HomeMy WebLinkAboutIndian River Phase II Final Report 2011INDIAN RIVER HYDROELECTRIC PROJECT PHASE II FINAL REPORT CONCEPTUAL DESIGN AND PERMITTING NOVEMBER 2011 Prepared For CITY OF TENAKEE SPRINGS P.O. Box 52 TENAKEE SPRINGS, ALASKA 99841 Prepared by POLARCONSULT ALASKA, INC. 1503 WEST 33RD AVENUE, SuiTE 310 ANCHORAGE, AlAsKA 99503 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report EXECUTIVE SUMMARY Polarconsuk Alaska, lnc.G This report summarizes activities performed in accordance with AEA grant agreement #2195348, awarded to the City of Tenakee Springs, Alaska (City) by the Alaska Energy Authority (AEA) in 2008. The grant budget included $100,000 in Denali Commission grant funds administered by AEA and $25,000 in matching funds provided by the City. The work conducted under the grant was organized into two phases. Phase I was a feasibility study of the proposed hydroelectric project on Indian River, completed in December 2009. Phase II advanced the conceptual design for the project and project permit activities. This report summarizes conceptual design and permit work completed under Phase II of the grant. The current conceptual design for the hydroelectric project is tabulated below. Conceptual design plans are included in the Appendix to this report. INDIAN RIVER HYDROELECTRIC PROJECT SUMMARY Static Head Design Flow Penstock Total Dynamic Head Turbine Type Installed Capacity Plant Capacity Factor Estimated Annual Hydroelectric Energy Generation Existing Typical Annual Utility Energy Demand Percent of Utility Load Supplied by Hydro Transmission Estimated Pre-Construction Costs Estimated Direct Construction Cost Estimated Construction Engineering, Administration, Management Contingency (15%) Estimated Total Installed Cost Annual Displaced Diesel Fuel for Utility Continuing Annual Diesel Consumption for Electrical Generation Annual Displaced Fuel for Heating Applications Net Present Value of Displaced Fuel & Project Benefits Net Present Value of Project Capital and Annual Costs Benefit -Cost Ratio Calculated with 2011 AEA Renewable Energy Financial Model November 2011 -Final Report 63 feet 50 cubic feet per second 1,534' of 36" Pipe 56 feet Cross-flow Turbine 180kW 76.2% 1,169,000 kWh 433,000 kWh 86.2% 4,014 feet of Three-phase 7.2kV buried cable $ 354,000 $2,560,000 s 320,000 $ 349,000 $3,583,000 31,400 gallons 3,500 gallons 6,500 gallons $5,200,000 $2,950,000 1.76 City of Tenakee Springs Indian River Hydroelectric Project . Feasibility, Conceptual Design, and Permitting Phase II Final R<>ronrt Polarconsult Inc. G Major permit applications for the project were filed in August 2010, and all major permits are currently being processed. The current issuance and/or processing status of major permits for the project are tabulated below. INDIAN RIVER HYDROELECTRIC PROJECT PERMITIING STATUS Permit I Decision Jurisdictional Determination Federal Energy Regulatory Commission Wetlands Permit U.S. Army Corps of Engineers Land Lease Alaska Dept. of Natural Resources Easements Alaska Dept. of Natural Resources Water Rights Alaska Dept. of Natural Resources Coastal Zone Consistency Determination Alaska Dept. of Natural Resources Fish Habitat Permit Alaska Dept. of Fish and Game Coordination, Road Use Permit U.S. Forest Service Status FERC has ruled that the project is Non- Jurisdictional Application filed 8/2010, multiple supplemental submittals to clarify project. Permit will be Nationwide Permit #17 for Hydropower Projects Application filed 8/2010. ADNR ruled leases not needed for this project Application filed 8/2010. ADNR Case #ADL 108047. Conceptual design is under review. Application filed 8/2010. ADNR Case LAS #27836. Conceptual design is under review, waiting for coordination with Fish and Game. Application filed 8/2010. Coastal Management Program has been terminated, no longer applicable. Application filed 8/2010. Conceptual design is under review. Conceptual design is under review. Coordinating with USFS on plans to put Indian River Road into long-term storage and on design of intake to enhance performance of fish pass structure at intake site. Schedule FERC Order Issued May 26,2010 Expected Issuance December 2011 Expected issuance in 2012 Expected issuance in 2012 Expected issuance in 2012 Expected issuance in 2012 Conceptual designs and permitting activity have been successfully completed under Phase II of the current grant. AEA is authorized to award the City funding to complete the design and permitting phases of this project under Round IV of the state's Renewable Energy Grant Program. These funds will allow the completion of design and permitting for the project. Construction is expected to occur in the summer of 2013 or 2014, contingent upon the City securing construction funds. November 2011 -Final Report II City of Tenakee Springs Polarconsult Alaska, Inc. G Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final w~r•nr1' TABLE OF CONTENTS EXECUTIVE SUMMARY ........................................................................................................... I TABLE OF CONTENTS ............................................................................................................ Ill ACRONYMS AND TERMINOLOGY .......................................................................................... IV 1.0 INTRODUCTION .......................................................................................................... ! 2.0 2.1 2.2 2.3 3.0 3.1 3.2 REVIEW OF PHASE I TASKS .......................................................................................... ! GRANT TASK 1: GRANT AND PROJECT ADMINISTRATION ............................................................. 1 GRANT TASK 2: PHASE I FIELD WORK ..................................................................................... 1 GRANT TASK 3: FEASIBILITY STUDY REPORT .............................................................................. 1 PHASE II TASKS ........................................................................................................... 2 GRANT TASK 4: CONCEPTUAL DESIGN ..................................................................................... 2 GRANT TASK 5: LIDAR SURVEY OF PROJECT AREA ..................................................................... 2 3.3 GRANT TASK 6: STAKEHOLDER MEETING AND PERMIT APPLICATIONS ............................................ 2 3.4 GRANT TASK 7: ADVANCE PROJEG PERMITS ............................................................................ 3 3.4.1 Federal Energy Regulatory Commission (FERC) Jurisdictional Determination ........................ 3 3.4.2 U.S. Army Corps of Engineers Permit Application & Permitting .............................................. 3 3.4.3 ADNR Land Lease Permit App!ication ...................................................................................... 4 3.4.4 ADNR Easement Application ................................................................................................... 4 3.4.5 ADNR Coastal Project Questionnaire ....................................................................................... 4 3.4.6 Water Rights Permit App/ication ............................................................................................. 5 3.4. 7 ADFG Fish Habitat Permit Application ..................................................................................... 5 3.4.8 USFS Coordination ................................................................................................................... 5 3.5 GRANT TASK 8: PHASE II FINAL REPORT .................................................................................. 6 4.0 CONCLUSIONS ............................................................................................................ 6 November 2011 -Final Report Ill City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final w ... r,nrT PolarconsuH Alaska, Inc. G. ADEC ADFG ADNR AEA cfs COE City DCOM FERC ft FY HOPE in kV kW kWh LIDAR mi MW ACRONYMS AND TERMINOLOGY Alaska Department of Environmental Conservation Alaska Department of Fish and Game Alaska Department of Natural Resources Alaska Energy Authority cubic feet per second U.S. Army Corps of Engineers City of Tenakee Springs Division of Coastal and Ocean Management (under ADNR) Federal Energy Regulatory Commission foot, feet fiscal year high-density polyethylene inch, inches kilovolt, or 1,000 volts kilowatt, or 1,000 watts. One kW is the power consumed by ten 100-watt incandescent light bulbs. kilowatt-hour. The quantity of energy equal to one kilowatt (kW) expended for one hour. Light Detection and Ranging mile, miles megawatt, or 1,000 kilowatts Plant capacity factor The amount of energy a power plant actually produces divided by the amount of energy the plant would produce if it operated at full output 100% of the time. Polarconsult Polarconsult Alaska, Inc. RFP request for proposals USFS U.S. Forest Service USGS U.S. Geological Survey November 2011 -Final Report IV City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final uaronrt- 1.0 INTRODUCTION Polarconsult Alaska, Inc. 6 This report summarizes activities performed in accordance with grant agreement #2195348, awarded to the City of Tenakee Springs, Alaska (City) by the Alaska Energy Authority (AEA) in 2008. The grant budget includes $100,000 in Denali Commission grant funds administered by AEA and $25,000 in matching funds provided by the City. The work conducted under the grant was organized into two phases. Phase I was a feasibility study of the proposed hydroelectric project on Indian River, and Phase II advanced conceptual design and permitting of the project. The City contracted with Polarconsult Alaska, Inc. (Polarconsult) in April 2009 to complete the authorized work items under the grant. The Phase I Feasibility Study of the project was successfully completed in November 2009. Phase II conceptual design and permitting activities were successfully conducted in 2010 and 2011. This report summarizes the Phase II activities completed under Phase II of the grant. Phase II deliverables are included in the report appendices. 2.0 REVIEW OF PHASE I TASKS 2.1 GRANT TASK 1: GRANT AND PROJECT ADMINISTRATION The City was responsible for grant and project administration. The City's Project Manager, Mr. Art Bloom, successfully coordinated all management functions for the grant. This grant task required grant administration, project coordination, grant reporting, bookkeeping, and accounting. The deliverable required of this grant task is the quarterly reports that have been submitted to AEA. 2.2 GRANT TASK 2: PHASE I FIELD WORK A field trip was completed in June 2009 under Phase I of the project. The purpose and accomplishments of the field trip are described in the Feasibility Study Report. 2.3 GRANT TASK 3: FEASIBILITY STUDY REPORT A draft of the Indian River Hydroelectric Feasibility Study prepared by Polarconsult was issued to the City and AEA for review and comment in September 2009. The Indian River Hydroelectric Feasibility Study Final Report, incorporating comments from the City and AEA, was issued in November 2009. November 2011 -Final Report 1 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report Polarconsuk Alaska, Inc. G 3.0 PHASE II TASKS 3.1 GRANT TASK 4: CONCEPTUAL DESIGN Polarconsult completed two conceptual designs for the project. The July 29, 2011 conceptual design plans are the current plans for the project. Half-size prints of both conceptual design plans are included in Appendix A. Please use the graphical scales on these plans. A cost estimate for the July 29, 2011 conceptual design is also included in Appendix A. » The first conceptual design was issued April 11, 2011. This conceptual design proposed construction of a bench along the east side of Indian River Canyon to provide access to the powerhouse site and for siting of the penstock. Based upon field assessment of the conceptual design alignments and site conditions in April 2011, this conceptual design was judged to be problematic for technical, environmental and cost reasons. » A second conceptual design was developed and issued July 29, 2011. This conceptual design minimized benching within Indian River Canyon. Construction access to the powerhouse is provided by a steep grade suitable for tracked equipment or winch operations, and the penstock was moved to the toe of the canyon and supported on trestles. Also, the power line alignment was moved to begin at the end of the City's existing electric system at the harbor, instead of at the end of existing three phase distribution approximately X mile to the west. 3.2 GRANT TASK 5: LIDAR SURVEY OF PROJECT AREA A Light Detection and Ranging {LIDAR) survey of the project area was performed to support Phase II conceptual design and permitting activities. Aero-METRIC, Inc. was contracted to perform the LIDAR survey in March 2010, and the data acquisition was completed in late April 2010. The LIDAR deliverables were provided to Polarconsult in June 2010. The LIDAR survey deliverables include: » Two-foot contour map of the project area » Black and white visible band intensity image of the project area These deliverables were used in development of the conceptual designs for the project and were also used in environmental analysis and permitting activities. A two-contour map and an intensity map of the project area are included in Appendix B. 3.3 GRANT TASK 6: STAKEHOLDER MEETING AND PERMIT APPLICATIONS A Declaration of Intention was filed with the Federal Energy Regulatory Commission {FERC) on February 26, 2010 to determine the jurisdictional status of the project. A stakeholder meeting was held in Juneau, Alaska on March 10, 2010. This meeting was convened during the thirty- November 2011 -Final Report 2 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Polar consult Alaska, Inc. G day public comment period for the FERC Declaration of Intention to insure stakeholders were aware of the project and solicit comment on the project. The meeting was attended by personnel representing most of the key permitting agencies involved in the project. An attendee list, meeting minutes, and copy of the meeting packet are included in Appendix C. Applications for major permits needed for the project were prepared and submitted in August 2010. The following applications were submitted: Y FERC Declaration of Intention; Y U.S. Army Corps of Engineers (COE) permit application; Y Alaska Department of Natural Resources (ADNR) land lease application; Y ADNR easement application; Y ADNR Coastal Project Questionnaire for Coastal Zone Consistency Review; Y ADNR Water Rights Application; and Y Alaska Department of Fish and Game (ADFG) Fish Habitat Application. Additionally, the project will require coordination with the U.S. Forest Service for use of Indian River Road for construction access and long term operations. Copies of these permit applications are included in Appendix D. 3.4 GRANT TASK 7: ADVANCE PROJECT PERMITS The current status of the review and issuance process for the major project permits is summarized in this section. Copies of the permit applications and relevant correspondence with the permitting agencies are included in Appendix D. 3.4.1 Federal Energy Regulatory Commission (FERC) Jurisdictional Determination A Declaration of Intention for the project was prepared and filed with the FERC on February 26, 2010. The FERC issued a finding of Non-Jurisdiction for the project on May 26, 2010. Documents included in Appendix D are listed below. 'Y Declaration of Intention (February 26, 2010) 'Y Finding of Non-Jurisdiction (May 26, 2010) 3.4.2 U.S. Army Corps of Engineers Permit Application & Permitting A wetlands permit application was submitted to the COE on August 31, 2010. In response to COE comments and questions, supplemental information was submitted to the COE in November 2010 and August 2011. Ms. linda Speerstra with the COE also attended a visit to the project site on April 21, 2011. The COE has been provided with all information needed to proceed with review and issuance of a wetlands permit for the project, and a permit is expected before the end of 2011. Documents included in Appendix D are listed below. November 2011 -Final Report 3 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report ";;-COE permit application (August 31, 2010) ";;-COE questions (September 14, 2010) ";;-Supplemental information submittal #1 (November 4, 2010) ";;-COE questions (December 17, 2010) ";;-Supplemental information submittal #2 (August 9, 2011) ";;-COE questions (August 29, 2011) 3.4.3 ADNR Land Lease Permit Application Polarconsult Alaska, Inc. 4 A land lease application was submitted to ADNR on August 31, 2010 for the intake and powerhouse sites. ADNR notified Polarconsult by email on September 14, 2010 that use of all state lands for the project will be authorized under a public easement (ADL 108047). Accordingly, the land lease application has been canceled and a lease of state land will not be required for the project. Documents included in Appendix Dare listed below. ";;-Lease Application (August 31, 2010) ";;-ADNR Email regarding lease (September 14, 2010) 3.4.4 ADNR Easement Application An easement application was submitted to ADNR on August 31, 2010 for easements for the access roads, penstock alignment, and power line alignments. ADNR notified Polarconsult by email on September 14, 2010 that use of all state lands for the project will be handled under a public easement, and assigned the easement application to case ADL 108047. Polarconsult submitted the July 29, 2011 conceptual design drawings to ADNR on September 1, 2011 and requested ADNR to proceed with processing the easement. Documents included in Appendix Dare listed below. ";;-ADNR Easement Application (August 31, 2010) ";;-Transmittal of 7/29/11 Conceptual Design Plans to ADNR (September 1, 2011) 3.4.5 ADNR Coastal Project Questionnaire A Coastal Project Questionnaire was submitted to ADNR's Division of Coastal and Ocean Management (DCOM) on August 31, 2010. Processing of the questionnaire and making a consistency determination has been waiting for completion of the COE permit application. Ms. Jill Taylor with DCOM attended a visit to the project site on April 21, 2011. Legislative action ended Alaska's Coastal Management Program effective June 30, 2011, so the consistency determination is no longer required. November 2011 -Final Report 4 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Polarconsult Alaska,lnc.G Documents included in Appendix Dare listed below. );-ADNR-DCOM Coastal Project Questionnaire (August 31, 2010) );-Email notice from Jill Taylor of program termination (June 29, 2011) 3.4.6 Water Rights Permit Application A water rights application was submitted to ADNR on August 31, 2010. The application was assigned LAS 27836 in October 2010. Current action is awaiting coordination with ADFG. Documents included in Appendix D are listed below. );-ADNR Water Rights Application (August 31, 2010) );-Confirmation of LAS# for Rights Application (October 4, 2010) 3.4.7 ADFG Fish Habitat Permit Application A fish habitat permit application was submitted to ADFG on August 31, 2010. The July 29, 2011 conceptual design drawings were submitted to ADFG on September 14, 2011 to allow ADFG to review the project and issue a fish habitat permit. Documents included in Appendix D are listed below. );-ADFG Fish Habitat Permit Application (August 31, 2010) );-Conceptual Design submittal (September 14, 2011) 3.4.8 USFS Coordination The USFS issued a Request For Proposals (RFP) in July 2011 to put Indian River Road into long term storage in 2012, which includes removing the culverts and log bridges from the 1.3 miles of Indian River Road needed to access the project site. The City reminded the USFS of the hydro project by email and letter in August 2011, and clarified that maintaining the road in a serviceable condition for heavy equipment traffic is necessary for construction and long-term maintenance of the hydro project. The USFS has indicated that they are amenable to modifying their RFP to accommodate the needs of the hydro project, and the City is working with the USFS on arrangements for long-term maintenance of the 1.3 miles of Indian River Road necessary for hydro project access. Documents included in Appendix Dare listed below. );-Letter to USFS from Polarconsult on behalf of City clarifying intended use of Indian River Road for hydro project (August 31, 2011) );-Excerpt of USFS RFP for Indian River Road Storage Project (July 29, 2011) November 2011 -Final Report 5 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report 3.5 GRANT TASK 8: PHASE II FINAL REPORT Polarconsult Alaska, Inc. G This document is the Phase II Final Report. AEA's review comments of the September 2011 draft of this report are included in Appendix E. Review comments have been incorporated into this report as described in Appendix E. 4.0 CONCLUSIONS All Phase II grant tasks have been successfully completed. All major permits are in place, and permit applications are being processed by resource agencies. AEA is authorized to award the City funds from the Renewable Energy Grant Program that will enable completion of permitting and final design for the project. Once these activities are completed and construction funds are secured, the project will be ready for construction. Provided that the City is able to obtain funding, construction is expected to occur in the summer of 2013 or 2014. November 2011 -Final Report 6 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report G Polarconsult Alaska, Inc. APPENDIX A-CONCEPTUAL DESIGN • Current Project Cost Estimate • July 29, 2011 (Release #2-CURRENT) • April11, 2011 (Release #1-Superceded) November 2011 -Final Report APPENDIX A City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report a ~ Polarconsult Alaska, Inc. The cost estimate presented in the 2009 Feasibility Study has been updated to reflect the more advanced conceptual design that has been developed for the project. The conceptual design was developed using the detailed UDAR topographic data. TENAKEE SPRINGS HYDROELECTRIC PROJECT CONCEPTUAL DESIGN COST ESTIMATE PRE-CONSTRUCTION COSTS (Feasibility Study, Engineering Design, Studies, Permitting, etc.) DIRECT CONSTRUCTION COSTS Transmission Line Access Trails/Roads Diversion /Intake Structure Penstock Trestle I Alignment Prep Penstock Powerhouse Equipment Shipping SUBTOTAL DIRECT CONSTRUCTION COSTS Construction Management & Administration Construction Engineering & Inspection Construction Contigency ( 15%) ESTIMATED TOTAL INSTALLED COST November 2011 -Final Report $354,000 $238,000 $433,000 $205,000 $444,000 $370,000 $512,000 $161,000 $197,000 $2,560,000 $160,000 $160,000 $349,000 $3,583,000 APPENDIX A ~ NOME \, BARROW ... I~~~ ~ ©DlJV @[? lf~~&~~~ ~[;)[]30~@~ ~CSB©1f[]30© ODVDCSDUU [Q)~~&[]3U~B~l1 LJ[3~&~[3 ~~~0~@~~ &[1&~~& SHEET INDEX CO. 1 PROJECT SCOPE, SI'EOFICATIONS, SURVEY CONTROL C3.3 ReSERVED C0.2 BEACH lANCING SITES C4.1 RfSERVED f":t-· ,- FAIRBANKS Cl.l ACaSS ROAD PlAN & PROFILE C1.2 ACCESS ROAD PlAN & PROFILE C1.3 ACCESS ROAD PlAN & PROFILf C5.1 POWERHOUSE PlAN, ELEVATl()NS, & SECTIONS El.l TRANSMISSION UNE PlAN & PROFILE I·~· "" .~ lk -. •, ~ . ?"r. ,.. ...... C2.1 INTAKE SITE PlAN, ELEVATl()NS & SECTIONS C3.1 PENSTOCK PlAN & PROFILE El.2 TRANSMISSION UNE PlAN & PROFILE E1.3 TRANSMISSION UNE PlAN & PROFilE C3.2 PENSTOCK PlAN & PROFILE polarconsult alaska, inc. ENGINEERS • PLANNERS • ENERGY CONSULTANTS 503 WEST J3RD AVE, SUITE 310 ANCHORAGE, ALASKA 99503 PHONE FAX 258-2420 2::08·241 CI1Y OF TENAKEE SPRINGS THIS PROJECT PENSTOCK STATE LO ON MAP (SHEETS C3.1-C3.2) PLANT DATA DIVERSION SPILLWAY ELEVATION 1 245 fEU HEADWATER ElfVA fiON .0 FEET POWERHOUSF FINISH FLOOR ElEVA 110N 65.4 FEU TAIL WATER ElEVATION 58.0 FEET PI ANT GROSS HEAD 63.0 FEET DESIGN FLOW -----.. ------~··--50 Cf'S 7 FlOW HEAD LOSS FULL FLOW DYNAMIC HEAD ·---~6 FEU 36" ¢ PENSTOCK --~···-----1,534 FEET RATED POWER OUTPUT 180 kW Dl POWER SECTION 16 SECTION 2T . --. -. - BEACH LANDING SITE (SHEET C0.2) NNECTION EXISTIN ELECTRIC M I IPOWERH~US~ I(SHEET C5.1) I POWER LINE (SHEETp E1.1-E1.3) . ...._ TENAK PROJECT LOCATION MAP AND _$HEET INDEX +-~----------~---·- TRAI BEACH LA / NDING SITE (SHEET C0.2 ) COPPER RIVER MERIDIAN T 4/S R63E 0 @ 8 ~ = ~ ~ ~ ~ 'i? 'i? @ tSZl @ tSZl ~ d 2) cv ~ 0 @8 ~@ = 8P (§)© =2) @~ ~~ d8 ~@ 2)@ [? ~~ ~@ @~ 8 @ @ 0 0 / ,.;.,.··\_ \ ...... // ,..-""' '( ./",.·"" \ / S1!>.1E 1\DE\J>J'lDS ---1.1s 1:3o~--­ (~eoR) r---- ', \'\1- \'<l>:-t... / ',~ ' / )1f; / / / 1 INCH • 200 fEET NOTE: THIS DRAWING IS MEANT TO BE PLOTIED ON ANSI D SIZE PAPER (22" x 34"). USE GRAPHICAL SCALES IF THIS PAPER IS A DIFFERENT SIZE. CONCEPTUAL DESIGN -NOT FOR CONSTRUCTION u t: 0 c~ Z31: <C<C Ill: ~c a:_, ~o~o I D. a: . 01- a:z a.o .... u ::l~ .... > Oa: III:::J a.UI z: 0 .. ! " ~ .... " " " I I " "' "' i!i " " " " " ~ r:r:-0 0 " e!. z: .. ~ ~ ~Ill~ " ~ ill ~ !il i I ,. i;l ~ .. ~ " t: s ::>" Ul .. .. ~~ ~ j " .. " !ii ~ = ~ " = 0 " " z ~ .. ~ .... 0 Ill: a. u iii: 1-~ ; lol c ~~ i c Ill >-:J: • • Ill: ... lol D > c iii: ~ z c E ~ DESIGNED: ___ JD_G DRAWN: JOG CHECKED: I SCALE: 1>5 NOTED FILE: TKE_OES2.0WG Sheet C0.1 OF \ \ : ---·---·-·--1 -----··---·-: ---------- \ \ \ \ r -, r ·--·-·-·-·-·-·-~ \ ----+---r------·-·-·--1-._ . .._l I I I I I ,------1-i i .............. ~ I ', .............. ..... ..... ..... .... ...... ·-·-. .._J· L.. ::::--I i ·-.., , r ·"'-··-.:::":"-~11.!:-:::-...._ __ ......_ US:s 2095 uss 2459 TErjAKEE TOWNSITE ·-i -----:;:· ... , ---31 .......... ........ ......... ........ ........ .... ........ ........... _ t'' ,.,--------\ / --) I ' _ _.... ' J \,. / ..... _/ ' '\._:;::TIDE LEVEL ',<._/ (NOTE 1) ·-I /, ,. . --. -..,' .--. --. :........ ,·--. .--· , .......... I / ·-·--.... ----;-· . - MEAN LOW WATER -• • / • (NOTE 2) - I ,'// I < \ " I I : I '~~ '\ \ ' < / ,/ '\: ', "' " ' ' " / " ' NOTES : '\. 1. ESTIMATED MEAN HIGH WATER AND MEAN TIDE LEVEL MEANDERS ARE BASED ON APRIL 2010 LIDAR SURVEY OF PROJECT AREA AND APR IL 2011 TERRESTR IAL SURVEYS BY POLARCONSULT. VERTICAL CONTROL FOR TERRESTRIAL SURVEY IS NOS BM #3 = 2 4 .77 FT MLLW . TIDE LEVELS AR E BAS ED ON NOS DATA FOR STATION 9452386: MHW = 14.1 0' MLLW MTL = 7 .82' MLLW MLW = 1.53' MLLW 2. ESTIMATED MEAN LOW WATER MEANDERS ARE BASED ON INTERPR ETATION OF OBLIQUE AERIAL IMAGERY OF THE HARBOR VICINITY AND AER IAL PHOTOGRAPH S. 3 . VEGETATION IS PRESE NT BELOW THE MEAN TIDE LINE . VES SELS USED FOR SH IPPING PR OJECT EQUIPMENT AND MATERIAL SHALL NOT BE BEACHED IN THESE VEGETATED AREAS . COORDINATE WITH CITY HARBOR MASTER . BEACH LANDING SITE IN TENAKEE SC ALE: 1" = 1 00' 'v,' \ \ ..... ....................... uss 6855 ............. "'./' _/,''\. 100 200 1 INCH • 100 rt£T NOTES : \ I I \ I _ __...... __.......---;(s\0':>0 \ I I I __......--\ I I \ I I \ I I \ \ I I 1?:. ',VI ,~ \§ I I I I I 1. ESTIMATED MEAN HIGH WATER MEAND ER IS BA SED ON RECORD MEANDERS FROM USRS C04 7S063E (1982) AN D INTER PRETAT ION OF AERIAL IMAG ERY. 2. ES TIMATE D MEAN TIDE LEVEL AND MEAN LOW WATER BASED ON AERIA L IMAGERY. 3. VEGETATION IS PRESENT IN AN D SEAWARD OF THE HATCHED AREA . VESSELS USED FOR SHIPP ING PROJEC T EQ UIPMENT AND MATERIAL SHA LL NO T BE BEAC HED IN OR BELOW THESE VEGETATED AREAS. BEAC H LANDING SITE AT INDIAN RIVER ROA D SCALE: 1" = 1 00' z 0 .I- ~ (.) )( :::J ~ 0::: ~ I- ~ .en ~~z wCil o Nl- ii; z,' 0 ~ '-' u; If 0::: ~ao z c( II 0(/) ....... o-~ a: 1-0~0 ....~~z c..(/) w -' ~~z 1-Cll 'n z w '-' Lli ...J- ::!: t3 en (/)(/)w (;~ 0 z~ -J: ...J ~~ <( 0 (.!) :::J ~~I- I-::J a.. ~ z ::::--...... ---- ·- w (.) z 0 (.) .....,. ·- 100 200 1 INCH • 100 FEET u c: ·--ca ~ fl) ca (ij .... 3 fl) c: 0 u ... "' 0 ~ 0 v; ~ "' ~ 0 - 0 z a. I l l ~~ .... NN & r:-r:-0 0 " ~!. ~ ~: . Ill ::l .. ~ a 2 ~ ., ~ ., ~ ~ 0 "' ;:> " 0 "'g: ~ ~~ . ~~ I ., .... "' " ., ~ .. ., .. 0 " ., Ill .. 0 " .. " z ~ ... ~ I) II II ~ u w ., 0 It: G. D C/1 ~ w u • ~ i: D iii ~ :c u • C) w z ..J ~ ~~ ~~ c 't l ot Q. j c C/1 )- :J: :J: I u lit ~ ~ w D > c CD i: • ... z ::!!i c ~ DESIGNED: JOG DRAWN:_ JOG CHECKED: SCALE: I<S NOTED FILE: TKLD£S2.DWC Sheet C0.2 OF / ) /y· / . I . ,/ { ) / \' ( / I ,/ ,. ~+oi ·+·';·-·-·'-+·-'·- \\ .. '('1 .··" / / r ( \ ) ! I i ,;1 r:; I i // \ LJ: ~ \ ( ~ 2+00 J+ 4+00 I 5+00 ·-·+-~-------~·-·/·-·-·+ 1 -----+·~ -----~-~ --~·-·+ 7 (_ ---·.:+·-·-·-- 0 / ~........ \_ TYPE 1/ ROAD "\ SECTION / ( . ..-/ ' ' r-' /..--..... ) ( ------ '---\ 0 ) ~I ( \ ) r'/ ~ ( r ...... -··.J \ ~ ' ' ' I \ !?I / ( ! r---./ / \ ~ <:::- 1 i I ACCESS ROAD JCJ INTAKE ;;£E,SHEET C1 .J~ oi ~ ( ,..,.,.-----/'. / ,,/ ,/' ,.· //• .:-:;,,--... ,' / . •) ; / / '01 MAIN ACCESS ROAD -PLAN VIEW SCALE: 1 " = 40' 40 80 PVI STA = 0+60.59 PVI ELEV -246.27 A.D. = -7.86 "' "' "' g ~ + • 0 N ~ ~ K = 7 .64 60.0000' VC 0 "? ~I"' 0> N + • 0 N ~~~ PVI STA • 2+14.65 PVI ELEV ~ 227.55 A.D . = 5 .93 K = 2J.61 .------140.0000' vc -----; ~~~ -.. LOW POINT ELEV • 197.60 LOW POINT STA • 7+03.76 PV1 STA ~ 7+14.10 PVI ELEV • I 96.50 A.D. = 21.22 K • 2 .36 l INCH • 40 Fm PVI STA • 8 +02. 16 PVI ELEV = 2D9.70 A.D. = -9.15 K = 10.92 1 00.0000' VC "' "' o< ;:; 260 ;' --4 --·"' I 1 l . --j ·--I ~ ~ I ti ' -. ·- 24D :I --. -'i _j· •4 I' I -~ ' -~~~~ ji r ' ·---; , 1 ·-· ___ ' r -• ! j L~i~~~~~ 220 :i -1 -., -; 1 I , 1-s. x . _ _ . , . •·, --·· •: ! .-f i f -+ • · -r--. . _____ ! :i ' j -~ i . " _1 1 1 t : +'· ·-1 ---· • -·"· --; · · r 1 2oo II . i ~ , ' ' . ~ i . :-!; -•• ·-I. ' . . 180 11 I -l. ~ ; - !- I L ..: I !: 140 i~ T .... 1 if 160 !! ·I . D!l~ ~~ ~:!\~ IS"!!~ ~1m ~~~ q~ ~lte . ao .1N . .r-. . o ·1 ·len ·• -n O tN cn1 ao!oi ~ •1t0 N 0 1N cnl· NN NN ~ ----~ 0 l' "'I ~ co lfl """leo ~~en 1.0~ u:i~ a~ ml""! q ll, ~~~ ~! co ,..... . 101 cnj m:g en ~~~ ~I ~~~ ~~ o l"' .. on N1i': No N l N ~~ ~1 ~~~ 9~ ~~~ ~~~ -~~~ ~~~ 0+00 0+50 "! o l_"' "''! ,..,l v 0 1 . ..,!...., ,.,1 a3IN ,.,1 NN N !N N J N!N 1 "',N Nl NIN N f - _ __L__ ! 1 -__ 1 --I I .,,,.... at co 0 1 .- 0 110 -~ -~ "'I~ Nl~ ! ____ L_ ____ L_ __ ~L-- -~ -1"' -~ '--• I T 1 8!~ __]: I 0 MAIN ACC ESS ROAD -PROFILE SCALE: 1" = 40' 2+00 2+50 3+00 J +50 4 +00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8 +00 8 +50 40 80 11NCtl •40FtEI 225 1 ORIGINAl GROUND SU FACE 225 I 16 ' WIDE ACCESS ROAI I -1:1 fiLL SLOPE I lYP) 200 200 ROAD SECTION TYPE 1 --(INTAKE ROA D 0+00 TO 9 + 75) J (MAIN ROAD 0+00 TO 1 6+50, 18+00 TO 19+00) SCALE: 1" = 20' ~ .--. 20 40 1 101 • 20 FI(T ,--r -·--r---.. RIC I ;-...... / ·!<AU~ CRUS EDR< K -... 1 SURF E C Ut<SE ~ _L 1:1 UT Fl L ' SLOF ES --.. 'l ........ --....... ~ ROAD SECTION TYPE 2 (MAIN (IN TAKE RD. 1 +50 TO 2+ 75, RD . 7 +50 TO 9+50) 6+50 TO 9+00) SCALE: 1" = 20' 20 40 1 INCH • 20 FUT ROAD SECTION TYPE 3 (MAIN RD. 19+00 TO 20+50) (5) (INTAKE RD. 9+75 TO 10+87) SCALE: 1" = 20' o 20 '" t-=t FA 1 IN04 -20 FEET 22 ORIGINAl GROUND SURFAC E 20 - ROAD SECTION TYPE 4 (MAIN RD. 16+00 TO 18+00) SCALE : 1" = 20' o 20 40 ::E 1 INCH • 20 FI£f NOT E: THIS DRAWING IS MEANT TO BE PLOTIED ON ANSI D S IZE PAPER (22" x 34"). USE GRAPHICAL SCALES IF THIS PAPER IS A DIFFERENT SIZ E. CONCEPTUAL DESIGN NOT FOR CONSTRUCTION 0 "' 0 .. i N ~ .. .. .5 N N " I I " ., ., "'"' ~ N N c -~ "'. ...... ;!; ll " ~ 5 ~: rn . = "' m .. 'i i :l 0 ~ ;;; ... a !:!., '3 5~ I ., .. rn .. c::: ~~ 0 . ~ ~ 0 I " .. a~ l'G 0 .. 0 ~ " = 0 u Q. z ~~ .. ~ ~~z Q ~ V> '-' (5 :X cr :i1 ,.; 1i ~ ~ ~~ ~$ g - ~ ~ 0 D: a.. c 0 .ll • 0 z ~ < z • j 01 c ~~ '1: Q. Ill ~ D: • • .ll D: 0 Cll ... c Cll > • ... a; ... 0 0 < z < c ~ DESIGNED: ___ JOG_ DRAWN:_ JOG CHECKED: SCALE: AS NOTEO f iLE: TICE_O€S2.0WC Sheet c 1 . 1 OF / / ........ ~. ) (_ I ' '· ' ' \ 1\CC~ ROllO .T6. INTAKE I I ~\ . $£E 1 SHEET C 1.3-----....: \ • :$, I CD MAIN ACCESS ROAD -PLAN VIEW SCALE: 1" = 40' 260 240 220 200 180 160 140 120 ___ ;_ 100 "1 80 ~- 60 f·- HIGH POINT ELEV ~ 220.74 HIGH POINT STA ~ 1 0+40.90 PVI STA -9+90.90 PVI ELEV ~ 220.74 A.D. ~ -5.85 K = 17.11 1 00.0000' VC -~ -j :--------- -L ----i .... ------- ----+-- -t-----------+---- i·-- ------t-- 40 -+~+--~-----_--+:-------+-, ----1 __...-------/ ___ .,/ __ \ I ) -' I ::f -+-- I i ! I I I 101 101N co l .-1N co l,.... o"" ~~ ~~~ ~I ~~~ ~~~ gllci ~ ~~ "'1-~~ J~ ~~ ! ! ! I I I I --r-----r---t 1 ·1 ol"' "'II...-ol ol--t ol. 0 1--t -1 ci l ~ ~ ": cil ci ": o)i ci ": oi l "'lo .... o N ! N io .-'I N lo .-! C"''l~ C"''l~ N l N ~~ N N j ~ Nl I I I ! ' I i 9+00 9+50 10+00 0 MAIN ACCESS ROAD -PROFILE SCALE: 1" = 40' 10+50 11+00 11+50 -------+ ---~-- ----i--- -----L 12+DO / __ :~-~··" _j -------~--- --:--- --l -i--- --+--- -----r-- i 13+50 ---~-----···· ---<" , __ --~---,_ ~ ----------~---------------- ---------...._____ --------------- ------·:··-------~ ------------ ------------------......... HIGH POINT ELEV = 220.74 HIGH POINT STA ~ 13+95.68 PVI STA = 14+ 70.68 PVI ELEV = 220.74 A.D. = -20.00 K ~ 7.50 LOW POINT ELEV = 191.96 LOW POINT STA = 16+39.56 PVI STA -16+ 14.56 PVI ELEV = 191.96 A.D. = 20.00 1------150.0000' vc -----1 14+DO l -:!~ ~i ci N 'N IN ! v i,.... ~~; N jN I 14+50 :gr,.._ II) ~ t '8 U)_ ~ __-ai_ 1;7) :llt"' ~--1 --;~:- en I ~tt ~t~j --!--- ----+--------~ ---~: -----+---+----r---~---+-~----·--------+------~: ----+ 1 i I ! i i i , ! ! I ,....1..r o !~ o len --~" 101 ,....101 .-\OJ ..-. o ..-; v !,., 101 u:;!tl"! u)l • ,.:ill"! ....:!«! w: Lt)!C! ...:!~ r-:;«! tri i tri j"! ci l ..-jeD .-I ~ .-:g ..-:;; o ! O'l i ~ m j ~ a:1 :i ,....\ co .~ 101 "'!N NJN N )N N!N N i ..... !..... ..-j..... ..... ..--1 ..-I..-..-I ! l ! i ! i I t I I 15+00 15+50 16+00 16+50 17+00 \' \ \ 40 1 INCH • 4(1 FEET -----60--) / /; \.._ ____ :._.; BARRIER FALLS #2 Jl /lrf:://_ /~ '/. I / ~,:. 80 -PVI --srA -= 17 -1'85:93 PVl H'fV ---a&.-47- AO. _ " __ 21.,36 Kr ""-2.3~ 5G-,OOOO' ~ e.-: ~! ---+--- PVI STA = 1 B+67.29 PVT"El"EV =h!9.~ 7 i ,11:0:-~-t~-1-8 -+K = 3 ;7.!! --· -so:aooo; vc T~~-.., -----J--0 _ ~ i --l-~ ~!]--~ N i ~tqh ~ -r ~ t--·en N -~---' -~ i ---i·-~ ' "' -->--+- "' ----t··--- i -------r -~----: --~---- -1----: ---+·· ~ )( a 0::: w ~~ D..c;; w 1-,.., !::lz u... Cllwo co::: Ci)~ u. zu. <( i5 1-- Z<( 0 0(/l fiL:t:z ~~z 0<( ...J c.. rn D..(/) \.J w:c-ID 1-,n 0 U. V-1 ::;;;w z zwo Li)<i! 0 ::iiU....J-!a~<( I- C) <3 :::> (.) ~ 1i: I-:::> ~~a.. 0::: CCJWt- ~~(.)C/) 1-::::> z z ~ 0 0 ~ (.) (.) u c: -ca ~ U) ca 1a ~ ::::J U) c: 0 u ... ca ~ ~ I ~ .. ~ Ill I I -.. 0 ~ Q. i:i ~ ~ ~ ~~z ~ ~ G5 ~ "' !z ~ i ~ \:if~ 0 - 01.-z ~ c:: 0 II: D. .. z j D. fc ~ ~ ... u ~ z j 0 .. " ~ .... N N I I ., ., " "' "' " ~r::' 0 0 ~e n 0 .. = .. ~ " ~ " ~ 0 "" "'g: ~i:! lil "' " ~ " .. .; 1!1 " .. 0! 0 " = 0 u " z ~ .. .... u ... .., 0 II: D. u a: t; ~ ~~ lll: c >-J: II: ... > a: z ~ c !: II ... • ~ • 1111 c: '1: G. Ill : ... II c: ~ -------+-+ ----------+--+-----~ __ ;_ _______ _ +---+------· + ----· 1'1 1 1 ..... ]..... m"" ,.,jte .• -I ...t tC! a:i «! o fC! .:I ~~~ ::~ ::~ e1 1.... ~-1-! 17+50 18+00 T I ~I re ~:.n "'I"' I 18+50 r·-1 ~I ~ ,J &1 1 ~ ~I I .,1..., u:;:J ..,_.., 19+00 I r--1"' ...,:1 ~ "I" 19+50 I "'' 0 ' .... I 20+00 40 11NCH•40F£ET JOG 20+50 I I CHECKED: I SCALE: /oS NOTED FILE: TKE OES2.0WG Sheet 80 c 1.2 OF o_, Vllz )>)> r ;><; f'Tlf'Tl )> .. () () f'T1 (/) ~·(/) 0 ;u 0 )> 0 ll ;u 0 :::!] r f'T1 ! ~· i!l 0 "' 8 r---,W-o\--0 194.7 195.7_1_ ~ -'i'hw.L ... g; 193.85 ..•. ___ JJ1bL ..... + 192.0 0 192.80""" 0 191.6 -'---~ 192.29 "'"' + _ __]J1J)_J__ "' 191.39 0 _...JJ!_~J-"' + ____ L~L.~--. 0 188.51 0 __ll!M. 186.26 "' 184.8 + "' 182.89 0 177.5 179"3-6 -·-"' 176.3 + 0 --,-77~55--0 ...... ..1.2~ "' + ... _J Z!LQ_ ___ "' 177.70 0 174.2 . + ___l~ 0 178.12 0 ........ l!.~ •. !! ___ . 177.0 + "' --178~ 0 __ Jl]_J__ "' + _ __j]p_,L_ -- 8 178.97 176.0 + 178.0 "'I g; 179.36 -+-.. en 177.6 ···w!Ci4--. • 0 -, ---·--· ;;; o; "' "' g, "' 0 0 0 ~r 1 BVCS: 0+09.38 -:-----"'" ; BVCE: 197.69 ' . ---_, l ~EVCS: 0+59.38 ' I EVCE: 193.56 aves: 1+15.79 .. BVCE : 1 92.50 EVCS : 1 +65. 79 EVCE: 1 90.55 BVCS : 1+95.56 -avcE: 188.79 EVCS : 2+45.56 ·-"""TT/i:E: 1 83.56 BVCS: 2+63. 12 BVCE : 180.92 ;! I -e-y~--• -+- 1 'I '' o.--~-PIL .. ·: I ' .;.. __ ,, 8\ICS : 5+37.40 SvCE : 179.28 1--t -· "' 0 0 0 0 q "\ .j ..... ' ' .. __ , I I : I I g; 0 0 0 q < n t J. g; 0 0 0 q < n "' 0 0 0 0 r 0. ~ ~~ ~~~~ '·, ~: ;;;~~~ ,..,:....,U)(..I en•· 0(... "'"' ~~ ~~~~ II I ~ I -II "'I -c... ..... -+ cno<O• Ul~? 0-..j "'"' ~~ ~~~~ II .II~: ~I II""' ~bo;t a>-..JO c...,u. -en + L_l77.9 g ,-17~ --·----t -... '•--II no .,rr 180.0 --i78.61-- en 178.1 + "' 177.90 0 ~ 175.2 -176.96 " " + ........ E~.ol ....... 8 175.79 " 173.5 174.38 " + 172.0 g; ·-nv8·-· _l~ "' 169.7 + 8 169.51 ___ ..!_~- 167.68 ~ ____ 1~§,L .... g; 165.53 0 + 8 162.7 163.05 l-11~ri.9~----.. ~ 14 6 .95 144.7 142.48 ';' L __ 136.2 "'1 137:54-- 0 141.1 L--fro~a-- ... + I _,. ~--...... , !" .•• -·--~ ·-· ·-----1----··t-t·· ' ' ., I' 'l l •·· -.~ Ll ,. lj; I :~ ' 101 .j -~--r ' ' ' ' EVCS : 7+37.40 o E\II:E : 173.60 l J aves : J+97.04 'I ~-' BvCE : "1 69.71 r ., ' I 'o o I ··t---~t f· II :I' ······""t ----~- +-+- 1 i ~ ~ BVCS :I 9+37,77 , eke 1 ~5 .84 --r ~ -1---,-~-: -·---, -:---~--"!---t· -- 'f :-'--;-• ! ' / , EVCSf 1b+7.F I tvC£: '1 39 .99 . -_.,_ -4-----+-------·-•· -~-.--.. 1 0 0 0 0 0 q (!\ 0 " 0 0 II 8 - 0 "' . 0 < • (') l. ~s.,., ,., > Q 0 g ~p~~~~ o nn!< Ul~ o ,.., II --tr ~ :--J I II en> !;2 -:"--+II < "'-l l.ol e» (..1 II n ....,o .....,lll :...:...+- VIOOI...., o<D "" ss ,._;a--f"lVl ?rj;! II M ~II ~~~~ cn:...O'I._ ...,en .... :...a "'• ~~ """' ~;;! II H "' -+ '""' "'" io:..,. "'" t...L.. ""' SlAT! ON 1 0+58 18"• CULVERT NOTE: THIS DRAWING IS MEANT TO BE PLOTTED ON ANSI D SIZE PAPER (22" x 34"). USE GRAPHICAL SCALES IF THIS PAPER IS A DIFFERENT SIZE. CONCEPTUAL DESIGN NOT FOR CONSTRUCTION ~ ~ 0 ~ ~1 ( -~o : ~~( INTAKE ACCESS ROAD PLAN AND PROAL[ !T> ........a..r ;;! • r -(.N iii INDIAN RIVER HYDROELECTRIC PROJECT i Tenakee Spring•, Ala•ka ~ s s NO . DATE Vl lz ()--I )> )> r ;><; ~f'Tl )> () () f'T1 (/) ~I (/) o_ ::o 0 )> 0 I ~~~ < h -·-~ i ·--::;: ;!; !'l -~0 y~z · \ -, 0 "'> !,;z 0 ', " ~.:: ~~ 1"1Z "'"' IO """ '=l:;l n"' ::~ ~(!; " I -) I i J '"-' \ ' \ \ V(' Y· \ l I / ·,., ,../ ·, ., ·, ., ·, ·,, --~ ...... } / c __ , '· ' REVISIONS polarconsult alaska. inc. ENERGY SYS'n:WS • EHVIROlUIENTAL SERVICES • !NGINEBRING DESIGN 1ft03 WEST 33RD AVE, SUITE 310 ANCHORAGE, A.USKA 99603 PHONE (807) 258-2 .. 20 PAX (807) 2~8-2418 : / \ \ ~y ,;; ; : \ ', ~'\ ~'<'1> "\ \\;:ORDINARY \ HIGH WATER \ ------~·~~~~~~~~~~~~ \ ~--.,. I '-.... _.,.-....................... ___ .....,-" f-fOOT CONTOURS ~ _:...~·?~- ' ---~:::~~~~-:::---, INTAKE ACCESS ROAD (SEE SHEET C1.3) FISH PASS LEASE SITE £_ ~ ~o_s:_o~ · I I I i ~· .• , j ', ' ·. i .\ · ... I ' . i \ ·~ ''' •i ) ' ' "'E'Tt..wos '~'00' / CONTOURS 110 ' I DIVERSION HEADWALL INTAKE STRUCTURE -----------~ \ ------, .. 0 ~ 1 100 I 'I i ' I I /1 I :·f.i 1. \'1 / 2-FfJOI_ CONTOU'\:' \ INTAKE STRUCTURE -PLAN VIEW SCALE: 1" = 10' \ ·, ' \ \ \ ; ~ ' .. I \ j\ ·i I \ \' '\ I ' ., I \ 10 20 1 1HCH • 10 FtET ( \ 130 NEW OHW L(V[L WITH ------------~1i~l'!rN------------""""' < ·~~' ·~,,., ----------------------,r-~ GROUND ' -------"------HYDRO INT"!<E ' EL 127.8' I ------------~~ 3D.OO' [1.5'' 10.0 I I 120 110 100 '> EXISTING OHW LEVEL 1 25.~ ~ ____ ---< I -,.......------------------- 1 i i DIVERSION STRUCTURE -SECTION LOOKING DOWNSTREAM SCALE : 1" = 5' I I EXISTING R SH PASS HEADWALL (BEHIND NEW WALL) EL 123.7' 10 1 INCH • 5 rEEl I 90 ~ 80 70 INTAKE STR UCTURE SCALE : 1" = 10' ' 130 I T SILL OF NEW FIRST f iSH NOTC H EL 120,5' 120 110 \ 100 r------- ~ t:-::-- f iSH PASS SECTION DOWN FISH PASS I ~ --f NEW DIVERS ION HEAD WALL ' ' _, __________ _ INTAKE STRUCTURE SECTION LOOKI NG UPSTREAM SCALE: 1" = 5' '-, PENSTOCK ON TRESTlES 10 2ll 1 INCH • 10 fEET SPILLWAY t ~OG 30' ~PSTRFAM OF SECT'PN ·s.-;c-OG 20' UPSTREA~---­ OF SECT!0!'.1 '\_ OG 10' UPSTREAM ' . OT SECTiON • 10 E3 E3 I t tNCH • S FEET ;i X N ~ a: w ~~ C.-l!j~ -z cnw oa: -w cnlt ~0 z z< ocn 0 0~ z 1-§~ (.) ....I a. (!) a. en -::J ~:X: en a:: a~ w 1-::iii o en ~~ _J z ::q~ <( 0 !Q~ ::J (.) ~ !::2 b: 0:: ~~ W 0 OC) (.) u. ~~ z 1-~::J 00 ~ uz ~ . " 0 0 u 2 .. -:s .... c .... .. I I " ., ., "" !i 01 N .. = r::-r: as !i 0 0 " ~~ " ~ .. ~: en . "' as :l .. u 'ii ~ 2 I " .... l:l" -o ~ ::>" Q Ill .. en 5 0 c s~ 0 . ~ ~ u !l " ~ E ~ ~ as ., ~ ~ 0 .. 0 0 ""' 1:1 0 u a. "' " z " -.. I ~ - g -....1 - C/1 z 0 ~ 1-... u C/1 w .. 0 z a: 0 II. Cl ~ u ~ • ~ ii Cl 1-;c w u w • fz ...r w Q ~~ c: j "t: II. Q II. )-C/1 w :1: I a: :::1 a: ~ 1- w Cl u > c: :::1 ii • .. a: Iii z c w E liC ~ ~ ~ DESIGNED: JOG DRAWN :_ JOG CHECKED: SCALE: AS NOTED FILE: TI<E_OES2.0WC Sheet C2.1 Of 81•a:-agz (LOB) XV.il cogee YXSY'lV '3:>V1IOH:JN.V oa•z-ao2 (L.oa) :INOHd otc urns 'aAY aacc J.SU coot N~IS!a 'D.NIHUNI'DN2 • 8331ABIS 'IYJ.NIJIH01:0A.N:I • SRaJA.lS A:li!I:DI.3 "3ZIS lN3~3:1.::HO V Sl ~3dVd SIHl :II S31V:IS lV:I IHd~~ 3Sn .• vt x .ll) ~3dVd 3ZIS a ISNV NO 03ll0ld 38 Ol !NV3VII Sl ~NIM~a SIHl :31 0N 0 NOIJ.:::>n"t~J.SNO:::> 'tiO.:t J.ON NE)IS3G 1VnJ.d3:::>NO:::> SNOISII\3~ ( 1-z w :,; -z 0 (.!)"<t ~ II :>::: • u~ f2w Ul ..J z <( W(.J O.Ul 31VO "ON ( l.:>3rOI:Id :>ll:ll.:>31301:10AH 1:13AII:I N'f'IONI -311JOI:Id ON't NYld >I:>OJ.SN3d -u ... 0 ~e Vl }; ,-~ \) fTl z Vl --i 0 ~.I~ II I ;g ~0 0 ~ ~ ~ § ,-fTl ,,...... Vl > 0 + 0 0 --i 0 Ol + 0 0 '-' ~ i!l • 0 0 + g ~I g;l + 0 0 ::: + "' 0 "' + g I "' " "' " .. , I I I I ··-~ . 0 0 II II :II • -~ :' ~~ I VI F I 1"1 :; I ~~ I !:(~ ·! )~ \, I , ' ', '" "' 0 i I ----· I : I I I r !. I I .. I I I I I .. : I i : . ·-r · I I i : : i I : ' ' I : I. I : I ' I I I i "' +.-.. --"' 0 :~, >-\·· L---· {-1 I "' + 0 0 "' + "' 0 fl gl • + g; "' + 0 0 "' + "' 0 "' + 0 0 I "·\\ 1 .II ~-·-f-·· ! ~~~ : ~~~ I 1"1> • ~:::j 1 on I 1"1 l ~ l I : ·:· I i ~ I I C> 1"1 : ... ~~ I 0 :<! I 1"1 C> I -< I C I z ·····-:-~ : ··! P-o-.~ N I """' "'-"'"' N • + "'• ....... ;.., N I_ "'" ""' "' I "'"' "'-~ I ."' ~~ N STATION 12+15 45' ELL ANGLED 4 1.6' UP FROM HORIZ. ( +33.5'V & 30.0'H) STATION 12 +62 VERTICAL 30' ELL END PENSTOCK TRESTLE START PENSTOCK IN EARTH BEDDING STATION 14+36.5 45' ELL ANGLED 1 5" DN FROM HORIZ . (-11.6'¥ & US'H) STATION 15+26 2 2.5' ELL ANGLED 34' DOWN FROM HORIZ . (-12.6'V & 18.TH) STATION 15+5 7 30' ELL ANGLED 45' UP FROM HORI Z. ( +21.2'V & 21 .2'H) CONCEPTUAL DESIGN NOT FOR CONSTRUCTION NOTE: THIS DRAWING IS MEANT TO BE PLOTIED ON ANS I D SIZE PAPER (22" x 34"). USE GRAPHICAL SCALES IF THIS PAPER IS A DI FFE RENT SIZE . I (/) \) ()fTl )> z 'V> fTl --i .. 0 ~o ,;:<; II '0 ;:o ~ 0 0 ~ ,- ~ ~ a fTl ~ (/) > 0 + 0 0 --i 0 0 + 0 .s ~ i!l 0 + 0 0 0 + "' 0 + 0 0 + "' 0 "' + 0 0 "' + "' 0 "' + 0 0 "' + "' 0 ... + 0 0 • + g; -+-"' " g 0 0 ~ STATION 0+00 INTAKE HEADWALL "' STATION 0 +35.7 z ~ " • n:;; o~~z "'"'"' -~ ~;ii ""'"' I"' ro. ou. N START PENSTOCK ON TRESTLE I STATION 2+10 START BRIDGE STATION 2+50 END BRIDGE I I STATION 2+59 ~ l 30' ELL I 1':8 ( I £.._ ~;tl >o i ' ~ .... ~--~ C.,(;) .• \ rrlr-J;:~ ~-.... I !iS ~8" . l STATION 3+15 0 ~"'g~ ) 30" ELL -~-e ··I r <> -< . I STATION 3+35 !O \ 45' ELL ,..,.. : ·--!-: ! ,/ . I 1 ,, ,, /' ', : II ~~ ~ STATION 4+30 I FABRICATED 65' ELL QQ) ,. . "' + 0 -; \ 0 "' + "' 0 "' + g "' + "' 0 .... + 0 0 .... + g; "' + " 0 "' + "' 0 "' + 0 0 "' + "' 0 0 + 0 0 0 + "' 0 ::: + 0 0 i \ ·~'. .. ' !\ " " IJ I, II II i _, I 0 II II II I I I , '• II ' I I --·· ·t ----r I i I I I I I I II I I • : 1.. :: I ' :· I I I. ·-· I f. ,. I I_ t"a> 0"-> N • I ~~ "'"' "' . N I """' "'-"'"' N • STATION 6+28 So· ELL STATION 7+ 74 30' ELL STATION 8+27 30' ELL :!l !'l 2 0 -) t NO. I DATE I RE'Y1 SIONS i F,; ~ ~ ~ PENSTOCK PROF'ILE ~o tN [ alaska, inc. polarconsult ENERGY SYSTEMS e ENVmONIIEHTAL SERV1C!9 e ENGINEERING DESIGN !I~ Pro;.ct ~ i:; INDIAN RIVER HYDROELECTRIC PROJECT ~ ~ ~ g 8 8 Tenakee Springe, Ala•lca • N 1603 WEST 33RD AVE. SUJTE 310 ANCHORAGE. ALASKA 99503 PHONE (907) 258-2420 FAX (907) 258-2419 \ --- "' ·~ ~------. .../ / _,."'' / ,"' ,...., i ............ ! \ ---~.... \ '\ \ -----' \ / -·, \ I ~ -------\---\ ,/ _//~---- \ --I (.--------.-- ·--I -.J ~\ -·-----.-------------------~------ ~ ~~ ~"~ -~~ ~----~ --~" r '"', ~ ~/--------.........._____________________ - "'"'--------.,_ -~ '~-" ""~- ~--- / ·,..._ .~o- ---~ ~~.,~ C'~_<.r_r . ..,(' ~--, r I ---------., L TAJLRAC E --------------......... I ,, ~~DIA~ Ri.fR '•,,,, I DEfLECfl!l 1 WALL I I I I I I ' I I I I I )' I I '-I ... I I ~ -., --, ,_ 0 POWERHOUSE -PLAN VIEW SCALE: 1" = 1 0' ,..,o '.'b · •. _6'o ', ·· .. , 10 20 1 INCH • 10 rr£T 120 110 100 90 80 70 60 1 ! t DEFLECTOR WALL POWERHOUSE -ELEVATION VIEW SCALE : 1 " = 1 0' 120 r-- 1 100 80 60 POWERHOUS E ELEVATION VIEW SCALE: 1 " = 1 0' i ~ OHW l I g OR IGINAL GRO UN D SURFACE I --t GENEiji\TOR 10 20 1 INCH • 10 f£ET 10 20 1 1N0i • 10 F'EET ~ )( ~ ~ 0:: w ~ui a..~ WI/) ~!z Cl)w co:: -w 1/)u_ ~~ z~< oc ~ z ,_§~ (!) (.) ~ e; -:::::> w :E en m ~ w 0::: 0 u. 0 1-::;;; en~ w _J z ~~ <C0 !!2 1/) :::::> (.) ~ ~ 1-0::: ~ iE a. 0 ~~ W C(!) (.) L1. !!2 ~ z ,_i!==> 0 0 ~ (.) z ~ I as ~ fl) " as r:l 'i i " " ~ :;j " ..... ~ ~ ~ -s ;,!; ; (II ~ ! ~; 0 . ~ ~ u ; ~ . ._ E t; :"! as t: ~~ -,.. ~ = 0 ~ ~ ~ a.~ ... \2 Q ~ <r. ~ g Ill z 0 t= ~ ~ ... Q z c z ~ "' ., i IL. u ii .... u "' ...I 0 .. • 0 c • 0 "' 1: .1 ~ }i '1: c .t ~ )- I ::1: iii a: .. 0 "' 1: "' > ~ Ill ii 5 ~ I % a: iS ~ ~ IL. DESIGNED: JOG DRAWN:_ J()(; CHECKED: SCALE: AS NOTEO FILE: l)((_JJES2 .0WC Sheet C5.1 Of In -o () 0 )> :,;; r fTl ~ ::u ~ r • z II fTl OJ I q-o ::u 0 ,., r= fTl 1l : l,j g l'l ;:! "l Ill 2i 0 ~ ~n o o oH -' ( NO. I DATE I ... fll F.i ~ ilj ~ ~ ~ OVERHEAD ELECTRIC UNE UPGRADE "' ;:: ?C z PLAN AND PROriLE ~~ I; ; " " r: ~ r -....... .. .... ;:;ELECTRIC .R0,. •• • --~ 8 8 8 -Tenakee Spring•, Ala•lca tn-o () 0 )> :,;; r fTl ~ ::u ~ r . z II fTl OJ I q-o > z < ,:;; :,;; ~ • l,jl'l l'l ~ 2i I -...., '-... -...., r;t 2 .}> ;x;: f7l f7l 2 r- f"Tl -1 1-·-G . "0 I o ~---r;., ! i ~· j '-./ 1(---·, i /W i j (0rf ,r::D, I I ::;; I I l, :;! i, ' I . L i I "\"·~ '· OJ I L I I I I I OJ I ---.. I OJ t-1 I I I I I . I I I I I I L . I ---1 '--r--l i 'l --.. \1 I ,~ \ / ~) ( J I I \ i I I I I ) I ' . c(J ,' I \j i ( j (I 1··. ! ~-->I ·). I rf ; ( I/ '. I ){ j . 1 I 11 // ,, . \ ~I I / \ ' ' ' \ . l \ ' f : ·'·I' '. ·, L. ( ),> 7 \ ·-). f I , ,.__.-} ; i r/~1 1 J ~\(''1 '1' ·'-<\', i r\ \ I '·\ ., ' I 1'-.. \ I _1· r ii!~.JI. j li ) 'I.! \ . "'o?' (. (· l I ' ,. 1-<y'kJ \}··'···\. ( ! i ~ '?1f:~-:_~~:~~~~< . I . ~"' Lr-C -; -~~ . ITI ;;o t ·'\_,. __ _...--.:, . .-.1 I "' . ·IY;:_f' ~---------- ,. . r }';:~\"" ~~,~~ ~~3~ ~I ( .. _,I ) (/I ~ '-... ( ' '...._ I / -fJ'$--I f ~ '-b., \ ', ... , . I ' CONCEPTUAL DESIGN NOT FOR CONSTRUCTION NOTE: THIS DRAWING IS MEANT TO BE PLOTIED ON ANSI D SIZE PAPER (22" x 34"). USE GRAPHICAL SCALES IF THIS PAPER IS A DIFFERENT SIZE. REVISIONS polarconsult alaska, inc. ENERGY SYSTEMS • ENVIRONMENTAL Sf!RVICES • ENGIN!IRING DESIGN 1~03 WEST 33RD AVE. S UITE 310 PHONE (807) 258-2420 ANCHORAGE, ALASKA 99~03 FAX (807) 258-2419 nnz-ogz (Lon) XV<! OZ:tz:-ggz: (LOB) aNOHd togee VJISV"IV '3!lYHOH:>NY o t & :u.rns ·u Y aH££ ~saa cog' HDISIO ~Nnii3HI9N3 • S3.JIAH88 '11'.LN3JII.NOliL\Ha • 8111JSJ.S A.Oli3N:I Dli•D"' '•8UJ.IdS -l!DU•.L ~ g g ~-----------------4----4-.0-N~(~=====l=O=l=r=O=~=d=O=I=~:=O=l=l=l~=O=~O=A=H==~=l=A=I~==N=Y=IO=N=I====~J ~001 "l'S~o ·~ 31UO~d ONY NY1d --11Y~l JNn ~~Od !;;-•• "' SNOISLI\3~ 31¥0 -'3ZIS 1N3~3:1.:UO V Sl ~3c1Vd SIHl.::ll S31V~S 1V~IH~E> 3Sn ·(.V£ x .U) ~3c1Vd 3ZIS a ISNV NO 03110ld 38 011NV3W Sl E>NIM~O SIHl :310N NOI.l~n~.LSNO~ ~0.:1 .LON N81S30 1Vn.ld3~NO~ .. 'J', ,. I / / i .-I' 3= w 5 z 5 Q. _J <a 0:: IXl 1- w II z . ::;· 0:: w w _J 3=<( 0 u Q. UJ "' NOll ,.;"': ........ +oo .... -I . ~ "' 0 .,; rg ·og+rz :s:lf.3 1 £9'0 8+ZZ '5:JA8 88' L8 '3:lA8 : l 9 '9<;+ LZ :s:JA8 <;vT8 '3:lfl3 LO'Z£+ LZ 'S:lfl) a ·c;e '3:lMI l0'Z8+0z 'S:lMii <;Z 'LB '3:lfl3 I I l 9 'Z8 '3:lfl3 Lv'6Z+LL 'S:Jfl3 "' 'o ' 0 ... ~. . ,... ~ ~ ::..:: . \ ez ·zg ;3 J I\8 lt lt L._ __ £_Z_T_Z+_v_L -'S-'JA~S--- "' "1 "' "' .... "' ,..: u ~ ;!:-.. "' (/) ;tlt 0 "' Ll 'l8+0 l .'S:lfl3 e ~·c;t '3 :JMI OL 'rs+s 1 :s:.jfl] , g<;·r> :]:JAB ' ~ OL T H61 :s:>MJ 0 "' ,.o -zr '3:>113 9STt+L '5 0113 L9 '8 -I):Jfl] ss·oe +o :s:>fl3 0 0 0 00 N OXl ~ N !2 ii Oi ....-~ ~ w ... "' ;;:: 0 u + .... N 0 0 + "' N 0 0 + N N 0 0 + ;:; 8 + 0 N 0 0 + ~ p \\8 II ~ I lg i ! r- li ~~0 l o ;!,:; 'i - li !!! .h t:. r It lil il i II \i ~ 1\~ 1: ji 8 i + li ~ il ll 0 I O !+ ,-,- i i 8 + ~ i l'g I + li "' li 0 l o 1 ;:; II lj ~ ! i !o ·•· ······-· i! ' ' 11 8 I + I"' i j o ~~ l .... I i I ~ w _J I"' i:i: 0 a:: I Q. 0 0 .. '" + _J N ~ 0 1-00 It w II "' 0 5: ci 0 0 ;: 0:: w w 3= _J <( 0 u Q. UJ coge6 YJISY'JY • OlC :UIOS '3AV i::>VHOH:JNV ( ) ( J / ) i / / I I ) () l· f } / _J <i: -tro I-Q) w II ~ . _J ~ ~JI'I~D.lSNV~l ]Nil JI~1JJ1J 01 dD~O JlDd OVJH~JAD ON3 ZH JlDd MJN ~ t +O!> NOI1V1S JNil Jl~lJJl] JNil Jl~lJ~H~JAO l~VlS OJI~n8 ONJ 9 ;~ JlOd MJN 8£ N011V1S a ISNV NO 03ilOldS~ 0~ S31VOS lVOIHdV1:1E> .LNV3~ Sl E>NIM 3Sn NOI.l~n~.lSN V}la SIH.L :3.LON c;r ·sa :J:>I\3 79·c;£ +rr :s:>l\3 OZ '68 :JJI\3 r9·os+rz :sJI\3 N81S3G 1~~.l~d03.:1 .iON ~NO~ ~ .... "' .; g 0 0 "' ~ ~ 0 0 "' .. 8 + ; 8 + :;>.: 0 0 + "' .., 0 0 + .... .., 8 + "' .., 0 0 + :!l g ~-+ .. .., 8 + .., .., 0 0 + "' .., g + ;;; 8 + 0 .., 8 + en "' g + re 8 + .... "' g + "' "' 0 0 + "' "' 0 0 + .. "' 0 0 + .., "' w _J G: 0 tr 0... _J <i: 0 tr Q) I- w II ~ . _J ~ I IAN RIVER HYDR OELECTRIC PROJ ©DLFU @[p LF§~&~§§ @~~D~@@ §[1§©LF~D© QDLFDl1DLFU [Q)§~&~ll UGJ§~LF U§~&~§§ @~~D~@@~ &. JCC c BARROW ,rt-. / ) 'i ../----; , '. / I _ _fl. FAIRBANKS /J ~·~~~~~ . "':./', ~"!~ .,... j ~ /, . ~< " ~ /r "<; J,~.., ,.., , NOME_/ ,.-:>-..'1>-'' r '""' · /.f ·1 / ' ""./ II J( • . I' \ "" '"" ,-\.. \ " } .r ,· -( o:: vr' I"" ~ "'--!' ;: . 1',_. ' . ~~ / 1-·\._$5~ ~ >-'~! -! • ,, . \ y~ BETH· ' ( . ~ ~ ANCHORAGE -i,.-;;<:-v\ -n .. · ... rA , - DILLINGHAM -, .r KODIAK , .. {I- /), / ' I UNALASKA _,d ,/ I / ~~ ~ ! .~ ,..!~'· I '.· ...• .,.A..I'JCci;;v i I;.J:,~i!fo'· ~.f.\ J ~0$_: crrY· OF TENAKEE STATE LOCATION MAP SHEET CO.l PROJECT SCOPE, SPEOFlCATIONS, SURVEY CONTROL Cl.l ACCESS ROAD PLAN & PROFILE C1.2 ACCESS ROAD PLAN & PROFILE Cl.J ACCESS ROAD PLAN & PROFILE C2.1 INTAKE SITE PLAN, ElfVATIONS & CJ.l ' SPRiNGs TOWNSiTE --r-----[-··-,-, ' c .Jr __, 1 .::..... ..r.= :::: 2 ;; -t :: .::Jc ::/0[ ..J[ ~ ::ZC :u:-~r_-:_ ~c ::Jc- EXISTING DIESEL POWER PLANT IT 7 I; ~~-~~-=i~ c -~'][--'C-:u-.:J: ... SURGE TANK ( 1SHEET C4.1) -----f -------- !P OWERHOUSE !(SHEET C5.1) I I POWER LINE (SHE~ E1.1-E1.4) I ------r------, TENAKEE INLET I alaska, inc. • PLANNERS • ENERGY CONSULTANTS PHONE (907) 258-2420 FAX (907) 258-2419 USFS ROAD 7500 _ ~~T_!_O~ ..!_5~-:_ ___ r_ (INDIAN RIVER ROAD) 22 23 ~ -----~ ------- I FOOT TRAIL COPPER RIVER MERIDIAN T47S R63E D @) ~ = ~ = ~ @5 I!!) @1 'i? 'i? @ ~ c:; ~ 'i? c::!J = @5 @1 ~ @5 D @~ ~@ = ~[? @@ =2) ®@5 l!!l[? @(!R) c::!J~ ~@ 2)@ [?fQ;l @10 [!!I]@ @~ ~[? @@ INTERCONNECTION WITH EXISTING ELECTRIC SYSTEM 600 1200 @ ~ PROJECT LOCATION MAP AND _SHEET INDEX 1 INCH = 600 FEET D D ' / /v / \ \,.... /: /' / \ / \ \ \.-" ' \ \ ..-\ \ \ \ G'~ Q.,f ,;:I ,<;(}'I ~~/ ~~?;>I .. "21 0~1 t_f.; \ .._o I I '\.1 STATE TiDELANDS ATS 1304 (HARBOR) '_:;£ I I ~ ( ~ ~ I I I I I I I I ' \ "0-?.-~4\ o,.. ·~ ~ o,.. ·. '\, -f.,\~ '"VOl· ~"" ' tv d :-1--<:1 ~."' ~ ' ' \ ' ,, ' ,. ' \ ' \ \ '\ \ ·v ,/ / / 'I .I / '-\ / SMALL BOAT HARBOR uss 6855 (STATE OF ALASKA) / / '\ / '\\ z r ~ / ' \ ~..,~ ·~~ \~~o:sr / ~/D / / I I / uss 2459 / (CITY OF ly TENAKEE SPRINGS) / \ / / / / / / I \ / / / / POWER LINE ALIGNMENT / ' " / ' ;-i y' ' '( \ / / / / / / / / / / / / / / / / / / / / / / / / / / / .· ( ' '\ \ } .· ~\P ,r/ ~ (s 21122 / / ~~ '\ / \ '\ / / 'l ' \ ' ' ' ' ' 0~ {5'<1' o,..'~o· /l\..:11 ' "''\;,"'<,:. "'"'"~ ~..o'\~. '13-1<,~\ "~ "\ I S.1-o ' ! I I' ~ ~%~ 4-1:,._, \ 200 \ \ \ 1 INCH = 200 FEET \ ' ' \ \ 400 \~'\ ~-'O-Il ~<"~_,. \ ! ' i \ \ \ \ \ \ ' \ \ ' \ \ \ \ \ \ \ \ \ \ § ~ ~ ';l ~ ES CONCEPTUAL DESIGN -NOT FOR CONSTRUCTION U> z 0 Vi GS 0: w ~ 0 z (.) c::: (!I c~ z~ <(<I( 0< >-c 1-O<_, ""o ~D-O< l 01-O<z o.o 1-u u>-...... ..,> 00< 0<::::1 D.(/) -I 0 Q ~ I ~ • 10:1 . N N " I I "' "' "'"' "' "' ~-; 0 0 ee "' " z < 0 .. = "' ::: " ~ g ""' "' "' "' ,.; > < <:.: :d "' < " .. oi "'" "'< II i ~ 1- u ... .., 0 0< D. u ii 1- u ... -' ... ~~ c >-J: 0< ... > ii z <I( c ~ DESIGNED: DRAWN:_ CHECKED: a ... • a c • ~ 0:: ;:: IL Ill • • ... a c • 1- JOG JOG SCALE: AS NOTED FILE: _ TKE~DES.DWG Sheet C0.1 OF ': j \--., \ ; / ' ; -.., / / ST.t>.. 0+00 • It_ INDIAN RIVER ROAD \ _, \ / i c• ~J / ~+09 8 MAIN ACCESS ROAD -PLAN VIEW ., SCALE: 1" = 40' <0 '" N + 0 cii ~ 260 240 220 200 180 160 140 120 100 80 a.',... oi .co ,..:· ~:~ ... N 0+00 PYI STA = 0+60.80 PYI ELEY = 246.26 A.D. --7.91 K ~ 8.00 63.2740' VC N <0 "' ,..: ... ... "' N "' + w 0 ~ cii u i:i o :W') .. ~~~ ~-~ I"')!. ;!;:~ ...... ,N 0+50 ~ "' ... N w ~ ' ,' ( ( -~1 ,) ; I .. ·· 2+00 .... \:LI~i;··;;,· CUT/FILL (TYP) / .... ·· I / i :-r-- -+- _j__ ! ~~~ l ' ' I I 3+9(} I .) ~I ~I I ; / I 101~ ro;~ ..... ,_ N!N 3+50 .. ·· _.I 0 .,; N // ,· ·"''' 4+00 rr)i,..., "1 \ .• ;;:<:! N' Ni~ Nj 4+00 J I / ~ j ,•' ~1~ ~!N N!N 4+50 ,/ ,' ~~ "' '" ~ ~:«; ~:~ 5+00 ... ··' 5+00 6+09. ( i ·' co' :i ~ ll'}! N o: oj"' 0 N j N~ N ~:~ o1 ~'~ crij "'' .... j ! .J.. 5+50 6+00 r-- ~-~ ~g -, ... 6+50 ,... .,; "'' o :r--·"' ~:,..: --·~ 7+00 7+0Q r---i rt)i ~: ! ~l~ "'!• .-l ~ _ L I 7+50 I I I .. ·/ ,' / .. :.---- :( / :1 / / / ·./ ~I .-i I I i L_ I I PY1 STA = 8+23.63 PYI ELEY = 189.69 A.D. = -5.81 K = 8 .00 T --·!; g : ~ .~ + OJ • <0 CQ -~----+ $- Vi~ ~--w -~ ~-~ ": v - ~:~ r::~ r-::~ ~!§ ~:~ §j~ j_ __ 8+00 8+50 40 80 1 INCH • 40 FEET I I t-·----· -------···----~------··---t_-------------------···----.. ···-----------J 225 i FRIGINAL GROUND SURFAii I 225 i -t== . ..j_=J:: 16' WIDE ACCESS ROAQ · 1 :;------....---1:1 FILL SLOPE l ('rrP) >-----· : I ! 200 SECTION TYPE MAIN ROAD 0+00 TO : 1" = 20' INTAKE ROAD O+OD 100 ROAD SECTION TYPE 2 (MAIN RD. 1 0+50 TO 15+50) SCALE: 1" = ORIGINAL GROUND SURFACE -----ifi .CuT SLOPE 100 100 rs· WTDE ACCESS ROAC .. -& -P~NSTGCK-BENGJ; • i 1:1 FILL SLOPE -------------- 75 f ---PENSTOCK-. ~ftel~ 't'AAIES) ,75 ~ 50 '50 ROAD SECTION [TYPE .3 (MAIN RD. 15+50 TO 19+ 77) SCALE: 1" = 40' INDIAN RIVER INDIAN RIVER CONCEPTUAL DESIGN NOT FOR CONSTRUCTION II V> z 0 v; (;'; "' w ~ ci z 0 c: ... "' 0 a. ... ..J G: 0 It: C1. 0 z <( z :5 I~ <( 0 It: Ul Ul ... 0 0 <( z <( 2 all'~~ ~ ~~ ~ Q I I I "'"' ""' N N r::r:: 0 0 ~ ~ ~~ rn 0 .. = .. 0 "' t g ""' (/] 0> 0> ~ ~ "' i:i 1-0 ... .., 0 It: 11. 0 ii! 1- 0 ... ..J i~ la:: 0 >-J: It: ... > ii! z <( i5 ~ DESIGNED : DRAWN CHECKED: a .lr • a c • Ill " 'i: Q. Ill • • .lr a c • ... JOG JOG MOD SCALE: AS NOTED FILE: TKE_OES.DWG Sheet c 1 . 1 OF / .. ·· /' J / / / ...... ··· _ ...... I STA 8+00 INTERSECT/ON WITH 11\ITAKE ACCESS ROAD (SEE SHEET C 1.3) 7+00. ACCESS '/ / t' ·,•' / 'I .' ~I .. ·· (1) MAIN ACCESS ROAD -PLAN VIEW SCALE: 1" = 40' PVI STA = 10+18 .35 PVI ELEV = 166.26 A.D. • 6 .42 K • 26.00 / ,,'· / _, 16 6 .9950' VC -----t 260 240 220 200 180 160 110 120 100 80 60 ~~ 21 Vi ~ t' OG Ire .... ,~.......--;:::, ~l:ii ~~ 1-\ ' I -'-------L 9+00 ;;; ..; ~ ~?Q 2.1Q. 200 J90 11+00 ,.· ' .. 1 ... ·· \ ( \ ~\ ~~\! ~-/'~·,,., i '(r~ j r\ ! \ " I ' \ STA 10~ TRANSITION FROM lYPE 1 ROAO SECTION TO TYP,E 2 ROAD SECTION (SEE SHEET ..-C::Vl -; r- .·~ / ! ,o<l. ~'!¥ ' ( #- I ~ie ~i:li ,- 11+50 I .. , .'I t, -:I~ 0 !• 1 r l J N't-- a:)tq "'"" ~~~ 12+00 .yo_-' : I i ..... ,...,!-"l-,..;!-: !.Of . ~~~ ~~~ ! I 12+50 r .AF'fRO)(~TIE DAYtiGHT OF CUT /FILi.~OPE~_5l):Pj \ _____ 1_~+.90---·-.. \ \ ~ .·< " ~ \ vc --; ~ ... ~nn ~,,.., N ~ ., ,.., + ,.., ,.., - t ,.-,I ,...., "'"' ~~~ -:"(0 ~: ....... ~!~ ol• -:,~ ~~ <-i' ..... . a> .o cil-: <{)' ~~ ~-· N' ~~ ~~ ~cD ~;; "'' ... -!:~ ,.,-,.,;~ -I -· -·~ -~ -I--1----1--I I 13+00 13+50 14+00 14+50 15+00 15+50 40 E==l 1=04 1 INCH • 40 FEET / "' -~ + "' - Vi ~ i "I"' ~i8 ~~~ ajC! ~~~ --9 ~ --1-j_ 16+00 80 .... :g -w u ~ .., .... ·"' ~,0 _o - 16+50 ~\ 'V' / ~i ~I } I I ' I I \ ; .\...WERtl.ousE SITE --+- 'I'SEE S~ C5 . 1 ~ \ ' i ~~ ' ~'~ ·:j: : I PVI STA _,.__ 17 +53.27 PV1 ELEV = 100.43 i>..o . .; -10.09 + ! i- '-1 / t / ! ; ;) -/.:; / ' I / ! _f;~-r,;: ": ., N -~ ~ ,., ., .... "' -.; <{) .. w + 0 Vl u !!! "' ~ ~ w <ii ~ ~ ! I "*:!~ ! ~-~ -:~~ ol• .... 1 -I.; ..: G'l:oi tD ;u;; ~2 ~ "'·a> "'a. "' _L. 1 7+00 17+50 18+00 ... ::g ;:~ N l ~i~ ~;a ... 0 ~~ lrii 0'1 ... .,; ~~;t "'t~ .,, ,....;fiJ .... jl _, 18+50 19+00 19+50 CONCEPT U AL DESIGN NOT FOR CONSTRUC TION V> z 0 Vi ~ "' w ~ ci z 0 c: ... ..... ;;: 0 a.: ~ ~ z j ~ I ~ 0 a.: Ill Ill ... u u <I( z ~ :I --II' 0 ~ ~ "' -~ ~ ~ Q I I ,, " :tl) V) : N ~ ; ;-r:- 0 0 :~C) .~- ~ ~ ~ .:: " ~ g ;:) "' en "' "' .; > < .. ,. :d " .. " !il ~ >II ~ ~ g 1 M ~ "' 0 (J ~ . ~ ~ 1--u ... ..., 0 a.: ~ u 0:: 1--u ... ..... }~ c >-X a.: ... > 0:: z <I( i5 ~ DESIGNED: DRAWN: CHECKED: 0 .. • 0 ~ • 01 c '1: ~ Cll • • .. 0 c • 1-- JOG JOG MOO SCALE: AS NOT(O FILE: TK(_O(S.DWG Sheet c 1.2 OF ·' \ ) .... ·:x -~~: 6 ttrG-91JfG (1..06) XV.!! OG)G-9~2 (1.06) 3.NOHd ~WIS3Q ~NIH3:iiNI~N3 ·-.:: /r: I / I V I I' 'I/ •, I I J/ I I I V 1 II I I I I I I I I I I / , I I I I 'I I f / ../ " w (I) :::J 0 J: "' w ;o 0 a. &O'i66 V!IISV'lV '3~VHOH.)NV OlC 3J.IOS 'S.AV mJCC J.S3Jl C091 o - <( -. o-<t:O Ult- (ll W ww u:z: UUl <( w zw <~ "' I SNOISIAJ!I ]1¥0 'ON 3: w > z ~ 0.. 0 <( 0 a::: 0 IJl -.1" IJl w () () <( w :.:: w ...J <( <( ...... () z IJl DII•DI'f' ••llu1•ds ••IIDU•J. l <> <> 0 0 ~ 5l 5l 0 ~ "' ~ 1::13ro~d ::ll~l::l3130~0AH ~3AI~ N'f'IONI "J ~I t-1') -. ... i;! ~ ~ Ej 8 £ ~ ~ z z "' ":i u ... 311.:10~d ON'f' N'f'1d O'f'O~ SS300Y 3>1Y!NI ~ ~ ~ ~ ~ 2!i ~ X <5 0 Ul ..: 0 -NOI1J ntJ1SNOJ tJQ_j lON N~IS30 lVnld3JNOJ <00> -'" ...:r-i en NOlte .-6 ;:6 II II +~.,...: N ~<0 ul~ w lii IIi:, II g ~~~;;lei"' oo . ll.ll,itit" :z::z: QQ :z::z: oo "'"' tO~~ !~:!~ I I"' ~ i:.. ' ~~q:.:: ;tit" 0 0 0 0 ci 0 ' Z''~tl !J:li\3 ~ 0Z 'L6+8 :s:>l\3 8 0 0 0 "' LLT~l '3:wl I on t+e :s:w3 60'L I+9 :~· 0 0 N .. '" N 0 0 "' l{ .. 0 0 I ··~n z·en B6'Zt ~ 0 0 ~'l t l + '" 69'Bt ~ o·o~l ZL'Z~ ~ 0 "' z· ~~~ + "' o·K ~ ~B 'L~~ 0 0 o·L~~ + "' 0'09 ~ LB'Z9L 0 "' z·zg ~ + .... ('(91 88'L9L 0 0 9T9~ .t fi: z ·gg ~ 0 ~ 06'ZLL "' ., ~ ·u ~ + ., <D ~ O'tL l LL'UI 8 B'~LL + "' ~S '6LI ('BLL L9'0BL 0 "' O'OBL + "' LO'~BL O'OBL I:O'LBL 0 0 0'6L L + "' 9'8L ~ BB 'OBL 0 "' Z'6L L + .., L'BLL tL'OBL 0 0 B'6LL + .., 9t'OBL t '6LL 9B'6Ll 0 "' Z'6L L + .... O'BLL 90'8LL 0 0 v 'LL L + .... LS'LL L Z'SL L 6Z'LL L 0 "' 0'9L L + N L'9Ll 0 0 + N w =:! ~•·os~ ·a L '06 ~ IJl -.1" IJl w 9 ~. ~6 ~ () ~. ~ 6 ~ () <( g~·~s~ 0 w w 0 :.:: 0 '·61 + ...J 0 <( <( ...... () z IJl 0 0 0 "' .., "' \ ~ ~ 1"-t- -$-t, '\" ' CD INTAKE STRUCTURE -PLAN VIEW SCALE: 1" = 1 0' 130 110 TWO NEW FISH PASS CELLS .// · .... i ~ '! i \__ ElOSr[NG ~ FISH~ :! i r i: ~ / / ' ' ,I' DIVERSION STRUCTURE ,- -----------r :I INTAKE ACC~S,S ROAD (SEE SHE?" <;1.3) ' ,.....__ LIMIT • ""-or i / CUT/FILL l / ' ' ' ' ' FISH !?ASS LEASE SITE - - -,_ -- -~ L _!\D_b_ \Q~~ I 10 1 INCH -5 FEET 150 ~~-=~T-1~~---~· 140 130 ' 120 110 100 INTAKE STRUCTURE -SECTION A-A SCALE: 1" = 10' EXISTING FISH LADDER I HEAD WALL (APPROX) ORIGINAL GROUND SURFACE EXISTING FISH LADDER (APPROX) 10 20 1 INCH : 10 FEET 10 20 1 INCH • 10 F"£IT z 0 I-zu G::::) (f)O:::: WI- OifJ z _jQ <Cu ::::) 1---0:::: o_o Wu_ u Zl-oo uz "' z Q ~ "' 0 r:::: ... !:< c 0 ~ - Ill z 0 ;:::: 0 "" Ill z 0 ;:::: <I( > "" _, "" _r z i:s ll. "" 0:: ~ .... 0 ~ 0:: .... Ill "" ~ <I( .... z - -I I 0 ~ " "' -~ : ~ " I I .... "" "'"' -;-~ 0 0 ee "'>< z .. 0"' = .. 0 ;; ~ g "'" "" ~ ~ .; > < .. "' ~ j " < " ,_. .; "'" "' .. .. 0: 0 "= : :g ~ -< .... 0 "" ...., 0 0:: ll. u .... 0 • ii< u c .... 0 "" • _, .. l~ c: 'i: lo:: ll. 0 Ill >-:I: • • 0:: .... "" u > c: ii< • .... z <I( i5 ~ r ~rr •L ~<L1 DESIGNED: JOG DRAWN: JOG CHECKED : MOD SCALE : AS NOTED FILE: II c2 '. 1 OF ', -- / -_, I 6 U·2-91i2 (L06) XV .:I £01i66 VXSV'lV ·a:!>VHOH.JNV 02 .. 2-U!iZ (L06) 3.N0lld OTC a.LJOS '3AV QH&& J.S:!I.M. &Oii1 N91S3Q :lNJH33NI:>N3 • 'OU! ·, I I I I I \ I I I I I I "' I I , ::.::~ I I \ u u 1 I ~~ 1 I ~5 A I a.>= I I ig I il z"' 1 A ot:l _J 1 I !i:5~ , I I / / OU\1-)~/. ----r---_. ....,.""A .............. E w ~ ,_, .. "'o !;2~ a.~ ,\!( . I v t' -1 ;, I I :-.... . , I 'h ., '"· ' ' • . SNOISii\3~ ' '· ~ w 5 z 5 CL I-z w 2 0 z (.? ~ ::J <l: :.:: u 0 w I- (/) _J z <l: w u CL (/) OJI•OIY '•lluJ•ds ••'lou•.l .L::>3f0~d O l~.l03130~0AH ~31\1~ NVION I -( 311JO~d ONV NV1d >tOO.LSN3d 31VO "ON -OllJ n ~lSNOJ ~OJ lON N8 1S 30 l'v'nl d3JNOJ 113 ~v 1"£8+6 N011W1S 6 "£9+0 ~:l01SN3d HlVlS a· Ll+O NOI!V!S 11VMO'o'3H 3 ~'o'1NI £ 9 I +O NOI!V!S ~ i ! \ ( \ I i I I I I \ \ i l 0 ~ 0 0 l !:! J 8 z ... \,l ~ V> '"" Q Q 0 0 "' <D ~ j i ~ q ~ 'Q 9 ~ :g • ~ 1'1') 8 V> z "" ~ U .._ ~ [:;3 ~ < :I: ~ 0 Q u "' £"£01 0 "' 1"6 01 + £"601 0 0 ~·o 1 1 + 1"8 0 1 0 "' ~·eo 1 + 0 ~"601 0 0 1'01 I + ~ r ·o , 1 0 "' ~·I I L + "' £"£01 0 0 ~·~o 1 + "' L "ll I 0 "' I "'' I + "' v "O IL 0 0 9 "1 LL + "' '"'" 0 "' g·~l I + .... 6 "1 11 iil 0 0 L" I I L + .... 1:; 1:' ~ ~ v ·tl 1 0 "' 0">1 I + "' 6 "1l0 L 0 0 6 "Cll + "' 1>"9 1 I 0 on 0 "£1 I + on ~-~~I 0 0 ~--lL + "' 6 "1>1 L 0 on O"C I I + • r ·~~ L 0 0 L"£~ I + .. v ·I~L 0 on ~-£1 I + "' t "9 1 I 0 0 g·o ~l + "' 8 "9 1 L 0 "' 6 "£1 I + N 0 0 + N 8 "8 1 L 0 on 1"61 I + 0 w w :.:: _J 0"6 LL <l: <l: I-u z (/) ...... ' .... ' -.... '·· enz-g~z {LOS) XY4 O<:t<:-9~2 (LOB) 3N011d ·_:.:..: '·· ...... " -:.:-. ' ' ., ·::. ..... ' " .,., ··· .... ' --- '· 0 "" ~"i ~·~ «il\ ;;;.., ~l)l 0 '·· ·. 0 + : .... ~ ':-., "' .... ' ' COc;66 V)ISV'lY '3DVMOH:)NY OlC 3:~InS ':fAY OU.CC .I.S:ill. CO~l JlVO 'ON ~ " ' A ' ~-. '· \ ·, \ .. / ' I ~ w > z 5 CL _.,- :;;.;.-<, -, Q\1.::1!' 1-z ~"yt~6\l.:l)5 w ~\ . ' :::; ' z 0 <:> "<t ::J <l: .... :.:: u 0 1-w VJ ..J z <l: w u CL (/) I I / DJI•DI'f' '•15UjJdS ee'IDUeJ. 1:! 1:! g § ~ " !j? ~ N J.~3ro~d ~I~J.~3130~0AH ~3AI~ N't'IONI ~ 9 PI!"OJd :g • ~ w f'0 0 8 .c "' "' z z "" ~ u .. 311.:10~d ON't' N't'1d >I~OJ.SN3d f;l ~ ~ "" ~ "' :z: (J G:: 0 0 0 (J "' N8 1S3 0 lVnld3JNOJ 0 0 + "" O:W "'"' 0 ;<::> .oo "' a. I + ,... 8 ·--"§7§9"""" + ,... ~ 9'6T ~ 0 'i "' 'i ?'9L + "' i5 "' r ·te 8 -~7§9' + "' 9 'l 6 0 "' t ·ei; + "' w ~:.:: ~~ ?'O Ol 0 0 6 '00l + "' 9 '00l :il -T6bT + :! l'ZOl 0 0 t 'tOl + .. ·-s·W~ 0 "' """"§"'iOTj;!; n .oi 0 0 t ·ol·l + ..., f soc 0 "' s·tT l + ~ 0 "' + w o=! 0 0:: ·o "' + (/) ~ z·eol 0 (/) w u t·so l u <l: 0 w 0 :.:: w "t 7 0L l + ~ ..J 0 <l: u z (/) 0 0 0 0 0 ~ N 0 "" "' ~~--~-~ .. ' ' '···· 61,.Z:-9c;;2: (L06) XVd OZ>Z-OOZ (L06) 3NOHd NDJS:Ja DNI H3 3NI DN3 e 'OU! 'B)! -......... _~ -.. \ ' ······- ---~~--- £0<;66 V)ISVlV ':!I~VHOH:JNV 01C :!I.LIOS 'XAV m:IEE J.."S:::!I.M. £0C..J SNOISI!(J~ 31~0 ~ ~ !? !? ~ ............ o)l•ol'., ••llu,~ds ••»~ou•l l ~ lOJrO~d Ol~l03130~0AH ~JAI~ NYlON I """" i:i .... z w '-' SNOI.LYA313 ONY NYld J.LIS >I NY.L J !>~ns ~ U\ ~ ·oN ........ NOi l Jn~lSNOJ ~OJ lON N81S 3 0 l'v'nld3JNOJ '-' 8 0 " "' ~ ~ ~ • ~ ~~ :Z ~ u ... ~ 0 ~ .... r 0 0 0 0 V1 ~ ~ !? !? ~ 3: 0 _J u.. Q:: w 0 > 0 ~ z ~ w w <.:J _J 0::: <( ::::> u V1 V1 0 ..... ~ z <( 1- w w <.:J _J 0::: <( ~ u V1 (f) RIVER BANK 8 POWERHOUSE -PLAN VIEW SCALE: 1" = 10' • POWER LINE ANO CONTROl~ {BURIED) TAILRACE LIMIT OF ·,,{CUT/FILL ,--WORKBENCH -SWITCRGEAR GE;NERATOR TURBINE STOP LOGS/ FISH BLOCK ' 110 100 90 80 ~OWERHOUSE 4 SCALE: 1 .. = 1 0. FINISH GRADE (ASSUMED ~:1 SLOPE) 10 20 1 INCH = 10 FEET 10 20 1 INCH • 10 FEET z 0 f-zu C)~ (J)0:::: Wf- OifJ z _JQ <(u ~ f-0:::: D._Q Wu_ u Zf-oo uz II "' z 0 ~ "' ~ 0 0 0 c " C/1 z 0 i= <:( > ... ...J ... c z <:( z I~ ... 1- iii ... C/1 :;) 0 ::1: ll< ... ~ 0 D.. ~I I DESIGNED: DRAWN: CHECKED: SCALE: FILE: _ .____ "' .. "' I " "' "' ;:: 0 e " < .. :: 0. ~ " t ~ '-"' "'"' "' .; > < <"' § j " < " ... .; "'" ., < " 0: 0 " 0: 0 " "' z -< 1- (.) ... -, 0 ll< D.. II (.) .X • ii: II 1-" (.) ... • ...J Ill 1~ 1: 'i: £11< Q. c Ill >-::1: • • ll< .X ... II > 1: ii: ~ z <:( c ~ JOG JOG MOD AS NOTED TKE_DES.DWG Sheet C5.1 OF f ' / / / / / X / / / / / -1J / START ATV TRAIL ALONG POWERLINE TENAKEE AYE. (1) ~OWER LINE TRAIL -PLAN VIEW SCALE: 1" = 40' •,v-;~ "/ I / / .. / I / / / •/ -1 /.' ! / . ,. j·f / / /" / / ' ' /· / uss 2459 ' / ~ ' ' ' \ / / / X I ! v \ I / I I I ' / / / /· i/ ' ' / I I / / / / ) A ' ' uss 6855 / 1/ ' ' ' ,~· " _~._ / ' . ' ' ' ' )" f /// ( / / (.) c: _.Ll -:A V> z 0 iii C5 "' "-' ~ 0 z ~ Q ~ z ~ z G f:j . 0 " "~ .. .. "'" I I "'"' "'" "'"' t:'r:' 0 0 ee n :c 0. ;: " "' ... " -0 :. " '.fJ g; .; > .., .., "' il j ".., " ... .; Ill " "'.., ~ 0: 0 ":c 0 w "z ~ .., PVI STA = 10+85.87 ~ _ PVI ELEV = 157.96 ;:;:: t; PVI STA -8+8 1.83 A.D. = 5.00 0 LoJ PVI ELEV = 144.46 K = 20.01 f 0 260 .A. .a ~ .a ~ ~ ... ~ A.D.=-9.69 o:: K = 20.65 1 00.0000' VC !i II. ] <(0 u • 240 .a TZ ~ .--~ .,...-200.0000' \IC 'i iii: .!! ZN 1-C ~ LO ~.,... ~ • 220 .. .. .. ~ --~ .. ' :ri \!5 .; ~ II. 0 -' 1:. eli ~ ~ ~ I.._ .J~ ~ 200 ~ ~ .a --.a .A · _..... · · .__.. ~ ci; --.• f I o • o:: II. ...... .-. .-.. ... § ~ Ui C,j Vi ~ ~'; e en ., ., u ~ u 65 :;;(o :r • 180 -___ ..... ~ A.D. = -13.0~ K = 6.~ ._ ,t ~ Gj 65 0:: o:: ~ •. ... <( ... 0 ~ tr· 11-11!1% ... :;:; ~ i 160 ..,.. --....._ M' .. ...-_____. ~ 65 65 6.62% A !!: 0:: ... ~ ~ z 140 ..-.: ~I ...... . I . ,... "'.I 1., ...... :;,: I"! II ~ ~ ~~ ~ ~ ~ ~ 120 -~ ~ ..:1"1 ,_,.,1 ~~:;; -:': 8 II. Vi 8 ~ Gj 100 + -~-1 ~~65 80 ,, ----~01 ;; 6 II DESIGNED: JOG 60 DRAWN: JOG 40 ~ ~ CHECKED: MDD I I SCALE: AS NOTED FILE: TKE_OES.DWG 4+00 4+50 5+00 5+50 6+00 6+50 7+00 7+50 8+00 8+50 9+00 9+50 10+00 10+50 11+00 11+50 12+00] '-- ~heet '" 80 CONCEPTUAL DESIGN 1INCH=40FEET NOT FOR CONSTRUCTION 1 . 1 ' ' ' ( / s/ ( ! 8 POWER LINE TRAIL -PLAN VIEW SCALE: 1" = 40' / (J / ! / ' ' ! ( i 14+00 14+50 .. ·· 15+00 / I , I ) (' / / 4,/ j / ... ·-" / 7 '- 18+00 / <o.,.Oo / / / / ,. ... / / / / .. / / / / / ,, / / _.) I / / I / / / / I ,.) ' ) .I ,/ I ~ .. \ / ( ' ' j 24+00 I / ( II () 0"' "' - .~ .. " "' "' I I "'"' " " "'"' "'>< z .. 0 .. ~ ~ " ~ g ;:>" (11 "' "' .; > < < " Q (11 0::! ::l .. .... oi (11 c.> 01 < " 0 0: "= ~I I ~ "' "' 0 " I ~~~ "' z 0 ~ "' ~ 0 z "' ::! .... .... 0 0 "' Ill: ..., D.. 0 HIGH POINT ELEV = 242.62 0< HIGH POINT STA -20+09.46 ~ D.. ~ PV1 STA -11+$7.~ PV1 STA • 20+41.05 ocf 0 • PVI ELEV = 237.17 PV1 ELEV = 243.58 z ~ ~ A.D . --9.27 A.D. --12.74 j 0 K z 10.79 K -7.85 D.. ~ ri "' Ill 100.0000' vc 100.0000' vc f : } ~ i c Ill G) 10 -I >- "' "'"' o-., :;( :r • "!r-::::"1 ;;;~ :;!:ll Ill: Ill:~ ~"'1 +~ +• atcxi ~ w 0 I.D +;:; CI)N mN +P') LaJ > C OCX) r-.N -.,...~ ON z -. ,..:~ -.. w .. N.. _ Ill: I- ";'"' .. w !'l~ !3 .. w ..J z ~C. !3~ ~ ili !'l~ o: <l .. ili ~ "' -ti tJ ' ----~ ~ G:i G:i ' ----~ - DESIGNED: JOG DRAWN: JOG CHECKED: ~DO SCALE: AS NOTED FILE: TKE_DES.DWC 15+50 16+00 16+50 17+00 17+50 18+00 18+50 19 +00 19+50 20+00 20+50 21+00 21+50 22+00 22+50 23+00 23+50 «l 11HCH•40ft(T BO CONCEPTUAL DESI GN NOT FOR CONSTR U CT ION Sheet E 1 .2 OF ... / " ( ' I \ 0 POWER LINE TRAIL -PLAN VIEW SCALE: 1" = 40' 260 240 Nl ~ ~ "' 220 POWER SCALE: X<§> 4i ·-/ ~,--... / '- 28+00 / / ....... "' 'D "' 0 it ., ~ gj + ., "' + N "' w "' ~ ~ ~ 27+00 27+50 28+00 28+50 29+00 / / ..· LOW POIN'r El.EV = 243.77 LOW POINT STA = 29+68.29 PV1 STA = 29+59.06 PVI ELEV = 242.06 A.D. = 14.20 K = 7.04 100.0000' VC "' "' 00() "' g: .,; ... + ... "' ON ~ .., .. w ~~ 29+50 30+00 i .. / HIGH POINT ELEV = 247.13 HIGH POINT STA = 30+ 71.37 PVI STA = 30+71.91 PVI ELEV = 248.59 A.D. = -11.70 K = 8.54 100.0000' vc O!o 0! _,... ;:; ~~ + g"' ;;; .. w ~ ~~ 30+50 31+00 40 80 I INCH "' 40 ftET /' ·J2+do ./ ., 'D .,; ... "' w u ;;:; 31+50 :' /) ./ 32+00 32+50 33+00 I I ! ..:J ' j / 33+50 / ' i ' / ; ' PV1 STA = 3-H37.58 PVI ELEV • 226.96 A.D . = 3.94 K = 25.41 1 00.0000' vc .... "' ' ~ ~ "' :!!! .... ... J ~ / •' ""'"<it z 0 1-zu 0=::) (!)0:::: wl- o(f) z _JQ <r:u =::) 1-0:::: Q_o Wu_ u Zl- 00 uz .... :::i + Ol'l ., Iii ~ 34+00 34+50 35+00 V> :z 0 Ui (t; "' w ~ c) z I 0 c:: ... ...J G: 0 0:: IL 0 zo <(0 + Zlll ~, ILO I- lo I Ill .... + _, :; ...... I-<( ........ zCII ::::; 0:: ... 3: 0 IL DATE· c"' "' -.. .. 01 N I I "' "' "' " N N -;-r:- 0 0 e.e "'>< z < 0 ... :::: 0. .!::: ·" t g ::> " rn "' "' r.i ~ ::! d "< " .. r.i rn " .. li n i! :":::: ~ . 0 u z " z w . -< I- () ... ..., 0 0:: IL () iii: I- () ... ...J l~ lo:: 0 >-:J: 0:: ... > iii: z <( 0 ~ DESIGNED: DRAWN: CHECKED: D Jt • D c • Dl c: 'i: Q. Ill • • Jt D c: • I- JOG JOG MOO SCALE : AS NOTED FILE: IKE_DES.OWG Sheet E 1.3 OF } ....._ / / " ,.< ' I / / / .' / 36+00 · .. ·· I / ,/ I ! i ../ :/ / / /,,. CD POWER LINE TRA IL -PLAN VIEW SCALE: 1" = 40' 260 240 220 200 180 160 140 120 100 80 60 ... N :!!: .., oti + N "' N .., .;; Vi ~ ~ PV1 STA = 35+82.14 PVI ELEV = 224. 10 A.O. = -12.84 K = 7.79 35+50 PO WER LIN E SCALE: 1" = ,.- _; ·~; ,.····"' _I / I / / . • I ; I ~·I ?; ( ) '·· : ' / / -·· / ( ' I ( J / i 38+00 .. ' .• 1 / ; ' -' / / 1/ ... / ,. ; / I ~· / i _,., I ... ·· 38+50 39+00 ' f .l!/11 I ' I,.··. II I .. .. .. I. / I I I / .- ' ) ... 4ll+'f 4 1+02.~5 / / t ,J 39+50 40+00 40+50 41 +00 41+50 42+00 42+50 43+00 43+50 "' 80 1 INCH "" 40 FEET / / ·I I I , I ·./ , j .· I 4f+O z 0 f-z u G =:) UJ O::: w f- oUJ z _jQ <Cu =:) f-er:: o_o WLL u Z f- 00 uz ~ ci z I ... ... L;: 0 a: a. 0 zo c(O + zon j..t a.o 1- 'o l o .... -on ~, 1-c( ...... z VI ::; a: ... ~ 0 a. D£SIGNED: DRAWN: CHECKED: SCAlE: FILE: 0"' " -.. .. " " I I "" "" " " r:r::- 0 0 ee "'" z < 0 .. :: "' 0 " t g 0>"' Ul "' "' .; > < <"' ~ j " < " .. .; Ul" "' < .. "' 0 ":c 0 u "' z -< 1- (.) ... ...., 0 a: a. 0 ... (.) • ii2 0 1-c (.) • ... ... Ill ... c }~ -.: a. 0 VI >-:r: • • a: ... ... 0 c > • ii2 ... z c( 0 ~ JOG JOG MOO AS NOTED TKE_DES.DWG Sheet E 1 .4 OF City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report 'l Polarconsult Alaska, Inc. APPENDIX B-LIDAR SURVEY DELIVERABLES • Two-Foot Topographic Map of Project Area • Black & White Intensity Image of Project Area November 2011 -Final Report APPENDIX B ST.O.iE TiOEI..AI'lDS --~~~ac ··· tHAf~.BOR) ' . "·, ~ .. ...... '• ', ~---~ '-...... ·'-~'. "'·~..,1- ':tP. "...>. - / \'<!>a<>,. /-\,'!;! " / ' / ""®····. '•_ ~ /:·;·. 2 -FOOT CONTOUR FROM LIDAR SURVEY ( 1 0 -FOOT MAJO R INTERVAL) SCALE: 1" = 200' l j ·,,1 ~-·"v-·· <. •, ~ . 5' ~ ' '-/ (. (--~· '·\ r .. ·. ){, 0 () _, \j 'I .. , / ~' !.§ill ~ i 21122 iJ' I _/ ~' \ \ 1''-:, ~~: _( _r:tf {} / ...... /--' ... r' \ ---( t, • f' ... Lr' c;· i'-;V~ !,._/ •\\. / \ ; . •, / :l -·-..... f • ..._ s--~j . " 0 ,, '.;/'i:~t· '.l ._, '0-_., .,. !;.:, • ..,,, ...... ,, (~·:"t -J 'v-.,..--.-:c~/'~--,-' ·i1"· ., '-,-0':,\J/ -~. . " _, i ?' /·':-v--, ->"'--. ..... " ... ·c..-__ ,_"'-_ \ 0-A'-b.\ \ -J.~~t , . o,._~a\ i I 1:: 1.,, \ I '\:~~t l \ 200 400 .l',a ,<1-\ . '\~o! \ !;OJ''::\ \ <.,1-a ··~ t? i" 6 •• ~ _,-,_ .. _s···.7' ,.) . '"'\ ·'. 1\ 0 y-· ./:-().--., )\_ \\ )\. /1 \ j' . ~\·~ .... )/ ) / .\ '( .:-;y \ -~-~~~ .(-.~ ... . . ;if' -.._,\, ,; '· ~ / -..-r~~,~j·",j \ r/ " ·-·-. . /-. . ' . J .:-''-; (" ~ ;:3~:-~ ;-~r ... ~:.~ \ ~. '.....}/ /_,/"...-_/ '·,\.,, ·, 1 INCH • 200 f'EET CONCEPTUAL DESIGN -NOT FOR CONSTRUCTION () z: 0 Cl ~ N ~ .... c: .. N N " I I ·-" "'"' "" a N N r:-r: iS ~~ " z: .. ~: :I l l ~ " > ; 0 ~ "' .... ., "' "3 !: 0 z: ::>" 0 "'g fl) ~ t:l c: li 0 . "' ~ ~ () ;I "' ... ~ Iii~ "' ., ~ 0 !; ~ 0 "= .. 0..., Q. 5 ~ ~ Ill a:: e~5 cZ I- zi z D ~~0 ... a::u • ~cu ..!! ~ el5l • fiLa::~ ca Ot-a:: c: a::ze~ 't: A.oo D. Ill l-UlL ~~e 1 0~~ D a:::>> c: ll..lllg: • .. ;:) Ill Ill: ~ ::::; DESIGNED: DRAWN:_ JOG CHECKED: SCALE : AS NOTED FILE: TKE_OES2.0WG Shee t LIDAR OF Vl< n-)>!:!! rCD 1"'1' .. 1"'1 ~ CD : )> II z 0 N;u g~ . c ~ . 8 a (') 0 z (') m ""0 ,, -1 c )> r 0 m CJ) G) z I z 0 -1 "T1 0 ::0 (') ''0 z CJ) -1 ::0 c (') -1 0 z ;u z z .... 1"'1 z U> ~ ..., :;o 0 3:: r 6 )> :;o (/) c ~ '.:< 8 8 ~ - ~:::l 1 rn --+-"' .. CD [ ::J c.n I I I~ 1;:1 I lg lg / / / -PROJECT PROPERTY AND SURVEY CONTROL DRAWING {INTENSITY IWAGE OVERLAY) -INDIAN RIVER HYDROELECTRIC PROJECT Tenakee Spring•, Ala•ka ENERGY SYSTEMS • ENVIRONKENTAL SERVICES e ENGINEERING DESIGN 1503 WEST 33RD AVE, SUI TE 310 ANCHORAGE, ALAS KA. 99~03 PHONE (907 ) 258-2 4 20 FAX (007 ) 2 08-2 ·<10 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report fl. Polarconsult Alaska, Inc. APPENDIX C-STAKEHOLDER MEETING • Meeting Summary • Meeting Sign-In Sheet • Meeting Packet November 2011 -Final Report APPENDIX C polarconsult alaska, inc .• 1503 West 33rd Avenue, Suite 310 ,:;-,,. Anchorage, Alaska 99503-3638 , ,_ ·- Phone: (907) 258-2420 ,-.· · FAX: (907) 258-2419 -. . MEETING RECORD DATEffiME: 3/10/2010 (3:00-4:00PM) SUBJECT: Indian River Hydroelectric Project-Pre Application Stakeholders' Meeting LOCATION: 400 Willoughby Avenue, Suite 400, Juneau, Alaska ATTENDEES (COUNTER-CLOCKWISE FROM SPEAKER): Joel Groves, Polarconsult (Owner's Representative) Art Bloom, City of Tenakee Springs (Project Proponent) Carol Goularte, USDA, U.S. Forest Service (USFS) Shawn Johnson, Alaska Dept. ofFish and Game (ADFG) Carrie Bohan, Alaska Dept of Natural Resources (ADNR) Division of Coastal & Ocean Mgmt. Audrey Alstrom, Alaska Energy Authority (AEA) Dan Bussard, ADNR (Water Section) Jim Anderson, ADNR (Land Section) David Lockard, AEA Doug Ott, AEA Jim Ferguson, ADFG Jackie Timothy, ADFG Katie Eaton, ADFG INVITEES (NOT IN ATTENDANCE): Sue Walker, NOAA-NMFS Phil Mooney, ADFG Stefanie Ludwig, State Historical Preservation Office Michele Metz, Sealaska Corporation Perry Edwards, USFS The stakeholders meeting was convened at 3:00PM, followed by introductions ofthe attendees. No stakeholders were present on teleconference. Mr. Groves gave a brief overview of the project history, technical details of the proposed project, and a current understanding of the resource issues pertaining to the project and major permits required for the project. (refer to the meeting agenda and information packet). The floor was opened to attendees to ask questions or offer their insights regarding anticipated permitting processes or issues. The discussion topics are summarized below. • Ms. Goularte stated that the USFS road is currently open only to off-road vehicles, and asked what type of traffic might be expected along the USFS road to support project construction and maintenance. Mr. Groves replied that a variety of motorized heavy construction equipment may be used for project construction. Project operations would normally use lighter vehicles. Major infrequent maintenance activities would require heavier vehicles. 10031 0-MEETINGMINUTES.DOC INDIAN RIVER PRE-APPLICATION MEETING DRAFT MEETING MINUTES POLARCONSULT ALASKA, INC. Ms. Goularte replied that the USFS would work with the City to permit this type of project traffic on the road. One particular concern is a failing bridge on the road in the vicinity of the project. Mr. Groves clarified that the bridge in question was above the portion ofthe road that would be used for this project. • Mr. Ferguson asked what type of intake structure was anticipated for the project. Mr. Groves replied that the conceptual intake design called for a low weir across the creek at or above the fish ladder at falls 4. A coanda-type intake screen would be built into the spillway downstream of the weir. Mr. Groves provided a brief overview of what a coanda screen is, how it works, and why it is being considered for this project. Mr. Ferguson commented that such an intake may not have impingement issues for small fish. Mr. Groves concurred, stating that flows down the surface ofthe intake screens would tend to flush any small fish off the screen, where they would be washed down the falls as under natural conditions. • Mr. Lockard asked what type of power line was being considered for this project and why. Mr. Groves replied that the type of power line had not yet been decided, but a buried cable was under consideration. An overhead line would be the other option. Preliminary review of system reliability, repair, and maintenance costs on a life-cycle basis favors a buried cable over an overhead line. The crossing at Indian River to the powerhouse would be overhead regardless of how the remaining line is constructed. • Mr. Johnson asked if the USFS had any water rights granted for the fish ladder at barrier falls 4. Mr. Groves and Mr. Bussard were uncertain if the ladder had been issued water rights. 1 Mr. Groves clarified that the USFS had defmed the minimum flow requirements for the fish ladder, and that the city's intent is to design the hydro intake to insure the fish ladder preferentially receives the minimum necessary flows during the migratory seasons. Mr. Bloom commented that the migratory seasons tend to coincide with high flows, so low flow management should not be a particularly critical issue. Mr. Groves commented that by co-locating the hydro intake with the existing fish ladder headworks at the top of the falls, the hydro project may be able to increase flows into the ladder during low flow periods on Indian River by directing in-stream flows from the natural falls into the ladder. • Ms. Timothy asked if the project fell under FERC jurisdiction. A review of ADNR's online water rights database on 3/18/10 did not return any record of water rights for the fish ladder. MARCH 10, 2010 PAGE 2 OF4 INDIAN RIVER PRE-APPLICATION MEETING DRAFT MEETING MINUTES POLARCONSULT ALASKA, INC. Mr. Groves replied that Polarconsult's jurisdictional analysis indicated the project was not under FERC jurisdiction. A Declaration of Intent has been filed with FERC to answer this question (docket Dil0-8-000). PERC's comment period for the DOl closes April9, 2010. • Mr. Lockard asked if any local permits would be required for the project. Mr. Bloom replied that he is not aware of any city permits that would be required beyond easements for the portions of the power line on city land. Mr. Groves mentioned that the project is not located within a state borough, so no borough- level permitting was necessary. Ms. Bohan mentioned that the project is not located within any local coastal management districts, so only the state-wide coastal management policies would be applicable. • Mr. Anderson asked if artificially enhanced fish resources received the same consideration in permitting as natural fish resources. Mr. Ferguson replied that for anadromous fish resources, the simple answer is yes. For resident fish resources, the simple answer is that it depends. • Mr. Lockard asked what type of communications were being considered for the project. Mr. Groves replied that communications were necessary between the diesel and hydro powerhouses to coordinate generation functions, and also between the hydro powerhouse and intake for head level control. Mr. Groves stated that communications could be achieved with fiber optics or copper, and the project budget assumed fiber optics. Mr. Lockard advocated for more communications capability over less, mentioning AEA's positive experiences with video capabilities at their newer rural power plants. Mr. Groves concurred, mentioning that sufficient bandwidth and power at the intake would help with project operations and could also aid the USFS' efforts to quantify salmon returns at Indian River. • Mr. Ott asked whether the project cost estimates were based on a unit installed-cost-per-kW of capacity, or if a more detailed method was used. Mr. Groves replied that the cost estimates were developed by estimating quantities for the various project elements, and applying unit costs for materials, equipment, labor, etc. The resulting estimate includes a 25% contingency. Mr. Groves stated that a more detailed cost estimate would be produced once the conceptual design was completed. • Mr. Ott (?) asked if there was equipment access between the project and Tekanee Springs, and how access logistics would be handled for project construction and operations. Mr. Groves replied that there was a well developed foot trail and suspension bridge from Tenakee Springs to the USFS road near the beach, but this was suitable only for foot traffic. Off-road vehicles can travel from Tenakee Springs to the beach landing at the USFS road along the tidelands during low tide. MARCH 10, 2010 PAGE3 OF4 INDIAN RIVER PRE-APPLICATION MEETING DRAFT MEETING MINUTES POLARCONSULT ALASKA, INC. Specific construction methods have not been decided, but generally, construction equipment and materials would be landed on the beach at the USFS road and all construction activities would be based from the USFS road and new access trails from the road to Indian River. Because the power line is located on the Tenakee Springs side oflndian River, equipment for line construction would be driven down the tidelands or moved via barge to Tenakee Springs for line construction. Construction personnel could be housed in Tenakee Springs and walk to the project site daily. Operations personnel would live in Tenakee Springs and walk to the project as needed for inspection, maintenance, and operations. If desired, a small garage could be built near the intersection ofthe walking trail and USFS road to house a vehicle(s) for project access. • Ms. Timothy(?) asked what the source of funds for the project were, and if they were already committed to the project. Mr. Groves replied that the current effort, which includes the feasibility study, conceptual design, and initial permitting, was funded with a Denali Commission grant administered by AEA. The City has also applied for additional funding through the FY 2011 round of the state's Renewable Energy Grant Program for permitting and design. The city's application was recommended for funding by AEA, but is subject to legislative approval and appropriations. The city has not started work on securing construction funding or fmancing. • Ms. Timothy mentioned that her office would develop a study plan and perform some fish trapping to assess the fish resources in Indian River. Ms. Goularte mentioned that the USFS had performed significant fisheries assessment work at Indian River in conjunction with their fish ladder project. Ms. Goularte mentioned that Mr. Perry Edwards with the USFS was familiar with their existing efforts and data. Mr. Ferguson mentioned that the USFS had completed a watershed analysis for the Indian River basin that included extensive environmental data pertinent to quantity and quality of potential fish habitat in Indian River 2 . There being no further comments or questions, Mr. Groves summarized the near-term project schedule. Polarconsult will prepare and submit permit applications for the project over the next month, and would advance conceptual designs in concert with resource agency comments over the next several months. Beyond that, the project schedule would depend on the level of effort and time necessary to secure project permits. Mr. Groves thanked attendees for their participation and adjourned the meeting at approximately 4:00PM. 2 Indian River Watershed Analysis, U.S. Department of Agriculture, U.S. Forest Service: Sitka Ranger District and Chatham Area Supervisor's Office. January 1996. MARCH 10, 2010 PAGE40F4 ~vtC #tC?t-£1 s:NtA 1'-P_~~ ./ ~ { 6-r, rJ M -fc {) \DA (-; rt>.f ;)&.v,· "'-C'jo«~ k@ {:;. fed. u. r qo 7 -1'17-'fl/8 ./ s·~GI.WV\ ~ ~ V\.)'0"\ (}J?(:~ (J_ sfAe~v.J n. jv~l\5"'"@ o.\c.){c". juv 10 7 f bf ~ L( 3-o ~ v C14,r?fri bttP~JV tl'J:r ~avv,{,/:p)]uv)(J4{ud,jrv' 'T&G·fl'f~ ~:."' · f/f-4-dre1 1/lsfro/V'-/lbfl t£(}1!-h~-< .;;t:tt'k.orJ ?7/-,So'/5 " Dq ~"~ G;-, ssov~-\);{) R do 11 i-dj:u;sq f ~~)<-/.;sh:-9 OJ ''( <S <:; • C5'(<; ~~'-I)£J( $"' 1..11 V /( _) 1 iJ; Ci 1/ c/pr S "''! @:__~' c, ~v / + dolr(§J_ atdecct;J 771-3/)~7 j ifrl• ff")lC//c/" tfJc:~kJif~jvr' ~~0 <?Jr;;:g w,2'~~;:~~~ ~~~~-lL\\cD AGENDA INDIAN RIVER HYDROELECTRIC PROJECT PRE-APPLICATION MEETING MARCH 10, 2010-3:00 PM 400 WILLOUGHBY 4TH FLOOR-JUNEAU 1. INTRODUCTIONS 2. PROJECT DESCRIPTION 3. PROJECT SCHEDULE 4. PERMITTING OVERVIEW 5. PERMITTING PROCESS & DISCUSSION 6. CONCLUDING REMARKS PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT CITY OF TENAKEE SPRINGS INDIAN RIVER HYDROELECTRIC PROJECT PROJECT OVERVIEW Indian River is located approximately one mile east of Tenakee Springs. Indian River has a series of 5 barrier falls occurring between river miles 0.6 and 1.3 above tidewater. The gross head over these five barriers is I 00 feet. The mean annual flow in Indian River through these barriers is about 137 cfs. Extreme minimum flows of down to 8 cfs can occur during late summer dry spells (July -August) and the winter months (December- February). Below barrier 5, Indian River is incised into a canyon about 50 to I 00 feet deep. The canyon walls are generally steeper along the west bank (the Tenakee Springs side), and less steep along the east bank, although rock outcroppings are common along both banks through this canyon. Recommended development of Indian River's hydropower potential is with a run-of-river hydroelectric project built along the east side of the river from the top of barrier 4 to the bottom of barrier 2. This project would be located on state land, with some of the transmission line crossing city land en route to Tenakee Springs. The USFS has constructed a fish ladder to improve fish passage in Indian River at barrier 4, and has also completed fish passage enhancements at barriers 2 and 5. TECHNICAL PARAMETERS Static Head Design Flow Penstock Total Dynamic Head Turbine Type Installed Capacity Capacity Factor Estimated Annual Energy Generation Existing Utility Energy Generation Transmission Estimated Direct Construction Cost Estimated Installed Cost Annual Displaced Diesel Fuel Continuing Diesel Consumption for Electrical Generation Benefit-Cost Ratio MARCH 10, 2010 60 feet 41 -77 cubic feet per second 1,550' of 30-42" HDPE 50 feet Ossberger Cross-flow 120-250 kW 87.1% 839,000-1,500,000 kWh 433,000 kWh 4,500 feet of Three-phase 7.2kV buried cable $1,752,000 $2,590,000 44,400 gallons 4,400 gallons 1.33 PAGE2 OF8 PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT CITY OF TENAKEE SPRINGS MARCH2010 APRIL 2010 SUMMER2010 INDIAN RIVER HYDROELECTRIC PROJECT PROJECT SCHEDULE -PRE-APPLICATION STAKEHOLDER CONSULTATIONS -SUBMIT DECLARATION OF INTENT TO FERC -PREP ARE AND SUBMIT PERMIT APPLICATIONS -FERC JURISDICTIONAL DETERMINATION -SITE SURVEY -REVIEW AND PROCESS PERMITS, DETERMINE PERMITTING SCHEDULE -PROJECT DESIGN SUBSEQUENT SCHEDULE WILL BE DETERMINED BY PERMITTING PROCESS MARCH 10, 2010 PAGE 3 OF8 PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT CITY OF TENAKEE SPRINGS INDIAN RIVER HYDROELECTRIC PROJECT OVERVIEW OF MAJOR PERMITS AGENCY PERMIT(S) REQUIRED STATUS NOTES Jurisdictional Submitted Finding of non- FERC Determination. 2/26/10 jurisdiction expected Corps of Application not May be eligible for Engineers Wetlands Permit. submitted yet NWP #17 USDA-USFS Project review. " - NOAA-NMFS Project review. " - USEPA/ADEC SWPPP (construction). " - ADEC To be determined. ADNR-Land Land lease & easement. " - ADNR-Water Water use permit 7 water " -rights. ADNR-Coastal Consistency review. " - ADNR-Dam None. " Safety - ADNR-SHPO Project review. " - ADFG Fish habitat permit. " - ADFG Wildlife Conservation. " - MARCH 10, 2010 PAGE 4 OF 8 PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT STATE INDEX MAP MARCH 10, 2010 o m F3 F3 FAIRBANKS ANCHORAGE LOCATION MAP PROJECT VICINITY MAP INDIAN RIVER • STUDY AREA (THIS PROE.JCT) CITY OF TENAKEE SPRINGS LOCATION MAP E3 0 2 E3 E3 MILES I L B 1' ·, PAGESOF8 PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT TONGASS NATIONAL FOREST BOUNDARY S16 S15 S21 S22 UPPER POWER LINE ROUTE C._,..,..-& ( 5, 900 FT.) """"""'-,-/~ ~/~OWER POWER '-/ / LINE ROUTE '-/ (4,400 FT.) ¥ DWNS/T£ 1 .. CITY OF TENAKEE SPRINGS 0 E3 E3 BARRIER\#4 (POTENTIAL INTAKE SITE) 1000 FEET ; BARRIER' J 1 j ~·r---------~------~ END OF 3-PHASE DISTRIBUTION TtNAK£.£ INLET ~ 1. PROPERTY LINES ARE INTENDED FOR INFORMATIONAL AND PLANNING PURPOSES ONLY. 2. CONTOUR DATA REPRODUCED FROM 1984 U.S. CORPS OF ENGINEERS STUDIES. MARCH 10, 2010 EXISTING FOOT TRAIL PAGE60F8 2000 PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT SECTION 15 SECTION 22 BA~IER #4 INTN<E LOCATION EXISTING USGS FISH LADDER ~E~4~TO P~S'Ji K ' 1,5 • BARRI[R #3 UPPER _eeWEIYtf~ l RQUlf" 5 ~ p! " ~IER #2 J ·-·-,.,.._ • .......,..... ~.,~~,.,_ ' ' ·~ ~" ' ~ " \ .. ~ ,....,... c.~ LOWER POWER LINE ROUTE 4.400 FT. MARCH 10, 2010 CITY OF TENAKEE SPRINGS 0 500 ~E3 FEET 2400' ACCESS TRAIL TO POWERHOUSE PROPOSED POWER HOUSE PAGE70F8 1000 PRE-APPLICATION STAKEHOLDER'S MEETING INDIAN RIVER HYDROELECTIRC PROJECT MARCH 10, 2010 CITY OF TENAKEE SPRINGS ~~~.~-··~-~--~~"~-~.~·~~~--~~ PAGES OF8 City of Tenakee Springs Indian River Hydroelectric Project 'l Feasibility, Conceptual Design, and Permitting Phase II Final Report Polarconsult Alaska, Inc. APPENDIX D-PROJECT PERMITTING DOCUMENTS • FERC Jurisdictional Determination • U.S. Army Corps of Engineering Permit Application & Documents • ADNR Land Lease Application & Documents • ADNR Easement Application & Documents • ADNR Coastal Project Questionnaire & Documents • ADNR Water Rights Application & Documents • ADFG Fish Habitat Application & Documents • U.S. Forest Service Coordination November 2011 -Final Report APPENDIX D City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report ~ Polarconsult Alaska, Inc. FERC JURISDICTIONAL DETERMINATION November 2011 -Final Report APPENDIX D 20100526-3076 FERC PDF (Unofficial) 05/26/2010 UNITED STATES OF AMERICA 131 FERC ~ 62,179 FEDERAL ENERGY REGULATORY COMMISSION City of Tenakee Springs Docket No. Dll0-8-000 ORDER RULING ON DECLARATION OF INTENTION AND FINDING LICENSING NOT REQUIRED (Issued May 26, 2010) 1. On March 1, 2010, the City of Tenakee Springs filed a Declaration oflntention (DI) concerning the proposed Indian River Hydroelectric Project, which will be located near the city of Tenakee Springs, on Chichagoflsland, Sitka Borough, Alaska, affecting T. 47 S, R. 63 E, sees. 15, 21, and 22, Copper River Meridian. PROJECT DESCRIPTION 2. The proposed run-of-river Indian River Hydroelectric Project will consist of: ( 1) a 6-foot-high, 30-foot-wide diversion structure, to be located at river mile (RM) 0.85; (2) a 40-inch-diameter, 1,550-foot-long penstock; (3) a 30-foot-wide, 40-foot-long, wood frame powerhouse, located at RM 0.55, housing a 250 kW turbine-synchronous generator; (4) a 50-foot-long tailrace returning flows back into Indian River; (5) a 5,900-foot-long transmission line; and (6) appurtenant facilities. PUBLIC NOTICE 3. Notice of the DI was issued on March 9, 2010. Protests, comments, and motions to intervene were to be filed by April 9, 2010. The U.S. Department of Agriculture, U.S. Forest Service, Tongass National Forest, filed a motion to intervene and comments on April19, 2010. The comments stated that the proposed project had the potential to affect Forest Service interests, but the comments did not relate to the issue of jurisdiction. No other protests, comments, or motions to intervene have been received. JURISDICTION 4. Pursuant to Section 23(b)(l) of the Federal Power Act (FPA), 16 U.S.C. §817(1), a non-federal hydroelectric project must (unless it has a still-valid pre-1920 federal permit) be licensed if it: 20100526-3076 FERC PDF (Unofficial) 05/26/2010 Docket No. DII0-8-000 2 • is located on a navigable water of the United States; • occupies lands or reservations of the United States; • utilizes surplus water or waterpower from a government dam; or • is located on a stream over which Congress has Commerce Clause jurisdiction, is constructed or modified on or after August 26, 1935, and affects the interests of interstate or foreign commerce. DISCUSSION 5. The proposed project will not occupy any public lands or reservations of the United States and will not use surplus water or waterpower from a Federal government dam. The proposed project would be constructed after August 26, 1935, and would be located on a Commerce Clause stream. 1 However, the proposed project would not affect the interests of interstate commerce, because the City of Tenakee Springs plans to sell the generated power to the Tenakee Springs Electric Utility, which is not connected to an interstate transmission grid. Therefore, the project does not require licensing under Section 23(b )(1) of the FP A. CONCLUSION 6. Consequently, Section 23(b)(l) of the FPA does not require licensing of the proposed project. If evidence to support the Commission's licensing jurisdiction is found in the future, Section 23(b )( 1) would require licensing. Under Section 4(g) of the FP A, the project owner could then be required to apply for a license. The Director orders: (A) Section 23(b)(l) of the Federal Power Act does not require licensing of the proposed Indian River Hydroelectric Project. This order is issued without prejudice to any future determination upon new or additional evidence that licensing is required. 1 The Indian River flows into Tenakee Inlet and Chatham Straits, tributary to the Pacific Ocean. 20100526-3076 FERC PDF (Unofficial) 05/26/2010 Docket No. Dll0-8-000 3 (B) This order constitutes final agency action. Requests for rehearing by the Commission may be filed within 30 days ofthe date of issuance ofthis order, pursuant to 18 C.F.R. § 385.713. William Guey-Lee, Chief Engineering and Jurisdiction Branch Division of Hydropower Administration and Compliance polarconsult alaska, inc. ENGINEERS • SURVEYORS • ENVIRONMENTAL CONSULTANTS SECRETARY FEDERAL ENERGY REGULATORY COMMISSION 888 First Street, N.E. Washington, DC 20426 FEBRUARY 26, 2010 Subject: Declaration of Intention for Indian River Hydroelectric Project Dear Secretary: On behalf of our client, the City of Tenakee Springs, Alaska, enclosed please find an electronic submittal of the Declaration of Intention for the Indian River Hydroelectric Project for your consideration. Thank you for your consideration in this matter. Sincerely, [signed] Joel D. Groves, PE 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net CITY OF TENAKEE SPRINGS, ALASKA DECLARATION OF INTENTION FOR THE INDIAN RIVER HYDROELECTRIC PROJECT SUBMITTED TO FEDERAL ENERGY REGULATORY COMMISSION February 26, 2010 prepared by polarconsult alaska, inc. 1503 West 33rd Avenue, Suite 310 Anchorage, Alaska 99503 Phone: (907) 258-2420 INDIAN RIVER HYDROELECTRIC PROJECT DECLARATION OF INTENT Declaration of Intention The Indian River Hydroelectric Project (project) is located at: State: Alaska Town: Street: County: Stream: River Basin Name: Tenakee Springs N/A Unorganized Borough (Sitka Recording District) Indian River N/A Township, Range, and Meridian: 47S, 63E, Copper River Meridian The exact name, business address, telephone number, fax number, and e-mail address of the applicant is: City of Tenakee Springs P.O. Box 52 Tenakee Springs, AK 99841 Tel: 907-736-2207 Fax: 907-736-2207 citytke@gmail.com The exact name, business address, telephone number, fax number, and e-mail address of the authorized agent is: Joel Groves 1503 W 33rd Ave #310 Anchorage AK 99503 Tel: 907-258-2420 Fax: 907-258-2419 joel @polarconsult.net The exact name, business address, telephone number, fax number, and e-mail address of the local electric utility company is: City of Tenakee Springs DBA Tenakee Springs Electric Utility P.O. Box 52 Tenakee Springs, AK 99841 Tel: 907-736-2207 Fax: 907-736-2207 FEBRUARY 26, 201 0 PAGE 1 OF5 INDIAN RIVER HYDROELECTRIC PROJECT DECLARATION OF INTENT PROPOSED PROJECT DESCRIPTION The proposed project is an up to 250 kW run-of-river hydroelectric project located on the Indian River approximately one mile south of Tenakee Springs, Alaska. The project would include the following major components: An intake structure consisting of an approximately 6-foot tall by 30-foot wide diversion structure spanning the creek near or adjacent to an existing USFS fish ladder located approximately at river mile 0.85. Apparatus to remove debris from the project water would either be incorporated into the diversion structure or constructed on uplands immediately adjacent to the diversion structure. The diversion structure would direct up to 80 cfs of water into a approximately 1,550 foot long penstock. The project would have a gross head of approximately 60 feet, and net head of approximately 50 feet. The project powerhouse would be located adjacent to Indian River at approximately river mile 0.55, and would house a crossflow turbine, synchronous generator, switchgear, controls, and related equipment. The tailrace would return flows back to Indian River. The project would generate approximately 1,500,000 kWh of energy annually, which would be transmitted to Tenakee Springs via an approximately 5,900 foot long three-phase 7.2kV power line. This project is a run-of- river project so there is no storage capacity. MAPS A Location Map and Project Map are attached on the following pages. The Location Map shows the general project location in Alaska, and the Project Map shows, in detail, the proposed locations of project features and location of federal, state and municipal land in the project vicinity. RIVER DURATION CURVE AND HYDROGRAPH Because this project is run-of-river, it has no storage or modification of flows downstream of the project. Therefore, only the flow duration curve and the stream hydrograph are shown. The curves are attached on the following pages. Hydrology data is derived from seven years of USGS stream flow data for Indian River, augmented by additional USGS data from nearby drainages with similar hydrology. JURISDICTIONAL ANALYSIS Navigability of the stream Indian River is not a navigable stream. Land Status The project lands are owned by the State of Alaska and the City of Tenakee Springs. Lands affected by the project are shown in the Project Map. Government Dam The project does not utilize waterpower from a Government Dam Interstate Commerce The project does not affect interstate commerce. Power from the project will be sold by Tenakee Springs Electric Utility to its customers located in Tenakee Springs. FEBRUARY 26, 201 0 PAGE 2 OF 5 INDIAN RIVER HYDROELECTRIC PROJECT DECLARATION OF INTENT Tenakee Springs is an electrical 'island' that is not electrically interconnected to adjacent communities or to any interstate electrical grid. N FEBRUARY 26, 201 0 PROJECT LOCATION MAP • II.ES FAIRBANKS ANCHORAGE MAP INDIAN RIVER • STUDY AREA (THIS PROE.JCT) 0 E"3 E"3 I ,. .. 2 MILES L 2'-- PAGE30F5 INDIAN RIVER HYDROELECTRIC PROJECT TONGASS NATIONAL FOREST BOUNDARY PROJECT MAP S16 S15 ' ' 0 E3 E3 DECLARATION OF INTENT 1000 FEET 2000 EXISTING LOGGING ROAD J--~~~----~~-----· ----------:::-::-:-t"::""::c-=----'-------'<--'--;;~fl------1 S21 [ S22 BARRIER #3 ·: I 1 -+1 I "f/~1-. ~·~~ UPPER POWER LINE ROUTE .,..-I. ~I. (5,900 FT.)~/" C. ~ S / PB1RRIER #2 ~/~OWER POWER .,/ / LINE ROUTE ~ / ( 4,400 FT.) ~ OWNSJT[ 1 .. END OF 3-PHASE DISTRIBUTION TENAkEE: INLET liQIES ' 1. PROPERTY LINES ARE INTENDED FOR INFORMATIONAL AND PLANNING PURPOSES ONLY. 2. CONTOUR DATA REPRODUCED FROM 1984 U.S. CORPS OF ENGINEERS STUDIES. FEBRUARY 26, 201 0 EXISTING FOOT TRAIL ' PAGE40F5 Iii -~ ~ 0 u:: Iii -~ ~ 0 u:: INDIAN RIVER HYDROELECTRIC PROJECT DECLARATION OF INTENT Average Daily Flows at Indian River Intake Site 300 250 200 150 100 50 0+-----~----,----,-----,----~-----,----,-----,-----,-----,-----,--- Jan Feb Mar 100 75 50 0% 10% 20% FEBRUARY 26, 201 0 Apr May Jun Jul Month Aug Flow Duration Curve for Indian River 30% 40% 50% 60% Sep Oct 70% 80% Duration (Percent of Time Flow is Equaled or Exceeded) Nov Dec 90% 100% PAGE 5 OF 5 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report 11-Polarconsult Alaska, Inc. U.S. ARMY CORPS OF ENGINEERS PERMITTING November 2011 -Final Report APPENDIX D Joel Groves From: "Speerstra, Linda POA" <Linda.Speerstra@usace.army.mil> Date: Monday, August 29, 2011 12:48 PM To: "Joel Groves" <joel@polarconsult.net> Cc: "Art Bloom" <artmbloom@gmail.com> Subject: POA-201 0-0758 Teankee Hydro Project HI Joel. Your information is well organized and easy to follow. I'll be reviewing the entire project under Nationwide Permit #17 Hydro Projects. We won't need to separate out by utility/roads etc. I've just finish reviewing it and have the following items that need additional clarification/information: Wetlands Delineation 1) send data sheets that determined the delineation 2) Include the methods used to determine the mosaic along with field notes to determine the ratios submitted. Site Plans 1) Include the potential landing sites for landing the equipment/materials ie; L TF and/or the beach access. Include the eel grass beds that you described near the beach access. HTL and MHW mark too. Project Access Roads 1) The description of the access road (the last 250 feet) station 18-20.50. You describe an estimated 250 cubic yards of fill into 1, 700 sq. ft of wetlands. I believe the fill would be below the OHWM oflndian River. Please clarify. 2) Will any of the roads be removed post installation? Powerhouse 1) How many cubic yards of material will be blasted in Indian River to establish the final grade of the tailrace channel? 2) Will sedimentation measures be used during blasting? 3) How much sheet pile and/or concrete will be required to stabilize between the powerhouse and OWHM of Indian River? Power Line 1 )The narrative indicates up to 15% of the power line would be located in uplands. Additionally a stream crossing would be required. Does the amount of fill include the stream crossing to bed the culvert? If so, reduce the wetlands fill and add to a category called waters of the U.S. (essentially below the ordinary high water line of a water body) Show the flow of water in the drawing too. Once you've revised those numbers please add it to the Table in the project description. If you have any questions please give me a call. Linda Regulatory Specialist Sitka Field Office P.O. Box 16 Sitka, AK 99835 Page 1 of2 9/16/2011 907-747-0658 -----Original Message----- From: Joel Groves [mailto:joel@polarconsult.net] Sent: Thursday, August 25, 2011 4:59PM To: Speerstra, Linda POA Subject: Tenakee Submittal Hi Linda, How's review of the submittal for Indian River coming along? Thanks, Joel Page 2 of2 9/16/2011 • P.c?.!~~~.~~.~!!c~"~~T~~a, inc. l LINDA SPEERSTRA U.S. ARMY CORPS OF ENGINEERS-AI~ASKA DISTRICT Sitka Regulatory Field Office PO Box 16 Sitka, AK 99835 August 9, 2011 Subject: Supplemental Information Submittal #2, Preconstruction Notification Form for NWP#l7, Indian River Hydro Project Dear Ms. Speerstra: On behalf of our client, the City of Tenakee Springs, Alaska, Polarconsult filed a Preconstruction Notification Form (PCN) and supporting documents with the Corps of Engineers (COE) on August 31, 2010 for a wetlands permit for the Indian River Hydroelectric Project. The COE provided review comments to Polarconsult on September 14, 2010. Polarconsult provided a supplemental information submittal addressing these comments to the COE on November 4, 2010. The COE then provided additional review comments on December 17, 2010. To help answer these questions, Polarconsult and the City hosted a site visit on April 21, 2011 that was attended by the COE and other agency personnel. Polarconsult has prepared this second information submittal to address the COB's questions from December 2010 and the April 2011 site visit, and allow the COE to complete processing the PCN and issue a wetlands permit for the project. The following supplemental information is attached: » Letter Report describing wetlands delineations completed for the project, summarizing project design, and summarizing measures to avoid and minimize wetlands impacts. > Conceptual Design for the project dated July 29, 2011. » Conceptual Design for the project dated April12, 2011 (superceded by the July 29 conceptual design, provided solely for reference). » An updated mitigation plan (replacing the plan submitted November 4, 2010). » Updated permit drawings (replacing drawings dated October 29, 2010). If you have any questions regarding this application or the project in general, please give me a call at 907-258-2420. Sincerelv_ s/ Joel D. Groves /s Joel D. Groves, PE Project Manager ill Art Bloom -City of Tenakee Springs Project Manager 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 ·FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net LETTER REPORT DATE: August 9, 2011 polarconsult alaska, inc. 1503 West 33rd Avenue, Suite 310 Anchorage, Alaska 99503-3638 Phone: (907) 258-2420 FAX: (907) 258-2419 TO: Linda Speerstra, U.S. Army Corps of Engineers. Sitka Field Office FROM: Joel Groves, PE --Polarconsult Project Manager SUBJECT: Wetlands Delineation, Project Design Summary, and Summary of Measures to Avoid and Minimize Wetland Impacts; Indian River Hydroelectric Project; Tenakee Springs, Alaska CC: Art Bloom, Tenakee Springs Hydro Project Manager 1.0 INTRODUCTION & OVERVIEW l.l Introduction The City of Tenakee Springs retained Polarconsult Alaska, Inc. to develop conceptual engineering designs and perform related professional engineering services for a run-of-river hydroelectric project the city is developing on Indian River. The hydroelectric project will supply an estimated 90% of Tenakee Springs' electricity/ eliminating approximately 31,000 gallons of fuel shipments to the community annually. The project will help to lower the extremely high price of electricity in the community. This letter report provides the following: 1. Documentation of wetland investigations and delineations performed to quantify wetlands impacts associated with project construction. 2. Provides a summary of the hydro project features and the wetland impacts associated with each feature. 3. Provides a description of the design modifications and strategies used to avoid, minimize1 and mitigate wetlands impacts associated with construction of this project. Hydro project features, footprints, and alignments described in this letter report are based upon the conceptual design drawings for the project prepared by Polarconsult and dated July 29 1 2011. These conceptual design drawings replace an earlier plan set completed April 14, 2011. The newer conceptual designs reflect revisions to the project that have been made to avoid and minimize wetlands impacts. The conceptual design described herein reflects the current development concept for the project, based on available technical and environmental information. These designs are subject to change as necessitated by economic, technical, environmental, and other factors as this project continues through the design and permitting process. 110809-WETLANDLETIERREPORT.DOC INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 1.2 Project Site The Indian River hydroelectric project site is located approximately one mile east of Tenakee Springs, Alaska on a combination of city and state land. The site is located within Sections 15, 21, and 22 of Township 47 South, Range 63 East, Copper River Meridian (see Permit Drawings). The project site totals approximately 4.23 acres (Table 1). Table 1: Summary of Project Area and Wetland Impacts by Project Feature Feature Total Area Area of Wetland Impact Volume of Wetland (acres) (square feet) Fill (cubic yards) Access Roads 2.00 Along intake access road: 7,000 1,000 Diversion I Intake 0.03 Diversion/Intake footprint: 1,000 1 100 1 Penstock 0.60 Trestle piers, on grade penstock: 1,500 100 Powerhouse Site 0.10 Powerhouse footprint: 3,000 1 700 1 Power Line 1.50 sta. 24+00 culvert crossing: 600 so incidental other (microsites): 9,200 750 TOTAL 4.23 18,300 + 4,000 1 = 22,300 1,9oo I 800 1 = 2,100 Wetland Impact Area Under NWP #12 for Utility Lines 9,800 SF (0.23 ac) Wetland Impact Area Under NWP #14 for Access Roads 7,000 SF (0.16 ac) Wetland Impact Area Under NWP #17 for Hydropower Projects 5,500 SF (0.13 ac) 1. Fill below ordinary high water line in Indian River The project site will be accessed from an existing U.S. Forest Service logging road (Road No. 7500) via approximately 3,200 feet of new access roads and/or trails. The project will feature a diversion and intake structure at an elevation of 120 feet on Indian River. This structure will be co-located with an existing fish pass built and maintained by the U.S Forest Service to establish a coho salmon population on Indian River. Up to 50 cubic feet per second (cfs) of water will be conveyed from the intake structure down to the powerhouse building via approximately 1,550 feet of penstock (pipeline). This penstock will be supported on trestles and located along and/or above the bank of Indian River. Approximately 4,000 feet of power line will connect the hydro powerhouse with the city's existing electric distribution system. The power line will cross Indian River overhead, and will run underground to connect with the existing overhead system near the small boat harbor. A small trail will be built along the power line route to provide access from Tenakee Springs for construction, inspection, maintenance, and repair of this power line. The project will not be directly accessible from this trail due to Indian River Canyon. PAGE 2 OF 9 INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 1.3 Wetland Delineation Methods The wetlands delineation for this project was completed using a Routine Level 3 delineation method, as set forth in the Corps of Engineers Wetlands Manual 1 and Alaska Supplement2 . The delineation relied on a combination of existing site information, new site information obtained for this project, and on-site wetland determinations in areas where existing information lacked sufficient detail to complete delineations at the mapping scales necessary for this project. Wetland determinations in the field were made using hydrophytic vegetation and wetlands hydrology assessment. Soil pits were not feasible during the April 2011 site visit due to frozen ground. In order to avoid misclassification of wetlands as uplands, hydric soils were assumed to exist at sites where the Wetlands Manual calls for the identification of hydric soils to make a wetland determination. The result of this approach is a conservative wetlands delineation for the project area. 1.4 Summary of Information and Investigations First, available existing information sources for the project site were obtained. Existing information includes: ~ U.S. Geological Survey (USGS) 1:63,360 scale topographic maps of the project area, 3 ~ Visible-band aerial color imagery of the project area, 4 ~ Infrared-band aerial color imagery of the project area, 5 ~ National Resource Conservation Service (NRCS) soil survey of the project area, 6 ~ National Wetlands Inventory (NWI) database, 7 ~ Corps of Engineers investigations letter report for Indian River Hydroelectric Project, 8 ~ Final Environmental Impact Statement (EIS) for Indian River Timber Sales, 9 and ~ Indian River Watershed Analysis. 10 1 Environmental Laboratory. 1987. Corps of Engineers Wetlands Delineation Manual, Technical Report Y-87-1, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS. 2 U.S. Army Corps of Engineers. 2007. Regional Supplements to the Corps of Engineers Wetland Delineation Manual: Alaska Region (Version 2.0), ed. J.S. Wakeley, R.W Lichvar, and C.V. Noble. ERDC/EL TR-07-24. Vicksburg, MS: U.S. Army Engineer Research and Development Center. 3 USGS quadrangle maps SITKA D-4 and SITKA D-5. 4 1 inch = 1,500 foot scale imagery acquired August 6, 2006. AeroMETRIC, US, Inc. 5 Alaska Satellite Facility. August 1979. University of Alaska Fairbanks, Geophysical institute. 6 USDA, NRCS. 2008. Soil Survey Tabular Database of the Chatham Area, Alaska; Soils of the Tenakee Springs Area, 1:24,000. (AK646). 7 U.S. Fish and Wildlife Service, National Wetlands Inventory. http://www.fws.gov/wetlands/Data/Mapper.html 8 U.S. Army Corps of Engineers. 1984. Small Hydropower and Related Purposes Letter Report for Tenakee Springs, Alaska. 9 USDA, USFS. 1979. Indian River Timber Sale(s) Final EJS. 10 USDA, USFS. 1996. Indian River Watershed Analysis. Sitka Ranger District & Chatham Area Supervisor's Office. PAGE30F9 INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 This information was supplemented with two field visits to the project site. Due to the remote project location, wetlands delineation field work was conducted concurrently with project evaluation and conceptual design efforts to economize on cost. Polarconsult engineers Joel Groves, PE and Michael Dahl, PE conducted initial field investigations from June 1 through June 3, 2009. Mr. Groves and Mr. Dahl were accompanied in the field by Mr. Art Bloom, the project manager for the City of Tenakee Springs. This field investigation was conducted to evaluate the project site for constructability; evaluate potential power, penstock, and access alignments; review proposed diversion/intake and powerhouse sites; and assess the presence of wetlands in the project vicinity. During this site visit, limited aerial reconnaissance of the project area was also completed. Field observations were used to develop the November 2009 feasibility study for the hydroelectric project. Subsequent to this field visit and completion of the project feasibility study, a UDAR topographic survey of the project area was performed in April 2010 by Aero-Metric U.S., Inc. The UDAR survey produced two-foot contours and a reflectivity map of the project area. Based on this data, a conceptual project design was completed April 14, 2011. Mr. Groves conducted additional field investigations from April 17 to 23, 2011. Mr. Groves was accompanied in the field by Mr. Bloom on this second field visit. Field activities in April 2011 included wetlands delineations in the project footprint, verification of the UDAR survey data in key areas, additional topographic surveys in key project locations, and a field review of the conceptual design for general constructibility and compatibility with environmental conditions in the project area. The April 2011 conceptual designs were revised to reflect field findings, and a new set of conceptual designs completed July 29, 2011. 2.0 SUMMARY OF WETLANDS INDICATOR INFORMATION 2.1 Summarv of Information on Hvdrophytic Veaetation The Indian River Timber Sale EIS, NWI database, and NRCS soil mapping datasets provide consistent overviews of vegetation in the project area at a 1:24,000 scale. These characterizations are consistent with field observations and aerial imagery. Small sites within the project area not captured by 1:24,000 scale mapping (sites from approximately 1,000 to 10,000 square feet) were also identified and mapped during field visits. 2.2 Summary of Information on Wetlands Hydrology The Indian River Timber Sale EIS and NRCS soil mapping dataset both provide a general narrative of site hydrology. This data is augmented with the detailed topographic mapping completed for this project and field observations. Field efforts in the project area focused on mapping small sites (approximately 1,000 to 10,000 square feet) not identified by previous mapping efforts. PAGE40F9 INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 2.3 Summary of Information on Hydric Soils Test pits were not feasible during the April 2011 site visit because the ground was still frozen. Information in the NRCS soils database and naturally exposed soil profiles in the project area are used to guide assessment of hydric soils. Where this data is insufficient, hydric soils are assumed to be present at candidate wetland sites. 3.0 DESCRIPTION OF PROJECT FEATURES AND WETLAND IMPACTS 3.1 Beach Landing Sites tor Proiect Equipment and Materials Materials and equipment for the project will be landed at two locations: (1) Materials for the hydro project will be landed at or near the existing log dump site at the beginning of Indian River Road. Two options are possible here. There is an existing shot rock pier that extends into the upper intertidal zone that was used for logging operations at Indian River in the early 1980s. There is also a spur road that ends at the beach just west of the pier. The beach at this location is comprised of broken rock and gravel, and is suitable to land a barge for materials and equipment offload. The lower intertidal zone in this area is populated by eel grass beds, so any landings at this site would need to coordinate with high tides to avoid beaching the barge or maneuvering in the eel grass beds. There is ample room in the upper intertidal zone for this. The beach in this area transitions from gravels into bedrock and forested uplands. There are no wetlands in the immediate area above the tidal zone. (2) Materials for the power line between the hydro project and Tenakee Springs will be landed in the vicinity of the small boat harbor in Tenakee Springs. The beach in this area is gravel with occasional large rocks and bedrock outcroppings. The upper intertidal zone is devoid of vegetation, but vegetation is increasingly present moving towards the low tide line. There is ample room to land a barge and offload materials and equipment. There are no wetlands in the immediate area above the intertidal zone. No wetlands impacts are identified from beach landings required for this project. There are no practical alternatives to beach landings to deliver the materials and equipment necessary to construct this project. No permanent improvements are proposed for the barge landing sites associated with this project. 3.2 Project Access Roads The main access route to the hydro powerhouse will be a 10 to 16-foot wide construction road extending from the existing U.S. Forest Service road down to the Indian River powerhouse. The road will be built with local materials using balanced cut and fill, and capped with geofabric and/or gravel where necessary. PAGE50F9 INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 The first approximately 750 feet of this road (station 0+00 to 7+50) crosses uplands that slope uniformly down towards Indian River at approximately 8%. This upland area is vegetated by mature conifer forest. This portion of the access road does not cross any wetlands or streams. The next approximately 850 feet of the access road (station 7+50 to 16+00) climbs a 20-foot tall embankment and follows the top of this embankment towards the powerhouse. This area is uplands, populated by mature conifer forest and deciduous brush. Forested wetlands are present in some areas along the toe of this embankment. The access route has been positioned away from the rim of this embankment to avoid any disturbance of these wetlands. This portion of the access road does not cross any wetlands or streams. The next approximately 200 feet of the access road (station 16+00 to 18+00) is a steep grade descending approximately 90 feet down the fall-line into Indian River Canyon. This is suitable only for passage of tracked equipment or winch operations. This grade ends on a uplands bench approximately 30 feet above Indian River. An approximately 3,600 square foot staging area will be built on this bench for powerhouse construction. This bench is vegetated with mature conifer forest. The northern end of this bench becomes increasingly brushy, and eventually transitions into a forested wetland. This portion of the access road and the staging area does not impact any wetlands or streams. The last approximately 250 feet of the access road (station 18+00 to 20+50) is a 10 to 14-foot wide access trail descending at 20% grade down to the powerhouse in the canyon. This road will be built on structural fill the toe of which will partially extend into Indian River in the immediate vicinity ofthe powerhouse. A sheet pile and/or concrete retaining wall will limit the footprint of this structural fill in Indian River and protect the fill from flood flows and erosion. Vegetation in this area is a combination of barren rock slopes/slides and vegetation (mostly alder with some willow and devil's club) near Indian River. Some conifer forest is present in less steep areas from approximately station 18+00 to 19+00. An estimated 250 cubic yards of fill into 1,700 square feet of wetlands are associated with this access road. A spur road will depart from the main access road at station 7+50 and head to the intake site. This road will have the same dimensions and construction as the main access road. The first approximately 900 feet of the intake road (station 0+00 to 9+00) will be located on moderate side slopes above the rim of Indian River Canyon. This road passes along the edge of a forested uplands/wetlands complex that is 50% upland I 50% wetland, and vegetated by mature conifers with deciduous under story brush. The last approximately 190 feet of the intake road (station 9+00 to 10+90) passes through a forested wetland (mixed conifer/deciduous canopy with brush and devil's club in the under PAGE 6 OF 9 INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 story) located on a bench above Indian River. This portion of the access road has been narrowed to a width of 10 to 14 feet to reduce wetland impacts. An 18-inch diameter culvert will be installed at station 10+60 to pass discharge from this wetland under the access road. The road is estimated to require 750 cubic yards of fill into 5,300 square feet of wetlands. Alternative methods to access the intake were evaluated and all are considered impractical for cost, logistic, and long term sustainability reasons. Permanent vehicular access to the intake is necessary for operations, maintenance, and repair, and will also reduce construction costs. Two short construction trail spurs are proposed off the intake access road to the rim of the Indian River Canyon to facilitate penstock construction. Both roads would be 10-foot wide temporary construction trails built of native material and used to transport penstock materials to the penstock alignment. Neither road passes through wetlands. All of these access alignments were evaluated on foot during the June 2009 and/or April 2011 field work. Wetlands delineations and impacted areas are indicated on the July 29, 2011 conceptual design drawings and August 9, 2011 Corps of Engineers permit drawings. The April14, 2011 conceptual design called for the access road to the powerhouse to be built at an approximately 15% grade. This required a bench to be built in Indian River Canyon for approximately 980 feet. This configuration would have required significant earth work and blasting, resulting in increased discharge of some of the spoils into Indian River and wetlands along this route. The April 2011 field work identified slope stability, cost, and environmental concerns with this approach. The currently proposed design with a steep track/winch line avoids these impacts. 3.3 Diversion I Intake Structure The proposed diversion and intake structure will be co-located with the existing concrete fish pass at barrier 4 on the west side of Indian River. The intake structure will add a new taller head wall and two additional fish cells to the top of the existing fish pass, as well as a hydro intake and a weir across Indian River. The head wall and water inlets will be designed to preferentially direct low flows first into the fish pass, second into the hydro intake, and third over the weir and into Indian River. The hydro intake will be built adjacent and parallel to the fish pass structure. The intake will utilize a coanda-effect inclined plate screen to filter debris out of the penstock and to allow all life stages of fish to pass over the screen and into Indian River. Except for the east end of the weir wing wall, the intake and diversion structure is located below the ordinary high water line of Indian River. The structure's footprint is devoid of vegetation and is mostly bedrock. Some areas have a thin mantle of gravels over bedrock. PAGE 7 OF 9 INDIAN RIVER HYDROELECTRIC PROJECT WETLANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 The diversion structure will require approximately 100 cubic yards of fill into 1,000 square feet below the ordinary high water line of Indian River. 3.4 Penstock The penstock alignment extends along the floor of Indian River Canyon for approximately 1,225 feet downstream from the intake structure (station 0+36 to 12+62). This portion of the penstock is built above grade with trestles supporting the pipe every 20 feet. The trestles will be supported by concrete or steel piers. Most of these piers will be founded on bedrock above the ordinary high water mark of Indian River. Piers located below the ordinary high water mark or within flood velocity hazard areas may include additional civil works to protect them from flood damage. The penstock alignment in this area is comprised of bedrock or a thin mantle of gravels and cobbles over bedrock. When present, vegetation is generally a combination of alders, willows, and sometimes devil's club. The last 325 feet of the penstock will be built on grade or buried. Approximately 90 feet (station 12+62 to 13+50) will be built on cribs installed on grade through a forested wetland (conifer forest with deciduous under story and devil's club). The remaining approximately 235 feet or the penstock alignment will be located in forested uplands and will be on grade or buried. The penstock will require approximately 100 cubic yards of fill into 1,500 square feet of wetlands and/or areas below the ordinary high water line of Indian River. The Aprill4, 2011 conceptual design called for the penstock to be installed on a trestle system along the east side of Indian River running at a 2% grade from the intake down to the powerhouse. This configuration would have required significant earth work and blasting, resulting in increased discharge of spoils into Indian River and wetlands along the route. The April field work identified slope stability, cost, and environmental concerns with this approach. The currently proposed trestle design avoids and/or minimizes these impacts. 3.5 Powerhouse The powerhouse will be located on fill placed partially below the ordinary high water mark on the east side of Indian River immediately downstream of falls #2. Soils at the powerhouse site are a combination of exposed bedrock and shallow gravel deposits over bedrock. Vegetation is not present below the ordinary high water line. A sheet pile and/or concrete retaining wall will be installed between the powerhouse site and Indian River to protect the powerhouse site from floods and erosion. This is the same wall associated with the access road to the powerhouse (Section 3.2). The tailrace channel and powerhouse foundation will be integral to this retaining wall. Blasting in Indian River will be required to establish the final grade of the tailrace channel. PAGE 80F 9 INDIAN RIVER HYDROElECTRIC PROJECT WETlANDS DELINEATION LETTER REPORT POLARCONSULT ALASKA, INC. AUGUST 9, 2011 No cut slopes are proposed in the canyon wall at the powerhouse site to avoid compromising the stability of the canyon slopes above the powerhouse. The powerhouse site will require approximately 700 cubic yards of fill placed in 3,000 square feet below the ordinary high water line of Indian River. The powerhouse site was moved upriver approximately 140 feet from the location in the April 14, 2011 conceptual design drawings. This revision was implemented for the following reasons: ~ The upriver site reduces the fill area below the ordinary high water line. ~ The canyon slopes at the upriver site appear to be more stable. ~ The upriver site is more compatible with river hydraulics than the original site. ~ The upriver site does not diminish the project's technical or economic performance. 3.6 Power Line The power line for the project will start at the small boat harbor and continue underground for approximately 3,850 feet to the west rim of Indian River Canyon. It will cross Indian River overhead and terminate at the powerhouse at approximately station 40+14. The power line route traverses sidehill country that is vegetated by conifer forest with deciduous understory in some areas. Several large emergent wetlands with forested wetland buffers in this area are identified in NWI, NRCS, and USFS information, and are apparent in aerial imagery and detailed topographic maps. The power line route avoids these areas. A small creek that drains this wetland area is crossed at station 22+00 with a 24-inch culvert. A maintenance trail will be co-located with the buried power line to allow inspection, maintenance, and repair of the power line. The trail will be 6 to 8 feet wide, and built of native materials. Vehicular access to the powerhouse will not be possible along the power line route due to Indian River Canyon. There are several small wetlands created by micro topography along the power line route that were not mapped in detail during field investigations. There is sufficient flexibility in the power line alignment to avoid impacting many of these small wetland areas. Fifteen percent of the total power line footprint is assumed to require wetlands fill. Based upon field review of the power line alignment, this is a very conservative allowance. The power line will require approximately 800 cubic yards of fill into 9,800 square feet of wetlands. PAGE 9 OF9 Joel Groves From: "Speerstra, Linda POA" <Linda.Speerstra@usace.army.mil> Date: Friday, December 17, 2010 10:48 AM To: <joel@polarconsult.net> Subject: Tenakee Springs Hydro Hi Joel. I'm almost back from leave. I do have some additional questions on the Hydro Project in Tenakee POA-20 10-0758. I'll list them below: 1) How many crossings will be needed on the 3200' road? What is the width of the road? Also, cubic yards of material necessary to bed the two crossings indicated. What is the size of the culverts? If the road is crossing any wetland areas the acreage and fill material will need to be tallied. If you aren't crossing wetlands state that in your narrative/application. Figure 2 of 5 indicates that the road to the intake will cross the top of a wetland area. 2) Will the penstock be bedded underground or in the stream? Figure 3 shows the intake structure with the penstock incased in something. Is the encasement concrete? Can you send me additional information on the intake unit with dimensions and type of material for each component. 3) How much riprap will be used and placed in the stream for the hydro unit placement? I need specific information on amounts of fill material and area of impact broken out by intake, powerhouse, penstock, road, trail, access area, etc. 4) Figure 4 Powerhouse indicates wetlands along the OHW. I'll need quantities for this location also. What is the deflector wall made of? You'll need to label river bank as OHW if that is what it is. 5) The compensatory mitigation measures described our minimization measures. Are you proposing compensatory mitigation? Bullet number 2 in compensatory mitigation discusses a coordinated effort with USFS and ADF&G. I would need more description on the enhancement work that would increase the functionality of the fish passage. Send drawings and pictures for the proposal. 6)I need drawings for the access trail, penstock at location determined, staging area for equipment, etc. 7) the CPQ indicated there will be fill in Section 10 waters (marine waters) is there a proposal for a staging area along the beach? I'm sure you'll have some questions. So please give me a call. I'm in the Juneau Field Office today 790-4490. I'll be back in the Sitka Field Office on Monday. Joel, if you have pictures of the area that would help a bunch. It's been years since I've been in Tenakee. If you have a field trip planned for the Page 1 of2 9/16/2011 spring please let me know and I'll tag along. Linda Linda Speerstra Regulatory Specialist Sitka Field Office P.O. Box 16 Sitka, AK 99835 907-747-0658 Page 2 of2 9/16/2011 ~ .. polarconsult alaska, inc . ENGINEERS • SURVEYORS • ENVIRONMENTAL CONSULTANTS LINDA SPEERSTRA U.S. ARMY CORPS OF ENGINEERS -ALASKA DISTRICT Sitka Regulatory Field Office PO Box 16 Sitka, AK 99835 Subject: Supplemental lnfonnationfor Preconstruction Notification Form, Indian River Hydro Project Dear Ms. Speerstra: November 4, 2010 Per our discussions September 14th' I am providing the additional information requested to process the permit applications for the City of Tenakee Springs' Indian River Hydroelectric Project. The following are attached: 1. Updated project maps including a wetlands delineation. Polarconsult has delineated wetlands within the project area through analysis of aerial infrared imagery, detailed topography for the project area (2-foot contours), visible-band aerial imagery of the project area, and on-the-ground field reconnaissance of the project area conducted in June 2009. Delineated wetlands are shown on the attached updated project figures. 2. A more detailed road plan showing water crossings. Based upon our wetlands delineation, the proposed road alignments do not cross any perennial streams. There are two locations, indicated on the attached Figure 2, where the roads cross minor ephemeral drainages. Standard crossing details are provided on the attached Figure 5. 3. A more detailed description of impacts itemized by project feature. Per your suggestion, we have reviewed the terms for Nation-Wide Permits #12 for Utility Line Activities, and #14 for Linear Transportation Projects. This project includes both access roads and utility lines, and therefore appears eligible for both NWPs. We have updated our estimates of wetlands impacts associated with the project, both in terms of project feature type and to reflect the findings of the wetlands delineation: Feature NWP Estimated Wetland Impact Area Utility Line #12 +1-4,000 SF (0.09 ac) Access Roads #14 +1-7,000 SF (0.16 ac) Hydropower Project Structures #17 +1-4,000 SF (0.09 ac) 4. A mitigation plan for impacts to waters of the U.S. A mitigation plan for impacts to waters of the U.S. has been completed and is attached. If you have any questions or require further information, please give me a call at 907-258-2420. Sincerelv. s/ Joel D. Groves /s JoellJ. Uroves, Pb cc: Art Bloom-City of Tenakee Springs Project Manager Enclosures: Revised project maps Mitigation Plan 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.oolarconsult.net PROPOSED CONNECTION TO TENAKEE ELECTRIC SYSTEM 0 E3 TENAk[£ INLET 1000 ' ~~--------------------~----~~~~~~~._~ 'L-~~~~~~~~~--~----~~~~~------~ >~L{ / ,(L/ // ,(/.{-4L.~:4L,tr<J-!-~ ~""'-.£+ 'I' ' ''p~~ED INTAKE SITE EXISTING IUSFS FISH LADDER SITE (ADL 1 06204) S16 S15 ~~---+--~~- ~ PROPOSED ACCESS ROADS r ·' ."\.; . PROPOSED ~ ~() POWER HOUS ~ SITE ~ ~ <} ,J EXISTING STATE LAND " ~-~,, ~}'-'0''"'';~ I "-. FOOT TRAIL "~" '\. ~ \.. ~. r--1-N-DI_A_N_R..,.I-VE..,.R---:-:H':"""YD:-::R~O~E..,.L=-Ec..,.TR~IC~P=-Ro=-J":":E~C~T--l . s I ' ~ PROJECT LOCATION MAP "'-... 2000 polaroonault alaska, Ina. 150J W.t 3.lrd Avenue, Suit. 310 Mcllon>Qe, -gg!!OJ lol: i07-25&-2420 Fax: 907-25&-241i EIIAII.: JOEI.Itl'aAACONSULl.NEl 2010 CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL. RESOURCES DIVISION OF MINING, LAND AND WATER ~ PROPOSED INTAKE ( EE FIGURE 3) L PROPOSED ACCESS ROADS < + 1-3,2oo') WETLANDS (TYPICAL) MINOR DRAINAGE CROSSING SEE FIGURE 5 (TYP) NOTES: SECTION 15 SECTION 22- 1. WETLANDS DELINEATION IS BASED ON FIELD OBSERVATIONS, AERIAL MAPPING, AERIAL INFRARED IMAGERY, AND TOPOGRAPHIC DATA. INDIAN RIVER HYDROELECTRIC PROJECT PROJECT MAP prepar y: polaroonault alaaka, l no. 1503 Wool llrd Avenue, !Ooito 310 Anon.,_, AIGolca 88:103 Tol: 807-2!18-2420 Far. 807-2!18-2418 DIM.: JOELOI'OLNICONSU.T.NET OCT. 29, 2010 CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES ""'-,, DMSION OF MINING , LAND AND WATER \ ( Sec: 15, 18, 21, 22: Twp 475: Ra~ 83E; Copper Rlwr Meridian ' SCALE: 1·=250' FIGURE 2 OF 5 FILE : TKE_DES,dw g 150 ORIGINAL GROUND AIR RELIEF VENT ~ . SURFACE HEAD BOX HYDRO INTAKE SCREEN ACCESS ROAD (COANDA TYPE) . 140 130 120 110 0 16 INTAKE STRUCTURE -PLAN VIEW LOOKING UPSTREAM SCALE: 1" = 16' F3 F3 130 120 . 110 0 AIR RELIEF VENT E3 E3 INTAKE STRUCTURE -SECTION VIEW A-A SCALE: 1" = 1 0' 10 I NOTES: 1. THE DIMENSIONS AND LOCATION OF THE EXISTING FISH LADDER ARE APPROXIMATE. 2. DRAWINGS ARE CONCEPTUAL AND SUITABLE FO PERMITTING AND PLANNING PURPOSES ONLY. 3. OHW = ORDINARY HIGH WATER. INDIAN RIVER HYDROELECTRIC PROJECT INTAKE STRUCTURE -ELEVATION AND SECTION prepare y: polarconault alaaka. inc. 1!)03 West 33rd AVenue. Suite J10 Anchoraqe. Aiaak.o 99503 Tel: 907-258-2~20 Fox: 907-258-2419 £1WL: JOElDF'Ol.JIRCONSULT.NET OCT. 29, 2010 CITY OF TIENAKEE SPRINGS STATIE OF AlASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER Sec: 15, 18, 21, 22; TVJ9 47S; Ranc.Je 83E:; Copper River Meridian SCALE: 1 ·=250' FIGURE 3 OF 5 FILE: TKE_DES.dwg 110 100 90 80 70 POWERHOUSE FINISH GRADE (ASSUMED ~:1 SLOPE) ORIGINAL GROUND SURFACE DRAFT TUBE DEFLECTOR WALL r"""f'i:=!;===;!::rr:!=rf:::!:::::ff"--.J 60 TYPICAL WATER LEVEL STOP LOGS/ FISH BARRIER POWERHOUSE -ELEVATION VIEW LOOKING UPSTREAM 16' ®POWERHOUSE PLAN VIEW SCALE: 1" = 20' WORKBEN(:H 10 20 0 " E3 E3 SCAI.£ .. Fm NOTES: 1. ALL DIMENSIONS AND LAYOUT ARE CONCEPTUAL APPROXIMATIONS. 2. DRAWINGS ARE SUITABLE FOR PERMITIING AND PLANNING PURPOSES ONLY. 3. WETLANDS DELINEATION IS BASED ON FIELD OBSERVATIONS, AERIAL MAPPING, AERIAL INFRARED IMAGERY, AND TOPOGRAPHIC DATA. 4. OHW = ORDINARY HIGH WATER. INDIAN RIVER HYDROELECTRIC PROJECT POWERHOUSE -PLAN AND ELEVATION prepared by: polaroonault alaska, ino. 1 ~03 W•t JJn:t Avanue, Suite J10 Anchorage, Alaaka 99503 Tel: 907-258-2420 Fax: 907-258-2419 EIIAIL: JOELOPOLARCONSULT.NET OCT. 29, 2010 CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DMSION OF MINING, LAND AND WATER Sec: 15, 18, 21, 22; Twp 475; Range 83E; Capper River Meridian SCALE: 1"=250' FIGURE 4 OF 5 FILE: TKE_DES.dwg ARMOR EMBANKMENTS AS REQUIRED TO PREVENT EROSION ACCESS ROAD EXISTING GRADE ACCESS ROAD ARMOR TRAIL AT CROSSING WITH GRAVEL AND COBBLES TO PROVIDE DR lVI NG SURFACE WEIR FABRICATED FROM ROCK-FILL GABIONS, TIMBERS, BOULDERS OR EQUAL MATERIALS SECTION A-A SECTION AT MINOR DRAINAGE CROSSING (TYPE 1) ACCESS ROAD CULVERT ARMOR EMBANKMENT BELOW CULVERT AS REQUIRED TO PREVENT EROSION ORIGINAL GROUND SURFACE ACCESS ROAD FILL ARMOR DOWNSLOPE SHOULDER WITH GABIONS, TIMBER, OR BOULDERS AS REQUIRED TO CONTROL EROSION FROM OVERTOPPING SECTION A-A SECTION AT MINOR DRAINAGE CROSSING (TYPE 2) NOTES: 1. NO PERENNIAL STREAM CROSSINGS OCCUR ALONG PROPOSED ROAD OR POWERLINE TRAIL ALIGNMENTS. DETERMINATION IS BASED UPON FIELD VISITS, TOPOGRAPHIC DATA, AND AERIAL IMAGERY. 2. WATER CROSSING DETAILS ON THIS SHEET ARE APPLICABLE FOR MINOR DRAINAGES INCLUDING EPHEMERAL STREAMS, EMERGENT SUBSURFACE FLOW AND SIMILAR WATER FEATURES. 3. DRAWINGS ARE FOR PERMITIING AND PLANNING PURPOSES ONLY. INDIAN RIVER HYDROELECTRIC PROJECT MINOR DRAINAGE CROSSING DETAILS prepared by: polarooneult alaska, inc. 1503 Weal 33rd Avenue, Suite 310 Anchorage, Alaska 99503 Tel: 907-258-2420 Fox: 907-258-2419 EMAI[., JOELOPOlARCONSULT.NEf OCT. 29, 2010 CllY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DMSION OF MINING, LAND AND WATER Sec: 15, 18, 21, 22; Twp 475; Range 8.3E; Copper Rlwr Meridian SCALE: 1 "=250' FIGURE 5 OF 5 FILE: TKE_DES.dwg Applicant Proposed Mitigation Statements Background: The U.S. Army Corps of Engineers (Corps) and the Environmental Protection Agency issued regulations that govern national compensatory mitigation policy for activities in waters of the U.S., including wetlands, authorized by Corps permits. The final mitigation rule was published in the federal register on AprillO, 2008, and became effective on June 9, 2008. The final rule establishes standards and criteria for the use of appropriate and practicable compensatory mitigation for unavoidable functional losses of aquatic resources authorized by Corps permits (33 CFR Part 332). Additionally, the rule requires new information to be included in Corps permit applications and public notices to enable meaningful comments on applicant proposed mitigation. In accordance with 33 CFR Part 325.1(d)(7), "For activities involving discharges of dredged or fill material into waters of the U.S., the application must include a statement describing how impacts to waters of the United States are to be avoided and minimized. The application must also include either a statement describing how impacts to waters of the United States are to be compensated for or a statement explaining why compensatory mitigation should not be required for the proposed impacts." For additional information, the final mitigation rule can be viewed at: http://www. usace.army.mil!cw /cecwo/reg/news/final_ mitig_ rule. pdf Mitigation is a sequential process of avoidance, minimization, and compensation. Compensatory mitigation is not considered until after all appropriate and practicable steps have been taken to first avoid and then minimize adverse impacts to the aquatic ecosystem. Please provide your proposed avoidance, minimization, and compensatory mitigation below: Applicant's Proposed Mitigation (attach additional sheets as necessary): 1. Avoidance of impacts to waters of the U.S., including wetlands: Please describe how, in your project planning process, you avoided impacts to waters of the US, including wetlands, to the maximum extent practicable. Examples of avoidance measures include site selection, routes, design configurations, etc ... Project features such as access roads, penstock, and trails will be routed to avoid wetlands and minor drainages where technically and economically feasible. 2. Minimization of unavoidable impacts to waters of the U.S., including wetlands: Please describe how your project design incorporates measures that minimize the unavoidable impacts to waters of the US, including wetlands, by limiting jill discharges to the minimum amount/size necessary to achieve the project purpose. Where fill of wetlands/waters or crossing of minor drainages cannot be avoided, such as at the intake, powerhouse, and other locations, the design of these features will minimize the impact to wetlands and waters. The powerhouse site will use a combination of rip-rap, retaining walls, piling, or other methods to minimize the powerhouse site footprint. The intake will be a concrete or similar structure built in a section of Indian River that flows over bedrock and cobbles, minimizing habitat loss relative to other intake sites. Access features will use culverts or other means as appropriate to cross minor drainages with minimal disruption of drainage patterns. 1 Applicant Proposed Mitigation Statements 3. Compensation for unavoidable impacts to waters of the U.S., including wetlands: Please describe your proposed compensatory mitigation to offset unavoidable impacts to waters of the US., or, alternatively, why compensatory mitigation is not appropriate or practicable for your project. Compensatory mitigation involves actions taken to offset unavoidable adverse impacts to waters of the US., including wetlands, streams and other aquatic resources (aquatic sites) authorized by Corps permits. Compensatory mitigation may involve the restoration, enhancement, establishment (creation), and/or the preservation of aquatic sites. The three mechanisms for providing compensatory mitigation are mitigation banks, in-lieu fee of mitigation, and permittee-responsible mitigation. Please see the attached definitions for additional information. Unavoidable impacts will be mitigated by one or more of the following measures: • Impacts along the banks of Indian River at the intake and powerhouse sites will be mitigated by revegetating the banks in these areas after construction. Typical existing bank-edge vegetation includes alders, willows, and devil's club, and these sites are deemed to be excellent candidates for successful revegetation. • Design of the project will be coordinated with USFS and ADFG to complement and where practicable enhance the functionality of the fish passage improvements USFS has constructed on Indian River. This mitigation effort will help support enhancement of the biological productivity of the resource. 2 Applicant Proposed Mitigation Statements Definitions: Enhancement: the manipulation of the physical, chemical, or biological characteristics of an aquatic resource to heighten, intensity, or improve a specific aquatic resource function(s). Enhancement results in the gain of selected aquatic resource function( s ), but may also lead to a decline in other aquatic resource function(s). Enhancement does not result in a gain in aquatic resource area. Establishment (creation): the manipulation of the physical, chemical, or biological characteristics present to develop an aquatic resource that did not previously exist at an upland site. Establishment results in a gain in aquatic resource area and functions. In-lieu fee program: a program involving the restoration, establishment, enhancement, and/or preservation of aquatic resources through funds paid to a governmental or non-profit natural resources management entity to satisfY compensatory mitigation requirements for DA permits. Similar to a mitigation bank, an in-lieu fee program sells compensatory mitigation credits to permittees whose obligation to provide compensatory mitigation is then transferred to the in-lieu program sponsor. However, the rules governing the operation and use of in-lieu fee programs are somewhat different from the rules governing operation and use of mitigation banks. The operation and use of an in-lieu fee program are governed by an in-lieu fee program instrument. Mitigation bank: a site, or suite of sites, where resources (e.g., wetlands, streams, riparian areas) are restored, established, enhanced, and/or preserved for the purpose of providing compensatory mitigation for impacts authorized by DA permits. In general, a mitigation bank sells compensatory mitigation credits to permittees whose obligation to provide compensatory mitigation is then transferred to the mitigation bank sponsor. The operation and use of a mitigation bank are governed by a mitigation banking instrument. Permittee-responsible mitigation: an aquatic resource restoration, establishment, enhancement, and/or preservation activity undertaken by the permittee (or an authorized agent or contractor) to provide compensatory mitigation for which the permittee retains full responsibility. Practicable: available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes. Preservation: the removal of a threat to, or preventing the decline of, aquatic resources by an action in or near those aquatic resources. This term includes activities commonly associated with the protection and maintenance of aquatic resources through the implementation of appropriate legal and physical mechanisms. Preservation does not result in a gain of aquatic resource area or functions. Restoration: the manipulation of the physical, chemical, or biological characteristics of a site with the goal of returning natural/historic functions to a former or degraded aquatic resource. For the purpose of tracking net gains in aquatic resource area, restoration is divided into two categories: re-establishment and rehabilitation. 3 polarconsult alaska, inc. ENGINEERS -SURVEYORS -ENERGY CONSULT ANTS specializing in energy conservation systems CONVERSATION RECORD DATE: PROJECT: TIME: September 14, 2010 09004 11:20AM CONTACT: I COMPANY: Linda Speerstra Coe PHONE#: FAX#: Taken By: 747-0658 Joel Groves SUBJECT: Initial Application Comments SUMMARY: Linda called to review application. Things she needs: 1. Wetlands delineation. Not shown on maps. Told her we had a good idea of where they are based on past field trips, topo, and aerial imagery, but a formal delineation hasn't been done. She said this would work on a preliminary basis and she would check with her supervisor on if this was sufficient generally. I mentioned that we did plan to mobe out again and could do the wetlands at that time. She asked of schedule, I said I wanted to receive all the comments from permitting agencies and then do a site visit to collect what data is necessary. Not sure if that will happen this fall or in the spring. She would like to accompany us on the visit if possible. 2. Road plan. She needs to see stream crossings, drainages, etc. 3. Mitigation Plan. There is a form for the PCN. I didn't see this. 4. Details on the 4,500' trail. There are a number ofNWPs that can be used for the project, so split it and impacts out into the hydro, the access route, and the utility corridor. That will help increase the minimums. She will email the Mitigation Plan form and recap the discussion. • . ' . polarconsult alaska, inc . ENGINEERS • PLANNERS • ENERGY CONSULTANTS LINDA SPEERSTRA U.S. ARMY CORPS OF ENGINEERS -ALASKA DISTRICT Sitka Regulatory Field Office PO Box 16 Sitka, AK 99835 August 31,2010 Subject: ?reconstruction Notification Form for NWP #17, Indian River Hydro Project Dear Ms. Speerstra: On behalf of our client, the City of Tenakee Springs, enclosed please find a completed Preconstruction Notification Form and supporting documents for the proposed Indian River Hydroelectric Project near Tenakee Springs, Alaska. If you have any questions regarding this application or the project in general, please give me a call at 907-258-2420. s/ Joel o. Groves /s -= JVvl u. uroves, PE Polarconsult Project Manager cc: Art Bloom -City ofTenakee Springs Project Manager Enclosures: Preconstruction Notification Form / Project Map and figures/ Revegetation Plan -" 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net I. ~ ~ U.S. Army Corps of Engineers, Alaska District PRECONSTRUCTION NOTIFICATION FORM May be used instead of Form ENG 4345 to request authorization under a Nationwide Permit (NWP) Applicant: CITY OF TENAKEE SPRINGS /DBA TENAKEE SPR. ELECTRIC DEPT. Phone: 907-736-2207 Address: PO BOX 52 Fax: 907-736-2207 City, State, Zip: TENAKEE SPRINGS, AK 99841 Cell/Direct Line: Point of Contact: ART BLOOM, PROJECT MANAGER e-mail: CITYTKE@GMAIL.COM Agent: Address: 1503 WEST 33RD AVENUE SUITE 310 City, State, Zip: ANCHORAGE, AK 99503 Point of Contact: JOEL D. GROVES Location of the Proposed Project Site : ·~··- Nearest Waterway: INDIAN RIVER Section, Township, Range, and Meridian: SECTIONS 15, 21, 22; T47S; R63E. COPPER RIVER MERIDIAN Latitude (in Decimal Degrees, NAD 83): 57d 47' 20" ON Longitude (in Decimal Degrees, NAD 83): 135d11'37" ow Nearest City: TENAKEE SPRINGS Subdivision: N/A Borough: UNORGANIZED USGS Quad(s): SITKA D-4 START AT BEACH LANDING FOR U.SFS.ROAD 7500 (INDIAN RIVER ROAD) APPROX. 1 MILE WEST OF Driving Directions to Site: TENAKEE SPRINGS. DRIVE UP ROAD APPROX.1.3 MILES. TRAVERSE APPROX. 1/4 MILE CROSS COUNTRY TO LEFT OF ROAD TO PROJECT SITE. Project Description : To ensure your project meets the requirements for a NWP. read all of the NWP General Conditions and Region·al Conditions, which can be found on our website at lc.cr-r"'t"''n of the proposed project. including the area of impacts and the volume of fill material to be used (If there is a that you think would apply to your proposed project. please include that in this section): IS A RUN-OF-RIVER HYDROELECTRIC PROJECT ON INDIAN RIVER PROJECT INCLUDES AN IN STREAM DIVERSION PENSTOCK PARALLELING INDIAN RIVER FOR APPROX 1.800 FT. A POWERHOUSE ADJACENT TO THE RIVER. A TAILRACE WATER TO THE RIVER. APPRO X 3,200 FT OF ACCESS TRAILS AND ROADS. APPRO X 4,500 FT. OF POWER LINE THE PROJECT TO TENAKEE SPRINGS ELECTRIC SYSTEM, AND APPURTENANT FEATURES. DIVERSION STRUCTURE. TAILRACE AND OTHER FEATURES WILL REQUIRE FILL IS EXPECTED TO QUALIFY FOR NWP #11. WETLANDS FiLL IS ESTIMATED AT APPROX 2,500 CYDS. AREA OF FILL IS ESTIMATED AT < 0.5 ACRES. any direct and/or 1ndirect adverse environmental effects that may result from the proposed proJeCt WILL BE PLACED ON STREAMBANKS AND BEDS AT DIVERSION POWEF<HOUSE SITES. AND POSSIBLY OTHER 1\REI\S ACCESS AND LINE ROUTES MAY REOUIRE SOME FILL OF WETLANDS ,---------------------------------------"--------------, Do you intend to use any other authorizations for any part of the proposed project or any related activity, for example. a NWP, General Permit (GP), or Individual Permit (IP)? r;;( YES or r NO If YES, specify what permit type (NWP. GP, IP) and for what aspect of the project: NWP #17 IS EXPECTED TO COVER ALL PROJECT ACT!VITES REQUIRING CORPS AUTHORIZATION. Will your proposed project result in the loss of greater than 1/10 of an acre of wetlands? IX:· YES or NO If YES, describe how you will satisfy the mitigation requirement in Nationwide Permit General Condition 20" If additional space is needed, please attach sheets. WETLANDS LOSSES ARE ESTIMATED AT BETWEEN 0.1 AND 0.5 ACRES. LOSSES WILL BE AVOIDED AND MINIMIZED THROUGH DESIGN OF PROJECT FEATURES. REMAINING LOSSES ARE UNAVOIDABLE DUE TO TECHNICAL AND TOPOGRAPHIC CONSTRAINTS. AS MlTIGA TION, APPLICANT WILL WORK WITH THE US FOREST SERVICE AND ADF&G TO CONFIGURE THE PROJECT TO IMPROVE THE FUNCTIONALITY OF EXISTING FISH PASSAGE ENHANCEMENTS ON INDIAN RIVER, INCREASING THE VALUE OF THE RIVER SYSTEM. Are there any threatened or endangered species that may be affected by the proposed work or utilize the designated critical habitat that may be affected by the proposed work? Contact USFWS or NMFS? YES or 15<: NO If YES, list all species: #20USFWS AND NMFS ON-LINE CONSULTATION RESOURCES DO NOT INDICATE ANY CRITICAL HABITAT IN THE PROJECT AREA" Are there any historic properties that may be affected by the proposed work? Contact SHPO? I YES or 15<: NO If YES, state which property or properties may be affected and/or attach a vicinity map indicating the location of the historic property or properties. US. CORPS OF ENGINEERS COMPLETED AN ARCHEOLOGICAL FIELD INVESTIGATION IN 1983-84 FOR A HYDROELECTRIC PROJECT AT THIS SITE. #20NO RESOURCES WERE IDENTIFIED WITHIN THE CURRENT DEVELOPMENT FOOTPRINT. 1-----------<-----. Will the proposed work involve ground disturbing activities? IX: YES or NO If YES. attach a short narrative describing the topsoil or organic materials (including seed) that you intend to use for rehabilitation. If you intend to use other native the source. Attach the following in addition to the above applicable items: Drawings of the site and project plans (For more information on acceptable drawings and plans. please vistt our website at http/lwww poa usace army millreg/perrnitapp btm and click on "Guide to Drawings") Delineation of special aquatic sites including wetlands, riffle and pool complexes, sanctuaries and refuges. mudflats, vegetated shallows, and/or coral reefs. You may request a delineation from the Corps" Please visit our website for the Request Jurisdictional Determination from the Corps Form at: http //www poa usace army mjl/reg/JD%20Request%20FoiiD~n20Web.p.dL Note: If you request a Corps delineation, be in receiving authorization for your proposed project Application is hereby made for a permit or permits to authorize the work described in this preconstruc!Jon notification form I certtfy the information in this preconstruction notification form is complete and accurate I further certify that I possess th authority to undertake the work described herein or am acting as the duly authorized agent of the applicant /1 _,. ~ ~tes (~) .. SIGNATURE OF AGENT . -~L ;J, __ Cf~~-- po.__...fl.CD,...,~JC\ ,D.LASKI.l., .~- Tenakee Springs Electric Utility Indian River Hydroelectric Project Revegetation U.S. Anny Corps of Engineers Preconstruction Notification Fonn Trees and shrubs will be logged from the work area and removed to an appropriate disposal area. Topsoil and overburden will be removed to the underlying mineral soils and stockpiled adjacent to the work sites. After civil earthwork has been completed, stockpiled topsoil will be spread over cut and fill slopes allowing revegetation of the slopes with existing local species. Areas prone to erosion will be covered with jute matting. In areas of steep fill slopes where counter-erosion measures are likely to be unsuccessful, topsoil may be omitted to avoid excessive erosion oftopsoil and fines into the river. Areas requiring additional seed will utilize seed as recommended by the local cooperative extensive service office. PROPOSED POWER LINE ROUTE PROPOSED CONNECTION TO TENAKEE ELECTRIC SYSTEM TtNAK[£ 0 1000 INLtr 2000 STATE LOCATION MAP ·····~ ~'K( <<~~ 0(.{.{/ ,({~ <(~ •. <-«<~{{~ <{£/+( I LOGGING ROAD EXISTING I USFS FISH LADDER (USFS #7500) I (ADL 106204) S16IS1 ~-~ .. ··~"' S21.S22 I PROPOSED ACCESS ROADS , -~·- PROPOSED • POWER HOUSE~ SITE : ... ~ EXISTING FOOT TRAIL INDIAN RIVER HYDROELECTRIC PROJECT PROJECT LOCATION MAP prepared by: polarconeult ataeka. ino~ 150J West JJn::l Aven!,le, Suite 3i0 Ancl"loroge, Alaska 99503 Tek 907-258-2420 <c<o 907-258-2419 EMAIL: J0£LOPOLAACONSULT,NET CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER Sec: 15, 16, 21, 22; Twp 475; Range 63E; Copper R'JVeT Meridian SCALE: 1·=1000' FIGURE 1 OF 4 FILE: TKE_DES.dwg EXISTING USFS FISH LADDER (APPROXIMATE LOCATION) ? ? 'b 'b PROPOSED PENSTOCK (+/-1,800') STAIT LAND_ 0 oz z:) ::sw ~t: -f---UVJ PROPOSED POWERUNE TO TENAKEE SPRINGS ( + 1-4,5oo') "a PROPOSED 0 POWERHOUSE (SEE FIGURE 4) 1So 0 PROPOSED ACCESS ROADS (+/-3,200') SECTION 15 SECTION22- 250 500 SCALE IN FEET INDIAN RIVER HYDROELECTRIC PROJECT PROJECT MAP prepared by: polaroonault alaaka, Ina. 1503 West JJrd Avenue, Suite 310 Anchorage, Ala11ka 99503 Tel: 907-258-2420 Fax: 907-258-2419 EWAll: JOELOPOL.ARCONSULT.NET AUGUST 6, 2010 CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DMSION OF MINING, LAND AND WATER Soc: 15, 16, 21, 22; Twp 47S; Range 63E; Copper River Worldlan SCALE: 1 "=250' FIGURE 2 OF 4 FILE: TKE_DES.dwg 150 140 130 120 110 ---------+------------------------~: -------------·--·--- ORIG:INAL GROUND HEAD BOX : HYDRO INTAKE SCREEN ACCESS ROAD AIR RELI~F VENT ~ ; SURFACE ---LAD~~----\CO.AJ;JDA TYPE} -.. .... . . .... ----------- IF REQUIRED} PYLONS EXISTING FISH LADDER HEAD WALL -------------------+---------------- ~ 16 INTAKE STRUCTURE -PLAN VIEW LOOKING UPSTREAM SCALE: 1" = 1 6' SCM.I IN FEET 130 110 TYPICAL WATER LEVEL PYLONS FOR FLASH BOARDS INTAKE STRUCTURE -SECTION VIEW A-A SCALE: 1" = 1 0' PENSTOCK 10 SCAlE IH fiTT NOTES: 1. THE DIMENSIONS AND LOCATION OF THE EXISTING FISH LADDER ARE APPROXIMATE. 2. DRAWINGS ARE CONCEPTUAL AND SUITABLE FO PERMITIING AND PLANNING PURPOSES ONLY INDIAN RIVER HYDROELECTRIC PROJECT INTAKE STRUCTURE-ELEVATION AND SECTION prepare y: polarconeult alaska, inc. 1503 West 33rd Avenue. Suite 310 Anchorage, Alollko 99503 Tel: 907-258-2420 Fox: 907-258-2419 EMAIL: JOELOPOLARCONSULT.NET AUGUST 6, 2010 CllY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER Sec: 15, 18, 21, 22; Twp 47S; Ran~e 83E; Copper River Meridian SCALE: 1·=250' FIGURE 3 OF 4 FILE: TKE_DES.dwg 110 100 90 80 70 POWERHOUSE DEFLECTOR WALL STOP LOGS/ FISH BARRIER --------------- POWERHOUSE ELEVATION VIEW LOOKING UPSTREAM TAILRACE 0 POWERHOUSE PLAN VIEW SCALE: 1" = 20' WORKBENCH SWITCHGEAR GENERATOR 10 20 sc.tU N Fill FINISH GRADE (ASSUMED ~: 1 SLOPE) ORIGINAL GROUND SURFACE 0 E3 E3 SCALE IN FEU NOTES: 10 1. ALL DIMENSIONS AND LAYOUT ARE CONCEPTUA APPROXIMATIONS. 2. DRAWINGS ARE SUITABLE FOR PERMITIING AND PLANNING PURPOSES ONLY INDIAN RIVER HYDROELECTRIC PROJECT POWERHOUSE-PLAN AND ELEVATION prepared by: polaroonault alaska, ino. 1SOJ West JJrd Avent.~e, Suite .310 Anchorage, Alaaka 9950.3 Tel: 907-258-2420 Fax: 907-258-2419 EWAJ~ JOELOPOLARCONSULT.NEf AUGUST 6, 2010 CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DMSION OF MINING, LAND AND WATER Sec: 15, 18, 21, 22; Twp 47S; Range BJE; Copper River Meridian SCALE: 1 "=250' FIGURE 4 OF 4 FILE: TKE_DES.dwg City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report ADNR LAND LEASING November 2011 -Final Report fl. Polarconsult Alaska, Inc. APPENDIX D Joel Groves From: Date: To: Cc: "Anderson, James W (DNR)'' <jim.anderson@alaska.gov> Tuesday, September 14, 2010 3:20PM "Asplund, Kristi L (DNR)" <kristi.asplund@alaska.gov> "Joel Groves" <joel@polarconsult.net> Page 1 of2 Subject: RE: NEW CPQ: Indian River (City of Tenakee Springs ELEC UTIL DPT Hydroelectric Development); ID201 0-0904J Kristi, The Lands section of DMLW originally requested two applications for this proposed project and two application were submitted by the City of Tenakee Springs agent-Polar consult Alaska inc., one application for a lease and another for an easement. After receiving these two applications Lands revaluated the project and determined that one authorization will work and we initialized both applications under an application for a public easement and have assigned it case file number-ADL 108047. For purposes of starting an ACMP review we consider our application complete. Jim From: Asplund, Kristi L (DNR) Sent: Wednesday, September 08, 2010 11:59 AM To: Roche, Frances E (DEC); Palmer, Sean P (DEC); Timothy, Jackie L (DFG); Kelley, David L (DNR); Bussard, Daniel P (DNR); Deats, Theodore A (DNR); DNR, Parks OHA Review Compliance (DNR sponsored); 'Speerstra, Linda POA'; cityoftb@aptalaska.net; juneau@fws.gov; mary.goode@noaa.gov; 'Degering.tracy@epamail.epa.gov'; 'Lacroix.matthew@epamail.epa.gov'; cityoftke@gmail.com Cc: Bohan, Carrie D (DNR); Groom, William M (DNR); Taylor, Jill A (DNR); Anderson, James W (DNR) Subject: NEW CPQ: Indian River (City of Tenakee Springs ELEC UTIL DPT Hydroelectric Development); ID2010- 0904J The Division of Coastal and Ocean Management (DCOM) received a Coastal Project Questionnaire (and supporting documents) for the following project: Applicant: City of Tenakee Springs Electric Utility Department Agent: Polarconsult Alaska Inc. (Joel Groves) Project Description: The project is a run-of-river hydroelectric project on Indian River to supply electricity to the city of Tenakee Springs. It will include an in-stream diversion structure at approximately River Mile (RM) 0.85, A penstock, and a powerhouse and tailrace at RM 0.55. The project will also include approx. 3,200 feet of access roads and trails, approx. 4,500 feet of power line from the power house to Tenakee Springs, and other appurtenant features. Location: Section 15, 21 & 22, Township 4 7 S., Range 63 E., CRM; in Tenakee Springs, Alaska ACMP Project Number: ID 20 1 0-0904] The CPQ and supporting documents are attached. The Federal Energy Regulatory Commission (FERC) has determined Section 23(b)(l) of the Federal Power Act does not require licensing of the proposed Indian River Hydroelectric Project (docket number DI 1 0-8-000). Please reply to this email if you have an interest in this project, if it requires your permit 9/16/2011 Page 2 of2 (or other authorization), or if you require additional time or information to make a determination. If a permit or authorization is required, what type is it and have you received an application for it? This email constitutes the DCOM's consultation with your agency/coastal district regarding the scope of review (per 11 AAC 110.020 (d)) unless your response received by 09 I 15 I 1 0 requests further consultation. This project may already be consistent with the ACMP under a General Consistency Determination (GCD), Categorically Consistent Determination (CCD) or General Permit (GP). If you think it is, please indicate which one. Per 11 AAC 110.700 (b) & (c), the DCOM will decide (in consultation) whether to apply a GCD. If the DCOM doesn't hear from you by 5:00PM 09/15/10, we will assume you don't have a permit in play. If you advise us after that date that a permit is required, you may be responsible for conducting an ACMP Single-Agency Review for the activity. If you have any questions, please contact me. Thank you for your time and cooperation with the ACMP. Kristi L. Asplund Natural Resource Specialist Department of Natural Resources Alaska Coastal Management Program phone: 1 (907) 465-2142 ~~ 1 (9on4Gs-3o7s dnr .dcomprajnu@alaska.gov ~Please consider the env~ronment before pnnting th1s e-maol 9/16/2011 • I ' ' polarconsult alaska, inc. ENGINEERS • PLANNERS • ENERGY CONSULTANTS JIM ANDERSON Division ofMining, Land and Water-Leasing Section Alaska Department ofNatural Resources PO Box 111020 Juneau, AK 99811 August 31, 2010 Subject: Land Lease and Easement Applications for Indian River Hydroelectric Project Dear Mr. Anderson: On behalf of our client, the City of Tenakee Springs, enclosed please find applications for a lease of state land and for access/utility easements for the Indian River hydroelectric project. It appears that the project is eligible for a non-competitive lease as a Public I Charitable Use at less than fair market value as allowed in AS 38.05.810(a)(1), (e), and/or (f). The City of Tenakee Springs is organized as a 2nd Class City, and operates its Electric Utility Department as a Public Utility under Certificate of Public Convenience and Necessity (CPCN) #363, issued by the Regulatory Commission of Alaska (RCA) in 1986. If you have any questions regarding this application or the project in general, please give me a call at 907~258-2420. Sincerely, Is/ :::::r~c:=;-,ec,~ Joel D. Groves, PE Polarconsult Project Manager cc: Art Bloom-City of Tenakee Springs Project Manager Enclosures: ADNR Land Lease Apnljcation / ~plicatiou lee ($!00.) w.lli\t:J:::., l...::ic..l>L .:;.,Jr-. Development Plan/ Map/ Coastal Project Questionnaire / RCA CPC'N tt363 / ADNR Eas_I~?J!tffiiA..llilhci!!iQll /, ·" LtJCA L "')l>v'r. -A~Iic·Jtinn Fee(~ 100:+ v-llL!D. Envin>nmcm~d Risk Questionmurc / Qth..:r l~erm!l t\ppll<;a!I~'O::>Lfu_r Be/erenc£1. ADNR \Vat,•r R1ghts ;\pphcatlOn _.. ADHi l1'h llab!lat Appl!cati(•n-/ CCH Wc·tland~ .'\pphcatton I UH · lmdtng of \,J(ln-Junsdtction / 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net ·. STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER D Northern Region 3700 Airport Way Fairbanks, AK 99709 (907) 451-2740 0 Southcentral Region 550 W 7th Ave., Suite 900C Anchorage, AK 99501-3577 (907} 269-8552 0 Resource Allocation and Development 550 W 7th Ave., Suite 1050 Anchorage, AK 99501-3579 (907) 269-8534 !8i Southeast Region 400 Willoughby, #400 Juneau, AK 99801 {907} 465-3400 APPLICATION FOR PURCHASE OR LEASE OF STATE LAND Date Applicant's -Name CI.T'-I Of 'f~~ <;fR1~ Mailing Address P.o. 136?< -52. Message Phone t<l"''l ~3'='-1.."2.(5::,. Work Phone ( ADL #(assigned by DNR) Doing business as:'T~IJA~ 'S~t~S t;~ c.;ni.I'N ~. 'tiMe-Soc. Sec.# and/or Tax ID # Is applicant a corporation qualified to do business in Alaska? 0 yes 1&1 no. Is the corporation in good standing with the State of Alaska, Dept. of Commerce and Economic Development? 0 yes no. N /A Is applicant 18 years or older? ~ yes 0 no. Are you applying for a~ lease or 0 sale? What kind of lease or sale are you applying for? Tideland; 'Ei(l Public/Charitable Use; 0 Grazing; 0 Millsite; 0 Negotiated; 0 Competitive. If a lease, how many years are you applying for? '55" years. Legal Description: C'Of'flgZ. re... Meridian, Township Ol.f':fo '5. , Range 06.'3.£"' , Section _6 1-"LL Municipality1"~~ ~~ .. ~~ Acres A/-L LORAN Reading (optional) __ -_____ _ Geographic Location: Sf0 tf=t. 'lo •• N ; l3 ~0 ll 1 TI It w What is the proposed use of and activity on the state land? ~!L ~o,.J "i.c..tLrri . -----~-------------------~---~ Are there any improvements on the land now? g) yes estimated value? .fi~M l~ • ~ B"-1 no. If yes, who owns the improvements, and what is their U.~. ~~ ot;;e.~Z.~JilE. U~LuF U, .. M~..., • Are there any improvements or construction planned? r yes 0 no. If yes, describe them and their estimated value. fl~~J(u:: ... ~T' e_::rr:;::r. VA.lJG: ?.b, ~tLL.to~ State the proposed construction date: 4 ( l /1on-; estimated completion date: q{( / Z0 1L Name and address of adjacent land owners and, if you are applying for tidelands, the name and address of the adjacent upland owners: C::::t'N .Of' ~.:£ <;prl.t~S.; tl. S • .fbk:Sr ~c..E:, Are you currently in default on any purchase contract or lease issued by the department? D yes b(f no. Within the past three years, has the department foreclosed or terminated any purchase contract or lease issued to you? 0 yes l{] no. Non-refundable filing fee: $100 Date Stamp: (Fee may be woived under 11 AAC 05.01 O(c)l 102-10:l (R<N. 10/01) Is the land applied for subject to any existing leases or permits? ~ yes 0 no. If yes, ~lease or 0 permit? Name lease/permit is issued under: U.S. +o~ ~IIICC, ADL l~?.~l..} Do you think you qualify for a non-competitive lease or sale?~ yes 0 no. If yes, under what provision of AS 38.05? O AS 38.05.035(b)(2) (to correct an error or omission); O AS 38.05.035(b)(3) (owner of bona fide improvements); O AS 38.05.035(b)(5) (occupied, or are the heir of someone who occupied the land before statehood); O AS 38.05.035(b)(7) (adjacent owner of remnant of state land, not adjoining other state land; O AS 38.05.068 and .087 (U.S. Forest Service Permittee); D AS 38.05.075(c) (upland owner or lessee); O AS 38.05.035(f) (erected a building and used the land for business purposes); 0 AS 38.05.102 (current long-term lessee or current shore fishery lessee); O AS 38.05.255 (millsite lease for mine-related facilities); ~ AS 38.05.810(a) (government agency; tax-exempt, non-profit organization organized to operate a cemetery, solid waste facility, or other public facility; or a subdivision's nonprofit, tax-exempt homeowners' association); 0 AS 38.05.810(b)-{d) (non-profit corporation, association, club, or society operated for charitable, religious, scientific, or educational purposes, or for the promotion of social welfare, or a youth encampment); ~AS 38.05.810(e) (licensed public utility or licensed common carrier); jg AS 38.05.810(f) (non-profit cooperative organized under AS 10.25, or licensed public utility); D AS 38.05.810(h) (Alaska Aerospace Development Corporation); 0 AS 38.05.810(i) (port authority); D AS 38.05.825 (municipality applying for occupied or developable tidelands); D other (please explain):_....:..._ _______________________ ___: __ _ If you have checked one of the above statutes, attach a statement detailing your qualifications under each requirement of that statute. Do you think you qualify to lease the land for less than fair market value? r;8l yes D no. If yes, under what provision of AS 38.05? Signature D AS 38.05.097 (youth encampment or similar recreational purpose); 0 AS 38.05.098 (senior citizen discount for a residential lease); ::JoeL i). c:1RD~ Date CrN af' 1"'6-J~I(~ <;;PPJ. ~ > · 11f applying on behalf of an agency, municipality, or organization, state which one NOTICE TO APPLICANT: ~other (please explain). ,-s '3B • .,c Btofct) ft) ~/ / \ ()/3)/2DIO ·-'-------------·-·---------- £-,...JCj't~( ,..:4' GJ~Su~A~ Title • This application will not be considered unless it is accompanied by the appropriate filing fee and completed in full. THE FILING FEE WILL NOT BE REFUNDED NOR IS rr TRANSFERABLE. All checks are to be made payable to the Department of Revenue. • Include a map (1 :63,360 USGS) or sketch plat showing location of proposed activities in relation to survey monumentation or fixed geographical features which fully illustrates your intended use, including the location of buildings and improvements and access points, labeled with all dimensions, and a development plan providing a complete list of proposed activities. • The applicant may be required to deposit a sum of money sufficient to cover the estimated cost of survey, appraisal, and advertising. If the land is sold or leased to another party, the deposit will be returned to the applicant. • The filing of this application and payment of the filing fee vests the applicant with no right or priority in the lands applied for. It is merely an expression of the desire to purchase or lease a parcel of land when and if it becomes available. Filing an application serves the purpose of notifying the state that an individual is interested in purchasing or leasing land. It is not a claim. nor does it in any way obligate the state to sell or lease land. • If the application site is in the Coastal Zone, include a Coastal Project Questionnaire (www.gov.state.ak.ustdgc/Projects/projects.html). • If the application is for use in conjunction with a guide/outfitter operation, include proof of a guide/outfitter certification for the use area. • If the application is for a commercial operation, include a copy of your business license. • If the application is for a commercial fish camp, include a copy of your limited entry pennit or an interim-use salmon set net permit. • If applying for a senior citizen discount, include fonn 102·1042. • AS 38.05.035(a) authorizes the director to decide what infonnation is needed to process an application for the sale or use of state land and resources. This infonnation is made a part of the state public land records and becomes public infonnation under AS 40.25.110 and 40.25.120 (unless the information qualifies for confidentiality under AS 38.05.035(a)(9) and confidentiality is requested). Public infonnation is open to inspection by you or any member of the public. A person who is the subject of the infonnation may challenge its accuracy or completeness under AS 44.99.310, by giving a written description of the challenged infonnation, the changes needed to correct it, and a name and address where the person can be reached. False statements made in an application for a benefit are punishable under AS 11.56.210. 102-103 (Rev. 10/01) City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report G Polarconsult Alaska, Inc. ADNR EASEMENT PROCUREMENT November 2011 -Final Report APPENDIX D Joel Groves From: Date: To: Attach: Subject: Hi Jim, "Joel Groves" <joel@polarconsult.net> Thursday, September 01,201112:05 PM "Anderson, James W (DNR)" <jim.anderson@alaska.gov> 110729-lndianRiverConceptDesign_R2.pdf; Solicitation_1.zip Tenakee Hydro Project It was a pleasure talking to you today. I've attached two items for your information: Page 1 of 1 1. Conceptual design drawings for the project. Easements will be needed for the access roads, intake, powerhouse, penstock, and part of the power line. 2. USFS notice of RFP for putting Indian River Road into storage. Regards, Joel Joel D. Groves, PE Polarconsult Alaska, Inc. 1503 West 33rd Avenue, 3rd Floor Anchorage, Alaska 99503 Tel: 907.258.2420 x204 Fax: 907.258.2419 Cell: 907.360.9042 joel@polarconsult.net 9/14/2011 • polarconsult alaska, inc. ENGINEERS • PLANNERS • ENERGY CONSULTANTS JIM ANDERSON Division of Mining, Land and Water Leasing Section Alaska Department ofNatural Resources PO Box 111020 Juneau, AK 99811 August 31, 2010 Subject: Land Lease and Easement Applications for Indian River Hydroelectric Project Dear Mr. Anderson: On behalf of our client, the City of Tenakee Springs, enclosed please find applications for a lease of state land and for access/utility easements for the Indian River hydroelectric project. It appears that the project is eligible for a non-competitive lease as a Public I Charitable Use at less than fair market value as allowed in AS 38.05.810(a)(1), (e), and/or (f). The City of Tenakee Springs is organized as a 2nd Class City, and operates its Electric Utility Department as a Public Utility under Certificate of Public Convenience and Necessity (CPCN) #363, issued by the Regulatory Commission of Alaska (RCA) in 1986. If you have any questions regarding this application or the project in general, please give me a call at 907-258-2420. Sincerelv. /s/~.ac_~~ Joel D. Groves, PE Polarconsult Project Manager cc: Art Bloom-City of Tenakee Springs Project Manager Enclosures: APNR Land Lea;;e ApJlhcation / 1-'tpplicatiem I ee ($1 00 ) w.61 ~ • Development Plan/ Map/ Coastal Project Questionnaire / RCA CPCN 11363/ AD NR Easeme1.11 ,~QQQ~il_tl9!! / Applwal!!m I,.,,(;!. l 0\}:t ~Jt.L!:(). Fnvnnnrncnt:tl R1sk Questionnaire / Other.J~£~:illl t _;:\pp ll(<lti(:IJ" [J-IJL {?de renee) ADNR Watc:r 1\tl;h!S Application.- i\[)F(i l1sh !labllal .\ppl1cation/ CC Jl Wc·tlan,b .•\ppl!catton Fl R{ I <>I :"iun-.lunschcllon / 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsultnet STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER 0 Northern Region 3700 Airport Way Fairbanks, AK 99709 (907) 451-2740 0 Southcentral Region Non-refundable application fee: $100* 550 W 7th Ave., Suite 900C Anchorage, AK 99501-3577 (907) 269-8552 APPLICATION FOR EASEMENT AS 38.05.850 ~ Southeast Region 400 Willoughby, #400 Juneau, AK 99801 (907) 465-3400 ADL #..,.--,~.,--,---­ (to be filled in by state) Applicant's Name Crt'-1 or '1'~~ ~t~~ Mailing Address P.O. ~ 5'2.. Doing business as: '/SAAit.o.£" ~S e~!C.. (mur.,. ~. E-Mail: Cf'N1'):'1£""<2 <:;,.)AIL .{.t)!I-A.. City/State/Zip let-~A~ Sf'21~$ 1 AK ~8'-tl 4- MessagePhone(~)~~~·-~_2_0_~~--~W~o=~~P~h~on~e~(--~~---E ____ ~S~oc~·~S~e~c~.#~a~nd~/~or~T~a~x~I~D~#~------------- Is applicant a nonprofit cooperative association? [ ] yes t><1 no. If yes, are you applying for an exemption under AS 38.05.850(b)? [ ] yes W no. If yes, please submit proof of nonprofit status (e.g. by-laws, articles of incorporation, tax statement). Location of activity/Legal Description: Municipality J(!)JAIGB: <PRt~4't , Meridian CoPFr!L. 12.tVe:JL Township 4--=1 "5 Range ___,G=-'?>~(£'=-----Section { '5 'Sw 1/4, 1/4_ Township <fT 'S Range 63 l£ , Section L.l E 1/2. I __ 1/4 ~~ (attach extra sheets as needed) Z?._ tJW t/.r.t 1/o; I "'"L I Total length of applied-for easement (feet): <S~ Acres encompassed by easement: f';l. (O.'T AC- Total width of applied-for easement (feet): 3o 'TO lOo \ (43,560 square feet 1 acre) Specific purpose of easement (e.g. electric utility, fiber-optic conduit or cable, telecommunications tower, road, bridge, airstrip/airport, driveway, trail, drainage), and type of anticipated traffic (e.g. plane, truck, heavy equipment): Explain . l -----... ,_ ('Z..l)CI' 6tec.1'"rt.IL l.lf'ttt\( ( Q:IM.M.U ... \(A'\1~$, At:t:.ess. • '30 w~ -rj_ fSx)' PEN<s.TOGK Roure A...S:::./ult.. Ac(o-~S. / wo' w~ +I" ~1..00 1 Au~.<;.<;. ~ -t "f'RAI<-5.., (Oo' L...l !tiC: ----- Are you applying for the Division of Mining, Land and Water to reserve a Public Easement? Yes Rf No D. Are you applying to be granted a Private Easement? Yes No JZI. (Note Annual rental fee required for private easement) •see 11 AAC 05.010 regarding fees for federal, state, and local government agencies Date Stamp: 102-112 (Rev. 10/01) State briefly the standards and methods of construction: e.g. regulated standards, winter trail, dirt trail, gravel road, paved road, etc.; clearing by hand, clearing/construction by mechanical equipment (state type of equipment to be used, e.g. J.D. 350, 944 F.E. loader, hydro-axe, D-8), or establishment by use only. ------------------- -Powcslf..~ \.;tl~ 5£ pJilr/GI~Ul4-1'¥WL r.-( '(>ewe.,. 4 t:t~~'> \N Gt.-tttl....:C. oua-. Is this an existing use? Yes 0 No fig. If yes, provide documentation verifying existing use, such as easement atlas, affidavits attesting to use and existence, pictures, etc. Construction to begin: _...:'S::.c....;.;_H_£:~:W_::___U!I"::>--"'--4=1-(.)IL ___ <-t....;..r../..:..l.:../..:_r_z.. ______________________ _ Construction to be completed by: _______ ~_,/~1/._,1...::7.-:::;;._ _________________ _ Other permits or authorizations applied for in conjunction with this proposed project: --------------- At:::.J~ ~ CJ!!A<;J'S.i C\1"'( of'...,...~ c;Att,..t;~ ~~e:.~~i ,4.0...(:1. WAlb'-t.t<lf~j If this authorization is granted, I agree to construct and maintain the improvements authorized in a workmanlike manner, and to keep the area in a neat and sanitary condition; to comply with all the laws, rules, and regulations pertaining thereto; and provided further that upon termination of the easement for which application is being made, I agree to remove or relocate the improvements and restore the area without cost to the state and to the satisfaction of the Director of the Division of Mining, Land and Water. (<f/~&:!Z-<:::712,.~ CZ0 2CA6 Applicant's Signature Date INSTRUCTIONS: Attach a USGS map (scale of 1:63,360) or a state status plat showing the location of the proposed easement, and an environmental risk assessment questionnaire (form 1024008A}. The final granting or a private easement or reservation of a public easement will be contingent upon our receipt of a plat depicting the post- construction location or the improvements. If your application is approved, instructions for the completion of the plat will be provided to you, or can be picked up at any of our offices. AS 3S.05.035{a) authorizes the director to decide what information is needed to process an application for the sale or use of state land and resources. This information is made a part of the state public land records and becomes public information under AS 40.25.110 and 40.25.120 (unless the information qualifies for confidentiality under AS 38.05.035(a)(9) and confidentiality is requested). Public information is open to inspection by you or any member of the public. A person who is the subject of the information may challenge its accuracy or completeness under AS 44.99.310, by giving a written description of the challenged information, the changes needed to correct it, and a name and address where the person can be reached. False statements made in an application for a benefit are punishable under AS 11.56.210. 102-112 (Rev. 1 0/01) 2 STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER 0 Contract Administration 550 W 7th Ave., Suite 640 Anchorage, AK 99501-3576 (907) 269--8594 Northern Region 3700 Airport Way Fairbanks, AK 99709 (907) 451-2740 0 Soulflcentral Region 550 W 7th Ave., Suite 900C Anchorage, AK 99501-3577 (907) 269--8552 ~ Southeast Region 400 Willoughby, #400 Juneau, AK 99801 (907) 465-3400 APPLICANT ENVIRONMENTAL RISK QUESTIONNAIRE The purpose of this questionnaire is to help clarify the types of activities you propose to undertake. The questions are meant to help identify the level of environmental risk that may be associated with the proposed activity The Division of Mining, Land and Water's evaluation of environmental risk for the proposed activity does not imply that the parcel or the proposed activity is an environmental risk from the presence or use of hazardous substances. Through this analysis, you may become aware of environmental risks that you did not know about If so, you may want to consult with an environmental engineer or an attorney. C !.T't oF 'It:.~~ <;PR.( r-4S Applicant's Name Address (cto~ l -=J!G. 270'1 cCflR 1 -=r~-'7-1.o1 Message Phone Work Phone Describe the proposed activity: f! U,j -OF ~ll.lclt.. ·1 a-JA~ <:PI-<011 s 6L<::<:rf2 1L un '--~1'1 ~. Doing Business As City C t1't "T\(E <?. · c:l Jl.lfA IL. , (Or/\ E-Mail Contact Person State Zip :::Jex;..__ ClPove:s ( P£J~tl_cuJoJ._.._xr) In the course of your proposed activity will you generate, use, store, transport, dispose of. or otherwise come in contact with toxic and/or hazardous materials, and/or hydrocarbons? Yes~ No 0 If yes. please list the substances and the associated quantities Use a separate sheet of paper, if necessary. C!.A 'SOLt,...e-D.c.~L"'i.-1 Mtff~ OIL 1-t W6ES f:"ot. ~~6fT fj"'R ,,...~.""') C'CJ~ r:Ttl.IJCT/o;l • V\ S ~..0::::. Ill. S C1.t.Lcu~.5 1024008A (Rev. 10/01) If the proposed activities involve any storage tanks. either above or below ground. address the following quest1ons for each tank Please use a separate sheet of paper, if necessary, and, where appropriate. include maps or plats. a Where Will the tank be located? __ t--=_:~...:..(A_,_· ___________________________ _ b. What 'Will be stored in the tank? __ 1'0_/_' A_'._. _· --------------------------- c What will be the tank's size in gallons? ---"f'_i_,_l A_._.------------------------- d What will the tank be used for? (Commercial or residential purposes?) !fl 1--~t r .. e Will the tank be tested for leaks? -'-~-If\_. -·--------------------------- f. Will the tank be equipped with leak detection devices? Yes D No 0 If yes, describe: NIA. Do you know or have any reason to suspect that the site may have been previously contaminated? Yes 0 No ·~r If yes, please explain: -------------------------------------- I certify that due diligence has been exercised and proper inquiries made in completing this questionnaire, and that the foregoing is true and correct to the best of my knowledge Applicant Date AS 38.05 035(a) authorizes the director to decide what 1nformat10n IS needed to process an application for the sale or use of state land and resources. This inforrmtion is made a part of the state public land records and becomes public information under AS 09 25 110 and 09 25.120 (unless the information qualifies for confidentiality under AS 38.05.035(a)(9) and confidentiality IS requested). Pubhc 1nformatoon is open to Inspection by you or any member of the public. A person 'htlo is the subJect of the information may challenge its accuracy or COfT1'Ieteness under AS 44.99 310, by giving a wntten description of the challenged informabon, the changes needed to correct it, and a name and address where the person can be reached False statements made In an application for a benefit are punishable under AS 11 56 210 102-4008A (Rev. 10/01) City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report 11. Polarconsult Alaska, Inc. ADNR COASTAL PROJECT QUESTIONNAIRE November 2011 -Final Report APPENDIX D DEPARTMENT OF NATURAL RESOURCES DIVISION OF COASTAL & OCEAN MANAGEMENT http://www.alaskacoast.state.ak.us City of Tenakee Springs Joel D. Graves 1503 West 33rd Avenue, Suite 310 Anchorage, AK. 99503 June 29, 2011 Subject: Review Termination/Program Termination Indian River (Tenakee Springs Hydro Development) ACMP I.D. # 2010-0904J Dear Mr. Graves: SEANPARNELL,GOVERNOR 0 P.O. BOX 111030 JUNEAU, ALASKA 99811-1030 PHONE: (907) 465-3562 FAX: (907) 465-3075 0 550 WEST 7TH AVENUE, SUITE 705 ANCHORAGE, ALASKA 99501-3559 PHONE: (907) 269-7470 FAX: (907) 269-3981 The Division of Coastal and Ocean Management (DCOM) has not yet initiated a consistency review of your above-referenced project. The Alaska Coastal Management Program (ACMP) is scheduled to terminate as of July 1, 2011. Should the ACMP sunset, your proposed project will no longer be subject to ACMP consistency review as of 5:00 PM, June 30, 2011. However, it is extremely important for you to note that, despite termination of the ACMP, you must still obtain any federal, state or local permits, licenses or authorizations your project needs. Because DCOM may not be able to inform review participants and the U.S. Army Corps of Engineers, please retain this letter as proof that your project is no longer subject to ACMP review. cc: Fran Roche -ADEC, Juneau David Kelley -ADNR/DML W, Juneau Kristin Dirks -ADNRIDML W, Juneau Jackie Timothy -ADFG/Habitat, Juneau Sincerely, Jill Taylor Project Review Coordinator "Develop, Conserve, and Enhance Natural Resources for Present and Future Alaskans. " Marla Carter ADFG, Anchorage State Historical Preservation Office -ADNR/SHPO, Anchorage Linda Speerstra-USACE Regulatory, Sitka CARRIE BOHAN DIVISION OF COAST AND OCEAN MANAGEMENT Alaska Department of Natural Resources PO Box 111030 Juneau, AK 99811 August 31, 2010 Subject: Coastal Project Questionnaire for Indian River Hydroelectric Project Dear Ms. Bohan: On behalf of our client, the City of Tenakee Springs, enclosed please find a completed coastal project questionnaire for the Indian River Hydroelectric Project. If you have any questions regarding this application or the project in general, please give me a call at 907-258-2420. Sincerely, /¥"~Ja~ Joel D. Groves, PE Polarconsult Project Manager ££.;. Art Bloom City of Tenakee Springs Project Manager Enclosures: ADNR Coastal Project Questionnaire ~/ Pther Permit Applications -ADNR lease and easement applications/ ADNR water rights application./ ADFG fish habitat application " COE wetlands application/ FERC Fmding of Non-Jurisdiction / -p,;..aeet:J~ / Pf~"' D~c-R-'"P 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management Coastal Project Questionnaire and Certification Statement The Coastal Project Questionnaire (CPQ) is a diagnostic tool that will identify the state and federal permit requirements for your project that are subject to a consistency review. You must answer all questions. If you answer "Yes" to any of the questions, please call that specific department for further instructions to avoid delay in processing your application. You can find an agency contact list online at http:/ /alaskacoast.state.ak. us/Contacts/PRCregcont.html. A complete project packet includes accurate maps and plan drawings at scales large enough to show details, copies of your state and federal permit applications, your answers to this questionnaire, and a complete consistency evaluation. DCOM will notify you within 21 days of receipt if the packet is incomplete and what information is still required. For additional information or assistance, you may call or email the Juneau Project Review at (907) 465-2142, or the Anchorage Project Review at (907) 269-7478. This CPQ document contains numerous hyperlinks (underlined text that has a connection to an internet web page) and is best viewed on-line. Additional instructions are available at http://www.alaskacoast.state.ak.us/Projects/pcpq.html • APPLICANT INFORMATION 1. CITY OF TENAKEE SPRINGS/DBA ELEC UTIL OPT Name of Applicant PO BOX 52 Address TENAKEE SPRINGS, AK 99841 City/State/Zip 907-736-2207 Daytime Phone 736-2207 CITYTKE@GMAIL.COM Fax Number E-mail Address 2. POLARCONSUL T ALASKA, INC. I JOEL GROVES Agent (or responsible party if other than applicant) 1503 WEST 33RD AVENUE SUITE 310 Address ANCHORAGE, AK 99503 City/State/Zip 907-258-2420 x204 Daytime Phone 258-2419 JOEL@POLARCONSULT.NET Fax Number E-mail Address • PROJECT INFORMATION Yes No 1. This activity is a: liJ new project 0 modification or addition to an existing project 2. If this is a modification or an addition, do you currently have any State, federal or local approvals for this activity? 0 0 NOTE: Approval means any form of authorization. If "yes," please list below: A IT A I# I D E .. D \pprova l ype 'pprova ssuance ate xprratwn ate FERC NON JURISDICTION 0110-8 5/26/10 N/A 3. If this is a modification, was this original project reviewed for consistency with the Alaska Coastal Management Program? .................................................................... ......................................................................................................... 0 0 Previous ACMP I.D. Number: (example: AK 0706-0SAA or ID2004-0505JJ) Previous Project Name: Previous Project Applicant: ________ _ • PROJECT DESCRIPTION Attach a complete and detailed narrative description of your new project or of your modification/addition including ALL associated facilities and changes to the current land or water use (if not already attached as part of an agency application). Clearly delineate the project boundaries and all property owners, including owners of adjacent land, on the site plan. The scale of the maps and plan drawings must be large enough to show pertinent details. Identify your proposed footprint or CPQ Revised 8/15/2008 Page 1 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management disturbed area. If this project is a modification to an approved project, identify existing facilities and proposed changes on the site plan. Proposed starting date for project: 4/1/2012 Proposed ending date for project: 9/1/2012 • PROJECT LOCATION and LAND OWNERSHIP 4. Describe/identify the project location on a map (Including nearest community, the name of the nearest land feature or body of water, and other legal description such as a survey or lot number.). Township 047S Range 063E Section 15,21,22 Meridian COPPER Latitude/Longitude 57 d4 7'20" I 135d 11 '37' (specify Decimal Degrees or Degrees, Minutes, Seconds) USGS Quad Map SITKA 04 5. The project is located on: [j] State land or water* D Federal land D Private land [j] Municipal land (Check all that apply) D Mental Health Trust land D University of Alaska land Contact the applicable landowner(s) to obtain necessary authorization. State land ownership can be verified using Alaska Mapper. *State land can be uplands, tidelands or submerged lands to 3 miles offshore. 6. Is the project within or associated with the Trans Alaska Pipeline corridor? ..................................................................... . • COASTAL DISTRICT 7. Is the project located in a coastal district? ......................................................................................................................... . If yes, identify the applicable coastal district(s) NONE and contact them to ensure your project conforms with district policies and zoning requirements. Coastal districts are a municipality or borough, home rule or first class city, second class municipality with planning powers, or coastal resource service area. A coastal district is a participant in the State's consistency review process. Early interaction with the district can benefit you significantly; please contact the district representative listed on the contact list at http://www.alaskacoast.state.ak.us/Contacts/PRCregcont.html • DEPARTMENT OF NATURAL RESOURCES (DNR) APPROVALS DNR DIVISION OF MINING, LAND & WATER-LAND SECTION 1. Is the proposed project on State-owned land or water or will you need to cross State-owned land for access? (NOTE: State land includes the land below the ordinary high water line of navigable streams, rivers and lakes, and in marine waters, below the mean high tide line seaward for three miles. State land does not include Alaska Mental Health Trust Land or University of Alaska Land.) ................................................................................................... . 2. If you answered yes to the question above, indicate the person you contacted at the appropriate Division of Mining, Land and Water regional office for information. a) Name/date of Contact: JIM ANDERSON 3/10/10 b) Is an application required for the proposed activity? .................................................................................................... . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: __________ _ DNR DIVISION OF MINING, LAND & WATER-MATERIALS SECTION 3. Do you plan to dredge or otherwise excavate or remove materials such as rock, sand, gravel, peat, or overburden from any land regardless of ownership? ..................................................................................................................................... . a) Location of excavation site if different than the project site: ______ _ Township __ Range __ Section __ Meridian __ 4. At any one site (regardless of land ownership), do you plan any of the following? ........................................................... . D Excavate five or more acres over a year's time D Excavate 50,000 cubic yards or more of materials (rock, sand, gravel, soil, peat, overburden, etc.) over a year's time D Have a cumulative, un-reclaimed, excavated area of five or more acres Yes No D 0 Yes No D 0 Yes No 0 D 0 D Yes No D 0 D 0 5. Do you plan to place fill or excavated material on State-owned land?............................................................................... D 0 a) Location of fill or material disposal site if different than the project site: ______ _ Township__ Range __ Section __ Meridian __ 6. If you answered yes to any question above, indicate the person you contacted at the appropriate Division of Mining, CPO Revised 8/15/2008 Page 2 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management Land and Water regional office for information. a) Name/date of Contact: ______ _ b) Is an application required for the proposed activity? ..................................................................................................... . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: __________ _ DNR DIVISION OF MINING, LAND & WATER-MINING SECTION 7. Do you plan to mine for locatable minerals such as silver, gold, or copper? ................................................................... ;. 8. Do you plan to explore for or extract coal? ....................................................................................................................... . 9. If you answered yes to any question above, indicate the person you contacted at the appropriate Division of Mining, Land and Water regional office for information. a) Name/date of Contact: b) Is an application required for the proposed activity? ..................................................................................................... . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: __________ _ DNR DIVISION OF MINING, LAND & WATER-WATER SECTION 10. Will this project or development divert, impound, withdraw, or use any fresh water (regardless of land ownership)? (NOTE: If you know of other water users who withdraw from the same source or any potential conflicts affecting this use of water, contact the Water Section. If you are obtaining water exclusively from either an existing Public Water Supply or from a rainwater catchment system, you are not required to contact the DNR Water Section regional office.) ..................... . a) Check all points-of-withdrawal or water sources that apply: D Public Water system (name):--:-:--:-=-::-:=----- [jj Stream or Lake (name): INDIAN RIVER DWell D Rain catchment system D Other: b) Intended use(s) of water: HYDROELECTRIC POWER GENERATION c) Amount (maximum daily, not average, in gallons per day): 51.7 MILLION GPO d) Is the point of water withdrawal on property you own? ............................................................................ . 11. Do you plan to build or alter a dam (regardless ofland ownership)? ................................................................................. . 12. If you answered yes to any question above, indicate the person you contacted at the appropriate Division of Mining, Land and Water regional office for information. a) Name/date of Contact: DAN BUSSARD 3/1 0/10 b) Is an application required for the proposed activity? ...................................................................................................... . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: __________ _ DNR DIVISION OF FORESTRY 13. Does your operation meet both of the following criteria on any land, regardless of ownership? a) The project will commercially harvest timber on 10 or more acres, or commercially harvest timber that intersects, encompasses, or borders on surface waters, and b) The project involves one or more of the following: site preparation, thinning, slash treatment, construction and maintenance of roads associated with a commercial timber harvest, or any other activity leading to or connected to a commercial timber harvest operation ..................................................................................................................... . 14. If you answered yes to any question above, indicate the person you contacted at the appropriate Division ofF ores try regional office for information. a) Name/date of Contact: b) Is an application required for the proposed activity? ..................................................................................................... . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: __________ _ CPQ Revised 8/15/2008 Page 3 of 18 D D Yes No D El D 0 D D Yes No El D D 0 D 0 0 D Yes No D 0 D D State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management DNR DIVISION OF OIL & GAS 15. a) Will you be exploring for or producing oil and/or gas? ......................................................................... . b) Will you conduct surface use activities on/within an oil and gas lease or unit? ............................................ .. If yes, please specify: ________ _ 16. Do you plan to drill a geothermal well (regardless ofland ownership)? ......................................................... . 17. If you answered yes to any question above, indicate the person you contacted at the appropriate Division of Oil & Gas office for information. a) Name/date of Contact: _____ _ b) Is an application required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation:----------- Visit the Division of Oil & Gas website for application forms and additional information. DNR OFFICE OF IDSTORY & ARCHAEOLOGY 18. Will you investigate, remove, or impact historical, archaeological or paleontological resources (anything over 50 years old) on State-owned land? .............................................................................................................. . 19. If you answered yes to the question above, indicate the person you contacted at the State Historic Preservation Office for information. a) Name/date of Contact: ______ _ DNR DIVISION OF GEOLOGICAL & GEOPHYSICAL SURVEYS Yes No D 0 D 0 D ~ D D Yes No D 0 Yes No 20. Is the proposed project located within a natural hazard area designated by a coastal district in the approved district plan? (Refer to the district plan or contact the coastal district office.) . . .. . . . . . . . . . . . . . . . . . .. . .. . .. . .. . .. . .. . .. . .. ... . .. . .. . .. . . . .. D ~ a) If "yes", describe the measures you will take in the siting, design, construction, and operation of the proposed activity to protect public safety, services, and the environment from potential damage caused by the designated natural hazard(s) in the Natural Hazards portion of the attached Coastal Consistency Evaluation (11 AAC 112.210). 21. If you have contacted someone, please indicate the person you contacted at the or the State for information. The Division of Geological & Geophysical Survey may have additional information on hazards for the area. a) Name/date of Contact: ______ _ DNR DIVISION OF PARKS & OUTDOOR RECREATION 22. Is the proposed project located in a unit of the Alaska State Park System including navigable waters, tidelands or Yes No submerged lands to three miles offshore? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0 23. If you answered yes to any question above, indicate the person you contacted at the appropriate DNR Division of Parks & Recreation office for information. a) Name/date of Contact: ______ _ b) Is an application required for the proposed activity? ............................................................................. . c) If "YES" then submit a signed copy ofthe completed application to the DCOM. If "No", explain why an application isn't required. Explanation: __________ _ DNR APPROVALS List the Department of Natural Resources permits or authorizations required for your project below: T f' 1 eded r· 1 ypes or project approva s or pemuts ne Date application submitted LAND EASEMENT AND LEASE ~UGUST 2010 !WATER RIGHTS ~UGUST 2010 COASTAL ZOME CONSISTENCY DETERMINATION ~UGUST 2010 • DEPARTMENT OF FISH AND GAME (DFG) APPROVALS Yes No 1. Is your project located in a designated State Game Refuge, Critical Habitat Area or State Game Sanctuary? . . . . . . . . . . . . ... 0 2. Does your project include construction/operation of a salmon hatchery? . . . . . . . .. . . .. . . . . .. . . . . . . . . . . . . . . . . . . . . . . . .. . .. . .. . . . . . 0 CPO Revised 8/15/2008 Page 4 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management 3. Does your project affect, or is it related to, a previously permitted salmon hatchery? . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . .. . .. . D ~ 4. Does your project include construction of an aquatic farm? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D 0 5. Will you work in, remove water or material from, or place anything in, a stream, river or lake? (NOTE: This includes work or activities below the ordinary high water mark or on ice, in the active flood plain, on islands, in or on the face of the banks, or, for streams entering or flowing through tidelands, above the level of mean lower low tide. If the proposed project is located within a special flood hazard area, a municipal floodplain development permit may be required. Contact the affected city or borough planning department for additional information and a floodplain determination.) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . .. . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . ... 0 D a) If yes, name of waterbody: _,_,1 N-"D='-IA-"N-'--'-R=IV-'-=E"-R=---------- 6. If you answered yes to any questions above, indicate the person you contacted at the appropriate Department of Fish and Game office for information. (For projects involving Hatcheries or Aquatic Farms, please contact the Division of Commercial Fisheries. Other projects should contact the Division o(Habitat.) a) Name/date ofContact: JACKIE TIMOTHY 3/10/10 b) Is an application required for the proposed activity? .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. 0 D c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: --------------------------------------------- DFG APPROVALS List the Department of Fish and Game permits or authorizations required for your project below: Types of project approvals or permits needed. Date applicatiOn submitted FISH HABITAT PERMIT AUGUST 2010 • DEPARTMENT OF ENVIRONMENTAL CONSERVATION (DEC) APPROVALS DEC DIVISION OF WATER Yes No 1 a) Will a discharge of non-domestic wastewater to lands, waters, or the subsurface of the state occur? (NOTE: Non- domestic wastewater includes wastewater from commercial or industrial facilities, excavation projects, wastewater from man-made containers or containment areas, or any other non-domestic wastewater disposal activities see 18 AA C 72.990 for definitions.) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ... D 0 b) Will a discharge of domestic wastewater or septage to lands, waters or the subsurface of the state occur? (see 18 AAC 72.990 for definitions.) . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . .. . .. . . . .. . . . . . . . . . . . . . . . . . . . . .. . . .. . . . . .. . . .. . . . . . . . . . . . . . . . . . . . . . . ... D 0 c) Will the wastewater disposal activity require a mixing zone or zone of deposit to meet Water Quality Standards (WQS)? (Many disposal activities require a mixing zone to meet WQS, contact DEC if unsure.) .. .. .. .. .. .. .. .. .. .. .. .... D 0 d) Will the project include a stormwater collection/discharge system? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D 0 e) Will the project include placing fill in wetlands? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . .. . . .. . . . . . . . .. ~ D f) Is the surrounding area inundated with water at any time of the year? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D 0 g) Do you intend to construct, install, modify or use any part of a domestic or non-domestic wastewater treatment or disposal system? . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. .. . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . .. . . . D 0 2. Does your project qualify for a general permit for wastewater? ............................................................... D D 3. If you answered yes to any questions above, indicate the person you contacted at the DEC-Division of Water for information. a) Name/date of Contact: -'-'N"-'/A'-'----- b) Is an application required for the proposed activity? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D 0 c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: COVERED BY CORPS PERMIT CPO Revised 8/15/2008 Page 5 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management DEC DIVISION OF ENVIRONMENTAL HEALTH 4 a) Will your project result in construction, modification, or operation of a facility for solid waste disposal? (NOTE: Solid waste means drilling wastes, household garbage, refuse, sludge, construction or demolition wastes, industrial solid waste, asbestos, and other discarded, abandoned, or unwanted solid or semi-solid material, whether or not subject to decomposition, originating from any source. Disposal means placement of solid waste on land.) ......... . b) Will your project result in treatment of solid waste at the site? (Examples of treatment methods include, but are not limited to: incineration, open burning, baling, and composting.) .............................................................. . c) Will your project result in storage or transfer of solid waste at the site? ...................................................... . d) Will the project result in storage of more than 50 tons of materials for reuse, recycling, or resource recovery? ........ . e) Will any sewage solids or biosolids be disposed of or land-applied to the site? (NOTE: Sewage solids include wastes that have been removed from a wastewater treatment plant system, such as a septic tank lagoon dredge, or wastewater treatment sludge that contain no free liquids. Biosolids are the solid, semi-solid or liquid residues produced during the treatment of domestic septage in a treatment works which are land applied for beneficial use.) .. 5. Will your project require application of oil, pesticides, and/or any other broadcast chemicals? .............................. . 6. Docs your project qualify for a general permit for solid waste? .............................................................. .. 7. If you answered yes to any question above, indicate the person you contacted at the DEC-Division of Environmental Health for information. a) Name/date of Contact: ___ _ b) Is an application required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation:----------- DEC DIVISION OF AIR QUALITY 8 a) Will you have an asphalt plant designed to process no less than five tons per hour of product? .......................... . b) Will you have a thermal remediation unit with a rated capacity of at least five tons per hours of untreated material? .. c) Will you have a rock crusher with a rated capacity of at least five tons per hour? ........................................... . d) Will you have one or more incinerators with a cumulative rated capacity of 1,000 pounds or more per hour? ......... . e) Will you have a coal preparation plant? ............................................................................................ . t) Will you have a Port of Anchorage stationary source? .......................................................................... .. g) Will you have a facility with the potential to emit no less than 100 tons per year of any regulated air contaminant? ... .. h) Will you have a facility with the potential to emit no less than 10 tons per year of any hazardous air contaminant or 25 tons per year of all hazardous air contaminants? ....................................................................................................... . i) Will you be constructing a new stationary source with a potential to emit greater than: ................................... . D 15 tons per year (tpy) ofPM-10 D 40 tpy of nitrogen oxides D 40 tpy of sulfur dioxide D 0.6 tpy of lead; or D 100 tpy of CO within 10 krn of a nonattainment area j) Will you be commencing construction, or (if not already authorized under 18 AAC 50) relocating a portable oil and gas operation? (answer "yes" unless you will comply with an existing operating permit developed for the portable oil and gas operation at the permitted location; or you will operate as allowed under AS 46.14.275 without an operating permit) ....................................................................................................................................... .. k) Will you be commencing construction or (if not already authorized under 18 AAC 50) relocating an emission unit with a rated capacity of 10 million Btu or more per hour in a sulfur dioxide special protection area established under 18 AAC 50.025? ....................................................................................................................... . l) Will you be commencing a physical change to or a change in the method of construction of an existing stationary source with a potential to emit an air pollutant greater than an amount listed in g) that will cause for that pollutant an emission increase (calculated at your discretion) as either an increase in potential to emit that is greater than: D 10 tpy ofPM-10 D 10 tpy of sulfur dioxide D 1 0 tpy of nitrogen oxides; or D 100 tpy of CO within 10 krn of a nonattainment area; or actual emissions and a net emissions increase greater than: CPO Revised 8/1512008 Page 6 of 18 Yes No D 0 D 0 D 0 D 0 D 0 D 0 D D D D Yes No D 0 D 0 D EJ D 0 D 0 D 0 D 0 D 0 D 0 D 0 D 0 D 0 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management D 10 tpy ofPM-10 D 10 tpy of sulfur dioxide D 10 tpy of nitrogen oxides; or D 100 tpy of CO within 10 km of a nonattainment area m) Will you be commencing construction or making a major modification of a Prevention of Significant Deterioration stationary source under 18 AAC 50.306? ........................................................................................... . n) Will you be commencing construction or making a major modification of a nonattainment area major stationary source under 18 AAC 50.311? ........................................................................................................ . o) Will you be commencing construction or reconstructing a major stationary source under 18 AAC 50.316, for hazardous air pollutants? Definition of Regulated Air Pollutants can be found at http://www .epa.gov /ttn/oarpg/t5/memoranda/rapdef.pdf ................................................................................................. . 9. If you answered yes to any questions above, indicate the person you contacted at the DEC-Division of Air Quality for information. a) Name/date of Contact: b) Is an application required for the proposed activity? ............................................................................. . c) If "YES" then submit a signed copy of the completed application to the DCOM. If "No", explain why an application isn't required. Explanation: __________ _ DEC DIVISION OF SPILL PREVENTION AND RESPONSE 10 a) Will your project involve the operation of waterborne tank vessels or oil barges that carry crude or non crude oil as bulk cargo, or the transfer of oil or other petroleum products to or from such a vessel or a pipeline system? ............ . b) Will your project require or include onshore or offshore oil facilities with an effective aggregate storage capacity of greater than 5,000 barrels of crude oil or greater than 10,000 barrels of non-crude oil? ..................................... . c) Will you operate facilities on land or water for exploration or production of hydrocarbons? .............................. . 11. If you answered yes to any questions above, indicate the person you contacted at the DEC-Division of Spill Prevention and Response office for information. a) Name/date of Contact: b) Is a plan required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy of the completed Oil Discharge Prevention & Contingency Plan to the DCOM. If"No", explain why an application isn't required. Explanation: __________ _ DEC APPROVALS List the Department of Environmental Conservation permits or authorizations required for your project below: Types of plan approvals or permits needed Date application submitted N/A • FEDERAL APPROVALS D 0 D 0 D 0 D D Yes No D 0 D 0 D 0 D D U.S. ARMY CORPS OF ENGINEERS (USACE) Yes No 1. Will you discharge dredged and/or fill material or perform dredging activities in waters of the U.S? Section 404 of the Clean Water Act requires that a Department of the Army permit be obtained for the placement or discharge of dredged and/or fill material into waters of the U.S., including wetlands (33 U.S.C. 1344). (Your application to the USACE would also serve as application for DEC Water Quality Certification.) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0 D 2. Will you place fill or structures or perform work in waters of the U.S? Section 10 of the Rivers and Harbors Act of 1899 requires that a Department of the Army permit be obtained for structures or work in or affecting navigable waters of the U.S. (33 U.S.C. 403) (Waters of the US. include marine waters subject to the ebb and flow of the tide, rivers, streams, lakes tributaries, and wetlands. If you are not certain whether your proposed project is located within a wetland, contact the USACE Regulatory Division to request a wetlands determination. For additional information about the Regulatory Program, visit www.poa.usace.armv.mil/reg) . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ... 0 D CPO Revised 8/15/2008 Page 7 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management 3. If you answered yes to the question above, indicate the person you contacted at the US Army Corps of Engineers for information. a) Name/date of Contact: _,_N...,/A,_,_ __ b) Is an application required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation:----------- BUREAU OF LAND MANAGEMENT (BLM) 4. Is the proposed project located on BLM land, or will you need to cross BLM land for access? .............................. . 5. If you answered yes to the question above, indicate the person you contacted at the Bureau of Land Management for information. a) Name/date of Contact: ___ _ b) Is an application required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: ----------- U.S. COAST GUARD <USCG) 6 a) Do you plan to construct a bridge or causeway over tidal (ocean) waters, or navigable rivers, streams or lakes? ........ . b) Does your project involve building an access to an island? .................................................................... .. c) Do you plan to site, construct, or operate a deepwater port? .................................................................... . 7. If you answered yes to any question above, indicate the person you contacted at the appropriate US Coast Guard office for information. a) Name/date of Contact: ___ _ b) Is an application required for the proposed activity? ........................................................................... .. c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation:----------- U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA) 8 a) Will the proposed project have a discharge to any waters? ...................................................................... .. b) Will you dispose of sewage sludge? ............................................................................................... .. c) Will construction of your project expose I or more acres of soil? (NOTE: This applies to the total amount of land disturbed, even if disturbance is distributed over more than one season, and also applies to areas that are part of a larger common plan of development or sale.) ..................................................................................... .. d) Is your project an industrial facility that will have stormwater discharge directly related to manufacturing, processing, or raw materials storage areas at an industrial plant? If you answered yes to c) or d), your project may require an NPDES Stormwater permit ........................................................................................................... . 9. If you answered yes to any question above, indicate the person you contacted at the US Environmental Protection Agency for information. a) Name/date of Contact: :...:Nc:..:./A-=---- b) Is an application required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy of the completed application to the DCOM. If"No", explain why an application isn't required. Explanation: SWPPP WILL BE FILED FOR CONSTRUCTION FEDERAL AVIATION ADMINISTRATION (FAA) 10 a) Is your project located within five miles of any public airport? ............................................................. .. b) Will you have a waste discharge that is likely to decay within 5,000 feet of any public airport? ....................... . II. If you answered yes to the question above, indicate the person you contacted at the Federal Aviation Administration for information. a) Name/date of Contact: ___ _ CPQ Revised 8/15/2008 Page 8 of 18 0 D Yes No D 0 D D Yes No D 0 D 0 D 0 D D Yes No D [!] D 0 0 D D 0 D 0 Yes No D 0 D 0 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management FEDERAL ENERGY REGULATORY COMMISSION (FERC) 12 a) Does the project include any of the following: ................................................................................... . I) a non-federal hydroelectric project on any navigable body ofwater 2) locating a hydro project on federal land (including transmission lines) 3) using surplus water from any federal government dam for a hydro project b) Does the project include construction and operation, or abandonment of interstate natural gas pipeline facilities under sections 7 (b) and (e) of the Natural Gas Act (NGA)? ................................................................... . c) Does the project include construction and operation of natural gas or liquefied natural gas importation or exportation facilities under section 3 of the NGA? ........................................................................................................ . d) Does the project include construction for physical interconnection of electric transmission facilities under section 202 (b) of the FPA? ................................................................................................................. . 13. If you answered yes to any question above, indicate the person you contacted at the appropriate Federal Energy Regulatory Commission office for information. a) Name/date of Contact: ___ _ b) Is an application required for the proposed activity? ............................................................................. . c) If"YES" then submit a signed copy ofthe completed application to the DCOM. If"No", explain why an application isn't required. Explanation:----------- U.S. FOREST SERVICE (USFS) 14 a) Does the proposed project involve construction on USFS land? ................................................................ . b) Does the proposed project involve the crossing of USFS land with a water line? ............................................ . c) The current list of Forest Service permits that require ACMP consistency review are online at http://alaskacoast.stat!;,!!k.us!Ciawhome/handbooklpdf!ll AAC llO.pdfin Article 4, 11 AAC 110.400, pages 28-30. Does your proposed project include any of Forest Service authorizations found on pages 28-30 of the ACMP Handbook? ............................................................................................................................. . 15. If you answered yes to any question above, indicate the person you contacted at United States Forest Service for information. a) Name/date of Contact: ___ _ b) Is an application required for the proposed activity? .......................................................................... .. c) lf"YES" then submit a signed copy of the completed application to the DCOM. lf"No", explain why an application isn't required. Explanation:----------- U.S. FISH AND WILDLIFE SERVICE (USFWS) 16 a) Is your proposed project on land managed by the USFWS? .................................................................... . b) Does your project require a Right of Way from the USFWS under 50 C.F.R. 29 and 50 C.F.R 36? ............................ .. 17. If you answered yes to any question above, indicate the person you contacted at the US Fish and Wildlife Service for information. a) Name/date of Contact: b) Is an application required for the proposed activity? ............................................................................. . c) lf"YES" then submit a signed copy of the completed application to the DCOM. lf"No", explain why an application isn't required. Explanation: ----------- OTHER FEDERAL AGENCY APPROVALS 18 a) Other Federal agencies with authorizations reviewable under the Alaska Coastal Management Program are posted online at h!!p://alaskl!coast.st~te.ak. us/Ciaw_homelhandbook!pdfi' II AAC II O.pdf in Article 4, II AAC 110.400, pages 28-30. Does your proposed project include any of the Federal agency authorizations found on pages 28-30 of Yes No 0 0 0 0 0 0 0 0 0 0 Yes No 0 0 0 0 0 0 0 0 Yes No 0 0 0 0 0 0 Yes No the ACMP Handbook? . . .. . .. . .. . .. . .. . .. . .. . .. . .. .. . .. .. . .. . .. . .. . .. .. . .. . . . .. . .. . .. . .. .. .. . .. . .. . .. . .. . .. .. . . .. . .. .. . . . . . . . . . . . . . . .... 0 0 b) If yes, which federal authorizations?-------------------------- CPQ Revised 8/15/2008 Page 9 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management 19. Have you applied for any other federal permits or authorizations?................................................................. 0 0 Agency Approval Type Date Submitted I I Note: The Coastal Project Questionnaire (CPQ) identifies state and federal permits subject to a consistency review. You may need additional permits from other agencies or the affected city and borough government to proceed with your activity. Attach the documentation requested under the Project Description. ACMP Consistency Evaluation & Certification Statement Pursuant to II AAC II 0.215 {a}{ I}(<;), the applicant shall submit an evaluation of how the proposed project is consistent with the statewide standards at 11 AAC I 12.200-11 AAC 112.990 and with the applicable district enforceable policies, sufficient to support the consistency certification. Evaluate your project against each section of the state standards and applicable district enforceable policies using the template below or by submitting a narrative description in letter or report form. District enforceable policies are available on the ACMP website at http://www.alaskacoast.state.ak.us. Definitions of key terms can be found at: II AAC 110.990,11 AAC 112.990 and II AAC 114.990. If you need more space for an adequate explanation of any of the applicable standards, please attach additional pages to the end of this document. Be sure to include references to the specific sections and subsections that you are evaluating. STATE~DESTANDARDS 11 AAC 112.200. Coastal Development Standard: (a) In planning for and approving development in or adjacent to coastal waters, districts and state agencies shall manage coastal land and water uses in such a manner that those uses that are economically or physically dependent on a coastal location are given higher priority when compared to uses that do not economically or physically require a coastal location. (b) Districts and state agencies shall give, in the following order, priority to (1) water-dependent uses and activities; (2) water-related uses and activities; and (3) uses and activities that are neither water-dependent nor water-related for which there is no practicable inland alternative to meet the public need for the use or activity. (c) The placement of structures and the discharge of dredged or fill material into coastal water must, at a minimum, comply with the standards contained in revised as of July 1, 2003. Evaluation: (a) How is your project economically or physically dependent on a coastal location? Why are you proposing to place the project at the selected location? N/A. THE INDIAN RIVER HYDRO PROJECT WOULD NOT BE LOCATED ADJACENT TO COASTAL (b) Evaluation of development priority. (1) How is the proposed project water-dependent? Explain. (2) How is the proposed project water-related? ~~!!· (3) lfthe proposed project is neither water-dependent nor water-related, please explain why there is not a practicable inland alternative that meets the public need for the use or activity. Explain. N/A. THE INDIAN RIVER HYDRO PROJECT WOULD NOT BE LOCATED ADJACENT TO COASTAL WATERS. (c) DCOM defers to the United States Corps of Engineers (USA CE) to interpret compliance with the referenced standards. If you plan to discharge or fill waters of the US, have you applied to the Corps of Engineers for the appropriate authorization? YES. PRE-CONSTRUCTION NOTIFICATION, EXPECT TO QUALIFY FOR NATIONWIDE PERMIT #17 CPQ Revised 8115/2008 Page 10 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management 11 AAC 112.210. Natural hazard areas. Standard: (a) In addition to those identified in II AAC 112.990, the department, or a district in a district plan, may designate other natural processes or adverse conditions that present a threat to life or property in the coastal area as natural hazards. Such designations must provide the scientific basis for designating the natural process or adverse condition as a natural hazard in the coastal area, along with supporting scientific evidence for the designation. (b) Areas likely to be affected by the occurrence of a natural hazard may be designated as natural hazard areas by a state agency or, under 11 AAC 114.250(b), by a district. (c) Development in a natural hazard area may not be found consistent unless the applicant has taken appropriate measures in the siting, design, construction, and operation of the proposed activity to protect public safety, services, and the environment from potential damage caused by known natural hazards. (d) For purposes of (c) of this section, "appropriate measures in the siting, design, construction, and operation of the proposed activity" means those measures that, in the judgment of the coordinating agency, in consultation with the department's division of geological and geophysical surveys, the Department of Community and Economic Development as state coordinating agency for the National Flood Insurance Program under 44 C.F.R. 60.25, and other local and state agencies with expertise, ( 1) satisfy relevant codes and safety standards; or (2) in the absence of such codes and standards; (A) the project plans are approved by an engineer who is registered in the state and has engineering experience concerning the specific natural hazard; or (B) the level of risk presented by the design of the project is low and appropriately addressed by the project plans. Evaluation: (a) Describe the natural hazards designated in the district plan as they affect this site. (b) Describe how the proposed project is designed to accommodate the designated hazards. How will you use site design and operate the proposed activity to protect public safety, services and the environment from potential damaged caused by known natural hazards? NO NATURAL HAZARDS ARE DESIGNATED IN THE AREA. THE PROJECT WILL BE DESIGNED BY LICENSED ENGINEERS WHO CONSIDER NATURAL HAZARDS AND THE SAFETY OF THE FACILITY. (d)( 1) Describe the measures you will take to meet relevant codes and safety standards in the siting, design, construction and operation of the proposed activity. ( d)(2)(A) If your project is located in an area without codes and safety standards, how is your project engineered for the specific natural hazard? Give the name of the appropriately qualified registered engineer who will approve the plans for protecting public safety, services, and the environment from damage caused by hazards OR (d)(2)(B) Ifthe level of risk presented by the design of the project is low, how do the project plans and project design address the potential natural hazard? THE PROJECT WILL BE DESIGNED BY LICENSED ENGINEERS IN ACCORDANCE WITH APPLICABLE CODES AND STANDARD INDUSTRY PRACTICE. 11 AAC 112.220. Coastal access. Standard: Districts and state agencies shall ensure that projects maintain and, where appropriate, increase public access to, from, and along coastal water. Evaluation: Please explain how the proposed project will maintain and, where appropriate, increase public access to, from and along coastal water. N/A. PROJECT WILL NOT AFFECT ASSESS TO COASTAL WATERS. 11 AAC 112.230. Energy facilities. Standard: (a) The siting and approval of major energy facilities by districts and state agencies must be based, to the extent practicable, on the following standards: ( 1) site facilities so as to minimize adverse environmental and social effects while satisfying industrial requirements; (2) site facilities so as to be compatible with existing and subsequent adjacent uses and projected community needs; Consistency Evaluation 8/15/2008 Page 11 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management (3) consolidate facilities; (4) consider the concurrent use of facilities for public or economic reasons; (5) cooperate with landowners, developers, and federal agencies in the development of facilities; ( 6) select sites with sufficient acreage to allow for reasonable expansion of facilities; (7) site facilities where existing infrastructure, including roads, docks, and airstrips, is capable of satisfying industrial requirements; (8) select harbors and shipping routes with least exposure to reefs, shoals, drift ice, and other obstructions; (9) encourage the use of vessel traffic control and collision avoidance systems; ( 1 0) select sites where development will require minimal site clearing, dredging, and construction; (11) site facilities so as to minimize the probability, along shipping routes, of spills or other forms of contamination that would affect fishing grounds, spawning grounds, and other biologically productive or vulnerable habitats, including marine mammal rookeries and hauling out grounds and waterfowl nesting areas; (12) site facilities so that design and construction of those facilities and support infrastructures in coastal areas will allow for the free passage and movement of fish and wildlife with due consideration for historic migratory patterns; (13) site facilities so that areas of particular scenic, recreational, environmental, or cultural value, identified in district plans, will be protected; (14) site facilities in areas of least biological productivity, diversity, and vulnerability and where effluents and spills can be controlled or contained; ( 15) site facilities where winds and air currents disperse airborne emissions that cannot be captured before escape into the atmosphere; (16) site facilities so that associated vessel operations or activities will not result in overcrowded harbors or interfere with fishing operations and equipment. (b) The uses authorized by the issuance of state and federal leases, easements, contracts, rights-of-way, or permits for mineral and petroleum resource extraction are uses of state concern. Evaluation: (a) If this standard applies to your project, please describe in detail how the proposed project is designed to meet each applicable section of this standard: (l)N/A. THE PROJECT IS NOT A MAJOR ENERGY FACILITY. (2)N/A. (3)N/A. (4)N/A. (S)N/A. (b) List the authorizations for state and federal leases, easements, contracts, rights-of-way, water rights, or permits for mineral and petroleum resource extraction you have applied for or received. N/A. THIS PROJECT DOES NOT INVOLVE MINERAL/ PETROLEUM RESOURCE EXTRACTION. 11 AAC 112.240. Utility routes and facilities. Standard: (a) Utility routes and facilities must be sited inland from beaches and shorelines unless (I) the route or facility is water-dependent or water related; or (2) no practicable inland alternative exists to meet the public need for the route or facility. Consistency Evaluation B/15/2008 Page 12 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management (b) Utility routes and facilities along the coast must avoid, minimize, or mitigate ( 1) alterations in surface and ground water drainage patterns; (2) disruption in known or reasonably foreseeable wildlife transit; (3) blockage of existing or traditional access. Evaluation: (a) If the proposed utility route or facility is sited adjacent to beaches or shorelines, explain how the route or facility is water dependent water related or why no practical inland alternative exits. N/A. UTILITY FACILITIES ARE NOT LOCATED ADJACENT TO COAST. (b) If the proposed utility route or facility is sited along the coast, explain how you will avoid, minimize or mitigate: ( l) alterations in surface and ground water drainage patterns; N/A. UTILITY FACILITIES ARE NOT LOCATED ADJACENT TO COAST. (2) disruption in known or reasonably foreseeable wildlife transit; N/A. UTILITY FACILITIES ARE NOT LOCATED ADJACENT TO COAST. (3) blockage of existing or traditional access. N/A. UTILITY FACILITIES ARE NOT LOCATED ADJACENT TO COAST. 11 AAC 112.250. Timber harvest and processing. Standard: ~~'-'--'-(Forest Resources and Practices Act) and the regulations adopted under that chapter with respect to the harvest and processing of timber are incorporated into the program and constitute the components of the program with respect to those purposes. Evaluation: Does your activity involve harvesting or processing of timber? Yes __ No_.,_ If yes, please explain how your proposed project meets the standards of the State Forest Resources and Practices Act. N/A. 11 AAC 112.260. Sand and gravel extraction. Standard: Sand and gravel may be extracted from coastal waters, intertidal areas, barrier islands, and spits if there is no practicable alternative to coastal extraction that will meet the public need for the sand or gravel. Evaluation: If your proposed project includes extracting sand or gravel from coastal waters, intertidal areas, barrier islands or spits, please explain why there is no practicable alternative to coastal extraction that meets the public need for sand or gravel. N/A. THE PROJECT DOES NOT INCLUDE EXTRACTION OF SAND OR GRAVEL FROM COASTAL 11 AAC 112.270. Subsistence. Standard: (a) A project within a subsistence use area designated by the department or under 11 AAC 114.250(g) must avoid or minimize impacts to subsistence uses of coastal resources. (b) For a project within a subsistence use area designated under II AAC II4.250(g), the applicant shall submit an analysis or evaluation of reasonably foreseeable adverse impacts of the project on subsistence use as part of (l) a consistency review packet submitted under II AAC 110.215; and (2) a consistency evaluation under 15 C.F.R. 930.39, 15 C.F.R. 930.58, or 15 C.F.R. 930.76. (c) Repealed 10/29//2004, Register 172. Consistency Evaluation 8/15/2008 Page 13 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management (d) Except in nonsubsistence areas identified under AS 16.05.258, the department may, after consultation with the appropriate district, federally recognized Indian tribes, Native corporations, and other appropriate persons or groups, designate areas in which a subsistence use is an important use of coastal resources as demonstrated by local usage. (e) For purposes of this section, "federally recognized Indian tribe," "local usage", and "Native corporation" have the meanings given in 11 AAC 114.990. Evaluation: (a) Is your proposed project located within a subsistence use area designated by a coastal district? Yes No " If yes, please describe how the proposed project is designed to "avoid or minimize impacts to subsistence uses of coastal resources:" N/A. (b) If your project is located in a subsistence use area designated by the coastal district, provide an analysis or evaluation of its reasonably foreseeable adverse impacts to the subsistence uses. N/A. (c) No response required. (d) If your project is not located in a designated subsistence use area, please describe any subsistence uses of coastal resources within the project area. Please be advised that subsistence use areas may be designated by the department during a review. SUBSISTENCE USES ARE ASSOCIATED WITH THE COASTLINE. THIS PROJECT IS NOT LOCATED ALONG OR ADJACENT TO THE COAST. NO SUBSISTENCE USES ARE KNOWN. (e) No response required. 11 AAC 112.280. Transportation routes and facilities. Standard: Transportation routes and facilities must avoid, minimize, or mitigate (1) alterations in surface and ground water drainage patterns; (2) disruption in known or reasonably foreseeable wildlife transit; and (3) blockage of existing or traditional access. Evaluation: If your proposed project includes transportation routes or facilities, describe how it avoids, minimizes, or mitigates ( 1) alterations in surface and ground water drainage patterns; AS TECHNICALY AND ECONOMICALLY PRACTICAL, ROUTING OF ROADS AND TRAILS TO AVOID OR MINIMIZE IMPACTS, USE OF CULVERTS TO MAINTAIN EXISTING DRAINAGE PATTERNS. (2) disruption in known or reasonably foreseeable wildlife transit; and THERE WOULD BE NO DISRUPTION OF WILDLIFE TRANSIT. (3) blockage of existing or traditional access. EXISTING USAGE OF AREA IS ON FOOT. PEDESTRIAN TRAFFIC WILL NOT BE BLOCKED BY THE PROJECT. 11 AAC 112.300. Habitats. Standard: (a) Habitats in the coastal area that are subject to the program are ( 1) offshore areas; (2) estuaries; (3) wetlands; Consistency Evaluation 8/15/2008 Page 14 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management ( 4) tideflats; (5) rocky islands and sea cliffs; (6) barrier islands and lagoons; (7) exposed high-energy coasts; (8) rivers, streams, and lakes and the active floodplains and riparian management areas of those rivers, streams, and lakes; and (9) important habitat. (b) The following standards apply to the management ofthe habitats identified in (a) of this section: (1) offshore areas must be managed to avoid, minimize, or mitigate significant adverse impacts to competing uses such as commercial, recreational, or subsistence fishing, to the extent that those uses are determined to be in competition with the proposed use; (2) estuaries must be managed to avoid, minimize, or mitigate significant adverse impacts to (A) adequate water flow and natural water circulation patterns; and (B) competing uses such as commercial, recreational, or subsistence fishing, to the extent that those uses are determined to be in competition with the proposed use; (3) wetlands must be managed to avoid, minimize, or mitigate significant adverse impacts to water flow and natural drainage patterns; (4) tideflats must be managed to avoid, minimize, or mitigate significant adverse impacts to (A) water flow and natural drainage patterns; and (B) competing uses such as commercial, recreational, or subsistence uses, to the extent that those uses are determined to be in competition with the proposed use; (5) rocky islands and sea cliffs must be managed to (A) avoid, minimize, or mitigate significant adverse impacts to habitat used by coastal species; and (B) avoid the introduction of competing or destructive species and predators; (6) barrier islands and lagoons must be managed to avoid, minimize, or mitigate significant adverse impacts (A) to flows of sediments and water; (B) from the alteration or redirection of wave energy or marine currents that would lead to the filling in of lagoons or the erosion of barrier islands; and (C) from activities that would decrease the use of barrier islands by coastal species, including polar bears and nesting birds; (7) exposed high-energy coasts must be managed to avoid, minimize, or mitigate significant adverse impacts (A) to the mix and transport of sediments; and (B) from redirection of transport processes and wave energy; (8) rivers, streams, and lakes must be managed to avoid, minimize, or mitigate significant adverse impacts to (A) natural water flow; (B) active floodplains; and (C) natural vegetation within riparian management areas; and (9) important habitat (A) designated under II AAC ll4.250(h) must be managed for the special productivity of the habitat in accordance with district enforceable policies adopted under 11 AAC ll4.270(g); or (B) identified under (c)(l)(B) or (C) of this section must be managed to avoid, minimize, or mitigate significant adverse impacts to the special productivity of the habitat. (c) For purposes of this section, (1) "important habitat" means habitats listed in (a)(l)-(8) of this section and other habitats in the coastal area that are (A) designated under 11 AAC ll4.250(h); (B) identified by the department as a habitat (i) the use of which has a direct and significant impact on coastal water; and (ii) that is shown by written scientific evidence to be biologically and significantly productive; or (C) identified as state game refuges, state game sanctuaries, state range areas, or fish and game critical habitat areas under AS 16.20; (2) "riparian management area" means the area along or around a waterbody within the following distances, measured from the outermost extent of the ordinary high water mark of the waterbody: (A) for the braided portions of a river or stream, 500 feet on either side of the waterbody; (B) for split channel portions of a river or stream, 200 feet on either side of the waterbody; Consistency Evaluation 8/15/2008 Page 15 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management (C) for single channel portions of a river or stream, 100 feet on either side of the waterbody; (D) for a lake, 100 feet of the waterbody. Evaluation: (a) List the habitats from (a) above that are within your proposed project area or that could be affected by your proposed project. #3 -WETLANDS AND #8 RIVERS. (b) Describe how the proposed project avoids, minimizes, or mitigates impacts to each of the identified habitat( s) in section (a) above. DESIGN WILL AVOID AND MINIMIZE IMPACTS. IMPACTS WILL BE MITIGATED WITH REVEGETATION AFTER CONSTRUCTION. (c) No response required. 11 AAC 112.310. Air, land and water quality Standard: Not withstanding any other provision of this chapter, the statutes and regulations of the Department of Environmental Conservation with respect to the protection of air, land, and water quality identified in AS 46.40.040(b) are incorporated into the program and, as administered by that department, constitute the exclusive components of the program with respect to those purposes. Evaluation: No response required. 11 AAC 112.320. Historic, prehistoric, and archeological resources. Standard: (a) The department will designate areas of the coastal zone that are important to the study, understanding, or illustration of national, state, or local history or prehistory, including natural processes. (b) A project within an area designated under (a) of this section shall comply with the applicable requirements of AS 41.35.010-41.35.240 and 11 AAC 16.010-11 AAC 16.900. Evaluation: (a) Have you contacted the State Historic Preservation Office (SHPO) to see if your project is in a designated area of the coastal zone that is important to the study, understanding, or illustration of national, state, or local history or prehistory, including natural processes? THE CORPS COMPLETED AN ON-SITE ARCHEOLOGICAL SURVEY OF THE PROJECT AREA IN '83-84. NO RESOURCES WERE IDENTIFIED IN THE CURRENT PROJECT FOOTPRINT. (b) If your project is within an area designated under (a) of this section, how will you comply with the applicable requirements in the statutes and regulations listed in (b)? N/A. Consistency Evaluation 8/15/2008 Page 16of18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management Affected Coastal District Enforceable Policies Evaluate each applicable district enforceable policy using a format similar to the one you completed above for the State Standards. District enforceable policies are available at http://alaskacoast.state.ak.us/. If you need more space for an adequate explanation of any of the applicable district enforceable policies, please attach additional pages to the end of this document. Applicable District Plan(s) __::.:...:__ __________________ _ Enforceable Policy: PROJECT IS NOT IN ~.:_:D::._:l_:c_S_:_T::._:R::._:IC:...:T......:P......:L=-A..c...N..c...:;_:A.:...:R..;;;;.E_;A..c.... -----------~-~ Evaluation: Enforceable Policy: ____ ----------------------______ _ Evaluation: Enforceable Policy: ---------------------------------- Evaluation: Certification Statement The infom1ation contained herein is true and complete to the best of my knowledge. I certify that the proposed activity complies with, and will be conducted in a manner consistent with, the Alaska Coastal Management Program. _.p;/_'-:::J6D-4/11.)~ Signature of Applicant or Agent Date Note.· Federal agencies conducting an activity that will affect the coastal zone are required to submit a federal consistency determination, per IS CFR 930, Subpart C, rather than this certification statement. ACMP has developed a guide to assist federal agencies with this requirement. Contact ACMP to obtain a copy. This cenification statement will not be complete until all required State and federal authorization requests have been submitted to the appropriate agencies. Cons,slenc.y F VC!Iual,on g: 15/2008 Page 17 of 18 State of Alaska, Department of Natural Resources, Division of Coastal & Ocean Management Project Description: Please provide or attach a brief description of your project including the planned work, any effects to coastal uses and resources and how your project is being designed to avoid, minimize and mitigate those effects. THE PROJECT IS A RUN-OF-RIVER HYDROELECTRIC PROJECT ON INDIAN RIVER TO SUPPLY ELECTRICITY TO THE CITY OF TENAKEE SPRINGS. IT WILL INCLUDE AN IN-STREAM DIVERSION STRUCTURE AT APPROX RIVER MILE 0.85, A PENSTOCK, AND A POWERHOUSE AND TAILRACE AT RM 0.55. THE PROJECT WILL ALSO INCLUDE APPROX. 3,200 FEET OF ACCESS ROADS AND TRAILS, APPROX.4,500 FEET OF POWER LINE FROM THE POWER HOUSE TO TENAKEE SPRINGS, AND OTHER APPURTENANT FEATURES. THE USFS HAS EXISTING IMPROVEMENTS ON INDIAN RIVER TO PROMOTE FISH MIGRATION TO UPSTREAM HABITAT. THE CITY WILL WORK WITH USFS AND ADF&G TO DESIGN THE PROJECT IN A MANNER THAT MAINTAINS AND/OR ENHANCES THE FUNCTIONALITY OF THESE IMPROVEMENTS. Project Area: Please provide or attach a map of your project location and your proposed work. (Including nearest community, the name of the nearest land feature or body of water, and other legal description such as a survey or lot number.) Nearest Community: TENAKEE SPRINGS Nearest Waterbody: INDIAN RIVER Legal Survey Description: N/A. ----------------------------------------------------- Consistency Evaluation 8/15/2008 Page 18 of 18 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report fl. Polarconsult Alaska, Inc. ADNR WATER RIGHTS PERMITTING November 2011 -Final Report APPENDIX D Joel Groves From: Date: To: Subject: Hi Joel, "Bussard, Daniel P (DNR)" <daniel.bussard@alaska.gov> Monday, October 04, 2010 11:11 AM "Joel Groves" <joel@polarconsult.net> RE: Receipt for Water Rights App-Indian River I Tenakee Springs Page 1 of 1 Your file has been created LAS 27836 and the receipt number is 3163114 as soon as I get Financial Services to fix something on the receipt I will email you a copy Dan Bussard 907-465-6363 From: Joel Groves [mailto:joel@polarconsult.net] Sent: Thursday, September 30, 2010 12:14 PM To: Bussard, Daniel P (DNR) Subject: Receipt for Water Rights App -Indian River I Tenakee Springs Hi Dan, My accounting office tells me that we haven't received a receipt for the Indian River I Tenakee Springs water rights application submitted in late August. Could you please have someone email or fax me the receipt? Thanks, Joel Joel D. Groves, PE Polarconsult Alaska, Inc. 1503 West 33rd Avenue, 3rd Floor Anchorage, Alaska 99503 Tel: 907.258.2420 x204 Fax: 907.258.2419 Cell: 907.360.9042 joel@polarconsult.net 9/16/2011 polarconsult alaska, inc. ENGINEERS • PLANNERS • ENERGY CONSULTANTS DAN BUSSARD DIVISION OF MINING, LAND AND WATER-WATER SECTION Alaska Department ofNatural Resources PO Box 111020 Juneau, AK 99811 August 31,2010 Subject: Water Rights Application/or Indian River Hydroelectric Project Dear Mr. Anderson: On behalf of our client, the City of Tenakee Springs, enclosed please find an application for water rights for the Indian River Hydroelectric Project. If you have any questions regarding this application or the project in general, please give me a call at 907-258-2420. Sincert>h' Joel D. Groves, PE Polarconsult Project Manager £.£.:. Art Bloom-City of Tenakee Springs Project Manager Enclosures: ADNR Water Rights Application ../ Application Fee ($900.) ../ ADNR lease and easement applications .-- Project Description (Development Plan) v M~ ~ ADFG Fish Habitat Application ./ Coastal ProJect Questionnaire ..- QtherPcrmit_AQQlications (For Re[erence) COE Wetlands Application FERC Finding ofNon-Jurisdtctton ./ 1503 WEST 33RD AVENUE • SUITE 310 ·ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 ·FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net DIVISION OF MINING, LAND AND WATER WATER RESOURCES SECTION www.dnr.statc.ak.us/mlw/watcr/indcx.htm II )NATURAL t.~ N""• !kp;uomeoo ~ \ . ~RESOURCES '-,. ··""'"' [-Anch-orage Office --·--· ' 550 West ih Avenue, Suite 1020 ; Anchorage, AK 99501-3562 Juneau Office PO Box 111020 Fairbanks Office 3700 Airport Way Fairbanks, AK 99709 : For ADNR-use ·o/Jir --- Datenime Stamp . (907) 269-8600 I Fax: (907) 269-8947 ~ . ---- : For ADNR Use Only 'LAS# I INSTRUCTIONS 400 Willoughby Avenue Juneau, AK 99811-1020 (907) 465-3400 Fax: (gQl)_§_tl_§.-~~-54 For ADNR Use Only CID# CID# - -. -------'-- 'r (907) 451-2790 Fax: (907) 451-2703 1~------~----. For ADNR Use Only Receipt Type WR APPLICATION FOR WATER RIGHT -----___ j [ 1. Complete one application for each water source (incomplete applications will not be accepted). 2. Attach copy of executed deed, lease agreement, or other possessory interest document for property where water will be used (applicant must own, lease, or obtain written authorization to use water on property). 3. Attach copy of legal access document (e.g. right-of-way, easement, permit) or application for legal access to water withdrawal point and transport route, if applicable, or copy of request or application for legal access to water withdrawal point. 4. Attach driller's well log for drilled wells (if already drilled and available). 5. Attach sketch, photos, plans of water system, or project description (if applicable). 6. Attach legible map that includes meridian, township, range, and section lines such as a subdivision plat, USGS topographical quadrangle, or borough tax map. Indicate location of water withdrawal, route of water transmission, water use area boundary, points of water use within boundary, and point of water return flow (if applicable). 7. Attach copy of approved ADEC water and wastewater system certificate (if applicable). 8. Attach copy of ADNR fish habitat permit (if applicable). 9. Attach notarized Statement of Beneficial Use of Water form and associated fee, if water system and water use are fully developed, and total water use does not exceed 500 gallons of water per day. 10. Attach completed Coastal Project Questionnaire (if applicable -see page 4 ). 11. Submit non-refundable fee (see page 4). I APPLICANT INFORMATION City of Tenakee Springs Organization Name (if applicable) Attn: Art Bloom Individual Applicant Name (if applicable) PO Box 52 Mailing Address 907-736-2207 '1aytime Phone Number 007-736-2207 ------------------------- Fax Number (1f available) 102-102(Rev 2/06) Page 1 of 4 Polarconsult Alaska, Inc. Agent or Consultant Name (if applicable) Attn: Joel Groves (Consultant) Individual Co-applicant Name (if applicable) Tenakee Springs AK State City 907-258-2420 (Polarconsult) Alternate Phone Number (optional) citytke@gmail.com E-Mail Address (optional) 99841 Zip Code I PROPERTY DESCRIPTIONS , Location of Water Use l s_LI_!J(jivlsionName~r_§l.!r:'-'~YN_ulll~~r -- ! N/A i ~------------ ----- 'i Location of Water S()lJrc~ ______ _ N/A Merigi~n Lie>\\ln§bip-f Ra:Qgg_j_§_ection , ol1arter §ectlons Copper 04 78 063E j ?~ j NE 1,4 I NW 1,4 . ~;;ivision Name or Sur;ey Number I ~~:lock or Tract I :~~i:;; no:;~ I f3_Eiri9E! 063E Section Quarter Sections 1 15 SE% sw% Location of Water Return Flow or Discharge {if applicable)_ GeograJJhic Name of Water Body or Well Depth Meridian Indian River --Section\ Quarter Sections 22 I NE% NW% I WATER SOURCE I · Ground Water • Type (e.g: drilled, feet) f -Date Completed -Weii£E2cluctior1 (;apacit~ j N/A N/A -----------------------'-------------------------------- Surface Water Type (e.g. stream, lake, spring) River I METHOD OF TAKING WATER {IF KNOWN) Pump Pump Intake _-___ Inches Pump Output -GPM • Gravity Pipe Diameter~--Inches Head +/-60 Feet Ditch L - H -W-Feet Reservoir L - H -W-Feet Dam L +/-60 H +/-6 W +/-1 Feet 102-102 (Rev 2r06i Page 2 of 4 ! N/A N/A Geographic Name Indian River Hours Working _-____ Hours/Day Length of Pipe -Feet (from pump to point of use) Length of Pipe +/-~~00 Feet {take point to point of use) Diversion Rate =._ ____ IQGPM or QJCFS Water Storage _-____ AF Water Storage _0 ____ AF I AMOUNT OF WATER Motel or Resort ···--···-·· ---~~-- Work Camps Domestic Irrigation ion-domestic Irrigation Other Water Uses [ . How ---T ·r·-Amount--. Many 1-+-__ . _ _ _ _ .. Type of Use l X! -~ I lx: Hydroelectric Power Generation Total Amount Requested 80 CFS or 51.7 MGD Expected date for water system and water use to be fully developed or date when existing use started 9/1/2012 Note: Pursuant to AS 46.15.180(a)(1 ). Crimes, a person may not construct works for an appropriation, or divert, impound, withdraw. or use a significant amount of water from any source without a permit, certificate of appropriation. or authorization issued under this chapter. 11 AAC 93.040 sets out the required information on an application for a water right. 11 AAC 93.050 authorizes the commissioner to decide what additional information is needed to process an application for a water right. This information is made a part of the state public water records and becomes public information under AS 40.25.110 and 40.25.120. Public Information is open to inspection by you or any member of the public. A person who is the subject of the information may 1llenge its accuracy or completeness under AS 44.99.31 0. by giving a written description of the challenged 1nformation. the ,nges needed to correct it. and a name and address where the person can be reached False statements made 1n an application for a benefit are punishable under AS 11.56.210. 102-102 (Rev 2/06) Page 3 of 4 SIGNATURE : The information presented in this application is true and correct to the best of my knowledge. I understand that per 11 AAC 93.040 and 11 AAC 93.050 additional information may be required by the department to adjudicate this application. Failure to provide requested information could result in this file being closed. _ ___,(~~ ~_"'1.1l&_tA0 ______ _ Signature Joel D. Groves REFERENCES Measurement Units GPO = gallons per day : CFS = cubic feet per second ! GPM = gallons per minute I AF = acre-feet r A.F. Y =.a .. cre ... -.fe .. e. t per ye.·a··· r (325,851 gallons/year) AFD acre-feet per day (325,851 gallons/day) MGD = million gallons per day . conversion-Table- J 5.000 GPO= 30,000 GPD= ! 0.01 CFS 0.05 CFS · 3.47 GPM 20.83 GPM i 5.60 AFY 33 60 AFY ! 0.2 AFD 0.09 AFD i 0.01 MGD 0.03 MGD I I 100 000 GPD= 0.2 CFS 69.4 GPM 112.0AFY 0.3AFD 0.1 MGD 500,000 GPO= 0.8 CFS 347.2 GPM 560 1 AFY 1.5 AFD 0.5 MGD Fees required by regulation 11 AAC 05.010(a)(8) 1,000.000 GPD= 1.5 CFS 694.4 GPM 1120.1 AFY 3.1 AFD 10 MGD Date Polarconsult Project Manager Titl~(if.appl!cabl~). _ • $100 for one single-family residence or duplex. or for water use associated with one single-family residence or duplex • $1,200 for activities related to oil and gas and associated substances • Fee varies for activities related to locatable minerals, unless the application is filed under 11 AAC 05.010(a)(9)(E)(i) or (9)(F)(i) -contact Water Resources Section for pre-application meeting • Fee varies for hydroelectric power generation -contact Water Resources Section for pre-application meeting • Fee varies for water removal out of a hydrologic unit under AS 46.15.035 or 46.15.037 contact Water Resources Section for pre-application meeting • $200 for 5.000 GPO or less for a use not listed above • $450 for greater than 5,000 GPO and no more than 30,000 GPO for a use not listed above • $550 for greater than 30,000 GPO and no more than 100,000 GPO for a use not listed above • $900 for greater than 100,000 GPO for a use not listed above Make checks payable to "Department of Natural Resources." Coastal Zone If this appropriation is within the Coastal Zone, and you are planning to use more than 1,000 GPO from a surface water source or 5,000 GPO from a subsurface water source. you need to submit a completed Coastal Project Questionnaire with this application. For more information on the Coastal Zone. contact the Office of ProJeCt Management and Perm1tt1ng; Anchorage 269-7470, Juneau 465-3562, www.dnr state.ak usiacmp/. 102·102 (Rev 2106) Page 4 of 4 City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report ADFG FISH HABITAT PERMITTING November 2011 -Final Report fl, Polarconsult Alaska, Inc. APPENDIX D Joel Groves From: Date: To: Cc: Subject: Hi Jackie, "Joel Groves" <joel@polarconsult.net> Wednesday, September 14, 2011 4:26PM "Timothy, Jackie L (DFG)" <jackie.timothy@alaska.gov> "Albrecht, Gregory T (DFG)" <greg.albrecht@alaska.gov>; "Johnson, Shawn L (DFG)" <shawn.johnson@alaska.gov> Re: Indian River Hydro-Tenakee Springs Page 1 of2 I've been working with Linda Speerstra at COE. Wetlands delineations are completed, and she sent me a few more questions about the project two weeks ago that I will have addressed shortly. Then she should be able to proceed with her process to issue a NWP. FYI, USFS also has these drawings, but I haven't yet received any feedback from them on the proposed modifications to the fish pass. I've configured the hydro diversion to improve performance of the fish pass and reduce O&M requirements on the pass structure (debris clearing, etc). Thanks, Joel From: Timothy, Jackie L (DFG) Sent: Wednesday, September 14, 2011 3:55PM To: joel@polarconsult.net Cc: Albrecht, Gregory T (DFG) ; Johnson, Shawn L (DFG) Subject: FW: Indian River Hydro -Tenakee Springs Hi there, Joel- Greg Albrecht will be taking over for Katie Eaton. I'll bring him up to speed, have him start coordinating in-house, and get in touch with you. Where are you with USACE permitting? Now the ACMP is gone we can issue when we are satisfied fish habitat impacts have been avoided, minimized or mitigated and fish passage can be assured. Thanks ... Jackie From: Joel Groves [mailto:joel@polarconsult.net] Sent: Wednesday, September 14, 2011 3:42PM To: Timothy, Jackie L (DFG) Subject: Indian River Hydro -Tenakee Springs Hi Jackie, I don't see that I ever sent you the concept design drawings for the Indian River hydro after we spoke last month -they are attached. My apologies for the delay! Please let me know who will be taking Katie Eaton's place in issuing the habitat permit, and as always give me a call if you have any questions. 9/16/2011 Thanks, Joel Joel D. Groves, PE Polarconsult Alaska, Inc. 1503 West 33rd Avenue, 3rd Floor Anchorage, Alaska 99503 Tel: 907.258.2420 x204 Fax: 907.258.2419 Cell: 907.360.9042 joel@polarconsult.net Page 2 of2 9/16/2011 • -. . polarconsult alaska, inc. ENGINEERS • PLANNERS • ENERGY CONSULTANTS JACKIE TIMOTHY REGIONAL SUPERVISOR Alaska Department of Fish and Game PO Box 240020 Douglas, AK 99824-0020 August 31, 2010 Subject: Fish Habitat Permit Application for Indian River Hydroelectric Project Dear Ms. Timothy: On behalf of our client, the City of Tenakee Springs, enclosed please find an application for a fish habitat permit for the Indian River Hydroelectric Project. If you have any questions regarding this application or the project in general, please give me a call at 907-258-2420. Sincerely, Is? ~~Rb..s:> Joel L. '-'lvvc:s, PE Polarconsult Project Manager ££.:. Art Bloom City ofTenakee Springs Project Manager Enclosures: ADFG Fish Habitat Permit ApplicatioQ ,/ -Site Rehabilitation/Restoration Plan/ Other Permit Applications (For Reference) COE wetlands application .-/ FERC Finding ofNon-Jurisdiction / Coastal project questionnaire / ADNR land lease and easement applications/ ADNR water rights application / 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net FH# ____________ __ GENERAL WATERWAY/WATERBODY APPLICATION ALASKA DEPARTMENT OF FISH AND GAME Division of Habitat Office Locations (Office Use O n ly ) A. APPLICANT 1. 2. Name: Cl~ o,f' '(E~.JAU:£ <;~~~~ '\)3A ~A.~~ SPRt...-::;'~ ~fl..\L \$\L(1"1 ~pr. Address (Mailing): P.o. &:>~ '5'2 (1"€..:>AU!B ~~~~s, AK 'l"S~\ Email Address: Crt'i 1¥£<:!.. CfAAtL. CXIr-J... Telephone: Clot-~~-1....'2C"':f Fax: _qo_O=F_-~__:__.;.~--"L_7.0-=-r1--'--------- 3. Project Coordinator/Contractor: Name: ::ToEc.... b . 4"(.l0~~ -PoLArr-co~su~...-\ ALAs!¢.., \~. Address: ('5c>~ w. ~~ Rc AvE,...,ve ¢t';to /A~<J~~J A'(... 9ct5o~ • Email Address: :TOE.L Q Pot.AJiteo,..)~T. i'JE.""I" Telephone: qo~-'2-58-"2.'-t'LO Fax: qo"?-'2..:::;8-'l..L(\.~ B. TYPE AND PURPOSE OF PROJECT: ~u~-O-F· 'Q\.\.l!Y'L \4"'(C:Jla~"t11t<L -PftCI,r~LT" w/ i:Jt\.C:f.:2-<":lci,..J P.8t:At£ f"tlLL.!. ~Y. AI f411!L M.\l£~~'0.8'S t PoW&l..t-\ou~ f··nllLRA.~ 1!f I\Vt91-Mt~"-o.r:;s, B£_..u.Jt...J ~us ~'2, pe.:::.tc;,.._~ -FL!IW uo 'ft.J Bo cf"S. i CAPA<:..rN. ~ 1""0 ?_So ~w. COr-lC(::fl'{'UAL €N£1(..J(:£1{\J1 (~ \,_J f>.i.c>lfi(€S ~ {: \t:"LL L ..J:)~M~ ..... c:-~-s.r<..J .f"LDc......, c...o<:..ATlo~ ~ PPccrdr ~t:A\U~J A,...t) C. LOCATION OF PROJECT SITE 1. Name of River, Stream, or Lake: or Anadromous Stream No: _....::.l ~l"t_-_L.f!_""L_--=l-=~==------'--------- 2. Legal Description : Township 4~~ Rang e G;~£ Meridian CR Section 1?/21.. USGS Quad Map <;In:~ D..L{ 3. Plans, Specifications, and Aerial Photograph. See specifi c instructions July 200 8 -3- D. TIME FRAME FOR PROJECT: r:'s"T". 4/l{lolt To q(t/?.o\2... ---'-------(mm/dd/yy) E. CONSTRUCTION METHODS: 1. 2. 3. Will the stream be diverted? t8J Yes 0No How will the stream be diverted? ~ ... ~ ~S, ~s, ~~f>S a'l-~ ~t:A~".> -A~ R.ec;;e::. • "lZZ Scu . .IJ Pt\.t:it'S.to""' ~uc.'f'l..tle, Howlong? ~~--l-_L __ M __ o_~ ___ s_. ______________________________________ _ Will stream channelization occur? Yes f8l No Will the banks of the stream be altered or modified? ~ Yes 0No 4. List all tracked or wheeled equipment (type and size) that will be used in the stream (in the water, on ice, or in the floodplain): To Bt ~M.~~ • How long will equipment be in the stream? 7..-"-MO~S.-{Nf'ltt ~tq<::,.::r. 5. a. Will material be removed from the floodplain, bed, stream, or lake? ~Yes 0 No Type: "t;A.~ / c:;PA.I)!3..../ B0/.:1.-fjl!{) ~ / ScfYJ.od<-( ~ Amount: A.:; R~QD . FbfL DVI.:t-'SI~ -=;"T'J2~ f"'()..J~"..> • +1-"20 C::'t~S • b. Will material be removed from below the water table? [:2(1' Yes If so, to what depth? U~~OW,..J 0No Is a pumping operation planned? ~ Yes 0 No If'" ~~~.(sa£ E.i) 6. Will material (including spoils, debris, or overburden) be deposited in the floodplain, stream, or lake? 181 Yes 0 No If so, what type? IJA.~ j.}.J>Tf:i/.1~'-S. ~M.. 8LJIL.t:>r~-< &,..LHe'$. f PH-P~. Disposal site location(s): ~J:. S. ALl!~ Pflo:S'"~ ft~ 1 Pf4. <;I\£ PAt> • 7. Will blasting be performed? ~ Yes No Weight of charges: _;__ __ ~-~<~ __ w_....J ____________________________________ _ Type of substrate: 8. Will temporary fills in the stream or fake be required during construction (e.g., for construction traffic around construction site)? 0 Yes g) No 9. Will ice bridges be required? Yes 'g No Ju'y 2008 -4- F. SITE REHABILITATION/RESTORATION PLAN: On a separate sheet present a site rehabilitation/restoration plan. See specific instructions G. WATERBODY CHARACTERISTICS: I Width of stream: +1-...?..o -6c' Depth of stream or lake: _+_l.._l_-,_S ___ _ Type of stream or lake bottom (e.g., sand, gravel, mud): ~v1::1..S, Bov<-t:dZS, C"t~~'S.. 13d::.Roa.., Stream gradient: 'JA(l.te.S F"t1G,v.... I% 'Tb 35cfo. (,.J ~(Sf'«r R<SO.c\.\ • A~~ Y -5%. H. HYDRAULIC EVALUATION: 1. Will a structure (e.g.1 culvert, bridge support, dike) be placed below ordinary high water of the stream? ZJ Yes 0 No 2. If yes, attach engineering drawings or a field sketch, as described in Step B. "5~ A~Ac.+t~ • For culverts1 attach stream discharge data for a mean annual flood (Q=2.3), if available. If applicable, describe potential for channel changes and/or increased bank erosion: M \ r-J.t tl\ r:.. L • f<l ~ ' ':,. \,.;C) sec v:n-o f>t3:lQ.ock.. CA ,.rtt.t,J l1'f YlOIK ~U~X A'l.l(th::T'. Will more than 25,000 cubic yards of material be removed? 0 Yes ~No If yes, attach a written hydraulic evaluation including, at a minimum, the following: potential for channel changes, assessment of increased aufeis (glaciering) potential, assessment of potential for increased bank erosion. I HEREBY CERTIFY THAT ALL INFORMATION PROVIDED ON OR IN CONNECTION WITH THIS APPLICATION IS TRUE AND COMPLETE TO THE BEST OF MY KNOWLEDGE AND BELIEF. /s/ <:T3Z!L412:l~ ----'- I 7£J!{) . ,, __ _ Signature of Applicant Date Juiy 2008 CITY OF TENAKEE SPRINGS ELECTRIC UTILITY DEPARTMENT INDIAN RIVER HYDROELECTRIC PROJECT FISH HABITAT PERMIT-A IT ACHMENTS 1. SKETCH OF DIVERSION STRUCTURE SEE ATTACHED FIGURE 3 2. SKETCH OF POWERHOUSE SITE SEE ATTACHED FIGURE 4 PREPARED BY POLARCONSUL T ALASKA, INC AUGUST2010 PAGEl OF4 CITY OF TENAKEE SPRINGS ELECTRIC UTILITY DEPARTMENT INDIAN RIVER HYDROELECTRIC PROJECT FISH HABITAT PERMIT-ATTACHMENTS 3. AERIAL PHOTOS PREPARED BY POLARCONSUL T ALASKA, INC AUGUST2010 PAGE 20F4 CITY OF TENAKEE SPRINGS ELECTRIC UTILITY DEPARTMENT INDIAN RIVER HYDROELECTRIC PROJECT FISH HABITAT PERMIT-ATTACHMENTS 4. RESTORATION/ REVEGETATION PLAN PREPARED BY POLARCONSUL T ALASKA, INC AUGUST2010 Below the project, the first half-mile of Indian River is a low gradient stream running at approximately 0.6%. This reach supports pink and chum salmon. From River mile 0.5 to 1.0, Indian River has an average gradient of about 2.7%, but drops through a series of five significant waterfalls or fish barriers. This is where the hydro project will be located. The value of this reach of the river as fish habitat is understood to be primarily as a migration corridor to upstream rearing and spawning habitat. Several past USFS projects have improved fish passage around the barrier waterfalls. The project will be designed to strike a balance between the need to control construction and operating costs and minimize impacts on fish habitat. Topography in the project area requires that the penstock and powerhouse will be located within the Indian River Canyon. This will require some trail work within the canyon, including blasting, which will generate some potential for erosion and sediment transport. Stormwater prevention measures will be used to control sediment transport. Generally, it is less costly and superior ecologically to avoid habitat impacts rather than restore or mitigate them. By close consultation with ADFG and USFS, the City of Tenakee Springs intends to create a realistic project design and construction approach for the hydro project. Primary project objectives with regard to fish habitat protection are expected to include: .. Avoid formation of new migration barriers along project reach. .. A void excessive sedimentation of downstream habitat areas. .. A void excessive degradation of stream bank vegetation. Each of these is briefly discussed below. Avoid Formation Of New Migration Barriers Migration barriers may be formed by: .. Reduction of flows in the bypass reach. It is unknown if reducing flows in the bypass reach will improve or impede fish passage. Reduced flows may eliminate existing velocity barriers. The USFS has established a minimum flow requirement for their fish ladder around barrier 4 of 10 cfs, which will also be available through the entire hydro bypass reach. Natural flows at the fish ladder exceed 10 cfs 99% of the time. The city proposes to design and operate the hydro project in a manner that maintains minimum flows through the fish ladder and bypass reach during critical migration seasons. Natural low flow periods occur during December through February and in late July through mid-September. .. Creation of new barriers by deposit of waste rock or fill into Indian River. Project construction will result in some placement of fill into Indian River. The volume, type, and location of fill will be determined through the design and permitting process. Avoid Excessive Sedimentation Of Downstream Habitat Areas Excessive sedimentation of downstream habitat areas will be avoided by: PAGE3 OF4 CITY OF TENAKEE SPRINGS ELECTRIC UTILITY DEPARTMENT INDIAN RIVER HYDROELECTRIC PROJECT FISH HABITAT PERMIT ATTACHMENTS PREPARED BY POLARCONSUL T ALASKA, INC AUGUST2010 'lll Project design to minimize generation of top soil, exposed cuts, and related civil works with erosion potentiaL 'lll Avoiding disposal oftop soil and fines into Indian River. 'lll Use of silt fences and similar storm water control measures to trap sediment. 'lll Revegetating cleared areas to reduce long-term erosion potentiaL A void Excessive Degradation Of Stream Bank Vegetation Excessive degradation of stream bank vegetation will be avoided by: 'lll A voiding construction activities on the stream bank. 'lll Restoring vegetation along disturbed areas of the stream bank. The stream bank in the project area is typically vegetated by a variety of willows, devil's club, and similar fast-growing plants. The potential for successful revegetation of disturbed areas of the stream bank is considered to be very good. PAGE40F4 FAIRBANKS STATE LOCATION MAP y ~/ {/~~ ~{</ ~/ u~ I PROPOSED INTAKE SITE EXISTING I USFS FISH LADDER I (ADL 106204) LOGGING ROAD (USFS #7500) 516 1 515 PROPOSED ~c --";:"-~/~ ~."~"'-~', ~ ~.'~,,~ ~2'~22 ,'~ ~~'~Q~- PROPOSED ACCESS ROADS ---~'-"----'~ PROPOSED POWER LINE ROUTE PROPOSED CONNECTION TO TENAKEE ELECTRIC SYSTEM 0 1000 E"3 E"3 SCALE IN FEET I 2000 EXISTING FOOT TRAIL S:,.:::o.._ ~, INDIAN RIVER HYDROELECTRIC PROJECT f,: PROJECT LOCATION MAP '-', 1----~~------------1 prepared by: polarconeult alaska. Inc. 150.] West 33rd Avenue, Suite 310 Anchorage, AlaSiko 99503 Tel: 907-258-2420 Fax: 907-258-2419 EMAIL: JOELOPOLARCONSULT.NET CllY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER Sec: 15, 16, 21, 22; Twp 47S; Range 63E; Capper River Meridian SCALE: 1 n=1000' FIGURE 1 OF 4 FILE: TKE_DES.dwg EXISTING USFS FISH LADDER (APPROXIMATE LOCATION) ?' ,. 't3 {, PROPOSED PENSTOCK (+1-1,800') STATI LAND_ 0 oz z::S ~w f:::~ -1-UUl PROPOSED POWERLINE TO TENAKEE SPRINGS ( + 1-4,soo') <'1 PROPOSED q;, POWERHOUSE FIGURE 4) 'so 0 PROPOSED ACCESS ROADS ( + 1-3,2oo') SECTION 15 SECTION22-. 250 500 SCALE IN FEET INDIAN RIVER HYDROELECTRIC PROJECT PROJECT MAP prepared by: polaroonault alaaka, lno. 1503 West 3Jrd Avenue. Suite 310 Anchoro(jje, AJoeko 99503 fe!: 907-158-2420 f'oll: 907-258-2419 EI!AJW JOfLOPOI.AACONSULT.NET AUGUST 6, 1TY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DMSION OF MINING, LAND AND WATER Sec: 15, 16, 21, 22; Twp 47$; Range 63E; Copper River Meridian SCALE: 1 "=250' FIGURE 2 OF 4 FILE: TKE_DES.dwg 150 ORIGINAL GROUND AIR RELIEF VENT ~ . SURFACE HEAD BOX HYDRO INTAKE SCREEN ACCE;SS ROAD LADD~C-~------1COANDA TYPE) --------------. lf REQU!Rffi} PYLONS 140 130 120 EXISTING FISH LADDER HEAD WALL 110 ------------------· +-----------------~--------------- INTAKE STRUCTURE -PLAN VIEW LOOKING UPSTREAM SCALE: 1" = 16' 130 TYPICAL WATER LEVEL 120 --------- 110 INTAKE STRUCTURE -SECTION VIEW A-A SCALE: 1" = 1 o' AIR RELIEF VENT PENSTOCK SCAlE IN FEET 10 ~ 0 16 E3 E3 sat! IN FEET NOTES: 1. THE DIMENSIONS AND LOCATION OF THE EXISTING FISH LADDER ARE APPROXIMATE. 2. DRAWINGS ARE CONCEPTUAL AND SUITABLE FO PERMITTING AND PLANNING PURPOSES ONLY INDIAN RIVER HYDROELECTRIC PROJECT INTAKE STRUCTURE-ELEVATION AND SECTION prepare y: polarconeult alaska, inc. 1 !i03 West 33rd Avenue, Suite 31 0 AnchOroge, Alcu1ka 99503 Tel: 907-258-2420 Fox: 907-258-2419 EMAIL: JOELOPOLARCONSULT.NET AUGUST 6, 201 0 CllY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER Sec: 15, 18, 21, 22; Twp 47S; Ranve 83E; Copper RIYer Meridian SCALE: 1·=250' FIGURE 3 OF 4 FILE: TKE_DES.dwg 110 ' 100 ORIGINAL GROUND SURFACE 90 POWERHOUSE 80 GENERATOR 70 DRAFT TUBE DEFLECTOR WALL r~t';::::!;===;I=;;::!=:;C:!::=tf---.J 60 TYPICAL WATER LEVEL STOP LOGS/ . Fl§.f:L !3~F<Bl~R_ ELEVATION VIEW LOOKING UPSTREAM 0 ~OWERHOUSE PLAN VIEW SCALE: 1" = 20' WORKBENCI-1 SWITCHGEAR GENERATOR 10 "' 0 ,. E3 E3 NOTES: 1. ALL DIMENSIONS AND LAYOUT ARE CONCEPTUA APPROXIMATIONS. 2. DRAWINGS ARE SUITABLE FOR PERMITIING AND PLANNING PURPOSES ONLY INDIAN RIVER HYDROELECTRIC PROJECT POWERHOUSE-PLAN AND ELEVATION prepared by: polarconault alaaka, inc. 1503 W•t .l.lrd Avenue, S~it111 .:510 Anchoro9•~ AJasko 99503 Tel: 907-256-2~20 FOlc 907-258-2~19 EMAIL: JOELOf'OLARCONSULT.NET AUGUST 6, 2010 CITY OF TENAKEE SPRINGS STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DMSION OF MINING, LAND AND WATER Sec: 15, 16, 21, 22; Twp 475; Range 83E; Copper RMir loter1dkln SCALE: 1 "=250' FIGURE 4 OF 4 FILE: TKE_DES.dwg City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report ~ Polarconsult Alaska, Inc. U.S. FOREST SERVICE COORDINATION November 2011 -Final Report APPENDIX D ------M8.(;A.RefTGef:fbARTE,-DI~TRICT--RkN£ER-···--······-------······--·---··· - USFS, Sitka Ranger Distlict 204 Siginaka Way Sitka, AK 99835 August 31, 2011 Subject: Request to Maintain Vehicular Access to Indian River Hydro Project via Indian River Road Dear Ms. Goularte: The City of Tenakee Springs (Tenakee) recently notified Polarconsult Alaska, Inc. (Polarconsult) that the U.S. Forest Service (USFS) plans to transfer approximately 20 miles of Indian River Road (USFS road 7500, 'IRR') into storage during the summer of 2012. As described in the USFS' request for proposals that was published July 291h, 2011, this project will involve replacing culverts and bridges along the road with hardened water crossings or off-highway vehicle (OHV) rated bridges. As the USFS is aware, Tenakee is actively pursuing a run-of-river hydroelectric project on Indian River, which is currently in the design and permitting phase. Tenakee expects the hydro project will be ready for construction in the summer of 2013. The project conceptual design, construction plan, and capital cost estimate all rely upon using the first approximately 1.3 miles of IRR for heavy equipment and light vehicle access to the project during construction and also for operations, maintenance, repair, and replacement (OMRR) activities over the life of the project. As advertised, it appears the IRR storage project will render IRR impassable to heavy equipment, requiring the city to either restore the road to a serviceable condition or employ more costly construction and OMRR methods. Either option will increase project costs, jeopardizing the project's economic viability and potentially forcing Tenakee to continue to rely on expensive diesel fuel for power generation. Tenakee formally requests that the USFS modify its IRR storage project such that the portion of IRR needed to access the project remain passable to heavy equipment and vehicular traffic. Tenakee is amenable to working with the USFS to reallocate avoided storage project costs to road rehabilitation and develop a reasonable plan for long term maintenance of the segment of IRR needed for hydro project access. Polarconsult has provided the USFS with conceptual designs that detail the location of the hydro access route and overall design of the project, and will continue to coordinate with the USFS on road use plans and permits necessary for use of IRR for this project. If you have any questions, please contact me at 907-258-2420, x204, or by email at joel @polarconsult.net. Sincerely, (s/~<:t~ Joel D. Groves, PE cc: -Art Bloom, City of Tenakee Springs Councilman and Hydro Project Manager Don Peagues, Mayor, City of Tenakee Springs 1503 WEST 33RD AVENUE • SUITE 310 • ANCHORAGE, ALASKA 99503 PHONE (907) 258-2420 • FAX (907) 258-2419 • HOMEPAGE www.polarconsult.net ~S(iLICI~T~A~T~I~O~N~,-::0:-::F::::F::::E::-:R:::-cAN~D::c-Ac-:W:=-A:-:RD::-:::c--~,--,l-::.T=H:;:ciS:::-C;;o;;Oo;cN;-o;TRA=-~cco;;T;;-;I;-;;-S-:A--:RA:---:-;;T""E;;;:;D:-:O;;c;RD=E:::;R~ ,--RA-T~IN-G---,-P~A_G_E_0~F-------- UNDER DPAS (IS CFR 700) l 36 PAGES 4. TYPE OF SOLICITATION ;;:-;:::-:-!~==::-------,----:'6--c. RE=Q~UI'=si=T'{(jNiPURCHASE 2. CONTRACT NUMBER .. . SOLICITATION NUMBER Total HUBZone Set- Aside AG-0116-S-ll-0118 0 SEALED BID (IFB) NUMBER [8J NEGOTIATED (RFP) 7/29/11 8. ADDRESS OFFER TO (If other than Item 7) See Item 7 533864 9. Sealed offers in original and ~cc__ __ or if hand carried, in the depository locat~d in copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, TNF Contracting Office until _±Q!.lpf11 local time --""=.:.::="=:'--·:···········-- (Hour) CAUTION-LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation. lO.FOR INFOR.\1A TION CALL: r\ Y! A. NAME Sherman Mayle ~· TELEPHONE NO. (NO COLLECT ;CALLS)Area Code/Number/Extension I 907-228-6244 DESCRIPTION ------· DESCRIPTION -···-· L?J\GE~ PART I-THE SCHEDULE PART II CONTRACT CLAUSES X X A 1 sou ciT A TION/COJ'<']1tA_~cT_Fo_RM ______ --+--'l-,---+~x~.J__~r--~._c_o_N_TRA ____ c.I-_t:;LAUSES .l 19-23 I 2-3 PART III LIST OF DOCUMENTS, EXHIBITS AND OTHER B SUPPLIES OR SERVICES AND PRICES/COSTS ATTACH . . c fDESCRIPTION/SPECS.fWORK STATEMENT-· . X X X D . PACKAGING AND MARKING X X X X X L X X M -c=c=~---=-=--:----7'-:-::-:---:-:--:---c----o-~c---:---O.:::.e::.F:c=F-=E:R (Must be folly completed by offeror) NOTE: Item 12 does not apply if the solicitation includes the provisions ai52.214-16, Minimum Bid Acceptance Perine!, __________________ _ 12. In compliance with the above, the undersigned agrees, if this offer is accepted within 60 calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the rice set o osite each item, delivered at the desi ated oint(s ), within the times ecified in the schedule. 30 CALENDAR DAYS CALENDAR DAYS l3.DISCOUNTFORPROMPTPAYMENT M !OCALENDARDAYS l20CALENDARDAYS (See Section I, Clause No. 52-232-8) ~ % % % % 14. ACKNOWLEDGMENT OF AMENDMENTS AMENDMENT NO~ .. DATE ~-i---A!-:-M:-=E::-:ND=:-M-:c:E:::-N-:c:T::c:N:-:-0:::-.--'-T-----cD:::-A-,-TE=--- (The offeror acknowledges receipt of amend- ments to the SOL!ClTA110N for offerors and 1~ ··············----------+---------+ ........... ~------~·--+------........... __ ...... . related documents numbered and dated): · tsA. --~c=-o:--cD-=Ec--rj:_:_:_:_ __ __._)l FACILITY L __ .. ___ --; NAME AND ADDRESS OF OFFEROR 15B. TELEPHONE NO. (Include area code and extension) 16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or Print) ISC. CHECK IF REMITTANCE ADDRESS IS DIFFERENT FROM ABOVE -ENTER !?.SIGNATURE IY SUCH ADDRESS IN SCHEDULE. ~----~---------~ ........... _ .. 11 i =--c----,;,-~c---=-j__---:---·· .............. ------__1----·~···· ............... ~-- 19. ACCEPTED AS TO .. ITEMS NUMBERED 22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN 10 U.S.C. 2304 (c) ( 41 U.S.C. 253(c) ( 23. SUBMIT INVOICES TO ADDRESS SHOWN IN q ITEM COMPETITION 24. ADMINISTERED BY (If other than Item 7) CODE CODE Prescribed by GSA-FAR (48 CFR) 53.214(c) PART I-THE SCHEDULE AG-0116-S-11-0118 TNF Indian River Road Storage PAGE 2 of36 SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS Indian River Road Storage Sitka/Hoonah Ranger Districts B.1 SCHEDULE OF ITEMS Base Item Item Description Unit Estimated Unit Total Number Ouantitv Price $ $ 1.1 203(01) Removal of Log Stringer Bridge Each 26 203(01) Removal and Transport of 40' Lump 1.2 Modular Bridge MP 8.368 Road 7500 Sum 1 $ $ 203(01) Removal and Transport of 80' Lump 1.3 Modular Bridge MP 8.737 Road 7500 Sum 1 $ $ 203(01) Removal and Transport of 60' Lump $ $ 1.4 Modular Bridge MP 9.835 Road 7500 Sum 1 203(01) Removal and Transport of 70' Lump 1.5 Modular Bridge MP 13.273 Road 7500 Sum 1 $ $ 557(01) Furnish and Install 50' Log Trail Lump 1.6 Bridge, MP 0.466 Road 7500 Sum 1 $ $ 1.7 802(03) Road Storage Mile 20.78 $ $ Lump 1.8 881(1) Mobilization Sum 1 $ $ TOTAL BASE $ Option Work Items Item Description Unit Estimated Unit Price Total Number Ouanti!l: 2.1 861(01) Resurface Bridge Surface SF 3,150 $ $ TOTAL OPTION $ TOTAL (BASE YEAR AND ALL OPTIONS) $ ____ _ B.2 Note AG-0116-S-11-0118 TNF Indian River Road Storage PAGE 3 of36 Line Items 1.7 and 2.1 are design quantities, which mean that ifthe quantity is within+/-15%, the contractor gets paid for the units listed in the schedule of items at the unit cost listed in the schedule of items - a fixed dollar amount even when the quantity changes if the change is within 15%. If quantities vary by more than 15%, then a Contract Modification is required B.3 Vendor Information Vendor Name: Phone Signature: Fax Address: Email City, State, Zip: TIN# Duns# Info Below requested to ensure payment info on record is accurate in the interest of preventing any delays in the distribution of any payments. Bank Name Last 4 digits of Acct # AG-0116-S-11-0118 TNF Indian River Road Storage PAGE 4 of36 SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK C.l Scope of Contract The intent ofthe contract is to perform road maintenance activities in accordance with the scope of work, worklist, specifications and attachments incorporated into this contract. Work includes installing waterbars, excavating and sidecasting road fill material, removing culverts and log bridges, removing modular bridges and transporting them to Thome Bay, Alaska, removing 2 abandoned vehicles, constructing a log stringer trail bridge, clearing brush from the roadway for equipment access, and seeding and fertilizing exposed organic soils on and along roadsides on approximately 20 miles of National Forest System Roads on Chichagoflsland. The removed culverts and hardware become the property of the contractor and must be removed from the National Forest. The Contractor shall furnish all labor, materials, equipment, tools, transportation, supplies, and perform all work required to maintain the facilities in accordance with the attached typical drawings, supplemental specifications and parent specifications. Road storage work in this contract involves stabilizing roads regarding drainage. Work will include a combination of drainage structure removal, waterbar construction, clearing the roadway of brush for project access and proper drainage, and seeding and fertilizing bare organic soils. Road storage work is payable on a per mile basis, regardless of the number of drainage structures removed or constructed for each mile, and the amount of seeding and fertilizing required. Approximately 9 miles of road storage will construct waterbars and fords for off highway type vehicle (OHV) passage at locations where culverts and bridges are removed, and at additional staked locations. The remaining 11 miles of road storage will not be left open to OHVs, these roads will have structures removed, waterbars constructed and be blocked to motorized vehicles with a barrier of rock borrow and logs. Spacing between waterbars will be 50 to 750 feet apart on each type of road storage. Refer to the drawings and worklist in Section J for details on each project road. The work includes removing and transporting modular steel bridges from the work area to the Thome Bay, Alaska sortyard. Moving the bridges on the Indian River road system may require additional work on the existing native log bridges, which were constructed in the late 1970s. Several bridges have undermined sill logs due to stream scour, and many have visible rot in the brow logs. The modular bridge furthest from the beach, a 70' Hamilton at MP 13.273 on road 7500 is located beyond a site where a log bridge has been previously removed. The span of the removed log bridge was 70' and it sat on log crib abutments approximately 15' above the stream elevation. Mobilizing beyond the removed log bridge site may involve construction of a temporary bridge provided by the Contractor, or it may involve additional excavation of the rock borrow approaches to allow equipment access through the stream and beyond the site. A site visit to the work area is recommended, the road leading to the removed log bridge site is presently open and drivable to OHVs. The work includes construction of a 50' native log trail bridge. Construction timber in the form of standing trees will be made available within 5 miles of the bridge site. Equipment cleaning will be required prior to mobilizing to the work site. Refer to the Special Project Specifications for details. The structures listed in the worklogs represent known locations of drainage structures needing work. Additional structures may be located during the project that require maintenance or removal, any work within the scope of the project associated with additional structures or additional required work to AG-0116-S-11-0118 TNF Indian River Road Storage PAGE 5 of36 stabilize the roads located on project roads is considered incidental to the rest of the project work. Many project roads are covered with vegetation such as alder and young spruce growth. The contract also includes an option for additional work furnishing and installing 4"x12" treated wooden planks for the middle joint on 3 modular bridges, and for furnishing and installing 3"x12" untreated wooden planks for the wear surface on the 3 modular bridges. Refer to Sections B and J for optional work details. In-stream timing restrictions are included in the contract for work in streams with fish populations. Refer to Section H for times and locations where this will affect work scheduling. Additionally, a pre- commercial tree thinning contractor will be using road 7500 from the beach to MP 10.935 and road 7502 in its entirety during the spring of 2012. There will be no road storage work allowed on these 2 road segments that interferes with OHV type vehicles before July 1, 2012. The Contractor shall assume all risk, loss, damage, or expense arising out of prosecution of the work, except as otherwise provided in the contract. C.2 Description and Location The project is located on Chichagof Island in southeast Alaska. The Indian River road system is isolated, and is accessible by air or salt water. There are no services available. Tenakee Springs is the nearest community to the work area, however there is no road connection between Tenakee Springs and the work area .. Juneau is the nearest full service community to the work area, approximately 30 air miles towards the east northeast. The Log Transfer Facility (LTF) that serves the Indian River road system is located in Sunny Cove. The present condition of the facility is ringed with a vegetated cover of alder trees. The shot rock fill at the LTF is in place, however the site has not been used for equipment transport since 1999. The Indian River road system is in similar condition, motorized traffic on the roads has been limited to OHVs for approximately 10 years, allowing alder and grass to spread towards the road center. All brush removed for equipment access shall be sidecast below the roadway and shall not be placed in or near streams creating the potential to affect stream flows. C.4 Mobilization Per FP-03, this work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site. Mobilization includes the obtaining of permits, insurance and bonds. When 5% of the original contract amount is earned from other bid items, 50% of the mobilization item, or 5% of the original contract amount, whichever is less, will be paid. When 10% of the original contract amount is earned from other bid items, 100% of the mobilization item, or 10% of the original contract amount, whichever is less, will be paid. C.5 Signing and Safety (a) A reflective SLOW MOVING VEHICLE emblem shall be attached to any equipment not designed to maintain a safe travel rate or that will be moving at a slow rate while performing maintenance. (b) It shall be the Contractor's responsibility to furnish black and orange reflective maintenance warning signs to alert motorists of maintenance operations. All signs shall conform to the standards for Temporary Traffic Control in accordance with the Manual of Uniform Traffic Control Devices (MUTCD). A minimum of one (1) City of Tenakee Springs Indian River Hydroelectric Project Feasibility, Conceptual Design, and Permitting Phase II Final Report G Polarconsult Alaska, Inc. APPENDIX E-PHASE II FINAL REPORT REVIEW COMMENTS November 2011 -Final Report APPENDIX E MEMORANDUM DATE: November 3, 2011 polarconsult alaska, inc. 1503 West 33rd Avenue, Suite 310 Anchorage, Alaska 99503-3638 Phone: (907)258-2420 FAX: (907) 258-2419 TO: Art Bloom, Tenakee Springs Project Manger FROM: Joel Groves, Polarconsult Project Manager SUBJECT: Response to AEA Review Comments on Indian River Hydroelectric Project Phase II Final Report CC: Phase II Final Report Appendix E The Client Review Draft of the Indian River Hydroelectric Project Phase II Final Report was provided to the City of Tenakee Springs on September 28, 2011 and the Alaska Energy Authority (AEA) on October 11, 2011. The AEA provided comments on October 31, 2011. AEA comments and Polarconsult responses are summarized below. As appropriate, AEA's comments have been incorporated into the final release of the Indian River Hydroelectric Project Phase II Final Report, dated November 2011. AEA Comments Received (Polarconsult responses in BLUE) 1. Section 2.3 -Refers to "Feasibility Study Report." Please include the title of the report, author, and date so that it is understood exactly which report it is being referred to. Section 2.3 has been modified to state the full name, date and author of the Feasibility Study report. 2. Appendix A: Conceptual Drawings a. Scales don't appear to be correct. In final report, please print on intended page size or fix scales. The conceptual design drawings are formatted as D size drawings (22" by 34"). The printed copies of the Phase II reports include half-size drawings for the readers' convenience. Graphic scale bars are included on all sheets to provide a correct scale regardless of what size paper is used to plot the drawings. This has been clarified in the narrative and on the drawings to avoid confusion. b. Sheet C1.2: The reference roadway section for the road in the steep drop into Indian River canyon (from Sta 16 + 15 to 18 + 40) is listed as Type 2. But the Type 2 section would apply only if the route were sideways to the hill slope, which it is not. A fourth typical roadway section has been added as Detail 6, Sheet Cl.l to represent the main access road from Sta. 16+15 to 18+40, and the callout on Sheet C1.2 has been corrected. 111103-TENAKEEPHASEIIREPORT _APOXE.DOC POLARCONSULT MEMORANDUM c. Sheet C1.2: The 54% grade drop down this steep hill will be a hazard for routine access to the powerhouse after construction. Please comment. The local community is very sensitive to minimizing the roads associated with this project, which is one reason for the proposed powerhouse access configuration. Two means of access to the powerhouse will be available post-construction. For routine personnel access, existing foot trails down this slope are adequate and safe to provide pedestrian access to the powerhouse. For equipment or heavy maintenance access, a permanent winch point will be provided at the top of this grade to allow materials, equipment or vehicles to be winched up and down this grade. Sheet C1.2 has been modified to show these provisions. d. Sheet C3.1: The location of the penstock on trestles in the canyon may be at risk during high water events. The final design for the penstock will evaluate flood stage in the canyon and site the penstock trestle above flood stage to the extent practical. Any penstock trestles that cannot be sited above flood stage will be built to withstand inundation and impact from flood debris (e.g., logs). The penstock design will also evaluate the potential for logs to directly impact the pipe spans and the penstock will be designed accordingly. e. Sheet C3.1-Detail2? Missing profile? Two of the same page? There is not a missing detail. Sheet C3.1 has been corrected. f. Sheet C5.1, Detaill-"leader" /"arrow to" some portions of the drawing are off, i.e., switchgear, load bank. The leaders on Sheet CS.l have been corrected. g. Did not review April drawings 3. The impact of the USFS Indian River Road Storage project upon the access for the Indian River Hydroelectric Project remains a concern to this reviewer. At worst case scenario the removal of existing log bridges and steel culverts by USFS contractors would negatively impact the construction cost of the hydro project. AEA requests the Grantee to continue to communicate with USFS on this issue to reduce these negative impacts as much as possible. The City is maintain an active dialog with the USFS on this issue to work towards an acceptable solution. The USFS has stated that they will make reasonable accommodations for the City's access needs to the project site. The City will keep AEA appraised of the status of these discussions. Page 2 of 2