Loading...
HomeMy WebLinkAboutReconnaissance Study of Hydroelectric Power Alternatives 1979SEW �.._ CH2M 005 :CHILL engineers planners economists scientists 5 March 1979 K12404.A0 City of Seward Box 337 Seward, Alaska 99664 Attn: Mr. Johnny Johnson City Manager Gentlemen: PROPERTY OF: Alaska Power Authority, 334 W. 5th Ave. 'Anchorage, Alaska 99501, RE: Reconnaissance Study of Hydroelectric Power Alternatives Attached are twelve (12) copies of the final report on the referenced study. Of the four sites considered, the Grant Lake project is the best source'of power from the standpoint of economic and environmental impact. The Crescent Lake site was second;'it was found to be less environmentally objectionable than in the past, but the study also found the likely potential power not as great as indicated in the FPC license appli- cation. It is recommended that the Grant Lake project be considered further as a supplemental source of power for the city. Crescent Lake might also be pursued, though the environ- mental conflicts will probably be more difficult to resolve. Either project would be a supplemental, not independent, source of power for your community, as neither would ade- quately meet the anticipated, future power needs. However, in view of rising fuel costs and the uncertain supply of power from a distant source, a hydroelectric project would certainly decrease the city's dependency on a distant power supply. 10. Anchorage Office 310 K Street, Anchorage, Alaska 99501 907/279-6491 Vk HIGHSMITH 42-M PRINTED IN U.S.A. Mr. Johnny Johnson 5 March 1979 K12404.A0 Page Two If you wish to pursue a hydroelectric project, the next phase of action would be preparation of a Federal Energy Regulatory Commission (FERC) permit application and to proceed with a preliminary design for a detailed analysis of the site. Please call if you have any questions. Also, we can easily arrange a presentation of this report if it would be helpful. We enjoyed completing this study and appreciate the invaluable help from the city staff. Sincerely, Corby H. Howell Project Administrator dea enclosure CITY OF SEWARD RECONNAISSANCE STUDY OF HYDROELECTRIC POWER ALTERNATIVES CONCLUSIONS AND RECOMMENDATIONS In this study, the proposed Grant Lake project was found to be the best hydroelectric alternative for a power source, from economic and environmental standpoints. At this reconnaissance level, examination revealed Crescent Lake as the second most desirable site. It is recommended that the City of Seward strongly consider the Grant Lake site as a possible alternative for a supplemental power source for their community. The Crescent Lake site might also be considered, though the environmental conflicts associated with this proposed project will be more difficult to resolve. INTRODUCTION The City of Seward now purchases power wholesale from Chugach Electric Association (CEA); the city owns and maintains standby generators only. On 15 January 1979, CEA notified Seward that the contract determining the quantities of and charges for the electric power and energy furnished to Seward was terminated, under terms of the contract itself, on 22 August 1972. CEA stated that power sales to Seward subsequent to that date have not been and are not now con- tractually mandated. With substantial growth in the Seward area expected and the price of the present wholesale power supply rising due to increasing fuel costs, city officials have decided to investi- gate the possibility of generating electricity with their own facilities. PURPOSE To assist the city in determining what direction to pursue for investigating and evaluating hydroelectric power, CH2M HILL was retained to examine several previously identified potential hydropower sites. These sites were ranked in order of highest potential, economically and environmentally, and the best site was recommended for city action. - 1 - METHOD Four sites having generation potential were selected based upon suitable physical conditions for producing energy. Location maps are on pages 3 through 6. These conditions included topography (for adequate height of water storage), hydrology (for adequate water flow and availability), and location (for proximity to existing transmission lines and access roads). After the sites were identified, these factors were further investigated using existing data, updating when necessary. This information is presented in the chart on page 7. This includes comparison of power potential, dam height, reservoir storage, and transmission/ road access. The Alaska Department of Fish & Game and the U.S. Forest Service were contacted and asked to identify conflicts and problems which could impact the construction of each hydro- electric site and to rank the sites based on acceptability. These points are also noted in the aforementioned chart. The cost data presented in the comparative chart were taken from reports referenced in the Bibliography. The costs were updated according to the Engineering News -Record Cost Index. The estimates for the Grant Lake alternative were updated in 1978 by CH2M HILL on a Unit Price Basis. These costs are for comparative purposes only and require further refinement for establishing budgets. - 2 - 1 "FISM-0- , E//Efi���." '. •,..� ♦�. cam.:, Z�-♦,�+�w; ore • ���� !R -1�' UNITED STATES J DEPARTMENT OF THE INTERIOR GEOLOGICAL SURVEY 15• .3770mm-L R t E. �: `�I, �t•�, 1 .��i �`��� � �� �. fi��•r� `_� \�1 � r\t �` `ram 1I' , \ ', �hr+�dfrt\Il�i;r i� �l 1 'Q I ,r/:- _-.�•.�.-_..; � �\\� � B �.��\ - `` �) . :, ' � ; r • ,� t � � �n '� o.n Mn+e9C • ',5��•.. - �� � ,,�1 , 1 ;,,`'. . ^ l• -moo ` •:1\ - /�,� l I � �(��✓`,� � \v�r. i - _ - ` -`_tea' •:'�.: • .1% ► � ,. p Sla Crow RntQ d /lam r�-� r°sw/J OF / r j � :�' o tsao � _� ate_, _ ' ���- �_... \,\�`� - \\ �_-• 1:`_ -- t� �,>w �' I ^`'��\ ��, ;•��_ � � .�, � •::mac �7= - .'ti���-=`�"'�� � , , . Station ' •°i i / ' `; "-'\ �i �� `� Jam\ / \\\�.._� •( 7. Black Point IQ 22 �u'n )t] f �\ � %� � ; it 1 /',11' t1 /' � � �<%!- -i '� - /r, �°" /- .''_�.� �� "�- •r�a-- _ ^tit y ATION i 112 o ` 1�' � ��o I��\ t; !' � � s•i .iE„ .• 15 _ .� �23; - �` ��`\ �-- t 350C, __= / 1 1 - i : i� ; 0 �I /�/ % , ' l^ \ `_ \ 1 ehti✓ --21 2i Ile ~ o� i ri,,--_ »•i � �% // , i ; r 7' 1 �� , �� �. �' - ''� ; , .� ,.1�`J,j •� `ice � '7 -� �� � a! "" ` t �A 9 1� /. �/' �i 31, 2 / H 33 10, mw 00 . � — ( 1, t / — : - M - � • � `��=E� .\ 26 1 !\,` tc�..i,, ' tt r � r 2) 33 �� z 4 &K - 1 is � _ _ ; i �_„-�_%�;. =-�.! ; �l� i � � 1 _;•� \ B � 5 � --n _ _) '� `• �\ \ �' _ `'-_`, _._.��� — �� ` �, Jam\ :) �1.. AH f Al, i•��_'�`: ^\\'+ , �I" �y.- a _`'__ --1._ �.r � -•j � /'� =J'-i _ i ��, � :// � _ ��' Its, � i' �,�� {V/'f /7 _- - ��`t: � �` � IL\;•l1, � �%��/�� j'r ��1 `-'/ �'' tom! � �=.. ; }: � : � J A � - � ' �� _ y . � ; ,. • ! '/ � , ` t1• it '\ �tll , .\,�-'�� � / V � ...=� 2320, D CR CIFNA I• LAKE PROJECT 133 34 35 36 31 32 33 72f3 0 � tip; \\ � - _..- ' , � ' -�,�� �✓ � —%'- - �- � ' �`_ --^ � �' i ��� � � ,f �� ,\� � ,,l � Its;; � .- _ � ` • r - ��� „�' �-�. 4 O ,1-�1. - j, ` I \� ` \ . _ =ii _ • � I .ice 1 "•-�-��� ''.:,� - ,tom\ .:.�'-��-,�os1" `� ` `+N ) � , -!`' � (')c• !� • `\ ` i ''yJ/�i_��' •� ' °,t_ �' � _ ., cv in fI cli Sl' •1 �� . i � �1 I i Y. �. V� � ' I I wt` � i Nam+ .1 .'r o •wp' �.. 1 � . j e {(j • a 1 00 I\ 04 Ate(-_ �' _______._-_ _�•'��t'' 1 i� s_ _-_- _ jj,,X •• _ ;� i� � \ 1 r � ���i �iv.' �t M . t y '\.�. �,��G. o \'" .� ^(J'(�•.�. "'' � ��` O �• Ma i1�t•' w,• .r.,i ,In • `` I� ��\" lam! '`•,??: •�('\ i i -` - r\�\\�, 34, i5o�" a-✓ �50os .:�3 1 •j.tt! i h``1L1 .,� �i 'k a =\ Site (In Ranking order) Grant Lake Dam 50 ft. high Res. 75,000 ac, ft. W. S. Elev. 740 ft. Mean head 250 ft. Regulated flow 170 cfa Crescent Lake Dam 50 ft. high Res. 50,000 ac. ft. W. S. Elev. 1,485 ft. Mean head 1,000 ft. Carter Lake dam 15 ft. high Regulated flow 40 cfs Resurrection River Dam 195 ft. high Res. 168,000 ac. ft. W. S. Elev. 425 ft. Mean head 300 ft. Average flow 400 cfs Snow River Dam 325 ft. high Res. 134,000 ac. ft. W. S. Elev. 1,200 ft. Mean head 740 ft. Average flow 600 cfs Access Road 1 mile 125 ft. bridge No present road Trail exists from Moose Pass to lake a miles No present road Trails exist into both Crescent and Carter Lakes Transmission Line Capacity Installed kW Land kWh/yr ownership 1 mile 6, 000 kW Chugach National Forest; Tie to Chugach 25 kV line 25.2 x 106 kWh/yr a further planning area + 4 miles north of Seward - Chugach terminal 1 mile 5,500 - 6,000 kW Chugach National Forest; Tie to Chugach 25 kV line 24.3 x 106 kWh/yr a further planning area +10 miles north of Seward - Chugach terminal Exists for about 5 miles 7 miles out of Seward. Could be 69 kV easily developed from (initial 25 kV) there. To new Seward substation 2 additional miles needed 3 miles 3 miles No present road 69 kV +Bridge Tie to Seward trans - +Railroad crossing mission line No structures now exist +11 miles north of Seward Reconnaissance Cost Estimate $0.040/kW r $0.065/kW 17, 800 kW East side - Chugach National $0.166/kW 85.8 x 106 kWh/yr Forest; a further planning classification. West side - public domain or Fish & Wildlife land under BUM dt Impacts Environmental Unresolved Factors Sheep & goat habitat. Creek Some sediment from supports sockeye L king glacial streams. salmon, close to lake outlet. Recreational area (grayling) sheep & goat habitat. Outlet stream supports king, sockeye & coho salmon. Important anadromous fish stream w/coho, chum & king salmon. Supports moose and bear habitat. eii lur s s on 62, 800 kg All Chugach National Forest $0.056/kW lmpurtant big gmna habitat 275 x 10 kWh/yr Upper portion - proposed Unacceptable to Fish & non -wilderness. Lower Game (State). portion - further planning NOTE: Total project area cost would be approxi- mately $128,000,000 - 7 - Some sediment from glacial streams. Heavy sediment load. Some avalanche problems. Very broad valley. Effect of glacial outbreak flood on reservoir. Flood protection benefit. Heavy scouring. SITE SPECIFICS Sites are presented in order of potential. Grant Lake: The dam for this site would be built at the outlet of the lake, with a crest length of about 550 feet, and a height of 50 feet. A small saddle dam would be needed. Approximately 75,000 acre-feet would be required for complete regulation of the 170 cfs flow. One mile of pipeline with about 800 feet of penstock would achieve an approximate mean head of 250 feet. Average power output would be 3,000 kW, with an installed capacity of 6,000 kW. The dam site is approximately one mile from the Seward Highway and the Alaska Railroad. Alaska Fish & Game ranked this site #1, as the project most likely to be acceptable from the environmental viewpoint. Grant Lake is an important sheep and goat habitat. The outlet creek supports -some sockeye and king salmon. These conflicts would need to be resolved. Grant Lake is presently in the Chugach National Forest. A permit, from the U.S. Forest Service, for the project would be required. The State of Alaska has selected land around Moose Pass in accordance with the Statehood Act of 1958, but it has not yet been conveyed to the state by BLM. This selection includes land on both sides of the Seward Highway, west of Grant Lake. A state permit would also be required for any access to the project site, after the conveyance has occurred. Crescent Lake: Many schemes have been suggested for this site; the most likely plan is to raise the level of the lake enough to reverse the flow into Carter Lake and out Carter Creek. Another consideration would be to tap the lake and lower it. The reverse -flow plan is presently the most economical. The Crescent Lake power plant would be about 31 miles north of Seward on the Seward Highway. The dam crest would be approximately 1,000 feet long and a 5- to 10-foot cut would be made between Crescent and Carter Lakes. A 15-foot dam would be built on the outlet of Carter, as well as the 50-foot dam on Crescent Lake. The average head would be about 1,000 feet with an average regulated flow of 40 cfs, an average power output of 2,770 kW, and an installed capacity of 5,500-6,000 kW. Reservoir capacity would be 50,000 acre-feet. Alaska Fish & Game ranked this project #2 in probable accept- ability, though some areas of conflict need to be resolved. The site is an important recreational area, is a sheep and goat habitat, and the outlet stream supports king, sockeye and coho salmon. Crescent Lake is located in the Chugach National Forest, and a permit for construction from the U.S. Forest Service would be required. Resurrection River: The dam site would be located approxi- mately seven miles northwest of Seward, about one-third mile below where Paradise Creek flows into Resurrection River. The most likely plan would be a concrete gravity dam, with a height of 195 feet and a crest length of 1,950 feet. Elevation 425 feet would be the maximum water surface elevation. A 22,000 foot tunnel would be constructed to carry water downstream to a power plant with a tailwater elevation of 100 feet. Reservoir capacity would be 168,000 acre-feet; average power output would be 6,900 kW, with an installed capacity of 17,800 kW. Average flow would be 400 cfs. The spillway might be a 100,000 cfs capacity. Resurrection River was ranked #3 by Fish & Game. The area supports moose and bear. It is also an important anadromous fish stream for coho, chum and king salmon. These conflicts could possibly be resolved. Resurrection River is the division line between Chugach National Forest and land controlled by the Bureau of Land Management. The BLM land has recently been withdrawn as a national monument, which may preclude any construction. If a project is possible, the permit would be issued by BLM, with U.S. Forest Service approval. Snow River: The dam site is located at a deep, narrow gorge on Snow River, approximately 9 miles upstream of Kenai Lake and 4.8 miles upstream of the Alaska Railroad. The dam would be 325 feet high with a crest length of approximately 820 feet. Normal maximum water surface would be at elevation 1,200 feet and would require two small auxiliary dams to close two saddles under 1200 feet. This would inundate Lower Paradise Lake. Average flow is about 600 cfs for an average power output of 31,400 kW, with an installed capacity of 62,800 kW. A tunnel 1.9 miles long with 0.4 miles of penstock would connect the reservoir and the power plant. - 9 - Debris may accumulate in the reservoir due to glacial outbreak floods or avalanches. This area has possible strong seismic activity. Also, the spillway must be designed for the glacial outbreak flooding which would be around 200,000 cfs. Fish & Game rated this site #4 and -the conflicts could probably not be resolved. The area is a big game habitat, with high recreational value. The area is in the Chugach National Forest. No withdrawals have been made in this area. A permit would be required from the U.S. Forest Service. - 10 - BIBLIOGRAPHY A lication for License for Crescent Lake H Project, Before the Federal Power Comm Seward, Alaska, Applicant, Project No. Harstad & Associates, 1956. droelectric ssion, City of 2171, Howard T. Indermukle, Vernon C., Preliminary Report on the Water power Possibilities of Snow River, Nellie Juan Lake and Lost Lake, Kenai Peninsula, Alaska, U.S. Geological Survey, OF-61-1, 1961. Johnson, Arthur, The Potential Waterpower of Grant, Ptarmigan, Cooper and Crescent Lakes, U.S. Department of the Interior, Geological Survey Open File, June 1955. Lamke, R. D. and Scully, D. R., "Snow River Flood - 1974", Water Resources Division, U.S. Geological Survey, 1-23-75, unpublished. Scour at Selected Bridge Sites in Alaska, U.S. Geological Survey, Water Resources Investigations 32-75, 1975. Selected information from the files of the Alaska Power Administration. rnMTArTq Our thanks to the following people for their contributions to this report. Mr. Bruce Barrett Alaska Department of Fish & Game Mr. Don Gotshall U-S. Department of Energy Alaska Power Administration Mr. Charles Harnish U.S. Forest Service Mr. Ted McHenry Alaska Department of Fish & Game Mr. Tom Murdock U.S. Army Corps of Engineers Mr. Maynard Nuss U.S. Forest Service Mr. Weldon Opp U.S. Army Corps of Engineers Mr. Dale Rusnell Alaska Division of Power & Energy Development �� CH2M HILL EXPLANATORY NOTES - CRESCENT LAKE HYDRO SURVEY It is important to understand certain terminologies related to hydroelectric projects in general, to understand findings for specific hydrologic site investigations such as Grant and Crescent Lakes. Capacity is a term used to describe the rate of power (kW) that can be obtained at any given time from a project. Obviously the turbine -generator sizes to be installed are optimized for maximum capacity related to the sustained capacity. It is not peak demand but average annual energy produced that must determine economic feasibility of a project. Primary Energy is a term that describes this annual average energy available. It converts the average runoff and impoundment capabilities of the hydro project to usable annual kilowatt hours to be sold. Load Factor describes the pattern of energy use (kWh) of a community related to the maximum demand (M . Typically Alaskan communities have ranges of 50%-70% load factors. The ideal hydro project for a community shows a good match between the annual runoff water energy (Primary Energy) and the community Load Factor energy use pattern. This allows design of specifics (dams, spillways, generator sizes, head, etc.) "tailored" to the community. Using Crescent Lake as an example, with development as described in the CH2M HILL Reconnaissance Study (5 March 1979) the optimum development would have an installed capacity of 6,000 kW and Primary Power of about 2,800 kW. This means it could deliver 2,800 kW year round. At a higher installed power output the project still could not sustain more than this 2,800 kW as a year round average. Estimates for Crescent Lake in previous years which show higher installed capacities do not suggest that this average 2,800 kW capability is significantly greater, particularly in view of the accumulated water records since those earlier estimates (1954). The present estimates for Crescent Lake indicate a regulated flow of about 40 cfs against 1954 estimates of a hopeful 70 cfs. The intervening 25 years have hardened the water record and decreased the prudent development capacity of the Crescent Lake project. ME ME CH2M HILL • CFS = cubic feet/second of water runoff • H = "head" = height in feet (average) of water above generating turbines • "Prime Power" is approximated by: PP = (Average annual CFS) x-(H) x (0.07) PP = kW = kilowatts capacity in this formula • Primary Energy = (Prime Power) x (8,760 hrs/year) PE = kWh energy in this formula • "Load Factor" is a term describing the energy use pattern of a particular community. Load Factor = L.F. = actual annual kWh energy peak demand (kW) x 8,760 hrs L.F. = kWh = dimensionless factor