Loading...
HomeMy WebLinkAboutAkutan Site No. 4 for Alaska Power Authority 1980AKU 010 AKUTAN CORPS OF ENGINEERS SITE NO. 4 FOR RL:CEIVED ! /l,~R G !, 19SG ,,~ASKA POWER AUTHORITY ALASKA POWER AUTHORITY Ll YCOPY BY R. W. RETHERFORD ASSOCIATES INTERNATIONAL ENGINEERING CO., INC. ~lARCH 1980 PROPERTY OF: Alaska Power Authority 334 W. 5th Ave. Anchorage, Alaska 9950t APA18/D Report to: Subject: Date: Weather: Alaska Power Authority Akutan C. of E. Site No. 4 Hydro Potential February 21, 1980 Snow with brief periods of sunshine Gusty winds Temperature@ 10:00 A.M. 22°F The stream flow near the mouth was measured to be 14 cfs on February 21, 1980 (Photo #1). The stream meanders through a relatively broad flat valley at a fairly uniform gradient to elevation 80 (aneroid barameter reading); a straight line distance of about 1.5 miles (Photos 2 & 3). The flow at elevation 80 was estimated at 3 cfs on the above date. The gradient steepens rapidly between elevation 80 and the summit at elevation 420 (Photo #4), a straight line distance of about 0.5 miles. There was no perceptible flow above elevation 250 (Photo #5). At elevation 200, the flow was approximately 1 cfs. Numerous springs and seeps appear along the stream bank between elevations 80 and 250 (Photo #6). Several small streams and seeps appear along each side of the valley floor between sea level and elevation 80 with the largest flowing about 2 cfs into the valley from the southwest about one mile from the head of the bay. It was reported by the Akutan Village Chief that the stream sup- ports a large pink salmon run in the first mile of the stream. Although no commercial use is made of the pink salmon in the area, the people of the village use the stream for sport and subsistence fishing. A powerhouse below elevation 80 would not be feasible as only 1 foot of head would be gained for each 100 feet of additional penstock. An intake structure at elevation 200 with an average estimated flow of 1 cfs and a powerhouse at elevation 80 would produce about 7.5 kW of power. A transmission line 3.25 miles in -1- APA18/D length would be required to deliver the power to the Village of Akutan. Because of the low flow, impracticable reservoir storage, salmon run, and transmission distance; this stream is not a viable hydro- electric site for the Village of Akutan. The Corps of Engineers Site No. 3 was examined and the power avail- able and development costs were found to be a valid assessment. Site No. 2 was evaluated and a slight modification from the Corps Report was made. From field observation it was determined that an additional 100 feet of head could be obtained by installing two diversion structures with an infinitesimal loss of flow. Using the Corps of Engineers assumption of 5 cfs as being good flow estimate for a run-of-river site, a capacity of about 105 kW is available. The tentative development scheme for Site No. 2 is as follows: 1. The run-of-river project would consist of two intake struc- tures at approximate elevation 300 to divert the water down the 1900 feet of 12-inch penstock. Transportation of con- struction materials to the site would be by highline due to the steep terrain and the total lack of any roads or vehicles. The diversion structures would be constructed of sheet pile. The powerhouse would consist of a modular unit containing either a single or double runner impulse turbine and generator with a maximum capacity of 200 kW and all required switchgear. The energy produced by this unit would be transmitted by 0.7 miles of 25 kV URD cable submerged across Akutan Harbor and 0.5 miles of wood pole transmission line to Akutan. -2- APA18/D Preliminary Cost Estimate for Site No. 2 Item Mobilize and Demobilize Diversion Structures Penstock (12 11 di a. ) Pre-packaged turbine generator, etc. (200 kW) Transmission Line (1.2 mi.) Substation Subtotal Contingencies 20% Engineering Supervision & Administration 16% Total Cost $ 500,000 125,000 200,000 275,000 75,000 35,000 1,210,000 242,000 1,452,000 232,300 $1,684,300 The above represents a tota 1 capita 1 cost of $8,420 per kW of installed capacity. The following are annual costs including operation and maintenance for a 50-year project life. Interest Annual Total Annual Rate Pa~ment O&M Cost 2% 53,645 2500 56,145 5% 92,300 2500 94,800 6-7/8% 120,090 2500 122,590 9% 153,610 2500 156,110 The following table portrays the cost per kWh based on various interest rates and an amortization period of 50 years. Two figures are given for each interest rate with one assuming that all power -3- APA18/D produced during the months of July through November would be util- ized and 60% of the available power is assumed to be utilized during the rest of the year. The second figure represents 100% utilization. Percent Amortization Interest Annual Utilization Period Rate Cost 100% Jul-Nov 50 yrs. 2% 56,145 60% Dec-Jun 100% year around 50 yrs. 2% 56,146 100% Jul-Nov 50 yrs. 5% 94,800 60% Dec-Jun 100% year around 50 yrs 5% 94,800 100% Jul-Nov 50 yrs. 6-7/8% 122,590 60% Dec-Jun 100% year around 50 yrs. 6-7/8% 122,590 100% Jul-Nov 50 yrs. 9% 156,110 60% Dec-Jun 100% year around 50 yrs. 9% 156,110 Respectfully submitted, Ga;zf,£~17 Carl H. Steeby, P.E. Principal Civil Engineer Robert W. Retherford Associates CHS:ng Acknowledgments: Mr. Luke Shelikoff, Chief-Akutan Village Plant Manager Craig Cross and Crew of the Western Sea - a tanner crab processing vessel - Cost $/kWh 0.080 0.061 0.134 0.103 0.174 0.133 0.221 0.180 who were kind enough to provide food, lodging and a skiff to the head of the bay. Enclosures: Photographs. -4- APA18/D PHOTO NO. 1 Stream near mouth at West end of Akutan Harbor. Flow measured at 14 cfs on 2-21-80. PHOTO NO. 2 c • C' .. Westerly view from Akutan Harbor. Summit of main stream channel is shown in approximate center of photo. The large mountain in the background is not in the watershed. -5- APA18/0 PHOTO NO. 3 Easterly view toward Akutan Harbor from approximate elevation 80. PHOTO NO . 4 Upstream view of main stream channel taken at elevation 200 showing summit at elevation 420. -6- APA18/D PHOTO NO. 5 Easterly view of valley from elevation 250. There was no flow at this elevation on February 21, 1980. PHOTO NO. 6 Upstream view of main stream channel at elevation 200. Flow estimated at 1 cfs on February 21, 1980. Note springs and seeps along stream channel. -7- . , ~· . , "' " ' .. 0• ~ ,, ·I " ,. ~ .. , . tu I~ '0 ~ .. '" " ·~ '1 .. " ~ " .. / -(~ J ,· . / ( r ~~ /' 1.%\ ., -+ I ' ' I . • f ' ' ' ,,.. : / -. \ \ j ,/ :_..--\~ { ( :,: ~ 1 / ', I I 1 ' ' ' \ ''-.__ I ,' •, ', \ \ ·~-------' J I ' ' ' ' --. ,' . ,' ', ".\ \ ., ,. .. v• . .. .... ' til ) : . ... ·• . -._ .. ,.~: .. /~ .. ·· ,' ... ~, .· .. ;_ . ; .. ' ' ·. '/ ·. .... ;· "'"'·, '" / ~·-. , , . ••· .• ·, • I. I I . \ ;-... ,. '''''t I . f. 1 , ....... ,. ,,,,,,. .. ,,, / .. ,_ ''" ~ ~~'1,·'1,,,, I I ·o 7 ,,,,,,, /""1'"'1'"'1' •···