HomeMy WebLinkAboutRivers and Harbors in AK Sitka and Petersburg-Wrangell Study Areas 1979SOE
008
RIVERS AND HARBORS IN ALASKA
SITKA AND PETERSBURG/WRANGELL STUDY AREAS
STUDY DOCUMENTATION
AlasKa . District~ Corp~ Q~ ~ngineers
Anchorage.. M:.a$ka.-,.
March 1979
1
I
-
I
I
l
1.
I
lU•U H.LIIUIHGIH
OJ. Olln881
800
~r;s
liJ.VO
_I
I
I
I
'
I
I
' I
RIVERS AND HARBORS IN ALASKA
PETERSBURG/WRANGELL AREA
STAGE II ANALYSIS OF HYDROELECTRIC DEVELOPMENT
This information is the result of studies conducted as part of
Rivers and Harbors in Alaska, Southeast Alaska Hydropower Study. The
analysis represents Stage II level of detail. The study did not pro-
ceed further due to local action which eliminated the need for addi-
tional hydropower development. The results of the study are summarized
in the Main Report of Rivers and Harbors in Alaska.
Item
HYDROLOGY
FOUNDATION AND MATERIALS
REGIONAL ECONOMY
TABLE OF CONTENTS
PROJECT DESCRIPTION AND COST ESTIMATES
POWER STUDIES AND ECONOMICS
ENVIRONMENTAL ASSESSMENT
CORRESPONDENCE
Item
Thomas Bay and Tyee Lake
Thomas Bay Site Plan
List of Plates
Thomas Bay Project Details
Tyee Lake Plan and Sections
Tyee Lake Profile and Sections
Tyee Lake Project Details
Section
A
8
c
D
E
F
G
Number
1
2
3
4
5
6
SECTION A
HYDROLOGY
PETERSBURG/WRANGELL HYDROPOWER STUDY
GENERAL
BASIN DESCRIPTION
Both Thomas Bay and Tyee Lake project sites are located on the
mainland in southeastern Alaska as shown on the location map, Plate 1.
Thomas Bay is approximately 40 air miles (67 km} northeast of Wrangell;
Tyee Lake is 38 air miles (63 km) southeast of Wrangell. In addition
to the above two alternative sites, 12 other potential hydropower sites
in the Petersburg/Wrangell area were screened as candidates for develop-
ment and are shown on Plate 1.
All of the alternate sites, including Tyee and Thomas Bay sites,
are at comparatively low elevation (below 2,000 feet). The Tyee Creek
watershed ranges in elevation from 1,387 feet at the lake up to approxi-
mately 5,000 feet. Thomas Bay watershed extends from an elevation of
1 ,514 feet at Swan Lake up to 6,300 feet. Neither watershed has an
extensive drainage area above the 4,500-foot level.
Thick stands of coastal coniferous forest occupy both the Tyee and
Thomas Bay watersheds from tidewater to approximately 2,750 feet. The
only exceptions are the steep, rocky, canyon walls as well as a few
scattered bogs and poorly drained meadows where tree growth is either
absent or stunted. Tree growth becomes increasingly dwarfed and scat-
tered above the 2,000-foot elevation. At higher altitudes, low, scat-
tered shrubs and subalpine herbaceous cover prevails, along with
extensive areas of barren rock slides.
Tyee Creek drainage contains three small glaciers with an area less
than 0.4 of a square mile, with no permanent snowfields. The Cascade
Creek drainage has extensive glacier and snowfield coverage. Of the
total 17.3 square miles, approximately 4 square miles on the south
side of the watershed are occupied by permanent snowfields and glaciers.
The terrain in both watersheds is mountainous and extremely rugged.
The stream channels from lakes to tidewater are exceedingly steep with
frequent cascades flowing through occasional, deep rock gorges.
STREAMFLOWS
Tyee and Cascade Creek drainages are both comparatively small water-
sheds with the exceptionally high runoff yield per square mile typical
of southeastern Alaska streams. For Tyee Creek, the average runoff is
12.8 cubic feet per second (cfs) per square mile. Cascade Creek average
is 11.9 cfs per square mile.
The highest discharge each year on both streams normally occurs in
June, primarily the result of snowmelt. The highest recorded peak flows,
however, have occurred in the months of September and October. The
onset of winter storm systems from the eastern Pacific bring heavy
precipitation to southeastern Alaska in the form of rain.
The greater portion of the annual runoff on both streams occurs in
the warm season from May through October. With the onset of freezing
temperatures in November, the streamflows decline rapidly to a winter
base flow, which is about 10 percent of the summer flow. Because of
A-2
the predominantly granitic nature of the substrata in these two water-
sheds, there is only meager ground water inflow after winter freezeup.
The average seasonal runoff for Tyee and Cascade Creeks is as follows:
Discharge
Tyee Creek
near Mouth
October 288
November 117
December 48
January 27
February 27
March 45
April 46
May 253
June 403
July 297
August 233
September 327
Annual 175
Record Minimum Month 11 (Mar 69)
Record Maximum Month 494 (Jun 67)
in cfs
Cascade Creek
near Thomas Bay
310
184
100
60
54
50
73
266
547
490
445
505
251
16 {Feb 69)
722 (Jun 67)
Despite the low average streamflows indicated for November through
March, the occurrence of occasional warm storms, even in midwinter, in
southeastern Alaska cause heavy runoff for brief periods. As an example,
on 23 January 1968, the discharge at Thomas Bay went from 40 cfs to
450 cfs in 48 hours.
A-3
CLIMATE OF THE AREA
GENERAL DESCRIPTION
Tyee and Thomas Bay drainages lie in comparatively temperate portions
of southeastern Alaska and experience the high precipitation character-
istic of that part of the state. Tyee Creek is located at approximately
latitude 56° N; Thomas Bay is at latitude 57° N. This is approximately
the same as Edinburgh, Scotland and Copenhagen, Denmark.
Southeastern Alaska is classed as a "Maritime" climate. The
dominating influence of the comparatively warm North Pacific Ocean is
evident in all seasons. In addition to the proximity of the ocean,
the configuration of the southeast Alaska coastline is one of numerous
fjords, bays, and inlets, such that water surfaces are everywhere
interspersed with land surfaces. This also contributes to the moderate
climate.
During the winter season, moisture-laden air masses move from the
North Pacific across the study area in regional-scale storm systems,
dropping precipitation in heavy amounts. Occasionally, stationary cold
inversions of air, which build up over the interior plateaus of Canada,
migrate southward bringing dry, northerly winds and lowering temperatures
in southeastern Alaska.
Nearly all the climatic data for southeastern Alaska is gathered
at stations near sea level. Therefore, the climatic records do not
present an accurate picture of conditions for Tyee and Thomas Bay
A-4
watersheds. Both have extensive portions of area above the 2,000-foot
level. For Thomas Bay, its close proximity to the major icefield in
the coast mountain range along the U.S.-Canada border accounts for
substantial climatic effects, such as cold drainage winds which are
not as pronounced to the west of the island archipelago. In addition,
the incidence of low clouds and fog at the higher altitude are more
frequent at both Tyee and Thomas Bay drainage than at adjacent lowland
stations.
TEMPERATURE
The climatic average temperatures near sea level at Petersburg and
Wrangell illustrates the mild winters and modest annual fluctuations:
Mean Dailt TemQeratures OF
Petersburg Wrangell
Maximum Minimum Maximum Minimum
January 34 23 35 25
February 36 25 37 26
March 41 28 43 31
Apri 1 49 33 50 35
May 56 39 58 41
June 62 45 64 47
July 64 48 65 50
August 63 47 65 49
September 58 43 59 45
October 49 38 51 39
November 41 31 43 32
December 36 27 37 27
There are few climatic stations in southeastern Alaska at elevations
above sea level. Records from Perseverance Camp near Juneau, at ele-
vation 1 ,400 feet, indicate that summer temperatures at high elevations
A-5
are about 4° F less than sea level readings. In winter the difference
is considerably greater, with temperatures about yo F lower than at
sea level.
Mean Monthly Temperature o F
January
February
March
Apri 1
May
June
July
August
September
October
November
December
Perseverance Camp
(elev. 1,400 ft)
20.9
26.3
25.8
37.8
42.2
48.8
53.5
53.5
50.4
37.6
31.3
22.3
Juneau
{ e 1 ev. 72 ft)
28.5
29.9
34.3
34.3
48.3
54.8
56.9
56.2
51.3
43.9
36.3
30.3
The data from Perseverance Camp is typical of Tyee and Swan Lakes.
Both are near the 1,400-foot elevation.
The lowest temperature on record for Petersburg and Wrangell are
-19° and -10° F, respectively. Whereas at Perseverance Camp the recorded
minimum over 4 years was -23° F. The highest temperatures recorded at
all three locations are 84°, 92°, and 81° F, respectively.
The seasonal temperature regimes between sea level at Petersburg
and high lake levels in the project area are significantly different.
Winter daytime temperatures normally exceed 32° F nearly every day at
sea level, however, there are long periods of continuous freezing tern-
peratures at lake level during the winter.
A-6
PRECIPITATION
Precipitation is heaviest during the fall months and generally
declines in the spring to a minimum in June. During early summer, the
North Pacific storm systems, which are the primary precipitation
producing mechanism in southeastern Alaska, are relatively weak and
few in number. The seasonal distribution of precipitation at Tyee and
Thomas Bay are reflected in the data for Petersburg and Wrangell.
Mean Monthly Precipitation
(inches)
January
February
March
April
May
June
July
August
September
October
November
December
Total
Petersburg
8.93
7.49
7.10
6.85
5.95
4.59
5.23
7.67
10.97
17.22
12.14
11 .06
105.20
Wrangell
7.27
5.89
5.43
5.05
4.13
3.96
5.25
6. 31
8.27
12.61
9.90
8.33
82.40
Very little of the precipitation occurs in convective-type showers.
Even with the substantial quantities of precipitation, the intensity is
comparatively low. Thundershowers are rare in the study area, aver-
aging only about one per year.
Although precipitation data is not available from either Tyee or
Thomas Bay areas, ample evidence exists that precipitation on the
A-7
watersheds greatly exceeds the sea level figures at Petersburg and
Wrangell. The measured depth of runoff from Tyee Creek, for example,
is 172 inches annually or 172 percent of the nearest sea level station
at Bell Island. A similar relationship is characteristic of high
elevation watersheds in all southeastern Alaska. It is due to the
orographic effect of the coast mountain ranges which cause rapid uplift
of maritime air masses forcing heavy release of precipitation. For the
Thomas Bay watershed, the percentage increase is 171 percent over sea
level percipitation.
As in all of southeastern Alaska, the total amount of annual pre-
cipitation in the Petersburg-Wrangell area is very dependable. During
the 56-year record at Petersburg, the longest period of low precipitation
occurred between 1950 and 1951. The 24-month total precipitation was
73 percent below normal. The driest year on record had 71.31 inches;
rarely does the annual total precipitation produce less than 90 inches.
The minimum month recorded was June 1924, when only 0.78 inches were
recorded at Petersburg. Rarely is the monthly total precipitation less
than 2 inches.
SNOW
Annual snowfall is a modest amount near sea level at the project
area. The annual average at Petersburg is 97 inches, for Wrangell it
is 61 inches. This represents about 8 percent of the total annual pre-
cipitation. Snowfall data is unavailable at the elevation of Tyee and
Swan Lake. However, in the record from Jumbo Mine at 1,500 feet in the
A-8
Ketchikan area snowfall constitutes about 25 percent of the annual
precipitation. Using this proportion, the annual snowfall at Tyee and
Swan Lake would be approximately 340 inches.
No snow courses are located in the immediate project watersheds.
However, the following courses are representative of this portion of
southeastern Alaska:
Course
Harriet Top
Hunt Saddle
Lake Shore
WINDS
Snow Course Data
Average Water Content (Inches)
Elevation (ft}
2,000
1,500
660
February 1
37.2
29.4
16.2
March
53.1
40.9
28.2
April 1
65.3
55.4
34.7
The only available wind measurements near the study area are at
Petersburg. The prevailing directions are south and southeast. Approxi-
mately 50 percent of the time wind speeds are below 8 mph. Wind speeds
over 25 miles occur only about 1 percent of the time. The highest
hourly average over a 4-year period on record at Petersburg was 46 mph.
Because of the orientation of the Bradfield Canal near Tyee Lake.
occasionally strong gravity winds originating over the interior ice-
fields blows through the terrain channel toward the ocean. This flow
of cold air is strengthened during winter by the steep pressure gradient
between the coast and the interior. Hourly average wind speeds from
the east in excess of 35 mph have been measured occasionally at Peters-
burg during the winter months. These gravity winds need to be considered
in transmission line design.
A-9
EVAPOTRANSPIRATION
For both projects the proposed reservoir site is at an already
existing lake. Because of the cool, cloudy climate in the study area,
the additional evaporation from the reservoir surface, as compared to
the present site loss (from the surface and existing vegetation), will
be negligible. For this reason no adjustment for reservoir evaporation
was made in the power studies. Following project completion, the
monthly operating records for the lake should be adjusted to estimate
the full natural flow. This can be accomplished by adding to the
calculated lake inflow the difference between the lake evaporation at
natural level and that for the operating level for the given month.
This value in any given month may be negative or positive, since the
actual lake surface area may be greater or less than the existing
natural lake surface area. Evaporation records should not be used from
another part of southeast Alaska, because the differences may be large.
An evaporation pan should be maintained along with the project weather
station.
A-10
STREAMFLOW RECORDS
AVAILABLE RECORDS
Stream gaging data are available on both Tyee and Cascade Creeks.
Records of average monthly discharge are fragmentary for Tyee Creek
and much more extensive for Cascade Creek.
Stream Gaging Records
Station Years Period of Record
Cascade Creek 38 Water Years 1918 -1928
1947 -1973
Tyee Creek 12 Water Years 1922 -1927
1964 -1969
For the earlier period of record at Tyee Creek the gage was located
1 mile further upstream from the gage location in the 1960's. The
measured average monthly runoff for both stations is given in Tables
A-1 and A-2.
The U.S. Geological Survey has determined the pH and specific
conductance for Tyee and Cascade Creeks. The U.S. Fish and Wildlife
Service has measured dissolved oxygen and temperature in Tyee Lake.
For the discharge on both creeks, there are several days each year
with no gage-height records. For this reason, and also because of the
scarcity of good field hydrographic measurements, the records for Tyee
and Cascade Creeks are rated as 11 fair 11 by the U.S. Geological Survey.
A-ll
EXTENSION OF STREAMFLOW RECORDS
In order to develop a complete 50 years of streamflow data, the
records for the above gages were correlated with those from other
streams in southeastern Alaska having long historical records. Because
of its comparatively longer record, the Cascade Creek gage was initially
used in a series of correlations with three streams which were similar
in drainage area, watershed aspect, and elevation. After determining
the best correlation for Cascade Creek and calculating the years of
missing record, (1929-1946) and (1974-1976), the Cascade Creek record
was then correlated with the shorter record for Tyee Creek and an entire
50 years of streamflow data calculated for Tyee Creek. The early record
(1922-1927) for Tyee Creek was not used in the correlation analysis.
The three streamflow records considered in the initial correlation
analysis for Cascade Creek are listed below:
Streamflow Records for Correlation Analysis
Station
Dorothy Creek near Juneau
Fish Creek near Ketchikan
Sawmill Creek near Sitka
Drainage Area in
Square Miles
15.2
32.1
39.0
Period of Record
1930-1967
1916-1978
1920-1922,
1928-1942, &
1945-1957
Because the record for Sawmill Creek contained so many gaps, it was
not considered further in the correlation analysis. Of the two remain-
ing streamflow records, Dorothy Creek appeared to give the best fit
data as a predictor of Cascade Creek. However, since Dorothy Creek
A-12
records were not available for 1929 and parts of 1942 and 1944, the
Fish Creek records had to be used to fill in the missing records for
those years.
The best relationship was found by dividing the monthly streamflow
into winter and summer portions. The resulting equations are as follow:
(May-Oct) Qc = 1.41 Qd + 68
(Nov-Apr) Qc = 1.89 Qd + 4
Where: Qc = Cascade Creek near Thomas Bay
monthly discharge in cfs.
Qd = Dorothy Creek near Juneau
monthly discharge in cfs.
For Tyee Creek the correlation equations were as follow:
(May-Oct) Qt = 0.740 Qc
(Nov-Apr) Qt = 0.700 Qc
Where: Qt = Tyee Creek near mouth
monthly discharge in cfs.
Qc = Cascade Creek near Thomas Bay
Although the above equations provide an acceptably good fit, it is
likely that in a more detailed study, precipitation records could be
used to improve the predictions considerably. Precipitation records
at Petersburg are only 30 air miles from Cascade Creek as compared to
95 air miles to Dorothy Creek. For Tyee Creek, there are precipitation
records at Wrangell and Bell Island, 30 air miles south.
A-13
ESTIMATED OAMSITE STREAMFLOWS
The streamflow records at the two proposed damsites (Swan Lake on
Cascade Creek, and Tyee Lake on Tyee Creek) were developed using the
assumpticr that a direct linear relationship exists between drainage:
area and streamflow. Since no gaging records exist at the propo~~d
damsites, there is no way to verify this assumption. However, because
precipitation generally increases with altitude, it is probable that
the true runoff at Tyee and Swan Lakes is higher than that estimated
by using the proportional drainage area relationship. In addition,
the streamflow at Swan Lake likely includes a substantial volume of
glacial melt which would not be equal at all elevations on the water-
shed. Therefore, this cannot be estimated accurately by the propor-
tional drainage area method.
For both Tyee and Swan Lakes, the actual winter flows are likely
lower and the summer flows higher than the figure derived by the pro-
portional drainage area method. This is because the areas contributing
inflow to the gaging sites receive more precipitation in the form of
rain throughout the winter than do the lake watersheds. In summer,
the lake watersheds have a greater proportion of their runoff from
snowmelt than is the case for the watersheds at the gaging sites.
The following relationships were used to estimate the damsite
streamfl ows:
.IJ.-14
(May-Oct) Qs = 1.06 Qd + 51
(Nov-Apr) Qs = 1.42 Qd + 33
(May-Oct) Qtl = 0.653 Qc
(Nov-Apr) Qtl = 0.617 Qc
Where: Qs = Cascade Creek at Swan Lake
monthly discharge in cfs
Qd = Dorothy Creek near Juneau
Qtl = Tyee Lake monthly discharge in cfs
Qc = Cascade Creek near Thomas Bay
The drainage areas used in the calculation are as follow:
Location
Cascade Creek near Thomas Bay
Cascade Creek at Swan Lake
Tyee Creek near Mouth
Tyee Creek at Tyee Lake
A-15
Drainage Area
Square Miles
23.0
17.3
16. 1
14.2
STREAMFLOW CHARACTERISTICS
FLOW DURATION
Because the duration of streamflow levels is critical in power
production~ the respective flow duration curves for mean daily discharge
for both Tyee and Cascade Creeks is presented in Figure A-1. For
Cascade Creek, the lowest daily flow of record is 14 cfs; the curve
illustrates that rarely does the flow drop below 20 cfs. Tyee Creek
has experienced a minimum daily flow of 7 cfs and rarely falls below
10 cfs. For 25 percent of the time, Tyee Creek is below a 25 cfs,
whereas Cascade Creek drops below 25 cfs only about 5 percent of the
time.
Tyee Creek has a median daily flow of 105 cfs as compared to a
mean daily discharge of 175 cfs. For Cascade Creek, the respective
values are 155 and 251 cfs. This wide disparity between mean and
median daily indicates the uneven nature of the flows on both streams,
and illustrates the need for storage control on a seasonal basis in
order to capture and use effectively the comparatively infrequent high
flows.
Despite its very short period of record, Tyee Creek has experienced
a maximum daily flow of 1,950 cfs which exceeds that of Cascade Creek
(1,870 cfs). The flow duration curve indicates the extreme rarity of
high flows on either watershed. Discharge in excess of 1,000 cfs
occur less than 5 percent of the time.
A-16
)•
· DAILY FLm~ DURATION CURVES
3000
2000
1000
PERIOD OF.RECORD
Cascade Creek 1918-1928 & 1947-1973
Ul 500 Tyee Creek 1964-1969
4-u
OJ
O"l
&..
"' .J:.: u
Ul ,.... 200 Cl
>,
r-~ .,....
q/; as
I:: 100 8q
"' (}'
G.J
:E
0 10 20 30 40 50 60 70 80 90 100
Percent of Time Daily Flow Exceeds Indicated Value
A-17
FIG. A-1
It should be kept in mind that these flows are at the respective
gaging sites and that the minimum flows at the proposed damsite would
be somewhat lower. The sharp drop in the curve for Tyee Creek above
the 60 percentile level is noteworthy. This indicates that low flows
on Tyee Creek do not sustain as well as on Cascade Creek. It should
be kept in mind that these flows are at the respective gaging sites
and that the minimum flows at the proposed damsites would be somewhat
lower.
LOW FLOW FREQUENCY ANALYSIS
Although the seasonal fluctuations in streamflow from summer to
winter are extreme on both Tyee and Cascade Creeks, the reliability
of the total runoff from year to year is exceptionally high.
The low flow frequency curve for mean annual discharge at Cascade
Creek is presented in Figure A-2. The clustering of points about the
median value (248 cfs) is an indication of the high reliability of the
flow. The 100-year expected low flow can be derived by extrapolation,
using the straight line assumption. This value is 165 cfs or 67 percent
of the median annual flow. Also, noteworthy is the 20-year low flow
which is 202 cfs, or 81 percent of the median annual flow. From the
low frequency curve it can be inferred that prolonged periods of low
runoff are not a problem in the study area.
On the upper end of the curve, it is apparent that the expected
high annual average flows are not greatly in excess of the median.
For the 100-year and 20-year return periods, the respective annual
A-18
(/)
4-u
<!)
01 s...
"""
-. . ,....
Cl
<U
:::l c c
cJ::
LOW EXCEEOANCE FREQUENCY PER HUNDRED YEARS
95 90 8!) 70 60 50 4-0 30 2.0
)
JO
l i
i I . I I
400 _
1
1. ANNUAL .L01ILfw ~REQ~ENC~
I CAsc;DECREEK! nrl THC~fS r I
f
j
300
200
100
I
-----· ----t :-I
!
l
I
I
! -·-i --
·I ----
!
·I ' I
.l
I
I
I· I
I I I : ! ... 0!
!
i .
:· l
I I .
I I I . ·--1 -. '!' .
1 I
I ! I I
' l j I I
eri od ofi Rec'ord i38 years)
I I l I I
I
!
I
, I
I
2 5 10 20
'
RETURN PERIOD YEARS
A-19
2 1
i
i
I
r I .
I
I
~
I
I
r
I
I :
I
l
50 100
FIG. A-2
flows are 322 cfs and 302 cfs. These flows are respectively 130 and
122 percent of the median annual flow. It would, therefore, be unnec-
essary at Cascade Creek to construct a reservoir for the purpose of
storing large volumes of water in the years of high streamflow to be
used in subsequent years. The main use of the storage would be to even
the flow on a seasonal basis.
The record for Tyee Creek is not of sufficient length to permit
the construction of a useful frequency curve. However, such a curve
for Tyee Creek should be comparable to that for Cascade Creek.
The 50-year calculated streamflow records for both Tyee and Cascade
Creeks at the damsites include low flow periods which are significant
in evaluating the hydropower potential of the streams. The following
table presents a listing of lowest single-year and lowest consecutive
2 years.
Low Streamflow Periods
of the 50-Yr Calculated Record (cfs)
Mean Annual
Stream 1-Yr 2-Yr Discharge
Cascade Creek at
Swan Lake 151 ( l 951 ) 178 (1932-33) 190
Tyee Creek at
Tyee Lake 126 (1935) 135 (1951-52) 164
It is significant that the lowest years are over 75 percent of
average, from a 50-year calculated period of record. The critical
period for power production depends on the project design as well as
the natural streamflow. The critical period is described in Appendix
E under Hydropower Analysis.
A-20
FLOOD CHARACTERISTICS
Floodflows on both Tyee and Cascade Creeks are generally confined
to the summer and fall months (Jun -Nov) and are mainly the result of
heavy, coastal orographic rainfall. Snowmelt flows also are high but
rarely approach the level of rain flood discharges, primarily because
solar energy is limited by the high incidence of cloud cover. The
rain flood peaks on both watersheds are accentuated by the comparative
lack of vegetative cover, and the exceedingly rugged topography. The
relatively larger area of snowfield and glacial coverage on Cascade
Creek would tend to attenuate the rain flood peaks on that watershed.
Although the majority of flood discharges are related to rainfall,
flood events are not necessarily characterized by a sharply rising
storm hydrograph with a high peak of short duration. The fairly steady
region-wide rainfall from a succession of North Pacific storm systems
usually results in a slowly rising flood hydrograph which may remain
high for 3 or 4 days.
PAST FLOODS
Although the streamflow records for purposes of floodflow analysis
are short for Cascade and Tyee Creeks, the following tabulation illu-
strates the order of magnitude during peak flows.
A-21
Flood Discharges of Record
(cfs)
Cascade Creek Tyee Creek
near Thomas Bay near Mouth
Momentary Daily Momentary Daily
Date Peak Mean Date Peak Mean
09/ll/47 3,280 10/23/65 2,440 1,950
10/03/61 2,480 1 ,870 09/24/68 2,200 937
09/30/57 2,350 2,040 09/04/66 1 ,620 1 ,320
09/30/72 1 '960 1 '780 10/19/64 1,490 1 '390
10/01/72 1,850 1 '380 10/10/67 1,420 1 ,280
07/08/52 1,800 1 '580 10/06/65 1 ,200 859
10/15/61 1 '760 1 ,320 07/11/69 1 '120 1 ,010
10/02/58 1 '740 1 '560 10/16/63 960 808
09/04/66 1 ,650 1,460 09/11/68 917 788
All of the above flood peaks of record are rain events. It should
be noted that the tabulation includes only the single historical peak
flows for each individual year. The peak flows for the entire period
of record would include many additional high flows.
FLOOD FREQUENCIES
The frequency curve of annual peak discharges at Thomas Bay is
presented in Figure A-3. The curve was developed using the procedure
as outlined in Beard, Statistical Methods in Hydrology (1962). Using
the values from the curve in Figure A-3, the flood peaks for various
return periods can be estimated:
A-22
-
99 98
4000
3000
.,..
c 2000
1000
EXCEEDANCE FREQUENCY PER HUNDRED YEA~S
eo BO 10 60 50 4C 30 2()
I
I
I
PEAK:DISCHARGE FREQUENCY
I I 1 I I
CASCADE C EEK;nr THOMAS BAY
i ,. ' I
1 I
I
I I , I
I
I.
I
\ ' I I
I ·.'I ·; 1 '
I
I .
, 'I I
I l
I
I
I
I !
I I . t -I I
I I
l' I I
; I
i
I
I
I
I I I .
I I
I I
I I
'
I i
'
I
I .
! '
I
i
I
(Peri~d o~ Re~ord!!l947,
: ! ! I I !
1f51-lr73) , I
!
IO
, I
I
5
2 5 I 10 20
RETURN PERIOD YEARS
A-23
1• l
2 1
100
FIG. A-3
Peak Discharge Frequency
Cascade Creek near Thomas Bav
Return Period
{Years)
2
5
10
25
50
100
Discharge
(cfs)
1,540
1 ,880
2,175
2,750
3,525
3,950
The historical record for Tyee Creek was not adequate to provide
a representative distribution.
PROBABLE MAXIMUM FLOOD
The probable maximum precipitation (PMP) for southeastern Alaska
was calculated by the Hydrometeorological Branch of the National Weather
Service for six locations. These sites include Cascade Creek and
because of the topographic similarity and geographic proximity the
same PMP was also used for Tyee Creek.
The National Weather Service PMP values were estimated using a
generalized elevation-precipitation curve and observed 3-day storm
events in the project area. A high and low range value were given
for each location of interest. In deriving the probable maximum flood
(PMF) for Tyee and Cascade Creeks, the low range PMP was used. The
depth in inches for various durations is as follows:
A-24
Probable Maximum Precipitation
Cascade and Tyee Creeks
Duration (hours}
6
18
24
30
48
72
Depth
8.50
15.25
17.50
19.50
24.25
29.75
Source: National Weather Service -Memorandum of 6 May 1977.
The hourly precipitation totals were then derived for a theoretical
72-hour storm using the method outlined by the National Weather Service
in the same 6 May 1977 memorandum. The hourly values were then used
to simulate a flood hydrograph for each watershed using the computer
program HEC-1, 11 Flood Hydrograph Package ... The PMF so derived is
appropriate only for the months of August through November. For the
snowmelt season (May -July), the values of PMF are about 30 percent
lower than the tabular values.
Location
Cascade Creek at
Swan Lake
Tyee Creek at
Tyee Lake
Probable Maximum Flood
( cfs)
Spring Probable
Maximum Flood
5,040
4,270
A-25
Summer Probable
Maximum Flood
7,200
6,100
The above estimated flood discharges are appropriate only for Swan
Lake and Tyee Lake and not for the respective gaging sites. They are
the inflow hydrograph peaks for each lake. In the second stage of the
project, a bin-wall dam is proposed at Tyee Lake. A standard project
flood {SPF) equal to one half the PMF was routed through the reservoir
using assumed spillway widths of 100, 150, and 200 feet. The corres-
oondino oeak outflows for the summer SPF at Tvee Lake were respectively:
1,470, 1,640, and 1,850 cfs.
A-26
WATER QUALITY
SEDIMENTATION
Both the Tyee and Cascade Creeks drainage basins are composed of
consolidated igneous bedrock with little soil mantle. The only excep-
tions are the muskeg areas which rarely contribute sediment load to
the streams because they are poorly drained. The only significant
glacial coverage is on Cascade Creek (4 square miles). Tyee Creek
drainage has only about 0.4 square mile in glaciers and permanent
snowfields.
During a reconnaissance field trip to Tyee Lake in June 1978, the
creek inflowing at the head of the lake was clear with no apparent
glacial flour or other sediment. For the above reasons, the sedimen-
tation rate for Tyee Lake is expected to be negligible for an assumed
100-year life of the project.
A rational method for estimating sediment yield was developed by
Elliott Flaxman in the Proceedings of the American Society of Civil
Engineers, Hydraulics Journal, December 1972. His formula is appli-
cable only for nonglacial streams and is of the form:
Log (S+lOO) = 6.21 -2.19 log
+ • 06 1 og
.016 log
(Xl + 100)
(X2 + 100)
(X3 + 100)
Where: S = Annual sediment yield in acre-feet
per square mile
= Annual precipitation + mean annual temperature
(inches and oF)
A-27
x2 = Watershed percent slope
X3 = Percent coverage of soil particles
with diameter 1. 0 mm
x4 = Soil aggregation index
(negligible for Tyee Creek)
The value of S calculated for Tyee Creek drainage using the above
formula was less than zero. This supports the conclusion that sedi-
mentation in Tyee Lake is negligible over a 100-year time span.
Because there is a large talus cone on the south side of Tyee Lake,
it is likely that falling rock debris from this source through time
would tend to reduce the active lake storage. It would be difficult
to estimate the frequency of rock debris slides into the lake.
For Swan Lake on Cascade Creek, the 100-year sedimentation rate
was calculated by the Bureau of Reclamation in a 1965 hydropower study.
That estimate was 3,000 acre-feet of the active storage capacity of
the lake. The calculation was based on sediment yield data from small
glacial streams both in Europe and North America. The 3,000 acre-feet
would be less than 5 percent of the planned active storage capacity of
72,000 acre-feet. The 3,000 acre-feet estimate can be added to the
inactive storage in the elevation area capacity curve for Swan Lake.
WATER QUALITY SAMPLING
Stream water quality data are not regularly measured on either Tyee
or Cascade Creek. Measurements of temperature and dissolved solids for
both streams were published in the 1967 records of the U.S. Geological
A-28
Survey. Because the data are 1-day samples, they cannot be used to
define the water quality conditions on the two streams.
Water Quality Samples
Station Date
Cascade Creek near
Thomas Bay 9 Apr 67
Tyee Creek near
Mouth 10 Apr 67
Specific
Conductance
Discharge (cfs) (Micromhos)
35.3 25
13.8 12
7.2
6.7
A brief study of Swan Lake on Cascade Creek was conducted by the
Alaska Department and Fish and Game in July and September 1974. Thermal
stratification was not well developed in the lake, either in July or
September. The thermocline extended to a depth of 80 feet in September,
where the temperature was 39° F. The lake surface temperature was 42° F
in July and 46° F in September.
High values of chlorophyll and organic carbon were found in Swan
Lake during the 1974 sampling. Most of the water quality parameters
sampled changed little from July to September, except for the calcium
to magnesium ratio which showed a marked decline. The Department of
Fish and Game attributed the decline to changes in concentration of
dissolved minerals in the surface runoff which comes in greater contact
with exposed bedrock in the summertime. They appeared to have over-
looked the fact that a greater proportion of the water in late summer
would be of glacial origin.
A-29
The water quality sampling data for Swan Lake from the 1974 study
are given in the following tabulation:
Water Quality Data, Swan Lake near Thomas Bay
July and September 1974
7 July 9 September
Location Outlet West End Outlet Center
Sample Depth
s1o2 Fe
Mn
Ca
Mg
Na
K
pH
(ft) 3
(mg/1 ) 2. 1
(ug/1) 30
{ ug/1) 0
(mg/1) 3. 0
(mg/1) 0.2
(mg/1) 0.5
{mg/1) 0. 3
Color (Cobalt Units)
Total Nitrogen {mg/1)
6.7
2
0.17
Tota 1 Nitrite
plus Nitrate
Ammonia
Phosphorus
HC03
C02 so 4
sl
F
Total Dissolved
Solids
Hardness as
Caco 3
(mg/1)
(mg/1)
(mg/1)
(mg/1)
(mg/1)
(mg/1)
(mg/1)
(mg/1)
0.08
0
0
12
8.6
1.6
0.6
0
(mg/1) 15
(mg/1) 11
3
2.0
40
0
3.7
0.2
1.0
0.4
6.6
2
0.14
0.04
0
0
i2
9.3
1.5
0.7
0
16
10
2
1.4
10
10
1.7
1.6
1.9
0. 1
6.5
3 o. 19
0.01
0.02
o. 01
9
4.5
0. 1
0
16
11
Source: U.S. Geological Survey, Limnologica1 Investigations ... in
Southeast Alaska 1977.
12
1.3
200
40
2.0
1.5
1.8
0
6.3
5
0.17
0.07
0. 01
0. 01
9
4.5
0. 1
0
16
11
The turnover rate for both Tyee and Swan Lakes is fairly high. Tyee
Lake waters are replaced on an average every 9 months; Swan Lake waters
are replaced about once each year. There are no extensive water quality
data for Tyee Lake. During a field visit on 8 June 1978, the U.S. Fish
and Wildlife Service found the lake temperature to be 54° F (10° C) at
a depth of 50 feet. Dissolved oxygen was measured at 12 parts per
mi 11 ion.
A.-30
TABLE A-1
TYEE CREEK NEAR WRANGELL
Recorded Monthly Discharge in Cubic Feet Per Second
Drainage Area {1922-1927) 14 Square Miles {1964-1969) 16.1 Square Miles
WATER YR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL
1922 172 158 371 268 185 278
1923 238 263
1924 410 337 245
1925 288 340 343 205 154
1926 128 179 280 240 77 117 146 210 270 256 199 140 188
1927 313 140 112 67 30 35 50 167 380 299 191 226 168
):::> 1964 333 65 114 67 49 27 59 150 337 340 312 197 180 I
w 1965 355 106 79 90 46 42 77 155 362 313 161 108 159 __.
1966 435 60 50 26 19 48 75 211 374 307 265 312 183
1967 222 128 50 36 26 20 23 270 494 305 240 403 185
1968 272 155 55 31 51 100 43 245 317 290 181 435 181
1969 223 126 38 14 13 11 72 284 426 285 244 156 158
TABLE A-2
CASCADE CREEK NEAR THOMAS BAY
Recorded Monthly Discharge in Cubic Feet Per Second
Drainage Area 23.0 Square Miles
WAfER YR OCT NOV OEC JAN --Frn-MAR APR MAY JUN JUL AUG SEP ANNUAL
1918 589 657 74 66 27 20 51 195 482 532 656 400 314
1919 376 185 91 161 27 27 75 155 322 476 571 487 248
1920 334 102 73 78 60 33 34 99 441 549 676 332 235
1921 158 128 35 33 41 40 35 200 510 432 370 403 199
1922 566 124 147 50 25 20 65 181 310 473 502 395 240
1923 252 253 64 28 41 55 90 248 511 450 507 555 255
::z:.., 1924 385 238 78 37 25 45 65 292 594 529 517 684 291
I 1925 357 204 85 19 334 488 623 451 315 248 w 20 25 33
N 1926 210 184 346 405 74 139 272 288 410 412 326 231 276
1927 389 162 135 54 20 31 33 165 551 481 420 530 249
1928 299 85 32 141 49 66 72 365 571 588 442 424 262
1947 189 227 38 43 41 187 164 327 510 389 369 527 251
1948 188 160 72 86 40 27 25 349 496 403 357 484 224
1949 217 146 48 45 25 35 61 290 445 495 460 455 228
1950 376 372 62 25 20 23 27 164 518 504 388 428 243
1951 140 86 49 42 26 29 45 291 584 487 332 285 200
1952 244 112 67 33 33 30 47 258 438 615 465 522 239
1953 473 159 63 33 30 30 43 350 458 389 412 385 236
1954 393 133 77 51 199 34 30 196 456 390 281 331 214
1955 258 223 149 67 46 36 50 136 424 554 549 438 245
1956 215 137 40 23 20 16 35 360 423 542 662 301 232
1957 233 205 194 69 42 34 52 302 491 444 353 481 243
TABLE A-2 (cont)
CASCADE CREEK NEAR THOMAS BAY
WATER YR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL
1958 270 253 87 101 39 43 90 301 485 421 434 208 229
1959 566 142 105 48 56 43 60 265 515 660 476 273 261
1960 407 146 200 69 51 51 129 311 438 565 503 423 275
1961 613 196 176 80 87 35 111 299 578 536 640 403 315
1962 562 163 55 139 125 42 58 203 526 616 479 514 291
1963 289 244 291 178 196 77 62 261 400 445 351 633 286
1964 333 86 120 87 65 41 58 144 592 615 463 259 239
1965 342 153 103 154 59 63 70 158 423 407 327 255 211
1966 474 96 64 55 42 52 88 227 502 485 475 462 253
)> 1967 330 167 66 55 33 32 48 299 722 477 507 599 279
I 1968 291 215 76 96 96 138 72 290 368 518 320 611 258 w
w
1969 235 150 62 20 16 19 39 287 589 508 450 317 225
1970 219 393 234 72 83 56 51 229 554 463 472 535 281
1971 326 177 45 53 34 31 43 217 528 502 541 342 238
1972 240 107 56 38 60 95 40 250 505 651 626 471 262
1973 433 153 54 49 52 42 71 238 488 563 612 715 290
TABLE A-3
TYEE LAKE DAMSITE
Unregulated Monthly Flow in Cubic Feet Per Second
Drainage Area 14.2 Square Miles
WATER YR OCT NOV DEC JAN-FEB MAR APR MAY JUN JUL AUG SEP .ANNUAL
1927 254 100 83 33 12 19 20 108 360 314 274 396 165
1928 195 52 20 87 30 41 44 238 373 384 289 277 171
1929 188 87 32 53 11 39 22 127 308 326 360 194 147
1930 359 180 77 16 17 27 58 114 226 348 387 305 177
1931 224 228 119 48 85 28 42 152 347 331 379 320 192
1932 237 77 22 24 19 17 34 109 274 311 303 296 144
J> 1933 241 52 28 25 21 16 27 124 182 275 292 214 126
I 1934 200 186 39 14 16 20 25 100 274 299 418 274 156 w
-+::> 1935 242 99 66 22 14 24 25 94 195 409 324 230 147
1936 230 70 99 24 17 25 38 145 336 319 294 372 177
1937 463 333 134 32 20 30 33 105 319 274 320 357 203
1938 398 103 60 52 47 82 27 160 233 301 270 404 179
1939 258 90 66 39 30 22 30 111 252 359 445 281 166
1940 281 166 90 34 41 22 46 150 243 339 415 335 181
1941 249 84 39 22 30 30 66 132 275 341 244 181 142
1942 232 143 44 101 21 34 51 148 293 280 253 308 160
1943 276 64 39 46 25 49 75 132 253 397 355 397 177
1944 407 186 130 62 22 45 46 144 353 317 311 240 190
1945 339 166 100 25 19 32 34 152 268 348 286 330 187
1946 411 57 25 20 20 22 25 173 304 289 350 257 164
1947 123 140 23 27 25 122 107 214 333 254 241 344 163
1948 123 99 45 53 25 17 16 228 324 263 233 316 146
TABLE A-3 (cont)
TYEE LAKE DAMSITE
WATER YR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL
1949 141 91 30 28 16 22 38 189 291 323 300 297 148
1950 246 231 38 16 12 14 17 107 338 329 253 279 157
1951 91 53 30 26 16 18 28 190 381 318 217 186 130
1952 159 69 42 20 20 19 29 168 286 402 304 341 156
1953 309 99 39 20 19 19 27 229 299 254 269 251 154
1954 257 82 48 32 123 22 19 128 298 255 183 271 143
1955 168 138 92 42 29 22 31 89 277 362 358 286 159
1956 140 85 25 14 12 10 22 235 276 354 432 197 151
1957 152 127 120 43 26 21 32 177 321 290 231 314 155
·;p. 1958 176 157 54 66 24 27 56 197 317 275 283 136 148
I 1959 304 w 88 65 30 35 27 37 173 336 431 311 178 169
U1
1960 266 91 124 43 32 32 80 203 286 369 378 276 183
1961 400 122 109 50 54 22 69 195 377 350 418 263 204
1962 367 101 34 86 78 26 36 133 343 402 313 336 189
1963 189 151 180 110 122 48 38 170 261 291 229 413 184
1964 217 53 74 54 40 25 36 94 387 402 302 169 155
1965 223 95 64 95 37 39 43 103 276 266 214 167 136
1966 310 60 40 34 26 32 55 148 328 317 310 302 164
1967 215 104 41 34 20 20 30 195 471 311 331 391 181
1968 190 133 47 60 60 86 45 189 240 338 209 399 167
1969 153 93 38 12 10 12 24 187 385 332 294 207 146
1970 143 244 145 45 51 35 32 150 362 302 308 349 181
1971 213 110 28 33 21 19 27 142 345 328 353 223 154
1972 157 66 35 24 37 59 25 163 330 425 409 308 171
1973 283 95 33 30 32 26 44 155 319 368 400 467 188
1974 213 21 35 5 14 15 43 203 336 365 293 222 148
1975 328 130 90 36 16 18 29 157 328 361 297 252 171
1976 188 71 89 88 25 26 32 151 325 407 338 306 172
TABLE A-4
CASCADE CREEK AT SWAN LAKE
Unregulated Monthly Flow in Cubic Feet Per Second
Drainage Area-17.3 Square Miles
WATER YR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL
1927 293 122 102 41 15 23 25 124 414 362 316 399 187
1928 225 64 24 106 37 50 54 274 429 442 332 319 197
1929 217 106 39 65 13 47 27 146 355 376 415 224 170
1930 414 219 94 19 21 33 71 131 260 401 446 351 206
1931 258 278 145 59 104 34 51 175 400 381 437 369 225
1932 273 94 27 29 23 21 41 126 316 358 349 341 167
:Po 1933 278 64 34 30 26 19 34 143 210 317 336 246 150
I 1934 230 227 48 17 20 24 31 115 316 345 481 316 182 w
()) 1935 279 121 80 27 17 29 30 108 225 . 471 373 265 170
1936 265 85 121 29 21 30 46 167 387 368 339 429 191
1937 533 406 163 39 24 36 40 121 367 316 369 411 236
1938 458 125 73 64 57 100 33 184 268 347 311 465 208
1939 297 110 81 48 37 27 36 128 290 414 513 324 193
1940 324 202 110 41 50 27 56 173 280 390 478 386 211
1941 287 102 48 27 36 36 80 152 317 393 281 208 165
1942 267 174 54 123 26 41 62 171 338 323 292 355 186
1943 318 78 47 56 31 60 91 152 291 457 409 457 205
1944 469 227 159 76 27 55 56 166 407 365 358 277 222
1945 390 202 122 31 23 39 41 175 309 401 329 380 205
1946 473 70 31 24 24 27 30 199 350 333 403 296 190
1947 142 171 29 32 31 140 123 246 384 293 277 396 189
1948 141 120 54 65 30 20 19 262 373 303 268 364 168
TABLE A-4 (cont)
CASCADE CREEK AT SWAN LAKE
WATER YR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP ANNUAL
1949 163 110 36 34 19 26 46 218 335 372 346 342 171
1950 283 280 47 19 15 17 20 123 390 379 292 322 183
1951 105 65 37 32 20 22 34 219 439 366 250 214 150
1952 183 84 50 25 25 23 35 194 329 462 350 393 180
1953 356 120 47 25 23 23 32 263 344 293 310 290 177
1954 296 100 58 38 150 26 23 147 343 293 211 249 161
1955 194 168 112 50 35 27 38 102 319 417 413 329 184
1956 162 103 30 17 15 12 26 271 318 408 498 226 174
1957 175 154 146 52 32 26 39 227 369 334 265 362 183
1958 203 190 65 76 29 32 68 226 365 317 326 156 172
)> 1959 350 107 79 36 42 32 45 199 387 496 358 205 196 I
w
'-I 1960 306 110 150 52 38 38 97 234 329 424 378 318 207
1961 461 147 120 60 65 26 83 225 435 403 481 303 237
1962 423 123 41 105 94 32 44 153 396 463 360 387 219
1963 217 183 219 134 147 58 47 196 301 335 264 476 215
1964 250 65 90 65 49 31 45 108 445 462 348 195 180
1965 257 115 77 116 44 47 53 119 318 306 246 192 159
1966 356 72 48 41 32 39 66 171 378 365 357 347 190
1967 248 126 50 41 25 24 36 225 543 359 381 450 210
1968 219 162 57 72 72 104 54 218 277 390 241 459 194
1969 177 113 47 15 12 14 29 216 443 382 338 238 169
1970 165 296 176 54 62 42 38 172 417 348 355 402 211
1971 245 133 34 40 26 23 32 163 397 378 407 257 179
1972 180 80 42 29 45 71 30 188 380 490 471 354 197
1973 326 115 41 37 39 32 53 179 367 423 460 538 218
1974 245 26 43 6 17 18 53 234 387 420 338 256 172
1975 378 159 110 44 20 22 35 181 378 416 343 290 199
1976 217 86 109 107 30 32 39 174 374 469 389 352 199
SECTION B
FOUNDATION AND MATERIALS
THOMAS BAY GEOLOGY
The dominant geological features of the region are: (1) the coast
range batholith and (2) the metamorphic zone immediately to the west.
The western part of the batholith is characterized by bands of gneiss
in various stages of assimilation.
Swan Lake is some 32 kilometers north, northeast of Petersburg at
(57° 02' N, 132° 45' W). Access to the area is best made by helicopter.
Although a floatplane can get into the lake there is no accessible
landing along Cascade Creek flowing out of Swan Lake. Swan Lake is
a perched lake, bypical of many lakes in the southeastern Alaska. Swan
Lake is located between high, steep valley walls some 4 kilometers from
the tidewater at Thomas Bay. Cascade Creek drops over 1,500 feet in
roughly 4 kilometer, flowing through Falls Lake, a long narrow lake,
about one-third of the way down from Swan Lake at elevation 1,197 feet.
The creek below Falls Lake is entranced by a very steep walled canyon.
GENERAL GEOLOGY
Swan Lake lies within the crystaline rocks of the Great Coast
Range batholith. Immediately to the west is the broad belt of meta-
morphic rock which parallels the western edge of the crystaline rocks.
A layered sequence of rocks is exposed at tidewater near the mouth of
Cascade Creek where it empties into Thomas Bay. These rocks are of
argillite texture and appear to be quite durable and resistant to
weathering and sea erosion. The crystaline rocks that surround the
8-1
lake outlet ranges from quartz diorite to banded gneisses. The gneissic
banding appears to be more prevelant as one goes downstream towards
Thomas Bay. The rock is very hard and dense with small to medium
grained crystals.
JOINT AND LINEAMENTS
The dominant structures and lineaments which trend N 10° E, dipping
nearly vertical. While other joints persist, they are not well defined.
Onion skin jointing is quite pronounced in several areas. Other joints
probably trending in a NW direction were observed in the lake outlet
area and along Cascade Creek. The major indication of the NW joints
appear as a cliff above Falls Lake. The trend of this resistant rock
mass is N 50° w. Elsewhere topographic features indicate structure
trending NW. A strong surface expression is reflected by the valley
in which Cascade Creek flows. This lineament strikes N 50° E. Three
different places along the valley, (1) at the damsite, (2) halfway to
Falls lake, and (3) at Falls Lake, reveiled no evidence of either
jointing or faulting. However, when traversing the shoreline on the
way to the powerhouse site a shear zone some 15 to 20 feet wide exists.
The exact location of shear zone at tidewater is not known, but it is
approximately halfway to the powerhouse site. If the location is true,
then it alines well with Cascade Creek lineament and confirms that
Cascade Creek is flowing in a fault controlled valley.
B-2
LAKE OUTLET
The valley geometry at the outlet of the lake is very favorable
for most any kind of structure, bt it a low wier or a higher structure.
The narrow canyon has steep walls which rise several hundred feet above
the lake and are not unduly fractured. Onion skin jointing exists
on the south wall, the north wall is covered with vegetation preventing
terrain observation. Large boulders filled the bottom of the stream
at the outlet of the lake.
TAP AREA
The area selected for the lake tap is in a massive rock formation
that doesn•t have a large number of joints or lineaments passing through
it. The bathymetry is fairly steep with no shelves or breaks in the
slope where silt could build up. The rocks above the lake are covered
over with vegetation. Special attention will be given to this vegeta-
tion cover above the tap area. It is quite probable the vegetative
cover will require removing to insure that it will not slide into the
lake and endanger the tap.
PRESSURE TUNNEL
In the scheme where two short tunnels are utilized, the upper
tunnel is expected to be unlined except for the rock trap and gate
area. The lower tunnel is the pressure tunnel and/or penstock which
enters the powerhouse. From limited observations in the field and from
topographic maps there doesn•t appear to be any major lineaments which
would cross the tunnel area. However, it is quite safe to expect some
B-3
such structure crossing the tunnel. The selected scheme, which has
the long power tunnel shows numerous lineaments, of which some crossings
will require remedial treatment. Disposal of excavated rock from the
tunnel(s) is best utilized to make a level area for camp and other
auxiliary features associated with the tidewater facilities.
POWERHOUSE
The powerhouse locations for the two-tunnel scheme is in a small
basin at roughly 550 feet elevation. The present design consideration
is to have an above ground powerhouse. The tailrace would follow an
intermittent stream to Cascade Creek, thence to tidewater. No major
geologic problems are anticipated for the powerhouse or tailrace. The
powerhouse location for the long tunnel is located above ground several
hundred meters NW of the mouth of Cascade Creek, the exact location
has not been determined. The rock rises quite rapidly from tidewater,
thus providing an excellent site for an underground powerhouse. No
obvious geologic problems were observed from a traverse of some 2 kilo-
meters along the shoreline.
B-4
TYEE LAKE GEOLOGY
Tyee Lake is about 45 kilometers SE of Wrangell on the Bradfield
Canal at (56° 12' N, 131° 30' W). Access to the area is made either
by helicopter or floatplane. Tyee Lake is a high perched lake at
elevation 1,370 MSL. The lake is nearly 4 kilometers long and 600
meters wide. The valley walls rise on either side of the lake to
elevations 7,600 meters. Tyee Creek leaves the lake through a very
narrow defile in the rockwall and forms a series of cascades over the
first 300 meters before leveling off to a gradual decline in tidewater
at the head of Bradfield Canal.
GENERAL GEOLOGY
Tyee Lake is within a matamorphic band which trends somewhat to
the north, northwest. The rocks at the lake are contorted gneiss with
some pegnatite stringers. Because of the heavily forested countryside
joints and other rock discontinueties were not observed.
JOINTS AND LINEAMENTS
The topographic experssion in the area leads to the interpretation
of at least two major lineaments trending N 60° Wand at least two
minor lineaments trending NS. Elsewhere throughout the area are
numerous lineaments which trend N 60° W. This appears to be the major
structural trend of the area. Only one of the N 60° W trending linea-
ments would affect the pressure tunnel. The width is estimated to be
over 6 meters thick of closely broken rock. This observation was
made from a 1ow flying helicopter while flying over Tyee Creek.
B-5
TYEE DAMSITE
The location for a dam is between two shear walls of the outlet of
the lake. When observed the rock appeared normally jointed, i.e.,
1 to 3 meters apart. The outlet is chocked with larger diameter water
logged trees devoid of their limbs. Also, large boulders prevailed
through the outlet channel. A fracture is presumed to pass through
the outlet channel. The attitude of the fracture is not known but it
must dip to one side or the other to where the outlet stream has
encountered more resistance to erosion. When observing the cascading
water below the outlet there is no obvious evidence of a fracture
passing through the portion of the rock.
TAP AND PRESSURE TUNNEL
The tap area is located near the outlet on the NE side of the lake.
The rock, while well covered with trees, is quite steep. Fractures
could not be observed due to the vegetation. Topographically it
appears as if the tap area is between two lineaments which trend N
60° W some 600 meters apart. It can be presumed that unusually close
spaced jointing would not occur within this mass of rock. However,
investigation for onion skin jointing is quite necessary. This type
of jointing was not seen elsewhere in the area. The pressure tunnel
will cross at least one NW trending lineament which is described above.
POWERHOUSE
The powerhouse is to be located very close to where Tyee Creek
enters tidewater at the head of Bradfield Canal. The present scheme
B-6
is for an above ground facility. There was no obvious rock defects
which would be a problem with foundations for the powerhouse.
SEISMICITY
All of coastal southeastern Alaska is in a moderately active seismic
zone which has been classified Zone 3 by the Corps of Engineers. In
Zone 3, earthquakes of magnitude 6.0 and greater can be expected.
While there are no recorded earthquake epicenters in the immediate
project area, the Fairweather-Queen Charlotte Fault systems are well
defined and lie approximately 80 to 90 miles to the west of the project.
Swarms of microseisms have been recorded in recent years in south-
eastern Alaska, but it is not clear whether these events are related
to faulting, glacial movement, or glacial unloading. However, as
there are only two recorded epicenters of earthquakes within 100 miles
(both magnitude less than 5.0) and the nearest epicenter for any
earthquake of magnitude 6.0 or greater is 135 miles northwest of
Wrangell, the immediate project area appears to be relatively inactive
to the extent of available records.
B-7
SECTION C
REGIONAL ECONOMY
ECONOMY OF THE AREA
GENERAL
The area that comprises Petersburg and Wrangell is shown on the
records of the State as the Wrangell, Petersburg Census Division. In
addition to these major communities, the area includes the village
of Kake (west of Petersburg) and the fish processing center known as
Scow Bay.
For the purposes of this report, the human and natural resources
closely related to Petersbury and Wrangell will be treated. The popu-
lations of these two centers are about the same, and while there is
some difference in the degree to which major resources are being
developed at each community, they have the same five basic resources
in common.
POPULATION (HUMAN RESOURCES)
Early in the century these two communities were active in the
fishing and mining industries as their main economic base, while they
were each involved as a way station for equipment and supplies for
those who were traveling to Juneau, Skagway, and beyond.
Beginning in the 1960's the area economy took on an atmosphere
of diversification, which set the stage for the present economy and
the development that can logically be projected to the future. Since
1960 the area economy has been based on wood processing activities,
fish processing, institutional services, tourism, and basic transpor-
taion. The labor force associated with activity in these resources
C-1
sets the stage for overall population trends for both areas. Popu-
lation trends stayed steady for the overall election district prior
to the 1960 with extreme seasonal fluctuations based on high employ-
ment during summer months and extreme unemployment during winter months.
With industrial diversification, population trends showed a steady
growth pattern until recent years when a slight reduction based on
cutbacks in the wood processing industry has developed. The following
table shows population trends for Wrangell and Petersburg individually
and combined, and also the population trend of the Census Division,
which takes into account the areas just beyond the city limits plus
Kake and Scow Bay. Projections to 2000 are shown as 3 and 5 percent
annual growth rate suggesting that a number of favorable developments
will occur.
Population Trends for Petersburg, Wrangell,
and the Census Division l!
2000
Area 1960 1970 1975 1977 3% 50! ,-'Q
Petersburg 1 ,502 2,042 2,300 2,200 4,342 6,757
Wrangell 1 '315 2,029 2,300 2,250 4,440 6,910
Total 2,817 4,071 4,600 4,250 8,782 13,667
Census Div. 3,400 4,913 5,700 5,600 11 ,052 17,200
ll State Department of Commerce and Community Profiles.
LABOR FORCE
The following table shows the most recent breakdown of the labor
force by employment categories. The low employment period, the midyear
C-2
period, and the yearly average are shown for the Census Division as
reported by the State Department of Labor.
Civilian Labor Force (1977)
January ~ August Annual Aug
Total 1,966 2,345 2,643 2 '131
Unemployed 555 (28%) 178 (7.6%) 286 ( 10.8%) 327
Employed 1 ,411 2 '167 2,357 1,804
Insured Employment by Category
Total 1,618 2,444 2,675 2,051
Mining * * * * Construction 54 192 211 146
Manufacturing 440 781 923 611
Transportation and
Public Utilities 192 237 287 233
Wholesale Trade * * * * Retail Trade 241 316 305 266
Finance 28 28 30 27
Service 143 146 150 145
Miscellaneous 31 169 204 * Government 467 547 537 506
Federal 81 146 143 116
State 386 401 393 389
* Withheld to honor disclosure regulation.
Future employment patterns are not expected to differ greatly
between now and the year 2000. If the basic plan for roads developed
to the interior, hydropower development, bottom fish development, and
increased tourism become a reality, there could be a slight change in
the ratio of population to the labor force. These conditions result
as an economy becomes diversified and mature.
C-3
(15.3%)
NATURAL RESOURCES
Wood Processing
The wood products industry is Wrangell's leading industrial activity.
The two mills of the area produce 40 percent of Alaska's lumber exports
and in 1978 employed 125 people at the mill sites.
In 1977 the lumber mills of the area exported approximately 70
million board-feet of lumber to the Japanese market. Sitka Spruce
cuts accounted for the bulk of the production with lesser amounts of
Western Hemlock and cedar logs. For years the mills operated two
shifts per day, but since 1976 production has been reduced to one
shift per day and about 60 employees. The forest inventory of the
Petersburg/Wrangell area is shown in the following table.
Timber Inventory
Acres in National Forest
Annual Allowable Cut (mill board-feet)
Sustained Yield Capacity (mill board-feet)
3,286,000
201 ,000
358,000
Some forecasts have suggest as many as 475 people employed in the
lumber industry by 1978. Present D-2 legislation before Congress,
spiraling costs, and a weak foreign market have created a serious
concern about the future of the industry.
Fisheries
Fishing activity has been the main industry of Petersburg with
forest products second by comparison. While salmon processing has
long been the most important fish resource, there is a growing interest
C-4
and involvement in the bottom fish industry and the newly established
fish hatchery experiments. The Crystal Lake Hatcher, 17.5 miles south
of Petersburg was funded by a 2.3 mill bond issue and has a capacity
of 6 million eggs, 4 million alevins, 2 million fingerlings, or 1
million smolt. The natural stream production of southeatern Alaska
can be supported and sustained and kept at a more uniform level through
the output of this plant. Employment in the fishing industry is
expected to be more constant than in the past and in general the fish-
ing industry of the Wrangell/Petersburg area is projected to have a
bright future.
Tourism
The tourist industry has become a major factor in the economy of
southeastern Alaska. Each city along the Inside Passage route holds
some special attraction and provides local guided tours and festivities
designed to promote tourism. The Petersburg/Wrangell area has many
local attractions such that the Stikine River and the migratory water
fowl nesting areas of Dry Straits.
Future development plans call for a highway from Wrangell to the
town of Stewart in British Columbia. This will allow tourists from
British Columbia to travel to Wrangell and Petersburg by ferry and
return via the Aarons Creek highway.
Tourism through southeastern Alaska amounted to over 500,000 people
who spent an estimated $369 million within the State and for trans-
portation. In recent years tourists have accounted for 70 percent of
C-5
the total revenues of the State ferry system and have been the main
reason for the 20 percent annual growth rate in that system since it
started in 1963. In addition to the ferry system it is estimated that
13~000 cruise ship passengers will visit Petersburg and Wrangell during
1978. If present plans for the future are followed, tourism will play
an ever increasing role in the economy of the Wrangell/Petersburg area.
Mining
The Petersburg/Wrangell area has played a supportive role as an
outfitting point for mineral research conducted along the Stikine
River. Copper deposits in the Scud River area of Canada have been
researched extensively by crews and equipment from Wrangell and
Petersburg. The impact that the mining industry will have on future
development of the area will remain unknown until questions involving
land use have been settled at the national and State level.
Transportation
Employment associated with transportation is estimated at 90 workers
in the lumber loading and longshoring categories. Freight arrives by
barge from Seattle and British Columbia ports and by the ferry boats
moving between Seattle and Skagway. Future changes will be consider-
able if mineral deposits along the Stikine are developed or if the
Petersburg/Wrangell area is chosen for a mineral processing plant.
Lumber mills in the area are supplied by log tows, which involves a
minimum of highway transportation. The Wrangell Narrows inland passage
is the main route for general freight and tourist passengers moving
C-6
in southeastern Alaska by a wide variety of carriers. During 1976,
827,347 tons of freight and 17,000 passengers moved through the port
of Wrangell, which involved log tows coming to the Wrangell mills and
shipments of logs to Japanese markets. During 1976 the port of
Petersbury handled 55,000 tons of general freight and 31,496 passengers
mostly tourists travely the Inside Passage. As with mining and other
waterborne commerce, the future of the transportation industry lies
with decisions yet to be made in the future land use of the region.
C-7
SECTION 0
PROJECT DESCRIPTIONS AND COST ESTIMATES
Reservoir
PERTINENT DATA
THOMAS BAY
Maximum Elevation, feet msl
Average Elevation, feet msl
Minimum Elevation, feet msl
Tailwater Elevation, feet msl
Surface Area at Maximum Elevation
of Reservoir, acres
Usable Storage, acre-feet
Hydrology
Drainage Area, square miles
Annual Runoff, acre-feet
Average Annual, cfs
Maximum Annual, cfs
Minimum Annual, cfs
Power Tunnel
Tunnel Size, feet
Tunnel Length, feet
Tunnel Grade, percent
Gate Chamber and Adit
Gate Chamber (underground)
Gates, Hydraulic Slide Gates
Ad it
Tunnel Size, feet
Tunnel Length, feet
Tunnel Grade, percent
Surge Chamber (excavated in rock)
Diameter, feet
Length, feet
Penstock
Type
Diameter, feet
Length, feet
Shell Thickness
Maximum, inches
Minimum, inches
Support Spacing, feet
Type
l ,525
1 ,490
1,345
45
570
70,500
17.3
137,560
190
236
151
8 (horseshoe)
12,030
0.5
2
10 (horseshoe)
490
0.5
10
361
Steel -ASTM A537
Grade "A 11
6
2,970
2
3/4
40
Concrete
Powerplant (Stage II)
Number of Units (total)
Type of Turbine
Installed Capacity, kW
Plant Factor, percent
Net Hed
Maximum, feet
Average, feet
Minimum, feet
Generator Rating, kW
Power Factor, percent
Voltage, kV
Powerhouse
Transmission line
Voltage, kV
Type
PERTINENT DATA
THOMAS BAY (cant)
Length, miles (Wooden H-pole)
Length, miles (Submarine Cable)
Transmission Losses, percent (energy)
System Characteristices (Stage II, at site)
Dependable Capacity, kW
Primary Energy, MWH
Average Annual Energy, MWH
4
Impluse
34
50
l ,470
1,445
1,300
8,500
90
13.8
Steel Structure on
Concrete Foundation
100
Wooden H-pole and
Submarine Cable
43
16
2
15' 400
170,200
191 ,500
Reservoir
PERTINENT DATA
TYEE LAKE
Maximum Elevation, feet msl (Stage II}
Average Elevation, feet msl (Stage II}
Minimum Elevation, feet msl
Tailwater Elevation, feet msl
Surface Area at Maximum Elevation
of Reservoir, acres
Usable Storage, acre-feet (Stage II)
Hydrology
Drainage Area, square miles
Annual Runoff, acre-feet
Average Annual, cfs
Maximum Annual, cfs
Minimum Annual, cfs
Dam -Steel Bin Wall
Height, feet
Top Elevation, feet msl
Spillway Crest Elevation, feet msl
Power Tunnel
Tunnel Size, feet
Tunnel Length, feet
Tunnel Grade, percent
Gate Chamber and Adit
Gate Chamber (underground)
Gates, Hydraulic Slide Gates
Adit
Tunnel Size, feet
Tunnel Length, feet
Tunnel Grade, percent
Surge Chamber (excavated in rock)
Diameter, feet
Length, feet
1,420
1 '395
1,240
30
573
126,700
14.2
118,730
164
204
126
48
1 ,421
1,420
8 (horseshoe)
4,900
0.5
2
10 (horseshoe)
490
0.5
10
361
Penstock
Type
Diameter, feet
Length, feet
She 11 Thickness
Maximum, inches
Minimum, inches
Support Spacing, feet
Type
Powerp1ant (Stage II)
Number of Units (total)
Type of Turbine
Installed Capacity, kW
Plant Factor, percent
Net Head (Stage II)
Maximum, feet
Average, feet
Minimum, feet
Generator Rating, kW
Power Factor, percent
Voltage, kV
Powerhouse
Transmission Line
Voltage, kV
Type
PERTINENT DATA
TYEE LAKE {cant)
Length, miles (Wooden H-pole)
Length, miles (Submarine Cable)
Transmission Losses, percent (energy)
System Characteristices (Stage II, at site)
Dependable Capacity, kW
Primary Energy, MWH
Average Annual Energy, MWH
Steel -ASTM A537
Grade "A 11
6
2,300
2
3/4
40
Concrete
4
Impluse
32.8
50
1 ,390
1 ,365
1 '21 0
8,200
90
13.8
Steel Structure on
Concrete Foundation
100
Wooden H-pole and
Submarine Cable
79
12
3
11 '1 00
126,500
138,800
GENERAL
A screening study was performed to determine the most feasible
hydropower sites in the Petersburg-Wrangell area. The following sites
were investigated in detail: Tyee Lake, Swan Lake, Swan-Falls Lakes,
Anita-Kunk Lakes, Goat Creek, Sunrise Lake, Scenery Lake, Virginia
Lake, and Olive Lake. The Aaron Creek, Crittenden Creek, Thomas Lake,
Ruth Lake, and Wilkes Range projects were eliminated in a preliminary
screening. A construction cost estimate was derived for each site that
was investigated in detail. Tyee Lake and Swan Lake possess the most
potential for meeting both short and long term power requirements based
on power capacity and construction costs, therefore, these two projects
will be discussed here. Swan Lake is located on Thomas Bay, 17 air
miles north of Petersburg. Tyee Lake is located on the Bradfield
Canal, 47 air miles southeast of Wrangell. A 100 kV single conductor
ground return submarine cable transmission system was studied for the
two selected plans. Initial cost estimates indicated this type of system
would be more economical than a conventional one. The conventional
system will be presented in this study based upon its known reliability
over a single conductor system. Should these projects be investigated
at a more detailed level, the DC Submarine Cable will be studied at
greater length as an alternate transmission system.
D-1
ANITA -KUNK LAKES
Two rockfilled concrete faced dams and two powerhouses would be
required in this scheme. A 60-foot-high dam would be constructed at
Anita Lake. A 2.5-foot diameter steel penstock 6,300 feet long would
be required. A diversion dam and ditch would be required to divert
Anita Creek into Kunk Lake reservoir.
A 110-foot-high dam would be constructed near the outlet of Kunk
Lake. The waterway would consist of an 8-foot diameter power tunnel
1,600 feet long and a 4-foot diameter penstock, 1,150 feet long. A
diversion dam and ditch is required to divert runoff from an unnamed
creek into Kunk Lake. An access road 5 miles long would be constructed.
The transmission line would consist of 17 miles of wooden H-pole and
1.1 miles of submarine cable. Power from this project would be deliv-
ered to Wrangell.
The installed capacity for this plan is 6,800 kW which would pro-
duce 29,770 MWH of average annual energy.
0-2
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
ANITA-KUNK LAKES HYDROPOWER PROJECT
CONCRETE FACED, ROCKFILL DAM, UNGATED
Feature
Account Cost
Number Item ( 1 '000)
MOBILIZATION AND PREPARATORY WORK 4,000
01 LANDS AND DAMAGES 264
03 RESERVOIRS 360
04 DAMS 24,242
07 POWER PLANTS 9,489
08 ROADS AND BRIDGES 3,000
19 BUILDINGS, GROUNDS, AND UTILITIES 1,000
SUBTOTAL 42,355
20% CONTINGENCIES 8,471
CONTRACT COST 50,826
30 ENGINEERING AND DESIGN 4,066
31 SUPERVISION AND ADMINISTRATION 4,391
TOTAL PROJECT COST 59,283
D-3
GOAT CREEK
This project would have a rockfill dam with a reinforced concrete
upstream face. It would be 950 feet long and 85 feet high at its
deepest section. It would impound a reservoir of 94,900 acre-feet. A
100-foot wide by 700-foot long, side channel spillway excavated out of
rock would be located in the right bank. An intake structure would
house two 8-foot by 8-foot caterpillar gates and a trashrack. The
power tunnel intake invert would be approximately the same elevation
at the existing lake water surface. An 8-by 8-foot concrete lined
horseshoe power tunnel would extend to a surge chamber 7,500 feet
downstream. The surge chamber would be 18 feet in diameter and 180
feet deep excavated in rock. Two 30-inch steel penstocks, each 1,000
feet long. would convey the water from the surge tank to the powerhouse.
The powerhouse would contain two power units which would have a com-
bined capacity of 15,950 kW. This would produce 69,870 MWH of average
annual energy. An access road 30 miles long would run along the Stikine
River and would connect the powerhouse with a dock located on the
Eastern Passage near Wrangell. The 69 kV transmission line to Wrangell
would run along portions of the access road and would consist of 31
miles of H-pole construction and 2.7 miles of submarine cable. Power
from this porject would be delivered to Wrangell.
~4
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
GOAT CREEK HYDROPOWER PROJECT
CONCRETE FACED, ROCKFILL DAM, UNGATED
Feature
Account Cost
Number Item (1,000)
MOBILIZATION AND PREPARATORY WORK 5,000
01 LANDS AND DAMAGES 732
03 RESERVOIRS 232
04 DAMS 24,080
07 POWERPLANTS 18,120
08 ROADS AND BRIDGES 12,400
19 BUILDINGS, GROUNDS, AND UTILITfES 1,000
SUBTOTAL 61 ,564
20% CONTINGENCIES 12,313
CONTRACT COST 73,877
30 ENGINEERING AND DESIGN 5,910
31 ~UPERVISION AND ADMINISTRATION 6,383
TOTAL PROJECT COST 86,170
D-5
OLIVE CREEK
A 30-foot-high rockfilled concrete faced dam would be required in
this scheme to create a reservoir on Olive Lake. The crest of the dam
would be at elevation 460 feet. A storage capacity of 5,000 acre-feet
would be created. The waterway would consist of a 4-foot diameter
penstock 7,150 feet long. The access road would be 3 miles long. The
transmission line would require 25 miles of overhead line supported by
wooden H-poles and a 0.4 mile section supported by steel towers for
crossing the Zimovia Strait. The 3,260 kW of installed capacity would
produce some 28,560 MWH of energy which would be transmitted to Wrangell.
D-6
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
OLIVE LAKE HYDROPOWER PROJECT
CONCRETE FACED, ROCKFILL DAM, UNGATED
Feature
Account Cost
Number Item (1,000)
MOBILIZATION AND PREPARATORY WORK 2,000
01 LANDS AND DAMAGES 336
03 RESERVOIRS 40
04 DAMS 6,580
07 POWERPLANTS 8,571
08 ROADS AND BRIDGES 1,500
19 BUILDINGS, GROUNDS, AND UTILITIES 1 ,000
SUBTOTAL 20,027
20% CONTINGENCIES 4,005
CONTRACT COST 24,032
30 ENGINEERING AND DESIGN 1,923
31 SUPERVISION AND ADMINISTRATION 2,076
TOTAL PROJECT COST 28,031
D-7
SCENERY LAKE
A 160-foot-high concrete arch dam would be required in this scheme
to create a reservoir on Scenery Lake. The crest of the dam would be
at elevation 1,040 feet. A lake tap at elevation 825 feet would utilize
a storage capacity of 135,000 acre-feet. An 8-foot concrete lined
horseshoe tunnel 13,900 feet long would connect with a 2,100-foot above
ground steel penstock. A 282-foot surge tank in unlined rock would
be constructed at the juncture of the power tunnel and penstock. A
1,400-foot adit would provide access to the underground gate control
structure. An access road 3 miles long would be required. A tramway
from the end of the access road to the damsite would be required. A
transmission line consisting of 23 miles of wooden H-pole overhead
line and 3.6 miles of submarine cable would delvier power to Petersburg.
This project would produce some 127,900 MWH of average annual energy
based upon an installed capacity of 29,200 kW.
0-8
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
SCENERY LAKE HYDROPOWER PROJECT
CONCRETE FACED, ROCKFILL DAM, UNGATED
Feature
Account Cost
Number Item (1,000)
MOBILIZATION AND PREPARATORY WORK 6,000
01 LANDS AND DAMAGES 312
03 RESERVOIRS 384
04 DAMS 34,772
07 POWERPLANTS 19 '140
08 ROADS AND BRIDGES 1 ,500
19 BUILDINGS, GROUNDS, AND UTILITIES 3,500
SUBTOTAL 65,608
20% CONTINGENCIES 13 '122
CONTRACT COST 78,730
30 ENGINEERING AND DESIGN 6,298
31 SUPERVISION AND ADMINISTRATION 6,802
TOTAL PROJECT COST 91,830
D-9
SUNRISE LAKE
This scheme would require a concrete faced rockfill dam 45 feet
high. The damsite dewatering during construction would be accomplished
by a gated diversion tunnel. The diversion tunnel would be 10 feet
square and 595 feet long. After dam and spillway construction, an 18
inch diameter steel penstock would be placed in the diversion tunnel
and connected to the gate structure. The 4,040-foot steel penstock
would connect to the powerhouse at elevation 300 feet. The powerhouse
would have one 3,300 kW unit which would produce approximately 14,330
MWH of average annual energy. A dock and 2.5 miles of access road
would be required. A transmission line consisting of 8 miles of wooden
H-pole overhead line and 2.1 miles of submarine cable would deliver
power to Wrangell.
D-10
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
SUNRISE LAKE HYDROPOWER PROJECT
CONCRETE FACED, ROCKFILL DAM, UNGATED
Feature
Account Cost
Number Item (LOOO)
MOBILIZATION AND PREPARATORY WORK 1,000
01 LANDS AND DAMAGES 126
03 RESERVOIRS 40
04 DAMS 3,097
07 POWERPLANTS 4,761
08 ROADS AND BRIDGES 330
19 BUILDINGS, GROUNDS, AND UTILITIES 1,000
SUBTOTAL 10,354
20% CONTINGENCIES 2,071
CONTRACT COST 12,425
30 ENGINEERING AND DESIGN 994
31 SUPERVISION AND ADMINISTRATION 1 ,074
TOTAL PROJECT COST 14,493
D-11
SWAN -FALLS LAKES SCHEME
This scheme would consist of a lake tap, two gated tunnels, dam,
powerhouse, transmission system, access road, living quarters, dock,
and seaplane float.
A lake tap would enter Swan Lake approximately 170 feet below the
existing lake surface. It would connect to a 2,000-foot-long unlined
tunnel and discharge into Cascade Creek 0.4 mile above Falls Lake. It
would be controlled with hydraulic lift gates located near the outlet.
There would be a wier 30 feet high located at the Falls Lake out-
let. A lined 1,900-foot long power tunnel 8 feet in diameter would
contain two vertical lift slide gates and a trashrack. The powerhouse
would contain two units having a combined coapacity of 14,400 kW. This
scheme would produce some 63,000 MWH of average annual energy. The
powerhouse would discharge back into Cascade Creek 0.5 mile above the
mouth. An access road, 1.4 miles long, would connect the powerhouse
with the dock area. The powerplant would be controlled from Petersburg
by a carrier communications system. A 69 kV transmission line would
connect the powerhouse with Petersburg. A transmission line would
also connect Petersburg with Wrangell. Between the power project and
Petersburg there would be 18.9 miles of overhead line constructed with
H-poles and 3.6 miles of submarine cable. Between Petersburg and
Wrangell there would be 26.5 miles of H-pole line and 11.5 miles of
submarine cable.
0-12
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
SWAN-FALLS LAKES HYDROPOWER PROJECT
LAKE TAP, BIN WALL DAM
Feature
Account Cost
Number Item (1 ,000)
MOBILIZATION AND PREPARATORY WORK 3,000
01 LANDS AND DAMAGES 562
03 RESERVOIRS 72
04 DAMS 11 ,397
07 POWERPLANTS 15,230
08 ROADS AND BRIDGES 1,100
19 BUILDINGS, GROUNDS, AND UTILITIES 775
SUBTOTAL 32,136
20% CONTINGENCIES 6,427
CONTRACT COST 38,563
30 ENGINEERING AND DESIGN 3,085
31 SUPERVISION AND ADMINISTRATION 3,332
TOTAL PROJECT COST 44,980
D-13
VIRGINIA LAKE
This scheme would require a concrete faced rockfill dam 130 feet
high. The dam crest would be at elevation 220 feet. An active storage
of 91,700 acre-feet would be used. Diversion during construction would
be accomplished by a portion of the steel penstock. A 9-foot diameter
aboveground penstock 4,000 feet long would connect to the powerhouse
at elevation 10 feet. An aboveground steel surge tank 130 feet high,
24 feet in diameter would be required. An access road 0.9 mile long
would be constructed. The transmission line would consist of 6.8
miles of wooden H-pole and 2.7 miles of submarine cable. The 40,080
MWH of average annual energy based upon an installed capacity of 9,150
kW would be transmitted to Wrangell.
0-14
TABLE
SUMMARY COST ESTIMATE
JANUARY 1979 PRICE LEVEL
VIRGINIA LAKE HYDROPOWER PROJECT
LAKE TAP, BIN WALL DAM
Feature
Account Cost
Number Item ( 1 ,000)
MOBILIZATION AND PREPARATORY WORK 3,000
01 LANDS AND DAMAGES 92
03 RESERVOIRS 632
04 DAMS 23,997
07 POWERPLANTS 6,926
08 ROADS AND BRIDGES 90
19 BUILDINGS, GROUNDS, AND UTILITIES 1,075
SUBTOTAL 35,812
20% CONTINGENCIES 7.162
CONTRACT COST 42,974
30 ENGINEERING AND DESIGN 3,438
31 SUPERVISION AND ADMINISTRATION 3,713
TOTAL PROJECT COST 50,125
D-15
THOMAS BAY HYDROPOWER PROJECT
This study investigated a lake tap without a dam as the scheme to
develop the hydropower potential of Swan Lake. One and two stage con-
struction sequences were considered with the latter delaying expansion
of the powerhouse until the Petersburg-Wrangell area power load projec-
tions indicated the need. Total project design power production would
be 34 MW.
SELECTED PLAN
The selected plan is a lake tap without dam that would be constructed
in two phases. See Plates 2 and 3. The first phase includes construc-
tion of a lake tap, power tunnel, underground gate chamber and adit,
underground surge chamber, an aboveground steel penstock, and an above-
ground powerhouse with two 8.5 MW power units. Other features include
a switchyard and transmission line through Petersburg to Wrangell,
reservoir clearing, dock and seaplane float on Thomas Bay, living
accommodations for the operating crew, and an access road connecting
the dock area, living complex, powerhouse, and the power tunnel portal.
The second phase consisting of expanding the powerhouse and installing
two additional 8.5 MW power units would be constructed when power load
projections indicated the need. Access to the project site during con-
struction would be by water up Frederick Sound, by seaplane or helicopter.
Access to the gate chamber adit would be by helicopter.
D-16
LAKE TAP
The lake tap would be made directly from the power tunnel with the
invert at elevation 1,345 feet above mean sea level, approximately 170
feet below existing lake surface. A rock trap would provide space to
catch and permanently store approximately 97 percent of the rock from
the final blast. The power tunnel branches off from the side of the
rock trap above the floor level so that rock from the blast would not
be diverted into the power tunnel itself.
LAKE TAP TRASHRACK
The lake tap entrance would be covered by a steel trashrack to
prevent debris from entering the power tunnel and reaching the turbines.
Divers would place the trashrack in 170 feet of water. The trashrack
would be anchored to the rock with rock bolts.
POWER TUNNEL
The power tunnel would be an 8-foot horseshoe shaped conduit,
approximately 12,030 feet long. Excavation for the power tunnel would
begin at a portal on the Thomas Bay side of the mountain. The excavated
material would be disposed of north of the portal to not interfere with
the penstock construction. For this study it was assumed that 1,790
feet of the tunnel would be lined with reinforced concrete 1 foot thick
and 1,014 feet of tunnel would be rock bolted. During construction of
the tunnel onsite conditions will determine the required amount of
concrete lining and rock bolting. An alternate power tunnel alinement
was studied, but it did not provide sufficient rock cover in the area
of the gate chamber.
D-17
GATE CHAMBER
The gate chamber would house two 6-by 10-foot hydraulically
operated slide gates. The chamber would be dry and located underground,
approximately 3,000 feet from the lake tap. A 12 inch diameter pipe
with manually operated gate valve would be located in the gate chamber.
This pipe would provide minimum streamflow when the lake was not dis-
charging at its natural outlet. Access to the gate chamber would be
by a 10-foot horseshoe adit 490 feet long and a vertical shaft 54 feet
deep. The gate chamber and adit would be constructed with helicopter
access and maintained by helicopter. For this study, it was assumed
that 74 feet of the adit would be lined with reinforced concrete 1 foot
think and 42 feet of adit would be rock bolted. During construction of
the adit, a field investigation would be made to determine the required
amount of lining and rock bolting.
SURGE CHAMBER
The underground surge chamber would be located approximately 11,550
feet downstream from the lake tap with an invert elevation of 1,262
feet. The surge chamber would be 10 feet in diameter, rising approxi-
mately 361 feet above the power tunnel and would open vertically to the
ground surface. A horizontal tunnel or drift would connect the surge
chamber to the power tunnel. It was assumed that 150 feet of the surge
chamber would be rock bolted. During construction onsite conditions
will determine the required amount of rock bolting.
D-18
PENSTOCK
The penstock would emerge from a concrete plub in the power tunnel
through a steel chamber. The penstock would be a 6-foot diameter,
2,970-foot-long, all welded structure supported on concrete piers. The
penstock would extend approximately 90 feet from the power tunnel plug
through an open tunnel on a 1 percent slope to the portal, and then
continue on the remaining 2,880 feet to the aboveground powerhouse.
The portion that lies between the tunnel portal and powerhouse will be
constructed on a steep hillside.
POWERHOUSE
The Thomas Bay powerhouse would be located approximately 0.5 mile
from the mouth of Cascade Creek. The powerhouse design would be for
eventual installation of four 8,500 kilowatt three-phase generators.
Each generator would be driven by a 11,600 horsepower nozzle impulse
turbine with a rotational speed of 400 RPM at a design head of 1 ,300
feet. During Phase I, only two 8.5 MW units would be installed in the
powerhouse which will initially be constructed for these two units.
The powerhouse would be of steel frame construction and would be
designed and located so that future expansion could be accomplished.
The powerhouse structure would contain the generators, turbines, a
30-ton bridge crane, and all other equipment required for operation
and maintenance.
D-19
SWITCHYARD AND TRANSMISSION SYSTEM
The Thomas Bay switchyard would be located southeast of the power-
house. It would initially contain one three-phase transformer with a
second to be installed when the powerhouse is expanded. The transmission
line would begin at the Thomas Bay powerhouse and run 59 miles through
Petersburg to Wrangell. The transmission system voltage would be 100
kilovolts. The transmission line would consist of 43 miles of wood-pole
H-frames and 16 miles of submarine cable. A total of three submarine
cable crossings would be required. The Frederick Sound north of
Petersburg and the Stikine Strait would be crossed by 12 miles of sub-
marine cable. The 16.5 miles of wood-pole H-frame transmission line
north of Petersburg would be constructed and maintained by helicopter.
The 26.4 miles of wood-pole H-frame transmission line on Mitkof Island
would be constructed and maintained using the existing road. Two new
substations would be constructed, one at Petersburg and one at Wrangell.
ACCESS ROAD
A 3.5 mile access road would be constructed from the powerhouse
to the power tunnel portal. Access to the gate chamber adit would be
by helicopter.
BUILDINGS, GROUNDS, AND UTILITIES
The camp would provide quarters and offices during construction
and permanent maintenance facilities during operation of the projects.
It would consist of the dock, seaplane float, dormitory for eight men,
residence for one family, warehouse, garage, and sewer and water systems.
D-20
POWERHOUSE (PHASE II)
During Phase II, the powerhouse would be expanded and two additional
8.5 MW power units would be installed. This construction would bring
the powerhouse to its design capacity of 34 MW.
D-21
DETAILED COST ESTIMATE
THOMAS BAY HYDROPOWER PROJECT
LAKE TAP WITHOUT DAM
Cost Unit Total
Account Cost Cost 1/
Number Descri~tion or Item Unit Quant ill_ (1 ,OOOT
MOB AND PREP WORK LS 5,000
01 LANDS AND DAMAGES
Reservoir Area
Public Domain AC 33 (50)
Private AC 7 0
Transmission Line
Public Domain AC 284 (256)
Private AC 131 118
Government Admin Cost 20
TOTAL -LANDS AND DAMAGES (444)
04 DAM
04.1 POWER TUNNEL
Rock Excavation CY 25,707 180 4,627
Concrete CY l '979 500 990
Cement CWT 11 '162 12 134
Reinforcement TON 50 1,500 75
Rock Bolts Grouted
1'' 0 X 10'-0'' EA 732 275 201
Lake Tap LS 1 500
Trashrack TON 10 7,500 75
TOTAL -POWER TUNNEL 6,602
04.2 GATE CHAMBER
Rock Excavation CY 1 '586 175 278
Concrete CY 736 600 442
Cement CWT 4' 151 12 50
Reinforcement TON 18.4 1 '500 28
Slide Gates w/hoist TON 60 5,000 300
Minimum Streamflow
Pipe w/valve TON 13.75 2,500 34
Rock Bolts Grouted
111 0 X 10'-011 EA 32 275
TOTAL -GATE CHAMBER 1 • 141
D-22
THOMAS BAY HYDROPOWER PROJECT
LAKE TAP WITHOUT DAM (cant)
Cost Unit Total
Account Cost Cost 1 I
Number Description or Item Unit Quant ilL (l,OOOT
04.3 ADIT
Rock Excavation CY 1 ,605 170 273
Concrete CY 100 500 50
Cement CWT 564 12 7
Reinforcement TON 2.5 1 ,500 4
Rock Bolts Grouted
1"0 X 10•-o" EA 10 275 3
TOTAL -ADIT 337
04.4 SURGE CHAMBER
Rock Excavation CY 1,094 200 219
Concrete CY 29 1,000 29
Cement CWT 164 12 2
Reinforcement TON .75 1 ,500 1
Rock Bolts Grouted
111 0 X 10•-o" EA 300 225 68
TOTAL -SURGE CHAMBER 319
04.5 PENSTOCK
6'0 Pipe TON 1, 524 4,500 6,858
Stiffeners, Anchors TON 107 4,500 482
Concrete Anchor Blocks
Concrete CY 306 500 153
Cement CWT 1 '726 12 21
Reinforcement TON 7.7 1 ,500 12
Concrete Piers
Concrete CY 89 600 53
Cement CWT 502 12 6
Reinforcement TON 2.2 1 '500 33
Clearing AC 7 6,000 42
TOTAL -PENSTOCK 7,660
TOTAL DAM 16,059
0-23
THOMAS BAY HYDROPOWER PROJECT
Cost Unit Total
Account Cost Cost l/
Number Description or Item Unit Quant ilL (1 ,oooi
07 POWER PLANT
07.1 POWERHOUSE LS 1 7,200
07.2 SUBSTATIONS
Petersburg EA 1 400
Wrange 11 EA 1 2,500
07.3 TRANSMISSION LINES
Wood Pole by Road MI 26.4 150,000 3,960
Wood Pole by Helicopter MI 16.5 300,000 4,950
07.4 SUBMARINE CABLE
Conductors MI 16 600,000 9,600
Terminals EA 6 10,000 60
TOTAL -POWERPLANT 28,670
08 ROADS AND BRIDGES
Clearing AC 31.4 4,000 126
Rock Excavation CY 170,197 15 2 '553
Common Excavation CY 6,627 5 33
Embankment CY 14,889 2 30
Gravel CY 7,307 7 51
Culverts 18 11 ~ LF 200 25 5
Bridge (100 1 .f.) EA 1 300
TOTAL -ROADS AND BRIDGES 3,098
19 BUILDINGS, GROUNDS, AND UTILITIES
Dock LS 1 500
Sea p 1 a ne F 1 oa t LS 1 100
Camp Facilities LS 1 2,750
TOTAL -BUILDINGS, GROUNDS, AND UTILITIES 3,350
SUBTOTAL -CONSTRUCTION COST 56,177
CONTINGENCIES 20% 11 '235
TOTAL -CONSTRUCTION COST 67,412
D-24
Cost
Account
Number
THOMAS BAY HYDROPOWER PROJECT
LAKE TAP WITHOUT DAM {cont)
Description or Item Unit Quant
ENGINEERING AND DESIGN 8%
SUPERVISION AND ADMINISTRATION 8%
TOTAL -PROJECT COST PHASE I
INTEREST DURING CONSTRUCTION
PHASE I INVESTMENT COST
D-25
Unit
Cost
ill_
Total
Cost 1/
(1 ,oooT
5,393
5,824
78,630
10,812
89,442
Cost
Account
Number
DETAILED COST ESTIMATE
THOMAS BAY HYDROPOWER PROJECT PHASE II
EXPAND POWERHOUSE
Description or Item Unit Quant
MOB AND PREP WORK LS
07 POWERHOUSE
07.1 POWERHOUSE EXPANSION LS
SUBTOTAL -CONSTRUCTION COST
CONTINGENCIES 20%
TOTAL CONSTRUCTION COST
ENGINEERING AND DESIGN 8%
SUPERVISION AND ADMINISTRATION 8%
TOTAL -PROJECT COST PHASE II
INTEREST DURING CONSTRUCTION
PHASE II INVESTMENT COST
TOTAL INVESTMENT COST
AVERAGE ANNUAL COST
OPERATION, MAINTENANCE, AND REPLACEMENT
TOTAL AVERAGE ANNUAL COST
D-26
Unit
Cost
ill_
Total
Cost 1/
(l,OOOT
1 ,350
9,000
10,350
2,070
12,420
994
l ,073
14,487
996
6,972
96,414
6,637
450
7,087
TYEE LAKE HYDROPOWER PROJECT
This study investigated two types of dams located at the outlet of
Tyee Lake and one scheme for lake entry. Studies were made using
different spillway crest elevations and lake entry elevations. One and
two stage construction sequences were considered with the latter delaying
construction of the dam until the Petersburg-Wrangell area power load
projections indicated the need. This latter scheme would eliminate
the need for diversion structures during dam construction. A lake tap
was studied as the method of lake entry. The dam types studied were a
double curvature thin-arch with concrete gravity spillway section and
a steel bin wall with rockfill. Water would spill over the entire
length of the bin wall dam during periods of high flow. Total project
design power production would be 32.8 MW.
SELECTED PLAN
The selected plan is the steel bin wall dam scheme with two con-
struction phases. See Plates 4,5, and 6. The first phase would include
construction of a lake tap~ power tunnel, underground gate chamber and
adit, underground surge chamber, an aboveground steel penstock, and
the powerhouse containing two 8.2 MW units. Other features include a
switchyard and transmission line through Wrangell to Petersburg, dock
facility, upgrading the existing airstrip, living accommodations for
the operating crews, and reservoir clearing. The second phase consist-
ing of building a bin wall dam at the outlet of Tyee Lake and installing
two additional power units in the powerhouse would be constructed when
D-27
power load projections indicated the need. Access to the project site
during construction and operation would be by water up the Bradfield
Canal and by airplane or helicopter. Access to the tunnel protals
and the damsite would be by helicopter as road access was found to be
too costly.
LAKE TAP
The lake tap would be made directly from the power tunnel with the
invert at elevation 1,240 feet above mean sea level which is approxi-
mately 150 feet below existing lake surface. The rock trap would provide
space to catch and permanently store approximately 97 percent of the
rock from the final blast. The power tunnel branches off from the side
of the rock trap above the floor level so that rock from the blast
would not be diverted into the power tunnel itself.
LAKE TAP TRASHRACK
The lake tap entrance would be covered by a steel trashrack to
Prevent debris from entering the power tunnel and reaching the turbines.
Divers would place the trashrack in 150 feet of water. The trashrack
would be anchored to the rock with rock bolts.
POWER TUNNEL
The power tunnel would be an 8-foot horseshoe shaped conduit approxi-
mately 4,900 feet long. Excavation for the power tunnel would begin at
a portal on the Bradfield Canal side of the mountain. The excavated
material would be disposed of east of the portal so disposal would not
interfere with penstock construction. For study purposes it was assumed
that 735 feet of the tunnel would be lined with reinforced concrete l
D-28
foot thick and 415 feet of tunnel would be rock bolted. The actual
amount of concrete lining and rock bolting will be determined by onsite
conditions during tunnel construction.
GATE CHAMBER
The gate chamber would house two 6-by 10-foot hydraulically operated
slide gates. The chamber would be dry and located underground approxi-
mately 3,000 feet from the lake tap. A 12-inch diameter pipe with
manually operated gate valve would be located in the gate chamber to
provide minimum streamflow when the lake was not discharging at its
natural outlet. Access to the gate chamber would be by a 10-foot horse-
shoe adit 850 feet long. For this study, it was assumed that 128 feet
of the adit would be lined with reinforced concrete 1 foot thick and
72 feet of the adit would be rock bolted. The actual amount of lining
and rock bolting would be determined by onsite conditions during tunnel
construction.
SURGE CHAMBER
The underground surge chamber would be located approximately 4,500
feet from the lake tap with an invert elevation of 1,215 feet. The
surge chamber would be 10 feet in diameter, rising approximately 275
feet above the power tunnel and would open vertically to the ground
surface. A horizontal tunnel or drift would connect the surge chamber
to the power tunnel. It was assumed that 100 feet of the surge chamber
would be rock bolted. During construction onsite conditions would
determine the required amount of rock bolting.
D-29
PENSTOCK
The penstock would emerge from a concrete plug in the power tunnel
through a steel reducer. The penstock would be a 6-foot-diameter 2,300-
foot-long, all welded structure supported on concrete piers. The pen-
stock would extend approximately 200 feet from the power tunnel plug
through an open tunnel on a 1 percent slope to the portal, and then con-
tinue on the remaining 2,100 feet to the aboveground powerhouse. The
portion that lies between the tunnel portal and powerhouse will be con-
structed on a steep hillside.
POWERHOUSE
The Tyee Lake powerhouse would be located on the Bradfield Canal
approximately 500 feet from the mouth of Tyee Creek. The aboveground
powerhouse design would be for eventual installation of four 8,200-
kilowatt three-phase generators. Each generator would be driven by a
11,200-horsepower impulse turbine, with a rotational speed of 450 RPM
at a design head of 1,380 feet. During Phase I, two 8.2 ~1W units would
be installed in the powerhouse which would be sized for two units. The
powerhouse would be of steel frame construction and would be designed
and located so that future expansion could be accomplished. The power-
house structure would contain the generators, turbines, a 30-ton bridge
crane, and all other equipment required for operation and maintenance.
The area for the powerhouse site is presently being used by a logging
company as a permanent base camp in which living accommodations and
maintenance facilities have been erected. A crude docking facility
0-30
has already been constructed. A short service road would provide access
from the dock to the powerhouse.
SWITCHYARD AND TRANSMISSION SYSTEM
The Tyee Lake switchyard would be located adjacent to the west side
of the powerhouse. It would initially contain one three-phase trans-
former with a second to be installed when the powerhouse is expanded.
The transmission line would begin at the Tyee Lake powerhouse on the
Bradfield Canal and run 92.2 miles through ~/rangell to Petersburg. The
transmission system voltage would be 100 kilovolts. The line would
consist of 79 miles of wood-pole H-frames and 12 miles of submarine
cable. There would be three major overhead crossings of water obstacles.
One 0.54-mile span across the Bradfield Canal, and two spans across the
Blake Channel (0.33 mile and 0.26 mile). Six steel self-supporting
towers would be required for the overhead crossings. The overhead con-
ductors would be 397.5 MCM ACSR without overhead ground wires.
The portion of the transmission line from Tyee powerhouse to Wrangell
Island (21 miles with three overhead crossings of water) would be con-
structed and maintained by helicopter. Nineteen of the 33 miles of
transmission line on Wrangell Island would be build using the existing
improved road on the northwest tip of the island. There are also several
miles of unimproved logging roads on Wrangell Island that would be used
to construct and maintain a portion of the transmission line. The
Forest Service has indicated that the logging roads would eventually
be extended toward the southern portion of the island and portions of
0-31
the island and portions of these might be avialable for construction
use. The portion of the transmission line not paralleling the unim-
proved logging roads would be constructed and maintained by helicopter.
A more detailed routing study would be made during final design. The
12 miles of submarine cable would connect Wrangell Island and Mitkof
Island. The 26 miles of transmission line on Mitkof Island would be
constructed and maintained using the existing improved road on the west
side of the island. Two new substations would be constructed, one at
Petersburg and one at Wrangell.
ACCESS ROAD
Road construction was considered too expensive because of the steep
rocky terrain. A service road less than 1 mile long will connect the
dock, airstrip, powerhouse, switchyard, and camp facilities. A tug
and shallow draft barge will be required to transport supplies and
equipment from vessels anchored in deep water in the Bradfield Canal.
BUILDINGS, GROUNDS, AND UTILITIES
The camp would provide quarters and offices during construction and
permanent maintenance facilities during operation of the project. It
would consist of the dock, airstrip, dormitory for eight men, residence
for one family, warehouse, garage, and sewer and water systems.
RESERVOIR CLEARING
The reservoir clearing operation would remove all timber to an
elevation of 5 feet above maximum flood water elevation. Merchantable
timber will be sold and the remainder would be stacked and burned. Downed
timber currently floating in the lake near the damsite would be removed.
D-32
BIN WALL DAM (PHASE II)
The selected plan includes a 48-foot-high dam constructed of heavy
steel gage bin wall cells (used conventially for retaining walls). The
cells would be tied together and filled with rock. The top layer would
contain heavy riprap to prevent rock movement during peak runoff periods.
The cells would be keyed into the rock sidewalls of the channel and a
concrete cutoff wall would be placed at the heel. The upstream face
would have a welded steel membrane. A 40-foot wide section would be
set 1 foot lower than the adjacent sections to confine streamflow to
the center of the dam. During high runoff periods, flow would be over
the dam's entire length. The bin wall type dam was selected because
it utilizes the surrounding material and would require a minimum of
heavy equipment for construction. Rockfill would be obtained from a
quarry site near the dam outlet. An alternate quarry site at the south
end of the lake was considered too costly.
POWERHOUSE (PHASE II)
During Phase II, the powerhouse would be expanded and two additional
8.2 MW power units would be installed. This construction would bring
the powerhouse to its design capacity of 32.8 MW.
ALTERNATIVE TYPE OF DAM CONSIDERED FOR SELECTED SITE -THIN ARCH DOUBLE
CURVATURE DAM WITH LAKE TAP
The dam would be approximately 375 feet long measured along the dam
crest and 100 feet high. Top of the dam would be a televation 1,467
feet. The spillway would be 80 feet long with a crest elevation of
D-33
1,447 feet. The spillway would be a concrete gravity section. The lake
tap would be at elevation 1,350 feet. The remainder of the project
would be the same as for the selected plan.
0-34
DETAILED COST ESTIMATE
TYEE LAKE HYDROPOWER PROJECT PHASE I
LAKE TAP WITHOUT DAM
Cost Unit Total
Account Cost Cost 1 I
Number Description or Item Unit Quant _w_ ( 1 ,oooi
MOB AND PREP WORK LS 5,000
01 LANDS AND DAMAGES
Transmission Line
Public Domain AC 649 (876)
Private AC 116 157
Government Admin Cost 20
TOTAL -LANDS AND DAMAGES (1,053)
03 RESERVOIR
Clearing AC 22 4,000 88
Downed Trees LS 30
TOTAL -RESERVOIR 111
04 DAM
04.1 POWER TUNNEL
Rock Excavation CY 10,450 180 1 ,881
Concrete CY 813 500 407
Cement CWT 4,585 12 55
Reinforcement TON 21 1 '500 32
Rock Bolts Grouted
111 0 X 1 o• -0 11 EA 303 275 83
Lake Tap LS 1 500
Trashrack TON 10 7,500 75
TOTAL -POWER TUNNEL 3,033
04.2 GATE CHAMBER
Rock Excavation CY 1,950 175 341
Concrete CY 580 600 348
Cement CWT 3,270 12 39
Reinforcement TON 15 1,500 23
Slide Gates w/hoist TON 60 5,000 300
Minimum Streamflow
Pipe w/va1ve TON 21.25 2,500 53
Rock Bolts Grouted
111 0 X 1 0' -0 11 EA 40 275 11
TOTAL -GATE CHAMBER 1 '115
D-35
TYEE LAKE HYDROPOWER PROJECT PHASE I
LAKE TAP WITHOUT DAM (cant)
Cost Unit Total
Account Cost Cost 1/
Number Description or Item Unit Quant ill_ (1 ,oooT
04.3 ADIT
Rock Excavation CY 6,117 170 1 ,040
Concrete CY 173 500 87
Cement CWT 976 12 12
Reinforcement TON 4.5 1 '500 7
Rock Bolts Grouted
111 0 X 10 '-0 11 EA 28 275 8
TOTAL -ADIT 1 '154
04.4 SURGE CHAMBER
Rock Excavation CY 810 200 162
Concrete CY 20 1 ,000 20
Cement CWT 113 12 2
Reinforcement TON 0.5 1,500 1
Rock Bolts Grouted
111 0 X 10'-0 11 EA 200 225 45
TOTAL -SURGE CHAMBER 230
04.5 PENSTOCK
6'0 Pipe TON 1 ,259 4,500 5,666
Stiffeners, Anchors TON 88 4,500 396
Concrete Anchor Blocks
Concrete CY 204 500 102
Cement CWT 1 '150 12 14
Reinforcement TON 3 1,500 5
Concrete Piers
Concrete CY 63 600 38
Cement CWT 355 12 4
Reinforcement TON 1 1 ,500 2
Clearing AC 7 6,000 30
TOTAL -PENSTOCK 6,257
TOTAL DAM 11 '789
D-36
TYEE LAKE HYDROPOWER PROJECT PHASE I
LAKE TAP WITHOUT DAM (cont)
Cost Unit Total
Account Cost Cost 1/
Number Descri~tion or Item Unit Quant ill_ (1 ,oooi
07 POWERPLANT
07. 1 POWERHOUSE LS 1 7,000
07.2 SUBSTATIONS
Petersburg EA 1 400
Wrangell EA 1 2,500
07.3 TRANSMISSION LINES
Wood Pole by Road MI 45 150,000 6,750
Wood Pole by Helicopter MI 35 300,000 10,500
Steel Self-Support Towers EA 6 75,000 450
07.4 SUBMARINE CABLE
Conductors MI 12 600,000 7,200
TOTAL -POWERPLANT 34,800
19 BUILDINGS, GROUNDS, AND UTILITIES
Dock LS 1 500
Inprove Existing Airstrip LS 1 200
Camp Facilities LS 1 2,750
TOTAL -BUILDINGS, GROUNDS, AND UTILITIES 3,450
SUBTOTAL -CONSTRUCTION COST 56,210
CONTINGENCIES 20% 11 ,242
TOTAL -CONSTRUCTION COST 67,452
ENGINEERING AND DESIGN 8% 5,396
SUPERVISION AND ADMINISTRATION 8% 5,828
TOTAL -PROJECT COST PHASE I 78,676
INTEREST DURING CONSTRUCTION 10,818
PHASE I INVESTMENT COST 89,494
D-37
DETAILED COST ESTIMATE
TYEE LAKE HYDROPOWER PROJECT PHASE II
BINWALL DAM
Cost Unit Total
Account Cost Cost
Number Descri~tion or Item Unit Quant ilL (1 ,000)
MOB AND PREP WORK LS 2,000
01 LANDS AND DAMAGES
Reservoir Areas
Public Domain AC 36 (54)
Private AC 0 0
TOTAL -LANDS AND DAMAGES
04 DAM
04.1 BIN WALL
Clearing AC 1 6,000 6
Rock Excavation CY 8,000 50 400
Overburden Excavation CY 5,500 35 194
Steel Bins TON 243 3,000 729
Rockfi11 for Bins CY 17,877 50 894
Rockfi 11 at Heel CY 367 50 18
Steel Plate on Face
of Dam TON 50 2,500 125
Concrete Cutoff Wall
Concrete CY 75 500 38
Cement CWT 423 12 5
Reinforcement TON 0.5 2,000 1
TOTAL -BIN WALL DAM 2,410
07 POWERHOUSE
07.1 POWERHOUSE EXPANSION LS 8,750
SUBTOTAL -CONSTRUCTION COST 13,214
CONTINGENCIES 20% 2,643
TOTAL CONSTRUCTION COST 15,857
ENGINEERING AND DESIGN 8% 1 ,269
SUPERVISION AND ADMINISTRATION 8~~ 1 '370
D-38
Cost
Account
Number
DETAILED COST ESTIMATE
TYEE LAKE HYDROPOHER PROJECT PHASE II
BINWALL DAM
Description or Item Unit Quant
TOTAL -PROJECT COST PHASE II
INTEREST DURING CONSTRUCTION
PHASE II INVESTMENT COST (1990 Present Worth)
TOTAL INVESTMENT COST
AVERAGE ANNUAL COST
OPERATION, MAINTENANCE, AND REPLACEMENT
TOTAL AVERAGE ANNUAL COST
D-39
Unit Total
Cost Cost
.ill_ ( 1 ,000)
18,496
1 ,272
11 '613
101,107
6,960
450
7,410
SECTION E
POWER STUDIES AND ECONOMICS
METHOD OF ANALYSIS
Initial Screening
HYDROPOWER ANALYSIS
The first step in the analysis was to select a series of project
sites which were close enough to the Petersburg-Wrangell service area,
such that transmission line distances were minimized. A total of 14
projects at 14 different sites received consideration in the initial
screening analysis. These are listed in Table E-1, together with per-
tinent data used in the evaluation.
The projects are listed in Table E-1 with the highest benefit/cost
ratios at the head of the tabulation. Further details on the projects
which were screened out are presented in the section entitled "Hydro-
electric Alternatives."
For projects listed in Table E-1 the pertinent data is that used
in the screening analysis. Further studies resulted in changes to the
project physical data for Tyee and Cascade Creeks. This also resulted
in changes to the benefit/cost ratios for those projects. For Cascade
Creek Scheme #2, the original estimated cost was found to be too low,
based upon observations during the field reconnaissance in June 1978.
Scheme #2 for Cascade Creek was subsequently dropped from consideration,
and the benefit/cost ratio shown in Table E-1 is no longer valid.
Scope
The hydropower analysis was limited to those project alternatives
which appeared to show promise based upon the initial screening and the
E-1
-·----o,:a rr~a~-~----··-----~
Pr_cj~~-------
Tyee Lake
Cascade Creek
Sch<O,~ 2
Cc s•:<d;; Creek
s~: he:~e I
Tno··,s Lake
01 ive Lake
Sunrise lake
Sc.€c.try Lake
(;'}-;: t (reek
~v[fl Lcke
\' ~ ir.ia La I.e
!.nit<' Crtek
run I: La~e
IIi lfes Creek
?.:~ r·uo Creei
(r~ tL: rd':n (r'H·k
fT1
I
N
14.1
19.1
17. 3
19.0
3.8
1.2
18.0
14.0
6.7
40.6
2.5
8.0
1.4
94
10.0
Transmissicn i inP
42 2.0
14.8 4.2
14.8 4.2
20.1 0
22 2.0
6.6 2. l
19.3 ~.2
25 1.5
14.3 4.2
8.0 L5
1.6 to 0
Kunk Lake
14.1 1.1
20 2.5
21.0 l.S
6.5 2.0
TAKLI r l
tiYfJ'.: 0\if R SCR! : :.(~ Mlf\L YS[S
SOUffiU>l ALA SKI\ -f'[ ': ERS 8URG-WRAtlGEI.l
·-· -~i-:iit;l e·· -~~~~ -~il L·d ---··--
t nor~y Length
( f~ ,, ".L. ---. !ftl
161 1 ,380 za.:~o 1 J~ ,:;00 4,500
210 550 14 .~;)0 63,372 3,400
192 1 .300 3H, ~ JO Hl,oUD 11,600
158 274 6,:~0 2n,?80 4,200
65 370 3,."00 z:.\, "60 None
15 1,608 3,: JL) 1 '· '30 None
215 1,000 29, 1?,' ,}l)t) 17,000
153 905 1~ •. a f.':,.~70 5,700
31 1,260 ~~,: JO ~.1.210 7,000
414 163 9,150 ~a.GS(l None
27 1,007 3,00 15,144 None
74 310 3,110 1,600.
15 1 ,400 2 ·' :s 2,400
400 118 6,~.'3 None
20 200 5~0 ".400 None
rutaY Aiu\,ia 1
Length Surge Height Benefits cost 0/C
{ft)_ __ cr. amber _lf_li ____ .....J!!l2.~".!".h ...... •.••. .2J[!OUS.Oildi,_ ______ Ratio
2,000 Yes 60 Rock 8,823 1,802 1.13
1,200 No 50 4,091 3,522 1.16
2,215 Yes laketdp 12,115 7,540 1.61
600 Yes 3 Dams 1,705 1 ,!:l35 .93
4,5(,(} No 30 Rock 1,649 2,195 • 75
3,~c:o flo 40 Rock 931 1 '135 .82
5CO Yes 94 Concrete A.-cell 8,297 7,191 1.15
1,000 Yes 10· Rock 4,532 6,747 .67
2,6CO Yes 5? Rock 1,506 l,Y ~ .77
2,450 No no Rock 2,600 J~ 1}25 .66
6,300 No 60 Hock
1,932 4 ,G42 .42
1,150 No 110 Rock
1,950 No 3 DctmS 801 1 ,92,0 . 41
3,000 No 2 Dams 1,817 4,t)6.l .39
3,700 No 30 Rock 155 799 0.19
field reconnaissance. One alternative project is a two-phase scheme at
Tyee Lake which includes an installed capacity of 14.4 MW for each
phase. The second project is at Thomas Bay on Cascade Creek, and con-
sists of two phases each having a total of 19.5 MW of installed capacity.
The Tyee Lake Phase 2 includes a 150-foot bin wall dam. No dam is
planned for the Thomas Bay site.
Methodology
The calculated set of 50 years of historical streamflow (1927-1976)
for each project was used in a simulated re·servoir operation study.
The computer program entitled "Empower 11 developed by the Alaska District
was used for this purpose. The program provides estimates of both the
installed capacity and total monthly generation for each reservoir
operating design configuration.
By performing successive runs with the program Empower, the maximum
generation for the period of lowest streamflows was determined for both
phases of both the Tyee and Thomas Bay projects.
The program output using Empower was also checked using the HEC-e
11 Reservoir Regulation" program developed by the Hydrologic Engineering
Center at Davis, California. Results were comparable in all significant
respects.
Both of the above computer programs include necessary assumptions
which may materially affect the estimated total generation. Both programs
indicated above have no seasonal volume forecast and consider the stream-
flow only on a month-by-month basis. This also means that high flows of
brief duration would not be taken into account for the monthly analysis.
E-3
Power Production Variables
The following variables include many of the necessary assumptions
used in the hydropower analysis.
Free Surface Evaporation: For both the Tyee and Thomas Bay projects
no new reservoirs are proposed. Because the lake level would be raised
at Tyee Lake in the second phase of development, the water surface area
may be slightly greater than for natural conditions. The difference
would~ however, be negligible because of the cool, cloudy weather which
prevails in the project area. Accordingly in the power studies, no
adjustment to the natural runoff was made for lake evaporation at
either project.
Effective Hydraulic Head: In both schemes under consideration,
the powerhouse would be located near tidewater. The tailwater elevation
was assumed to be 15 feet elevation for both projects, and no tailwater
rating curve was used in the power studies. For Tyee Lake the conduit
friction head losses averaged 30 feet. Because of the extremely long
tunnel at the Thomas Bay site, the total conduit head loss is 45 feet.
The values for effective head given in the following table are for
average flow conditions at average lake elevation.
Effective Head
Project Net Effective Head (ft)
Thomas Bay
Scheme 1, Stage I 1,445
Stage I I 1 ,445
Tyee Creek
Stage I 1 '322
Stage II 1 ,365
E-4
These were calculated by deducting the friction losses and tailwater
elevation from the gross head. These values were used in the simula-
tion studies.
Sedimentation
Sedimentation rates on Tyee Lake are assumed to be negligible and
no adjustment in the storage capacity curve was made. For Swan Lake,
however, a 50-year sedimentation of 1,500 acre-feet of the active storage
was deemed necessary. The reducted storage volume was used in the
operational studies but did not significantly affect the results.
Plant Factor
For the operational studies, a plant factor of 50 percent was assumed
of the ultimate developmetn phase on both projects. The basis for
selection of the plant factor for both projects is solely to maximize
available firm capacity by utilizing all water that can be made avail-
able eitehr from streamflow or reservoir storage. The selection of the
50 percent plant load factor is not necessarily optimum for the Petersburg-
Wrangell service area from the standpoint of economics or system require-
ments.
Monthly Electrical System Load Curve
Using the monthly system energy consumption for Petersburg and Wrangell
combined, during 1970-1977, the following seasonal load curve was
derived.
E-5
Petersburg-Wrangell Monthly Electrical Load
Month
~t
Nov
Dec
Jan
Feb
~r
Apr
May
Jun
Jul
Aug
Sep
Total
Percent Annual
8.4
8.8
9.6
8.5
7.8
8.8
7.5
7.6
7.5
8.4
8.7
8.4
100.0
The demand is at a minimum in June when streamflow is highest and
at maximum in early winter when streamflow is very low, or moderate in
quantity. The overall load is fairly even throughout the year.
The above data, however, did not include the possible future addi-
tion of load to the system from sawmills and canneries at Wrangell which
at present generate much of their own power. Industrial consumbers
might change the shape of the curve substantially. Also, not apparent
in the above load curve is the fact that the loads at Petersburg and
Wrangell tend to fluctuate heavily from year to year depending on the
success of the commercial fish catch •
. Flow Requirements
In the power studies for both Tyee and Thomas Bay, no fish release
requirements below the respective lakes were used. The rugged nature
of the stream channels below the lakes precludes all but intertidal
E-6
spawning. The possible need for maintianing the lake levels for recrea-
tional purposes was not included in the power studies. This is an area
for further refinement in future planning stages.
Power Potential of Alternative Development
The initial screening process resulted in the elimination of all
but three of the original 14 projects. Then, following the field recon-
naissance, one of the remaining three projects were eliminated. That
project was a smaller scheme on Cascade Creek (Scheme 2) wherein Falls
Lake rather than Swan Lake would be used as the operating intake reser-
voir for the power tunnel to Thomas Bay. It was determined in the field
that road access to Falls Lake would be prohibitively costly, therefore,
rendering Cascade Creek, Scheme 2, unattractive for further study. The
hydropower analysis for the remaining two alternatives were carried out
with the following results.
At Site Generating Capability
Tyee and Thomas Bay
Thomas Bay
Scheme 1, Stage I
Stage II
Tyee Creek
Stage I
Stage II
Installed
Capacity
(Megawatts}
19.4
38.8
14.4
28.8
Prime Energy
(Megawatt Hours)
139,500
170,200
110' 200
126,500
E-7
Average
Annual Energy
(Megawatt Hours)
147,500
191,500
117,200
138,800
The prime energy is the dependable generation for the year with the
most adverse water conditions. The difference between actual energy
and prime energy is the secondary energy. The following are pertinent
physical data for the Tyee and Cascade Creek alternatives.
Storage Data Swan and Tyee Lakes
Maximum Gross Active Inactive
Water Surface Storage Storage Storage
e 1 ev. ft. ac-ft ac-ft ac-ft
Swan Lake
Stage I 1 ,515 (Lake) 97,500 70,500* 25,500
Stage II 1 '515 97,500 70,500* 25,500
Tyee Lake
Stage I 1,387 (Lake) 81 ,500 110,300 28,800
Stage II 1,420 97,900 126,700 28,800
* Adjusted for sedimentation
E-8
EXISTING ELECTRICAL UTILITY SYSTEM
At present, power in the Petersburg/Wrangell area is supplied by
the city of Petersburg Municipal Power and Light Department and the
city of Wrangell. Resources for Petersburg are the Blind Slough Hydro-
electric Project with a nameplate capacity of 1.6 MW and diesel electric
generation with total nameplate capacity of 6.9 MW. Resources for
Wrangell are diesel electric. Total nameplate capacity is 7.75 MW with
2.25 MW due for retirement in 1985.
HISTORICAL LOAD GROWTH
Table E-2 shows historical annual system loads for the years 1968
to 1977. This information is derived from a report by Robert W. Retherford
Associates, Preliminary Appraisal Report Tyee Lake Hydroelectric
Potential, September 1978.
FUTURE POWER NEEDS
Three different load forecasts have been made for the Petersburg/
Wrangell market area. The medium load growth case is based on a 6 per-
cent annual growth rate assumption made in the Virginia Lake Appraisal
Report, August 1977, by R.W. Beck and Associates. In a letter from APA,
they advised examination of one load case that would assume a move toward
an all-electric economy. For this case we applied a 100 percent increase
in 1990 energy demands over the figures shown in the Beck study. The
low load case was evaluated using data from the Retherford report.
E-9
TABLE E-2
HISTORICAL ENERGY AND PEAK DEMAND
Petersburg Wrangell Total
Year Enersf catacitx En erg) Catacitx Energ1 Catacitx
(MWh kW) (MWh kW) (MWh kW)
1968 12' 191 2,400 6,663 1 ,470 18,854 3,870
1969 12,434 2,600 6,620 1 ,420 19,054 4,020
1970 13,673 2,650 7' 199 1 '700 20,872 4,350
1971 16,314 2,950 8,275 2,050 24,589 5,000
1972 16' 352 3,000 8,998 2,250 25,350 5,250
1973 16,314 3,200 9,724 2,250 26,038 5,450
1974 18,735 3,500 10,205 2 '150 28,940 5,650
1975 18,373 3,250 10,753 2,600 29 '126 5,850
1976 19,200 3,440 11 ,054 2,650 30,254 6,090
1977 19,344 3,750 12,405 3,000 31,749 6,750
E-10
COSTS
Detailed construction cost estimates for Thomas Bay and Tyee Lake
are presented in Section D, Project Descriptions and Cost Estimates.
Construction of Phase I is estimated to start in 1986 with power-on-
line in 1990. Phase II would have a 2-year construction period with
second phase completion for the Thomas Bay project i• 2002 and in 1998
for Tyee. Total estimated first cost of Thomas Bay is $93 million and
Tyee Lake is $97 million.
INTEREST DURING CONSTRUCTION (IDC)
Interest charged on money expended during the construction period
is considered an additional cost of the construction phase. Simple
interest is calculated at 6-7/8 percent for each year's expenditure and
added to first cost to establish the investment cost.
AVERAGE ANNUAL COST
Expenditures and IDC made after the 1990 POL date of Phase I are
discounted to 1990. The resultant total investment cost is then trans-
formed into an average annual fixed cost by applying the appropriate
capital recovery factor associated with the 6-7/8 percent interest
rate and 100-year project life.
OPERATIONS, MAINTENANCE, AND REPLACEMENT COSTS
AN O,M&R cost of $450,000 is added to the average annual cost to
obtain a total average annual cost.
HYDROPOWER BENEFITS
Power
Annual power benefits were computed by applying the unit value of
$62.5 per kilowatt year by capacity and 50.6 mills per kilowatt hour
E-11
for energy to the usable output of the hydropower project. Benefits
were computed for each year of the 100-year economic life of the project
and were then discounted, using a 6-7/8 percent discount rate, to the
1990 POL date to determine the combined present worth. This present
worth value is then transformed to an average annual benefit by applying
the appropriate capital recovery factor. The medium load growth fore-
cast for Thomas Bay results in an annual power benefit of $7,174,000.
The corresponding figure for Tyee Lake is $6,036,000.
Justification
A summary of project costs and benefits for Tyee Lake and Thomas
Bay appears in Table E-3.
Project
Tyee Lake
Thomas Bay
TABLE E-3
Average Annual Costs
Interest &
Amortization
6,960,000
6,637,000
OM&R
450,000
450,000
Average Annual Power Benefits
Tyee Lake
Thomas Bay
$6,036,000
$7,174,000
Plan Justification
Tyee Thomas
Annual Costs 7,410,000 7,087,000
Annual Benefits 6,036,000 7,174,000
Net Benefits -1,374,000 87,000
Benefit Cost
Ratio . 81 l. 01
Total
7,410,000
7,087,000
These figures indicate that the Thomas Bay project is marginally justified.
E-12
Variations in the Load Forecast
The high growth rate load forecast would result in more rapid
utilization of power and thus, higher power benefits. In this case,
net benefits for Tyee Lake would be 61,000 with a benefit cost ratio
of 1.01. The same scenario for Thomas Bay results in net benefits of
$2,838,000 with a benefit-cost ratio of 1.40.
E-13
(/)
1-
1-
<(
~
<(
(.!)
lJJ
~
z -
>-
1-
0
<(
a..
<(
0
-
50
40
30
20
10
TYEE
MEDIUM PEAK LOAD
CAPACITY FORECAST
PHASE I 13.8 MW
REQUIRED DIESEL 1.5 MW
EXISTING DIESEL 12.38 MW
PHASE n 12.1 MW
~ O~--~r----r----r----r----~~~~~~~~~~~--~~--~----r----r----T---~----,---~~---r---4
87 ~68 89 91 92 93 94 95 97 98 99 2000 2 3 6
(/)
I-
I-
140
120
tOO
<( 80
3:
<(
(!)
(!)
z
>-60
(!)
a:
laJ z
laJ
40
20
rr,
' '-~ 0
PHASE I 111.9 GWH
DIESEL
EXISTING HYDRO
87 88 89 90 91 92 93 94
PHASE II 13.0 GWH
'----DEMAND CURVE
TYEE
MEDIUM HYDRO
ENERGY FORECAST
12.4 GWH
95 96 97 98 99 2000 2 3 4 5 6
'~ . '
60
. .) 20
:::(
1.
:::(
.)
10
0 I e
THOMAS BAY
MEDIUM PEAK LOAD
CAPACITY FORECAST
I
9!
PHASE I 18.8 MW
I
91
EXISTING DIESEL 12.38 MW
EXISTING HYDRO 1.6 MW
PHASE U 17.3 MW
·--~--~--~.~--~.----r---~~----~~----J.~
~ • 20• 2 .. 3
180
160 PHASE I 143.1 GWH
140
120
,:n
:~ DEMAND CURVE i~
i:.;:
;~ 100 t~
rc:!>
"Z
>-eo
(_!)
X:
J.l z
:'.J.I
60
THOMAS BAY
MEDIUM HYDRO
40 ENERGY FORECAST
DIESEL
20
"" I .......
'.J EXISTING HYDRO 12.38 GWH
0
"~ <>C: ""' ' .
SECTION F
ENVIRONMENTAL ASSESSMENT
EXISTING ENVIRONMENTAL SETTING
PHYSICAL SETTING
General Description
Southeast Alaska stretches nearly 600 miles along a narrow strip
of mainland averaging 120 miles wide, east of longitude 141 degrees
west from Dixon Entrance on the south along the Canada-Alaska border
to Cape Fairweather on the north. Included in the southeast region
is the Alexander Archipelago which lies directly offshore to the west.
Sixty percent of the total land area is mainland and the rest consists
of islands lying immediately offshore for a total surface area of
approximately 42,000 square miles.
Petersburg and Wrangell are located approximately one-third of the
way up the Alexander Archipelago on Mitkof and Wrangell Islands respec-
tively. The two islands are separated by 10 miles near the Stikine
River Delta, with Wrangell lying approximately 30 miles southeast of
Petersburg. See Project and Load Center, Figure F-1, for locations.
Both the Thomas Bay and Tyee Lake project sites are located on the
mainland in southeastern Alaska. Thomas Bay is located approximately
40 air miles northeast of Wrangell and Tyee Lake is 38 air miles south-
east of Wrangell. Thick stands of coastal coniferous forest occupy both
the Tyee and Thomas Bay basins from tidewater to approximately the
2,750-foot elevation. Interspersed within the basins are bogs and
poorly drained meadows where tree growth is either absent or stunted.
At higher altitudes, low, scattered shrubs and subalpine herbaceous
cover prevail along with extensive areas of barren rock faces and rock
slides.
F-1
Geology and Topography
The Tyee Lake, with a basin 14.2 sq. mi. drainage area at the pro-
posed damsite varies in elevation from 1,387 feet at the lake to 5,000
feet at the highest point in the basin. The Thomas Bay basin with a
17.3 Sq. mi. drainage area at the proposed damsite varies in elevation
from 1,514 feet at Swan Lake up to 6,300 feet at the highest point in
the basin. The topographic features in the area influence drainage,
climate, vegetation, and animal distribution as well as man 1 s occupancy
of the land. The southeast has experienced fairly recent volcanic
activity, indicated by post-glacial deposits of ash and pumice. The
mountains on the mainland form a glacier-covered upland 5,000 to
10,000 feet high. Deep steep-walled U-shaped valleys dissect the
upland, while numerous spectacular fjords afford passage far into the
Coast Range. The massive mountains are bordered by cliffs that plunge
several thousand feet to tidewater.
Bedrock is exposed or near the surface throughout most of southeast
Alaska, including the Petersburg and Wrangell area. Three northwest-
trending belts of sedimentary and metamorphic rocks have been recognized,
and igneous intrusives are widespread throughout. The dominant northwest-
trending structure pattern is accentuated by numerous linements and
faults of cretaceous-tertiary age.
Unconsolidated deposits cover most all of the lowlands in this region,
but they are thin or absent in much of the uplands. Deposits of sand,
silt, and gravel occur along the streams, however, they are generally
small.
F-2
Glaciers are responsible for many distinctive land features such
as sharp ridges between glacial troughs, extensive U-shaped valleys and
truncated adjacent valleys, scenic linear fiords, scraped and scratched
valley floors, and broad outwash plains. Much of the Petersburg area
is mantled by a thin veneer of till, which has a district impact on
drainage patterns and groundwater availability. The fine-grained com-
ponents in glacial till affects porosity and permeability of sediments.
Climate
Petersburg-Wrangell area has a maritime climate characterized by
mild winters, cool summers and year-round rainfall. The physical
barriers posed by the Coast Range and lesser ranges cause high rainfall
totals throughout southeastern Alaska. Petersburg•s annual average
precipitation is 105 inches, varying between a high of over 17 inches
in October and a low of between 4 and 5 inches in June. Snowfall is
heavy and wet but seldom accumulates to a depth greater than 30 inches.
Temperatures are strongly influenced by the proximity of the sea
as well as by geographic latitude. As a result of the sea•s moderat-
ing influence, Petersburg•s annual average temperature varies between
the warmest (July) and the coldest (January) months at 26 degrees
Fahrenheit.
Climate conditions within the lower elevation of the area are not
severe. However, in the higher elevations severe conditions with
greater quantities of precipitation and higher winds prevail.
Water and Air Quality
Because of the near pristine nature of the project area, the quality
of the water and air are high. Water and air quality have not been
F-3
degraded, since there has been only limited human activity in the
area. There has been little natural degradation of the water resources
because the lakes act as basin catchments, reducing the maximum sedi-
ment concentrations in the streams flowing from the lakes. In addition,
most of the streams in the area are not subject to much glacial influ-
ence. Principal sources of air pollution in the region are activities
of the forest products industry.
Esthetics
Scenic values abound in this largely undeveloped region. Myrias
islands, a deeply indented coastline, forests, mountains, glaciers, and
the ocean combine to form superb vistas. The study area ranks high in
all elements of esthetic quality including: vividness, visual intact-
ness, unity, and visual uniqueness. Logging operations near the two
project areas as well as along portions of the transmission route
detract somewhat from the natural beauty of the area.
BIOLOGICAL SETTING
Vegetation
Dense forest covers most of Mitkof and Wrangell Islands. However
in areas of poor drainage tall tree growth degenerates into scrub forest,
shrubs, and eventually, to muskeg. With the exception of the shore areas
along the northern portion of Wrangell and t1itkof Islands most of the
area is within the Tongass National Forest. Tall trees are generally
hemlock-Sitka spruce in mixed stands with small mixtures of western
red cedar and Alaska cedar.
F-4
In the forest areas, shrubs occurring within the timber trees
are predominantly huckleberry and blueberry, while mosses and ferns
comprise the bulk of the ground cover. The muskeg areas are generally
treeless and are covered mainly by sphagnum moss, sedges, rushes,
and low shrubs, although some isolated open stands of lodgepole pine,
hemlock or cedar do occur.
Major vegetation types do not occur in clearly defined areas but
intermingle greatly as a result of local variations in drainage and
relief. There is no true alpine vegetation on either Mitkof or
Wrangell Islands because elevations do not exceed 2,500 feet. At the
upper levels of both islands, the dense forests give way to scrubby
and shrub growth.
Wildlife
Terrestrial Species. The wildlife of any area is largely depen-
dent on the vegetation available for its survival. Each type of
vegetation supports a different type of wildlife, often on a seasonal
basis. The region has a wealth of big game animals. Brown, grizzly,
and black bears, moose and deer, typically inhabit the surrounding
area. The area also has an abundance of small fur-bearing animals,
including: otter, beaver, squirrel, mink, and ermine.
Game birds include blue grouse and three species of ptarmigan as
well as ducks and geese. Shorebirds, gulls, cormorants, herons, murrelets,
murres, and cranes are abundant in these areas. Bald eagles reside and
breed along most of the shoreline in the area. Trumpeter swans are
known to breed at Crystal Lake on Mitkof Island and frequently migrate
over the project site.
F-5
At higher elevations on the mainland alpine tundra occurs in open
terrain where barren rocks and rubble are interspersed with low plants,
cassiopes, mountain-heath, dwarf willow, avens, alpine azalea, lichens
and mosses.
There is an abundance of marine related birds within the Petersburg
Wrangell area. Two species of seater (surf and whitewinged), five
species of gulls (bonapart, black-legged kittiwake, mew, herring and
galacious-winged), the common murre and the pelagic commorant are the
most abundant species found in the area.
Marine Mammals. Harbor seals and harbor porpoise have been observed
in the area as year around residents. Stellar sealions, Dall porpoise,
humpback and killer whales are frequently observed in nearby Frederick
Sound and Sumner Strait.
Finfish and Shellfish. Five species of Pacific Salmon (chinook,
pink, coho, chum, and sockeye}, two species of anadramous trout (steel-
head and cutthroat) and one species of anadroamous char (Dolly Varden)
are found in the Petersburg-Wrangell area.
Spawning occurs from June to September with large numbers of
migrating adults passing through the area. The young return to the sea
between mid-March and early June.
The area also contains halibut, sablefish, lingcod, greenling,
several species of rockfish, several species of flatfish and noncom-
mercial roundfish.
Tyee Lake supports a population of Arctic grayling. Swan Lake at
Thomas Bay supports a healthy population of stocked rainbow trout.
F-6
Threatened or Endangered Species
The only species listed by the U.S. Fish and Wildlife Service as
threatened or endangered which may be present in the project area is
the American peregrine falcon, (falco peregrines anatum).
Several species of wildlife that are considered threatened or
endangered in the lower 48 states have substantial populations within
Alaska. Such species include the American bald eagle, wolf, and grizzly
bear.
There are no known threatened or endangered vegetative species
in this social, economic, and cultural setting.
Archeological Resources
Knowledge of the prehistoric period for southeast Alaska is quite
sketchy, although it is known that Tlingit Indians long had fish camps
in the area. While archeological potentials have not been widely
explored, potential sites are relatively abundant because of the long
record of human occupancy in the region.
ECONOMIC SETTING
Fishing and Fish Processing. Both Petersburg and Wrangell have
an economy based largely on fishing and the fish products industry.
Salmon and halibut are the principal species caught and processed.
However, crab and shrimp are also important to provide employment
throughout most of the year. Sablefish, herring, sole, and flounder
are also caught in commercial quantities.
F-7
Mineral Exploration and Development. There are no known mineral
deposits of commercial value in the immediate vicinity of Petersburg-
Wrangell. However, both communities have played a supporting role
as an outfitting point for mineral exploration along the Stikine River.
Timber Processing. Logging and wood processing give added strength
to the economies of Petersburg-Wrangell. There is one mill located
in Petersburg which saws cedar for boats, fish boxes, home buildings
and other local uses. The two mills in ~lrangell produce 40 percent
of Alaska's lumber exports.
Employment. Unlike many larger and less isolated communities,
Petersburg has a relatively simple, clearcut economic base. Histori-
cally, the basis of the city's existence has been fishing and fish
processing, although this has recently been supplemented by logging.
Economic activity in these two commodity producing industries has
served to bring money circulating within the community.
Since Wrangell's economy is somewhat less diversified and more
dependent on the logging industry, the future of which is questionable,
pending settlement of the land withdrawal issue, future employment
projection is difficult.
Transportation. Petersburg and Wrangell like all other
Southeastern Alaska cities, are extremely isolated by physical barriers.
The island location in the narrow mountainous Alaska Panhandle causes
complete reliance on marine and air transportation.
The Marine Highway Ferry System links Petersburg-Wrangell with
other Southeastern Alaska cities as well as Seattle. This system is
F-8
heavily used by out-of-state tourists, especially during the summer
months.
Both communities are served by scheduled commercial aircraft.
Present jet flights provide convenient access to all parts of Alaska
as well as to the contiguous United States.
Commodities primarily are shipped containerized via the Alaska
Ferry System or by privately owned barge companies.
Tourism
The tourist industry has become a major factor in the economy of
southeastern Alaska. Each city along the inside passage route holds
some special attraction and provides local guided tours and festivities
designed to promote tourism. The Petersburg/Wrangell area has many
local attractions such as the Stikine River and the migratory water
foul nesting areas of Dry Straits.
Most lands associated with the two hydropower projects are
located within the Tongass National Forest. At the present time, a
comprehensive land use plan is being prepared for the Tongass in
accordance with the Federal Land Policy and Management Act of 1976.
The future status of the project area lands is uncertain because of the
Alaska Native Claims Settlement Act (ANCSA). In addition, Section
17(d)(2) of ANCSA (national interest lands for wilderness designation)
may affect the proposed project although there are currently no
proposals which would include the project area.
The potential for the development of resources in the project
area, notably timber and minerals is quite high. It is expected that
F-9
any development in presently undisturbed areas will increase the
potential for additional future development of the forest and mineral
resources. This is because decision makers are ususally hesitant to
make the initial decision which will irreversibly commit undisturbed
lands. Once lands are disturbed further disturbance or development
is not usually considered as major an issue as initial development.
F-10
SECTION G
CORRESPONDENCE
FEDERAL ENERGY REGULATORY COMMISSION
RI:GIONAL OFFICE
!1!1!1 8ATT1£RY STREET, ROOM Atll
SAN P'RANCIBCD. CA 94111
Colonel George·R. Robertson
District Engineer
Alaska Q1str1ct, Corps of Engineers
P. 0. Box 7002
Anchorage, Alaska 99510
Dear Colonel Robertson:
August 9, 1978
Please refer to your letter of June 1, 1978 (NPAEN-H-HY), in which you
requested estimates of power values for Sitka and the Petersburg-
Wrangell area.
The power values are provided on the enclosed Tables 1, 2 and 3. We
believe that all of the data you require for your sensitivity analyses
studies are provided. A reasonable single power value for the combined
Wrangell-Petersburg market area may be calculated by weighting the power
values for the respective areas according to the 1977 peak demand and
energy requirements shown on the tabulation below.
Historical Power Reguirements
Wrangell Municipal light & Petersburg Municipal Power &
Power Oe~artment light Oe~artment
Year Demand EnerW Demand Energy kW MW kW MWh
1972 2 250 8 998 3 000 16 352
1973 2 250 9 724 3 000 16 314
1974 2 000 10 305 3 500 18 735
1975 2 600 10 753 3 250 17 369
1976 2 650 11 054 3 670 18 103
1977 3 000 12 732 3 750 19 344
Growth in peak demands for the period 1972-1977 were at average annual
rates of 5.9 percent and 4.6 percent respectively for the Wrangell and
Petersburg systems. We suggest that a dependable capacity study of the
proposed Takatz Creek project be made in view of the magnitude of present
loads and the indicated load growths.
_ ..
-
-2-
If we can be of further assistance, please do not hesitate to call
upon us.
Attachments (3 tables)
cc: North Pacific Div.
Corps of Engineers
Very truly yours,
~ -r-'=-:?. ~ <::::-:::--· >? ........ ~--'-' -f,-P ~. ol.-'(
Euge~ 'Neblett
Regiona.JI Engineer
Table 1
Hydroelec~ric Power Plant Power Values at Market
Wrangell, Alaska
Plant Description
Capacity
Investment Cost
Heat Rate
Service life
Fuel Cost
Annual Plant Factor
Capacity Cost
Fixed Cfiarges
(Costs as of 7/1/78)
KW
$/kW
Btu/kWh
Years
(F02) ¢/106 Btu
%
Interest or Cost of Money
Amortization (Depreciation)
Interim Replacements
Insurance
Taxes
Fixed Charges -Total
Fixed Charges -Total
Fuel Inventory
Fixed O&M
A~. & Gen. (39% Total O&M)
Annual Capacity Cost
at Bus Bar
Energy Cost
Fuel (311 ¢/106 Btu x 11,100 Btu/kWh)
Variable O&M
Total· Energy Cost
at Bus Bar
Diesel Engine-Driven
Generating Plant
1 500
320
11 100
35
311
50
Financina ·
Municipal Fe eral
- - -Percent --
7.50 6.625
0.65 0.785
0.35 0.35
0.25 0.25
1.00
9.75 8.01
- - -$/kW-yr. - - -)
31.20 25.63
2.53 2.06
6.40 6 .'\0
24.94 24.94
65.07 ' 59.03
mills/kWh
34.52
13.14
47.66
34.52
13. 14
47.66
Hydroelectric Power Plant Power Values At Market
, Wrangell, Alaska
\}1 • (Costs as of 7/1 /78)
Capacity Value
Financing
Energy
Municilal Federal Value
/kW-yr. mills/kWh
A. Cost of Thermal Plant Output
@ Generator Bus (Market)
1. Capacity 65.07 59.03
2. Energy 47.66
B. Hydro-thermal Capacity Value
Adjustment
1. Capacity (5% of A 1) 3.25 2.95
c. Value of Hydro Plant Output
@ Market
1. Capacity 68.32 61.98
2. Energy 47.66
. l
I > ~I l \ ' .,
l ·'f'\
I
"-"" v ~·
~~ ~ ; ~~
•," ~ '
d 11
Hydroelectric Power Plant Power Values at Market
Petersburg, Alaska
·Plant Description
Capacity
Investment Cost
Heat Rate
Service .Life
Fuel Cost
Annual Plant Factor
Capacity Cost
Fixed Charges
(Costs as of 7/l/78}
kW
$/kW
Btu/kWh
Years
( Fo 2 ) ¢11 o6 Btu
%
Inter·est or Cost of ~toney
Amortization (Depreciation)
Interim Replacements
Insurance
Taxes
Fixed Charges -Total
Fixed Charges -Total
Fuel Inventory
Fixed O&M
Adm. & Gen. (39t Total O&M)
Annual Capacity Cost
at Bus Bar
Energy Cost
Fuel (355 ¢/106 Btu x 11,100 Btu/kWh)
Variable O&M
Total Energy Cos~
at Bus Bar
Diesel Engine-Driven,
Generating Plant
1 500
320
11 100
35
355
35
Financing
Municipal Federal
- - -Percent - - -
7.50 6.625
0.65 0.785
0.35 0.35
0.25 0.25
1.00
9.75 8.01
31.20
2.02
4.48
17.46
55.16
39.41
13.14
52.55
· $/I<W-yr.
mills/kWh
25.63
1.64
4.48
17.46
49.21
39.41
13.14
52.55
•
'
A.
B.
c.
Hydroelectric Power Plant Power Values at Market
,1 Petersburg, Alaska
~91 1 (Costs as of 7/1/78)
Capacity Value
Financing
Municilal Federal
/kW-yr.
Cost of Thermal Plant Output
at Generator Bus (Market)
1. Capacity 55.16 49.21
2. Energy
Hydro-thermal Capacity Value
Adjustment
1. Capacity (5% of A 1) 2.76 2.46
Value of Hydro Plant Output
at Mark.et
l. Capacity 57.92 51.67
2. Energy
{cor 1
)• I
Energy
Va 1 ue,
mi 11 s7k\
52.55
52.:..
;
l
lable 3
Hydroelectric Power Plant Power Values at Market
Sitka, Alaska
Plant Description
Capacity
Investment Cost
Heat Rate
Service Life
Fuel Cost
Annual Plant Factor
· Capacity Cost
Fixed charges
(Costs as of 7/l/78)
kW
. $/kW
Btu/kWh
Years
(F0 2 ) ¢/106 Btu
%
Interest of Cost of Money
Amortization (Depreciation)
Interim Replacements
Insurance
Taxes
Fixed Charges -Total
Fixed Charges -Totai
Fuel Inventory
Fixed O&M
Adm. & Gen. (39% Total O&M)
Annual Capacity Cost
at Bus Bar
Energy Cost
Fuel (336 ¢/106 Btu x 10,000 Btu/kWh)
Var.iable O&M
Total Energy Cost
at Bus Bar
Diesel Engine-Driven
Generating Plant
2 500
360
lO 000
35
47
30
Financin~
Municipal ~ederal
Percent
7.00 6.625
0.72 0.785
0.35 0.35
0.25 0.25
0.35
8.67 8.01
$/kW-yr.
31.21 28.84
1. 31 1. 20
3.69 3.69
14.38 14.38
50.59 48.11
mills/kWh
33.60 33'. 60
12.62 12.62
46.22 46.22
'
.1, 1
I
Hydroelectric Power Plant Power Values at Market
Sitka, Alaska
(Costs as of 7/1/78)
Capacity Value
Financing
Municipal Federal
$/kW-yr.
A. Cost of Thermal Plant Output
at Generator Bus
1. Capacity 50.59 48.11
2. Energy
8. Air-break Switch at Plant
1. Total Annual Cost 0.15 0.14
c. Cost of Thermal Plant Output
at 12 kV Terminals
1. Capacity 50.74 48.25
2. Energy
D. Hydro-thermal Capacity Value
Adjustment
1. Capacity (5% of C ·1) 2.54 2. 41
E. Value of Hydro Plant Output
at Market
1. Capacity 53.28 50.66
2. Energy
lahle 3
{cont'd
,, \<
Ener:gy
Value
mi 11 s/kWh
46.22
46.22
46.22
T!lO:·ll\S DAY POIVEH co:::.JISSIO:l
TYEE LAKE HYDROELECTRIC PROJECT
NOTICE OF INTENTION
Public notice is hereby given t.'lat the Thomas Bay Power Com.'llission is
actively engaged in preparing a Federal Energy Regulatory Commission
(FERC) license application to construct the proposed project to be know1
. .:ls 'l'yee Lake Hydroelectric Project. Please direct correspondence to:
Hr. Harry Sundberg, Secretary, Thomas Bay Power Commission, Box 613,
Nrangell, Alaska 99929; copy of correspondence to: Robert i'l. Rether fo.r ,
Associates, P.O. Box 6410, Anchorage, Alaska 99502.
The proposed project would be on the Tyee Creek, in latitude 56°ll'N and
longitude 1Jl 0 3l't'i as shotvn on the U.S.G.S. quad sheet Bradfield Canal
(A-5) Alaska (in the region of the City of Hrangell). 'l'he proposed
project would affect lands of the United States, U.S. Forest Service,
Tongass National Forest. The proposed development of the Tyee Lake
Hydroelectric Project contemplates: A ten foot diameter unlined tunnel
4800 feet in length tapping Tyee Lake at elevation 1330 and the dotvn-
stre<lm portal at elevation 1300; a gate shaft and gate at the tunnel
entrance with gate controls placed above the second stage development; a
surge tank near the lower tunnel portal excavated in bedrock; a steel
penstock 7.050 feet in length from the tunnel portal to the powerhouse
varying from 7' -6" dia.'Tieter at the top to 5' -0" diameter at the trifur-
cation near the pmverhouse; a pmverhouse (probably underground) near the
mouth of Tyee Creek at tidewater containing two 7, 500 K\v impulse turbine-
generator sets; provisions for a third turbine-generator set of 15,000
J:.:I•T and the use of the tailwater for future aquaculture development.; a
115 KV tran~mission line approximately 42 miles in length ·,·lith the
alignment along the north shore of Bradfield Canal to Blake Island, over
water crossing to Blake Island and to Wrangell Island, northwesterly
along Blake Channel to Capel point, across ~'irangell Island and northerly
to a point near Ft. i<lrangell Seaplane Ramp; a substation to step down
the voltage from 115 KV to 35 ~v for transmission to Petersburg and to
the 1'/rangell distribution voltage; a 35 KV double circuit. submarine
cable from Nrangell Island to t·ioronko fski Island approxi:nately 2. 5 miles
in length, westerly across ~·roronko£ski Island to near \'ledge Pt., a
double circuit subrn\lrine cable to Vank Island approximately 2.7 miles in
length, north\,·esterly across Var.k Island to USC & CS station "t'<'l:ove", a
double circuit subrnctrine cable from V<u:k Island to i·litkof Island E!pproxi-
mately 3.1 mile!:> in length, then parallel the Nitkof highway to a substa-
tion in the Sco'" Day <1rca of Petcr!jburg. The second stage development,
circa 1995, will consist of a dam at the outlet of Tyee Lc1ke. for a
normal n:axir:mm water surface elevation of 1440; install one 15,000 Kl.·J
ir:l[Julse turbine-generator uni.t; install a step-up substation from 35 :r:.v
to 69 KV a.t the South end of Hitkoff Island. The project is expectt;cl to
prov.lde GC!1 180 :·ll·ih of primary and 34,141 t1'.~h of seconlluxy enerqy n the
first stage development and 131,280 >Mh of primary and average c~crgy
upon completion of the second stage to the Petersburg-Hrangell service
area.
Any agency, organization or person desiring to be heard is invited to
comm·;:;nt on tl1e proposed project. Th;.; Thomas Bay Power Com..'nission antici-
p<:!t<.::~.> fili.ny the Application for License in September 19'/':). Co1~.ments en
the Project should be received prior to Jun. e l)\197.9 t.o· .. be incorporu.ted
in the Application. /}J ~ i'i(")
c~t;_(!l ~1~'k 0 ~ ~ ~ ~-c.r
Harry SunBberg, Secretary~
Thomas Bay Pmver Commission
RIVERS AND HARBORS IN ALASKA
SITKA STUDY AREA
Following is a January 1979 updated cost estimate of the Takatz
Creek Project near Sitka. It is based on the design and quantities
developed by the Alaska Power Adminsitration (APA) and presented in
APA's January 1978 report.
.
Invitation No. Date I ./A of ' 24S£:::.PI97~1 I ' CONSTRUCTION COST ESTIMATE
OrawingNok
TA-11.1 79 RA'Y't PROJECT TAKATZ CREEK PROJECT OcoeE A OcoeE c Goot> ()F
SITKA, ALASKA IC CODE B ncooE o
IF$J(,ator j 1 Check~r
LOCATION ( ;-IAP/ ..... 4.!:..:A.. Zl/ ~.1'7 1:.:. C..,..
TOTAL I
QUANTITY MATERIAL LABOR FREIGHT
Unit ~ Total
Mat'l a Labor ~ Total
No. Units Unit Price Cost Clnit Hrs. Rote Cost Olf Wt -
CLEARING LANDS 2~a~c. ,
TOHERS AND FIXTURES I t).:;:>(j t!>OO
POLES AND FIXTURES /, Dr::'O a-~
OVERHEAD CONDUCTORS AND /
/, .::>oo ooo
DEVICES /
ROADS AND BRIDGES /So C>t:>D
-"
CLEARING LANDS .q/ a Oc>
STRUCTURES AND IMPROVEMENTS 2, .Y 6 :;' aoc
;
qf 47 L/-55" J; 00
S GP.! I" I~(!' ~<:::::'/ L..l r1 Ei'S (:z;:;, 1/j"O :cJ<" y) ··-1% -l?:A/71) PG.eJ
~riNC: ~~p~
. '---
.!/7:S:'O.:l~ ;:::::,.C" - -Ec.rDI 12' 8t ~.;I £ h:-
.Orr/F-2 Co::;'/ f.ro=~~ '!"'I ;~i$.
.. -. t=:ry) -.. , 9. 4191 00(: :::.:h 'jf"Jf3, _.;.)-./.r,
/2":~ FANDD B'7 v St F:t:'l:' VIS~'('"> ,_j AA.J.V ~VM )'.(, h
-·~-
#
..
-~--·-~ ~6 '-C"Jr 57-4'2/ 0 b~
-
l -
-
NPA FORM ( ) FEB. 1964 23 Rev.
CONSTRUCTION COST ESTIMATE 1---------
hwttahon No. Date I /5 f ')I
.2 "f S .E.'P F/7 o Sht. --:-__:____:
Drawino No.
f.!.P.!.!R~OJ:!.!E::..::C~T-.~T~AKA~TL!:Z.,_ . ...!>.C:£R~Elii.E.!:!:.K...JPwR~O~J!.£Et.l.:Cc!.T _____________ .........j D CODE A D CODE C
LOCATION SITKA, ALASKA IDcooE a D cooE o
, __ o_u_A_NT...,I,T_Y_-+--,---,M,-A_T_E_R_IA_L __ ~ LABOR FREIGHT
r-wt ./ T ofot
No. Units Unit ~~i~e Cost T_o.!:!.J!.!r0~~-_J_;R!!!a!!..'t!..!e-+-~C~o.!..!st __ j.!!M!!:!o.!...lt'lc...:8~:e..J& l. . .loi.Ja ib~IO!.!..Ir_t"./"iJ'---"U~nn!.!.iitt-t-_W,, t
TOTAL
DAM STRUCTURE
OUTLET WORKS
--~~-
I·--ST_R_U_C_TU_R_E_S_& __ I __ MPR __ OV~'E~ME:N~I~T~'S _____ 4-----4----4----4--------+----4----+----+--------~3~.~~/_4.~~=~=·~~---1-
WATERWAYS
WATER\~IEELS, TURBINES, &
GENERATORS
1----------------+-----+---+--+-------+---·
~ ::J8d 0~ 'l ..
1
/ !I
1
0·"""" __ _11 ....
ACCESSORY ELECTRIC EQUIPMENT r. -'i./
f-M-I S-C-E-'L_L_A_N-EO-U._S_E_Q_U_IP_I:_fE_N_T ___ -+----1-----+·-··--,'5'B 1/-:oc-" ---1-
ROADS AND BRIDGES ---+-----·-l-----+---1---------+----+-----b .:>o.B.~ r
~--=-=-::.:=--=-:..::...:._----+.-+----+----+---------+----+---+---+--~~""""+---.-l·
STATION EQUIPMENT, ELECTRIC //.?, 00,_.-.:;, ~--
······· -+-----+---t-·-·····---+-------+---t-----+----+-------1--<~L,t...: ,==~--·-T
!--S-T-RU_C_T_UR_E_S_&_IMP_R_O_V_E_H_E-NT-S--+-----t-··-·------+---·····-+------+----1-----+---+----+--7--5,-
1
-o--o-
0
-, -t--·----,-
STATION EC'UIPHENT ,-E--L-E-CT_R_I_C_+----+--+--+------t----+---+---+-----+-___::_....:::_t.._;:___........:"'-t--.. 1
{ .. B57,n""""' 1--· ---------------. ..-----+---·---+-----·· --t-----~-----~---I
·······-··---~--------·--·-··--+-·-----f---.. ·--·-t----·--·1--·-·--------+----+----~!--··-----+---··-·---+----·---·---, .. 1
---·-----·-----·-·--+-------!------+----····-·--· --------+-----+----+--···"·--·-!-----·--·-··-+-------f--I
-----~----· ------··--·---·-·--------+-----+---·--· ~-·--+------+----+----.!-----+-----+--------------1
1------------·-------·-·----c-·· ·--+--------·-··1------lf----+---+----+-----f----------··--------.......... 1
... --~----~----.~~--~-----~--~----~-------!~-_·-··_·--·----~r---_-+-_---------..J~----~-.__-----+--,==---=--~~-
. · .. : FO · ··•· 23 ( Hev) FfA 1964 ·
' . I lnvltat1on No. Data I I: Sht. L_ of l CONSTRUCTION COST ESTIMA'TE 2 2-51:?? 1'1 lb
Takatz Creek Project OrawinQ No.
PROJECT OcooE A OcooE c
Alaska fC CODE ncooE
I EStimator tt~ecker
LOCATION Sitka, 8 D ~ / ·-, -' _, ,. I
·-~l-::1 : '" '•
QUANTITY MATERIAL LABOR TOTAL FREIGHT
Unit ~ Total ~ Tot
DAM STRUCTURES No. Units Unit Price Cost t Hrs. Rate Cost Mat't a l obor nit w
Care of creek during construe
-~-
tion & unwatering foundations LS loo.:?ooe
Excavation, 21,500 CY
/
common iO -:Z/~~
Excavation, rock 11 000 CY ?o -.38".::!~
Mob & demob for grouting LS /5 00~ -·----
Drilling grout holes 12,600 LF 20 -?52. a~~
Metal pipe and fittings for
-
foundation groutin~ 3 200 LB 3~ /2/oe>a
··~
Hookups to foundation erout '-
holes 230 EA ,-;5-I~CJ'5d
Pressure grouting foundations 12_Ji00 SKS ..., ... -..;.t> .1_10: C)r:JQ
.l!g_tal tubing and fit tines for
eroutinl! contraC'.tion ioints 3 BOO LB 5-let oc.>a
Hookups to contraction ioint ·-
grouting systems 40 EA 195~ 5L/od
/
Pressure grouting contraction
joints and temperature contra.
I ---
systems 250 SKS $5-B75o
Cement 32,500 BBL 2o-6:54,o"o
Reinforcement bars 61,000 LB ._,65 3~0:Jo ·--
ConcrPtP in dams 29 000 CY jr;;':!J:"
----~---· ',_; 5366,~
/
NPA FORM ( ) FEB. 1964 23 Rev.
lnYIIat•on No.
CONSTRUCTION COST ESTIMATE
PROJECT Takatz Creek Proiect OcooE A
LOCATION Sitka, Alaska II CODE B
QUANTITY MATERIAL
Unit % DAN STRUCTURES (cont.) No. Units Unit Price Cost I
Concrete in dam parapets and
curbs 130 CY 475
He tal tubing and fittings for I
temperature control systems 7,800 LF I !_J":./J
-:'~
TPrnnPrRturF> rnnlrnl nf <'nn
c_rete 0 000 CY .!.f 5o
Thermocouple wiring 3,000 LF 6 -
He tal seals -4,200 LF jLj--
Netal grout groove COVF>rS 200 LF g-
'
Instrumentation of dams
(collimation) LS
Pipe handrails 2,000 LB -:£~
--r-
S 1ht-nt-,:,l --
Contingencies (20%+)
-..
Total ------------f-----
.. ->--·
---------------~------------------.... ·--·--------. -----~--
-----~--
-----·--·-----·-~ ----
!-----· --f-·-
i _l _ '--,~. -· _L
' ,-,-----_._ -----
Date I Sht Z-of
DrawinC) No.
OcooE c
ncoDE
[tsllmotor ~~h~~;e~ (
D .t:
LABOR
TOTAL FREt
Total
Hrs. Rate Cost Mot't 8 Labor % Unit
GHl
ra
~
----r
S~75o l ']
_...,_
/0 0 ... "":·~
I i J./5", 000
}9, -1 /) 0 0
r
58 80 0 -,
I I co DO ,---I
I
35.ooo =t= I
47 ()()0 l
-I-I
Q 5 3C) "'~ I .)
1 D 1 q'J<
I --I
' ~ I) '].'f 7 _, r-I
I 0 ~l.\1.-, ~:~
--j
I I _ _,__ --~~·----.
---------l--1
·---~--r--------------------t· .. --------------r-I ----T I ---,f I ,-----1
------'----
' .
I Invitation No. Date :::t
COST ESTIMATE· jSht....;.:;:_ of_
CONSTRUCTION I
Orawim~a No.
PROJECT Takatz Creek Project OcooE A OcooE c
I CODE DcooE
,E$Ilmotor tc~ecll!,--~~--,-
LOCATION Sitka, Alaska 8 D 7 ~f:t? 1 :a '_.)
QUANTITY MATERIAL LABOR TOTAL FREIGHT
Unit ~ Total ~ Tot'
OUTLET \~ORKS No. Units Unit Price Cost I Hrs. Rate Cost Mot'l 6 labor Jnit W•
Excavation, common, for ---
channel 2 ,20( CY ~-IS" U.OO
Cement 32' BBL ::::o -I::; s;o o
",...
Reinforcement bars SO. DOC LB jO">
f -
.:.? '? \OD
-~---
Concrete in trash rack struct. 7( CY --2-.s-000 :::'c.:Jt.::l
_(:gn~rete in gatehouse super-
structure 4C CY --oo,.!) ::.o ·) ·) l)
"'~
Concrete in e:atehouse !=:uh-
structure 14( CY -~~-L\'2. 00 0 -Concrete in blackouts 1C CY .(,~ 6 0 0 (')
High pressure gates and hoist --
4 by 4 feet, 4 each 100,00( LB ...... .::;-::> lc::;o_ IJt)Q ----~
Conduit liners, 4 bv 4 feet,
2 each 34,00( LB 3~ I \ () '5" ,')f)
{
Controls for high pressure
gates 1,02 LB .B -8 I 1.~ :)
~Jkhead gate seat & guides 6 so LB 3-IC\ 5-":lO
Bulkhead gate slot closure 6 ,00{ LB 4-~L.f 000
Access stairwav 20 50 LB :j-:_:) \ s--:n
Electrical system, including ,___ -
heaters LS 25CJ!}t-'
I
·--
l.o56 ·o~ao
NPA FORM ( ) FEB. 1964 2 3 Rev.
lnv•tot1on No.
CONSTRUCTION COST ESTIMATE
PROJECT Takatz Creek Project DcooE A
LOCATION Sitka, Alaska !r CODE 8
QUANTITY MATERIAL
Unit ~ OUTLET \.JORKS (rrmr ) No. Units Unit Price Cost I
s •• hr()t-.::11
Contingencies (20%+)
Total -----
---1--·--1--
--
--f--
1------
----c---·--------1---
f---
-· ----------------·----1-------------+--
---------------·······---------------·------------1-·
-~ -.__ -'-......__ I ----------~PA IM il FEB. 11f64 2~ l l'iev.)
Date
OrowinC) No.
OcooE c
ncoDE
IEstlmotor
D
LABOR
Total
Hrs. Rate Cost
I '":): ~ 01~!)
I -::2., \ 2-1 z
l-3l ZTZ...
'
---
1--
Mot'l
TOTAL
8 Labor
I L' Sht._f __ o
~~n:ec~ei ___
2. --..,r;e
FREI
~--WI
Unit
GHT
To!
w_
l
~---1 . -l
7·~1 (~;'.')·'
--~~ -----.... , .... -.
l _l ___ ., ,--I ,---------r·· I
I I
---~-~~-
1 l
F l -~---I
:~r I --. ------1
I --I
-I ·---------------T---I -+---1
·----------,
. -tT _______ l
I -----L__ ----
' lnvttotfon No. ;~ ;
Dote .
pnt.Lof ___ ' CONSTRUCTION COST ESTIMATE
OrawinQ No.
Creek Proiect PROJECT Takatz OcooE A D CODE c
•1 CODE B rlcooE o
1 Estlmator ~c~~ck_er
LOCATION Sitka Alaska z_ s E: ,, -: '' ' )
QUANTITY MAT ERIAL LABOR TOTAL FREIGHT
Unit ~ Total ~ ·rotc
STRUCTURES AND IMPROVEMENTS No. Units Unit Price Cost t Hrs. Rate Cost Mot't a Labar t Wt
Excavation common (includes
talus) 14 250 CY q-lz.B '2<;"0
3n -; gg Excavation, rock 6.600 CY ') Q ()
I
Compacted backfill 3,400 CY /6-S'l no o ,., -)
Concrete, first stage 2.800 CY :~1:3 &:f_n ·:100
j -
4,200 26 -Cement BBL Bw ODr:
Reinforcement bars ! 10,000 LB CJ6§ ?_(c,(-" <::::)D
Structural Steel 30,000 LB /.::::-~ ._.._ -·4-D -. "":> 0.')1
···-
Miscellaneous metalwork 15,000 LB .i~ --4 ;:;;;-' 00 f)
I
Metal decking, 2-inch insula-
tion and rubber roof 6,540 SF ;q-Rs () 'D
I
Insulated metal wall panels 10,600 SF /o -i0bl)')')
Niscellaneous building items LS LS 35c"Jt"'Jdo
-' /5.o_Od(:) Heating and ventilation -LS LS ,
Embedded o:ininR' 8 oon T.R . Lf.-3;J. ODD
+~ l
Exposed piping 6,000 LB 2..l i)t}f)
4~ ·'
Motor-driven water pumps 4,000 LB \ ~..., 000
I
Fire pn •teet ion system for oi
rooms 1,200 LB 6-l ?.oo
Subtotal ~.::: l~o CJsol --
Contingencies (25%+) I
~:82 l ~g
Total 3 'i 1 ~ G88 3. lf-I..Lf... ikhs --
--~-· --·-
NPA FORM ( ) FEB. 1964 23 Rev.
CONSTRUCTION COST ESTIMATE
PROJECT Takatz Creek Proj._e.c..t_
LOCATION Sitka, Alaska
QUANTITY MATERIAL
Unit WATER\.JAYS No. Units Unit Price Cost
Excavation_, common in o..E_en
cut for in ta!<e structure and
penstock anchors and piers 11, 50( CY /o -·--
_Excavation, all da~ses. .in
open cut for intake structure
atehouse 2 Eenstock anchors -and piers and surge tank 2 80( CY ::;a
Excavation all classes for-
_gate shaft and house, and
surge tank 2,50( CY 1-..z-I I '
]:xcayation, all classes, for
:un~~l 10 2 40( CY /1}-
Structural ilteeJ tunnel ilU[!-
po ·ts 95) 00( LB 16o
I -----~-"---
Drilling grout holes 2J70j LF ~---
Pipe and fitting for founda-
tion grout holes l' 50( LB ~) ;:,
l -1-----,_c __
r--~ _:.......,.;.. ---
Hoolzups 9( EA __ r::' ,--
!--··"::>?
Pre~~1Jre grouting 2 '70( CF ...., .;:; -·-.. ~~' -----------1----
Cement ___ ___2_!_80( r___})B!:__ .:_?-1--····---------·-·
rJ.:l.S _Rei_!.lf9rc;ement ba_r_;:;_ I_iO, O_QJ 1~!? : -.... !------·----------
-·
jf.·--·---.JPA .... ,ijM23(R' I FEB 1964 ev.,
-_j_ -_j_ -'--
tnvllahon No.
OcooE A OcooE c
lC CODE B _OcoeE D
LABOR
~ Total
Hrs. Rate t
-
I
«
-----t---
..... __ f--
..
-·---------~
-----
Date . I Sht_1_ot
Drawino No.
! Estimator t~.-reckif·
7-Z ~
TOTAL FREI
Cost Mat'l 8 Labor ~ Unit
GHf
To
.Y!
\IS 0•!0 ------
\ -+ () 000
--l -T
-1
1-j ~~ ") ()() T -~--· I ']
--
lL,~ ]·;·; .,
i""" :::')') I --t ,_
I ~:..+ ')n;)
-I e::: .? -:::.o
I -5~ ~ .;; ----' __ -~1 _, -: :::: )0 ---
; ,_:) "'),. ',-. .. ---·----~ ---I j
'--' 9 I f) f)'i) ---r
f' I
--~--'-----
"\ ID
I i ' ) Invitation No. Date ) 7
CONSTRUCTION COST ESTIMATE
ht. __ ot __
I
1 I
Drawing No.
Takatz r.reek Pro1ect PROJECT DcooE A OcooE c
II CODE ncooE
IEshmotor tChecker
LOCATION Sitka, Alaska B D Z-?. -<~P -.~ C;.
QUANTITY MATERIAL LABOR TOTAL FREIGHT
WATERHAYS (cont.)
Unit ~ Total ~ Total
No. Units Unit Price Cost I Hrs. Rate Cost Mot'l 8 Labor Unit. Wt
Concrete in inro'!kP f':trnrtnrP ·-···· ·.-......_
and gatehouse ~¥. ..::::-.-:")~I) ·-~·.:;j,;:l ·,.,':::;> . -
Concrete in gate shaft and
surge tank 1,100 CY -----.~: -::-; ..._,{) ·'" ., )"'" .
ConcrPtP in nPnc::t-nrk Anrhors
·~-
and oiers 1.750 CY Ll-ac:j-. ;· ')) ) '":'·")
--
Concrete in tunnel lining 3,500 CY ~-c.;) ·. 4Q) )")')
) ;
Concrete in blackouts 15 CY /" -br"YJ .;;j )("))
Trashracks 16,200 LB ;75 ·,..5:::-)
Catehouse metalwork 3 200 LB ;)56 \ I 2.0:-J ._.,
J
Roller mounted gate 6 X 8.
foot, 1 each 24,000 LB .,2.5 ::::-r !") r;·"' --..
'
Frames and guides for roller-
mounted 8,500 LB
,....._
gate -... ~ .~ ~):) ._j -'
_Hoist for roller: rno.u.n..ted_gate .24 000 LB 3-l' ;J:) :?
Control svstem 4 000 LB 9-:-=. -;._ ') ) :)
__ Penstock and wve branch dia-
BOO,OOO 2 -meter 66 inches LB l.!..:,. •) ;') /) :::v
Bulkhead gate, 6 X 8 foot,
1 each 14,500 LB j'72 2-') ~lD r-
Frames and guides for bulk-
head gate 6 000 LB /~ I 0 ~ :JO
NPA FORM ( ) FEB. 1964 23 Rev.
IOYIIOtiOO No.
CONSTRUCTION COST ESTIMATE
PROJECT Takatz Creek Project OcooE A
LOCATION Sitka, Alaska CcooE B
QUANTITY MAT ERIAL
Unit %. \.JATERHAYS (cont.) No. Units Unit Price Cost I
Electrical svstem for remote
operation LS LS
Subtotal
Contingencies (20%+)
Total --·
---
--·
--
·-
f--· ------~---c--
·--
----·---·-~ -------------
#
·-~-· -----~------·-· ;,, -------·'---·-·
OcooE c
DcooE D
LABOR
Total
Hrs. Rate
-------
Date . I Sht_i_ of.
OrawinQ No.
Estimator [c;'~cker z -;f,'-/
"") ·.A
TOTAL FREIG
Cost Mat'l 8Lobor ~ Unit
HT
Tote
W!
T -
L/6.ooa
01 3'2.. ') .g•....;.0
J
\ ?Jr.,:.. I~"'~
\\ \ ss-Qr;,.'3 \\,\.85,::.\0..:l
' l .--~· r --I
r------I
1 -r -r
1 ·---l -I -·----
f -------·· I --'---··· -r
l
'i r
t I j ' bate ~ lnvnatu:m No. . q f
I CONSTRUCTION COST ESTIMATE
1ht._o __
1
Drawing No.
PROJECT Takatz Creek Proiect OcooE A OcooE c
tt:.stlmotor :hi!!,.,kAr
LOCATION Sitka, Alaska lr CODE B O~ODE 0 I zz <:,"EI' .... ::;. c
QUANTITY MATERIAL LABOR TOTAL FREIGHT
WATERt.JHEELS, TURBINES AND Unit ~ Total ~ ·rOtC'
GENERATORS No. Units Unit Price Cost mt Hrs. Rate -~~-Q_st Motl a Labor t Wt
Cement 1.200 BBL /') -~ 2-t+ ()()r)
'
Reinforcement bars 90 000 LB ()t:>G -3 -~
-~-...... ---'); ') .. )Q
Concrete, second stage 800 CY ::::.",::):;) --:z_ Lj 0 ')I")'}
I
Vertical impulse turbine, 4
~·,..--
iets, 14 000 hp at 886 ft. ·---
head, 400 rpm, 164 c.fs, 2 ea. 60,000 LB .-,5;;::>
-!-9 lt'J ~-'oo
Governors for turbines, 2 ea. 24,000 LB LjG:::~ I f).C5 1 0<)
I ---
Embedded pipe 8,000 LB L/-3 2 {)f){) ---'
Expo!:jed pipe 6,000 LB Lj-!:e> 2l ".YOr'J .
Hot or driven water pumps 3,000 LB L).-l?-ooo
Generators, synchronous, ver-
tical, 3-phase, 10,000-kw,
---
0.9 pf, 6,900-volt, 400 rpm,
2 each LS LS -? 000 0~/)
/ /
Carbon dioxide svstem for
1,200 /""'"' -(r; generators LB -::::::> 1)00 -----~--·-
Subtotal : '-\ \ l soo
~-
Contingencies (15%+ ") l z lo20
Total ~~'1~0 121: .~ -~-.(j '"') ·' ~ -:•{ --: ~ ./'"" ~ -J
/ ·-· .!::..:: .. ~:.:."
NPA FORM ( ) FEB. 1964 23 Rev.
lnvttotlon No. Date
of
CONSTRUCTION COST ESTIMATE _t~~ -~0
PROJECT Takatz Creek Proiect
LOCAT!ON Sitka, Alaska ---
QUANTITY
ACCESSORY ELECTRIC..U. EQUIP. No. Units Unit
Switchgear for generators
6.9-kv, with 1.200 amp, 250
mva breakers, surge protectiv
equipment and potential trans
formers, 2 each LS LS
.G.ene.r.atQL_exci tation ruhi cl P~ •
2 each LS LS
Rl11'l <:rrurtnre non -.::egregater!
3-phase, 15 kv, 1,200A 100 LF ...
NP11rr.::~l o-rnnnrli no .,.,, 1 i r.mont-
(10-kva, 6900/120/240-volt -
distribution transformer and ---~~--
7-kw, 3-ohm resistor) 2 sets LS LS
. -·---~-
Hain control and graphic ·---
boards, in-line, dual--type -·----
(8 panels) LS LS
----~
Unit gage boards (generator &
---
hvdraulic panels) 2 each LS t--..1.L ·----
Station-service unit sub (two
··-~·
300 kva, 6600-480 volt trans-
--------~ ""
formers, two 6600-_volt discon f---.... i· .... --~
ne.c t· S!,r i t..ch--,.;omp~n.t.s..,..-.----.... __ ----
. ·~-·-· --·r--~ ~ ~--·""'-----~ -
OcooE A DcooE c
L CODE B OcooE 0
MATERIAL LABOR
Unit ~~ Total
Price Cost t Hrs. Rote
-
-
--~~-~ ..
----·------~ -..
--------
1----------·--·-----·--·-
------
Orawin'i) No.
[Estlmotor
Cost
&a~~CJ
7
.5'~ ' 0·) L)
·'
5'o.o~.:)
7
u.;. / -/ () ::J '-
2v...J ,}·J
-
2~Q?'Q
TOTAL
Mat'! 8 Lobor
rheEkei _
~-.: ::.:::
FRE
Wt ~
IGHT
Tot!
----------l
Ul)it l""
I
-i
----=i
-r
f ~---I ...
··--··
T ·-.
I
·-L
-··----
--·-~
--------
1
l
I
\
1
I
I
l
I
I
I
l
I
.... ···-1---c• . ~·--------------1---·----.. -1--[ I
l
I
·--·--·· ... c .. ------· J-~ ·--.. ·-~-----··-
'~ -'-----I ~--'
_r
I I l ~-l \ :. I E
\ lnvetat•on No. Dote . ' ' _( Snt. ..:..:.__ of_ CONSTRUCTION COST ESTIMATE
Takatz Creek Project
OrawinCJ No.
PROJECT OcooE A DcooE c
IC CODE
1 t.sflmolor t~ecKer Sitka, Alaska llcooE -.. .... -LOCATION 8 D .__ ;;._ _ _)Ff-., I
QUANTITY MATERIAL LABOR TOTAL FREIGHT
Unit ~ Total ~ Tot
ACCESSORY ELECT. EQUIP. (cont No. Units Unit Price Cost t Hrs. Rote Cost Mafl S Lobor Jnit w -·
. -··-··--,..--
460-volt switchgear section ·-
with 2 main and 10 feeder .. ______
breakers LS LS .9;!,::? ·? D ..
/
--=-..... ' -----
Lighting transformer 75 kva,
480-120/208 volt, dry type,
with ±10% voltage regulator, . ----·· .. -
1 each LS LS /C! (?c' 4 ~-·--····
Panelboards, 600-volt, a-c I ---· ·-· ·--
power distribution 8 each I.S LS -.;~. <'10 ,,
Grounding svstem, copper 6 000 LB /5-_Z:;i/6~6 ·-,._...,....._ ___ , .. ·····-
Battery_ chargers 1 two 25 amp -
and panelboard LS LS I q """" I'J -'/ ·--
Station battery 125 volt ----~ ~
200 ampere hour LS LS /S:e>c)6
Conduit, nonmetallic, 3-inch 100 LF I{-/66cJ L. .
Cable No. 4 AWG, 7,500 volt '·-
shielded rubber 20Q LF .~-12e>o
"' ' ' ----'
Conduit system, rigid metalli LS LS :J-s,~j
---·~-
'' --
Station-service and control
cable LS LS
CO'> Test cabinet, 1 each LS LS .<o r.:>co f--·--.' . ---~-
rfic]d test eq ,;,...monl-1 C!OI-T.S T S 6ooo
~ ,. -·-
NPA FORM ( ) FEB. 1964 23 Rev.
CONSTRUCTION COST ESTIMATE
-----
PROJECT Takatz Creek Proiect
LOCATION Sitka, Alaska --.--------------
QUANTITY MATERIAL
(cont.) Unit ELECTRICAL EQUIP~fDT No. Units Uni! ___ Price Cost
Supervisorv control equip. , ·--f---
for controlled &
lnvttotton No. I ~ote
0 C;DE A 0 COD~ ;-r;"· NO ~
st motor
lc CQDL!l __ O <:9J)J:_I) ~-~---~··
TOTAL
LABOR -Total
Cost Mot't 8 Labor Rate
I
I
'7 Sht. __:_;;;;_ of
Checker
I FREIGHT
IWt ./"1 Tot(
Vi)nit I W1 5u:.: I Hrs. ·---:I~~=--~ ----l-··-I
I I ---·
'·~·-. ~ ~ ~-' I
-relay type,
~--·.,--··· J. ~:G . I I controlling ends LS LS ~7q,ctJ:d .. ~-
Power line carrier equip. for
-·-~ ~ ··-·
c;ontro]led and controlling --·-----"-
.. ends LS LS 32096..
/
1--------'-·
Subtotal
--~-"'-'~-
(1 ~":> 8 0 0 :-· ~-·-·-
Contingencies (20% +-) 1 ss-li.o 0
Total II 1 1 o. 9ioo l ill ')::') .
I I
I I
I I
I I
I I
J -I
~1 I ---.-----I I -----·-·
--------~ --__ ... ~
~"---·--
--··-
I I
I I -----·--... ------
-·--·--------------~------··--·-~---------·-· --···
---·-·--·· --~--·-
~~---· -·-------~ -· ----~ ------·-------~--------------··
' ------·--·-·-----·-·-----------·-·
-··~ --·-----·---··~· .. ----·-
--------------f------····--··----f--· "-----
I I
~ I
I I
-1 I
f---··· --·~ ·---~----·--1-----------~-----· --,--·--·~·---· ---j I
..
--
-.
I t'
--.,---.--_..._ -'--_c_ ----,_--·· --·1 __ I
1 I I lnv1lahon No. i I;-Date .
CONSTRUCTION COST ESTIMATE-·i Sht. ___;;;;:_of_
OrawinQ No.
PROJECT Takat7. Creek Proiect OcooE A OcooE c
Sitka, Alaska I CODE ClcooE
iEstlmotor ~CfH!Cke;-.
LOCATION B D 72 '--:.~('--"' ~-
QUANTITY MATERIAL LABOR TOTAL FREIGHT
MISC. EQUIPMENT Unit ~ Total ~ To!
No. Units Unit Price Cost I Hrs. Rate Cost ,ot'l S Labor t w
Crane, so ton 71.00( LB 25_:: 177 Oo~
/
"tolono rail hoist, 3 ton
--~~-,. --
(machine shop) 1,00( LB ·3-3d 6c.'
Outdoor monorail hoist, 3 ton 1.40( LB -..-.-r .tf2~ c_")
7 ,ooc J 75" ' -r--
Lathe, 20 by 96 inch LB 2.L ?<;o ---
Upright drill press, 21 inch 3,00( LB 3~ H z_ c;-0
---·--
Universal shaper, 24-inch 9,60( LB ~ 7..r:" . .... ~ (_, 00 I)
::;.75 I ---
Power hacksaw, 6 X 6 inch 1,10( LB ..... -4 1"'2-0
Pedestal grinder, 12 X 2 inch 50( LB -:; 7.5 !9,1S ,; -
Pedestal arbor press, 5 ton 75( LB ~3-::? 2'3 I ""2__ -
Portable pi:pe and bolt thread·
ing machine, 1/4 to 2 inch 60( LB 37§ z_-z...s-o -------. ~---
Air compressors and motors 5 00( -LB -o_, 21 t)()t:) -;7§ ·;----
Air receivers and P!Ping sys. 2' ooc LB ?1. '"'\ :)') ----
Fire extinguishing equipment 1,20( LB o-s..:: ----G 000 --
Oil purifier 4,00( LB ..c::--2.0 ')'""1 ·) .......
·---
Subtotal 2:.\11 Be; n
Contingencies (20%+) ;_,3 ~10
Total 38~ 8-z-c . :::' ~ .f.t_ ":.< " i--I -----~ --
---
NPA FORM ( } FEB-1964 23 Rev.
CONSTRUCTION COST ESTIMATE
r---------------------------~--------"--~--t---~~"----------------+.::;D'::":·,a::-:-:w:-':in=o•No. ---
lnvtloltan No. Date
\ Sht !'-/ nf
._P ___ R-'-O·J"'"E"-c-'--r _____ T_ak::..:..a;;.;,_t""'z;;.._.;:C:..::r:..;:;ec::e..:.:k_.;;;..P:::..ro:::.....L..CL. e:::..c:::..t:::..----------------1 D CODE A 0 CODE c
I -0 rrsnmc_cif-or_-~--~ fCnecker Sitka, Alaska iC CODE B n CODE __L __ 2-z_. <)FfY __., ,:
MAT E-R-1 A-L--Ll-!-==-=~~-'---'--LA"'-B><-'0"'-'R~ t()TA L -r-FRE IG H~ LOCATION
QUANTITY
Mot'l 81,.g~Qr ~~~ T~ ---r-1
Unit Hrs / Total ~R:::;OAD::::::.:S::._:A_::N_:::D::...._::B:.:.:R:.:::I_:::D::.::.GE_:::' S:::__ _____ .j.!N.!eo~. ::::U:.:.:ni_:_:t s4~U::_:_n:_!_i t----1f-!-P~ri:;:_:ce4 __ __:::C.:::.o':..:'--to:::;._/"1J___:::.h:.:.:.nn-'-'-111lt Hr s. Rote Cost
Clearing road\·laV I I
Excavation, all classes
-I
----+-~--+---r~--t
CHP, 60-inch, 12-gage ::r-----1 I '"'i"': ol
:p ~:~p~::~::: , 12 gage ·-+-------+--+-:.:__:::_;:;:_f----------------t· ----__ -__ '= _ +~~-·--~-,~-:_+,-_ .• _-__
Reinforced concrete bridge, ____ _
1
_2_o_x __ 2_2_0_f_o_o_t ________ --t_4_,_4_oo--+-_s_F___ //~-'-1.-3: /d.
Reinforced concrete bridge, --"--+-----+---+-------------+-------+----l-----t-----t---····-
_2 __ 0_X_l_O_O_f_o_o_t____ _ ____ .. __ 2_::.__, 000 __ __?E __ __/j___o -~ ~---~---+-----+------+---_____ 1 _-=....,--_-::_o=---·~--~-·-· ·-·-~.-r c;,1____ __
Guide posts 400 EA .:?5-1'-\.o ,-, I r------~-------------------+------t---~-'~4----------4-----+------·~ 1
Crushed rock surfacing 1 \0 ') )~') t---------------'"'-----+----"---~1-----t---'---=::::_-+-----t---· r-----1-----,-
Y?_c_k_,_30_X_2_5_0 ___ f __ o_o _t ------+---+------------t-------+r--75o, ~).£.:::~ ----I
I
I
I
I
I
I
I
I
I
I
I
I :=s;,e=!.a=~-P•=l-=an:t'e=~f:l~o_a~~·============:=~~~~~~--~~::::~-~--------~-~---_~_-··-------P~~~~~--~
Subtotal -1 ;>~
-~::: ~n ge--i-e--s-_Q-01%-+·: )---t-----t--------+~---~-------+-t----_ -_ -----~-~+---===:=--~==:-_____ =·-· ----1 ... f-~-.-~ ..... ~:--<~'-':...,., 1=~.;,.e~...;;.r;+------~-····-~O .Y .,!, " I
i --~---,.--1-======--f·---=~-:-.----=====::===--:=~-~-~~:_--.,....-_-........ ·=-'-,....· __ ' __ ..,._.._ __ /--.,------_·_ _[_ J ~~~-~~~~ ~-'\~ev.i , --c..-
' ' J ; ' i
lnvllot1oo No. Data !. --
CONSTRUCTION COST ESTIMATE--' ,, Sht. /";---~~=
Orawinljl No.
PROJECT Takatz Creek Project OcooE A DcooE c
Sitka, Alaska L CODE B ncoOE
Estlmotor ~~n~cller
LOCATION 0 -:' '"~ ~J~. --·"'-..
I STATION
. TOTAL QUANTITY MATERIAL LABOR FREIGHT
Unit ~ Total ~ Tor
EQUIPMENT, ELECTRIC No. Units Unit Price Cost I Hrs. Rate Cost Mot't a L obor Unit w
"Prrwo:>r transfonner 3-ohase
12,800-kva, 115 grd., Y/66.4-
6.6-kv, 2 each LS LS . -q g ~~r:~l:'~>_t:J
/ --·--
Switching bav 115-kv, with
two horn-gap disconnect
C~----
switches and one 2-pole auto-
--
rnatic high-speed grounding
switch LS LS 235..C>:Z2 -
Transformer oil and fire pro-·--
tection piping systems 10,000 LB 5--::;a, ..odD
Subtotal C:> 7 o. DI'>O
Contingencies (15%+) Cj~ ()00 .,
Total 11.2, ono .. ,_ ..
I
---··-
"'"""'~~~~
~
··--~-
NPA FORM ( ) FEB. 1964 23 Rev.
lnvttotton No.
CONSTRUCTION COST ESTIMATE -
PROJECT Takatz Creek ---Project DcooE A
LOCATION Sitka, Alaska lC CODE 8
QUANTITY MATERIAL
SUBSTATION-20,000 kv Unit ~ STRUCTURES A:.'ID INPROVRN'RNTS No_ Units Unit Price Cost I
Grad tg' fencing, lighting,
rf!Ud snrfacino LS LS
Contingencies (25%+)
Total
----·-
--
!-·---
----·----~-
~----------------
------I----·-----~
--------------
---·--·----------c·-
··-"----------~ ---
----···-----
--·· ----------
"~--~--~-~------~---------------
~----------""' r--''' '
,,, __
~-----·--.. ----------
---~-------------~--r-'---
-
OcoeE
DcooE
LABOR
Total
Hrs. Rate
-----------
Date
OrawinQ No.
c 1 Estlmator
0
Cost Mot'l
\ Sht. 10 of
---fcne~er
7 ~ ~ Fi:'-:' ...,.., """"' ' ' • .J
TOTAL
a l obor
FREIG
~ Unit r-~-
Hf
To·
~
-I
~~bOO ·-----
-------~-
~-----r
,_, __ I
15 (')1)0 l ----, IS f) I) f)
! I -_.,.. _ _...-.
---I --I ··---' I -----+ I -~-·-··· I
-J I --1-------------
1 I ----I -------· T I
I I ·--------c-----I ---r I
' '' I I ------------I -------····------------·---· ----------------------!·~----l ±-~= I '---· --"-~-
·~ r
·--------~ .. .:_'-----'---I --o,-
. k [ ' I ! ' • i
I lnvtlatton No. Date .
COST ESTIMATE ' fSht. r7 ot __
CONSTRUCTION ,,
1
Drawing No. ,.~. ----
PROJECT Takatz Creek Proiect OcoDE A DcooE c
Sitka, Alaska !L CODE llcoDE
1 Estlmotor tCheck~r
/
..
LOCATION B D 2 7 ~~ ..,
~ :_..
QUANTITY MATERIAL LABOR . TOTAL FREIGHT
Unit ~ Total ~ Toto
STATION EQUIP~lliNT, ELECTRICAL No. Units Unit Price Cost I Hrs. Rote Cost Mot I 8 Labor Unit Wt
Power transformer, 3-phase,
11,000 kva 110-12.5 grd. --
Y7.2-kv, 2 each LS LS 3j5~----/)
I J-= Swit;~hin2: bav 115-kv with
two horn-gap disconnect
switches and one 2-pole auto-
rna tic high. speed grounding
switch LS LS 2q5ooo
Switching bay, 12.5-kv with
two horn-gap disconnect
switches LS LS ,,..
?,-, O:::J<)
/
Line bay, 12.5-kv, with 500
mva OCB LS LS /lo tJDQ
Subtotal lU-s-D00
'
Contingencies (15%+) \ \ I lSC)
Total s-, ':::> ._-, Is;;) ~~~ --~, (,C)( ) ("'I
I
--~-~--. ---
··--~-·-
-
NPA FORM ( ) FEB. 1964 23 Rev.
CONSTRUCTION COST ESTIMATE
PROJECT Takatz Creek Project
LOCATION Sitka, Alaska
2 miles of steel
..
75-f towers, QUANTITY phase spacing, 170-ft to line Unit attachment, & 26 miles of woo !Wo. Units Unit Price
pole H:.frame, no OGW
CLEARING LANDS LS LS -
TO\.JERS AND FIXTURES--2 MILES LS LS -
POLES AND FIXTURES--26 MILES LS LS
. -~-
OVERHEAD CONDUCTORS AND DE-
VICES--28 MILES LS LS
--~---------,~--
ROADS AND BRIDGES LS LS
-~--------~
1-...
-
lnv•lat 1on No. Date
Orawim,J No.
OcooE A OcooE c
rEshmotor
IC CODE 8 OcooE 0
MATERIAL LABOR
% Total
Cost Hrs. Rote Cost Mot'l '
-1 aa~ .:jcv
!oCJa ~GV
/
I/ Ol?"' CJ6 p
[7 _j __
I. 0 ""'' ""' c b . _____ .,.__ ...
----
75o ~f!II!J ··-/
f· 15 ..... , s-0 {)(', /'
·-· I l
TOTAL
a labor
I Sht_:i_
~
of
!c;eclter
?. '::'>>=='.
I_ FRE IGHT r-.. Wt
/ Unit ~
----
Tore
W!
_._ 1-----
I
~ -t ---~
···---·--·
---·-·
··-f----
---···
l
l
I .,
I
1--------·--------·"-f--··----------!-------·· 1-----I
i
I
----·--------------------------*--·---·---·-1---
---------·----. --1----------~~~ --t----····------· . ~-
1------~~--------..
------------· ....
----•... f-----1-" -.. .. --·-·~---
'--"· ----· f---"---.~-
----·-·-'--···
t . ----. _c_____J .L_ JPA JM ---r ~ .. ~-. ·-·· ~.·
j
FEB. 19fS4 2~ \ Hev.)
I 1 ! ' ' t i ' i . ' ' Invitation No. Date .
IShl.~of __
CONSTRUCTION COST ESTIMATE I
Orowino No.
PROJECT Takatz Creek Proiect DcooE A OcooE c
Sitka, Alaska lr CODE ncooE
1 Estlmator ~~hecker
LOCATION 8 D _, -. .--Z..---r:::r' ..J ·-
QUANTITY MATERIAL LABOR TOTAL FREIGHT
Unit ~ Total ~ Tore
CLEARING LANDS No. Units Unit Price Cost I Hrs. Rote Cost Mot'l 8 Labor t WI
Campsite 3 AC 25~1'l'D
/
Contingencies (20%+) /..p 2.-~0
Total 2_1 ~50 3\ ~/"' ..
J --------.
------··--
-
1------
NPA FORM ( ) FFB_ 1964 23 Rev.
CONSTRUCTION
PROJECT Takatz Creek Project
LOCATION Sitka, Alaska
STRUCTURES AND IMPROVEHENTS
Site _grading, excavation
Site grading, compacted em-
bankment
Water System
Excavation
CMP, 36-inch (perforated)
Graded gravel backfill
Chlorination house
Chlorination equipment
Supply line, 4-inch, 3-ft
cover
Storage tank, 20,000 gal.
(steel and insulated)
Hose stations, 2 each
Distribution line, 4-inch
(3-ft cover)
----SewerEZ_e Svstem
Sewerage line, 6-inch
Hanholes
-·-·
Septic tank, -
Excavation
Backfill
~ ~ . PA IM , n , FEB. 1964 c.~\ ev.l
4,000-gal
COST ESTIMATE
QUANTITY MATERIAL
Unit
No Units Unit Price Cost
28 000 CY 5-
24,000 CY 5-
200 CY Ia -
50 LF Ga-
200 CY lo -
LS LS
LS LS ----
6,500 LF ~"-
LS LS
LS LS
------~~-r-----·
.2..o -600 LF
1,600 LF ? --D
5 EA /.2~
90 CY lo---f-····-···-
45 CY --? r-·
lnv•tat1on No. Date
Orawim~ No.
OcooE A OcooE c
Esllmotor
·C CODE B DcooE 0
LABOR
~~ Total
Hrs. Rate Cost I
1'+0 ono
l Z.o 000
ZooO
:Soo o
2-o ''> o
/5c;>ao ...
-:::7 0 ,:}C)
/
\;jO.DoC::
3o cJLJ ~
/
3 0.::)0
/
)2 OtY)
-------------
:::; -z.o,)u
f---I
~.-)') r----~~
qoo
Z-2C:: .
i ~
Sht.~of I ~ )
\~,;necker ·
z.._ 2. .::.._ r;: p --:
TOTAL FREI
t.llat'r a Labor ~ Unit
GHT
Toi
w_
-T
1
I
1
I
I
f
l -~-----~
===f' -I r--1 ··r--1 F -~ ---l --------T I ·---·r ----I -----··-+ .. I ·-------I ~._,FI
' lmntatton No. Dote . l 7.
CONSTRUCTION COST ESTIMATE::. J Sht......::;:,l_ of_
Orowim~ No.
PROJECT Takatz Creek Project OcooE A OcooE c
L CODE B DcooE
Estlmotor t~~cks~. LOCATION Sitka, Alaska 0 ~ 4.0 -
QUANTITY MATERIAL LABOR TOTAL FREIGHT
Wo. Units
Unit ~ Toto I
Mat'l S L obor ~w STRUCTURES & 1HPROVEMENTS (co Unit Price Cost t Hrs. Rate Cost
~ Concrete 20 CY 5oo 10 {):)0
Reinforcement bars 2,000 LB o6'5 1300
Paving, 2-inch bituminous, --r--
with 4-inch c.r. base 3,000 SY /5-45 1)()0
I
Rlilrlinqc:
2-bedroom, 3
.. __
Residences, each LS LS 2-aooar
Dormitory, 16-man, 2 each LS LS J5'CJOO<""Y':
/
Mess hall for 70 employees LS LS 2aooc:>~
Warehouse LS LS 2~.C'~I'l
/
Garage LS us /7o aoo
7
Administration building LS LS 2/'~. C>~, .•
··-
Subtotal 2 L.\ 1..., C1 4-'2S ·--Contingencies (20%+) 4u.3 :135' --
Total 2.'11,~~\() 2 qr"\~ c OrO
) I
·-
.
-
-----~
I
'" NPA FORM ( ) FEB. 1964 23 Rev.
E
~ d'
~
K U I U I .
rf
\)
~
+
D
~
t
~
£ ...p
~
("
-o ..
C"
p
~
0
1\
~ •'
.~
s u * Ill E II
sr"~,r
<
~
EXIST ING
ROAD -/
,I
I ,; ,.,
~fP .::IR "r I
I
I
' ' I
I
I
(
.................
()
... ~
...... ~
... .., r
"··~ 'to~ ....
·~,,. ... ~
.... A',,, IJ ~ ',V CJ
CA 9LE G',_ 0 ~ WilANG~-
ZAREMBO I.
(J
():
~ ~
1.1 '<'(]~ \'".,
·~}" <"
"' IS'
<
-z_
, -.A·~~
u~ • t
t'-~
.c.
" t
...... ~ ...
..................
\
~ ..,
...,
(I
.......
I
I
I
I
I
. ..,.,. .. , .....
I
~· ·~1""~
• I .. _
I
I
SlU)Y LOCATION
-,
Pa f'''", Oc,an
LOCATION MAP
. ----... ~ ... -··· -·
5 0 5 10 15 20
U MAD'------------· :..1111 1tl.D \"'•• "
~
.;, .,
---
' ' " ' ' "
SCALE IN MI L ES
~
~ --~
5J
' q,
~
~ CREEK
6. R U T~ L AK E
7 SCE NERY L AKE
B. SUNRISE L AK E
9. THOtootS L AKE
10 VI RGINI A L AKE
11 WILKES RA NGE
TYEE LAKE
RIVERS AN D HARB ORS IN ALASKA
INTERIM FEASI BILITY RE PO RT
ON HYDROELECTRIC POWER
PETERSBURG /WRANGELL AREA,ALASKA
STAGE II
THOMAS BAY AND TYEE LAKE
TRANSMISSION LINE
A L ASKA OISf"ICT, COI'PS 0' f.NOIN f.[ltS
ANCHO"AG[,ALASK A
PLATE I
~
·!
~
·!
....
ACCESS R:;AD ~
SEA
~ SCALE IN FEET
PLAN
1000 0 1000 2000 3000
TO PETERSBURG
'-
LAKE
~
' ,
. ,•
#
RIVERS AND HARBORS IN ALASKA
INTERIM FEASIBILITY REPORT
ON HYDROELECTRIC POWER
0
PETERSBURG/WRANGELL AREA,ALASKA
STAGE ll
THOMAS BAY
SITE PLAN
SELECTED PLAN
ALASKA DISTRICT, CORPS Of' ENGINEERS
ANCHORAGE , ALASKA
PLATE 2
EXISTING a NORMAL
POOL EL. 1514
ELI
.
CD
I ,._ ,._
·TRASH RACK
(BY DIVERS)
LAKE TAP
ROCK TRAP
AOIT
12" OIA . STREAM
FLOW OUTLET
PIPE -------~
CONCRETE UNING
SLOPE 0.5%
20 TON
MONORAIL
DETAIL OF GATE STRUCTURE
NOT TO SCALE
8' HORSESHOE POWER
TUNNEL
ACCESS
HATCH
~ POWER
~
AD IT
"
INVERT EL. 1305
'
\_GATE STRUCTURE
(SEE DETAIL)
PROFILE
SCALE IN FEET
zce,. 9 290 4 00 600
.--1-----, : r----, I
I I I I HYD . 1 1-~
I : 1UNIT I .,.. . '
-----•·J , HATCH
~
PLAN-GATE ROOM FLOOR
NOT TO SCALE
CONCRETE PLUG
NOT TO SCALE
PENSTOCK
NOT TO SCALE
ROCK
TRAP
.
Cl)
'
'!!
~---------ROCK BOLTS------,
\
\
~
,·
.\..._ ___ _
z
~
-,..,
STEEL ORIFICE
PLUG
TYPICAL UNLINED
TUNNEL SECTION
NOT TO SCALE
SURFACE
8'-o"
MIN .
SURGE TANK
NOT TO SCALE
AS REQUIRED
DESIGN LINE--------...
, . ., -+" ""
TYPICAL LINED TUNNEL SECTION
6' DIAMETER STEEL
PENSTOCK
SURGE TANK
COVER
AIR FLOW
NOT TO SCALE
~ ,
RIVERS AND HARBORS IN ALASKA
INTERIM FEASIBILITY REPORT
ON HYDROELECTRIC POWER
..
0
PETERSBURG/WRANGELL AREA, ALASKA
STAGE II
POWER TUNNEL PROFILE AND SECTIONS, GATE
STRUCTURE PLAN AND DETAIL, SURGE TANK,
PENSTOCK AND CONCRETE PLUG DETAILS
THOMAS BAY SELECTED PLAN
ALASKA DISTRICT , CORPs OF ENGINEERS
ANCHORAGE, ALASKA
PLATE 3
----------------------------------------------------------------------------~----~--~----~---.___~~~· ~~~--------------0
--..---'
../"'
rt££
t.AK£
EL 1420
WELDED STEEL FACE TO BIN
WALL FOFi I.'PERVIOUS MEMBRANE
; I
. -----====
SITE PLAN
SCALE IN FEET
~ 0 ~ ~
I
/"'STEEL BIN WALLS (RETA INING WALL)
FILLED WITH ROCKFILL
'
CONCRETE CUTOFF WALL STRIP EXISTING MATERIAL:
SECTION 0
SCALE I N FEET
~ o ~ m ~
TOP OF IS1 SET OF BIN WALLS \
{
EXISTING STREAM BED PROFILE
....-ROCK FILL
--
ASSUMED BEDROC1(
•'£ liiiCUI) STEEL ~STOCK, C'e
TU
TYEE LU'.£ RESERVOI II SITE
,·.zooo•
. ,
• r
E3..-:E:L -__~:'{ C I WILE ,.._._:;[ -:r=::=F ~ -.E3
~ ( --~-....., '5000 ruT
SECTION 0
SCAU .. f'EET
w o ~ ~ •o
-,c' ,......-I
--< 7 4 TOP OF 4th SET OF BIN WALLS
~ --~ TOP OF 6th SET OF BIN WALLS
RIVERS AND HARBORS IN ALASKA
INTERIM FEASIBILITY REPORT
ON HYDROELECTRIC POWER
PETERSBURG/WRANGELL AREA,ALASKA
STAGE li
TYEE L AI<E DAM
PLAN AND SECTIONS
SELECTED PLAN
ALASKA OISTitiCT, co.IPS OF ENG I NEEIIS
ANCt«>~'AGE • ALASKA
PLATE 4
:Y 14;;2 t lllN WALl. DAM CIIEST >
LAKE TAP, ELV 1240' IIOCK TRAP
SECTION 8
NTS
POWER TUNNEL, e' H<lf~SESHO£
GATE CHAMBER
05'Y.. SLOPE -
.,
TAP AREA cb-l'"\:f4'--,_ __ ....1i,,G.'"o/"C-~--.-~ ''/ -, t
L_ ---L_j
SECTION 0
6~··~----------~~
LAKE TAP
PLAN
NTS
DEAD END TRAP ~
,~:.,
I• •; • i • .... ~ •I
SURGE CHAMBER AIR FLOW I
Sl..RGE CHAMBER
\ ... ~ "~
PENSTQCI(
... ·. ,, ..
6'e STEEL PENSTOOK
''··. \
GROUND SURfACE
:)
~ J
"
.. l
RIVERS AND HARBORS IN ALASKA
INTERIM FEASIBILITY REPORT
ON HYDROELECTRIC POWER
PETERSBURG/WRANGELL AREA,ALASKA
STAGE n
POWER TUNNEL PROFILE
LAKE TAP PLAN AND SECTIONS
TYEE LAKE SELECTED PLAN
ALASKA OISTfiiCT, CORPS OF ENGINE EM
ANCHORAGE , A.LASt<A
PLATE 5
•
GATE VAI.YE
I
I
.... 1 STREAM F\..OW I
~·~~/~
•
·. ..
. . .
• '0> ••
:I>
1:)
I• II !II \GATE LEAF 6'X lc1
" :,.. $> ..
~ .. _.,._ . .. --~ t>
~ ~
~· ~ -~ ·I:J' .. -· (T .. • .. •
PLAN AT GATE CHAMBER FLOOR
N .TS.
•
~
0
.. .·
... ..
•
) ~ .
. ~ ·.
·'.
• . ·
. ..
..
-. ~ .. • • ... ;
• \0 ~ . .
'· •
' ~ . --.
··. ,
' '=·
• 0
AQ~T
--~'11.
TYPICAL UNED TUNNEL SECTION
N.l:S.
'
·' ~ . ·
• .
I
I
I
I
I
I
I
I
I
I ___ j
...
; . ..
SECTION 8
N.TS.
I DESIGN U ll[
I ~
I ---+----t--+--
TYPICAL ~UNED TUNNEL SECTION
N. T.S.
0
RIV ERS AND HARBORS IN ALASKA
INTERIM FEASIBILITY REPORT
ON HYDROELECTRIC POWER
PETERSBURG/WRANGELL AREA,ALASK
~I STAGE U
GATE CHAMBER PLAN AND SECnONS
AND T UI'I'£L SECTIONS
TYEE LAKE SELECTED PLAN
ALASl(A DISTRICT, CORPS 01' ENG INEERS
ANCHORAGE , ALASKA
PLATE 6
I
I
I