HomeMy WebLinkAboutKing Cove Hydro Project Engineering Excellence Awards 19951995 Engineering Excellence Awards
King Cove
Hydroelectric Project
Category D3
Energy Production/Conservation
Submitted By:
li)~
HDR Engineering, Inc.
2525 C Street
Suite 305
~chorage,AJaska
99503-2689
Submitted to:
Consulting Engineers
Council of Al aska
February 14, 1995
The King Cove Hydroelectric Project:
HDR Engineering Brings Hydropower to King Cove
King Cove, Alaska, on the Alaska Peninsula, is home to an 800 kW run-of-the-river hydropower
facility recently constructed to replace the city's diesel-generation system. HDR Engineering's
involvement in the project has encompassed every phase of this project, from feasibility studies
and fmancing to design and construction management. By balancing the needs of the client with
environmental and engineering design constraints, HDR has not only ensured the success of this
project, but through its example, has made hydroelectric generation a more viable option for
rural Alaska communities.
Sandwiched between the stormy Gulf of Alaska and the even stormier Bering Sea, the
community of King Cove is 624 air miles southwest of Anchorage and seven days via ship from
Seattle. Like most communities in Alaska, no road links this community to another, so access
is limited to air or sea transportation when weather permits. The same landscape that isolates
King Cove from the rest of the state, however, also has made this area well suited for
hydropower. The steep mountains that surround the community provide head and the area's 52
inches of snow and 33 inches of rain each year provide for the volume of flow.
Although the area was generally well suited to this type of project, it was not without complex
problems. Inaccessibility; grizzly bears; steep, glacial streams with high sediment and bedloads;
near constant rain and snowfall; and 120 mph winds were problems that required original
solutions. The city's·remote location posed one of the greatest challenges. During all phases
of the project, traveling to the project site took a major effort of coordination. This was
especially true during construction as the entire crew had to be relocated to the site, as well as
housed and fed for the life of the project. What is even more unusual is that during initial site
visits, team members carried shotguns for protection from the local grizzly bear population.
King Cove's isolation made securing equipment a complex process, as all materials from the
9,000-pound flywheel to the correct nut to bolt it down had to be barged in from Seattle or
flown in from Anchorage. With the week-long journey by ship from Seattle, the project leaders
had to manage the project effectively to keep to its tight schedule and budget. As a product of
this effort, the HDR team completed this $5.7 million project on time and under budget.
The design and construction of the project also presented complex challenges that required
innovative solutions. While most hydroelectric projects rely on a single source of water to drive
the turbine, the required head could only be obtained by placing the intake high on the mountain
and constructing two intakes on two branches of Delta Creek (Glacier Creek and Clear Creek).
The high bedload and environmental constraints would not allow the impoundment of significant
quantities of water, so a run-of-the-river design was required. These two characteristics
-separate intakes and a run-of-the-river design-were accommodated with a unique concept for
control. Located at a higher elevation, the Glacier Creek intake was designed as the primary
source of water. Under normal con,, tions, this intake draws water from Glacier Creek and sends
King Cove Hydroelectric Project
Engineering Excellence Awards
it to the powerhouse below. A check valve installed at the Clear Creek intake prevents Glacier
Creek water from backing up through the Clear Creek intake during high flow conditions.
When Glacier Creek flow becomes insufficient to meet the city's power needs, the pressure in
the pipe drops and the water flows "open channel." When this "open channel" flow reaches the
pool level of the Clear Creek intake, it triggers the intake to let Clear Creek flows into the
system. This two-intake balancing act works without any mechanical controls, a unique,
foolproof, passive control design.
The HDR design also had to address the high bedload and sediment load in the tributaries.
Because of the steep terrain and the relatively recent recession of glaciers from this area, both
streams carry extremely high loads of sediment-as is evident by the large fan in Delta Creek
and, hence, its name. Moreover, 8-to 12-inch boulders have been observed tumbling
downstream during floods. To keep the intakes fully operational and reduce long-term
maintenance needs, HDR designed a sluiceway with a side intake trashrack at each of the
tributaries. Opening the sluice gate during floods allows bedload to flush harmlessly by the
trashrack while turbine operation continues. To remove fmer materials, a sediment chamber
with a separate sluice pipe is positioned between the intake grate and the penstock.
To keep the intakes from becoming blocked by frazil ice in cold temperatures, HDR designed
them to be submerged in small, quiescent pools. By enabling a layer of ice to form over the
intake structures, the intake screen does not become blocked; instead, water flows under the ice
surface and into the penstock. As a backup to these intake protection systems, water level
sensors upstream and downstream of the intake trashracks alert plant operators if the trashracks
become plugged. HDR's cold regions experience not only enabled the project team to identify
a potentially serious problem, but allowed the company to engineer a cost-effective solution--one
that did not carry a high operations and maintenance price tag.
To best use the available head and flow, power is generated by a Gilkes Turgo impulse turbine,
a dual-jet unit equipped with hydraulic deflectors to control flows. Design parameters were 292
feet gross head and 242 feet net head at full load. The rated synchronous generator output is 805
kW at 0.90 power factor. The unit also includes a speed governor because it was designed to
operate as the sole source of power for the community. As is typical of small communities in
Alaska, King Cove's system is not connected to another town's electrical system or to a grid
system. To accommodate fluctuations in user loads that would otherwise be absorbed by a grid
network, HDR's design included a 9,000-lb flywheel. This flywheel both stores and provides
energy to ensure smooth transitions during load changes.
With a peak city load of 500 kW, the existing city system could not produce the load required
for proper testing. Moreover, the constant on-line and off-line operations inherent to the start-up
debugging sequence would neither be convenient to city residents nor easy on electrical
equipment. Instead of settling for a scaled-back testing process or risking city equipment, a
"water rheostat" was constructed as a load bank. The HDR team hauled an empty, 3-yard
dumpster from town, fllled it with salt water, installed copper electrodes, and connected it to the
hydroelectric facility. The salt provided the conductivity, the electrodes linked the dumpster
2 liR
King Cove Hydroelectric Project
Engineering Excellence Awards
directly to the generator, and the heating of the water provided the demand for power. With the
entire King Cove projected load for the year 2020 distributed to the dumpster, the project team
tested the operation of the new equipment from no output to full capacity with no impact to the
city system.
Making certain this system could handle the residents' projected electrical needs was particularly
important because King Cove is a rapidly expanding community. In five years the current diesel
system would not have met the city's demand. Providing for this community's growing electrical
needs is a necessary part of maintaining the residents' standard of living.
Although the design and construction of a 800 kW hydropower facility may not be considered
unusual in the lower 48 states, this effort in Alaska is ground breaking. King Cove's interest in
hydroelectric projects has spanned a decade, but HDR was the first finn to make it a reality.
King Cove, with its steep mountains and high precipitation, could be any of a hundred
communities in Alaska. Because of King Cove's success, it will become a prototype for all
other facilities in the region. In demonstrating that a hydropower facility can meet a city's
long-term electrical needs, HDR has begun a transition from more expensive, diesel-burning
systems to the cheaper, cleaner option of hydropower. Given the uncertain future costs and
storage requirements of diesel fuel and its impact on the environment, residents have been
pleased to learn that the new system is saving the city over 400 gallons of fuel each day. As
summed up by City Manager Gary Hennigh, "HDR's work has been incredibly well received
by the community, and the residents are thrilled with the product." By overcoming extraordinary
environmental and technical challenges in one of the country's most remote locations, HDR has
improved the quality of life in King Cove and forever secured a niche for hydropower in Alaska.
3
~ COVE HYDROELECTRIC PROJECT
OWNER: RDA CITY OF KING COVE, ALASKA
HDR worked with the city through every step of the process from feasibility studies
and financing to design and construction management.
King Cove's remote location presented unique challenges to the project
team. Field work for the feasibility study, for example, required team
members to tote shotguns for protection from grizzly bears.
The area's 5,000 foot mountains and heavy precipitation made the landscape well suited
for hydropower. Note the two intakes on the left-and right-hand sides of the photo.
Wit h no roads linking King Cove to another community, access was limited to air or sea
transportation when weather permitted. Barges like this one brought equipment and
materials from Seattle or other locations in Alaska.
Before construction
During construction
Before and during construction shots of the Glacier Creek intake, one of the two intakes needed for this
run-of-the-river design. Set at different elevations, the two intakes required an engineering balancing act
to make them work successfully.
During construction
After construction
During and after construction shots of the Glacier Creek intake, one of the two intakes needed for
this run-of-the-river design. Set at different elevations, the two intakes required an engineering
balancing act to make them work successfully.
With a short construction season, crews built the intakes between
June and September.
Crews built and buried 6,700 feet of 32-inch steel penstock from the
intake to the powerhouse.
A multidisciplinary effort, this project involved water resources, transportation, and
other elements, as captured by this shot of a road and pipeline crossing.
Because the existing system could not produce the load required to test
the facility, HDR transformed this dumpster into a load bank. By filling
it with salt water, installing copper electrodes, and distributing the entire
projected load for the year 2020 to it, the team tested the facility to full
capacity.
City of King Cove
Located 5 miles from town, 2 miles of new road was required to access the hydropower facility,
which consists of intakes on two tributaries of Delta Creek, 6,000 feet of buried penstock, a
powerhouse, a single 800 kW impulse turbine and generator, 5 miles of buried electric cable, and
a SCAD A system for remote monitoring and control.
Funding
1993-1994
HDR's Involvement in the Project
Feasibility Study
1991
Delta Creek
Topographic Mapping
1992
Final Design Work
1994
Procurement
of
Materials
1994
Construction
1994
King Cove Hydroelectric Facility
OnLine
November 1994
Environmental
Studies and
Permitting
1993
Funding Sources lOr the
King Cove Hydroelectric Project
Grants:
State/ Alaska Energy Authority $2,500,000
(granted to city)
State/Deparnnent of Administration $500,000
U.S. Deparnnent ofEnergy
Aleutians East Borough
City of King Cove
Loans:
Farmers Home Administration
(Hickel Administration
match of Aleutians East
Borough/ City of King
Cove/State of Alaska
funds)
$250,000
(through Tribal Council)
$250,000
$250,000
(cash from city permanent
fund)
$I ,800,000
(25 years/ 5.5% interest)
CITY OF KING COVE
February 14, 1995
Awards Selection Committee
Consulting Engineers Council of Alaska
Anchorage, Alaska
Subject: Engineering Excellence Award for the King Cove Hydroelectric Project
Dear Selection Committee:
Since November 1994 the King Cove hydroelectric facility has been on line, providing for the
electrical needs of about 200 households and ten commercial and government facilities. A major
part of the city's success in seeing the hydroelectric project become reality was our steadfast
confidence and faith in HDR Engineering. HDR oversaw all phases of the project.
Each member of the HDR team provided consistent and timely professional guidance throughout
the project. Project Manager Duane Hippe is an extremely competent engineer, and even more
importantly, he is a quality individual. These two factors were very instrumental in our decision
to go with HDR the whole way on this project.
For bush communities contemplating similar projects, this experience has shown me that it is
imperative early in the process to secure the services of professionals who clearly understand
both the community and the range of technical and financial components of the project. These
professionals must be trustworthy, so you feel confident taking their advice and comfortable
voicing any concerns. HDR Engineering was just that firm to the City of King Cove. Through
this firm's efforts, the city has made its vision for a hydropower facility become reality.
Sincerely, 1 . ,
_jLL~--((j~ ;;i
Gary4fennigh
City Manager
1600 A STREET. SUITE 103
ANCHORAGE, AK 99501·5146
(907) 274-7555
(907) 276-7569 FAX
P.O. BOX 37
KING COVE, AK 99612
(907) 497-2340
FAX (907) 497·2386