Loading...
HomeMy WebLinkAboutPtarmigan Lake Proposed Hydroelectric Project; Reconnaissance Report 2009Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report Prepared for: Kenai Hydro, LLC HDR Alaska, Inc. 2525 C Street, Suite 305 Anchorage, AK 99503 March 2009 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report Table of Contents Introduction .......................................................................................................................... I Project Area Previous Studies ................................................................................................................... 2 Environmental Considerations ............................................................................................. 3 Fish Resources ...................................................................................................................... 3 Wetlands ................................................................................................................................ 4 Hydrology and Water Quality ............................................................................................ 4 Recreation ............................................................................................................................ 5 Subsistence, Cultural and Historical Resources ................................................................... 7 Subsistence ........................................................................................................................... 7 Cultural and historic resources ........................................................................................... 7 Land Ownership, Mining Claims, and Water Rights ........................................................... 7 Project Arrangement Alternatives ........................................................................................ 8 Alternative 1 : Lake Tap ...................................................................................................... 8 Alternative 2: Penstock ....................................................................................................... 8 Summary of Alternatives .................................................................................................... 9 Turbine Sizing ...................................................................................................................... 9 Energy Generation ............................................................................................................... 9 Results ................................................................................................................................. 10 Cost Estimates .................................................................................................................... I 0 Assumptions ....................................................................................................................... ! 0 Results ................................................................................................................................. 11 Results ................................................................................................................................. 11 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report Economic Evaluation and Alternatives Ranking ............................................................... 12 Conclusions ........................................................................................................................ 12 References .......................................................................................................................... 13 Tables ................................................................................................................................ 14 Figures ................................................................................................................................ 20 Appendix A -Land Status Information ............................................................................. 28 Appendix B -Energy Calculations .................................................................................... 31 Appendix C -Cost Information ......................................................................................... 50 Appendix D -Project Photographs .................................................................................... 58 List of Tables Table 1. Maximum counts of Chinook and Sockeye salmon adults during stream surveys on Ptarmigan Creek* ........................................................................... 15 Table 2. Water temperature measurements at Ptarmigan Creek, 1950 to 1958 (from AEIDC 1983, source USGS 1981) .................................................................... 16 Table 3. Manual Instantaneous Flow Measurements.* ..................................................... 16 Table 4. USFS campgrounds on the Kenai Peninsula ...................................................... 17 Table 5. USPS-maintained trails on the Kenai Peninsula ................................................. 17 Table 6. Parameters for the two alternatives considered at Ptarmigan Lake. Elevations of maximum headwater (HW), minimum HW, tailwater elevation and net head (in feet) are given for each alternative. Design flow (cfs), capacity (MW), average inflow (cfs), and active storage (acre-feet, AF) are detailed for each project.. ..................................................................... 18 Table 7. Energy generation estimate summary for the alternatives considered. Capacity (MW) and annual energy production (GWh) are shown for each alternative. The modeled plant factor and seasonal benefit are also given for each alternative. For details of energy calculations, see Appendix B. ....... 18 Table 8. Reconnaissance-level cost estimates for all alternatives. Rated capacity (MW) and estimated project cost are presented for each alternative in millions of dollars (for details of cost estimates, see Appendix B). Cost estimates assumed a 0% minimum instream flow requirement (0 MIF) .......... 19 Table 9. Estimated energy cost ($/KWh), economic rank and environmental rank of all alternatives considered (for details of cost estimates, see Appendix B). Energy cost estimate assumed a 0% minimum instream flow requirement (0 MIF) .............................................................................................................. 19 11 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report List of Figures Figure 1. General location of proposed hydroelectric facilities at Ptarmigan Lake on the Kenai Peninsula, Alaska .............................................................................. 21 Figure 2. The anadromous reach of Ptarmigan Creek. The anadromous reach is defined as the section of stream in which anadromous fish are documented by the A WC; Johnson and Daigneault 2008) .................................................... 22 Figure 3. Average monthly flow data at Ptarmigan Creek. Average annual flow (for period of record 1947-1958, from USGS gauge #5244000) is shown as a solid horizontal line (103 cfs) ........................................................................... 23 Figure 4. Flow duration curve for Ptarmigan Creek. Percent exceedence, the value of the x-axis, is the percent of the time flow surpasses the value on the y-axis. This curve was generated using data from the period 194 7-1958, from USGS gauge #5244000 ..................................................................................... 23 Figure 5. Ptarmigan Creek historic discharge data from USGS gage 15244000 (1947- 1958) and HDR 2008 manual instantaneous flow measurements. Mean discharge (heavy blue line), 10% flow exceedence (dashed aqua line), and 90% flow exceedence (pink line) are shown for historical data. HDR 2008 manual stream flow measurements are shown as black dots ............................ 24 Figure 6. Private parcels of Ptarmigan Lake area. State and Federal lands are shown by yellow. Private properties are denoted by other colors ............................... 25 Figure 7. Water rights and mineral claims in the Ptarmigan Lake area. Federal mining claims are shown by yellow shading. Aqua shading denotes state mining claims .................................................................................................... 26 Figure 8. Alternative 1 for the proposed project at Ptarmigan Lake. Location of intake at approximately elevation 755 ft, possible tunnel route, powerhouse location and proposed access routes are shown above ...................................... 27 iii ADF&G AEIDC AHRS APA AWC BLM oc cfs em Of DNR EPA FERC ft G&A GWh HEP m KPB kWh LLC mi mm MSL MW MWh NWI O&M RVDs US ACE USFS USFWS USGS Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report Acronyms and Abbreviations Alaska Department of Fish and Game Arctic Environmental Information and Data Center (University of Alaska) Alaska Heritage Resources Survey Alaska Power Authority Anadromous Waters Catalog Bureau of Land Management Degrees Celsius Cubic feet per second centimeter Degrees Fahrenheit Alaska Department of Natural Resources Environmental Protection Agency Federal Energy Regulatory Commission feet general and administrative Gigawatt-hours Hydroelectric Evaluation Program inch Kenai Peninsula Borough kilowatt-hours Limited liability company mile millimeter Mean sea level Megawatt Megawatt-hours National Wetlands Inventory Operations & maintenance Recreation visitor days U.S. Army Corps of Engineers U.S. Forest Service U.S. Fish and Wildlife Service U.S. Geological Survey IV Introduction Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report Kenai Hydro LLC (KHL) contracted with HDR Alaska, Inc. to evaluate the feasibility of small- scale hydroelectric projects at Crescent Lake, Ptarmigan Lake, Falls Creek, and Grant Lake near Moose Pass, Alaska (Figure 1 ). This reconnaissance report examines the viability of small-scale hydroelectric energy generation at Ptarmigan Lake that would minimize environmental and other impacts. A team consisting of engineers and environmental scientists made reconnaissance-level site visits and analyzed existing information in order to determine if further feasibility analyses were appropriate based on potential constructability, cost effectiveness, and potential environmental impacts. The scope of work defined for this assignment included: • Field reconnaissance by team members; • Review of available project documentation and related information; • Development of conceptual alternatives; • Review of existing hydraulic and hydrologic parameters; • Estimation of energy production and project costs; • Preparation of this reconnaissance report. This report should be considered a high-level overview intended to identify projects which demonstrate a basic measure of feasibility and to eliminate projects that have evident fatal flaws from an engineering and environmental perspective; this report also provides information to enable KHL to determine economic feasibility. Project Area Ptarmigan Lake is located 6 miles (mi) south of the community of Moose Pass, Alaska (pop. 206), approximately 25 mi north of Seward, Alaska (pop. 3,0 16), and just east of the Seward Highway (State Route 9); this highway connects Anchorage (pop. 279,671) to Seward. The Alaska Railroad parallels the route of the Seward Highway, and is also adjacent to the project area. The town of Cooper Landing is located 24 mi to the northwest and is accessible via the Sterling Highway (State Route 1) which connects to the Seward Highway approximately I 0 mi northwest of Moose Pass. Ptarmigan Lake (I square mi) is located at an elevation of approximately 755 feet (ft) above mean sea level (MSL), and is approximately 200 feet deep along the center of most of its length. The lake is approximately 3.5 mi long and less than 0.5 mi wide. Total drainage area of Ptarmigan Lake is approximately 29.8 square mi at the lake outlet. Several glacial and clear water tributaries feed Ptarmigan Lake and drain the mountains on either side of the lake. The Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report lake is ringed by mountains of the Kenai Mountain Range to the east, north and south, with elevations of over 5,000 ft (USFWS 1961). A flat-bottom valley extends 3 mi from the upper end of the lake. Resident Dolly Varden (Salvelinus malma) are present in Ptarmigan Lake; the lake does not support anadromous fish (USFWS 1961; Johnson and Daigneault 2008). Ptarmigan Creek (mean monthly flow l09 cubic feet per second [ cfs] 194 7 -1958), Ptarmigan Lake's only outlet, runs west approximately 4.5 mi from the northwest end of Ptarmigan Lake to drain into the east end of Kenai Lake. Kenai Lake drains to the Kenai River at its west end near Cooper Landing. Anadromous and resident fish species are present in Ptarmigan Creek, including salmon, trout and others {Johnson and Daigneault 2008; USFWS 1961; Figure 2). Water was glacially turbid during early and mid summer and clear the rest of the year, with peak flow occurring in July (USFWS 1961 ). Previous Studies Investigations of potential hydropower production at Ptarmigan Lake date back to the 1940s. The USGS collected continuous stream flow data from 1947 to 1958 (USGS gage number 15244000) at the mouth of Ptarmigan Creek (see Hydrology and Water Quality below). The U.S. Geological Survey (USGS) conducted geologic investigations for a potential hydroelectric power site at Ptarmigan Lake in the 1950s (Piatker 1955). This study investigated suitability of geologic formations to support potential dams, and provided data for feasibility of drilling tunnels for potential lake taps in the area (Piatker 1955). Ptarmigan Lake was identified as a potential project in the 1981 U.S. Army Corps of Engineers (USACE) National Hydroelectric Power Resources Study (US ACE 1981 ). 1960, a hydropower project on Ptarmigan Lake was proposed by Chugach Electric Association (CEA). CEA was issued a preliminary permit for this project by the Federal Energy Regulatory Commission (FERC; permit no. 2262). The proposed plan of development included diversion of flows from Ptarmigan Creek, Grant Lake and Falls Creek to a common powerhouse located on Lower Trail Lake (USFWS 1961 ). Lake levels of both Grant and Ptarmigan Lakes were proposed to be raised to 770 ft elevation through construction of dams. Environmental studies were conducted by the USFWS from 1959 to 1960 at Ptarmigan and Grant Lakes and Falls Creek as a condition of this permit requiring CEA to "cooperate with the U.S. Fish and Wildlife Service (USFWS) and Alaska Department of Fish and Game (ADF&G) with the specific intent of developing a plan which will cause the least damage to fish and wildlife resources, with the primary consideration being given to maintenance of flows in the lower three mi of Ptarmigan Creek and lower one half mile of Grant Creek that are adequate tor the environmental requirements of fish life, and of designing such mitigation measures as may be desirable and reasonable (Article 1 0) Information was summarized in a document (USFWS 1961) in order to provide data from which articles could be promulgated for protection of fish and wildlife in the license application should CEA apply for a FERC license. At the time, the proposed hydropower facility at Ptarmigan Lake competed with larger federal hydropower developments (e.g. projects at Susitna River and Bradley Lake; USFWS 1961 ). Natural gas was discovered and developed on the Kenai 2 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report Peninsula around the same time and competed with the proposed project at Ptarmigan Lake. These other projects also had potential to provide for area power needs (USFWS 196 Proposals for development of hydropower by the Alaska Power Authority (APA, now Alaska Energy Authority) from the Susitna River were abandoned in 1986 due to inadequate financing 1• Bradley Lake was developed and began producing hydroelectric energy in 1991 ( 120 MW capacityi; today, southcentral Alaskan Railbelt communities are highly dependent on natural gas generation (AEA 2009). Our literature review has yielded no record of why the original proposal at Ptarmigan failed to proceed, but lack of funding for development is a likely cause, as in the case of the much larger potential project at the Susitna River. Environmental Considerations The following presents a general overview of potential expected environmental considerations for a hydroelectric project at Ptarmigan Lake. This section describes fish resources, wetlands, hydrology and water quality, recreation, subsistence, and cultural resources of the project area. The area is managed using several specific management plans, including the Chugach National Forest Plan (Meade 2006), Kenai River Comprehensive Management Plan (DNR 1998), and Kenai Borough Coastal Management Plan (KPB 2008). Another search for all relevant land management plans would be required as part of FERC licensing and by other required permitting processes. The USFWS (1961) conducted environmental baseline studies in the project area. For the purposes of this feasibility report, HDR Alaska did not conduct any environmental work beyond initial reconnaissance visits and stream gaging (see Section Hydrology and Water Quality). Fish Resources Ptarmigan Lake and Creek support different assemblages of fish species and possess varying quality and quantity of fish habitat. Only resident Dolly Varden have been found in Ptarmigan Lake and its tributary streams (USFWS 1961 ), whereas anadromous fish are present in Ptarmigan Creek (Johnson and Daigneault 2008). Ptarmigan Creek supports documented runs of spawning anadromous fish. The following sections provide information on fish resources for each water body. Chinook (Oncorhynchus tshawyscha), sockeye (0. nerka) and coho salmon (0. kisutch), were listed as present in Ptarmigan Creek in the A WC; Chinook and pink salmon ( 0. gorbuscha) were identified as spawning in the stream (Johnson and Daigneault 2008; Figure 2). The gradient of the stream is steep, dropping 319ft in 4.5 mi. Water was glacially turbid during early and mid- summer and clear the rest of the year, with peak flow occurring in July (USFWS 1961 ). The lower 2.9 mi of Ptarmigan Creek is classified as anadromous in the A WC (Johnson and Daigneault 2008). Sockeye salmon were seen within 0.5 mi of the lake outlet during an aerial 1 http://www.adn.com/264/story/286162.html 2 http://www.homerelectric.com/bradley%201ake.htm 3 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report survey (August 4, 1960), but a waterfall in the upper 0.5 mi of stream prevented upstream migration in 1959-60 (USFWS 1961 ). Juvenile Chinook and coho salmon, Dolly Varden and coastrange sculpin (Cottus aleuticus) were caught in minnow traps during periodic sampling from August 1959 to January 1961. Chinook fry appeared to use Ptarmigan Creek as rearing habitat for much of the year, and were more abundant than coho fry, which were also caught during summer and winter. Dolly Varden and sculpin were caught more often in summer than winter, indicating their presence in the stream during salmon spawning. Fishermen also caught more Dolly Varden during the summer months. Rainbow trout (Oncorhynchus mykiss) and Arctic grayling (Thymallus arcticus) were also caught by sport fishers (USFWS 1961 ). The USFWS ( 1961) reported spawning survey data tbr Ptarmigan Creek for the period 1954 to 1959; the highest actual count of sockeye salmon was on 25 August 1954, when 1,382 sockeye were counted (this count included an estimated 200 fish seen off the mouth of the river in Kenai Lake). Chinook and coho were also noted in these earlier surveys (0 to 9 Chinook, 0 to 3 coho). Spawning habitat was more favorable in the lower 3 mi of stream than in the upper 1.5 mi, which have a steeper gradient and higher water velocity (USFWS 1961). Records from ADF&G stream surveys conducted in most years from 1970 to 1994; maximum counts range from 0 to 31,516 sockeye in 1988 (Table I). Maximum count of Chinook was 300 fish in 1948.3 No detailed habitat descriptions or data were located in our literature review. USFWS reported that substrate varied from medium and small rubble to large rock (USFWS 1961 ). Wetlands No detailed wetland information was located in our review of literature on the Ptarmigan Lake drainage. No additional investigation of wetlands was performed for the purposes of this feasibility report. Data regarding wetlands resources in the project area are available from the National Wetlands Inventory (NWI) mapping system; evaluation of this database was outside the scope of this reconnaissance-level report. Hydrology and Water Quality The USGS installed a stream flow recording gage (#15244000) at the terminus of Ptarmigan Creek. This gage recorded continuously for 11 years between 194 7 and 1958. The drainage area at the gage site was 32.6 square mi. To estimate the hydrology of Ptarmigan Lake, the daily flows of gage 15244000 were scaled by the ratio of the drainage area at the outlet to create a simulated daily flow file. The average monthly flow and a flow duration curve representing this data is shown in Figures 3 and 4 below. Historical water quality data are limited to that collected by USFWS from 1959 and 1960. On July 14 and 15, 1960, water temperature in the tributaries of Ptarmigan Lake ranged from 39 °F 3 http://www.sf.adfg.state.ak.us/ SARR!FishDistrib/Nomination/FDDNomHome.cfm; nomination number 09-098 in Anadromous Waters Catalog. 4 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report to 50°F. Water temp was 4 7°F at the mouth of the braided stream entering the upper end of lake on July 16, 1960 (USFWS 1961 ). A temperature profile of Ptarmigan Lake taken July 15, 1960 showed a smooth decline in temperature from 58°F at the surface to 40°F at 230 ft with no thermocline. Water chemistry data obtained July 15, 1960, from the surface of Ptarmigan Lake found the following: 0.4 ppm C02, no C03, 31.0 ppm HC03, pH=7.4, and 5.4 ppm DG-(USFWS 1961). These values were similar to ones found in Grant Lake, corresponding to typical water quality of low-productivity Kenai Peninsula area water bodies (AEIDC 1983; APA 1984). Water temperatures at the outlet of Ptarmigan Lake were measured periodically in the fall of 1959 and 1960, and in summer 1960. In September and October, temperatures ranged from 41 to 48.0°F (n=4 days). In June, July and August, temperatures at the outlet varied from 49 to 54°F (n=5 days). Temperatures in Ptarmigan Creek were measured in fall and summer, and a limited amount of measurements were made in winter. From September to November, temperatures ranged from 39 to 49°F (n=9 days). In June, July and August, temperatures ranged from 48 to 54°F (n=9 days). In February, March and April, temperature was 32 to 33°F (n=3 days; USFWS 1961 ). Water temperatures were uniform from lake outlet to mouth of Ptarmigan Creek (USFWS 196 The USGS conducted intermittent water sampling at Ptarmigan Creek from 1950 to 1958 adjacent to the campground (USGS unpublished data 1981, cited by AEIDC 1983; Table 2). In December, January and February, water temperatures ranged from 32 to 34°F (n=4 days). Temperatures ranged from 36 to 48°F from April through May (n=4 days). Water temperatures during the summer months ranged from 50 to 52°F (n=4 days). During the fall months (September through November), temperatures ranged from 41 to 47°F (n=5 days; Table 2). HDR Alaska staff gathered instantaneous discharge data at Ptarmigan Creek on October 5 and October 24, 2008. Stream discharge measurements were taken at a site that allowed safe fording of the stream using standard USGS gauging protocols (Buchanan and Somers 1969). Manually collected discharge at Ptarmigan Creek site was 83.2 cfs on October 5 to 86.3 cfs on October 24, 2008 (Table 3). Measurements from 2008 were compiled with historical discharge data from USGS Gage 15244000 (1947-1958; Figure 5). Wetted stream width ranged from 44.4 (October 24, 2008) to 45.9 ft (October 5, 2008; Table 3). Recreation The Kenai Peninsula supports significant tourism from residents of the region, of Anchorage, of Alaska and from outside of Alaska. Kenai Peninsula Borough Coastal Management Plan (KPB 2008) includes the Ptarmigan Creek/Ptarmigan Lake as a designated recreation use area. The U.S. Forest Service (USFS) administers Chugach National Forest, which surrounds most of the project area; the project area is located within the Seward Ranger District. Peak use of area campgrounds (Table 4) coincides with salmon runs (APA 1984). Total recreational use of Seward Ranger District campgrounds in 1981 was estimated at 442,400 recreation visitor days (RVDs), representing 40% of l.1 million total RVDs for the entire Chugach National Forest (APA 1984). 5 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report The project area is currently developed for recreation, with campgrounds (Table 4) and trails (Table 5) in the project area maintained by the USFS. The Trail River campground consists of 88 campsites and is located approximately 0.6 mi north of the mouth of Ptarmigan Creek on the north eastern shore of Kenai Lake, on the west side of the Seward Highway (Table 5). Ptarmigan Creek Campground offers 16 campsites and is located adjacent to the creek on the east side to the Seward Highway (Table 5). Ptarmigan Lake trail is 7.1 mi long and connects Ptarmigan Creek campground to Ptarmigan Lake; the trail parallels the creek. This trail is used for fishing access and to reach Ptarmigan Lake. In 1959-1960, USFWS ( 1961) estimated that a limited amount of fishing for Dolly Varden occurs in Ptarmigan Lake. The project lies within the Ptarmigan/Grant Lake subunit of Chugach National Forest for backcountry motorized winter use, and receives very little use from any winter user group (motorized or non-motorized; Meade 2006). Helicopter skiing is also permitted in the Ptarmigan/Grant Lake subunit (Meade 2006). The USFWS (l961) reported that most Ptarmigan Creek fisherman target Dolly Varden. Lesser fisheries included Chinook salmon, rainbow trout and occasional Arctic grayling (USFWS 1961 ). Most fishing at Ptarmigan Creek in 1959-60 creel surveys took place during the last half of August. The most commonly caught fish were Dolly Varden (6-16 inches). A few rainbow trout were also caught (I 0-16 inches). Limited fishing for Chinook occurred at the mouth of Ptarmigan Creek and waters of Kenai Lake immediately adjacent to the stream mouth. Fisherman reported occasionally catching Arctic grayling, though they were not seen in surveys (USFWS 1961 ). Current 2009 sport fishing regulations allow sport fishing on Ptarmigan Creek June 11 May I. Ptarmigan Creek is closed to salmon fishing. Rainbow trout are limited to one fish less than 16 inches per day, and retention of Dolly Varden is limited to one fish less than 16 inches per day.4 Current sport fishing effort is unknown, but fishing for Dolly Varden and rainbow trout remain popular activities in the area.5 Habitat types are similar at both Grant and Ptarmigan Lakes (USFWS 1961). Game animals present in the area are likely the same as those present at Grant Lake and include mountain goat, black bear, brown bear, Dall sheep, and moose (APA 1984; USFWS). USFWS (1961) also reported that furbearers present were mink, beaver, marten, weasel, and wolverine, but that little or no trapping occurred. Small game animals available according to USFWS (l961) were ptarmigan, spruce grouse and snowshoe hare, with little or no hunting pressure. Current levels of trapping and small game hunting effort in the area are unknown. The USFS has plans for the lditarod Trail in the local area, and the location of these proposed improvements will need to be identified in future work. More detailed information assessing recreational use of the project and adjacent areas is needed in order to comply with requirements of the Federal Energy Regulatory Commission (FERC) license application. Detailed user data are available upon request from the USFS. 4 http://www.sf.adfg.state.ak.us/statewide/regulations/southcentral/SCkenai.pdf 5 Ptarmigan Creek Campground listing at http://www.reserveamerica.com/ 6 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report Subsistence, Cultural and Historical Resources Subsistence The Ptarmigan Lake drainage is not a designated subsistence use area according to the Kenai Peninsula Borough Coastal Management Plan (KPB 2008). Qualified residents of Cooper Landing may harvest moose in game units 7, 15A and 15B on the Kenai Peninsula under Federal subsistence regulations6 (the project area is located in game unit 7.) Federally-qualified subsistence users of Cooper Landing are also allowed to take salmon through a dip net/rod-and- reel fishery, and lake trout, Dolly Varden, and rainbow trout in the Kenai River through a rod- and-reel fishery 7 . A more detailed analysis of subsistence uses of the project area will be required by FERC licensing and other permitting processes. Cultural and historic resources Based on a preliminary investigation of Alaska Heritage Resources Survey (AHRS) data at the State Office of History and Archaeology, 65 cultural resource sites have been documented in the general vicinity of Grant Lake, Falls Creek, and Ptarmigan Lake. Several of the sites are listed on or eligible for the National Register of Historic Places. Most cultural resource sites are located along Upper and Lower Trail lakes and Trail River. A more detailed review of cultural and historic resources of the project area will be necessary to comply with requirements of the FERC license application process. Land Ownership, Mining Claims, and Water Rights HDR researched public land, private holdings, mineral claims and water rights of the Ptarmigan Lake area using information from Alaska Department of Natural Resources (DNR) land status maps 8 and case file abstracts9, the Bureau of Land Management (BLM)10 , the State Recorder's Office 11 and Kenai Peninsula Borough12 • Full documentation of the land research that was completed is included in Appendix A. Private property (37 parcels, Figure 6) is located in or near the project area; parcels are located near the mouth of Ptarmigan Creek and Kenai Lake, and along the Seward Highway (Figure 6). No private lands are known to overlap with project facility footprints (Figure 6). In response to 6 http://alaska.fws.gov/asm/newsrellr050208.html 7 http://alaska.fws.gov/asm/newsrel/r051107.html 8 http:/ /mapper .landrecords.info/ 9 http://dnr.alaska.gov/projectsllasllasmenu.cfm 10 http://sdms.ak.blm.gov/sdmsl 11 http:// dnr.alaska.gov/ssd/recofflsearch.cfm 12 http://www.borough.kenai.ak.us/assessingdeptf 7 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report correspondence with the USFS, several specific sites have been excluded from the overall project area. The sites excluded from the Ptarmigan project area include the Ptarmigan Lake campground and the Kenai Lake Work Center East. The proposed project does not impact either of these sites. One state mining claim is located north of Ptarmigan Creek (Figure 7). Four subsurface water rights are located along Ptarmigan Creek near the downstream boundary of project area (Figure 7). Two surface water rights are located just to the south of the subsurface rights (Figure 7). Project Arrangement Alternatives This section of the report describes arrangement of a project for hydroelectric generation at Falls Creek. Two project alternatives were evaluated for Ptarmigan Lake: • Alternative I -Lake Tap • Alternative 2 -Penstock Both alternatives assumed that a powerhouse would be located on Ptarmigan Creek at an elevation of approximately 550 ft. Neither alternative would feature storage, in order to avoid potential impacts on Ptarmigan Lake from fluctuating water levels that would result from storage and drawdown. The facility would be operated as a run-of-the-river project. In order to provide instream flows for fish habitat, water would be released from the lake; no storage in the lake was used in energy calculations. Three different flow regimes were used to calculate the energy available. Each alternative considered is discussed below. Alternative I: Lake Tap A lake tap would divert water from Ptarmigan Lake (Figure 8). A sluiceway capable of releasing incremental flows to Ptarmigan Creek and a spillway would be constructed at the natural outlet. A small gate house would be constructed near the lake and an 8-foot diameter 8,000-foot-long horseshoe shaped tunnel would convey water to the powerhouse. The powerhouse would be located around elevation 550 feet (Figure 8) and would contain a single Francis-type turbine, synchronous generator and associated switchgear and controls. A new 0.5-mi access route beginning near Kenai Lake would be used to reach the powerhouse (Figure 8). This route to the powerhouse would avoid private land adjacent to the Seward Highway in the area just south of Ptarmigan Creek. A new 2-mi access route would connect the powerhouse and the gate house, generally traversing the lower shoulder of Andy Simons Mountain. The gate house access route would minimize impacts to the surrounding environment and require minimal clearing. An overhead line would provide power transmission, following the access route from the powerhouse to the transmission line on the Seward Highway. Alternative 2: Penstock In this alternative, a small outlet structure would divert water from Ptarmigan Lake with a small outlet structure. A simple diversion structure/intake would be located at the natural outlet of Ptarmigan Lake. A sluiceway capable of releasing incremental environmental flows to 8 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report Ptarmigan Creek and a spillway would be located next to the intake. This structure would be designed to be as non-intrusive as possible, and to blend into the surrounding environment. Water would be conveyed to the powerhouse via a 2.5-mi, above ground steel penstock supported on saddle supports. In determining the size of the penstock, an attempt was made to optimize the size of the penstock and the power produced because of the low available head. The penstock was sized at 72 inches in diameter to significantly reduce head loss and create more power. The powerhouse and access route would be similar to the route in Alternative. Summary of Alternatives Table 6 summarizes the key parameters of alternatives that were evaluated. Maximum headwater was the same for both alternatives (755 ft, natural elevation of Ptarmigan Lake). Minimum headwater would also be 755 ft for both alternatives, since no storage or drawdown was proposed. All alternatives would include a tailwater elevation of 550ft (powerhouse located alongside Ptarmigan Creek). Since elevation was the same for both headwater and tailwater for both, alternatives, net head was the same ( 190 ft) for both alternatives (Table 6). Design flow was 220 cfs (see Turbine Sizing, below) both alternatives (Table 6). Each would have a similar capacity of 3.4 MW (Alternative l, lake tap) and 3.0 MW (Alternative 2, penstock). Both alternatives would use an average inflow of I 00 cfs, and neither alternative would create storage (Table 6). The differences in available energy are due to friction losses in the penstock alternative. Turbine Sizing For determining turbine size, the rated flow of the turbine was sized at approximately 15% on the flow duration curve (Figure 4), or 220 cfs. A sensitivity analysis indicated that design flows within I 0% of this assumption yield near identical energy generation estimates. As such, this assumption seems appropriate for this level of study. Other Alternatives Not Reviewed All alternatives developed for a Ptarmigan Lake project configuration were run of the river options; no options with additional storage in the lake or drawdown of the lake below its natural elevation were pursued. All options developed were developed assuming that instream flow would be required for fish in Ptarmigan Creek. Energy Generation The energy generation for Alternative I was estimated using HDR's proprietary software "Hydroelectric Evaluation Program" (HEP). HEP is specifically designed to model run-of-river operations. HEP uses tabulated daily flows, turbine and generator efficiencies, friction coefficients and physical parameters to simulate energy production for a period of stream flow record. Turbine and generator efficiencies are determined from tables. Output from HEP consists of effective capacity rating of the unit(s), simulated production in MWh, percent 9 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report operating time and overall plant factor. The following were the key assumptions used in modeling energy production: • For the alternatives with storage, a water-to-wire efficiency was assumed at 85%. For the generating equipment likely to be used at this project, turbine efficiencies can vary greatly depending on the flow. • Tailwater elevation was assumed to remain constant over all flows. In practice it would likely vary slightly; however there is not enough data to refine this assumption. • For daily simulations, head loss was calculated using the daily flow. For monthly simulations, the project was assumed to operate at the best gate position, corresponding to a head loss of7.5%. • The effect of instream flow requirements on energy production was estimated. The instream requirements were increased incrementally to show a range of power production, starting at 0% (no instream flow released to the stream, all flow is used to generate power), 33% of flow released to the stream, and 66% of flow released to the stream. Results Table 7 presents estimates of reconnaissance-level energy generation for 0%, 33% and 66% of average monthly flow for the two alternatives considered. Both alternatives would produce the most energy with 0% flow (Alternative 1: 9.7 GWh; Alternative 2: 8.9 GWh). Energy production estimates decreased as instream flow increased, with 3.2 GWh and 2.7 GWh produced annually by Alternatives 1 and 2, respectively, and 66% instream flow (Table 7). Cost Estimates An opinion of probable construction costs was derived for the project presented above. The approach used was to develop base work units and unit prices and then apply these units and prices consistently to the various project features. Assumptions The following assumptions were used in the cost estimate: • Indirect construction costs associated with engineering, construction management, licensing, permitting and the owner's internal costs were added to the direct construction cost estimate as either percentages or lump sum amounts. • Design engineering was assumed to be 10% of the total direct construction costs. • A lump sum value of $1,000,000 was assumed to provide environmental baseline studies in support of the FERC licensing application. As well as preparation for the FERC licensing application. 10 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report • The Owner's General Administration and Overhead of the design and construction was assumed to be 5% of the total direct construction costs. • Construction management was assumed to be 5% of the total direct construction costs. • A contingency of 30% was added to the total of the direct and indirect construction costs to reflect uncertainties of layout and design that wouldn't be resolved until later in the development process. • Interest accrued during a 3-year construction period was assumed to be 7% and was added to the total of the direct and indirect construction costs. • The estimate assumed first-year operations and maintenance (O&M) expense were comprised of the following three expenses o Total labor, expenses and owner's general and administrative (G&A) expenses were estimated at $300,000/yr 13 • o A repair and replacement fund of $50,000 was also included. o General liability and business interruption insurance was estimated at $1.00 per $100.00 of asset. • Cost estimates assumed that the project would be designed for un-manned operations and would be part of a larger organization; thereby the project would experience lower administrative expenses. On-site O&M labor would be limited to periodic inspections and seasonal maintenance. Results Table 6 presents the results of the reconnaissance level cost estimates for the two alternatives. It should be noted that the costs in Table 6 are relative and not absolute. It is estimated that Alternative 1 (Carter Creek) would cost $56.6 million, and that Alternative 2 (Crescent Creek) would cost $30.1 million in 2008 dollars (Table 6; see Appendix C, Cost Information). Results It is estimated that Alternative l (la:ke tap) would cost $70.2 million, and that Alternative 2 (penstock) would cost $38.3 million in 2008 dollars (Table 8; see Appendix C, Cost Information). Both of these estimates assumed no instream flow. 13 The estimated G&A expense could be reduced if several of the sites investigated are constructed which would allow some economies to be realized between the similar operations of the hydroelectric projects. 11 Ptarmigan Lake--Proposed Hydroelectric Project Reconnaissance Report Economic Evaluation and Alternatives Ranking A detailed economic evaluation was not included in the scope of this work. However, in order to provide a conceptual view of the economics, we have made some general assumptions. We have chosen to present the results as estimated annual cost per kilowatt-hour (kWh) in 2008 dollars. In deriving these costs, we assumed that the project could be financed through the issuance of bonds. Our assumption was that 100% of the debt would be financed at 6% for 30 years. Using these assumptions, the project would have a 2008 range in price of energy from $0..48/kWh to $0.61/kWh. For this evaluation, 0% minimum instream flow (MIF) was used as base case (Table 9). A complete analysis of cost of each of the alternatives requires not only consideration of the financial parameters but also an integration of environmental and licensing considerations. These latter concerns are not nearly as tangible as estimating costs and energy, so their impact on cost is subjective at this point. Based upon past experience, we have integrated them as fairly as possible into the ranking (Table 9). Conclusions While the tunnel option is the more expensive on a capital cost basis and cost per kWh basis, it is also the most benign when considering visual impacts of the project. When selecting the preferred option for this project, thought must be given to the tradeoff between each of the alternatives. Ultimately, the cost for generation must be evaluated by KHL and a decision must be made regarding the value of the power generated. 12 References Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report Alaska Department of Natural Resources (DNR). 1998. Kenai River Comprehensive Management Plan. Rep. from Division of Land and Division of Parks and Outdoor Recreation in conjunction with Alaska Department of Fish and Game, Habitat and Restoration Division, and Kenai Peninsula Borough. Anchorage, Alaska. Alaska Energy Authority (AEA). 2009. Alaska energy -a first step toward energy independence. A guide for Alaskan communities to utilize local energy resources. Prepared by Alaska Center for Energy and Power. Anchorage, AK. Alaska Power Authority (APA). 1984. Grant Lake Hydroelectric Project Detailed Feasibility Analysis. Volume 2. Environmental Report. Rep. from Ebasco Services Incorporated, Bellevue, Washington. Arctic Environmental Information and Data Center (AEIDC). 1983 Summary of environmental knowledge of the proposed Grant Lake hydroelectric project area. Final Report submitted to Ebasco Services, Inc., Redmond, Washington, University of Alaska, Anchorage, Alaska. Johnson, J. and M. Daigneault. 2008. Catalog of waters important for spawning, rearing, or migration of anadromous fishes -Southcentral Region, Effective June 2, 2008. Alaska Department of Fish and Game, Special Publication No. 08-05, Anchorage, Alaska. Kenai Peninsula Borough (KPB). 2008. Coastal management plan. Effective June 2008. Meade, J. 2006. Draft environmental impact statement: Kenai winter access. United States Department of Agriculture, Forest Service, Alaska Region, Chugach National Forest. Anchorage, Alaska Plafker, G. 1955. Geologic investigations of proposed power sites at Cooper, Grant, Ptarmigan, and Crescent Lakes, AK. U.S. Geological Survey Bulletin 1 031-A. U.S. Government Printing Office, Washington D.C. U.S. Army Corps of Engineers (USACE). 1981. National Hydroelectric Power Study, Regional Report. Regional Report: Volume XXIII Alaska. USACE North Pacific Division, Portland, Oregon and Alaska District, Anchorage, Alaska. U.S. Fish and Wildlife Service (USFWS). 1961. Ptarmigan and Grant Lakes and Falls Creek, Kenai Peninsula, Alaska, progress report on the fish and wildlife resources. Department of the Interior. Juneau, Alaska. U.S. Geological Survey (USGS). 1981. Surface water quality records, Southcentral Alaska, 1949-1974. Unpublished computer printout. 13 Ptarmigan Lake-Proposed Hydroelectric Project Reconnaissance Report -Tables Table 1. Maximum counts of Chinook and Sockeye salmon adults during stream surveys on Ptarmigan Creek* Year Chinook 1970 7 1971 9 1972 0 1973 No data 1974 13 1975 0 1976 11 1977 0 1978 1 1979 25 1980 8 1981 54 1982 No data 1983 31 1984 3 1985 No data 1987 12 1988 20 1989 5 1990 3 1991 No data 1992 No data 1994 No data (*From data on file with ADFG; Sockeye 3,000 45 0 I ,041 558 186 505 1,513 3,529 532 5,752 4,370 7,525 9,709 18,000 26,879 13,887 31,516 34,84 3,230 4,268 3,147 1,077 http://www .sf.adfg.state.ak. us/ SARR/FishDistrib/Nomination/FDDNomHome.cfm; nomination number 09-098 in Anadromous Waters Catalog). 15 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report-Tables Table 2. Water temperature measurements at Ptarmigan Creek, 1950 to 1958 (from AEIDC 1983, source USGS 1981 ). Date 07/10/1950 08/2211950 10/04/1950 02/2711952 05/20/1952 06/19/1952 09/16/1952 01/30/1953 04115/1953 08/06/1953 I 0/03/1957 ll/06/1957 12/ll/1957 01/22/1958 05/2111958 07/16/1958 10/20/1958 Time 21:45 17:20 22:00 20:00 19:00 6:00 17:00 12:30 10:55 10:00 9:30 9:45 18:00 Temperature COF) 50 52 44 32 44 44 47 32 36 52 42 41 34 32 48 51 50 Table 3. Manual Instantaneous Flow Measurements.* Date 10/5/2008 10/24/2008 Instantaneous Wetted stream discharge (cfs) width (ft) 83.2 86.3 45.9 44.4 *Collected by HDR staff, October 2008 16 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report-Tables Table 4. USFS campgrounds on the Kenai Peninsula. Location Number of sites Cooper Creek 26 Crescent Creek 9 Porcupine Creek 24 Primrose Creek 10 Ptarmigan Creek 16 Quartz Creek 45 Russian River 84 Tenderfoot Creek 27 Trail River 88 Table 5. USFS-maintained trails on the Kenai Peninsula. Location Length (mi) Carter Lake 3.5 Crescent Creek 6.4 Devil' s Pass 10 Grayling Lake 1.5 Gull Rock 5.1 Hope Point 2.5 Johnson Pass 23 Lost Lake 7.5 Primrose 7.5 Ptarmigan Creek 7.1 Rainbow Lake 0.24 17 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Tables Table 6. Parameters for the two alternatives considered at Ptarmigan Lake. Elevations of maximum headwater (HW), minimum HW, tailwater elevation and net head (in feet) are given for each alternative. Design flow (cfs), capacity (MW), average inflow (cfs), and active storage (acre-feet, AF) are detailed for each project. Alternative l 2 Description Lake tap Penstock Max. HW, ft 755 755 Min. HW, ft 755 755 Tailwater, ft 550 550 Net Head, ft 202 180 Design Flow, cfs 220 220 Capacity, MW 3.4 3.0 Avg. Inflow, cfs 100 100 Active Storage, AF 0 0 Table 7. Energy generation estimate summary for the alternatives considered. Capacity (MW) and annual energy production (GWh) are shown for each alternative. The modeled plant factor and seasonal benefit are also given for each alternative. For details of energy calculations, see Appendix B. Annual Energy (GWh) Average monthly Alternative l Alternative 2 flow for instream (lake tap) (penstock) flow 0% 9.7 8.9 33% 6.4 4.9 66% 3.2 2.6 18 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Tables Table 8. Reconnaissance-level cost estimates for all alternatives. Rated capacity (MW) and estimated project cost are presented for each alternative in millions of dollars (for details of cost estimates, see Appendix B). Cost estimates assumed a 0% minimum instream flow requirement (0 MIF). Alternative 1 (0 MIF) 2 (0 MIF) Description Lake tap Penstock Capacity (MW) 3.4 3.0 Estimated project cost $70.2M $38.3M Table 9. Estimated energy cost ($/KWh), economic rank and environmental rank of all alternatives considered (for details of cost estimates, see Appendix B). Energy cost estimate assumed a 0% minimum instream flow requirement(O MIF). Alternative 1 (0 MIF) 2 (0 MIF) Energy Cost $/kWh $0.61 $0.48 19 Economic rank 2 Environmental rank 2 0 N "~' ~> Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Figures Kenai Hyelro Feclllty Siting Project ----=---liD ___ ,. __ ..... ~ Figure 1. General location of proposed hydroelectric facilities at Ptarmigan Lake on the Kenai Peninsula, Alaska. 21 -Stream .a.a.a.. Anadromous Reach Miles 0 0.5 Land Status -Alaska Railroad 0ChugachNF 0 Slate of Alaska CJPrivate ~ Kenai Lake Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Figures ~""'~., ~ .... (1 Figure 2. The anadromous reach of Ptarmigan Creek. The anadromous reach is defined as the section of stream in which anadromous fish are documented by the A WC; Johnson and Daigneault 2008). 22 300 250 200 -.!!! (.J i'150 .S! u... 100 50 0 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Figures Ptarmigan Creek Average Monthly Flows 103 cfs mean annual flow OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP Figure 3. Average monthly flow data at Ptarmigan Creek. Average annual flow (for period of record 1947-1958, from USGS gauge #5244000) is shown as a solid horizontal line (103 cfs). 800 700 Ptarmigan Creek Flow Duration 600 -500 13 i 400 0 u::: 300 200 100 0 0 10 20 30 40 50 60 70 80 90 100 % Exceedance Figure 4. Flow duration curve for Ptarmigan Creek. Percent exceedence, the value of the x-axis, is the percent of the time flow surpasses the value on the y-axis. This curve was generated using data from the period 1947-1958, from USGS gauge #5244000. 23 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Figures Figure 5. Ptarmigan Creek historic discharge data from USGS gage 15244000 (1947-1958) and HDR 2008 manual instantaneous flow measurements. Mean discharge (heavy blue line), 10% ·flow exceedence (dashed aqua line), and 90% flow exceedence (pink line) are shown for historical data. HDR 2008 manual stream flow measurements are shown as black dots. 24 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Figures -- 1 LAND STATUS I KPB Parcels ...,.._:a -...~----....- Legend GJ .....,._, 01011---111!1-......-I.Micl -110-~1-4 -1211-C.. .... __ ._ -131--... 0IIIr -1110 _ _, ... --c-.:ill--336 LAOdgo-.....,.. Cobra ---"""""""'"' -3110c:-.iol_,llldg -820 .,_ Sc:hool -140-a..dl -8110 -Aooulyllldg ---.. .__ & ... - """"" -3(-4.100-) ; :---, ... 1 ~01Apl20011 --.....-.. --ICPII.--USF5 HR Figure 6. Private parcels ofPtarmigan Lake area. State and Federal lands are shown by yellow. Private properties are denoted by other colors. 25 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Figures LAND STATUS 1 Water Rights & Mineral Estate l'nljecl AID 2 flllc:..k- Kenoi 11n-11o111191.- Legend .. State Mining Claim .. Federal Mining Claim • Surface Wfll.er Right • Subsurface Water Right GJ Projet Area 2 ~ Lake/Pond ~ lceMass Prqect -2 (-2,600 -=-> ; L-__ ___,Miles 0 0.5 Dole: 22 ~ 2008 --~ sour..: ADNR. KPI!, GtiA lil\ 1 Figure 7. Water rights and mineral claims in the Ptarmigan Lake area. Federal mining claims are shown by yellow shading. Aqua shading denotes state mining claims. 26 ~}ill 3 R Alask a, Inc . /V" ~ ·..... (!I ~ Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Figures KHL SITE EVALUATION PROJECT OPTION DESCRIPTIONS PTARMIGAN LAKE ~ IDee 2008 r=;- Figure 8. Alternative 1 for the proposed project at Ptarmigan Lake. Location of intake at approximately elevation 755 ft, possible tunnel route, powerhouse location and proposed access routes are shown above. 27 = 0 ·-...... = OCI e N -~ = """i ri"J = ...... = ...... 00. "'0 = = ~ < ~ ... "'0 = ~ c. c. < I I I I I I I I Private Property PARCELID TAXAREA USUOE ACREAGE LEGAL T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513012 MAINTENANCE Vacant t. LOT9 - T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513013 MAINTENANCE Vacant 2 LOT 10 T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513014 MAINTENANCE Vacant t. LOT 11 T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513015 MAINTENANCE Vacant 2 LOT 12 T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513020 MAINTENANCE Vacant 0 LOT2A T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513021 MAINTENANCE Vacant 0 LOT 4A . T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513022 MAINTENANCE Vacant 1 LOT 5A T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67 -KPB ROAD · 1 00 Residential 0003532 LAWING EXTENSION U.S SURVEY 3532 12513023 MAINTENANCE Vacant 1 LOT 6A T 4N R 1W SEC 25 SEWARD MERIDIAN SW 67-KPB ROAD 1 00 Residential 0003532 LAWING EXTENSION U S SURVEY 3532 12513024 MAINTENANCE Vacant 1 LOT7A 67-KPB ROAD 1 00 Residential T 4N R 1W SEC 25 SEWARD MERIDIAN SW GOVT 12513025 MAINTENANCE Vacant 43 LOT 1 67 -KPB ROAD 1 00 Residential T 4N R 1W SEC 25 SEWARD MERIDIAN SW GOVT 12513026 MAINTENANCE Vacant 22 LOT2 67 -KPB ROAD 1 00 Residential T 4N R 1W SEC 25 SEWARD MERIDIAN SW GOVT 12513030 MAINTENANCE Vacant 14 LOT6 67-KPB ROAD 850 General T 4N R 1W SEC 25 SEWARD MERIDIAN SW 12513031 MAINTENANCE Institutional 25 0007398 US SURVEY 7398 LOT 2 67 -KPB ROAD 1 00 Residential T 4N R 1 E SEC 19 SEWARD MERIDIAN SW GOVT 12532104 MAINTENANCE Vacant 605 LOTS 1 THRU 4 & E1/2 & E112 W1/2 T 4N R 1E SEC 30 SEWARD MERIDIAN SW GOVT 67-KPB ROAD 1 00 Residential : LOTS 1 THRU 4 & NE1/4 NE1/4 & W1/2 NE1/4 & E1/2 12532105 MAINTENANCE Vacant 398 W1/2 67-Kt-'I::S KUAU 1100 Kes1oe nt1a1 T 4N R 1W SEC 24 I t.IIE~If)I,AN sw GOVT 12532413 MAINTENANCE Vacant 46 LOT 13 . -- State Mining Claims OWNER ADDRESS CllYSTATE I.ANDVAL UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $26,900 UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $26,900 UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $26,900 UNITED STATES BLM 222 W 7TH AvE STOP 13 ANCHORAGE, AK 99513 $26,900 ALASKA STATED N R 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 $11 ,500 UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $12,100 UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $18,700 UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $19,600 - UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $17,40( ALASKA STATED N R 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 $175,80C ALASKA STATED N R . 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 $123,80C ALASKA STATED N R 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 -$100,20C UNITED STATES BLM 222 W 7TH AVE STOP 13 ANCHORAGE, AK 99513 $136,90( ALASKA STATED N R 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 $296,500 .. ALASKA STATED N R 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 $278,500 ALASKA STATED N R 550 W 7TH AVE STE 650 ANCHORAGE, AK 99501 $133,400 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix A -Land Status IMPVAL ASSESSED TAXABLE PLAT $0 $26,90C $0 FEDERAL $0 $26,90C $0 FEDERAL $0 $26,900 $C FEDERAL $0 $26,900 $C FEDERAL $0 $11 ,500 $0 STATE $C $12,1 00 $0 FEDERAL $0 $18,700 $0 FEDERAL $0 $19,600 $0 FEDERAL $0 $17,400 $0 FEDERAL I $0 $175,800 $0 STATE $0 $123,800 $0 STATE $0 . $100,20C $0 STATE $73,700 . . $210,600 $0 FEDERAL $0 $296,50C $0 STATE $0 $278,500 $0 STATE $0 $133,400 $0 STATE PARCEt IDTTAXAREA I USEAGEI ACREAGI[: LEGAL OWNER ADDRESS I CITYSTATE I LANDVAL IIMPVAL I ASSESSED I TAXAB ... ETPLAT IADL 560916 40IS 4N 1E 19/ LAST SHOT THendrickson Aanes 29 I I I I I I I Surface Water Rights Subsurface Water Rights PARCEL ID I TAXAREAJ USEAGETACREAGE I LEGAL lAS 7272 IADL203436 ADL203436 IADL 213038 OWN~R Kaiser Janis J . Usda Forest Svc Chuaach National Forest Usda Forest Svc Chuaach National Forest Bair Betty H Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix A -Land Status ADDRESS I CITYSTATETLANDVAL IIMPVALI ASSESSED I TAXABLE I Pl:AT 30 ' ---, r.l':l t:"'' = 0 ..... ....... ~ -= c:.i -~ u ;;;..... t)J) -ClJ = ~ = ~ ..... "'0 = ClJ Q.; Q.; < Ptarmigan Cr. 0 MIF POWER GENERATION DATA FILE USED: PTARM.QCH MODEL DESCRIPTION PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 8000 96 .01 0 HEADWATER ELEV: 755 TAILWATER ELEV: 550 GROSS HEAD: 205 NET HEAD@ FULL LOAD: 202.3 NAMEPLATE CAPACITY (kW): 3386.6@ 1 POWER FACTOR STATION SERVICE LOSS: 1 TRANSFORMER LOSS: 1 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 -FRANCIS Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B-Energy Calculations GENERATOR SELECTED: GE MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FES MAR 0 0 0 0 0 0 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FES MAR 1948 1356.9 725.2 461.3 0.0 0.0 0.0 1949 1350.0 317.8 0.0 0.0 0.0 0.0 1950 944.8 1106.3 184.5 0.0 0.0 0.0 1951 219.4 0.0 0.0 0.0 0.0 0.0 1952 411.3 0.0 0.0 0.0 0.0 0.0 1953 1806.1 1699.5 551.3 0.0 0.0 0.0 1954 1208.4 0.0 0.0 0.0 0.0 0.0 1955 584.0 530.2 0.0 0.0 0.0 0.0 1956 0.0 0.0 0.0 0.0 0.0 0.0 1957 0.0 68.6 0.0 0.0 0.0 0.0 1958 1148.6 1301.6 79.1 0.0 0.0 0.0 APR 0 APR 13.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.7 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations MAY JUN JUL AUG SEP 0 0 0 0 0 MAY JUN JUL AUG SEP TOTAL 1234.5 2228.1 2361.7 2044.6 961.1 11386.6 642.3 2262.4 2418.9 2119.2 1868.6 10979.2 766.9 2020.9 2389.9 2336.7 1876.6 11626.6 556.2 1466.4 2252.5 1596.4 2336.6 8427.5 0.0 1472.9 2226.7 1688.5 865.9 6665.4 1528.5 2340.8 2418.9 2069.6 1295.1 13709.8 696.9 1976.8 2019.0 1929.2 863.4 8693.7 0.0 1484.5 2413.0 1871.2 953.6 7836.6 155.4 1495.6 2322.7 2216.3 1071.7 7261.8 697.1 2005.2 1742.0 1795.6 2246.1 8554.6 1018.1 2330.4 2349.2 2190.4 960.5 11390.7 AVERAGE 820.9 522.7 116.0 0.0 0.0 AVERAGE PLANT FACTOR: 0.33 AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 194 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES %LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 0.0 92.8 0.0 20 0.0 94.9 0.0 30 50.0 96.3 48.2 40 80.0 97.0 77.6 so 84.0 97.3 81.7 60 88.0 97.5 85.8 70 90.5 97.7 88.4 80 92.0 97.7 89.9 90 93.5 97.7 91.4 100 92.0 97.7 89.9 0.0 2.4 34 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix B-Energy Calculations 663.3 1916.7 2265.0 1987.1 1390.8 9684.8 Ptarmigan Cr. 33% MIF POWER GENERATION DATA FILE USED: PTARM.QCH MODEL DESCRIPTION PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 8000 96 .01 0 HEADWATER ELEV: 755 TAILWATER ELEV: 550 GROSS HEAD: 205 NET HEAD @ FULL LOAD: 202.3 NAMEPLATE CAPACITY (kW): 3386.6@ 1 POWER FACTOR STATION SERVICE LOSS: 1 TRANSFORMER LOSS: 1 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 FRANCIS Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations GENERATOR SELECTED: GE MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FEB MAR 34 27 13 7 5 4 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FEB MAR 1948 865.9 655.7 397.2 0.0 0.0 0.0 1949 806.3 81.8 0.0 0.0 0.0 0.0 1950 560.3 777.5 123.0 0.0 0.0 0.0 1951 13.3 0.0 0.0 0.0 0.0 0.0 1952 0.0 0.0 0.0 0.0 0.0 0.0 1953 1417.0 1389.6 365.2 0.0 0.0 0.0 1954 839.0 0.0 0.0 0.0 0.0 0.0 1955 284.9 343.0 0.0 0.0 0.0 0.0 1956 0.0 0.0 0.0 0.0 0.0 0.0 1957 0.0 0.0 0.0 0.0 0.0 0.0 1958 941.2 890.7 0.0 0.0 0.0 0.0 APR 7 APR 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 36 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report-Appendix B Energy Calculations MAY JUN JUL AUG SEP 27 75 84 64 52 MAY JUN JUL AUG SEP TOTAL 966.6 1862.7 1968.1 1348.2 193.3 8257.8 618.4 1779.0 2207.7 1559.7 1450.6 8503.4 467.3 1345.7 1746.8 1789.0 1372.5 8182.0 176.7 458.6 1530.4 642.1 1828.9 4650.0 0.0 673.8 1339.9 750.8 231.4 2996.0 1151.8 2339.1 2390.1 1438.9 524.7 11016.4 447.5 1066.3 938.6 1150.5 14.4 4456.4 0.0 715.7 2261.0 1092.2 448.2 5145.0 0.0 546.9 1565.4 1610.9 381.5 4104.6 483.7 1318.2 550.8 1011.0 1983.0 5346.7 468.2 2004.0 1697.7 1626.9 152.4 7781.2 AVERAGE 520.7 376.2 80.5 0.0 0.0 AVERAGE PLANT FACTOR: 0.22 AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 231 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES % LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 0.0 92.8 0.0 20 0.0 94.9 0.0 30 50.0 96.3 48.2 40 80.0 97.0 77.6 50 84.0 97.3 81.7 60 88.0 97.5 85.8 70 90.5 97.7 88.4 80 92.0 97.7 89.9 90 93.5 97.7 91.4 100 92.0 97.7 89.9 0.0 0.0 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations 434.6 1282.7 1654.2 1274.6 780.1 6403.6 Ptarmigan Cr. 66% MIF POWER GENERATION DATA FILE USED: PTARM.QCH MODEL DESCRIPTION PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 8000 96 .01 0 HEADWATER ELEV: 755 TAILWATER ELEV: 550 GROSS HEAD: 205 NET HEAD@ FULL LOAD: 202.3 NAMEPLATE CAPACITY (kW): 3386.6@ 1 POWER FACTOR STATION SERVICE LOSS: 1 TRANSFORMER LOSS: 1 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 -FRANCIS Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix B-Energy Calculations GENERATOR SELECTED: GE MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FEB MAR APR 68 54 26 14 10 8 14 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FEB MAR APR 1948 402.4 620.7 342.1 0.0 0.0 0.0 0.0 1949 402.4 0.0 0.0 0.0 0.0 0.0 0.0 1950 277.4 518.0 66.5 0.0 0.0 0.0 0.0 1951 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1952 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1953 989.6 1040.1 41.4 0.0 0.0 0.0 0.0 1954 587.6 0.0 0.0 0.0 0.0 0.0 0.0 1955 129.3 226.6 0.0 0.0 0.0 0.0 0.0 1956 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1957 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1958 802.3 517.6 0.0 0.0 0.0 0.0 0.0 39 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations MAY JUN JUL AUG SEP 54 150 168 128 104 MAY JUN JUL AUG SEP TOTAL 738.4 1181.2 1140.8 537.0 0.0 4962.7 586.4 817.0 1449.9 741.7 1051.6 5049.0 145.3 627.0 565.7 991.0 804.8 3995.8 0.0 0.0 458.0 0.0 1192.8 1650.7 0.0 112.4 216.6 179.0 0.0 508.0 710.1 2172.6 1855.2 606.6 130;6 7546.1 238.0 78.8 15.6 360.8 0.0 1280.7 0.0 242.2 1613.1 399.8 163.1 2774.0 0.0 18.7 430.0 645.1 14.4 1108.2 262.3 529.3 0.0 184.9 1551.5 2528.0 173.4 1263.0 528.2 743.2 0.0 4027.7 AVERAGE 326.4 265.7 40.9 0.0 0.0 AVERAGE PLANT FACTOR: 0.11 AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 291 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES % LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 0.0 92.8 0.0 20 0.0 94.9 0.0 30 50.0 96.3 48.2 40 80.0 97.0 77.6 50 84.0 97.3 81.7 60 88.0 97.5 85.8 70 90.5 97.7 88.4 80 92.0 97.7 89.9 90 93.5 97.7 91.4 100 92.0 97.7 89.9 0.0 0.0 40 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B-Energy Calculations 259.4 640.2 752.1 489.9 446.3 3221.0 Ptarmigan Cr. 0 MIF POWER GENERATION DATA FILE USED: PTARM.QCH MODEL DESCRIPTION PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 13000 58 .011 0 HEADWATER ELEV: 755 TAILWATER ELEV: 550 GROSS HEAD: 205 NET HEAD @ FULL LOAD: 125.9 NAMEPLATE CAPACITY (kW): 2107.4@ 1 POWER FACTOR STATION SERVICE LOSS: 1 TRANSFORMER LOSS: 1 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 -FRANCIS Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix B-Energy Calculations GENERATOR SELECTED: GE MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FEB MAR 0 0 0 0 0 0 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FEB MAR 1948 1118.1 480.2 343.3 0.0 0.0 0.0 1949 1117.1 297.1 0.0 0.0 0.0 0.0 1950 774.9 869.0 171.2 0.0 0.0 0.0 1951 207.4 0.0 0.0 0.0 0.0 0.0 1952 387.8 0.0 0.0 0.0 0.0 0.0 1953 1335.9 1288.7 517.5 0.0 0.0 0.0 1954 930.5 0.0 0.0 0.0 0.0 0.0 1955 509.8 431.5 0.0 0.0 0.0 0.0 1956 0.0 0.0 0.0 0.0 0.0 0.0 1957 0.0 65.7 0.0 0.0 0.0 0.0 1958 799.2 1042.3 76.0 0.0 0.0 0.0 APR 0 APR 12.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 12.3 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix B-Energy Calculations MAY JUN JUL AUG SEP 0 0 0 0 0 MAY JUN JUL AUG SEP TOTAL 925.0 1447.0 1500.8 1443.0 866.2 8136.2 405.7 1467.4 1505.2 1457.0 1321.5 7571.1 685.8 1403.4 1510.5 1507.3 1348.6 8270.7 516.9 1187.3 1479.0 1302.4 1458.0 6151.0 0.0 1099.8 1500.4 1294.4 762.9 5045.4 1207.7 1456.6 1505.2 1463.1 1077.1 9851.7 610.9 1414.1 1474.5 1410.6 796.7 6637.4 0.0 1064.1 1506.4 1378.8 772.4 5663.0 148.2 1188.9 1515.7 1503.8 928.6 5285.2 605.4 1409.4 1352.6 1391.5 1453.1 6277.7 916.9 1459.4 1508.3 1492.8 872.2 8179.3 AVERAGE 652.8 406.8 100.7 0.0 0.0 AVERAGE PLANT FACTOR: 0.38 AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 194 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES % LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 0.0 92.8 0.0 20 0.0 94.9 0.0 30 50.0 96.3 48.2 40 80.0 97.0 77.6 50 84.0 97.3 81.7 60 88.0 97.5 85.8 70 90.5 97.7 88.4 80 92.0 97.7 89.9 90 93.5 97.7 91.4 100 92.0 97.7 89.9 0.0 2.3 43 Ptarmigan Lake-Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations 547.5 1327.0 1487.1 1422.3 1059.8 7006.2 Ptarmigan Cr. 33% MIF POWER GENERATION DATA FILE USED: PTARM.QCH MODEL DESCRIPTION PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 13000 58 .011 0 HEADWATER ELEV: 755 TAILWATER ELEV: 550 GROSS HEAD: 205 NET HEAD @ FULL LOAD: 125.9 NAMEPLATE CAPACITY (kW): 2107.4@ 1 POWER FACTOR STATION SERVICE LOSS: 1 TRANSFORMER LOSS: 1 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 -FRANCIS Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix B-Energy Calculations GENERATOR SELECTED: GE MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FEB MAR APR 34 27 13 7 5 4 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FEB MAR APR 1948 744.6 421.9 288.6 0.0 0.0 0.0 0.0 1949 686.0 77.8 0.0 0.0 0.0 0.0 0.0 1950 465.2 598.2 115.4 0.0 0.0 0.0 0.0 1951 12.8 0.0 0.0 0.0 0.0 0.0 0.0 1952 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1953 1105.2 1112.6 348.4 0.0 0.0 0.0 0.0 1954 643.7 0.0 0.0 0.0 0.0 0.0 0.0 1955 256.6 288.3 0.0 0.0 0.0 0.0 0.0 1956 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1957 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1958 649.4 732.5 0.0 0.0 0.0 0.0 0.0 7 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B-Energy Calculations MAY JUN JUL AUG SEP 27 75 84 64 52 MAY JUN JUL AUG SEP TOTAL 775.4 1311.8 1382.8 1069.7 183.7 6178.4 389.9 1299.9 1491.0 1196.5 1028.5 6169.5 434.8 1027.3 1361.1 1370.3 1041.7 6414.0 168.3 420.0 1186.2 590.4 1410.3 3788.0 0.0 580.1 1133.6 648.6 213.3 2575.5 956.0 1457.2 1508.6 1139.0 459.9 8086.8 408.9 938.9 850.4 964.3 13.9 3820.1 0.0 589.0 1482.2 871.4 366.7 3854.3 0.0 499.3 1243.8 1274.7 355.0 3372.9 440.7 1019.4 503.7 875.9 1377.4 4217.0 431.2 1409.4 1313.4 1258.8 144.1 5938.8 AVERAGE 414.9 293.7 68.4 0.0 0.0 AVERAGE PLANT FACTOR: 0.27 AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 231 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES %LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 0.0 92.8 0.0 20 0.0 94.9 0.0 30 50.0 96.3 48.2 40 80.0 97.0 77.6 so 84.0 97.3 81.7 60 88.0 97.5 85.8 70 90.5 97.7 88.4 80 92.0 97.7 89.9 90 93.5 97.7 91.4 100 92.0 97.7 89.9 0.0 0.0 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix B Energy Calculations 364.1 959.3 1223.3 1023.6 599.5 4946.9 Ptarmigan Cr. 66% MIF POWER GENERATION DATA FILE USED: PTARM.QCH MODEL DESCRIPTION PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES 1 13000 58 .011 0 HEADWATER ELEV: 755 TAILWATER ELEV: 550 GROSS HEAD: 205 NET HEAD@ FULL LOAD: 125.9 NAMEPLATE CAPACITY (kW): 2107.4@ 1 POWER FACTOR STATION SERVICE LOSS: 1 TRANSFORMER LOSS: 1 TRANSMISSION LOSS: 1 SCHEDULED DOWN TIME: 1 TURBINE SELECTED: 1 -FRANCIS Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations GENERATOR SELECTED: GE MINIMUM INSTREAM FLOWS OCT NOV DEC JAN FEB MAR APR 68 54 26 14 10 8 14 SIMULATED PRODUCTION IN MEGAWATT-HOURS YEAR OCT NOV DEC JAN FEB MAR APR 1948 354.3 411.8 244.7 0.0 0.0 0.0 0.0 1949 349.3 0.0 0.0 0.0 0.0 0.0 0.0 1950 231.2 372.0 63.0 0.0 0.0 0.0 0.0 1951 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1952 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1953 788.6 859.1 39.3 0.0 0.0 0.0 0.0 1954 440.6 0.0 0.0 0.0 0.0 0.0 0.0 1955 121.4 198.6 0.0 0.0 0.0 0.0 0.0 1956 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1957 0.0 0.0 0.0 0.0 0.0 0.0 o.o 1958 566.5 431.7 0.0 0.0 0.0 0.0 0.0 48 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix B Energy Calculations MAY JUN JUL AUG SEP 54 150 168 128 104 MAY JUN JUL AUG SEP TOTAL 631.0 896.7 866.2 447.8 0.0 3852.7 390.1 662.6 1154.7 629.6 709.3 3895.7 138.0 486.2 520.4 834.2 618.3 3263.3 0.0 0.0 413.4 0.0 1060.4 1473.8 0.0 106.0 204.1 168.4 0.0 478.5 605.3 1430.0 1382.8 468.4 117.3 5690.8 225.1 75 .o 15.0 326.7 0.0 1082.3 0.0 228.5 1218.9 346.7 137.4 2251.5 0.0 17.8 367.0 569.6 13.9 968.3 247.4 426.9 0.0 146.6 1138.1 1959.0 161.5 971.7 469.0 600.0 0.0 3200.4 AVERAGE 259.3 206.7 31.6 0.0 0.0 AVERAGE PLANT FACTOR: 0.14 AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 291 THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES %LOAD TURBINE GENERATOR COMBINED ---------------------------------------- 0 0.0 0.0 0.0 10 0.0 92.8 0.0 20 0.0 94.9 0.0 30 50.0 96.3 48.2 40 80.0 97.0 77.6 50 84.0 97.3 81.7 60 88.0 97.5 85.8 70 90.5 97.7 88.4 80 92.0 97.7 89.9 90 93.5 97.7 91.4 100 92.0 97.7 89.9 0.0 0.0 49 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix B -Energy Calculations 218.0 482.0 601.0 412.5 345.0 2556.0 0 tr) = 0 ... ..... = e -~ = """" ..... ~ 0 u I u ~ ... -e = ~ ~ ~ < I Item 330 331 .1 332 .1 .2 .3 .4 .5 .1 .2 .3 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix C Cost Information PTARMIGAN LAKE OPINION OF PROBABLE COST Alternative 1 • Lake Tap I auanttty I Unit I Unit Cost Amount LAND AND LAND RIGHTS . 1 Land Rights • Generation Plant 1 LS $ 50,000 $ 50,000 .2 Special use permits 1 LS $ 50,000 $ 50,000 .3 SuMiying 1 LS $ 100,000 $ 100,000 STRUCTURES AND IMPROVEMENTS POWERHOUSE $ . 1 Excavation 1900 CY $ 150 $ 285,000 .2 Concrete (ind. reinforcement) 275 CY $ 1,200 $ 330,000 .3 Metal Building 2500 SF $ 150 s 375,000 .4 MI$C. Metals 1 LS $ 50,000 $ 50,000 .5 HVAC, Plumbing & Eledrical 1 LS $ 50,000 $ 50,000 .6 Grounding Grid 1 LS $ 25,000 $ 25.000 . 7 Fire Protection 1 LS $ 25,000 s 25,000 RESERVOIRS, DAMS AND WATERWAYS SITE WORK $ . 1 Clearing/Drainage/Erosion Control 1 LS $ 50,000 $ 50,000 DAM AND SPILLWAY s . 1 Excavation CY $ 150 s .2 Care of Water/Diversion LS $ 100,000 s .3 Concrete (structural) CY $ 1.200 $ .4 Concrete (mass) CY $ 1,000 $ INTAKE $ . 1 Excavation CY $ 150 s . 2 Care of Water/Diversion LS $ 100,000 $ .3 Trash racks 1 LS $ 50,000 $ 50,000 .4 Control Gates/Valve wlopen~tor LS $ 150.000 $ .5 Concrete (struc1ural) CY $ 1,200 s .6 Concrete (mass) CY $ 1,000 $ . 7 Mi$C. Metals LS $ 25,000 $ .8 Siphon pipe (marl & installation) LF $ 750 $ . 9 Siphon electrical & mechanical LS $ 100,000 s SLUICEWAY $ . 1 Excavation CY $ 150 $ .2 Care of Water/Diversion LS $ 100,000 $ . 3 Sluice Gate wloperator LS $ 100,000 $ .4 Concrete ( struc1ural) CY $ 1.200 $ WATER CONDUCTORS AND ACCESSORIES PENSTOCK $ .a Clearing ACRE $ 25,000 $ .b Steel penstock materiel 250 LF $ 310 $ 77.500 .c Concrate (thrust blocks and supports) CY $ 1.200 $ .d Penstock installation 250 LF $ 150 $ 37,500 .e Slope stabilization Ml $ 250.000 $ .f Surge tank LS $ 100.000 $ TUNNEL .a Excavation 8000 LF $ 2,500 $ 20,000,000 .b Tunnel Support 5000 LF $ 500 $ 2,500,000 .c Lining 2000 LF $ 1,000 $ 2.000,000 .d Gateshaft excavation 300 LF $ 2.000 $ 600.000 .e Shaft support and lining 300 LF $ 500 $ 150,000 .f Concrate (structural) 1100 CY $ 1,200 $ 1,320,000 .g Gates 1 LS $ 500,000 $ 500,000 .h Lake tap 1 LS $ 1,500,000 s 1,500,000 .I Gate house 1 LS $ 150,000 s 150.000 TAILRACE .a Excavation 1000 CY $ 35 s 35,000 .b Support and lining 1 LS $ 75,000 $ 75,000 51 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix C-Cost information --·-············~·-·········- 333 WATERWHEELS, TURBINES AND GENERATORS .1 Supply 1 LS $ 1,530,000 s 1,530,000 .2 Install 1 LS $ 500,000 $ 500.000 334 ACCESSORY ELECTRICAL EQUIPMENl .1 Switchgear 1 LS $ 150,000 $ 150.000 .2 Station Service 1 LS $ 150,000 $ 150,000 .3 Control Panel 1 LS $ 250,000 $ 250,000 .4 Conduit/wires/cables 1 LS $ 150,000 $ 150,000 .5 Power to intake 1 LS $ 75,000 $ 75,000 335 MISC. POWER PLANT EQUIPMENT .1 Cooling Water System 1 LS $ 25,000 $ 25,000 .2 Powerhouse crane 1 LS $ 250,000 $ 250,000 336 ROADS, RAILROADS AND BRIDGES .1 Highway to Powerhouse 0.8 Ml $ 500,000 $ 375,000 .2 Access to gate shaft 2.0 Ml $ 500.000 $ 1,000,000 .3 Bridge LS $ 200.000 $ .4 Clearing/Drainage/Erosion Control 1 LS $ 100.000 $ 100,000 350 LAND AND LAND RIGHTS .1 Land rights -transmission line 1 LS $ 10,000 $ 10,000 STRUCTURESANDIMPROVEMENTS 352 (TRANSMISSION FACILITY) .1 Substation foundations 1 LS $ 50,000 $ 50,000 .2 Oil spill containment 1 LS $ 25,000 $ 25,000 .3 Grounding grid 1 LS $ 10,000 $ 10,000 353 STATION EQUIPMENT .1 Main transformer 1 LS $ 120,000 s 120,000 .2 Accessory switchgear equipment 1 LS $ 350,000 $ 350,000 356 OVERHEAD CONDUCTORS & DEVICES .1 New pole line 0.5 Ml $ 750,000 s 375,000 Total Direct Construction Costs s 35,900,000 Design Engineering 10% $ 3,590,000 FERC and other licensing $ 1,000,000 Owner's General Administration & overhead 5% $ 1.795.000 Construction Management 5% $ 1,795,000 Subtotal $ 44,080,000 Contingency 30% $ 13,224,000 Interest during construction 7% $ 12.896.000 2008 Estimated Project Cost $ 70,200,000 Annual Energy, MWh 9,700 Debt Service $ 5,099,954 O&M $ 790,800 2008 Cost of Energy. $/kWh $ 0.607 52 I Item 330 331 .1 332 .1 .2 .3 .4 .5 .1 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix C-Cost Information PTARMIGAN LAKE OPINION OF PROBABLE COST Alternative 2 • Penstock I auantlty I Unit I Unit Cost Amount LAND AND LAND RIGHTS .1 Land Rights -Generation Plant 1 LS $ 50,000 s 50.000 .2 Special use permits 1 LS $ 50,000 s 50,000 .3 Surveying 1 LS $ 100,000 s 100.000 STRUCTURES AND IMPROVEMENTS POWERHOUSE s . 1 Excavation 1900 CY $ 150 s 285,000 .2 Concrete (incl. reinforcement) 280 CY $ 1,200 s 336,000 . 3 Metal Building 2500 SF $ 150 $ 375.000 .4 Misc. Metals 1 LS $ 50,000 s 50,000 .5 HVAC. Plumbing & Electrical 1 LS $ 50,000 s 50,000 .6 Grounding Grid 1 LS $ 25,000 $ 25,000 . 7 Fire Protection 1 LS $ 25,000 s 25,000 RESERVOIRS, DAMS AND WATERWAYS SITE WORK s .1 Clearing/Drainage/Erosion Control 1 LS $ 50,000 s 50.000 DAM AND SPILLWAY s . 1 Excavation 500 CY $ 150 $ 75,000 .2 Care of Water/Diversion 1 LS $ 100,000 $ 100,000 .3 Concrete (structural) CY $ 1,200 $ .4 Concrete (mass) 400 CY $ 1,000 $ 400,000 INTAKE s . 1 Excavation 375 CY $ 150 s 56,250 .2 Care of Water/Diversion 1 LS $ 100,000 $ 100.000 .3 Trash racks 1 LS $ 50,000 s 50,000 .4 Control Gates/Valve wloperator 1 LS $ 150,000 $ 150,000 .5 Concrete {structural) 100 CY $ 1,200 s 120,000 .6 Concrete (mass) CY $ 1,000 s . 7 Misc. Metals 1 LS $ 25,000 s 25,000 .8 Siphon pipe (mat'l & installation) 500 LF $ 750 s 375,000 .9 Siphon electrical & mechanical 1 LS $ 100,000 $ 100.000 SLUICEWAY s .1 Excavation 300 CY $ 150 $ 45.000 .2 Care of Water/Diversion 1 LS $ 100,000 $ 100,000 .3 Sluice Gate wloperator 1 LS $ 100,000 s 100,000 .4 Concrete (structural) 100 CY $ 1,200 $ 120,000 WATER CONDUCTORS AND ACCESSORIES PENSTOCK $ .a Clearing 30 ACRE $ 25,000 $ 750,000 .b Steel penstock material 13000 LF $ 310 $ 4,030.000 .c Concrete (thrust blocks and supportS) 2300 CY $ 1.200 $ 2.780,000 .d Penstock installation 13000 LF $ 150 $ 1,950,000 .e Slope stabilion~tion 3 Ml $ 250,000 $ 625,000 .f Surge tank 1 LS $ 100,000 $ 100,000 53 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix C Cost lf!formation .2 TUNNEL .a Excavation LF $ .b Tunnel Support LF $ .c Lining LF $ .3 TAILRACE .a Excavation 1 LS $ 25,000 $ 25,000 .b Support and lining 1 LS $ 25,000 $ 25,000 333 WATERWHEELS, TURBINES AND GENERATORS .1 Supply 1 LS $ 1,350,000 $ 1,350,000 .2 Install 1 LS $ 500,000 $ 500,000 334 ACCESSORY ELECTRICAL EQUIPMENT .1 Switchgear 1 LS $ 150,000 $ 150,000 .2 Station Service 1 LS $ 150,000 $ 150.000 .3 Control Panel 1 LS $ 250,000 $ 250,000 .4 Conduit/wires/cables 1 LS $ 150,000 $ 150,000 .5 Power to intake 1 LS $ 75,000 $ 75,000 335 MISC. POWER PLANT EQUIPMENT .1 Cooling Water System 1 LS $ 25,000 $ 25.000 .2 Powerhouse crane 1 LS $ 250,000 $ 250.000 336 ROADS, RAILROADS AND BRIDGES .1 Highway to Powerhouse 0.75 Ml $ 500,000 $ 375,000 .2 Powerhouse to intake 2.50 Ml $ 500,000 $ 1,250,000 .3 Bridge 0 LS $ 200,000 $ .4 Clearing/Drainage/Erosion Control 1 LS $ 100,000 $ 100,000 350 LAND AND LAND RIGHTS .1 Land rights -transmission line 1 LS $ 10,000 $ 10,000 STRUCTURES AND IMPROVEMENTS 352 (TRANSMISSION FACILITY) .1 Substation foundations 1 LS $ 50,000 $ 50,000 .2 Oil spill containment 1 LS $ 25,000 $ 25.000 .3 Grounding grid 1 LS $ 10,000 $ 10.000 353 STATION EQUIPMENT .1 Main transformer 1 LS $ 100,000 $ 100,000 .2 Accessory switchgear equipment 1 LS $ 350,000 $ 350,000 356 OVERHEAD CONDUCTORS & DEVICES .1 New pole line 0.5 Ml $ 750,000 $ 375,000 Total Direct Construction Costs $ 19,200,000 Design Engineering 10% $ 1,920.000 FERC and other licensing $ 1,000,000 Owner's General Administration & overhead 5% $ 960.000 Construction Management 5% $ 960,000 Subtotal $ 24.040,000 Contingency 30% $ 7.212,000 Interest during construction 7% $ 7.034,000 2008 Estimated Project Cost $ 38,290,000 Annual Energy, MWh 7,006 Debt Service $ 2,781,727 O&M $ 590.400 2008 Cost of Energy, $/kWh $ 0.481 54 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix C Cost Information Dam Type Simple concrete gravity Crest Length 250ft Max height 9ft Crest width 1.5 Section length height area, sf vol, cy A 50% 100% 54 250 B 30% 80% 37 102 c 20% 50% 17 31 383 Excavation Width 27 Depth 2 Volume 500 cy Box Intake Length 30 Width 15 Height 15 Thickness, avg 1.5 Concrete volumes Floor 25 cy Walls 75 Total 100 cy Excavation 375 cy Sluiceway Length 30 Width 10 Height 18 Thickness, avg 2 Concrete volumes Floor 17 cy Walls 70 87 Excavation 300 cy 55 PENSTOCK Head Flow Vel, max Dia, req t, req t, handling t, min wt,ft area Cost Material Lining Coating Supports Span Length # Width, 2d Depth, .Sd Height, .5d Vol Thrust Blocks # Width, 2d Depth,2d Height, 2d Vol Total Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix C Cost Information 205ft 220 cfs 12 fps 72.0 inches 0.1777 0.2300 0.2300 162.6 lbs 18.8 $ 1.50 lb $243.87 $ 1.50 sf $ 28.27 $ 1.50 sf $ 28.27 $300.42 60ft 13000 217 12 3 3 866.66667 21.7 12 12 12 1386.6667 2253.3333 56 Ptarmigan Lake Proposed Hydroelectric Project Reconnaissance Report -Appendix C-Cost Information POWERHOUSE Powerhouse structure Prefabricated Metal Building ($/sf) Length Width Thickness Draft tube chamber Length Width Depth Thickness, avg Concrete Volumes Foundation Floor Prefabricated Metal Building ($/sf) 57 150 50 50 2 15 15 10 4 88.9 185.2 274.0741 375000 Excavation 1900 riJ -= 00 or, Q. = -btl 0 ... 0 -= =... ... ~ Qj ·s ,_ =... Q ~ ."""' "0 = Qj Q. ~ Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report -Appendix D -Project Photographs Ptarmigan Lake looking from the head water toward the natural outlet (NW). Ptarmigan Lake looking at the natural outlet. 59 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix D -Project Photographs Ptarmigan Lake looking at the natural outlet. Proposed intake at the natural outlet. Head of Ptarmigan Creek. Natural falls and constriction at diversion site. 60 Ptarmigan Lake -Proposed Hydroelectric Project Reconnaissance Report-Appendix D -Project P_hotographs Aerial view of recreation area and powerhouse location. 61