 -D1
4) inch4
Do -Outside diameter (in)
D· -Inside diameter (in) I
hw -Height of water above top of pipe (in)
We -Vertical soil load on pipe Qb/in)
Pv = 7.1 psi
'Yw = Specific weight of water = 0.361 lb/in3
B' -1,500 psi
3.3.7 Vacuum
Vacuum loads shall be equivalent to an internal pressure of one half atmosphere (7.35 psi
absolute).
3.3.8 Flotation
The penstock will be stable for uplift with a factor of safety 1.5 for an inspection condition
where the pipe is completely empty and the surrounding soil is in a fully saturated condition.
3.3.9 Waterhammer
The design maximum internal dynamic pressure rise due to waterhammer will be SO percent
above maximum static head. Turbine design shall take this into account.
3.3.10 Temperature and Thermal Loads
Thermal loads associated with expansion and contraction of exposed penstock will be
calculated based on maximum and minimum air temperatures of 80 cp and -40 cp' respectively.
4.0 THRUST BLOCKS
The penstock will be designed to resist thrust loads on the pipe at bends by gravity and
friction along the base or by the use of thrust blocks where necessary. The geotechnical
consultant will provide allowable bearings for foundation materials for use in thrust block
design. The powerhouse thrust block will be designed to resist the load on the guard valves
and pipe bends just upstream of the turbines. Anchor rings will be designed for thrust blocks
to accept dead-end thrust.
Hydrostatic thrust at bends will be calculated according to the following equation:
m-4
T-2xyxHxAsinll{l
Where: T -Thrust force (kips)
'Y = Unit weight of water, 0.0624 kip/fr
H -Head on the penstock centerline (feet)
A -Area of the pipe (sq feet)
.(.\ -Deflection angle of bend (degrees)
Hydrodynamic thrust at bends will be calculated according to the following equation:
T -1.41 p VQ(l-cosA)lfl
Where: T -Thrust force (lb)
p -Density of water, 1.94 slug/ft3
v = Water velocity, ftl sec
Q -Flow rate (ft3/sec)
s.o ELBOWS
Elbows for bends in general will have a minimum radius of seven pipe diameters and will be
fabricated in accordance with A WW A C208. The maximum deflection per joint will be 6
degrees. Miter ends will have a maximum deflection angle of 5 degrees. Elbows will be two
piece through 22.5 degrees, three piece through 45 degrees, four piece through 67 .) degrees,
and five piece through 90 degrees.
6.0 PENSTOCK APPURTENANCES
6.1 Manholes
Insulated pre-cast manholes will be used to access manways on the penstock. Manway
function will be incorporated with air-vac valves. Manholes will be installed o~y at air
release or vacuum breaker locations, as this should provide sufficient access . manholes.
Manholes will be flanged nozzle-type conforming to A WW A C208. Manhole openings will
be provided with permanent blind flanges. Manhole lids will be made with fairings flush with
the top of the penstock.
6.2 Air Release and Vacuum Release Equipment
Air and vacuum release facilities will be designed at the intake structure and at the abrupt
change in slope downward in the profile along the pipeline to permit the release of air that
may accumulate during filling of the pipe and to admit air into the pipe during draining or if
negative pressures occur in the pipeline.
m-5
Release facilities will be designed to withstand and function under design pressures as
applicable. Nozzles or openings for valves will be designed in accordance with A WW A
C208. All air valves will be installed with a shutoff valve on the pipeline side and will be
installed in insulated pre-cast manholes. (need to evaluate if heat is necessary)
6.3 Leak Detection System
A leak detection system will be designed to close the penstock shut-off valve in the event of
a major pipeline leak. Design and programming of controls to perform this function will be
byHDR.
7.0 TRENCHING
The penstock will be in a cut-and-cover trench having a bottom width a minimum of 3 feet
wider (18 inches each side) than the pipe outside diameter to allow space for the pipe zone
material to be compacted. Trench depths will be 6 inches below the grade of the outside
bottom of the penstock to provide a uniform bedding support for the entire length. Bedding
will be compacted 114 inch minus angular or river run material. Backfill for the pipe zone
material will be. well graded crushed stone or gravel and will be placed to a height of 1 foot
above the pipe. Backfill may also be lean concrete in specific areas. A minimum soil cover
of 4 feet will be provided.
Trench details will show power and communication cables to be installed along with the pipe.
Trench cutoffs will be installed at regular intervals or as needed to handle trench drainage.
m-6
1.0 INTRODUCTION
ROADS AND SITE DRAINAGE
SECTION IV
This section presents design criteria for the Access Roads and Site Drainage. It covers the
design of pennanent access roads, service roads, small creek crossing, and site drainage for
the entire project. Layouts and designs developed with this criteria will be used to prepare
construction cost estimates.
2.0 REFERENCES
1. U.S. Department of Commerce National Engineering Handbook Section 4,
Hydrology. August 1972. ·
2. American Association of State Highway and Transportation Officials
{AASHTO). Standard Specifications for Highway Bridges. Latest Edition.
3.0 ACCESS ROADS
A pennanent access road will be constructed extending from the existing Newhalen-Nondalton
Road about 6. 7 miles to provide access to the powerhouse.
To the extent possible, access roads will be aligned to minimize cost and environmental
impact. The access roads will be used for construction and maintenance and the design speed
limit will be 20 mph. These roads will be limited access roads, and will not be designed to
DOT highway standards.
The access roads will be pennanent all-weather roads. The access road will be approximately
35,400 feet long. The access roads will have a minimum 16-foot traveled way and will be
surfaced with suitable crushed rock or gravel. The road bed will be raised slightly above
surrounding grade for drainage and to help it blow clear of snow in winter. Road width will
be widened at horizontal curves to allow trucks delivering pipe and other equipment to
negotiate each curve. Every 2,000 feet or at strategic locations, turnouts will be provided.
Grades will be limited to a maximum 15 percent. Curves will have a minimum radius of 65
feet. Maximum excavation slopes will be 3/4H:IV in soil and 1H:4V in rock, but are subject
to revision following results of geotechnical investigations. Excavated slopes will be benched
where the vertical depth of excavation exceeds 20 feet. Retaining walls will be installed to
reduce backs lope cuts where appropriate. Maximum fill slopes will be 1.5H: 1 V. Drainage
ditches and culverts will be installed to carry runoff from the roads.
Road surfacing material will be crushed or native rock having a maximum aggregate size of
2 inches. Surfacing materials will have a minimum thickness of 6 inches. The surfacing will
be sloped to drain.
IV-1
4.0 SITE DRAINAGE
4.1 Ditches
Drainage ditches will have a minimum depth of 18 inches and a minimum slope of 2 percent.
Runoff velocities will be limited to 3 feet per second where no annor protection of the ditch
is provided. Appropriate annor protection will be designed where velocities exceed 3 feet per
second.
4.2 Culverts
Culverts will be comagated metal with a minimum diameter of 18 inches. The minimum
depth of cover over culverts will be 12 inches. Culverts will have slopes of at least 2 percent.
4.3 Peak Flow Rates
Flow rates produced by stormwater runoff from small drainage areas will be determined by
the Rational Formula:
Q =CIA
Where: Q = Peak Flow, cfs
C = Runoff Coefficient, 0.5
I = Rainfall Intensity, 1.8 inlhr, (25-year)
A = Drainage Area, Acres
4.4 Conveyance Sizing
Drainage ditches will be sized for the calculated runoff flow rate for the area drained. Sizes
will be determined by Manning's Equation:
Where:
AJ(Jil -Qn
1.49 s112
Q =Flow Rate, cfs
N = 0.024 for ditches
R =Hydraulic Radius = AlP, ft
A = Area of Flow, sf
P = Wetted Perimeter, ft
S = Slope of Ditch, ft/ft
Culverts will be sized and designed in accordance with Reference I. Manning's roughness
for comagated culverts will be 0.024.
IV-2
1.0 INTRODUCTION
POWERHOUSE
SECTIONV
This section presents design criteria for the powerhouse and related powerhouse equipment.
It covers the design of the powerhouse structure, turbine generator, auxiliary equipment,
indoor switchgear and controls. Layouts and designs developed with this criteria will be used
to prepare construction cost estimates.
2.0 REFERENCES
3.0 GENERAL DESCRIPTION OF FACll...ITIES
The powerhouse will consist of a room cut into the cliff face large enough to house the
turbines, generators and control equipment.. The room shall be made large enough to
accommodate larger units up to 1.5 MW total capacity in the future. The open end of this
room facing downriver will be closed in with cast-in-place concrete. Water will exit the
powerhouse through a tailrace opening over a tailrace wall that will hold minimum tailwater
elevation at about 15 feet above the normal falls tailwater level.
The generating units will be designed for fully automatic shutdown and for one-button start-
up. The plant shall also be designed with a SCADA system that will allow remote monitoring
of the plant from the village over telephone lines. An 8 ton crane will be provided for
maintenance use and to help move equipment to the elevator for removal. Enough floor space
will be provided inside the powerhouse to allow to disassemble the turbine to perform a
runner removal.
4.0 TURBINE/GENERATOR
The turbines for this project will be two francis type horizontal shaft units. Flywheels will
likely be included with the units to improve stability and reduce waterhammer problems. The
draft tube outlets will exhaust into a chamber below the powerhouse floor where an artificially
high tail water elevation is maintained by a tailrace overflow weir, allowing the powerhouse
floor to be set up well above waterfall tailwater level. The rated synchronous generator
output will be 350 kw each at 0.95 powerfactor, 480 volts AC, 60Hz. A wicket gate position
controller will be provided, either electrically or hydraulically operated. A speed governor
will also be necessary when the unit is operating isolated from any other generating source.
S.O PLANT CONTROLS
5.1 Load Controls
Two levels of load control will be provided. The primary load control system would be used
when the entire power system of the villages is being carried by the hydro plant. It would
be used to operate and load the turbine. This level of load control would consist of an
V-l
. electronic voltage and frequency control system that would control transmission line voltage
by turning on and off a series of resistance heaters mounted in a water tank. This tank could
be located just outside the powerhouse and use a small amount of river water to continually
flush through this tank, or it could be located elsewhere in the system. If, for example, the
village was using 350 kW of power, but the turbine was generating 400 kW, line voltage
would begin to rise. The load controller senses this rise and begins to tum on heater coils to
"waste" the excess 50 kW of power to control line voltage. As loads vary, heater units are
turned on and off. This method of control simplifies turbine controls, since wickets gates
don't have to move to follow loads, they can be just set in one position (above system load
needs) and left there.
The second load control method will be a programmable controller based load control
program that will maximize plant output based on available water. Headwater level signals
will be used to open or close wicket gates in response to availability of water from the
intakes. A load limiter could be set to "block load" the turbine output to any pre-selected
level that uses less than the total available amount of water. In this arrangement, the hydro
plant would be synchronized to an energized transmission line and would follow transmission
line voltage as controlled by the village diesel plant. This load control mode will be necessary
at times the village diesel plant is generating part of the power being used in the system.
For example, the machine can be set at 112 load and it will stay at this output as long as there
is enough water to operate at this load. This "block loading" method of load control would
be useful when the village wants to control the power system from the village diesel plant and
not enough power is available from the hydro plant to carry the entire system. If water levels
drop, the level control system would cut back turbine output and the diesels would have to
pick up the load.
5.2 Back-Up Power
A small diesel back-up generator {approx. 30 kW) with diesel storage and day tanks will be
provided to provide power during any extended outage and to keep station batteries charged
during outages. Field flashing or some similar method will be used to bring the generator on-
line for isolated operation. Station batteries will provide DC control power and an inverter
will provide AC power for critical functions such as computer power supply.
5.3 Other Powerhouse Equipment
Other powerhouse equipment that will be included in the design includes:
8 ton Rated Portable Crane
Building HV AC
Lighting
Switchgear, including metering, protective relays, synchronizing equipment, breakers,
Pfs and CTs
Neutral Grounding equipment
Communications equipment
Drainage and oily water separator
V-2
6.0 POWERHOUSE STRUCTURE
The powerhouse would consist of a semi-underground cavern cut into the face of the rock cliff
near the base of the falls. The room would be large enough to house the turbine generators,
switchgear, controls and also provide some maintenance laydown area. Rock excavated for
this room may need rock bolts or shotcrete installed to provide long term stability. The room
will be made large enough to accommodate two larger 700 kW units to replace the 350 kW
units in the future. The powerhouse floor elevation will be selected to be from 10 to 15 feet
above nonnal tailwater at the base of the falls to avoid having to dewater the powerhouse site
during constn,~ction and to provide better operating conditions during winter icing conditions.
The penstock and the access elevator will come down the cliff !ace in a slot excavated in the
rock down to the powerhouse. The elevator will provide enough capacity to handle removal
of equipment for maintenance in the future.
V-3
1.0 INTRODUCTION
TRANSMISSION LINE
SECTION VI
This section presents design criteria for the transmission line. It covers the design of outdoor
switchgear and transformers at the powerhouse end of the line, the buried transmission line,
associated vaults and communications lines. Layouts and designs developed with this criteria
will be used to prepare construction cost estimates.
2.0 REFERENCES
1. Letter from Power & Control Engineering to INNEC, dated 7115/94, from
Robert E. Dryden.
3.0 GENERAL DESCRIPTION OF FACILITlES
Power from the plant generators will be generated at 480 V AC. Indoor switchgear will be
installed in the powerhouse. Main leads will run up to the surface at the top of the falls to
a main step-up transformer rated 7200/480 V, 3 Phase, approx. 1000 kVA. It may be
possible to locate the main transformer inside the powerhouse, and this will be investigated.
The transmission line will be buried along the gravel access road to the Newhalen-Nondalton
Road. The line will be 260 mil 25 kV EPR insulated concentric neutral cable direct buried
along the new access road, a minimum of 4 feet deep. The line will be operated at 7.2 kV,
3 phase, 60 Hz. kWh metering will be provided at the powerhouse. Splices will be in
sectionalizer vaults, spaced approximately 4000 feet apart (total of 10 sectionalizers). A
multi-pair shielded telephone type communications cable will be buried along with the
transmission line to provide voice and SCAD A communications. An additional 4 miles of this
telephone cable will need to be installed along the Newhalen-Nondalton Road to reach a tie-in
point to existing cables (total telephone cable length 10.7 miles).
In order to allow the new plant to perform "coldu start-up, it may be necessary to install some
additional switches or reclosers at various points in the existing INNEC system. These
switches would allow parts of the system to be turned off while other sections are brought on
line in sequence. This would avoid having to pick up the entire system load instantaneously.
The need for this equipment will be determined later.
It may be necessary to install some power factor correction condensers in the system. This
will also be confirmed later.
As part of the plant load controls, it may be desirable to identify some system loads that could
be dispatched on or off at any time, such as water heaters, etc. These loads could be fitted
with automatic relays that would turn them off and on in response to system voltage, and they
could be used to supplement the resistance heater load control system. The need for these
additional controls will be determined later.
VI-1