HomeMy WebLinkAboutChester Lake Dam Replacement Project 1984Approved
Approved
Approved
MANAGEMENT PLAN
CHESTER LAKE DAM REPLACEMENT PROJECT
METLAKATLA, ALASKA
ALASKA POWER AUTHORITY
334 West 5th Avenue
Anchorage, Alaska
~
~~
~?
Adopted by Board of Directors -December 13, 1984
6044/302/D3/1
. -.,
• J'
..•
. J
' ,.
•
•"\
. ,··~
•
/. \ .'' , .. ' \ I . \ . ''-_) ,_,
t.·-.:~···, ~·e~; ..
,., '·'·' .. "I .._ ..
-:r. !" \ .
""' •• J ~~ I\ 4-••• /
\ ·, .. ~~··'
......
\ .r> '·,
~\. ' ·. '-, \ .... ._ ..
\ ' ...... ,
0.. ~ c:: 0 •.-4 ~ C1l u 0 ,..J ~ u Ill .,.., 0 1-4 ~ ....... 1 N Ill 1-4 :::l 00 •.-4 ~
.... m m ....
>-2
4
(l
~
0 u ·
(.9 z
[
w w z ·, (.9
z ··w ·
CHESTER LAKE MANAGEMENT PLAN
TABLE OF CONTENTS
SECTION TITLE
I PURPOSE OF MANAGEMENT PLAN
II GENERAL PROJECT INFORMATION
III PROJECT MANAGEMENT CONCEPT
IV ORGANIZATION AND STAFFING
v SCOPE OF WORK
VI DESIGN MANAGEMENT
VII CONSTRUCTION MANAGEMENT
VIII PROJECT TRANSFER
IX PROJECT MILESTONES
X PROJECT COST ESTIMATE
6044/302/D3/2
1-1
SECTION I
CHESTER LAKE MANAGEMENT PLAN
PURPOSE OF PROJECT MANAGEMENT PLAN
This project management plan provides the project management
guidelines; anticipated project costs; schedule milestones;
organizational staffing; and the design and construction
management procedures which will be followed during the
construction of the Chester Lake Dam. Managers will be
required to develop detailed procedures for specific project
activities in accordance with the policies and general guide-
lines outlined herein or those which will be provided by
future updates of this plan. Other detailed procedures
implementing the policies and general guidelines set forth in
this plan will be developed by the Power Authority.
6044/302/03/3 Page 1-1
SECTION I I
CHESTER LAKE MANAGEMENT PLAN
LOCATION AND HISTORY
2-1 GEOGRAPHIC LOCATION AND LAND OWNERSHIP
Chester Lake is located on Annette Island, approximately 20
miles south of Ketchikan and two miles east of Metlakatla,
Alaska. (See Project Location Map, Figure 2-1). The existing
Chester Lake Dam was constructed in 1927 and in the 1930's the
dam was raised to a height of 21 feet. The lake serves as the
potable water supply for Metlakatla. The surface elevation of
the lake is 845 feet. The drainage area is a scant 1.62
square miles. Chester Lake and its environs are located
within the Annette Island Reserve and are under the jurisdic-
tion of the Metlakatla Indian Community. The Reserve was
created by an act of the U.S. Congress in 1891 and comprises
the entire 134 square miles of Annette Island.
6044/302/D3/4 Page 2-1
2-2 HISTORY
The Power Authority initiated a feasibility analysis of a
hydroelectric project for Chester Lake in 1981. The project
called for the replacement of the old dam with a larger new
dam. In 1983 the Legislature authorized the Power Authority
to construct the Chester Lake Hydroelectric Project for $13.2
million under the Energy Program for Alaska, however, no
funding was appropriated.
Due to uncertainties in the financing and timeliness of
redeveloping a hydroelectric generation facility at Chester
Lake, the Metlakatla Indian Community and the Power Authority
have not finalized any power sales agreements for the project.
Updated load forecasts completed in 1984 indicated that
several other electrical system improvements and some
conservation measures directed at electric space heating may
be warranted before finalizing a schedule for new generation
facilities at Chester Lake. These items will be addressed in
an update of the feasibility report to be available in early
1985.
In any event, due to the deteriorated condition of the old
dam, community leaders became concerned about the water supply
and the effect that its loss would have on the health and
welfare of the populace. They petitioned their legislators
for the funds to repair the dam. As a result, the Legislature
appropriated $100,000 in HB 691 to the Department of Community
and Regional Affairs for temporary repairs of the dam
consisting of caulking and bracing. These repairs were
completed in September 1984. In 1984 an additional $3.3
million was appropriated in SB 409 to the Power Authority for
construction of a replacement dam of a design which would be
compatible with future hydropower development of the project.
6044/302/D3/5 Page 2-2
3-1 INTRODUCTION
SECTION III
CHESTER LAKE MANAGEMENT PLAN
PROJECT MANAGEMENT CONCEPT
The basic project management phases of the Chester Lake Dam
Replacement Project are the Design Phase, the Bid
Solicitation, the Evaluation and Contract Award Phase, and the
Construction Phase of the project.. Project management
concepts include systematic activities of planning,
implementation, and control needed for successful completion
of the Chester Lake Dam Replacement Project. The project
concept is to coordinate the activities of the project
participants to ensure that the project is completed to
specification, on schedule and within budget.
3-2 POLICIES RELATIVE TO PROJECT MANAGEMENT
The Power Authority has flexibility in determining the
relationship of the organizational elements of the project.
For this project the design will be accomplished by an
engineering consulting finn while the Power Authority staff
will perform the overall project management including the
construction management functions. A single construction
contractor will accomplish all procurement and construction.
The responsibility for management of the project, including
design, will be transferred from the Power Authority's
·Planning Division to Projects Division upon initiation of the
design. Upon completion of construction, ownership of the
project will be transferred to the Metlakatla Indian Community
which will be responsible for project operations and
maintenance.
3-3 STAFFING REQUIREMENTS
The major day-to-day project participants are the Power
Authority's Project Manager and Construction Coordinator, the
Design Engineer's Project Manager and Onsite Engineer, and the
Construction Contractor. The Power Authority staffing
requirements will be a part-time project manager, a full-time
construction coordinator during construction, part-time
support by a cost scheduler and contract administrator, a
project accountant and necessary clerical support. All
personnel requirements can be met within the current level of
staffing of the Power Authority.
6044/302/D3/6 Page 3-1
3-4 PROJECT PARTICIPANTS
The key participants in the Chester Lake Dam Replacement
Project will be the Alaska Power Authority Board of Directors,
the Alaska Power Authority staff, the Metlakatla Indian
Community, the Design Engineer and the Construction Contrac-
tor. The Federal Energy Regulatory Commission (FERC) is not a
participant at this time since this project does not involve
power generation.
3-5 THE ALASKA POWER AUTHORITY BOARD OF DIRECTORS
The Board exercises broad, general control over the Power
Authority staff and establishes general policies for project
development. The Board will review and endorse the Project
Management Plan which will authorize the Power Authority staff
to proceed with the final design of the selected configuration
and to solicit bids and award a contract for the construction
of the project. Since there will be no construction of power
generation facilities, there is no requirement for conditional
power sales contracts with the Metlakatla Indian Community.
3-2 STAFF OF THE ALASKA POWER AUTHORITY
It is the responsibility of the staff of the Power Authority
to implement the Board of Directors policies, establish
internal and external management control, and provide an
adequate number of trained personnel to ensure that the
project is constructed to specification, within budgeted cost
and on schedule. The Project Manager for this project is
responsible for the administration of all design and con-
struction operations associated with the project except for
the construction safety program which is the responsibility of
the construction contractor. The Project Manager will also
serve as the chief point of liaison with the Metlakatla Indian
CoDlmunity. The Construction Coordinator will be the onsite
representative for the Power Authority through the con-
struction phase. He will provide assistance to the Project
Manager for the administration of the construction contracts,
and will perform the quality assurance function during con-
struction. Prior to construction he will assist in the review
of contract plans and specifications.
3-6 METLAKATLA INDIAN COMMUNITY
The ~etlakatla Indian Community has sovereign jurisdiction
over the land and water resources of Annette Island. Prior to
initiation of construction, an agreement between the Power
Authority and the ~1etl akatl a Indian Community wi 11 be neces-
sary. This agreement will provide the right-of-entrys
necessary for construction and will provide for the transfer
6044/302/D3/7 Page 3-2
of ownership and O&M responsibility for the project to the
Community upon completion of construction. A Waiver of
Sovereign Immunity or similar vehicle will also be required
from the Community to allow State inspection of the completed
dam under the State Dam Safety Program administered by the
Division of Land and Water Management, Department of Natural
Resources.
Coordination with the Community will be required for site
access for prospective bidders and for the access of contrac-
tor personnel, equipment and material. While the Community
will not be directly involved in the bid evaluation and
project management, periodic priefings would be conducted to
keep the Community advised on project developments plus
provide a means for Community input on the project. Upon
completion, the Community will assume the responsibility for
the operations and maintenance of the permanent project
facility .. The Power Authority will provide the necessary
start-up trai~ing and operations manuals for the Community.
3-7 DESIGN ENGINEERING
Due to the deteriorated state of the existing dam, it is
imperative that the construction of the replacement dam be
accomplished during the 1985 construction season. Consequent-
ly there is insufficient time available to implement the
normal RFP process of soliciting proposals in order to select
a design firm for this work. The possibility of utilizing a
two-step design/construct bidding procedure was considered,
however, this is also too time consuming to complete
construction during the 1985 season. The design of this
project will, therefore, be accomplished by utilizing Harza
Engineering Co., the engineering firm which prepared the
feasibility studies for Chester Lake and is currently still
under contract with the Power Authority.
Although Harz a 1 s contract is presently only for the
feasibility study work, the RFP under which this firm was
selected and the contract itself provided for the possibility
of design, preparation of plans and specifications, and
construction management services for the project. Harza
Engineering was selected on the basis of the entire RFP and is
considered we 11 qua 1 i fi ed to accomp 1 ish the added work. A
contract amendment will be negotiated to accomplish the design
portion of this project and to assist the Power Authority
during the construction phase.
The design work to be accomplished will be limited to that
which is necessary to maintain the Community•s potable water
requirements and to provide for compatible with future
expansion into a hydroelectric generation facility. Design of
6044/302/03/8 Page 3-3
the complete dam, powerhouse, penstock and transmission lines
will not be part of this contract.
The Design Engineer will prepare the plans and specifications
for the construction contract and will assist the Power
Authority in the bidding and contract award process. During
construction they will provide an onsite full-time engineer to
resolve any design related problems and to assist in the
administration of the construction contract. The Design
Engineer will prepare as-built drawings for submission to the
Power Authority upon fi na 1 acceptance of the dam. They wi 11
also prepare the operations and maintenance manual for the dam
and present an orientation/training session to the Community's
operations personnel prior to transfer of the project.
3-9 CONSTRUCTION
Construction of this project will be accomplished through the
use of a single construction contract. The contract will be
awarded through the use of state competitive bidding proce-
dures. The contractor will be responsible for procurement of
all permanent project materials as well as all construction
required to complete the project. Additionally, the contrac-
tor will be responsible for: Quality Control and testing;
jobsite safety; transportation to and from the jobsite;
establishing and operating construction camps, as necessary;
and maintaining the supply of potable water to the community
during construction.
6044/302/03/9 Page 3-4
4-1. INTRODUCTION
SECTION IV
CHESTER LAKE MANAGEMENT PLAN
ORGANIZATION AND STAFFING
This section defines the project team organization and out-
lines the systems and policy guidelines upon which the project
management approach is based.
4-2 ORGANIZATION AND STAFFING APPROACH TO CHESTER LAKE PROJECT
The internal matrix organization which will be used to manage
the Chester Lake Project is depicted in Figure 4-1. This
organization chart was developed to meet the specific project
needs of the Chester Lake Dam Replacement Project. The solid
lines on the organization chart indicate functional relation-
ships as defined in the Power Authority organization. The
dashed lines represent relationships between project team
members either on a full-time or part-time basis.
The focal point of the Chester Lake matrix organization is the
Project Manager. The Project Manager wi 11 directly manage
project activities and provide the nucleus of supervision,
1 i a i son, coordination, and communication between a 11 interna 1
and external participants in the project. The Project Manager
will define and clarify all parties' roles and responsibil-
ities.
In the matrix organization, the day-to-day supervision of the
project staff will shift from functional managers to the
Project Manager. For instance, the Cost Scheduler will be
supervised by the Project Manager (dashed 1 i ne} rather than
the Director of Administration (solid line). The Project
Manager must provide highly visible guidance and leadership of
all project activities on a continuing basis. Implicit in
this leadership is the requirement that standards and
procedures of all parties involved in the project be
respected.
The Project Manager will be ultimately responsible for ensur-
ing compliance to the policies and project guidelines set
forth in this plan. Additionally, the Project Manager will be
responsible for continually re-evaluating the scope of project
work to be performed by the contractor and conveying direction
if necessary to all parties. The Project Manager will define
the integration of other organizations outside the Power
6044/302/03/10 Page 4-1
Authority Project Management Team and will formally define
organization interfaces. The Project Manager will a 1 so be
responsible for coordination and liaison with the Metlakatla
Indian Community.
4.3 PROJECT TEAM
The Project Team will consist of the following members:
0
0
0
The Project Manager will have the responsibility of
managing and coordinating the activities of all project
participants and the design and construction contractors.
The Project Manager will have the authority and
responsibility to develop, approve and enforce procedures
used in execution of project functions and will be
responsible for the identification and resolution of
problems and solutions to problems which impede project
completion or increase the risk of cost overruns and
technical deficiencies. He will also perfonn the
Construction Management Function by directing
administering and managing the construction contract.
The Project Manager will report to the Director of
Construction.
The Construction Coordinator will be the Power Authority
representative on-site and will provide a liaison and
communication interface to the Project Manager located in
Anchorage. He will monitor construction progress at the
project site and assist the Project Manager in the
administration and management of the construction
contract. The Construction Coordinator will anticipate
and identify field problems and relate them to the Power
Authority Project Manager. The Construction Coordinator
will provide onsite direction to the construction
contractor through coordi~atio~ with the Project Manager,
and will assist the Project Manager in estimating and
negotiating required contract changes. The Construction
Coordinator will a 1 so be the Power Authority • s Qua 1 ity
Assurance Manager during construction and will perform QC
audits of the contractor•s quality control functions and
witness critical testing. The Construction Coordinator
will report to the Project Manager.
The Cost Schedule Controller will maintain the cost
schedule system for the Chester Lake Project. The
controller will be located in Anchorage and will monitor
project costs and schedule progress and variances to
projected cost and schedule forecasts. The cost schedule
controller will prepare monthly project reports on costs
and schedules. The controller will be responsible for
monitoring changes to breakdown of contract work and will
6044/302/03/11 Page 4-2
0
0
be responsible for monitoring project costs and
schedu 1 es. The centro 11 er wi 11 report to the Project
Manager and the Director of Administration.
The Contract Administrator will be responsible for
contract administration support functions. The contract
Administrator will establish and maintain contracts
files; process and expedite pay estimates and change
orders following approval by the Project Manager; draft
correspondence pertaining to contract issues; and attend
and record contract meetings such as contract
negotiations, project review meetings and claims
negotiations involving Power Authority personnel. The
Contract Administrator will report to the Project Manager
and the Director of Administration.
The Project Accountant wi 11 provide project support
functions such as processing pay requests through the
State accounting system and general ledger financial
statements. Finance and Administration personnel wi 11
report to the Project Manager and the Associate Executive
Director of Finance/ Administration.
4.4 DEVELOPMENT OF PROJECT STANDARDS AND PROCEDURES
The development of standards and procedures for all aspects of
the Chester Lake Dam Replacement Project will be the ultimate
responsibility of the Project Manager. The Design Engineer
will develop the functional procedures for activities which
will occur within his organization. In all cases, the Power
Authority Project Manager will be responsible for reviewing,
revising, and approving contractor-developed procedures. For
a delination of Power Authority procedure responsibilities for
all aspects of the Chester Lake Project, please see Table 4-1.
6044/302/D3/12 Page 4-3
t4JI
FUNCTIONAl SUPERVISION FIGURE 4-1 p
AlASKA POWER T
AUT~OIHTY
E!CECUTIVE
OIRECTOR
I
I I
ASSOCIATE EXECUTIVE AS SOC I ATE EXECIJTI VE ASSOCIAH EXECUTIVE ASSOCIATE
OIRECTOR. PROJECTS OIRECTOR, OPERATIONS OI~FCTOR, PLANNING EXWJTIVE
OIRECTOR
I -FINANI:E
O!RECTOR
CONSTRUCTION DIRECTOR
AOMINISTRATION
I
PROJECT
MANAGER -------r-- - --------- ---~------__ _..._ -~------------r-
I
I I I I I
CONSTRUCTION COST CONTRACT PRO,JECT MANAGF.R • PROJECT
COOROINATOR SC~EOUlER AOMINISTRATOR FHSIRILITY Af.f.OIJNTANT
·,~,::
...
TABLE 4-1
RESPONSIBILITY CHART
PROCEDURE TITLE
Bid Solicitation
Bid Evaluation
Contract Preparation
Project Team Organization,
Interfaces, Communications,
and Functional Responsibilities
Document Control/
Project History
Contract Compliance
Cost and Schedule Control
Cost Estimating
Project Accounting
Quality Assurance/
Quality Control
As-Built Drawing Control
Submittal Processing
Constructability Reviews
Change Order Processing
Construction Contract
Administration
Project Reporting
Safety Reviews
Communications
6044/302/13
RESPONSIBLE
ALASKA POWER AUTHORITY
MANAGER
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Project Manager
Cost Schedule Controller
Projects-Director of Engineering
Project Accountant
Construction Coordinator
Project Manager
Project Manager
Project Manager
Contract Administrator
Contract Administrator
Project Manager
Construction Coordinator
Construction Coordinator
Table 4-1
5-l GENERAL
SECTION V
CHESTER LAKE MANAGEMENT PLAN
SCOPE OF WORK
The construction to be accomplished under this project manage-
ment p 1 an wi 11 be limited to the dam itself and nat the
construction of a complete hydroelectric facility.
Senate Bill No. 409, as enacted by the governor, reads:
Sec. 274. The sum of $3,300,000 is appropriated from the
general fund to the Alaska Power Authority far the
Chester Lake Dam repairs and construction.
This funding appropriation was intended to repair or replace
the existing Chester Lake Dam an an expedited basis in order
to protect and maintain the community's potable water supply.
It was further intended that any construction work accom-
plished be designed such that it would be compatible with
possible future hydro power development of the site.
5-2 WATER STORAGE REQUIREMENTS
The existing dam was originally used as a hydropower project
and as a source of potable water for the Community of
Metlakatla. In 1956 the powerhouse was abandoned and the
project was used solely far water supply purposes.
The current spillway elevation of the dam is approximately 845
ft MSL and maintains the reservoir lake at this level except
during periods of low runoff. Historical data on water
consumption rates far the Community are essentially nan-
existent, however, it is known that at times the water level
in the reservoir drops several feet below the spillway ele-
vation. Although residents cannot recall having run aut of
water, the Community has expressed serious concern about such
a possibility. Construction of a replacement structure
should, therefore, as a minimum sustain the current reservoir
storage capacity with a spillway elevation of 845 ft. MSL.
5-3 COMPATIBILITY WITH FUTURE HYDROPOWER DEVELOPMENT
The feasibility of Chester Lake as a hydropower site has been
addressed by twa separate studies. The first of these was
prepared by R. W. Retherford Associates in 1977. The second
6044/302/14 Page 5-l
is the feasibility study being prepared by Harza Engineering
for the Power Authority. The feasibility reports show that
Chester Lake can be developed as a hydropower project either
on a small scale as a run-of-the-river project; or, on a
larger scale involving water storage and controlled release.
Thus, depending upon the ultimate level of hydro development,
the crest elevation of the dam structure varies substantially.
For a storage/release project the recommended dam has a
spillway crest elevation of 885 ft MSL, while the minimum
spillway elevation for a run-of-the river project is 845 ft
MSL. The current water elevation behind the existing dam is
845 ft MSL which is the minimum acceptable storage capacity to
maintain the community's year around potable water supply.
The dam to be constructed must, therefore, maintain the
minimum water storage requirements and allow for the various
options of future hydropow.er development of the site.
5-4 DESIGN OPTIONS
The current level of funding is sufficient to meet the immedi-
ate needs of protecting the community's water supply, however,
it is insufficient to construct the entire dam for the maximum
hydropower development scenario. The dam to be constructed
with the current appropriation must, therefore, be built in
such a manner as to allow for future expansion (i.e. raising),
or be bu i 1 t such that it will not interfere with future
hydroelectric expansion.
To achieve the intended goals at Chester Lake within the
current funding level there are three possible design options
available. These are:
Option 1: Repair the existing dam to maintain the Community's
potable water source and to provide compatibility
with future development of a hydropower dam.
Option 2: Construct a new dam which is designed to allow for
expansion and will become an integral part of a
larger hydropower dam. (See Figure 5-1)
Option 3: Construct a new dam of an interim design which will
maintain the potable water supply and accommodate
run-of-the river development but must be replaced if
maximum hydro development is chosen. (See Figure
5-2)
Each of these scenarios has recently been reviewed as part of
the project feasibility study. The results of these eval-
uations is summarized below.
6044/302/15 Page 5-2
Option 1: Repair Existing Dam
The repair of the existing dam, although feasible, is not
recommended for the following reasons:
a. The integrity of the existing structure is unknown. The
structure was built in 1927 and neither the design
drawings nor the specifications can be found. Due to
it's questionable strength, repairs to the structure
would have to be of such a magnitude as to provide the
full required dam strength, thus rendering the existing
dam of no value.
b. Repairing the existing structure would require either a
near complete draw down of the lake or construction of a
separate coffer dam upstream. Complete draw down of the
lake is unacceptable as the lake is the community's only
source of water. Construction of a coffer dam would
increase the cost substantially and make repairs to the
existing dam more expensive than uti1 izing the existing
structure as a coffer dam and building a replacement dam
downstream.
Option 2 -Construction of a New Dam of an Integral Design
This option allows for future expansion of the project to
maximum hydro development by designing the initial dam to
become an integral part of the larger dam. The dam would be
of a concrete gravity-arch design. The penstock penetrations
and gate facilities will be sized to provide for maximum
future generation. Construction of this option has been
evaluated for two possible spillway elevations: 845 ft MSL
and 850 ft MSL. The cost of these options, and the advantages
and disadvantages are discussed below:
Option 2A; Gravity Arch, Elevation 845
Estimated total project cost:
$2,743,000.
Advantages:
Lower first cost than option 28
Allows for run-of-river hydro development
Can be raised to any elevation up to 885' for future
development
Disadvantages:
6044/302/16
Provides only minimum storage capacity
Higher first cost than options 3A and 3B
Page 5-3
Requires maximum removal of existing structure
Option 28; Gravity Arch Elevation 850
Estimated total project cost:
$3,226,000.
Advantages:
Provides additional storage capacity
Allows for immediate run-of-river development
Can be raised to any elevation up to 885' for future
development
Inundates existing structure, minimizing removal
Disadvantages
Higher first cost than other options
Option 3 -Construction of a New Interim Dam
This option allows for an initial cost savings to be realized
by designing the dam to a specific height. The dam would be
of a concrete thin-arch design which could not be incorporated
or expanded into a higher dam. The dam wourcf be designed and
located to facilitate the construction of a larger dam
downstream at a later date. The dam would also be designed to
allow for immediate run-of-river development.
Similar to Option 2 this design was also evaluated at ele-
vations 845 ft and 850 ft. The advantages and disadvantages
are discussed below:
Option 3A; Thin-arch, Elevation 845
Estimated total project cost:
$2,014,000.
Advantages:
Lowest first cost of all options
Allows for run-of-river development
Disadvantages:
6044/302/17
Provides only minimum storage capacity
Requires maximum removal of existing structure
Page 5-4
Cannot be increased in height
Option 38; Thin-arch, Elev. 850
Estimated total project cost:
$2,368,000.
Advantages:
Lower first cost than options 2A and 2B
Allows for run-of-river hydrodevel opment.
Provides additional storage capacity
Inundates existing structure, minimizing removal
Disadvantages:
Higher first cost tban option 3A
Cannot be increased in height
5-5 SELECTED DESIGN
The design option selected for this project is Option 2B;
gravity-arch dam, elevation 850. This design option has the
greatest flexibility to accommodate all scenarios of
hydropower development for the project. The design allows for
immediate development of run-of-river generation and provides
additional storage capacity which will alleviate any potential
water shortages due to 1 ow flows or increased water
consumption . .
The added project cost for this design option is $1,212,000.
over the least cost alternative. The total project cost for
Option 2B, however, is still well within the available funds
for the project. This option will maximize the immediate and
long term benefits of the project, and eliminate the
possibility of constructing an interim dam which may become
obsolete in the near future.
5-6 SCOPE OF WORK
The work to be constructed under this project will consist of
the following design features:
A concrete gravity-arch dam
Spillway elevation at 850 ft MSL
Penstock and gate structure sized for maximum potential
hydrogeneration
Diversion conduit and emergency outlet
6044/302/18 Page 5-5
Potable water supply conduit
Excavation and toe construction to accommodate expansion
to elevation 885
Repairs as required to existing potable water supply line
and pressure reducing station to restore functionability.
6044/302/19 Page 5-6
FIGURE 5-l OPTION 2
885'
850'-----------------
' 845-~
EXISTING
DAM----t.,..l
FIGURE 5-2 OPTION 3
FUTURE
DAM
INTERGAL
DAM -GRAVITY
ARCH...;
CONCRETE
885'----------------------------r---~
850'
INTERIM DAM
THIN ARCH-
CONCRETE
------------------845'-
~""""""",...,.._,..,....,
EXISTING
DAM----t~
FUTURE
DAM
SECTION VI
CHESTER LAKE MANAGEMENT PLAN
DESIGN MANAGEMENT
6-1 OBJECTIVES OF DESIGN MANAGEMENT
The design objectives for the Chester Lake Project are to
achieve minimum construction costs while achieving technical
engineering adequacy, economy in operation and maintenance;
and assuring that appropriate consideration is given to sound
construction practices, qua 1 ity assurance requirements, and
environmental and safety aspects. It is the Power Authority's
pol icy not to issue bid documents for 11 bidding only!' but to
issue final plans and specifications. The schedule for
project construction takes this policy into account.
The Power Authority a 1 so encourages maximum utilization of
lump sum bid items but recognizes that unit price bid items
will be necessary where quantities cannot be firmly estimated
(i.e. rockbolts, etc.).
6-2 ADMINISTRATION OF DESIGN MANAGEMENT
Design management will be the responsibility of the Power
Authority's Project Manager. Matrix support from Project
Administration, Engineering, Construction and Environmental
and Licensing Sections of the Power Authority Projects
Directorate will be provided on an as needed basis. Studies,
designs, drawings, specifications and other documents prepared
by the Design Engineer will be subject to the approval of the
Power Authority.
6-3 DESIGN ENGINEERS RESPONSIBILITIES
The final design for the Chester Lake Dam Replacement Project
will be performed by the Harza Engineering Company. This
design effort is scheduled to begin in January 1985 contingent
on Board approval.
The Design Engineer will accomplish the following:
A. Perform any topographic and field surveys, test borings
and subsurface geotechnical investigations deemed neces-
sary beyond that information obtained during the fea-
sibility phases.
6044/302/20 Page 6-1
B. Prepare final design documents based on the results of
the investigations performed.
C. Prepare plans and specifications and bidding documents
for the construction contract.
D. Prepare a construction cost estimate based on the ap-
proved final design and specifications.
E. Assist the Power Authority in securing, analyzing, and
evaluating bids for construction.
F. Provide engineering services during construction
including review and approval of contractor submittals.
Prepare design revisions as necessary due to design
modifications or unforeseen site conditions or during
critical construction operations.
G. Prepare the project start-up manual and the operations
and maintenance manual. Conduct training classes as
required for O&M personnel.
H. Assist the Power Authority in resolution of contract
disputes and provide expert testimony if required.
I. Cooperate, participate, and develop quality assurance
plans and procedures as directed by the Project Manager.
J. Assist in the accomplishment of other Project related
Engineering tasks as directed by the Project Manager.
6-4 REVIEW AND APPROVAL OF DESIGN DOCUMENTS
Procedures for the distribution, review, and approval of
design documents and for monitoring and controlling the review
cycle shall be established by the Power Authority Project
Manager to meet the requirements of all participants. Draw-
ings, specifications, and contract data will be reviewed and
approved as directed by the Power Authority Project Manager.
Design reviews by the Power Authority will be conducted at the
50% and 90% design levels as a minimum. As a part of the
design review process, the Power Authority will perform
constructability reviews of the design and contract documents
to identify such items as: cost control and cost reduction
measures, procedural and language modifications, improvements
to enhance constructability and construction operations. The
constructability review will primarily occur at the 50% design
level so that maximum benefits can be obtained by revising the
design.
6044/302/21 Page 6-2
All design work will be 100% complete and ready for con-
struction prior to initiating the bidding process.
6-5 ENVIRONMENTAL PROTECTION
Although the Environmental Report for the Chester lake
Hydroelectric Project identifies minimal impact as a result of
construction, careful attention will be given by the Power
Authority's Environmental staff to the implementation of
contra 1 and enforcement measures to prevent any unnecessary
impact to the environment. These measures will be
incorporated into the construction contract. Special
attention will be given to protection of water quality within
the reservoir to eliminate any poissibility of contamination
to the community's water source. All necessary pennits will
also be identified and obtained directly by the Power
Authority. Monitoring and enforcement of penni ts and
environmental stipulations during construction will be the
responsibility of the Power Authority's Construction
Coordinator.
6-6 INDEPENDENT COST ESTIMATE
Pursuant to State Statute and Power Authority policy, an
independent cost estimate was prepared during the feasibility
study process. The independent estimate was based upon full
hydroelectric development of the project and verified Harza's
feasibility estimates. New cost estimates for the various
design options addressed by this Project Management Plan were
recently prepared by Harza based upon the 1 imited scope of
construction to be accompli shed under the dam replacement
project. These estimates were reviewed against the
independent estimate and found to be consistent. Prior to the
opening of bids for construction the Power Authority will
perform a detailed review of the Engineers esti.mate based upon
the final design. This estimate will serve as a check against
the validity of the Project Cost Estimate contained in Section
X and will allow for bid cancellation if necessary.
6044/302/22 Page 6-3
SECTION VII
CHESTER LAKE HYDROELECTRIC PROJECT
CONSTRUCTION MANAGEMENT
7-1 OBJECTIVES OF CONSTRUCTION MANAGEMENT
Construction management objectives for the Chester Lake Dam
Replacement Project include monitoring and controlling
construction activities to achieve minimum construction costs,
accomplish construction schedule milestones on time, conform
to design plans and specifications, conform to Alaska Power
Authority policies and project objectives, and accomplish
project safety and environmental objectives.
7-2 ADMINISTRATION OF CONSTRUCTION MANAGEMENT
Due to the relatively small size of this project, and the fact
that all construction will be accomplished under a single
contract, the Construction Management Function will be
accomplished directly by the Power Authority. Construction
management of the Chester Lake Project will be the respon-
sibility of the Power Authority•s Project Manager. The
Project Manager wi 11 report to the Director of Construction
and will supervise the Power Authority Construction Coordina-
tor who will be located on the jobsite. Matrix support from
the Project Administration, Environmental and Licensing,
Construction, and Engineering Sections of the Power Authority
Projects Directorate will be provided. Matrix support will
also be provided by the Associate Executive Directors of
Operations and Finance. These support personnel will be under
the operational supervision of the Project Manager.
7-3 ROLE OF CONTRACTED DESIGN FIRM DURING CONSTRUCTION
The responsibilities of the Design Engineer for the Chester
Lake Project are outlined in Section VI of this document.
Prior to and during construction, the design firm will prepare
technical plans and specifications to be included in bidding
documents, provide support to resolve design problems or
review critical construction operations, supervise and monitor
procurement activities, and insure that the project is con-
structed in accordance with design objectives. The design
firm wi 11 have a phys i ca 1 presence on-site throughout the
construction phase to provide immediate engineering
assistance.
6044/302/23 Page 7-1
7-4 CONSTRUCTION CONTRACT BIDDING
The sing 1 e construction contract for this project wi 11 be
competitively bid and awarded to the lowest responsive,
responsible bidder. Preparation of the construction contract
invitations for bid will follow the Power Authority approval
of the plans, specifications and contract package.
The bidding document for construction contract will be
prepared through the combined efforts of the Design Engineer
and the Power Authority's Project Manager. Bidding documents
will contain General, Special and Technical specifications and
will be specifically developed for the Chester Lake Project.
The Engineer will prepare the technical provisions of the
bidding document to include the plans and technical speci-
fications and that portion of the Special Provisions relating
to Design. The Power Authority Project Manager will be
responsible for the preparation of the General Provisions and
the Special Provisions in coordination with the Design Engi-
neer. The Design Engineer will finalize, assemble, reproduce,
and issue the bid document for advertisement.
The Bids wi 11 be received and opened by the Power Authority.
Bid Evaluations will be performed by the Project Manager in
conjunction with the Design Engineer, and the State's Attorney
General's Office. A five percent Bidder's Preference will be
applied in accordance with State Statutes. Notice of Intent
to Award, Award and Notice to Proceed wi 11 be issued by the
Power Authority.
7-5 CONSTRUCTION ACTIVITIES
During the construction phase of the project, the Project
Manager with support from the matrix organization will accom-
plish the following tasks:
A. Contract Administration. The Project Manager will
administer the fixed-priced construction contract from
bidding through contract completion. All contract
correspondence wi 11 be between the Project Manager and
the contractor. Any design changes, drawing releases or
shop drawing reviews will be directed through the Project
Manager in order to maintain full control over
correspondence to contractors.
B. Monitor and Supervise Contractor Submittals. The Project
Manager will review, and where necessary coordinate with
the Design Engineer all contractor submittals. Data
submittals which generally do not require Design Engineer
review include: contractor construction schedules, cost
breakdown data, and contractor QC or safety plans. All
6044/302/24 Page 7-2
contractor technical submittals requiring a
design-related review and approval will be routed to the
Design Engineer through the Project Manager. The Project
Manager will establish logs to maintain a record and the
current status of each submittal and will operate a
suspense system to assure that timely action is taken on
each submittal.
C. Perform Quality Assurance Functions. The Quality Assur-
ance (QA} Program will be performed and managed by the
Power Authority•s Construction Coordinator. During bid
packaging and contract review tasks, the Construction
Coordinator will recommend contract revisions to assure
that a rigorous Contractor QC program can be enforced.
During construction, the contracted Construction Contrac-
tor is responsible for the development and implementation
of a full scale Quality Control Program including the
performance of QC testing. However, all phases of
construction will be inspected and quality control tests
will be witnessed by the Power Authority•s Construction
Coordinator. The construction contractor is also
re$ponsible for quality control of materials procurement
and will be required to submit appropriate documentation
and certifications. The onsite Design Engineer
representative will provide assistance to the Con-
struction Coordinator on an as required basis. The
construction coordinator will maintain the QA/QC records
for the project.
D. Process Construction Contractor Payment Estimates. The
construction contractors must prepare a monthly payment
estimate based on an approved bid breakdown and on unit
prices. The Construction Coordinator will review these
estimates and verify the quantities, unit prices and
retention amounts and will recommend approval of the
payment requests to the Project Manager or return them to
the construction contractor for correction. Approved pay
estimates will be processed for payment through proper
Power Authority channels.
E. Maintain Photographic Records of Project Progress.
Photographs and slides are an invaluable record of
progress status and an excellent aid in claims prevention
or resolution. The Construction Coordinator will provide
photographic coverage of the project on a periodic basis
for progress and on a site specific basis for claims
documentation. Photographs will be compiled in albums
with date, description and photographer identified.
These albums will become part of the fipal project files.
6044/302/25 Page 7-3
F. Process Change Orders and Contract Modifications. The
Project Manager will have the responsibility and authori-
ty to negotiate Change Orders to the construction con-
tract and prepare Change Orders for approva 1 • However,
the fi na 1 approva 1 authority wi 11 remain with the Power
Authority•s Contracting Officer. The Construction
Coordinator will have authority to issue directives to
the Contractor after review and concurrence by the
Project Manager. Change orders will be identified,
processed and resolved as expeditiously as possible. All
change orders/modifications will be forward priced
whenever possible.
6044/302/26 Page 7-4
8-1 GENERAL
SECTION VIII
CHESTER LAKE MANAGEMENT PLAN
PROJECT TRANSFER
Upon completion of all construction activities and final
acceptance by the Power Authority, the project will be trans-
ferred to the Metlakatla Indian Community. The Community will
then become responsible for the operations and maintenance of
the facility.
All terms and conditions relating to the transfer of the
project will be made part of the Power Authority/Metlakatla
Chester Lake Agreement between the Power Authority and the
Metlakatla Indian Community, which will be negotiated prior to
project construction.
8-2 OPERATION AND MAINTENANCE TRAINING
As part of the facility transfer, the Power Authority through
the Design Engineer will provide operations and maintenance
training to the Community. Start-up, and operations and
maintenance manuals will also be provided.
8-3 PROJECT RECORDS
The completed project records will be retained by the Power
Authority in the event the project is someday developed into a
hydropower facility. Copies of the as-built drawings, vendor
instructions, O&M manu a 1 s and other documents necessary to
operate and maintain the facility will be provided to the
Metlakatla Indian Community.
6044/302/27 Page 8-1
SECTION IX
CHESTER LAKE MANAGEMENT PLAN
PROJECT MILESTONES
The project milestones for the Chester Lake Dam Replacement Project
are:
Milestone
Board Approval
Negotiate Change Order for Design
Begin Design
50% Design Review
90% Design Review
Issue Invitation to Bid for Construction
Bid Opening
Award Contract/NTP for Construction
Start Construction
Complete Construction
6044/302/28 Page 9-1
Date
13 December 1984
17 December 1984
1 January 1985
15 February, 1985
15 March 1985
15 April 1985
1 June 1985
15 June 1985
1 July 1985
31 October 1985
Construction Costs:
1. Mobilization
2. Access
TABLE 10-1
PROJECT COST ESTIMATE
3. Dam, Spillway of Intake
4. Water Supply
5. Camp
6. Indirect Cost
7. Profit
Total Construction Cost
Engineering (@ 8%)
APA Construction Management (@ 5%)
APA Administration (@ 4%)
Subtotal
Contingency (@ 20%)
Total Project Cost
Appropriated Funds Available
6044/302/30
$ 190,000
600,000
619,000
27,000
335,000
226,000
300,000
$2,297,000
184,000
115,000
92,000
$2,688,000
538,000
$3,226,000
$3,300,000
10-1 COST ESTIMATE
SECTION X
CHESTER LAKE MANAGEMENT
PROJECT COST ESTIMATE
The Project Cost Estimate for the Chester Lake Dam Replacement
Project is summarized in Table 10-1. This estimate is based
upon the recommended Design Alternative (Option 28):
construction of a concrete gravity-arch dam, elevation
850 ft MSL. The total estimated project cost is $3,226,000.
which is less than the $3,300,000. of appropriated project
funding currently available.
6044/302/29 Page 10-1