Loading...
HomeMy WebLinkAboutAPA Financial Assessment Tazimina River Hydroelectric Project 1987Alaska lower Authority Financial Assessment Tazimina River Hydroelectric Project June 1987 FINANCIAL ASSESSMENT OF THE TAZIMINA RIVER HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY JUNE 1987 9220/739/1 FINANCIAL ASSESSMENT OF THE TAZIMINA HYDROELECTRIC PROJECT I. INTRODUCTION PURPOSE OF REPORT AND SUMMARY OF FINDINGS This report addresses the financial feasibility of the proposed Tazimina Hydroelectric Project (the "Project"), a 700 kilowatt facility which would provide power to the Il iamna-Newhalen-Nondal ton Electric Coopera- tive ("INNEC"). This assessment is based in part on costs of power incurred with and without the Project and the corresponding rate shock.. Power Authority staff analysis found the Project to be marginally economically feasible. Further investigation as summarized in this report shows the costs of power incurred with the Project are far in excess of the alternative costs in the early years. For this reason, it is recommended not to proceed with the Project at this time; and de- tailed financial studies have not been performed. II. PROJECT DESCRIPTION The Project would be built at Tazimina Falls on the Tazimina River north of Iliamna Lake. It is a run -of -river development and includes a transmission line to the INNEC facilities at Newhalen. Excluding interest during construction and other financing costs, Project costs are estimated to be $6.9 million in 1986 dollars. The costs are assumed to be incurred over a 21-year period. A summary of the estimated costs and the anticipated construction schedule are shown in Exhibits 1 and 2, respectively. 9220/739/2 III. FINANCING OPTIONS INTRODUCTION Because State financing of the Project would probably be less expensive than private financing by INNEC, State financing was first considered. The options considered included the following: A) General Fund appropriation. B) General Fund loan. C) Power Project Loan Fund loan, and D) Revenue bonds issued by the Alaska Power Authority for the Project. Options A and B appear to be unlikely at this time due to reduced State revenues. Option C also appears unlikely at this time as the Power Project Loan Fund is presently funded through General Fund appropriations, and the amount required is more than is available at this time. This option, however, will be investigated in the event revenue bonds are prohibi- tive. REVENUE BONDS Based on the assumed construction costs and cash flow, a bond sizing analysis was performed to estimate the amount of bonds required. Such requirements are summarized in the following table and shown in detail in Exhibit 3. 9220/739/3 Estimated Bond Financing Requirements ($000) Construction Costs (1) $8,020 Discount and Financing Expenses (2) 371 Capitalized Interest (3) 2,403 Debt Service Reserve Fund (4) 986 Subtotal $11,780 Interest Earnings (5) (1,170) Rounding (10) Total Bond Requirements $10,600 (1) Based on a construction cost of $6.9 million in 1986 dollars escalated over the construction period at an assumed annual in- flation rate of 4.5 percent. (2) Assumed to be 3.5 percent of the issue size. (3) Interest incurred during the capitalization period based on an interest rate of 8.5 percent per year. (4) Equal to one year's debt service based on the assumed interest rate and a 30-year amortization period. (5) Interest earnings on the various bond funds during the capitali- zation period assuming reinvestment rates ranging from 6.0 - 8.5 percent. Annual debt service on such a bond issue with an assumed interest rate of 8.5 percent and 30-year amortization period would be $986,000 per year. This would be offset in part by interest earnings on the Debt Service Reserve Fund assumed to be approximately $75,000 per year, for a total net debt service of $911,000 per year. POWER PROJECT LOAN FUND A loan funded from the Power Project Loan Fund would have the advantage of little or no financing costs, reduced interest during construction, and no reserve fund requirements. Under this program the capital requirements would be approximately $8.75 million, assuming interest is capitalized during the construction period at 8.5 percent per year. Annual debt service would be approximately $815,000 per year. 9220/739/4 IV. FINANCIAL ANALYSIS Operating costs of the Project are estimated to be $60,000 (1986 dol- lars) per year plus 1.5 cents per kilowatt-hour. Accordingly, total costs of the Project including debt service are: Power Project Revenue Bond Loan Fund Debt Service $911,000 $815,000 0&M - Fixed 71,500 71,500 Subtotal 982,500 $886,500 Energy Requirements(MWh)2 2,126 2,126 Cost (¢/kWh) 1 0&M - Variable (t/kWh) 46.2 1.8 41.7 1.8 Total Cost R/kWh) 48.0 43.5 1 Base year estimate escalated at 4.5 percent per year to 1991. 2 Estimated. Forecasted energy requirements are based on a three percent load growth of the INNEC load and do not include any potential sales at Keyes Point on Lake Clark. The current cost of power at INNEC is approximately 45.5 cents/kilo- watt-hour. The costs for fuel and plant operation and maintenance account for approximately 17 cents of this amount. Thus, the costs incurred by the utility with or without the Project are 28.5 cents per kilowatt-hour (45.5-17.0). Assuming that the diesel generators would be run 5 to 10 percent of the time during Project outages, an additional 2 cents per kilowatt-hour should be added to the base cost, yielding a total base cost of 30.5 cents per kilowatt-hour. As shown in the table below, the costs with the Project would be at least 60 percent greater than costs incurred without the Project. 9220/739/5 Project Comparison Costs (¢/kWh) Revenue Power Project Bond Loan Fund Base Costs 30.5 30.5 Project Costs 48.0 43.5 Total Costs with Project 78.5 74.0 Costs without Project 45.5 45.5 V. RECOMMENDATION Given the large increase in revenue requirements associated with the Project, it is recommended not to proceed with the Project at this time. If diesel prices or load requirements increase more than expected, the economic and financial feasibility can be reassessed. 9220/739/6 Exhibit 1 Tazimina River Hydroelectric Project Cost Estimate (1986) FERC Estimated Acct Description Cost 330 Land & Land Rights (Not Included) 331 Powerplant 659,000 332 Waterways 1,483,000 333 Turbines and Generators 556,000 334 Accessory Electrical Equipment 300,000 335 Miscellaneous Power Plant Equipment 115,000 336 Roads 1,500,000 352/353 Substation & Switching Station 50,000 354 Transmission 500,000 Mobilization & Demobilization 400,000 5,563,000 Allowance for Indeterminates 537,000 Direct Cost $6,100,000 Engineering and Design 500,000 Construction Management 300,000 Total Cost $6,900,000 9220/739/7 / a: w )§ --/ iL 2 ---- o Sa a, 8 z / b §■ � N § �| § o E L o § 2 r 0 a: n � � « S 2\ � � | Sul/ LL§% a% | m« | � $ LLU � o Cl \ \ 2 >-o w 12 z § k§ $ ���� �\ § §/� �� § § § a.c2 2� a w < > w a � « uj o >w 12 2 w � § k E b'§���2 w r —N � U c \ k k § U. I < w M=!@ /kLU < � � o 22 �e n � / < z CC z k\ Lu w/ E 2 ZF- Z2 @>- ® �� <F w v �z wo �S L L o 0 W � � � W G U � U _ < _ W i n LU O � C / 2B-may Exhibit 3 l%:, 1 CONSTRUCTION COST 8,028 GENERAL INFLATION 4.5% WORKING CAPITAL 0 INTEREST RATES: EXPENSES: BONDS 8.5% DISCOUNT 35.0 REINVESTMENT RATES: F.A. FEE 0 CONSTRUCTION FUN 6.0% F.A. EXPENSES 0.0 CAP INT FUND 6.5% B.C. FEE 0.0 DSR FUND 8.5% B.C. EXPENSES 0.0 OTHER FUNDS 8.5% WA EXPENSES 0.0 CAPITALIZATION PER. 32 MONTHS AMORTIZATION PERIOD 30 YEARS ANNUAL CASH FLOW (CY) ANNUITY FACTOR 0 1986 $ NOM'L $ 1988 420 459 1989 3,240 3,697 1990 3,240 3,864 6, 900 8, 028 Page 1 of 3 Page 2 of 3 LA LI'7 1,1 e Q e t Q' M M rQ'1 r! rM"1 N AJ m M1l CMV !.D 9 fV 6 ' J I 1 ti I I O 1 � I p� M LG IA < �.,,pp � I� M � m n n ,S m O� t• LG W, N M m ��pp � r7 6 `, .-. [T� u7 ^J d ^J M r 9 m 1J u7 M � � �� N N .•. m m m Y'] e M �. � r'D M 'm ? N m M ... R+ v li ] i �v y " c i vi vi v+ m m r� r I,u' uo m m m m m m m y m m y m m y m y y m m m 9 m y m 6 m y y y y 9 9 I LL � I po L m m m m m m m 9 m m m m m m 6 y m 9 m m y m m 9 m m y y 9 9 6 9 I U] I t n- n- r r n r n- r- r n- r r-n n r r- r- r- -- r r v o i w i 1 MAMA, AAAm+A,AAAv�l��cl, LL L'I [/1 I I M M N a, N a, N (L m m m m m m------ li ] IA u7 U' V! V! N N ^J N f j N ip I I Q¢ G I I I I Lt 1 li 7 Q Y'] Q t li Y lfY < Q y Q Z i U I I N Q I U i i I MZ I my,m 1N {�'� � � � � � � � � I I v• N [V [V N ILL M I"'] ram] I�1 I LL � I rr rr ram] M M M �(1ll ��pp rM'] M M N N 2 T m m t` ip Lf] .^ Ora N ... m r"'I NI N N cl� nl V+ M y7 y-� �pp� y7pp� m OM'I T �p Lf]+ fail N [U If] If'1 m N ... .-� ..+ N ♦�. 1 m I (fl I mmm m m ^ r ^ 1py� pry m Tp m rn ^ ^ LO Y"J I`7 �.. m Q O+ a i>0 I� LL Q N 9 Lo 6 G M CC V I 1 O I I �G LO LO LO LO LG LO 1f9 1/') e e � r"'1 r"1 r"1 r'i ry m N N N -+ m m m m m m m m m m m m m Is! m m m m m m m m m m m m m m m m m m m m m m 11. i m m m m m , a IA 9 V] m — .� 1!] U! — — = N 4 ^ 9 m %n n Ln — — = N Q li7 m a0 If'1 (� Page 3 of 3 BOND SUMMARY 3000) CONSTRUCTION COST on DISC. 8 FIN. 371 CAP. INT. FUND 403 DEBT SVC. RESERVE 986 WORKING CAP., OTHER 0 SUBTOTAL 11,760 INT. EARNINGS (1,170) ROUNDING SURPLUS (10) TOTAL 10,600 ANNUAL DEBT SERVICE 986 INT. EARNINGS 74