HomeMy WebLinkAboutKing cove Oldharbor Larsenbay Hydro project Vol A Final Summary Report 8-1982Volume A
FINAL SUMMARY REPORT
Feasibility Studies for
KING COVE HYDROELECTRIC PROJECT
OLD HARBOR HYDROELECTRIC PROJECT
LARSEN BAY HYDROELECTRIC PROJECT
Reconnaissance Study for
TOGIAK HYDROELECTRIC PROJECT
Submitted by
DOWL ENGINEERS
ANCHORAGE, ALASKA
In Association with
TUDOR ENGINEERING COMPANY
SAN FRANCISCO, CALIFORNIA
DRYDEN & LARUE
ANCHORAGE, ALASKA
AUGUST 1982
e•
ALASKA POWER AUTHORITY
Volume A
FINAL SUMMARY REPORT
Feasibility Studies for
KING COVE HYDROELECTRIC PROJECT
OLD HARBOR HYDROELECTRIC PROJECT
LARSEN BAY HYDROELECTRIC PROJECT
Reconnaissance Study for
TOGIAK HYDROELECTRIC PROJECT
Submitted by
DOWL ENGINEERS
ANCHORAGE, ALASKA
In Association with
TUDOR ENGINEERING COMPANY
SAN FRANCISCO, CALIFORNIA
DRYDEN & LARUE
ANCHORAGE, ALASKA
AUGUST 1982
ALASKA POWER AUTHORITY
SUMMARY VOLUME
CONTENTS
Section
Page
FOREWORD
I.
INTRODUCTION
I-1
II.
KING COVE SUMMARY
II-1
III.
OLD HARBOR SUMMARY
III-1
IV.
LARSEN BAY SUMMARY
IV-1
V.
TOGIAK SUMMARY
V-1
NBI-432-9526-SC i
FOREWORD
This volume, Volume A, is a summary report incorporating
the findings, conclusions, and recommendations of the feasibil-
ity studies for King Cove (Volume B), Old Harbor (Volume C),
and Larsen Bay (Volume D) and the reconnaissance study for
Togiak (Volume E). Volumes B through E are comprehensive
individual project reports that present the findings and recom-
mendations of studies to assess the economic, technical,
environmental, and social feasibilities of hydroelectric
projects for these four villages.
Each of the volumes for the individual project reports
consists of 12 sections and six appendices. The first section
of each report is a concise summary of all activities conducted
for the particular project. Following a brief introduction,
Section I, these summaries from each volume are reproduced here
as Sections II, III, IV and V and some similarity in format and
narrataive will be noted. Selected photographs, figures and
drawings have also been included with each summary section as
appropriate.
NBI-432-9526-SF ii
TOGIA
KING COV
Ci 0
oQ oD LARSEN BAY
LOCATION MAP FIGURE
1-1
SECTION I
INTRODUCTION
A. GENERAL
This summary report presents the overall results of studies
conducted to appraise proposed hydroelectric projects at King
Cove, Larsen Bay, Old Harbor and Togiak. With the exception of
Togiak, all studies were at the feasibility level and included
the optimal sizing of all project features. The studies for
Togiak were at a reconnaissance level since the prior studies
were not as extensive and since the proposed project involves a
small dam and is more complex.
The studies were authorized by the Alaska Power Authority
as a result of numerous prior studies of energy alternatives
that had recommended hydroelectric projects as the best source
of future electric energy for the four villages. In addition
to the hydropower alternative, the continued use of diesel
generators, the installation of waste heat recovery equipment,
and the installation of wind powered generators were all
considered as possible future energy sources.
The overall results of these studies indicate that feasible
hydroelectric projects can be constructed at King Cove, Old
Harbor and Larsen Bay. The study for Togiak indicates that a
hydroelectric project of sufficient size to satisfy the overall
electric demands is marginal at best and then only if 7.0 miles
of the required 11.6-mile access road to the site is con-
structed by the Alaska Department of Transportation. It may,
however, be possible to construct a much smaller hydropower
site near Togiak which would satisfy at least a portion of the
electrical needs of the village. This site is currently being
assessed at a preliminary level and will be addressed in a
later report.
NBI-432-9526-SI I-1
Any or all projects studied could be constructed and on-
line by January 1985 if a decision to proceed is made by
December 1982.
B. PURPOSE AND SCOPE OF STUDIES
The primary purposes of the studies for King Cove, Larsen
Bay and Old Harbor were to prepare recommendations of the best
configurations for developing dependable sources of hydro-
electric energy supplies for the villages and to determine the
engineering, environmental, and economic feasibilities of the
projects. For Togiak the primary purpose was to determine if
any feasible project could be constructed with the intent to
optimize the project features in the next phase if overall
feasibility was demonstrated.
The general scope of the studies consisted of first
projecting the future electrical energy needs of the villages
over a 20-year planning period and developing alternative
diesel and hydroelectric project scenarios to meet those
projections. Increases in demand for energy and the cost of
petroleum products were recognized for a 20-year planning
period extending from 1982 through 2001. The demands and costs
were assumed to be constant after the 20-year planning period.
The period for economic evaluation extended 50 years past the
on-line date for the hydroelectric alternative. Economic
comparisons were then made between these alternatives, the
environmental effects were assessed, and conclusions and
recommendations were formulated.
NBI-432-9526-SI I-2
The diesel alternative for each village was know❑ as the
"base case" plan and was essentially a continuation of the
present diesel generating plants, enlarged as necessary to
accommodate future growth. Heat recovery, to be used for local
space heating, was incorporated with the base case plans to the
maximum extent that is economically feasible. Wind generation
was also considered as part of the base case plan and was found
to be economically feasible, although of limited value, at all
four sites.
Some hydroelectric energy was also used for space heating.
I❑ assessing power and energy priorities for the hydroelectric
energy for each village, the first priority was given to the
direct electrical demand for the village. The second priority,
when excess energy was available, was the cannery demand (King
Cove only) and the third priority was the village space heating
demand.
C. OVERALL STUDY RESULTS
A table presenting the size, average annual energy
generated, the estimated cost (in 1982 dollars), the fuel oil
displaced by the hydroelectric energy, and the benefit/cost
ratio (B/C) for each project is presented below. The B/C
ratios shown reflect the benefits from waste heat recovery, and
wind generation and the utilization of excess electrical energy
for space heating (and the cannery at King Cove). A more
detailed summary is contained in the following sections of this
volume: King Cove, Section II; Old Harbor, Sect -ion III; Larsen
Bay, Section IV; and Togiak, Section V.
NBI-432-9526-SI I-3
Average
Annual 1982 Fuel Oil
Project Size Energy Cost Displaced/Yr. B/C
(kW) ^\J kWh $ (Gal. )
King Cove 575 \ _.2,280,0001. 3,744,90010Yr143,700 2.011
054
Larsen Bay 270 " , 1, 090, 00e, 2, 8;1, 400 °ii0Ap 85,700 1.237
yd
Old Harbor 340 0�'L--1,310,000,4`11=3,082,300 �; N' 1039300 1.403
Togiak 432 6iV 2,660,00041119 7,047,200 189,800 1.024
(lid 'CA. i C..'•. 5� 92n°fin
The values given above for fuel oil displacement are for a
combination of diesel fuel used for diesel generators and space
heating.
As the B/C values in the above table indicate, the projects
for King Cove, Larsen Bay, and Old Harbor are feasible. The
Togiak project is marginal.
As is presented in the following more detailed summaries
for each project, it is possible to derive several different
B/C ratios for each of the projects. This is because the
calculated B/C ratio for a given project depends on which
combination of assumptions concerning waste heat recovery (from
the diesel generator), space heating (from the hydroelectric
energy in excess of the villages electrical demands) and
supplemental wind generators are utilized. For example, the
B/C ratios presented above are somewhat lower when the benefit
of space heating with excess hydroelectric energy is not
included.
D. STUDY PARTICIPANTS
DOWL Engineers, of Anchorage, Alaska, was the primary con-
tractor for the study. DOWL was assisted by two subcontractors-
-Tudor Engineering Company of San Francisco, California, and
Dryden & LaRue of Anchorage, Alaska. DOWL performed the project
management functions and provided all geological, geotechnical,
NBI-432-9526-SI I-4
and environmental information. Tudor, as principal subcontrac-
tor, supplied all hydroelectric expertise for the project and
compiled the project report. Dryden and LaRue formulated the
demand projections and supplied all diesel generating and
transmission line information.
E. ACKNOWLEDGEMENTS
The cooperation of the many federal, state, and local
agencies and local residents contacted during the course of the
study is gratefully acknowledged. This list includes, but is
not limited to, the Alaska Power Administration, the Alaska
Department of Fish and Game, the Alaska Department of Trans-
portation, the U.S. Army Corps of Engineers, the U.S. Geologi-
cal Survey, and the U.S. Fish and Wildlife Service. The assis-
tance of the Rockford Corporation and the Locher Construction
Company, a subsidiary of Anglo Energy Company, is also acknow-
ledged. We especially wish to thank the Alaska Power Authority
and their program manager for the project, Mr. Don Baxter.
NBI-432-9526-SI I-5
SECTION II
KING COVE
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume B--
Feasibility Study for King Cove Hydroelectric Project. Included
for general background information are several items from that
report: Exhibit VI-1, Photographs of the Project Area; Figure
VII-39 Projected Monthly Generation, Demand, and Usage; and
selected project drawings which include Plate I, the General
Plan, Plate III, the Penstock Plan, Profile and Details, and
Plate VI, the Powerhouse Plans and Sections. References to
figures, exhibits, and plates in the summary presented here
refer to items in Volume B, the full feasibility report for the
King Cove Hydroelectric Project.
NBI-432-9526-SKC II-1
KING COVE
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying
King Cove with electrical energy had recommended a hydro-
electric project as the best source. As a direct result of
these prior studies and recommendations, the Alaska Power
Authority authorized a feasibility study to investigate in
detail the hydropower potential in the vicinity of King Cove.
This report summarizes the activities conducted for the
feasibility study. These activities included projections of
energy needs, formulation of a hydroelectric project plan and
an alternative base case plan to meet the electrical energy
needs of King Cove, detailed analyses of economic feasibility
of each option, and preparation of an environmental assessment
of the effects of the project.
The results of the study indicate that a 575 kilowatt (kW)
hydroelectric project can be constructed at King Cove, that the
project is considerably more economical than the base case
alternative, and that the environmental effects of the project
are minor.
The estimated total construction cost of the proposed King
Cove hydroelectric project is $3,743,900 i❑ January 1982
dollars. The project could be implemented and on-line by
January 1, 1985, if a decision to proceed with the project is
made by December 1982. During an average water year, the
proposed project would be capable of supplying more than 90
percent of the electrical needs and some of the space heating
needs in the project area. The equivalent savings in diesel
fuel in the year 2001 would be about 120,000 gallons for direct
electrical demand and 23,000 gallons for space heating.
NBI-432-9526-SKC II-2
B. AREA DESCRIPTION
King Cove is located on the western end of the Alaskan
Peninsula near the beginning of the Aleutian Island chain.
With the exception of Cold Bay/Fort Randall 18 miles to the
northwest, the nearest major towns are Dillingham, King Salmon,
and Kodiak, 300 to 400 miles to the northeast. The selected
hydropower site is located on Delta Creek about five miles
north of town. The project area and the proposed site are
shown on Plate I of Appendix A.
C. POWER PLANNING
Power planning for the King Cove Project was conducted
using standards set forth by the Alaska Power Authority.
Previously recommended potential hydroelectric sites were
investigated and the project area was surveyed to evaluate
potential new sites. After detailed study, a project was
selected and then compared with a base case plan. The base
case plan consisted of a continuation of the present diesel
generation system, enlarged as necessary to meet future
growth. The base case also included the installation of waste
heat recovery and wind generation. These were both found to be
viable for installation.
Present energy demands for King Cove for direct electrical
uses, cannery use, and space heating were estimated and future
uses in these same categories were projected. The projections
were based on forecasts of increases in the number of customers
and increased usage rates. Population growth and employment,
legislation and other political influences, life style changes,
and other factors can influence future energy demands but they
were not explicitly treated.
NBI-432-9526-SKC II-3
The period of economic evaluation used was 53 years, which
starts in January 1982 and extends for the 50-year life of the
hydroelectric project after the estimated on-line date of
January 1985. The energy demands for King Cove were increased
for 20 years starting i❑ January 1982 and extending through
December 2001. The demands were then held level over the
remainder of the economic evaluation period. The cannery
demand was assumed to remain constant over the entire period.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be the
direct electrical needs of King Cove, second priority would be
for the cannery requirements, and remaining energy would be
used for space heating to as great an extent as possible.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine -
generator system to produce electric power. In the case of the
recommended King Cove Hydroelectric Project, a low weir will
act as a dam to divert water from Delta Creek through an inlet
structure and into a penstock (conveyance pipe). The penstock
will be 36 inches in diameter and it will carry the water about
5300 feet to the powerhouse, where it will be passed through
the turbine -generator system to produce electric energy. The
project will incorporate a sediment basin near the diversion
weir to trap and remove sediment from, the water before it
enters the penstock; otherwise, coarse sediment might damage
the turbine.
The powerhouse will have the capacity to produce 595 kw of
electrical power. A transmission line will be constructed to
transmit the power generated at the plant to King Cove. Access
NBI-432-9526-SKC II-4
to the powerhouse facilities will be provided by building a new
road to link up with the existing road at the King Cove
Airport. The transmission line will follow the alignment of
the new access road and the existing road from the airport to
King Cove. The general plan and features of the proposed
project are presented on Plates I through VIII of Appendix A.
Photographs of the project area are presented in Exhibits VI-1
and VI-2 at the end of Section VI and in the Environmental
Report, Appendix E.
Under the recommended plan, energy generated by the hydro-
electric plant will have to be supplemented by diesel genera-
tion. The entire existing diesel capacity will be required as
standby and backup power. The hydroelectric generation will be
adequate to meet the direct electrical needs of King Cove (not
including the cannery) during most of the year; however, from
December through March diesel will be necessary to supplement
the hydrogeneration. Diesel will also be needed at times to
meet the needs of the cannery located in King Cove.
In all, during an average water year the proposed hydro-
electric project will be capable of supplying more than 90
percent of the electrical needs of King Cove and approximately
one-third of the cannery needs.
Average annual energy production from the hydroelectric
plant will be 2.28 million kilowatt-hours (kWh) and the average
annual plant factor will be about 45 percent, which means that
the plant is expected to generate about 45 percent of the
energy that it could produce if the turbine -generator unit was
operated continuously at full capacity.
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of King Cove assumed that the existing diesel system
NBI-432-9526-SKC II-5
u
would continue to be used as the sole source of electric power,
excluding the cannery. Because of apparent economic benefits,
it was assumed that the system would incorporate waste beat
recovery that would be used for space heating. The
installation of wind generation equipment was also considered
and was found to be economically viable. The existing diesel
plant's capacity was judged to be adequate to meet peak demands
on the King Cove system throughout the period of study.
The diesel system at King Cove now uses about 70,000 gal-
lons of fuel oil per year; this rate was expected to increase
over the next 20 years to more than 128,000 gallons per year.
Waste heat recovery was expected to displace the use of 17,000
gallons of fuel oil per year by the year 2001.
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
base case costs to the net present worth of the proposed hydro-
electric project costs using specified real price escalation
and discount rates. Net present worth is the present value of
the costs that would be incurred over a comparable economic
evaluation period of 53 years for both the base case and the
hydroelectric project.
The net present worth of the total cost of the base case
plan is $9,287,000. This net present worth is $8,790,000 after
adjustment for waste heat recovery; $8,170,800 after adjustment
for wind energy; and $12,983,900 after adjustment for the can- .
nery credit. In order to compare all alternatives to the
hydroelectric project, all costs other than the cost of the
hydroelectric project and its diesel supplement were applied as
adjustments to the base case. The net present worth of the
base case, after all adjustments, including the space heating
credit associated with the hydro project, is $14,203,900.
NBI-432-9526-SKC II-6
For the proposed hydroelectric project, the present worth
of the costs is $7,053,100. A comparison of these net present
costs with the base case net present costs indicates that the
recommended hydroelectric project is considerably more
economical than the alternative base case.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For this project the calculated B/C ratio is
1.317 when the hydro project is compared to the base case only,
1.246 when the base case is adjusted for waste heat recovery,
1.158 when the wind energy credit is also considered, 1.841
when the cannery credit is added, and 2.011 when all adjust-
ments have been made.
The annual unit costs of energy production for the base
case and recommended hydroelectric alternatives were calculated
for each year of the economic analysis in order to determine
the optimum timing for development of the hydroelectric proj-
ect. This analysis indicates that the hydroelectric project is
viable for immediate development.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The environmental study results indicate that the effects
of the project will be minor due to the limited scope of the
project activities, the lack of major fish or wildlife
resources in the immediate area, and the availability of
measures to mitigate potential effects from the construction
and operation of the facilities. Minor socioeconomic benefits
will occur as a result of project construction and maintenance
and cheaper electric rates made possible by the project.
Additional environmental studies do not appear to be warranted
NBI-432-9526-SKC II-7
unless regulatory agencies or local residents express addi-
tional concerns.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that the
proposed 575 kW project is feasible and that the energy demands
of King Cove are sufficient to utilize the hydroelectric
plant's planned capacity. The proposed project is a more
economic means of meeting the area's future electric needs than
the base case diesel alternative. Environmental effects of the
proposed project are minor.
In view of these findings, it is recommended that actions
be initiated to implement the project.
NBI-432-9526-SKC II-8
Y s IK
ror-
r M ^•l -1 � � r�� ' �
a
800'TOTAL ELECTRICAL DEMAND
"NOT INCLUDING HEATING DEMAND)
700 -
600
500
• We
300
200
HYDROELECTRIC ENERGY
AVAILABLE FOR
HEATING DEMAND
HYDROELECTRIC
POTENTIAL.
DOI
390
38 6
ooe
REQUIRED DIESELDIRECT ELECTRICAL DEMAND
GENERATION ( NOT INCLUDING HEATING
0 - OR CANNERY DEMAND)
J F M A M J J A S 0 N D
MONTH
DETAIL DATA
4000
t 1
3000 / TOTAL COMBINED DEMAND
2000
0
0
-. 1000 TOTAL ELECTRICAL
x DEMAND
t HYDROELECTRIC 2001
Y POTENTIAL _ a 1985 .
co
Ww
-
Ial 0 .
J F M A m J J A S 0 N D
MONTH
OVERALL DATA
m-.
,n: .c,_L, f, _... ... a.>. ... �. n.. y'.:Fczr ." ,.: ... X_i. •F rv. ....: cW s. iv:.+.r
KING COVE HYDROELECTRIC PROJECT
PROJECTED MONTHLY ENERGY GENERATION, DEMAND, AND USAGE
FIGURE
l
�
r-�.. ri
L-- , -
7
/I UilER3mN WE4R
. z �� RENstae�--kµ, ROJECT AREA
.PR� Eb ACCESS RgAp
L -T A AND TRANSMISSION LINE
AIRYTAIP
� m
r
' 1' "PRP�O$ED
RANSNIS.V�iN 11NE
-
�� i
L7�
'
KING CO
`-
/
1�-ems
M R E
E.���
a
-
i
. PROJECT PLAN
m
O 2 Z
KING
BRISTOL
BAY
COLD BAY OO
PRCSTY PEAK
, /�
S �
PASS
3 MILES
LOCATION MAP
NTS
VOI A
.IOF L
MT NO
MT ®TON a
KING COVE,
O
VICINITY MAP
NTS
SEE ACCESS ROAD
AND PENSTOCK
CREEK CROSSING
DETAILS
DIVE-R=SSIIION FA6a6.7F0
40
NSTt90iF AN6-7!\CCESS ROADa�,`J'��L a' �\ '°`•t'O\ \��` ��\u1 `� �'.
PLAN
SCALE 1 1"- 250'
I
50
ACCESS ROAD AND
TRANSMISSION LINE
TO KING COVE IS MILES)
VIA AIRPORT (1/2 MILE)
30
o �
� J
RING GIRDER
\DRESSER
COUPLING)
�a1
TROC
OF ROCK
SECTION A
RING GIRDER
_ 36= / STEEL PIPE
NATURAL GROUND (ROCK)
SELECT ROADBED FILL
SLOE 2%
• +A i TOP OF ROCK
TYPE I- SIDEHILL (ROCK)
BACKFILLED SLOPE 2%
TRFNf.N�
ROADBED FILL
I 36-/ FIBERGLASS PIPE
1 b" SAND BEDDING
y I'-O' EACH SIM
(TYR)
TYPE II - LEVEL GROUND
GROUND
i
TYPE 8
Y /n
WO
TYPE D � � TYPE D
I
TYPE ID
TYPE D
4]5
-
- MMM---
. -----iiV
4]5
PE NSTvCK/ACCESS ROAD TYPES'
- '
12
SELECT ROADBED FILL
450
EL 436
DIVERSION FACILITIES
-
c - - -- -
450
���_
LGROUND
425
-
425
SLOPE 2X _
(SOINAMU
400
-
-
_
400
COVER
I.
-
:
(MIN)
ji
BACKFILLED TRENCH
575
-
3Y5
36" A FIBERGLASS PIPE
350
—PENSTOCK AND ACCESS ROAD
'�.
`;
o
550
3" SAND BEDDING
o.m
325
- �.
�
325
ham{
Z 300
--,..
_ -�„
d
vi.
300
(TYP)
o
DELTA CREEK
TYPE IQ- SIDEHILL (SOIL)
zis
���
zis
m 25D
�,.
m
`
_ POWERHOUSE
2sa
SELECT ROADBED FILL
14'jL2
1
¢
m
_
(NOZZLE EL 215 )
—1�
flIPRAP(AS NECES6ARY)
zzs
¢
225
%
F
o
"
-�----.,�
FLOODPLAIN
w W 20azaa
OVER(MIN)
175
mOCAL
pity.m1]5
MATERIALI30o
w
m
v�i w
vLi
150
6' A FIBERGLASS PIPE
J
W 125
125
'SAND BEDDING
o+W 5 10
15 20 25 50 35 4o
43 5o ss
TRENCH
STATIONING , FEET
NOTE'
PROFILE OF PENSTOCK /ACCESS ROAD NO TERRAIN WAS ENCOUNTERED REWIRING
THE TYPE I SECTION DURING THE FIELD RECONNAISSANCE,
SCALE: 1""250' HORIZ. IT IS INCLUDED HERE IN CASE LATER MORE DETAILED
I"= Ed VERT. INVESTIGATIONS YIELD EVIDENCE OF SUBSURFACE ROCK.
0 4 6 12 16 20 24
SCALE : I "" 4'
0 50 100 150 200 250 300
SCALE : I" " 50'
0 250 500 750 Iwo 1250 1500
SCALE : I"= 250'
TYPE 14'- FLOODPLAIN
TYPICAL PENSTOCK /ACCESS ROAD SECTIONS
SCALE; 1"-4'
CHAIN LINK FENCE I 1I PARKING AREA-- ,
\ CCNST TION/ACCESS ROAD PERSONNEL DOOR
\ Q EQUIPMENT
Poo � ENTRANCE DOOR
c: \
RI PARKING AREA
D i EQUIPMENT MOUNTING SKID
POWER TRANSFORMER
\ \\ ELECTRICAL SWITCHGEAR FL. EL. 212.0
BURIED Q � TRANSMISSION LINE GENERATOR
ENSTOCK�~•� -- -'�
2¢ `` BEARING LUBRICATION SET
FLYWHEEL
B
/ ACCESS ROAD
/ • y 36" DIA. PENSTOCK SPEED INCREASER
POWERHOUSE/
V. ryy TURBINE SHUTOFF VALVE
` O B
II 6" DIA. PENSTOCK DRAIN
RIPRAPPED TAILRACE �� 1
N SLOPE
\�= TURBINE
2� 206—�.
^\ RIPflAP
�I DELTA CREEK l \ TAILRACE 4`�
A•ZQW '• I --*A
30
POWERHOUSE PLAN
SCALD
I6
GENERAL PLAN
SCALE: I'm 20'
GENERATOR SPEED INCREASER TURBINE TURBINE
EQUIPMENT
MOUNTING SKID FENCE
4TAILIACE
TURBINE
PREFABRICATED
WALL SHUTOFF VALVE METAL BUILDING
EQUIPMENT
DOOR 35'-0° A 36'-0"
RIPRAP /
FL. EL. 212.0
NATURAL GROUND l AILRACE
36" DIA.
PENSTOCK
STATE OF ALASKA
PROFILE -SECTION A PROFILE -SECTION B ALASKA POWER AUTHORITY
SCALE 3 = -0 SCALE: A = 1'-0= 1'-0 ANCHORAGE,ALASKA
16 16
0 3 10 16 20 26 30 KING COVE HYDROELECTRIC PROJECT
SCALE : 16" • I'-0 .
POWERHOUSE- PLANS AND SECTIONS
O 20 40 60 So I00 120
SCALE :I"=20' DOWL ENGINEERS TUDOR ENGINEERING COMPANY
ANCHWAGE, ALASKA SAN PRANCISCO,CAUFORNIA
PLATE M
SECTION III
OLD HARBOR
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume C--
Feasibility Study for Old Harbor Hydroelectric Project.
Included for general background information are several items
from that report: Exhibit VI-2, Photographs of the Project
Area; Figure VII-3, Projected Monthly Generation, Demand, and
Usage; and selected project drawings which include Plate I, the
General Plan, Plate III, the Penstock Plan, Profile, and
Details, and Plate V, the Powerhouse Plans and Sections.
References to figures, exhibits, and plates in the summary
presented here refer to items in Volume C, the full feasibility
report for the Old Harbor Hydroelectric Project.
NBI-432-9526-SOH III-1
OLD HARBOR
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying Old
Harbor with electrical energy recommended a hydroelectric
project as the best alternative. As a direct result of these
prior studies and recommendations, the Alaska Power Authority
authorized a feasibility study to investigate in detail the
hydropower potential in the vicinity of Old Harbor.
This report summarizes the activities conducted for the
feasibility study. These activities included projections of
energy needs, formulation of a hydroelectric project plan and
an alternative base case plan to meet the electrical energy
needs of Old Harbor, detailed analyses of economic feasibility,
and preparation of an environmental assessment of the effects
of the proposed hydroelectric project.
The results of the study indicate that a 340 kilowatt (kW)
hydroelectric project can be constructed at Old Harbor, that
the project is considerably more economical than the base case
alternative, and that the environmental effects of the project
are minor.
The estimated total construction cost of the proposed Old
Harbor hydroelectric project is $3,082,300 in January 1982
dollars. The project could be implemented and on-line by
January 1, 19859 if a decision to proceed with the project is
made by December 1982. During an average water year, the
proposed project would be capable of supplying more than 85
percent of the electrical needs and about it percent of the
space heating needs in the project area. The equivalent
savings in diesel fuel in the year 2001 would be more than
83,000 gallons for direct electrical demand and more than
19,000 gallons for space heating.
NBI-432-9526-SOH III-2
B. AREA DESCRIPTION
Old Harbor is a small village located on the southeast
coast of Kodiak Island, 50 miles southwest of the city of
Kodiak. The selected hydroelectric development site for Old
Harbor is located on Midway Creek across Midway Bay from the
village.
C. POWER PLANNING
Power planning for the Old Harbor Project was conducted
using standards set forth by the Alaska Power Authority.
Previously recommended potential hydroelectric sites were
investigated and the project area was surveyed to evaluate
potential new sites. After detailed study, a project was
selected and then compared with a base case plan. The base
case plan consisted of a continuation of the present diesel
generation system, enlarged as necessary to meet future
growth. Wind generation was also considered as part of the
base case. Wind generation was found to be a viable means
supplemental generation.
Present energy demands for Old Harbor for direct electrical
uses and space heating were estimated and future uses in these
categories were projected. The projections were based on
forecasts of increases in the number of customers and increased
usage rates. Population growth and employment, legislation and
other political influences, life style changes, and other
factors can influence future energy demands, but were not
explicitly treated.
The period of economic evaluation used was 53 years,
beginning in January 1982 and extending for the 50-year life of
the hydroelectric project beyond the estimated on-line date of
January 1985. The energy demands for Old Harbor were increased
NBI-432-9526-SOH III-3
for 20 years starting in January 1982 and extending through
December 2001. The demands were then held level over the
remainder of the economic evaluation period.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be for
the direct electrical needs of Old Harbor, and remaining energy
would be used for space heating to as great an extent as
possible.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine -
generator system to produce electric power. In the case of the
recommended Old Harbor Hydroelectric Project, a low weir will
act as a dam to divert water from Midway Creek through an inlet
structure and into a penstock (conveyance pipe). The penstock
will be 24 inches in diameter and will carry the water about
2200 feet to the powerhouse, where it will be passed through
the turbine -generator system to produce electric energy.
The powerhouse will have the capacity to produce 340 kw of
electrical power. A transmission line will be constructed to
transmit the power generated at the plant to Old Harbor.
Access to the powerhouse facilities will be provided by
building a new road from Midway Bay to the facilities and by
building a dock at the bay. The dock will be reached by boat
from Old Harbor. The transmission line will be constructed
from the powerhouse across the upper end of Midway Bay to Old
Harbor. The general plan and features of the proposed project
are presented on Plates I through VI of Appendix A. Photo-
graphs of the project area appear in Exhibits VI-1 through VI-4
at the end of Section VI and in the Environmental Report,
AppPridix E.
NBI-432-9526-SOH III-4
Under the recommended plan, energy generated by the hydro-
electric plant will have to be supplemented by diesel genera-
tion. The entire existing diesel capacity will be required as
standby and backup power. The hydroelectric generation will be
adequate to meet the direct electrical needs of Old Harbor
during most of the year; however, during periods from the end
of November to the first of April it will be necessary to
supplement the hydroelectric generation with diesel power.
In all, during an average water year the proposed hydro-
electric project will be capable over the project life of
supplying an average of more than 90 percent of the electrical
needs of Old Harbor and approximately 15 percent of the space
heating requirements.
Average annual energy production from the hydroelectric
plant will be 1.31 millio❑ kilowatt-hours (kWh) and the average
annual plant factor will be about 44 percent, which means that
the plant is expected to generate about 44 percent of the
energy that it could produce if the turbine -generator unit was
operated continuously at full capacity.
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of Old Harbor assumed that the existing diesel system
would continue to be used as the sole source of electric
power. Because there are no significant heating loads near the
plant, it was assumed that the system would not incorporate
waste heat recovery that would be used for space heating, since
it probably would not be economical to relocate the plant
nearer a heating load. The existing diesel plant's capacity
was judged to be adequate to meet peak demands on the Old
Harbor system throughout the period of study.
NBI-432-9526-SOH III-5
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
base case costs to the net present worth of the proposed hydro-
electric project costs using specified real price escalation
and discount rates. Net present worth is the present value of
the costs that would be incurred over a comparable economic
evaluation period of 53 years for both projects. All costs
other than the cost of the hydroelectric project and diesel
supplement were considered as adjustments to the base case
cost.
The present worth of the total costs of the base case plan
is $8,182,800. If this cost is reduced by the wind energy
credit of $330,400, the net present worth is $7,852,400.
Adding the space heating credit at $1,234,600 results in a
final net present worth of $9,087,000.
For the proposed hydroelectric project, the present worth
of the costs is $6,475,000. A comparison of this net present
cost with the base case net present costs indicates that the
recommended hydroelectric project is considerably more
economical than the alternative base case.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For this project, the calculated B/C ratio is
1.264 when the hydroelectric energy used only for the direct
electrical needs of Old Harbor is compared to the base case
only and 1.213 when the wind energy credit is included.
Inclusion of the space heating credit results in a final B/C
ratio of 1.403. These B/C ratios indicate that the proposed
hydroelectricproject is highly feasible.
NBI-432-9526-SOH III-6
The unit costs for each year of operation for both the base
case and the hydroelectric alternative were calculated and
compared in order to determine the optimum timing for project
development. This analysis indicates that the project is
viable for immediate development.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The study results indicate that the adverse environmental
effects of the project will be minor due to the limited scope
of project activities, the limited nature of the fishery
resources in Midway Creek, and the availability of measures to
mitigate the potential effects from the construction and
operation of the facilities. Implementation of the project
should bring some socioeconomic benefits to Old Harbor. The
local payroll will be expanded during construction and some
employment should be provided for local residents both for
construction and maintenance of the facilities. The project
should also bring a dependable and cheaper supply of electric
power to the local residents.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that the
proposed 340 kW hydroelectric project is feasible and that the
energy demands of Old Harbor are sufficient to utilize the
hydroelectric plant's planned capacity. The proposed project
is a more economic means of meeting the area's future electric
needs than the base case diesel alternative. - Environmental
effects of the proposed project are minor.
In view of these findings, it is recommended that actions
be initiated to implement the project.
NBI-432-9526-SOH III-7
Z-IA lIHIHX3
N
ADO
3snOHN3MOd
'R V.'d`� � { Fa' y 6, jr •T �I:� ,.�..� r.-.r^:3. jy .`S, n�+ � i Y�� 'r �.�
' •*, l�.f'.,�Y^ t tee 4%Z `� •^ ay y , f
'C'y, lYia-
r
' R
d13M NOISd3AI0
'1SV3Hinos 9NIHOOI '31IS 103f Odd 30 SVWVdOWVd
d13M NOIS83AIC
2-
3anoiA
3J,isn (INV `ONdW30 `NO11b83N30 AO33N3 AlH1NOW 03103m8d
103rO8d 0181331308CI1H 80138VH a10
VIVO lIV83AO
H1NOW
0 N 0 s V r r w v W 3 r
0661 �.►� ` 001
IOOZ /
1VI1N310d
ONVW30 % 318133130,80AH
1V318103-13 ooz
ivioi
002
�� \
OOb
61
oo5
i l es 009
\ 0OL
1 0NVW30 03N19WOO 1V101�
% J 008
_. - 006
_ 0001
m
z
m
x-
s
x
0
0
0
VIVO -1Ib130
a N 0 s d r r W v
9e1'00�`// ,
066
.00,�� % \
�100Z
1VI1N310d
318133-13060AH
(INVW30 ON11V3H
1331N Ol 318V-1IVAV
AOa3N3 3161331308CAH'
H1NOW
w q r
0
NOIlV83N39 OZ
13S310 038inO38,
/ - ob
09
08
F 001
031
(ONVA30 ONIIV3H
EJNIOf110N1 lON) Obi
V0121I33-13 133810
m
081
_. .. OOz
ozz
m
z
m
x
O
0
O
0
31VOS 01 LON
dVW AlINIOIA
3l 38 01 l
dVW NOIlVOOI
ONVISI NVIOON►
S31IWI �I I £ Z
b t7
dui 3TU8—d
� l i
\.. aebiIln Nlnos !� \
os.
b=.1:9-MS
SN01133S OVOLI SS300V / M301SN3d '1V31dAl
1105 11114301S -MTd
(dAl)
„0 ,Z ♦'aD
SWO38 ON" .1
3d1d SSVIBW38141 �,Vz
HON381 0 IdMM
0N0089 IVMOIVN
Tin O380V08 10313S
NOONO 13A31- H 3dA1
WA1)
301S H0tl3 „0-,I L
SM am ONVS.£
3dld SSY1983BId /„bZ - �—
I aNOal3S ("NIN)
1V8N1VN 111d 0380tl08103135 83A03,9
3d015 'NON381
031118NOV8
(S01V1) 111H301S-I 3dA1
ZI
,I
%Z 3dO1S
llld 0380W8103135\
(sniVl) aNO080 ltlt101tlN�\\
3d1d 9.07
83amm oNIN
.001=„ 131VOS
009 OW
OOD am OOz 001 0
,Ob=„1; 31V3S
003 OOz
091 OZI 09 at 0
,V-j:31VOS
"183A ,OV =.I
'ZI80H ,001=„I :31VOS
bz oz
91 El 9 b 0
OV08 SS333V/ N001SN3d d0 311d08d
1333 ' NOIIVIS
ZL 12 OZ 61 91 LI
91 SI el £I 21 II pl 6 B L 9 S b f
Z p
02
02
Ob
No
09
y
09
09
pe
l
o
Z
—
37ZZON)
Oa
m
`(0193
35003flO
001
\
om
011
F
Del n
'0
y
091
3
O
`
091
ooz
— N338O AVM01W
.'�
091
O
OFZ
OFF
0tl08 553301 Nb15N3H —
ozz
oez
- \
oaz
Oo£
am
02£
\�
02f
Ob£
09£
OBE
M 3dAl n 3dA1
V N0I103S
(311N ZI NOI
01
,001•„1 :31VOS
NVId
s3un1�v3Nolsa3nla-
(SOIV1 NO) I3dA1
,Oz=,1 :31vos
ozl 001 00 09 Ob oz 0
,b =„ I : 31tlos
bz oZ 91 z1 8 b 0
0-,1 £:31nS
09 9Z 02 91 01 9 0
31tlos
H N01103S-311alOHd
13A31
b=„P 3lVOS aNnON9 ONIISI%3
O N01103S— 30V8lIV1--OjLWw---
ONVA ONtl
V3NV ONINatld
Wows IV13W
031VO1N9V33ad
H0110 38VNIVNG
2 ajI
3NIl ONnoao iVNI01N0-
B
H3Stl3
a00c
alms ONj1 wn
NOW
91
31tlos
NV ld 3snOH83MOd
rd
4 V
S 3NnSS3ad
a N001SN3d
INS 3NISan1
3nl ON18V39
11SN34 0„bz
l=H10313
\\J
-•: r. NOO1SN3d O,bZ
99'13'ld _ — _ 13A31
aNnoa9 9xuSIz3
3AlIA
3301nHS 3NISWI
(311W Z 7 N000 Atl8 AtlM01W Dl oVOa
91
0-,I = F' 31tlo5
V N01103S-3lIjOHd
,OZ=,I :3ltloS
NVld�H3N39
SECTION IV
LARSEN BAY
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume D--
Feasibility Study for Larsen Bay Hydroelectric Project.
Included for easy reference are several items from that
report: Exhibit VI-1, photographs of the project area; Figure
VII-3, Projected Monthly Generation, Demand, and Usage; and
selected project drawings which include Plate I, the General
Plan, Plate III, the Penstock Plan, Profile, and Details, and
Plate V, the Powerhouse Plans and Sections. References to
figures, exhibits, and plates in the summary presented here
refer to items in Volume D, the full feasibility report for the
Larsen Bay Hydroelectric Project.
NBI-432-9526-SLB IV-1
LARSEN BAY
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying
Larsen Bay with electrical energy had recommended a hydro-
electric project as the best available source. As a direct
result of these prior studies and recommendations, the Alaska
Power Authority has authorized a feasibility study to
investigate in detail the hydropower potential in the vicinity
of Larsen Bay.
This report summarizes the activities conducted for the
feasibility study. These activities included projections of
energy needs, formulation of a hydroelectric project and an
alternative base case to meet the electrical energy needs of
Larsen Bay, detailed analyses of economic feasibility, and
preparation of an environmental assessment of the effects of
the project.
The results of the study indicate that a 270 kilowatt (kW)
hydroelectric project can be constructed at Larsen Bay, that
the project is considerably more economical than the base case
alternative, and that the environmental effects of the project
are minor.
The total cost of the proposed Larsen Bay hydroelectric
project is $2,821,400 in January 1982 dollars. The project
could be implemented and on-line by January 1, 1985, if a
decision to proceed with the project is made by December
1982. During an average water year, the proposed project would
be capable of supplying more than 85 percent of the electrical
needs and about 14 percent of the space beating needs in the
project area. The equivalent savings in diesel fuel in the
year 2001 would be about 69,000 gallons for direct electrical
demand and 16,000 gallons for space heating.
NBI-432-9526-SLB IV-2
B. AREA DESCRIPTION
The village of Larsen Bay is located near the junction of
two fjords, Larsen Bay and Uyak Bay, on the northwest coast of
Kodiak Island. Shelikof Strait, separating Kodiak Island from
the mainland, lies 14 miles to the northwest and the city of
Kodiak lies 60 miles to the east. The selected hydroelectric
power site is on Humpy Creek, a small tributary of Larsen Bay
fjord about one mile south of town. The general project area
and the proposed project site are shown on Plate I of
Appendix A.
C. POWER PLANNING
Power planning for the Larsen Bay project was conducted
using standards set forth by the Alaska Power Authority.
Previously recommended potential hydroelectric sites were
investigated and the project area was surveyed to evaluate
potential new sites. After detailed study, a project was
selected and then compared with a base case plan.
Present energy demands for Larsen Bay for direct electrical
uses and space heating were estimated and future uses in these
categories were projected. The projections were based on
forecasts of increases in the number of customers and increased
usage rates. Population growth and employment, legislation and
other political influences, life style changes, and other
factors ca❑ influence future energy demands but they were not
explicitly treated.
The period of economic evaluation used was 53 years, which
starts in January 1982 and extends for the 50-year life of the
hydroelectric project after the estimated on-line date of
January 1985. The energy demands for Larsen Bay were increased
for 20 years starting in January 1982 and extending through
NBI-432-9526-SLB IV-3
December 2001. The demands were the❑ held level over the
remainder of the economic evaluation period.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be the
direct electrical needs of Larsen Bay, and any remaining energy
would be used for space heating.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water (head) into electrical energy. Generally, a hydroelec-
tric power project consists of a dam to produce the head or to
divert stream flows so that they can be passed through a
turbine -generator system to produce electric power. In the
case of the recommended Larsen Bay Hydroelectric Project, a low
weir will act as a dam to divert water from Humpy Creek through
an inlet structure and into a penstock (conveyance pipe). The
penstock will be 27 inches in diameter and will carry the water
about 2700 feet to the powerhouse, where it will be passed
through the turbine -generator system to produce electric
energy.
The powerhouse will have the capacity to produce 270 kw of
electrical power. A transmissio❑ line will be constructed to
transmit the power generated at the plant to Larsen Bay.
Access to the powerhouse facilities will be provided by
building a short length of new road to link up with an existing
road that extends to an existing and abandoned dam near the
site of the new powerhouse. The transmission line will follow
the alignment of the new access road and the existing road to
Larsen Bay. The general plan and features of the proposed
project are presented on Plates I through VII of Appendix A.
Photographs of the project area are presented in Exhibits VI-1
through VI-4 at the end of Section VI and in the Environmental
Report, Appendix E.
NBI-432-9526-SLB IV-4
Under the recommended plan, energy generated by the hydro-
electric plant will have to be supplemented by diesel genera-
tion. Larsen Bay does not currently have a central diesel
generating plant and the plan will therefore require the
construction of diesel facilities for standby and backup
power. The hydroelectric generation will be adequate to meet
the direct electrical needs of Larsen Bay during most of the
year; however, from December through March diesel will be
needed to supplement the hydroelectric generation. A new
electrical distribution system will also be required since none
currently exists.
During an average water year the proposed hydroelectric
project will be capable of supplying more than 90 percent of
the electrical needs of Larsen Bay and approximately 20 percent
of the space heating over the life of the project.
Average annual energy production from the hydroelectric
plant will be 1.09 million kilowatt-hours (kWh) and the average
annual plant factor will be about 46 percent, which means that
the plant is expected to generate about 46 percent of the
energy that it could produce if the turbine -generator unit was
operated continuously at full capacity.
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of Larsen Bay assumed that the use of individual
existing diesel generating plants would be discontinued and a
new centralized diesel generating plant would be constructed.
Because of apparent economic benefits, it was assumed that the
proposed system would also incorporate waste heat recovery that
would be used for space heating. The possibility of installing
wind generation equipment was also considered, and was found to
be economically viable.
NBI-432-9526-SLB IV-5
It was assumed that the diesel system for the 1982 base
case would require about 51,500 gallons of fuel oil per year;
this amount was expected to increase over the next 20 years to
more than 80,000 gallons per year. Waste heat recovery was
expected to displace the use of 17,000 gallons of fuel oil per
year by the year 2001. The wind generators are expected to
displace about 12,000 gallons of oil by 2001.
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
proposed base case costs to the net present worth of the pro-
posed hydroelectric project costs using specified real price
escalation and discount rates. Net present worth is the
present value of the costs that would be incurred over a
comparable economic evaluation period of 53 years for both
projects.
The present worth of the base case only, that is, diesel
generation, is $7,532,100. If this cost is reduced by the
savings that could be realized from the installation of waste
heat recovery, the present worth is $6,725,100; further
reducing this cost by the benefit obtainable from wind
generation yields a present worth of $6,432,000. All costs
except the cost of the hydroelectric project and its diesel
supplement were considered as adjustments to the base case.
The cost of the space heating credit was added to the base case
because it represents a benefit that would not be realized if
the base case plan was implemented. The next present worth of
the base case after all adjustments is $7,348,600.
For the proposed hydroelectric project, the present worth
of the costs, is $5,941,700. A comparison of this net present
cost with the base case net present costs indicates that the
NBI-432-9526-SLB IV-6
recommended hydroelectric project is considerably more
economical than the alternative base case.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For this project, the B/C ratio for the base
case only is 1.268. The B/C ratio after adjustment for waste
heat recovery is 1.132; after additional adjustment for wind
generation, the B/C ratio is 1.067; and after all adjustments,
the B/C ratio is 1.237. These B/C ratios indicate that the
proposed hydroelectric project is highly feasible.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The environmental study results indicate that the effects
of the project will be minor due to the limited scope of the
project activities, the inability of salmon to spawn above the
old diversion dam on Humpy Creek, the abundance of alternative
areas available for trapping, hunting, and general recreation,
and the availability of measures to mitigate potential effects
from the construction and operation of the facilities. Minor
socioeconomic benefits will occur as a result of project
construction and maintenance and cheaper electric rates made
possible by the project. Additional environmental studies do
not appear to be warranted unless regulatory agencies or local
residents express additional concerns.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that the
proposed 270 kW hydroelectric project is feasible and that the
energy demands of Larsen Bay are sufficient to utilize the
hydroelectric plant's planned capacity. The proposed project
is a more economic means of meeting the area's future electric
needs than the base case diesel alternative. Environmental
effects of the proposed project are minor.
NBI-432-9526-SLB IV-7
In view of these findings, it is recommended that actions
be initiated to implement the project.
NBI-432-9526-SLB IV-8
POWERHOUSE DIVERSION WEIR
VILLAGE OF LARSEN BAY, LOOKING NORTH FROM UPPER HUMPY CREEK.
THE POWER PROJECT IS LOCATED IN THE LOWER CANYON NEAR THE
CENTER OF THE PHOTO.
EXHIBIT VI-1
200
180 HYDROELECTRIC ENERGY
AVAILABLE FOR SPACE
HEATING — — ,
WE*
140 DIRECT ELECTRICAL
DEMAND(NOT
INCLUDING HEATING
120 DEMAND)
100
l
80 / \
HYDROELECTRIC
POTENTIAL
�\ N 2001 / 1
_ V
so ` /'sso /
40 � 1986
REQUIRED DIESEL ,
20 GENERATION
v
J F M A M J J A S O N D
MONTH
DETAIL DATA
2001500
� C \
TOTAL COMBINED DEMAND
f
lk
400
`
1990
300 \j 1985
200
` I
HYDROELECTRIC
POTENTIAL —
I
TOTAL ELECTRICAL
100 DEMAND
^ \ ✓ / 1990 2001
1985
0
J F M A M J
MONTH
A S O N U
OVERALL DATA
LARSEN BAY HYDROELECTRIC PROJECT
PROJECTED MONTHLY ENERGY GENERATION, DEMAND, AND USAGE
FIGURE
�/ 1
0
M U;
'N 4 0,4F A L iY A Y IJ Iu r A K
--oo
B A Y
Cabins
Anc,e,
ca� Co
(Ab6i 'd) File z
S
L A
35
Pi
PROJECT PLAN
0 1 T 11 3 1 1 1
4 4 Iil MILES
LOCATION MAP
NOT TO WALE
VICINITY MAP
NTS
Div
FAC
ri
ALKWAY SURFACE
kEONCRET9 ENCASEMENT
HUMPY CREEK
PE 6
PENSTOCK
TOP OF ROOK
TYPE Di- CONCRETE ENCASED
PENSTOCK/ ACCESS ROAD TYPE
CONCRETE
ENCASED
ROADWAY IS STREAMSED,
EL 386.5
TT-Y�PE—IQ
TYPE I PENSTOCK INSTALLATION
TYPE I
TYPE III
TYPE II
390
+-F
Sea
370
30
350
24"(/jPENSTOC,K'
.
40
330
f
T
f 320
\
o
310300
4
HUMPY rREEK
280
J
\\
260
20
\
\\\\
240230
220
O
\
w
O
210
Q
WN
330
320
310
300
290
260
270
260
250
240
230
220
O 3 < OHOVSE 210
200 E m S O NOZZLWERE El 19S 200
ABANDONED CAN
0.00 1+00 2+00 3W0 4+00 5.00 6.00 i+00 9+00 9.00 10+00 Ib00 12.00 13+00 14.00 I6+00 AHON 17+00 16+00 19`00 20+00 21+00 22+00 23400 24+00 25+00 26+00 2N00 2W00 29W0
STATIONING FT NOTE- MEAN SEALEVEL ELEVATION = IOOft 3 SITE DATUM
PROFILE OF PENSTOCK/ACCESS ROAD
RING GIRDER SCALE • 1' • 100' HORIZ.
I"• 20' VERT.
27"/ STEEL PIPE
RING GIRDER 12,
1 `�� NATURAL GROUND (ROCK) ` 12' SELECT ROADBED FILL
IX2ESSER �� BACKFILLED
COOPLING SELECT ROADBED FILL TRENCH SLOPE 2% _
�— SLOPE 25L IS
NATURNATURGROUND
SLOPE �2% 3'COVER F3"MAND
ROADBED FILL NATURAL 1
(MIN.) GROUND(SOIL) 31 COVERu• ., v✓
I' (MIT BACKFILLED TRENCH
WBERGLASS PIPE i 2T"/ FIBERGLASS PIPE
TOPOF ROCK Jl TOP OF ROCKA BEDDING
SECTION q 12' ---i I
1 EACH SIDE " SAND REDOING
�- '-O(
ITYP) i
TYPE I- SIDEHILL (ROCK) TYPE II - LEVEL GROUND O.D..2'-O" TYPE IQ- SIDEHILL (SOIL)
(TYP)
TYPICAL PENSTOCK / ACCESS ROAD SECTIONS 0 4 B 12 16 20 24
SCALE; 1'"4' SCALE: 1"• 4'
_...ANCHOR BLOC �A BEARING LUBRICATION SET
TOO . \ \ PRESSURE SET
Pp \
_\ r
GOVERNOR
27"DIA. PENSTOCK Y� `' �-.
In B
M1
TURBINE SHUTOFF VALVE I —
\ 1 ---- TURBINE 6"DIA PENSTOCK GRAIN �-_-- -_
TAILRACE
ABANDONED DAM ELECTRICAL SWITCHGEAR
\ SPEED INCREASER
FLYWHEEL
PE STOCK I FLOOR EL 192 GENERATOR
ABANDONED WOOD STAVE 111
PENSTOCK
K EQUIPMENT MOUNTING SKID
1
m\\ PERSONNEL DOOR
I y
I OW RN U I•f \\ ''•GA T
I \�\ ~ EQUIPMENT DOOR J LA
SWITCHYARD PARKING AREA
I I I I I-
\ 1 1 I I I I c�-'•
-
/J I r r l I / r PLAN
ry / ACCESS I • A
ROAD 1 / SCALES 6• I�0
N A
CONCRETE MAT FOR
/ •� •\ CREEK CROSSING
CONSTRUCTION/ACCESS ROAD
�o TRANSMISSION LINE
GENERAL PLAN
SCALE- I"-20'
TURBINE SPEED INCREASER GENERATOR TURBINE-
TURBINE -
ANCHOR BLOCK
TURBINE SHUTOFF VALVE PREFABRICATED
METAL BUILDING
a
H1
EQUIPMENT MOUNTI G 7LPARKING AREA
SKID _
SELECT MATERIAL
NATURAL GROUND
y!. TAILRACE TAILRACE SLOPE
STATE OF ALASKA
ALASKA POWER AUTHORITY
ANCHORAGE,ALASKA
PROFILE— SECTION A PROFILE— SECTION B 0 3 10 13 20 26 30
SCALE! 16•I'—O SCALE+3•• LARSEN BAY HYDROELECTRIC PROJECT
0
16 SCALE 16 I'-p
POWERHOUSE -PLANS AND SECTIONS
0 20 40 60 Bo 100 120
SCALE1"- 20'-0 00W1_ ENGINEERS TUDOR ENGINEERING COMPANY
ANCHORAGE, ALASKA SAN FRANCISCO, CALIFORNIA
PLATE V
SECTION V
TOGIAK
SUMMARY
INTRODUCTORY NOTE:
Presented in this section is the Summary from Volume E--
Reconnaissance Study for Togiak Hydroelectric Project. Included
for general background information are several items from that
report: Exhibit VI-1, Photographs of the Project Area; Figure
VII-4, Projected Monthly Generation, Demand, and Usage; and
selected project drawings which include Plate I, the General
Plan, and Plate II, Alternative A - Plans and Sections.
References to figures, exhibits, and plates in the summary
presented here refer to items in Volume E, the full feasibility
report for the Togiak Hydroelectric Project'.
NBI-432-9526-ST V-1
TOGIAK
SUMMARY
A. GENERAL
Several prior studies of alternative means of supplying the
Togiak area with electrical energy had recommended a hydroelec-
tric project as the best source. As a direct result of these
prior studies and recommendations, the Alaska Power Authority
authorized a reconnaissance -level feasibility study to investi-
gate in detail the hydropower potential in the vicinity of
Togiak.
This report summarizes the activities conducted for the
reconnaissance study. These activities included projections of
energy needs, formulation of alternative hydroelectric projects
and a hypothetical base case to meet the electrical energy
needs of Togiak, detailed analyses of economic feasibility, and
preparation of an environmental assessment of the effects of
the project.
The results of the technical studies conducted indicate
that a 432 kilowatt (kW) hydroelectric project utilizing a 38-
foot-high concrete dam could be constructed on the Quigmy River
to meet the electric demands of Togiak. However, the results
of the economic analyses indicate that the hydroelectric
project would have only marginal feasibility. An additional
project on the Kurtluk River is currently under investigation.
The results of this investigtion will be presented in a
subsequent report.
The total cost of the proposed Togiak hydroelectric project
is $7,047,200 with the 4.6-mile road option and $8,169,600 with
the 11.6-mile road in January 1982 dollars. The project could
be implemented and on-line by January 1, 1985, if a decisio❑ to
NBI-432-9526-ST V-2
proceed with the project is made by December 1982. During an
average water year, the proposed project would be capable of
supplying about 99 percent of the electrical needs and about 30
percent of the space heating needs in the project area. The
equivalent savings in diesel fuel in the year 2001 would be
144,000 gallons for direct electrical demand and 44,000 gallons
for space heating.
B. AREA DESCRIPTION
Togiak is a small village located on Bristol Bay about 70
miles west of Dillingham and 400 miles southwest of
Anchorage. The hydroelectric site selected for detailed study
is on the Quigmy River about 12 miles west of Togiak. The
smaller village of Twin Hills, four miles east of Togiak, was
included i❑ the assessment of the future power needs of the
area.
C. POWER PLANNING
Power planning for the Togiak Project was conducted using
standards set forth by the Alaska Power Authority. Previously
recommended potential hydroelectric sites were investigated and
the project area was surveyed to evaluate potential new
sites. After detailed study, a project was selected and then
compared with a base case plan. The base case pla❑ consisted
of a continuation of the present diesel generatio❑ system,
enlarged as necessary to meet future growth. The installation
of waste heat recovery equipment and wind generators was also
considered as part of the base case plan.
Present energy demands for Togiak for direct electrical
uses and space heating were estimated and future uses in these
same categories were projected. The projections were based on
forecasts of increases i❑ the number of customers and increased
usage rates. Population growth and employment, legislation and
NBI-432-9526-ST V-3
other political influences, life style changes, and other
factors can influence future energy demands but were not
explicitly treated.
The period of economic evaluation used was 53 years, which
starts in January 1982 and extends for the 50-year life of the
hydroelectric project after the estimated on-line date of
January 1985. The energy demands for Togiak were increased for
20 years starting in 1982 and extending through December
2001. The demands were then held level over the remainder of
the economic evaluation period. As stated, the neighboring
community of Twin Hills was included in estimating future
energy demands.
For the proposed hydroelectric project, it was assumed that
the first priority of use for the energy produced would be for
the direct electrical needs of the Togiak area, and any remain-
ing energy would be used for space heating.
D. DESCRIPTION OF RECOMMENDED HYDROELECTRIC PROJECT
Hydroelectric power plants transform the energy of falling
water into electrical energy. Generally, a hydroelectric power
project consists of a dam to produce the head or to divert
stream flows so that they can be passed through a turbine -
generator system to produce electric power. In the case of the
alternative projects considered to bring hydroelectric power to
Togiak, three dam configurations and two access road options
were evaluated. These are described below. All three of the
dams considered would divert water from the Quigmy River
through an intake structure and pass the water through a tur-
bine -generator system to produce electric energy. An access
road would be constructed from Togiak to the project facilities
and a transmission line would be constructed along the access
road alignment to transmit the power generated at the plant to
Togiak.
NBI-432-9526-ST V-4
The general plan and features of the recommended hydroelec-
tric project are presented in the plates of Appendix A. Photo-
graphs of the project area are presented in Exhibits VI-1
through VI-3 of Section VI and in pages 2, 10, and 15 of
Appendix E.
The site selected for investigation was a narrow canyon
suitable for either a concrete or rockfill dam. Since both
types were apparently technically feasible, two concrete dams
(38 and 28 feet high) and one rockfill dam were investigated to
evaluate their economic feasibility and confirm their technical
feasibility. Although the Quigmy River above the proposed dam
site locations might not be a major spawning area, the
preliminary designs for all three dam alternatives incorporated
fish ladders to allow for fish passage.
An 11.6-mile road would be required to provide access from
Togiak to the proposed facilities. The Alaska State Department
of Transportation and Public Facilities, Division of Aviation,
is investigating the possibility of building a road along the
first seven miles of the proposed access road alignment in
order to reach a gravel source needed to construct an airport
to serve Togiak. Two possibilities exist for obtaining an
access road for the proposed hydroelectric project:
1. The entire 11.6-mile road would be built as part of
the hydroelectric project.
2. The Alaska Department of Transportation would build
the first seven miles of the road and the hydroelec-
tric project would build the remaining 4.6 miles.
The investigations conducted during this study indicate
that the most favorable combination, and indeed the only one
that could be economically feasible, is the 38-foot-high
concrete dam with only 4.6 miles of the access road being
funded by the project.
NBI-432-9526-ST V-5
E. BASE CASE PLAN
The base case plan formulated to meet the projected energy
demands of Togiak assumed that the existing diesel system would
continue to be used as the sole source of electric power. It
was also assumed that the system would be modified to incorpor-
ate waste heat recovery that would be used for space heating.
Wind generation would also be installed as part of this plan.
The existing diesel plant's capacity was judged to be adequate
to meet peak demands on the Togiak system throughout the period
of study. The forecasted energy demands for the base case
included the requirements for Twin Hills.
F. ECONOMIC ANALYSIS
The economic analysis was based on the Alaska Power
Authority criteria that compare the net present worth of the
base case costs to the net present worth of the alternative
proposed hydroelectric project costs using specified real price
escalation and discount rates. Net present worth is the
present value of the costs that would be incurred over a
comparable economic evaluation period of 53 years for both
projects.
The net present worths of the base case are as follows:
Base Case Only
Waste Heat Credit
Subtotal
Wind Energy Credit
Subtotal
Space Heating Credit
Total
Alternatives A & C
$11,027,600
999,400
10,028,200
540,700
9,487,500
2,463,000
$11,950,500
NBI-432-9526-ST V-6
Alternative B
-.$111027,600
999,400
10,028,200
540,700
9,4879500
1 234,800
17221,300
I
The space heating credit was shown as an increase in cost
to the base case so that all present worths could be compared
to the hydroelectric project standing alone.
For the three alternative hydroelectric projects studied,
the present worth of the costs is as follows:
Alternative A
Alternative B
Alternative C
W/11.6-Mile ,Road
$12,758,400
13,037,400
13,257,700
W/4.6-Mile Road
$11,668,600
11,947,600
12,167,900
As can be noted from the table, the only hydroelectric
alternative with a lower present worth cost than the base case
is alternative A, and then only if the 4.6-mile roadway can be
constructed.
An additional measure of project feasibility is the bene-
fit/cost (B/C) ratio. The B/C ratio is the present worth of
the project benefits divided by the net present worth of the
project costs. For the alternative studies for this project,
the calculated B/C ratios were as follows:
B/C Ratio B/C Ratio
W/11,6-Mile Road W/4.6-Mile Road
Alternative
A
0.937
1.024
Alternative
B
0.822
0.897
Alternative
C
0.982
_. 0.901
NBI-432-9526-ST V-7
These results indicate that Alternative A, the 38-foot-high
concrete dam with 432 kW installed capacity, is marginally
feasibile only if the Alaska Department of Transportation con-
structs the first 7.0 miles of the required 11.6-mile access
road. If the entire 11.6-mile road must be constructed, the
project is a break-even proposition.
G. ENVIRONMENTAL AND SOCIAL EFFECTS
The study results indicate that a hydroelectric project at
the Quigmy site could have potentially serious environmental
impacts, but measures such as fish ladders could likely miti-
gate the most serious effects. Additional studies are recom-
mended to answer questions related to the downstream effects of
the dam impoundment on salmon spawning; coho (silver) salmon
runs; minimum water requirements for fish below the proposed
dam; selection of a suitable access route; and methods to
ensure safe passage of out -migrating young salmon. Additional
study of fish passage facilities is also recommended.
H. CONCLUSIONS AND RECOMMENDATIONS
The studies conducted for this report indicate that a
marginally feasible project consisting of a 38-foot-high
concrete dam with 432 kW installed capacity could be con-
structed at the Quigmy River site. The next step in project
implementation, the preparation of a Definitive Project Report
to optimize the project features, should be pursued only if the
Alaska Department of Transportation constructs the initial 7.0
miles of the necessary 11.6-mile-long access road.
A more detailed investigation of a much smaller hydroelec-
tric site on the Kurtluk River three miles from Togiak could be
pursued, but the project would meet only a small portion of the
Togiak electric demands. The site is currently being investi-
gated at a preliminary level and will be addressed in a
subsequent letter report.
NBI-432-9526-ST V-8
5
TOGIAKIS QUIGMY RIVER DAM SITE: AIR PHOTO LOOKING UPSTREAM.
THE DAM AXIS IS ACROSS THE NARROW CHANNEL IN CENTER OF THE
PHOTO,
_ EXHIBIT VI-1
TOGIAK HYDROELECTRIC PROJECT
PROJECTED MONTHLY ENERGY GENERATION, DEMAND, AND USAGE
INSTALLED CAPACITY = 432 kW
FIGURE
M-4
BORROW SV7E
`TOGIAK $ ,
K
~ � PROPOSED ACCESS ROAD PROPOSEEXISTING ROAD RA ANDSMI CANNERY : TWIN HILLS
-' - AND TRANSMISSION LINE PROPOSED TRANSMISSION LINE � x.
/ �r
T O G/ A K B A Y
PROJECT PLAN
LOCATION MAP
NOT TO SCALE
VICINITY MAP
NOT TO SCALE
0 z
MILES
I
i TOCK
OE
SWI RD
PARKING
AREA
El
FLOW
\l SPILLWAY
200
ETE GRAVITY SLOCK6 \
GENERAL PLAN
SCALE 0- 20
SHUT-OFF
q26
DVERHAN 1�1 -
REM_
-1.31----FISH LADDER
A \
TUR6INE CONTROL PANELS
Ililllllllll
POWERHOUSE PLAN
NTS
B
INCREASER
GROUND
o FLOOD
--
o RES. E
STR€AMSED-f L. I70 _ _
SECTION A
SCALE • 1"• 10'
SECTION B
SCALE - I" - 10'
0 10 20 30 40 SO 60
SC LE I .. 10
0 20 40 60 SO 100 120
SCALE - I- • 2d