Loading...
HomeMy WebLinkAboutBlack Bear Creek Potential 1984- - ..... .. - .... }.St%l'-.-Re...-y CusJ:_,·. HYDROPOWER POTENTIAL OF BEAR CREEK FOR HOPE, ALASKA OCTOBER, 1984 Alaska District U.S. Army Corps of Engineers Pouch 898, NPAEN-PL-P Anchorage, Alaska qEPL.; ro, o\TTENTtQN Of: DEPARTMENT OF THE ARMY U.S. ARMY ENGINEER DISTRICT, ALASKA POUCH 898 ANCHORAGE, ALASKA 99506-0898 Plan Formulation Section December 7, 1984 NOTICE OF COMPLETION OF NEGATIVE FEASIBILITY REPORTS FOR HYDROELECTRIC POWER AT FOUR ALASKA LOCATIONS I am announcing completion of reports on potential hydroelectric power generating facilities at four Alaska locations: Anaktuvuk Pass, Kaktovik, Hope, and Seldovia. In all cases, after careful investigation and evaluation, I found that Federal development of the facilities is not feasible at this time. All of these potential projects would require supplementation with other sources of electricity during the winter, when flows of Alaskan streams dwindle and when demand for electrical power is greatest. The four locations were studied pursuant to a resolution of the U.S. Senate Committee on Public Works dated October 1, 1976, directing the Corps of Engineers to determine the feasibility of installing small hydroelectric plants in isolated Alaskan communities. The studies evaluated future needs for electrical power at each of the sites and alternatives available to meet those needs. While the Corps had primary responsibility for conducting the studies, numerous other Federal, State, and local agencies and groups contributed. A public involvement program was maintained. All sites were identified in regional reconnaissance studies performed by engineering firms under contract. The Corps conducted followup field investigations. Each location is briefly described below. Anaktuvuk Pass: This community is in a mountain valley in the central Brooks Range above the Arctic Circle, 250 miles north-northwest of Fairbanks. The present diesel facilities for electrical generation are 01-med and operated by the North Slope Borough. The optimum project was found to be a run-of-river system on Inukpasugruk Creek with a 22-foot-high rockfill dam and 3,250 feet of steel penstock. Its single turbine would have a total capacity of 200 kilowatts (kW). The creek would have sufficient streamflow to produce power during about 4 months of the year. The project I'Jould cost about $6 million and would have a benefit-cost ratio of 0.3 to 1. (A ratio of greater than 1 to 1 is required to • • meet Federal economic evaluation criteria.) The total cost of using this hydroelectric project in conjunction with the town diesel system exceeds the cost of continuing to generate·power with the diesel system alone. Kaktovik: This village is located on Barter Island in the Beaufort Sea just off the north coast of Alaska. The island is separated from the coast by a narrow 1 a goon. A hydropower reconnaissance study using existing topographic maps of northeastern Alaska found that a site on the Okpilak river near Kaktovik might be marginally feasible. Corps field investigation determined that this site is founded on an alluvial deposit and the stream bank provides no suitable dam or diversion site. The stream gradient is gradual, approximately 25-40 feet per mile; thus an extremely long penstock would be required. Due to the long winter season, sufficent streamflow to produce power would be available only 4 months of the year. Study of the site was terminated because of lack of technical feasibility for hydropower development. Hope: Hope is situated in Southcentral Alaska, on the south side of Turnagain Arm about 25 air miles south of Anchorage. The community currently receives single phase power produced by gas turbines from Chugach Electric Association (CEA), which operates a 1 arge network that serves Anchorage and other towns in the area. Tying the proposed hydropower plant into the existing CEA grid was found to be more economical than using its output only for the communities along the Hope feeder line, since the plant could not meet the full feeder line demand in winter. Three dam sites on Bear Creek near Hope were considered. The lowest one would be optimum, due to considerably higher penstock and road improvement costs for the upper sites. The run-of-river project evaluated for this site would include a gabion diversion structure 6 feet high and a polyethylene penstock 1,640 feet long. Six plant sizes were considered; the one selected would have two turbines with a total capacity of 150 kW. The project would cost about $1.5 million and would have a benefit-cost ratio of 0.3 to l. The costs would exceed the benefits by $97,000 per year. Seldovia: Seldovia is located on the west coast of the Kenai Peninsula, 16 miles southwest across Kachemak Bay from Homer. Electrical power is currently supplied to Seldovia by Homer Electric Association (HEA), which purchases the power from CEA. A project site on Windy River was selected. The run-of-river project analyzed for this site would have a rockfilled bin diversion structure 8 to 10 feet high and 3,420 feet of penstock, part polyethylene and part steel. The single turbine would have a capacity of 590 kW. Failure of the transmission line from Homer causes frequent power outages, especially in winter; the community then uses d i ese 1 generators provided by HEA. Some of these power losses may be avoided with a hydropower project, although low stream flows during the winter would limit potential hydropower production available from the Windy River. The project would cost 2 about $5.2 million and would have a benefit-cost ratio of 0.6 to 1. It is not economically feasible for Federal construction at this time. Please pass this information on to others interested in these reports who may not have received this notice. Further information on any of the above studies may be from my office or from Mr. Carl Borash, Chief of Formulation Section, Post Office Box 898, Anchorage, 99506-0898. The telephone number is (90 75 2632. Saling Colonel, Corps of Engineers District Engineer 3 obtained my Plan Alaska ()) c: ·-.L... Q) lb' V:>(b ~ CD ~ 0 ~ FOUR LOCATIONS INVESTIGATED FOR HYDROELECTRIC POWER 0ECEr18ER 1984 pac\~\c eAnaktuvuk Miles I Pass I I F-==. =L --· --. --q 0 200 400 1 l HYDROPOWER POTENTIAL OF BEAR CREEK FOR HOPE, ALASKA SUMMARY The Alaska District, U.S. Army Corps of Engineers, investigated the hydropower potential for Hope, Alaska. Those sites along Bear Creek near Hope were studied, and one site was selected for further evaluation. A run-of- river project evaluated for this site would feature two turbines with a total capacity of 150 kilowatts. Due to low winter streamflows, the project could not produce a dependable capacity year-round. An annual average of 767,000 kilowatt-hours (kWh) could be fed into the Chugach Electric Association feeder line serving the Hope area. The project would cost about $1.5 million, or $141,000 annually, and would provide about $44,000 of benefits each year. The costs exceed the benefits by $97,000 per year. PERTINENT DATA SHEET General Data Project Installed Capacity (kW) Number of Units Diversion Height (ft.) Penstock Type Penstock Length (ft.) Penstock Diameter (in.) Allowable Penstock Pressure (psi) Transmission Line Length (miles) Access Road Length (miles) Gross Head {ft.) Design Net Head (ft.) 150 2 6 High Density Polyethylene 1,640 18 125 1 1.3 210 195 Average Annual Energy (MWh) Average Annual Usable Energy (MWh) 767 767 Economic Data (50 Years, 8-3/8 Percent Interest, 1984 Prices) Project First Cost Investment Cost Annual Cost Annual Benefits Annual Net Benefits Benefit-Cost Ratio ~ l ,449,000 $ 1,538,000 s 141,000 s 44,000 s -97,000 0.31 CONTENTS Introduction Study Area Historic and Projected Energy Use Site Information Site Inspections Site Description Land Ownership Water Use and Hydrology Mineral Claims Environmental Design Considerations Layout of Facilities Diversion/Intake Structures Penstocks Powerhouse Layout Generation Facilities Access Transmission Energy Analysis and Plant Selection Energy Potential of Bear Creek Selected Damsite Selected Plan Economics Benefit Analysis Cost Analysis Evaluation Conclusions and Recommendations Page 1 1 4 5 5 5 8 8 9 10 11 11 11 11 15 15 16 16 18 18 19 20 21 21 22 26 26 Figure No. 1 2 3 4 5 6 7 8 Table No. l 2 3 LIST OF FIGURES Title Page Location and Vicinity Maps 2 Projected Energy Demand, CEA Hope Feeder Line 6 Peak Discharge Frequency, Bear Creek 9 Facilities Layout 12 Diversion and Intake (Typical) 13 Alternative Diversion and Intake 14 Net Benefits 19 Energy Demand versus Energy Potential, Damsite 3 20 LIST OF TABLES Bear Creek Average Monthly Flows Summary of Damsi te Options Summary of Project Features (Damsite 3) 8 18 20 HYDROPOWER POTENTIAL OF BEARCREEK FOR HOPE, ALASKA OCTOBER, 1984 INTRODUCTION The evaluation of small hydroelectric systems was authorized by a 1 October 1976 United States Senate Public Works Committee Resolution which directed the U.S. Army Corps of Engineers to determine the feasibility of installing small prepackaged hydroelectric units in isolated Alaska communities. In 1982, a regional inventory for small hydropower projects in Southcentral Alaska was completed. This inventory analyzed more than 30 sites, recommending nearly 20 for more detailed examination, including the Bear Creek site near Hope. The Bear Creek site was one of six selected by the Alaska District from this group for field reconnaissance and additional analysis. STUDY AREA Location. Hope is situated iC the southcentral region of Alaska, on the south side of Turnagain Arm at 60 55' 15 11 N. latitude, 149° 38' 30" W. longitude. It is about 25 air miles south of Anchorage, and nearly 60 air miles northeast of Kenai. The community of Hope is located in the general area of the mouth of Resurrection Creek. The community of Sunrise is located about 9 miles from Hope on the Hope Highway. Homes and cottages are scattered along the Hope Highway. In addition to dwellings and some small businesses a State Department of Transportation shop is located at Silvertlp, near the junction of the Hope and Seward Highways. Public Services. A summary of the various public services in Hope is provided below. Government. Hope, which is the largest community along the Hope Highway and serves as a center, is classified as an unincorporated community, with no formal structure of government overseeing the affairs of the area. All responsibilities for planning, zoning, area education, providing other public services, etc., are maintained by the Kenai Peninsula Borough. Input into the borough's planning process for Hope is provided from members of the Hope Community Council. - 1 - Q ~ 'l. cr .. . -:.2- Police Protection. Police protection for the community is provided by the Alaska State Troopers stationed in Girdwood. Troopers visit the area frequently, as the access road to the community is part of the state highway system. Health Facilities. There are no health facilities available in Hope. Most medical treatment needed by local residents is obtained from health facilities in Anchorage. Emergency cases can be evacuated by air to hospitals in Anchorage. Education Facilities. Education in Hope is provided for students in grades K-12. The local school currently consists of a one-room schoolhouse. However, a considerably larger two-room school is expected to be started by 1985. Enrollment at the school has fluctuated only slightly, ranging from about 15 to 20 in recent years. Transportation. Hope is accessible to Anchorage and Kenai Peninsula communities by means of the Hope Highway, which connects to the Seward Highway. It requires approximately 2.5 hours to travel the roughly 90 road miles between Anchorage and Hope. In 1980 and 1981 general road improvement upgraded the 18 miles of highway from the Silvertip turnoff to Hope and extended road access to about 20 picnic and camp sites in the area. A small runway about one mile from Hope can accommodate light aircraft; however, no regularly scheduled air service is available to the community. Boat traffic in the Hope area is limited and dangerous due to mud flats and extreme tidal action in Turnagain Arm. The Resurrection Trail is well known by hikers as a 30-mile trail from Hope to Cooper Landing on the Sterling Highway. Human Resources Demographic Data. The population in the Hope area has fluctuated fairly widely over the years, as evidenced from decennial population counts by the Census Bureau. The lowest recorded count was in 1930, when 15 persons were reported. The 1980 count of 103 was the highest. Local estimates indicate a 1983 population of 120. Population fluctuation in past years was mostly attributed to the availability of mining jobs in the area. In recent years the community has attracted people seeking a more relaxed, rural type lifestyle. The table on the following page indicates 1920 to 1980 census counts taken in Hope. Year 1920 1930 1940 1950 1960 1970 1980 U.S. Census Population Counts Hope, Alaska 1920-1980 Population Percentage Change 44 15 71 63 44 51 103 -3- -65.9% +373.3 -11.3 -30.2 +15.9 +1 02.0 The 1980 census statistics show that 91 percent of the population in Hope were white, 3 percent were Alaska Natives, 3 percent were Asian and Pacific Islanders, and 3 percent were classified as "other". Em lo ment. The economy of · Hope is based mainly on the recreationa tourist trade of fishermen, hikers, backpackers, campers, and placer gold miners. A cafe, a small store, a bar, a sawmill, a log cabin kit manufacturing plant, and three campgrounds are located in Hope/Sunrise. Several Anchorage residents maintain recreational cabins in the area. Most residents travel to Anchorage or Seward to shop, to purchase fuel, and to obtain supplies. Virtually all area businesses are owner operated and create essentially no additional employment. Because of the area's remoteness and long term objective to maintain a quiet rural type of lifestyle, no significant business growth is anticipated in the near future. Future Development. In recent years (1980-81} the highway development program for the Kenai Peninsula has provided improved and maintained year- round access to the community of Hope. The general area has a strong attraction for summer tourists, hikers, miners, and campers. Some increase in the lumber industry can be expected to satisfy the area demand for precut log homes and cabins. Community leaders generally support the claim that tourism and summer recreation will continue to be the main attraction in the foreseeable future. HISTORIC AND PROJECTED ENERGY USE Hope currently receives single phase power from Chugach Electic Association (CEA) produced by gas turbines. Energy costs to the consumer vary between 8 and 10 cents per kilowatt-hour (kWh) depending on the quantity used and the area served. These rates (January 1984} were implemented following a 1983 Alaska Public Utilities Commission directive to equalize rates throughout the southcentral region. This rate may not reflect the actual cost of serving long distance and small consumers. According to CEA, about 90 percent of the energy sales in Hope were for residences and 10 percent were for small commercial ventures. There are about 60 active electric meters in Hope, of which 51 are residential. About 15 residences have small privately owned standby gasoline generators of the 2-to 5-kilowatt size. A sawmill and adjacent log home are powered by their own 250 kW three-phase diesel generator and are not connected to CEA lines. There are an estimated 10 additional buildings in Hope that are not presently being served by CEA. During 198.3, 976 MWh of energy passed through the Hope substation. Line losses accounted for 5 percent or 49 MWh; Hope used 63 percent or 615 MWh; Sunrise used .30 percent or 29.3 MWh; and the State highway maintenance shop used 2 percent or 19 M Wh • A 50-kW standby diesel generator is maintained at Hope by CEA to provide power should service be interrupted. In recent years outages have been avoided by a combination of tree management along the feeder line and unusually mild winters. -4- Most dwellings in Hope and Sunrise are heated with either wood or oil. There may be some use of liquefied natural gas for space heating as well as cooking. No use of waste heat is known. Gasoline for autos, recreational vehicles, and machinery is stored in personal bulk tanks because the nearest gas station is 2.5 miles away. There are no known wind generation systems in town. Increased energy demand by current users, and demand by new homes and existing homes not currently using CEA service, have been considered in the three future demand scenarios shown in figure 2. The medium case represents the projected electrical energy demand assumed most likely to occur, and yields an annual equivalent demand for the project life (1990-2040) of 1,1.50 MWh. The energy demand forecast is based on the demand trend in recent years, with consideration given to the population trend and factors governing the economic growth. CEA has forecasted area-wide growth of energy demand but has not given particular attention to Hope, realizing that its growth would be negligible in relation to the large growth expected in much larger communities, especially Anchorage. Construction of a hydroelectric project at Hope would not be expected to alter this projection unless the project substantially lowered costs to local power consumers. The monthly distribution of energy demand is expected to remain essentially unchanged. The expected increased demand attributed to new connections by new weekend cabins and possible new demand by the existing sawmill, which currently produces its own power, may tend to increase the usage during the warmer months. This increased demand during the warmer season is not expected to significantly offset expected increased demand by year-round residences owned by persons employed in support services and businesses. Year-round residents would tend to use much more electricity during the winter months than would typical residents during the summer months. SITE INFORMATION Site Inspections The Bear Creek site has been visited by interdisciplinary study teams from the Alaska District on the following occasions: 31 August 1982 31 August 1983 (semipermanent stream gage installed) 17 October 1983 On 27 April 1984, a team composed of Alaska District and S &: S Engineers, Inc., personnel visited the site and serviced the stream gage installation. Site Description The uppermost diversion site (at about 1,350 feet elevation) is 8,250 feet upstream of the railroad cars used as a reference datum. The railroad cars are 4,155 feet upstream of the paved Hope Highway and approximately one mile east of Hope and are accessible by a 12-foot wide gravel road. Estimated head -5- /C.: SO 47*::;/NTH' 466L//VPT/0/(/ ------_ (#/G# 730-+--------~---------r--------~--------~--------~------~ FIGURE 2 PROJECTED ENERGY DEMAND, CEA HOPE FEEDER LINE -6- (as measured on the 29-31 August &3 field trip) is approximately 700 feet above the powerhouse site, or 740 feet above the railroad cars. Graywacke bedrock outcrops flank each side of the stream. Ledgerock is estimated 2 to 4 feet below creekbed gravels. Although moderately fractured, these abutments could support a structure of sufficient size for this project. Some remedial treatment for lateral seepage control would be required. Rock is available on or near the site, salvaged from sorted piles of boulders removed from earlier placer mining operations. The potential diversion sites are narrow. Full crest overflow spillways would therefore be practical. Sediment and ice would be important considerations for all sites if year-round operation is expected. A second diversion site is located 1,250 feet downstream of the first (7 ,000 feet above the railroad cars). Estimated head lost between these sites is about 120 feet (stream gradient about 10% overall). This site is again between graywacke abutments, nearly vertical for about 25 to 40 feet. A large avalanche runout zone would be crossed by development of either of the above sites. This zone extends from between 2,900 and 3,400 feet above the railroad cars. Vegetation is primarily grasses with small stands of alder and intermittent young (less than 5-foot) trees. At the downstream side of this avalanche zone a third potential diversion site exists. This site is approximately 2,700 feet above the railroad cars, with an estimated 250-foot head difference (21 0 feet to the powerhouse site). A good road leads to this point. Rock (hard, brittle,massive graywacke with moderate fractures) abutments are about 25 feet apart at water level, 35 feet apart 5 feet above the water, and 50 feet wide 15 feet above the water. A debris dam at this point traps an estimated 5 feet of sediment. There is one small (50-foot-wide) avalanche chute below this site. It is revegetated and contains a number of spruce trees which appear to be approximately seven years old. For the most part the access (century-old wagon) trail up the right bank has a revegetated cut bank. Possible placement of the penstock beneath this bank would afford a substantial degree of protection from avalanche potential. There is no undercut bank in the large runout zone noted previous! y. Complete burial of the pipe would probably be required at this point, since a roadbed must also be prepared in lieu of the footpath. The remainder of the trail could be upgraded to serve as an access road and a penstock corridor. The first 1/2 mile above the railroad cars is essentially a 12-foot travel surface, except in a short reach where placer operations have encroached. The remainder is an overgrown trail of between 3 and 6 feet in travel width. Grade is essentially gradual (about 10%) with three short locations with grades of between 15 and 25 percent. The moderate cover of spruce, birch, and alder trees would require clearing to widen the access trail. All tributaries to Bear Creek are small enough to be crossed with culverts. No major structures would be required for construction access. -7- Land Ownership The entire project would be located within Chugach National Forest boundaries and existing right-of-way and electrical easements. A Special Use Permit from the U.S. Forest Service would be required to construct and maintain a hydropower project. Water Use and Hydrology Records obtained from the State of Alaska's Department of Natural Resources (DNR) indicate that there are currently five permits to appropriate water from Bear Creek. Of these, only two are upstream of the powerhouse and might therefore affect project feasibility. One permit is for 6 cfs, 365 days/yr, for hydropower generation, and would be diverted within NW}f. SW}f. Section 1, which is the vicinity of the upper damsite. The other permit is for 1.3 cfs, April through December, for placer gold mining operations, and would be diverted within SW~ NW~ Section 35, T ION, R2W, S.M., which is probably downstream of, but could be just upstream of, the powerhouse. The remaining four permits amount to 0.6 cfs and would not affect project feasibility since the water used for the Bear Creek hydropower project would be returned to the creek and would still be available to the permit holders. Monthly flows averaged over the period of record are listed in table 1 for each of the damsites. The data indicates that no flow at all may be available to the Bear Creek project during some months since the existing water rights upstream are in excess of the flow available. If the permit holder of 6 cfs does not construct a hydropower plant by 1988 the permit will expire. A transfer of rights is possible, with approval from the DNR, but under no circumstances could the rights be sold. Figure 3 shows peak discharge frequencies for the three sites. TABLE 1 BEAR CREEK AVERAGE MONTHLY FLOWS, cfs Damsite 111 Damsite 112 Damsite 113 JAN 2.4 2.5 3.1 FEB 2.1 2.2 2.7 MAR 1.8 1.8 2.3 APR 2.0 2.1 2.6 MAY 8.3 8.6 10.8 JUN 19.3 20.1 25.0 JUL 17.8 18.6 23.3 AUG 9.9 10.4 13.0 SEP 7.6 8.0 10.0 OCT 7.9 8.3 10.4 NOV 4.7 4.9 6.1 DEC 3.1 3.3 4.0 -8- ~ \j ~ ~ ~ ~ ~ ~ Ettr'I~;..(/G""6 /NTE?t"'Y~ /..(/ ~ ~ 1t:1 J/IP "1!1 Fe' .!It:?~ N J!t? /If? S" Z" / l/&10 ~ ?t'd I rid .4fl/l? ....., ..., Z!III:J A:» 90 $) ?'c:::' ~ u ~~ I ~ ~ &??' ~ / "A ~-~· / .,. tf"t? ,d(7 4d .5ld ~~ .. ~ D / v I ftl l ! L I 2f::7 z ~ /If' ;NJ ..::1 ~ .. i::t' ~ 10 c-..r-~..:~6' /JICI'l'"<ID!'YA'&-y..-.,~4 .D"A'!J#"#AI"IIF.G A'A"~=-a. 4 :!JitpN/.-.:1"/TL """· / r'"VP.P~.) ---·-.Q)f,AI'/,1(/'.#cpG _,_.,.,q., _,.,., .::1y1N/.-6'17£ ~-2 R'.I'P#M-?<!?EAI"A"E-4: .S:// ...:T¢$.-~/rEA/d . ..3" {L.OW£/f") ----- FIGURE ! , PEAK DISCHARGE FREQUENCY, BEAR CREEK Mineral Claims Active mining claims along Bear Creek extend from Hope Road upstream to beyond the upper damsite and encompass all land adjacent to the channel. Claims are typically 1,320 ft. in the direction of the creek and 660 ft. across. Uplands are also being mined, the extent of which varies from 800 to 2,000 ft. left of the creek and from 300 to 1,000 ft. right of the creek. The miners are entitled to all subsurface rights as long as they adhere to Federal and State mining laws and perform and record the annual assessment work. The surface rights, however, are retained by the public and are administered by the Federal Government. -9- Environmental Bear Creek, 5 miles long, runs from the mountains above Hope to tidewater at Turnagain Arm •. Its width varies between 10 and 20 feet. Most of the vegetation along the creek at the proposed diversion sites can be classified as subalpine shrub and herbaceous. Alder thickets lie close to the creek throughout its course. Below approximately 1,300 feet mean sea level (msl), large stands of cottonwood, birch, and hemlock join alder in lining the stream. The powerhouse area and penstock routes are in coastal spruce- hemlock forest. The creekbed is composed mainly of gravel and cobble, with coarse sand filling the interstices. Years of heavy placer mining operations have altered the stream, even changing its channel. These operations continue at present. In some locations sediment has been deposited 6 feet deep, causing diversion of the stream in summer. This diversion encroaches on private property and some small parcels of agricultural land. Other impacts of placer mining include reduction of the fishery resource and degradation of water quality. The upper portion of Bear Creek flows year-round; however, the lower part ceases to flow on the surface in winter. A field investigator recently found the lower portion of the creek, from the mouth to 0.2 river-miles upstream, to be completely dewatered with the gravel streambed exposed. Streamflow upstream of this stretch indicated subterranean flow. This dry surface condition occurs primarily during November through April. Lower reaches of the creek, below the powerhouse location, are choked by sand and gravel, causing the water to overflow its banks and braid before flowing into the tidal flats. The Alaska Department of Fish and Game (ADF&G) considers Bear Creek important for the migration, spawning, or rearing of anadromous fish, tagging it State Anadromous Fish Stream No. 274-60-10160. ADF&G surveys report that Bear Creek supports pink and coho salmon and Dolly Varden throughout its length. However, adult pink salmon were collected only in the tidal flats near the clogged stream channels leading to the creek's mouth. Wildlife signs along the creek are not abundant. Bear tracks were observed, but they were limited to the tidal flats and the footpaths leading to the potential diversion sites. Bear droppings were observed once in the upper part of the study area. Moose seats and tracks were found in the upper part of the area, but little evidence of winter browsing was seen. Both moose and bear have been heavily hunted in the area; mountain goat and Dall sheep are no longer commonly found. Small mammal use of the creekside appears limited. Major environmental impacts would not be expected to result from construction of a diversion structure, a penstock, a powerhouse, or a transmission line at the Corps of Engineers' preferred sites, since the area is already heavily impacted by placer mining operations. To minimize disturbance to fish and wildlife, erosion control, revegetation, and construction timing measures would be warranted. -10- DESIGN CONSIDERATIONS Layout of Facilities Three potential sites have been investigated. All three would be run- of-river facilities, with gross head varying from 700 to 210 feet. All sites have feasible penstock routes which could be combined with access roads. The relationship of the facilities is shown in figure 4. The powerhouse site would be in the floodplain approximately at the end of the existing gravel service road. Diversion/Intake Structures Structures at all three sites would be gabion diversion structures. The broad base of this type of gabion structure, along with the gabion's inherent combination of flexibility and stability, would provide good protection against ice forces (see figure 5). Manhole-type intakes would be set with intake levels approximately one to two feet below the dam height. Trashrack covers for the intakes would be installed to prevent clogging by debris; additionally, by keeping the intake elevations sufficiently below the dam, most debris would stay on the surface and be carried past the intake. A maximum dam height of approximately 6 feet would be required for the largest penstock and was assumed in all cases. Frazil ice conditions should be further investigated if the project progresses to the design stage. At the lowest site (site 3), due to the potential for frazil ice and debris, an infiltration gallery and low concrete dam (see figure 6) were considered. The hydraulics of this installation, however, indicated that a gallery the full width of the stream and at least 200 feet long would be required to provide the range of penstock flows assumed at this site. The steep natural gradient and massive bedrock at this site produced excessive excavation costs for the gallery installation, and it was deleted from further consideration. Penstocks In all cases, penstock routes would closely parallel the creek, taking advantage of the topography to maintain moderate slopes in the upper reaches. Penstock lengths would be approximately 7,150 feet, 5,900 feet, and 1,640 feet for sites 1, 2, and 3 respectively. A short portion (approximately 200 feet) of the penstock for site 2 would require significant side-hill benching, and probably rock-bolting; the remainder of that route as well as the other sites could take advantage of natural benches on moderate side slopes. The site 2 penstock would also require the greatest amount of new access construction. This penstock would intersect the existing trail approximately 1,200 feet downstream from the damsite. High density polyethylene pipe is considerably cheaper than steel pipe, but does not exhibit the same strength characteristics. Polyethylene pipe with -11 - -12- FIGURE 4 FACILITIES LAYOUT BEAR CREEK HYDROPOWF~ PROJECT ~00 I 0 MANHOLE INTAKE RIPRAP PROFILE GABIONS . . . i:, · 3' x IO'x 12' (TYP.} y A./OT£: O'V.t!ft? A".:: c:. .P'//"9'~­ ..:5/ .::J/\/4 V -4 .RJ/ BET~ecA/ .:'r.rTE:S~ PERSPECTIVE VIEW (RIPRAP NOT SHOWN) -13- FIGURE !5 DIVERSION AND INTAKE (TYPICAL) BEAR CREEK HYDROPOWER PR OJ EC T N. T. S. A • PLAN VIEW ~/' J/£,A:/T t?~A'VE.C. /AIF/£:7"~/P...V , ' 'A'T.e-v.A'..:.r.e cv#.t:.~ER.Y 1 . LJ'A'I'~.</E;(' R</EL.tt. $C ...eE.a/ P//i!£; 6 tP /.1?}' /S"'.5T.C. C~.!!"C/c:::'..f' P/...OE GALLERY SECTION A-A FIGURE 6 ALTERNATIVE DIVERSION a INTAKE DAMSITE SECTION 8-8 HYDROPOWER PROJECT N.T.S. -H- inside diameters of 32" and 12" can withstand 80 and 160 pounds per square inch (psi), respectively, whereas the same sized 1/4" steel pipe can withstand about 225 and 600 psi, respectively. Polyethylene pipe could be used for the damsite 3 option and would be 40 to 50 percent cheaper than comparable steel pipe. Pipe pressures for the upper damsite options require the use of steel pipe. Partial use of polyethylene pipe (in the upper reaches where pressures are low) was considered, but savings amounted to only about 5% of total penstock costs. Powerhouse Layout The powerhouse would be a conventional indoor plant with the substructure constructed of reinforced concrete and the aboveground housing being a pre-engineered 40' x 30' x 20' metal building. Natural foundation materials at the site are sand, gravel, and cobbles. The powerhouse would contain the turbine, generating unit, controls, governors, and switchgear. Control facilities would be for an unmanned plant, and protective devices would operate automatically to protect the equipment. Generation Facilities Generation would be by Pelton-type turbines, driving single phase (10), 60 Hz, 480 V, 0.8 power factor synchronous generators. Drip proof housing would be provided. The generator would be open ventilated with an 80°C rise, Class B insulation and no provisions for overload. The generator would have full runaway speed capability. Excitation systems would be in accordance with manufacturer's standards. Power Transformer. One 480 V/14.4 kVA 10 transformer, OA class with minimum non-premium impedance would be provided. All necessary terminations, switchgear, and protective devices would also be provided. Load Controller. The size of the jets and thus the power output of the turbines would be controlled by a needle in the center of the needle nozzles and needle tips. The movement of the needle would be controlled by the governor. A jet deflector would be located just outside the nozzle tlp to deflect the jet from the buckets to effect sudden load reductions. Generator Voltage System. The connection between the generators and breakers would be with cable. The generator and station service breakers would be metal enclosed drawout type rated 600 V, with 1600 amp frames. The breakers would be combined in a common switchgear lineup along with generator surge protection and instrument transformers. Unit Control and Protective Equipment. Unit controls would consist of manual startup and shutdown circuits, basic protective relays, and basic instrumentation. Protective relays for each unit would include generator differential, overspeed, overvoltage, and ground overcurrent. Instrumentation for each unit would include a voltmeter, an ammeter, a wattmeter, and a watthour meter. The controls would be contained in a single cabinet. No annunciation or station battery would be provided. -15- Station Service. The station service power would be obtained via a tap between the generator breaker and the main power transformer. The station service distribution panel would be adjacent to the generator switchgear lineup. Station service power distribution would be at 480 volts, single phase transformed to 120 volts single phase power. Standby diesel generation (approximately 25 kW) sufficient to supply station power needs would be provided. Access From the Hope Highway to the powerhouse site, the project area is accessible by a one-mile gravel service road that would require only minor up- grading. For approximately 1/2-mile above this area, the access consists essentially of a 12-foot travel surface, except in a short reach where placer operations have encroached. The remainder of the existing access is an overgrown trail of between 3 and 6 feet in travel width. Grade on most of this trail is approximately 10%, with three short locations with grades between ' ')-'6 and 25%. No blasting is anticipated along the final access route. li1 all cases the access road and penstock route would be combined, with the penstock being protected as much as possible under the toe of the cutbank. This would preclude the need for clearing and grading two separate rights-of- way, and also provide an additional measure of protection for the penstock without restoring to full burial. Four major avalanche chutes are present within the project area. Progressing upstream, they are located as follows. The first is just downstream of site 3. It would probably not have a significant impact on a site 3 penstock, but would effect both sites 1 and 2. The second is between sites 2 and 3, and is just up-slope from the point at which the existing cat trail crosses the stream. It is at this point that a new access route would need to diverge from the cat trail and follow another, older existing trail further uphill. The third chute is located between sites 2 and 3. This chute is extremely large and goes all the way across the stream. It would have significant impact on the penstock routes for sites 1 and 2. The fourth chute, which is also quite large, is just upstream from site 2, and would impact the site 1 penstock. TRANSMISSION Hope currently receives power from Chugach Electric Association (CEA) via a 14.4 kV single phase (10), 2 wire (2W) distribution line which originates at the three phase (30) transmission line from Anchorage. The single phase substation is 21 miles from the proposed Bear Creek powerhouse site. CEA does not anticipate a need for 30 power in Hope. Electricity is normally generated and transmitted as three phase power; however, single phase systems are the rule for supplying electricity to residences and other small consumers. If power was generated at Bear Creek by a conventional three phase generator, single phase power could be delivered to the Hope customers (and excess back-fed into the CEA grid) by one of two methods: -16- Option 1 -Transmit all power produced at Bear Creek as 30. This would require construction of 1 mile of all new 30 line and the upgrading of 20 miles of existing 10 line to 30. The 10 transformer at the existing 10 substation would have to be replaced with a 30 transformer. Switching gear would also be provided. The cost of this option would be about ~4,750,000. Option 2 -Dead-end two phases at Bear Creak and tie the remaining phase into the existing 10 line. This option would only cost about S 17 5,000, since only one mile of new 10 line and switching gear would be required. However, dead-ending two phases would result in the loss of about 4296 of the total power produced and associated project benefits. It would also cause an imbalance in the 30 system which could ultimately lead to mechanical failure. Provisions for dummy loads would reduce the potential for failure. An additional option is available and would eliminate both the high transmission cost and excessive power losses. Option 3 -Generate power at Bear Creek with a 10 generator. Single phase generators with ratings higher than 50 kVA are not readily available but could be built to specifications. The additional cost associated with using a 10 generator over a 30 generator becomes more pronounced as plant size increases but would not significantly affect total project costs. The additional expense is also justified when considering that it would displace extremely high transmission line costs, as well as provide maximum project benefits. Transmission line costs associated with this option would be about the same as for option 2, $17 5,000. This option is the most economical and therefore assumed in subsequent analyses. Two alternatives for the distribution of power produced at Bear Creek were investigated. The first assumed that the power would be fed into the existing CEA grid system, and the second assumed that only the communities along the Hope Feeder Line would utilize the power. The first alternative would allow all energy produced at Bear Creek to be marketable. Marketable energy for the second alternative would be the lesser of energy produced and energy simultaneously demanded. Benefits associated with the second alternative would therefore be significantly lower than those associated with the first. Costs would be about the same; switching gear would vary slightly. lt is obvious that the first alternative yields the greatest net benefits, and the second is therefore excluded from further consideration. Transmission voltage for the new 1 f/J line would be 14.4 kV 1 f/J 2W. Fuse- type disconnects would be provided on all three sides of the intertie point. -17 - ENERGY ANALYSIS AND PLANT SELECTION Energy Potential of Bear Creek For each of the three dam sites considered, a wide range of installed capacities was evaluated. The program HYDUR was used to estimate the average annual output for each plant, based on physical constraints of the assumed turbine and the flow characteristics of Bear Creek. Table 2 summarizes the project features and energy potential associated with each dam site. TABLE 2 Summary of Damsite Options Installed Penstock Gross Avg. Annual Damsite Capacity Length Diameter Head Output No. (kW) (ft.) (in.) (ft.) (MWh) 200 12 1,317 to 7,150 to 700 to 1,000 26 2,296 2 200 14 1,271 to 5,900 to 580 to 1,000 28 2,034 3 75 14 519 to 1,640 to 210 to 500 32 720 -18- Selected Damsi te The National Economic Development (NED) Plan provides the basis for evaluating the options available. Benefits and costs were developed for each of the damsites and corresponding plant sizes, as outlined in the section on Economics. That plant which shows maximum net benefits would be the selected, or optimum, plant. Even though the upper two damsites have the potential to provide about twice as much power as does the lower site, net benefits were consistently higher for the lower site options; all were negative. Maximum net benefits for damsite 1 were -$233,000 (200 kW plant), -$213,000 for damsite 2 (also the 200 kW plant), and -$97,000 for damsite 3 (150 kW plant). Damsite 3 is therefore the optimum site. Figure 7 shows the evaluation graphically. 0 1---------~--------L---------L-------~--------_J /5ELECTEL7} ,; -300 FIGURE 7 I NET BENEFITS -19- Selected Plan Of the plant sizes considered at damsite 3, the 150 kW option provided maximum net benefits and is therefore the selected plan. Detailed benefit and cost analyses are given in the Economics Section to show how the maximum net benefits were derived. Below, in table 3, are the turbine configurations and penstock sizes for each option, as well as the resulting average annual output. Installed Capacity (kW) 500 200 150 125 100 75 TABLE 3 Summary of Project Features (Damsite 3) Turbine Sizes (kW) 200,300 75,125 50,100 50,75 2@50 25,50 Penstock Diam. (in.) 32 22 18 18 16 14 Avg. Annual Output (MWh) 720 846 767 691 619 519 Figure 8 shows the temporal distributions of the energy potential of the creek at damsite 3 and the energy demand at Hope (assuming moderate growth and near-term historic monthly breakdowns). It is readily noted that times of peak demand do not coincide with times of peak flow (and peak power production). This emphasizes the desirability of tying the proposed hydropower plant into the existing CEA grid. /A/5T.A' L<t!:.t:L? C....4 P~/ r ....Y (.ii> e~ / (11:' ..?~ K .A/ FIGURE 8, ENERGY DEMAND YS .. ENERIY POTENTIAL, OAMSITE 3 -20- ECONOMICS Benefit Analysis Benefits for the Bear Creek project were developed based on the potential energy savings that would be realized from the most likely alternative electrical generating method. Only the fuel portion of CEA production costs can be avoided with construction of the project, since it would not eliminate any existing or future electrical generating capacity. Energy purchased from CEA is currently produced by natural gas turbines. The natural gas currently costs CEA a weighted average of $1.23 per million BTU (mBTU). In 1997 current gas purchase contracts will expire and gas costs are assumed to increase to the world price of $3.36/mBTU. The average annual equivalent gas price for 1990 (the assumed power-on-line date for the Bear Creek project), based on a combination of existing contract prices and current world prices, would be $2.55/mBTU, which is equivalent to S0.032/kWh. Data Resources, lnc. has ascertained that the cost of natural gas (as well as other fueb) rn1y be .::1ssumed to increase over time at a significantly higher rate than other costs would (labor, machinery, materials, etc.). This net increase in future fuel prices represents an additional cost which can be avoided by hydropower development and is therefore claimed as a project benefit. The relative rates of increase of natural gas costs determined by Data Resources, Inc. are as follows: Period Rate 1983-1985 3.69% 1986-1990 3.69 1991-1995 4.99 1996-2000 2.68 2001-2014 1.72 2015, on 0 These annual growth rates were applied undiscounted from the present to 1990 (POL date) and then discounted annually at 8 3/8% to the end of a 50 year project life (2040). The fuel escalation factor resulting from this future growth is 1.85 (i.e. 1.85 x avg. avoided fuel cost = total avoided cost), which means that the fuel escalation benefit alone is 0.85 times the average avoided fuel cost, or S.027 /kWh. All energy produced at Bear Creek would be usable since that in excess of the demand in the immediate Hope vicinity would go into the CEA grid system for distribution to other users. The average annual output was therefore credited with the full gas cost benefit and fuel escalation benefit (S0.059/kWh, total). -21- Other benefits were considered but not found applicable. There would be no dependable capacity benefit since winter flows are extremely low. Benefits for displaced diesel costs associated with power outages on the CEA distribution line would not be significant since the frequency of outages and time down are minimal. In addition, outages occur mainly during the winter when the power potential of Bear Creek is not sufficient to meet the demand in Hope. No employment benefits were claimed since Hope does not qualify as an area of high and persistent unemployment. Benefits for the plants at damsite 3 are summarized below, since that site was found to be the optimum (see Energy Analysis). Benefits shown are l OOO's of dollars. Installed Capacity (kW) 500 200 150 125 100 75 Avg. Annual Output (MWh) 720 846 767 691 619 519 Displaced Gas Cost Benefit 23 27 24 22 19 17 ($.032/kWh) ($1,000) Fuel Escalation Benefit 19 23 20 19 16 14 ($.027/kWh) ($1,000) Total Annual Benefits ($1,000) 42 50 44 41 35 31 Cost Analysis Costs were derived for each of the project sizes based on October 1984 prices, and included the following items: damsite development (mobilization, demobilization, gabion diversion, manhole-type intake, road improvements, land acquisition), penstock (steel for upper sites, high density polyethylene for lower site), powerhouse, transmission, contingencies (20%), engineering and design (7 .5%), supervision and administration (6.5%), and interest during construction (18 months at & 3/&%). Costs were amortized over 50 years at & 3/&%. An additional &% of the annual investment costs was included to account for operation and maintenance. As with the benefits, a breakdown for plants at the lowest damsite, site 3, is given since that site was found to l:?e the optimum. -22- Costs shown are 1OOO's of dollars. Installed Capacity (kW) 500 200 150 125 100 75 Site Development Mob and Demob 60 (typ) Diversion 9.5 (typ) Intake 8 (typ) Road Improvements 156 (typ) Land Acquisition 2 (typ) Penstock· 403 264 212 212 195 164 Powerhouse 490 465 460 460 455 450 Transmission 175 (typ) ------ Subtotal 1,304 1' 140 1,082 1,082 l ,060 l ,024 Contingencies 261 228 216 216 212 205 Engr. & Design 98 86 81 81 80 77 Supv. & Admin. 85 74 70 70 69 66 -..........- T ota1 First Cost 1,748 1,528 1,449 1,449 1,421 1,372 IDC 108 94 89 89 88 84 Total lnv. Cost 1,856 1,622 1,538 1,538 1,509 1,456 Amortized Cost 158 138 131 131 129 124 OM & R 13 11 10 10 10 10 T ota1 Annual Cost 171 149 141 141 139 134 -23- DETAILED COST ESTIMATE (150 kW option) ITEM/DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL MOB & DEMOB 1 LS $60,000 $60,000 DIVERSION & INTAKE Rock Excavation 15 CY 100 $1,500 Mat Gabions (3'xl0'x12') 4 EA 1,250 5,000 Riprap 30 CY 100 3,000 Precast Concrete Manhole 1 EA 5,000 5,000 Trashrack 1 EA 3,000 3,000 Total Diversion & Intake $17,500 ROAD IMPROVEMENTS Upgrade Existing Road 5,400 LF 13.70 $74,000 Construct New Road 1,640 LF 50 82,000 Total Road Improvements $156,000 LAND ACQUISITION Special Use Permit Fee 8 AC 250 $2,000 PENSTOCK 1 gu (I.D.) Poly- ethylene Pipe 1,640 LF $129 $212,000 POWERHOUSE Structure 1 LS $140,000 $140,000 Turbines/Generator 1 LS 146,000 146,000 Accessory Electric 1 LS 143,000 143,000 Aux. Systems & Equip 1 LS 11,000 11,000 Switch yard 1 LS 20,000 20,000 T ota1 Powerhouse $460,000 -24- TRANSMISSION LINE New !-phase Trans. Line Transfer Switching Station Total Transmission Line SUBTOTAL Contingencies (20%) Engineering & Design (7 .5%) 1 1 Supervision & Administration (6.5%) TOTAL FIRST COST Interest During Construction TOTAL INVESTMENT COST Mile 125,000 $125,000 LS 50,000 50,000 $175,000 $1,082,000 216,000 81,000 70,000 $1,449,000 89,000 $1,538,000 -25- Evaluation Net benefits and benefit-cost ratios for damsite 3 are summarized below: Installed Annual Annual Net Capacity Costs Benefits Benefits B/C Ratio 500 kW $171,000 $42,000 -$129,000 0.25 200 149,000 50,000 -99,000 0.34 150 141,000 44,000 -97,000 0.31 125 141,000 41,000 -100,000 0.29 100 139,000 35,000 -104,000 0.25 75 134,000 31,000 -103,000 0.23 CONCLUSIONS AND RECOMMENDATIONS A hydropower project on Bear Creek could not meet the full energy demand for the CEA Hope Feeder Line, due to low winter flows. Tying the proposed plant into the existing CEA grid is much more economical than using the hydro power for the communities along the Hope Feeder Line only. Of the three damsites considered, the lower one was optimum, due to considerably higher penstock and road improvement costs for the two upper s1tes. The optimum plant size was 150 kW. None of the numerous options investigated show positive net benefits. No further Corps of Engineers studies of hydropower development at Bear Creek are warranted at this time. -26-