HomeMy WebLinkAboutChitina Final Report 2008REGIONAL HYDROELECTRIC
INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
May 2, 2008
Prepared for
ALASKA ENERGY AUTHORITY
813 West Northern Lights Blvd.
Anchorage, Alaska 99503
Contracting Agency
LCMF
615 East 82ndAve., #200
Anchorage, Alaska 99518
Prepared by
polarconsult alaska, inc.
1503 West 33rd Avenue, Suite 310
Anchorage, Alaska 99503
Phone: (907) 258-2420
POLAR CONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
TABLE OF CONTENTS
ACRONYMS AND TERMINOLOGY ..................................................................................................... 111
EXECUTIVE SUMMARY .......................................................................................................................... 1
1.0 INTRODUCTION .......................................................................................................................... 3
1.1 PROJECT EVALUATION PROCESS .................................................................................................. 3
1.2 SUMMARY OF INVESTIGATIONS .................................................................................................... 4
1.3 CHITINA PROJECTED ELECTRICAL REQUIREMENTS ...................................................................... 5
1.4 COMMUNITY BACKGROUND ......................................................................................................... 6
2.0 PREVIOUS STUDIES ................................................................................................................... 7
2.1 LIBERTY CREEK··························································································································· 7
2.2 FIVEMILE CREEK .......................................................................................................................... 7
2.3 TROUT LAKE································································································································ 8
2.4 Fox CREEK .................................................................................................................................. 8
2.5 O'BRIEN CREEK ............................................................................................................................ 8
3.0 SELECTED PROJECT ANALYSIS .......................................................................................... 10
3.1 O'BRIEN CREEK, Low HEAD PROJECT ....................................................................................... 10
3.2 O'BRIEN CREEK, HIGH HEAD PROJECT ...................................................................................... 12
3.3 FIVEMILE CREEK ........................................................................................................................ 15
3.4 CONCEPTUAL DESIGN ................................................................................................................ 16
4.0 ECONOMIC ANALYSIS ............................................................................................................ 19
5.0 CONCLUSION AND RECOMMENDATIONS ........................................................................ 21
6.0 REFERENCES ............................................................................................................................. 23
TABLES
TABLE 1 -PROJECT CONFIGURATIONS AND MINIMUM OUTPUTS .................................................................... 9
TABLE 2 -O'BRIEN CREEK LOW HEAD COST ESTIMATE ............................................................................... 11
TABLE 3 -O'BRIEN CREEK LOW HEAD PROJECT SUMMARY ......................................................................... 11
TABLE4-O'BRIEN CREEK, HIGH HEAD COST .............................................................................................. 14
TABLES-O'BRIEN CREEK, HIGH HEAD CONFIGURATION ............................................................................ 14
TABLE 6 -FIVE MILE CREEK PROJECT SPECIFICATIONS ................................................................................. 16
TABLE 7 -FIVEMILE CREEK COST ESTIMATE ................................................................................................ 18
TABLE 8 -ECONOMIC SUMMARY·················································································································· 19
FIGURES
FIGURE 1. VICINITY MAP ............................................................................................................................... 2
FIGURE 2. O'BRIEN CREEK, LOW HEAD PROJECT MAP .................................................................................. 3
FIGURE 3. O'BRIEN CREEK, HIGH HEAD PROJECT MAP ................................................................................. 4
FIGURE 4. FIVEMILE CREEK PROJECT MAP···································································································· 5
MAY2,2008 PAGEi
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
PROJECT PHOTOS
PHOTO 1. O'BRIEN CREEK, LOW HEAD PROJECT INTAKE SITE
PHOTO 2. O'BRIEN CREEK CANYON AT FOX CREEK.
PHOTO 3. O'BRIEN CREEK, HIGH HEAD INTAKE
PHOTO 4. O'BRIEN CREEK, HIGH HEAD INTAKE
PHOTO 5. O'BRIEN CREEK, HIGH HEAD INTAKE LOCATION BEFORE FLOOD
PHOTO 6. O'BRIEN CREEK, HIGH HEAD INTAKE AREA AFTER FLOODING
PHOTO 7. O'BRIEN CREEK, HIGH HEAD INTAKE AREA AFTER FLOODING
PHOTO 8. BANK EROSION NEAR FROM INTAKE
PHOTO 9. DOWNSTREAM VIEW OF UPPER RIDGE ON O'BRIEN CREEK
PHOTO 10. UPSTREAM VIEW OF UPPER RIDGE ON O'BRIEN CREEK
PHOTO II. VIEW OF SECOND RIDGE ON O'BRIEN CREEK
PHOTO 12. SECOND RIDGE ON O'BRIEN CREEK
PHOTO 13. O'BRIEN CREEK POWERHOUSE SITE, HIGH HEAD PROJECT
PHOTO 14. SLIDES ALONG COPPER RIVER HIGHWAY
PHOTO 15. SLIDES ALONG COPPER RIVER.
PHOTO 16. ROAD ADJACENT TO FIVEMILE CREEK
PHOTO 17. EXPOSED ROCK FORMATION, FIVEMILE PROJECT
PHOTO 18. FIVEMILE AERIAL PHOTO.
PHOTO 19. FIVEMILE CREEK, POSSIBLE INTAKE SITE.
APPENDICES
APPENDIX A, HYDROLOGY ANALYSIS
APPENDIX B, GEOTECHNICAL REPORT, SHANNON WILSON
APPENDIX C, SL"MMARY OF FLOODING IN SOUTH CENTRAL ALASKA, OCTOBER, 2006. USGS
MAY2,2008 PAGEii
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
ACRONYMS AND TERMINOLOGY
AEA
APA
ATV
cfs
CVEA
EPS
ft
HDPE
m
kVA
kW
kWh
LCMF
LIDAR
mi
PCE
Polarconsult
USGS
MAY2,2008
Alaska Energy Authority
Alaska Power Administration
All terrain vehicle
cubic feet per second
Copper Valley Electrical Association
Electric Power Systems, Inc.
feet
high-density polyethylene
inch
kilovolt-amp
kilowatt
kilowatt-hours
LCMF, LLC
Light Detection and Ranging
mile
Power Cost Equalization Program
Polarconsult Alaska, Inc.
United States Geological Survey
PAGE iii
POLARCONSULT ALASKA, INC.
EXECUTIVE SUMMARY
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
This report has been prepared at the request of Alaska Energy Authority (AEA), Rural
Energy Group. Its purpose is to assist in the evaluation of hydropower resources
available to the community of Chitina, Alaska. Based on field investigations, analysis of
resource suitability, and community power needs, recommendations have been provided
for additional investigation and development activities.
The continued investigation of O'Brien Creek was the initial intent of this project and
required field activities to select a project configuration among the alternatives presented
in the O'Brien Creek Hydroelectric Conceptual Design Report (Polarconsult, 2005). A
record flood in 2006 (USGS, 2006) caused drastic changes to the stream bed, resulted in
slope stability problems, and caused landslides along the proposed penstock alignment
and Copper River Highway effectively cutting off access to the project. In addition,
discontinuous permafrost was found along the penstock and access alignment. It became
apparent that a re-evaluation of the conceptual design and cost assumptions was required.
The primary focus of this report is the continued evaluation of the O'Brien Creek
resource and a preliminary review of Fivemile Creek and other creeks to determine the
best potential hydro project alternative. The end result is a more comprehensive review
of the hydropower alternatives for Chitina.
Fivemile Creek was originally not pursued as a project alternative because a 4 mile
transmission line was required and it was reported that there was little or no discernable
stream flow in the winter time. Since the 2005 analysis, an extension of the power line
from Chitina to a new diesel powerhouse located at the airport (immediately adjacent to
Fivemile Creek) is planned and will be completed in the near future. As a result, the
economic viability of the Fivemile project is improved and prompted further
consideration during this investigation.
Field reconnaissance of the Fivemile project in 2007 suggests that it is a favorable
alternative to the O'Brien Creek project in several respects. The benefits include existing
access, better soil conditions, and a nearby interconnection point to the electric grid. In
addition, the smaller size of the project makes it a better fit for Chitina's current electric
requirements. The project is currently envisioned as having a design output of 300 kW
and a minimum winter output of 110 kW. An economic analysis of the project indicates
is has a benefit to cost ratio of 2.0 in a "growth" scenario and 1.3 in a "no growth"
scenario.
Given the current economic and technical difficulties of constructing a project on O'Brien
Creek, investigative efforts would be more efficiently spent evaluating a project on
Fivemile Creek. It is concluded that further evaluation of the potential for hydropower
on Fivemile Creek is warranted.
Further investigative activities on Fivemile Creek should include:
• Installation of a stream gauge near the intake location
• Stream flow measurement to correlate weir readings at the culvert
PAGEl
POLARCONSUL T ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
• A Light Detection and Ranging (LIDAR) survey of the area suitable for project
layout
• Preliminary geotechnical investigation
• Identification of regulatory requirements
• Preparation of a conceptual design report
• Development of a project cost estimate
• Refinement of project economics
The cost to perform these investigative activities is estimated to be $100,000-$150,000
and will be used to prepare a conceptual design report and refine the project cost
estimate.
MA¥2,2008 PAGE2
POLARCONSUL T ALASKA, INC.
1.0 INTRODUCTION
REGIONAL HYDROELECTRIC INVESTIGATION
CHlTINA, ALASKA
FINAL REPORT
The Alaska Energy Authority (AEA), Rural Energy Group is pursuing the evaluation of
hydroelectric projects for the community of Chitina, Alaska, in order to lower energy
costs. The increasing costs are the result of escalating costs of diesel generation upon
which the community currently depends. Through the use of a renewable hydroelectric
resource, the community will benefit from long-term independence from the escalating
costs of diesel.
To achieve this goal, AEA has taken steps to identifY the most suitable hydroelectric
projects available to the community. This has required the review of existing studies of
alternatives, a conceptual evaluation of desirable project alternatives, initial field
investigations, and fmally a more detailed evaluation of those projects that are most likely
to satisfY the electrical generation needs of the community. Each of these evaluations
required a careful review of project configurations, costs, and benefits to make an
equitable comparison between projects, resulting in a determination of the project most
appropriate and economical for Chitina.
This report details previous studies, field investigations, analysis of project configurations
and resource availability, and a review of community power needs. The summary of
previously investigated projects provides a comprehensive understanding of the
alternatives that had been explored. The investigative work has been an iterative effort to
further identify the best hydro resource available to the community. The initial project
focus was the continued investigation of potential hydro projects on O'Brien Creek due
to its large water resource and its capability to meet the long-term electrical needs of the
community. The report provides detailed characteristics of the O'Brien and Fivemile
Creek projects and a detailed hydrology analysis. In addition, recommendations have
been provided to guide the additional investigation and activities necessary to proceed
with the development of a hydroelectric project to meet Chitina's needs.
Figures attached with the report include a vicinity map (Figure 1) that shows the location
of Chitina, the drainage basins being considered for hydro development, and the nearby
United States Geological Survey (USGS) stream flow gauging sites. Figures 2 through 4
show the location of each of the most favorable project alternatives.
Polarconsult Alaska, Inc. prepared this report under the August 30, 2007 proposal,
September 21, 2007 notice to proceed, and subsequent changes in scope requested by
AEA. The work was coordinated through the term contract between LCMF, LLC and
AEA.
1.1 PROJECT EVALUATION PROCESS
The selection and evaluation of hydro projects suitable for construction is an iterative
process that involves several steps. Evaluation of prospective hydro projects began with
the selection of superior projects by using existing data and reports. This effort primarily
was based on finding a project that could provide sufficient power to meet the energy
needs of the community and then considering the technical feasibility and associated cost
of the project. Those projects that could provide sufficient power and could be
constructed within reasonable economic limitations were submitted to AEA for further
MAY PAGE3
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
consideration. Numerous potential projects that initially appeared feasible have been
conclusively eliminated through this process.
The process resulted in the recommendation to further evaluate O'Brien Creek for its
hydroelectric potential. In coordination with AEA, several data gathering and review
iterations were necessary to evaluate the O'Brien Creek project configurations with the
best potential to provide hydropower to the community. As a part of this process, AEA
requested the scope of the investigation be expanded to include the evaluation of
Fivemile Creek.
1.2 SUMMARY OF INVESTIGATIONS
The initial review and analysis of a potential hydro project on O'Brien Creek began in
September 2004. A review of existing studies, maps, and potential project configurations
was undertaken. Potential projects were identified and an aerial field trip via helicopter
was arranged in October 2004 to visually investigate the terrain conditions.
Following the 2004 field trip, Polarconsult coordinated the collection of Light Detection
and Ranging (LIDAR) data for the project area to further evaluate project options
including access, penstock, and transmission routes. LIDAR data provides a detailed
image of the ground topography. Due to the vast area of the site, this data was used to
cost-effectively evaluate the surface conditions. In December of 2004, the LIDAR data
was used to develop a more detailed and reliable evaluation of project alternatives.
A Conceptual Design Report (Polarconsult, 2005) was completed that outlined the
various project options based on the selection of the preferred project intake site. The
project configurations being considered offered alternatives for site access, power house
location, and transmission considerations. The report included a project cost estimate and
recommendations for further work that included selection among these alternatives along
with stream flow and geotechnical investigations.
In April of 2005, a field trip was conducted to assess the minimum stream flow available
at the preferred project intake site. The measurement of the minimum stream flow is
critical to evaluating the ability of the project to meet the power needs of the community.
This trip also afforded the opportunity to evaluate the terrain near the intake site as well
as along the proposed project routes by helicopter. The visual assessment during this
field trip also served to validate the LIDAR data.
Subsequent to the 2005 field trip, local reports of severe landslides along the Copper
River Highway prompted a reconsideration of the option that sited the powerhouse and
the project access route near Eskilida Creek. The extensive nature of the slides
eliminated those options and forced a reassessment of the project and associated costs.
In October of 2007, a geotechnical and more detailed investigation of the remaining
project options was undertaken. As part of this work, a comprehensive review of project
alternatives for O'Brien Creek was conducted. During this investigation, significant
changes in the site conditions were identified resulting from a severe flood in 2006
(USGS, 2006). The flood resulted in landslides and slope stability concerns near the
proposed intake and along the first mile of the penstock route. The landslides along the
Copper River Highway required the penstock to bridge O'Brien Creek near the
MAY2,2008 PAGE4
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
powerhouse. In addition, the discovery of permafrost conditions along the penstock route
required another reassessment of the project and associated costs.
During the same field investigation, a brief evaluation of Fivemile Creek was conducted.
This change in project scope was performed in recognition of the fact that the feasibility
of a hydro project on Fivemile would avoid many of the difficulties encountered on
O'Brien Creek. Although a Fivemile Creek project is significantly smaller than O'Brien
Creek, it was recognized to have the potential to meet the current power needs of the
community for a much lower cost. The decision was made by AEA to utilize the
mobilized design team and available helicopter to evaluate the feasibility of developing a
hydro project on Fivemile Creek.
The fmdings of the O'Brien fieldwork were summarized in a brief report (Polarconsult,
2007a) that enumerated the significant construction challenges and the anticipated
increases in project costs associated with developing a hydro project on O'Brien Creek.
As a result, other more favorable hydro alternatives were focused on.
A separate and similarly brief report summary of the Fivemile Creek project was also
prepared that included some basic hydrology information and field observations. It was
concluded that the low winter stream flow in Fivemile Creek was critical to assessing the
potential value of the project. In order to progress in a timely manner with the new focus
on Fivemile Creek, a plan involving local residents constructing and monitoring a weir to
verify winter low stream flows on Fivemile Creek was undertaken during the winter of
2007 and 2008.
The results of the 2007 investigations of the O'Brien Creek project, Fivemile Creek
project, and other relevant previous work are presented in this report.
1.3 CHITINA PROJECTED ELECTRICAL REQUIREMENTS
The current and projected electrical requirements for Chitina were required to determine
the adequacy of the proposed hydroelectric project to meet the electrical needs of the
community. A projection was summarized in the Chitina Rural Power System Upgrade
report (LCMF, 2005). The findings of this report and current information have been
provided in this summary.
The findings of the LCMF report indicated a 189 kW absolute peak demand at the end of
FY2015. This was based on an increase in the demand based on 6-year historical
population growth for Chitina of 3.26% plus a step increase in demand of 68 kW (peak)
related to the tie-in of the Chitina Airport to the existing community.
These conclusions are augmented by information provided by the Fiscal Year 2007
Statistical Report of the Power Cost Equalization Program (PCE) which provides data for
the period from July 1, 2006 to June 30, 2007, and by information from Mr. Martin
Finnesand, the power plant operator for Chitina Electric. The 2007 PCE report shows
that the community used 33,789 gallons of fuel at an average cost of $2.52 per gallon.
Each gallon of fuel produced 13.34 kWh of electricity. The total generation was about
450,086 kWh which is equivalent to a continuous power output of 51.4 kW.
For a community load profile, the absolute peak demand overestimates power usage.
The calculation of the probable peak was made to anticipate long-term peak loads.
MAY2,2008 PAGES
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Discussions with Mr. Finnesand indicated that the current peak demand is approximately
75 kW. This does not include the additional loads that will come when the power line
extension is constructed to the airport, which is expected to be approximately 30 kW
(factored peak) for the clinic and DOT maintenance facility. Applying the 3.26% growth
factor applied to the current 75 kW peak demand plus an estimated 30 kW peak results in
a 124 kW probable peak for FY2015.
The peak demand in Chitina occurs during the summer and winter. The summer peak is
caused by the seasonal increase in population and the increased refrigeration loads to
freeze salmon caught by the residents and summer visitors. The timing of the summer
peak load is ideal for a run-of-river hydroplant, as it has more than sufficient capacity
since water flows increase greatly during the summer.
1.4 COMMUNITY BACKGROUND
Chitina is located on the west bank of the Copper River at its confluence with the Chitina
River, at mile 34 of the Edgerton Highway, 53 miles southeast of Copper Center. Chitina
was established in the early 1900s as a support town for mining in Kennicott but was
nearly abandoned after the mine shut down in 1938. The 2000 census population was
123.
The climate in Chitina is characterized by long, cold winters and relatively warm
summers. Total annual precipitation averages 12 inches. Temperature extremes from a
low of -58 to a high of 91 degrees Fahrenheit have been recorded (Alaska Community
Database, 2008).
During the summer, subsistence dipnetting for salmon on the Copper River brings a large
number of Alaskans from Anchorage and other areas of the state. Employment is
primarily with the village council, village corporation, or the National Park Service.
Many residents are self-employed or work in retail establishments. The summer influx of
fishermen, tourists, and campers provides some cash income through fish guiding and
other services.
The terrain near Chitina is rugged, with the Chugach Mountains rising steeply from the
banks of the Copper River. A series of small lakes is located in the narrow valley along
the Edgerton Highway between the townsite and the airport. A bridge crosses the Copper
River at the townsite leading into the Wrangell St. Elias National Park and the road to
McCarthy and the Kennicott Mine. The park on the east side of the Copper River near
the bridge consists of National Wilderness and Preserve areas.
South of Chitina, the Edgerton Highway becomes the Copper River Highway. This is an
unimproved trail accessible by four wheel drive and all terrain vehicles (ATVs). In the
1920s, it was the alignment of a railroad track that extended to Cordova, crossing the
Copper River via the Million Dollar Bridge. The old railroad grade has not been
maintained and recent flooding has taken out bridges and caused landslides that have
effectively blocked travel between O'Brien and Eskilida Creeks.
Chitina is accessible by road system and the small airport. The driving distance from
Valdez to Chitina is 116 miles. Driving distance from Anchorage is 247 miles. The
Chitina Airport has a 2,850-foot gravel runway.
PAGE6
POLARCONSUL T ALASKA, INC.
2.0 PREVIOUS STUDIES
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Previous reports considered many possible configurations and locations for hydroelectric
projects near Chitina. The U.S. Department of Energy and the Alaska Power
Administration (APA) performed a study in 1981 evaluating four potential hydroelectric
sites within 10 miles of Chitina (AP A, 1981 ). The study included an evaluation of the
feasibility of an intertie between Chitina and the Copper Valley Electrical Association
(CVEA) system at Tonsina as well.
The APA study concluded that there were no reasonably developable small hydro sites in
Chitina given the combined economics of providing transmission and distribution and the
low power demand. The study suggested that a more favorable solution was to construct
a larger hydro (500 kW) on Fivemile or Liberty Creek along with the intertie. The excess
energy from the hydro would be sold back to CVEA during the summer to offset the cost
ofthe hydro and local distribution system.
A study of an intertie was performed by Electric Power Systems, Inc. (EPS) to determine
the possible routing and estimated costs for a single-phase overhead tieline from Lower
Tonsina to Chitina along the Edgerton Highway (EPS, 2003a). This intertie would
connect Chitina's existing distribution system to CVEA's single-phase distribution line.
The total cost to construct this line was estimated at $2,190,960 (EPS, 2003a). The cost
of the line was compared to the cost of a replacement generation plant and was concluded
to be cost prohibitive.
The following is a summary of several different projects that have been considered for
hydro development.
2.1 LIBERTY CREEK
The APA report examined a project on Liberty Creek below the falls. This project was
configured with 250 feet of head with the pipe suspended from the canyon walls.
Minimum winter production would be approximately 60 kW.
The presence of a State Recreation Site at Liberty Falls is anticipated to be a substantial
impediment to obtaining approval to build a project. To permit the project, the falls
would have to be avoided, limiting design options. A project could be entirely located
upstream of the falls, but the creek is in a deeply incised canyon for several miles making
construction and access a significant difficulty.
Another option that was not considered in the AP A report was to lengthen the penstock
and place the powerhouse on the banks of the Copper River, netting approximately 550
feet of head. This configuration would produce about 130 kW in the winter and have a
capacity of 300 kW. This option would have a 6,500-foot pipeline with a 6-mile
transmission line. The high cost of the transmission line alone is expected to result in the
project not being economically viable.
2.2 FIVEMILE CREEK
AP A found that Fivemile Creek could support a hydro plant in the summer but did not
expect enough water in the winter to make development worthwhile. Additionally, at the
MAY2,2008 PAGE7
Douglas Ott
From: Douglas Ott
Sent: Wednesday, April16, 2008 10:08 AM
Alan Fetters To:
Cc:
Subject:
Lenny Landis; Peter Crimp
Chitina Hydro Investigation
Alan,
I have reviewed the draft report prepared by Polarconsult entitled Regional Hydroelectric Investigation, Chitina, Alaska.
I concur with the general conclusion that O'Brien Creek should not be further investigated at this time for hydroelectric
development However, I do not believe the high head configuration of Fivemile Creek is necessarily the best hydro
option for Chitina.
My review comments are as follows:
1. Page 9: Table llists two configurations for Fivemile Creek, but the narrative does not discuss the low head
option. I would like to see this narrative provided in the report.
2. Page 18: I have low confidence in the Table 7 cost estimate. The cost estimate does not have any line item cost
identified for construction of the pioneer road needed to install the 8500 feet of penstock required under this
hydro concept Additionally there is no cost attributed for rock excavation at either the intake structure or to
bury the penstock. There is also no cost identified for the power line needed at the intake site to operate the
screening system. Nor is there any cost listed for the Edgerton Highway pipeline crossing.
3. Page 20: The economic analysis should probably only consider a no-growth option for Chitina. If any trend is
considered it might even be for negative growth, since the general trend is for population growth in the larger
communities of rural Alaska due to out-migration from the smaller communities.
4. Page 20: The B/C ratio for Fivemile Creek will go down when the costs of my comment 2 items are factored into
its construction cost, very possibly bringing into question the viability of this option.
5. The low head option of Fivemile Creek (or some intermediate head option) would be better matched to Chitina's
limited power needs. The creek flow data measurements taken in early 2008 were encouraging. The hydro
project would be more inexpensive in this configuration and have less economic risks of construction cost
overruns. Operationally, the hydro in this configuration could provide most of the power needs of Chitina
except for a few months of the year when it would be supplemented by diesel generators.
* * * *
-:fi~P~~
/lete'UUttWe &~ad&~ &~
~ 1~ V~pue.tt ad &xtzMt A~
S"/3 71/e<~t~ LitJiu ?J~
A~. J'fJ: 99503
tzk (907) 771-3067
tx ( 907) 771-3044
1
~T~ear,kl::l$(;ai,](IQ!1tl\.l·.l;al!.o~rxe~r·f ,~, M~ntn''':~<rJi\Cfilnmu!Jijy,;~-j~mes$1\:KWHi~en.;ole$elj. r!lel};t:lsedlOles~I>'J:~~»>ti~$al'•i.:~· {k~~m,4l~;,M~Wbll~~~~~,E ~~)f:::~~~~"J.d~~~~:~¢?~e!!tfl dfcost ... ·I
2007 1 2006 July Chitina 43439 3375 12.87 300 87600 44161 1 0
2 2006 August Chitina 41255 3118 13.23 300 87600 46345 1 0
2007 3 2006 September Chitina 36798 2882 12.77 300 87600 0
2007 4 October Chitina 38789 3079 12.60 300 87600 48811 1 0
2007 5 2006 November Chitina 41382 3021 13.70 200 58400 17018 0 0
2007 6 2006 DecemberChitina 40557: 2876 14.10 110 32120 -8437 0 632.46 2340.097
2007 7 2007 January Chitina 40332 2816 14.32 110 32120 -8212 0 615.59 2277.691
2007 8 2007 February Chitina 32384 14.04 110 32120 -264 0 19.79 73.22339
2007 9 2007 March Chitina 34850 13.65 110 32120 -2730 0 204.65 757.1964
2007 10 2007 April Chitina 29957 2265 13.23 110 32120 2163 0
2007 11 2007 May Chitina 34477. 2742 12.57 200 58400 23923 1
2007 12 2007 June Chitina 36406 13.21 300 87600 51194
450626 13.34 264774 1 1472.488756 5448.208
2008 1 2007 July. Chitina 40222 12.90
2008 2 AugustChitina 37407 3164 11.82
2008 3 2007 September Chitina 32804 2829 11.60
2008 4 October 34300 2919 11.75
2008 5 2007 November Chitina 33840 2897: 11.68
2008 6 2007 December Chitina 37615 3129 12.02
2008 7 2008 January Chitina 36730 3099 11.85
2008 8 2008 February Chitina 36768 3148 11.68
1190938 91881 12.96
FY 2007 1 Jul-06
2 Aug
3 Sep
4 Oct
5 nov
6 Dec
7 Jan-07
8 Feb
9 Mar
10 Apr
11 May
12 Jun
POLARCONSUL T ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITrNA, ALASKA
FrNAL REPORT
time of the report, a 4-mile transmission line would have been required to connect to
Chitina Electric. The project considered by APA had 300 feet of head. Such a project
would have a minimum winter power production of30 kW. This would require the diesel
plant to run most of the winter to handle peak loads.
Another alternative for Fivemile Creek was a high head configuration. This
configuration utilizes an intake at an elevation of about I ,570 feet and a powerhouse
located at about 530 feet. This option would produce a minimum power output of about
110 kW in the winter and would be designed for a maximum output of about 300 kW.
This is the option that is more thoroughly investigated, and ultimately recommended,
later in this report.
2.3 TROUT LAKE
The existing hydroelectric project on Trout Lake has never been fully operational due to
problems keeping the siphon portion of the penstock from leaking air. EPS prepared the
Chitina Hydro Evaluation report (EPS, 2003c ). This report details the investigation of
the existing hydro and evaluates the feasibility of bringing the system back into service.
EPS initially recommended bringing the project online if the costs to do so were minimal.
The EPS report states that the Francis turbine output is 63 to 85 kW at a net head of 82 to
121 feet and flow of 11.3 to 12.7 cubic feet per second (cfs). The actual output of the
Trout Lake hydro under full output was found to be 52 kW. The report found the cost to
restore operation of the hydro to be approximately $50,000. This was under the
assumption that the penstock air leaks could be easily repaired. After consideration of the
EPS report, the conclusion reached by LCMF was that the Trout Lake project was not
worth pursuing as a possible hydropower resource for Chitina.
The capacity of the turbine on Trout Lake, about 60 kW, is not indicative of the ultimate
value of this resource. The amount of water on a yearly basis is very limited due to the
small drainage area. Coupled with the very poor efficiency of a Francis turbine at low
operational flows, the potential winter power production is essentially zero. The limited
output and other operational considerations combined with the relatively high cost and
uncertainty of restoring operation warrant, as a minimum, delaying any investment into
this project until further analysis of the Fivemile project is completed.
2.4 FOX CREEK
APA also investigated the potential for a project on Fox Creek. Helicopter over flights,
and later review of LIDAR data, confirmed the conclusion by APA investigators that the
canyon was too steeply incised to effectively construct a project there.
2.5 O'BRIEN CREEK
The APA report considered a project located along the lower reaches of O'Brien Creek.
This project sited the intake location above the Fox Creek discharge and the powerhouse
downstream from the Fox Creek discharge. Net head was estimated to be approximately
300 feet with a 2,700-foot-long pipeline.
Polarconsult reviewed this project using LIDAR data and found that approximately 5,300
feet of pipeline would be required to obtain 300 feet of head. The intake elevation would
MAY2,2008 PAGES
POLARCONSULT ALASKA, !NC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
be at approximately 850 feet, with the powerhouse at 550 feet. This option would
generate 220 kW in the summer and have a minimum power output of about 80 kW in the
winter. The transmission line associated with this project would be about 2.3 miles long.
Polarconsult evaluated other design configurations for hydropower on O'Brien Creek
(Polarconsult, 2005). These were high head options that considered the intake sited at an
elevation of about 1,950 feet and powerhouse located on either the Copper River or
somewhere along the lower reaches of O'Brien Creek. These options would have the
ability to produce significantly more power than the low head options. Depending on the
turbine size selected, this option could generate 470 kW in the summer and have a
minimum power output of about 390 kW in the winter.
The higher head option, with a substantial amount of extra energy available, was the
primary focus of investigations upon which this report is based. The LIDAR data
indicated that such a project appeared feasible and would be accessible via a road access
located about 2 miles south of the O'Brien Creek mouth near Eskilida Creek.
Both options on O'Brien Creek are discussed in more detail in the sections to follow.
Table 1 compares the various project configurations.
Table 1 -Project Configurations and Minimum Outputs
Location Basin area Head Min. Flow Min. Output
(sq mi) (ft) (cfs) (kW)
O'Brien low head 34.0 300 4.43 80
O'Brien high head 31.8 1500 4.13 390
Liberty Creek 27.9 550 3.63 130
Fivemile low head 13.2 300 1.73 30
Fivemile high head 12.6 1040 1.65 110
MAY2,2008 PAGE9
POLARCONSULT ALASKA, INC.
3.0 SELECTED PROJECT ANALYSIS
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Several hydro projects were considered for further analysis based on the potential to meet
the power needs of the community and be economically viable. The selected projects
were analyzed to determine if further investigation was appropriate. The projects
considered under this section are low head and high head project configurations on
O'Brien Creek and an analysis of a high head project on Fivemile Creek.
3.1 O'BRIEN CREEK, LOW HEAD PROJECT
A low head project that located the intake and powerhouse in the canyon near the
discharge of Fox Creek was considered by APA.
The project envisioned by APA, and considered here, is described using the LIDAR data
gathered and differs slightly from the AP A report due to more accurate topographic
information (Figure 2). The intake location for this project is at an elevation of about 850
feet. Siting the intake another 600 feet further upstream could net additional head;
however, the bank on the west side gets very steep and a large outcropping exists that
imposes a practical limitation for access. The AP A report placed the powerhouse near
Fox Creek at an elevation of 620 feet. Since a road is required for intake access, a better
solution is to locate the powerhouse further downstream at an elevation of about 550 feet.
This adds about 2,300 feet of penstock but reduces the transmission line length.
The field visit in 2007 afforded only a brief aerial look into this option. Based on
pictures and video, the intake site is rocky and gravelly with what appears to be a
significant amount of talus material coming off both banks. Construction of an access
road on the west bank will encounter the same soil conditions that were found higher up
in the drainage, namely unstable glacial till. Such soil conditions will make long-term
maintenance of and access to the intake difficult.
The intake location may present the problem of establishing an effective water cutoff due
to the potential for significant amounts of permeable material at the base of the creek bed
(Photo 1 ). This can make the collection of low water flows difficult.
The pipeline and access road would need to be adequately protected from slides and
erosion of the embankment (Photo 2). Enough loose material exists so that trenching
appears feasible; however, the material may not be suitable for backfill without
screening. A culvert or bridge over Fox Creek will be required as well.
The powerhouse site has enough area to adequately be located above flood stage and is
not on a steep slope. The transmission line would likely follow the access road.
Overall, this low head option for O'Brien Creek is more economical than the higher head
options evaluated. However, the project is expected to be more expensive and would
likely have a higher maintenance cost than a project on Fivemile Creek due to the narrow
and difficult canyon conditions and transmission line costs. Additionally, it is expected to
produce less power than Fivemile Creek. Should conditions on Fivemile Creek turn out
not to be very favorable, then a closer look at this project is worthwhile.
MAY 2,2008 PAGEIO
POLARCONSUL T ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
In comparison to the high head option on O'Brien Creek, this lower head project would
be better for just meeting Chitina's current energy needs.
Table 2 -O'Brien Creek Low Head Cost Estimate
Description Cost
Materials
Pipe $ 238,500
Turbine $ 150,000
Controls $ 70,000
Intake $ 85,000
Powehouse $ 80,000
Transmission $ 287,500
Access $ 50,000
Labor $ 250,000
Equipment $ 150,000
Shipping $ 150,000
Subtotal $1,511 ,000
Contingency (25%) $ 380,000
Subtotal $1,891,000
Profit/Overhead (25%) $ 470,000
Engineering $ 210,000
Administrative $ 70,000
Total $2,641,000
Table 3 -O'Brien Creek Low Head Project Summary
Basin Area 34.1 sqm1
Winter Minimum Flow 4.6 cfs
Design Flow 17.0 cfs
Pipeline Length 5,300 ft
Nominal Pipeline Dia 18 m
Transmission Length 12,350 ft
Intake Elevation 850 ft
Powerhouse Elevation 550 ft
Static Head 300 ft
Dynamic Head 220 ft
Design Power Output 220 kW
Winter Power Output 80 kW
MAY2,2008 PAGE 11
POLARCONSUL T ALASKA, INC.
3.2 O'BRIEN CREEK, HIGH HEAD PROJECT
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Several high head project configurations have been proposed for O'Brien Creek. The
Polarconsult 2005 report recommended a project where the powerhouse was located
along the banks of the Copper River about 1 Y2 mile downstream from the mouth of
O'Brien Creek (Figure 3). An access road was to be constructed 0.5 miles to the south
that was to follow an existing ATV trail. Access to the project and the transmission route
required the use of the Copper River Highway. Given the large amount of power that was
available with the high head project, this option appeared to be the most favorable.
Since the field investigation in 2005, extensive slide activity has occurred on the Copper
River Highway between the mouth of O'Brien Creek and the proposed powerhouse
location. The slide has been described as a major obstacle that will remain unstable for a
considerable time. The high cost and dangerous conditions* associated with the slide
have, for the time being, precluded further consideration of this alternative. For this
reason, a closer look at other options was undertaken in 2007.
* " ... repairing the original slide was going to cost an estimated $10 million and it's gotten a lot
worse since-it's not safe to work on the road. 'We had a hydrologist go look at it, and he said
the whole mountain is unstable,' Thies said. 'I don't see any way you can put that thing back in
shape.'" Fairbanks Daily News-Miner, March 12, 2007.
The fieldwork in 2007 primarily focused on finding a new powerhouse location and
project access route to avoid the slide area. The other alternatives considered locating the
powerhouse somewhere along the lower reach of O'Brien Creek with access ascending in
the same area. Additional work during the field trip involved evaluating soil conditions,
intake locations, and construction issues.
During the 2007 field trip, several conditions were encountered that affected previous
project concept design and cost assumptions:
1. It was discovered that the flood event of 2006 (USGS, 2006) completely reshaped
the intake area (Photos 4-8) and caused new landslides and slope stability
problems along the proposed pipeline route (Shannon Wilson, 2007).
2. The soil conditions along the penstock route were found to be poor with broad
areas of bog and discontinuous permafrost requiring more costly construction
methods.
3. The steep initial ascent of the access road would require the use of a winch line
and a helicopter to move personnel, equipment, and materials, resulting in
additional costs to access the project during construction and future maintenance.
Relocation of the powerhouse required crossing O'Brien Creek with the high pressure
pipe over a bridge able to withstand the 2006 flood and increasing the total pipeline
length by about 3,000 feet for a total of 18,500 feet. The transmission line would be
reduced by 1.3 miles for a total length of about 2.0 miles.
The project cost estimate was also affected by the presence of permafrost soils identified
along the penstock and access route (Shannon Wilson, 2007). Once disturbed, these soils
can thaw, creating pools of water and areas of active soil movement. If widespread, the
permafrost will dramatically slow the progress of pipeline installation. Where there is
MAY 2,2008 PAGE12
POLARCONSUL T ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
permafrost, anchors need to be installed to keep the pipe from floating when empty and to
provide restraint at bends and on slopes. A separate maintenance access route may be
necessary after initial construction to avoid subsequent bogs and poor soil strength where
the pipeline disturbance has melted the permafrost.
Both the additional access difficulties and the presence of poor soils significantly
complicated the design, construction, and maintenance aspects of the project. The
consequence of this is a large increase in the planning, engineering, and administrative
efforts. Similarly, due to unforeseen construction risk, the contingency costs also
increase substantially.
The extensive erosion, landslides, and slope stability concerns resulting from the 2006
flood also affect the project costs. The intake area was found to be inundated with
alluvial material. As a result, it is expected to be more difficult to capture low stream
flows.
The floods caused undercutting and large landslides along the side hill that the original
design called for benching the pipeline in. The unstable slopes dictate that the pipe
should now be buried at the base of the side hill along the edge of the creek. This will
require thicker wall high-density polyethylene (HDPE) pipe buried at a greater depth in
the flood prone area to withstand higher pressures and boulders in the backfill. To
maintain the same project power output, the pipe diameter will need to be increased to
compensate for the thicker walls.
As a result of these findings, the construction cost of a high head project is significantly
higher than previously estimated. An estimate of the total project cost for the high head
project with the powerhouse located on O'Brien Creek is presented in Table 4 with the
project specifications shown in Table 5.
The development of a high head project is not economical based on the cost and current
power requirements of Chitina. If a market for significantly more power were available,
this project would warrant further consideration. Such a project may have a rated
capacity anywhere between 900 kW and 2500 kW.
MAY2,2008 PAGE 13
POLARCONSULT ALASKA, INC.
Table 4-O'Brien Creek, High Head Cost
Description
Diversion I Intake I Desander
Penstock
Powerhouse/Turbine/Generator
Access and Bridge
Power Transmission System
Equipment
Labor
Shipping
Subtotal Direct Costs
Contingency (25%)
Subtotal Estimated Cost
Overhead & Profit (25%)
Total Construction Cost
Engineering
Construction Mana~ement
Total Project Cost
Cost
$150,000
$600,000
$300,000
$75,000
$420,000
$560,000
$375,000
$200,000
$2,680,000
$670,000
$3,351,000
$838,000
$4,188,000
$350,000
$165,000
$4,703,000
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Table 5 -O'Brien Creek, High Head Configuration
Basin Area 31.8 sqmt
Winter Minimum Flow 4.1 cfs
Design Flow 6.5 cfs
Pipeline Length 18,500 ft
Nominal Pipeline Dia 12 m
Transmission Length 17,600 ft
Intake Elevation 1,950 ft
Powerhouse Elevation 450 ft
Static Head 1,500 ft
Dynamic Head 1,130 ft
Design Power Output 470 kW
Winter Power Output 390 kW
PAGEI4
POLARCONSULT ALASKA, INC.
3.3 FIVEMILE CREEK
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
A project on Fivemile Creek was evaluated and is presented as the recommended project
for further investigation (Figure 4).
The initial review presented in the APA report indicated that a Fivemile Creek project
lacked sufficient water to generate enough power for local needs during the winter. In
addition, the project required a 4-mile extension of the transmission line to connect with
the community.
The impediments to developing Fivemile Creek were considered in 2005 and prompted
the investigation of a project on O'Brien Creek. O'Brien Creek was known to have more
than enough water to meet the power generation needs for Chitina, even during the
lowest flows of spring. At that time, the presumed location for the new diesel power
plant was in the town of Chitina, which would have required a 4-mile transmission line to
connect Fivemile to the city grid. As a result, a project on O'Brien Creek was considered
to be more feasible.
The high cost of developing O'Brien Creek and the decision to locate the new diesel
power plant near the airport prompted a more detailed review of the Fivemile Creek
project. During the 2007 field trip, an aerial reconnaissance of the Fivemile project area
was performed and a short excursion was undertaken to search for a possible intake
location and pipeline route out of the steeply incised canyon.
Analysis of the project indicated that a high head option for the project was the only way
to provide sufficient power to justify development of the project. This required
placement of the intake site near the 1,570-foot elevation contour. Aerial inspection of
the site indicated the possibility of mild side slopes suitable for a penstock route that was
not apparent during the prior review of topographic maps.
Considering Fivemile Creek as a potential alternative location for a hydroelectric facility
focused on the availability of water for power generation. Based on the fmdings of the
hydrological investigation (Appendix A), there appears to be enough water to make a
project viable on Fivemile.
The field inspection focused on a project with an intake elevation of 1,570 feet and a
powerhouse located near the Copper River at an elevation of about 530 feet. The choice
of intake location was based on review of the USGS contour map and a brief aerial
observation that confirmed more suitable terrain at the higher elevations. A handheld
GPS and altimeter was used to locate the possible intake location. An existing four wheel
drive trail that ascends the drainage on the ridge on the north side of the creek was used
to ascend to an elevation of approximately 1,450 feet followed by a foot survey to the
creek.
The terrain encountered included flat benches with soil and medium-sized spruce trees
and rock cliffs. The predominant terrain was a slight to moderate side hill (slopes of
about 2.5:1) with dense spruce and dead fall over soiL Active erosion, landslides, or
slope instability were not observed.
PAGElS
/? {IrA.)"-/
~(I+Jjrt
WloPs.
35500
I Fiscal= Year I Fiscai_Month I Calendar Year I Month I Communitt,.Names I KWH Gen Diesel I Fuel Used,.Diesel j kwh/gal I P (kW) I E (kWh) I Excess E (kWhll Excess% I diesel fuel need I df cost I
2007 1 2006 July Chitina 43439 3375 12.87 300 87600 44161 1 0
2007 2 2006 August Chitina 41255 3118 13.23 300 87600 46345 1 0
2007 3 2006 September Chitina 36798 2882 12.77 300 87600 50802 1 0
2007 4 2006 October Chitina 38789 3079 12.60 300 87600 48811 1 0
2007 5 2006 November Chitina 41382 3021 13.70 200 58400 17018 0 0
2007 6 2006 December Chitina 40557 2876 14.10 110 32120 -8437 0 632.46 2340.097
2007 7 2007 January Chitina 40332 2816 14.32 110 32120 -8212 0 615.59 2277.691
2007 8 2007 February Chitina 32384 2306 14.04 110 32120 -264 0 19.79 73.22339
2007 9 2007 March Chitina 34850 2554 13.65 110 32120 -2730 0 204.65 757.1964
2007 10 2007 April Chitina 29957 2265 13.23 110 32120 2163 0
2007 11 2007 May Chitina 34477 2742 12.57 200 58400 23923
2007 12 2007 June Chitina 36406 2755 13.21 300 87600 51194
450626 33789 13.34 264774 1 1472.488756 5448.208
2008 1 2007 July Chitina 40222 3118 12.90
2008 2 2007 August Chitina 37407 3164 11.82
2008 3 2007 September Chitina 32804 2829 11.60
2008 4 2007 October Chitina 34300 2919 11.75
2008 5 2007 November Chitina 33840 2897 11.68
2008 6 2007 December Chitina 37615 3129 12.02
2008 7 2008 January Chitina 36730 3099 11.85
2008 8 2008 February Chitina 36768 3148 11.68
1190938 91881 12.96
FY 2007 1 Jul-06
2 Aug
3 Sep
4 Oct
5 nov
6 Dec
7 Jan-07
8 Feb
9 Mar
10 Apr
11 May
12 Jun
POLARCONSUL T ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CH!TTNA, ALASKA
FINAL REPORT
It was concluded that a good probability of finding a penstock alignment could be
benched to avoid significant rock excavation. However, this initial impression is based
on visual observation and needs to be verified.
Below the intake site, Fivernile Creek flows through a confined canyon that becomes
more incised in the downstream direction. At the intake site, the creek is confined tightly
on the south side (opposite the pipeline side) by canyon-like cliffs and steep slopes. The
north bank at the intake, which is where the pipeline would traverse, had some exposed
rock but did have a stretch of flat to slightly sloped ground that may have consisted of
large alluvial material. The flat ground gave way to a steep slope and some cliffs about
100 feet away from the creek. Above the intake site, the north bank of the creek rises
steeply again then appears to flatten out again. Just downstream from the intake site, the
north bank appears to remain relatively flat and accessible for some distance.
The Fivemile Creek project would be high head with about 1,040 feet of elevation drop
between the intake and powerhouse. This project is able to produce 300 kW of electricity
at a flow of 5 cfs. The Fivemile Creek Project specifications are presented in Table 6.
Table 6-Fivemile Creek Project Specifications
Basin Area 12.65 sqmt
Winter Minimum Flow 1.65 cfs
Design Flow 5.0 cfs
Pipeline Length 8,500 ft
Nominal Pipeline Diameter 12 m
Transmission Length 2,000 ft
Intake Elevation 1,570 ft
Powerhouse Elevation 530 ft
Static Head 1,040 ft
Dynamic Head 940 ft
Design Power Output 300 kW
Winter Minimum Output 110 kW
Annual Potential Energy 2.04 GWh
Estimated Cost* $2,010,000
*Approximate estimate of costs based on assumed site conditions to be verified by further investigation.
3.4 CONCEPTUAL DESIGN
The Fivemile Creek intake area is fairly narrow and appears to be confined in a bedrock
channel that will allow for a relatively simple diversion to capture flows. Although the
total project flow is only 5 cfs, the small dam and intake will require a design to support
the occasional extreme flood with large trees and boulders being carried downstream.
However, site conditions suggested that the area withstood the 2006 floods without
significant bed or bank changes and channel meandering. Additionally, in the winter, a
substantial amount of glaciation is anticipated. As such, the dam and intake will be
subject to significant ice loads. Additional design features should include a pool deep
enough to prevent freezing of the slow moving water down to the streambed and
insulation to minimize heat loss.
MAY2, PAGE16
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
A significant amount of dead wood and spruce needles should be expected in the stream
flow. A self-cleaning screen system will be required to keep debris from entering the
pipeline. Power at the intake site is required to operate screening systems. A head level
control system will be required to monitor water availability.
The section of penstock extending approximately 3,200 feet from the intake is envisioned
to traverse the hillside until it crosses the existing four wheel drive trail. As described
above, the embankment on the north side of the intake is relatively flat, leaving sufficient
room to establish an access trail and pipeline bench. Collection of topographic survey
data will determine the best location for the pipeline and access route and, subsequently,
the intake location.
An inspection of the soil conditions was made along the four wheel drive access trail that
ascends from the Edgerton Highway up to the peak of the mountain on the north side of
Fivemile Creek. This trail leads to an abandoned mine. Only a few sections of the trail,
primarily close to the highway, have appreciable topsoil. Most of the trail was rocky with
large cobbles and occasional patches of exposed bedrock. The bedrock appeared
competent. If insufficient soil or loose rock is found along the pipeline route then burial
may be quite difficult. However, a gravel pit is located along the trail approximately ~
mile from the highway (per discussions with Martin Finnesand), and may serve as a
source of material for bedding, padding, and mounding the pipeline. Sufficient burial is
important for this project in order to obtain low-cost pipeline protection from movement
and insulation to guard against freezing.
HDPE pipe could be used for the 3,200-foot low pressure section. Steel pipe is required
for the remaining high pressure section. Once the traverse is completed out of the creek
canyon, there are several pipeline route options. The topography is at a 12% to 18%
grade.
This large potential area will dictate a thorough investigation to find the best route to
minimize construction and maintenance costs. A LIDAR survey of the area is
recommended to avoid terrain features shown on the low resolution USGS quad map.
A future geotechnical investigation along the proposed pipeline route should be done with
the intent of minimizing rock excavation and identifying good natural bedding
conditions. This route almost certainly will not coincide with the existing four wheel
drive trail. Crossing the Edgerton Highway will also be required. It is expected that the
pipeline will be buried under the highway.
The suggested powerhouse location was chosen to maximize the static head while
avoiding airport property. The final location selected should address these considerations
along with long-term erosion potential of the banks of the Copper River, vehicle access to
the powerhouse, pipeline alignment, transmission line length, and the pipeline crossing
location of the Edgerton Highway.
The State of Alaska Department of Fish and Game does not list Fivemile Creek as an
anadromous stream. Visual inspection of the mouth of the creek also indicates that this
stream is not suitable fish habitat. Therefore, the tailrace does not need to drain back into
Fivemile Creek. This will also simplify permitting requirements.
MAY2,2008 PAGEI7
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Table 7 -Fivemile Creek Cost Estimate
Item
Materials
Pipe
Turbine
Controls
Intake
Powerhouse
Transmission
Labor
Equipment
Shipping
Subtotal
Contingency (25%)
Subtotal
Profit/Overhead (25%)
Engineering
Administrative
Total*
Amount
$ 220,000
$ 150,000
$ 70,000
$ 50,000
$ 60,000
$ 50,000
$ 200,000
$ 150,000
$ 150,000
$1,100,000
$ 280,000
$1,380,000
$ 350,000
$ 210,000
$ 70,000
$2,010,000
*Approximate estimate of costs based on assumed site conditions to be verified by further investigation.
MAY2,2008 PAGE18
POLARCONSUL T ALASKA, INC.
4.0 ECONOMICANALYSIS
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
A comparative analysis of the O'Brien high head project and the Fivemile Creek high
head project alternatives were made against the projected diesel generation costs. Based
on this comparison, the Fivemile Creek project is superior to the O'Brien Creek project.
Further, the Fivemile Creek project will more than pay for itself in savings in fuel that
would otherwise have been used in the diesel plant.
The following assumptions were used to make this analysis:
Item Value
Fuel use in FY2007 33,789 gallons (AEA, 2008)
Fuel cost for 2008 $3.70 per gallon (Data from Martin Finnesand)
Increased demand on Airport tie-in 30kW*
Total Yearly Energy from Airport 25,000kWh *
Current peak demand for community 75 kW (Data from Martin Finnesand)
Power generated in FY2007 450,586 kWh/_l! (AEA, 2008)
Annual increase in energy growth 3.26%/year {LCMF, 2005)
Loan payment period 30 years
Real discount rate 3% (AEA Alternative Energy RFP, Dec. 6, 2007)
*Energy usage is estimated. A 25-kW genset can carry the DOT State Maintenance Facility Loads, and 5
kW is the estimate for the Clinic. Assumed average load is about 3 kW. Based on conversation with
Martin Finnesand.
For the purposes ofthis comparison, the analysis used the current peak demand of75 kW
plus the 30 kW probable demand for the Chitina Airport tie-in. Based on load growth
projections, the calculation for peak demand growth was made with the 75 kW demand
escalating for 30 years at a rate of 3.26% per year (LCMF, 2005).
The total energy demand used in these calculations is the FY2007 power generated
(450,586 kWh) plus the assumed static demand of 25,000 kWh from the airport and
clinic. Daily peak load requirements and subsequent diesel use were factored in as well.
Present worth values were then calculated based on the value of fuel displaced for diesel
generation by the respective hydro project. The following table summarizes the
construction costs, projected value of fuel saved, and the benefit to cost ratio under
different growth scenarios.
Table 8 -Economic Summary
Project Construction Cost
O'Brien, High Head $ 4,703,000
O'Brien, Low Head $ 2,641,000
Fivemile*** $ 2,010,000
* PV = Present value at real discount rate.
** B/C Benefit to cost ratio.
No Growth
Savings PV* B/C**
$ 2,600,000 0.6
$ 2,500,000 0.9
$ 2,600,000 1.3
3.26% Growth
Savings PV* B/C**
$ 4,100,000 0.9
$ 3,500,000 1.3
$ 3,900,000 1.9
*** Approx. est. of costs based on assumed site conditions to be verified by further investigation.
MAY2, 2008 PAGE19
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
This analysis did not include the potential benefits gained by using excess electricity for
heating or other purposes. The heating value of surplus electricity produced by the
projects can positively affect their economic values, offsetting local use of heating fuel.
MAY2,2008 PAGE20
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
5.0 CONCLUSION AND RECOMMENDATIONS
The 2007 field investigation provided additional information to evaluate the O'Brien
Creek hydro project alternatives. The field investigation also included the Fivemile
Creek project. This report includes a summary of previous projects in the area as well as
further evaluation of the O'Brien and Fivemile Creek alternatives.
Previously unidentified field conditions resulted in a significant change in the design
concept and cost assumptions for the proposed configurations on O'Brien Creek. These
changes were the result of a record flood in 2006 (USGS, 2006) that caused drastic
changes to the stream bed, resulted in slope stability problems, and caused landslides
along the proposed penstock alignment and Copper River Highway. The landslides along
the highway effectively cut off access to the project. In addition, discontinuous
permafrost was found along the penstock and access alignment. These conditions
required a re-evaluation of the conceptual design and negatively affected the project
economics and construction risks.
A preliminary investigation of Fivemile Creek was conducted to evaluate the
hydroelectric potential of the resource. A previous analysis of the Fivemile project
required the construction of a 4-mile-long power line to Chitina. Since the 2005 analysis,
an extension of the power line from Chitina to a new diesel powerhouse located at the
airport (immediately adjacent to Fivemile Creek) is planned and will be completed in the
near future. As a result, the economic viability of the Fivemile project is improved and
prompted further consideration during this investigation.
Field reconnaissance of the Fivemile project suggests that it is a favorable alternative to
the O'Brien Creek projects in several respects. The benefits include existing access,
better soil conditions, and a nearby interconnection point to the electric grid. In addition,
it is the lowest estimated cost and the best fit for Chitina's current electric requirements.
This results in favorable economics and significantly reduced construction risks.
A comparative analysis of the project alternatives was made against the projected diesel
generation costs. Based on this comparison, the Fivemile Creek project is superior to the
both O'Brien Creek projects. Further, should the electrical load increase as predicted by
LCMF, the Fivemile project remains the superior project in terms of economics and
ability to meet Chitina's energy needs.
The project on Fivemile Creek is currently envisioned as having a design output of 300
kW and a minimum winter output of 110 kW. The construction cost of the Fivemile
Creek project is $2,010,000. The Fivemile Project has a benefit to cost ratio of 2.0 in a
"growth" scenario and 1.3 in a "no growth" scenario.
Continued investigative efforts should focus on evaluating the potential of a hydro project
on Fivemile Creek.
MAY2,2008 PAGE2l
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Further investigative activities on Fivemile Creek should include:
• Installation of a stream gauge near the intake location
• Stream flow measurement to correlate weir readings at the culvert
• A Light Detection and Ranging (LIDAR) survey of the area suitable for project
layout
• Preliminary geotechnical investigation
• Identification of regulatory requirements
• Preparation of a conceptual design report
• Development of a project cost estimate
• Refinement of project economics
1
, i.J;
The cost to perform these investigative activities is estimated to be $100,000-$150,00d\_. \'1 1w
and will be used to prepare a conceptual design report and refine the project cost
estimate.
MAY2,2008 PAGE22
POLARCONSUL T ALASKA, INC.
6.0 REFERENCES
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
AEA (Alaska Energy Authority). 2008. Statistical Report of the Power Cost Equalization
Program, Fiscal Year 2007. February.
Alaska Community Database, Community Information Summaries (CIS). 2008.
http://www.dced.state.ak.us/dcalcommdb/CF CIS.cfm?Comm Boro Name=Chitina
APA (U.S. Department of Energy and Alaska Power Administration). 1981. Preliminary
Evaluation of Hydropower Alternatives for Chitina, Alaska. February.
EPS (Electric Power Systems, Inc.). 2003a. Chitina Electric Power Generation and
Delivery System Inspection. March.
EPS. 2003b. Lower Tonsina to Chitina Single Phase Overhead Tieline Feasibility Report.
July.
EPS. 2003c. Chitina Hydro Evaluation. August 28.
Fairbanks, Morse & Co. 1981. Hydraulic Handbook. First Edition.
LCMF. 2005. Conceptual Design Report, Chitina Rural Power System Upgrade, Draft
Revision 1. September 6.
Polarconsult (Polarconsult Alaska, Inc.). 2005. O'Brien Creek Hydroelectric Conceptual
Design. March 21.
Polarconsult. 2007a. O'Brien Creek Hydroelectric. October 31.
Polarconsult. 2007b. Fivemile Creek Inspection and Concept Design. October 31.
Shannon Wilson. 2007. O'Brien Hydroelectric Project, Geotechnical Report. November
14.
USGS (United States Geological Survey). 2006. Summary of Flooding in Southcentral
Alaska. October. http://ak. water. usgs.gov/flood/20060ctober/index.php
MAY2,2008 PAGE23
POLARCONSULT ALASKA, INC.
MAY2,2008
FIGURES
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
PROJECT VICINITY ~AP
PROJECT
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA. ALASKA 1
O'BRIEN CREEK
DRAWN: DH
CHECKED: ___ Ill.
polarconeult alaeka. Inc.
SCALI: 1"•& WII.!S
Fll.E: ----=1 1003 W1!:ST 33RD AVB. SU1TI 310 PHONE (80'7) 2015-2420
ANCH ORAGE, ALASKA VV~03 FAX 2~8-IUUI
PROJECT
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA 2
DRAWN: __ ....J!!!
CHECKED: ___ 011
SCAlf: 1"•6 IIUS
Rl£: __ __!!!!IW'q
..... ,
O'BRIEN CREEK HIGH HEAD PROJECT WAP
polarconault alaaka. Inc.
maRCY BTB"''D(I • mniiiOJifiUNT.Q. lfD'YICKB • IDIGIJGDUNG H81CN
UIOll WIIIIT 33RD AVII, surrB 310 PHONE (H7) 21111 -2420
ANCHORAGE, ALASU VV303 P'AX (V07) 2311-UUt
PROJECT
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA 3
4
llo\TE: 4/8/2008 c
DESIGNED: __ DH ~-::::::::=::=;=:=:=::=::=::=:=:=:::::===:=:::::==:==F'=IV=E=._.~I=LE==C~R~EE:;K:=P=R=O=J~E~C~T~._.;;A~P~=:::;:;:::::;;:::::::=======~
DRAWN: DH polarconault alaska Inc PROJEcT
CHECKED: __ Do\ • "
IDfDIOrr ..,..,..,. •• BJmiiOJOIICNTAL ""'""'"" •• NG!NDR!N~ DIBIGN REGIONAL HYDROELECTRIC INVESTIGATION
SCALE: 1"=6 NILES CHITINA, ALASKA
FlGURE
FILE: __ __!!!!!YAI'q 1603 W'l!:ST 33RD AVB. SUITl!: 310 PHONE (P07) 268-2.20
ANCHORAGE, AL.\SJtA Vlit~03 P'AX (&07) 2C!IB-2418
POLARCONSUL T ALASKA, INC.
MAY2,2008
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
PROJECT PHOTOS
POLAR CONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
PROJECT PHOTOS
PHOTO 1. O'BRIEN CREEK, LOW HEAD PROJEC! INTAKE SITE .............................................................................. 2
PHOTO 2. O'BRIEN CREEK CANYON AT FOX CREEK ............................................................................................... 3
PHOTO 3. O'BRIEN CREEK, HIGH HEAD INTAKE .................................................................................................... 4
PHOTO 4. O'BRIEN CREEK, HIGH HEAD INTAKE .................................................................................................... 4
PHOTO 5. O'BRIEN CREEK, HIGH HEAD INTAKE LOCATION BEFORE FLOOD .......................................................... 5
PHOTO 6. O'BRIEN CREEK, HIGH HEAD INTAKE AREA AFTER FLOODING ............................................................... 6
PHOTO 7. O'BRIEN CREEK, HIGH HEAD INTAKE AREA AFTER FLOODING ............................................................... 7
PHOTO 8. BANK EROSION NEAR FROM INTAKE ...................................................................................................... 8
PHOTO 9. DOWNSTREAM VIEW OF UPPER RIDGE ON O'BRIEN CREEK .................................................................. 9
PHOTO 10. UPSTREAM VIEW OF UPPER RIDGE ON O'BRIEN CREEK .................................................................... 10
PHOTO 11. VIEW OF SECOND RIDGE ON O'BRIEN CREEK .................................................................................... 11
PHOTO 12. SECONDRIDGEON0'BRIENCREEK ................................................................................................... 12
PHOTO 13. O'BRIEN CREEK POWERHOUSE SITE, HIGH HEAD PROJECT .............................................................. 13
PHOTO 14. SLIDESALONGCOPPERRIVERHIGHWAY ........................................................................................... 14
PHOTO 15. SLIDES ALONG COPPER RIVER ........................................................................................................... 15
PHOTO 16. ROAD ADJACENT TO FIVEMILE CREEK ............................................................................................... 16
PHOTO 17. EXPOSED ROCK FORMATION, FIVEMILE PROJECT .............................................................................. 17
PHOTO 18. FIVEMILEAERIAL PHOTO ................................................................................................................... 18
PHOTO 19. FIVEMILE CREEK, POSSIBLE INTAKE SITE ........................................................................................... 19
MAY2,2008 PAGE 1
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPoRT
Photo 1. O'Brien Creek, Low Head Project Intake Site
Taken from a screen capture of a video recording, this is a view looking upstream towards
the assumed location of the intake for the low head project on O'Brien Creek. Note the
fractured rocky embankment and unstable slopes. Capturing low water flows will be
difficult due to substrate permeability. (2007 Polarconsult)
MAY 2 ,2008 PAGE2
POLARCONSULT ALASKA, INC . REGIONAL H YDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPoRT
Photo 2. O'Brien Creek Canyon at Fox Creek.
View upstream along the pipeline route of the low head O'Brien Creek project. Access and
penstock bench would be located along the right side of the stream. (2007 Polarconsult)
MAY2,2008 PAGE3
POLARCONSULT ALASKA, INC.
Photo 3. O'Brien Creek, High Head Intake
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Creek bed and banks during flow measurement at intake area before flood. Photo taken just upstream from the intake and is looking
downstream. (2005 Polarconsult)
Photo 4. O'Brien Creek, High Head Intake
Photo was taken just downstream from the intake and is looking downstream. (2007 Polarconsult)
MAY2,2008 PAGE4
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Photo 5. O'Brien Creek, High Head intake location before flood
Intake was presumed to be located at the 1950' elevation that is near the bottom middle of the photo on the curve of the stream. Stream
flow is from left to right. (2005 Polarconsult)
MAY2,2008 PAGE5
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Photo 6. O'Brien Creek, High Head intake area after flooding
View looking downstream at intake location that is near the upper mid dle of the p hoto where the creek jogs to the left. The first ridge
crossing can be seen about a 114 mi further downstream at near the top middl e of the photo. (2007 Po larconsu lt)
MAY2,2008 PAGE6
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Photo 7. O'Brien Creek, High Head intake area after flooding
Photo shows debris and boulders moved during the 2006 flood event. (2007 Polarconsult)
MAY2,2008 PAGE7
POLARCONSULT ALASKA, INC . REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Photo 8. Bank Erosion Near from Intake
Along the east embankment of O'B rien Creek just upstream from the intake. Due to slope
stability concerns, the p ipeline and access would have to be located at the toe of the slope.
(2007 Polarconsult)
MAY2,2008 PAGE8
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, A LASKA
FINAL REPORT
Photo 9 . Downstream View of Upper Ridge on O'Brien Creek
This photo shows the first (upper) ridge crossing for the O'Brien Creek project. The requ ired cut through the ridge is approximately 25
feet. Geologist indicates that this cut will likely not encounter rock. (2007 Polarconsult)
MAY2,2008 PAGE9
POLARCONSULT ALASKA, INC.
Photo 10. Upstream V iew of Upper Ridge on O'Brien Creek
REGIONAL HYDROELECTRIC INVESTIGATION
CmTINA, ALASKA
FINAL REPORT
View of the first ridge crossing on O'Brien Creek. Active erosion is visible indicating loose material. Competent rock plane is visible on
the right side of the ridge . (2007 Polarconsult)
MAY2,2008 PAGE 10
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Photo 11. View of Second Ridge on O'Brien Creek
This photo is taken from the top of the first ridge looking downstream. The pipeline and
access route would be located along the creek bed because unstable slopes prevent
benching (numerous areas of erosion are visible). The second ridge crossing is visible in
the top middle of the picture as the low spot along the hill crest. (2007 Polarconsult)
MAY2,2008 PAGE ll
POLARCONSULT ALASKA, INC.
Photo 12. Second Ridge on O'Brien Creek
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
This is a closeup of the second ridge and the basin divide looking downstream from the upper ridge. As evidenced by the erosion, the
ridge appears to consist ofloose material. The cut through this ridge would be about 25 feet. (2007 Polarconsult)
MAY2,2008 PAGE 12
POLARCONSULT ALASKA, INC.
MAY2,2008
REGIONAL HYDROELECTRIC INVESTIGATION
ClnTINA, ALASKA
FINAL REPORT
Photo 13. O'Brien Creek Powerhouse Site, High Head Project
(2007 P olarconsult)
PAGE 13
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
MAY2,2008
Photo 14. Slides Along Copper River Highway
(2007 Polarconsult)
PAGE 14
POLARCONSULT ALASKA, INC.
Photo 15. Slides Along Copper River.
REGIONAL HYDROELECTRIC INVESTIGATION
CmTINA, ALASKA
FINAL REPoRT
This photo shows slides that occurred along the Copper River between O'Brien Creek and Eskilida Creek. This area was the presumed
access route recommended in the 2005 report. (2007 Polarconsult)
MAY2,2008 PAGE 15
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITlNA, ALASKA
FINAL REPORT
Photo 16. Road adjacent to Fivemile Creek
The road was constructed for mine access and goes to the top of the peak just south of
Liberty Creek. (2007 Polarconsult)
MAY2,2008 PAGE 16
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
Photo 17. Exposed Rock Formation, Fivemile Project
This exposed rock formation was found during the traverse to the intake site and appears to
be visible in the aerial photo. (2007 Polarconsult)
MAY2,2008 PAGE 17
POLARCONSULT ALASKA, INC.
CONTOURS FROM USGS DEM
DATA. AERIAL PHOTO IS NOT
ORTHORECTIFIED.
~' ~ ~ESTIMATED
LOCATION
Photo 18. Fivemile Aerial Photo.
REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPoRT
This aerial shows the low pressure pipe area. The creek does not become steeply incised until well below the intake site.
MAY2,2008 PAGE 18
POLARCONSULT ALASKA, INC.
Photo 19. Fivemile Creek, Possible intake site.
REGIONAL HYDROELECTRIC INVESTIGATION
CmTINA, ALASKA
FINAL REPORT
Note basement rock outcrop on left and narrow stream section . Stab le stream banks and spruce tree on right suggest insignificant
damage to site from the 2006 flood. (2007 Polarconsult)
MAY2,2008 PAGE 19
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
APPENDIX A-HYDROLOGY ANALYSIS
MAY2,2008
CHITINA HYDROLOGY ANALYSIS
April 11, 2008
prepared by
polarconsult alaska, inc.
1503 West 33rd Avenue, Suite 310
Anchorage, Alaska 99503
Phone: (907) 258-2420
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
TABLE OF CONTENTS
TABLE 1 -HYDROLOGIC BASIN SIZE, ELEVATION, AND LOCATION ........................................................................ 2
FIGURE 1-USGS MEDIAN DAILYUN1T FLOWDATA(CFS/SQt\11) .......................................................................... 3
TABLE 2 -FLOW MEASUREMENTS .......................................................................................................................... 4
TABLE 3 -WINTER HYDROGRAPH FACTORS .......................................................................................................... 4
FIGURE 2 -O'BRIEN CREEK SUMMER FLOWS CORRELATED TO USGS GAUGE SITES .......................................... 5
FIGURE 3 -LITTLE TONSINA MEDIAN UNIT FLOW AND CHITINA ESTIMATED UNIT FLOW .................................... 6
FIGURE 4 -FIVEMILE CREEK POWER OUTPUT ... ············· ....................................................................................... 6
PHOTO 1 -O'BRIEN CREEK FLOW MEASUREMENT 1, -0.7 MI ABOVE INTAKE SITE ............................................... 7
PHOTO 2 -O'BRIEN CREEK fLOW MEASUREMENT LOCATION 2, AT !NT AKE SITE .................................................. 8
FIGURE 5 -O'BRIEN CREEK FLOW MEASUREMEI'>TS MAP ..................................................................................... 8
FIGURE 6 -FIVEMILE CREEK WEIR DESIGN ......................................................................................................... 10
PHOTO 3 -lNST ALL ED WEIR, EARLY IN WINTER ................................................................................................... 11
PHOTO 4 -VIEW OF WATER SPILLING OVER WEIR ................................................................................................. 11
PHOTO 5 -VIEW OF WEIR, LATER WINTER ............................................................................................................ 12
TABLE4-WEIRIFLOWMEASUREMENTS .............................................................................................................. 12
APRIL 11 , 2008
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
An analysis of the hydrology in the Chitina area was conducted to estimate the quantity of
water available to the projects being evaluated. The stream flow characteristics directly
affect the power production and associated economic viability of the respective projects.
None of the creeks in the Chitina area have continuous stream flow data available. The
USGS performed numerous summer and fall flow measurements looking for high flows in
O'Brien Creek but only performed one low flow measurement in April. This information is
presented in a study performed by AP A in 1981. These measurements were made near the
mouth of O'Brien Creek just upstream of the bridge. The study further stated that local
residents indicate the stream runs year-round.
The 1981 study made an effort to forecast the low winter flow and power production using
data from Squirrel Creek. The resulting low flow was estimated to be between 3.4 and 2.2
cfs.
The USGS has gauging data for the Little Tonsina River, Tebay River, and Squirrel Creek,
all of which are situated at latitudes similar to O'Brien Creek and Fivemile Creek. The
following table summarizes the various locations, basin sizes, and elevations for the project
locations discussed and the three USGS sites.
Table 1 -Hydrologic Basin Size, Elevation, and Location
USGS Site Basin size Elevation Latitude Longitude Begin No of
Location No End Date Records
O'Brien Mouth 46.3 450 61.4817 -144.4556
O'Brien Intake, APA 34.0 920 61.4733 -144.4906
O'Brien Intake, PCA 31.8 1950 61.4608 -144.5408
Fivemile Culvert 13.3 620 61.5822 -144.4375
Fivemile Intake, APA 13.2 890 61.5811 -144.4475
Fivemile Intake, PCA 12.6 1550 61.5781 -144.4819
Little T onsina River 15207800 22.7 1850 61.4800 -145.1500 9/1/1972 9/30/1978 2221
Tebay River 15211500 55.4 1796 61.2300 -144.2000 7/1/1962 6/30/1965 1096
Sguirrel Creek 15208100 70.5 1520 61.6700 -145.1800 7/1/1965 9/30/1975 3744
All data from each USGS site was averaged for each day and divided by the basin area to
get the average daily flow per square mile for each of the gauged sites. The following chart
shows the results.
APRIL ll, 2008 2
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
Figure 1 -USGS Median Daily Unit Flow Data (cfs/sqmi)
8 -' ·e -Tebay
C'
7 ~ -L Tonsina Unit Flow
.1!! -Squirrel .£.
6 ~
0
iL
5 :: c
::J
4
3
2
1
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
As shown in Figure 1, there is an extreme amount of variability, both in the summer and
winter. Squirrel Creek has significantly lower flows than both the Tonsina and Tebay on
discharge per unit area basis. This is probably due to the fact that it is further north and
most of the basin lies on the north flank of the Chugach Range. Squirrel Creek probably
lacks precipitation due to down sloping effects under the predominant southerly flow
regnnes.
On a discharge per unit area basis, both the Little Tonsina River and the Tebay River
exhibit very similar winter flow characteristics. The summer flows, which differ
significantly, are not relevant for the size of project that is being considered in Chitina.
Because of the climate conditions in Chitina, the stream flow in all of the creeks in the area
tends to drop off rapidly at the onset of winter. It quickly reaches a low flow that is
relatively constant until the spring thaw. For purposes of providing power year round, this
low flow period is critical for determining the project economics. Generally, all of the
projects in this report and in the AP A report easily exceed Chitina's power requirements in
the summer. The AP A report recognized the importance of this low flow p eriod and,
rightfully, made it one of their primary concerns in evaluating the various project options.
The following table is a list of actual low flow measurements made on O'Brien and
Fivemile Creeks. This data is compared with averages and minimums on the USGS sites.
APRIL 11 , 2008 3
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
Table 2-Flow Measurements
Location
O'Brien Mouth
O'Brien Intake, PCA
------·Date __ Fio~jfisl __ .:;;_U.:_:_ni-'-t _F:...:.Io ...... w_,(""-cf=s:_::./s_:Jq_mc..c.i'-) _
Fivemile Culvert
Fivemile Culvert
Fivemile Culvert
Fivemile Culvert
Little Tonsina River, Median Min
Tebay River, Median Min
Squirrel Creek, Median Min
Little T onsina River, Min
Tebay River, Min
Squirrel Creek, Min
4/23/1976 4.00 0.086
4/15/2005 4.00 0.126
1/7/2008 2.44 0.183
2/6/2008
2/20/2008
3/5/2008
3/9
4/15
3/8
4/1/1974
4/15/1964
4/5/1967
2.26
2.10
1.93
4.50
16.00
11.50
3.00
14.00
9.00
0.170
0.157
0.145
0.198
0.289
0.163
0.132
0.253
0.128
As stated in the APA report, the USGS measured a stream flow of 4.0 cfs on 4/23/1976. On
the same date (4/23/1976) that the USGS measured the O'Brien flow, the USGS gauge data
at Little Tonsina River was 6 cfs, whereas the median for that day is 5.5 cfs. The lowest
Tonsina record is 3 cfs. No similar comparison data is available for the flow measurements
done in 2005 and 2008.
The first three readings taken at the Fivemile Creek culvert were not collected in the
springtime when the absolute minimum flow is likely to occur; however, the final
measurement made on 3/5/08 nearly coincides with the minimum spring flow on the Little
Tonsina. All of the above spring flow measurements at O'Brien and Fivemile Creeks
indicate the springtime unit stream flows near Chitina are lower than the median values at
the gauged USGS sites.
The USGS reading done on 4/23/1976 at the O'Brien mouth is significantly less than that
measured by Polarconsult on O'Brien and Fivemile Creeks. A possible explanation for this
is that a significant portion of the stream flow occurs as groundwater flow. The USGS
measurement was taken at the mouth, where the streambed consists of a gravel outwash
plane that would allow for such an occurrence.
The 4/23/76 flow measurement at the O'Brien mouth will be discarded as an outlier.
Therefore, choosing the Little Tonsina River as the basis for a unit winter hydrograph, the
following data points are used to obtain an appropriate scale factor.
Table 3-Winter Hydrograph Factors
Location Date Flow Unit Flow L Tonsina Unit Flow Ratio Predicted Flow % Diff
O'Brien Intake, PCA 4/15/2005 4.00 0.126 0.220 57% 4.60 15%
Fivemile Culvert 1/7/2008 2.44 0.183 0.264 69% 2.32 -5%
Fivemile Culvert 2/6/2008 2.26 0.170 0.264 64% 2.32 2%
Fivemile Culvert 2/20/2008 2.10 0.157 0.242 65% 2.12 1%
Fivemile Culvert 3/5/2008 1.93 0.145 0.198 73% 1.74 -10%
Average 65.7%
APRIL 11, 2008 4
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
As shown, the resulting average ratio is 65.7%. This factor was applied to the winter
portion of the Little Tonsina data set to obtain daily average fl ow values that directly
convert to project output. The predicted flows for the dates that actual flows were
measured are shown in the table also.
The remainder of the unit hydrograph, early summer through early winter, is obtained from
the Little Tonsina River flow record as well. A comparison with the Little Tonsina and
Squirrel Creek basins was performed using the stream flow measurements done by the
USGS at O'Brien Creek that are presented in the AP A report. (The AP A report data is
included on page A-13.) The following chart clearly indicates that O'Brien Creek flows
correlate well with the Little Tonsina River (88%) and not very well with Squirrel Creek
(52%).
Figure 2 -O'Brien Creek Summer Flows Correlated to USGS Gauge Sites
14.0 _,-------~-~----------~------,
12.0
e 1o.o
CT
1/) i 8.0 u -~ 6.0 u::
:!:::
t:
:J 4.0
2.0
0.0 ~-
0 0 ..-,.... ,.... ,.... .._ .._ .._
'<t ..-,....
..-0 0 .._
1.0 0 .._ co 0 ..-0
N N N ('I) '<t '<t 1.0
t::: ,.... ,.... ,.... ,.... ,.... ,....
(0 .._ .._ 05 .._ .._
O'l O'l ,.... co 1.0
0 ..-N 0 ..-N N .._ .._ .._ .._ (0 .._ .._ co CX) O'l co ,.... co 0 0 0 0 0 0 0
1.0 1.0 co co co co ,.... ,.... ,.... ,.... CX) O'l O'l ,.... ,.... ,.... t::: ,.... ,.... ,.... ,.... ,.... ,.... ,.... ,.... t::: .._ .._ .._ .._ .._ .._ .._ .._ .._ (0 .._ ..-'<t ('I) co ('I) '<t '<t co O'l CX) ('I) 1.0
0 0 N N ..-N ~ 0 0 N 0 0 ~ .._ .._ .._ (0 .._ .._ .._ .._ .._ .._ .._ ,.... O'l '<t ,.... CX) ,.... CX) O'l ,.... 1.0
0 0 0 0 0 0 0 0 0 0 0 0 0
Date
Based on the above, a unit hydrograph is developed using the median unit flows of the
Little Tonsina winter data scaled by a factor of 65.7 %. The graph is then scaled up linearly
from the middle of April through the end of May to match the Little Tonsina River (on a
cfs /sqmi basis). From the end of May until the end of September, the graph is simply the
Little Tonsina River median record scaled by basin area. Then the graph is scaled back
down linearly from the beginning of October through November using the 65 .7% winter
production factor. The following chart shows the Little Tonsina River median hydrograph,
the scale factor used, and the resulting O'Brien/Fivemile Cre ek (Chitina) hydrograph.
APRIL 11 , 2008 5
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
Figure 3-Little Tonsina Median Unit Flow and Chitina Estimated Unit Flow
4.5
4
3.5 -
3
2.5 -·e
C"
2 ~
!II -J!
C.) -
1.5 ~ ~
IL.
:!::: 1 c:
::J -L Tonsina Unit Flow
-Chitina Unit Flow
0.5 -Chitina Scale Factor
0
..... ..... ..... ..... ---..... N ("I) 0 .....
The resulting estimated median minimum springtime flow for the O'Brien Creek intake
(PCA) is 4.1 cfs, and for the Fivemile Creek intake, 1.6 cfs. Using a maximum flow of 5
cfs, the following chart shows the estimated power output for a project on Fivemile Creek
along with the assumed stream flows. The stream flow should be verified through physical
measurements and the installation of a stream gauge.
350 -~ -300 ...
Gl ~
0
D..
250
200
150
100
50 ..... ..... --..... N
APRIL 11, 2008
..... ..... ..... ..... -("I) co 05 0 .....
Figure 4 -Fivemile Creek Power Output
..... -..... .....
.....
C\i .....
6
POLARCONSULT ALASKA, I NC. CHITINA HYDROLOGY ANALYSIS
FLOW MEASUREMENT DATA AT O'BRIEN INTAKE SITE. 4/15 /2005
Location 1 (-0.7 mi upstream of intake site) Location 2 (intake site)
N61 °27 .8536' W144 °33. 6790' N61°27.6543' W144°32.5137'
4/15/2005 13:00 Flow 4.1 4/15/2005 15:00 Flow 3.9
s d v q s d v q
2 0.00 0.00 0.00 2 0.00 0.00 0.01
3 1.05 0.00 0.00 3 0.55 0 .20 0.11
4 1.20 0.30 0.36 4 0.41 0 .55 0.23
5 1.18 0 .25 0.30 5 0.78 0 .55 0.43
6 1.62 0.40 0.65 6 0.37 0 .00 0.00
7 1.17 0.60 0.70 7 0.58 0.00 0.00
8 0.93 0.60 0.56 8 0.91 0 .00 0.00
9 1.09 0.45 0.49 9 0.75 0.35 0.26
10 1.05 0.50 0.53 10 1.16 1.00 1.16
11 0.98 0.40 0.39 11 1.08 1.20 1.30
12 0.57 0 .28 0.16 12 0.82 0.50 0.41
13 0.70 0.00 0.00 13 0.00 0.00 0.00
14 0.00 0.00 0.00 14 0.00 0 .00 0.00
~
I
I
Photo 1-O'Brien Creek Flow Measurement 1, -0.7 mi above intake site
APRIL 11 , 200 8 7
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
Photo 2 -O'Brien Creek Flow Measurement Location 2, at intake site
:-. :"1-~e k .
'-=--~-~~· .,.,....... ...
33
FLOW MEASUR MENT .1
--;:5'·
--------~~---~-~~?-~~¥~--~-;~~~~~~~~~~~---~~~~~~~~
Figure 5 -O'Brien Creek Flow Measurements Map
APRIL 11,2008 8
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
FLOW MEASUREMENT DATA AT FIVEMILE CREEK CULVERT
Measurements at Fivemile Creek were performed by installing a weir at the outlet of the
culvert that goes under the Edgerton Highway. The following drawing and pictures detail
the weir design and installation. Measurements and installation were performed by Martin
Finnesand of Chitina Electric and reported to Polarconsult. The table following the
photographs summarizes the measurements and the flow values.
APRIL II, 2008 9
POLARCONSULT ALASKA, INC. CHITINAHYDROLOGY ANALYSIS
FACE OF
CULVERT
r \\
2~ '
'
WEIR fORMULA, Q "' ·
L ,.
,~ .. MIN
~" -----<--~
I ~------------5'------------~
~------------------------s·--------------------~-4
C0 WEIR ELEVATION
SCALE: 3/4" = 1'
1----------1'± -----1
3/4"t~x4" BOLT
IN 7/8" HOLE
1----6" ----1
BENT OR WELDED
1/4" PLATE, 2" WIDE
TACK WELD NUT AND STUD
0. WEIR SECTION
SCALE: 3" = 1'
WATER SURFACE
(ESTIMATED)
2 LAYERS 1" EXTERIOR
RATED PLYWOOD . GLUE
AND SCREW TOGETHER
(POLYURETHANE GLUE)
1/4" THICK RUBBER SEAL
{GLUE TO PLYWOOD)
8.5" All THREAD
FLAT WASHER
Figure 6 -Fivemile Creek Weir Design
APRIL II, 2008 10
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
Photo 3 -Installed Weir, early in winter
Photo 4 -View of water spilling over weir
APRIL 11,2008 II
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
Photo 5 -View of weir, later winter
Water Height Measurements (above crest):
Table 4 -Weir/Flow
Measurements
Date
1/7/2008
2/6/2008
2/20/2008
3/5/20 08
Height (ft) Flow (cfs)
0.44 2.44
0.42 2.26
0.40 2.10
0.38 1.93
APRIL II , 2008
PUMP TESTING 209
Following are sketches of various weir types, with formulas for
calculation of flow over each :
Rectangular Su;>presse:l
~-------8------~
Francis Formula, Q = 3.33Bh3'~
or the more accurate Rehbock
Formula,
Q = ( 3.228 + 0.435 h.) B!J ;I •
z ~.-
V -Notch
Thompson Formula,
Q = 2.54h'l•
Rectangu'ar Contracted
8
Francis Formula,
Q = 3.33h8/~ (B-0.2h)
Cipolletti
Sides Slope 1 :4
Cipolletti Formula,
Q = 3.367Bh'i '
12
POLARCONSULT ALASKA, INC. CHITINA HYDROLOGY ANALYSIS
The following USGS flow measurements performed at O'Brien Creek were presented in
the Preliminary Evaluation of Hydropower Alternatives for Chitina, Alaska (U.S.
Department of Energy and Alaska Power Administration, 1981 ).
O'Brien Creek
Hydrology -USGS data
Drainage Area a = 44.8 sq. mi.
Year
Recording
date
Gage
Ht.-ft
19fcl
1971
1972
7/71
8/72
6/9/72
9/29/72
1973 7/73
1974 6/74
1975 7/1/75
1976 8/76
7.32
5.16
4.34
3.66
4.47
3.87
Miscellaneous data from USGS report 1976, Page 260
5/14/70
8/18/70
8/18/70
10/01/70
6/7/71
6/9/72
8/16/72
9/29/72
6/7/73
6/19/74
7/26/74
6/25/75
9/4/75
4/23/76
7/13/76
8/24/76
1977 7/77
1978 6/12/78
Unpublished USGS data
APRIL 11, 2008
5/24/77
7/6/77
8/9/77
9/28/77
7/6/78
5/3/79
5/25/79
6/26/76
4.12
unknown
cfs
310
1670
830
192
36
492
317
530
440
93
231
74
36
137
192
111
36
101
80
69
291
46
4.0
153
58
770
102 or more
107
576
210
74
182
47
86
180
13
POLARCONSUL T ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
APPENDIX B-GEOTECHNICAL REPORT, SHANNON WILSON
MAY2,2008
November 14, 2007
Polarconsult Alaska, Inc.
1503 West 33rd Avenue, Suite 310
Anchorage, Alaska 99503
Attn: Mr. Earle Ausman, P.E.
SEA TILE
RICHLAND
PORTLAND
FAIRBANKS
ANCHORAGE
DENVER
SAINT LOUIS
Phone: (907) 258-2420
RE: O'BRIEN CREEK HYDROELECTRIC PROJECT, CHITINA, ALASKA
This letter report documents the results of reconnaissance studies by Shannon & Wilson,
Inc. for the O'Brien Creek Hydroelectric Project near Chitina, Alaska. The project includes the
development of a pipeline along O'Brien Creek approximately 3 miles long. The pipeline will
stretch between a water intake structure and a power house on O'Brien Creek approximately 4
and lf4 miles, respectively, upstream from its confluence with the Copper River. At the time of
our site visit, the exact locations of the project structures and the alignment had not been
finalized. The purpose of this study was to visit the various portions of the project with the
design team and the Alaska Energy Authority (AEA) and observe the soil and rock conditions
visible from the surface. The observations made during our reconnaissance are to be used in
developing preliminary, conceptual design of the project features, and in feasibility studies.
Presented in this letter is a description of our reconnaissance efforts, field observations made
during reconnaissance, and opinions about further development of the project.
Shannon & Wilson performed this work in accordance with our agreed-upon scope which
included approximately three days for the field reconnaissance and eight hours for preparation of
this summary letter report. Mr. Earle Ausman of Polarconsult Alaska, Inc. authorized the work
verbally on September 28, 2007.
Field Reconnaissance
The reconnaissance effort took place between October 3 and 5, 2007, and was conducted
by Mr. Kyle Brennan, P.E., a geotechnical engineer from our Anchorage office. Our field
explorations included aerial observations, hand-excavated test pits, and surface observations
along the project alignment. Reconnaissance was conducted with helicopter support provided by
Era Helicopters from Valdez, Alalska. . We made observations along the project corridor at
discrete locations that we recorded using a handheld Global Positioning System (GPS) unit. The
notes collected during our reconnaissance are summarized in the attached spread sheet and
5430 FAIRBANKS STREET ·SUITE 3
ANCHORAGE, ALASKA 99518
907·561·2120 FAX 907·561·4483
32-1-01942
O'Brien Creek Hydroelectric Project,
Chitina, Alaska
November 14, 2007
Page2
SHANNON &WILSON, INC.
selected photographs are included on the attached photo pages. Approximate locations of the
observation stations are plotted on a United States Geophysical Survey (USGS) quadrangle map
included as Figure 2.
Observations
After conducting our site visit, it is our opinion that the project area traverses four distinct
regions, each with its own unique characteristics. These four regions are indicated on the
attached site plan (Figure 1) and are referred to in this report as the Intake, Upper Pipeline,
Middle Pipeline, and Lower Pipeline Areas.
The Intake Area includes Observation Points OP-01 through OP-06. This area of
O'Brien Creek appears to be in an erosional state as the main channel is lined by terraced
benches of sand and gravel on its south side. The channel bottom meanders through this area and
we observed log and debris jams frequently in this area. The soil slopes on the south side of the
river appear to be relatively stable and vegetation (alders and willows) appear to be well
established, except for a few isolated circular slide features. This portion of the channel appears
that it could be a relatively high energy area during high flow events as we observed boulders up
to 8 feet in diameter. At the east end of this area, the creek rounds a sharp rock knob and
moraine ridge (effectively damming the river and forcing it to flow around the rock knob)
extends from the knob to the south. The ridge is shown on Photos 5 and 8 and appears to
comprise till material which we estimate, from limited surface exposure, that it likely includes
silt, sand, and gravel with scattered cobble and boulder-sized material.
The Upper Pipeline Area is the portion of the project that includes Observation Points
OP-7 through OP-12. This portion of the alignment traverses a north-facing soil slope above
O'Brien Creek. Photographs 9, 13 and 17 show the typical signs of instability along the slope
and suggests that the slope is active and in an oversteepened and erosional state. The soils
exposed in the slides were consistent with typical glacial till soils and tended to consist of
gravelly, silty sand with scattered areas of cobbles and boulders. The failure areas appeared to
consist of mostly circular slumps that, on average, appeared to propagate 1 0 to 20 feet into the
subsoils. The exposed scarps were typically 35 to 40 degree slopes and we observed tension
cracks above crests of most of the scarps in the undisturbed portion of the slopes. The creek area
at the bottom of the slopes is somewhat wider than in the Intake Area and is choked in areas with
logs and other debris. The creek appears to be in an erosional state here also as it is meandering
on the valley floor and eroding the toe of the soil slope to the south.
32-1-01942
O'Brien Creek Hydroeiectric Project,
Chitina, Alaska
November 14,2007
Page3
SHANNON &WILSON, INC.
The Middle Pipeline Area includes the portion of the project covered with Observation
Points OP-13 through OP-15. In this area, the project traverses off the steep slopes above
O'Brien Creek and onto a flat, gently sloping table land. The ground cover in this area ranges
from alders and willow trees to spruce stands with boggy areas. We excavated two hand-dug test
pits in this area (near Observation Points OP-13 and OP-15). Near Observation Point OP-13 we
encountered approximately 1. 7 feet of peat overlying gray, silty, clayey sand. Below 1.5 feet in
this test pit, the soils were frozen. Near Observation Point OP-15, we encountered 3.5 feet of
peat and organic silt over silty, gravelly sand with no frozen soil. Given the project vicinity and
our observations in the test pits, we believe that this portion of the project likely contains
discontinuous permafrost that is likely ice rich and not thaw stable. In addition, we observed
only one area along this portion of the project where rock outcropped at the ground surface and
that was just northeast of Observation Point OP-14. We anticipate that much of this area is
covered with peat soils that likely average around 5 feet thick overlying silty, moraine soils.
Bedrock is likely deeper than 5 to 10 feet below the ground surface over most of this portion of
the project.
The Lower Pipeline Area comprises Observation Points OP-16 and OP-17 and marks the
area where the slope begins to steepen as the project approaches O'Brian Creek and the potential
power house location. In general, slopes in this area range from 25 to 35 degrees and vegetation
is well established. Much of this area is covered with peat ori the ground surface, except for the
final slope into the O'Brien Creek channel (between Observation Points OP-16 and OP-17)
where bedrock appears to be covered with only 6 to 12 inches of organic silt soil. The bedrock
consists of black shale that is platy'in nature and strongly bedded. The slope in this area appears
to follow the orientation of the bedding of the bedrock and where exposed, the rock is slippery
and has a greasy texture.
Conclusions
In general, the design and construction of the proposed project facilities should present
some significant challenges. Much of the mineral soil along the project is glacial moraine and by
virtue of its gradation, will likely be difficult to handle during construction. These types of soils
are typically dense or very dense in place and will need to be excavated with relatively large
earth-moving equipment. Also, they are moisture sensitive and once they are disturbed and
exposed to moisture, they will likely tend to . loose strength and be difficult to place with
compaction control. Additionally, these soils tend to be frost sensitive and tend to heave when
frozen in the presence of excess water.. Organic soils also persist over much of the project and
32-1-01942
#
O'Brien Creek Hydroelectric Project,
Chitina, Alaska
November 14, 2007
Page4
SHANNON &WILSON, INC
they too provide some of the same challenges in handling during construction. Organic soils also
compress under loading and may not be able to reliably support construction equipment.
The slopes on the south side of O'Brien Creek in the Upper Pipeline Area are active
slopes and are in a cycle that includes periodic sliding, erosion of the slope toe by the creek,
subsequent over-steepening, and additional sliding. Construction on these slopes will be
hazardous and disturbance of the slops and vegetative mats will allow additional moisture to
penetrate into the ground and reduce overall stability. It is our opinion that these slopes should
not be host to a buried water line and they should be avoided during construction. On slopes that
are not currently sliding, but are above unstable slopes, setbacks should be established and the
final design should include some sort of drainage provision that would not allow water to load
the slope from the pipeline trench and other features that mitigate slope disturbance and
destabilization.
Features that are located in the flood channel of O'Brien Creek should be designed to
withstand flood events and the associated erosion and deposition of stream sediments. Our
observations indicate that much of the creek is in an erosional state and that the main channel
meanders in the relatively narrow canyon bottom. Given the narrow width of the channel and
steep side slopes, we believe that the river system may be prone to damming by debris slides and
break-out floods that can carry large amounts of sediment down-stream.
In general, the rock conditions along the project {where exposed) appear to be favorable
for use in development of the project. The rock, while shaley and platy in nature, should provide
support for rock anchors if used in the design of this project. Further observation and analysis
should be conducted to establish the type and depth of penetration for these anchors.
Additionally, given our observations, we believe that the bedrock will likely be rippable to
several feet or more below the soiVrock horizon depending on how fractured or platy the rock is.
We recommend that further explorations and analysis be conducted once a more
developed design is established. Additional explorations can consist of hand borings or hand dug
test pits along a defined pipeline alignment, more detailed rock exposure mapping in areas that
will require working with bedrock (if needed), and detailed slope analyses to establish needed
setbacks from slope scarps and recommendations for slope mitigation. We are available to
review conceptual and preliminary designs of the project to assist you in detecting potential
problem areas related to geotechnical issues.
32-1-01942
O'Brien Creek Hydroelectric Project,
Chitina, Alaska
November 14,2007
Page 5
CLOSURE AND LIMITATIONS
SHANNON &WILSON, INC.
The analyses and conclusions contained in this report are based on site conditions as they
presently exist. It is assumed that the reconnaissance is representative of the surface and
subsurface conditions throughout the site, i.e., the conditions everywhere are not significantly
different from those disclosed by the explorations.
Unanticipated conditions are commonly encountered during construction and cannot fully
be determined by merely conducting reconnaissance or excavating hand-dug test pits. Such
unexpected conditions frequently require that additional expenditures be made to attain a
properly constructed project. This information should be used in preliminary design and
feasibility studies only and once a preferred route is selected, additional explorations should be
conducted to characterize the subsurface conditions along the preferred alignment.
Shannon & Wilson has prepared the attachment Important Information About Your
Geotechnical/Environmental Report to assist you and others in understanding the use and
limitations of the reports.
Sincerely,
SHANNON & WILSON, INC.
Prepared By:
:?2~
Kyle Brennan, P.E.
Senior Geotechnical Engineer
Attachments: Figure 1: Vicinity Map
Figure 2: Site Plan
Figure 3: Field Notes
Photo Pages
Approved By:
~~dm~
Senior Associate
Important Information About Your Geotechnical/Environmental Report
32-1-01942
Project Location
!
1 0 1100 2200 4800
APPROXIMATE SCALE IN MILES
Alaska
O'Brien Creek Hydroelectric Project
Chitina , Alaska
VICINITY MAP
November 2007 32-1-01942 = IIJ SHANNON & WILSON , INC. Fi g. 1
_, Geotedmical & Environmental Consuttants
~
~
I ..
!
6i
-o
D
D
D
~OXI MATI!: LOCATION OF 08SERVA.TI DN POINT OP-01 VISITED BY SHANNON & W ILSON,
0CTOIIER 3 Tl1ROUGH 5, Z007
INLET AREA
UP'PER PI .. EUNE AREA
MIDDLE PII"EliNE AREA
Adapt..:t tn:m uses VoldN 8-2 OuoO-onQI•
~
1,000 2.000
APPROXIWA 1E SCALE IN FEET
4,000 -
O'BRIEN CREE~ HYDROELECTR IC PROJECT
CHinNA, Al..ASitA
S ITE PLAN
1 ... 11 !J'IIsf_ll;' ~co1 ~2 .("q.: .. i "'-"1 LOWER PIPELI NE AREA = Ill SHANNON !I WILSC!\, II'.C. FIG. 2 ~ ~ _, ....___.~~--
~= _ _.
!Ill
§ ..
@
;r
~ ! ~
i
~ I
FIGURE 3 --FIELD NOTES
Point# Site Description
OP-01 Landing zone near approximate location of intake structure.
Slide on south side off channel approximately 60 feet high, 20 feet wide,
OP-02 and 10 feet deep. Slide debris indudes gravelly, silty sand and scattered
boulders.
Narrow section of O'Brien Creek. Well pronounced, alluvial benches
OP-03 extend laterally from the creek to the south. Steep rock slopes extend to
the north.
Upstream from a morainal ridge extending south from a rock knob.
OP-04 Pipeline will likely cut approximately 20 feet into the saddle formed by the
ridge.
On top of moraine ridge. Appears to be a boulder moraine/ridge
extending from a rock mass near stream. Looking back up the valley -
OP-05 the south side looks like a thick moraine and the north side is more
shear/rocky. Looking at the downstream side, there are some over-
steepened slopes displaying active erosion.
On a moraine slope that is exhibiting recent failure. Slope angles 35 to
OP-06 38 degrees. There are pronounced tension cracks above the crest of the
failure scarp.
Gentle slope down to the north above O'Brien Creek. Ground is covered
OP-07 with peat and vegetation indudes dense willow, alder, and spruce trees.
Ground surface is wet and spongy.
A running surface drainage flowing downslope into O'Brien Creek.
OP-08 Boulders and cobbles are in the streambed and silty, clayey, gravelly
sand exposed in the banks.
On O'Brien Creek at the base of major slides. Pipe will cut right above
OP-09 existing slide scarp crest. Scarp face is approx. 40 degrees and natural
slope is approx. 35 degrees. Scarp face is 60 to 70 feet high.
Exposed, recent slide on O'Brien Creek side of medial moraine. Natural
(pre-slide) slope appears to be approximately 40 degrees. Slide is
OP-10 approximately 60 feet wide and 10 feet deep with a 30-foot runout but
continues in isolated flows almost all the way to O'Brien Creek.
On top of Ridge on the south side of O'Brien Creek. The feature is
narrow (10 to 20 feet wide at the top) and is likely a lateral or medial
OP-11 moraine, steep on both sides. Slopes down to O'brien Creek @ 40 to 45
degrees for about 40 feet then levels out to 30 degrees. Signs of active
erosion and slides.
On the same moraine ridge as OP-11, to the northeast. Clayey, silty,
OP-12 gravelly sand with cobbles and boulders. Slopes down to O'Brien creek
exhibit active erosion. Pipeline will likely cut 20 to 30 feet down into the
moraine ridge.
Spruce stand with muskeg bottom ground cover on a north facing slope.
OP-13 Frozen soil conditions detected about 1.5 feet bgs. Peat to about 1. 7
feet. Mineral soils beneath the peat comprise gray, silty, clayey sand with
gravel.
Bog area with standing water on the ground surface. A hand-dug test pit
OP-14 reveals approximately 2 feet of peat over gray silt. Water fills the hole
rapidly and it is difficult to tell if the ground is frozen.
Landing zone area. A hand dug test pit reveals approximately 3.5 feet of
OP-15 peat and organic silt over silty, gravelly sand; moist. No noticeable frozen
I around or groundwater.
On top of steeply sloping "gully" that will likely provide a corridor for the
pipeline. Slope is covered with dense alders and willows and bedrock
OP-16 appears to be covered with approximately 6 to 12 inches of organic silt
overburden. Bedrock consists of black, shaley material with strong
bedding that is oriented approximately parallel with the overall slope
orientation.
OP-17 On O'Brien Creek near the proposed location of the new powerhouse.
Pipeline will likely come down the slope from the south.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
November 2007
SHANNON & WILSON, INC.
WGS83 Datum
Northing Easting
61.46143 -144.54069
61.46141 -144.53982
61.46128 -144.53746
61.46107 -144.53526
61.46098 -144.53404
61.45997 -144.53450
61.45854 -144.52743
61.45997 -144.52355
61.46189 -144.41990
61.46106 -144.51723
61.46081 -144.51717
61.46115 -144.51649
61.46960 -144.48667
61.46994 -144.48626
61.47954 -144.46627
61.48538 -144.46914
61.48595 -144.46513
Photo
1
2
3.4
5
6,7,8
9
10
NA
17
13
11
12
15
14
16
NA
18
Figure 3
Field Notes
32-1-01942
ATTACHMENT
PHOTO PAGES
SHANNON & WILSON, INC.
32-1-01942
Photo 1: At OP-01 looking downstream at the approximate
location of the intake structure.
Photo 2: At OP-02 looking downstream. Note terraced bench in
background.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 1 AND 2
November 2007 32-1-019042 =111 SHANNON & WILSON, INC. Fig. 4
.. Geotechnical & Environmental Consultants
Photo 3: At OP-03 at recent
erosion in the alluvial bench on the
south side of O'Brien Creek.
Photo 4: At OP-03 exposed shale bedrock
on the north side of O'Brien Creek.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 3 AND 4
November 2007 32-1..019042 =111 SHANNON & WILSON , INC. Fig. 5
-Geotechnical & Environmental Consultants
Photo 5: At OP-04 looking downstream . Morainal
ridge is visible in the background.
Photo 6: At OP-05 looking upstream.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 5 AND 6
November 2007 32-1-019042
1 =11·1 SHANNON & WILSON, INC. I Fig. 6
Geotechnical & Environmental Consultants
Photo 7: At OP-05 looking downstream . Slides on
south side of creek are visible in background.
Photo 8: At OP-05 looking south along
morainal ridge .
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 7 AND 8
November 2007 3 2-1-019042 l!!!tl'l SHANNON & WILSON, INC. Fig. 7 iiiiil' Geotechnical & Environmental Consultants
Photo 9: At OP-06 looking east down
slide scarp.
Photo 10: At OP-07 looking south up
small drainage.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 9 AND 10
November 2007 32-1-019042 =1111 SHANNON & WILSON, INC. Fig. 8 I -Geotechnical & Environmental Consultants
Photo 11: At OP-011 looking west
along morainal ridge.
Photo 12: At OP-12 looking east along
morainal ridge.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 11 AND 12
November 2007 32-1-019042 =111 SHANNON & WILSON, INC. Fig. 9
~ Geotechnical & Environmental Consultants
Photo 13: At OP-10 looking south at
slide scarp.
Photo 14: At OP-14 looking southwest
over muskeg bog.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 13 AND 14
November 2007 32-1-019042 =111 SHANNON & WILSON, INC. Fig. 10
. Geotechnical & Environmental Consultants
Photo 15: At OP-13 at the hand-dug
test pit in frozen permafrost.
Photo 16: At OP-15 looking east near
hand-dug test pit. Clearing is a recently
cleared landing zone.
O'Brien Creek Hydroelectric Project
Chitina, Alaska
PHOTOS 15 AND 16
November 2007 32-1-019042
~II SHANNON & WILSON, INC. Fig.11 iii I Geotechnical & Environmental Consultants
Photo 17: At OP-09 toe of typical
active slope along south side of
O'Brien Creek.
Photo 18: At OP-17 looking east, downstream
on O'Brien Creek. Note the wide valley floor
and terraced river banks .
O'Brien Creek Hydroelectric Project
Chitina , Alaska
PHOTOS 17 AND 18
November 2007 32-1-019042
~II SHANNON & WILSON, INC. Fig. 12 iii I Geotechnical & Environmental Consultants
SHANNON & WILSON, INC.
ATTACHMENT
IMPORTANT INFORMATION ABOUT YOUR
GEOTECHNICAL/ENVIRONMENTAL REPORT
32-1-01942
SHANNON & WILSON, INC.
Geotechnical and Environmental Consultants
Attachment to 32-1-01942
Date: November 2007
To: Polarconsult Alaska, Inc.
Re: O'Brien Creek Hydroelectric Project,
Alaska
Important Information About Your Geotechnical/Environmental Report
CONSULTING SERVICES ARE PERFORMED FOR SPECIFIC PURPOSES A.'ID FOR SPECIFIC CLIENTS.
Consultants prepare reports to meet the specific needs of specific individuals. A report prepared for a civil engineer may not be adequate for
a construction contractor or even another civil engineer. Unless indicated otherwise, your consultant prepared your report expressly for you
and expressly for the purposes you indicated. No one other than you should apply this report for its intended purpose without first
conferring with the consultant. No party should apply this report for any purpose other than that originally contemplated without first
conferring with the consultant.
THE CONSULTANT'S REPORT IS BASED ON PROJECT-SPECIFIC FACTORS.
A geotechnicaVenvironmental report is based on a subsurface exploration plan designed to consider a unique set of project-specific factors.
Depending on the project, these may include: the general nature of the structure and property involved; its size and configuration; its
historical use and practice; the location ofthe structure on the site and its orientation; other improvements such as access roads, parking lots,
and underground utilities; and the additional risk created by scope-of-service limitations imposed by the client. To help avoid costly
problems, ask the consultant to evaluate how any factors that change subsequent to the date of the report may affect the recommendations.
Unless your consultant indicates otherwise, your report should not be used: ( 1) when the nature of the proposed project is changed (for
example, if an office building will be erected instead of a parking garage, or if a refrigerated warehouse will be built instead of an
unrefrigerated one, or chemicals are discovered on or near the site); (2) when the size, elevation, or configuration ofthe proposed project is
altered; (3) when the location or orientation ofthe proposed project is modified; (4) when there is a change of ownership; or (5) for
application to an adjacent site. Consultants cannot accept responsibility for problems that may occur if they are not consulted after factors,
which were considered in the development of the report, have changed.
SUBSURFACE CONDITIONS CAN CHANGE.
Subsurface conditions may be affected as a result of natural processes or human activity. Because a geotechnicaVenvironmental report is
based on conditions that existed at the time of subsurface exploration, construction decisions should not be based on a report whose
adequacy may have been affected by time. Ask the consultant to advise if additional tests are desirable before construction starts; for
example, groundwater conditions commonly vary seasonally.
Construction operations at or adjacent to the site and natural events such as floods, earthquakes, or groundwater fluctuations may also affect
subsurface conditions and, thus, the continuing adequacy of a geotechnicaVenvironmental report. The consultant should be kept apprised of
any such events, and should be consulted to determine if additional tests are necessary.
MOST RECOMMENDATIONS ARE PROFESSIONAL JUDGMENTS.
Site exploration and testing identifies actual surface and subsurface conditions only at those points where samples are taken. The data were
extrapolated by your consultant, who then applied judgment to render an opinion about overall subsurface conditions. The actual interface
between materials may be far more gradual or abrupt than your report indicates. Actual conditions in areas not sampled may differ from
those predicted in your report. While nothing can be done to prevent such situations, you and your consultant can work together to help
reduce their impacts. Retaining your consultant to observe subsurface construction operations can be particularly beneficial in this respect.
Page 1 of2
3/2004
A REPORT'S CONCLUSIONS ARE PRELIMINARY.
The conclusions contained in your consultant's report are preliminary because they must be based on the assumption that conditions
revealed through selective exploratory sampling are indicative of actual conditions throughout a site. Actual subsurface conditions can be
discerned only during earthwork; therefore, you should retain your consultant to observe actual conditions and to provide conclusions. Only
the consultant who prepared the report is fully familiar with the background information needed to determine whether or not the report's
recommendations based on those conclusions are valid and whether or not the contractor is abiding by applicable recommendations. The
consultant who developed your report cannot assume responsibility or liability for the adequacy of the report's recommendations if another
party is retained to observe construction.
THE CONSULTANT'S REPORT IS SUBJECT TO MISINTERPRETATION.
Costly problems can occur when other design professionals develop their plans based on misinterpretation of a geotechnicaVenvironmental
report. To help avoid these problems, the consultant should be retained to work with other project design professionals to explain relevant
geotechnical, geological, hydrogeological, and environmental findings, and to review the adequacy oftheir plans and specifications relative
to these issues.
BORING LOGS AND/OR MONITORING WELL DATA SHOULD NOT BE SEPARATED FROM THE REPORT.
Final boring logs developed by the consultant are based upon interpretation of field logs (assembled by site personnel), field test results, and
laboratory and/or office evaluation of field samples and data. Only final boring logs and data are customarily included in
geotechnicaVenvironmental reports. These final logs should not, 1m.der any circumstances, be redrawn for inclusion in architectural or other
design drawings, because drafters may commit errors or omissions in the transfer process.
To reduce the likelihood of boring log or monitoring well misinterpretation, contractors should be given ready access to the complete
geotechnical engineering/environmental report prepared or authorized for their use. If access is provided only to the report prepared for
you, you should advise contractors of the report's limitations, assuming that a contractor was not one of the specific persons for whom the
report was prepared, and that developing construction cost estimates was not one of the specific purposes for which it was prepared. While a
contractor may gain important knowledge from a report prepared for another party, the contractor should discuss the report with your
consultant and perform the additional or alternative work believed necessary to obtain the data specifically appropriate for construction cost
estimating purposes. Some clients hold the mistaken impression that simply disclaiming responsibility for the accuracy of subsurface
information always insulates them from attendant liability. Providing the best available information to contractors helps prevent costly
construction problems and the adversarial attitudes that aggravate them to a disproportionate scale.
READ RESPONSIBILITY CLAUSES CLOSELY.
Because geotechnicaVenvironmental engineering is based extensively on judgment and opinion, it is far less exact than other design
disciplines. This situation has resulted in wholly unwarranted claims being lodged against consultants. To help prevent this problem,
consultants have developed a number of clauses for use in their contracts, reports and other documents. These responsibility clauses are not
exculpatory clauses designed to transfer the consultant's liabilities to other parties; rather, they are definitive clauses that identity where the
consultant's responsibilities begin and end. Their use helps all parties involved recognize their individual responsibilities and take
appropriate action. Some of these definitive clauses are likely to appear in your report, and you are encouraged to read them closely. Your
consultant will be pleased to give full and frank answers to your questions.
The preceding paragraphs are based on information provided by the
ASFE/Association of Engineering Firms Practicing in the Geosciences, Silver Spring, Maryland
Page 2 of2
3/2004
POLARCONSULT ALASKA, INC. REGIONAL HYDROELECTRIC INVESTIGATION
CHITINA, ALASKA
FINAL REPORT
APPENDIX C -SUMMARY OF FLOODING IN SOUTH CENTRAL
ALASKA, OCTOBER, 2006. USGS
MAY2,2008
USGS ASC Summary of flooding in Southcentral Alaska, October 2006 Page 1 of3
USGS Home
Contact USGS
Search USGS
Summary of flooding in Southcentral Alaska, October 2006
1 Alaska Science Center I Water Office I National Water Information System (NWIS) I Contacts I
October 2006 Flooding in the Seward-
Prince William
Sound areas, Alaska
PROVISIONAL FLOOD PEAKS AND RECURRENCE INTERVAl
NUMBER OF
PREVIOUS DATE OF PEAKS PEAK
STATION PERIOD OF PEAK HIGHER DISCHARGE DATE ANI
NUMBER STATION NAME RECORD DISCHARGE PREVIOUS THAN (FT3/S) TIME OF PE
(FT3/S) PEAK OCTOBER
2006
15200280 Gulkana River at 1973-78; 12,700 9/12/1990 15,300 10/? /2( Sourdough 1989-2004 none
15207800 Little Tonsina R near 1972-78 214 7/20/1977 none 570 est 10/9-1 0/~ Tonsina
15208000 Tonsina River at 1950-82 8,490 Tonsina 6/17/1962 none b14,000 est 10/9-10/~
15208100 Squirrel Cr at Tonsina 1964-82 1,200 6//1964 1 in 19 yr c1, 100 est 10/9/20
15208200 Rock Cr nr Tonsina 1966-95 225 5/29/1989 1 in 29 yr 200 10/9/20
15210025 McCarthy Creek nr 1994-current 4,000 9/27/2000 none 7,100 est 10/9-1 0/~ McCarthy
15211700 Strelna Cr near Chitina 1971-96 670 8/12/1985 unknown unknown 10/9-1 0/~
15211900 O'Brien Creek near 1970-82, 84-1,950 6/6/1990 unknown unknown unknov Chitina 96
15212000 C R' ChT 1950, 52-53, opper 1ver nr 1 ma 56 _90 380,000 8/8/1981 1 in 38 yr 334,000 10/1 0/2(
15212500 Boulder Creek nr Tiekel 1964-current 1,330 8/7/1981 none
1,700 10/9-1 0/~
http:/ /ak. water. usgs.gov /flood/20060ctober/index. php 4/9/2008
USGS ASC Summary of flooding in Southcentral Alaska, October 2006 Page 2 of3
(revised)
15212800 Ptarmigan Creek Trib nr 1965-70, 95-85 9//1965 none 184 10/9/20 Valdez current
15214000 Copper R. @ Million 1913, 1988-415,000 9/23/1995 none 447,000 10/11/2006 Dollar Bridge 95
15215990 Nicolet Creek near 1990-current 988 11/3/1994 8 in 15 yr 557 10/9/2006 Cordova
15225997 Solomon Gulch Top of 1986-current 3,280 10/11/1986 none 3,350 10/9/2006 Falls
15226600 Lowe River in Keystone 1976-77, 18,700 9/22/1995 none 42,000 10/10/2( Canyon near Valdez 1995
15227500 Mineral Creek near 1990-current 5,570 6//1976 5 in 16 yr 3,500 10/9/20 Valdez
15236200 Shakespeare Creek at 1970-80, 84-690 9/20/1995 13 in 33 yr 491 10/9/20 Whittier current
15237550 Mt. Alice Creek nr 1990-95 1,340 10/11/1986 2 in 7 yr 600 est 10/9/20 Seward
15237730 Grouse Cr. at lake 1997 -current 478 2/5/2003 none 901 10/9/2006 Outlet near Seward
15238010 Salmon Creek near 1990-95 8,500 10/11/1986 1 in 6 yr 6,200 est 10/9/20 Seward
15238600 Spruce Creek near 1967 -current 13,600 10/11/1986 1 in 40 yr 3,640 10/9/20 Seward
15239050 Middle Fork Bradley R 1979-current 1,470 9/20/1995 1 in 26 yr 1,350 10/9/2006 near Homer
15243950 Porcupine Creek near 1963-89, 4,000 10/11/1986 1 in 28 yr 3,800 est 10/9/20 Primrose 2003
15248000 T .1 R" L . 1947-77, 87, ra1 1ver near awmg 2003 8,200 10/24/2002 15 in 31 yr 4,000 10/9/20
15250000 Fails Creek near 1963-76 693 9/15/1966 2 in 9 yr 500 est 10/9/20 Lawing
* note, recurrence intervals have not been adjusted using 2006 peaks
Last revised 6/22/2007
Accessibility FOIA Privacy Policies and Notices
http://ak.water.usgs.gov/flood/20060ctober/index.php 4/9/2008