HomeMy WebLinkAboutElim Pre-Reconnaissance Report 1982E:_r
001
c. 2
PRE-RECONNAISSANCE REPORT
ELIM HYDROELECTRIC PROJECT
Submitted by
00WL ENGINEERS
ANCORAGE, ALASKA
In Association with
TUDOR ENGINEERING COMPANY
SAN FRANCISCO, CALIFORNIA
DRYDEN & LARUE
ANCHORAGE, ALASKA
December 1982
for
ALASKA POWER AUTHORITY
A. INTRODUCTION
1. Background
ELIM HYDROELECTRIC PROJECT
PRE-RECON REPORT
At the request of the Alaska Power Authority a pre-reconnaissance
evaluation was made of potential hydroelectric projects in the vicinity of
Elim~ Alaska. A team composed of a hydroelectric engineer~ hydrologist and
geologist made an on-the-ground reconnaissance of two of the more favorable
sites on July 8 and 9~ 1982. A separate geologic reconnaissance report is
appended to this report.
This additional Elim reconniassance work was recommended to APA in the
11 Reconnaissanace Study for Energy Requirements and Alternatives for Kaltag,
Savoonga, White Mountain and Elim 11 , prepared by Holden & Associates, et al.
dated June 1981. The results of this work should form the basis for a
decision on whether to proceed with a feasibility study.
2. Location
The village of Elim is located on the south side of the Seward
Peninsula on the shore of Norton Sound. Nome is 95 miles to the west and
Anchorage 450 miles to the southeast. The two sites investigated on the
ground, Peterson Creek and Quiktalik Creek, are located 5 and 1.5 miles
respectively southwest of Eli m, as shown on Plate 1. The powerhouse for
eithe.r site would be located near the shore and would be accessable from
the sea during the summer or by Iditarod sled trail in winter.
B. PROJECT DESCRIPTION
1. Alternatives Studied
Two potential hydroelectric sites were selected for field investigation
NBISF-313-9528-ER 1
from a group of eight sites screened for power head and stream flow
potential. All sites are run-of-the-river with no significant storage at
the diversion weir. The sites selected are similar to 11 Plan Two 11 and 11 Plan
Four .. as set forth in the report .. Regional Inventory and Reconnaissance
Study for Small Hydropower Projects in Northwest Alaska 11
, prepared for the
Corps of Engineers by Ott Water Engineers, Inc., May 1981.
The basic hydrogeological problem in the Elim area is that drainage
basins of two or more square miles with potentially attractive water
supplies are invariably characterized by flat stream gradients that would
require long, relatively large diameter penstocks to develop significant
head and resulting power. In contrast the steep headwaters of these
basins, which have a good head potential and are well suited for construc-
tion of an economical penstock and power plant, have a marginal water
supply. No intermediate situation exists. The Quiktalik and Peterson
Creek sites represent, respectively, the best of these two conditions.
2. Peterson Creek Alternative Project
This alternative would utilize a 6-foot weir in a 5-foot wide channel
to divert water to a 3700-foot long, 14-inch penstock. An impulse turbine
would utilize 205 feet of gross head and a maximum flow of 6.7 cfs to
develop 68 kilowatts of power. The powerhouse would be located near the
mouth of the creek approximately 100 feet from the shore of Norton Sound.
A preliminary project plan and profile and typical powerhouse layout are
shown on Plate 1. Photographs of the powerhouse and diversion weir sites
are shown on Figures 1 to 3.
3. Quiktalik Creek Alternative Project
This alternative would utilize a long low (6-foot) diversion dam and/or
canal to divert water to a 6,600-foot, 30-inch penstock located on the
south side of the broad valley. A tube turbine would utilize 65 feet of
gross head and a maximum flow of 18 cfs to develop 69 kilowatts of power.
The powerhouse would be located at the base of the bluff approximately
500 feet from the shore of Norton Sound and 1500 feet upstream of the
NBISF-313-9528-ER 2
alluvial mouth of the creek. Only 1.5 miles of transmission line would be
required to connect the powerhouse to the vi 11 age. Despite the shorter
transmission line, the Quiktalik site is judged to be clearly inferior to
the Peterson site in overall construction cost.
4. Site Access and Transmission Line
Access to the Peterson Creek powerhouse site would be by boat from Elim
during the anticipated May through October operating season. The power-
house would be located within 100 feet of the beach. Winter access, if
needed, would be over the Iditarod Trail.
A simple guyed-tower transmission line would follow the coast to
fullest extent practical. It would be constructed and inspected from a
skiff. A portion of the line may have to be constructed above 150-foot sea
cliffs.
The Quiktalik site could be accessed by extending a road 1-1/4 miles
beyond the Elim airstrip.
5. Hydrology
The preliminary estimates of stream flow presented here for Peterson
Creek and Quiktalik Creek are based on recorded stream flows on two streams
near Nome, the Snake River and Crater Creek. While these streams are
100 miles west of the project area they are closest known gages with a
similar meteorological exposure along the south slope of the Seward
Peninsula. The potential project streams drain much smaller basins than
the gaged streams and have much lower effective elevations of the basin
orographic divide, thus the project basins are less efficient at inducing
precipitation and subsequent runoff than the gaged streams.
The following Table gives the characteristics of the gaged and project
streams:
NBISF-313-9528-ER 3
HYDROLOGIC COMPARISON
Peterson Quiktalik Snake Crater
Stream Creek Creek River Creek
USGS Gage No. 15621000 15668200
Drainage Area at Diversion/Gage
(sq. mi.) 1.49 7.0 85.7 21.9
Elevation of Orographic Divide
(ft.) 1300 1000 2000 3200
Mean Annual Flow (cfs) 2.8* 10.5* 183 55.6
S::Jecific Yield (cfs/sq. mi.) 1. 9* 1.5* 2.0 2.5
M·~asured Flow 7/12/82
at Diversion/Gage 5.9 17.0 172
at Mouth 5.3 25.0
*Adopted values
An average annual flow of 2.8 cfs was adopted for the selected Peterson
Cr·eek site. The initial estimates of the flow duration curve (Figure 4)
and the monthly hydrograph (Figure 5) were based on the 16 years of
rE!corded flows from the Snake River near Nome and prorated to Peterson
Creek on the basis of the respective mean annual flow (2.8/183).
As shown in the monthly flow hydrograph, 90 percent of the annual flow
occurs in May through October. This, along with the harsh winter
conditions at the remote sites indicates that any hydroplant should be shut
down during the winter and the penstock drained. This seasonal operation
plan will avoid major icing problems and potentially high operation and
NBISF-313-9528-ER 4
maintainance costs while only marginally reducing the total energy
production.
6. Power and Energy Production
A turbine design flow of 6.7 cfs, equal to 10% on the flow duration
curve was selected for reconnaissance evaluation of the Peterson Creek
Project. A small skid mounted impulse turbine would be used. This turbine
is capable of operating efficiently down to 10 percent of its capacity
(C.70 cfs) which corresponds to a 60 percent flow exceedance. In contrast
the Quiktalik Creek Project would require a much larger tube type turbine
which has a low range limit of about 30 percent of its design capacity.
The following table compares the two projects:
Power and Energy Development
Project
Item Peterson Qui kt ali k
Design Flow ( cfs) 6.7 18
Gross Head (ft) 205 65
Penstock
Diameter (in) 14 30
Length (ft) 3700 6600
Net Head ( ft) 156 54
Efficiency ( %) 77 84
Power (kW) 68 69
Av•:!r age Annual Energy (MWH) 197 195
NBISF-313-9528-ER 5
C. ECONOMIC ANALYSIS
Preliminary estimates of costs and benefits associated with the Peter-
son Creek Project were assessed to provide an indication of the feasibility
of the proposed project. The initial results of this analysis indicate
that the Peterson Creek Project is marginally uneconomical. Thru com-
pari son of the project features the Qui ktal i k Creek Project was determined
to be substantially uneconomical and no further analysis was made.
1. Economic Criteria
The Peterson Creek Project was assessed using the criteria and method-
ology presented in Section IX of the Old Harbor and other Feasibility
Studies recently completed for APA by this firm. These criteria are based
on the APA standard criteria for economic analysis.
2. Cost Estimate
The cost estimates for the site were based on the information prepared
for the feasibility studies for 01 d Harbor, King Cove and Larsen Bay.
Quantity estimates were prepared and unit prices derived from the above
referenced reports were then applied. These unit prices were judgementally
modified as necessary to suit this particular application. This estimate
is summarized below:
Item
Direct Construction
Contingencies
Contract Cost
Engineering and Administration
Total Project Cost
Power (kW)
Cost per kW
NBISF-313-9528-ER
Cost Estimate
6
Amount
$1~626,000
244~000
1~870,000
300,000
$2,170,000
68
$31,900
3. Project Energy Planning
The average monthly energy generation that could be realized from the
Peterson Creek Project was compared to the monthly direct electrical
demands derived from the 11 Reconna i ssance Study of Energy Requirements and
Alternatives for Kaltag, Savoonga, White Mountain and Elim 11
, June 1981, and
from AVEC approved annual power projections. This determined the amount of
hydroelectric energy that could be used to meet the projected demand, and
the required amount of supplemental diesel generation that would be
necessary if the hydroelectric project is built. A detailed explanation of
the methodology used for this energy accounting is included in Chapter VII
of the Feasibility Study for Old Harbor Hydroelectric Project. This
accounting was performed for 1985, 1990, 2000, and 2034. The results of
the accounting are presented below.
Energy Demand and Generation
Required
Direct Direct Demand Diesel
Demand Met by Hydro Generation
Year ( 1000 kWh) (1000 kWh} ( 1000 kWh}
1985 480 163 317
1990 504 167 337
2000 700 192 508
2034 700 192 508
4. Benefit/Cost Analysis
The annual costs associated with the hydroelectric project were esti-
mated using the energy values presented above. These costs include the
cost of supplemental diesel generation and were developed in a manner
consistent with the methodology advanced in Chapter IX of the Old Harbor
Study. The costs were discounted to January 1982 at three percent
interest. The present worth of the base case is $7,791,500. The present
worth of the hydroelectric project, including the supplemental diesel
costs, is $8,420,100. The present worth of the cost of the hydroelectric
project was considered as a cost. The costs of the base case were consid-
ered to be a benefit. This methodo 1 ogy is in accordance with the method-
ology requested by APA. A summary of present worths is presented below:
NBISF-313-9528-ER 7
Present Worth Summary
Present Worth of Benefits
Present Worth Base Case Only
Present Worth of Costs
Present Worth Cost of Hydro Project
(Includes Present Worth Cost of
Supplemental Diesel)
The present worths presented
benefit/cost ratio for the project.
is as follows:
B/C = 7,971,500 = 0.95 8,420,100
$7,971,500
$8,420,100
above were used to determine a
The benefit/cost ratio for the project
The benefit/cost ratio presented above indicate that the project is not
feasible.
D. ENVIRONMENTAL OVERVIEW
The primary impact of the Peterson Creek Project appears to be
disruption of the local wildlife during one season of construction. No
fish were observed in Peterson Creek and its comparatively steep gradient
and small flow may preclude any material loss of local fisheries. In
contrast, salmon were observed in Quiktalik Creek and the substrate is
gravel suitable for salmon spawning.
NBISF-313-9528-ER 8
E. CONCLUSIONS
1. A 68 kW hydroelectric project capable of producing approximately
200,000 kWh during the six month summer season is potentially developable
on Peterson Creek.
2. The preliminary cost estimate of the project designed, contracted
and constructed under conventional APA procedures is approximately
$2,200,000.
3. The preliminary estimate of project benefit/cost ratio is 0.95.
4. A hydroelectric project is not viable at Elim under conventional
development procedures.
F. RECOMMENDATIONS
1. APA should reconsider the project under a small engineer-
constructor performance contract or demonstration project. The sma 11 size
of the project may permit major economies in design and construction costs
if it were developed outside of the conventional APA/AVEC institutional
framework and bidding procedures.
2. Flow measurements should be made at Peterson Creek during the 1983
May-October season. This may be most economically achieved by installing a
2-foot measuring flume and simple 30-day float recorder. Flows in excess
of 15 cfs need not be accurately measured. Reports from local people and
the carbonate geology of Peterson Creek suggest that the total season flow
may be considerably greater than estimated here. If verified this would
materially improve the project•s power benefits.
NBISF-313-9528-ER 9
~-r-----------------------~-----------------------------------------------------------------------·--------------------------------~ ~
\
I
I
I
r -I ! I
I
J
I
I
!
I
I I
! I ' I I I I I I ' I
{ I I
I
I
I
\
\
/
PLAN
FEET
2~0~~~----------~-------------------------------------------
200 ~............ ;;>' ~l'"t UIA.MI:. I k" r;.N;p I U'CI\
a~~ --···--· ·-· ·---· ~
z
0
~ 100 ..,
.J ..,
$0--------------------------------------------~~--~------
a ------------------~--------------~------------~~~r-
1 3700' 1
PROFILE PETERSON CREEK
NORTON SOUND
3000
TURBINE
TYPICAL IMPLUSE TURBINE POWERHOUSE
.JilL
I
/
LINE
"
j
ELIM
VICINITY MAP
LOCATION MAP
NOT TO SCALE
0 I 2 3
~ I ~--..-,--+--------------~. I '
31 COVER
'· f"": 14" FIBERGLASS PENSTOCK
TYPICAL PENSTOCK SECTION
lin.
MILES
STATE OF ALASKA
ALASKA POWER AUTHORITY
ANa!OfiAGE, ALASKA
.ELIM HYDROELECTRIC PROJECT
PETERSON CREEK PROJECT
DOWL ENGINEERS
ANCHORAGE , ALASKA ~~:C~'="
PUTI·l
~
1.1.1
1.1.1 a::
'-J
u..
0
::1:
1-
::;)
i
~
1.1.1
1--~
1.1.1
~
1.1.1
~
8
::;)
0
::1:
::1:
r-·~
a::
~
~
~.·
0
/l.
~;
Q..
~
1.1.1
1.1.1 a::
'-J
z
~ a::
1.1.1
1-
1.1.1
~
LI.J
1--V')
0::: -!:ij
z
0 -V')
0:::
LI.J > -c
:w::
LI.J
LI.J
0::: u
z
~
0:::
LI.J
1-
LI.J c..
9.0
8.0
7.0
6.0
5.0
4.0
3.0
2.0
'"fit 1.0 -...
..9
3:
0 ii 0
\
~
~
MEANANNUACFLOW-2:8cfs ' \
\
\
' ~ ' ............_
' 0 10 20 30 40 50 60 70 80 90 100
PERCENT (0/o) OF TIME FLOW EXCEEDED
PETERSON CREEK
FLOW DURATION CURVE
FIGURE
4
II I
10
9
8
7
6
5
4
2.8 cfs
-~---------------AVERAGE ANNUAL FLOW
2
-(f) -.s
~ g
LL 0 0 N 0 J F M AM J
MONTH
PETERSON CREEK
AVERAGE MONTHLY FLOWS
I
i
I
I I
I
i
!
I
I
I
------
J A S
FIGURE
5
GEOLOGIC RECONNAISSANCE OF THE ELIM AREA
Introduction
On behalf of the Alaska Power Authority, DOWL Engineers and
Tudor Engineering conducted a preliminary reconnaissance
level study of potential hydropower sites in the Elim area.
Elim is approximately 95 miles east of Nome. Field studies
were conducted on July 8, 9, 1982. On the basis of previous
work and our own reconnaissance, sites on Quiktalik and
Peterson Creeks were selected for study. The geologic
reconnaissance work was designed to identify potential fatal
flaws in developing these hydropower sites; to provide
information necessary for very preliminary design work; and
to provide a basis for determining future work necessary if
either of these projects went into the detailed feasibility
stage. Any comprehensive determination of foundation condi-
tions for a diversion structure, penstock, roads, and power-
line will require a more detailed feasibility study.
Topography
Elim is on the south side of the Seward Peninsula bordering
Norton Bay which is part of Norton Sound. The area is
dominated by gentle slopes between bedrock outcrops that
form ridges and hills. The tops of the hills are generally
barren with
and spruce
highest peak
Norton Bay.
the lower slopes being vegetated with shrubs
forests. In the immediate area of Elim the
is Mt. Kwinink which rises 2,000 feet from
Further to the north, the Darby Mountains reach
elevations of over 3, 000 feet.. Valleys, in most cases, are
~ENGINEERS
broad and have stream gradients on the order of 50 feet per
mile.
Geology -Peterson Creek
The Peterson Creek Valley is remarkably steeper and narrower
than most valleys in the Elim area. Most of the creek flows
along a contact between a crystalline limestone and a
schistose marble. The limestone is reported to be Devonian
in age and the marble is assigned to the Precambrian {Miller
et al, 1972). Field evidence including brecciation of the
rock, slickensides, and the straightline nature of part of
the creek suggest that this valley is excavated along a
fault line. Although activity of this fault has not been
determined, regional geologic evidence suggests that it is
inactive.
The proposed diversion site is in colluvial and alluvial
materials in the stream bottom at an elevation of approxi-
mately 215 feet above sea level. No bedrock abutments are
present in the creek bottom although bedrock does crop out
on the east valley wall approximately 75 feet away. Thick-
ness of the surficial materials has not been determined,
however, based on exposed areas, thicknesses are expected to
be on the order of 25 feet. If determination of this thick-
ness is important to the final design, seismic work or
drilling should be undertaken.
A powerhouse location near sea level would be located on
schistose marble. This marble is strongly foliated and
trends N. 45° E. with a dip of 64° W. The marble shows rock
clevage along discrete layers which probably average 1/2
-2-
~ENGINEERS
inch in thickness. Locally layers of a brown mica schist
predominate. In some areas a green talc-chlorite schist
tends to form layers up to 3 feet in thickness.
The marble should provide excellent foundation material for
a powerhouse. Blasting will be required for excavation.
Drilling operations are relatively easy in limestone and
marble because calcite {CaC03}, the major mineral in these
rocks, is relatively soft {Mohs scale 3}. Care should be
taken to place the powerhouse out of reach of storm waters.
A road connecting the powerhouse and the diversion structure
would be on the colluvial and alluvial materals in the creek
bottom. Near the powerhouse some bedrock may be encounter-
ed. Slope stability appears adequate although further
investigations should be made once a specific road/penstock
route has been identified. Permafrost is expected to be
prevalent in this area, except immediately next to the
stream and the bay. A more detailed geotechnical investiga-
tion is necessary to determine actual conditions along the
penstock, access road and powerline routes and to provide
adequate design data to address this condition.
Springs are common in the Peterson Creek valley. This fre-
quency may relate to the presence of a fault and associated
breccia. Typically fault zones contain impermeable
materials which form a barrier to the flow of ground water
and cause it to surface. While the Peterson Creek basin is
small {2 square miles}, flow in the creek may be augmented
by recharge from other basins. Limestones and marbles typi-
cally have water flowing in solution cavities and it may be
that the fault breccia has sufficient resistance to impede
deep ground-water flow and allow it to surface.
-3-
~ENGINEERS
Sand and gravel for construction purposes are not available
at this site. Sufficient material is probably present at
the mouth of Quiktalik Creek, approximately 3 miles away.
Quiktalik Creek
The site investigated for possible diversion is in a broad
valley filled with colluvial and alluvial materials. No
bedrock abutments are present. The underlying bedrock is
probably a recrystallized Devonian limestone. Springs are
common in this area and may also be related to faulting.
Faults have been mapped in this area (Miller, et al, 1972)
although evidence for them was not gathered during this
reconnaissance study.
A possible powerhouse site would be located on alluvial
sands and gravels that appeared to be permafrost-free. A
connecting road/penstock could be built in the valley
bottom, however there would be local drainage problems
because of the low gradient to the valley (approximately 50
feet/mile). Slope stability should not be a problem.
Sand and gravel for construction purposes are probably
available from the mouth of this creek. Further testing
would be necessary to define the extent and quality of this
resource. Gravel deposits also exist at Moses Point and
along the Moses Point -Elim road.
Seismic Risk
Seismic risk in this area is low. As shown in Figure 1 peak
bedrock acceleration over a 50-year plant life is expected
to be within 5 to 10% g. These g values have a probability
-4-
~ENGINEERS
of exceedence of 10%. Standard Uniform Building Code con-
struction procedures should provide an acceptable level of
seismic hazard protection.
The Elim area is sufficiently far away from major earthquake
zones on both sides of the Pacific such that Tsunami are not
a major hazard in this area.
Transmission Line Corridor
Between Peterson Creek and Elim, two options should be
investigated for powerline siting. Option A would be to run
the line along the beach and tie the poles into the bed-
rock. Option B would run along the Iditarod trail.
If Option A were selected, poles could be bolted to the
bedrock which is present for approximately 3.5 miles of the
4.5 mile distance. Beach sands and gravels are present the
remainder of the way. This option would have two major
advantages: (1) avoidance of permafrost (2) easy construc-
tion since access could be from the water.
Option B would involve a line higher up on the slope. Power
poles would be set in colluvial and alluvial materials that
are in the permafrost zone. Some poles (probably less than
10%) would have to be set in bedrock. An alignment along
the Iditarod trail would allow for winter maintenance of the
line. Summer maintenance could be via all-terrain vehicle,
if a road was too expensive to construct.
Geotechnically either option may be acceptable. However, if
it is consistent with design requirements Option A probably
would be more economical to construct.
-5-
~ENGINEERS
The powerhouse at Quiktalik Creek would be less than 1. 5
miles from Elim. Either a beach route or a route along the
Idi tarod trail would be sui table should this site be de-
veloped.
-6-
~ENGINEERS
UJ a: :::;) CJ L&.
c:
0 ·--al ...
<D -<D
()
()
<
...111::
()
0 a:
...111:: as
G) a..
~
Cl)
a:
0
::E
Cl) -UJ
Cl)
CD a: ..Jw 3: w O! O<' z w