Loading...
HomeMy WebLinkAboutAtka Relocation of Project 1983• ! r 1< " { { \. '- ' ATK 003 Lu. ~~I ... . . .. F.?,~? '•\ .,. ...... . :: +kif. ~~}\i:.\. :' .. ~ ':~ L-.... Iii ~ii/IJ w.iii.· ~r;::--: Y' . f'-l )d .. _, , --~~ "RELOCATION OF HYDROELECTRIC PROJECT AT ATKA, ALASKA" Prepared for: ALASKA POWER AUTHORITY by: NORTHERN TECHNICAL SERVICES August, 1983 NORTHERN TECHNICAL SERVICES ANCHORAGE, ALASKA August 1, 1983 Alaska Power Authority 334 West 5th Avenue Anchorage, Alaska 99501 NORTHERN TECHNICAL SERVICES 750 WEST 2ND AVENUE, SUITE 100 • ANCHORAGE, ALASKA 99501 (907) 276-4302 Attention: Ms. Margaret Lesniak Re: Draft Report in Fulfillment of Contract Number CC-08-2266 Amendment No. 2, Relocation of Existing, Non-Functional Hydroelectric Plant at Atka, Alaska Dear Ms. Lesniak: Please find attached a draft report on the feasibility of re- locating the existing, non-functional hydroelectric generation plant on Atka Island to a site on Chuniisax Creek. In fulfillment of. the amendment contract between Northern Technical Services and the Alaska. Power Authority, a reconnais- sance survey of Chuniisax Creek was completed by personnel from van Gulik & Associates, Inc. and Northern Technical Services and a draft report prepared by van Gulik & ~ssociates, Inc. There are several locations which satisfy the basic require- ments, but one, with intake at Falls D, is clearly superior to all the others in most respects. It requires the least in additional materials and has the easiest access in terms of moving the powerhouse equipment to the site. It appears superior in terms of ease of contruction of the powerhouse foundation and tailrace. Lastly, it meets what we understand to be the optimum design characteristics of the turbine. It does, however, place the powerhouse between the first and second falls Ms. Margaret Lesniak Page 2 within ~n area reached by some anadromous fish. The information in your report on Aquatic Environment leads us to conclude the impact would be minimal and we, therefore, suggest the project be installed at that location. Preliminary cost estimates are included. The lower estimate is on the basis of the village constructing it utilizing its own labor resources~ the other reflects the cost of labor if contracted. Should the concerned agencies conclude that reduction of the flow in the upper third of the reach below Falls B would cause unacceptable impact, the alternative is to place the intake at Falls F with the power plant in the vicinity of Falls B. The powerhouse location is less desirable and might require some foundation exploration, and the pipeline length would be about 1,800 feet, nearly twice the length of the other. There is some potential for impact on land-locked Dolly Varden. Sincerely, NORTHERN TECHNICAL SERVICES William D. Pyle Partner WDP/pgh 082-011 Attachment RELOCATION OF HYDROELECTRIC PROJECT AT ATKA, ALASKA Reconnaissance of Chuniisxax Creek was accomplished on 8 and 9 June 1983 for the purpose of evaluating relocation of the existing, non-functional hydro-electric plant to some site on that creek. The existing turbine was designed to operate with a head of 103 feet and with a flow of 10 cubic feet per second (cfs), generating 50 Iav at that flow. Levels were run to establish the relative elevation of pertinent topographic features. Most distances were obtained by stadia but some were chained as well to check the stadia accuracy. During the reconnaissance two flow measurements of the stream were made; flows were in excess of 20 cubic feet per second. The stream has more than enough water to satisfy the flow requirement except perhaps for the driest part of the year which might occur in some part of June and July and again in winter months when the discharge might be limited by colder weather. It would appear that for perhaps three months of the year the flow ~ight drop to about 10 cfs but during the remainder of the year would be in excess of the design flow requirements of the turbine. There are five site possibilities which can provide an elevation difference in excess of the head of 103 feet for which the turbine was designed. In four of these, the intake structure would be located at the sixth falls upstream (Falls F) and powerhouses located. at various sites downstream. One configuration could develop a head in excess of the design head with an intake structure located at the fourth upstream falls (Falls D). The first four would require pipelines ranging in length from about 1,500 feet to about 1,800 feet. The fifth would require a pipeline of about 950 feet. Two-possibilities with an intake at Falls D could develop about 81 feet and 88 feet of head with pipelines of about 500 feet and 790 feet, respectively. These would produce power in the range ·0° j\ [1. T i\M [ l of 30-35 KW. An eighth configuration, which provides considerably less elevation differential but which would be an attractive option for further analysis if a new turbine/generator/pipeline were to be considered, would simply utilize all the head and flow available at Falls D. The available head is about 35 feet and while sufficient hydrologic information is not yet available to estimate the annual power production, it would appear that 40 to 50 KW could be readily developed. This site would be the simplest to develop of all sites examined. Fisheries The following is based on an analysis of the aquatic environment in Chuniisxax Creek performed in 1982. Pink salmon represent the most significant anadromous fi~~ species in the creek. Their habitat is restricted to the stream below the first falls (Falls A) and would not be affected by hydro development. Silver salmon were observed below Falls A and a few have been reported to have surmounted that falls and reached the second. A development with power plant located below Falls B would have some small impact. Chum salmon were not observed in the stream but villagers have reported that chum have been know to spawn there. They are capable of surmounting the first falls, however, their preferred spawning habitat is much the same as the pinks and hydro development would consequently have little impact. Dolly Varden trout inhabit the stream from the mouth to above the area under consideration. Those above the second (Falls B) are landlocked and would be impacted on somewhat depending on the particular site configuration. They were observed throughout the area up to the seventh falls and in the small streams tributary to the main stream. Hydro development would likely have minimal impact on this fish population. Anadromous Dolly Varden would be affected by any development with powerhouse located downstream of Falls B. The impact would depend upon the amount of water diverted to the powerhouse as compared to the total amount available and on the timing of spawning in relation to the periods of low flow when the diversion might result in the stream being significantly dewatered for a short distance. The length of reach involved would be a maximum of about 350 feet. Description of Alternatives The alternative most nearly matching the turbine design parameters and requiring the least amount of new pipe (if any) for the water conveyance would involve an intake at the elevation of Falls D, a pipeline about 930 feet long placed in a generally straight line (about 60 degrees east of south) , crossing the stream to a powerhouse location on the left bank. This location would place the tailrace about 300 feet downstream of the second falls (Falls B) , roughly a third of the reach between the first and second falls. Installation at this site will develop the full potential the existing power plant is capable of producing. It should have minimal impact on fisheries. This site is the most advantageous of possible sites on the stream from the standpoint of accessibility for getting the generating equipment to the site. The unit can be broken down into its smallest components, moved by skiff to a location approximately 500 feet from the site and moved by some vehicle such as Nodwell or winched and carried, in stages, over to the site. The point to which a line of levels was run is about 105 feet below the elevation of the intake location. Between that point and the elevation of the stream an additional 15 to 20 feet of head can be obtained, depending on the location chosen for the powerhouse. The turbine designer indicated that the generation with this particular turbine would be optimum at about 125 feet, and this can be approached at this location. Some probing and test excavation would be necessary to determine the bes·t location for the powerhouse foundation and the tailrace. Variations on this alternative would provide for the same intake but with the powerhouse located on the right bank at Falls B or downstream opposite the location described above. These would provide about 80 to 88 feet of head, somewhat less than the design head for this particular turbine. The alternatives with intake located at Falls F could develop about 110 feet if terminated at Falls B and in excess of 140 feet of head if the powerhouse were located in the same place as described above in the first alternative. These would require 1500 to 1800 feet of pipe. They offer no particular hydraulic advantage. They present some additional construction difficulty since material and equipment would have to be moved farther upstream.· The location offering 140 feet of head is not practical to develop using the existing turbine. Those alternatives with the powerhouse at or near Falls B would have the least potential impact on anadromous fish habitat. Conclusions The first alternative described above is ideally suited for installation of the generating equipment and penstock material presently located at Atka. The available head approaches the [ optimum for this particular turbine. There should be more than enough flow available most of the time. The site requires the least overland conveyance of the equipment and construction supplies. Should it be determined that this installation would cause unacceptable adverse impact on anadromous fisheries as a consequence of reducing the stream flow in the reach from Falls B to the powerhouse location by the amount diverted for generation, the most productive alternative would be to install the intake at Falls F, and the powerhouse on the north bank of the stream near Falls B. The conveyance pipeline could be located north of the stream and would not require any crossing of Chuniisxax Creek. It would need to be elevated slightly through a low area where it would cross a small tributary stream. A minimum of 900 feet of additional pipe would be required and to reduce head losses it should be of a larger diameter than the 12" on hand. This larc;rer diameter pipe would make· up the upstream half of the pipeline. The suggested location and the alternate are shown on the attached location map (Figure 1). Transmission The project would require about 4,000 feet of transmission line to reach the central generating building in the village. It should be buried and, to reduce line losses, include a step-up transformer at the powerhouse and a step-down at the village. Step up to 480 volts should be sufficient. The line should be three wire with neutral; #4 - 5 kv should be sufficient. Intake The intake structure would be located just above the fall of Falls D. Since there will be no attempt to regulate the stream .. ,. .. ~'J. •. . ~ ..... .· .· ... .f' ~ t?. f~~""' .w\ '!.] • •J l rr.~ ~. { ,: , ·• • ;~ J(•·t .. 4 ·~ ~ ' ·· ... :.. • '·' i:""·~ '·. "· ~ ;..);.~·' • ::,. '• ::l '": ~"::t t ~ . 0 ··~ . ~~•'\~ .. X .. . ~ a: .• ~/&• I' w ~-· ~ ··.·~'.· .~; ~ ·. ·" )r' ." . ·•.· .. ; .• w f A .... , (/J • ~ 1-::l : .•,.' 0 . 'f. X a: w ~- (/) (/') C/) (/') C/) ...J ..J ..J ..J ..J ...J ..J ..J ..J ..J ct ct <( ct <t u..· u.. u.. u.. u. -'0 "0 .= Ill c ... -,o ..-(\J r() q-t-~ <X: co (.) 0 w :::(.: ~~ z · ' O' -.a:.;. ~ .. ... ~ ... . '! ., C/) (/') ..J ..J ..J ..J ct ct u.. u.. .c. .c. It) lO w u.. w . ~~I! ' < tit· -· .... ~J ·~z~~~ •·: .. . . -~·~·"' ~- ••• ~... .• • .!I'. '.f ., ' J . .v-•, ..,:.. ·. I ·~~·~·· •· " ·~ . .a';:u-.: .,, :. ~~~t ... . }~. ,..~~ • • • ..... • ·~ •• , ;&. _.,;ill r ,,. • • ~. ·.~ .. ~" ~>:It~ ' ' . . .t£. ' . . I ,;I., . ,. ~ .. ;t . <.., f..-:·;..:.~·~· ~ );.·. ·.~ ~ • ~~-~-~~'f •• ~tt.:a/~ .. ,;· i4 . ~ . .~. ·~ • WJi .. ,..., .... ~~ . ·~··· ·..,~ . .1 '·"''Jo _,. ' ,.,.. .t· ~~ i . . ~. . ... ' -- ~ '-"-< 0~ ~ --0 I C\1 co 0 a. <( ~ z 0 -t-< (.) 0 ...J ._ (.) UJ J 0 a: a. .. .., 0 a: 0. -C!' II. .. 0 lO C\1 II .. .. -.. (,) w flow with storage, a low over-flow diversion weir sufficient to properly submerge the intake should suffice. Water will be flowing over the weir most of the time. Because of this and the need to securely anchor and form the intake, the weir and intake should be of concrete. The intake should be screened and provided with a gate for closure of the pipe. The slide gate installed at the existing dam near the village can probably be adapted to the site. Because of the likelihood of ice backup at the intake and possible damage to the penstock, the short length of pipe from the weir to the falls where the penstock leaves the stream should probably be of polyethylene or corrugated metal pipe. Powerhouse The general configuration of the powerhouse at the existing installation is satisfactory for a site on Chuniisxax Creek. The precise location should be chosen with a view to maximizing t~~ head and minimizing the amount of concrete needed over rock for the footing. Care should be exercised to insure the tailrace will not erode. Some probing and hand test excavation will be needed in order to select the most appropriate spot. Pipeline If the existing pipeline is ,carefully salvaged it should all be usable at the new site. Some 800 feet is installed and about 140 feet of unused pipe is available. The pipe from the intake to the point where it leaves the stream at the falls should probably be polyethylene or HPC to reduce possibility of ice damage to the pipe. PVC should be satisfactory for the remainder. A relief valve should be installed near the intake to permit dewatering of the pipe. Two trestles would be required for support. The first would be for the sake of hydraulic efficiency and would support the pipe from the falls across a gully to a saddle about 250 feet away. The average height would be about 15'. The alternative would be to install the pipe on a curve rather than a straight line. About 80 to 100 feet of additional pipe with several elbows would be required but the timber supports could be much simpler with the pipe essentially following the contour around to the saddle. The simpler approach is recommended. The other trestle is unavoidable. It would cross Chuniisxax Creek to the left bank powerhouse location. The pipe would approach the creek bank at ground le~el then follow the steep bank downward to the trestle at an elevation slightly higher than the loc~tion chosen for the powerhouse on the other bank. The trestle would support the pipe from the right bank to the powerhouse on the other side. The construction should be perhaps a bit more substantial than the supports constructed for the stream crossing just below the dam at the existing installation because of the possibility of icing. In most respects, installation of the pipeline itself from intake to powerhouse is not significantly different from the existing installation at the site near the village. Turbine/Generator The existing equipment can be fully utilized on Chumiisxax Creek. The suggested location provides about the optimum head for this specific turbine and the stream should have adequate flow most of the time. In the intervening period since the equipment was acquired and installed, a central generation system has been installed at the village: and the hydro plant, which previously would have operated independently, will now be operating in parallel with the diesel- driven system. This interface needs careful attention. If this installation proceeds, provision should be made for a visit to the village by a representative of the vendor (Hydro-Watt} and the installer of the diesel-driven system (Pacific Diesel} , to insure that the speed controller and other equipment are correctly installed and can be operated with assurance by the village. It is particularly important that the speed control immersion units be properly installed. Construction/Installation The villagers are likely fully capable of constructing the weir and intake, installing the penstock, constructing the powerhouse and installing the transmission line and step-up and step-down transformers. they should be guided by a competent field engineer in locating and at critical times in the construction of the powerhouse and the weir and intake structure. Consultation should be arranged with the vendor who supplied the generation equipment to insure that the system is properly integrated with the diesel-driven generation and that any additional protective devices or equipment are considered and installed as appropriate. For the hydro installation to be efficient in displacing the use of diesel fuel, it should operate as a dependable base load plant. Some care should be taken to insure that it will do so. MAJOR COST ITEMS 1. Power house (10 cy foundation@ 800 plus bldg) $12,000 2. Diversion & Intake (5 cy @ 800) 3. Penstock (Existing pipe. Timbers & Labor@ SO/ft.) 4. Transmission Line and Transformers (0.76 mi @ 90,000) 5. Mob/Demob 6. Contingencies @ 25% (Possibly some additional pipe) 7. Consultation, Test & Startup Engineering Assistance $ 6,000 $10,000 Subtotal 4,000 47,500 68,400 131,900 100,000 231,900 60,000 (291 ,900) Say $300,000 16,000 Total $316,000 Say $320,000 If villagers can construct project using own labor resources with engineering assistance and consultation: MAJOR COST ITEMS 1. Powerhouse (move existing powerhouse plus 10 cy con) 2. Diversion & Intake 3. Penstock (assume 500 feet requires support every 10 feet and materials @ 100 each support) 4. Transmission & Transformers (wire $3.5/ft. Portland: assume $10 to Atka. Transformers 2 @ $2,000 5. Contingencies @ 20% (Possibly some additional pipe) 6. Consultation, Test & Startup Engineering Assistance $ 6,000 $10,000 Subtotal Total $10,000 4,000 5,000 44,000 $63,000 14,000 77,000 16,000 $93,000