HomeMy WebLinkAboutSilver Lake Appendix 8 1992..
APPENDIX 8
Alternatives No. 8 and No. 9
Silver Lake Hydroelectric Project
APPE."l>IX 8
LIST OF TABLES
Table l -En~rgy ~lode! -Alternative A
Table 2 -En~rgy Model -Alternative B
Table 3 -Cost Estimate -Alternative A
Table ~ · Cost Estimate -Alternative B
Table 5 -O&M Cost Estimates
Table 6 -Results of Economic Caparison of Projects
Table 7 -Comparison of Alternatives
LIST OF FlGl..iRES
Figure 1 -Estimated Average Monthly Flows
Figure 2 -Silver Lake Storage Curve
LIST OF DRAWINGS
Drawing 1 -Silver Lake -Alternative A -Site Plan
Drawing 2 -Silver Lake -Alternative B -Site Plan
Appendix 8
Introduction
Silver Lake is located approximately 15 miles southwest of Valdez, A.K. The lake is
approximately 3 miles long. has a maximum width of about 0. 7 miles, and has a surface area
of about 978 acres at water surface elevation 306. The outlet of Silver Lake fonns the Duck
River which flows into Galena Bay.
Silver Lake was identified by the USGS in 1915 as having significant hydroelectric generating
potential. The project was most recently studied in 1982 as pan of the Cordova Power Supply
feasibility studies.
HDR was contracted by the Alaska Energy Authority in the summer of 1992 to incorporate the
alternative of a Silver Lake Hydroelectric Project into their Allison Lake Reconnaissance study
as a means of providing power to the City of Valdez, AK. This appendix contains an up-to-date
reconnaissance level estimate of the costs and energy production for two alternative Silver Lake
project arrangements as discussed below. The costs and energy production estimates were then
insened into the Allison Lake economic evaluation model and the results compared to the other
Allison Lake alternatives.
General Project Fearures
A variety of possible configurations for a hydroelectric project at Silver Lake have been
proposed in the past, each with different project features, dam height and energy output. To
select the configuration as the subject of this reconnaissance repon, HDR reviewed the extensive
literature developed by USGS, the Army Corps of Engineers, ud the Alaska Power Authority
in the 1982-83 time period. HDR also interviewed Mr. Thorn Fisher of Whitewater Engineering
of Bellingham, WA, who is the project proponent of a potential project on Silver Lake.
Since the completion of the draft Allison Lake Reconnaissance Study, the future energy demand
situation in Valdez has been clarified somewhat by the actual start of constnJction of the Petro
Star refinery (making the "high" load energy growth scenario much more likely). Annual
energy requirements of the refmery should average about 25 million kWh/year. lbat, with the
Valdez current diesel requirement of about IS million kWh/year, indicates that a Silver Lake
project of at least 40 million kWh/year would be desirable to be able to offset all diesel
generation, at least for some time into the future. A Silver Lake project with 45 million
kWh/year capacity or more would be desirable to allow diesel generation to be avoided at CVEA
for a longer period into the future.
Based upon these developments, HDR selected two basic Silver Lake Hydroelectric Project
configurations to be used for this reconnaissance evaluation. Alternative A is the largest of the
Page 1
Appendix 8
alternatives studied by Stone & Webster Engineering in their 1982-83 work (Reference 8). It
would incorporate a 125-foot-high RCC (roller-compacted concrete) dam, 6,000-feet of 108-inch
pipeline and a 15 MW powerhouse located at El. 65 on the Duck River. The powerhouse would
be equipped with three 5 MW Francis turbines. Transmission to Solomon Gulch would be via
approximately 22 miles of overhead transmission line. Annual generation would be about 44.8
million kWh/year as discussed below. Alternative B is the general project configuration being
proposed by Whitewater Engineering in 1992. It would consist of a l()()..foot·high RCC dam,
10,000-feet of 108-inch pipeline along the access road and a 14 MW powerhouse located at el.
10 on Reverse Creek. The powerhouse would be equipped with two 7 MW Francis turbines.
Transmission would be via 2.2 miles of overhead ttansmission line to Galena bay and then by
a submarine cable to Valdez. Annual generation would be about 48.8 million kWh/year. For
each alternative. selected turbine size was based on the anticipated peak demand load from
Valdez so the project could act as a backup to Solomon Gulch. Site plans of the two alternatives
can be found on Drawings 1 and 2 at the end of this appendix.
An alternative briefly considered was the concept of a tuMel and lake tap into Silver Lake with
no dam. This alternative has potential of producing about 29 million kWh/year. Compared to
the Allison Lake TuMel with Hydro option, this project would be more expensive both to build
and operate. It would require roughly the same tuMelling volume (shoner length but large
diameter), a much larger powerhouse (roughly 15 MW vs. 3.5 MW) and a much longer
transmission system. Since this alternative would be very costly and would not meet Valdez's
demand as described above, it was ruled out for funher study.
Presently, the only access to the Silver Lake area is by air or water. Each alternative plans to
make use of a new pennanent dock siruated on Galena Bay connected to the project site by about
2 miles of pennanent access road. The project would be operated remotely from Valdez. A
caretaker would be required to perform routine maintenance and observation tasks and would
live at or near the site.
Options for project configurations might include a concrete gravity or arch or embankment dam
instead of the RCC dam proposed, or a ttlMel to replace the pipeline as a means of conveyance.
It is felt that generally these options would be more of a technical challenge and would be more
costly than the configurations studied here. The selected configurations, in our opinion.
represent projects that are large enough to displace the diesel requirements for CVEA while
remaining technically straight-forward. Although .~veral optional configurations for each
alternative exist, optimization of the design is beyond the scope of this study.
Hydrolo&y
Hydrologic information for the Silver Lake basin is very limited. Stream gage data for Duck
Page 2
...
-.. ---
...
• ..
• -
•
•
...
• ..
.. -
..
-
..
Appendix 8
River is only available for a seven·month period in 1913 and a five-month period in 1982.
Nonnally, at least a lO·year period of record is desired to synthesize flow records with any
confidence for a given stream. Due to the lack of data, we have chosen to make use of monthly
average stream flow data based on a correlation to Power Creek as referenced in Table A-vn
of Reference 5. Based on this correlation, the average monthly flows are shown in Figure 1
below. Based on our review of the methodology used to generate this data, we believe it to be
of acceptable accuracy for this level of study.
SiLVEH LAKE
600 ,---------------------------------------~
500
400 l
"'
I
....
<.)
\0.1
li
'i :;cor
u
!/)
0
:<CO
Figure 1
Enera:y Production
It is assumed that due to the large storage capacity of Silver Lake, the Silver Lake Project would
be operated as a fully regulated project. This method of operation would allow the project to
Page 3
Appendix 8
produce power on demand. The reservoir storage and the sizing of the units would also allow
the project to serve as a backup to the Solomon Gulch Project, supplying all of CVEA · s capacity
requirements in the event Solomon ·JUlch had to shutdown temporarily. A reservoir storage
curve for Silver Lake is shown in Figure 2.
To simulate energy production for Silver Lake, a spreadsheet model was developed which
assumes this totally regulated flow. In the model, the reservoir is assumed to stan full in
October. The monthly average energy requirement that would be placed on the project is
determined by assuming a total yearly energy demand for Valdez from the load forecasts and
subtracting what could be generated from Solomon Gulch. Valdez's demand is assumed to be
distributed 70% for winter and 30% for summer as in the Allison Lake Reconnaissance Study.
To calculate energy production for a given month, an average head is determined by making use
of the reservoir storage curve and comparing inflow to outflow. For each of the Silver Lake
alternatives we have assumed that a 5 cfs minimum instream flow release would be required.
Head loss in the system has been assumed to be a constant 10-ft. Efficiencies and losses have
been assumed as follows:
Efficiencies
Turbine 92%
Generator 98%
Transformer 99%
Losses
Station Service
Downtime
Transmission
1%
4%
.3%/mile
The combination of these efficiencies and losses results in an average net efficiency of 80% .
To determine the ma.x.imum energy production capacity for each alternative, the yearly energy
demand is increased in the model until it reaches a point at which the Silver Lake alternative is
just able to meet the demand and still be able to refill to the original starting pool elevation. The
simulations can be seen in Tables 1 & 2.
The model indicated that an average of approximately 44,150 MWh (43,57.5 MWh winter/1, 175
MWh summer) annually could be produced from Alternative A and 48,750 MWh annually
(46,375 MWh winter/2,37.5 MWh summer) could be produced from Alternative B. Alternative
B, with a lower dam, makes more energy than Alternative A because the powerhouse is set
closer to sea level, increasing the average net head.
Project Costs
Project costs were determined by estimating quantities for major construction features and
applying unit costs to these quantities. To estimate the costs for Alternative A, quantities
established by Stone & Webster (Ref. 10) were used with the same 1992 unit costs applied as
Page 4
... ..
..
-..
...
• -.. .. ..
•
-•
..
..
• .. -
-..
-
..
Table 1
=:-=-:::-=--:-:::-==-==-==-===-:--=(: .hvd .•8 ~ Sllve r Sllv~ r "k:
ALASKA ENERGY AUTHORITY
ALLISON LAKE RECONNAISSANCE STUDY
~------.-----~-·--
Alteroative A -Stooe & Webster Eodneeri.ag
Yearly Demand 99~50 M'Wars Intake Elev.: 306 Storage
Sol. G. Summer 28600 M 'W "hrs Pool Starting Elev.: 415 161:!33
Sol. G. \\'inter .25900 M'W"hrs Powerhouse Elev.: 65 ft
L"n-met Summer 1175 MWhrs Assumed Head Loss: 10 ft
Cn-met Winter ·H.57.5 ~fWhrs Assumed Eft. 0.8
Min. ln.stream Flow: 5 cfs
i Pool I Pool Monthly
' : 1 Avg i Start . Monthly Ending Average Energy
Month Inflow Acre-ft 1 Demand! EJev Flow Storage , Elev Generation
Oct :129 19922 5447 425 315 163175. 425. 5447
~ov 172 9937 5447 425 317 153995 423 5447 I
Dec
Jan
Feb
:\far
Apr
Mav
June
July
Aug
~Qt
64 3628 5447 420 324 138084' 415 5447
53 2951. 5447 410. :B4 120874: 405. 5447
.51 2555 5447 399. 346 102539 I 393 5447
33 1722 5447 387 361 82515. 381 .5447
35 1785 5447 374 379 61471 366 I .5447.
19~ 11~83' ~447 3~! 396 49301 ~~4. ~447
441 294 73981 1 25 44 34 21 359 i 294
545 33204 294 368 20 106005: 379: 294
506 30806 294 389 18 135703 399 I 294
486 28622 294 408 17 163276' 417 294
Ending Pool Elevation 425
SUMMARY OF GENERATION
Storage Used: 171721
Replaced: I 727W
10]8 OK
. Winter Prodllction 43575 100%
Summer Prod!Jction __ I::..:lc..:.;75"-100~
44750 MWhrs
Yearly Demand
Sol. G. Summer
Sol. G. Winter
Un-met Summer
L'n-met Winter
·Month Inflow
Oct 329
Nov 172
Dec 64
Jan 53
Feb 51
Mar 33
Apr 35
Ma\' 195
June 441
July 545
Aug 506
Se:Qt 486
Table.::!
ALASKA ENERGY AUTHORITY
ALLISON LAKE RECONNAISSANCE STUDY
Altemative B -Whitewater Engineering
103250 MWhrs Intake Elev.: 306
28600 MWhrs Pool Starting Elev.: 400
25900 MWhrs Powerhouse Elev .: 10ft
2375 MWhrs Assumed Head Loss: 10 ft
46375 MWhrs Assumed Eff. 0.8
Storage
121..\90
Min. lnstream Flow: 5 cfs
' i I Pool i I Pool Monthly
i j Avg j Start 1 Monthly. Ending Average Energy
! Acre-ft Demand Elev I Flow I
Stora Elev Generation '
19922 5797 400; 309 122807' 400 I 5797
9937 5797 400 i 3lli 114016 ; 398 I 5797
J
3628
I
5797: 395 317 98510 i 390 5797
2951 5797: 384: 327· 81740! 379 5797
2555. 5797. 373! 338 63891 I 367 5797
1722 5797 360: 353! 44349 1 353 5797
1785: 5797 345 i 370 23796 I 337 5797 ;
11683 5797 328 I 388 1,107 3~3 5797
25944. 594 317, 39 35696. 328 594
:;no4. 594 :n8: 36 66705: 350 594
30806 594 362: 34 95454 372 594
28622. 594 382 32 122124
:
391 594
Ending Pool Elevation 400
SUMMARY OF GENERATION
Storage Used: 172130
Replaced: ]72759
629 OK
Winter Production 46375 1009(
Summer Production _ ____,!2~3:..:..:75::..._ 100%
48750 MWhrs
..
... ..
...
• ...
• .. -
•
..
• ..
•
•
..
•
• ..
•
• ---
• ... ..
.. -
"'5:
-+4: -
420
!
4:!G ._
r-I .., 36G -,,
~ 360 ' -~ ! > ;; :!4: -;;
~ 320 -....
v L z: 300
0 ' -:180 l
:(
> L w :215C
~
"" L 24C
;<;,Q I
I
:2CO
I
' 190
Figure 2
/
I
' I
Q i I
100
50
Appendix 8
I 200
150
CTnousands)
SiO~GE Ctcre-ft)
I I
250 350
were used for all alternatives in the Allison Lalce Reconnaissance study. For Alternative B, new
quantities were estimated and the same unit costs applied.
As a basis for the estimate, it is assumed that access to the site would be via boat to a newly
construe led dock on Galena Bay. and then by a pennanent access road to the powerhouse and
dam. The pipeline has been assumed to be placed in the finished road bed.
The dam was assumed to be constructed of roller-compacted concrete. RCC was selected due
to its speed of installation and low cost as compared to conventional, formed, structural
concrete. The RCC gravity structure was assumed to be lined with structural concrete to
provide additional freeze-thaw and erosion protection.
PageS
Appendix 8
The powerhouse is assumed to have a structural/mass concrete foundation, CMU walls, and a
metal, trussed roof. Additional line items have been included in the estimate for HVAC,
plumbing. electrical, miscellaneous metals, and inlet valves.
Mobilization was considered to be a significant factor affecting the cost of construction. The
remote access and climatic conditions are going to hamper construction and limit the number of
contractors vying for the construction contract. The shon construction season may require
multiple mobilizations. It has been assumed that once the major equipment has been mobilized
and a base camp established, construction will proceed at conventional rates. Due to the lack
of accommodations in the area, an additional cost will be incurred in either housing or
transponing the work force. To account for these factors, a 15% mobilization cost has been
added to the dam and powerhouse cost estimates.
The estimated 1992 construction cost of the two alternative configurations are:
Alternative A (Stone & Webster)
Alternative B (Whitewater)
$54,350,000
$60,560,000
For a detailed breakdown of the above costs, refer to the attached detail sheets, Table 3 & Table
4. It is assumed that both options would stan in 1998. In establishing these costs, it should be
noted that unit quantities and prices were estimated so that adjustments could be made easily in
the future. These opinions of probable construction costs are based on only this reconnaissance
level study of the site. However, unit prices used in these estimates are the same as in all other
estimates in the Allison Lake Reconnaissance Study. Therefore, we believe the relative ranking
of projects that will result from the economic analysis that follows will be valid.
Environmental Considerations
This section provides a brief description and discussion of some of the environmental issues that
may arise as a result of development of a project at Silver Lake. This review is not intended
to be a complete environmental impact assessment as this is beyond the scope of this level of
repon. Rather it is intended to highlight some of the environmental differences between the two
studied alternatives and identify environmental impacts of both alternatives that might require
funher studies in the future. Reference S represents the most extensive environmental research
done to date at and around the project site.
Topography
Silver Lake is situated in a glacially fonncd bowl surrounded by steep mountains on three sides.
The eastern-most section of the lake is bordered by a low lying delta. The natural nonnal pool
Page 6
-
..
..
-
..
• ..
•
•
• ..
• ... -
• .. -
-
-
FERC
-\.:..: :-; ~' ...
' ·-.. ...
~:;! ..
.1
' ·-
.3
A
.5
.6
332
.l
.l
~
.3 ...
.5
.6
a.
!'1.
~
, ....
.!
~ ·-_'I ...
l~~
.l
.~
334
.1
~
.3
33.5
.l
\.L'I.SK.-\ E.'-"E.RGY -\L-rHC•RfTY
::=!L \ E L~ PROJECT
\.L lt:.R. "'·-\ TIVE A -ST 0 ~ '"E 0. V.. 1: BSTER
DEPJLED COST ESTL\t~ TE tl99: Dollan)
Descr.nuon Quant ltv
L-\.'\U :>.SD L-\.SD RIGHTS
Land R:ghts -Generation Plant I
CSFS Spec1al Cse Perrnu 1
Surveymg ,
L
FERCt.'SFS Land L"se Fees :;
T ota.l -o\cc Nc .. >Xl -La.nd and Land R12hl.$
STR UCT'l 'RES A;"''D IMPROVE:ME!'.'TS
POWERHOUSE
E:scavat1on 4j00,
Concrete t mcludmg remiorcmg) 1.100
Building SupentNcnae 1
HVAC. Plumbmg &. Electrical L
Miscellaneous Metals l
Inlet \' alves :;
Subtotal.
Mobilization 11 I
Total -Ace No. 331 -Srucrures and Jmprovemenl.$•'
RESER VOlRS. DAMS. AND WATERWAYS
DAM. INTAKE. SPIU..WAY
Dock :1 II
:\ccess Road :1 28CXXJI
E::lcavauon SOO>i
Rock Drilling (Grout holes & dratn5) 4.(00
Grout Curtain 1400 I
Concrete
Structural 1.500:
RCC .soo:XJ!
DivcrsJOn & Care oiWatcr 1'
-I
PE.'ISTOCK :i
Steel Penstock Material (108" installed) I 600)1 I
SuPJ)Qns (Concrete) 400).
Surge Tank ! 14(J)X) I .,
Trll'urcauon
SUbtotal iJ
1
Mobilization •i
Total-Ace No. :t~2-Reservoir. Dams.&. Waterwavs1t
TL 'RBINES AND GENERA TORS II
Supply li 31
Install
:I
31
I
I
Total -A« No. 333 -Turbines and Generators 1i
:!
ACCESSORY EILCTRICA.L EQUIPMENT
!l
I
Swi\Chge2r 1\
Control Panel 1, ! Miscellanoous Elecuicai ' ll
I '
Total -Ace No. 334 -Ac:c. Electrical EQul!nnent 1 I
:I MISCEI.l.A."''EOUS MECHANICAL EQUIPMENT .
Crace(20Ton) i)
1 ! I
Total -Ace No. 33.5 -Misc. Mechanical EauiDment ·I
198: 198: :99: :)~:
Cmt Cnlt Pnce :\moun! iS) Cn11 Pnce .V!lountiSl
S837-~ S837.100 Sl.OOJ.COJ Sl.OOJ.OOJ
L.5 so so S:;Q.OOJ S.10.00J
LS so so S!OO.OOJ; SlOO.COO
YR so so Sl5.00J $45 . .)))
S837_100 s 1.1':'~ .00>
CY i Sl6 S72J:X:Xl $75 S:l3ij00
CY Sl.995 $2.194.500 Sl.OOJ SUOO.CXX>
LS ! s:.;66.188 1.'7,66.188 $600,00) I S600.1XD
LS so so 5100.000 Sl<Xl.OOJ
LS so so sso.ooo s.so.ooo
EA so so sso.ooo. Sl50.1XXl
$2.632.688 s::.13~ .SOO
so S73U50
S2.63Z.OIJ8 $2.5''1~0
LS i Sl$0.(0.) i Sl50.CXXJ $400,00). S400.000 u= $601 S1.680.CXXJ S75 S:!..!OO.cro
CY ' $40.00 f $200..00) S75 • S375JXD ' u= S2S I SlOO.OOJ
..
SS<l S200,1XX)
CY I 5501 $7'0,(00 SlOO; S140.00J
CY 1 Si80! S1.170.<XXl S1.CXXl' s 1.500.00)
CY i 5601 S3.(XX).<XXJ 5100! s.5 .IXX),IXX}
IS I l<XXl<XXl \ Sl.CXX:).(:XD ssoo.coo S.500.<ro !
i
1
LF ' 52..400 I S14,400,<XXJ $1.000 S6.000.00l
CY S7801 S..'l.17n00J $.500 S2.00J.CXXJ
I.B : S4i S5t'iO.<XXl $..'1 $420,!Xll
LS SOl so SllO.CXX) suo.coo
$2S~.~ Sl8. 745,COO
Sl.874..SOO
'OArnf !IIl S20.619.500
I
EA i 5990JD): Sl.970.<XXJ S l.O!O.IXlO I s:uso.ooo
EA I SOl so s.11s.cm: S945.000
'S2.970.<XX> I s-&.09S.<m
LS I S300.CXXI $300,<XXl SZSO.OOJI SZSO.IXXI
LS so so S90.COO. S90.(XX)
I LS ! SOl so $100.CXXli $100.(0)
I
I I tm.OOJ I S440.CXD
; I
l
LS i SO! so S50.00J I S50.COO
so I s.so.cm
FERC
Acr ~C'
.~.s:
.1
~ --~ ..
~~~
.1
~ ·-
:lS6 . ..
Table 3
-\L-\:iK.-\ E.'"'ERGY ALTIJoRm·
SILVER LAKE PROJECT
. -\LTER....,AID"E A-STONE & \\"EBSfER
DETAILED COST ESmiATE 11992 Dollarsl
Descri'ptton Quanttt\' Unn
511\ UCTL 'RES .Au.'"D IMPRO\'E.\.-fE.'"TS
(fRA."lSMISSIOI" FAClUTY)
Substallon Foundauoos
Oil Spill ContaJNnent
Grounding Grtd
Tota.!-Ace No. :<52-Structures&. Improvements
SCBST A TION EQUIPME.."''T &. STRUCTURES
Main Transfoauer ,.
.'\ccessory Swnch~ar Equipment
Total -Acx: No. ~S~ -Substation Ecruroment &. Structures
FIXTI..'RES. CONDUCTORS&. DEVICES
NewPoleLne
Total-Ace No. 356-Fixtures. Conductors& Devices;.
SUMMARY
LAND AND lAND RIGHTS
STRUCIURESAND IMPROVEMENTS
RESERVOIRS. DAMS. AND WATERWAYS
Th'RBINES AND GENERA TORS
ACCESSORY ELECTRICAL EQUIPMENT
MISCEllANEOUS MECHANICAL EQUIPMENT
STRUCTURES AND IMPROVEMENTS
SUBSTATION EQUIPMENT&. STRUcruRES
FIXTURES. CONDUCTORS&. DEVICES
Total Direct ConStruction COStS
Design Engineering@ ~
FERC and Other ucensing
ConstructtCII Mgmt. @ 8%
Subtotal:
Contingency ( 20% on equipment)
Conttngency ( :'.0% on remainder·!
Interest D.tring ConSt. (2 J1fS@ 4.5%)
1992 E.sumated Project Cost
199S Estimated PrOJect Cost ( @S% per Year)
Plant Mu. OUtput (MW)
ProJected Annual EnerSY-MWh.']T
Cost Per Installed kW -1992
-1995
Annual Debt Servu:e
( 100% debt. 9%. 30 y:r)
30 Year Levelized Power Cost per kWh
O&.M Allowzce
Estimated Annual Cost -1995
1 LS
l LS
[ LS
1 LS
1 LS
22 • MILE'
1982
Unit Prtce
so
so
so
SSOO.OOJ so .
S42.S.CXXl
1982
Amount{$)
so
so
so
so
SSOO.OOJ
so
SSOO.CXXl
S9.350.CXXl
S9_150Jl'Xl
$8:'17.100
52.632.688
S26.0SO.CXXl
$2.970.\XX)
SJOO.CXXl so
so
SSOO.CXXJ
S9.1SO.CXXJ
S-42.639.988
199.2
Unit Price
S10.CXXJ i
SlO.CXXl
SlO.OOJ.
$200.(XX)
SHXl.CXXl
SJOOJXX>
JYSI::
Amount tS)
SlO.OClO
S!O.OOJ ·
$[0.0Cl0
SJO.CXXJ
S200.(XX)
SlOO.(XX)
SJOO.(XX)
S6.600.CXXl
S6.600.COO
Sl.l iS.OOJ
S2.S7l.:SO
520.619.500
S4.095.(XX)
S440.(XX)
S50.CXXl
SJO,(XX)
S300.CXXl
-.. .. -
•
• ..
..
• ..
..
... ..
...
..
• ..
S6.600.(XX)
S~5.880.i50
s:~.219.268 -
S400.CXXJ
$2.870.460 ..
S4l..130.4 78 ...
SZ..29":' .CXXl
S7-118.7::.5 •
S2..i:;9.8~9
S54.<~.0J2 -
$62.900.749 .. 15 (XX)
...a"'5(1 ..
$~.6!:!
S4.l9~ •
56.11:.5:9 ..
so.:~
50.00':'0 •
so 1 4:;B
...
n::RC
.),.:: s .'
..
.. . ·-
~ -..
44.
"
1
. 1 . ..
.. < ...
.:'
.6
J~2
.1
.l .. ...
.3
A
.5
.G
a.
h.
~
, ·-
1 . '
'
.3
A
.5
~~,:.
.1 . ..
..
334
.1 ,
.J
~35
.1
,_.:_ \:::-K."'-:=:_,·E;;: _:j J "'-L ;.-!.::: R5TY
~IL\'ER L~ PRCJECT
:..L TER. -.;.-\Tl\ E 8 --~ Hr:l: WATER E.---:Gr-;EERc-;G
DET~LED COST EST:~l-\rE 1:99: Dollars 1
Descnpt!cn QuantHv
L~...;o -~"D L~SC RIGHTS
L..lnd RighiS -Generauon Plant 1
L'SFS SpeClai Use Permit i
Sur.-eyLng 1
FERC t:SFS Llnd Use Fees . _,
Total -Ace No. ;;:;o-Llnd and Land Ri2h1S
STRUCTURES AND IMPROVEME'ITS
PO\\'ERHOl:SE
Etcavatlon 1.000 .
Concrete (mcludt.ng remfon;mg) 500
Building Superstruct:ure 1 :
HV A C. Plumbing&.: Electncal '! 1 .
Miscellaneous Meta.ls 1 '
Inlet Valves 2
Subtotal
Mobuizauon
Total-AccNo.3Jl-St:ucturcsandlm'Drovementa.!
'
RESERVOIRS. DAMS. AND WATERWAYS
DAM. INTAKE. SPillWAY I
Dock I 1 ; I
Access Road ,I 25000.
E.tcavat1on I 5000; i
Rock Drilling (Grout holes & drams) 4.000!
Grout CUnam i 14001 .I
Concrete
StNcrural 5000 i
RCC :I 14300/
DiversJon &. Care of Water ;I 1 : "
PENSTOCK
Steel PensUldt Material (108") 100001
Install a lion 100001
Suppons (Concrete) i 52001
Surge Tank 'I 1i
Bifurcation I 11
Subtotal,
Mobilization il
Total-Ace No. 332 -Reservoir. Dams.&. Waccrwan
il i
TilRBINES AND GENERA TORS
Supply
ti
2i
Install 2:
!I I
Total-Ace: No. 333-Turbines and Generators I! I
' !
ACCESSORY ELECI'RICAL EQUIPMENT I
Switchgear tl
Control Panel 1 :
Miscellaneou.s Eec:tncal lj
Total-Ace: No. 334-Ace:. Elec:tric:al &uie>mentj
' !
I
MISCEllANEOUS MECHANICAL EQUIPMENT !
Crane ll
'
Total-Ace No. 335-Mise. Mechanical &ui'Dmentl
·--,.;.
L'n11 L'm: Pr:ce .·\.:ncunr 1 S 1
LS s 1.000.000 ' Sl.000.00)
LS SJO.OOO SJO.OOO
LS s1oo.ooo· SlOO.OOO
YR Sl.5.000 S*5.000
s 1.1 ':'~ ,ry)f)
CY S7.5; S".5.000
CY Sl.OOO S500.COO
LS $250.000! $250.000
LS $100.000 SlOO.OOO
LS sso.oooi S50.000
EA S50.000 SlOO.OOO
Sl.075.(X)J
Sl61 "!50
Sl.2.~.250
LS $400.000' S400.DOg
LF S75 51.875.000
CY S7S' s:;1s.ooa
LF SS01 SlOO.OOO
CY $100! Sl40.000
CY : Sl.OOOi 5.5.000.000 i
CY stool Sl,430.000
LS ' ssoo.ooo: $500.000
i
I
I
lF ' S4001 $4,000.000
lF S600 1 $6.000.000
cY S500l 52.600.000
LS S300.000 $~00.000
LS saooool $80..00)
' i 522.900.000
S3.435.00J
Sl0.335,000
i
EA ' Sl-'OO.COO I $3.000.000 I
EA I $4.50.000! $900.000
' !
' ! $3,900.000 i
I
i s~.ml LS S250.<XXI
LS $9().00)! $90.00)
LS Sl00.£XX) SlOO.(X))
i
I S440COO
'
LS S.50.CXX> I sso.ooo
S50.000
FERC
Ace Sc
::.~:
.l .
'*
' -
1C\~
. 1 . ..
:J5c
.1 . ·-
\.; .. A . .SK.-\ E:"ERGY .-\l.,'THORm·
SIL\'ER L~ PROJECf
.-\LTER.'-'.-\ TI\'E B-V.liTTE WATER E.'IIG~EERr-:G
DETAILED COST ESTL\1/\.TE (1992 DoUars1
Descnot!On
STRUCTURES AND IMPRO\'EMEJ\'TS
(TRA.."'SMISSION FACIUTI' >
Substation Fou.ndatlons
Oil Spill Contamment
Grounding Grid
Total -Ace No. :15:: -Strucl\lres &.ImerovementS
SUBSTATION EQUIPMEJI.'T &. STRUCTURES
MaiD Transformer
Acce550ry Switchgear Equipment
Total -Ace No. 35:<-Substation E.Quioment &. Structures
FIXTURES. CONDUCTORS&. DEVICES
NewPolel,jne
Submanne Cable to Valdez
..
Total -Ace No. :<56-Fixtures. Conducmn &. Devices•:
SUMMARY
LAND AND LAND RIGHTS
STR UcnJRES AND IMPROVEME.llfl'S
RESERVOIRS. DAMS. AND WATERWAYS
TURBINES AND GENERATORS
ACCESSORY ELECTRICAL EQUIPMENT
MISCEllANEOUS MECHANICAL EQUIPMENT
STRUcnJRES AND IMPROVEMENTS
SUBSTATION EQUIPMENT & STRUCTURES
FIXTURES. CONDUCfORS & DEVICES
Total Direct Construcuon CostS
Design Engineering @ 9%
FERC and Other Licensing
Construction Mgmt. @ 8%
Subtotal:
Contingency (20% on equipment)
Contingency (30% on remainder)
Interest During Const. (l yrs@ 4.5%)
1992 Estamated Project Cost
1995 Estimated Project Cost (@S% per Year)
Plant Max. Output (MW)
ProJected Annual Energy-MWht]'r
Cost Per Installed leW-1992
-1995
Annual Debt Service
(100% debt. 9%. :W yr)
30 Year Levelized Power Cost per kWh
O&M Allowance
Estimated Annual Cost -1995
Quar: t:n1t
1 LS
1 LS
1 LS
1 ' LS
1 LS
2.2. MILE
1 LS
L'nit Pnce
SlO.OOJ:
S10.000
$10.000
5200.CXXl i
SlOO.CXXl:
5JOO.CXXl;
S6.000.CXXJ
Amount lSI
S10.0CXJ
S10.000
SIO.OCXJ
s~o.ooo
S200.000
SlOO.OOO
S300.000
5660.000
S6.000.000
$5.660.00)
SLI75.000
51.2.16.250
526_135.000
53.900.000
5440.000
550.000
SJO.OOO
$300.000
S6.660.000
S40.ll6.2~0
S:\.6 I I-l6:<
5400.000
S3.210.100
$47.147.713
52.270.000
$8.632.875
Sl~'H 1.016
560.561.604
570.107.626
14.000
48750
S4326
55.008
56.824.021
S0.1400
$0.0070
S0.1470
-
-
....
..
•
•
..
•
... -
• ..
•
•·
• ..
•
•
.. -..
... -.... ..
..
Table 5
SILVER LAKE
COST ESTI~tA TE
0707J-Ol0-l.S9
08H92
f: .byd\585.silver·silvro&m. wk 1
OPERATIONS & MAI~'TE:--;A."'CE
ALT
A
Stone & Webster
~I~TE~~~t~~------~~--~-------------=En~eermg
Hydro Mamtenance ( .S9C of equip. costs) $120,000
Pipeline Maintenance $20,000
Road Maintenance $40,000
Operator Subsistance $50,000
Boat'Ai.r Travel Costs To Site $17,000
Snow Equipment Costs SlS,OOO
Insurance $80,000
Labor SlOO,OOO
FERC & Other Permit Fees $18,000
Major Replacements Reserve Fund $50,000
Fuels/OiJstConsumables $15,000
d · · at' Cos SO
Total
Notes:
l. This assumes two operators Jivmg m housmg provided at the site.
2. Project will have to maiiitam a seaworthy boat to insure access to
site under most conditioDS, a snowcat to msure access to dam
and powerhouse aU winter, as weU as a truck, plow andsmaU backhoe.
3. Travel costs to site cover costs for maintenance crews to get to and from
site for any major repairs, annual shutdowns, inspectioDS, etc.
4. Assumes salary of SSO,OOO!yr for each of two operators.
ALT
B
Whitewater
Engineering
$120.000
$20,000
$40,000
$50.000
$17,000
SlS.OOO
$80,000
$100,000
$18,000
SSO,OOO
~.This assumes no annual charge for use of native lands or related annual fees.
Appendix 8
elevation of Silver Lake is El. 306. The outlet to Silver Lake fonns the Duck River which flows
westerly for about 1.5 miles where it discharges into The Lagoon at the head of Galena Bay.
The upper ponion of Duck River flows through steep rock canyons and has 5 waterfalls of at
least 10 feet, the highest waterfall being about 60-feet-high located about 3000 feet upstream of
the lagoon. This waterfall has been considered by many to be the first impassible fish barrier
on the Duck River.
Wildlife Habitat
Silver Lake and the surrounding area is the home of a sizeable goat population and is one of the
most popular goat hunting areas in Prince William Sound. Black bear habitat in the region is
also rated good to excellent, with bears feeding on the salmon that spawn in the area. Deer are
few in the area and waterfowl use is not extensive (Ref. 8).
There will be a loss of habitat associated with both of the alternatives proposed for Silver Lake
due to the raising of the lake elevation. For Alternative A, the pool elevation would be raised
125 feet to El. 425 increasing the surface area of the lake by about 700 acres. Alterative B
would raise the lake 100 feet to El. 400, increasing the sutface area of the lake by about 600
acres. The effect of raising the pool elevations on loss of wildlife habitat for both alternatives
will have to be srudied funher before any conclusions can be drawn. What is known is that
access and exposure to the region will be increased with any development in the area.
Both alternatives as srudied in this appendix will use a pipeline to convey the water from the
intake to the powerhouse. At this time it is envisioned that the pipeline will be buried for the
majority of the route and that it shouldn't pose a barrier to the free travel of wildlife.
Air Quality
An advantage of either of the hydroelectric project alternatives investigated here is the
improvement of air quality in Valdez due to the reduction of required diesel generation. The
amount and duration of the air quality improvement is variable and dependent on a number of
factors. A detailed review of this is beyond the scope of this section.
Fisheries
The Duck River and surrounding lagoon area is reported to be one of the most productive
regions in Prince William Sound for pink salmon. Pink salmon escapement has been estimated
to average around 51,000 per year (Ref. 8). Chum salmon and Dolly Vardon are also abundant
in the area. Salmon spawning beds have been identified in the Duck River, The Lagoon.
Reverse Creek and a number of other small tributaries in the area. Development of a
Page 7
-
•
...
•
•
.. ..
•
• ..
• ..
•
.. ---..
....
•
....
'"
Appendi.x 8
hydroelectric project at Silver Lake will introduce some issues that will require funher study.
Perhaps most importantly is the issue of minimum instream flow. How, when, and where this
flow is release-d could have an effect on salmon production in the region.
The distinguishing factor between the two alternatives presented here is the location of the
tailrace, or the point where flows are returned to the stream. The Alternative A powerhouse is
located on the Duck River at El. 65 above what is considered to be the impassible fish barrier.
Water would be returned to the Duck River prior to reaching the salmon beds. Minimum
instream flow for this alternative would most likely be based on supponing the aquatic life in
the bypassed reach of the Duck River above the impassible salmon barrier. This requirement
is anticipated to be small and attainable. Alternative Bon the other hand plans to make use of
a powerhouse located on Reverse Creek. This configuration will pennanently lower the flows
on the Duck River even in the spawning areas and increase the natural flows on Reverse Creek.
What effect this altered flow regime will have on the overall fish population for the area will
require detailed funher study.
Each alternative will be using an intake located at or about El. 300. At certain times water
would be drawn from deep within the reservoir. This water would tend to be colder and have
a lower dissolved oxygen content than the corresponding surface water. How this would affect
the fisheries is unknown, however much could be done with regulation and design detail
modifications to offset or mitigate these concerns.
Other
There are additional environmental issues associated with project development at Silver Lake.
including erosion and sedimentation control, aesthetics, noise, recreation, and others. It is
reasonable to expect some level of study will be necessary to address each of these issues if
fun her project development proceeds. Detailed review of these issues is outside the scope of
this study.
Ecogomic Eyaluatigg
Using the estimated construction costs, the two alternatives were plugged into the economic
analysis model developed for the Allison Lake Reconnaissance study. Annual O&M costs were
estimated for both alternatives to be about $575,000 per year (sec Table 5). Variable O&M
savings for both alternatives were taken at the high level ($.03165/kWh) since at least in early
years, all diesel generation by CVEA could be offset. Runs were made for all combinations of
load growth and fuel price escalation as iD the Allison Lake Reconnaissance Study. Run output
is attached at the end of this section. The results are \hown below in Tables 6 & 7. The project
with the highest benefit:cost ratio is still the Allison l.a.ke w/ Hydro option, as found in the
Page 8
I
Appendix 8
Allison Lake Reconnaissance Study.
Table 6
Results of Economic Comparison of Projects
I.
ALTERNATIVE (3)
Allison Lake Tunnel w/ Hydro (1)
Silver Lake Alternative A (1)
(Stone & Webster Engineering)
Allison Lake Pipeline w/ Hydro (1)
Silver Lake Alternative B (1)
(Whitewater Engineering)
Raise Solomon Gulch Spillway 32 ft. ( 1)
Raise Solomon Gulch Spillway 5 ft. (2)
Lower Solomon Gulch Intake (2)
End Use Conservation (2)
Allison Lake Stand Alone Hydro (1)
l:ses variable O&M savings of $0.03165/kWh.
Uses variable O&.M saviD1s of $0.01/kWh.
Net Benefits Benefit: Cost
Ratio
$20,320,658 1.70
$29,291,969 1.58
$9,805,844 1.55
$29,440,364 1.53
$6,509,336 1.33
$1,009,602 1.66
$530,132 1.43
$300,069 1.73
($12.191.263) 0.73
Average
Annual
Diesel
Displaced
{M\Vh)
27396
44053
15434
. 47439
14817
1674
1025
747
19666
3. All cases using "Hip" load JTO'Wth forecut (w/ Petro Star) ud AEA fuel price escalatioo forecast.
Page 9
...
...
...
-
..
...
• .. .. ..
...
•
• -
•
i; ..
• -.. -..
.... ..
-
•·
..
Appendix 8
Conclusions
The Allison Lake Tunnel w/ Hydro option has the highest benefit:cost (BC) ratio of all options
investigated. with a net benefit of about $20.3 million. Both Silver Lake options investigated
had slightly less but still attractive BC ratios of 1.58 and 1.53. Net benefits of both options
were higher than Allison Lake Tunnel w/ Hydro at about $29.3 million. Clearly, both Allison
and Silver Lake projects have attractive features. Allison Lake Tunnel w/ Hydro has a lower
1992 capital cost of about $34 million compared to Silver Lake at about $54 million. Operating
uncertainties are less wilh Allison Lake, and its proximity to Valdez makes construction logistics
easier to handle. The Allison Lake project, however, does not satisfy all of CVEA's diesel
generation demand for the high (w/ Petro SW) load growth case. Silver Lake does, at least in
early years of operation. Silver Lake, being a larger project than Allison Lake, also generates
a higher net benefit.
The analysis of the Silver Lake Project points out one area of possible risk with the project.
Referring to Table 7, it can be seen that under the high load growth forecast (with Petro Star)
the Silver Lake Project has the highest net benefits. Under the medium or low load growth
forecasts, however, the net benefits drop considerably, and are negative for all cases in the low
load growth projection. This is because under low load growth, not all the energy from the
project could be used right away. reducing the fuel and O&M savings. Although the Petro Star
load and the economic activity from the Alyeska Pipeline appear stable at the present, it is
possible the pipeline could shutdown sometime early in the next century. If this occurred, and
the Petro Star load was lost, Silver Lake project economics could be adversely affected.
We believe that constructing either of these two projects, Silver Lake or Allison Lake, does not
rule out construction of the other. As can be seen from the high load growth case economic
model runs, if either Silver Lake option is constructed and is on line by 1998, CVEA will still
need to resume some diesel generation by 2004, only 6 years after the project comes on-line.
Should load growth exceed the "High" case scenario, diesel generation would be needed again
even sooner.
An integrated approach to providing power for CVEA and the Valdez area is necessary. From
the technical standpoint, projects at Allison Lake and Silver Lake are feasible. Under high load
growth projections, both projects are beneficial. Under medium or low load growth scenarios.
the Silver Lake project is less beneficial. We recommend both projects be studied in greater
detail. Selection of which project to proceed with fU'St will depend on actual load growth.
availability of capital to both CVEA and the State of Alaska, and other institutional issues.
Page 10
Appendix 8
References
l.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Alaska Power Authority, Application for Preliminary Pennit for the Silver Lake
Hydroelectric Project, P-6861-000, November 18, 1982.
Alcat Engineering, Cordova-Valdez DC Transmission Tie Line Feasibility Repon. May
1' 1982.
DOWL Engineers, Cordova Power Supply Feasibility Analysis: Silver Lake Alternative -
"Study Plan" Environmental, May 1982.
DOWL Engineers, Geology and Geotechnics of the Proposed Silver Lake Hydropower
Project, Draft, Spring 1983.
DOWL Engineers, Draft Environmental Field "Study Plan" (1983-84), Silver Lake
Alternative, Cordova Power Supply Feasibility Analysis: Phase U, June 10, 1983.
International Engineering Company, Inc., Final Report: RecoMaissance Study of Energy
Requirements and Alternatives for Cordova, June 1981.
Stone & Webster Engineering Cotperation, Cordova Power Supply, Interim Feasibility
Assessment, Execunve Summary, June 1982.
Stone & Webster Engineering Cotperation, Cordova Power Supply, Interim Feasibility
Assessment, Volume 1, June 1982.
Stone & Webster Engineering Cotperation, Cordova Power Supply, Interim Feasibility
Assessment, Volume 2, June 1982.
Stone & Webster Engineering Cotperation, Cordova Power Supply, Interim Feasibility
Assessment, Addendum 1, Revised Cost Estimates, November 1982.
Page 11
... -..
-
..
•
..
.. .. ..
• ..
•
•
• ..
.. ---.. -
...
-
Allison Lake Reconnaissance Study
Prepared for
State of Alaska
Walter J. Hickel, Governor
Alaska Energy Authority
Charlie Bussell, Executive Director
701 East Tudor Road
PO Box , 90869
Anchorage, AK 995, 9
(907) 561-7877
September 1992
PrePared Under Contract No. 2800413 by:
HOR EnginHring, Inc.
Building B
4446 Business Park Blvd.
Anchor•o•. Al•lka 99503· 7 1 1 8