HomeMy WebLinkAboutSolomon Gulch Hydroelectric Project Reservior Capacity Increase Feasibility Study 1991SOLOMON GULCH HYDROELECTRIC PROJECT
RESERVOIR CAPACITY INCREASE
FEASIBILITY STUDY
SOLOMON GULCH HYDROELECTRIC PROJECT
RESERVOIR CAPACITY INCREASE
FEASIBILITY STUDY
Prepared for
Copper Valley Electric Association
P.O. Box 927
Valdez, Alaska 99686
Prepared By
HDR Engineering, Inc.
11225 S.E. Sixth Street
Building C, Suite 200
Bellevue, Washington 98004
November 1991
SOLOMON GULCH HYDROELECI'RIC PROJECT
RESERVOIR CAPACI'IY INCREASE FEA:SmiLI'IY STUDY
TABLE OF CONTENTS
Section
Introduction
I. Alternative Descriptions and Recommended Alternative
n. Hydrology and Hydraulics
m. Energy Production
N. Cost Estimate
v. Economic Analysis
VI. Environmental Concerns and Other Issues
vn. Dam Safety
vm. License Amendment Requirements
IX. Conclusions and Recommendations
AIWendices
1. Bridgestone Cost Quotations -Rubber Dam
2. Connection Diagram -2-foot Dam
3. Connection Diagram -5-foot Dam
4. Letter from Bridgestone regarding ic~ performance
i
~
1
2
8
8
9
10
10
13
13
14
SOLOMON GULCH PROJECT
RESERVOIR CAPACITY INCREASE PROJECr
Introduction
HDR Engineering Inc. (HDR) was retained by Copper Valley Electric Association
(CVEA) of Valdez, Alaska to study the feasibility of raising the spillway crest on the
existing Solomon Gulch Dam by either 2 feet or 5 feet The resulting increase in storage
would allow CVEA to operate their hydroelectric generating facilities at Solomon Gulch
later into the year and help offset or eliminate the need for supplemental diesel
generation on their system. The study by HDR is being conducted in two phases; 1) a
pre-feasibility analysis to determine quickly if the project makes sense economically and
to identify any fatal flaws; and 2) a more detailed feasibility study to be conducted only
in the event that the Phase I study indicates a viable project This report is confined to
the presentation of the findings of only the Phase I study.
Background:
The Solomon Gulch Hydroelectric Project, FERC #2742, is located on the south shore
of Valdez Harbor about 4 miles southeast of the City of Valdez. The project was
originally owned by CVEA and was constructed between 1978 and 1982. In 1982, the
project was purchased by the Alaska Power Authority, now the Alaska Energy Authority
(AEA). The project is operated by CVEA through an agreement with AEA. Solomon
Lake is impounded by a asphaltic concrete faced rock:fill dam with a concrete ogee
spillway with a crest elevation of 685 feet msl. The reservoir impounded by the dam is
about 640 acres in area with a live storage of approximately 31,000 acre-feet Two 48-
inch pipelines approximately 3,800 feet long carry· water to the powerhouse, which is
located adjacent to tidewater at the shore of Valdez Harbor. The powerhouse has two
vertical shaft Francis units which operate over the range of 645 to 590 feet of head and
have a total installed capacity of 12 MW. The project provides power for the City of
Valdez and Glennallen community via a transmission intertie.
In addition to the Solomon Gulch Hydroelectric Project, the CVEA also operates two
diesel generating facilities at Glennallen and at Valdez, that are used to supplement
generation from Solomon Gulch. The Solomon Gulch Reservoir is glacially fed, and
follows a general pattern in filling and drawdown closely related to the timing of glacial
melt runoff. Typically, the reservoir is drawn down to a minimum over the winter when
there is little if any inflow. Beginning in early May, inflow from snow and glacial melt
begins to increase and the reservoir begins to fill The reservoir is usually completely full
by mid-July and water spills over the spillway until mid-October. By November 1, inflow
is greatly reduced by freezing conditions up on the glacier. The hydroelectric plant cuts
back production, but the reservoir level steadily drops until all available storage is used
up, usually sometime in late March or early April. The supplemental diesel generation
plants must be started up and operated under very uneconomic conditions until runoff
begins again in May and the hydro plant can be restarted.
1
The objective of studying the feasibility of raising the spillway by either 2 or 5 feet is to
capture a portion of the runoff that currently is spilled from mid-July to mid-October, so
lhat the period of operation of the hydro facility may be extended into the spring,
hopefully long enough to make full operation of at least one of the diesel facilities
unnecessary.
I. Alternative Descriptions and Recommended Alternative
The existing spillway at Solomon Gulch Reservoir has a crest elevation of 685 feet msl.
The rockfill dam and dike have a crest elevation of 690 feet, or 5 feet above the spillway
crest. In addition, there is a 5-foot high "wave wall" on the top of the dam and dike with
a crest elevation of 695 feet msl.
There have been several dam stability analyses done on the Solomon Gulch dam and
spillway. These analyses show that the wave wall is stable under flood conditions that
have as much as 9 feet of water going over the spillway. For this reason, we have
assumed for this preliminary study that it is both feasible and safe to raise the Solomon
Gulch Reservoir by up to 5 feet without doing any construction work or adding to the
existing dam and dike structures. Any raising of the spillway more than 5 feet, in our
opinion, would necessitate using the wave wall as a water retaining structure at all times,
which we believe would not be acceptable to FERC. In that case, raising of the rockfill
structures would also be required, at a large increase in cost. We have, therefore, limited
our review of alternatives to a maximum of 5 feet increase in additional reservoir storage.
We have examined several alternative methods for raising the spillway, including:
• Rubber dam -2-feet high
• Rubber dam -5-feet high
• Flashboards -5-feet high
• Steel Flap Gates -5-feet high
Steel Flap Gates
Based on historic costs for steel flap gates, they were immediately rejected for further
consideration at Solomon Gulch. Initial costs are from 1.2 to 1.8 times as expensive as
the Bridgestone Rubber Dam. Refer to Figure 1. Installation costs are also much greater
and considerably more field installation time is necessary with steel flap gates. Finally,
steel flap gates invariably reduce the spillway capacity of the existing spillway to some
degree since the gate itself takes up room on the spillway crest, even when lowered. This
would result in a higher peak reservoir elevation during the design flood, which would
result in potential ovenopping of the wave wall. To handle this condition, extensive
modifications would have to be employed.
2
10.5
9.5 -:. • • (!! 8.5 li • ..
(.)
0 ::: 7.5
CD
"i ::
6.5
5.5
4.5
.2 .4
Cost of Crest Gates (F.O.B. Site)
.8 1.0 1.2
Cost tn U.S. Dollars x 1,000,000
Figure t
Ncces: 1. &eludes Cost ot lnstallaOOn
1.4
2. Each line contains manutacturet's name and
numbet,length and type of gate.
3. BIS indicates Bridgestone quote
1.6 1.8
I .•
'
,.
, ..
Wood Flashboards
Installation of 5-foot high wooden flashboards on the spillway was examined. First time
installation costs amount to approximately $100,000with subsequent replacements costing
approximately $30,(X)() per replacement.
There are several drawbacks to a flashboard installation. In this case, when the
flashboards failed, the 90 boards (5 feet by 6 feet) would wash down into Solomon Gulch
Creek. Some boards could·possibly be recovered at considerable effort from the creek
bed, and some will be washed into the bay and lost. This could create some local debris
problems in the creek. When the flashboards f~ all the stored water will be lost for the
season, since the boards could not be reinstalled until there is no flow over the spillway.
H a high flow event occurred between July and October which caused a flashboard failure,
the benefit of raising the spillway crest would be lost for that year. Flow records confirm
that flood events in this drainage basin are most likely between June and September each
year. Flashboards also perform quite poorly under ice conditions. Ice that forms on the
reservoir surface can exert pressure on the boards and could make them fail prematurely.
In particular, high winds can blow sheet ice against the boards, causing them to fail.
Finally, flashboards typically are somewhat erratic when it comes to how and when they
fail. Typically, some boards fail with only minimal overtopping, while others stay in place
and may never fail throughout a flood event. This makes control of reservoir level during
a flood more difficult, and again could result in a higher peak reservoir elevation during
the design flood and overtopping of the wave wall. For these reasons, flashboards were
rejected as a viable option at Solomon Gulch.
Inflatable Weirs or Dams
An inflatable dam appears to have all the correct characteristics to make it a good
selection for Solomon Gulch. Some of these characteristics include:
.1) Can be raised and lowered quickly.
2) Can be raised while flow is passing over it
3) Good performance under ice conditions.
4) Very minor reduction in spillway capacity.
5) Simple and quick to install.
6) Can be partially lowered ~d re-raised if desired.
There are several types of inflatable dams, including FabriDam, which is inflated with
water, and Sumitomo (Japan), Floecksmuhle Energietechnik GmbH (Germany) and
Bridgestone (Japan) rubber dams, which are inflated with air. Fabridams were not
reviewed due to the risk of freezing. Based on the review of alternatives, the low pressure
air inflatable rubber dam was selected as the alternative for further study. As requested
by CVEA, a 2-foot high and a 5-foot high alternative were examined.
Of the three remaining companies who supply this type of dam, Bridgestone has the most
extensive overall experience, and virtually the only experience of the three in the United
3
! "
States. Sumitomo has extensive experience in Japan and the Far East. Floecksmuhle has
very limited experience only in Europe and at this time its product is not being considered
further in this study. The Bridgestone product differs from Sumitomo's rubber weir in
two substantial ways:
(1) Bridgestone's fabric is an EPDM (Ethylene Propylene Diene Monomer) fabric
laminated with nylon and is much heavier than Sumitomo's. For a 5.0-foot high
rubber dam, the Bridgestone bladder would be 1/2-inch (12.5 mm) thick.
Sumitomo's fabric for the same height dam would be less than 3/16-inch (4.1 mm)
and made of laminations of synthetic rubber and nylon.
(2) Sumitomo does not have an automatic level control system to monitor and maintain
a constant upstream water level. Bridgestone has extensive experience with
automatic level controls and offer their SCUL system (System for ,Controlling
Upstream (water) .Level). Both products have fail-safe methods of deflation.
For these reasons, the Bridgestone "Rubber Dam" appears to be a more suitable option
for this project. Due to the volume of water and the beneficial ability to control the
reservoir water leyel via an automatic control system, the Bridgestone product is
considered exclusively henceforth, even though the cost of their rubber dam is slightly
higher than Sumitomo's "Sumigate."
The inflatable rubber dam system considered here, therefore, is patterned after the
Bridgestone Rubber Products "Rubber Dam." The Bridgestone product has been proven
to be a durable, dependable system for impounding and releasing water on naturally
flowing rivers. The Solomon Gulch Reservoir Rubber Dam System will be comprised of
several components, including: two rubber bladders, embedded anchor bolts and clamping
plates, inflation/exhaust piping, drain piping. automatically actuated blowers and exhaust
valves, control panel, and fail-safe deflation mechanisms.
Rubber dams are readily adaptable to different foundation and end pier conditions.
Rubber dams are commonly retrofitted onto existing dams as a replacement for
flashboards and steel gates. In this case, a small concrete shelf would need to be poured
on the upstream face of the existing spillway to form a flat connection surface for the
rubber dam. It is not possible to chip a flat area onto the top of the existing spillway
since there are post-tensioned rock anchors embedded in the existing spillway with the
bolt tops just below the top surface of the dam crest.
The foundation of the rubber dam system involves the embedment of steel clamping
plates along the foundation slab and end piers. The lower clamping plates are secured
to the foundation by anchor bolts designed to withstand the pullout force exerted on the
foundation due to lateral hydrostatic forces on the rubber bladder. The rubber bladder
is laid over the anchor bolts, and fittings for the air inlet/ exhaust line, pressure sensing
line and drain line are secured to the inside of the bladder. A spacer is placed next to
the foundation with upper clamping plates and nuts threaded onto the protruding anchor
bolts. Air inflation/ deflation, pressure sensing and drain piping for both rubber dams will
be connected to a small control building sited on the rockfill dike next to the spillway.
4
, ...
Rubber Dam Control Building
The control building will be located at the east end' of the non-overflow spillway dike next
to the spillway. Three phase 480 volt and 125 volt DC electrical service to the building
will be supplied from the valve bouse at the toe of the existing dam. The control building
will contain the control panel, control-interface panel, electrical distribution panelboard,
lighting panelboard, two 3 phase blowers (one for each rubber dam), two motor-controlled
air exhaust valves, two fail-safe bucket actuated air exhaust valves, and the terminus of
the rubber bladder drain and pressure sensing pipes (two each).· The two air
supply I exhaust systems will be interconnected to allow rubber dam inflation by a non-
designated blower while the designated blower is out of service. In addition, an isolation
valved connection will be provided on the air supply system to allow inflation of the
rubber dams with a portable gasoline powered compressor in case of emergency. The
drain piping and all low points in the piping systems will be drained to a sump in the
basement of the control building. The drainage will be pumped back to the reservoir
through an oil/water separator by a submersible sump pump.
The control building will be reinforced concrete slab on grade with an insulated metal
superstructure. The building will be approximately 10-feet wide by 25-feet long.
The building will be kept heated to approximately 45•F by 5 kW and 3 kW electric
beaters. A 12-incb in-line HV AC blower will supply 600 cfm air during periods that the
building is occupied by maintenance workers. The building exhaust duct will also serve
as air supply and/or air exhaust for the rubber dam blowers. The building air supply and
exhaust will be provided by two screened ducts through the roof.
Rubber Dam Control System
The rubber dam inflation/ deflation system is controlled through the SCUL control panel
in the control building. The control center of the rubber dam system is a programmable
. . logic controller (PLC). The PLC is programmed to receive input from transducers
sensing internal bladder pressure and reservoir water surface elevation. The PLC will
actuate the blowers or the exhaust valves to either inflate or deflate the rubber dams.
The PLC will be contained in a NEMA Type 4 control panel. The control panel will also
contain operating controls, setting switches, status and alarm indication, metering, and
regulators for the bl~wers and the electrically-operated exhaust valves.
The control system monitors and regulates the internal bladder pressures and
automatically inflates and deflates the bladde.~. A pressure transducer is tapped into the
pressure sensing air piping from each rubber dam. Internal bladder pressures are
continuously monitored and signals relayed to the control cabinet. Upon loss of rubber
bladder internal pressure, the blower is actuated to inflate the bladder to its normal
operating pressure. Lowering the internal pressure will be accomplished by actuation of
the automatic air exhaust valve. The rubber bladders will be controlled to an internal
pressure of 3 to 4 psi. Due to the bladders' low internal pressures, each blower is capable
of maintaining full inflation pressure in all· but the most catastrophic ruptures. Bullet
5
i'
holes are considered non-catastrophic, are almost self sealing, and can be repaired while
the bladder remains inflated.
The control system also includes a water level transducer for the purpose of providing a
constant reservoir water surface elevation. The normal operating water surface elevation
,will be El. 690.0. The PLC will actuate the blowers or the exhaust valves to inflate or
deflate the rubber bladders in sequence to maintain this constant reservoir elevation.
Upon increasing flow and upon total deflation of the two main span rubber dams, the
water surface will increase naturally.
In case of loss of power, the rubber dam system is equipped with fail-safe bladder
deflation systems at a set point of El. 690.5. The control system will activate gravity feed,
water-filled buckets and counter-weighted valve systems to totally deflate the rubber
bladders.
Under either the normal or fail-safe deflation modes, the rubber dams will deflate at such
a rate as to provide a gradually increasing downstream water surface, providing safety for
people downstream in or near the spillway channel. This can be accomplished by
properly designed deflation pipe sizes.
In addition to the normal operations of the SCUL syste~ the control system will include
provisions for a communications interface and backup electrical power source, in
accordance with CVEA standards.
Rubber Dam Operation
The rubber dam system will be self controlling and integrated with the powerplant control
systems. The SCUL will be programmed to inflate/deflate the rubber dams to control
the reservoir water surface at El. 690.0.
The SCUL system will control the rubber dams' internal pressure at all times. Each
rubber bladder will be operated in series. In the event a loss of electrical power to the
SCUL occurs, the rubber dams will retain their prepower-loss states unless the water level
rises to the fail-safe set points. If this occurs, both of the main dam's rubber dams will
automatically and totally deflate at an overtopping elevation of 690.5 via a gravity feed
bucket system so as to preclude damage and overtopping, as discussed above.
The rubber dam system is capable of being operated during low temperatures ( -30 ·F) and
during heavy ice and debris conditions. It can be operated at any level of
inflation/deflation without concern for vibration and damage to the bladder.
Expected Maintenance
Since the rubber dam system is designed to operate unattended, there is no need for daily
service as long as normal operation is observed. The PLC will operate the system and
locally annunciate alarms in the event a malfunction occurs. Provisions for remote alarm
6
annunciation and control are possible and may be initiated through the existing plant
control system if desired by CVEA
The manufacturer claims that rubber dam bladders have an estimated life of over 30
years. The EPDM rubber compound is UV and ozone resistent and not readily
susceptible to wear, tearing, or puncture. Leaks are rare, generally caused by exceptional
conditions, and are typically not a threat to operation of the system. Normal leaks can
be repaired while the bladder is inflated by installing rubber plugs which are supplied with
the bladder. No specific maintenance is required for the rubber bladders. There is no
exposed metal which requires painting or other maintenance. Anchor bolts and clamping
plates are fabricated of stainless steel.
Rubber dams are susceptible, however, to damage by firearms or knives. The Weeks
Falls Hydroelectric Project, upstream of the Snoqualmie Falls Project on the South Fork
Snoqualmie River, Washington State, is a non-remote, unattended installation of a rubber
dam in a public par~ which bas not experienced this type of vandalism in 5 years of
operation. Puncture by rifle fire is also possible, but, due to the low inflation pressure of
the bladder, catastrophic collapse is not likely. Due to the elasticity of the bladder, the
bole created by a fired projectile is less than one-third the projectile's diameter. Because
of the pressure sensing capability of the control system, the blowers are capable of
keeping the bladders inflated to their prescribed internal pressure and assure that the
bladders will remain in their upright posture. · Bullet holes have been detected at the
Weeks Falls Project, but have only resulted in minor air loss and have hardly been
noticeable by cycling of the blower. These boles have been easily patched with no plant
downtime and at very low cost.
At times of total deflation of the rubber dams, the bladder drain valve should be opened
to drain any internal moisture. Most of the moisture inside the bladder is carried by
pumping air into the large volume of the rubber bladders. In turn, most moisture exits
during deflation. Though rarely required, a check of the drain valves during deflation is
recommended.
Access to the downstream side of the dam will be possible any time there is not water
spilling over the spillway. Upstream access is only possible, for inspection purposes,
whenever the reservoir is drawn down.
During operation of the dam, it is possible for floating debris to be lodged on the
intermediate pier or rubber dam end walls. It is also possible during lower flow events,
when the rubber dams are fully inflated, to have debris bang up on the bladders. Such
debris may be able to be dislodged and moved downstream by partial deflation of the
rubber dam and sluicing tbe debris. Persistent and large debris may require cutting and
removal by boat. We are not aware of any debris damage to any rubber dams currently
in operation.
7
t"
i
r·
, •.
t··
i
II. Hydrology and Hydraulics
There has been a considerable amount of hydrologic work done on the Solomon Gulch
Reservoir, both as part of the original design and as part of the 5-year Dam Safety
Inspection. We reviewed the spillway design criteria, reservoir area and rating curves,
spillway rating curves and the probable maximum flood event studies performed by both
R.W. Retherford Associates and Chas. T. Main, Inc. HDR used this information as the
basis for flood and reservoir flood routing calculations.
The spillway design flood for Solomon Gulch Reservoir is an event which has a maximum
reservoir inflow of 48,300 cubic feet per second (cfs) and a maximum spillway outflow of
37,135 cfs. At this flow rate, there would be 8.5 feet of water passing over the spillway,
leaving about 1.5 feet of freeboard to the top of the wave wall. We would want to be
sure that any modification to the spillway would not affect its flood carrying capacity and
would not raise the maximum flood reservoir elevation, since there is only 1.5 feet of
freeboard under the current situation.
Since raising the spillway 5 feet is the worst case scenario, we examined the hydraulics of
this case first. Please refer to Table 1 and Table 2, the Flood Routing Computations for
the current situation and the 5-foot increase case. We assumed that the 5-foot rubber
dam was fully inflated and the reservoir was full at the start of a design flood. When
there was one-tenth of a foot (0.1 foot) of water spilling over the rubber dam, the dam
was lowered. From Table 2, it can be seen that almost all the stored water is spilled out
of the reservoir in 3 hours. Inflow from the flood doesn't peak until after 17 hours from
the start of the flood. Therefore, the impact of the extra storage is minimal. Comparing
the design flood base case to the 5-foot increase case shows that after about 6 hours into
the flood event, the impact from the extra 5 feet of storage is difficult to detect.
We conclude from this analysis that:
1) Raising the spillway 2 feet or 5 feet will not impact the maximum reservoir surface
elevation during a flood if the rubber dam is lowered early in the flood event.
2) The rubber dam control system should be designed to automatically lower the dam in
the event of a flood occurring, and should be as fool-proof as possible
3) Any time the rubber dam is inflated and the reservoir is full, completely lowering the
rubber dam will result in a flow of about 19,000 cfs down the spillway creek for a brief
period, dropping down to about 10,200 cfs after the first hour. A flood of this magnitude
is still only about balf of the design flood, but is expected to have some downstream
impact.
III. Energy Production
Raising of the spillway crest will increase energy production at Solomon Gulch by three
ways:
8
r'
· · .Solomon Gulch Reservoir
-E.xlatlng Conditione
FLOOD ROUTING COMPUTATIONS
Average I •,.,.... Average Average In ere-
Rate Inflow Average Rate Out-Flow mental Total Reservoir
Time for ll t Inflow Out-now for ll t Storage Storage Elevation
Hours ... Sec:ond-Ft Ac:re-Ft Sec:ond-Ft Ac:re-Ft Ac:re-Ft Ac:re-Ft End ll t
0 31500 685
1.31 500 55 47 6 + 49 31549 685.1
2.31 700 58 134 11 + 47 '31596 685.2
3.31 2100 175 530 44 +131 31727 685.5
4.31 8000 667 2753 229 +437 32164 686.5
5.31 10900 908 5923 494 +415 32579 687.5
6.31 11700 975 7786 649 +326 32905 688.0
7.31 12000 1000 9812 818 +182 33087 688.5
8.31 12300 1025 9812 818 +207 33294 688.5
9.31 15200 1267 11988 999 +268 33562 689.0
10.31 17100 1425 14305 1192 +233 33795 689.5
11.31 18200 1517 16754 1396 +121 33916 690.0
12.31 19800 1650 16754 1396 +254 34170 690.0
13.31 20600 1717 19329 1611 +106 34276 690.5
14.31 22800 1900 22023 1835 + 65 34341 691.0
15.31 29000 2417 24833 2069 +347 34688 691.5
.16.~1 40100 3342 27753 2313 . +102.9 35697 692.0
17.31 48300 4025 37135 3095 +930 36625 693.5
18.31 34000 2833 37135 3095 -261 36364 693.5
19.31 15300 1275 27753 2313 -1038 35326 692.0
20.31 8300. 692 19329 1611 -919 34407 690.5
21.31 . 6800 567 14305 1192 -625 33782 689.5
22.31 6200 517 9812 818 -301 33481 688.5
23.31 5700 475 7786 649 ' -174 33307 688.0
24.31 4500 375 7786 649 -274 33033 688.0
Baae Caae 1991
Table 1
From FERC License +2742 Exhibit K
Drawing No. H01-F•04-2011-R49 rev. 3 dated 1-3-83
I,
. TABLE 2
FLOOD ROUTING -SOLOMON GULCH RESERVOIR WITH NEW FIVE-FOOT RUBBER DAM
0 I 1.31 I 0 I I 685.0 I I I I I 34,170 690.0 Start
Flood
. 1.31 I 1.31 I soo I 55 685.1 47 5 49 34,219 690.1 Drop
Rubber
Dam
I
I 1.31 I 700 58 688.6 10,200 14,764 1,220 -1,162 33,056 I 688.5
I
2.31
3.31 I 1.31 I 2,100 175 687.4 5,571 7,885 652 -477 32,580 I 687.5
4.31 I 1.31 I 8,000 667 687.7 6,648 6,110 50S 162 32,742 I 687.7
5.31 I 1.31 I 10,900 908 688.3 8,983 7,816 646 262 33,004 I 688.3
6.31 I 1.31 I 11,700 975 688.5 9,812 9,397 777 198 33,202 I 688.5
7.31 I 1.31 12,000 1,000 688.6 9,812 9,812 811 189 33,391 I 688.6
8.31 I 1.31 12,300 1,025 688.9 11,541 10,676 882 143 33,534 I 688.9
9.31 I 1.31 I 15,200 1,267 689.6 14,797 13,169 1,088 178.6 33,713 I 689.5
10.31 1.31 17,100 1,425 690.0 16,753 15,775 1,304 121 33,833 I 689.9
11.31 1.31 18,200 1,517 690.0 16,753 16,753 1,385 132 33,965 I 690.0
12.31 I 1.31 I 19,800 1,650 690.0 16,753 16,753 1,365 265 34,230 I 690.3
13.31 I 1.31 I 20,600 1,717 690.8 20,950 18,851 1,558 159 34,389 I 690.9
14.31 1.31 22,800 1,900 691.5 24,833 22,891 1,892 8 34,397 I 691.1
15.31 1.31 29,000 2,417 691.5 24,833 24,833 2,052 364 34,761 I 691.5
16.31 Flood routing after hour 15.31
matches flood routing base case
without new rubber dam.
1) Increased storage in the reservoir after the inflow stops in November each year.
2) Higher average head in the reservoir by either 2 feet (0.3%) or 5 feet (0.77%).
3) Increased capture and less spill of inflow during July through October
Increases caused by 1 or 2 above can be estimated directly with good accuracy. Increases
due to 3 above are highly variable and difficult to estimate. In some cases, lack of
sufficient load on the system would prevent these gains from being realized. Therefore,
increased generation for reason three has not been estimated in this study.
At 645 feet of effective head, for example, one turbine at nearly full load of 5,010 kW
uses 108 cubic feet per second of water. This means the unit can run about 0.11 hours
on one acre-foot of water (43,560 cu. ft) and produce about 561 kWh of energy.
From the turbine efficiency curves, it can be seen that this output of 561 kWh/acre-foot
will remain fairly constant with either a 5-foot or a 2-foot head increase. Raising the
spillway will also result in a higher average head throughout the operating year of a small
percentage. This will increase annual production accordingly. The following table shows
the projected energy increases for spillway elevation increases of both 2 feet and 5 feet
2 Feet 1,000 ac-ft 561,000 kWh 120,000 kWh 681,000 kWh
5 Feet 2,500 ac-ft 1,402,000 kWh 300,000 kWh 1,702,000 kWh
IV. Cost Estimate
The cost estimate to install either a 2 foot or a 5 foot Bridgestone Rubber Dam on the
Solomon Gulch spillway was prepared by obtaining a firm quotation from Bridgestone for
. . the dams and by estimating unit quantities of concrete, rebar, anchor bolts, electrical
wiring, etc. The estimates are shown on the following four pages. Cost estimates for
FERC licensing are prepared with two separate options, a minor amendment or a major
amendment. Reasons for this approach are explained in the section on FERC licensing
below.
Delivery of the rubber dam is normally 5 months from p~~cement of order. Construction
time in the field should be completed in about 3 months, one month of preparation prior
to dam delivery and 2 months for complete installation.
The total estimated cost for the 2-foot increase project is $723,148. The estimated cost
for the 5-foot increase project is $1,547,548.
Both estimates contain contingency, 20 percent for construction costs and 40 percen~. for
licensing and permit costs. If further confirming feasibility studies are conducted, these
contingencies should be able to be reduced.·
9
ITEM
1
2
3
4
s
6
7
8
9
10
11
12
13
14
15
16
COPPER VALLEY ELECTRIC ASSOCIATION
SOLOMON GULCH RESERVOIR HEIGIIT INCREASE
DET AD..ED COST ..ESTIMATE (January 1992 Dollars)
TWO FOOT INCREASE CASE
DESCRIPTION
Mobilization
Rubber Dam Including Controls
(2-Two Foot Dia. X 225')
Control House Building
Electrical :
480V Service To Control House
Control House Internal Wiring
Dam Installation:
Remove Splitter Piers
Concrete for Dam support (form & pour)
Drill in Rebar
Set Anchors
Form and Pour new center pier
Install Rubber dams
Bridgestone Site Rep.
Start-up and Test
Design Engineering
Construction Management
SUBTOTAL CONSTRUCTION
Contingency
TOTAL-CONSTRUCTION ONLY
Page 1 of 4
Quantity Unit
1 Is
1 ea
250 sq ft
1260 ft
1 Is
17 ea
25 cuyd
1 Is
1 Is
5 cuyd
2 ea
40 days
1 Is
1 Is
Is
20%
Unit$ Cost$
$10,000 . $10,000
$273,000 $273,000
$75 $18,750
>
...... ) .............. ; ··•.
$4 $5~040
$6,000 .$6,000
: ..
.........•••.•.•.•..••......•.•..•••......... :
$500 . )$8,500
$1,000 . •$25.0()()
$3,000 > .$3;~
$2,000 . $2,000.
$1,000 (· $5~000
$8,000 ; >}.$1~.{)()()
$600 <'$24;000.
$55,000 $55,0()()
$25,000 $25~00()
>:-_-· :>: <:>::::::-:: __ : :·:·==:~:.
$481,29().
·-~ :-:::.>(:··· :::;:-:.::::-__ :_·_::?::
. $96,258.
~~tm!iB.ri
FERC Licensing:
(Assumes Minor Amendment)
17 Prepare Draft Licensing Plan & Proj. De 1 Is $15,000 $15,000
18 Agency Consultation 1 ls $12,000 <$12,000
19 Draft Amendment Application 1 Is $5,000 $5,000
'""' 20 Agency Review and Comment 1 ls $10,000 $10,000
21 FERC Filing and Follow-up 1 ls $5,000 $5,000
22 Contingency 30% >$14,100
Subtotal FERC Licensing . $61,100
FERC Licensing:
(Assumes Major Amendment)
17A Prepare Draft Licensing Plan & Proj. De 1 Is $20,000
18A Agency Consultation 1 ls $15,000
19A Conduct Public Hearing(s) 1 Is $5,000
20A Perform Required Studies 1 Is $30,000
21A Draft Amendment Application 1 Is $10,000
22A Agency Review and Comment 1 Is $12,000
23 FERC Filing and Follow-up 1 Is $12,000
24 Contingency 40%
Subtotal FERC Licensing
25 TOTAL COST (Minor Amendment)
26 TOTAL COST (Major Amendment)
Note: Estimated licensing costs are based on the assumption that CVEA staff will provide
significant support for required field work and studies, including labor, small tools
and transportation
2 of4
ITEM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
COPPER VALLEY ELECTRIC ASSOCIATION
SOLOMON GULCH RESERVOIR HEIGHT INCREASE
DETAILED COST ESTIMATE (Janwuy 1992 Dollars)
FIVE FOOT INCREASE CASE
DESCRIPTION Quantity Unit
Mobilization 1 ls
Unit$ Cost$
$10,000 •$10,000
.~ .
Rubber Dam Including Controls
(2-Five Foot Dia. X 225')
1 ea $471 ,ooo <$tn,Oo6
Control House Building
Electrical :
480V Service To Control House
Control House Internal Wiring
Dam Installation:
Remove Splitter Piers
Concrete for Dam support (form & pour)
Drill in Rebar
Set Anchors
Form and Pour new center pier
Install Rubber dams
Bridgestone Site Rep.
Start-up and Test
Design Engineering
Construction Management
SUBTOTAL CONSTRUCTION
TOTAL-CONSTRUCTION ONLY
Page 3 of 4
250 sq ft
1260 ft
1 Is
17 ea
502 cuyd
1 Is
1 Is
5 cuyd
2 ea
45 days
1 Is
1 Is
1 Is
20%
::::_:·-=:~:+:;=-=.::.:::=::><
··········\·················i .....•....... $15 ::$18~750
···• in i••••••<••
$4 <",;\"i~;~
$6,000 .· . $ti,OOO
.·-.-·-·· ,,., .. _ ..
::-_: :::~ ::: C::: ::-:::-::-=:::_ :::.::X-::·=:~ ~i
$500 rr~1~~~rm:!
$1,000 $502~000
$3,000 .····••·· $3,000 $2,000 > $2~000
$1,000 ·. $5,000
$10,000 :: $2(),()()0
$600 •.... $27,000
-::-:::):/>?F>:\/:::_=:.
$5,000 $5,000
~ ;= ): ) . :~~;~ :' _; -~ ~-;: :-:.:·:=':: ~;=;=~:;·;. ;_ ;:
$60,000 $60,()00
$25,000 $25,ooh
st,i~&.i~
. ..
$233,658 ..
ili~~~iJ,iM
17
18
19
20
21
22
17A
18A
19A
20A
21A
22A
23
24
25
26
FERC Licensing:
(Assumes Minor Amendment)
Prepare Draft Licensing Plan & Proj. De
Agency Consultation
Draft Amendment Application
Agency Review and Comment
FERC Filing and Follow-up
Contingency
Subtotal FERC Licensing
FERC Licensing:
(Assumes Major Amendment)
Prepare Draft Licensing Plan & Proj. De
Agency Consultation
Conduct Public Hearing(s)
Perform Required Studies
Draft Amendment Application
Agency Review and Comment
FERC Filing and Follow-up
Contingency
Subtotal FERC Licensing
TOTAL COST (Minor Amendment)
TOTAL COST (Major Amendment)
1
1
1
1
1
1
1
1
1
1
1
1
Is
Is
Is
Is
Is
Is
Is
Is
Is
Is
Is
Is
$15,000 $15,000
$12,000 $12,000.
$5,000 .ss.ooo
$10,000 $10,000
$5,000 $5,000
30% $14;100
$61,100
··. . . -....
:--_::>:}::.:::::·::::::
$20,000 . · .. $20,000
$15,000 ·.. $15;000 .
ss,ooo .· 'sS,oocl
$30,000 ; ; $30,000
$10,000 $lO,o00
$12,000 . ·.·. $1~~000
$12,000 $12,000
,' -__ :: ·_ :_-:/::>·_::\:)_\~>.V
40% s4i~6o0
<$145,600
!!111ll1%
1;14.1~11!\:
Note: Estimated licensing costs are based on the assumption that CVEA staff will provide
significant support for required field work and studies, including labor, small tools
and transportation
Page 4 of4
V. Economic Analysis
Following is a simple comparison of the study results for the 2 foot and 5 foot options:
5-Foot Increase $1,547,548. 1,702,000 0.91
2-Foot Increase $723,148. 681,000 1.06
This simple comparison shows the 5-foot increase project is considerably more cost
effective than the 2-foot increase project. Further analysis will only address the 5-foot
increase project.
For this study, it was not possible to perform a detailed economic analysis of the project
mainly due to uncertainty about financing methods, sources and costs of funding and
potential savings. However, the chart below illustrates some potential economics based
on some simple assumptions:
The savings shown above are only assumptions and do not consider potential savings from
operator costs at the hydroelectric project or other potential savings at the diesel
generating plants.
VI. Environmental Concerns and Other Issues
H a project was undertaken to raise the spillway at Solomon Gulch, we would expect a
variety of environmental concerns to be raised by local, State and federal agencies with
jurisdiction over the project. We have reviewed the existing FERC License for the
project as well as the original FERC License Application and the original project
environmental impact statement. Following is a list of questions, concerns and issues that
we believe will be raised as part of the permit process for raising the spillway:
10
SHORT-TERM IMPACIS
A) Disturbance to Wildlife
Will construction-related noise, human presence and activity cause significant
impacts to wildlife? ("Significant" in this context usually means a permanent
or long-term loss in local population level).
Note: According to the Final EIS for the original project, "several wildlife
species inhabiting the proposed project area are considered endangered, but
maintain stable populations within Alaska. They include the wolf and
brown/grizzly bear." -FERC, Final EIS, 1978, Page 2-20.
No rare, threatened or endangered plants are known to exist in the project
area. -FERC, Final EIS, 1978, Page 2-20.
"There are no wetlands or other known areas of critical environmental
concern connected with the proposed action of the Solomon Gulch Project." -
Application for License, Exhibit W, Page 38, R. Retherford Associates, 1975.
B) Construction Timing
How will the timing of construction activities affect fish and wildlife?
Note: For the original project, the ADFG requested that blasting activities be
scheduled for mid-summer to fall, when big game populations are generally
dispersed to higher elevations. -FERC License Application, Exhibit S, 1976.
C) Water Quality Impacts
1) What will be the effects of increased turbidity, suspended solids,
construction materials, and other pollutants in the lake or creek?
2) Will there be any alteration to the downstream flow regime during
construction which will affect water quality parameters such as temperature
and dissolved oxygen, or minimum flows?
3) What will be the impacts to existing fiSh and fisheries habitat from
construction activities?
Note: Native salmon spawning in Solomon Gulch Creek appears to be very
limited. ADFG found that only 200-500 pink and chum salmon used the
creek for spawning and only in the intertidal area in odd-years. -FERC
License Application, Exhibit S, 1976.
ADFG also found no resident ·fish population in Solomon Lake. -FERC
License Application, Exhibit S, 1976.
11
,-
I·
4) What will be the impacts to Water Quality and Fisheries from leachate
from abandoned mines?
D) Air Quality Impacts
What will the be the effects of increased dust and hydrocarbon emissions to
local air quality?
E) Erosion and Sedimentation
What will be the effects of erosion and sediment on vegetation, wildlife
habitat, water quality, and fisheries?
LONG-TERM OPERATIONAL IMPACfS
A) Wildlife
1) Will the higher lake level block any wildlife passage or inundate any
unique habitat?
2) Will project features (dam) result in the loss of wildlife habitat?
B) Fisheries
1) Will draw down of lake under the new lake level conditions cause water
quality impacts, such as changes to temperature or dissolved oxygen in
discharge waters?
2) What will be the effect of increased· discharge water to downstream fish
populations and habitat?
3) What will be the effect of increased discharge water to the downstream
fish hatchery operation? (Increased winter flows are expected to improve
hatchery operations).
C) Recreation
1) Will the higher lake level inundate existing or proposed recreation
facilities?
2) What will be the increased visual impacts, if any, of the larger new dam?
3) What will be the effect of the project on recreational demand in the area?
Will public access be improved or new demand created?
12
Raising the reservoir level on an impoundment will automatically trigger the need for a
FERC Ucense Amendment. There are basically two types of amendments, a minor
amendment and a major amendment.
The minor amendment is used when there are no significant environmental impacts
expected from a change and no objection by any agencies or the public. FERC will deem
the change to be a "non-significant action" on the part of FERC, give public notice of the
change, and in the Federal Register asking for comments after the notice period if there
are no intervenors, FERC will issue the amendment. This process normally can take 6
months and as little as 3 months from date of application.
A major amendment is used if there is any chance of significant environmental issues
surfacing or any controversy over the proposed change. It is also used any time FERC
must say the change is a "significant action". If there is any Agency opposition to the
change it will likely require a major amendment The major amendment process includes
the ECPA three stage consultation process, preparation of draft license amendments,
study plans, three stages of agency consultation and public hearings. It is difficult to
process a major amendment in less than 1-1/2 to 2 years due to statutory notice and
waiting periods for agency review and comment
FERC staff indicated in the informal conversation that this project .muJJ;l be a candidate
for a minor amendment based upon our explanation of the proposed improvement. We
would need to prepare a complete project description and solicit Agency comments. If
we get support from all the local agencies and can settle all potential issues to everyone's
satisfaction before we officially apply to the FERC, they may well treat the application
as a minor amendment. If, however, any agency requests the full three stage consultation
process, FERC will have no option but to treat the project as a major change, which
would demand the major amendment process.
This uncertainty makes it difficult to assess this aspect of the overall project.
Unfortunately, further study will not eliminate this uncertainty. Initial agency contactS will
give us some indication of local concerns and agency positions, but some uncertainty will
still exist on this issue up until FERC accepts the application and confirms it as either a
minor or major change.
Our cost estimates used for economic analysis in this report assumed a major amendment
would be necessary. ·
IX. Conclusions and Recommendations
It is concluded that:
1) Both the 2-foot increase and the 5-foot increase projects are feasible technically.
2) Increase beyond 5 feet will require dam structure modification and will be very costly.
With proper controls, the 5-foot increase will not affect the flood routing of the probable
maximum flood through Solomon Gulch Reservoir.
14
i-
I~
3) The 5-foot spillway height increase is more attractive than the 2-foot increase.
4) The 5-foot increase project is estimated to cost $1,547,500. Additional annual
generation of 1,702,000 kWh is projected as a result of this change.
It is recommended that:
1) CVEA examine the potential system wide savings from this potential project and
compare the costs we have ·projected to the potential benefits. Our simplified analysis
indicates that savings in excess of nine cents per kilowatt hour will need to be realized
just to make the debt service payments for the project.
2) CVEA should make a GO/NO GO decision on this project. If a GO decision is made,
HDR will proceed with a more detailed and in depth analysis of the project, including a
more in depth environmental review, informational contacts with fish hatchery and key
agencies, refinement of design and cost estimates and preparation of preliminary design
layouts and drawings.
Other issues that need to be reviewed should the project proceed include:
*
*
*
*
Review downstream facilities for flood impacts due to lowering the rubber dam,
especially the fish hatchery.
Review bridge abutments on access road to check impact of flood from lowering
dam.
Verify turbines and penstocks capability to handle higher pressure.
Investigate benefits to fish hatchery from additional availability of water.
HDR is available to assist CVEA in whatever ways possible in making the GO/NO GO
decision.
15
APPENDICES
1. Bridgestone Cost Quotations • Rubber Dam
2. Connection Diagram • 2-foot Dam
3. Connection Diagram -5-foot Dam
4. Letter from Bridgestone regarding ice performance
! .
r
October 10, 1991
Mr. Jack Snyder
HDR
Suite 200, Building C
11225 S.E. Sixth Street
Bellevue, WA 98004-6441
RE: YB call of October 1 0:
Solomon Gulch Rubber Qam
Dear Mr. Snyder,
~R/06ESTORE
BRIDGESTONE ENGINEERED PRODUCTS COMPANY
7659 775 Avenue West
Oak Harbor, WA 98277
A Division of Bridgestone/Firestone, Inc.
TEL: (206) 679·1249
FAX: (206) 675-6558
Thank you for your call today concerning the Solomon Gulch Project. Enclosed
please find the following:
1) Price quotes for 2'H x 235'L x 2 span Rubber Dam and 5'H x 235'L x 2 span
Rubber Dam
2) Copy of simplified cross section of Solomon Gulch Spillway. Based on this
sketch our engineering staff will make drawings showing how 2' and 5' high
Rubber Dams might be attached to the existing structure. These drawings
should be completed in about two weeks.
3) Copy of letter sent to Mr. Mike Easley of Copper Valley Electric.
4) Bridgestone Rubber Dam sales and technical information consisting of
White Folder and Grey Binder.
The ability for the Rubber Dam to greatly increase the utility of the reservoir
seems, at first glance, to make this project cost-effective. Determining that is
your job. Mine is to provide all the information necessary to aid your evaluation
of the Bridgestone Rubber Dam option. I look forward to working with you.
Very truly yours,
CK~~~ St~;;aGrave
Bridgestone En ineered Products Company
CC: BEP-N
5230C
I ~·
BRIDGESTONE RU8BER OAM PRICE ESTIMATE
Project: Solomon Gulch
Date: October 10, 1991
SPEC/FICA TIONS
Height: 2 feet
Length: 235 feet (on foundation)
Side Slope: 1 : .5 (V:H)
Anchor: Single Anchor Une
Cost Per Span: US $129,050
Number of Spans: 2
Optional Control SYS Cost: US $25,000
Quote Offer. US $283,099
PRICE
PRICE CONDITIONS
Price Condition: FOB job site.
Delivery Terms: To job site within fiVe months of purchase order and drawing approval.
Packing: Bridgestone standard (wooden case/roll), normally containerized.
Payment: Net 90 days.
Validity: Until January 8, 1992
Standard Equipment:
Rubber Darn Body; Embedded Plates; ClaJ'll)ing Plates; Anchor Botts; Spacer Pipes; Air Blower;
Control Panel; Automatic Deflation Mechanism; Design Documents, Drawings and Manuals.
FIXing Components:
Clamping Plate: Galvanized ductile cast iron JIS FCDSOIASTM A536 GR.60
Embedded Plate: Galvanized rolled steel JIS SS41/ASTM A36
Anchor Bolt: Galvanized chrome molybdenum steel JIS SCtM35fASTM A29 GR.4235
Nut: Galvanized carbon steel JIS S45C/ASTM A575 GR.1045
Control System: 5
Inner pressure of Rubber Dam is controlled in pre-set range by automatic air supply/exhaust function.
Automatic Deflation System:
Bucket Type
Excluded From Price:
Concrete and Civil Works, .Installation Cost, Site Advisor for installation of Rubber Darn.
(Per October 11l/91 request of Mr. Jack Snyder of HDR.
· ory Manager
red Products Company
J
BBIDGESTOHE RUBBER DAM PRICE ESTIMATE
Project: Solomon Gulch
Date: October 10, 1991
SPEC/FICA TIONS
Height: 5 feet
Length: 235 feet (on foundation)
Side Slope: 1 : .5 (V:H)
Anchor: Single Anchor Une
Cost Per Span: US $232,782
Number of Spans: 2
Optional Control SYS Cost: US $25,000
Quote Offer: US $490,563
PRICE
PRICE CONDITIONS
Price Condition: FOB job site.
Delivery Terms: To job site within fiVe months of purchase order and drawing approval.
Packing: Bridgestone standard (wooden case/roll). normally containerized.
Payment: Net 90 days.
Validity: Until January 8, 1992
INCLUDED IN PRICE
Standard Equipment:
Rubber Dam Body; Embedded Plates; Clamping Plates; Anchor Bolts; Spacer Pipes; Air Blower;
Control Panel; Automatic Deflation Mechanism; Design Documents, Drawings and Manuals.
FIXing Components:
Clamping Plate: Galvanized ductile cast iron JIS FCD501ASTM A536 GR.60
Embedded Plate: Galvanized rolled steel JIS SS41/ASTM A36
Anchor Bolt: Galvanized chrome molybdenum steel JIS SCM435JASTM A29 GR.4235
Nut: Galvanized carbon steel JIS S45C/ASTM A575 GR.1045
Control System: [ 5 ]
Inner pressure of Rubber Dam is controlled in pre-set range by automatic air supply/exhaust function.
Automatic Deflation System:
Bucket Type
Excluded From Price:
Concrete and Civil Works. Installation Cost, Site Advisor for installation of Rubber Dam.
(Per October 10/91 request of Mr. Jack Snyder of HOR.
rritory Manager
red Products Company
COMMENTS
]
I,
,_
,.
Solomon Gulcti Rubber Dam
2.'
---ll:..-------· _ .....
AfP/ZIJX
I f.t-
2 Foot Case
Rubber Dam
Rubber Dam
' / t\J /
~ ' /
~
"'
1> ... ...
/ ... ~ ' " ~
./ ..
s;.
I
-1:::.
t\=T\'\OJ) .. ~"
'Wi:il:>"G 'Sil.fiVE
\ I \
/-It" ' \
.. t
\
\
\
I \ I' ~~
I M~'O ~
< ~C.j.\'0 wf'.\..i.. "CO ~ ::>
::0 ;r;,
I ,.,
-,,
'"'
Solomon Gulch Rubber Dam
5 Foot Case
October 10 1991
Mr. Mike Easley
Copper Valley Electric
P.O. Box45
Glenn Allen, Alaska 99588
Dear Mr. Easley,
.Jti/U6ESTOI/E
BRIDGESTONE ENGINEERED PRODUCTS COMPANY
7659 775 Avenue West
Oak Harbor, WA 98277
A Division of Bridgestone/Firestone, Inc.
TEL: (206) 679·1249
FAX: (206) 675-6558
Pursuant to your call of September 30 and my fax of October 1 please find
enclosed photographs of our Palmer Falls Rubber Dam undergoing ice over-
topping. Although I know you already have our literature, I have enclosed
another set as well.
I would like to advise you that today I received a telephone call from Mr. Jack
Snyder of HDR who advised that his firm had been engaged by Cooper Valley
Electric for the Solomon Gulch Project. I advised him that it may be helpful at
this stage to have· detailed drawings showing attachment of the Rubber Dam on
the crest of the spillway and that we can proceed with such if provided a cross
section of the existing spillway. Mr. Snyder said he would fax same. I hope to
forward such drawings to him in two weeks.
I look forward to the privilege of working with you.
Very truly yours,
ineered Products Company
cc: HDR Mr. Jack Snyder
BEP~N
I .
..
PALMER FALLS RUBBER DAM
ALTHOUGH THIS ICE IS THIN, 3 FEET IS COMMON AT THIS SITE
SEE ATTACHED SUPPLY EXAMPLE FOR PICTURES
OF THIS RUBBER DAM WITHOUT ICE
I.
I
PALMER FALLS RUBBER DAM
ALTHOUGH THIS ICE IS THIN, 3 FEET IS COMMON AT THIS SITE
SEE ATTACHED SUPPLY EXAMPLE FOR PICTURES
OF THIS RUBBER DAM WITHOUT ICE
PALMER FALLS RUBBER DAM
ALTHOUGH THIS ICE IS THIN, 3 FEET IS COMMON AT THIS SITE
SEE ATTACHED SUPPLY EXAMPLE FOR PICTURES
OF THIS RUBBER DAM WITHOUT ICE
! ---
PALMER FALLS RUBBER DAM
ALTHOUGH THIS ICE IS THIN, 3 FEET IS COMMON AT THIS SITE
SEE ATIACHED SUPPLY EXAMPLE FOR PICTURES
OF THIS RUBBER DAM WITHOUT ICE
.JRID6ESTORE HYDROELECTRICITY
HUDSON RIVER
U.S.A.
Rubber Dam atop rehabilitated Dam. Powerhouse is on the left .
. .
Flashboards were replaced with two Rubber Dam spans.