Loading...
HomeMy WebLinkAboutBradley Lake Geology Report Vol 1 1991A Iaska Porer Authority FINAL CONSTRUCTION GEOLOGY REPORT BRADLEY LAKE HYDROELECTRIC PROJECT Homer, Alaska VOLUME 1 GEOLOGY REPORT AND APPENDIX A PRBPARED BY: BECHTEL CORPORATION SAN FRANCISCOJ CALIFORNIA ALASKA ENERGY AUTHORITY Anchorage, Alaska BRADLEY LAKE HYDROELECTRIC PROJECT FINAL CONSTRUCTION GEOLOGY REPORT May, 1991 Prepared by: BECHTEL CORPORATION San Francisco, CA Section 1.0 2.0 2. 1 2.2 2.3 2.3.1 2.3.2 2.4 2. 4. 1 2.4.2 2. 4. 3 3.0 3. 1 3.2 3.2.1 3.2.2 3.3 3. 3.1 3.3.2 3.4 3. 4. 1 3.4.2 3.4.3 4.0 4. 1 4.2 T A B L E 0 F INTRODUCTION POWERHOUSE Site Description Vicinity Geology Geology of Excavation Rock Weathering Ground Water C 0 N T E N T S Excavation of Slopes and Foundations Controlled Blasting and Overbreak Rock Reinforcement Foundation Conditions POWER TUNNEL MANIFOLD, PENSTOCK TUNNEL AND ACCESS ADIT General Description Access Adit Excavation and Support Geology Penstock Tunnels Excavation and Support Geology Power Tunnel Manifold Excavation and Support Geology Tunnel Lining and Grouting LOWER POWER TUNNEL General Description Tunnel Boring Machine (TBM) 1-1 2-1 2-1 2-1 2-2 2-3 2-4 2-4 2-5 2-8 2-9 3-1 3-1 3-1 3-1 3-2 3-2 3-2 3-3 3-5 3-5 3-7 3-9 4-1 4-1 4-2 Section 4.3 4. 3. 1 4. 3. 2 4.3.3 4.4 4. 4. 1 4.4.2 4.4.3 4.4.4 4.5 4. 5. 1 4. 5. 2 4. 5. 3 4. 5. 4 4. 5. 5 5.0 5.1 5.2 5. 2. 1 5.2.2 5.2.3 5. 2. 4 5.3 5. 3. 1 5.3.2 5. 3. 3 5.4 5.4.1 5.4.2 5.4.3 6.0 6.1 T A B L E 0 F C 0 N T E N T S Tunnel Sta 5+20 to Sta 14+10 Excavation and Support Geology Tunnel Lining and Grouting Tunnel Sta 14+10 to Sta 31+60 Excavation and Support Geology Design Modifications Tunnel Lining and Grouting Tunnel Sta 31+60 to Sta 177+51 Excavation and Support Geology Continuous or Skip Lining Tunnel Lining and Grouting High Pressure Compaction Grouting UPPER POWER TUNNEL AND GATE SHAFT INTAKE CHANNEL, AND POWER TUNNEL SHAFT General Description Upper Power Tunnel and Gate Shaft Excavation and Support Geology Concrete Lining and Grouting Seepage Barrier Grout Curtain Intake Channel Excavation and Wall Reinforcement Geology Removal of Rock Plug Power Tunnel Shaft Excavation and Support Geology Concrete Lining and Grouting DAM, SPILLWAY, AND DIVERSION TUNNEL GATE SHAFT General Description 4-4 4-4 4-6 4-9 4-10 4-10 4-12 4-15 4-15 4-16 4-16 4-19 4-26 4-26 4-29 5-1 5-1 5-2 5-2 5-3 5-4 5-6 5-7 5-7 5-9 5-10 5-12 5-12 5-13 5-15 6-1 6-1 Section 6.2 6. 2. 1 6. 2. 2 6.2.3 6.2.4 6. 2. 5 6.3 6. 3. 1 6.3.2 6.3.3 6.4 6. 4. 1 6. 4. 2 6. 4. 3 6. 4. 4 7.0 7. 1 7.2 T A B L E 0 F Dam and Cofferdam Foundation Excavation C 0 N T E N T S Plinth Excavation and Foundation Treatment Foundation Geology Rockfill Materials Foundation Grouting Spillway Foundation Excavation and Treatment Geology Foundation Grouting Diversion Tunnel Gate Shaft Excavation and Support Geology Concrete Lining and Grouting Seepage Barrier Grout Curtain MIDDLE FORK AND NUKA DIVERSION General Description Excavation 6-2 6-3 6-4 6-6 6-8 6-10 6-11 6-11 6-12 6-13 6-14 6-14 6-15 6-16 6-16 7-1 7-1 7-1 Section 1.0 2.0 2.1 2.2 2.3 2.3.1 2.3.2 2.4 2.4.1 2.4.2 2.4.3 3.0 3.1 3.2 3. 2. 1 3.2.2 3.3. 3.3.1 3.3.2 3.4 3.4.1 3.4.2 3.4.3 4.0 4. 1 4.2 T A B L E 0 F INTRODUCTION POWERHOUSE Site Description Vicinity Geology Geology of Excavation Rock Weathering Ground Water C 0 N T E N T S Excavation of Slopes and Foundations Controlled Blasting and Overbreak Rock Reinforcement Foundation Conditions POWER TUNNEL MANIFOLD, PENSTOCK TUNNEL AND ACCESS ADIT General Description Access Adit Excavation and Support Geology Penstock Tunnels Excavation and Support Geology Power Tunnel Manifold Excavation and Support Geology Tunnel Lining and Grouting LOWER POWER TUNNEL General Description Tunnel Boring Machine (TBM) Section 4.3 4. 3. 1 4.3.2 4.3.3 4.4 4. 4.1 4.4.2 4.4.3 4.4.4 4.5 4. 5. 1 4. 5. 2 4. 5. 3 4. 5. 4 4. 5. 5 5.0 5. 1 5.2 5. 2. 1 5.2.2 5.2.3 5.2.4 5.3 5. 3. 1 5. 3. 2 5.3.3 5.4 5. 4. 1 5.4.2 5.4.3 6.0 6. 1 T A B L E 0 F C 0 N T E N T S Tunnel Sta. 5+20 to Sta. 14+10 Excavation and Support Geology Tunnel Lining and Grouting Tunnel Sta. 14+10 to Sta. 31+60 Excavation and Support Geology Design Modifications Tunnel Lining and Grouting Tunnel Sta. 31+60 to Sta. 177+51 Excavation and Support Geology Continuous or Skip Lining Tunnel Lining and Grouting High Pressure Compaction Grouting UPPER POWER TUNNEL AND GATE SHAFT INTAKE CHANNEL, AND POWER TUNNEL SHAFT General Description Upper Power Tunnel and Gate Shaft Excavation and Support Geology Concrete Lining and Grouting Seepage Barrier Grout Curtain Intake Channel Excavation and Wall Reinforcement Geology Removal of Rock Plug Power Tunnel Shaft Excavation and Support Geology Concrete Lining and Grouting DAM, SPILLWAY, AND DIVERSION TUNNEL GATE SHAFT General Description Section 6.2 6. 2. 1 6. 2. 2 6. 2. 3 6.2.4 6. 2. 5 6.3 6. 3. 1 6.3.2 6.3.3 6.4 6. 4. 1 6.4.2 6.4.3 6.4.4 7.0 7. 1 7.2 T A B L E 0 F Dam and Cofferdam Foundation Excavation C 0 N T E N T S Plinth Excavation and Foundation Treatment Foundation Geology Rockfill Materials Foundation Grouting Spillway Foundation Excavation and Treatment Geology Foundation Grouting Diversion Tunnel Gate Shaft Excavation and Support Geology Concrete Lining and Grouting Seepage Barrier Grout Curtain MIDDLE FORK AND NUKA DIVERS!ON General Description Excavation Volume 1 2 2 2 2 2 A P P E N D I C E S Final Geology and Supporting Data Appendix A B c D E F Title Project Photographs Powerhouse Power Tunnel Manifold, Penstock Tunnels, and South Access Adit Lower Power Tunnel Upper Power Tunnel & Gate Shaft, Intake Channel, and Power Tunnel Shaft Main Dam, Spillway, Diversion Tunnel Gate Shaft, and Middle Fork and Nuka Diversions The above appendices of figures, plates, and tables are referenced in the text of this report. Most of the plates have been adapted from Stone & Webster Engineering's project design drawings by the deletion of data considered non- essential for the purposes of this geologic report. Figures are intended to reflect the as-built geologic conditions of the Bradley Lake Hydroelectric Project; however, the figures do not show in every detail the constructed conditions. Adapted plates are included to show the primary project features, as well as to indicate the extent of excavation and rock reinforcement. Appendix A B c D LIS'!' OF FIGURES, PLATES, AND 'lABJ:&CJ Plate No. 2-1 2-2 4-1 4-2 Figure No. 2-1 Title Project Photographs Powerhouse Rock Reinforcement Plan and Section Powerhouse Excavation & Rock Reinforcement and Sections Geologic Maps, Powerhouse Excavation Walls - 8 sheets 2-2 Geologic Maps, Powerhouse Foundations - 2 sheets 3-1 Geologic Face Maps, South Access Adits -20 sheets 3-2 Geologic Maps, Power Penstock Trench and Portal -3 sheets 3-3 Geologic Maps, Unit No. 1 Penstock Tunnel and Thrustblock - 7 sheets 3-4 Geologic Maps, Units No. 2 Penstock Tunnel and Thrustblock -10 sheets 3-5 Geologic Maps, Unit No. 3 Penstock Tunnel and Thrustblock -21 sheets 3-6 Geologic Tunnel Logs & Maps, Power (Manifold) Tunnel -30 sheets 3-7 Geologic Map, Power (Manifold) Tunnel Portal & Bridge Abutment Power Tunnel, Bid Option B Plan & Profile Power Tunnel Intersection with South Access Adit LIST OF FIGURES, PlATES, .ARD TABLBS -(continued) Appendix Plate No. 4-3 4-4 E 5-1 5-2 Figure No. 4-1 4-2 Table 4-1 Table 4-2 Table 4-3 5-1 5-2 Title Geologic Log and Maps, Lower Power Tunnel Sta 5+20 to 14+10 -40 sheets Power tunnel Geologic Plan & Profile -4 sheets Power Tunnel Alignment & Major Faults Geologic Tunnel Logs, Lower Power Tunnel Sta 14+10 to Sta 177+50 -82 sheets TBM Daily Progress Lower Power Tunnel Tape Extensometer Data Lower Power Tunnel -19 sheets Strain Gage Readings Lower Power Tunnel - 3 sheets Pilot Hole, Power Tunnel Vertical Shaft - 4 sheets Geology Map, Upper Power Tunnel Gate Shaft Collar Excavation Power Tunnel Gate Excavation, Sections Power Tunnel Gate Shaft & Chamber, High pressure Grouting 5-3 Geologic Tunnel Logs - 6 sheets 5-4 Geologic Face Maps, Upper Power Tunnel -13 sheets 5-5 Geologic Map, Power Tunnel Gate Shaft LIS'!' OF FIGURES, PLA'l'ES, AND TABLES -(continued) Appendix Plate No. 5-3 5-4 5-5 5-6 F 6-1 6-2 6-3 Figure No. 5-6 5-7 Title Power Tunnel Intake Channel Excavation Plan Power Tunnel Intake Portal Excavation Plan & Section Power Tunnel Intake Channel Excavation Sections & Details Geologic Wall Haps, Power Tunnel Intake - 3 sheets Power Tunnel Shaft Sections Geologic Wall Haps, Power Tunnel Vertical Shaft - 8 sheets Main Dam Rock Excavation Plan & Profile 6-1 Geologic Hap, 6-2 6-3 6-4 6-5 6-6 Main Dam Plinth Foundation - 5 sheets Geologic Data Summary, Main Dam Toe Plinth Foundation - 2 sheets Concrete Face Rockfill Dam Sections Main Dam, Drilling and Grouting, Plan and Profile Spillway Plan and Section Geology of Spillway Foundation -3 sheets Main Dam Spillway Drilling & Grouting Main Dam Spillway Drilling & Grouting Profile LIST OF FIGURES, PLATES, ARD TABLES -(continued) Appendix Plate No. Figure No. 6-4 6-7 7-1 7-2 Title Main Dam Diversion, Gate Shaft Excavation Sections Geologic Maps, Main Dam Diversion Gate Shaft - 2 sheets Middle Fork Diversion, Intake & Upper Channel Profile & Sections Nuka Diversion, Nuka River Outlet Structure Plan REFERENCES: 1. conformed Copy General Civil Construction Contract Contract No. 2890060 Bradley Lake Hydroelectric Project Volume 3 Volume 5 Volume 6 Civil, Structural and Architectural Technical Requirements General Civil Contract Design Drawings Geotechnical Interpretive Report Supporting Documents Prepared by Stone & Webster Engineering Corporation 2. Bradley Lake Hydroelectric Project Main Dam and Spillway Grout Curtain October, 1989 Prepared by Bechtel Civil, Inc. 3. Bradley Lake Hydroelectric Project Project (Jobsite) Files File Retainer Bechtel Civil, Inc. Construction Manager 4. Bradley lake Hydroelectric Project Lower Power Tunnel High Pressure Compaction Grouting Sta 65+00 t Sta 31+60 Prepared by Stone & Webster Engineering Corporation with Inspection Records by Bechtel Corporation, Construction Manager 1.0 INTRODUCTION The Owner of the Bradley Lake Hydroelectric Project is the Alaska Energy Authority (AEA), previously known as the Alaska Power Authority (APA). Stone & Webster Engineering Corporation is the project design Engineer and Bechtel Civil, Inc. is the Construction Manager. Construction began July 1, 1988, and by November, 1989 most of the final foundation and underground excavation had been completed. At the end of 1990 construction of the power facilities. was essentially completed. The Bradley Lake Hydroelectric Project is located on the east side of Kachemak Bay about 27 miles northeast of Homer, Alaska. The principal project features consist of a 145 ft high rock-fill concrete face dam, a 3.6 mile long, 15.1 ft excavated diameter power tunnel, and an outdoor two unit 70 MW powerhouse operating under a maximum head of approximately 1,000 feet. The general location of project features are shown on Plate 1-1 at the end of this section. The primary intent of this report is to document the "as- built" engineering geology for the constructed facilities. Documentation developed during and at the conclusion of construction is intended to serve a number of purposes which include those given below: 1. The report is a requirement of FERC regulations for project licensing. 2. The project contract documents specified the ments for geologic mapping of excavations for features. 1 - 1 require- principal 3. During construction, mapping to identify and record geologic features, e.g. faults, shear seams, weak rock, water in flows, that may require monitoring and/or remedial measures prior to covering with permanent concrete. 4. As an adjunct logging of open and mentation of rock performance which to (3.) above, geologic mapping and underground excavations provides docu- characteristics, ground quality and can be useful in settling contractor claims of changed conditions. 5. The report provides a geologic record of the excava- tions for the Owner. This information can be useful in the development of remedial measures in the event a geological related problem arises after the facility goes into opera- tion. In fulfilling the above requirements, geologic mapping was done for all the principal project features, tunnels, shafts, dam, spillway, and the powerhouse foundations including interior and exterior walls. Geologic maps, logs, and data sheets completed during construction of the project features are included in the Appendices. The report also includes a discussion of the project geology and rock conditions encountered during construction. Selected photo- graphs of selected excavations and geologic features of project features and rock conditions during various stages of construction are given in Appendix A. With few excep- tions, which are discussed subsequently in the report, the geology and rock conditions encountered during construction are in substantial agreement with the pre-construction Geotechnical Interpretive Report (GIR) with Supplements, 1 - 2 prepared by the Stone & Webster Engineering Corporation (SWEC). Included in the responsibilities of the project Construction Manager were monitoring, mapping, and recording of geotechnical aspects of the Bradley Lake Hydroelectric Project throughout the construction period, July, 1987 through November, 1990. These geotechnical activities included: o Geologic mapping of tunnels, shafts, foundations, and open excavations o Monitoring near surface and underground excavations and providing geotechnical assessments of any geological related concerns to engineering and construction managers. o Inspection and direction on final foundation prepara- tion for dam and powerhouse o Monitoring and inspection of pressure and contact grouting of dam foundations and grouting o Blasting vibration monitoring This report is organized into five main sections: Introduction Powerhouse Manifold and Penstock Tunnels Main Dam and Spillway Upper and Lower Power Tunnel 1 - 3 For background project geology, reference should be made to the previously mentioned Geotechnical Interpretive Report (GIR). This report with supplements provides a detailed comprehensive description of the geology and the expected rock conditions based on pre-construction geotechnical studies and field investigations. The project geologist, Dale L. Roberts, who prepared this report was assigned to the Bradley Lake Hydroelectric Project full time. Other Bechtel geologists; Hike Beathard, John Sollo, Peter Yen, and Jacque Lord on temporary assign- ments monitored the foundation grouting of the main dam and spillway. Doug Isler formerly of (SWEC) performed most of the geologic field mapping and prepared the draft report write up for the Lower Power Tunnel from Sta. 14+10 to Sta. 177+51. To avoid constraints on the Bechtel project geologist, arrangements were made for a geologist from the Engineer to assist the Construction Manager with tunnel geologic mapping activi- ties. 1 - 4 ' I BRADLEY JUNCTION I . .., ..... / ·-'"~. ' . ,, .. :.· .. . . •'' ... _ .. ~ . "' '• -- :;_.~. . ::-· . . .A! .. ·. . .· .. . . . •.. ..: .--·. ·.:~ ,-'k#, < . ':·: :, ~-.t''· ~t~~4~~-:~: '·:~;.: ... ~·~.,~:::*_, ,· . ·~ . .._ · .. .:,. .. _·,.,-·.·· .·. : ~ :-~-. . .. ; ... ·. __ ~~--· ··.·.- .,· . . i: . -, . ::.:~ .. .- I j r' { I . (_. ':.· .APAPTED FROM FIG. 2 OF" OtR (SWEC) TRANSMISSION LINE ROUTE L_----------------------------------~----------- REV1SED 8 /3188 t.-..-2 I , ·. I ·, SCALE fil MI.ES -. ···:-·-~---·· ........ .. .. .................... llGHTlL SAN FRANCISCO ·. ' '· . · .. ' · •. ' ' ALASKA ENERGY AUTHORITY . A~loret•• Al .. lle' BRADLEY LAKE HYOROELE PROJECT FEATURES ---- '• •, 17707 PLATE 1-'f ·· . ._. -· 2.0 POWERHOUSE 2.1 Site Description The outdoor powerhouse is located near the head of Kachemak Bay approximately one mile south of the Bradley River entrance. The site is benched into the hillside above the line of high tide. The powerhouse tailrace extends westward from the top of the hillside onto the tidal flats. Water is conveyed to the powerhouse from the raised Bradley Lake at El 1070 via a vertical shaft and a 3.6 mile power tunnel. At the lower end of power tunnel three short penstock tunnels branch-off into the powerhouse from the manifold section of the power tunnel. During an earlier stage of site preparation construction a large rock bench was excavated to El 40 at the base of the mountain front. The rock surface of this level bench was the starting point for the powerhouse excavation. The lowest excavated foundation level, the invert of the turbine-generator pits, is El -9. 2.2 Vicinity Geology Rocks in the surrounding vicinity of the powerhouse consist of Cretaceous age assemblage of folded and sheared graywacke, argillite and chert. These lithologies occur both separately and intermixed with transitional contacts for the most part. The most significant geologic structural feature was a shear seam (i.e. minor fault) exposed in a ravine south of the powerhouse and subsequently exposed along the full length of the back (east) wall of the power- house excavation. This shear seam had been delineated during earlier site investigations and described as Z2 shear zone in the GIR (see bottom of page 1-3). The project 2 - 1 facilities are in a seismically active region of southern Alaska, but no Recent age displacements along faults at or near the site have been recorded (GIR). The design basis earthquake is 0.35g (GIR). Bedrock at the powerhouse vicinity consist mainly of graywacke with minor areas of argillite with and without chest. 2.3 Geology of the Excavation Geologic mapping of the powerhouse excavation was conducted as the excavation progressed downward. With few exceptions both the wall and final foundation surfaces were mapped at a scale of 1"=10'. Geologic maps with notes were prepared for most of the final excavated surfaces. These maps, Figure 2-1 (8 sheets) and Figure 2-2 (2 sheets) are included in Appendix B. Graywacke, the predominant rock type exposed in the power- house excavation, is moderately fractured and moderately jointed. Many of the joint surfaces are iron stained. The dominant joints trend N60-85W and typically dip 80 to 85 degrees south. The graywacke hardness is relatively greater than that of argillite and the jointing in graywacke is more distinct. Argillite, a much darker gray color than graywacke, is less well jointed but has strongly developed foliation with considerable fracturing of the foliated layers. Whitish chert frequently occurs within the dark gray argillite as thin, discontinuous, elongated lenses and nodules. The chert content in argillite ranges generally from 10 to 20 percent. The argillitic shear seam identified as Z2 during the pre-construction investigations (GIR) is prominently exposed on the back (east) wall of the powerhouse excavation for the 2 - 2 full length of the powerhouse as well as through the switch- yard. The dark grey argillitic seam within largely graywacke rock mass is generally 12 to 18 inches wide, but on the south side of Penstock 3 portal excavation the seam width is as much as 50 inches. The dip of the shear seam is about 25 to 35 degrees east into the hillside. The shear seam, which could also be classified as a fault, is strongly foliated and cross fractured with numerous silkensided surfaces. Locally discontinuous thin layers of plastic clay and soft decomposed argillitic rock are prevalent. With- standing the weak character of this shear seam, its location mainly along the back wall of the powerhouse excavation had little effect on the wall stability or foundation bearing strength. A near vertical dacite dike intersects the northeast corner of the powerhouse excavation. It is about 20 feet wide, highly weathered and very closely jointed and fractured. Fresh dacite is gray, whereas in the weathered outcrop at the powerhouse excavation the color is noticeably uniform light buff. The altered rock contact transition between the dacite and graywacke is less than a foot wide. There is very little difference in the slope stability characteris- tics of the two rock types. 2.3.1 Rock Weathering The most prevalent unanticipated rock condition in the powerhouse excavation area is the degree and extent of rock weathering. The starting grade of the powerhouse site, which had been previously excavated, was El 40. Over the northern two-thirds of the site, highly weathered and closely fractured rock extended downward an additional 20 to 30 feet. Over the southern third of the site the depth of 2 - 3 the weathered rock condition is somewhat less, ranging from 5 to 15 feet. Also, the degree of weathering is relatively more intense at the front (i.e. bay side) half of the powerhouse excavation. Generally, the back (east) half of the powerhouse excavation below El 2 where rock cover was greater, the extent of weathering is less and was classified as moderately weathered. There are a few small areas of slightly weathered rock in the excavation below El 2. The effects and consequences of rock weathering during excava- tion of the powerhouse are discussed in Section 2.4. 2.3.2 Ground Water Although water accumulated in the powerhouse excavation which required light pumping for control, most of the water was from sources other than groundwater. Much of the water entering the powerhouse excavation came from underground drainage of the manifold tunnel through the connecting penstock tunnels. Ground water from the foundation was only a small portion of the flow; perhaps 1 or 2 gal/min emanated from joints and fractures at a few isolated locations in the east wall of Units 1, 2, and 3. Another suspected source of water entering the deeper powerhouse excavations may have been seawater from the bay seeping beneath the base of the cellular cofferdam at times of high tide. The combined flow from these sources probably was no more than 5 to 10 gal/min. 2.4 Excavation of Slopes and Foundations The blasted rock surface at El 40, previously excavated under another contract was the starting level of the power- house foundation excavation. tion from El 40 to El -9 was The entire powerhouse excava- completed by drill and blast 2 - 4 methods. Blasted rock was removed by backhoe and front-end loader. The contract specifications included a number of provisions defining the method of excavation to be used by the Contrac- tor. The maximum excavation lift was limited to 11 feet. Controlled blasting was specified with the intent of mini- mizing overbreak. Extensive rock reinforcement of the cut slopes was also detailed on the design drawings. These and other provisions for completing the powerhouse excavation are discussed separately below. 2. 4. 1 Controlled Blasting and Overbreak The contract documents contained a number of specific requirements for conducting control blasting of final cut slopes in the powerhouse excavation. Requirements for controlled blasting included the following: 1) Cushion blast method be utilized for all final cut slopes. 2) Maximum blast hole spacing of 2 feet. 3) Maximum explosive charge of 1/4 lb/ft. of hole. 4) Maximum lift height of 11 feet. 5) Maximum overbreak allowance of 6 inches. 6 ) A $400/cu-yd penalty for overbreak beyond 6 inches. Starting with the above criteria, prior to production excavation, the Contractor performed the specified blasting tests for the purpose of establishing ·a hole charge weight that would minimize overbreak beyond the 6-inch tolerance. None of the cushion blast tests achieved the desired re- sults. The specified Trimtex explosive (1/4 lb/ft.) with several pound bottom charge were used in most of the final excavation line holes above El 18. In one section of the 2 - 5 east wall of Penstock 3, the presplit method was tried with good results, but this method was not permitted by specifi- cation. Below El 18 the Contractor tried modifying his hole charges; 200 grain primacord was used in place of the 1/4 lb/ft. Trimtex. Results were mixed using smaller hole charges, but generally there was less overbreak below El 18 than above. There were several causes for excessive overbreak of final cut slopes particularly above El 18. These included: (1) the weathered and fractured condition of the rock, (2) poor execution of the control blasting, and (3) unfavorable orientation of geologic joint~ng relative to the direction of the cut slope. As previously described in 2.3.1, Rock Weathering, the graywacke rock, with local exceptions, from El 40 to El 18 in Unit 3, and from El 40 to El 2 in Units 1 and 2 is highly weathered. As a consequence this highly weathered, weak, fractured rock was susceptible to readily breaking and parting along joints and fractures even though small explosive charges were used in cushion blasting. After scaling of the loosened rock beyond the blasted surface, the overbreak above El 18 along the final cut slopes ranged from 12 to 30 inches for most of the cut slopes. Locally, sections of the east wall north of Unit 2 were overbroke as much as 3 to 5 feet. The extent of excessive overbreak was strongly influenced by weathered condition of the graywacke rock. highly Although the weathered condition of the rock had a strong influence on the limited success of controlling overbreak by cushion blasting, other factors such as, poor execution of cushion blasting and unfavorable geologic structure contrib- uted significantly to the excessive overbreak. Overbreak of the final slope of the south wall of the powerhouse excava- tion was largely due to the above two factors. At the south 2 - 6 wall the moderately weathered and hard graywacke was strong- ly jointed. Joints spaced at 12 to 24 inches intersected the final face at a highly acute angle with the cut slope face. Cushion blasting of the final cut slope was done by loading every other hole (4ft. spacing). Owing to the near vertical attitude of jointing, upon blasting large blocks of rock either fell out or were considerably loosened resulting in excessive overbreak after scaling. With better execution of the cushion blasting such as lightly loading every hole on 2-foot spacing, or perhaps reduced spacing to 18 inches, may have improved the chances of reducing the overbreak. Excessive overbreak of several feet, due to the high degree of rock weathering and unfavorable joint orientation, also occurred along the east wall above El 28 and along the walls and corners of the turbine discharge pits below El 18. The geologic conditions at the powerhouse site reported in the GIR (Volume 6 of the contract bid documents) were not significantly different from those encountered in the powerhouse excavation. However, the expectation that cushion blasting method, given the predicted rock condi- tions, could control overbreak to the specified 6-inch maximum was overly optimistic. While specifying a of $400/cu-yd for overbreak quantities beyond the penalty 6-inch tolerance made the Contractor put more effort in to minimiz- ing overbreak, it did not necessarily assure the desired results: The highly weathered rock conditions were not adequately taken into consideration when specifying results to be achieved by control blasting. The Contractor's claim for overbreak in the powerhouse excavation was largely based on unreasonableness of the 6 inch overbreak tolerance for the encountered rock conditions. Settlement of the 2 - 7 $400/cu-yd penalty was resolved by mutual agreement between the Contractor and the Owner. 2.4.2 Rock Reinforcement Extensive rock reinforcement of cut slopes was included in the design of the powerhouse excavation (Appendix B, Plates 2-1 and 2-2). All final cut slopes excavated by cushion blasting methods were reinforced with pattern rock bolts, dowels and chain link mesh. Additionally, large diameter rock anchors were installed horizontally in the rock wall at the back of the powerhouse to maintain long term stability. The bar diameter of the rock anchors varied from 1 to 1-3/8 inches, and the length ranged from 3 to 60 feet. Anchorage and encapsulation was provided by resin cartridges. Wall reinforcement was installed progressively downward as each 11-foot lift was excavated. There were five different types of rock anchorages used the powerhouse excavation. These types were designated A-1, A-2, A-4, A-6, and A-9. All were tensioned with exception of the A-6 dowels. The A-1 types were 10 feet long, 5 kip tension vertical dowels installed one foot back at 6-foot spacing along every cut slope wall. A-1 type rock bolts were installed horizontally typically on 6 x 6 foot pattern on every cut slope face. These resin anchored, pattern rock bolts 10 to 25 feet long were tensioned to 30 kips. A-4 rock anchors 1-3/8 inches in diameter were installed in clusters of 4 to 6 anchors at several locations on the east wall, over the penstock tunnel portal and in the foundation at El 18 and El 2. Clusters of A-4 anchors were installed at 15 locations. A-9 rock anchors, 1-3/8 inches in diameter with corrosion protection were installed vertically in 2 -8 clusters of 9 at the spherical valve locations for Units 1 and 2 and as rock anchors in the penstock thrust block foundations. The A-9 anchors, 50 feet in length, were tensioned and locked-off at 165 kips. Problems with drilling and installing the A-1 tensioned rock bolts were few. In a small percentage of the holes, prima- rily those in the highly weathered rock, hole caving and sloughing slowed down drilling, but only a few holes had to be redrilled. Tensioning of the A-1 rock bolts to 30 kips also was accomplished with only a few anchorage failures out of the more than 1500 A-1 rock bolts installed. Hole sloughing was more of a problem in the horizontal holes drilled for the 1-3/8 inches A-4 anchors on the east wall. These bolts were up to 40 feet long; maintaining a stable hole for inserting the resin cartridges and installing the bolt was critical. Although considerable time and effort was expended by the Contractor in A-4 bolt installation, only one had to be abandoned and all met the tensioned 180 kip proof load and 165 kip lock-off. 2.4.3 Foundation Conditions At Units 1, 2, and future Unit 3 the three main foundation levels in the powerhouse excavation are El 18, El 2, and El -9 (Appendix B, Figure 2-2, sheet 4). The lowest level in the powerhouse is the foundation of the turbine/generator pit. Dimensions of the powerhouse foundation area for the three units are 90 x 254 feet. The foundation rock for all three units consists primarily of graywacke with smaller areas less than 10 percent of foliated argillite with minor chert. For the most part the 2 - 9 foundation rock is moderately to slightly weathered. The foundation rock surface at El 18 is relatively more weathered than at El 2. Rock in the turbine discharge channels in all three units is moderately to locally highly weathered. Although the foundation rock is closely jointed (6" to 2") spacing and fractured, the joints and fractures are reasonably tight. The rock is uniformly hard with few shear seams or large areas of weak rock. Occasional thin shear seams of less than a few inches in width were observed in the rock foundation of all three units. Rock material in these steeply dipping shear seams is finely fractured, in part foliated, and lightly interspersed with discontinuous clay. Apart from the relatively minor rock seams there was one significant shear seam which traversed the entire length of the powerhouse and the switchyard as well. It is located on the east wall of the powerhouse excavation at Units 2 and 3 (Appendix B, Figure 2-1, Sheets 1 and 2) and crosses the foundation at El 2 in the northeast corner of Unit 1. This prominent shear seam is designated as Z-2 in the GIR. The characterization of this argillite, foliated seam has been previously described in Section 2.3. The width of the Z-2 shear seam in the Unit 1 foundation ranges from 6 to 24 inches. The foundation surface of the powerhouse after preparing and cleaning for concrete placement was typically irregular and below grade, but no special treatment or dental excavation was needed. A levelling mat of concrete was placed over the inverts of Units 1 and 2 to facilitate rebar placement. The foundation surface of the future Unit 3 was not completely cleaned up; the specifications called for backfilling the Unit 3 excavation to El 18, which was done. 2 -10 The foundation rock of the substation consists of highly weathered, but reasonably competent intermixed graywacke and argillite. A series of prominently displayed, closely spaced joints are prevalent over the north half of the foundation. The argillitic, closely foliated Z2 shear seam previously mentioned crosses the center of the foundation. A geologic map of the substation foundation is included in Appendix B, Figure 2-1 (Sheet 8). 2 -11 3.0 POWER TUNNEL MANIFOLD, PENSTOCK TUNNELS AND ACCESS ADIT 3.1 General Description Water conveyed from Bradley Lake through the upper and lower power tunnels to the powerhouse Units 1 and 2 and future Unit 3 consist is distributed through a reach of manifold tunnel and three short wye-branch penstock tunnels. These lower tunnel reaches are lined with steel penstock pipe encase with pumped backfill concrete. To allow construction of the manifold-penstock tunnel system to proceed concur- rently with the lower power tunnel excavation a separate temporary bypass access adit was excavated just south of the powerhouse. Further details of the tunnels are described below. 3.2 Access Adit 3.2.1 Excavation and Support Excavation of a 250-ft long approach trench was needed to provide access to the temporary adit portal. Final slopes of the trench were excavated by the presplit method with reasonably good success considering the weathered and fractured condition of the graywacke rock. The cut slopes were reinforced with pattern 10-ft long resin anchored and tensioned (30 kips) rock bolts on a 6 x 6 foot pattern; chain link mesh was also installed. The south access adit intersects the lower power tunnel about 175 feet in from the portal. Drill and blast method was used to excavate the access adit; the excavated diameter is 16.5 feet. Horseshoe shaped steel sets on 4-ft centers and patterned rock bolt array were installed from the portal to the wye intersection with the manifold section of the lower power tunnel. 3 - 1 3.2.2 Geology Geologic mapping of the walls and crown similar to that completed for the other tunnels was not done for the tempo- rary access adit due to time constraint. wood lagging, particularly in the crown, Steel sets and obscured much of the rock surface which greatly reduced the rock exposure for mapping. However, individual geologic tunnel face maps at 1" c 10' scale were completed after most the daily advances. Face maps of the access adit are included in Appendix c, Figure 3-1 (20 sheets). Rock types encountered in the access adit to the intersection with the manifold tunnel (Sta. 5+22) consisted of slightly weathered to fresh argillite with 10 percent chert, graywacke and intermixed argillite and graywacke; estimates of their respective percentages were 30, 50, and 20. The blocky rock was closely jointed and fractured from the blasting consequently there was need for the installation of of pattern rock bolts. At the Contractor's option WF 6 x 20 steel arch sets were also installed on 4-ft centers. The tightness of the rock jointing improved beyond the first 100 feet in from the portal. It appeared that rock bolts in the crown could have provided the adequate safe supports, but the Contractor elected to continue with steel sets. 3.3 Penstock Tunnels 3.3.1 Excavation and Support The three short penstock tunnels for Units 1, 2, and future Unit 3 turbine-generators exit the rock slope behind the east wall of the powerhouse. A short, 35-ft long open trench leads to each portal. The penstock tunnels are parallel; penstock tunnels 1 and 2 are separated by about 40-ft rock pillar and the pillar between penstock tunnels 2 3 - 2 and 3 is about 85 feet. The lengths of penstock tunnels 1, 2, and 3 including the thrust block chambers are 50, 85, and 140 feet, respectively. Each tunnel intersects the manifold tunnel at about 50 degree angle. All have the same excavat- ed diameter of 14 feet to the thrust block chamber and a 10-ft diameter to the intersection with the manifold tunnel. The penstock tunnels through the thrust blocks are enlarged to approximately 20 x 22 feet chambers. Inverts of the thrust block chambers are approximately 5 feet below the invert of the penstock tunnels. The plan and sections of penstock tunnel excavation is included in Appendix C, Plate 3-1 (Sheet 1). The penstock tunnels were excavated by drill and blast method. Pattern rock bolts and W 6 x 20 and 4W x 13 steel arch sets on 4-ft centers were installed. Steel sets were shown on the drawings for the thrust block chambers. Due to better than predicted rock conditions, steel sets were deleted from the thrust block chambers for penstocks 2 and 3. Steel sets were installed in penstock 1 thrust block chamber not because of lower rock quality but to provide added wall support to resist possible rock disturbance from nearby blasting of the manifold tunnel. Each of the thrust block chambers roofs was reinforced with a webbing of steel straps and pattern rock bolts. The penstock tunnels includ- ing the thrust block chambers during and after excavation were essentially dry. 3.2.2 Geology Geologic conditions of the penstock trench walls are reason- ably stable considering rock weathering ranges from moder- ately to highly weathered. Shear seams intersect the walls and some joints are filled with soft clay. Geologic maps 3 - 3 including notes of the penstock trench walls and the penstock tunnel portal are given in Appendix C, Figure 3-2 (Sheets 1, 2, and 3). Geologic conditions in each of the penstock tunnels were ideal for stability. Although steel arch sets on 4-ft centers, in addition to pattern rock bolts were installed in the tunnels, the steel sets could have been deleted without any concern for loss of stability. As previously mentioned, the steel arch sets were deleted from the thrust block chambers of penstock tunnels 2 and 3. The geology of the penstock tunnels was mapped at 1" = 20' scale and the thrust blocks at 1" = 20' Appendix C, Figures 3-3, 3-4, and 3-5. Separate geologic face maps of each penstock tunnel excavation were also prepared daily, and are also included in Appendix C as noted above. Intermixed graywacke and argillite occur in penstock tunnel 1 where as the principal rock type encountered in penstock tunnel 2 is graywacke. Three rock types are present in penstock tunnel 3: graywacke, intermixed graywacke/argillite with 10 percent chert. With the exception of the prominent shear seam intersecting the thrust block chamber of penstock tunnel 3, rock in the three tunnels beyond approximately 20 feet in from the portals, is generally fresh and hard. The rock is closely jointed. The joint traces are slightly undulating the joints are tight with smooth, clean surfaces. The shear seam exposed mid-height on the penstock 3 thrust block chamber walls is 12 to 18 inches wide. The shear seam is the same one that crosses the east wall of the powerhouse excavation previously described in and designated at Z-2 in the GIR. Section 2.0, Par. 2.4.3 The dip of the seam is about 35 degrees northeast; it disappears beneath the tunnel invert about 30 feet upstream of the thrust block excava- tion. Material within the seam is foliated, argillitic and 3 - 4 although closely fractured, fractures are reasonably tight. Some slickensides were observed in the seam as well as thin clay coating along some fracture surfaces. Rock exposed in the roofs of the three thrust block chambers is slightly weathered. Joint spacing ranges from 4 to 12 inches with 6-inch spacing predominant; beyond the blast damage zone (approximately 12 inches) jointing is tight. Joints typi- cally dip steeply north with an east-west strike (see Appendix, Figures 3-3, 3-4, and 3-5). 3.4 Power Tunnel Manifold 3.4.1 Excavation and Support The curved reach of the lower power tunnel downstream of the wye intersection with the south access adit is referred to as the manifold tunnel. The manifold section of the power tunnel is about 420 feet is 16 feet. The three in length; its excavated penstock tunnels branch diameter off the manifold tunnel at about a 50 degree angle (see Appendix C, Plate 3-1). Like the penstock tunnels the drill and blast method was used to excavate the manifold tunnel. Similar to the penstock tunnels there is also a tunnel enlargement for a thrust block in the manifold tunnel. It is located about 45 feet upstream from the main portal. Differing from the penstock thrust block chamber of all around enlargement, in the manifold tunnel thrust block only the invert was lowered by 3 feet and lengthened 10 feet. This design change was deemed necessary because of the low rock cover above the thrust block chamber combined with the moderately weathered rock conditions in the roof. To facilitate installation of wye sections of steel penstock at each of the penstock tunnel intersections, an additional 3 3 - 5 feet of rock was excavated from the crown of the manifold tunnel. At the wyes of penstock tunnels 2 and 3, the higher roofs were extensively reinforced with pattern rock bolts. At the wye section of penstock 1 tunnel a number of steel sets, supported on one side by a broad arch steel were installed, Appendix C, Figure 3-1, (sheet 2). spandrel, At this location the steel sets were not deleted as was done at the penstock 2 and 3 intersections. Because of the close proximity and geometry of the intersection there was concern that the stability of the manifold tunnel might possibly lessen with time (over one year) before the steel liner was installed and backfilled around with concrete. With exception of a few localized areas, rock conditions in the manifold tunnel upstream of the thrust block excavation (Sta 1+68 to 5+20) were reasonably stable. One minor water inflow of less than 1 gpm was encountered; otherwise, the tunnel was essentially dry. The original design specified W 6 x 20 steel sets on 4-ft centers, as well as pattern (6x6ft.) rock bolts in the crown for the full length of the manifold tunnel. Additionally, structural steel support members at the penstock intersection were indicated. Owing to better than expected rock conditions, only three short sections of steel horseshoe shaped sets, two of which were specified by design were installed. Tunnel support loca- tions in the manifold tunnel are indicated on the geologic tunnel logs of the manifold tunnel, Appendix C, Figure 3-6, (Sheets 1 and 2). At the main portal, owing to the acute angle of the portal face with the tunnel centerline, as well as the highly weathered rock conditions, the initial 40 feet of tunnel had to be supported on 2-ft centers. Withstanding the adverse portal geometry and poor rock condition, tunnel excavation progressed without major delays through this 3 - 6 section. With exception of one short section of tunnel shotcrete was applied over the rock surface above springline from the main portal to 10 feet upstream of the penstock 3 tunnel intersection. As mentioned above adverse portal geometry also affected slope stability of the approach cut leading to the power (manifold) tunnel portal. Because these side slopes also serve as abutments for a permanent bridge across the front of the tunnel portal, extensive rock reinforcement was included in the design. An indication of the extent and type of rock reinforcement is shown in Appendix C, Plate 3-2. After installation of the rock bolts, the bridge abut- ment cut slope and the area around the portal entrance was shotcreted in entirety. 3. 4. 2 Geology With the exception of a conditions in the manifold few localized areas, geologic tunnel upstream of the thrust block excavation were favorable for maintaining the tunnel opening with minor support. Most of the rock types de- scribed in the GIR for the powerhouse area were mapped in the manifold section of the lower power tunnel. These included intermixed graywacke, argillite, argillite with chert and dacite. After the rock was cleaned, intervals where argillite with chert occurred foliated structure was prominently displayed in the roof, wall, and in the invert. Well developed, near vertical jointing stood-out on the tunnel walls in sections where graywacke and intermixed graywacke and argillite occurred. Several shallow dipping shear seams were mapped. Locally these seams were as wide as 12 inches but more generally seam widths were less than 6 inches. Typically, the seams material is foliated and 3 - 7 closely fractured argillite with very little clay. Differ- ent type seams were encountered at the wye intersection of the manifold tunnel and the temporary access adit. These shear seams of only a few inches in width are filled with soft, whitish clay and brecciated rock. They are inclined downstream about 50 degrees intersect the tunnel roof about 15 feet upstream of the pillar intersection. Rock fallout and destabilized roof conditions occurred as a result of these adverse seams. The intersection area is further described in Section 4.3.2. At another shear seam location immediately downstream of the intersection, a half of dozen steel sets were installed because of the associated blockiness of the rock. Withstanding a few argillic shear seams the rock downstream of steel sets to the thrust block is fresh and hard. Joint spacing is mainly 12 to 18 inches and the joints are tight. Overall, the rock conditions for this section of tunnel provide to a stable opening. Geolog- ic maps and logs of the power (manifold) tunnel from Sta 1+07 to 5+40 are included in Appendix C, Figure 3-6 (Sheets 1 through 30). Rock in the thrust block below the manifold tunnel invert (i.e. from El 17.5 to El 10) is fresh, sound argillite. Above the tunnel invert in the walls and crown the argillite is slightly weathered and somewhat blocky, but still rela- tively competent. Owing to marginal rock cover above the thrust block, design changes in the thrust block chamber were made. These modifications are briefly discussed in Par. 3.4.1, and in addition to the geologic mapping, are further explained in Appendix c, Figure 3-6 (Sheets 3 of 30). 3 - 8 Geology of the power (manifold) tunnel portal and bridge abutment is given in Appendix C, Figure 3-7. Initially both highly weathered intermixed graywacke and argillite and dacite were exposed in the portal face. Approximately 30 feet in from the portal the tunnel face consisted mainly of moderately weathered argillite. As indicated on the geology maps, closely spaced, near vertical joints are prevalent on both rock face above the portal and on the bridge abutment cut slopes. 3.4.3 Tunnel Lining and Grouting Permanent steel liner encased in pumped concrete were installed in the three short wye penstock tunnels and in the manifold section of the lower power tunnel. Additionally the massive concrete thrust blocks were cast-in-place around the steel penstocks in the four tunnel sections. Prior to placing the steel liners and the backfill surround- ing concrete in the tunnel sections, a system of l-inch diameter grouting pipe loops were installed in the tunnel crown including separate loops for the thrust blocks. Grout piping included riser pipe into high points in the tunnel crown for air venting. Contact grouting of the three penstock thrust blocks was done August 22 and 23, 1989. A water-cement ratio of 2:1 was used initially which was thickened to 1:1 when the pressure started to increase (i.e. after grout pipe system filled and return valve was shut.) The Contact grouting pressure was 30 psi. The total grout takes in penstocks thrust block of 1, 2, and 3 were 16, 38, and 16 sacks, respectively. The crown manifold tunnel thrust block including a short section of the manifold tunnel downstream 3 - 9 of the thrust block and a short section of penstock 1 tunnel upstream of the thrust block were contact grouted though a preset pipe loop. A total of 94 sacks of cement was placed on October 6, 1990. In mid-July, 1990, the portion of tunnel upstream of the thrust block of penstock tunnel 2 and 3 was contact grouted through a preset pipe loop with 1:1 grout at 50 psi. Penstock tunnels 2 and 3 took 71, and 143 sacks, respective- ly. The last manifold tunnel section to be contact grouted extended several hundred feet downstream and upstream, from the wye intersection with the south access tunnel Sta. 5 x 40). Grouting was done through a continuous grout and vent pipe installed in the tunnel crown upstream and downstream from a bulkhead at the wye intersection. Contact grouting was done on April 4, 1991. The total sacks of cement place was 170. 3 -10 4.0 LOWER POWER TUNNEL 4.1 General Description The lower power tunnel extends from the downstream portal near the north end of the powerhouse to the base of the 725-ft power tunnel vertical shaft. The downstream portal is at Sta 1+00 and the base of the shaft is at Sta 177+05, a distance of 17,605 feet. The downstream 420 feet of the power tunnel is also designated as the manifold tunnel section which branches off into three penstock tunnels. The manifold portion of the power tunnel is intersected by the temporary south access adit at Sta 5+20. Excavation and concrete lining of the lower power tunnel was done through the access adit. The manifold section of the power tunnel has been previously described in Section 3.0. Section 4.0 describes the lower power tunnel upstream of Sta 5+20. The design alignment of the lower power tunnel upstream of the wye intersection (Sta 5+20) is straight except for a small directional change of 7 degrees near the half way point. The slope of the tunnel is 1.667 percent. A plan and profile of the power tunnel is presented in Appendix D (Plate 4-1). From the portal Sta 1+00 to Sta 31+60 the permanent tunnel lining consist of pumped concrete around an 11-ft diameter steel liner. From the end of steel liner the tunnel is lined with reinforced concrete to Sta 37+60. Upstream from Sta 37+60 to the lower elbow of the power tunnel shaft, the concrete lining is unreinforced except through three fault zones where the lining is reinforced. The Contractor elected the TBM option for excavating the lower power tunnel. Until the TBM arrived on site and was 4 -1 assembled ready for use, the drill and blast method of tunneling had progressed to Sta 14+10. The TBM operation commenced at Sta 14+10 and continued to the base of the power tunnel vertical shaft, a distance of 16,295 feet. Geologic mapping was done for the entire lower power tunnel. Mapping of the tunnel side walls and plan view at springline was done on 8.5 x 11 inch sheets at a scale of 1" = 20' scale. Other data entered on the map sheets includes rock type, geologic description, excavation progress, support method, special condition and comments and water inflow. Geologic face maps of the drill and blast tunnel headings were also prepared. Geologic log sheets for the lower power tunnel for both the drill and blast reach to Sta 14+10, as well as that excavated by TBM are included in Appendix D. 4.2 Tunnel Boring Machine (TBM) Withstanding several wide fault zones described in the GIR other conditions such as rock quality, rock hardness, and tunnel length were favorable for excavating the lower power tunnel with a tunnel boring machine (TBM). A used (1979) Robbin TBM Model 148-213/3 was purchased in Norway by Enserch Constructors, J.V. and shipped to Robbins Equipment, Inc. in Seattle, Washington for reconditioning. After the reconditioning, the TBM with trailing gear and supporting equipment was shipped by barge to the jobsite, arriving February 9, 1989. The diameter of the TBM cutter head is 15.1 feet which is larger than needed for the finished 11-ft I.D. A mutually beneficial arrangement for accepting the larger tunnel diameter was agreed to by the Engineer and the Owner. 4 - 2 The front section of the TBM which includes the cutter head with thirty-five 17-inch diameter cutters and opposing gripper pads is 35-ft long. The rear section attached to the front section by the main support beam is about 20-ft long; the operators console and hydraulic power units are located on this section. The attached trailing gear deck sections are about 400 feet in length. Approximately the first 60 feet or so of the trailing gear houses electrical control cabinets, transformers power cable reel, air scrub- ber, and the bridge conveyor overhead. The deck sections of about 320 feet behind the electrical gear section includes a double track with California switch which accommodates two 10-car trains with 6 cu-yd muck cars. Located overhead on T-support columns is the muck conveyor for loading cars and the twin ventilation pipes which extend forward to the front section of the TBM. A photograph of the TBM and trailing gear decks taken outside prior to moving into the tunnel is included in Appendix A. Considerable preparatory work was necessary prior to the TBM in to the tunnel. A 120-ft long starting with circular concrete walls was constructed. The moving chamber tunnel invert downstream to the access adit portal was cleaned to rock and a leveling concrete mud mat was placed. Air ventilation pipe and other obstructions in the tunnel were removed to provide clearance for the TBM. Rail track had to be lain from the tunnel heading to the marshalling yard outside. After weeks of preparation in the marshalling yard, the TBM and trailing gear were moved into the tunnel to the starting chamber (Sta 14+10). Two weeks of final assembly including electrical, mechanical, and hydraulic work and welding of 4 - 3 the outside cutter and bucket assemblies on to the cutter head was done. Approximately 160 hours of welding was involved. Assembly and electrical and hydraulic checkout was completed by March 4, 1989 and the first trial run of the TBM was made. By March 8, most of the minor operational and equipment problems were corrected to where the TBM was operational more than 12 hours per day. The Contractor's work schedule for TBM operation was 7 days a week, 3 shifts, with maintenance done on day shift. The TBM check-out period lasted about one week, after which the daily advance for the first month of operation (March, 1989) averaged 115 feet. The TBM completed excavation of the lower power tunnel (Sta 172+29) September 6, 1989. Overall TBM monthly progress averaged 104 feet a day. Best daily progress was 275 feet which was reportedly a worlds record for this diameter tunnel in hard rock. Further description of the TBM tunnel- ing excavation are described in Section 4.5.1. Daily TBM progress is given in Appendix D, Table 4-1. 4.3 Tunnel Sta 5+20 to Sta 14+10 4.3.1 Excavation and Support The south access tunnel excavation continued from Sta 5+20 to Sta 6+40 where the alignment coincides with the power tunnel alignment. The right wall of the access adit (look- ing downstream) was then widened by "slashing" to achieve a curve to the right in the power (manifold) tunnel alignment. At Sta 5+20 a full tunnel face was developed on the manifold tunnel alignment. The roof span of 39 ft at the fork of the manifold and access tunnels (Sta 5+20) transitions to 14.5 ft at Sta 6+40. Upstream of the wye intersection in the 4 - 4 widened tunnel section between Sta 5+20 and Sta 6+40 the specified 10 and 15-ft long pattern, tensioned (30 kips) rock bolts were installed in the crown. A plan of the intersection of the south access adit with the power tunnel including the rock bolt pattern is shown in Appendix D, (Plate 4-2). Upstream of Sta 6+40 to Sta 14+10 the excavated tunnel diameter is approximately 14.5 feet. The last 120 feet was enlarged and a 50-ft section of concrete lining was in- stalled on the walls to form a starting chamber for the TBM. The drill and blast heading upstream of Sta 6+39 advanced without difficulty at an average rate of 35 feet per day (3 shifts). No steel tunnel support sets were installed. Rock bolts were installed as needed. In general, the Contractor installed four 6-ft long tensioned (5 kip) bolts on a radial pattern in the arch at 4 to 5-ft spacing. Where shear seams were encountered, supplemental rock bolts, as required, to assure stability were installed. Adverse excavation conditions were encountered upstream from the wye intersection between Sta 5+55 and Sta 5+20. During widening (downstream advance) of the power tunnel into the right turn of the manifold tunnel, several subparallel clay seams up to 12-inches wide were encountered causing fall-out and unstable roof conditions. The shear seams were not unexpected because one had been encountered during the excavation of the access tunnel. However, the consequences of the clay shear seam geometry became more apparent during tunnel widening (slashing). With widened roof spans of (30 to 39 feet) localized rock failure occurred adjacent to the clay seams. Withstanding the adverse clay seam orientation instability of the clay seam material and adjacent altered, 4 - 5 fracture rock was controlled. Careful advance was made by drilling and blasting shorter (4 feet) rounds closely followed by installation of 10 and 15-ft long tensioned rock bolts on centers as close as 3 feet. Six-inch wide steel straps were also used between pairs of rock bolts. Welded wire mesh was pinned to the roof area above springline between Sta 5+65 and Sta 5+20 and a minimum 3-inch thickness of shotcrete was applied over the entire roof area. No further instability was observed for the treated area. 4.3.2 Geology Geologic logs of the walls and crown of the lower power tunnel between Sta 5+20 and Sta 14+10 were made continuously during excavation. Also, geologic face maps of the tunnel heading were completed daily. Geologic mapping (40 sheets) for this reach of tunnel is included in Appendix D, Figure 4-1. The heading was advanced typically at 35 feet per day, consequently tunnel face maps can be as much as 35 feet apart. Mapped rock units encountered consisted of argillite, graywacke, and intermixed graywacke and argillite. Rock types for this reach of tunnel change moderately frequent; ranging from 40 to 120 feet. Although not easily delineated, short (10-50 feet) transition zones of intermixed graywacke and argillite frequently occur at the contact between graywacke and argillite. Joint frequency is variable but mostly spaced at 12 to 18 inches. Perhaps 25 percent of the jointing is outside this range but rarely exceeds 24 inches on the high side but on the low side 12 to 6 inches is not uncommon. Fracturing appears to be less than the core logs of exploration holes indicated. Overall, the rock along this tunnel reach would be described as moderately jointed and fractured. 4 - 6 For tunnel intervals delineated as argillite, the rock is tightly foliated, in part with chert stringers and lenses paralleling the foliation. Foliation is more strongly developed in some areas than others; one such tunnel inter- val Sta 12+00 to Sta 12+50, foliation is particularly well displayed. Argillite that is foliated is not necessarily less stable than graywacke except that shear seams appear to occur more frequently in argillite. Foliated argillite layers although mostly less than 0.5 inch thick are tight in fresh unweathered condition; the rock mass is moderately hard and fractured. Graywacke on the other hand being as much as 50 percent harder than argillite breaks out (drill and blast tunneling) more blocky. The jointing on the tunnel walls is relatively more developed in graywacke. The irregular wall surface gives the appearance of excessive overbreak. A survey of overbreak for this reach of tunnel revealed local areas of excessive overbreak, but for the most part overbreak beyond the allowed tolerance of 12 inches was minor. As previously mentioned brecciated shear seams, predominant- ly 3 to 12 inches wide, occur more frequently in the argillite or argillite with chert. Frequency of shear seams is variable but a 50-ft interval of tunnel without inter- secting at least one would be unusual. Most shear encountered consist of closely foliated and closely tured, platy, argillitic rock with minor clay coating seams frac- along some fracture surfaces. Relatively, few shear seams are brecciated truly clay gouge seams. Argillitic shear seams of less than 12 inches width generally did not cause any unusual stability problems. In a couple of instances argillitic seams as much as 18 to 24 inches wide were 4 - 7 intersected in the tunnel without significantly effecting tunnel advance. Shear seams with intercalated clay gouge generally cause some localized instability and require some type of tunnel support to retain fallout from the roof. This was the case for a short interval of tunnel immediately upstream of the wye intersection of access and manifold tunnels between Sta 5+20 and Sta 5+55. Within this 35 feet interval two subparallel clay seams or small faults ranging from 6 to 12 inches in width obliquely crossed the tunnel intersection. A third seam with less inclination (dip) intersected one of the two seams in a roughly diagonal direction. Clay gouge was several inches wide in the two parallel seams and the adjacent highly altered, closely fracture and partly brecciated rock zone was up to 29 inches wide. The inter- section by the third seam although relatively narrower with minor clay added to the instability. This adverse geologic structure conditions resulted in several feet of fallout from the tunnel roof in two localized areas. Continuous light water dripping from the clay seams also caused inter- mittent sloughing of clayey material. As previously de- scribed in 4.3.1, this unstable zone was carefully excavated in short advances and the wide roof spans 30 to 39 feet were progressively stabilized with extensive rock bolting and shotcreting. rock bolting, (Plate 4-2). Design support for these wide spans relied no steel sets were specified, Appendix on D, Ground water inflow for this reach of tunnel (Sta 5+20 to Sta 14+10) was minor; there was only one location of flowing water. High on the left wall looking (upstream) at Sta 13+8~_!nJ!-ial water inflow estimated at 8 gpm emanated from 4 - 8 a joint fracture. of water. Within stopped. There were several locations of dripping a month these water sources essentially 4.3.3 Tunnel Lining and Grouting The manifold section of the lower power tunnel downstream from Sta 5+20 to the main portal. This of the steel penstock was installed and encased with concrete from Sta 5+20 to the main portal in fall of extends portion pumped 1989. Because of the continued need for tunnel access for person- nel and equipment, the liner from Sta 31+55 downstream to Sta 14+10 continuing to Sta 6+55 could not be started until after the concrete lining of the lower power tunnel was completed August 25, 1990. In fact, due to need for access to supply equipment and materials for finishing and contact grouting of the tunnel concrete lining, installation of the first section of steel liner at Sta 31+11 did not commence until November 6, 1990. The steel lining installation and welding work was completed to Sta 14+10 on December 8, 1990 and progressed to the closure section at Sta 5+55 on Decem- ber 16, 1990. The 40-ft long liner sections were welded together outside the tunnel into 120-ft long sections before transporting into the tunnel on rail. Typically three 120-ft sections were installed in the tunnel and welded together each week. Concrete encasement of the steel liner was done after each 120-ft section was added and welded; however, the advancing concrete face was kept about 120 feet upstream of the last liner joint being welded. Installation of the closure sections of steel liner at Sta 6+55 including concrete placement around the liner was completed the end of March, 1991. 4 - 9 Contact grouting along the crown of the tunnel through the pre-tapped holes in the steel liner from Sta 31+55 to Sta 14+10 started December 27, 1990 and was completed January 9, 1991. Grouting was placed at 30 psi using a 1:1 grout mix. From Sta 14+10 to 6+55 the tunnel was excavated by drill and blast method and grout takes were somewhat larger than the TBM bored tunnel upstream of Sta 14+10. Contact grout takes for this section averaged approximately 0.60 sacks per lineal foot. Void or concrete "skin" grouting backfill was between the steel liner and also performed. Twenty-two the ( 22) locations of voids were identified by sounding of the liner. These locations were drilled and tapped for contact grout. In the reach between Sta 14+10 and Sta 6+55 the total void grout injected between the steel liner and the concrete was nominal. 4.4 Tunnel Sta 14+10 -Sta 31+60 4.4.1 Excavation and Support The lower power tunnel including the penstock and manifold tunnel sections from portals up tunnel to Sta 31+60 will be lined with steel varying in thickness from 3/4 inch to two inches. Between the steel liner and the excavated rock surface, unreinforced concrete with a 28-day compressive strength of 2,500 psi will be placed. The lower power tunnel between Sta 14+10 (end of drill and shoot tunnel) and 31+60 (end of steel liner) was excavated by tunnel boring machine (TBM). TBM progress, support requirements, and water inflow data are included on the geologic tunnel logs in Appendix D, figure 4-2 (82 sheets). 4 -10 The tunnel advance through this section averaged mately 106 feet per day after a normal four day approxi- breaking period during which time minor modifications were completed and crew responsibilities were clarified. The TBM started mining on March 4, 1989 and completed this section on March 22, 1989. Rock support within this section was predicted by the Geotechnical Interpretive Report (GIR) to be equivalent to that required in a generally highly fractured rock mass. The actual rock mass encountered was more closely repre- sented by the moderately fractured to sound classification of rock mass quality. The difference between actual and predicted rock mass quality is difficult to access quantita- tively because the GIR tunnel ground classifications are based upon a drill and blast excavation techniques. The use of a TBM results in reduced support requirement, a fact which was readily observable near the beginning of the TBM bore. Just downstream of the TBM bore, in the drill and blast section, the jointing and fracturing is clearly exposed and support bolts are installed (usually coincident with overbreak) where intersecting planes required ground support. Upstream, within the TBH bored section, the jointing and bolting is occurred. fracturing infrequent, are and less very clearly little exposed, rock over excavation With exception of two relatively short zones described below, normal rock treatment within this 1,750-ft long section was accomplished with "spot bolts" installed only at locations which were thought to have potential for insta- bility and/or fall out. These bolts and the decisions to install them were made based upon the condition of the rock 4 -11 exposed between the TBM cutter head and grippers, a distance of roughly 20 feet. On occasion, additional spot bolts and 8 inch wide x 14-gage steel strap was installed from off of the trailing gear deck or from a work platform installed on a railroad flat car behind the TBM and trailing gear. Two short sections within this tunnel reach required significant support within localized zones of highly fractured rock. These zones occurred between Sta 23+95 to Sta 24+20 and Sta 26+20 to Sta 26+40. Both areas consisted of closely jointed and fractured, blocky rock in the left rib (left sidewall looking up station, i.e., upstream) above spring- line and the left crown. These zones were supported with rock bolts and steel strap and were significant enough to slow TBM boring advance. Thin shear zones evidenced by some clayey coatings infilling joints and fractures may have influenced weathering and frequency of fracturing within these zones. Subsequent ground stability has not changed over time; no further fall out or deterioration of sta- bility has occurred. 4. 4. 2 Geology Lithology within this tunnel reach is interpreted in the GIR to be mostly graywacke with lesser quantities of argillite with chert, argillite, intermixed graywacke and argillite and dacite. A comparison of actual lithology with predicted lithology in this limited zone (10 percent of the entire lower power tunnel) would lead to inconclusive results. A more reasonable comparison is contained in this report as Appendix D, Plate 4-3 which summarizes the entire power tunnel graphically giving estimated and as-built percentag- es. Notwithstanding, relatively more intermixed argillite and graywacke was encountered within this section than graywacke as predicted. Dacite was not encountered, but a 4 -12 small amount of greenstone, the total tunnel was found. tively equivalent. More quantify lithologies, is lithology on advance rate. the only greenstone located in Other lithologies were rela- important than an to determine the attempt affect to of Throughout this section, advance was rapid regardless of the variable lithologies, but slowed in the aforementioned zones requiring moderate support to maintain stability. However, the difference in rock strength of the principal lithologies was not great. Advance rate in the power tunnel is mostly influenced by structural integrity of the rock mass, more so than the rock type. This fact is further developed in Section 4.5 for the remainder of the lower power tunnel TBM excavation. Jointing and fracturing within the TBM less well exposed than they would be in bored section are a drill and blast tunnel. Joints and fractures intercepted by the tunnel bore that trend normal to the tunnel alignment are very difficult to distinguish unless they are open or closely spaced and locally plucked out along the joint trace by the boring action of the TBM. Joints and fractures trending sub-parallel to the tunnel alignments are more readily visible due to break away of thin wedges formed by the actual angle of intersection between tunnel wall and joint/ fracture trend. The resulting "kerf" typically 1/2 to 2 inches deep varies in shape from a vertical line for verti- cal joints cutting the tunnel perpendicular to its axis to truncated ellipses for vertical and/or steeply dipping joints intersecting the tunnel acutely to the alignment. Kerfs occur on both walls but are more prevalent on the left wall (looking upstream) and rarely occur on the roof. The development of kerfs is possibly due to several causes. Cutting action of the clockwise rotation of the TBM cutter 4 -13 head bucket teeth can cause strong abrasive force acting on thin joint intersections. The gage cutter wheels exert tangential forces as well as forward loads during their travel path across joints and seams. This action can result in break out of small rock slivers along discontinued ties. Another mechanism for localized failure is due to pressure exerted by the TBM gripper pads. Jointing and fracturing within this reach (Sta 14+10 to 31+60) was stabilized where necessary by spot bolts and limited use of steel straps unless fall out was progressive as in the two areas described in Section 4.4.1. These areas of highly fractured rock were stabilized by extensive use of 6-ft long rock bolts and steel straps approximating a 4-ft by 4-ft pattern. No known fault was predicted to intercept this reach of tunnel. However, three surface lineaments were identified on aerial photographs. In the tunnel three shear zones were mapped for this reach, however, the shears did not line up with the surface lineaments. This apparent lack of correla- tion is not an unusual condition, as the lessor surface lineaments identified on aerial photographs do not necessar- ily imply a corresponding linear feature at tunnel depth. The shears were thin, closely fractured, generally 6 inches to 12 inches wide with minor associated jointing and frac- turing. One shear, however, at Sta 23+95 to Sta 24+20 had a larger zone of associated jointing and fracturing approxi- mately 5-ft wide (discussed in Section 4.4.1). Minor rock support was installed except as described in Section 4.1.1 at Sta 23+95 to Sta 24+20. 4 -14 Point source groundwater inflows intercepted in this reach were minor, less than 10 gpm. The aggregate flow however approached 600 to 700 gpm. 4.4.3 Design Modifications From Sta 14+10 to Sta 31+60 the power tunnel included a steel liner as designed. Hydrofracture testing of rock was performed within the transition zone from the end of the steel liner through the reinforced concrete lined section and to unreinforced Sta 37+60). Although concrete lining (Sta 31+60 to the test results were inconclusive, the Federal Energy Regulatory Commission, (FERC) recommended not to extend the steel liner beyond Sta Board 31+60. The Board's recommendation was based upon favorable quality of rock exposed. However, based on later design decisions, the concrete lining was reinforced to Sta 38+60 and in 17 separate sections upstream. High pressure compaction grout holes initially planned to extend to Sta 38+00 on earlier recommendations by the FERC Board. Subsequently the compac- tion grouting was extended upstream to Sta 65+00 by SWEC, with the FERC Boards concurrence, because of the potential for tunnel leakage through open joints/fractures with large water inflows. 4.4.4 Tunnel Lining and Grouting The sequence of the steel liner installation and the contact grouting procedures were presented in Section 4.3.3. There it was mentioned that the first 120-ft section of steel liner went in the tunnel to Sta 31+77 on November 6, 1990. The upstream end of the 10-ft diameter steel liner connected into a concrete transition to the 15-ft ID concrete tunnel lining. Working downstream installation of the 120-ft sections of steel liner was completed to Sta 14+10 4 -15 mid-December. The placement of concrete backfill around the steel liner was completed shortly thereafter. Contact grouting of the crown through pre-tapped holes in the liner from Sta 31+77 to 14+10 was completed in early January, 1991. Void grouting between the liner and the concrete was done more or less concurrently with contact grouting. Grout takes for contact grouting averaged 0.60 sacks/LF. Void grouting grout takes were minimal. 4.5 Tunnel Sta 31+60 -Sta 177+51 The lower power tunnel from Sta 31+60 (end of steel liner) to Sta 177+51 (vertical shaft) was excavated by TBM. This segment of tunnel was designed to be lined with a twelve inch minimum thickness concrete lining with a 28-day com- pressive strength of 3,000 psi. Steel reinforcement was incorporated into the concrete lining in a number of sec- tions after evaluating the excavated tunnel ground condi- tions. 4.5.1 Excavation and Support Excavation of this segment began on March 23, 1989 and was completed on September 6, 1989. The tunnel advance through this section averaged approximately 100 feet per day. TBM progress support method and water inflow data are included on the geologic tunnel logs in Appendix D1 Figure 4-1 (82 sheets). Rock support within this section was predicted by the GIR to range from none in sound rock to circular heavy steel sets in poor rock within fault zones. This segment of the lower 4 -16 power tunnel is discussed in the GIR as six separate sec- tions divided upon the basis of two known large scale fault zones, an inclined shaft option, and intervening sections. A lengthy comparison of predicted and as-built support requirements is beyond the scope of this report. Only a summary of actual support placed and the structures and lithologies encountered are presented. The predominate (over 90 percent) form of rock support installed within the TBM bored tunnel consisted of non-patterned 6-ft long A-2 type spot rock bolts. The majority of these type of bolts were installed from drill locations between the TBM cutter head and the TBM gripper pads. Rock bolts were installed in holes drill with jack-leg rock drills using epoxy resin cartridges. This type of support was installed where individual blocks of rock, localized shear zones or closely spaced joints and fractures were considered to have failure/ fall out potential. In zones where the frequency of frac- turing and/or fall out was deemed excessive for single spot bolts to achieve support, supplemental support was used in conjunction with A-2 type rock bolts. Supplemental support included steel straps (8 inches wide x variable length x 14 gage steel), rolled steel channel (C 10 x 20 formed arch), rolled steel "mine ties", steel channel "lagging" (MC 10 x 6.5 x 2), welded wire fabric (WWF 4 x 4), and various sizes of wood timber blocking and wedges. Also available to the Contractor was a selection of 4 types of steel sets including an arch set (240 degrees arch) and 3 full ring (full circular section) variable weight/strengths and placement frequency. 2-piece sets of Although the need for steel sets was predicted and an allowance of 1500 full circle sets was provided in the Contract and were purchased by the Contractor only one installation of steel 4 -17 sets was made within the TBM bore. Full circle steel sets on (W6 x 25, 60ksi) on 4-ft centers were installed within the Bull Moose Fault Zone between Sta 68+00 and 72+00. Although deemed necessary by the Contractor the placement of these 100 sets was not done until after the TBM had cleared the fault zone. The Construction Manager was not in agree- ment with the Contractors determination that sets were needed. Installation of the sets was made under the "Con- tractor's Option" clause of the specifications. Throughout this section 177+51), the majority of of tunnel (i.e., Sta 31+60 to tunnel support beyond spot rock bolts was installed in fractured rock associated with shears and faults. The most significant zones of support were usually in areas of multiple shears intersecting each other with overlapping highly fractured zones. The intersection of low dip angle and high dip angle shears caused wedge shaped blocks of fall out until stable arching was achieved or cribbing and support steel was placed. In two locations on the left wall in cavities caused by raveling and fall out, Sta 103+20 and Sta 103+60, the Contractor chose to place backfill concrete behind the TBM gripper pads to provide necessary bearing to the gripper thrust for advanc- ing the TBM. The three known faults penetrated by the TBM within this section were substantially less difficult to bore through than was expected from the most conservative interpretation of the GIR discussion of tunnel ground classification. The maximum support required approximated a 4 x 4-ft pattern of rock bolts from springline to springline with alternating rolled steel channel and rolled steel mine ties. After this initial treatment, welded wire fabric (WWF) was placed with additional rock bolts where necessary. 4 -18 Within this section the excavated tunnel bore will be lined with unreinforced concrete lining a minimum of 1-ft thick. Reinforced concrete lining in limited sections will be placed in accordance with specifications and drawings. An option to "skip line" the lower power tunnel between Sta 84+00 and Sta 177+05 was developed by the Engineer at the Owner's request. The outcome of the tunnel lining option is described in Section 4.5.3. 4.5.2 Geology The lithology description within this section is interpreted in the GIR to cover the full range of rock types recognized for the project area. Appendix D, Plate 4-3 in conjunction with the continuous geologic tunnel log, Appendix D, Figure 4-2 best describes the actual range and percentages of rock types that were excavated. The predicted and as-built rock type percentages compare favorably. The relative hardness of the various rock types cannot be shown conclusively to have significantly affected the TBM excavation rate. Rather, the rate of penetration was more influenced by condition of the cutters, the capacity of the belt conveyor and the muck train cycle time. Structural geology of shears, faults, and joint/fracture splays locally affected the TBM advance rate, but in the overall tunnel length the effect of geologic conditions encountered in the lower power tunnel on advance rate was not significant. To further amplify the lack of harness control on penetration rate, two examples are given below. From Sta 33+54 through Sta 40+62 average advance rate of 187 feet per day was achieved in nearly predominantly graywacke which has a relatively higher strength than argillite. In this interval a world record run of 275 feet per day as verified by the TBM manufacturer was also achieved. The final five days of TBM bore averaged 4 -19 74 feet per day in a massive graywacke. At this haulage was at its maximum, and cutter wear extended to the maximum possible to conserve time,muck was being change out time. Daily TBM advance rates from March 4 to 1989 (Sta 14+10 to 117+51) are presented Appendix D. September 6, in Table 4-1, Three significant geologic lineaments identified on ground surface above the tunnel were recognized as scale fault traces from earliest investigations (GIR). were colloquially named the Bull Moose, Bradley River, Bear Cubs Faults. Locations of these fault traces the large They and with respect to the tunnel alignment are included in Appendix D, Plate 4-4. The GIR includes detailed descriptions of the anticipated tunneling conditions and hazards associated with these faults based upon deep angle borings which penetrated the Bull Moose and Bradley River fault zones (Bear Cubs Fault was not drilled). The Bull Moose Fault (Sta 65+80 to Sta 72+00) was the first to be encountered by the TBM. It was approached with extreme caution by the Contractor with a 2-inch diameter "feeler" probe hole being advanced approximately 75 feet in advance of the cutter head prior to subsequent TBM advance. The probe hole provided several pieces of advance knowledge about the boring condi- tions ahead. It provided an indication of on rock hardness, soundness, the presence or lack of ground water and the relative pressures. Withstanding the great care and caution exercised, the Bull Moose Fault System was penetrated at a surprisingly high average penetration rate of 138 feet per day. Four mapped zones of faulted, sheared and brecciated rock were identified as coincident with those represented by the GIR along with additional relatively minor mapped gouge/breccia shear zones. Three faulted zones were 4 -20 associated with dacite dikes. The near Sta 66+90 displayed duplication first zone encountered of a thin dacite dike giving an inferred right lateral senses of offset. Minor delay in TBM advance to install channel, strap, and rock bolts to support fractured rock associated with this dacite and a thick dacite dike at Sta 71+00. Advance rates were nonetheless high throughout the fault system. The Bradley River Fault was next encountered from Sta 145+00 to Sta 148+40. The first fault splay was thin and easily penetrated with no support needed. The second and third splays were each approximately 30-ft wide. Both zones were highly deformed, sheared and faulted, the entire zones being considerably brecciated with clayey gouge seams to 3-inches thick. Withstanding the advance geologic conditions these zones were bored relatively quickly. However, installation of a large number of channel sections with cribbing, and rock bolts were necessary to stabilize the zones. Upon completion of the TBM bore through the zone, additional WWF and rock bolts were added from the trailing gear deck to further stabilize the rock mass. Owing to the absence of ground water within the faulted sheared zones, the wall rock retained a fair degree of intactness. Fall out of up to 3 feet occurred near the TBM gripper pads at several locations where lateral thrusts were large enough to deform and displace the gouge/breccia, giving rise to rebound slough- ing. The Bear Cubs Fault (Sta 164+90 to Sta 167+20) occurred within a zone of numerous low angle to high angle shears requiring extensive support using rock bolts, channel, lagging, and welded wire fabric. The TBM bore was slowed through this area due to frequent localized blocky rock fall 4 -21 out which was supported behind the cutter head with bolts, channel, and lagging. With better access, WWF steel chan- nels were added from the trailing gear deck to further complete the support. The shears were not unusually exten- sive, however, they were intercepted at a low angle which, with associated jointing and fracturing, caused numerous small wedge failure blocks. The stability of these blocks was further affected by TBM cutting action and gripper pad pressures. To summarize the impact of the three major faults on TBM tunnelling, a number of statements can be made. The three faults were located within the intervals predicted in the GIR. Each fault caused only minor delays to TBM progress. The faults were relatively dry and without significant weathering of gouge and breccia zones. The absence of serious adverse ground conditions such as running or squeez- ing ground allowed a significant acceleration in tunnel schedule. The widths of gouge/brecciation (especially within the Bradley River Fault) were consistent with GIR predictions. The predicted severity of the gouge/ brecciation although reasonably accurate failed to impact support requirements to the degree implied in the GIR. Had the local stress fields, ground water regime or weathering influences been more adverse, the full range of GIR predict- ed problem ground conditions may have been encountered. Shear zones, in which movement has occurred on a large scale so as to partially crush and brecciate the rock, occurred frequently throughout the TBM bore. More than 100 such zones were mapped within the lower power tunnel. Shear zones were distinguished from fault zones based upon width and position with respect to projected surface fault 4 -22 locations. Whereas shears may be associated with faults on the basis of similar genetic origin, age and may be actual splays of recognized faults, they are so designated to segregate them from the three known faults. In addition, a lack of marker beds and general mixing of lithologic types during tectonic accretion has destroyed sedimentary struc- tures which may have been used for reconstruction of fault/ shear geometry. Typically, shears were identified based upon the presence of clayey gouge, brecciation, and local- ized joint, fracture, and calcite rehealed tension fracture frequencies. They varied in size from several inches to several feet of gouge/breccia thickness with associated fracturing ranging from inches to tens of feet wide. The impact of shears upon TBM advance ranged from none to considerable. The majority of shears encountered were either not in need of support or were supported with spot rock bolts. In general, low dip angle shears and areas of several shears intersection within or near the perimeter of the tunnel bore and shears having soft, weathered, and easily erodable gouge/breccia caused TBM delays. The worst case was located near the halfway curve where two zones of intersecting shears combined with eccentric thrust of the TBM caused heavy fall out. To provide adequate gripper thrust for tunnel advance, two placements of fill concrete were made in raveled out cavities. Also, heavy use of blocking, channels, and rock bolts to stabilize the zones. Several days were expended in these zones with reduced advance rate between the supported zones. Most support of less significant shear zones was accomplished immediately behind the TBM cutter head causing little or no advance delays. 4 -23 Joints and fractures were encountered throughout most of the TBM excavated tunnel bore. The frequency and orientation of joints and fractures contributes strongly to overall rock mass quality. Jointing and fracturing that was not clearly associated with faulting and shearing was for the most part widely spaced. Three localized zones of closely spaced joints were encountered that required moderate rock support with channels, rock bolts, steel strap, and limited WWF welded wire mesh. They occurred at Sta 26+25, Sta 44+40, and Sta 169+60. Normally, where joints and fractures were closely spaced support consisted of either spot rock bolts or spot rock bolts in association with short channel sec- tions. Except as noted above, jointing and fracturing had a minor impact on TBM advance, needed support being installed concurrently with advance. Ground water inflows within this section of TBM bore was encountered in quantities close to those predicted in the GIR. The primary source of ground water seepage into the tunnel was through joints and fractures and occasionally shear zones. The faults were relatively dry. The largest sustained zone of ground water inflows occurred from numer- ous joints oriented near parallel with the tunnel alignment between Sta 80+50 and Sta 89+00. Total aggregate flow from the tunnel approached 5,000 gpm peak when the heading advance had reached Sta 84+00 during steady boring through a zone of competent intermixed graywacke and argillite which required only minimal rock support. Inflow occurred inter- mittently along joint traces suggesting that the slightly undulating joint surfaces had been moved differentially a few inches or less thereby dilating the joints. Dilation of joints could open considerable space for percolating ground water to fill. Beyond the area of high inflows (up tunnel 4 -24 from Sta 89+00) ground water inflows decreased steadily. The remainder of the tunnel bore saw only occasional in- creases of high ground water inflow. Two highs of note occurred at Sta 104+50 (associated with intense shearing at the half way curve) and at Sta 157+50, a localized zone of open, travertine coated joints. Ground water was handled effectively by the Contractor through the use of pump stations. Collection sumps, seven in all were installed in the left rib near invert. Water was pumped into a 24-inch diameter discharge pipe extending to the portal and on to settlement ponds. The affect of ground water inflows on excavation was notable only within two zones, those at Sta 82+00 through Sta 89+00 and Sta 157+50. At these locations cuttings ranging from clay sized to fine gravel sized particles were washed out from under the cutter head and accumulated in the tunnel invert. The washout necessi- tated slusher and hand mucking of accumulated rock cuttings from the invert to allow installation of the railroad ties and rails. This type of mucking, along with difficult access and working conditions for disc cutter changes in front of the cutter head resulted in advance delays. Tunnel instrumentation consisting of tape extensometer and vibrating wire strain ments. Extensometer gages provided for in the bid pin sets were installed in the docu- Bull Moose Fault and the Bradley River Fault. Vibrating wire strain gages were installed on the steel sets within the Bull Moose Fault. The instrumentation installed within the Bull Moose Fault gave no indication of ground movements of any significance. Tape extensometer measurement sheets are given in Table 4-2. Strain gage readings are presented in Table 4-3. Both tables are included in Appendix D. 4 -25 The extensometer pin sets installed within the Bradley River Fault gave no indication of significant movement at the first two pin set locations (Sta 140+31 and Sta 144+40). At locations Sta 147+76 and Sta 148+15, inward movements of 0.243 inches maximum were recorded. The mechanism for these minor inward movements was not clearly understood. Possible causative factors include load relief from gripper pad deformations, squeezing ground, swelling ground, or stress relaxation due to excavation related reorientation of insitu stresses. Regardless of cause, the reinforced concrete liner specified for this zone is designed for the load transfer which may occur long term. 4.5.3 Continuous or Skip Lining SWEC at the request of the Owner, identified large segments of the lower power tunnel upstream of Sta 84+00 having requisite qualifications to remain unlined. A process of evaluation was developed to define the "skip lining" propos- al including unreinforced concrete liner, reinforced con- crete liner, reinforced shotcrete "patch lining", additional spot rock bolts (with and without channel) additional scaling, and no treatment. The proposal was reviewed by the FERC Technical Review Board and found to be lacking in justifiable economic cost/benefit as well as requiring addition conservatism with regard to treatments in unlined segments. The Contractor's cost evaluation provided to the Owner was not considered a justifiable savings by the Owner and the decision was made not to partially line but to continuously line the entire tunnel. 4.5.4 Tunnel Lining and Grouting After completing the concrete lining of the power tunnel vertical shaft including the lower elbow concrete, lining of 4 -26 lower power tunnel was started at the beginning of March, 1990. From the end of the transition of the lower elbow (Sta 177+04) 93 consecutive placement were completed down- stream ending at Sta 31+45 on August 25, 1990. Most of the lining placements were 150 to 180-ft long, some were 210 to 240-ft in length. Placement concrete volumes ranged from typically 250 to 375 cu-yd. There were numerous concrete placement problems particularly the upstream half of the tunnel which resulted in numerous but limited areas of segregated concrete exposed in the concrete lining. Con- crete lining repairs took months to complete. Handling numerous large water inflows during concrete placement was a persistent problem frequently caused localized degradation of concrete. Rebar reinforcement in the concrete lining was installed at 19 locations. Tunnel lining sections with rebar ranged from 20 to 700 feet, but most ranged from 140 to 230 feet. The total footage of reinforced lining was 2,305 feet. Contact grouting of the lower power tunnel started early May, 1990 and was completed in late September, 1990. During this period grouting work was interrupted by the Contractor for his purposes several times; the actual time spent grouting was perhaps two months. The contact grouting work was performed by the general civil contractor (i.e. Enserch). Due to other ongoing construction activities, the Contractor tended to skip some reaches, but for the most part contact grouting was performed from downstream end to the upstream. The design drawings called for two lines of grout holes in the crown 20 degrees left and right of vertical. The hole spacing is staggered so as to be on 10-ft spacing. However, the double grout hole line layout was modified shortly after starting grouting to a single 4 -27 grout line of holes spaced 10 feet apart down the center of the crown. After grouting several hundred feet of double line with minimal take, a single line down the center of the crown was tried and felt to be more effective in filling the shrinkage voids. The single line of grout holes was uti- lized for contact grouting the concrete lining for the remainder of the tunnel length. For the most part the Contractor's performance of the grouting went well. In zones where water flowed from contact grout holes grout at 30 psi plus water inflow pressure was pumped until excessive pressure build up occurred. In many cases the grout and water advanced to the next hole to be grouted. The concrete lining construction joints were generally tight against the crown which limited the grout travel to the length of lining placements. Contact grouting was done with water-cement ratio of 1:1. Quantifying the grout takes for filling the voids in the crown from those required to seal off water inflow below the concrete lining invert for many reaches of the tunnel can only be approximated. Grout take records indicate that in those reaches with little or no water inflow, grout takes in the crown were around a quarter of a sack of cement per foot. In those reaches of concrete lining through signifi- cant water inflows total contact grouting quantities includ- ing grouting water drains in the invert ranged from a half of sack to locally as much as two sacks of cement per foot. Approximately 8,200 bags of cement were used in contact grouting of the tunnel concrete lining (14,500 ft). Contact grouting was not a separate pay quantity; the Contractor had to include these cost in the concrete lining. 4 -28 4.5.5 High Pressure Compaction Grouting Recognized in the design was the need for compaction grouting of a reach of tunnel upstream from the end (Sta 31+55) of the steel liner to minimize the possibility of excessive water loss during tunnel operation. For a reach of tunnel at the downstream end with low rock cover opera- tional water head is considerably greater than static ground water head outside the tunnel. Without treatment of a rock zone (20 ft + or -) around the tunnel to seal open water passages and to improve the rock mass modulus, excessive water losses from the tunnel through opened shrinkage cracks and construction joints in the lining may occur. The need and extent of rock treatment was observed in more detail after excavation of the tunnel was completed. Geologic mapping of rock fractures and joints and monitoring of water inflow in this low cover reach of tunnel provided data for developing a treatment plan. After studying and field checking the geologic data SWEC developed a comprehensive plan for high pressure compaction grouting to seal and consolidate the open fractures and joints in the near field around the tunnel. Their grouting program was expanded and modified beyond that indicated in the contract documents. The SWEC grouting plan called for compaction grouting coverage to continue upstream to tunnel Sta 65+00 from the required high pressure ring grouting near the end of the steel liner, Sta 31+55. The SWEC work plan (Option C) for compaction grouting which included hole locations and all the details of sequencing and carrying out the work under the direction of the Construction Manager is included as an attachment to the SWEC compaction grouting report. A copy of Option C work plan is also retained in the project files. 4 -29 For this final geology report the basic scope of the grouting plan is briefly described below and a summary of compaction grouting results is given in Table 1. Details on the results of compaction grouting between Sta 31+45 and Sta 65+00 can be read in the SWEC final compaction grouting report retained in the project files. The report is cited in the referenced list of this report. Compaction grouting was done utilizing four arrangements at different tunnel intervals. pattern data is summarized below: grout hole The grouting 1) From Sta 31+47 to 31+78 six-ring grout curtain of eight holes each, 60-ft long, grouted in three stages at 165, 500, and 500 psi. 2) From Sta 31+90 to Sta 34+60, eight holes 30-ft deep, spaced 15-ft apart, grouted in two stages at a maximum pressure of 165 psi. 3) From Sta 34+60 to Sta 65+00 both a six and two-hole pattern of holes 20-ft deep, grouted at 240 psi in one stage. Two-hole pattern on 40-ft centers and six-hole pattern on 20-ft centers. Stationing of the six-hole and two-hole pattern grouting is given below: Six-hole Two-hole 35+60 to 38+60 39+00 to 43+60 43+60 to 45+20 45+60 to 46+00 4 -30 46+00 to 47+86 48+20 to 50+50 50+50 to 52+30 52+70 to 61+20 61+20 to 62+20 62+60 to 65+00 After starting a hole with 2:1 water-cement mix initially most of the grouting was then completed using 1:1 mix. Total grout injection was limited to a maximum of 120 sacks of cement per hole. The primary intent of the compaction grouting was to fill the open joints and fractures for one tunnel diameter around the tunnel opening thus sealing off the water and improving the rock mass modulus. A higher rock mass modulus is expected to result in a relative reduction in water loss through the concrete lining due to minimizing crack opening in the concrete lining during tunnel operation. Drilling of the compaction grout holes, using a single boom jumbo with rotary percussion drill was started October 31, 1990 at Sta 65+00, drilling progressed downstream. High pressure grouting started soon afterward on November 7, 1990. Typically 450 feet of drilling was completed each day (3 shifts). Grouting progress depended on grout takes of individual holes. Many of the holes made water and these holes usually took significantly more cement than low inflow or dry holes. Table 6-1 taken from the SWEC compaction grouting report summarizes grout hole connection, drilling and grout (sacks of cement) quantities placed within station intervals. SWEC's data was obtained from daily drilling and grouting records kept by full time Bechtel shift grouting inspectors. Compaction grouting under Option C work plan, 4 -31 was completed February 1, 1991. The Contractor's grouting operation was performed seven days a week, three shifts/day with a 30-day shutdown during the month of December, 1990. 4 -32 TABLE 1 Summary of High Pressure Compaction Grouting Lower Power Tunnel Drilling Redrilling No. of No. of Grout Sand Station Interval Description (LF} (LF l Holes Connections (Sacks) (Sacks) 31+47.5 to 31+77.5 60 ft, 3 stage 2,880 1,920 47 141 0 31+90 to 34+60 30 ft, 2 stage 4,740 2,280 158 310 1,595 120 34+60 to 35+60 2-hole ring 80 0 4 4 191 0 35+60 to 38+60 6-hole ring 1,920 0 96 96 594 0 38+60 to 43+60 2-hole 480 0 24 24 69 0 43+60 to 45+20 6-hole 1,140 0 57 57 158 0 45+20 to 45+60 2-hole 40 0 2 2 0 0 45+80 to 47+80 6-hole 1,280 0 60 64 1,170 80 48+20 to 50+20 2-hole 240 0 12 12 94 0 50+ 50 to 52+50 6-hole 1,520 220 78 92 2,106 0 52+60 to 60+70 2-hole 1,020 100 49 56 1,480 0 61+20 to 62+20 6-hole 760 0 38 39 422 0 62+60 to 65+00 2-hole 280 0 14 _J& __JA _Q TOTALS 16,380 4,520 639 911 200 5.0 UPPER POWER TUNNEL AND GATE SHAFT, INTAKE PORTAL, AND POWER TUNNEL SHAFT 5.1 General Description The power tunnel is segmented into two sectors largely by elevation. The upper power tunnel at El 1029 is separated from the lower power tunnel (El 301) by an interconnecting 720 foot vertical shaft. The length of the upper power tunnel from the inlet portal to the power tunnel vertical shaft is 738 feet. The portal of the upper power tunnel is at the downstream end of a deep approach channel which opens into Bradley Lake. Approximately 520 feet downstream from the portal the upper power tunnel is intersected by a gate shaft. A profile of the upper power tunnel, gate shaft and the power tunnel shaft is included in Appendix E, Figure 5-1. As was done at the main dam, construction activities at the upper power tunnel work were suspended during the colder winter months of 1988-89. During the winter months of 1989-90 limited construction activity, mainly concrete placement, was continued. Completion of the lower power tunnel excavation in September, 1989 allowed access to start the raise boring of the vertical shaft. The raise bore drilling was completed the first week of November, 1989. Concrete lining of the power tunnel vertical shaft exclusive of the upper and lower elbows, did not start until early January, 1990; slip form lining took less than six weeks to complete. 5 -1 5.2 Upper Power Tunnel and Gate Shaft 5.2.1 Excavation and Support Drill and blast method of excavation was utilized for both the upper power tunnel and power tunnel gate shaft. Exca- vated diameter of the gate shaft is 29 feet. Elevation at the top and bottom of the shaft is 1194 and 1029, respec- tively. Initially 4-foot and later 6-foot drill rounds were utilized to sink the 150 deep foot gate shaft. A large crane was used for lowering and hoisting workers, materials, and equipment; it was also used to hoist shot rock. In place rock suitable for setting the shaft collar was encoun- tered 16 feet below the ground surface El 1194. Owing to weak materials around the top of the shaft, excavation for the shaft collar foundation had to be laid back at 1:1 Appendix E, Figure 5-2. After the shaft collar and lining was completed back to ground surface compacted backfill was placed around the shaft lining. Below the shaft collar (El 1178) excavation of 6-foot rounds progressed to invert of the upper power tunnel without incident. Installation of 6 x 6 foot pattern rock bolts around the wall perimeter closely followed shaft excavation Appendix E, Plate 5-1. A full excavation cycle drilling, shooting, mucking, and installing rock bolts usually took more than two shifts. Concrete lining in 10-foot lengths was placed from the ground surface downward keeping 20 to 30 feet above the blasted surface. Light {est. total 2 gpm) water inflows oc- curred from several point sources on the shaft walls. After concrete lining of the shaft inflow discharged from horizon- tal joints resulting in persistent, heavy dripping at the base of the shaft concrete lining. Grouting behind the lining was done subsequently to stop the dripping. 5 - 2 After the gate shaft (which provided personnel and equipment access to the upper power tunnel) was completed to tunnel level, excavation of the 13-foot excavated diameter upper power tunnel was initiated. The downstream heading toward the power tunnel vertical shaft was completed first followed by excavation of the upstream heading toward the entrance portal. A temporary rock plug was left in the upstream heading over the 1989-90 winter to keep water in the intake channel from entering the tunnel. Rock stability in the upper power tunnel was very good; only widely scattered "spot" rock bolts were installed. The specified smooth wall blasting method was utilized with moderate results, it was not always well executed. Water inflow into the upper power tunnel was negligible. Initial flows of 1000 gpm and sustained inflows of 500 gpm were predicted in the GIR. 5.2.2 Geology Similar to the rock types exposed in the dam foundation nearby, graywacke, argillite and intermixed graywacke and argillite also occur in the upper power tunnel and gate shaft. Geologic mapping of the gate shaft revealed primari- ly graywacke for the full depth. Graywacke also occurred in the upper tunnel downstream of the gate shaft. Upstream from the gate shaft all three rock types were present. Approaching the tunnel intake argillite predominated. Geologic tunnel logs of the upper power tunnel are given in Appendix E, Figures 5-3 and 5-4. Excellent geologic conditions for maintaining a stable opening with minimal rock reinforcement prevailed throughout the upper power tunnel. Similarly good geologic conditions were encountered in the gate shaft excavation; support consisted of the specified pattern rock bolts. The 5 - 3 graywacke rock mass quality is sound and exhibits moderately high hardness. Both the argillite and intermixed graywacke and argillite was fresh and moderately hard. Strong joint- ing generally spaced 12-24 inches is prevalent on the walls of perhaps 50 percent of the upper power tunnel, as well as the gate shaft. Elsewhere jointing is not well developed. In the intervals of argillite the rock is more massive in that the common foliated structure is absent for the most part. Similar primary joint trends of N 60 to 85 W with 85 N dips were observed in both the gate shaft and upper power tunnel. Several near vertical, iron stained joints with minor clay were mapped. Two of the more prominent seams extended from El 1178 to 1140. Minor thin (less than 1/4-inch} discontinuous inclusions of soft clay were ob- served along these two shear seams. Below El 1140 in the gate shaft and most everywhere in the upper power tunnel joints were unweathered and very tight. Geologic mapping of the gate shaft walls is presented in Appendix E, Figure 5-5. The several shear seam encountered in the upper power tunnel were relatively minor and did not significantly affect the tunnel stability. 5.2.3 Concrete Lining and Grouting Reinforced 12-inch thick concrete lining was placed through- out the upper power tunnel and in the shaft upper power tunnel gate. The length of concrete placement forms used in lining the shaft and upper tunnel were 10 and 50 feet, respectively. In the shaft lining a flexible membrane with one end embedded in the previous pour and the other against the wall were used for water stops at each construction joint. The membrane water stop was not entirely effective. Leakage occurred through several of the lining construction joints and low pressure grouting to seal off the leakage was 5 -4 done with good success. Concrete placement in the shaft was done in 10-foot lifts from the top down staying 20 to 30 feet above the blasting for shaft excavation. Ten feet of lining was generally completed every other day. Concrete lining of the 13-ft excavated diameter circular upper tunnel upstream of the gate shaft chamber was done between October 21 and December 1, 1989. The portion of tunnel lining downstream between the gate chamber and the upper elbow of the vertical power tunnel shaft was done six months later, from July 1 to July 12, 1990. The upper tunnel lining was reinforced with rebar and the lining was completed in two stages, the invert first followed by the arch. Contact grouting of the crown of the upper power tunnel was completed through two lines of staggered holes spaced 10 ft apart. Contact grouting using 1:1 mix at 30 psi injection pressure was completed July 23 and 24, 1991. A total of 125 bags of cement was injected above the crown lining in the tunnel section upstream of the gate shaft. In the tunnel section downstream of the gate shaft grout take was consid- erably higher. A total of 282 sacks of cement were used in contact grouting of the crown. The crown of the power tunnel intake lining was contact grouted mid-July 1990. Two rows of grout holes of 16 each in the crown of the transition structure were grouted using 2:1 mix at 30 psi. The total grout injected was 410 sacks. These relatively large grout takes would indicate consider- able void space behind the lining. Grouting adjacent to the horizontal construction joints in the gate shaft concrete lining was also done although none 5 - 5 was originally intended. Water leakage occurred around the water stops along many of the construction joints (i.e. every 20 feet). Most grout takes of 1:1 water-cement mix occurred in relatively few holes. Grouting was effective in stopping most of the leakage. 5.2.4 Seepage Barrier Grout Curtain To provide a seepage barrier upstream of the upper power tunnel gate shaft and gate chamber three radial high pres- sure grout rings were completed. Each ring consisted of 15 to 18 staggered holes located immediately upstream of the gate chamber. Staggered 2-inch diameter holes in three rings 30 to 60 ft long, radially 20 degrees apart and were inclined upstream at 10 degrees. The rings designated as GSG1, GSG2, and GSG3 shown in Appendix E, Plate 5-2 are spaced 6 feet apart, at Sta 186+60, 186+66, and 186+72, respectively. These three rings, drilled and grouted through the tunnel concrete lining were completed working 3-shifts per day from August 27 to September 6, 1990. On days, when downtime was minimal, typically 100 to 200 feet of drilling per shift was completed. Drilling was done with drills mounted on a two boom jumbo. Ring grouting was done shortly after completing the drilling of the three ring holes. Grouting started with GSG1 ring followed by GSG3 and finally the intermediate ring GSG2. The holes in each ring were grouted single stage at 160 psi using a water-cement ratio of 2:1. Grout takes in the three rings were relatively low, most holes took less than one sack. Total cement injected into 5 - 6 rings GSG1, GSG2, and GSG3 were 21, 18, and 23 sacks, respectively. Void skin grouting of the gate chamber steel liner was also done. A total of 38 holes were drilled and grouted. Grout take was nil, only 2-1/2 sacks of 2:1 grout in total. Only 14 of the 38 holes took grout. 5.3 Intake Channel 5.3.1 Excavation and Wall Reinforcement The open channel from Bradley Lake to the intake portal of the upper power tunnel is approximately 350 ft in length. Excavation of the intake channel started at El 1230 descend- ing to El 1090, side slopes cut 35-ft high vertically were separated by progressively wider benches 20 to 40-ft wide. The overlying rock quarried from the intake channel was used for rockfill material in the main dam construction. Start- ing at a base level of El 1090 (after the overlying rock had been removed) the intake channel was excavated by drill and blast method in several lifts down to portal invert eleva- tion of 1026. A temporary access/haul road to the channel bottom was constructed along the east wall. To allow excavation to be done in the dry a temporary rock plug, which was later removed, was left across the channel near the shoreline of Bradley Lake. The width of the channel at the top and bottom is 80 and 60 feet, respectively. The side walls with a 10-ft wide bench at El 1055 are vertical. A plan of the power tunnel intake channel excavation is shown on Appendix E, Plate 5-3. The intake tunnel portal cut slope is also vertical, without a bench (i.e. 64-ft high cut slope). Near the entrance to the intake a 10-ft deep rock trap was excavated in the bottom of the intake channel. 5 -7 Perimeter blasting along the wall lines was done by the specified cushion blasting method. Overbreak caused by blasting resulted in irregular bench surfaces particularly on the outside corners. However execution of cushion blasting of the vertical walls of the intake channel was well done. Even wall surfaces without significant overbreak were achieved. The specified design reinforcement of the cut slopes/walls was extensive. Pattern A-1 type (l-inch diameter) tension (5 kips) rock bolts were installed on the channel wall and on the vertical face above the intake portal Appendix E, Plate 5-4. Most A-1 rock bolts range in length from 15 to 35 feet. Around the arch of the intake portal and in three rows along both intake channel walls A-4 type (1-3/8 inch diameter) tension (165 kips) rock bolts were installed. Rock bolt length varied, the A-4 type installed at El 1085, 1065, and 1045 are 35, 22, and 18 feet long, respectively. A-4 rock bolts above the arch of the tunnel intake are 30 feet in length. Vertical dowels, A-2 type (l-inch diameter) were installed before excavation around the perimeter of the intake channel (El 1090) and at El 1030 before excavation at the downstream edge of the rock trap excavation. Locations of the rock reinforcement installed in the intake channel are shown on Appendix E, Plate 5-5. Excavation of the cut slopes and benches of the intake channel excavation and rock quarry above El 1090 were previously mentioned. One year later the adequacy of the scaling and cleanup of the slopes and rock benches above the channel walls came into question. There was concern that detached rock could be further loosened and dislodged by ice movement down the slope causing damage to the intake gate structure. After considerable debate with the Contractor, a 5 - 8 change order was issued to the Contractor for scaling the slopes and benches above the top of the intake channel (El 1090). The slopes were scaled and the benches cleaned back 3 feet from the outside edge and the accumulated rock debris was disposed. This work was started in late September and completed in October, 1990. 5.3.2 Geology The predominant El 1090) consist rock types in of argillite, the intake channel (below intermixed argillite and graywacke. Graywacke was also exposed in a short section of wall and the rock plug on the east side of the channel. Graywacke rock was predicted in the GIR for the tunnel intake area. In the excavation argillite and intermixed graywacke and argillite were exposed. Geologic mapping of the intake channel wall was performed at a scale of 1" = 10'. Geologic map sheets are included in Appendix E, Figure 5-6 (3 sheets). For the most part cushion blasted rocks forming the vertical walls of the intake channel are sound, widely jointed, and massive appearing. Many of the more visible joints were slightly opened by the blasting effects. Above the intake portal for approximately 20-ft joint spacing of 2 to 5 feet is relatively closer than the 5 to 10-ft spacing on the walls. Primary jointing strikes N 70 -80 W and the joint dips typically exceed 70 degrees to the north. A secondary joint set that appears as an undulating, roughly horizontal trace strike N 40 -50 W on the west wall and N 40 -50 E on the east wall. Dips for these secondary joints are low, approximately 10 degrees south. 5 - 9 For the most part joint attitudes did not adversely influ- ence wall stability. As previously mentioned graywacke is exposed in the channel excavation upstream in the vicinity of the rock plug. The graywacke while moderately fresh and hard is strongly jointed and blocky. Considerable overbreak along the joints and shear seams occurred on both the outside corner of the El 1090 bench and on vertical cut the more slopes. The occurrence of shear seams elsewhere on channel walls were few and mostly minor. One of the visible shear seam which had N 70 E strike and 75 degree (west) south dip extended from El 1090 down along the left side of the intake tunnel portal to El 1026. The shear seam was 6 to 12 inches wide with minor intercalated discontinu- ous clay in finely fractured, platy rock. Because of its location Appendix E, Figure 5-5 (sheets 1 of 3) and attitude the seam had no adverse effect on the stability of the high vertical face above the intake portal. Overall, rock stability of the intake channel cut slopes would have to be assessed as very good. 5.3.3 Removal of Rock Plug As previously mentioned in 5.3.1 above, a rock plug approxi- mately 75 feet wide at the base (El 1055) and 29-feet wise at the crest (El 1090) was left in place across the entrance to the intake channel temporarily to allow excavation and concrete work in the intake area to be done in the dry. Upon completion of the intake channel excavation, tion of the intake structure, insertion of the trash racks and the completion and closure of construe- gate and the upper power tunnel gate valve the plug was no longer needed it was removed by the Contractor. 5 -10 Preparation and execution of the rock plug September and October, 1990 involved a number removal in of steps. Briefly summarized below were the main considerations and work activities included in the Contractor's approved work plan 1. A determination of expected over pressure on the intake structure 240 feet away from the blast zone. 2. A blasting vibration limit of 5 inches per second at the structure resulting in a maximum explosive charge per delay of 780 pounds. 3. Pre-grouting of a row of holes across the top of the rock plug on the upstream (i.e. lake side) side to consolidate and minimize leakage prior to starting plug excavation. 4. Removal of a slice of rock by careful drilling and blasting from both the upstream and downstream side of the plug to minimize the rock quantity for final removal. 5. Drilling for final plug removal six rows, 45-feet deep blast holes inclined upstream and downstream from the vertical center row. 6. Established a maximum explosive charge per hole 113 pounds with 6 holes per delay for total of 678 pounds per delay. Overall powder factor up to 1.4 pounds per cubic yard. 5 -11 7. Flood intake channel to lake level prior to blasting. 8. During blasting operate a "bubbler" air cushion at the front of the intake structure. Utilize the services of an outside blasting to develop and implement the drilling and plan. specialist blasting The objectives of the rock plug removal by well planned blasting were achieved with good success. Breakage of the rock plug met expectations. Throw rock into the intake channel was minimal. The heaved rock was leveled off above water level (El 1073). Excavation shot rock from the intake channel was done mostly with the Cat 245 backhoe working on the muck pile and to a lessor extent with the Manitowoc 4000 crane using a 4 cu-yd clam bucket. 5.4 Power Tunnel Vertical Shaft The 720-ft vertical shaft with 90 degree elbows top and bottom completes the connection of the upper and lower reaches of the power tunnel. The upper and lower power tunnels were previously described in Sections 5.0 and 4.0. 5.4.1 Excavation and Support Excavation of the power tunnel vertical shaft was done by raise boring. First, to provide a center guide for the raise bore head, a 14-inch diameter pilot hole was drilled from the ground surface (El 1250) to the invert grade of lower power tunnel (El 301) refer to Appendix E, Figure 5-1. Drilling of the pilot hole took 15 days (24 hr days), which was longer than initially scheduled. Soon after TBM excava- tion of the lower power tunnel had reached the pilot hole, the raise bore equipment was mobilized and drilling was 5 -12 started October 2, 1989. Similar to the pilot hole drilling raise bore drilling also was slower than expected. The raise bore was holed through at the invert of the upper power tunnel (El 1029) November 4, 1989. Several days of down time occurred during the drilling period due to a generator outage. Progress summary sheets of pilot hole and of the raise drilling is included in Appendix E, Figure 5-l. After completing the raise bore drilling and shaft outfit- ting, a preliminary inspection of the rock stability condi- tions in the shaft was conducted. For the most part rock conditions in the shaft were good. Several localized fall-out zones and break-out occurred along a number of vertical joint-seams that definitely required rock bolt support and wire mesh. Pattern rock bolt support for the entire length of shaft was specified on the design drawings Appendix E, Plate 5-6. However, based on reasonably good rock conditions, a design change was made not to rock bolt and mesh the entire shaft. Instead rock bolts and wire mesh were installed in areas of poor wall rock stability and elsewhere including the upper and lower elbows to assure safe working conditions. Approximately 1,300 six-foot long resin encapsulated rock bolts were installed in the straight portion (647 ft) of the shaft. Approximately 100 resin rock bolts were 10-ft rock bolts. Welded wire fabric and/or wire mesh and limited mine straps were placed over approximately 30 percent of the shaft walls. Total water inflow into the shaft, most of which enters near the top of the shaft, appears to be less than 15 gpm. 5.4.2 Geology The slow penetration rate while drilling both the pilot hole and the shaft indicate graywacke was the predominant rock 5 -13 type encountered. Logs of a nearby boring drilled during the pre-construction investigations also indicated a majori- ty of graywacke rock. After completion of excavation and installation of rock bolts geologic mapping of the shaft was done from a steel 3-deck work platform which was lowered and raised by a large drum hoist located at the top rim of the shaft, within the upper tunnel. Geologic mapping of the shaft walls confirmed the occurrence of graywacke as indicated by the pilot hole drilling. In the upper 80 ft of the shaft the graywacke is intermixed with perhaps 30 percent argillite. Slight to locally high weathering occurs along some shear seams and joints. Elsewhere the rock is fresh, sound, and moderately jointed. For the most part, jointing is tight, many of the joints are re~ealed with calcite. Completed geologic mapping of the vertical shaft is attached. There are three main geologic structural conditions which resulted in localized rock instability in the shaft walls. 1) Steeply included shear seams and joint seams at several locations both with and without soft clay infill~ oriented roughly normal to the shaft walls. 2) Steeply inclined joints subparallel to the shaft walls; approximately eight locations. 3) Localized fractured rock areas associated with shear seams subparallel to the shaft walls; two locations. Instability at these locations resulted in rock fallout from the shaft walls which in most cases left potentially 5 -14 unstable blocks of various sizes around the edges of the fallout areas. Generally, fallout along joints and near vertical seams is less than 6 inches (i.e. into the shaft wall) and as much as 12 inches for steeply inclined joints. The most significant unstable area in the shaft is on the northeast wall at a depth of 300 ft. This located fallout area is approximately 15 ft wide at the top and narrows to 3 ft in width approximately 50 ft below. Generally from 1 to 2 ft of fallout, locally as much as 3 ft has occurred from this area. Rock around the irregular edges of the fallout zone is moderately weathered and closely fractured. The back face of the fallout area appears to be a joint surface subparallel to the shaft wall. The geologic mapping of the power tunnel vertical shaft including geologic notes are presented in Appendix E, Figure 5-7. Mapping of the circular shaft is represented on flattened quadrants at a horizontal and vertical scale of 1" = 20'. 5.4.3 Concrete Lining and Grouting After completing excavation and rock bolting/wire mesh support in the power tunnel vertical shaft, the Contractor prepared the lower elbow of the shaft for concreting. The concrete lining of the lower elbow started just prior to the Christmas break and was completed at the end of January, 1990. Upon completion of the lower elbow preparations were made for concrete lining of the straight portion (647-ft) of the shaft. Steel forms 20 feet in height were used to successively concrete line the shaft from the bottom Concrete was hauled (approximately 8 miles) from the plant near the powerhouse in transit mix trucks 5 -15 upward batch to the collar of the gate shaft where it was dropped through a vertical pipe to the based of the gate shaft. From here it was pumped 200 ft to the vertical shaft where it was dropped again through a pipe down the shaft into remix pot at the top of the concrete forms. Concrete shaft lining work started February 5 and was completed March 13, 1990. There was no contact grouting behind the concrete lining of the straight portion of the shaft. However, contact grouting in the crown of both the upper and lower shaft elbows was done. A single line of eleven contact grout holes around the crown of the lower elbow lining were drilled and grouted at the end of August, 1990. Two holes took 8 and 11 sacks of 1:1 mix at 30 psi; the remainder of holes were tight. For the upper elbow, prior to concrete placement, a looped grout pipe had been preset in the dome above the upper elbow. The concrete rock contact above the upper elbow was grouted July 5, 1991; eighteen sacks of cement were placed. On this same date the remainder (197') of the vertical shaft pilot hole (14") was also grouted. A pipe was sealed in the bottom of the pilot hole (i.e. at the top of the dome above the upper elbow). Grout (1:1) was pumped in from the bottom until grout overflowed from the top of the hole. A total of 150 sacks of cement was used to backfill the pilot hole. 5 -16 6.0 DAM, SPILLWAY, AND DIVERSION TUNNEL GATE SHAFT 6.1 General Description The Bradley Lake Hydroelectric Project facilities are separated into two areas, the upper area at general eleva- tion of 1100 to 1200 and the lower area tens of feet above sea level. Facilities of the two areas are connected by the 3.6 mile lower power tunnel. Road access between the two areas is 8 miles long. The upper facilities described in this section include the dam and cofferdam, spillway, and the diversion tunnel gate shaft. They are all located in the vicinity of the Bradley Lake outlet. Most of the upper facilities were under construction during the summer season of 1989. Excavation of the diversion tunnel not described here was completed in 1987 under a previous contract. The main dam including the concrete face was essentially com- pleted by September, 1989. By this same date spillway construction was approximately 45 percent complete and was finished by July, 1990. The cofferdam was constructed the summer before (1988) as was the initial dam foundation stripping and quarry development. Owing to snow accumula- tion and extreme low temperatures at the upper facilities area, the Contractor elected to shut-down construction operations on the dam and spillway from mid-November, to March, 1990. 1989 In March, 1990 the Contractor resumed construction opera- tions at the upper works. During early spring and summer the spillway structure was completed, the diversion tunnel gate shaft excavated and lined, finishing work on the dam was completed. A temporary fish-water bypass and other required rock and concrete work was in progress in the 6 - 1 diversion tunnel through the winter of 1990-1991. Permanent equipment was also installed during this time. By mid-April, . 1991 the upper works were essentially completed. 6.2 Dam and Cofferdam The main dam was constructed near the outlet of Bradley Lake between a massive rock knob forming the right abutment and a broad rock nose at the end of a sloping ridge. The upstream toe of the dam is less than 200 feet from shoreline of Bradley Lake. The cofferdam across Bradley Lake outlet was constructed within this 200-ft wide zone. Flow into the Bradley River was diverted through the diversion tunnel. The crest length and height of the main dam is approximately 600 feet and 140 feet, respectively. The upstream concrete face and the downstream slope of the rockfill embankment have similar side slopes of 1.6H:V. The concrete face is joined to a concrete toe plinth founded on sound bedrock. A foundation seepage barrier is provided by a single line grout curtain along the length of the plinth. The power tunnel inlet portal is slightly upstream and to the west of the left abutment of the dam. Rock quarried from a rock mass above the tunnel intake channel was used as rockfill in the dam. The cofferdam, constructed across the outlet channel of Bradley Lake was constructed with a central core founded on bedrock to minimize leakage. Geomembrane sheet- ing was installed the length of the core from bedrock to the crest of the cofferdam to further reduce leakage. The crest length and maximum height of the cofferdam was approximately 100 feet and 25 feet, respectively. Bedrock exposed in the cofferdam core trench foundation including abutments consist mainly weathered graywacke rock overlain primarily with previous, dense, sandy, silty 6 - 2 gravels and boulders. Because of continual leakage from Bradley Lake through the upstream side of core trench, the cofferdam foundation was never completely dewatered before the start of core material placement. Consequently, compac- tion at the rock contact was less than desired due to saturation of core materials. Leakage through the cofferdam foundation near the right abutment continued throughout foundation excavation and construction of the main dam. It was necessary for Contractor to operate a dewatering pump full time to remove water (est. 125 gpm) leaking through the cofferdam. 6.2.1 Foundation Excavation The base of the dam embankment is approximately 550 feet wide upstream to downstream. Its breath across the river bottom is approximately 280 feet. Foundation excavation in the river channel consisted of alluvial deposits and local- ized areas of glacial till. On the lower half of the left abutment slope excavated materials consisted of colluvium and talus deposits. Whereas on the right abutment bedrock was exposed for the most part. A plan and profile of the rock excavation for the main dam is shown on Plate 6-1, Appendix F. The thickness of the excavated alluvial deposits was vari- able ranging from as much as 15 feet in one deep bedrock depression near the upstream toe on the west side of the river channel to more generally one to three feet downstream of the dam axis. Excavated talus/colluvium deposits which extended from the river channel approximately 200 feet up the slope of left abutment were as much as 10 feet thick locally, but more generally one to three feet thick. The quantity of talus excavated from the lower right abutment 6 - 3 was relatively minor. Excavation of most of the unsuitable foundation materials was done by backhoe and dozer. The stripped bedrock foundation surface in the river channel area, with the exception of the large depression near the plinth line was highly irregular, pock marked with large and small potholes and elongated shallow, narrow erosion chan- nels. Foundation preparation for the river channel portion of the embankment foundation consisted machine cleaning of the bedrock, as allowed in the specifications. Rock excava- tion and rock surface preparation beneath the embankment portion of the dam was minimal. On the upper two-thirds of right abutment slope bedrock was widely exposed as was the upper third to a lessor extent on left abutment. 6. 2. 2 Plinth Excavation and Foundation Treatment Requirements for excavation and rock surface preparation of the plinth foundation were considerably more stringent than for the embankment foundation. Foundation elevations for the various plinth segments were specified on the contract drawings. The depth of acceptable foundation rock varied, but in general rock excavation ranged from a few feet to as much as 10 feet below the original rock surface. Foundation excavation removed all the weathered unsound rock as well as providing for a more uniform slope transition from one plinth segment to another. Careful blasting was done to avoid excessive fracturing of the plinth foundation. However, over excavation occurred in portions of some plinth segments. Preparation of the foundation for concrete included scaling of all rock fragments loosened by blasting and cleaning-washing with high pressure water jets. The actual foundation width prepared for detail cleanup was approximately 15 feet. An a additional 10 to 20 feet of natural rock surface upstream of the plinth foundation was 6 - 4 also sufficiently cleaned to permit inspection and delinea- tion of any geologic features which could affect foundation treatment including curtain grouting. Minor quantities of lean concrete were placed locally in a number of plinth blocks to level out sharp irregularities in the plinth foundation. A dozen or so thin shear seams 6 to 12 inches wide crossed the plinth foundation. Several of the wider seams in plinth foundation segments B, C, and A required minor foundation dental treatment, i.e. excavation to twice the width and filled with concrete. The locations of these shear seams and their character are further described in 6.2.3 Foundation Geology. Owing to weathered condition of the rock above an open joint seam near the up-slope end of Segment A, a considerable quantity (approximately 60 cu-yd) of rock was removed and subsequently replaced with concrete. At final excavation depth the aperture of this particular joint was 1 to 3 inches. Holes for washing the joint were drilled further up the slope. Return water from the open joint did not appear for a couple of hours; the joint seam was only weakly responsive to air-water jetting. Special attention was given to treating the open joint during foundation grouting. Details are given in a separate dam foundation grouting report listed in the references. A prominent erosion channel that crossed the plinth founda- tion at the west end of Segment D at the base of a high rock face on the right abutment was found to be deeper than expected. At approximately El 1038 the width of the rock channel narrowed from 8 to less than 4 feet and was filled with densely compacted boulders and gravel. Exploratory rotary percussion holes revealed infill bottomed at El 1034. 6 -5 To facilitate infill removal additional rock excavation by drilling and blasting was done. After excavation and cleanup, the shear seam along the bottom (El 1032) of the erosion channel was found to be tight and less than 6 inches wide. Concrete backfill was placed in over excavated erosion channel back to base of the plinth, El 1052. For the most part the final plinth foundation on the right abutment was excavated and constructed along a narrow 4 to 5 feet, upward sloping (30°) bench which had been drilled and blasted from a high precipitous rock face. With one excep- tion, the condition of the rock both in slope stability and soundness was very good. Approximately two-thirds up the right abutment plinth slope additional rock excavation was required in a 30-foot wide zone. It was necessary to remove highly weathered, fractured and blocky rock associated with an open joint seam along one side of a huge, massive rock wedge. At plinth foundation grade, the open joint seam pinched-out and was tight. However, outside (upstream) the joint, 6 to 10 inches wide, was infilled with silty gravelly sand up to the ground surface. Dental treatment of this open joint seam consisted of excavation of the infill material down one to two feet all along it surface exposure (approximately 50 feet) and backfilling with small aggregate concrete. 6.2.3 Foundation Geology Geologic mapping was limited primarily to the plinth founda- tion where the excavated rock surface had been cleaned and prepared for concrete placement. Machine cleaning of the foundation surface beneath the rock fill embankment limited mappable exposures to gross geologic features. However, close inspection of the machine cleaned foundation surface 6 - 6 did not reveal any significant geologic features such as faults or soft materials. Several narrow erosion/scour channels and a number of large, shallow potholes were present. The most prominent, undulating scour channel of 1 to 3 feet in depth, is located along the base of the right abutment rock knob. It extends perhaps 50 feet upstream and downstream of the dam axis. Some of the scour channels were filled with dense clay till, others were infilled with densified sandy gravel. The orientation of the erosion channels appear to be controlled by north trending joints. The portion of embankment foundation in the river channel and on the right abutment is almost entirely graywacke. Rock quality is good; weathering is minor. Primary joint spacing where it could be seen appears to be spaced several feet apart. Although the surface of the massive rock knob forming the right abutment had been discolored by weather- ing, the penetration depth than 12 inches. Above the jointing on the precipitous of weathering is generally less channel on the right abutment rock wall is widely spaced, ranging from a few feet to as wide as 10 feet or more. Foundation preparation for the rock fill embankment against this right abutment area was minimal. A thin veneer of colluvium and talus was removed from isolated erosional rock pockets and from narrow, elongated depressions along some prominent joints where erosion had occurred in the past. On the left abutment slope above the river channel graywacke predominates, but localized areas of argillite within the graywacke mass occur also. Several small bedrock areas on the left abutment were overlain by thin deposits of colluvium. Colluvium was also present in narrow ravines located between small knobs partly isolated from the main 6 -7 rock mass of the left abutment. Exposed foundation rock after stripping was moderate to locally highly weathered. Geologic mapping of the plinth foundation at a scale of 1" = 20' was completed as each segment of the plinth was being prepared for concrete placement. Geology maps (five sheets) of the plinth foundation segments including brief geologic description are given in Appendix F, Figure 6-1, signifi- cant geologic features occurring in each segment of plinth foundation have been summarized and are included in Appendix F, Figure 6-2. In summary, the dam plinth weathered graywacke. The closely jointed, without is founded on fresh to slightly foundation rock is sound, but major geologic defects. Minor defects were encountered in the form of shear seams 6 to 12 inches in width, most with intercalated 1 to 3 inches wide, discontinuous clay layers. These thin seams were treated as provided for in the specification. In plinth Segment A and the right abutment plinth open joint seams were uncovered. These too were treated by cleaning and grouting in Segment A and partially excavating and filling with concrete on the right abutment. For further geologic discussion of the plinth foundation the reader should refer to Appendix F for the "as-built" mapping and descriptions of the plinth foundation geology. 6.2.4 Rockfill Material The primary source of embankment rockfill materials come from the rock ridge from which the power tunnel intake channel was excavated. Rockfill is composed primarily of graywacke with perhaps one-third of the quarry rock 6 -8 consisting of argillite and intermixed argillite and graywacke. The intake channel extends approximately 320 feet from the water's edge of Bradley Lake to the tunnel portal. Rock cover over the intake channel before excava- tion was about 200 feet. Rockfill (quarry) development work starting at the top of the ridge was done during the summer and fall season of 1988. Large quantities of stripped materials requiring drilling and blasting had to be wasted to eliminate unsuitable materials, i.e. soil, vegetation and excessively weathered rock. In this stripping operation the ridge top was roughly leveled-off to El 1200. Useable portion of quarried rock above El 1200 was dozed over the rock cliff where it was loaded and hauled to the darn founda- tion for placement and compaction. Late spring of 1989, after the winter shut down, quarrying operations and darn embankment construction resumed. There were five construc- tion material zones in the darn embankment, Appendix F, Plate 6-2. Zones 1 and 5 consisted of upstream and downstream slope protection materials. Zone 2 consisted of a horizon- tal layer of rockfill materials placed directly on the machine cleaned foundation surface. Rockfill in Zone 3 upstream of centerline and Zone 4 downstream formed the bulk of the embankment. Zones 2, 3, and 4 were obtained directly from angular shot rock developed in the quarry. Zone 5 riprap was developed by selectively separating oversize shot rock 36 to 48 inch diameter. Tunnel muck from the TBM operation at the lower power tunnel was hauled to the darn for use as Zone 1 materials. After testing for gradation and permeability, the tunnel muck was found acceptable and was substituted for the specified Martin River aggregates. Ready availability of the tunnel muck strongly influenced the Contractor's request to change material sources. Com- pacted tunnel muck provided an excellent bedding material 6 - 9 for the concrete facing of the dam. Dam embankment materi- als were compacted with 6 passes of a smooth drum 10-ton vibratory roller. Dam embankment construction was completed by mid-summer and the placement of the concrete face slabs was completed early September, 1989. 6. 2. 5 Foundation Grouting A single line grout curtain was completed through the concrete plinth for its entire length. A change order by the Engineer extended the left and right abutment grout curtains 200 and 120 feet, respectively beyond the ends of the abutments. Grouting of the plinth foundation was completed the summer of 1989. The grout curtain extensions were partially done in 1989, but due to low winter tempera- tures, grouting was temporarily terminated. Grouting was restarted and completed in the spring of 1990. Details of the dam foundation grouting are given in a separate Bechtel report, Main Dam and Spillway Grout Cur- tain, October, 1989. For this report a generalized a plan and profile of the main dam drilling and grouting program is shown in Appendix F, Figure 6-3. Also, included on the profile and in the notes is a summary of grout takes by plinth segment. An approximate total of 680 sacks of cement were injected in the dam plinth foundation. Of this total approximately 85 percent of the sacks were injected in three holes. The majority of the grout holes were tight, taking no grout or a nominal amount. Grout takes in the left and right abutment extensions were approximately 195 and 21.5 sacks, respectively. One hole on the right abutment exten- sion took 850 sacks. Details of the abutment extension grouting is included in above-mentioned separate grouting report. 6 -10 6.3 Spillway The concrete spillway structure was constructed across a narrow rock saddle between the massive rock knob forming the right dam abutment and the precipitous rock cliff rising from the base of the mountain mass to the east. Crest elevation at the abutments of the spillway is El 1090 and the overflow section is El 1080. The length of the spillway structure at the crest is about 275 feet. Curtain grouting was done from the foundation rock surface. Drainage holes located in a gallery at the base of the spillway structures were drilled prior to completion of gallery roof construc- tion. A plan and section of the spillway is shown in Appendix F, Plate 6-3. 6.3.1 Foundation Excavation and Treatment Excavation of the spillway foundation lasted over several months starting in Hay, 1989 and completed August, 1989. With exception of deep erosional feature at the base of the right abutment, the remainder of the foundation consisted of variously weathered graywacke bedrock. The erosional feature consisted of a deep, enclosed depression 15 to 25-ft wide incised upstream by a deeper, narrower channel 2 to 5-ft wide. Until excavated the channel had been filled with dense alluvial deposits. The lowest elevation of the excavated incised channel at the upstream toe of the spillway was approximately 35 feet lower than the bedrock surface at the downstream toe. West of the erosion channel to the end of the left abutment the stripped rock surface was highly uneven, in part due to past glaciation and in part to differential weathering along open, repetitious jointing. Drilling and blasting was 6 -11 necessary to remove excessively weathered, blocky rock and to satisfy design foundation elevations. In several local areas "over" excavation of up to 10 feet was necessary to reach suitable foundation rock conditions. A high (El 1200) precipitous rock face existed on the right abutment side of the spillway. Although the rock was massive and of good quality the design called for a thin slice of rock to be removed to develop a bench at the base at El 1145. The rock slice was removed by pre-split blasting resulting in a continuous, even surface. Foundation excavation in the spillway was done by backhoe and dozer. Most of the rock excavation was pushed or cast upstream as permitted by the specification. Final foundation preparation included detail scaling of loose rock materials and cleaning of the founda- tion surface with pressurized air and water jetting. Special seam treatment was done in the incised channel and in several local areas where inverted V-shape, elongated rock projections occurred in the foundation. Lean concrete was applied to fill and even out these and other near surface irregularities. 6.3.2 Geology Foundation rock in the spillway consist entirely of graywacke. At foundation grade the rock is generally fresh to slightly weathered for an 100-ft wide section east of the right abutment including the deep erosion channel and the precipitous rock face. Over the next 175 feet of foundation to the end of the left abutment rock weathering is slight to moderate. The dominant geologic structure is the strong repetitious northwest trending joint system. This joint system prevails across the entire spillway foundation. Over most of the foundation area this reasonably tight. Withstanding persistent jointing was the generally tight 6 -12 jointing, there were a number of short sections (less than 5 feet) of individual joints that were open 1/2 to 2 inches in otherwise sound rock. The extent of the openness of these joints was further demonstrated by the relatively high grout takes during foundation curtain grouting. A brief summary of the spillway foundation grouting is given in Section 6.3.3 of this report. Several shear seams, 3 to 12 inches wide were mapped in the final spillway foundation. Two of the seams traversed the full width of the foundation. The seam material consists mainly of finely fractured rock materials discontinuously interspersed with minor clay. As part of the foundation preparation these seams were scaled and washed with air and water jets to a tight surface. A further description of the spillway foundation geology is given on three geology map sheets included in Appendix F, Figure 6-4. 6.3.3 Foundation Grouting A separate grouting report was prepared for main dam and spillway. The report, Main Darn and Spillway Grout Curtain Construction Report, gives a detailed description of curtain grouting and includes grouting records and drawings. In this report a location map of grout and drain holes and a summary of the grout takes including, large individual hole takes is provided in Appendix F, Figures 6-5 and 6-6. As indicated on Figure 6-6 most of the grout take was consumed in seven holes; takes ranged from 93 to 356 sacks. These large grout takes closely corresponded to locations of open joints in the spillway foundation which are indicated on the spillway foundation mapping in appendix F, Figure 6-4. In other sections of the spillway foundation contact grouting was also done along the grout curtain line after one or more 6 -13 lifts were placedi grout takes were low. Drain holes located in the spillway gallery (indicated on Appendix F, Figure 6-5) were drilled by rotary percussion methods. Drilling was done through preset nipples after completion of curtain grouting, but prior to construction of the gallery roof. Previously mentioned in 6.2.5 was the curtain grout line extensions of 160 and 120 feet on the left and right abut- ment of the main dam. The right abutment extension ties into the left abutment spillway curtain grout line. A description of the extension grout curtain results is included in the above cited grouting report. 6.4 Diversion Tunnel Gate Shaft The short (400 feet) diversion tunnel, excavated during a previous contract, passes through the rock knob forming the main dam right abutment. Approximately 110 feet upstream of the diversion tunnel outlet portal the 20-foot diameter 110 feet deep vertical gate shaft was excavated and lined with concrete to the crown of the diversion tunnel below. 6.4.1 Excavation and Support The shaft collar preparation was initiated March 14, 1990. Sinking by the drill and blast method was started March 22 and was excavated through the crown of the diversion tunnel a little more than a month later, April 27, 1990. Similar to the power tunnel gate shaft, sinking blast rounds were 5 feet deep. One-half of the shaft bottom was drilled, shot, and mucked at a time (i.e. alternating benches). Except near the bottom where minor water inflow was encountered the shaft wall excavation was dry. Wire mesh and rock bolts 6 -14 were installed, over the entire shaft surface. A ring of fifteen 10-ft long rock bolts were spaced at an average of 6-ft apart every 5 ft in elevation. Three-foot long rock bolts were installed between the rings as well as between bolts in the rings where it was required to pin the wire mesh to the rock surface. Shaft excavation outlines and design support is shown in Appendix F, Plate 6-4. 6.4.2 Geology The rock in the shaft walls consists primarily of graywacke with occasional lenses of argillite. The rock is generally fresh, hard, and massive. Slight to moderate weathering and staining occurs locally on some joint and shear planes. This weathering is more prevalent near the surface and become negligible with depth. Jointing is generally tight. Many joints are filled with calcite and calcite veinlets occur frequently on the walls of the shaft. Only one significant geologic condition was noted in the shaft, which resulted in an overbreak fallout of 6 ft in the southeast wall at a depth of 86 ft (El 1110}. The fallout occurred along the footwall of a 6-in thick clay/silt shear plane. This plane may be connected to a similar shear noted in the mapping of the diversion tunnel. The shaft was generally dry except for minor seepage of surface water in the upper part of the shaft. However, it was noted that water drained out of the shaft when it was in contact with the shear seam mentioned above. After the excavation crossed the shear plane the seepage no longer occurred. It appears that the shear seam is connected to either the diversion tunnel or the surface excavation of the right abutment of the dam or possibly the left abutment wall of the spillway. 6 -15 The mapping was done from either platform suspended into the shaft a steel basket or a by a crane. Rock steel debris had collected behind the wire mesh in some areas. Prior to mapping, the walls were washed with a high pressure hose to remove the powder cover from the blasting operation. The walls were moderately clean with only limited areas where the dust cover was still present. As a result of the conditions in the shaft the strike and dip of joints and shear sets were not measured directly, except at the bottom of the shaft. The strike was approxi- mated by extrapolating from known north, east, south, and west plumb lines dropped from reference points on the surface at the top of the shaft. Dips were approximated by measurements perpendicular to the estimated strike direc- tion. Geology mapping of the diversion tunnel gate shaft is shown in Appendix F, Figure 6-7. 6.4.3 Concrete Lining and Grouting Different from the power tunnel gate shaft where concrete lining was placed from top to bottom as excavation pro- gressed, the lining in the diversion tunnel gate shaft was placed upward from the bottom of the shaft after excavation. Lining was done using 10-ft high forms. Water stops were included at each construction joint. Concrete lining commenced May 4, 1990 and finished two weeks later on May 17, 1990. No contact grouting was done behind the concrete lining in the diversion tunnel gate shaft. 6.4.4. Seepage Barrier Grout Curtain Upstream of the main dam diversion tunnel gate chamber, two sets of triple rows of high pressure grout rings, similar to those upstream of the power tunnel gate shaft, were 6 -16 completed. One triple ring of holes was located approxi- mately 20-ft upstream of the gate shaft centerline. The second triple ring was approximately 115-ft upstream of the shaft centerline. Hole depths were 40 feet in the upstream ring set and 30 feet in the rings closest to the shaft; spacing between individual rings was 5 feet. In the up- stream ring set grout holes above the tunnel springline were inclined downstream somewhat so as to overlap the lower ends of the spillway curtain grout holes which terminated about 15-ft above the diversion tunnel. Pressure grouting (110 psi) of the triple ring of holes nearest the diversion tunnel gate shaft was done mid-April, 1991. The 30-ft long holes, 15 to 17 holes in each ring, were grouted in one stage with a 2:1 water-cement grout mix. There was no grout take, other than a nominal amount used to backfill the hole, in any one of the holes in the three rings. Apparently all the open rock fractures/joints had been sealed by the previously completed spillway curtain grouting done from the surface. The drilling and grouting of the three rings of holes upstream of the gate shaft chamber, Sta 2+35, Sta 2+40, and Sta 2+45 was done during early March, 1991. Eight of the radially-oriented holes (those above springline) were extended in depth from 40 to 60 feet. Holes were inclined 15 degrees downstream to meet the curtain grout holes drilled from the surface. The upstream ring was grouted first, the downstream ring second, and the middle ring last. Holes were grouted with 2:1 water-cement mix in one stage at 100 psi. Grout takes in the 15 hole ring patterns at Sta 2+35, Sta 2+40, and Sta 2+45 were 22, 1, and 41 sacks, respectively. Locations and hole orientation of the grout 6 -17 rings in the main darn diversion tunnel are shown in Appendix F, Plate 6-4. By way of Change Order No. 127, twelve 60-ft deep, radially oriented 2-inch diameter drain holes inclined 15 degrees upstream were drilled at Sta 0+82 in the diversion tunnel. The holes started 15 degrees below springline and were spaced 20 degrees apart. These drain holes were installed to intercept any leakage by passing the spillway grout curtain in the vicinity of the gate shaft chamber. 6 -18 7.0 MIDDLE FORK AND NUKA DIVERSION 7.1 General Description The Bradley Lake Hydroelectric Project also includes the supplemental construction of two facilities for diverting offstream water into the Bradley lake watershed. One of the works consists of two small, low earthen dikes and a diver- sion channel with a concrete outlet weir. The other facili- ty diverts the Middle Fork Bradley River on north side into an existing drainage leading to Bradley Lake. Construction work for the Middle Fork and Nuka diversion was done under a separate contract to Alaska Energy Authority. The facilities were designed by SWEC and the construction managed by Bechtel. The work was contracted to low bidder, Wilder Construction Co., Inc., Anchorage, Alaska. Total contract cost was $1,729,095. The construction started June 10, 1990 and was completed August 7, 1991. Due to remoteness of the construction sites and the stringent ac- cess/environmental restrictions all construction personnel, materials, and equipment were airlifted by helicopter to and from the jobsite. 7.2 Excavation Construction involved excavation of soil and rock mainly for diversion channels and fill placement for low earthen dikes. The channel for the Middle Fork diversion was 900 feet long. Although the metagraywacke and argillite rock was fractured and weathered the deeper portions of channel excavation at both sites required drilling and blasting. A total of 43,718 cu-yd of undifferentiated soil and rock excavation was done. 7 - 1 Location and cross sections of the Middle Fork and Nuka diversions are shown in Appendix F, Plates 7-1 and 7-2. 7 - 2 / ~~ ;7/'C:"}Pk Vp?k~e / A h//c:'~e-e;5 B __ C: P, E t F c2re /)1 0 h/7/e z- + \ Photo Selection Final Geology Report PoHerhouse & Penst.ocks & l!anifold Tunnels Book No. (Jile,9=n4'Ve rl~!s. Page,No. ~Photo Nc. Date ~34/ d,_/1 4 9/08/88 1 2 ~·/!If 1 9/24/88 2 v{621 g'A 9 10/13/88 5 /682/ 5 6 2/12/89 4 ~97 / 4 5 1/06/89 6 /817/5 _§. 3/18/89 6 photos Additional Photos for Cover Book No. Page No. Photo No. Date 3 /~84 / <P 8 11/20/88 9 vi2ss/ ;e>li : 5/16/89 9 /1:;94 / t2A-12 6/14/89 2 V~85'/ VI _] 10/20/88 * 4 photos Photos to be printed 3" x 3" size. Book No. Page No. Photo No. Date 11 /1593/ r 8 7/27/89 ~ Portion of East wall of Pm·1erhouse cushion blasting El 4C -18 South wall of Powerhouse El 40 -El 18 Dark color -shear seam along the East wall of P.H. Pmverhouse Unit, proof load- ing 1-3/8 in corrosion resistant anchors at spherical valve foundation Graywacke rock jointing Penstock 1 tunnel wye Pmverhouse Units 1 & 2 excavation El 2 winter conditions Subject Winter scene drilling toe plinth -main dam at TBH in tunnel large water inflm1 Drilling in upper power tunnel gate shaft East \vall of Pm1erhouse excavation, Penstocks 1 & 2 Subject Dam site area, dam nearly topped out, shaft collar & quarry intake -taken from shaft pilot hole pad Photo Selection Final Geology Report Dam & Spillway, Quarry Book No. Page No. Photo No. Date 1 ~24 / (,,+ 6 / 9/02/88 7 ~023 / 7A 9 4/10/89 8 vl106 ,/'' ;2-13 4/25/89 8 vC121 2-2 4129/89 8 v1~94 / 7 8 5/06/89 / 9 ;;_354 / 2A 4 6/01/89 9 /1384/ 4 4 6/05/89 11 7/27/89 8 photos Subject Main Dam Foundation Excavation Lcoking at Right Abutment Main Dam -Toe Plinth excavation, lmv-er left abutment Main Dam -Toe Plinth foundation Block C-3, Note thin clay seam Main Dam -Toe Plinth foundation Block B2 Main Dam excavation of infilled erosion channel noted shear seam base of vertical rock wall Main Dam Right Abutment plinth -note rock cut slope Main Dam -Rock Wedge along Plinth Foundation -Note infilled joint Main Dam -Quarry and PoHer Tunnel intake excavation Photo Selection Final Geology Report Lower Po\-rer Tunnel and Manifold Book No. 3 3 3 5 5 6 6 6 7 Page No. Photo No. ~76'/) ~4./3A /s; /?23 916/ q 1 4 1 5 1 5 8 9 photos Date 11/18/88 11/14/88 11/17/88 2115/89 2/25/89 3/20/89 10/29/89 3/30/89 4/30/89 Subject Lower Power Tunnel, shotcreting at wye intersection Lower Tunnel Drill & Blast, loading holes Rock bolting shear seam Sta 5+60 LoHer Power Tunnel TBM arrival at tunnel yard TBM Cutting Head in Lower Tunnel Starting Chamber Typical rock bolts & straps power tunnel Water inflow from tunnel face and accumulation of TBM rock cuttings in invert Typical formed steel channel support in arch rock bolted Bad ground Sta 44+60 >·lOod blocking in shear seam behind gripper pad doe5 /Jt:JI-yo /~~ /,1/::;>pe~Ce_s . . -.L-r! :Jce3 ah L-~~ e~c/ oP ~c /u &' --P- 7-//e re?dr~ ;i;-if Portion of East wall ot Powerhouse cushion blasting El 40 -18 South t'lall of Powerhouse El 40 -El 18 Dark color • shear seam tr along the East wall of P.H. Powerhou~e Unit, proof load- ing 1 ~3/8 ~ corrosion resistant anchors at spherical valvf foundation East wal.l. of Pouernouse excavation, Penstocks 1 & 2 Pouerhouse Units 1 & 2 excavation tl 2 winter conditions Lower Tunnel Drill & Bl ast, loading holes lbck bolting shear Se am Sta 5+60 Lower Powe t Tunne l TBH arrival at tunnel yard TBM Cutting Head in Lower Tunnel Starting Chamset tad ground Sta 44+60 wood blook1n<J in ·shear seam behind gripper pAd Typical rock bolts & straps power tunnel Water inflow from tunnel face and accumulation of ~M ~ock cuttings in invert 'i'BH :Ln tunne 1 la i nflo\-1 Typical formed st~ channel 5uppdft in arch rock bolted Drilling in upper pouer tunnel gate shaft Main Dam Foundation IXeavation Looking a~ Right Abutment Winter scene drilling toe pl inth -main dam Main Dam -Toe Pl inth excavation, lower left abutment Main Daa -Right Abutaent Rock wedge adjacent to Plinth foundation Main Dam -Toe Plinth foundation Block C-3, Note thin clay seam Main Dam -Toe Plinth f~dation Block 82 Main Dam excavation of infilled erosion channel noted shear seam base of vertical rock wall Hain Dam Right Abutment plinth -note rock cut slope Dam site area, dam ne~rly ~opped out, shaf t collar & quarry intake -taken from shaft ~i10 ~ hole pad Main Dam -Quarry and Po\·ter Tunnel intake excava~ion