HomeMy WebLinkAboutFalls Creek Reconnaissance Report 2009Falls Creek
Proposed Hydroelectric Project
Reconnaissance Report
Prepared for:
Kenai Hydro, LLC
Prepared by:
~ -HDR Alaska, Inc.
2525 C Street, Suite 305
Anchorage, AK 99503
March 2009
Falls Creek Proposed Hydroelectric Project
Reconnaissance
Table of Contents
Introduction .......................................................................................................................... !
Project Area ................................................................................................................ 1
Previous Studies .......................................................................................................... 2
Environmental Considerations ............................................................................................. 2
Fish Resources ............................................................................................................ 3
Wetlands ..................................................................................................................... 3
Hydrology and Water Quality ..................................................................................... 4
Recreation ............................................................................................................................ 4
Subsistence, Cultural and Historical Resources ................................................................... 5
Subsistence .................................................................................................................. 5
Cultural and historic resources ................................................................................... 5
Land Ownership, Mining Claims, and Water Rights ........................................................... 6
Project Arrangement ............................................................................................................ 6
Project Description ..................................................................................................... 7
Energy Generation ............................................................................................................... 7
Cost Estimates ...................................................................................................................... 8
Assumptions ............................................................................................................... 8
Results ......................................................................................................................... 9
Economic Evaluation ........................................................................................................... 9
Conclusions and Recommendations .................................................................................... 9
References .......................................................................................................................... ! 0
Tables ............................................................................ ; ................................................... 12
Figures ................................................................................................................................ 17
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report
Appendix A -Land Status Information ............................................................................. 25
Appendix B -Energy Calculations .................................................................................... 29
Appendix C -Cost Information ......................................................................................... 33
Appendix D -Project Photographs .................................................................................... 39
List of Tables
Table 1. Falls Creek scale factors (determined by APA 1984) used to simulate flow of
Falls Creek from stream flow data collected at Grant Creek ........................... 13
Table 2. Temperature comparisons for Grant Lake, Grant Creek and Falls Creek ......... 14
Table 3. 2008 instantaneous flow measurements collected at Falls Creek by HDR staff,
October to December 2008 .............................................................................. 14
Table 4. USFS campgrounds on the Kenai Peninsula ..................................................... 15
Table 5. USPS-maintained trails on the Kenai Peninsula ................................................ 15
Table 6. Parameters for the project arrangement considered for Falls Creek .................. 16
List of Figures
Figure 1. General location of proposed hydroelectric facilities at Falls Creek on the
Kenai Peninsula, Alaska .................................................................................. 18
Figure 2. The anadromous reach of Falls Creek .............................................................. 19
Figure 3. Mean monthly discharge of Falls Creek, modeled using data from USGS gage
15246000 (1947-1958) at Grant Creek ............................................................ 20
Figure 4. Flow duration curve for Falls Creek ................................................................. 20
Figure 5. Falls Creek modeled discharge based on data from USGS gauge 15246000
(194 7 -1958) at Grant Creek ............................................................................. 21
Figure 6. Private parcels of Falls Creek area ................................................................... 22
Figure 7. Water rights and mineral claims in the Grant Lake area .................................. 23
Figure 8. Proposed project arrangement at Falls Creek ................................................... 24
11
ADF&G
AEIDC
AHRS
APA
AWC
BLM oc
cfs
em
op
DNR
EPA
FERC
ft
G&A
GWh
HEP
In
KPB
kWh
LLC
ml
mm
MSL
MW
MWh
NWI
O&M
RVDs
USACE
USFS
USFWS
USGS
Falls Creek Proposed Hydroelectric Project
Reconnaissance "'"..-.,. .. ,
Acronyms and Abbreviations
Alaska Department of Fish and Game
Arctic Environmental Information and Data Center (University of
Alaska)
Alaska Heritage Resources Survey
Alaska Power Authority
Anadromous Waters Catalog
Bureau of Land Management
Degrees Celsius
Cubic feet per second
centimeter
Degrees Fahrenheit
Alaska Department of Natural Resources
Environmental Protection Agency
Federal Energy Regulatory Commission
feet
general and administrative
Gigawatt-hours
Hydroelectric Evaluation Program
inch
Kenai Peninsula Borough
kilowatt-hours
Limited liability company
mile
millimeter
Mean sea level
Megawatt
Megawatt-hours.
National Wetlands Inventory
Operations & maintenance
Recreation visitor days
U.S. Army Corps of Engineers
U.S. Forest Service
U.S. Fish and Wildlife Service
U.S. Geological Survey
iii
Introduction
Falls Creek Proposed Hydroelectric Project
Reconnaissance
Kenai Hydro LLC (KHL) contracted with HDR Alaska, Inc. to evaluate the feasibility of small-
scale hydroelectric projects at Crescent Lake, Ptarmigan Lake, Falls Creek, and Grant Lake near
Moose Pass, Alaska (Figure 1).
This reconnaissance report examines the viability of small-scale hydroelectric energy generation
at Falls Creek that would minimize environmental and other impacts. A team consisting of
engineers and environmental scientists made reconnaissance-level site visits and analyzed
existing information in order to determine if further feasibility analyses were appropriate based
on potential constructability, cost effectiveness, and potential environmental impacts.
The scope of work defined for this assignment included:
• Field reconnaissance by team members;
• Review of available project documentation and related information;
• Development of conceptual alternatives;
• Review of existing hydraulic and hydrologic parameters;
• Estimation of energy production and project costs;
• Preparation of this reconnaissance report.
This report should be considered a high-level overview intended to identify projects which
demonstrate a basic measure of feasibility and to eliminate projects that have evident fatal flaws
from an engineering and environmental perspective; this report also provides information to
enable KHL to determine economic feasibility.
Project Area
The project is located approximately 1.5 miles south of the community of Moose Pass, Alaska
(pop. 206), approximately 25 miles north of Seward, Alaska (pop. 3,016),just east of the Seward
Highway (State Route 9); this highway connects Anchorage (pop. 279,671) to Seward (Figure 1).
The Alaska Railroad parallels the route of the Seward Highway, and is also adjacent to the
project area. The town of Cooper Landing is located 24 miles to the northwest and is accessible
via the Sterling Highway (State Route I) which connects to the Seward Highway approximately
10 miles northwest of Moose Pass.
Falls Creek flows into Trail River just downstream of Lower Trail Lake (approximately 1.8
miles downstream of Grant Creek). The Falls Creek watershed drains steep terrain between the
Grant Lake and Ptarmigan Lake watersheds, is 11.9 square miles in area, contains no lakes, and
has no major tributaries. Estimated mean annual flow of Falls Creek is 38 cfs; stream flow
during the winter is minimal. Falls Creek is 42,240 ft (approximately 8 miles) long, average
Falls Creek Proposed Hydroelectric Project
Reconnaissance
stream gradient is 418 ft/mi and stream width averages 15 ft wide. The Falls Creek substrate
includes cobble, boulder deposits, few gravel bars and a thin layer of fine silt near the mouth; the
lower one mile of stream has been extensively channelized and modified by placer mining (APA
1984). Three to four acres adjacent to the active channel in the lower 0.5 miles are covered with
tailings and 100 yards of the streambed in this area has been relocated (AEIDC 1982).
The lower 2,300 ft of Falls Creek is classified as anadromous in the ADF&G Anadromous
Waters Catalog (A WC). Anadromous fish species present in Falls Creek included juvenile
Chinook (Oncorhynchus tshawytscha) and juvenile Dolly Varden (Salvelinus malma) (USFWS
1961, Johnson and Daigneault 2008, AEIDC 1982).
Previous Studies
The hydroelectric potential at Grant Lake, approximately 1 mile north of Falls Creek, has been
evaluated several times as a potential power source for the Seward/Kenai Peninsula area. In
1954 R.W. Beck and Associates (cited in APA 1984) prepared a preliminary investigation and
concluded that a project was feasible. In 1980 CH2M Hill (cited in APA 1984) prepared a pre-
feasibility study for a Grant Lake project and concluded that a project developed at the site was
feasible.
The most extensive study was performed by Ebasco Services, Inc. in 1984 for the Alaska Power
Authority (APA 1984). Falls Creek (Figure 1) was investigated by Ebasco in 1984 for the
Alaska Power Authority (now Alaska Energy Authority) as a possible source of additional flows
that could be diverted to nearby Grant Lake in support of a hydroelectric project there (APA
1984).
Environmental Considerations
The following presents a general overview of potential expected environmental considerations
for a hydroelectric project at Falls Creek. This section describes fish resources, wetlands,
hydrology and water quality, recreation, subsistence, and cultural resources of the project area.
The area is managed using several specific management plans, including the Chugach National
Forest Plan (Meade 2006), Kenai River Comprehensive Management Plan (DNR 1998), and
Kenai Borough Coastal Management Plan (KPB 2008). Another search for all relevant land
management plans would be required as part of FERC licensing and by other required permitting
processes.
Ebasco (APA 1984) compiled a feasibility report on the Grant Lake hydroelectric project,
including detailed environmental studies of water use and quality; aquatic, botanical and wildlife
resources; historical and archaeological resources; socioeconomic impacts; geological and soil
resources; recreational resources; aesthetic resources; and land use. The Arctic Environmental
Data Center (AIEDC 1982 and 1983) and USFWS (1961) conducted environmental baseline
studies in the project area. For the purposes of this feasibility report, HDR Alaska did not
conduct any environmental work beyond initial reconnaissance visits and instantaneous flow
measurements (see Hydrology and Water Quality below) and this overview draws mainly on
these historical reports.
2
Fish Resources
Falls Creek Proposed Hydroelectric Project
Reconnaissance "'""'"'"'
The lower 2,300 ft of Falls Creek is classified as anadromous in the A WC (Figure 2) (Chinook
salmon present; Johnson and Daigneault 2008). Anadromous species, including juvenile
Chinook salmon and juvenile Dolly Varden have been found in its lower section; a series of
waterfalls prevents fish passage above the lower 2,300 ft of the stream (USFWS 1961, Johnson
and Daigneault 2008, AEIDC 1982).
Current 2009 sport fishing regulations allow sport fishing on Falls Creek June 11 -May l. Falls
Creek is closed to all salmon fishing. Rainbow trout (Oncorhynchus mykiss) are limited to one
fish less than 16 inches long per day. Dolly Varden fishing is limited to one fish less than 16
inches long per day 1• Current sport fishing effort is unknown.
Previous investigators suggested that Falls Creek may have limited salmon spawning potential in
its anadromous reach due to low water temperatures that may limit its production; this was
supported by a lack of observations of spawning salmon during week-long field visits in October
1981 and March, May, June, and August 1982 (AEIDC 1982 and 1983) and "frequent" stream
surveys during late summer 1959 and 1960 when salmon were running in adjacent streams
(USFWS 1961 ). Instream cover available to juvenile fish consists of debris jams and a few
cutbank meanders (AEIDC 1982). Local residents have reported that salmon spawning did
(AIEDC 1983) and did not (USFWS 1961) occur in Falls Creek. Seward ADFG biologist T.
McHenry also reported that salmon spawn in lower Falls Creek (pers. comm. in AIEDC 1983).
In minnow trapping from August 1959 through January 1961, juvenile Chinook were only
caught in the lower 200 yards of the stream, though traps were set from the mouth to one mile
upstream (February through April and December not sampled; USFWS 1961). Dolly Varden,
including juveniles, were caught throughout the sampling area. Coastrange sculpin (Coitus
aleuticus) and slimy sculpin (Cottus cognatus) were caught during August (USFWS 1961).
Investigators sampling fish in Falls Creek from 1981 to 1982, caught less species than in 1959-
1961. Minnow trapping from the mouth of Falls Creek to the area just below the active mine
(October 1981; March, May, June and August 1982) only Dolly Varden were caught in Falls
Creek. Dolly Varden were caught throughout the creek including in the area just below the
active mine. These fish were caught during all months sampled except March and May 1982; in
winter, Falls Creek was frozen solid and provided no overwintering habitat (AIEDC 1983).
Wetlands
No detailed wetland information exists in historical reports for the Falls Creek area. No
additional investigation of wetlands was performed for the purposes of this feasibility report.
Data regarding wetlands resources in the project area are available from the National Wetlands
Inventory (NWI) mapping system; evaluation of this database was outside the scope of this
reconnaissance-level report.
1 http://www.sf.adfg.state.ak.us/statewide/regulations/southcentrai/SCkenai.pdf
3
Hydrology and Water Quality
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report
Continuous streamflow data was collected from May to October 1982 as part of the Ebasco
studies (APA 1984). This streamgage was located near the mouth of Falls Creek. The average
flow during this period was 38 cfs .
Because of the short period of record at Falls Creek, long term estimates of the flow in Falls
Creek were estimated by comparison to adjacent Grant Creek which was gaged continuously by
the USGS for 11 years between 194 7 and 195 8. This gage (USGS # 15246000) was located
approximately 0.3 miles upstream of the mouth of Grant Creek. To estimate the hydrology of
Falls Creek, the mean daily flows from the Grant Creek gage for May through September were
scaled by factors determined by Ebasco (APA 1984; Table 1) to create a simulated daily flow
file. In estimating the hydrology for hydropower generation, Ebasco assumed that flows in Falls
Creek would be minimal during the months of November through April and therefore generation
would not be possible (and therefore was not estimated). Ebasco estimated the average monthly
flow for May through October to be 56 cfs (Figure 3). During these ice-free months, Falls
Creek's average monthly flow was lowest in May (8 cfs) and October (11 cfs), and highest in
mid summer (approximately II 0 cfs). Estimated flows rarely exceeded 200 cfs or dropped
below 70 cfs (Figure 4).
Water temperature in Falls Creek was generally colder than neighboring Grant Creek, ranging
from 7.0°C (12.6°F) colder in July, 1959, to 2.5°C ( 4.5°F) colder in October 1981 (APA 1984;
Table 2). Water quality of Falls Creek was typical of low-productivity Kenai Peninsula area
streams (AElDC 1982).
HDR measured stream flow and stream dimensions at Falls Creek on October 5 and October 24,
2008 (Table 3). Measurements were taken at a site approximately 100 ft downstream of the
Seward Highway Bridge, using standard USGS gauging protocols. Falls Creek modeled
discharge data were compiled with field measurements from 2008; field-measured values fell
within the expected range of modeled values (Figure 5).
Recreation
The Kenai Peninsula supports significant tourism from residents of the region, of Anchorage, of
Alaska and from outside of Alaska. Kenai Peninsula Borough Coastal Management Plan (KPB
2008) includes the lower portion of Falls Creek as a designated recreation use area.
The U.S. Forest Service (USFS) administers Chugach National Forest, which surrounds most of
the project area; Falls Creek is located within the Seward Ranger District. Peak use of area
campgrounds (Table 4) coincides with salmon runs (APA 1984). Total recreational use of
Seward Ranger District campgrounds in 1981 was estimated at 442,400 recreation visitor days
(RVDs), representing 40% of 1.1 million total RVDs for the entire Chugach National Forest
(APA 1984).
The project area is not developed for recreation, with the exception of a primitive route (not
maintained by USFS) to mining claims on Falls Creek. USFS-maintained trails of the Kenai
Peninsula are shown in Table 5. The USFS has plans for the Iditarod Trail in the local area, and
4
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report
the location of these proposed improvements will need to be identified in future work. More
detailed information assessing recreational use of the project and adjacent areas is needed in
order to comply with requirements of the Federal Energy Regulatory Commission (FERC)
license application. Detailed user data are available upon request from the USFS.
The project area receives unknown levels of recreational use such as hunting, recreational
mining, hiking, backpacking and camping, mostly in spring and summer. Actual use of the Falls
Creek area in the 1980s was limited to snow machining and horseback riding (AIEDC 1983).
Snowmobiles continue to utilize the area in winter. The project lies within the Ptarmigan/Grant
Lake subunit of Chugach National Forest for backcountry motorized winter use, and receives
very little use from any winter user group (motorized or non-motorized; Meade 2006).
Helicopter skiing is also permitted in the Ptarmigan/Grant Lake subunit (Meade 2006). Game
animals present in the area are likely the same as those present at Grant Lake: mountain goat,
black bear, brown bear, Dall sheep, and moose (APA 1984). The USFWS (1961) reported that
Falls Creek received no fishing pressure; AIEDC (1982) found evidence of sport fishing at the
confluence of Falls Creek with Trail River.
Subsistence, Cultural and Historical Resources
Subsistence
Falls Creek and the surrounding areas are not designated a subsistence use area by the Kenai
Peninsula Borough Coastal Management Plan (KPB 2008). Qualified residents of Cooper
Landing may harvest moose in game units 7, 15A and 15B on the Kenai Peninsula under Federal
subsistence regulations2 (Falls Creek is located in game unit 7.) Federally-qualified subsistence
users of Cooper Landing are also allowed to take salmon through a dip net/rod-and-reel fishery,
and lake trout, Dolly Varden, and rainbow trout in the Kenai River through a rod-and-reel
fisher/. A more detailed analysis of subsistence uses of the project area will be required by
FERC licensing and other permitting processes.
Cultural and historic resources
Based on a preliminary investigation of Alaska Heritage Resources Survey (AHRS) data at the
State Office of History and Archaeology, 65 cultural resource sites have been documented in the
general vicinity of Grant Lake, Falls Creek, and Ptarmigan Lake. Several of the sites are listed
on or eligible for the National Register of Historic Places. Most cultural resource sites are
located along Upper and Lower Trail lakes and Trail River. Several mining-related sites are
located in the area between Falls Creek and Grant Lake. A more detailed review of cultural and
historic resources of the project area will be necessary to comply with requirements ofthe FERC
license application process.
2 http://alaska.fws.gov/asm/newsrel/r050208.html
3 http://alaska.fws.gov/asm/newsrel/r0511 07.html
5
Falls Creek--Proposed Hydroelectric Project
Reconnaissance Report
Land Ownership, Mining Claims, and Water Rights
HDR researched public land, private holdings, mineral claims and water rights of the Falls Creek
area using information from Alaska Department of Natural Resources (DNR) land status maps4
and case file abstracts 5, the Bureau of Land Management (BLM)6, the State Recorder's Office7
and Kenai Peninsula Borough8 .
All lands on which project facilities would be located are under either State or Federal ownership
(Figure 6). No private lands are known to overlap with project facility footprints. Private
property (33 parcels; Figure 7) is located along the Seward Highway and the lower portion of the
Falls Creek access route.
Falls Creek is used extensively for placer mining during summer months (APA 1984; also seen
during HDR site visits in 2008). Land adjacent to Falls Creek is almost continuously claimed for
placer mining from 1,300 ft elevation to the mouth for the creek. Mining claims are located both
along Falls Creek and on hillsides of the drainage (15 federal mining claims and four state
mining claims within the project area). Several of these claims were seen during site visits and
are located in the vicinity of the preferred intake site (Figure 7; see Appendix A for more
information).
A search of official records found that the Falls Creek project area contains one subsurface water
right at its far west end (Figure 7). APA (1984) noted that several cabins were located within 2
miles of the mouth of Falls Creek and operated under USFS special use permits; water was likely
carried in from outside the project vicinity. A water right of 1 cfs was reported (for placer
mining on Falls Creek at 1200 ft elevation; APA 1984).
Project Arrangement
This section of the report describes arrangement of a project for hydroelectric generation at Falls
Creek. Two project alternatives were evaluated for Falls Creek:
• The alternative described in this report would be a stand-alone project that would
discharge its water back into Falls Creek. This project would be run of the river because
the Falls Creek basin is to steep to create a significant amount of storage.
• Another project alternative (described in the Grant Lake Reconnaissance Report; HDR
2009) would divert water from Falls Creek north to Grant Lake, where water would be
4 http://mapper.landrecords.info/
5 http://dnr.alaska.gov/projects/las/lasmenu.cfin
6 http://sdms.ak.blm.gov/sdms/
7 http://dnr.alaska.gov/ssdlrecoff/search.cfin
8 http://www .borough.kenai.ak.us/assessingdept/
6
Fails Creek-Proposed Hydroelectric Project
Reconnaissance Report
used to generate power from the Grant Lake project. This alternative has the advantage
of using Grant Lake for storage.
Project Description
The intake for Falls Creek would be located at approximately the 800 ft elevation (Figure 8).
Water would be conveyed to the powerhouse via a 40-inch diameter 5,000-foot-long above
ground steel penstock supported on concrete saddles. The powerhouse would be located at
approximately elevation 500 and would contain a single Turgo-type turbine, synchronous
generator and associated switchgear and controls. A new 0.25-mile access route to the
powerhouse would branch from an existing route which begins near the downstream end of
Lower Trail Lake. The access route to the intake would use an upgraded existing mining route,
with only a short spur needed to the intake. An overhead transmission line would following the
powerhouse access route.
Key project parameters are presented in Table 6 below. Maximum headwater elevation would
be 800ft, with a minimum headwater of 500 ft. Tailwater elevation would also be at 500 ft
(powerhouse located alongside Falls Creek). Net head for this run-of-the-river project would be
approximately 245 ft. Design flow was I 05 cfs, resulting in a capacity of 1.8 MW (see Turbine
Sizing below). Average inflow was estimated to be 56 cfs (Table 6).
For determining turbine size, the rated flow of the turbine was sized at 15% on the flow duration
curve for the months the project would be in operation. This resulted in a design flow of 105 cfs,
and a capacity of 1.8 MW. A sensitivity analysis indicated that design flows within 10% of this
assumption yield near identical energy generation estimates, demonstrating that this assumption
was appropriate for this level of study.
Energy Generation
The energy generation for Alternative 1 was estimated using HDR's proprietary software
"Hydroelectric Evaluation Program" (HEP). HEP is specifically designed to model run-of-river
operations. HEP uses tabulated daily flows, turbine and generator efficiencies, friction
coefficients and physical parameters to simulate ·energy production for a period of stream flow
record. Turbine and generator efficiencies are determined from tables. Output from HEP
consists of effective capacity rating of the unit(s), simulated production in MWh, percent
operating time and overall plant factor.
The following assumptions were used in modeling energy production:
• The project would not operate during the months of November through April
• All available flow was used for energy production. There was no minimum instream
flow release in the bypass reach of Falls Creek.
Using these assumptions the average annual energy generation was estimated at 3,900 MWh
corresponding to an annual plant factor (the average percentage of full capacity used over a
7
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report
given period of time) of 24%. Plant factor was very low because the project would be shut down
due to low flows approximately 223 days per year (see Appendix B , Energy Calculations).
Cost Estimates
An opinion of probable construction costs was derived for the project presented above. The
approach used was to develop base work units and unit prices and then apply these units and
prices consistently to the various project features.
Assumptions
The following assumptions were used in the cost estimate:
• Indirect construction costs associated with engineering, construction management,
licensing, permitting and the owner's internal costs were added to the direct construction
cost estimate as either percentages or lump sum amounts.
• Design engineering was assumed to be 10% of the total direct construction costs.
• A lump sum value of $1,000,000 was assumed to provide environmental baseline studies
in support of the FERC licensing application. As well as preparation for the FERC
licensing application.
• The Owner's General Administration and Overhead of the design and construction was
assumed to be 5% of the total direct construction costs.
• Construction management was assumed to be 5% of the total direct construction costs.
• A contingency of 30% was added to the total of the direct and indirect construction costs
to reflect uncertainties of layout and design that wouldn't be resolved until later in the
development process.
• Interest accrued during a 3-year construction period was assumed to be 7% and was
added to the total of the direct and indirect construction costs.
• The estimate assumed first-year operations and maintenance (O&M) expense were
comprised of the following three expenses
o Total labor, expenses and owner's general and administrative (G&A) expenses
were estimated at $300,000/yr9 •
9 The estimated G&A expense could be reduced if several of the sites investigated are
constructed which would allow some economies to be realized between the similar
operations ofthe hydroelectric projects.
8
Falls Creek~ Proposed Hydroelectric Project
Reconnaissance Report
o A repair and replacement fund of $50,000 was also included.
o General liability and business interruption insurance was estimated at $1.00 per
$100.00 of asset.
• Cost estimates assumed that the project would be designed for un-manned operations and
would be part of a larger organization; thereby the project would experience lower
administrative expenses. On-site O&M labor would be limited to periodic inspections
and seasonal maintenance.
Results
It is estimated that a run-of-river project on Falls Creek would cost $17.3 million in 2008 dollars
(see Appendix C, Cost Information).
Economic Evaluation
A detailed economic evaluation was not included in the scope of this work. However, in order to
provide a conceptual view ofthe economics, we have made some general assumptions. We have
chosen to present the results as estimated annual cost per kilowatt-hour (kWh) in 2008 dollars.
In deriving these costs, we assumed that the project could be financed through the issuance of
bonds. Our assumption was that 100% of the debt would be financed at 6% for 30 years. Using
these assumptions, the stand alone project would have a 2008 price of energy of $0.451 per kWh.
Conclusions and Recommendations
The stand-alone project alternative evaluated in this report has an estimated 2008 price of energy
of $0.451 per kWh. This cost is high compared to other generation options available to KHL.
The cost is high primarily because there is no storage available within the basin and because the
plant would be shutdown for 60% of the year. The second alternative which would divert water
from Falls Creek north to Grant Lake, where water would be used to generate power from the
Grant Lake project was reviewed as part of Grant Lake feasibility studies (HDR 2009), and may
be a more feasible option than a stand-alone project at Falls Creek.
9
Falls Creek Proposed Hydroelectric Project
Reconnaissance
References
Alaska Department of Natural Resources (DNR). 1998. Kenai River Comprehensive
Management Plan. Rep. from Division of Land and Division of Parks and Outdoor
Recreation in conjunction with Alaska Department of Fish and Game, Habitat and
Restoration Division, and Kenai Peninsula Borough. Anchorage, Alaska.
Alaska Power Authority (APA). 1984. Grant Lake Hydroelectric Project Detailed Feasibility
Analysis. Volume 2. Environmental Report. Rep. from Ebasco Services Incorporated,
Bellevue, Washington.
Arctic Environmental Information and Data Center (AEIDC). 1982. Preliminary summary of
environmental knowledge of the proposed Grant Lake hydroelectric project area.
Interim report submitted to Ebasco Services, Inc., Redmond, Washington, University of
Alaska, Anchorage, Alaska.
Arctic Environmental Information and Data Center (AEIDC). 1983 Summary of environmental
knowledge of the proposed Grant Lake hydroelectric project area. Final Report
submitted to Ebasco Services, Inc., Redmond, Washington, University of Alaska,
Anchorage, Alaska.
Buchanan, T.J., and Somers, W.P. 1969. Discharge measurements at gauging stations. In
Chapter A8, Book 3, Techniques of water resources investigations of the United States
Geological Survey.
CH2M Hill. 1980. Feasibility assessment-hydropower development at Grant Lake. City of
Seward, AK.
HDR Alaska, Inc. (HDR). 2009. Grant Lake proposed hydroelectric project draft
reconnaissance report. Submitted to Kenai Hydro, LLC.
Johnson, J. and M. Daigneault. 2008. Catalog of waters important for spawning, rearing, or
migration of anadromous fishes Southcentral Region, Effective June 2, 2008. Alaska
Department of Fish and Game, Special Publication No. 08-05, Anchorage, Alaska.
Kenai Peninsula Borough (KPB). 2008. Coastal management plan. Effective June 2008.
Meade, J. 2006. Draft environmental impact statement: Kenai winter access. United States
Department of Agriculture, Forest Service, Alaska Region, Chugach National Forest.
Anchorage, Alaska
Plafker, G. 1955. Geologic investigations of proposed power sites at Cooper, Grant, Ptarmigan,
and Crescent Lakes, AK. U.S. Geological Survey Bulletin 1 031-A. U.S. Government
Printing Office, Washington D.C.
10
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report
Quilliam, R. 1982. Personal communication. 1982. Resource Assistant, U.S. Department of
Agriculture, Forest Service, Chugach National Forest, Seward, AK.
R. W. Beck and Associates. 1982. Kenai Peninsula power supply and transmission study
supplement.
U.S. Fish and Wildlife Service (USFWS). 1961. Ptarmigan and Grant Lakes and Falls Creek,
Kenai Peninsula, Alaska, progress report on the fish and wildlife resources. Department
of the Interior. Juneau, Alaska.
U.S. Geological Survey (USGS). 1981. Surface water quality records, Southcentral Alaska,
1949-1974. Unpublished computer printout.
11
Tables
12
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report-Tables
Table 1. Falls Creek scale factors
(determined by APA 1984) used to
simulate flow of Falls Creek from
stream flow data collected at Grant
Creek.
Month Scale factor
October 6.2%
November 0
December 0
January 0
February 0
March 0
April 0
May 5.2%
June 24.2%
July 21.2%
August 14.6%
September 13.4%
13
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report-Tables
Table 2. Temperature comparisons for Grant Lake, Grant Creek and Falls Creek. Adapted
from Table 2-8 in APA (1984). Values for Grant Lake were surface temperatures.
Temperature
difference
between
Falls Grant Lake
Grant Grant Cr. and Grant Cr
Date Source Lake CF} Cr. {°F} {oF} {oF}
111311959 USFWS (1961) 39.9 32.5
6/8/1960 " " 46.0 41.0
6/1711960 " " 53.1
7/2011960 " " 53.1 52.0 41.0 1.1
8/811960 " " 55.0 52.0 3.1
8/1311960 " " 52.0 51.1 44.1 0.9
9/111960 " " 50.0 42.1
9/1411960 " " 48.9 41.0
10116/1930 " " 44.1 42.1 36.0 2.0
1011311981 AIEDC ( 1982) 45.0 42.8 38.3 2.2
3/2/1982 " " 35.6 33.8 1.8
6/911982 " " 43.9 43.7 39.2 0.2
8/311982 " " 57.2 54.5 41.9 2.7
Average Temperature
Difference {°F} 1.7
Table 3. 2008 instantaneous flow measurements collected at
Falls Creek by HDR staff, October to December 2008.
Date
10/5/2008
10/24/2008
Instantaneous
discharge (cfs)
22.1
13.9
14
Stream width (ft)
19.1
16.7
Temperature
difference
between
Grant Cr.
and Fails Cr.
11.0
7.0
6.1
4.5
4.5
12.6
7.6
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report-Tables
Table 4. USFS campgrounds on the Kenai Peninsula.
Location Number of sites
Cooper Creek 26
Crescent Creek 9
Porcupine Creek 24
Primrose Creek 10
Ptarmigan Creek 16
Quartz Creek 45
Russian River 84
Table 5. USPS-maintained trails on the Kenai Peninsula.
Location Length (mi)
Carter Lake 3.5
Crescent Creek 6.4
Devil's Pass 10
Grayling Lake 1.5
Gull Rock 5.1
Hope Point 2.5
Johnson Pass 23
Lost Lake 7.5
Primrose 7.5
Ptarmigan Creek 7.1
Rainbow Lake 0.24
15
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report-Tables
Table 6. Parameters for the project arrangement
considered for Falls Creek. Elevations of maximum
headwater (HW), minimum HW, tailwater elevation
and net head (in feet) are given for each alternative.
Design flow ( cfs ), capacity (MW), average inflow
(cfs), and active storage are detailed for the project.
Parameter Value
Max. HW, ft 800
Min. HW, ft 800
Tailwater, ft 500
Net Head, ft 245
Design Flow, cfs 105
Capacity, MW 1.8
Avg. Inflow, cfs 56
Active Storage, AF 0
16
Figures
17
~·~
~
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Figures
K.nal Hydro FacUlty I --
Siting Project -=---lill ----~ ---Propoud I o------··~--
Project Stucly At.a c:::::J-·-...... ...... _
Figure 1. General location of proposed hydroelectric facilities at Falls Creek on the Kenai Peninsula, Alaska. ·
18
Falls Creek-Proposed Hydroelectric Project
Reconnaissance ·Report -Figures
Proposed Project Study Area
-stream
............._ Anadnomous
Reach
Land St.llue
• Alaeka Railroad
0Chugath NF
1:0:1 St.lla of Alaska
OPrtvate ~
Miles 'lJ'
0 0 ·25 0·5 HOR Alalko, Inc.
December 2008
Figure 2. The anadromous reach of Falls Creek. The anadromous reach is defined as the section of stream in which anadromous fis~
are documented by the A WC; Johnson and Daigneault 2008).
19
-~
() -3:
0
LL.
120 -,-
100
80
60
40
20 11
Falls Creek -Proposed Hydroelectric Project
Reconnaissance Report -Figures
Falls Creek Mean Monthly Flows 108 110
56 cfs mean
0 I -+-I -i
OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP
Figure 3. Mean monthly discharge of Falls Creek, modeled using data from USGS gage
15246000 (1947-1958) at Grant Creek, adjusted by monthly ratios developed by Ebasco (APA
1984; using one open water season of flow data. at Falls Creek). Average annual flow (for
period of record 1947-1958, from USGS gauge #5246000) is shown as a solid horizontal line (56
cfs).
500
Falls Creek Flow Duration
400
:§' 300
() -3:
~ 200
100
a t-~--~--~--~--~~==~~~==~~
0 10 20 30 40 50 60 70 80 90 100
% Exceedance
Figure 4. Flow duration curve for Falls Creek. Percent exceedence, the value of the x-axis, is
the percent of the time flow surpasses the value on the y-axis. This curve was generated using
modeled data from USGS gage 15246000 (1947-1958) at Grant Creek, adjusted by monthly
ratios developed by Ebasco (APA 1984; using one open water season of flow data. at Falls
Creek).
20
200
180
160
140 -Daily Mean -'t:i 120 -Manual Measurements, 2008 -(I)
e' 100 tU ..c.
0
(/) 80 i5
60
40
20
0
,"-.
';:,q,.<:'
,"-~'):J ~'"':> ,t;..
<.:.~ ~1> ~ ~~
Falls Creek
Modeled Discharge
Pt 5':>
'::JVJ."" ';:,.s-~ t;E~
~v
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report-Figures
• • --,----,
~~ ~ro ~ro ~
C:>Qj~ ov ~0 <::)0J
Figure 5. Falls Creek modeled discharge based on data from USGS gauge 15246000 (1947-1958) at Grant Creek, adjusted by
monthly ratios developed by Ebasco (AP A 1984) using one open water season of current flow data. Mean discharge is shown by a
heavy blue line in cubic feet per second. Manually collected instantaneous stream flow measurements collected in 2008 by HDR
Alaska are shown as black dots.
21
Falls Creek -Proposed Hydroelectric Project
Reconnaissance Report -Figures
LAND STATUS I
KPB Parcels
..,.__z
F·~__ ..........__
legend
Q Poajol-2
c:::J ioo-...-
-~~~~-.....-..... -110-~1-4
-120AnidoftlioiC.. -130--H-
-131--IIIIpOniJ
c::J IIIO-"""""""'IIIdg -3011--
-33&1J1dgo -IUiplo CoMa
---CooniMn:iol --c-.---,llldg -820-----a...v. -~~~~--..,----
-~ a. ... -
Piojlal-2 (~--> ;
~ 01 April20011
J.Aa:l«lR~
-AllNt ICPB. GINA. USFS
lill
Figure 6. Private parcels of Falls Creek area. State and Federal lands are shown by yellow. Private properties are denoted other
colors.
22
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report-Figures
LAND STATUS
Water Rights
&
Mineral Estate '
PrajectAIU2
F*COBM...,_ --l!oftlugll.-
Legend
.. State Mining Claim
.. Federal Mining Claim
• Surface Water Right
• Subsurface Water Right
GJ Projet Area 2
.. Lake/Pond
2i> lceMass
Prqocl -2 (-2,500 ..... )
~
~--L.. __ _JMiles
0 0.5 1
o.e: 22 ~ 2008
-t«lR eng;r.mg s.un:.: ADNR , KPB , GINA
lil\
Figure 7. Water rights and mineral claims in the Grant Lake area. Federal mining claims are shown by yellow shading. Aqua
shading denotes state mining claims.
23
-""'-
~-~~HR
\. H'§R Alaska , Inc.
···-~V''
Falls Creek -Proposed Hydroelectric Project
Reconnaissance Report -Figures
KHL SITE EVALUATION
PROJECT OPTION DESCRIPTIONS
FALLS CREEK
Oato
Dec 2008
Figure 8. Proposed project arrangement at Falls Creek for the stand alone option. Location of
intake at approximately elevation 800 ft, possible penstock route, powerhouse location and
proposed access routes are shown above.
24
Appendix A -Land Status Information
25
PARCELID TAXAREA USEAGE ACREAGE Ll:l.:iAL OWNER ADDREsS
T 4N R 1W SEC 13 SEWARD MERIDIAN
12532421 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 6 SW GOVT LOT 8 ALASKA STATE D N R 550 W 7TH AVE STE 650
T 4N R 1W SEC 13 SEWARD MERIDIAN
12532422 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 36 SWGOVTLOT9 ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1W SEC 13 SEWARD MERIDIAN
12532423 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 1 SW GOVT LOT 10 ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1W SEC 13 SEWARD MERIDIAN
12532424 67-KPB ROAD MAINTENANCE 131 Mobile Home Imp Only 9 SW GOVT LOT 11 ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1E SEC 3 SEWARD MERIDIAN
SW SECTIONS 3 & 4 & 8 THROUGH 17 &
20 THROUGH 26 & 32 & 36 & PORTIONS
OF SECTIONS 1 & 2 & 5 EXCLUDING
GRANT LAKE & PORTIONS OF
SECTIONS 27 & 28 & 29 & 33 & 34 & 35
EXCLUDING PTARMIGAN LAKE &
12532109 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 19,096 PORTIONS OF SECTIONS 30 & 31 E USDA FOREST SERVICE 3301 C ST STE 300
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516007 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 1 SURVEY 86-176 LOT 6 ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516008 67 -KPB ROAD MAINTENANCE 110 Residential Units 1-4 1 SURVEY 86-176 LOT 5 PFLUM TIMOTHY M 19445 POND MEADOW AVE
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516009 67 -KPB ROAD MAINTENANCE 110 Residential Units 1-4 1 SURVEY 86-176 LOT 8 BARNETT THOMAS E 3124 MADISON WAY
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516010 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 1 SURVEY 86-176 LOT 7 ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516011 67 -KPB ROAD MAINTENANCE 120 Residential Cabin 1 SURVEY 86-176 LOT 10 LYNCH SHAWN M PO BOX24
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516012 67 -KPB ROAD MAINTENANCE 110 Residential Units 1-4 1 SURVEY 86-176 LOT 9 HANLEY JAMES P 3910 W 37TH CT
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516013 67-KPB ROAD MAINTENANCE 110 Residential Units 1-4 1 SURVEY 86-176 LOT 12 ROTGABER GEORGE E PO BOX 164
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516014 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 1 SURVEY 86-176 LOT 11 ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0910009 ALASKA STATE LAND
12516015 67-KPB ROAD MAINTENANCE 1 00 Residential Vacant 0 SURVEY 86-6 TRACT B (ADL 217604) ALASKA STATED N R 550 W 7TH AVE STE 650
T 4N R 1E SEC 18 SEWARD MERIDIAN
12516018 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 10 SW 0000000 US SURVEY 8666 LOT 2 UNITED STATES BLM 222 W 7TH AVE STOP 13
T 4N R 1W SEC 13 SEWARD MERIDIAN
12516019 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 8 SW 0008666 US SURVEY 8666 LOT 1 UNITED STAlES BLM 222 W 7TH AVE STOP 13
T 4N R 1W SEC 13 SEWARD MERIDIAN
12516020 67 -KPB ROAD MAINTENANCE 105 Residential Improved Lam 2 SW 0008666 US SURVEY 8666 LOT 3 UNITED STAlES BLM 222 W 7TH AVE STOP 13
T 4N R 1W SEC 13 & 24 SEWARD
MERIDIAN SW US SURVEY 7391 LOT 2
EXCLUDING THAT PTN AS PER ARRC
12514101 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 81 6043 ALASKA RAILROAD CORPORAl! ON PO BOX 107500
T 4N R 1W SEC 24 SEWARD MERIDIAN
SW USS 7391 THAT PORTION OF LOT 2
12514103 67 -KPB ROAD MAINTENANCE 651 Leased Commercial __ , 0 AS PER ARRC 6509 ALASKA RAILROAD CORPORATION PO BOX 1 07500
------
26
CITYSTATE
ANCHORAGE, AK 99501
ANCHORAGE, AK 99501
ANCHORAGE, AK 99501
ANCHORAGE, AK 99501
ANCHORAGE, AK 99503
ANCHORAGE, AK 99501
BEND, OR 97702
ANCHORAGE, AK 99508
ANCHORAGE, AK 99501
MOOSE PASS, AK 9963
ANCHORAGE, AK 99517
MOOSE PASS, AK 996:1
ANCHORAGE, AK 99501
ANCHORAGE, AK 99501
ANCHORAGE, AK 99513
ANCHORAGE, AK 99513
ANCHORAGE, AK 9951?
ANCHORAGE, AK 99510
ANCHORAGE, AK 99510
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report-Appendix A Land Status
LANDVAL IMPVAL ASSESSED TAXABLE PLAT
$100,600 $0 $100,600 $0 STATE
$312,800 $0 $312,800 $0 STATE
$17,600 $0 $17,600 $0 STATE
$52,100 $0 $52,100 $0 STATE
$11,457,600 $0 $11,457,600 $0 FEDERAL
$13,800 $0 $13,800 $0 STATE
$13,800 $53,300 $67,100 $67,100 PRIVATE
$13,900 $11,800 $25,700 $25,700 PRIVATE
$12,700 $0 $12,700 $0 STATE
$12,500 $22,900 $35,400 $15,400 PRIVATE
$13,600 $62,000 $75,600 $75,600 PRIVATE
$12,700 $27,300 $40,000 $40,000 PRIVATE
$11,300 $0 $11,300 $0 STATE
$8,900 $0 $8,900 $0 STATE
$57,700 $0 $57,700 $0 FEDERAL
$70,200 $0 $70,200 $0 FEDERAl
$48,600 $1,000 $49,600 $0 FEDERAl
$252,500 $0 $252,500 $0 STATE
$13,000 $8,900 $21,900 $21,900 STATE
PARCELID TAXAREA USEAGE ACREAGE LC\:IIU. OWNER
T 4N R 1W SEC 13 & 24 SEWARD
MERIDIAN SW FALLS CREEK GROUP
12515001 67-KPB ROAD MAINTENANCE 110 Residential Units 1-4 5 US SURVEY 2519 LOT K (HS R1) LINDQUIST GARY V & JULIE R
T 4N R 1W SEC 24 SEWARD MERIDIAN
SW 0000000 FALLS CREEK GROUP U S
12515002 67 -KPB ROAD MAINTENANCE 11 0 Residential Units 1-4 5 SURVEY 2519 LOT J (HS 38) MERRITT WILLIAM T JR & JUDY L
T 4N R 1W SEC 24 SEWARD MERIDIAN
SW 0002519 FALLS CREEK GROUP OF
HOMESITE-USS 2519 LOT I THAT
PORTION BEGINNING AT THE
NORTHEAST CORNER OF LOT I
PROCEED WEST 361.68 FT TH
SOUTHERLY ALONG THE EAST BANK
OF TRAIL RIVER 78 FT TO THE BANK OF
12515006 67 -KPB ROAD MAINTENANCE 11 0 Residential Units 1-4 1 A SLOUGH TH VIT ARIS CLIFFORD R & KATHLEEN A
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516003 67 -KPB ROAD MAINTENANCE 120 Residential Cabin 1 SURVEY 86-176 LOT 2 BARTOLINI TONY
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516004 67-KPB ROAD MAINTENANCE 120 Residential Cabin 1 SURVEY 86-176 LOT 1 KROMREY MARK T & KAREN L
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516005 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 1 SURVEY 86-176 LOT 4 ALASKA STATED N R
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516006 67 -KPB ROAD MAINTENANCE 120 Residential Cabin 1 SURVEY 86-176 LOT 3 CARTER LARRY JAMES (JIM) LIVING TRUST
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
SURVEY 86-176 TRACT A EXCEPT ASLS
12516022 67-KPB ROAD MAINTENANCE 100 Residential Vacant 37 86-6 ALASKA STATED N R
T 4N R 1W SEC 13 SEWARD MERIDIAN
SW 0880002 ALASKA STATE LAND
12516023 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 45 SURVEY 86-176 LOT 1-A ALASKA STATED N R
T 4N R 1 E SEC 7 SEWARD MERIDIAN
SW GOVT LOTS 1 THRU 7 & E1/2 &
12532102 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 560 NE1/4 NW1/4 ALASKA STATED N R
T 4N R 1E SEC 18 SEWARD MERIDIAN
SW GOVT LOTS 1 THRU 5 & E1/2 & E112
12532103 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 544 NW1/4 & NE1/4 SW1/4 ALASKA STATED N R
T 4N R 1E SEC 19 SEWARD MERIDIAN
SW GOVT LOTS 1 THRU 4 & E1/2 & E1/2
12532104 67 -KPB ROAD MAINTENANCE 100 Residential Vacant 605 W1/2 ALASKA STATED N R
T 4N R 1W SEC 24 SEWARD MERIDIAN
12532401 67 -KPB ROAD MAINTENANCE 1 00 Residential Vacant 43 SWGOVT LOT 1 ALASKA STATED N R
27
ADDRESS ci1YSTATE
31087 SEWARD HWY SEWARD, AK 99664
POBOX 172 MOOSE PASS, AK 9963
30919 SEWARD HWY SEWARD, AK 99664
8901 E RAVENDALE DR PALMER, AK 99645
PO BOX68 MOOSE PASS, AK 9963
550 W 7TH AVE STE 650 ANCHORAGE, AK 99501
3804 ARKANSAS DR ANCHORAGE, AK 99517
550 W 7TH AVE STE 650 ANCHORAGE. AK 99501
550 W 7TH AVE STE 650 ANCHORAGE, AK 99501
550 W 7TH AVE STE 650 ANCHORAGE, AK 99501
550 W 7TH AVE STE 650 ANCHORAGE, AK 99501
550 W 7TH AVE STE 650 ANCHORAGE, AK 99501
550 W 7TH AVE STE 650 ANCHORAGE, AK 99501
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Appendix A -Land Status
LANDVAL IMPVAL ASS!:SSED TAXABLE PLAT
$54,400 $188,700 $243,100 $223,100 PRIVATE
$39,100 $110,300 $149,400 $129,400 PRIVATE
$20,300 $108,200 $128,500 $108,500 PRIVATE
$17,400 $16,200 $33,600 $33,600 PRIVATE
$17,400 $22,800 $40,200 $40,200 PRIVATE
$17,000 $0 $17,000 $0 STATE
$17,600 $1,000 $18,600 $18,600 PRIVATE
$277,600 $0 $277,600 $0 STATE
$233,800 $0 $233,800 $0 STATE
$423,100 $0 $423,100 $0 STATE
$411,200 $0 $411,200 $0 STATE
$296,500 $0 $296,500 $0 STATE
$35,600 $0 $35,600 $0 STATE
PARCEL ID TAXAREA USEAGE ACREAGE LEGAL
AK932 EW 21 S 4N 1E 9 SE
AKAA 055112 21 S4N1E21NE
AKAA 076796 7 S4N 1W24 NE
AKAA 030237 22 S4N 1E21 NE
AKAA 076794 21 S4N1E16NW
AKAA 055109 21 S 4N 1E 16 SE
AKAA 055111 21 S 4N 1E 21 NE
AKAA 076795 4 S4N 1W 13 SW
AKAA 030239 21 S4N 1E 17 SW
AKAA 087532 21 S4N 1E 16SE
AKAA 055107 21 S 4N 1E 21 NE
AKAA 031337 21 S4N1E16NW
AKAA 055110 21 S 4N 1E 16 SW
AKAA 055113 21 S 4N 1E 16 SE
AKAA 055108 21 S4N 1E 16
AKAA 055114
OWNER ADDRESS CITYSTATE LANDVAL
------
28
IMPVAL ASSESSED
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report -Appendix A -Land Status
TAXABLE PlAT!
Appendix B -Energy Calculations
29
Falls Creek Alaska POWER GENERATION
DATA FILE USED: FALLS.QCH
MODEL DESCRIPTION
PIPE # LENGTH DIAMETER MANNING'S n MINOR LOSSES
1 5000 40 .011 2
HEADWATER ELEV: 800
TAILWATER ELEV: 500
GROSS HEAD: 300
NET HEAD@ FULL LOAD: 245.2
NAMEPLATE CAPACITY (kW): 1831.6@ 1 POWER FACTOR
STATION SERVICE LOSS: 1
TRANSFORMER LOSS: 1
TRANSMISSION LOSS: 1
SCHEDULED DOWN TIME: 1
TURBINE SELECTED: 1 -TURGO-GENERAL
GENERATOR SELECTED: GE
30
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report -Appendix B-Energy Calculations
MINIMUM INSTREAM FLOWS
OCT NOV DEC JAN FEB MAR APR
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Appendix B -Energy Calculations
MAY JUN JUL AUG SEP
------------------------------------------------------------------------------------------------
0 0 0 0 0 0 0 0 0 0 0 0
SIMULATED PRODUCTION IN MEGAWATT-HOURS
YEAR OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP TOTAL
---------------------------------
1948 197.8 0.0 0.0 0.0 0.0 0.0 0.0 142.7 1224.7 1297.2 799.4 275.5 3937.2
1949 174.8 0.0 0.0 0.0 0.0 0.0 0.0 79.3 1156.6 1236.9 680.9 790.5 4119.1
1950 110.2 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1054.0 1275.2 976.5 630.3 4046.2
1951 8.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1022.7 1245.6 788.0 919.2 3983.9
1952 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1019.6 1287.6 885.7 496.0 3688.9
1953 282.1 0.0 0.0 0.0 0.0 0.0 0.0 153.6 1266.0 1308.2 996.4 542.4 4548.7
1954 167.3 0.0 0.0 0.0 0.0 0.0 0.0 60.2 1189.6 1168.4 795.1 368.0 3748.5
1955 70.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 889.8 1301.1 815.2 482.1 3558.4
1956 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 870.1 1235.1 927.7 393.3 3426.2
1957 0.0 0.0 0.0 0.0 0.0 0.0 0.0 68.8 1188.3 1040.3 774.2 845.0 3916.5
1958 126.8 0.0 0.0 0.0 0.0 0.0 0.0 36.7 1245.1 1209.6 848.5 269.6 3736.3
AVERAGE 103.4 0.0 0.0 0.0 0.0 0.0 0.0 49.2 1102.4 1236.8 844.3 546.5 3882.7
AVERAGE PLANT FACTOR: 0.24
AVG. # DAYS/YEAR SHUTDOWN DUE TO LOW WATER: 223
31
THIS SIMULATION USED THE FOLLOWING EQUIPMENT EFFICIENCIES
% LOAD TURBINE GENERATOR COMBINED
--------
0 0.0 0.0 0.0
10 70.1 92.8 65.0
20 79.4 94.9 75.4
30 83.7 96.3 80.6
40 84.9 97.0 82.3
50 85.9 97.3 83.5
60 86.0 97.5 83.9
70 86.0 97.7 84.0
80 86.0 97.7 84.0
90 86.0 97.7 84.1
100 86.0 97.7 84.0
32
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report -Appendix B -Energy Calculations
Appendix C -Cost Information
33
Item I
330
331
.t
332
.1
.2
.3
.4
.5
.1
.2
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Appendix C-Cost Information
FALLS CREEK
OPINION OF PROBABLE COST
Alternative 1 -Run of River
I I Quanti~ I Unit I Unit Cost I Amount
LAND AND LAND RIGHTS
.1 Land Rights -Generation Plant LS $ 50,000 $ 50,000
.2 Special use permits LS $ 50,000 $ 50,000
.3 Surveying LS $ 100.000 $ 100.000
STRUCTURES AND IMPROVEMENTS
POWERHOUSE $
.1 Excavation 1000 CY $ 150 $ 150,000
.2 Concrete (incl. reinforcement) 210 CY $ 1.200 $ 252,000
.3 Metal Building 2500 SF $ 150 $ 375,000
.4 Misc. Metals LS $ 50,000 $ 50,000
.5 HVAC. Plumbing & Electrical LS $ 50,000 $ 50,000
.6 Grounding Grid LS $ 25,000 $ 25,000
. 7 Fire Protection LS $ 25,000 $ 25.000
RESERVOIRS, DAMS AND WATERWAYS
SITE WORK $
.1 Clearing/Drainage/Erosion Control LS $ 50,000 $ 50.000
DAM AND SPILLWAY $
.1 Excavation 400 CY $ 150 $ 60,000
.2 Care of Water/Diversion 1 LS $ 100,000 $ 100,000
.3 Concrete (structural) CY $ 1,200 $
.4 Concrete (mass) 400 CY $ 1,000 $ 400.000
INTAKE $
.1 Excavation 375 CY $ 150 $ 56,250
.2 Care of Water/Diversion 0 LS $ 100,000 $
.3 Trash racks 1 LS $ 50.000 $ 50,000
.4 Control GatesNalve w/operator 1 LS $ 150,000 $ 150,000
.5 Concrete (structural) 100 CY $ 1,200 $ 120,000
.6 Concrete (mass) 0 CY $ 1,000 $
. 7 Misc. Metals LS $ 25,000 $ 25.000
SLUICEWAY $
.1 Excavation 300 CY $ 150 $ 45,000
.2 Care of Water/Diversion 0 LS $ 100.000 $
.3 Sluice Gate w/operator 1 LS $ 100,000 $ 100,000
.4 Concrete (structural) 100 CY $ 1,200 $ 120,000
WATER CONDUCTORS AND ACCESSORIES
PENSTOCK $
.a Clearing 11 ACRE $ 25,000 $ 286,961
.b Steel penstock material 5000 LF $ 130 $ 650,000
.c Concrete (thrust blocks and supports) 200 CY $ 1.200 $ 240,000
.d Penstock installation 5000 LF $ 150 $ 750,000
.e Slope stabilization 0.5 Ml $ 250,000 $ 125,000
TAILRACE
.a Excavation LS $ 25,000 $ 25,000
.b Support and lining LS $ 25,000 $ 25.000
34
333
.1
.2
334
.1
.2
.3
.4
.5
335
.1
.2
336
.1
.2
.3
350
.1
352
.1
.2
.3
353
.1
.2
356
.1
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Appendix C-Cost Information
WATERWHEELS, TURBINES AND GENERATORS
Supply LS $ 810.000 $ 810.000
Install LS $ 500.000 $ 500,000
ACCESSORY ELECTRICAL EQUIPMENT
Switchgear LS $ 150,000 $ 150,000
Station Service LS $ 150.000 $ 150,000
Control Panel LS $ 250.000 $ 250,000
Conduit/wires/cables LS $ 150.000 $ 150,000
Power to intake LS $ 75.000 $ 75,000
MISC. POWER PLANT EQUIPMENT
Cooling Water System LS $ 25,000 $ 25.000
Powerhouse crane LS $ 250,000 $ 250,000
ROADS, RAILROADS AND BRIDGES
Existing road to Powerhouse and Intake 0.50 Ml $ 200.000 $ 100,000
Existing road upgrades 1.50 Ml $ 100.000 $ 150,000
Clearing/Drainage/Erosion Control LS $ 100.000 $ 100.000
LAND AND LAND RIGHTS
Land rights -transmission line LS $ 10,000 $ 10,000
STRUCTURES AND IMPROVEMENTS
(TRANSMISSION FACILITY)
Substation foundations LS $ 50.000. $ 50,000
Oil spill containment LS $ 25,000 $ 25,000
Grounding grid LS $ 10,000 $ 10,000
STATION EQUIPMENT
Main transformer LS $ 75.000 $ 75,000
Accessory switchgear equipment LS $ 350.000 $ 350,000
OVERHEAD CONDUCTORS & DEVICES
New pole line 0.50 Ml $ 750.000 $ 375.000
Total Direct Construction Costs $ 8.200,000
Design Engineering 10% $ 820.000
FERC and other licensing $ 1.000,000
Owner's General Administration & overhead 5% $ 410.000
Construction Management 5% $ 410,000
Subtotal $ 10,840,000
Contingency 30% $ 3.252.000
Interest during construction 7% $ 3.172.000
2008 Estimated Project Cost $ 17.270.000
Annual Energy. MWh 3.800
Debt Service $ 1.254.647
O&M $ 458.400
2008 Cost of Energy, $/kWh $ 0.451
35
Dam
Type
Crest Length
Max height
Crest width
Section
A
8
c
Excavation
Width
Depth
Volume
Box Intake
Length
Width
Height
Thickness. avg
Concrete volumes
Floor
Walls
Total
Excavation
Sluiceway
Length
Width
Height
Thickness. avg
Concrete volumes
Floor
Walls
Excavation
Falls Creek Proposed Hydroelectric Project
Reconnaissance Report -Appendix C Cost Iriformation
Simple concrete gravity
100ft 1300
15ft
2
length height area. sf vol. cy
50% 100% 143 264
25% 80% 96 89
25% 50% 43 40
393
45
2
333 cy
30
15
15
1.5
25 cy
75
100 cy
375 cy
30
10
18
2
17 cy
70
87
300 cy
36
PENSTOCK
Head
Flow
Vel , max
Dia , req
t , req
t , handling
t , min
wt, ft
area
Cost
Material
Lin i ng
Coati ng
Supports
Span
Length
#
W idth , 2d
Depth , .5d
Height, .5d
Vol
Th r ust Blocks
#
Width , 2d
Depth ,2d
Height, 2d
Vol
Tota l
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Appendix C-Cost Information
300ft
105 cfs
12 fps
40.1 inches
0.1447
0.1502
0 .1 502
59 .1 lbs
10 .5
$ 1 .50 l b $ 88 .59
$ 1.50 sf $ 15.73
$ 1.50 sf $ 15.73
$ 120.06
60ft
5000
83
6 .6772739
1.6693185
1.6693185
57.429176
8.3
6 .6772739
6 .6772739
6 .6772739
91 .886682
149.31586
37
Falls Creek-Proposed Hydroelectric Project
Reconnaissance Report -Appendix C Cost Information
POWERHOUSE
Powerhouse structure
Prefabricated Metal Building $150/sf)
Length
Width
Thickness
Discharge chamber
Length
Width
Depth
Thickness. avg
Concrete Volumes
Foundation
Floor
Prefab building cost
38
150
50
50
2
15
8
5
2
17.0
185.2
202.2222
375000
Excavation
1000
Appendix D -Project Photographs
39
Falls Creek -Proposed Hydroelectric Project
Reconnaissance Report -Appendix D -Project Photographs
Looking upstream at one of potential intake sites at
Falls Creek.
40
Falls Creek -Proposed Hydroelectric Project
Reconnaissance Report -Appendix D -Project Photographs
Second potential intake at Falls Creek. Proposed penstock would
exit on the left hand side of this photograph.
Aerial view of Falls Creek area.
41