HomeMy WebLinkAboutBlack Bear Lake Penstock Siphon Study Report 1987J-lARZA ENGINEERING COMPANY CONSULTING ENGINEERS
BLACK BEAR LAKE HYDROELECTRIC PROJECT
PENSTOCK SIPHON STUDY REPORT
1 50 SOUTH WACKER DRIVE CHICAGO. ILLINOIS 60606-4288
TEL [31 2) 855-7000 CABLE HARZENG CHICAGO TELEX 25-3540
BLACK BEAR LAKE HYDROELECTRIC PROJECT
PENSTOCK SIPHON STUDY REPORT
1. SCOPE
This report describes a study of a siphon to draw water
from Black Bear Lake for the proposed 3.0 MW hydroelectric
project. This siphon would be used instead of a dam, which
would have raised the lake level to provide storage, and an
intake for water withdrawals. The study includes an estimate of
the project construction cost with the siphon system. The
siphon and upper penstock in this study have been sized for a 3
MW hydro plant, the proposed first stage of a potential 6.0 MW
development of the resource. A profile of the proposed upper
penstock for the siphon concept is shown on Exhibit 1. The size
of the vertical shaft and lower penstock remain as sized in
previous feasibility studies for a 6.0 MW project.
2. DESCRIPTION
2.1. The use of a siphon to draw water from a lower water
source is practical to a depth up to 25 feet. Theoretically,
standard atmospheric pressure (76 em of mercury) could raise
water to a height of 33.9 feet at sea level. At the altitude of
Black Bear Lake (El. 1687 MLLW datum) atmospheric pressure
equals about 31.9 feet of water. However, siphons are consid-
ered to be practical for no more than 75% of atmospheric pres-
sure. The topography of Black Bear Lake and its outlet permits
the use of a siphon to provide the intake of water for a pen-
stock to the hydro plant. This penstock, can be routed in
ground about 10 feet above the existing lake elevation, thus
providing the ability to draw the lake down about 15 feet. An
-1-
BLA
I""J '"' ' ' ~ ,.-~ \
'"'J'
intake on the siphon penstock in the lake would be located about
5 feet below this minimum drawdo~1 elevation to provide submer-
gence to reduce vortex formation and to protect the intake from
damage or clogging by ice. This submergence would also allow a
small margin for error in plant operation to prevent a brake in
the siphon action in the event that operation of the turbine
continues beyond the minimum drawdown elevation. In the design
proposed, if the siphon action does break, it would take over an
hour to reestablish the siphon.
2.2. The proposed siphon system would consist of the fol-
lowing main equipment: two vacuum pumps, electric motor driven,
rated 450 cfm at 22 inches of mercury (equals 25 feet of water)7
vacuum tank1 a seal water supply pump1 and unit heaters for a
small building enclosing the vacuum pump equipment. Piping
would consist of the connections from the penstock to the vacuum
t~.nk, from the tank to the vacuum pumps and. for seal water,
from the lake to the vacuum pumps& Power for operation of the
siphon system equipment would be provided from the powerhouse
via an interconnection line as described in the Feasibility
Report Updateo
2.3. The proposed siphon system would be designed to
start the siphon action at any lake level down to the lowest
designed drawdown level. The vacuum tank and pumps would be
located on the high point of the upper penstock approximately
360 feet downstream from the intake. This point would be about
50 feet downstream of the location of the dam axis shown in the
February 1987 Feasibility Report Update.
-2-
The operating procedure would be as follows:
1. To fill the penstock with water, the turbine
inlet valve and by-pass valve at the powerhouse
would be closed. An air inlet valve on the
vacuum tank would be closed. The intake valve at
the vacuum pump would be opened and the pump
started to evacuate air from the tank and pen-
stock. After the penstock is filled with water,
the vacuum pump intake valve would be closed and
the turbine inlet or powerhouse by-pass valve
opened. With the turbine inlet valve open, the
turbine can be started and siphoning action would
commence.
2. TO dewater the penstock, the turbine would be
shut-down and the by-pass valve opened. The air
inlet valve on the vacuum tank would be opened to
allow air to enter the penstock and water to
drain toward the powerhouse and through the by-
pass. The upstream portion of the penstock would
drain to the lake. Opening the air inlet valve
will break the siphon and will shut-off flow in
the penstock which eliminates the need for an
intake gate or valve at the entrance of the pen-
stock.
2.4. The proposed intake would consist of a cylindrical
trashrack formed by vertical steel bars supported by horizontal,
bars bent into rings, with a horizontal flat circular plate on
top of the cylinder serving as a velocity cap. The cylindrical
intake trashrack would be welded to a miter reducing bend of 90
degrees which would be welded to the steel penstock. The intake
-3-
would be located in Black Bear Lake where the natural water
depth is 30 feet. Soundings of the lake show this depth to be
about 182 feet from the lake shore near the lake's outlet creek.
The discharge required for 3.0 MW of generating capacity is 32
cfs (with net head of approximately 1,300 feet). To obtain an
approach velocity of one foot per second the size of the cylin-
drical intake would be 3'-6• in diameter and 3 feet high. Sixty
3/8 inch thick vertical bars equally spaced on the circumference
of t.he supporting rings would result in openings of 1.824• wide.
The height of the intake with miter reducing bend would be 7
feet above the center line of penstock. With a minimum submer-
gence of 5 feet the maximum drawdown of the lake would be about
15 feet below the present natural lake elevation. The natural
lake is at elevation 1687 and the penstock centerline at the
miter bend would be at approximately El. 1660. This would pro-
vide a lake drawdown to El. 1672.
2.5. In the Feasibility Report Update of February 1987,
the water conduit system for the 6.0 MW alternative consisted of
the following:
a) An upper steel penstock of 48 inch diameter and about
325 feet long,
b) A vertical concrete lined shaft of 48 inch diameter
about 1237 feet deep, and
c) A lower steel penstock of 30 inch diameter about 2,800
feet long.
The computed total head loss for this system is 106.84 feet for
64 cfs and 33.24 feet for 32 cfs. Replacing the dam (as shown
in the feasibility report update) with a siphon will increase
-4-
the upper penstock length by 310 feet~ The increase in length
consists of 128 feet from the dam axis location to the lake bank
and 182 feet from bank into lake at penstock intake. It is
proposed that the upper penstock for the 3.0 MW siphon alterna-
tive be sized to have approximately the same total head loss as
the 6.0 MW alternative (at maximum plant discharge) but without
changing the shaft and lower penstock diameters" On this basis
the diameter of the nearest standard size pipe for the upper
pensi:ock would be 20 incheso The head loss in t.he 20 inch O.Do
upper penstock~ 48 inch I.D. shaft and 30 inch O.Do lower pen-
stock for 32 cfs flow is estimated to be about 76 feeto At
minimum lake Elo 1672 the net head for the plant would be 1335
feet. For future expansion of the plant to 6.0 MW, the upper
penstock would be replaced by a larger pipe, but the shaft and
lower penstock would not require change.
2.6. Approximately 182 feet of pipe would be placed under-
water at the upstream end of the upper penstock. It is proposed
that this pipe be protected by dumping rock fill underwater to a
one foot thickness over the top of the pipe. A layer of rip-rap
would be placed over the rockfill. This protection would pre-
vent damage to the pipe by ice with lake drawdown and possible
erosion of pipe foundation by wave action in the vicinity of the
pipe. During project operation, the lake bed adjacent to the
pipe and its protective material should be inspected when the
lake is drawn down and rockfill/rip-rap placed 'if necessary. In
the event of failure of the power supply or control lines from
the powerhouse to the siphon equipment, an emergency portable
generator could be flown by helicopter to the siphon site.
2.7. The total internal volume of the water conduit sys-
tem, as proposed, equals 30,607 cubic feet. With the 450 CFM
-5-
vacuum pump capacity proposedf the time required to evacuate all
air in the conduit is 68 minutes.
2.8. Black Bear Lake has not been surveyed below its water
surface; therefore, its water volume below the surface is not
known exactly. An estimate of its volume can be made by extra-
polating the reservoir area/volume curves. Extrapolation from
natural snrface at Elo 1687 to El. 1672 gives a volume of 2650
ac.re~·feet. Since there is so1ue uncertainty about the under
wateL topography, it is recommended that a usable storage of
2000 acre-ft be assumed for the 15 feet of drawdown. Based on
reservoir operation studies performed for the 3.0 MW B.W.EL.
1695 alternative (2000 acre-feet of storage) the estimated 3.0
MW siphon intake alternative average annual energy generation
would be about 18,000 MWh.
2.9. The environmental impacts of this alternative include
the following:
a) Shores not previously or naturally exposed will be
exposed.
b) Fish habit will be reduced when the lake is drawn down
during winter. There may also be a drawdown during
late summer in dry years.
c) Lake outflows, by way of the creek, will be eliminated
during drawdown.
d) The distance from the Forest Service cabin to the lake
shore will increase during winter and some late summer
periods.
-6-
3. COST ESTIMATE
Based on the cost estimate for the 3.0 MW H.W.EL. 1695
Stage I alternative presented in the Feasibility Report Update,
the construction cost of the project has been estimated for the
3.0 MW generating plant with the siphon system. This estimated
cost is for the complete power generating plant but without any
transmission lines from its substation. The estimated transmis-
sion line costs for several options of serving load demand cen-
ters are shown in Table III-1 0 on page III-2'7 of the February
1987 Feasibility Report Update. The elimination of the dam and
its replacement by a siphon system, reduces the work required in
the vicinity of Black Bear Lake which reduces mobilization and
logistics costs. Contractor's indirect costs have been revised
for these changes. The changes in quantities for construction
consist of elimination of all dam work, revision of upper pen-
stock steel, excavation, backfill and bedding, underwater place-
ment of pipe and its protection. Quantities for the vertical
shaft, lower penstock, powerhouse, access roads and substation
are unchanged. Costs have been estimated for the siphon system
equipment and a small building to protect this equipment. A
summary of the estimated construction cost is shown in the table
below. A detailed estimate is shown on Exhibit 2.
-7-
Item No.
SUMMARY OF COST ESTIMATE
January 1986 Price Level
Description Estimated Cost
330
331
332
333
334
335
33(~
Land & Land Rights $ 73,000
630,000
7,499,000
641,000
584,000
57,000
560,000
196,000
1,100,000
353
Powerstation & Improvements
Reservoir, Dams & Waterways
Turbine & Generator
Accessory Electrical Equipment
Miscellaneous Mechanical Equipment
Access Road
Substation Equipment & Structures
Mobilization & Logistics
Subtotal Direct Cost
Contingency Allowances Civil 15%
Equip. 10%
Total Direct Cost
Engineering & Administration 17.5%
Total Estimated Construction Cost
-8-
11,340,000
1,480,000
150,000
12,970,000
2,270,000
$15,240,000
DATE MAR 06 1987 HARZA ENGINEERING COMPANY
I3MWSF1284C1 FEASIBILITY ESTIMATE (LFC/RAM D)
PROJECT 3.0 MW. HWL EL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UHIT
UNIT
PRICE
TOTAL
PRICE
------------------------------------------------------------
330.
LAND &
LAND RIGHTS 1 LS 73088.00 73#080
SUBTOTAL.PAGE 73.000
SUBTOTAL -A/C 330. LAHD & LAND RIGHTS 73.000
~ ~ ~~
' ' ,,
~~
~
.,
""" ,:·\
DATE MAR 06 1987 HAR2A EHGIHEERIHG COMPAHY
I3MWSF1284Cl FEASIBILITY ESTIMATE <LFC/RAM D)
PROJECT 3.0 MW. HWL EL 1687, SIPHOH IHTAKE
ITEM DESCRIPTION QUANTITY ·UHIT
330.5
MOBILIZATIOH &
LOGISTICS 1 LS
UHIT
PRICE
lt0000B~a0
------------------------------------------
SUBTOTAL.PAGE 2
SUBTOTAL -A/C 330. S MOB ILI2ATIOH & LOG lSTICS
TOTAL
PRICE
1.1aa.aaa
t.taa.aaa
t,taa,aaa
~ ~t
' "-l'1.:_
~~ ~
n
,.,
DATE MAR B6 1987 HARZA ENGINEERING COMPANY
13MWSF12B4C1 FEASIBILITY ESTIMATE <LFC/RAM D)
PROJECT 3.B MW, HWL EL 1687, SIPHON INTAKE
UNIT TOTAL
ITEM DESCRIPTION QUANTITY UNIT PRICE PRICE
----------------------------------------------------
331.
POWERSTATION &
IMPROVEMENTS
331.1
POWERHOUSE
331.11
DIVERSION &
CARE OF WATER 1 LS 35BBB .• BB 35,BBB
' ~
331. 12
CLEARING. HEAVY 3 AC 1B5e!B.BB :·. 31.500
331. 13
EXCAVATION. TALUS 175B·CY 10.5B 18.375
331. 14
FILL 750 CY 8.80 6,.600
331. 15
SUBSTRUCTURE
CONCRETE 345 •CY 53B.BB .. 182,.850
331. 161
SUPERSTRUCTURE
CONCRETE 65 CY 79B.BB 51.350
331.162 ~ MASONRY 47B SF 2B.50 9,.635
~ 331. 163 ~k INSULATED METAL
PANELS 37BB SF 7.05 26.085 ~~
--------------------------------------------------~~ Ul
SUBTOTAL. PAGE 3 361.395
DATE MAR 06 1987 HARZA ENGINEERING COMPANY ·
I3MWSF1284C1 FEASIBILITY ESTIMATE (LFC/RAM D)
PROJECT 3.0 MW. HWL EL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UNIT
331. 164
ARCHITECTURAL
TREATMENT 1 LS
331. 165
STRUCTURAL STEEL 58a0e:Ls
331. 166
INSULATED METAL
ROOF 3900 SF
331. 167
HVAC & PLUMBING 1 LS
331. 168
MISCELLANEOUS
METALS 2080 LB
331.2
STATION YARD
331.21
FILL 25B CY
331.22
CRUSHED ROCK
SURFACING 60·cy
331.23
CHAIN LINK FENCE &
GATE 160 LF
331.24
CONCRETE
FOUNDATION PADS 28 CY
UNIT
PRICE
55500.00
2.75
6.45
251380.08
2.75
8.88
25.00 :
32.50
548.00
TOTAL
PRICE
55.5B0
137.500
25. 155
25.800
5,500
2.200
1.5013
5,200
10.800
-------------------------------------------------------
SUBTOTAL. PAGE 4 268,355
SUBTOTAL-A/C 331. POWERSTATION & IMPROVEMENTS 629,750
.~,
~ ~~ ~~
' ~~
DATE MAR 06 1987 HARZA ENGINEERING COMPANY
I3MWSF1284Cl FEASIBILITY ESTIMATE <LFC/RAM Dl
PROJECT 3.0 MW. HWL.EL 1687, SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UNIT
332.
RESERVOIRS, DAMS,
& WATERWAYS
332.3
WATERWAYS
332.31
IIHAKE
332.311
CONCRETE -STRUCT.
<BUILDING EQUIPMENT
& FOUNDATIONS) 7 CY
332.312
TRASHRACK & BEND 930 ·LBS
332.313
BUILDING 240·SF
332.314
VACUUM PUMPS.
CONTROLS.
TRANSFORMER. AND
MISC. EQUIPMENT 1 LS
332.315
POWER SUPPLY &
CONTROL LINES 1 LS
332.32
PENSTOCK
332.321
UPPER PENSTOCK
332.3211
EXCAVATION
332.32111
EXCAVATION.
OVERBURDEN 360 CY
UNIT
PRICE
875.00
3.70
55.50
1000130.00
735130.00
13.00 ---------------------------------------------
SUBTOTAL.PAGE 5
TOTAL
PRICE
6.,125
3,441
13.320
100.000
73.500
4.680
201.066
~ ,,
~\ ~ ·~
' IJ~ \ ' \"K
~f\l
DATE MAR 06 1987 HARZA ENGINEERING COMPANY ·
13MWSF1284C1 FEASIBILITY ESTIMATE CLFC/RAM D)
PROJECT 3.0 MW. HWL EL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UNIT
UNIT
PRICE
---------------------------------------------------
332.32112
EXCAVATION. ROCK 400 CY 57.50
332.3212
BACKFILL 690 CY 16.50
332.3213
BEDDING 35·CY 45.50
332.3214
CONCRETE THRUST
BLOCKS & SADDLES 6 CY 1150.00
332.3215
GRAVEL FILL
<FOR PENSTOCK
SUBMERGED PORTION) 300:cy 42.50
332.3216
RIPRAP
(FOR PENSTOCK
SUBMERGED PORTION) 200:cy 62.00
332.322
LOWER PENSTOCK
332.3221
EXCAVATION
332.32211
EXCAVATION.
TALUS 3900 CY 19.00
TOTAL
PRICE
23,000
11.385
1.593
6.900
12.750
12 .. 400
74. 100
-----------------------------------------------------
SUBTOTAL. PAGE 6 142,128
.I)
!"'
~ ~\ S:.. . '
()\~
~' ~I\ ~
DATE MAR 06 1987 HARZA ENGINEERING COMPANY
I3MWSF1284C1 FEASIBILITY ESTIMATE <LFC/RAM D)
PROJECT 3.0 MW. HWL.EL 1687. SIPHON INTAKE
]TEM DESCRIPTION QUANTITY UNIT
UNIT
PRICE
TOTAL
PRICE -----------------------------------------------------------
332.32212
EXCAVATION. ROCK
332.3222
BACKFILL 4100 CY 8.80 36.080
332.3223
BEDDING 1800 CY 25.00 45,000
332.3224
CONCRETE THRUST
BLOCKS & SADDLES 15 CY 985.00 ' 14.775
332.323
PENSTOCK SHAFT
332.3231
EXCAVATION 1240:LF 1350.00 1,674.000
332.3232
CONCRETE LINING 730 CY 1150.00 839.500
332.324
TUNNEL EXCAVATION
& SUPPORT 1660 LF 20130.00 3,320.000
.. 332.325
PENSTOCK STEEL
332.3251
UPPER SITE
POWER CONDUIT 33500 L8 3.05 102.175
---------------------------------------------------------------
SUBTOTAL,PAGE 7 6.031. 530
~\~
~ "-l~
~~ ~f\,
DATE MAR 86 19B7 HARZA ENG.INEERUIG COMPANY
I3MWSF1284Cl FEASIBILITY ESTIMATE CLFC/RAM DJ
PROJECT 3.8 MW. HWL EL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY ;UNIT
UNIT
PRICE
TOTAL
PRICE
-----------------------------------------------------------
332.3253
LOWER SITE
POWER CONDUIT 3628EI8 .. LB 3.85 1,1El4,1EI8
332.326
TAILRACE & STREAM
CHANNEL IMPROVEMENT
332.3261
EXCAVATION. TALUS 1988 CY 1a.sa 19,950
------------------------------------------------
SUBTOTAL,PAGE 8 1.124.asa
SUBTOTAL -I:VC 332. RESERVOIR. DAMS, & WATERWAYS . 7,49B,774
~~ l))~ ,,
' ~f\)
•:""' '"'I
DATE MAR 06 1987 HARZA ENGINEERING COMPANY
I3MWSF1284Cl FEASIBILITY ESTIMATE (LFC/RAM D>
PROJECT 3.8 MW. HWL EL 1687~ SIPHON INTAKE
ITEM DESCRIPTION QUANTITY UNIT
333.
TURBINE &
GENERATOf.!
333.1
TURBINE c.
GOVERNOR
333.2
GENERATOR
SUBTOTAL;PAGE 9
1 EA
1 EA
SUBTOTAL -0/C 333. TURBINE & GENERATOR
UNIT
PRICE
399000.00
253808.08
TOTAL
PRICE
399~000
253,888
641 .. 000
641~088
.;
~~ ·~ ~~
' \ '\.a-
'" l" ~£\)
...()
ll)
co
DATE MAR 06 1987 HARZA ENGINEERING COMPANY ·
I3MWSF1284Cl FEASIBILITY ESTIMATE CLFC/RAM D)
PROJECT 3.0 MW~ HWL EL 1687, SIPHON INTAKE
ITEM DESCRIPTION QUANTITY :uNIT
334.
ACCESSORY
ELECTRICAL
EQUIPMENT
334. I
ACCESS. ELEC. EQPT.
334.2
SUPERV'SRY CONTROLS
334.3
COMMUNICATIONS
I. LS
LS
'LS
UNIT
PRICE
.39B00E1.0EI
125000. EIEI ·
690El0.BB
TOTAL
PRICE
390,EIEIEI
125,EIEI0
69.800
----------------------------------------------------------
SUBTOTAL,PAGE lEI 584,EIEIB
SUBTOTAL-A/C 334. ACCESSORYELECTRICAL EQUIPMENT 584,BBB
~ ~\~ ~~ ~" \ ~~
( '
DATE MAR 06 1987 HARZA EHGINEERIHG COMPANY ·
I3MWSF1284Cl FEASIBILITY ESTIMATE <LFC/RAM D>
PROJECT 3.0 MW. HWL EL 1687, SIPHON INTAKE
ITEM DESCRIPTION QUANTITY:UNIT
335.
MISCELLANEOUS
MECHANICAL
EQUIPMENT
335. 1
POWERHOUSE CRANE
335.2
MISC. EQPT.
1 LS
1 LS
----------------------------------------·
SUBTOTAL.PAGE 11
UHIT
PRICE
48008.013
955B.BB
SUBTOTAL -A/C 335. MISCELLANEOUS MECHANICAL EQUIP~
TOTAL
PRICE
48.888
9,558
57.558
57.558
~ ~~ ·~ ~~ ~f\)
·;')
DRTE MAR 06 1987 HARZA ENGINEERING COMPANY
I3MWSF1284Cl FEASIBILITY ESTIMATE CLFC/RAM D)
PROJECT 3.0 MW, HWL EL 1687. SIPHON INTAKE
ITEM DESCRIPTION QUANTITY:UNIT
336.
ACCESS ROAD 1 LS
SUBTOTRL,PAGE 12
SUBTOTAL -R/C 336. ACCESS ROAD
UNIT
PRICE
560000. 013 .
TOTAL
PRICE
5613.000
560,000
560.0013
N
' .
~\~ ' ~ ~' ~~~
~f\)
DATE MAR 86 19B7 HARZA ENGINEERING COMPANV
I3MWSFI2B4CI FEASIBILITY ESTIMATE <LFC/RAM D)
PROJECT 3.8 MW. HWL EL 1697. SIPHON INTAKE
ITEM DESCRIPTION QUANTITV:UNIT
UNIT
PRICE
TOTAL
PRICE
---------------------------------------------------------------
353.
SUBSTATION
EQUIPt'ENT 8.
STRUCTURES
353.1
TRANSFORtERS
353.2
SWITCHES, BREAKERS,
8. MISCELLANEOUS
SUBTOTAL.PAGC 13
1 EA 68580.08 . 68 .. 588
1 LS 135888.88 . 135 .. 888
195.588
SUBTOTAL -0/C 353. SUBSTATION EQUIP. & STRUCTURES 195.588
GRAHD TOTALS 11.339.,574
.
~~
' ~ ~ ~'
'\ ~f,
~~
0
..0
("()