Loading...
HomeMy WebLinkAboutAPA Transmission Line Assessment Bradley Lake Hydroelectric Project 1986[ .. BRA [ 113 0 0 Alaska Power Authority LIBRARY COPY DATE l r BRA 113 ISSUED TO PRINTID IN U.S.A. TRANSMISSION LINE ASSESSMENT BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY FEDERAL ENERGY REGULATORY COMMISSION PROJECT NO. P-8221-000 Prepared By STONE & WEBSTER ENGINEERING CORPORATION ANCHORAGE, ALASKA AUGUST 1986 . TABLE OF CONTENTS TRANSMISSION LINE ASSESSMENT TABLE OF CONTENTS Section Section Title 1.0 1.1 1.2 1.3 2.0 2.1 2.2 2.3 2.4 3-0 3.1 3 .1.1 3.1.2 3 .1.3 3.1.4 3.2 3-3 LIST OF TABLES LIST OF FIGURES LIST OF MAPS EXECUTIVE SUMMARY INTRODUCTION PURPOSE FERC LICENSE COMPLIANCE RESOURCE AGENCY CONSULTATION TRANSMISSION LINE ALIGNMENT FERC ROUTES KACHEMAK BAY MUDFLAT ROUTE SUBMARINE CABLE ROUTE REFINED FERC ROUTE TECHNICAL EVALUATION ROUTE Soils Slope Erosion (Fox River Lowlands) Liquifaction Wind throw TRANSMISSION STRUCTURE CONSTRUCTION 4.0 ENVIRONMENTAL EVALUATION 4.1 ROUTE 4.1.1 Land Use/Ownership 4.1.2 Cultural Resources 4.1.3 Aerial Visual Resources 4.1.3.1 Air Traffic Routes and Volume 4.1.3.2 Aerial Visibility 4.1.4 Vegetation 4.1.5 Wildlife and Fish 4.2 TRANSMISSION STRUCTURE 5.0 ECONOMIC EVALUATION 6.0 MITIGATION 1.0 RECOMMENDATIONS 8.0 BIBLIOGRAPHY 9.0 TABLES i 3-028-mc Page No. iii iv v vi 1-1 1-1 1-1 1-2 2-1 2-1 2-1 2-1 2-2 3-1 3-1 3-1 3-1 3-2 3-2 3-3 3-3 4-1 4-1 4-1 4-2 4-4 4-4 4-6 4-10 4-12 4-14 5-1 6-1 7-1 8-1 9-1 Section 10.0 11.0 12.0 13.0 3-028-mc TRANSMISSION LINE ASSESSMENT TABLE OF CONTENTS Section Title FIGURES AGENCY CONSULTATION APPENDIX A MAPS 11 Page No. 10-1 11-1 12-1 13-1 .. ) "' .. LIST OF TABLES LIST OF FIGURES LIST OF MAPS 1 2 3-028-mc LIST OF TABLES Acreages of vegetation types ooourring within the right-or-way of the refined and FERC transmission line routes. Summary of direot and indirect displacement of key wildlife species during construction of the FERC transmission line route and influence of mitigation during operation. iii Figure 2 3 4 5 ~-028-mc LIST OF FIGURES Title General Plan Refined Transmission Line Route Steel X-Tower Transmission Structure Seward Sectional Aeronautical Chart Refined Transmission Line Route Vegetation Map iv LIST OF MAPS (in Back Pocket) Title Sheets/Plates Land Ownership Information, Proposed 3 sheets Transmission Line Route Route Map 3 sheets Exhibit G 3 plates 3-028-mc v EXECUTIVE SUMMARY The Transmission Line Assessment details the technical, environmental, and economic merits of a refined transmission line route and tower structure for the Bradley Lake Hydroelectric Project transmission lines, and discusses the effects on land use/ownership, aerial visual resources, and cultural resources. The refined route was aligned to: ( 1) take advantage of better drained, glacial till upland areas and avoid wet bogs with deep peat layers; (2) avoid tower foundation problems on Kachemak Bluffs and Kachemak Bay tidelands ; ( 3) avoid potential windthrow of trees by placing towers on headlands projecting in to Kachemak Bay tidelands; and ( 4) a void private property, and locate the route near the outer boundaries of section line easements to avoid conflict with future public use. An aerial and cultural pedestrian survey within a 2.1 mile segment of the refined route di.scovered no architectural, surface, or subsurface cultural resources. The Hilmer Olsen Fox Farm property will be protected from project disturbance by an "off limits" enforcement policy. Air traffic routes and volume in the vicinity of the Bradley Lake transmission line are discussed. Aerial visibility of the transmission line was related to number and length of straight-line segments, other nearby linear features, and interspersed vegetation communities. The transmission lines will be used as a landmark by air traffic and will not stand out as an unusual adverse visual anomaly on the terrain below the aerial observer. The refined route crosses one less vegetation type and has 77.3 more acres within the right-of-way corridor than the FERC licensed route. Steel X-towers, which have distinct technical and economic merits over the wood H-frame poles, will be used. A cost savings of $500,000 to $600,000 be realized by the refined route utilizing steel X-towers. 3-028-mc vi , .... SECTION 1.0 INTRODUCTION 1.0 INTRODUCTION 1.1 PURPOSE The Transmission Line Assessment constitutes a request for design change to the FERC Order Issuing License for the Bradley Lake Hydroelectric Project, Project No. P-8221-000. It presents to the Federal Energy Regulatory Commission (FERC) for concurrence and approval the proposed revised alignment for the Bradley Lake transmission lines. This assessment details the technical, environmental, and economic merits of the revised alignment, and discusses its effects on land use/ownership, aerial visual resources, and cultural resources in the Project area. The record of resource agency consultation and related correspondence is included in this filing. 1.2 FERC LICENSE COMPLIANCE The Transmission Line Assessment is designed to comply specifically with requirements set forth in Articles 37 and 40 of the FERC License. Article 37 states the "Licensee, after consultation with the Alaska Department of Natural ResoL}rces (DNR), shall determine the need, if any, to change the transmission line alignment to avoid conflicts with existing or proposed land use. Within one year from the date of issuance of this license, Licensee shall file with the Commission a report on the consultations and shall file for Commission approval, an application for amendment of the license that details any proposed changes in the transmission line alignment. The comments of DNR on the report shall be included in the filing." Article 40 states the "Licensee shall determine the impacts of the transmission line corridor on views from air traffic in the area, including: (1) an analysis of the existing air traffic, including the volume and the routes of air traffic in the vicinity of the project facilities; (2) a discussion of pipelines, transmission lines, roads, 3-028-mc 1-1 and other linear corridors, which, together with the Bradley Lake transmission line corridor, would affect visual resources when seen from the air; and ( 3) the degree to which the transmission line corridor should be mitigated. The results of the analysis shall include any mitigative measures recommended by the Licensee, and the comments and recommendations on the analysis by the Department of the Interior and the Alaska Department of Natural Resources, and shall be coordinated with the analysis conducted under Article 37. The Licensee, within 1 year from the date of issuance of this license and before beginning any transmission line construction or maintenance activities of a land-disturbing nature, shall file the results of the analysis with the commission. Unless the Director, Office of Hydropower Licensing, instructs otherwise, Licensee may commence land-disturbing activities 90 days after the filing dat~ of the report. 11 The Transmission Line Assessment also fulfills the requirements of Article 38 of the FERC License by meeting State of Alaska requirements for protection of historic cultural resources. Further, this assess- ment elaborates on discussions of visual impacts and mitigation measures for the transmission line presented in the Visual Resources Mitigation Plan (Alaska Power Authority 1986) prepared to meet the requirements of Article 39 of the FERC License. 1.3 RESOURCE AGENCY CONSULTATION The Alaska Power Authority has developed the revised alignment of the transmission lines in conjunction with resource agencies. Resource agencies consulted were the Alaska Department of Natural Resources, Alaska Department of Fish and Game, u.s. Fish and Wildlife Service, U.S. Forest Service, Alaska Department of Environmental Conservation, National Marine Fisheries Service, U.S. Department of the Army, and Alaska Office of Management and Budget. Local experts in the fields of windthrow, bark beetle infestation, and avian collision mortality were also consulted. 3-028-mc 1-2 SECTION 2.Q; TRANSMISSION LI.NE ALIGNMENT 2.0 TRANSMISSION LINE ALIGNMENT The Alaska Power Authority proposes to construct two parallel 115,000 volt (115 kV) transmission lines from the Bradley Lake powerhouse to intersect the Fritz Creek-Soldotna 115 kV transmission line (Bradley Junction), planned for construction by the Homer Electric Association, Inc. (Figure 1). The Alaska Power Authority has considered several route and structure alternatives, including the ( 1) FERC alignment, (2} Kachemak Bay mud flat alignment, (3) submarine cable, and (4) refined FERC alignment. 2.1 FERC ROUTES The FERC alignment was licensed by the FERC on December 31, 1985, and is shown on Figure 2. 2.2 KACHEMAK BAY MUD FLAT ROUTE As an alternative to routing the FERC licensed transmission lines in the rugged, tree covered terrain between the powerhouse and the Fox River Lowlands crossing point, the Alaska Power Authority during 1985 considered locating the 115 kV lines on the Kachemak Bay mudflats. Construction of overhead transmission lines on the mudflats would infringe upon the Fox River Flats Critical Habitat Area. The transmission lines would also be threatened by foundation failure resulting from soil liquefaction due to earthquakes (see Section 3.1.3). Because of these problems, this route alternative was eliminated from further consideration. 2.3 SUBMARINE CABLE ROUTE The Alaska Power Authority also evaluated the use of submarine cables. Each of the proposed 115 kV transmission lines would require a total of four cables (three cable circuits plus one spare), totalling eight cables. Installation of these cables within the mudflats would be technically difficult and expensive. Unlike a typical submarine 3-028-mc 2-1 crossing, where most if not all of the cable is placed directly on the floor of the waterbody, the Bradley Lake cables would be trenched and buried for their entire length. Each cable would probably require its own trench. Equipment movement and trenching would result in substantial surface disturbance. Data indicates that cohesionless, saturated soils would likely be encountered along at least part of the trench routes. These granular materials could make it difficult to hold trench walls in place and/or cause water problems within the trenches. Additionally, heavy cable reels (approximately 60 tons per phase per run) would have to be removed fran a barge and transported over the mudflats for instal- lation in the trenches. This movement of heavy materials and equipment could create significant impacts on the Fox River Flats Critical Habitat Area. It is estimated the submarine cable option would cost approximately 4.5 times more than a comparable length of overhead line. Because of this greater cost, in addition to the above-mentioned construction difficulties, use of submarine cable was not considered practicable. 2.4 REFINED FERC ROUTE Further evaluation and refinement of the FERC alignment, conducted as a part of the Project Phase II of engineering and design, resulted in a third possible alternative (Figure 2). Although both the FERC licensed alignment and the refinement proposed in this report are feasible, the refined alignment offers distinct advantages over the FERC alignment. The following discussion evaluates the technical, environmental, and economic merits of the refined FERC alignment. 3-028-mc 2-2 TECHNICAL EVALUATION 3.0 TECHNICAL EVALUATION 3.1 ROUTE 3. 1. 1 Soils Soil boring information received after submittal of the FERC License Application revealed the presence of deep layers of peat in the low-lying wet bogs on the glacially fluted plains between Bradley Junction and the bluffs on the west side of the Fox River lowlands. To minimize potential foundation problems, the FERC route was adjusted to take advantage of better drained, glacial till upland areas. This alignment provides greater long-term line reliability. It also offers less potential for adverse environmental impacts resulting from more frequent maintenance and/or repair of structures when the ground is thawed in the summer, which is the likely time when foundation problems would occur. Where unavoidable, wet bogs are crossed at narrow points utilizing the most direct route possible. Angle points requiring heavy, guyed and anchored three-pole structures are not sited in these areas. River scour depth studies and loop meander investigations were also conducted to assist in the selection of the most sui table foundation design and site locations for tower structures. 3.1.2 Slope Erosion (Fox River lowlands) The headwardly eroding Kachemak Bluffs along the west side of the Fox River lowlands are characterized by active surface skin slides. Utilizing results of a detailed field investigation and a comprehensive geotechnical study of the rate of bluff erosion, the route accomplishes the 500 feet transition from plateau to valley in one span. By avoiding the use of intermediate transmission structures, susceptibility of the line to slab failure is minimized. An adjustment in the angle of approach also minimizes the crossing of Remote Parcel Lease ADL 206393, as noted in Section 4.1.1. 3-028-mc 3-1 3.1.3 Liquefaction The Kachemak Bay tidelands and Fox River lowlands are subject to liquefaction caused by earth tremors. It is estimated that a 5.5 or larger magnitude earthquake on the Richter scale will liquify the saturated soils. Techniques to reduce this problem have not been proven to be practicable. It was concluded that the best way to minimize the potential risks of liquefaction on the proposed transmission lines was to (1) modify the FERC alignment to cross the Fox River lowlands with the fewest number of transmission structures possible and minimize angles, and (2) avoid placement of the transmission lines within the mudflats north of the powerhouse. 3.1.4 Windthrow A potential for windthrow exists on the steep, Sitka spruce-covered slopes northeast of the powerhouse. Large, interior trees have not developed root systems capable of supporting the stems under full wind stress. If a right-ot-way is cut through this vegetation, trees along the right-ot-way edge may blow down due to heavy downslope and southeasterly winds. The blowdown would be greatest on the leeward side ot ridges and on upper slopes where wind turbulence is more pronounced. Once down, the spruce trees provide a breeding ground for spruce beetles (Dendroctonus rutipennis) and also increase the potential for wildfires unless promptly removed. Limited access would make removal of windthrown trees difficult. Overall, windthrow would create an on-going right-ot-way maintenance problem and degrade the aesthetic quality of the area. To minimize these potentially disruptive effects, the refined route has been aligned along several peninsula-like high points or headlands which extend into the mudflats. Here, the clearing for the right-of-way is reduced, and the threat ot windthrow limited to the leeward side of specific headlands where timber is tall. A U.S. Forest Service windthrow expert has been consulted to check the refined FERC route to identify potential for wind throw. The U.S. Forest Service expert determined that windthrow of trees is not a potential problem for the majority of the transmission line corridor. 3-028-mc 3-2 Trees in the majority of the area are relatively short in stature and sufficiently spaced to be windfirm. Trees on four specific headlands were identified as having the potential for wind throw. Removal of trees between the right-of-way boundary and the tidelands was prescribed to prevent windthrow problems in these four areas. 3.2 TRANSMISSION STRUCTURE In the FERC License Application, the Alaska Power Authoirty proposed to use wood pole H-frame towers. Subsequent to issuance of the FERC license, steel X-towers have been evaluated for use rather than wood poles. Following consultation with resource agencies, the Alaska Power authority adopted the steel X-tower for use on the Bradley Lake 115 kV transmission lines. The X-tower is (1) simpler in design than the wood pole H-frame, (2) stronger, (3) weighs approximately one-third less, (4) offers a longer ruling span, (5) offers greater foundation stability with driven H-piles (over direct embedment of the wood H-frame), and (6) is fire resistant. In terms of constructability, the X-tower has fewer structural parts and is easier to assemble. Driven steel H-pile foundations will be used for the steel X-towers. Tower foundations in the Fox River lowlands will have riprap armament to prevent flood damage. 3.3 CONSTRUCTION Technical considerations to be addressed in constructing the refined FERC alignment are similar to the FERC route. Scheduling, mode of clearing, and disposal of slash are essentially identical for both routes. Transmission line clearing will be accomplished as outlined in the Mitigation Plan (Alaska Power Authority 1985a) and Vegetation Clearing Plan (Alaska Power Authority 1986a). Felling of trees within the right-of-way can feasibly occur at any time of year. Tree and 3-028-mc 3-3 slash removal in or across sensitive areas (e.g., wet bogs, steep hillsides, or critical habitat areas) will be conducted in a manner that minimizes environmental impacts. Rubber-tired, low-ground bearing pressure vehicles will be used wherever practicable to transport transmission towers and related construction equipment across sensitive areas. Helicopters may be used in areas with difficult access. Ground activity will be confined primarily to the right-of-way, and to selected access locations. Construction may be conducted during winter in oertain areas where frozen soils will facilitate movement of equipment and minimize environmental damage. Soil stabilization techniques as described in the Alaska Power Authority Best Management Practices (BMP) Manual "Erosion and Sedimentation Control" will be implemented to minimize local erosion. 3-028-mc 3-4 4.0 ENVIRONMENTAL EVALUATION 4.1 ROUTE 4.1.1 Land Use/Ownership In an April 12, 1985 letter to the FERC regarding the FERC Draft Supplemental Environmental Impact Statement, the Alaska Office of Management and Budget, Division of Governmental Coordination (on behalf of the Alaska Department of Natural Resources) requested the final transmission line right-of-way be located near the outer boundaries of section line easements to avoid conflict with future public use. In response to this request, the first 4.5 miles of the FERC route alignment extending east from Bradley Junction have been shifted off the section line (Land Ownership Information, Sheet 1 of 3). The shift in route alignment from the south side of the section line to the north side in this area was made to assure sufficient distance between the 115 kV transmission lines and State Subdivision ASLS 80-155 (Land Ownership Information, Sheet 1 of 3) and to minimize the crossing of poorly drained peat-filled bogs. The refined route provides a shorter, more direct crossing of relatively similar terrain between Sections 26 and 27 and between Sections 34 and 35 of T. 3S, R.10W, Seward Meridian, and limits the crossing of property included in a land exchange application by the Seldovia Native Association (ADL 221933) to the extreme southwest corner of the parcel (Land Ownership Information, Sheet 2 of 3). The transmission line was also shortened when Homer Electric Association moved the Fritz Creek -Soldotna 115 kV transmission line and the Bradley Lake transmission line intersection at Bradley Junction 1 mile east (Figure 2). The FERC route crossed Remote Parcel Lease ADL 206393 in Section 35, T.3S, R.9W, Seward Meridian (Land Ownership Information Sheet 2 of 3). Efforts to minimize impact on this parcel have resulted in an alignment that now traverses only the extreme southern corner of the property, yet still facilitates an acceptable routing through the 3-028-mc 4-1 complex terrain bordering the Fox River lowlands (Route Map, Sheet 2 of 3). Surveying of the remote land areas along the refined route is currently in progress. With the exception of the privately owned Hilmer Olsen Fox Farm (U.S.S. 2937), the refined route alignment maintains sufficient distance from all other known private property to minimize possible land use conflicts. To avoid placement of the 115 kV transmission lines within the steep, tree-covered terrain northeast of the powerhouse, the refined route alignment is now centered on several headlands that extend into the Kachemak Bay mudflats. As a consequence, the alignment now crosses over the Fox Farm property (Land Ownership Information, Sheet 3 of 3). No towers are located on the property. The alignment over the Fox Farm is a necessary trade-off to limiting the sidehill scar and minimizing windthrow problems associated with the clearing of a right-of-way on the steep slopes immediately east of the property. Further discussion on the subject of windthrow is included in Section 3.1.4 of this assessment. 4.1.2 Cultural Resources An intensive cultural resource pedestrian survey has been conducted on the entire FERC route alignment (Woodward-Clyde Consultants 1984). No previously unidentified cultural resources were located during that survey. A 2.1 mile segment of the refined FERC transmission line corridor south of Caribou Lake was identified by the Alaska Department of Natural Resources (ADNR) State Historic Preservation Office for survey of cultural resources. An aerial and pedestrian cultural resources survey of this segment was conducted in June 1986 (Appendix A). No architectural features, surface features, or subsurface cultural resources were discovered within the surveyed segment of the refined FERC corridor (Alaska Heritage Research Group 1986). 3-028-mc 4-2 Although not crossed by the FERC licensed route, the Hilmer Olsen Fox Farm has also been field surveyed (Woodward-Clyde Consultants 1984). Evaluation of the Fox Farm resulted in the determination that the site was eligible for inclusion in the National Register of Historic Places. The State Historic Preservation Officer concluded that no direct impact to the Fox Farm from overpassing transmission lines was expected (Cutler 1986). However, indirect impact resulting from increased human activity in the area was possible. Concurrence of the State Historic Preservation Officer with the refined FERC alignment was contingent upon the following protective measures: 1) The historic site will be posted as "off limits" to all personnel associated with the construction and operation of the Bradley Lake Hydroelectric Project. As part of the environmental briefing for each employee, there will be an educational segment to sensitize the employee to the cultural resources within the Project area and to the potential for encountering other such resources in the Project area. 2) There will be monitoring of this "off-limits" site.conducted by the Alaska Power Authority Environmental Field Officer (EFO). 3) Should cultural resources be located during construction, all work which would disturb such resources will be stopped and the appropriate authorities contacted for consultation. The Alaska Power Authority, State Historic Preservation Office, Advisory Council on Historic Preservation, and FERC may participate in determining the eligibility for inclusion of the discovered resource in the National Register as well as development of mitigation measures, as appropriate. 3-028-mc 4-3 Routing the transmission lines along the headlands immediately adjacent to the mudflats will not have a direct impact on any of the structures located on the Hilmer Olsen Fox Farm site. It could, however, have an unavoidable indirect influence on the visual integrity of the site. The potential for vandalism could also increase as construction activities would occur closer to the immediate Fox Farm area. Adverse effects will, however, be minimized by strict enforcement of the above-mentioned measures. 4.1.3 Aerial Visual Resources The proposed 115 kV transmission lines will alter the visual quality of the area, and be in contrast with the existing natural character of the region, particularly when viewed from the air. There are no appreciable differences in visual impact between the two alternative .routes with the exception of the area between the powerhouse and the Fox River crossing point. Here, the FERC alignment was located higher on the mountainside, thus requiring an uninterrupted clear-cut through dense, closed coniferous forest. Windthrown trees "unraveling" along the exposed right-of-way edge, as described in Section 3.1.4 of this assessment, would further increase the visual impact from both aerial and ground perspectives. By moving the transmission lines off the mountainside and onto the headlands extending into the Kachemak Bay mudflats, visual impacts are reduced. Aerial views of a cleared, straightline corridor area are also broken by both forested and non-forested areas between the high points. Although the refined route places the transmission lines in closer, more open view from the immediate Kachemak Bay area, overall visual consequences are reduced by the backdrop of tree-covered mountains to the immediate east of the route. The weathering steel X-tower transmission structure blends effectively into this type of landscape backdrop. 4.1.3.1 Air Traffic Routes and Volume Two charted Federal Aviation Administration (FAA) airways provide approaches to and from Homer on the north. Victor 435 airway passes approximately 6 miles to the east of Bradley Junction on radial 344° for air traffic between Kenai and Homer (Figure 4). Victor 438 airway 3-028-mc 4-4 passes approximately 1.5 miles to the east of Bradley Junction on radial 003° for air traffic between Anchorage and Homer (Figure 4). Aircraft flying by instrument flight rules (IFR) follow charted airways north of Homer at elevations above 5,000 feet mean sea level (MSL). IFR aircraft flying at these higher elevations would usually be above cloud ceilings, thereby obscuring aerial views of the transmission line corridor. Air traffic following Victor 438 would come in closest proximity to the transmission line corridor, affording higher probabilities of greater observation frequencies than from air traffic on Victor 435. Aircraft flying by visual flight rules (VFR) approaching or departing Homer on the north can fly any route and altitude that does not violate VFR minimums. Aircraft travelling to/from Anchorage or vicinity commonly follow the Fox River drainage at the head of Kachemak Bay, which is a natural lowland route into the Homer area. Both private and commercial aircraft flying VFR can take the route along Kachemak Bay and the Fox River drainage. A portion of the transmission line corridor would be visible to any aircraft travelling generally north and south between approximately Victor 438 and the Fox River lowlands. Scheduled commuter air service presently is provided to Homer by two air taxi operators based in Anchorage. These operators use aircraft with maximum capacity of 10 to 19 passengers. Between 14 and 16 total daily arrivals and departures at the Homer airport are currently scheduled by these two air taxi operators, depending on the day of the week and time of year. Thus, up to 30 flights of scheduled air taxis could potentially fly in the near vicinity of the transmission line corridor each day during the summer months. Both scheduled commercial and general aviation traffic decreases during the weekdays and · the winter months. The Homer airport runway is oriented on a southwest-to-northeast longitudinal axis. Aircraft position their approach well in advance of the point of touch-down. Aircraft landing from or taking off to 3-028-mc 4-5 the northeast may swing over the west end of the transmission line near Bradley Junction when making their approach or departure, respectively. Though flight schedules and frequency are constantly changing, the FAA Homer Flight Service Station (FSS) records contact with approximately 20 to 30 arriving and departing air taxi VFR and IFR aircraft each day during the summer months. Some unknown proportion of these air taxi contacts are with operators based in Anchorage to the north. Depending on the flight rules under use and the specific terminology used, some air taxi traffic may be classified as general aviation traffic by the FSS and thus are not included in the above estimate. Homer FSS is open on a part-time basis from 6 a.m. to 10:30 p.m. daily. During 1985, Homer· FSS reported 6, 264 IFR aircraft radio contacts and 46,819 VFR aircraft contacts, totalling 53,083 aircraft contacts. A contact includes landing, departing, and overflying aircraft. There are no records kept by FAA which would indicate the proportion of these contacts using the flight corridor between approximately Victor 438 and the Fox River lowlands. 4.1.3.2 Aerial Visibility Straight-line segments of the transmission line corridor will be most visible from the air when the view angle is parallel to and intersecting the axis of the segment, and by aircraft flying at higher elevations (e.g. above 2,500 feet MSL). As currently designed, the 19 mile transmission line corridor is composed or 15 individual straight-line segments. Segments range fran approximately 0.1 to 3 miles in length. The transmission line corridor can be divided into three sections for assessment of aerial visual resources: ( 1) the uplands plateau from Bradley Junction to top of the Kachemak Bluffs; (2) Kachemak Bluffs to the east side of the Fox River lowlands; and (3) Fox River lowlands to 3-028-mc 4-6 the powerhouse. For assessment of aerial visibility, aircraft are considered to be over flying the transmission line corridor at 2,500 feet MSL. Seven straight-line segments occur in approximately 10 miles of transmission line corridor on the uplands plateau. These segments will have the highest viewer frequency from air traffic flying on or near Victor 438 and across the uplands plateau. The seven segments on the uplands plateau range from 0.8 to 3 miles in length. The 3 mile segment is located furthest fran the Victor 438 airway. Two of the seven segments are parallel and in close enough proximity to be visible simultaneously from Victor 438. These two segments total approximately 1.2 miles in length. Two straight-line segments occur in the approximately 4 mile Kachemak Bluffs to the east side of the Fox River lowlands section of the transmission line corridor. This section will be most visible to air traffic flying the Fox River drainage. The two segments are 1 • 5 and 2.6 miles in length. The two straight-line segments in this section of transmission line corridor are not oriented parallel, and will probably not be viewed simultaneously along the entire length of their longitudinal axis by aircraft flying at moderate altitudes through the Fox River drainage. Aircraft flying the Fox River drainage would generally fly at lower elevations (e.g., 1,500 -2,000 feet MSL) than those flying over the adjacent upland plateaus (e.g., 2,500 feet MSL). Six straight-line segments occur in the 5 mile Fox River lowlands to powerhouse section of the transmission line corridor. This section would also be most visible to air traffic flying the Fox River drainage. Segments range from 0.1 to 2.1 miles in length. Several of these segments are located nearly parallel, though unless the aircraft was flying parallel to and over the corridor at high altitude (e.g., 2, 000 feet above ground level) most of the segments would not be 3-028-mc 4-7 visible simultaneously. The tall spruce trees bordering the corridor in this section will obscure a portion of the right-of-way when viewed from a lateral aerial view (e.g., from aircraft flying parallel to the Fox River drainage). Throughout the entire length of the transmission forested vegetation is interspersed with and lower-growing shrub and herbaceous vegetation types. line corridor, dissected by Trees will be cleared fr001 the corridor to minimize potential for grounding of the conductors and to maximize the time interval between required clearings. Tree stumps will not be grubbed. On the uplands plateau, approximately 6.8 miles of spruce forest is interspersed with wet graminoid bogs and low shrublands along the 10 mile section. Approxi- mately 5 of 9 miles ot transmission line corridor between the Kachemak Bluffs and the powerhouse are forested by spruce and 0. 75 miles by mixed spruce/balsam poplar. The remaining 3.25 miles are shrublands and herbaceous sedge-grass tidal flats interspersed through the forest. The discontinuous pattern of forested vegetation and low-growing shrubs and herbaceous vegetation will tend to break the linear pattern of trees cleared from the transmission line corridor. This discontinuous vegetation pattern, coupled with relatively short straight-line segments, will minimize the aerial visual impact of the · corridor. On the east side of the Fox River lowlands, the transmission line corridor will be widened to include. spruce trees between the right-of-way boundary and the tideline on selected projecting headlands. This additional 9. 3 acres of tree clearing to prevent windthrow will visually emphasize the transmission line corridor from the air to a minor degree. However, the discontinuous vegetation pattern between cleared headlands and herbaceous sedge-grass tidal flats will present a mosaic of vegetation textures and colors to the aerial observer which will further detract from the linear feature of the corridor. In addition, regrowth of spruce trees within the 3-028-mc 4-8 corridor will tend to blend colors of the corridor into the surrounding forest, particularly on the uplands plateau where mature spruce forests are composed of relatively short {e.g., 15 to 20 feet) trees. The uplands plateau is heavily disected by randomly spaced and oriented cleared seismic survey lines (Route Map, Sheet 1 of 3). These linear features are very common throughout the western Kenai Peninsula. Though narrow (e.g., 10 to 15 feet wide) in relation to the transmission line corridor, their very presence trains the aerial observer's eye to the commonality of linear features throughout this area. The transmission line corridor will not stand out as an unusual adverse visual anomaly on the terrain below the aerial observer. The Fritz Creek-Soldotna 115 kV transmission line under construction by Homer Electric Association, Inc. will intersect the Bradley Lake transmission line at Bradley Junction (Figure 4). Oriented almost due north and south and perpendicular to the Bradley Lake transmission line, the Fritz Creek-Soldotna transmission line will probably become a commonly flown VFR air traffic route and landmark between Kenai/Soldotna and Homer. VFR pilots are well known to follow linear corridors such as roads and transmission lines, particularly in inclement weather. Because the Fritz Creek-Soldotna transmission line is almost a direct route between Kenai/Soldotna and Homer, it is likely to be heavily used by VFR traffic. The FAA Air Traffic Manager -at the Homer FSS suggested that the Bradley Lake transmission line would become a landmark for air traffic into and out of Homer to the north. Construction of the Bradley Lake transmission line corridor, in combination with the Fritz Creek-Soldotna transmission line and random seismic lines, will not detract from the aerial view of the surrounding landscape. There are no other linear features such as transmission lines or roads in the general area of the Bradley Lake transmission lines. 3-028-mc 4-9 FAA requires that marker balls be strategically placed to promote saf'ety of low-flying aircraft. Marker balls will be placed where transmission lines cross Sheep Creek and Fox River waterways between PI9 and PI10 (Exhibit G, Plate 3). Marker balls will also be used to minimize collision mortality of low-flying waterfowl with transmission lines crossing the Bradley River between PI12 amd PI13 (Exhibit G, Plate 3) • When used, marker balls will also make the transmission lines more visible to the aerial observer. However, high visibility of transmission lines at specific points will also increase safety margins for low-flying aircraft. The advantages of increased safety for aircraft and waterfowl outweigh the disadvantage of increased aerial visibility. 4.1.4 Vegetation The refined transmission line route was overlaid on the vegetation map of the Project area (Figure 5). The study area boundary was enlarged where necessary to include the refined route. The included area was vegetation mapped from 1 : 1 ,000 scale black and white aerial photography. Angle points for each of the straight-line segments were located using a digitized map product scaled to 2 inches to 1 mile. The vegetation map is not rectified, so some horizontal distortion is ·present. However, segment length tl,tween angle points were similar for distances calculated from Alaska State Plane Coordinates, Zone 4, and those measured from the . vegetation map. Differences between calculated and measured distances averaged 71 feet (standard deviation .±. 57.5 feet), ranging from 9 to 217 feet, for 14 straight-line segments. Most east-west horizontal distortion was purposefully concentrated in the segment between PIS and PI9 which bridges the Kachemak Bluffs (Exhibit G, Plate 3 of 3). This segment was chosen to be shortened by 416 feet because ( 1) diversity of vegetation types was low (only 5 types), (2) the segment was relatively short (1.5 miles) and oriented generally east-west, and (3) unavoidable horizontal distortion was present on aerial photography over the 750 feet elevation difference between PIB and PI9. 3-028-mc 4-10 Though limited distortion in segment lengths was present, total length of the transmission lines differed by only 0. 03 miles between the vegetation map (18.97 miles) and distances calculated from State Plane Coordinates (18.94 miles). The error in segment lengths was considered acceptable given the level of mapping detail in the vegetation maps. Areas affected by the transmission line corridor were calculated by (1) accumulating linear distances measured by the bisection of the corridor centerline with individual vegetation polygons, (2) converting the linear map distances (mm) to distances on the ground (feet), (3) multiplying the ground distance by the corridor width to obtain square feet, and (4) converting square feet to acres. Corridor clearing width is 350 feet between Bradley Junction (PI1) and the east side of the Fox River lowlands (PI10), and 400 feet between PI10 and the powerhouse (PI16). Corridor width is wider than the 225 feet naainal clearing width and 50 feet selective clearing width presented in the Vegetation Clearing Plan to accaamodate increased line swing and tower heights associated with longer ruling spans to be used with the steel 1-towers. Acreages of vegetation types crossed by the refined route are similar to the FERC route (Table 1 ) • The refined route crosses more coniferous forest, shrub types,· sedge-grass types, and unvegetated areas than the FERC route. The refined route crosses less deciduous forest, mixed forest, and tall grass types than the FERC route. The refined route is shorter (by approxi.Etely 1 mile) than the FERC route, but the right-of-way corridor is wider. Total acreage within the right-of-way corridor of the refined route is 839.7 acres, which is an increase of 77.3 acres over the 762.4 acres within the FERC route corridor. '!be refined route crosses 21 different vegetation types, while the FERC route crossed 22 vegetation types. Only forested vegetation and shrubs with the potential to become a hazard to the transmission lines within the right-of-way corridor will be cleared. Within the refined route right-of-way, 38.6 more acres of coniferous forest, 14.6 less acres of deciduous forest, and 22.9 less acres of mixed forest will be potentially be cleared than within the 3-028-mc 4-11 FERC route right-of-way. An additional 9.3 acres of closed coniferous forest will be cleared from headlands between the right-of-way boundary and the tideline along Kachemak Bay to minimize windthrow. The longer ruling span of the steel X-towers allow many towers to be strategically placed on ridges or headlands. When spanning from ridge top to ridge top, a portion of the right-of-way in deep valleys may not be cleared if maximum line sag clears tree tops by a safe margin. The safety margin is influenced by many factors including ruling span, tower height, prevailing wind direction, depth of the valley slope, and tree height. Clearing widths in forested vegetation types at tower location may also be narrower than the right-of-way width. A minimum clearing width sufficient to safely pass construction and maintenance equipment may be required in types where growth of vegetation restricts travel. Areas within the right-of-way will be cleared of forested vegetation and maintained in an early seral stage. Vegetation regrowth will be controlled at intervals designed to minimize hazards of contact with overhead lines. The refined route crosses little sensitive habitat on the Fox River lowlands. Only 12.8 acres of tall alder/fresh water · herbaceous sedge-grass vegetation type occurs within the right-of-way corridor between PI9 and PI 10 east of Sheep Creek. This area is part of the Sheep Creek-Fox River outwash floodplan and does not represent sensitive or unique wildlife habitat. North of the powerhouse, transmission lines skirt over edges of the mudflats as they pass between headlands. Though construction access to headlands may be gained across mudflats, transmission lines or towers will not directly disturb the herbaceous sedge-grass vegetation types between headlands. 4.1.5 Wildlife and Fish North of the powerhouse, the refined route borders the eastern boundary of the Fox River Flats Critical Habitat Area (Route Map, Sheet 3 of 3). Approximately 6.1 acres of the right-of-way corridor 3-028-mc 4-12 between PI12 and PI13 extends within the boundaries of the Critical Habitat Area. However, the entire acreage of transmission line right-of-way within the Critical Habitat Area is confined to the Bradley River channel which occurs below mean high tide. will be placed within the Critical Habitat Area. No towers Overhead transmission lines extending over this short section of the Bradley River (approximately 0.3 miles) will be maintained above a 50 feet minim\111 sag height, except under severe winter icing conditions. Transmission lines are not expected to adversely affect waterfowl and shorebirds that may use this portion of the Critical Habitat Area. The probability or waterfowl being in the area during the winter when the extreme design case of a 30 feet minimum sag height will occur is low. Colored markers (e.g., orange globes) will be used to make the transmission line collductors more visible to low-flying waterfowl~ Markers for waterfowl will be strategically placed where transmission lines cross over the Bradley R1 ver between PI12 and PI13 (Exhibit G, Plate 3). Collision with transmission lines is not expected to be a significant cause of mortality in terms or the total number of waterfowl found at the head of Kachemak Bay (Yanagawa 1986). The relatively minor changes in vegetation type acreages between the refined route and FERC route do not significantly affect the assessment of habitat alteration or loss for key wildlife species previously addressed in the License Application, Mitigation Plan, and Terrestrial Impact Assessment Report (Alaska Power Authority 1985) (Table 2). Slightly more forest will potentially be cleared by the refined route (33. 3 acres), but the additional clearing will not result in additional adverse effects. Moose will be benefitted by forest clearing in areas which will naturally revegetate to browse species (e.g., primarily willows and balsam poplar). Black bear are a mature forest species, and will benefit from any forested areas not cleared within the right-of-way corridor. Overhead transmission lines in non-forested areas will not adversely influence habitat value for wildlife or fishery resources. 3-028-mc 4-13 4.2 TRANSMISSION STRUCTURE The weathering steel X-tower transmission structure is compatible with the environmental setting of the Bradley Lake Hydroelectric Project area. Aesthetically, the structure will blend well into the surrounding landscape. The steel x-tower is comparable in size, and utilizes similar construction and maintenance procedures as the wood H-frame. The steel X-tower structure meets or exceeds recanmendations for raptor protection contained in Olendorff et al. ( 1981). Because of the low potential for lightning, an overhead ground wire will not be used, thereby avoiding a high ground plane in close proximity to energized cooouctors. The horizontal cooouctor configuration also reduces the probability of bird collisions. The steel X-tower provides for long span lengths, thus reducing the total number of structures required on the landscape and increasing the opportunity to reduce overall environmental impact. Greater foundation stability provided by the driven H-piles of the X-tower will require less frequent maintenance, which offers less potential for environmental impact. 3-028-mc 4-14 5.0 ECONOMIC EVALUATION The refined transmission line route effectively reduces the length of the FERC licensed route by about 1 mile. Total length of the refined route is 19 miles, while the FERC route was about 20 miles long. Based on use of the steel X-tower and two parallel transmission lines, 8 to 10 towers and the associated costs of construction including foundations, conductor line, insulators, and installation were eliminated by the shorter refined FERC route. The cost savings of constructing the shorter refined FERC route over the FERC route is about $500,000 to $600,00 for the double circuit line. The estimated cost per mile for steel X-towers versus wood H-frame poles is comparable (e.g. within $4,000 per mile of double circuit line). In areas where helicopters may be necessary to transport and erect towers, the lighter steel X-tower can be handled by $2,500 per hour helicopters whereas the heavier wood pole H-frame structures will require much larger $6,000 per hour helicopters. These, and the previously discussed distinct advantages of the steel X-tower, led to the decision favoring their use for the Bradley Lake transmission line. Forested acreages from Table. 1 were oompared to determine comparative clearing costs. Coniferous Forest Deciduous Forest Total Refined alignment 581.3 acres 4.1 acres 585.4 acres FERC alignment 533.4 acres 18.7 acres 552. 1 acres Difference 47.9 acres 14.6 acres 33.3 acres The total forested acreage is largely unchanged (33. 3 acres) . The cost of clearing corridors for the two routes is essentially the same, particularly if some areas with low growing trees that will not contact conductors are not cleared within the refined route. Wider right-of-way widths along the Fox River lowlands will add higher 3-028-mc 5-1 proportions of larger Sitka spruce trees, from which a portion of the clearing costs may potentially be recovered through their harvest and sale. Based on cost comparisons for transmission line clearing, no definitive cost differences exist between the two routes. 3-028-mc 5-2 SECTION 6.0 MITIGATION 6.0 MITIGATION The refined transmission line corridor has been sited near the outer boundaries of section line easements to avoid conflict with future public land use. The refined FERC route also avoids private land holdings wherever practicable. The minimum clearing width of the transmission line right-of-way corridor necessary to ensure safe Project operation and infrequent re-olearing will be conducted. Large, accessible Sitka spruce timber will be removed for sale where practicable. Small or inaccessible spruce timber and spruce slash larger than 2 inches in diameter will be out into 2 to 4 feet lengths and scattered through the cleared area to minimize or prevent infestation by spruce beetles. Hardwood trees will be felle.d in place. Felled trees will be removed from streams and rivers. Salvage of otherwise inaccessible felled trees for firewood by local residents will be encouraged if removal is conducted in a manner that minimizes environmental damage. Tower structures will be constructed of weathering steel which will blend into the natural brownish-green colors of the vegetation. Non-specular (non-reflective) conductor wires and sky gray insulators will blend into the landscape. The I-tower structure casts less shadow than almost any other comparable structure. Natural revegetation of spruce trees will eventually blend the right-of-way corridor into the surrounding terrain from an aerial view, though substantial surface disturbance or burning may be necessary to promote revegetation of spruce trees. The minimum tower heights necessary to complete the spans will be used. Marker balls will be strategically placed on conductor lines where required to promote aircraft safety and minimize waterfowl collisions. The transmission line will serve as a landmrk for air traffic. No other mitigation measures are proposed for the Bradley Lake transmission line. 3-028-mo 6-1 SECTION 7.0 RECOMMENDATIONS 7.0 RECOMMENDATIONS The Alaska Power Authority concludes the transmission requirements of the Bradley Lake Hydroelectric Project can best be met by constructing two parallel weathering steel X-tower type 115 kV transmission lines with steel H-pile tower foundations along the refined transmission line route. 3-028-mc 7-1 SECTION 8.0 BIBLIOGRAPHY 8.0 BIBLIOGRAPHY Alaska Heritage Research Group, Inc. 1986. An Archeological Survey Near Caribou Lake, Southcentral Alaska. Prepared for the Alaska Power Authority. June. 12 pp. Alaska Power Authority. 1985a. Mitigation Plan. Prepared by Stone & Webster Engineering Corporation for the Alaska Power Authority, Bradley Lake Hydroelectric Project. November. Alaska Power Authority. 1985b. Terrestrial Impact Assessment Report. Prepared by ENTRIX, Inc. and Stone & Webster Engineering Corporation for the Alaska Power Authority, Bradley Lake Hydroelectric Project. November. Alaska Power Authority. 1986a. · Vegetation Clearing Plan. Prepared by Stone & Webster Engineering Corporation for the Alaska Power Authority, Bradley Lake Hydroelectric Project. March. Alaska Power Authority. 1986b. Visual Resources Mitigation Plan. Prepared by Stone & Webster Engineering Corporation for the Alaska Power Authority, Bradley Lake Hydroelectric Project. March. Cutler, R. B. 1986. April 18, 1986 letter from State of Alaska, Department of Natural Resources, to Tom Armin ski, Alaska Power Authority. Olendorff, R. R., A. D. Miller, and R. N. Lehman. 1981. Suggested Practices for Raptor Protection on Powerlines -The State of the Art in 1981. Raptor Research Report No. 4. Raptor Research Foundation, Inc. St. Paul, Minnesota. 111 pp. 3-028-mc 8-1 Woodward-Clyde Consultants. 1984. Historical and Cultural Pedestrian Survey. Prepared for the Alaska Power Authority, Bradley Lake Hydroelectric Project. December. 22 pp. plus appendices. Yanagawa, C. M. 1986. April 24, 1986 letter from Alaska Department of Fish and Game, Division of Habitat, to Tom Arminski, Alaska Power Authority. 3-028-mc 8-2 Code 10 20 22 23 26 27 28 51 62 71 84 TABLE 1 Acreages of vegetation types oacuring within the right-ot-way of the refined and FERC transmission line routes. 1/ Vegetation Type Refined FERC Route Route CONIFEROUS FOREST 572.0 533.4 Closed coniferous forest 384.5 352.4 Open coniferous forest 187.5 181.0 open coniferous forest 60.7 57.6 open coniferous forest/tall alder 10.0 0.3 open coniferous forest/tall alder/ low willow/mesic herbaceous sedge-grass 8.6 4.6 open coniferous forest/bog 31.2 13.7 open coniferous forest/low willow 42.2 63.0 open coniferous forest/low shrub/ low willow 34.8 41.8 DECIDUOUS FOREST 4.1 ·18.7 Open deciduous forest 4 .• 1 0 open balsam poplar forest 4.1 0 Open paper birch forest 0 18.7 open birch forest/tall alder 0 18.7 MIXED FOREST 3.1 26.0 mixed spruce-balsam poplar forest, closed and open 3.1 26.0 TALL GRASS TYPES 7.1 21.2 tall grass on flats 7. 1 21.2 3-028-JW Table 1 (continued) SHRUB TYPES 180.2 128.7 Tall alder 65.6 39.0 101 tall alder 52.8 32.0 103 tall alder/freshwater herbaceous sedge-grass 12.8 7.0 105 Tall willow 2.8 1.8 Low shrub 111.8 87.9 112 low willow 0 9.0 113 low shrub bog 111.8 78.9 SEDGE-GRASS TYPES 41.6 27.1 121 mesic herbaceous sedge-grass 14.7 15.5 125 freshwater herbaceous sedge-grass 2.7 9.2 126 saltwater herbaceous sedge-grass 24.2 2.4 UNVEGETATED AREAS 31.6 7.3 131 pond 1.1 141 tidal river or stream 7.4 142 low gradient perennial stream or river 13.4 152 low gradient perennial river or stream/ floodplain _iJ TOTAL ACREAGE 839.7 762.4 11 Corridor right-of-way 350 feet wide between PI1 and PI10 and 400 feet wide between PI10 and PI16. 3-028-JW SECTION 1'0,0 FIGURES BRADI£Y JUNCTION r-HOMER ELECTRIC ASSOCIATION FRITZ CREEK-SOLDOTNA 118 KV I TRANSMISSION LINE I I REFINED TRANSMISSION LINE ROUTE .· \ ..... .. REVISED 4/8/88 u 5 ···~· .. -.~~ .. \ .... -· .. -~ ~ ... ·'--< II W m r-u 3 I -· .. · ... :: .•· ·'· .. / / ' / \ \ \ z 0 i= 0< -> lw X._~ 1-w ct:Jw a: w 3: 0 1- I X -1 w w 1- f/) w ::i < a: u. :!: ~ 0 Cl.. 0 0 0 3: 0 cr.; UJ (") ~ w 0: ::::> en (!) i -u. z < a: 1- a: UJ := 0 1- I X ..J UJ UJ 1-en 0 0 0 0 0 ~ 0 0 0 0 [ D 0 0 0 0 D • O'b!"- • g•r " -......: < ......... \ .... SEWARD SECTIONAL AERONAUTICAL CHART ~~fffil:2i££!i.J~~~Ii! FIGURE 4 ---------------------------· ---. OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL REPORT ------------------------------~ BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY -REFINED TRANSMISSION LI.NE ROUTE VEGETATION MAP ----------.------y-------1' --~ STONE & WEBSTER E IBIT I ~ ENGINEERING CORPORATION XH FIGURE 5 ) ~---------L..------....L--------f' - "' / ' SECTION 11.0 ~' AGENCY CONSULTATION ... 11.0 AGENCY CONSULTATION CHRONOLOGICAL INDEX OF CORRESPONDENCE Date November 6, 1985 February 5, 1986 February 26, 1986 March 21, 1986 March 24, 1986 April 10, 1986 April 11, 1986 April 15, 1986 April 17, 1986 April 18, 1986 April 18, 1986 April 23, 1986 April 24, 1986 April 25, 1986 April 25, 1986 April 30, 1986 3-028-mc Source of Correspondence Notes of Telephone Conversation, Stone & Webster Engineering Corporation Agency Review Meeting Notes of Conference, Stone & Webster Engineering Corporation Alaska Department of Fish and Game, Division of Habitat Kerr and Associates Alaska Power Authority Notes of Telephone Conversation, Stone & Webster Engineering Corporation Alaska Department of Natural Resources, Division of Land and Water Management Agency Review Meeting Notes of Conference, Stone & Webster Engineering Corporation U.s. Department of the Interior, Western Alaska Ecological Services Alaska Department of Natural Resources, Division of Land and Water Management Trip Report, Corporation Stone & Webster Engineering Alaska Department of Natural Resources, Division of Land and Water Management Alaska Department of Fish and Game, Division of Habitat Stone & Webster Engineering Corporation Alaska Department of Natural Resources, Division of Parks and Outdoor Recreation Land Field Services, Inc. 11-1 April 30, 1986 April 30, 1986 May 2, 1986 May 2, 1986 May 5, 1986 May 5, 1986 May 7 t 1986 May 23, 1986 June 4, 1986 June 5, 1986 June 19, 1986 July 3, 1986 July 7 f 1986 July 9, 1986 July 11, 1986 3-028-mc Source of Correspondence Alaska Department of Natural Resources, Division of Land and Water Management John M. Bridges, Wildlife Biologist Alaska Department of Natural Resources, Division of Land and Water Management Alaska Department of Natural Resources, Division of Land and Water Management Alaska Department of Natural Resources, Division of Land and Water Management Alaska Power Authority u.s. Department of Canmerce, National Marine Fisheries Service Alaska Department of Natural Resources, Division of Land and Water Management Alaska Department of Natural Resources, Division of Land and Water Management Agency Review Meeting Notes of Conference, Stone & Webster Engineering Corporation Alaska Power Authority Notes of Conference, Stone & Webster Engineering Corporation Notes of Telephone Conversation, Stone & Webster Engineering Corporation Notes of Telephone Conversation, Stone & Webster Engineering Corporation Notes of Conference, Stone & Webster Engineering Corporation 11-2 / \ J.O. No. iSSOO -i oi' _L_ Al~sk3 Power AuthoritY r:;t ~ wf'q-g JJ-1 a'- fiT/.4,3 File No. 15500. ( J"Z... ) INSTRUCTIONS: Summarize your phone discussion, noting participants, date & time of call. Indicate desired distribution at right. Call reporter must insert File Number(;) and Subject(s) in file box above. Clerk takes care of Chrono file copy and distribution. I DISTRIBUTION: JJMPlantefDLMatchett DOC GF )( JJGarrity/Chron Files ;>( T Critikos/Bee JM:: -::X,..A..-- DPRyan )c: JMMissel :X NABishop/ANCJBk TK~ WP~ ~ LCDuncan CLClark TTReilly GEEng M L Rp,St»\'N.>'Ns::.t=> :>< Call Date II r s, ~~S' Time ~·. \~ P!") Incoming----Outgoing X Between NoR-m \S\S'W<:>P SWEC & ____________ ___;;APA D'"E ~c.ru..\'N~9.M SWEC & B,oe C\l:n-S,. & ~\'<..£ <0St~~i~ Originated by: _...~N~·t...~.:::!..l\uSaJ:'MS:RIIE:Iill~:..------- DISCUSSION: \:J\ScS>SS\4bN WS\& 4S.\Q 2-~WitAQ\~fa £\S>~ ~ 2\ 1:sN ~ F' uE: 9> 'it.l bUS -$)<C:'-\Na9ct \) !!!Sttb.....,. M~\.\ym\'t=~ . &a. C&s«:r\~ "'l..aN~ 'SO-L\~"§_b-W u..)c.y,.:>QE.'S) \).\ ~ £$QC. \.\C~~ 5;§9'!\..\CJ¥\S>N. \~S>L\.~~~ N,.,..,. Sii:n--' ~§">.\QE!Ij) 9::3\)L,c trns.w ot:\wc...'fS. 1"Wf. 5&\b"«'t-(\,. -w~, \S S'"\~t!r\..\'j.5l> f<..\:)~ \Jb)t:>S$j'SM>'S>' SibNS> C&~(S)g$ 'N'3'W hl~ ~ ~yv..osc\1 '"S'S;!. ""S'5c.s mtrt"ss.cs rHEee; t 2 t-Jo c.os:r tog_ J"B\<; li?lb\41-DF-WAlf. BL-D-99:md NOTES OF CONFERENCE ADF&G STIPULATIONS BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY Held in the SWEC Conference Room Anchorage, Alaska February 5, 1986 Present for: J.O. No. 15800.12 WP 98D-6 Alaska Power Authority (APA) T. Arminski D. Trudgen Agencies: Don McKay ADF&G/Habitat Phil Brna ADF&G/Habitat Hank Hosking USF&WS Stone & Webster Engineering Corporation (SWEC) N. Bishop M. Fisk E. Puch The Attendence Sheet is Attachment 1. Attendees agreed to go through the Coastal Consistency Letter under ADF&G Title 16 Permits -Eleven permits Items A-K to develop appropriate stipulations listed below: a. b. c. d. e. f. g. h. L 2-283-JJ Activity Bradley River Dam Airstrip Powerhouse & Switchyard Barge Dock & Staging Area Lower Camp (including effluent discharge) Martin River Material Site Transmission Line Spoil Disposal/Waterfowl Nesting Area Martin River Material Site Access Road Bradley River Fox River Flats Critical Habitat Area Kachemak Bay CHA Kachemak Bay CHA Kachemak Bay CHA Martin River Bradley River Fox Creek Fox River Sheep Creek Fox River Flats CHA Kachemak Bay CHA Battle Creek Kachemak Bay ( (.. Stipulation for Barge Dock and Staging Area "No sheet pile shall be driven during the period of May 1 through 15". CONSTRUCTION CAMP The Construction Camp requires no special stipulations. MARTIN RIVER BORROW SITE The Martin River Borrow Site requires no special stipulations. TRANSMISSION LINE The transmission line will require stream crossing permits once the ADNR Right-of-Way permit is submitted. The stipulations were deferred until the transmission right-of-way is finalized. WATERFOWL NESTING AREA The Dredge Spoil Disposal Area/Waterfowl Nesting Area needs no stipulation. MARTIN RIVER ACCESS ROAD The Martin River Material Site Access Road requires stream crossing permits until the bridges are in place. The bridge abutments need to be kept out of the active slough and river channels. Stipulation for the Martin River Material Site Access Road "Until such time as the bridges are completed construction equipment will be allowed to cross the tidal slough and Battle Creek during the period May 15 and July 15 only. The stream bottom at the stream· crossing sites must be graded and smoothed at the end of this period. Bridge abutments will not be allowed in the active channel of the tidal slough. To protect the Battle Creek stream channel and bridge abutment rip-rap may extend into the stream channel but cannot restrict flow." ACCESS ROADS The roads require no addi tiona! stipulations as all construction is restricted to within the work or clearing limits. MFisk:JJ 2-283-JJ 5 l , •. ~ hirua7 6; /7'86 4~ 7B;77 sf~4~H?s ~~ ,~ ·.-• I • •• -:: ... . , . . .· . . .· -' .. , ... ·. '~ . " : . . ·_.. '·" • '.~ l .... · -~~ _'7~ :·_ /j_ ~Q.:JNV CG;-13v R E ~: f I V ED P 2/l'f~ \k\ ~ ( t; I ti MEMORANDUM ~,-.0 •. 1986 State of Alaska ro Patty Bielawski, Project Coor~O~~E ..,q~re: Office of Management and Budget · · · L~-·.•::0 .. ::._._ Division of Governmental Coordination FILENO: February 26. 1986 Anchorage FROM Dennis Kelso, Deputy Co~m~issioner Department of Fish and Game SU~EC~ ID#851213-14A 071-0YD-2-850502 Alaska Power Authority Bradley Lake 1 ~()'V\.<-~ 0 ' \{\<-¥.,"'\ BY: --nonald 0. McKay \ Revised Consistency Finding Habitat Biologist Habitat Division Anchorage The Alaska Department of Fish and Game (ADF&G) has reviewed additional technical specifications for design and construction of the Bradley Lake Hydroelectric Project since our consistency reconmendation of 13 January . 1986. In addition, we met with representatives of the Alaska Power Authority (APA) on 5 February 1986 to discuss stipulations to be included in AOF&G Title 16 permits. Based on these events, we have developed additional (. stipulations to be included in the revised consistency finding. ' The department finds that Title 16 pennits will be required for the following activities: Activity Area Authoritl a) Bradley River Bradley River AS 16.05.870 Dam b) Airstrip Fox River Flats AS 16.20.260 Critical Habitat Area c) Powerhouse and Kachemak Bay AS 16.20.260 Swi tchyard Critical Habitat Area d) Barge Dock and Kachemak Bay AS 16.20.260 Staging Area Critical Habitat Area e) Lower Camp Battle Creek AS 16.05.870 (including effluent discharge) f) Martin River Martin River AS 16.05.870 Mate ri a 1 S i te g) Transmission Line Bradley River AS 16.05.870 Fox Creek AS 16.05.870 Fox River AS 16.05.870 Sheep Creek AS 16.05.870 02.001A(Rev. 1()179) ......... ( . '' I'" • ,-•: ' ' • : ~. o, • .; ·• I Ms. Patty Bielawski -2- Fox River Flats Critical Habitat Area h) Spoil Disposal/ Kachemak Bay Waterfowl Nesting Critical Habitat Area Area • • -~ ... t· .• February 26, 1986 AS 16.20.260 AS 16.20.260 i) Martin River Battle Creek AS 16.05.780 AS 16.20.260 Site Access Road Kachemak Bay Critical Habitat Area j) Airstrip to Fox River Flats Powerhouse Road Critical Habitat Area Kachemak Bay Critical Habitat Area k} Powerhouse to Kachemak Bay Camp Access Road Critical Habitat Area AS 16.20.260 AS 16.20.260 AS 16.20.260 Because of the complexity of this project. the department will issue separate permits for each of the eleven activities. The plans and specifications, and mitigation plan are part of the permit applications and are therefore incorporated by reference in the permits. The department recommends that this project be found consistent with the Alaska Coastal Management Program (ACMP} subject to the following stipulations which will be included on each of the eleven required Title 16 permits: 1. Revisions to the plans and specifications or mitigation plan which deal with activities regulated by the department under its various statutory authorities will require departmental approval and/or permit amendment. Plans of Operations for construction of permitted activities shall be submitted to the department for review and approval for compliance with stipulations contained herein. The department reserves the right to condition the approval and to require mitigation as appropriate. 2. The APA shall upon request, furnish transportation from Homer to the project site and quarters ·for department representatives to inspect project activities. 3. Routes to minimize flights over concentrations of wildlife in Kachemak Bay and Fox River Flats Critical Habitat Areas will be developed by the Power Authority and approved by the ADF&G. 4. Access to the project site shall be limited to air access and water access only. Construction activities and access will be restricted to within the clearing limits or working limits shown on the construction drawings. Landing craft and shallow draft barges may beach near the Martin River borrow site on the gravel · .. . -· . . . "'~ ... : ~-'· '':'-~·· . -..... -. .... . ... ' .. Ms. Patty Bielawski -3-February 26, 1986 outside the work area, near the construction campsite between Access Road Station 590+00 to 595+00 only in the work limits, in the powerhouse area Access Road Station 520+00 to 490+00 only within the work limits, and near Sheep Point Access Road Station 567+00 to 550+00 only within the work limits. Landing areas shall be accessed as follows: at the campsite when the tides exceed elevation 7.0 feet (project datum), at the powerhouse when tides exceed elevation 6.0 feet, at Sheep Point when tides exceed elevation 4.0 feet and at the Martin River Borrow Site when tides exceed elevation 0.0 feet. The barge dock area may be used for access when the tide exceeds elevation -4.0 feet {project datum) within the work limits only. 5. Access areas and work limits of project features shall be surveyed and staked in the field. 6. Plans and specifications for access to and construction of the transmission line within Fox River Flats Critical Habitat Area and crossings of fish streams shall be developed by the APA and approved by the ADF&G. In addition, the following stipulations will be placed on specific permits to ensure consistency with the ACMP: A. Bradley River Dam 1. The lake drawdown to initiate diversion through the tunnel shall be controlled so that the Bradley River flow remains within 1.5 times historical average monthly flow as measured at the USGS Gauge above Riffle Reach in the Lower Bradley River. · 2. If initial filling of the reservoir begins between January 1 and July 1, then during this period flows measured at the USGS streamflow gage near Riffle Reach in the Lower Bradley River shall be a minimum of 40 cfs during reservoir filling. After July 1, flows shall be increased 5 cfs per day to 100 cfs by July 15. Thereafter, the following minimum flows shall be maintained as measured at the USGS streamflow gage near Riffle Reach in the Lower Bradley River to the extent controllable at the Bradley lake Dam: May 1 through September 15 September 15 through October 31 November 1 through April 30 100 cfs 50 cfs 40 cfs 3. During project operations (after initial reservoir filling), the minimum stream flows as measured at the USGS streamflow gage near Riffle Reach in the Lower Bradley River will be Kerr and Associ ares----------------- Mr. Del LaRue Dryden and LaRue 6436 Homer Drive Anchorage, A 1 ask a · (Hand Delivered) Dear Mr. LaRue, 21 March 1986 This letter report is a follow up to our discussion on Wednesday. March 19, at your office, regarding the proposed Bradley Lake transmission corridor. In our •Timber ReconnaissanceM report to the Alaska Power Authority (APA), dated January 21, Dick Sanders and I noted clearing will expose the residual timber to both windthrow and subsequent bark beetle infestation. · Specifically, on page 24: "This segment (the transmission line) and the support facility wi l1 likely experience moderate to severe windthrow problems from trees newly exposed to down slope and southeasterly winds ••• exposed stand boundaries will "unravel" along the. road, construction areas, and any cleared area under the transmission line. Prompt removal or treatment will keep insect hazard low." We discussed this on Wednesday with Tom and Mark Baringham. I gathered research material on blowdown from the U.S. forest Service and have summarized it in this letter along with recommendations. The Problem. Windthrow commonly follows initial cutting in Alaskan coastal forests. Interior trees have not been exposed to wind stress along their full stem lengths; roots and stem support systems are not able to withstand the wind. The worst case scenario would find significant blowdown.and a major beetle infestation followed by fires; the most likely case would be some blowdown·requiring "maintenance" or clean up for several years. The best situation would be not exposing any interior timber. Once windthrown. spruce trees provide an ideal breeding ground for bark beetles that can grow rapidly to epidemic proportions and emerge to attack living trees. This happened at Tyonek when oil company seismic lines were cleared and trees left untreated. The dead trees are a fire hazard and aesthetically "jarring"; the Summit lake area is a good example (on the Chugach National forest) of beetle killed trees with both characteristics. There were few bark beetle infested trees in the areas we cruised. However, timber felled by the Corps for helicopter landings has apparently attracted large numbers of beetles. Dave Trudgen (APA) and Jim Peterson (State Division of Forestry) visited the area after our report was written. P.O. Box I I 1293 • Ar.,:horage. Al<lska D!lSI I • (007) 346·3141 /346·1624 - Wind. I found wind rosettes for the Kodiak and Kenai areas only. A copy is enclosed, as published in the University of Alaska Regional Profiles. It appears that southeast to southerly winds are common storm winds in the area. Hazards. The following are listed from the three (3) sources collected. 1. Blowdown is greater on the leeward sides of ridges. 2. More damage is noted on upper slopes, less damage is found along bottoms where wind turbulence is less pronounced. 3. Slowdown is ~ore severe on areas of high water table and/or very shallow soil. 4. Saddles, notches, and valleys will channel winds and create greater local turbulence. Mitigation. There are several possible mitigating factors. I. Cutting lines may be located parallel to prevailing storm winds. 2. Heavy blowdown will be found quite soon after exposing the stand. Losses will decline as trees grow root systems to compensate. Plan for salvage prior to cutting (e.g. roads). 3. Leeward boundaries may be thinned to "lift" the wind and decrease pressure on exposed crowns and stems. Leave strips are ineffective, based on my experience on Prince of Wales Island. Winds find an area of least resistance and "blow ~ut" narrow portions of the strip. Later winds widen the opening an~ eventually create a continuing salvage problem. I -have enclosed a photocopy of a leave strip on Prince of Wales that I checked with an ADF&G Habitat Biologist in the mid 1970's. The area we are walking in was originally a minimum of 100 feet in width; you could not see through the leave strip. Identification. Alaskan experience suggests hazard identification as the first step in estimating the problem. I have enclosed copies of one of the references, "A Presentation to the Logging Systems Workshop on Minimizing Windthrow as a Result of Logging" by Bob Burke, February 12, 1979. Dick Sanders and I did not find any major patches of windthrow. The occasional tree found was-blown down by southeasterly winds, at least on ~Y sa~ple plots. The stand is young and windfirm at this time. Recomnendatfons. Either Dick Sanders or I could prepare the hazard overlay discussed in Burke's paper. This could be compared with likely corridors and areas of major problems identified. Keeping the corridor as lo\~ as possible (on the slope) and cutting a minimum amount of timber (or none at all) is the easiest solution. I suspect serious chalJenges would be made to relocating the corridor out of timbered areas. In that event, an outside Mexpert" in the field of windthrow should be considered. I believe Dr. Bob Ruth and Dr. Bob Alexander are both retired now from the U.S. Forest Service and could possibly serve in that capacity. Bob Burke is still working for the Forest Service in Petersburg and could possibly be retained through an Intergovernment transfer for a week or so. References. I used three (3) publications, listed below. 1. "Reducing Wind Damage in the Forests of the Oregon Coast Range" by Dr. Robert Ruth and Ray Yoder, Research Paper Ho.7, U.S. Forest Service, July, 1953. 2. "Minimizing Windfall Around Clear Cutting in Spruce-fir Forests" by Dr. Robert R. Alexander, U.S. Forest Service, June, 1963. 3. ''A Presentation to the Logging Systems Workshop on Minimizing Windthrow as a Result of Logging" by Bob Burke, Forester, U.S. Forest Service, February, 1979. Let me know if I can help with hazard overlays or in securing services of an outside expert. Sincerely, Calvin L. Kerr Forester CLK;clk encl cc: Mr. Richard C. Sanders \ ";) (:) UV • v I I.~ ( \ NOTES OF CONVERSATION WITH FORREST SERVICE IN PETERSBURG, AK April 10 1 1986 Caller: Called: Ron Krohn, Lead Electrical Engineer, SWEC Bob Burk, U.S. Forrest Service, Petersburg, Ak (Cl.o\l '"111.-~~\ 1 Discussed having Bob evaluate our transmission line corridor for windfall along a cleared corridor. Also, if we need to write a scope of work to have him come to the site, we would have a better idea of the requirements that need to be in the scope of work. Bob requested that I bring a set of "stereo covers" of the entire route along with some kind of aerial photos showing know windfall/unravelling problem areas. With this knid of information, he should be able to assess the type of problem. One of the things I need to discuss with him on the meeting is how much clearing should be required in specific areas of the corridor. The current plan is that I will have a set of stereo covers run by Walker Alaska to take along with me. I will travel on April 17 and meet with Bob on that day and the next morning if necessary. If problems arise, I can stay over and return on the 19th. Ron Krohn Lead Electrical Engineer f" I~ .1. II'\""- ~ c.o-J-.1 ,._ ~ ~-e 112 -'{Z..8<6 ll2--L-!'2..~ \ 1 DEPARTMENTOFNATURALRESOURCES DIVISION OF LAND AND WATER MANAGEMENT April 11, 1986 Gary L. Ransan Right-of-Way Agent Alaska Power Authority P.O. Box 190869 Anchorage, Alaska 99519 Oear Mr. Ransom: REC!IVf!) ~y ALASK:. :-· · :· · -.·,.-, · ·J .86 ABR 18 BILL SHEFFIELD, GOVERNOR 555 CORDOVA STREET POUCH7.oo5 ANCHORAGE. ALASKA 99510..7005 PHONE: (907)276-2fl53 You have asked questions in your Ma.rch 24, 1986 letter about the Seldovia exchange that do not have clear answers; first a short background. The state's catmittment to the Seldovia exchange canes fran a May 7, 1979 memorandum of understanding between the state, the Kenai Peninsula Borough, Seldovia Native Association, Inc. and Cook Inlet Region Incorporated. In this memorandum Seldovia Native Association (SNA) and the state agreed to a full exchange of all SNA 1 and within Kachemak Bay State Park for state land. A shortfall of this agreement is that it sets no deadline for completion of the exchange~ Progress has been made over the years in two small phased exchanges and this particular proposal you have asked about was to result in the completion of tne exchange. The value of the state land offered in this exchange proposal exceeded a threshold dollar limit and thus required legislative approval for completion. SNA did not accept the land appriasal report and we therefore did not enter into the final exchange agreement that should have been submitted to the legislature in January. SNA did, however, introduce through their local legislators their own bill for completing the exchange. Tl1e state fee 1 s the tenns of this bill are unf.avorab 1 e to the state's int~rests and has not supported it. It seems u'llii<ely at this time that the land near Caribou Lake that you are intere.sted in will be conveyed to SNA this year. There is however, an unfulfilled committment to complete this exchange and these lands may remain segregated fran the state public domain for an attempt next year to canplete the exchange. It is therefore not possible to answer your 1 ast three questions with any credibility. r f a 1 tern ate possible, a appropriate. routing for the Bradley Lake transmission line is not right-of-way application to cross these lands may be The current land status does not prevent ONR from processing Gary L. Rans<l"1 Page 2 April 11, 1986 such an application on lands contained in the state's Seldovia pool. The outccme of any such application will depend on canments received through agency and public review. Sincerely, Dennis P. Oaigger, Manager Special Projects Unit cc: Meg Hayes, SCRO Tom Hawkins. DLWM 7) ~.:(~~;:; .. ·.· NOTES OF CONFERENCE AGENCY DESIGN REVIEW BRADLEY LAKE HDYROELECTRIC PROJECT ALASKA POWER AUTHORITY Held at Stone & Webster Engineering Corporation (SWEC) Conference Room 800 "A" Street, Anchorage, Alaska April 15, 1986 at 9:00 AM PURPDSE Present for: J.O. No. 15800.12 WP 98A Alaska Power Authority (APA) Tom Arminski Dave Trudgen Dames & Moore Jim Hemming John Morsell Dryden & LaRue, Inc. Del LaRue Agencies Hank ijosking, USF&WS Robert Cutler, DNR Deborah Heebner, DNR Bill MacClarence, ADEC Mike Lewis, ADEC Dan Wilkerson, ADEC Tim Rumfelt, ADEC Don McKay, ADF&G/Habitat Stone & Webster Engineering Corporation (SWEC) Norm Bishop Ron Krohn Elaine Pucb The meeting was held to discuss (1) Project Status, (2) Transmission Line Alignment, (3) Site Preparation Contract Bid Documents, (4) Proposed Salmon Escapement· Survey Methods, (5) Vegetation Clearing Plan, (6) Erosion Control Plan, and (7) Visual Resources Mitigation Plan. Attachment 1 is the agenda. Attachment 2 is the sign-in attendance sheet. Attachment 3 is a draft of the Assessment of Transmission Line Alternatives. Attachment 4 is a draft of the Salmon Escapement Survey Scope of Work. 2-533-JJ 1 of timber to be burned was not stated. The ADEC calculated close to 2700 acres to be burned. Mr. MacClarence was also concerned about the control strategy for smoke. ADEC is concerned that this would have the potential to be another Point MacKenzie. Mr. Bishop explained that the total clearing in Phase I is less than 77 acres. The powerhouse clearing is complete, the roads will be run along the tidal flats where possible. Clearing will be done in the camp site area and the Martin River. Some of the timber to be cut is cottonwood. Timber classified as commercial will have the bark removed. Timber to be used for house logs will not have the bark removed. Mr. calvin Kerr, Forester, determined there would be enough logs to construct approximately 1 to 2 houses. No reservoir clearing or transmission line clearing will take place under Phase I site work. The ADNR is concerned about use of the timber if merchantable. Merchantability will be determined through on-project utilization or timber sale. It is expected that the contractor will bury slash and debris from road clearing due to the narrow road width. Spoil locations have been identified and a permit submit ted. It is made clear to the contractor in the bid documents that he will need to obtain a ADEC permit to burn slash and debris. The ADEC asked that the opacity standards be explained for incinerators. Mr. Bishop responded that the incinerator specification is complete and that the incinerator is sized so that a permit is not required for its operation. Mr. Dan Wilkerson requested a few points of clarification be made to the bid documents.-Solid Waste permits must be obtained as well as food service permits and a plan review for potable water. The contractor will be the operator for the temporary facilities. Mr. Bishop responded that the wastewater from the permanent camp leach field will have zero discharge. The water rights are being obtained for the permanent camp well. The bid docunents include information to flag permits that have been obtained or are needed. Dames & Moore will be responsible for permit tracking for compliance. 3. Transmission Line Alignment Del LaRue or Dryden & LaRue, Inc. discussed the work completed to date on the transmission line design and the alignment. Th~ current plan is to do a centerline survey this summer and a fabrication contract in 1987/88 followed by a construction contract. The line will consist of two individual tower 115 kV circuits. The types of structures being considered are the wooden H frame and the steel X tower. The steel X tower is simple, stronger and fewer towers per mile are required, therefore, the spans can be increased. On an economic basis there is no significant cost differential. Mr. Hosking asked if foundations had to be built for the towers. Driven steel H-pile foundations are proposed. No concrete foundations are anticipated. The foundations in the Fox River Valley will have riprap armament. The Corps of Engineers route has been modified and the line terminates at the Homer Electric line. The line runs parallel to section lines and avoids swamps and private property where possible. Exceptions are where the line crosses the . SE corner of the Swanson property and the western edge of the Hilmer-Olsen fox farm. Coming out of the Fox River Valley near the 2-533-JJ 3 ' '~"'; : Swanson property, the transition from plateau to valley is made in one span thus eliminating towers on the hillside. The Fox River Flats emergency airstrip is avoided. The towers will be of varying height depending on the topography (approximately 80 to 85 ft). A windthrow problem may exist on the steep spruce covered slopes north of the powerhouse. These trees have weak root support systems. If a right-of-way is cut through this vegetation some additional trees may blow down. Therefore, the line bas been moved down from the hillside to span knob to knob. Right of way clearing has been greatly reduced. Windtbrow consultation with Mr. Bob Burke of the U.S. Forest Service in Petersburg, Alaska has been on-going. Mr. Burke has worked on windthrow problems in logging operations in Alaska and has been asked to investigate the severity of the problem and to m1n1m1ze this problem. Mr. Ron Krohn (SWEC) will be meeting with Mr. Burke on Thursday and Friday, April 17 and 18. Mr. Don McKay requested the notes from Mr. Krohn's meeting with Mr. Burke. With regards to aesthetics, the lines will alter the visual quality of the area and be in contrast with the existing natural character. Mr. Norm Bishop summarized the attempts being made to address environmental concerns. All streams and the Bradley River will be crossed perpendicularly, minimal crossing of wetlands will be done, clearing will be minimized, the Fox Farm buildings will not be disturbed, no towers Will be located· in the flats. A question was raised as to what type of access is needed to put up the lines and towers. Del LaRue responded that in certain areas it may be done by helicopter. Some sections could be erected with ATV's. It was noted that Don McKay had not seen the alignment before today. Mr. McKay will send comments in a few weeks. Hank Hoskings asked if a higher wire span would be used in the pond area near the Olsen Fox Farm to accommodate the flight path of the water fowl. Hr. LaRue said the towers could be heightened to accomplish this. All that changes is the economics of the tower design and the limitations of space on the knobs for the foundations. Attachment 3, the Draft Assessment of Transmission Line Alternatives was distributed at the meeting. Written comments were requested by the end of April. 4. Salmon Escapement Survey Attachment 4, the Draft Salmon Escapement Survey, was distributed. Mr. Bishop indicated that this document was a working copy and comments were requested. Comments are to be submitted by the end of April to Mr. Tom Arminski, APA. A request was made that Brad Smith, NMFS (who was not in attendance) be sent a copy of this survey. 5. Vegetation Clearing Plan ADEC voiced a concern that the contractor clearly understands the requirements and permits needed for burning as a method of disposing of 2-533-JJ ·").·" ' . ..... APRIL 15, 1986 AGENCY MEETING BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY AGENDA Attachment l Held at 9:00 AM at the office or Stone & Webster Engineer ~orporati~n, 800 •A" Street, Anchorage, Alaska. 1. PROJECT STATUS 2. TRANSMISSION LINE ALIGNMENT 3. SITE PREPARATION CONTRACT BID DOCUMENTS 4. SALKIN ESCAPEMENT SURVEY 5. VEGETATION CLEARING PLAN 6. EROSION CONTROL PLAN 7. VISUAL RESOURCES MITIGATION PLAN 2-506-JJ ······ ······· ..•...•.•. ~.·-"····-~-" ...... ~.\.-~.·~t-..· ... ,.,. _.,._., ............ . tl ~ ).io~u f31Sf.IO~ ; j~ A~ J~· jt.' :t:~·-i ve.. -Vet£( ~en. f/AH /<C. !lo.sR'/,.J t7 f;. t c"' f/er t~~~w~"-. He e.lo ''vY 41 i-!1-e~«JIItlltl:f' ,·-j ~ f\ll e r-~ 1/ T2e-t.. t.,;z {?;r Lot0 'l_-ro~\' f/jjtiVE.. '7/_, ({!- () 1 / f /Vf J C. C/rl ~ "7 r ~ .:. 1;'!-:c L ~ ~.v,· 1 ,,'~ 11)~~/i12.S'fA./ . ~ ;f{,m/l.t.T ... . \/\IV~ ,.....C\t\ PI-, -~ ATTENDANcE AG>E.tJC.y M E'E Tl NG:.. A'i>RlL 15,1'i9lo AGENcy ::5-r;,,.;e ~ WB~JC!:f2- At:. (Yow iL rz. A v.-fh- 4-Pft F ti.J S A/'A DN~ ./)a.t~SJ./41161'6 ' o~.,.. t1AI}4U'e_ ~Ybtr.v{4:z&t. ~e. SwL_c_ Sw£c Aoc=c 4PFc AD~ ft'De=-c.. P;.\J;. ~ " It-ir-A),\..~ Attachment 2 PI-toNe fr 277 ~ z. q.c_ 1 ~6 i -t-e;:; .56~-787 7 7C2-:Z.:t 7 9- 1& )._-).). --:tf ~'L -3J'-~ ._r, (_ -)] c," . .:::Sc:f?-~6~5 z. ( -z -Z..J·{ z_ l z 77-2.40 7 z::e?-z':>-3_s 2 77'-25".?? :l-7 ~ . ';f _:) 3 3 r • ) DRAFT ASSESSMENT OF TRANSMISSION LINE ALTERNATIVES 1.0 GENERAL Alaska Power Authority proposes to construct two parallel 115,000 volt ( 1 1 5 kV) transmission lines from the Bradley Lake powerhouse to the Fritz Creek-Soldotna 115 kV transmission line (Bradley Junction), planned for construction by Homer Electric Association (Figure 1). The Alaska Power Authority has considered several route and structure alternatives, including {1) FERC alignment, (2) refined FERC alignment and (3) submarine cable. 1.1 Previously Considered Route A total of three alternative route alignments were addressed in the Alaska Power Authority's Application for License and the Federal Energy Regulatory Commission (FERC) Final Supplemental Environmental Impact Statement. The FERC alignment, which was included in the FERC License issued December 31, 1985, is shown on Figure 2. As an alternative to routing the proposed transmission lines in the rugged, tree covered terrain between the powerhouse and the Fox River Valley crossing point, the Alaska Power Authority, during 1985 conside~ed locating the .115 kV lines on the Kachemak Bay mud flats. C'onstruction of' overhead transmission lines on the mud flats would infringe upon the Fox River Flats Critical Habitat Area. The transmission lines would also be threatened by foundation failure resulting from soil liquefaction. Because of these problems, this route alternative was eliminated from further consideration by the Alaska Power Authority. 1.2 Submarine Cable Route The Alaska Power Authority also evaluated the use of submarine cables. Each of the proposed 115 kV transmission lines would require a to tal 3-028-mc -1- of four cables (three cable circuits plus one spare}. Installation of these cables within the mudflats would be quite difficult and expensive. Unlike a typical submarine crossing, where most if not all of the cable is placed directly on the floor of the effected waterbody, the Bradley Lake cables would be trenched and buried for their entire length. Each line (four cables total} would probably require its own trench. Data indicates that cohesionless, saturated soils would likely be encountered along at least part of the trench routes. These granular materials could make it difficult to hold trench walls in place and/or cause water problems within the trenches. Additionally, heavy cable reels (approximately 60 tons per phase per run) would have to be removed from a barge and transported over the mudflats for instal- lation in the trenches. This movement of heavy materials and equipment could create significant impacts on the Fox River Flats Critical Habitat Area. It is estimated that the submarine cable option would cost approxi- mately 4.5 times more than a comparable length or overhead line. Because or this additional cost, along with the above mentioned construction difficulties, use of submarine cable was not considered rurther. 1.3 Refined FERC Route Public concern and further evaluation and refinement of the FERC alignment, conducted as a part of the Project's design phase, has resulted in a third possible alternative (Figure 2). Although both alignments are feasible, the refined alignment offers certain advantages over the FERC alignment. 3-028-mc -2- ) 2.0 TECHNICAL EVALUATION 2.1 ROUTE 2.1.1 Soils Soil boring information received after the issuance of the FERC License revealed the presence of large amounts of peat in the swampy areas between Bradley Junction and the bluffs on the western side of Fox River Valley. To minimize potential foundation problems, the FERC route was adjusted to take advantage of better drained, glacial till upland areas. This alignment provides greater long term line reliability. It also offers less potential for adverse environmental impacts resulting from having to maintain and/or repair structures when the ground is thawed in the summer, the likely time when foundation problems would occur. Where unavoidable, swampy areas are crossed at narrow points . utilizing the most direct route possible. Location of Angle Points requiring heavy, guyed and anchored three-pole structures, is also avoided in these areas. 2.1.2 Slope Erosion (Fox River Valley) The headwardly eroding bluffs along the west side of the Fox River Valley are characterized by active surface slab failures. Utilizing results of a detailed field investigation along with a comprehensive geotechnical study or the rate of bluff erosion, a preferred route alignment was selected which facilitates the transition from plateau to valley in one span. By avoiding the use of intermediate transmission structures, the line's susceptibility to slab failure is minimized. (This route refinement also minimizes the crossing of Remote Parcel Lease ADL 206393, as noted in Section 3.0). 3-028-mc -3- '·· 2.1.3 Liquefaction The Kachemak Bay tidelands and Fox River Valley are subject to liquefaction caused by minor earth tremors (i.e., given a 5.5 magnitude earthquake on the Richter scale, the saturated soils will liquify resulting in zero shear values). Theoretical techniques to reduce this problem have so far proven to be unacceptable. It vas therefore concluded that the best way to minimize the potential negative effects of liquefaction on the proposed transmission lines vas to: a) modify the FERC alignment such that the Fox River Valley is crossed with the fewest number of transmission structures possible and minimum line angles, and b) avoid placement of the transmission lines within the mud flats north of the powerhouse. River scour depth studies and loop meander investigations were also conducted to assist in the selection of the most suitable foundation design and structure site locations. 2. 1. 4 Windthrov A vindthrov problem may exist on the steep, spruce covered slopes north of the powerhouse. Interior trees in this shallow soiled bedrock area have weak root and stem support systems that have never been exposed to full wind stress. I.f a right-of-way is cut through this vegetation, a significant number of additional trees along the right-of-way edge are expected to blow down due to heavy down slope and south.:Jasterly winds. The blovdovn would be greatest on the leeward side of the ridge, with the largest amount upper slopes where wind turbulence is more o.f damage done on pronounced. Once vindthrown, the spruce trees may provide an ideal breeding ground for bark beetles and increase the potential for fire damage, unless promptly removed. Overall, the wind throw effect would create an on-going right-of-way maintenance problem and may degrade the aesthetic quality of the area. To minimize the potentially disruptive effects, the route has been realigned along several peninsula-like 3-028-mc -4- high points or headlands which extend into the mud flats. Here the tree clearing for the right-of-way is reduced and the threat of residual timber blowdown limited to the immediate headland areas only. Windthrown consultation with Mr. B. Burke of the U.S. Forest Service in Petersburg, Alaska is on-going. Mr. Burke has worked with windthrow problems associated with logging operations in Southeast Alaska and has been requested by the Alaska Power Authority to suggest measures to minimize the opportunity for windthrow from occurring. 2.2 TRANSMISSION STRUCTURE Both the wood pole H-frame and steel X-tower are technically acceptable structure types for the Bradley Lake 115 kV transmission lines. From the standpoint of reliability and maintenance, each structure has its own advantages. For example, the wood pole H-frame is not guy dependent; is a structure commonly known to maintenance personnel. They are easier to replace in an emergency as most utilities maintain an inventory of wood poles and associated hardware and materials. Conversely, the X-tower is simpler in design; weighs approximately one-third less than a comparable H-frame structure; has a longer ruling span; offers greater foundation stability with driven H-piles (over direct embedment of the wood H-frame) ; and is fire resistant. In terms or constructability, the X-tower has a distinct advantage over the H-frame in that it has fewer structural parts and is easier to assemble. 3.0 ENVIRONMENTAL EVALUATION 3.1 ROUTE 3.1.1 Land Use/Ownership In its April 12, 1985 letter to the FERC regarding the Project's Draft Supplemental Environmental Impact Statement, the Alaska Office of 3-028-mc -5- Management and Budget, Division of Governmental Coordination (on behalf of the Alaska Department of Natural Resources), requested that the final transmission line right-of-way be located near the outer boundaries of' section line easements to avoid conflict with future public use. In response to this request, the first 4.5 miles of the FERC route alignment extending f'rom Bradley Junction have been moved orr the section line (Land OWnership Inf'ormation, Sheet 1 of 3). The shif't in route alignment from the 'south side of the section line to the north side in this area was made to assure sufficient distance between the 1 15 kV transmission lines and State Subdivision ASLS 80-155 (Land Ownership Information, Sheet 1 of 3) and to minimize the crossing of' poorly drained peat filled swamps. An additional mile of the FERC route along the section line between Sections 26, 27, 34 and 35 (T3S, R10W) has also been eliminated in conjunction with a route ref'inement that: 1) provides a shorter, more direct crossing of relatively similar terrain·, and 2) limits the crossing or -property included in a land exchange application by the Seldovia Native Association (ADL 221933) to the extreme southwest corner of the parcel (Land Ownership Information, Sheet 2 of 3). The FERC route crossed Remote Parcel Lease ADL 206 393 in Section 35, T3S, R10W (Land Ownership Inf'ormation Sheet 2 of 3). Efforts to minimize impact on this parcel have resulted in an alignment that now traverses only the extreme southern corner of the property, yet still facilitates an acceptable routing through the complex terrain along the Fox River Valley (Route Map, Sheet 2). The ref'ined route alignment maintains suff'icient distance from all other private property to minimize possible land use conf'licts, with the exception of the privately owned Hilmer Olsen Fox Farm (U.S.S. 2937). To avoid placement of the 115 kV transmission lines within the steep, tree covered terrain north of the powerhouse, the refined route alignment is now centered on several headlands that extend into the Kachemak Bay mud flats. As a consequence,. the alignment now crosses 3-028-mc -6- .)) over the western edge of the Fox Farm property (Land Ownership Information, Sheet 3). The proposed transmission lines could have an adverse impact on the potential use and economic value of this property. The Alaska Power Authority is sensitive to this problem, but recognizes it as a necessary trade-off to limiting the side hill scare and minimizing windthrow problems associated with the clearing of a right-of-way on the steep, bedrock slopes immediately east of the property. Further discussion on the subject of windthrow is included in Section 2.0 of this Assessment. 3.1.2 Cultural Resources An intensive cultural resource pedestrian survey has been conducted on the entire FERC route alignment. No previously unidentified cultural resources were located during the survey. Although portions of the refined route have not been field surv~yed, it can be assumed that fev, if any, cultural resources would be encountered along the nev alignment, given that it: a) is located in relative close proximity to the route of the original survey, b) crosses similar terrain to that previously investigated, and c) the terraine types crossed are not those that generally reveal cultured resources. Although not crossed by the FERC route, the Hilmer Olsen Fox Farm was also field surveyed. Evaluation of the Fox Farm resulted in the determination that the site was eligible for inclusion in the National R"egister or Historic Places. The Alaska State Historic Preservation Officer concluded that no direct impact to the Fox Farm was expected. However, indirect impact resulting from increased human activity in the area was possible. The Alaska Power Authority was therefore directed to implement the following protective measures: 1) The historic site will be posted as "off limits" to all personnel associated with the construction and operation of the Bradley Lake Project. As part of each employees ' job briefing, there will be an educational segment to sensitize 3-D28-mc -7- ) the employee to the cultural resources on-project and to the potential for encountering other such resources in the project area. 2) There will be periodic monitoring of this "off-limits" policy to be conducted by the Alaska Power Authority's Environmental Field Officer (EFO). 3) Should cultural resources be located during construction, all work which would disturb such resources will be stopped and the appropriate authorities contacted for consultation. The Alaska Power Authority and the State Historic Preservation Office, as well as the Advisory Council on Historic Preservation and FERC may participate in determining the resources' eligibility to the National Register as well as a mitigation plan, if appropriate. Routing the proposed transmission lines along the headlands immediately adjacent to the mud flats will not have a direct impact on any of the structures located on the Fox Farm site. It could, however, have an unavoidable indirect influence on the site's visual integrity. The potential for vandalism could also increase as construction activities would occur closer to the immediate Fox Farm area. Adverse effects should, however, be minimized by strict enforcement of the above mentioned measures. The State Historic 1'!-eservaticrn Officer will be requested to render an opinion on this matter along with the need for additional field survey of the refined route alignment. 3.1.3 Visual/Aesthetics The proposed 115 kV transmission lines will alter the visual quality of the area, and be in contrast with the region's existing natural character, particularly when viewed from the air. There are no appreciable differences in visual impact between the two alternative 3-028-mc -8- <•"''"'): < < < routes with the exception of that area between the powerhouse and the Fox River crossing point. Here the FERC alignment was located higher on the mountainside, thus requiring an uninterrupted clear-cut through heavy closed coniferous forest. The windthrow effect of trees ~unraveling" along the exposed right-of-way edge, as described elsewhere in this assessment, would further increase the visual impact from both aerial and ground perspectives. By moving the transmission lines off the mountainside and onto the headlands extending into the Kachemak Bay mud flats, clearing requirements are greatly reduced. Aerial views of a cleared, straightline corridor area are also broken by the forested areas between the high points. Although this alternative places the transmission lines in closer, more open view from the immediate bay area, overall visual consequences are reduced by the tree covered mountain "back-drop" to the immediate east of the route. Both wood pole H-frame and weathering steel X-tower transmission structures can blend effectively with this type of landscape back-drop. 3.1.4 Terrestrial Resources It is anticipated that the refined transmission route alignment will not present any appreciable differences in wildlife and vegetation impacts over those previously addressed in the Alaska Power Authority License Application, Mitigation Plan, and Terrestrial Impact Assessment Report. Some benefit could be gained from a shorter, more dlrect crossing of the Fox River Valley in terms of reducing the possibility of birds colliding with the transmission lines. Despite its closer proximity to the Fox River Flats Critical Habitat Area north of the powerhouse, the refined route is not expected to cause any significant increase in waterfowl collisions in that flight intensities are expected to be relatively low along the mountainous shoreline. To avoid crossing of poorly drained, peat filled bogs and parcels of private property, that po~tion of the refined route alignment between 3-028-mc -9- ) ·.··)''·.·.' '-""><,·, ii } Bradley Junction and Fox River Valley would cross more coniferous forest type vegetation and less low shrub bog (Figure 4). Between the powerhouse and the Bradley River, the refined route crosses approximately one mile less closed coniferous forest than the FERC alignment. This relocation also offers the added benefit of reducing the potential effects of windthrow, as discussed in Section 2.1.4. 3.2 TRANSMISSION STRUCTURE The wood pole H-frame and steel X-tower transmission structures are compatible with the environmental setting of the Bradley Lake Hydroelectric Project area. Aesthetically, both structure types can blend well with the surrounding landscape. Both are comparable in size, will require essentially the same amount of. right-of -way, and will utilize similar construction and maintenance procedures. The two structures meet or exceed recommendations contained in the Raptor Research Foundation's Raptor Research Report No. 4 Suggested Practices for Rapt or Protection on Power lines ( 1981 ) • Neither the H-frame or X-tower would utilize an overhead ground wire, thereby avoiding a high ground plane in close proximity to energized conductors. The structures' horizontal conductor configuration will also reduce the probability of bird collisions. The X-tower does provide for longer span lengths, thus reducing the total number of structures-required on the landscape and increasing the opportunity to reduce overall environmental impact. Greater foundation stability provided by the X-tower's driven H-piles also offers less potential for environmental impact caused by a higher frequency of maintenance activities. 4.0 ECONOMIC EVALUATION It is desired to see if the refinement in the transmission line effect! vely changed the l~ngth of the transmission lines and thereby 3-028-mc -1'0- changed the cost. Also forested lengths were compared to determine comparative clearing costs. Lengths are scaled from Figure 2 as follows: FERC alignment Refined alignment 20 miles 19.2 miles The overall length is essentially unchanged based on this scaling accuracy. The vertical relief may add some inaccuracies. The cost of the two routes is essentially the same. Forested lengths were compared based on Figure 2 and the photomosaics. The results are as follows: FERC alignment Refined alignment 10 miles 9 miles The clearing costs are essentially the same. In conclusion, this cursory examination shows no definitive cost differences, the economics are essentially unchanged. 5.0 SUMMARY The Alaska Power Authority believes that it can best meet the transmission requirements of the Bradley Lake Hydroelectric Project by constructing two parallel X-tower type 115 kV transmission lines along the refined transmission line route. 3-028-mc -11- BRADLEY JUNCTION ,...._HOMER ELECTRIC ASSOCIATION I FRITZ CREEK-SOLDOTNA 116 KV TRANSMISSION LINE I I ~~~ /~ REFINED TRANSMISSION LINE ROUTE .... ···!,; .! ... :' t!} .... : <II 0 ,., REVISED 4/8/88 ,r J( "' \\ 'r',' r-'<"'--? ) ~. \1 _'.;... .... ~~ @ "'~ ..... ... .., "'~ t \ .. : \ ...... ...C) ..... \. ·· ... ,.~ .. --.. · .. ..... \ ·~-~ .. --...... -.! ~~ ... ' •, 't '~ .. ···--··- •.·, -... _ _: ....... """".e ....... ... . .,. ···-•• 1 .. -.··· ·-:.;-__ .. : .. _.:.:· -~ ~--'~·. :r:~~ .. -... _)) .---·· : :, ··.·. G(-..,.c:-('1"~ I )> -\== :' ,. ... / ,. .,,.4. ~ ' ,/ # /-~ \%. GENERAL PLAN ·; . ~ / FIGURE 1 ·· .. -~ ! , I 1/. \ / \ \ / / a: w ~ 0 I- I X ..J w w 1- (/) w ::E < a: 1.1. I J: w ..J ~ 8 0 ~ United States Department of the Interior RECORD CCPY Western Alaska Ecological Services Sunshine Plaza, Suite 28 411 W. 4th Ave. Anchorage, Alaska 99501 RECEIVED IN REPL V REFER TO: APR 21 1986 ( WAES Mr. Thomas Arminski Alaska Power Authority P.O. Box 190869 '86 ABR 21 A9 :18 . ..., SWEC-ANCHORAGE .1\PR I 7 1986 Anchorage, Alaska 99519-0869 Dear Mr. Arminski: Re: Assessment of Transmission Line Alternatives Bradley Lake Hydroelectric Project The U.S. Fish and Wildlife Service has reviewed the subject document which was distributed at the agency meeting on 15 April 1986. We have no objection to the Alaska Power Authority pursuing the refined Federal Energy Regulatory Commission alignment as proposed. Under this proposed alignment revision, wetlands habitat (saitwater herbaceous sedge grass) and small ponds southwest of the Hilmer Olsen Fox Farm will be crossed by the overhead transmission line. To minimize the frequency of birds colliding with the conductors, we suggest the line sag be held to an elevation corresponding to the tree tops on the headlands where the towers are to be located. As birds will access and exit the area from and to the Kachemak Bay side of the ponds, waterfowl flight patterns to this pocket of habitat will likely be over sedge flats and below the tree top level of the landward spruces. We thank you for the opportunity to comment and request you keep us apprised of any new alignment developments. · ;iW-~ Field Supervisor cc: ADF&G, ADEC, ADNR, DGC, EPA, NMFS -Anchorage '·; "1 (,, ... t'-;":'1.· . -·-· ..... ____ ......... . MEMORANDUM State of Alaska DEPT. CF NATURAL RESOURCES, DIV. CF LAND & WATER MGH., SOUTHCENTRAL REGION TO: Tom Arminski, Acting o.ULEIVED DATE: Aprill8, 1986 Environment and Licensing APR 2'2 1986 FILE NO: Bradley Lake Hydro ~~~ SWEC-ANCHORAii!EPHONENO: 762-2274 FROM: Robert B. Cutler suBJECT: SHPO Concurrence on APA Unit, Project Manager Transmission Line Alignment In a conversation with Judith Bittner, SHPO, on April 14, 1986, it was agreed that APA's proposed alignment of the Bradley Lake Transmission Line near the Hilmer Olsen Fox Farm, on the Bradley River side, was acceptable. Although the transmission line will have secondary impacts to the site, in the sense of the negative visual impact, it will have no direct effects on the site. The following conditions will apply to SHPO's concurrence with the transmission line alignment in the vicinity of the Hilmer Olsen Fox Farm: cc 1. The site will be "off-limits" to all personnel. 2. No direct impacts will occur on the site. 3. The educational program stipulation on historic sites will be adhered to at all times. Norm Bishop, SWEC Judith Bittner, SHPO Mike Vediner, CO Ned Farquhar, CO 02·001A Rev. 10/79 I TRIP REPORT WINDTHROW OF TREES ALONG TRANSMISSION LINE CORRIDOR BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY J.O. No. 15800.09 WP 46A Trip to Petersburg, Alaska April 18, 1986 Present for: Stone & Webster Engineering Corporation (SWEC) R. Krohn 1. Bob Burke of U. S. Forest Service met with me in his office to discuss possible windthrow problems. The transmission corridor is presented on drawings SWB9-211-1 through 3 and has been physically divided up into one inch lengths for reference in this document. Reference numbers for stereo covers taken t'or the route are indicated on the drawings. What follows is · a seotion by section description . of recommendations by Mr. Burke as to where we may expect problems, starting from Bradley Junction. 2. Recommendations: SECTION 0 -1.5 1.5 -2.5 2.5 -3 3 -4.25 4.25 -7-75 7-75 -9.5 9-5 -15 15 -18 18 -22.75 22.75 -24.5 24.5 -27 27 -32.5 32.5 -34.5 34.5 -36.5 36.5 -44.5 44.5 -51 51 -511.5 54.5 -56 56 -62.5 62.5 -63 63 -63.5 63.5 -66 2-586-JJ CQMMENIIRECOMHEUDATION Open grown, windfirm llliskegg/peet Scrubby timber, windfirm, take only miniDlUJil Peet Open grown, wind firm Peet Open grown, windfirm Peet, sparse trees, windfirm Peet, scrubby timber, windfirm Open grown, windfirm Peat, scrubby timber Open grown, scrubby timber, windfirm Peet Open grown, scrubby timber, windfirm Peet, scrubby timber, open grown, windfirm Peet, scrubby timber, open grown, windfirm scrubby timber, open grown, windfirm Bluff, sparse windfirm timber Peat, scrubby timber Cottonwood, don't take extra River and Silt Scattered cottonwood, windfirm 1 ( ' SECTION 66 -71 71 -71.5 71.5 -74.25 75 -79 79 -81 81 -82 82 -84 84 -85 85 -86.5 '86.5 -88 88 -89.5 89.5 -95.5 95.5 -98 QQMMENT/RECQMHENPATION River, silt, scrubby timber and peet Small trees, don't take extra Ridges and draws, most likely windfirm, don't take extra Nice timber, potential for windtbrow on the steep slope. Recommend minimal cut. Open grown, open slopes Fairly well open grown, should be windfirm Adjacent to tidal flats, take extra point of trees on the seaward side or the knob Small timber, windfirm Nice timber, possible windthrow on downhill side, fringing only, don't take extras River Small timber, should be no windthrow Very good potential for windtbrow, take timber all the way to tideline. Landside or corridor is small t:lmber and should be windtirm Mud and knobs. Clear •knobs all the way ~o tideline Good potential for windthrow on the few remaining trees, clear all the .wa.y tg ·the tideline. I ·requested that Mr. :Burke provide me with a general set or guidelines concerning windthrow. The following are his comments. a. When the trees are open grown, they are likely to be wind.firm. b. Short trees will be windtirm. c. Windthrow is most likely to occur in tall trees that are closely grown. The root systems are all near the surface. d. In general, don't take extra trees to circumvent windthrow unless an end ot the unravel can be predicted. 4. r asked Mr. Burke to assess the previous alignments between the powerhouse and the Fox River that had been considered with respect to windthrow. His general observations are as follows: a. The best timber appears to be those that are closest to the tideline. b. The higher elevation the timber is, the more windfirm it will be because it is shorter and more open grown. 2-586-JJ 2 I ' c. Mild windthrow is all that would be expected in the higher elevations with the smaller trees. d. In corridors in between, the wind throw could be worse as the timber is bigger and not as open grown. 5. I draw the tollowing conclusions trom J11f discussions with Mr. Burke: a. For the majority ot the transmission line corridor, windthrow is not a problem. On all but the Eaat end of the corridor the trees are all open grown. b. On the tina! run from the Fox River to the powerhouse, the trees are larger. This is the only area along the transmission line corridor where windthrov is even ooncievable. c. On the downhill side ot the headland knobs where only a narrow strip would be lett it minillUII clearing were to occur, the maxiiiiUil opportunity for windthrow exists. Mr. Burke concurs that these narrow strips should be taken. d. In all other locations, the mini.JDull amount ot timber should be cleared tor the right ot way to meet technical requirements. e. In general, windthrow is not the problem that we bad suspected and little action will be required to circumvent problems. Ronald F. Irohn Lead Electrical Engineer RFIC/JJ Attachment 2-586-JJ 3 ( MEMORANDUM State of Alaska DEPT. OF NATURAL RESOURCES, OIV. OF LAND & WATER MGMT. , SOUTHCENTRAL REGION ro: T 001 ~nn~nski, Ac~ing ~-Mtert= J V ED DATE: Perm;~ing and L1cens1~L\,~ ~~ ~ • FILENO: TI-RU: Robert B. Cutler APR 2 4 1986 APA Unit, Project Manag~r TELEPHONE NO: WEC-ANCHORME FROM: Deborah K. Heebner SUBJECT: Natural Resource Off April 23, 1986 Bradley Lake Hydro 762-2274 Transmission Line Route Land Ownership Information At your request, we have reviewed the Proposed Transmission Line Route Land Ownership Information maps provided to us by APA March 18, 1986. The information is adequate except for two discrepancies. 1. The remote parcel lease of Daniel M. Cowart, ADL 216838, is not drafted accurately, but instead parallels the seismic line 30 feet away and is totally within Section 35, T3S, RlOW, S.M. Cowart's Corner #2 is 70 feet, at a 55°NE bearing, from Swanson's ADL 206393. 2. The 50 foot right-of-way application of Joseph F. De Smidt, ADL 219905, does not extend northwest from Section 29 to Section 19 of T3S, RlOW, S.M. as depicted on the APA maps, -but instead makes a corner to a southwest direction and intersects the transmission line route. We would like to emphasize the importance of submitting the right-of-way application as soon as possible due to the current status of the remote parcel lease, AOL 206393, and the Land Exchange Application, ADL 221933, in Sec. 27, T3S, RlOW, S.M. The current remote parcel lease agreement provides the state with the authority to reserve the right-of-way. If this lease should go to sale contract and patent, the parcel owner could not convey or rent any portion of the land for 10 years and the state could not reserve the right-of-way except through condemnation, or possibly exchange. The final Land Exchange Agreement, ADL 221933, was never signed by Seldovia Native Association who disagreed with the appraisal. It is unlikely the state will abandon the exchange (pers. comm. Dennis Daigger, AONR) which·is due to expire June 1. A new preliminary exchange agreement will have to be renegotiated at that time, with a reappraisal of the land. The current status of the Preliminary Exchange Agreement does not preclude the issaance of the right-of-way, although AONR must go through agency and public contact prior to issuing the letter-of-entry. Seldovia would have the opportunity at this time to object to the right-of-way. If you have any questions, please feel free to call. DEPARTltiENT OF FISII AND GAltiE April 24, 1986 Tom Anni nski Alaska Power Authority P. 0. Box 190869 701 E. Tudor Road Anchorage, Alaska 99519-0869 Dear Mr. Anninski: RECEIVED APR 2 4 1986 BILL SHEFFIELD, GOVERNOR SWEC-ANCHORAGE 333 RASPBERRY ROAD ANCHORAGE. ALASKA 99518·1599 Re: Bradley Lake Hydroelectric Project-Assessment of Transmission Line Alternatives The Alaska Department of Fish and Game (AOF&G) has reviewed the Draft Assessment of Transmission Line Alternatives for the Bradley Lake Hydroelectric Project. The department is cognizant of the slope erosion, liquefaction, and windthrow problems associated with the placement and construction of transmission Tines from the Bradley Lake powerhouse to the Fritz Creek-Soldotna junction. Based on the available information presented in the assessment of transmission line alternatives, the department does not object to the refined Federal Energy Regulatory Commission (FERC) alignment as the preferred Bradley Lake transmission line alignment. Waterfowl mortality resulting from collision with transmission lines is expected to be insignificant in terms of the total number of waterfowl found at the head of Kachemak Bay. However, the siting of the refined FERC alignment along headlands between the Bradley Lake powerhouse and the Bradley River could have some impact on waterfowl that use mud flats, ponds, and the shoreline in this area. At the April 15, 1986 Bradley Lake Hydroelectric Project Agency Meeting, department personnel were infonned that transmission line height between the two towers situated on the headlands immediately southwest of the Hilmer Olson Fox Farm would be approximately 27 feet above ground level at their lowest point. Low transmission line height between the headlands could result in high localized collision mortality for waterfowl that utilize the mud flats and ponds between the headlands. The department therefore makes the recommendation that transmission structures on the two headlands southwest of the Hilmer Olsen Fox Farm be increased in height so that the transmission lines would be no less than 50 feet above ground level at their lowest point between structures. Increasing the transmission line height in this area would reduce waterfowl collision mortality and preserve waterfowi local use of the mud flats and ponds between the headlands. ( Mr. Tom Arminski -2-April 24, 1986 Siting of the refined FERC alignment across Sheep Creek and the Fox River inland of high density waterfowl areas alleviates much of the department's early concern with respect to waterfowl collision mortality in this area. With respect to the visibility of the transmission line, the department recorrmends that the transmission line itself be made as visible as possible to avoid waterfowl collision mortalities. Thank you for the opportunity to review the Draft Assessment of Transmission line Alternatives for the Bradley Lake Hydroelectric Project. Should you have any questions concerning our comments or recommendations, please contact myself or Don McKay of the Habitat Division at 267-2283. Sincerely, /) //.d / {;tdf~t~~ Carl M. Y gawa~ Regional upervisor Habitat Division Anchorage (907) 267-2283 cc: G. Bas, ADF&G D. Clausen, ADF&G R. Kramer, ADF&G D. Holdermann, ADF&G H. Hosking, USFWS/WAES 0. Wilkerson, ADEC B. Cutler, ADNR C'i. · .. ,, :"·'· ' •.. ~ . : :,. t '> • •• r • • , i . ~ ·, I • . ·.,, , -. Land Field Services 301 West 64 th Avenue Anchorage, Alaska 99502 JJMPlante/DLMatchett Gen Files/DOC JJGarrity/chron TCritikos, JBK 46A-ld NABishop RKrohn w/att w/att w/att w/att w/att April 25, 1986 J.O. No. 15800.09 WP 46A-1d ALASKA DEPARTMENT OF NATURAL RESOURCES COMMENTS LAND OWNERSHIP INFORMATION TRANSMISSION LINE ROUTE BRADLEY LAKE HYDROELECTRIC PROJECT Enclosed is C:.l.l April 23, 1986 memo from the Department of Natural Resources to Mr. T. Arminski of the Alaska Power Authority. This memo provides comments concerning land ownership along the transmission line route. Please review the Cowart and De Smidt land parcel locations, and if you agree with ADNR's comments, please make the necessary changes in the ownership information maps and advise us accordingly. Please call Mr. R. Krohn at 277-2427 if you have any questions on the above. Theodore Critikos Deputy Project Manager TC/RK/JJ Enclosure cc: Mr. Del LaRue, Dryden & LaRue, w/enc NOTED APR 2 ~ 1986 r. Critlkos 2-559-JJ MEMORANDUM State of Alaska RECEIVED DIVISION OF PARKS AND DEPARTMENT OF NATURAL RESOURCES OUTDOOR RECREATION Bob Cutler APA Unit, Project Manager MAY 0 5 19~tTE TO DNR FILE NO: ·sWEC-ANCHORAGE FROM: ~ ¥-1-~7 Judith E. Bittner~~~~ TELEPHONE NO SUBJECT: State Historic Preservation Officer April 25, 1986 1130-13 762-4108 Draft Transmission Line Alternatives Review, Bradley Lake Hydro We cannot agree with Stone & Webster's conclusion on page 7 that " ••• it can be assumed that few, if any, cultural resources would be encountered along the new alignment •.• " At least portions of this new alignment are in areas of considerably higher probability than the surveyed route. We request consulta- tion with APA and Stone & Webster to determine those portions of th new alignment that should be surveyed. We do agree that the previously proposed mitigation measures should accommo- date the new visual effect on the Hilmer Olsen Fox Farm. cc: Tom Arminski, APA Norm Bishop, Stone & Webster DR:tls ALASKA STATE PARKS Let's Put Them on the Map! ( LAND FIELD SERVICES, INC. P.O. Box 111705 AnchOI'age, Alaska 99511 561·1671 P.O. Box 2510 F ai rtlanks, Alaska 99707 452·1206 April 30, 1986 RECEIVED MAY 051986 SWEC-ANCHORAGE Mr. Theodore Critikos Deputy Project Manager Stone & Webster Engineering Corporation Bradley Lake Project Office P. 0. Box 101520 Anchorage, Alaska 99510 RE: Land Ownership Information Bradley Lake Hydroelectric Project Dear Mr. Critikos: As requested in your letter of April 25, 1986, we have reviewed the ADNR comments in the April 23, 1986, memo from the Department of Natural Resources to Tom Arminski, and do not feel that changes in the ownership maps are necessary at this time. Our response to Ms. Heebner's comments follow: 1. The narrative legal descriptions applicable to the Daniel Cowart (ADL-216838) and John Swanson (ADL- 206393) parcels, as taken from the ADNR records, con- tain rather vague and imprecise data. In fact, if taken literally: (1) The Swanson parcel does not close upon itself; and (2) The Cowart parcel would overlay, or conflict with, the southwesterly portion of the Swanson parcel. The portrayal of both parcels on the ownership maps represents our best estimate of the intended locations of said parcels based upon not only their narrative legal descriptions, but also the sketch plats associated with such parcels, also derived from the ADNR case files. We have found that in some in- stances this information conflicts with itself. We too noted the intent of Mr. Cowart's parcel to be 30 feet from and parallel to the seismic trail centerline. The seismic trail as depicted on the ownership maps is based upon the trail as observed from the aerial photo mosaic prepared by Dryden & LaRue Inc. for Stone & Webster. Due to the uncontrolled nature of the mosaic, some distortion in position of the various features is expected. Thus it was necessary for us to bring to- ( Mr. Theodore Critikos April 30, 1986 Page 2 2. gether the imprecise legal description data , and the uncontrolled photo mosaic features, onto an accurate portrayal of the various Section, Township and Range data. In such instances compromises must be made, and the only alternative that .. we had was to try to arrive at what we felt was the intent of the parties (Cowart and Swanson), given the priority of their filings. Only an on the ground survey will finally define the parcels' actual locations. It is our understanding from ADNR that Joseph DeSmidt's right-of-way application (ADL-219905) is intended to follow the seismic trail (note that it is only an application, and has not been granted): and was filed to establish access rights for Mr. DeSmidt and the public. Again using the aforementioned aerial photo mosaic, a great many trails become evident; however none. are readily apparent on the photos that •make.s a corner to a southwest direction and intersects the transmission line route•. I'm not trying to imply that such a trail does not exist: it just was not apparent in the materials that we had to work with. Also, my recollection of the ADNR case file for ADL-219905 was that there is only the most meager of a map in the file to describe the intended location of the trail; and that there was no narrative legal description to sup- port it. Again using the photo mosaic, we tried to portray the seismic trail to the best of our ability: however its actual location cannot be.determined until an actual survey takes place. I have discussed the foregoing with your Mr. Ron Krohn; and by copy hereof I am providing my comments to Mr. Arminski and Mr. LaRue. Very truly yours, LAND FIELD SERVICES, INC. tU~~ Warren L. Krotke WLK/jb ~ MEMORA:~t;M State of Alaska DEPT. Cf" NATaT• DIV. Cf" LAKl & WATER MGMT., SruTHCENTRAL REGION TO: Oav~d ft,_.: '.~~~~i . DATE: April 30, 1986 ProJe£t M'at@, PPA . /' t:t::t, R E c E I v Eo· FILE NO: Bradley Lake Hydro .t ,~~:.~. ... (···· .... , . ·.> APR~& 1986 TELEPHONE NO: 762-2274 ~~:· ·:· t.t,argaret J. Hayes ~··' :: ·~·:.:;_·,'J!tegional Manager ~,~ .,_~·::"~.:7::--··-~···; ·~ .. ' .... ? SWEC~ANCHORAGE suBJECT: Review of Assessment of Transmission Line Alternatives ..... ·,·-~ .) .. : ··-~ \ ... x,_~ :1'i:j: · The Department of Natural Resources has reviewed the draft "Assessment of . }~· Transmission Line Alternatives" for the Bradley Lake Hydroelectric Project. We have no objection to the refined Federal Energy Regulatory Commission alignment as proposed. .:.:-.. ~ : . ' . .... ... : ~-' ... , .... We understand this document is a cursory examination of the refined alignment and we expect further detail.inlehe Vegetation Clearing Plan on clearing limits, number of acres of timber tQ;be c~eared and specific land ownership data (acres). .. . / .·r : . · .. ;1 .~::: . : .' ·. •·•·• .... . , The new alignment should reduce windthrown trees along the transmission corridor in the Fox River area. The Vegetative Clearing Plan for the. transmission line should also address the monitoring and disposal of windthrown trees along the transmission line. We do not agree with Stone & Webster's conclusion on page 7 that "it can be assumed that few, if any, cultural resources would be encountered along the new alignment ••• " At least portions of this new alignment are in areas of considerably higher probability than the surveyed route. APA should consult with the State Historic Preservation Officer to determine those portions of the new alignment that should be surveyed. · ' We do agree that the previously proposed mitigation measures should accommodate the new visual effect on the Hilmer Olsen Fox Farm. The Division of Geological and Geophysical SUrveys (OGGS) did not have adequate time for a thorough analysis of the Assessment of Transmission Line Alternatives, and, therefore, the comments of DGGS will be submitted in a. separate memo within the week. We thank you for the opportunity to comment. If you have any questions, please do not hesitate to call. cc Tom Arminski, APA Norm Bishop, SWEC 02 ·001 A tRev. 1 01791 .'. • ··-'t.j ) ) Mr. Del LaRue Dryden and LaRue, Inc. 6436 Homer Drive Anchorage, Alaska 99518 Dear Del: R E C E l V E D MAY -5 1986 RECEIVED MAY 12 1986 SWEC-ANCHORAGE April 30, 1986 In response to our telephone conversation of April 25, 1986, I have examined the maps and aerial photographs relating to the Bradley Lake 115 kV transmission lines. Below you will find comments on the routes and their potential impacts on waterfowl utilizing the wetlands south of the Fox Farm. The area of concern appears to be two open-water wetlands lying in the floodplain of Bradley Creek. This portion of the floodplain is apparently in an old river bend which is occasionally flooded. The ponds are both less than 5 acres in area, appear to be fairly shallow and as such are probably utilized as feeding areas for dabbling ducks (mallard, teal, pintail, etc.) which stage on the Fox River Flats prior to vernal and autumnal migration. These waterfowl typically follow watercourses and topographic depressions from their loafing and resting areas to and from their feeding areas during their daily movements. SUch flight paths are generally known as "communication flywaysn (as opposed to "migratory flywaysn which the birds use to journey between wintering grounds and summer nesting areas). When using . communication flyways, waterfowl generally fly within 200 feet of the surface. However, only direct observation of waterfowl utilizing this area can determine flight behavior, population density and activity. It is my opinion that any of the three alternative alignments in this area could be built with minimum impact to waterfowl. The two alternates would have little effect on d1:1cks utilizing the ponds in the area in question. The proposed route's location, in relation to the ponds, could increase the potential for collisions with the lines. However, the use of orange globes would reduce that potential, as would the absence of shield or static wires (see enclosed report which I researched and prepared). The presence of the lines over these two wetlands will likely reduce waterfowl use of them. However, because the conductors will be extremely high, it is unclear as to the extent the utilization will drop. ) Mr. Del LaRue April 30, 1986 Page 2 The foregoing observations are based on my professional opinion and my experience with waterfowl observations in relation to existing transmission lines after reviewing topographic maps and aerial photographs. As I indicated previously, actual field observations may indicate this particular area has unique characteris- tics or provide insight which could revise my stated opinions. However, from the maps and photographs, there appear to be no major concerns that cannot be mitigated. · I appreciate the opportunity to assist you. If you have any questions or comments or if I can be of further service, please don't hesitate to contact me. JMB/ksw Enclosure Respectfully, 9-L)11.~ John M. Bridges ·wildlife Biologist ) INTRODUCTION BIRD COLIJSIONS Literature Review Agency /Utility Contacts Summary TABLE OF CONTENTS POTENTIAL ENVIRONMENTAL IMPACT ASSOCIATED WITH A SUBMARINE CABLE CROSSING LITERATURE CITED CP&L2/Es-40 Page r 1 1 1 4 9 10 13 ) INTRODUCTION The primary purpose of this report is to provide a concise summary of the current literature on bird collisions with high voltage transmission lines (HYTL} and review some of the problems with this issue encountered by the electrical utility industry throughout the country. __ Knowledgeable individuals were contacted by Gilbert/ Commonwealth staff to obtain results of recent investigations of bird-HYTL interactions. Personal contacts included both industry sources and resource management agencies in each of the four major migratory flyways in North America. A generic description of the environmental issues that can be associated with a submarine cable crossing was also included as part of the study effort. BffiD COLI.J.SIONS Literature Review Birds in flight have been known to collide with obstacles in their flight path. These collisions have occurred with buildings, t_elevision and radio towers, transmission and distribution lines, telephone lines and fences. A synopsis of pertinent issues gleaned from Gilbert/Commonwealth's in-house literature relating to bird collision mortality is presented below. Bird-transmission line interactions are not a new phenomenon, as evidenced by Michener (1928} who authored one of the earliest accounts of this problem. There is a plethora of literature on bird collisions with man-made obstacles, much of which has been annotized in Weir (1976). Avery (1978) presents a fair summary of transmission line impacts on birds. However, until recently, few researchers included sufficient information in their data to assess the significance of collisions to the regional bird population (Gauthereaux, 1978). While many different species have been reported as apparent collision casualties (Goddard, 1976), the primary concern in the literature seems to be with large, slow-flying birds which are less maneuverable, such as wading birds, and fast, low-flying birds, such as wa~erfowl and shore birds. Resident birds tend to rapidly acclimate to new transmission lines, while immatures and migrants, which are newly arrived, tend to avoid feeding and/or loafing within one-quarter mile of transmission lines until· they become CP&:L/Es-40 1 accustomed to it, which takes approximately one month (Bellrose, illinois Natural History Survey, personal communication). Within the last fiv~ years, few studies of the problems dealing with bird strikes at HVTL's have been conducted. One of these studies was conducted by the U.S. Fish and Wildlife Service and funded by utilities in the Mid-American Power Pool (MAPP) (McConnon, United Power Association, personal communication). The report has been out in draft form since 1983; however, according to the U.S. Fish and Wildlife Service Editorial Office, the final report will not be published until late spring 1986. The draft report of the study funded by MAPP foun.d the observed mortality for all species was about 1.8 percent of the bird flights observed, which Faanes (in press) concluded: "This in itself, for the species considered, was not biologically significant." Two other studies have been funded by Bonneville Power Administration (Willda.n Associates, 1982; Beaul.aurier, 1981}. Beaulaurier {1981} conducted experiments on short sections of two transmission lines, one in Washing- ton and one in Oregon, in which the overhead groundwire was removed from previously studied transmission lines. The purpose was to determine what effects this removal would have on bird collisions. Willdan Associates (1982) examined the impact of a 500 kV transmission line at an island in the Columbia River. Their ) studies included the effects of habitat alteration and changes in waterfowl use. _) Older studies, before 1983, which provided sufficient data to determine the effects on regional populations indicate that mortality associated with transmission line collisions generally represent less than 1.0 percent of the populations studied (Table 1). For comparison, Willard et al. (1977) considered hunting mortality to be as high as 30.0 percent in some waterfowl populations, which apparently recovered sufficiently on an annual basis to provide a huntable population. Special concern has been expressed by Central Power & Light Company about diving ducks colliding with transmission lines. The populations of individual species of diving ducks seem to have fewer numbers than other anatid subfamilies. Therefore, in reviewing the literature, special efforts were made to find those sources which identified the species involved in collisions. Results of studies examined in this review indicate that diving ducks were not a major component of the birds which collided with lines. Among these were Faanes (in p'ress): 11 Among CP&L/E$-40 2 ) ) TABLE 1 SUMMARY OF REPORTS OF BrRD COLLISIONS WITH "POWER LINES" WHERE PERCENTAGE OF POPULATIONS STUDIED COULD BE DETERMlliED Author(s) Stout and Cornwall (1976) Anderson (1978) Wiese (1979) James and Haak (1979) Beaulaurier (1981) Malcolm (1982) Willdan Associates (1982) CP&L/E5-40 Percentage of population suspected of collid~ with "power lines. n 0.07 percent of nonhunting mortality of North American waterfowl was by collision with tele- phone or power line Between 0.2 and 0.4 percent · of maximum number of birds present in power plant slag pit collided with lines exiting from plant 0.03 percent mortality observed in 2,791 flights of wading birds flying near three different sets of HVTLs Based on population estimates at two study areas, 0.57 and 0.46 percent daytime collisiorl$, 0.84 and 0.92 percent nighttime collisions Collision rate averaged 0.52 percent of bird flights for two studies on one site and 0.89 percent of bird flights on another site Collision percentage of birds using a wetland in Montana is between 0.3 and 0.4 percent based on population estimate Collision percentages during two year study at two different study areas ranged from 0.002 percent to 0.05 percent 3 ) ) waterfowl, the diving ducks appeared to encounter few problems when in flight near a power line."; :Malcolm (1982) reported diving ducks represented approxi- mately 100 of 3,218 known bird collisions; Cassel et al. (1979) reported 4 of 105 individuals were diving ducks; Anderson (1978) reported approximately 1. 7 percent of those waterfowl that collided with lines were diving ducks; and McKenna and Allard (1976) found 4 of 2~4 individual birds found were diving ducks. In summary, birds do collide with man-made objects, including electric transmis- sion and distribution lines. In some studies, most bird collisions with transmission lines were found to occur at the shield wire. These collisions occur d~ring all types of weather conditions and may or may not be fatal to the birds. Large birds, waterfowl and wading birds (herons, egrets, etc.) are the most commonly reported casualties, but it is unclear whether larger birds are more likely to collide with the line or merely more observable after the collision than smaller birds. Current published literature on the subject provides no means to eliminate these collisions, and attempts to minimize them are poorly studied. In one reported mitigative case history, B.eaulaurier (1981) found tha.t bird collisions with a transmission line were reduced by 50 percent when shield wires were marked with orange globes or removed entirely. Agency/Utility Contacts Resource management agencies and utility companies throughout the United States were contacted to determine their experience with and/or policies regarding bird collisions with transmission lines. In cases where Gilbert/Commonwealth staff had prior knowledge of experiences with this issue, we contacted specific individuals within the agency/utility. Where specific personnel were not known, we directed our inquiries to staff of Utility Transmission Engineering Departments and the Environmental Planning Departments of agencies. The contacts made are reported in Table 2. These are divided into the four major migratory flyways: Atlantic, Mississippi, Central and Pacific. Many.· of the agencies' and utilities' areas of concern overlap more than one nyway. In. these instances, contacts are listed in the table based on the headquarter location of the agency/utility. CP&L/E5-40 4 TADLB 2 THLHPIIONB CONTACTS RBOARDING BIRD COLLISIONS WITH TRANSMISSION LINBS• i\gcncy Atlnntic Flyway Florida Game nnd Freshwater fish Commission Florida Deportment of Environmentnl Review Suneoast Seabird Sanctuary Florida Power Corpora lion Seminole Electric Cooperative Orlando Utilities Commission Person Contacted Perry Oldenberg Landon Ross Ralph lleath Or. Dave Voigts Mike Roddy DIU Shoup · Bird Collision JnrormaUon The agency hBll no poUcy or regulations regarding bird collisions with transmission Unes. The agency has no policy or regulations regarding bird colUslons with transmission Unes. The Suncoast Scnblrd Sanctuary round that 9-lnch orange globes attached to transmission lines reduce the number or bird collisions. Bird colUslons were a problem on an HVTL Intersecting a waterbird nesting and feeding area. Orange balls were used to reduce the number or collisions. No problems known. At a coai-Cired power plant, the USPWS and Florida G&FC recommended, among other things, that wetland habltot be established on the site. The only area available Cor such a development was under an IIVTL exiting the plant. Both agencies withdrew their recommendation. • Attempts were olso mnde to contact the following Individuals, who were unavailable! 1. Bob Jessen, Minnesota Department or Natural Resources 2. Or. William Anclcrson, nllnols Natural History Survey 3. Roger Woodworth, Woshington Water and Power Compony 4. John llucknllee, Electric Power Research Institute CP&: 1.1/Es-40 Agency A lion tic Flyway (Cont 'd.) Florida Power and Light Compnny South Carolina Public Service Authority Mnrylnnd Department oC Natural Resources Allegheny Power Service Corpora tlon New York Power Authority Mississippi Flywn;r: United Power A.~soclntlon Cooperative Power Association u.s. Fish and Wildlife Service C P& 1.2/E&-40 Person Contacted Dr. Ross Wilcox CharUe Hamer Tom Magette Don Thomas John Hecklau Dan McConnon Will Kaul Carl Korschgen TABLB2 (Continued) Bird Collision Information Nearly all or their problems have been with response to consumer complaints associated with distribution lines. Response was to use 9-lnch orange balls. There were no repeated complaints rouowlng placement. No problems known. The agency has no poUcy or regulations regarding bird collisions with transmission lJnes. No problems known. There have been occasional collisions by great blue heronsr no mitigation measures have been Implemented. They relocated a lJne route to avoid crossing an open water wetland. The Minnesota DNR required a submarine crossing (1500 reet) to avoid the potential Cor collisions with migratory waterCowl. C.P.A. also uses conductor sized shield wire In some wetland crossings, which Jppears to be errectlve. The LaCrosse, Wisconsin, ortlce was conducting studies on avian movement patterns on the Upper Mississippi River using radar and laser techniques. The study was not completed due to lack or rundlng. Observations Indicated some collisions with a new transmission line would be Inevitable; however, local populations would become accustomed to the line and migrants would be higher than the line. Agency Mississippi Flywoy (Cont'.d) Illinois Nnlurol History Survey Tennessee Volley Authority Central Flyway u.s. Fish and Wildlife Service Nebraska Public Power District l(anso~ Gns and Electric Company Knnsos Power and Light Company C P& 1.3/ E5-4 0 Person Contacted Dr. William Anderson Dr. Frank Bellrose Walter Thomas Dr. Harold Kantrude Mark Czaplewski Mike Miller Tom Bozeman TADLR 2 (Continued) Bird Collision Information In studies on Lake Sangchris In central fiUnols, Anderson noted that waterfowl avoided an IIVTL rather than Cly through It or under lt. lie recommends that, when possible, waterfowl use sreos be avoided during the routing process. Dr. Bellrose has noticed a reduction or waterfowl use within one-quarter mile or a new transmission line tower. lie round that local residents would acclimate quickly, and did not believe waterfowl collisions were a problem. TVA has used orange boLls (size unknown) to minimize bird collisions at speciCic locations. Studies or bird movements In relation to HVTLs have been conducted, and the results are In press. The Northern Prairie Research Center conducted a study In the northern Great Plains on bird collisions with transmission lines (see Fasnes, In press). No recent (since 1983) studies hove been done by their ornce. The company relocated a 345 kV line route to minimize Impacts to a waterfowl staging area on the Platte River. They also experimented with vibration dampers and wind spoilers on shield wires to Increase visibility. These had little effect and Increased Icing and wind loading problems. There have been no problems with birds colliding with transmission Unes1 however, some ducks Clew Into the side or a power plant. No mitigation measures have been Implemented. During routing shidles, several agencies suggested the use or orange globes at a crossing or a Corps or Engineers reservoir. None were req~lred and none were placed on the line. 00 Agency Central Flyway (Cont'd.) Public Service Company of Colorado Public Service of New Mexico Pncifie Flyway Pugct Power Company Pnclfie Gas and Electric Compnny Sierra Paclflc Power Company Pacirlc Power nnd Light Company Donncville Power Administration WRshington Water & Power Company CP& L4/E&-40 ., Person Q>ntactcd A. Dean Miller Dale Stahlecker Mel Walters Mark Dedon Steve Siegel Steve Wilder Jack M. Lee Roger Woodworth TADI.H 2 (Continued) Bird Q>Uislon Information They Cllmed 20 days during two migration periods to monitor crane movements In relation to transmission lines. It was noted that most casualties were caused by panic (lushes. They noticed no difference In flight behavior at spans with normal static wires and spans with larger static wires. A report on bird coUlslons with HVTI.s was prepared u part oC Section 1 consultation and Is not at this time available Cor public distribution. When rebuilding an existing line across a lake with 300-400 resident trumpeter swans, 1 or 2 swans were killed In the Clnt 30 years or the line's llfe1 orange globes were plnced on the new conductors. (No static wires were used.) The effectiveness of globes was questioned. They use orange globes on IIVTL crossings of flyways when required. Their effectiveness Is unknown. No problems known. They were required to move a Une route In Klamath Basin to minimize the potential for waterfowl collisions. Studies conducted Indicate coUislons were reduced by approximately 50 percent It shield wires were marked or removed. State or Montana accepted monetary compensation for loss of 100-200 waterfowl per year In lieu or other mitigation. No problems known. ) The Atlantic flyway contacts reported the occurrence of occasional bird collisions, which has resulted in utility attempts to minimize these impacts using orange globes on the shield wires. None of the regulatory agencies contacted within the Atlantic flyway had policies or guidelines regarding bird/transmission line inter- actions. Incidents of occasional bird collisions were also reported by selected utilities in the Mississippi flyway. Where mitigative measures were implemented to reduce bird mortality, -orange balls were used on shield wires: except in one instance, where a 69 kV line crossed the inlet of a lake heavily used for recreation and regulatory agencies required installation of a submarine cable. None of the agencies contacted had developed specific policies or guidelines regarding this issue. In the Central flywayt very few instances of bird/transmission line problems have been encountered by the utilities contacted. In the few instances where utilities were required to implement some mitigation, usually orange balls, no studies have been undertaken to determine their effectiveness. The Public Service Company of Colorado, with others in the "Crane Study Group," has completed the most recent work to document bird/transmission line problems. The concensus of their work was that most collisions were caused by "panic flushes" (birds startled into flight) and that increasing the size of shield wires had limited effect on bird flight patterns. The assumption was that larger shield wires would be more visible to birds. Those utilities contacted in the Pacific flyway which reported problems with bird collisions indicated they have used orange balls as a means of mitigation. An interesting side note is that, the State of Montana has accepted monetary compensation, in lieu of requiring other mitigative measures to compensate for waterfowl losses. Summary In general, bird collisions with transmission lines are not considered a· major problem except in isolated cases. The accepted method for reducing collisions has consistently been the use of orange globes on shield wires and/or conductors, and CP&L/E$-40 9 removal of shield wires in areas of low isoceraunic activity. These measures have been reported by several utilities and agencies to reduce bird collisions. While ) certain groups of birds reportedly are more vulnerable to collisions, the loss of these birds seldom represents more than one percent of the population present. Although particular concern for diving ducks has been expressed, they normally do not appear to have problef!.lS avoiding transmission lines. POTENTIAL ENVIRONMENTAL IMPACT ASSOCIATED WITH A SUBMARINE CABLE CROSSING Options to overhead transmission line construction are available, but generally speaking are more costly and also pose potential hazards to the environment. Con- sideration of a submarine cable for electrical distribution purposes generally requires more time for permitting activities and construction because of the seasonal aquatic studies often needed to prepare an acceptable environmental assessment, and the time restrictions often placed on construction schedules to avoid conflict with sensitive ecological issues. Results of previous submarine cable crossing projects indicate that once construc- tion of a cable is complete, under normal operating conditions, there are no known environmental impacts on the marine ecosystems under which they pass. The primary marine environmental risks associated with the installation of an under- water circuit occur either during their construction or as a result of the accidental . . discharge of the cooling fluid during the line's operation (assuming that cooling fluid is required). Offshore construction activities, particularly dredging operations, involve physical disruption·· of the bottom substrate material, resulting in suspension of fine sediments with attendant temporary deterioration of water quality, and redeposi- tion of these materials in surrounding areas. Potential adverse effects on biota from these operations include physical disruption of bottom habitat, destruction of benthic organisms, decreased light penetration and reduced photosynthetic activity of phytoplankton, avoidance of the near-field area by fish and other larger mobile organisms, and release of potentially toxic materials from sediments, if they are contaminated. The severity of potential impact is dependent upon the 'sensitivity CP&::L/E5-40 10 ) of existing aquatic resources and the specific construction techniques to be employed. Regulatory agencies frequently require ecological studies to identify the presence or absence of sensitive ecological species and the characterization of dredge spoils to as::ist in the evaluation of potential impact. Results of regulatory review and project approval frequently restrict construction schedules to specific time frames aimed at a~~iding critics.} fish spawning or migratory periods. If dredge spoils are found to be contaminated they must be hauled to an approved upland or ocean disposal site. These types of restrictions attendant to addressing environmental concerns, only add to the high cost of a submarine cable. If rock substrata are encountered in the trench required for cable placement, additional potential impact to aquatic resources can be realized. Explosives used for this type of work produce a sharp shock wave with an abrupt front of great pressure intensity. This type of shock wave is potentially injurious to fish, particularly those having air bladders. The impaCt range for fish with air bladders appears to be about 150-200 yards when utilizing a 30 pound charge. Fish without air bladders usually are not injured unless they are very close to an explosion. The potential impacts due to blasting on fish can be an important environmental issue associated with a submarine cable project. For this reason, blasting is usually scheduled to avoid spawning periods of commercial and sport fisheries. The establishment of such construction windows frequently eliminates many of the concerns of regulatory agencies, but may restrict construction to a few months of the year. Should blasting .be necessary during other months, appropriate methods of detecting large schools of fish can be implemented and all blasting operations performed only when aggregations of fish are outside the area where harmful effects may be expected (i.e., 250 yard radius). Operational-phase impacts to the aquatic ecosystem relate primarily to the potential escape of the line's cooling fluid (if such a system is required). Rupture of the line can be caused by such incidents as a ship running aground, erosion of the cover material and exposure to currents and wave action, potential damage from future dredging or construction operations, or potential damage due to an .anchor being dragged across or snagging the cable. Low viscosity polybutane dielectric fluid (L VP} is a commonly employed cooling fluid in submarine 'cables. The CP&L/E5-40 11 ) ) potential release of this substance into the water column has been the concern of regulatory agencies and environmental intervenors. While toxicity studies with pollution-tolerant fish and brine shrimp have resulted in high survival percentages, the effects of L VP on sensitive plankton, algae and other fish species are apparently not known. CP&L/E5-40 12 ) IJT.ERATURE CITED Anderson, W. L. 1978. Waterfowl collisions with power lines at a coal-fired power plant. Wildl. Soc. Bull. 6:77-83. · Avery, M. T. (ed.) 1978. Impact of transmission lines on birds in flight. u.s.D.I. Fish and Wildlife Service. FWS/OB5-78/48. 151 p. Beaulaurier, D. L. 1981. Mitigation of bird collisions with transmission lines. Bonneville Power Admin. Portland, OR. 83 p. Cassel, J. F., D. W. Kiel, Janet J. Knodel, and J. M. Wiehe. 1979. Relation of birds to certain power transmission lines in central North Dakota. United Power Assoc. Elk River, MN. 50 p. Faanes, c. A. (in press}. Assessment of powerline siting in relation to bird strikes in the northern Great Plains. U.S. Fish and Wildlife Service, Jamestown, North Dakota. Gauthreaux, S. A. Jr. 1978. The impact of transmission lines on migratory birds: Assessment of completed, ongoing and planned research and an analysis of future research needs. Depart. Zool., Clemson Univ. Goddard, S. V. 1976. Special studies: number and composition of birds killed by striking transmission lines from the Prairie Island Nuclear Generating Plant. Northern States Power Co. James, B. W. and B. A. Haak. 1979. Factors affecting avian flight behavior and collision mortality at transmission lines. U.S. Depart. Energy, Bonneville Power Admin. 109 p. Malcolm, J. M. 1982. Bird collisions with a power transmission line and their relation to botulism at a Montana wetland. Wildl. Soc. Bull. 10:297-304. McKenna, Michael G. and Gary E. Allard Nov. 1976. Avian mortality from wire collisions. North Dakota Outdoors. Vol. XXXIX, No. 5. Stout, Jack and George W. Cornwell. 1976. Nonhunting mortality of fledged North American waterfowl. J. Wildl. Manage. 40(4):1976. Weir, R. D. 1976. Annotated bibliography of bird kills at man-made obstacles: A reivew of the state-of-the-art and solutions. Environ. Manage. Serv., Canadian Wildl. Serv ., Ontario. Wiese, J. H. 1978. A study of the reproductive biology of herons, egrets and ibis nesting on Pea Patch Island, Delaware; report for the period March through September 1977. Delmarva Power & Light Co. .- Willard, D. E., J. T. Harris, and M. J. Jaeger. 1977. The impact of a proposed 500 kV transmission route on waterfowl and other birds. Willard and Assoc. Inst. Environ. Studies. Madison, WI. · CP&L/E5-40 13 ) ) Willdan Associates, Inc. 1982. Impact of the Ashe-Slatt 500 kV transmission line on birds at Crow Butte Island: post-construction study final report. Bonne- ville Power Assoc. Portland, OR. r CP&:L/E5--l0 14 MEMORANDUM State of Alaska DEPT. OF NATURAL RESOLRCES, DIV. Cf' LAND & WATER MGMT., SOUTHCENTRAL REGION TO: Tom Arminski, Acting Director DATE: May 2, 1986 Environment and Licensing FILE NO: Bradley Lake Hydro THiU: Robert B. Cutler APA Unit, Project Manager TELEPHONE NO: 762-2274 FROM: Deborah K. Heebner SUBJECT: Transmission line Route Natural Resource Officer RECEIVED w Map Review ALASK,,~.~~~-·-~ · We have reviewed the Transmissi~i~2Yt~~ketch 17, SWB9-2ll-3 for Bradley Lake Hydroelectric Power~o!@et-~r~~~by Stone & Webster. A check of the most current land status data on file with OLWM revealed only the land conflicts listed below. ADL 24501 Fox River Cattlemen's Association Grazing Lease USS 2937 Fox Farm If you have any questions, please do not hesitate to call. . ---; ~L":':..~l'l __ _ _____ i Sw6<- l I 1---------2 ---- 02.001A IRw. 10/791 - MEMORANDUM State of Alaska DEPT. OF NATURAL RESOLRCES, DIV. OF LAND & WATER MGMT., SOUTHCENTRAL REGION TO: Tom Arminski, Acting Director Environment and Licensing DATE: May 2, 1986 FILE NO: Bradley Lake Hydro ~~~ TELEPHONE NO: 762-2274 FROM: Robert B. Cutler suBJECT: SHPO Concurrence on RE'c;:-rv=-o ov r1r· d T i . APA Unit, Project Manager ALA SK,~ ~ -~·; --.·: '-,, ... J.ne ransm ss1on ine Route "86 HAY -7 A9 :So The APA's proposed refinement of the Bradley Lake Hydroelectric Project's Transmission Line is acceptable to the State Historic Preservation Office (SHPO), subject to the following being accomplished: An Intensive Pedestrian Archaeological Survey be performed in that area of the proposed transmission line corridor, in non-muskeg areas, as generally depicted on the enclosed map and specifically identified, at the meeting held at Stone & Webster (May 1, 1986) on your photo map by Tim Smith, SHPO, in the following general areas: Sec. 25, T3S, RllW, S.M. Sec. 30, T3S, RlOW, S.M. Upon review of the survey results, SHPO will advise you as to their concurrence on this portion of the transmission line. Except for the area identified above, SHPO has agreed (by conversation with Judith Bittner, SHPO, on May 2, 1986) that the Refined Transmission Line Route satisfies FERC Sec. 106 requirements. Your evaluation of alternative routes has resulted in an alignnent that alleviates, to the maximum extent possible, any impact to known resources, including the Hilmer Olsen Fox Farm. tnclosure cc Judith Bittner, SHPO Tim Smith, srFO Ned Farquhar, CO Mike Vediner, CO Norm Bishop, SWEC 02-001A IR8¥. 101791 RECEIVED MAYo 7 1986 SWE'C-ANCHORAGE -I !J ,._., ' ........ -. , .• ...1 • "-. _.._/U..nau::::::~.z;ul~,J~JU!,i;;~Jl..-.-_~ -~tf;-_C: ~J,;],Nt 1-------. ,.., ~, •• ,<•;tt s .! ).J, n ~rf!: f :II' ........._.. p~ l ;nc.,,.,.., w (/lf4rll} ..# H r::. I . r- J'~~. DEJ•ART,IEXT OF XATURAL RESOURCES DIVISION OF LAND AND WATER MANAGEMENT SOUTHCENTRAL REGION ~~ay 5, 1986 BILL SHEFFIELD. GOVERNOR 3601 C STREET BOX 7.005 ANCHORAGE. ALASKA 99510-7005 PHONE: (907) 561-2020 RECEIVED MAY 07 1986 SWEc-ANCHORAGE Joseph F. De Smidt, Jr. Box 776 CERTIFIED MAIL # P 540 499 145 RETURN RECEIPT REQUESTED Sterling, AK 99672 Re: ADL 219905, Right-of-Way Permit Application Dear Mr. ~t :.Jo-e.....- I apologize for the delay in responding to your letter of November 24, 1985, regarding the Right-of-Way Application, ADL 219905. A review of this application has raised several concerns on the route selected. Although the easement requested has been traditionally used, the location may not be the most advantageous due to the long circuitous route and the presence of peat and poorly drained soils. Also, it does not appear that one single route is continually used but rather several routes are taken across wetland areas, especially south of Caribou .Lake. An example of this is on the ~GS topographic map; a trail is depicted which parallels your requested right-of-way, but isn't the trail that was applied for by you. In conclusion, this office feels that it may be premature to reserve an easement across an area that may be unsuitable for a longterm, permanent easement. Your use of those state lands as described (i.e. four wheel drive vehicles, ATV's, three wheelers, etc.) is a generally permitted activity which can occur without a right-of-way easement. If you are able to identify a specific alignment where a right-of-way easement can be properly located (i.e. centerline description tied into survey monumentation) that will be used by the public continually and avoid having a variety of trails across this area, then a right-of-way permit will be considered. This situation is not unique, but it is not in the state's best interest to establish a specific right-of-way easement on a "floating11 trail. Mr. De Smidt May 5, 1986 Page 2 This decision is final insofar as the Southcentral Region is concerned. Any further appeal should be addressed to the Director of the Division of Land and Water Management, in writing, within 30 days from receipt of this letter: Tom Hawkins, Director Division of Land and Water Management P.O. Box 7005 Anchorage, Alaska 99510-7005 If you have any questions regarding this matter, please contact Deborah Heebner at 762-2274. · Sincerely, ~~ Regional Manager ~ Alaska Power Authority APA/OTHR/0018 May 5, 1986 Mr. Robert Cutler Division of Land and Water Alaska Department of Natural Resources State ot Alaska 3601 "C" Street, Frontier Building Pouch 7-005 Anchorage, Alaska 99510-7005 ALASKA DEPARTMENT OF NATURAL RESOURCES ( ADNR) APRIL 23 AriD 25 MEMO VISUAL RESOURCES MITIGATION PLAN VEGETATION CLEARING PLAN EROSIO~! CONTROL PLAN BRAPLEY LAKE HYDROELECTRIC PROJECT Sill Sheti1e1d. Governor ~~ Thank you for providing agency consultation on the Bradley Lake Project '·s Visual Resources Mitigation Plan, Vegetation Clearing Plan and Erosion Control Plan. The Power Authority has responded to each of ADNR' s April 23 and 25, 1986. comments on the attached pages. For your convenience, the ADNR comment is followed by the Power Authority's response. Thank you for your continued consultation. Should you wish to discuss the responses please contact Mr. Thomas J. Arminski or my self at (907) 561-7877. Very truly yours, ALAS~A POWER AUTHORITY ~fi~J(~ David R. Eberle Project Manager DRE/NAB/JJ Attachment PO Box 190869 701 East Tudor Rood Anchorage. Alaska 99519-0869 (907)561·7877 2-601-JJ ALASKA DEPARTMENT OF NATURAL RESOURCES (ADNR) DIVISION OF LAND AND WATER MANAGEMENT APRIL 23, 1986 LETTER FROM MS. MARGARET J. HAYES VISUAL RESOURCES MITIGATION PLAN BRADLEY LAKE HYDROELECTRIC PROJECT Page 2-13. Paragraph two: ADNR Comment On page 2-13, it is stated that the "Regulatory agencies contacted during ongoing consultation have reported no public concern over visual effects of the project." On April 15, 1986, DNR held a public hearing in Homer to discuss Phase I of the permitting process (i.e., leases, material sales, contracts). Testimony taken during that hearing did not indicate visual impacts as a primary concern. However, DNR feels that given the keen awareness of local residents to environmental concerns of the project, comments specific to the Visual Resources Mitigation Plan, if solicited, would be received. Public concern over visual impacts regarding the. transmission line corridor is expected. Alaska Power AuthoritY Response: The transmission line will have a visual assessment once the alignment is finalized. Visual Resources are being considered in the transmission line design as well as many other environmental, technical and economic. Your concern will be addressed as part of the transmission line visual assessment. 2-569-JJ 3 ALASKA DEPARTMENT OF NATURAL RESOURCES (ADNR) DIVISION OF LAND AND WATER MANAGEMENT APRIL 23, 1986 LETTER FROM MS. MARGARET J. HAYES VISUAL RESOURCES MITIGATION PLAN BRADLEY LAKE HYDROELECTRIC PROJECT 5. 1 Description of Pro 1ect Design Considerations to Minimize Erosion and Sedimentation -General ADNR Comment The feasibility of maximizing winter construction activities to minimize erosion should be addressed. Guidelines for the design phase should also include specifications for monitoring of activities causing erosion. Alaska Power Authority Response: Due to scope and geotechnical considerations winter construction will be limited during the Site Preparation Contract and Main Construction Contract. Prudent engineering practice requires the placement of unfrozen soil · and rock in the dams, roads and work areas. The underground work can proceed during the winter. Winter construction and special ATV's (i.e., nodwells or wide track vehicles) will be utilized for the transmission contract in environmental sensitive areas. This measure will limit land disturbance and erosion. 2-569-JJ 8 UNITED STATES DEPARTMENT OF COMMERCE National Oceanic and Atmospheric Administration NationaZ Marine Fisheries Se~Jice P.O. Bo:c 1668 Juneau, Alaska 99802 RECEIVED May 7, 1986 PEC~IVfr'J qy ALAS~,' -· . -..• '· MAY 1 4 19BS .SWEC·ANCHDRAGE "86 HAY 13 A10 :44 Mr. Tom Arminski Alaska Power Authority P.O. Box 190869 Anchorage, Alaska 99519-0869 Dear Mr. Arminski: We have reviewed the draft Assessment of Transmission Line Alternatives for the Bradley Lake Hydroelectric Project and have recently met with Stone and Webster personnel to discuss proposed revisions to the line routing. Based upon this in- formation, we agree with the "refined alignment" corridor utilizing steel x-tower supports. Sincerely, /f _(·kg~ Ro)iert w. McVey ~rector! Alaska Region ---· ., '! -: ~~~:;._:~--<_: ---· ·\--.. t-.;.-;..;...::i: ;...;,;, r .Cf.: I &:zt-N'JJGI ::= I s~k I ' ' ..... :·~. 'J ". I --------------- ---J'l'ans'",)reJ ~! ./f/asi~< R.t.~!lW) LUI IJw,·SI;,... i il.tpMI-m-.f ( )}a/-AJ L"'"J ..,..d. wc:t;;;;\ RECEIVED /f)MJ~~~-r Fox River Flats Critical Habitat Area . MAY 2 3 RfCO AUsKA POWER AUlliORITV (A) Township 4 South, Range 10 West. Seward Meridian Section 20 S~ (not tide or submerged land) Section 21 ~ (not tide or submerged land) Section 2Z ~ Section 23 ~ (not tide or submerged land) Sections 25-29 Sections JJ .. J6 (B) Township 4 South, Range 9 West, Seward Meridian Section 30 ~ (not tide or submerged land) MEMORANDUM State of Alaska DEPT. Cf" NATURAL RESOURCES, DIV. CF LAND & WATER MGMT., SOUTHCENTRAL REGION TO: David R. Eberle DATE: June 4, 1986 Project Manager, PPA THRU: Robert B. Cutler~ APA Unit, Project Manager FILE NO: Bradley Lake Hydro TELEPHONE NO: 762-2274 FROM: Deborah K. Heebner u'./J Natural Resource Officer suBJECT: Review of Assessment of Transmission Line Alternatives The Division of Geological and Geophysical SUrveys (DGGS) has finally reviewed the draft "Assessment of Transmission Line Alternatives" for the Bradley Lake Hydroelectric Project. OGGS indicated in their comments that the concise, rigorous thoroughness of the report was to be ccmnended. I have attached the specific comments of OGGS for your examiniation. !l<H:bsp/0176p BECEIYEO. .~JN 0 5 1986 ~'M POWER AUTHCRI'll RECEIVED JUN 061986 . SWEC-ANCHORAGE MEMORANDUM State of Alaska TO: FROM: SCOTT CHRISTIE DGGS:ANCHORAGE . .-:?/ RANDY UPDIKE l L DGGS:EAGLE RIVER MAIL STOP: DATE: FILE NO: TELEPHONE NO: SUBJECT: 29 May 1986 688-3555 BRADLEY LAKE HYDRO TRANSMISSION LINE REALIGNMENT REVIEW At long last I have had an opportunity to review the above referenced document. Attached herewith you will fin~ my comments which I hope will be of some value to the team working on this project. As indicated in my comments, I was very pleased with the quality of the report ..• someone should be congratulated on some thoughtful and thorough work. Please express my apologies for being so late in getting the review completed. Also,. express my thanks for giving me the opportunity to comment on this aspect of the project. ENGINEERING GEOLOGY SECTION Alaska Division of Geological & Geophysical Surveys .c , JiT~~~:t:;r ;:it. ;SUBJECT: Bradley Lake Hydroelectric Dam Project . i. 1 ,l. l~_;·-::,-:..::· ~:~;.::;;: -~ .. ·,-::.:. ... ""-:: .. · ..... 'ITEM: Draft ~ransmission Line Alternatives Review ,.,r_.....,,,c. . ,,, J ,, 1 , ,,.;.·; .' •• : ; . • . 1 Updike::chief of Section '-:--.~··; .1:·£~-;"' ~;~~~ ."~-: discussed: (1) FERC alignment, +E,;;;i~~riHil'fl"'•:•';...::;;,e..r;~:iit~02~t."~= .. t .. ·'-'"·r::;·· ·~ ! ., .;-;.' , ~· · i · Bay mud flats route, (3) Submarine ._;tj~~~l!';~,;~.:;·~ :. ~,~· -. I.' .. -!_ -t, 1 ~ • ·~:~-•. ) Refined FERC ·alignment-. · '!fd~~~~,~!..;;·~'"--~~;·.1"-'i.-;i,..~ .;<..;, ~1r~(~--:· r·~ 'f,;L~}, _not appear· 'feasible from a ge.o-:.:·· ' ' . -. : .. • :. •,. ·! 1·-; -:.•..:·~·~ . -· '' I - andpoint .. because of serious lique~ : _..;:..~ .. , •• ~--. :i<.~~---~ ..... ~~-.:~· ·~; ••. b-le-ms. ~ .. I agree.: w·i th the elimination ~t. ~r;..~~..: "" .. ; .. ~..J.J: ... :.. ,. -: : :....;"l.t.~-;11,-. :· . . ·--~ 1 ternat~ ve. ·,. ·., .. .:rl:,~::: ;..,. •. , •.... r • "· ·~1~·~ f·a·~·f~~-~e ~o~:i:~~·'' tha~,-other"subm~~i .?"j•~.~:.lt:~'.f,;:S::"'!-:141"'~?~!~1;.~~ .-\~.""1":"~-:· • ..: ' : ... ;..:;:: -;' .•. -J ."': • • • : ---.... - 'presently in operation in the state-. . :~~·1:f;!l'-, ,li,.,;.· !;.;;s~:;,_ .... ~-i-•. ·: .• :--: . .."· ..... ···,··':·!'·, •. .1. . ... ;.~ --~--.._ ..• · • -. ~: . -·~. '-~ . • ,• Chugach Electric Beluga line across Knik ~· .:;~.-:_::~::-~·-·' ::'•>.· : .. :· .,.,.···~~---: :' ,., -:.-1~-~· Arm to· Anchorage).· "Trenching problems of lique- :~·· ·:l,; :. ~:-..:.· .. :;t.i~'.: ~~-' -. \ .<!'• ...... ~.:~. . . ·.~ ~ i '. ' .. iable ~,soils, water ··inflow;·· and maintenance of :.J~::i~.~~-·-~!t·~·.-.:~;·t::::~ .... :.· -~. . .4. • ', • '. :;--' --· j · grade "alignment, ·plus the logistics· of ·reel : , .... ~t~ .·,~ ;, ·; ··:.:r:-:~; .. -"1":'o<<.-~ • • . y . • , • ~ . . ::~'>: . fr.l~~>-_tran~port . affects not only. the cost of the project f;r~:r.,.,:.~~;i6.,1:r~¥-',..;•!' ·, .. ·:•i,;;.·.,· .. .-:.f·_;:> ..• ·''· ' . .. _. ; , .; -1 , .::,~·~:-;. ...i: :.;.:~.;;::.but the assurance of success, maintenance and .l~t<.·~----"~,·~· -~·-~~·-_,-·_, .. :tr,. a'"l-1-.· -. .... ~1 .::~.' :·' ·-. ··:· ;;io~i ~-oz:'i~g~·du~~ng life_, ().f. .. th~ _f ~ci.~i ty,. and -~~~1.;;:·-.. -A,,., '-'~ifillii7~Tx ~~t~~.i~~~~,de~;f -~ht·~~·~~~1i~r~~~~-~~ddi.~i~~~·i1~;, . ;.!J~:-;.!.(~~1)-.,.~-~.:-:-· ... ·.1~-·;:~~t _ _., ~ ··.:'.: ~d , ... ;;._" ••• ~·;·>·.. ~ j ---..... --.~:_-•. : -~->-. -~~--., i_ :·:the potential .for lateral displacement. of sub-'';:". ,)~~~~ ~.--~. · ···?--=:..J-;::~>t.. ·• · · ..... .:·· ·• ·~ ~ ···~~-........ ; ... :: · • 1 ·-. :·~·"'"" ··~·~;:.e.:'~..:. .;r~·:· .. : · ·i-';, ·marine soils in the event of major earthquakes · ·~-· ' ... ~ -~ , '.,.;. ~·f ' .. ' ' -• ·! ,« -~..:· ..... ' , ..... ·~!"! ...... ..., .. ....,~ ~ -...... ..:::;., ]"·-· ~~-:-'-~-::..;i,~3•<;;i:~ _could cause rupture of one or more lines·; with. -' ... ".1 .. :.·" .. "'; ~ .. ~l-. · ~~, .. '""-·-:-_ .. · .• , J ·~· : .. ~ : •••• -... '" • -1 ··~•. ~.-.~··.'".:.:..~'":'·"'~-;., ... ~.l~~··r··"r.,_:."':'::,;-r~-~-.\.' , .. _,·--::u .. , ~repa'i~·s· bei~g ,;ery difficult. ~location ·-a:nd ·ac~~s.SY:~-::<. :~-·:-~·' • _...:-:-' .~.·,,: !~ ::·~. • • .,., ,.L~·,. '"• :~..,_ .. ~~ ._.. ''"','.._' ·-·on the plus side, habitat and visual concerns would ... be benefited. I agree with the elimination of this alternative. 4.] Concerning Route (4), the northwest segment has been realigned to take advantage of till hills rather than peat low areas. Thick peat was cited as the main concern. What type of soil underlies ENGINEERING GEOLOGY SECTION Alaska Dirision of Geological & Geophysical Surveys l.: :·:•:;\~;1~~~:;~~~::~~~:~ ~;.: [ Bradley--L~ke' ·Hy-dro Transmission Review/· Page 2] · .:<·· b~',1::1J~~~l~;-S" :' : ,; -: ' ·, 1,~,~~~--:~>~~~J.}.~,"-~~!.l...t~t~~I.~-----~-·-~;. ~ .. \ ·l < • • ·: •• ~t.:.=:;'•i::;;~;.b~ ·:.eccepta)?le ~-contingent upon strip excavation · ~.:U.r:_~cl, '•~~~~et'~,,.;;.~~~~~~~~~'~;;~ ·?•--"" -~ . . .;j ~ .. _ .. ~:.!:·'".:-._~--·--_-.• -_·---.·-:_··~~···1·;··~·,·1~.:._ •• ~.~-••• ·.::_~···:·:··.·:·;•-~.-'..: • · "'f · '~-S ~~·:If<·· ·c) f · the .,.pe_!'-t .zone , ,>:ins t a 11 at ion of drain system ,· ~~-:" · . -~-~:;.;>!. .,J:<>"-··:;,_,i·:;::>.1I'._.:~..,.J'••!::;j,',..~•· C•i•T·~ ,l _, . ·-~~:~.{.and ''backfill. wfth.NFS gravel. However, I would · .:.· ,, ·,$?-"fi;:-~.,o.:.::J,11;·~A~~j;;~;,<t'~~..;~ .'~~"'· ''r0 • .: • ,ct~·~·!;.i··~· .. . i:4 ·,.:-:-:!i.'-t..-';;\_:.:,_ten,d. to ·.t!u~p~:-~.Jr~~t .. s':lscept.1.ble clayey .si 1 ts !~.:..~·~ ,_,-.;.'~~~--~~~jf{J:;::r~~~;-;· ..,.,;:.~-1H ·-:-''-· .. ·."1-·. ~ .. :.:'· ~;r:':'~'.-.;:.::~o.'j::jt:under .the· peat ·which· would be poor for foundation ~· /,.~~~t~:~-;~~ Ji ... ¥=1-~!~-~~~,h~'4!..~~~s-:'!,~~#·j,i~i~: 1.~~~;;·":~~.; ~. . ,... . . • -,.·:~ :;; :':~. c~=.r."d:~t"v or.k :and .ma.J.ntenance ;·:.:.·~"'.! .suggest the bor.J.ngs be . ~;t~·;~· .... ·:/'-:-~~ ~f :·.~~~~,~:~~-~-~1 ~ ..... ·~·~:v~:-l:"-t:~?~·;. _. -~.:.;:~!"~ ._!S'~.:,1 ~: ~-:~-. . I . . •.. ·.-: ,.·~ -· .i:~f}.·.~ ", ·_ ·;y·;;:;_ · eviewed ~o-nce· more· for (a) peat thickness, · ·.: ·,, . t:::\<~-~.,~-·:~;-__ ·~r~a,~ ;:,r.:~~::...;;;a~~~p.,.·r~-:....~·-•:, .... ~~~1"·:~:i~~-: .. l •• j'" .", .... •· --.;_ :~--:··- .. ):;i.i;~~:;:·~·: ..• .:.;r1~1f-:A · ·soil,:-types 'beneath the peat, ·and (c) natural ;;~·.54:~:i<E?.::~'-t:~:-::,,:s.Jt·;A · !"..:1~~;.~t--r~-~··i_r<"~;·,~_:·-''·t:1 .... :;-:~-·: .:· ·-:" ·. , :_ · _,. · ~ ·:,__ ·..; ~~:~f:.v~X~.;~··;>~.,;.~:;~-~~ oist~r.; 1 7-onteri~, ·yariation with depth. With no , , ;;~-j~-f~;-i~-~·)+'7~;':~~ ~-:~·r:~:r---~-7-.. ~~·.:f-1 w. ·~~·p·· ..• ~ .. · . ... ' ~: .. .•. ~ •.•. ~~ : ,;_ ,.r•,r-·-"; dd.1.t.1.onal data ava.1.lable to me I would support ... : :l~~ ... ~.: ... ·.,:.::~~ .. : :_ :.~ .. ~;.:l. -~ ~:: ~~;~"1:..:/.-:-~,.~~--~-o.-.. ;' .~ -:~ ". : . ' ' ::~r:;r;fi~·:;::·; :·:_,;;f~.~~~~.f:r _ll..t;::_re_~l.ignmen~. pr~posed •.. ·_The severity of. the ._,.t-<.[ ·•1;'~.: ,..,.. -•.~ : • ' ..,.-~.-.. :_.,.i.:-• .. ~rl-.;;_.1,. U •-• "'~ f f•'l' L4---~t. •· , • • i·K,.;L.: · · ~-~:{.tJ~~:;.cor_r!-do~ .. li~e ·.angles __ pre::;ent_ i~ the_ original FERC -J: ~•, ; ' ;;.:, ·f~·-;,._ --. f:.~ ;."'r• c J --;:.-:..·-;.f+.r~:t.r • ~ -• t-' .., .. .., .. ~ , • -_, ·.Ir::,:·--·~L ~1: ~~· :; ·:.~ri}~..:~,align~ent ~Is favorably' 'reduced by the revised 1 J1.;..~;:~;-..;-, ~ . ti}'~J·..:l·:.···t"'•_ f:-.:..j:. ~-~~ .. : ... ~~~;::~·.... -··· j I~'·. j+~.: I · ... ·-~ ·~1.-~:{~~-..-:· f~~4'.:s.] I:or· the "segment of route '(4). 'traversing the west ,~t,-~~~i~_::._;~ -·~:1j~~t~~1~bl~Jf'f'·~~f-"~F~~ ·,Rl ~e-;''·~~J.'i~~-~--:1~~·: ~hould p~~bably .-.~-~· ~;~~i··"'!~t"~J~~--__ :_:_:;;·~.-;-:-!;~=~·--;~7: 4:~:;1:-~-'i.~~~~t~-1-r~-~ _.. .... -··-· . -I ·"":. ~ .~~L_1:;,:n · ~~' '~;:;.;:;~i.ti:~..:·}~·ask, ;why· is the supposed resistant projection ~ :1 ,:a~ !"':'~;.fr .. !.:.;•;:/ ~-· __ ... ,_-:.. .. 1<. '?:'j.!:~!~~~ '" ', ~ .. :1~; _;_,, · --· _ ~ ~ ·t -~ • ..:..: · ~ ~ ~ : __ _ r:~Y.52:;:(~~·:::~;;:~;~~~;t~~~-~;;~!~+J~~~~--;l?~~se.~~ _a~ ~~:is . selected point? . Ba~ed - .:!,~:??~~:.:-:~:·-:·~-~;"',:~~:-~¥~;;;:.··solely on _t;he topographic map (fig. 2) I would , .,~.. ~·~,_.;·"t'• ..• / 'J ... :r .. ~~ ~~L.-i~·4~~::-.... .t·:~-. -.. .. ~ .. ~. ~~·---:-.:~ :··.: .. io,o• • -·~·.: -~..--··- ·. :: · ~~·,.;·~::n t,--~(0);~":.-:gue.s~-~-t.~a~~~-~is ~i-~_,an~;area _of _gla<:_i~l. mo~a~ne ;/ ~-·: : ;t~t~ !t.~J·~:t· !-..3.~i~1~~~!-~i~t :e.t~J;:"'"~~~~~~ ,r~~:;;c.;.~!.:_.Lj. -... ·~~!• v·., ~··· .,.._...u-.. ~•~~~·-· ~=.,.:~'lA-':t~i--~-~.:i.:~~:~ .. ,.,~ · ··~;~, O:"'l'l~:·.~:: .Y~~.,·.~. whi_ch }~,·.re,:~dst;~nt ~.to _erosion, stands :·in_: a s.~e_ep · -~~*~.s.. fj~~;j~--\"«t_... :_: : • .::;;..,'{;.: ":"-:£:: ~.;_ ;\.'-_-4 ~-~-~~--~~.-11\··~·.·; ·~~.J~~~-· .. -4~. . ,_ -~. t • ... ~ .. : ...;.e :.,..---..:\~'h.· "':"". :;:;' .. · -·~·'=""''" ..... : ;~~~,~~a:· -: .·r;r:.;·: bluff .. slope, ·and should have excellent foundation .. ''::"\....::i~'!"~;~.-;::"'~."'1-;. ~· :.:·:~-: ·=; ··.. ·:·--.~:: .... ~~"'_:---._. ~· .. ::. ...... ;:_.;.:.: .. _-:.:;;.:i:':"""~ •• ;:'t'_ .• : . • . ,· :-· --4:.. ,.·:~ , ',• .. ··:· .. ~~··. ~.:;.-c :...*' ··----:~ :~: ~~-· .... :-;:,;~.:;-:-:;.:;i~:. characteristics~ . The only two alternatives I c·an " ·.0\~,:~;,~~--:.7'; ,,,_, 1 -''.·.see are di'~~·~;i~,,~-ou~h'in sects •. 2 and ll:~he"re' ?<! ::~:: /< ·i :t.~ ~·-"'~~~~t·;~t~;~~~;·o~·inent-c points exisi} :_·I h~:..~~· ''t;·k~n;,.~- •• 1 _,; -. ' ' the liberty of drawing an optional Fox River .. -~-· .c-: approach on a copy of the provided fig. 2. 1 This . .--:-. option probably impacts the habitat issues but if not might be worthy of consideration because it (a) reduces by at least 1 mile the length of this segment of the corridor, angles to the slope. ENGINEERING GEOLOGY SECTION Alaska Division of Geological & Geophysical Surveys -" . ,':.-~ -~1 I. . ~ [Bradley Lake ,Hydro Transmission Review/ Page 3] quite variable foundation conditions but this will be ··adequately considered in siting of towers. If not previously noted this first segment may be subject to avalanche run-out. At the proposed tower site locations in the bedrock segment ( 2. 5 -·-. .. _;;: ~ ~. ~ -:-.1 ... -:...: ---.. :-~ to 4. 5 miles from the powerhouse) careful geologic __ . -----,~:=_?~J-~~ evaluation of bedrock structure will be necessary · , -· '-_ ::._~---:-? to assure r~ck slope 'stabil-ity~~~ At··"fh~--s:i~~t{~~-~';r,::~:;:~~~~~' the approach of potentially active faults to the_ ;:7~'· _ ·'i_~-~l ~--~ -·-_:-_ ;._:_-·:£~?~ . --~--·--~-,~' --~!;-~::-: ·~--~ .. ~-~~~j·~-----~-71-~ --~ ENGINEERING GEOLOGY SECTION Alaska Division of Geological & Geophysical Sutveys ' . , . ·: . ·· .. ,_ -.:; .· ~ .--~ -./ -...... ~4-.... -. -"·-"" • ~, L, __. ........_ I (/') UJ (\J ~ w ~ 0 0: a: ::) w > CJ i= - ~ lJ.. z a: w ~ ....J ~ [~ ~!OTES OF CO!'JFERENCE MIDDLE FORK DIVERSION AGENCY REVIEW MEETING BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POHER AUTHORITY J.O. 15500.12 \·!P 980-6 Held in the Conference Room Present for: Stone & Webster Engineering Corp. 8oo A Street Anchorage, AK 99501 June 5, 1986 PURPOSE Agencies: Don McKay, ADF&G/Habitat Hark Kuwada, ADF&G/Habitat Bob Cutler, ADNR Michael Granata, ADNR Deborah Heebner, ADNR Leroy Latta, ADNR Hank Hosking, USF':.JS Scott Hansen, COE Patty Bielawski, DGC/ACHP Alaska Power Authority (APA): Toa Arminski Stone & Webster Engineering Corporation (SWEC) Uorm Bishop Hyrl Fisk Bill Steigers The meeting was held to discuss a preliminary assessment of the technical, econooic, and environmental considerations of alternatives for the Middle Fork Diversion. Two distinct alternatives to the FERC Lioonse Application were discussed: (1) an open channel diversion; and (2) overland construction access to the Middle Fork diversion site. Attachment 1 is the meeting agenda. Attachment 2 is the sign-in attendance sheet. Attachment 3 is a pz>eliminary assessn~nt of the proposed alternate open channel diversion and construction access for the Middle Fork Diversion. DISCUSSION T. Arminski presented a short introduction to the Middle Fork Diversion. 1-303-JH 1.0 Old 3usiness N. Bishop presented the results of a May, 1986 assessment by SWEC of the height of transmission lines over the tidal flats near the Hilmer Olsen Fox Farm. It has been determined that the 50 feet minimum conductor heights can be maintained as recommended by ADF&G/Habitat without major tower modifications. o The minimum height of the transmission line conductors above the mud flats under "normal" loading conditions will be approximately 67 feet. This condition is taken with a temperature of 40°F which represents the prevailing condition when waterfowl are present during spring and fall. o When the temperature increases on the conductors from 40° to 60°F, the minimum height of the conductors will be about 65 feet. o A 30 foot minimum sag height could occur under the extreme design case when 1.7 radial inches of wet snow occurs on the conductors. This has a probability of occurring once in 50 years based on our meteorologist's report. o The probability of waterfowl being in the area at the time when the extreme design case will occur is low. This design case will occur during the winter when the birds are not present. T. Armin ski reported that no settlement with the U.S. Department of Interior (USDI) and the National Park Service (NPS) has been reached related to the resolution of water rights fr001 the Nuka Glacier, although APA is continuing to discuss the matter with them. All FERC Article Compliance plans have been approved, and APA is prepared to begin construction of the Bradley Lake Project. However, the APA Board of Directors has, at this time, decided to delay proceeding with the Project until an agreement is reached. Responding to a question by P. Bielawski on whether an amendment to the FERC License Application would be needed if final resolution of the matter resulted in less water being diverted froc the Nuka Glacier, T. Arminski indicated that APA might have to go back to FERC if water quantities differed substantially fran those stated in the License Application. N. Bishop stated that total diversion of the Nuka Glacier flows contributed about 13% of the average annual energy output of the Project. Existing flows from the Nuka Glacier would contribute about 7% of the average annual energy. Up to 30% of the average annual energy of the Project could be derived during short periods of time fran the Nuka Glacier flows, depending on localized summer precipitation anomalies in the basin. 2.0 New Business N. Bishop introduced B. Steigers as a new addition to the staff at SWEC. With this staff addition, SWEC will be in a position to conduct revisions of terrestrial impact assessments and mitigation plans for 1-30 3-JW 2 ~ Alaska Power Authority APA/OTHR/0054 June 19, 1986 Ms. Patty Bielawski Office of the Governor Sto:e of Alos~o Office of Management and Budget Division of Governmental Coordination 2600 Denali Street, Suite 700 Anchorage, Alaska 99503 COASTAL PROJECT QUESTIONNAIRE TRANSMISSION LINE RIGHT-OF-WAY APPLICATION BRADLEY LAKE HYDROELECTRIC PROJECT Attached is the completed Coastal Project Questionnaire, the Alaska Department of Natural Resources (ADNR) Application for the Transmission Line Right-of-Way Permit and the Alaska Department of Fish & Game (ADF&G} Application for a Transmission Line Stream Crossing Anadromous Fish Protection Permit. Should you have any questions please contact Mr. T.J. Arrninski. Very truly yours, ALASKA POWER AUTHORITY David R. Eberle Project Manager DRE/EP/JJ Attachment 2-690-JJ • * * • • * * • • * * * * * * * * * * * PLEASE ANSWER ALL QUESTIONS. PLEASE INCLUDE MAPS OR PLAN DRAWINGS WITH YOUR PACKET. AN INCOMPLETE QUESTIONNAIRE MAY BE RETURNED AND WILL DELAY THE REVIEW OF YOUR PROJECT. PART A Applicant: Alaska Power Authority P.O. Box 190869 Contact Person:H.r. D.R. Eberle, Project Mgr. P.O. Box 190869 Address: __ ~70~l~E~a~s~t~T~u~d~o~r~R~o~a~d __________ _ Address: 701 East Tudor Road --------~~~~~~~~~------------ Anchorage, AK 99519-0869 Anchorage, Alaska 99519-0869 Phone (day): (907) 561-7877 Phone (day): (901) 561-7877 Brief description of project or activity, including timing: ------------------------------- See Attachment ··Location of Project: -------------------------------------------------------------- Township ___ Range ___ Meridian ___ Section ___ Aliquot Parts ___ USGS Map ______ _ Is the project on: private land x __ ;:;.;;._ __ _ state land x federal land x __ __;,:~-------- municipal land __ _ ownership not known --- Identify which region of the State (see attached map) the project is in: northern southcentral x southeast ------ * * * * * * * * * * * • * * * • * * * * PART B 1. Do you currently have any State or federal approvals/permits for this project? If yes, please list below. Permit/Approval Type Permit/Approval # Ex pi ration Date See Attachment 2. Will you be placing structures, or placing fills in any of the following: tidal waters. streams, lakes, wetlands*? Yes No X X * If you are uncertain whether your proposed project area is in a wetland, contact the Corps of Engineers, Regulatory Branch at (907) 753-2720 for a wetlands determination. 3. If yes, have you applied for or do you intend to apply for a U.S. Army Corps of Engineers (COE) permit? (The COE has jurisdiction over activities described in No. 2 above.) If yes, please indicate [in Question No. 4 below], when you applied to the COE or when you intend to apply. 4. Have you applied or do you intend to apply for other permits from any federal agency? If yes, list below. Agency See Attachment Permit/Approval Type Date you submitted or plan to submit application • • • • • * * * * * * • • * * * * • * * PART C DEPARTMENT OF NATURAL RESOURCES Yes X X 1. Is the proposed project on State-owned lands or will you need to cross x State lands for access? (Note: ln addition to State owned uplands, the State has jurisdiction over most lands below the o'rdinary high water 1 ine of streams, rivers, lakes, and mean high tideline of the tidelands seaward for three miles.) 2. Do you plan to use any of the following State-owned resources? a. Sand and Gravel Yes --No X If yes, amount? ------ Source? ----------------------------------------------------- b. Timber Yes --. If yes •. amount? -------------------No X c. Other Materia 1 s Yes No x If yes, what material? ----7(-pe-a~t-.~b-u~il~dr.i-n_g __ st~o-n-e-,-e~t~c-.~)-------- 3. Are you planning to use surface water? Subsurface water? If yes , amount? ________________________________ _ Source? ___________________ ___ 4. Will you be building or altering a dam? 5. Do you plan to drill a geothermal well? 6. Will you be exploring for or extracting coal? 7. Will you be harvesting timber from 10 or more acres? - 3 - X No X X X X X Yes No ·3. Will you be investigating or removing historic or archeological resources on State-owned lands? ·9. Will the project be located in a State park or State Recreation Area? (including the Kenai River Special Management Area) .~JO. Is any portion of your project placed below the ordinary high water line of a stream, river, lake or other water body? IF YOU CORRECTLY ANSWERED NO TO ALL THESE QUESTIONS, YOU DO NOT NEED APPROVAL -~ROM THE ALASKA DEPARTMENTicrF NATURAL RESOURCES (ONR). GO TO PART. 0. IF YOU ANSWERED YES TO ANY OF THESE QUESTIONS, CONTACT ONR TO IDENTIFY AND OBTAIN ANY .. ,~ECESSARY APPLICillON FORMS. · lf you have already contacted ONR, are you now submitting application(s) .. .for permits or approvals? If yes, list DNR approvals for which you are now !pplying: Transmission Line Right of Way If no, indicate the reason below: a. (ONR contact} told me on (date) that no DNR approval.s or permits were required for this project. b. Other. ---------------------------------------------------- .~ART 0 DEPARTMENT OF FISH AND GAME Yes X Will you be working in a stream, river, or lake (this includes running x water or on ice, within the active floodplain, on islands, the face of the banks, or the stream tideflats down to mean low tide)? Name of stream or river Sheep Creek, Name of lake -------Fox River, Fox Creek, Lower Bradley River If no, go to question number 3. 2. If yes, will you be doing any of the follow·ing: a) Building a dam or river training structure? b) Using the water? c) Diverting the stream? d} Blocking or dammi~g the stream (temporarily or permanently)? e) Changing the flow of the water or changing the bed? f) Pumping water out of the stream or lake? g) rntroducing silt, gravel. rock, petroleum products, debris, chemicals, or wastes of any type into the water? h) Using the stream as a road (even when frozen), or crossing the stream with tracked or wheeled vehicles, log-dragging or excavation equipment (backhoes, bulldozers, etc.)? X X X X No X X X X X X X i) Altering or stabilizing the banks? j) Mining or digging in the beds or banks? k} Using explosives? 1) Building a bridge (including an ice bridge)? m) Installing a culvert or other drainage structure? n) Constructing a weir? 3. Is your project located in a State Game Refuge, Critical Habitat Area, or State Game Sanctuary? 4. Does your project include the construction and operation of a salmon hatche_ry? 5. Does your project affect a previously penmitted salmon hatchery? IF YOU CORRECTLY ANSWERED NO TO ALL THESE QUESTIONS, YOU 00 NOT NEED A PERMIT FROM THE ALASKA OEP~ENT OF FISH AND GAME (DFG). GO TO PART E. IF YOU ANSWERED YES TO ANY OF THESE QUESTIONS, CONTACT THE REGIONAL HABITAT DIVISION OFFICE TOIDENTIFY AND OBTAIN ANY NECESSARY APPLICATION FORMS .. Yes If you have already contacted OFG, are you now submitting an application x for penmit(s)? If yes, list DFG approvals for which you are now applying: Transmission Line Stream Crossings/Anadromous Fish Protection Permit If no, indicate the reason below: a. (DFG contact) told me on (date) that no OFG approvals or permits were required for this project. b. Other. -------------------------------------------------- PART E DEPARTMENT OF ENVIRONMENTAL CONSERVATION 1. Will a discharge of wastewater from industrial or commercial operations occur? 2. Will your project generate air emissions from the following: a) Diesel generators totaling more than 1000 hp? b) Other fossil fuel-fired electric generator, furnace, or boiler totaling greater than 1000 hp? c) Asphalt plant? d) Incinerator burning more than 1000 1 bs. per hour? e) Industrial process? No X X X X X X X X X X X X X X X 3. Will a drinking water supply be developed that serves more than a single-family residence? 4. Will you be processing seafood? 5. Will food service be provided to the public or workers? 6. Will the project result in dredging or disposal of fill in wetlands or placement of a structure in waterways? (Note: If you are applying to the Corps of Engineers for a permit for this activity, the Corps will automatically request certification from DEC.) 7. Is on-lot sewage or greywater disposal involved or necessary? ··-a. Will your project result in the development of a currently unpermitted facility for the disposal of domestic or industrial solid waste? --9. Will your project require offshore drilling or vessel transport of oil, or other petroleum products as cargo, or include onshore facilities with an effective storage capacity of greater than 10,000 barrels of such products? 10. Will your project require the application of oil or pesticides to the surface of the land? IF YOU CORRECTLY ANSWERED NO TO ALL THESE QUESTIONS, YOU DO NOT NEED A PERMIT Yes OR OTHER APPROVAL FROM THE~LASKA DEPARTMENT OF ENVIRONMENTAL CONSERVATION (DEC) . . -GO TO PART F. IF YOU ANSWERED YES TO ANY OF THESE QUESTIONS (SEE CLARIFYING NOTE IN NO. 6~ ABOVE, CONTACT THE DEC RtGIONAL OFFICE TO IDENTIFY AND OBTAIN ANY NECESSARY APPLICATION FORMS. If you have already contacted the Alaska Department of Environmental Conservation, are you now submitting an application for permit(s)? '··If yes, list the permits for which you are now applying: · If no, indicate the reason below: a. (DEC contact) told me on (date) that no DEC approvals or permits were required for this project. b. Other. -------------------------------------------------- * * .-. * * * * * * * .... * .... * *. * .. .PART F ."o the best of my knowledge, this information is accurate and complete. .. s:; gned Date No X X X X X X X X 10 COMPLETE YOUR PACKET, PLEASE ATTACH YOUR STATE PERMIT APPLICATIONS AND COPIES OF YOUR FEDERAl .A.PPLICATIONS TO THIS QUESTIONNAIRE. PLEASE SUBMIT YOUR PACKET AS INDICATED ON PAGE ONE. p questionnaire/PERMIT BL-D-128 PART A ATTACHMENT COASTAL PROJECT QUESTIONNAIRE BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY Description of Project: Alaska Power Authority (Applicant) proposes to construct and operate a hydroelectric generation project with an installed capacity of 90 mega- watts (MW) on the Kenai Peninsula, approximately 105 miles south of Anchorage and 27 miles northeast of Homer, Alaska. The project would consist of the following: (1) 125-foot high, concrete-faced, rockfill dam, with a crest elevation of 1,190 feet above project datum, located at the outlet of Bradley Lake. (2) 20-foot high diversion dam with a crest elevation of 2, 204 feet, located on the Middle Fork of the Bradley River. (3) 6-foot diameter underground pipe from the Middle Fork Diversion Dam to Marmot Creek, a tributary to Bradley Lake. (4) A low diversion dike on the Upper Nuka River immediately below the Nuka Glacier. (5) 11-foot diameter, 18,610 foot long power tunnel from an intake at Bradley Lake to a powerhouse at sea level. (6) Powerhouse located adjacent to Kachemak Bay, containing two 45-MW Pelton generating units. (7) A 20-mile long, 115 kilovolt (kV) two-circuit transmission line from the powerhouse to the proposed Horner Electric Association Fritz Creek-Soldotna Transmission Line. (8) Access facilities, including a barge dock, airstrip, approxi- mately 10 miles of on-site access roads, and two construction camps. A more detailed description of the proposed project is provided in the Corps of Engineers (COE) Application for Department of the Army Permit, submitted with the Coastal Zone Consistency Review Permit Application Packet. Drawings of the various project facilities are included on COE Application Sheet Numbers 3-21. - 1 - BL-D-128 The proposed Bradley Lake Hydroelectric Project will be constructed under three primary contracts, as follows: ACTIVITY START DATE COMPLETION DATE Construction of barge dock, May, 1986 January, 1987 access roads, main dam diversion, and power tunnel portal excavation; establishment of camp facilities and telecommunications; reservoir clearing. Construction of powerhouse, May, 1987 March, 1990 power tunnel, main dam, and all other facilities except transmission lines. Construction of transmission lines. January, 1988 December, 1988 Location of Project The proposed project is located on the Kenai Peninsula within a Federal Power Withdrawal executed under Public Land Orders (PLO) 3953 and 4056 dated March 15, 1966 and July 18, 1966, respectively. The withdrawal lands are administered by the U.S. Army Corps of Engineers, Alaska Dis- trict. The Bradley Lake Hydroelectric Project lands were originally reserved in the Geological Survey Power Site Classification No. 436, dated August 29, 1955. The tentative project. boundary is presented in FERC Application for License, Volume 1, Exhibit G. A tabulation of lands of the United States and State of Alaska within the project boundary is included in FERC License Application, Exhibit A, Section 6.0 (Project Lands). The Kenai Peninsula Borough is the local governing body with jurisdiction over the Project site. PART B Question No. 1 -State or Federal Approvals/Permits Permit Approva 1 Type Permit/Approval No. Expiration Date ADNR Water Rights LAS No. 2836 ADNR Water Rights LAS No. 2838 ADEC Solid Waste Disposal No. 8523-BA006 January 25, 1991 -2 - BL-D-128 Permit Approval/Type ADFG Lower Camp Including Effluent Discharge, Battle Creek Stream #241-14-10610 ADFG Powerhouse and Switchyard ADFG Barge Dock and Staging Area ADFG Airstrip to Powerhouse Access Road ADFG Martin River Material Site Access Road, Battle Creek Stream #241-14-10610 ADFG Powerhouse to Lower Camp Access Road ADFG Martin River Material Site Martin River Stream /1241-14-10600 ADFG Spoil Disposal/ Waterfowl Nesting Are• ADFG Bradley River Dam Bradley River-Stream #241-14-10625-2010 ADFG Airstrip Construction and Operation ADNR Lease of Alaska Tide and Submerged Lands ADNR Leasing of Lands Other Than For The Extraction of Natural Resources ADNR Material Permit Permit/Approval No. Bradley Lake-1 071-0YD-2-850502 (AK851213-l4A) Bradley Lake-l 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Bradley Lake-l 071-0YD-2-850502 (AK851213-14A) Bradley Lake-1 071-0YD-2-850502 (AK851213-14A) Submitted November 15, 1985 Submitted November 15, 1985 Submitted November 20, 1985 - 3 - Expiration Date December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 December 31, 1990 BL-D-128 Question No. 4 -Other Federal Permits Agency Federal Energy Regulatory Commission Army Corps of Engineers Army Corps of Engineers Environmental Protection Agency Permit/Approval Type Hydroelectric License Discharge of Dredged or Fill Material into U.S. Waters Structures or Work in or Affecting Navigable Waters of the U.S. Permit to Discharge into Water -National Pollutant Discharge Elimination System (NPDES) - 4 - Date Submitted April 4, 1984 Submitted November 1, 1985 Submitted November 1, 1985 Submitted August 29, 1985 STATE CF ALASKA DEPARTMENT Cf NATURAL RESOURCES DIVISION OF LANDS APPLICATION FOR RIGHT -OF -WAY PERMIT ACL ------- Date June 2 1 86 The undersigned Alaska Pot..rer Authority residing at 701 E. Tudor Road, --------------------------------------- Anchorage, Alaska 99519-0869 hereby applies to the Director of the Division of Lands, (See Department of Natural Resources, for Right-of-Way Attached) feet in width and Approx. 19 miles (See ~~ in length located in Section Attached) , Township , Range -------- Meridian, containing an area of Approx. 810 ------acres as shm.,.n on the plat attached hereto in triplicate copies, for the purpose of constructing and maintaining thereon~ Two (2) 115-kv transmission lines for private, ~~~ii«~x±Rk~~' yearlong use (strike inapplicable words). State briefly the standards of construction of proposed improvements: The propo~ed transmission lines will be design~d in accordance with t~e National Electric Safety Code and Rural Electrification Administration (REA), Bulletin 62-1 (Design Manual for High Voltage Transmission Lines) as well as permit stipulations of the Alas~a Department of Natural Resources (ADNR) and other affected Agencies. Specific construction practices will be included in the Construction Contractor's Plan of Operation which will be submitted to ADNR following Contractor selection. Constructed -------~~----------Construction to begin ----~J~a~n~u~a~rJy~,~l~9~8~8~---------- To be completed ____ D~e~c~em~be~r~~l~98~8~----------------------------------------- If this application is approved, I agree to construct and maintain the improvements authorized in a workmanlike manner, to keep the area in a neat and sanitary condition; if said right-of-way is to be constructed across leased lands, I agree to reimburse the lessee for all damages to crops and improvements, to the extent of the fair market value thereof, which may be damaged or destroyed as the resulc of the constnJction of said right-of-way, and to comply with all the laws, rules and regulations pertaining thereto: and *provided further that upon termination or relocation of the Right-of-Way for which application is herein made, I agree to remove or relocate the improvements and resw:-e the area without cost to the State and to the satisfacticn of the Director. Signacure of Applicant ( Instruct:.ions for preparation of plat: Attach a copy of a letter-size plat, she·"' centerline and boundaries of right-of-way, sho'N ties from centerline to establis:.::d mom.rnents and section corners, show conflicts ·,...ith other rights-of-way, if any, sea 3"-4" per mile, type of survey.) *Not applicable to State Agencies. 10-112 (75) ll/84 Right of Way Width ATTACHMENT APPLICATION FOR RIGHT-OF-WAY PERMIT BRADLEY LAKE HYDROELECTRIC PROJECT Right of .Way between Bradley Junction and Bradley River is to be 350 feet in width, except for the section of transmission line from the powerhouse to the Bradley River which may be 400 feet in width. In this section, 2300 foot spans and topography dictate a wider width at the tower base. State Lands Crossed By Proposed llSkV Transmission Lines T.3S, R.lOW Section 27, 28, 29, 30, 34, 35, 36 T.3S, R.llW Section 21, 22, 23, 15, 26, 28, 29, 30 T.4S, R.9W Section 6, 7, 8, 17, 19, 20, 30, 31 T. 4S, R. 1 OW Section 1, 35, 36 Drawings Title Land Ownership Information* Route Map* Number SWB9 SWB9 220-1, 2, 3 211-1, 2, 3 *NOTE: This information will be field verified by the survey. BL-D-128 TRANSMISSION LINE STREAM CROSSINGS ANADROMOUS FISH PROTECTION PERMIT This letter constitutes the Alaska Power Authority's Application to the Alaska Department of Fish & Game ( ADF&G) for the transmission line stream crossings for the Anadromous Fish Protection Permit. The APA plans to construct two parallel 115 kV transmission lines from the proposed Bradley Lake Hydroelectric Power Plant to the Fritz Creek-Soldotna 115 kV transmission line at Brad!ey Junction located approximately 20 miles northeast of Homer. The total length of transmission line is approximately 38 miles (two 19 mile parallel lines). The APA has considered several route and structure alternatives and has selected a refined FERC alignment. The transmission line route follows the Kachemak Bay tidelands on the east side up into Fox River Valley. The transmission line crosses the valley and up the bluffs on the western side of Fox River Valley, The anadromous streams being crossed include Sheep Creek, Fox Creek, Fox River, and the Lower Bradley River. The transmission centerline has been located off sectionlines to provide for future public use of sectionline rights of way. Access to the project site is only by helicopter. A trail to Caribou Lake crosses the transmission line route in the Caribou Hills. The attached Drawings, Nos. SWB9-220-1, 2, 3 and SWB9-211-1, 2, 3 show the refined route. Also attached is a table describing the alignment. The assessment of the transmission line alternatives was distributed for agency review and comments incorporated into the design. The transmission line was previously included in an ADF&G application for the Anadromous Fish Protection Permit and Critical Habitat Area Permit. Construction is scheduled to begin in January 1988 and be completed in December 1988. 2-712-JJ TABLE 1 BRADLEY 115 kV TRANSMISSION LINES BQUIIHQ ALIQNMEHI May 151 1986 BRADLEY/SOLDOTNA LINE BRADLEYIDIAt1QND RIDQE LINE _fL Hoc thing Easting Section/Towoshio/Ran&e _ll_ Northing Easting Sect1on/Townsb1o/Raog~ 1 BS 2,155,496 275,949 SEC.29, T3S, R 11W 180 2,155,396 275,948 SEC. 29 I T3S, 2BS 2,155,360 283,749 SEC.28, T3S, R 11W 280 21155,260 283,771 SEC. 28, T3S, 3BS 2,156,158 286 1 124 SEC. 21, T3S, R11W 3BD 2,156,056 286,137 SEC.21 I T3S, 4BS 2,156,222 293,841 SEC. 23, T3S, R 11W 11BD 2,156,121 293,807 SEC. 23, T3S, 5BS 21154,458 296,209 SEC.26, T3S, R 11 W 5BD 2,154,358 296,165 SEC.26, T3S, 6BS 2,153,746 306,727 SEC.30, T3S, R10W 6BD 2,153,6118 306,710 SEC. 30, T3S, 7BS 2,148,975 321 1912 SEC.34, T3S, R10W 7BS 2,148,881 321,858 SEC.34, T3S, 8BS 2,145,861 3 24 ,117 7 SEC.35, T3S 1 R10W 8BD 2,145,769 324,1123 SEC.35, T3S, 9BS 2,144,8114 332,200 SEC. 36, T3S, R10W 9BD 2,144,751 332,148 SEC.36, T3S, lOBS 21 1341 3 30 34 0, 890 SEC. 8, T4S, R 9W lOBO 21 1 34 1 17 0 340,760 SEC. 8, TllS, 11 BS 2,123,360 338,435 SEC. 19 I T11S, R 9W 11 BD 2,123,388 338,338 SEC. 19, T4S, 12BS 2,120,518 336,975 SEC. 30, T4S, R 9W 12BD 2,120,585 336,895 SEC.30 1 T4S, 13BS 2,115,405 330,818 SEC.36, T4S, R10W 13BD 21115,1163 330,729 SEC.36, T4S, 14BS 2,1131530 327,840 SEC. 35, T4S, R10W 14 BD 2,113,585 327 174 5 SEC. 35 I T4S, 15BS 2,113,155 327,482 SEC.35, TitS, RlOW 15BD 21113,215 327 1400 SEC.35, TllS, 16BS 2,112,590 3 27, 17 7. 5 SEC. 2, T5S, R10W 16BD 2, 112,590 327 1 131. 5 SEC. 2, T5S, 1iQ.lE.S 1. Coordinates are projected state plane coordinates. 2. PI 1BS and PI 1BD is the proposed Bradley Junction and intersection of HEA's proposed Fritz Creek/ Soldotna line. 3. Final layout of Bradley Junction may require structures to be located in SEC.30, T3S, R11W. 2-639-JJ R 11 W R 1 1W R 11 W R 11W R 11W R10W RlOW R10W RlOW R 9H R 9W R 9W R10W R10W R10\V R10W NOTES OF CONFERENCE AIR TRAFFIC VOLUMES NEAR HOMER, ALASKA BRADLEY LAKE HYDROELECTRIC PROJECT Held in the Anchorage Federal Building, Air Traffic Division, Third Floor, July 3, 1986 PURR:lSE Present for: J.O.No. 15800.12 WP 98A Federal Aviation Administration Jack Schommer Dick Mathews Stone & Webster Engineering Corporation Bill Steigers The meeting was held to discuss Federal Aviation Administration (FAA) records on volume and routes of air traffic in the vicinity of the Bradley Lake Project in reference to the transmission line visual assessment. After intrcduction of the type of records and information sought by B. Steigers, J. Schommer and D. Mathews looked up records of the number ~ contacts that Homer Flight Service Station has recorded during fiscal year and calendar ;year 1985. Homer Flight Service Station has no tower and is operated on part-time basis from 6:00 a.m. to 10:30 p.m. daily. Aircraft contacts include arrivals, departures, and overflights of airplanes. During fiscal year 1985 (October 1, 1984 through September 30, 1985), 5,430 IFR aircra.f't and 46,767 VFR aircraft were contacted •. During 9alendar year 1985, 6,264 IFR aircraft and 46,819 VFR aircraft were contacted. VFR contacts include air taxi operators operating under VFR. During fiscal year 1985, 625 IFR flight plans and 19,260 VFR flight plans were filed with Homer Flight Service Station during calendar year 1985, 699 IFR flight plans and 19,642 VFR flight plans were filed with Homer Flight Service Station. Closed flight plans are not maintained on permanent file. During fiscal year 1985, 42,027 aircraft advisories were given by Homer Flight Service Station. During calendar year 1985, 43,099 aircraft advisories were given by Homer Flight Service Station. Advisories can be given to approaching, departing, or overflying aircraft. 4-037-DB 2 J. Schommer and D. Mathews emphasized that this information was the best known available tor air traffic volumes in the Bomer area. The information contained ·in advisories, contacts, and tiight plans. are not compiled by FAA by point o~ origin or departure. The air traffic controller at Bomer Flight Service station doea not know the origin or destination or arriving or departing aircraft not tiling flight plans. Many pilots do not tile flight plans. FAA does not have the information to determine which airplanes are travelling the northern route in the vicinity or the transaaission line corridor. Many aircraft travelling the northern route do not even contact Homer Flight Service Station. Soma aircraft do not have radios, and may land and take ott trom the uncontrolled Bomer airport without contacting the Flight Service Station. 4-037-DB J.O. No. 15500 & 15800 File No. 15800. ( 12 NOTES OF TELEPHONE CONVERSATION BRADLEY LAKE HYDROELECTRIC PROJECT Alaska Power Authority SUBJECT Air Tratric Patterns Near Homer, Alaska DISTRIBUTION: Sheet 1 of _2_ INSTRUCTIONS: Summarize your phone discussion, noting participants, date & time of call. Indicate desired di.stribution at right. Call reporter must insert File Number(s) and Subject(s) in file box above. Clerk takes care or Chrono rile copy and distribution. JJMPlante/DLMatchett DOC GF __ 1:..-_ B. SteiS!rs 1 M. Fisk 1 J. Finnimore 1 E. Pucb 1 D. Eberle {APA~ 1 Call Date 7-7-86 Time Between Bill Steigers Originated by: Bill Steigera DISCUSSION: JJGarrity/Chron Files 1 T Critikos JBK TK WP 98A ---"'-1 _ DPRyan RPWynn (Homer} NABishop LCDuncan CLClark JHron GEEng MMiddaugb WCSherman JSYale RKrobn JNowak T1.4 1 2:00 p.m. Incoming Outgoing __ x_ SWEC & APA SWEC & Chi2 Dodd& Homer FSS (FAA) (907) 235-8588 & ( ) The Homer FAA Flight Service Station (FSS) was called to request inrormation on volume and altitude of air trarric flying between Victor 438 airway and the Fox River Lowlands. Chip Dodd was the air trarfic controller on duty. IFR trafric flying Victor airways north of Homer are directed to fly at 5,000 reet MSL or above. VFR traffic flys at any altitude that meets VFR minimums. ERA Helicopters and South Central Airlines are the two air taxi operators flying scheduled routes between Anchorage and Homer. Flight Service Sta tiona record number or contacts, which is equal to number of airplanes, each day by IFR and VFR categories. South Central Airlines and ERA Helicopters are considered air taxis because or the size and type or aircraft they fly, whereas Alaska Airlines is considered an air carrier because of the larger aircraft they fly. Flight Service Stations separate air traffic into three oa tegories: air taxi operators, general aviation, and military. Up to one-half of the air taxi contacts on a daily basis may in fact be categorized as general aviation trarfic. For example, a South Central Airlines oargo airplane passing over Homer but not landing may be catagorized as general aviation, depending upon how the aircrart identifies itself. 4-036-DB Sheet 2 of _g_ About six military aircraft contacts are made per week at the Homer Flight Service Station. Three to four air carrier contacts are made per week. Air carriers contacting Homer include Alaska Airlines and Japan Air Lines. Mr. Dodd obtained the daily activity record for the month of July, and provided the number of contacts by IFR and VFR designations for July 3 through July 6, 1986. July 3rd had 18 VFR and 12 IFR contacts, totaling 30 contacts. July 4th had 22 total contacts, and July 5th had 22 contacts. July 6th had 12 VFR and 7 IFR contacts, totaling 19 total contacts. A contact is equivalent to aircraft arriving or departing Homer. Only one contact is recorded per approach or departure although the aircraft may contact the flight service station more than one time. Mr. Dodd estimated that Homer Flight Service Station has 20 to 30 VFR and IFR aircraft contacts per day on the average. When asked how many of these air taxi contacts were aircraft who took the direct route north out ot Homer, he estimated well over one-half ot the VFR contacts take the direct route to the north. ACTION R~UIRED: Contact Homer Flight Service Station Air Traffic Manager tor additional inforua tion. 4-036-DB J.O. No. 15500 & 15800 NOTES OF TELEPHONE CONVERSATION BRADLEY LAKE HYDROELECTRIC PROJECT Alaska Power Authority File No. 15800.(12) 98A SUBJECT Air Traffic Volumes and Routing North of Homer DISTRIBUTION: Sheet 1 of 1 INSIRQCTIONS: Summarize your phone discussion, noting participants, date & time of call. Indicate desired distribution at right. ~ reporter must insert File Number(s) and Sub1ect(s) in file box above. Clerk takes care of Chrono file copy and distribution. JJMPlante/DLHatchett DOC GF _ __._ __ JJGarrity/Chron Files T Cri tikos JBK TK ~ WP ill _ _.._ __ DPByan NABishop LCDuncan CLClark JHron GEEng B. Steigers HMiddaugh J. Finnimore WCSberman E. Puch JSYale H. Fisk BKrohn D. Wnln (Homer) Jlfowak D. Eberle (APA) T1.4 Call Date 7-9-86 Time _.....,1 ;&,;;l4~0"-P._.M...__ Incoming __ Outgoing __.x.__ Between _ __.B""i .... l..,.l~Stllt.leii.OiiW!ge03iU.rllil.s ___ SWEC & --------------APA ----------SWEC & -----------( ) & Roy Hoyt. Air Traffic Manager (FAA) Homer Flight Service Station {901) 235-8588 Originated by: --~Bi.l~l~S~t~e~i~ge~r~s---------- DISCUSSION: There are no records for determining volume of traffic using the northern routes between Homer and Kenai/Anchorage. Tapes are stored for 90 days and then erased. Minimum IFR elevation between Homer and Kenai is 5,000 feet HSL. A heading emanating from a VOB is called a radial. Air traffic is heavier on weekends than during the week, and heavier in summer than winter. Hr. Hoyt said that "lots• of air traffic uses the northern route, with the particular route taken dependent to a large extent on the weather. He would not venture a guess of the number of airplanes. Many aircraft do not even contact the Homer FSS. Mr. Hoyt commented that he, as a pilot, would not be bothered by the presence of the transmission line. Hr. Hoyt felt that most pilots would use the transmission line corridor as a landmark. ACTION REQUIRED: None 2-862-JJ NOTES OF CONFERENCE RECOGNIZING CULTURAL RESOURCES BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY Held in the Conference Room of Alaska Power Authority Anchorage, Alaska July 11, 1986 10:35 a.m. PURPOSE Present for: State Historic Preservation Office Tim Smith Bechtel Civil & Minerals, Inc. John Smith Dames & Moore Consulting Engineers Jim Hemming John Morsell Dave Eri-ckson Alaska Power Authority (APA) Tom Arminiski Dave Trudgen Marnie Isaacs Stone & Webster Engineering Corporation (SWEC) Bill Steigers The purpose of the meeting was for environmental monitoring field officers on the Bradley Lake Hydroelectric Project to receive a brief overview on how to recognize cultural resources that may be discovered during construction. DISCUSSION T. Smith, State Historic Preservation Officer (SHPO) in Anchorage, gave a brief overview of identified cultural resources in the Bradley Lake Project area. He stated that the transmission line will come close to, but not harm, the Hilmer Olson Fox Farm. T. Smith indicated that, to his knowledge, the construction activities for the Bradley Lake Project should not negatively impact any known cultural resources. 4-052-DB T. Smith then gave an overview of the archeology of southcentral Alaska. Alaska has been inhabited for some 12,000 years. Early inhabitants were nomadic hunter-gatherer peoples, who established tent camps which we now called •archeological sites". Stone flakes exist as the primary cultural remains used to document presence of those peoples, which are difficult for the untrained eye to recognize. Some 3,000 to 5,000 years ago the peoples were more sedentary, establishing semi-permanent structures {e.g., 1 year). The houses were subterranean, built by first digging holes approximately 3 feet deep and then constructing walls approximately 3 feet in height. The Kachemak Bay peoples are thought to be related to the Eskimos who came into the area about the time of Captain Cook. Remnants of occupation by these people are relatively recent in origin, so they are easiest to find. T. Smith then presented a generalized slide show pictorially describing some of the cultural resources and archeological digs that have been uncovered throughout the state of Alaska. Shown were atone and bone tools, cache pits {which were used to store fish), and remains of dwellings. In the Kachemak Bay area, most of the archeological sites are located near the sea. At these semi-permanent campsites, the occupants consumed mostly s~ellfish and sea mammals. A dark organic layer overlaid by shells, stone flakes, and general garbage from camps are indications of these sites. These piles of human garbage are referred to as "middens". Some tools that these people used included stone tools they made from slate, bone tools, and net weights made fran stones. T. Smith also brought to the meeting examples of tools and stones that had been worked. There was discussion about establishing a list of qualified, local (to Homer) archeologists or natural historians that would serve as a ready volunteer source tor the Alaska Power Authority to draw from if construction activities uncovered a suspected archeological find. J. Smith (Bechtel) indicated that on a project he was working on in Washington, a local archeological society produced a list of qualified members to act on behalf on the State Preservation Officer. When a suspected cultural resource was uncovered during construction, the local volunteer archeologist was called upon to assess the significance of the find. If the find warranted further investigation or was suspected to be a significant find, the volunteer archeologist contacted the State Preservation Officer for further direction. If the Preservation Officer considered the find significant then the site would be personally inspected. J. Smith felt this system had worked well because it involved a local group as well as assisted the Preservation Officer who could not be on site at all times. The APA has conducted discussions with the Alaska SHPO about establishing a similar group of local individuals to act on the behalf ot the SHPO to conduct site inspections when a suspected cultural resource is discovered. T. Smith indicated that many states had archeological societies in cities with populations over 50,000 people. But in Alaska, no such local archeological societies exist. T. Smith indicated that the closest known registered or certified archeologist 4-052-DB 2 was in Soldotna. However, there are a number ot residents local to Homer who could probably serve as site representatives tor inspections ot suspected finds. T. Arminski indicated the local archeologists would donate their time on a volunteer basis, but the APA would pay their expenses and provide transportation to and trom the site. The meeting was adjourned at 11:59 a.m. 8&~ BSteigers/DB 4-052-DB 3 r r n [ L [ u [. SECTION 12.0 APPENDIX A AN ARCHAEOLOGICAL SURVEY NEAR CARIBOU LAKE, SOUTHCENTRAL ALASKA A Research Report Prepared By ALASKA HERITAGE RESEARCH GROUP, I~C. FAIRBANKS , ALASKA For STONE AND WEBSTER ENGINEERING CORPORATION ANCHORAGE, ALASKA June 1986 INTRODUCTION • Project Focus • Physical Setting Cultural Setting METHODS Projected Impacts • Survey Methods Navigation • Shovel Probes RESULTS TABLE OF CONTENTS Aerial Investigations • Surface Investigations Subsurface Investigations • CONCLUSIONS REFERENCES CITED FIGURES Figure 1. Project Location Map Figure 2. Survey Area and Vicinity Figure 3. Approximate Line of Survey .. Figure 4. View Eastward Toward Base of Hill South of Caribou Lake • Figure 5. Map Pocket: Example of Tree Stump and Nearby Ground Disturbance • Blueline Photomosaic of the Survey Area page 1 1 1 4 9 9 9 10 10 10 10 11 11 11 12 2 3 5 6 6 INTRODUCTION Project Focus The Alaska Power Authority engaged the consulting firm of Stone and Webster to provide engineering and environmental technical expert- ise for the proposed Bradley Lake hydroelectric project, located on the Kenai Peninsula, southcentral Alaska. Following consultation between Stone and Webster and the Alaska State Historic Preservation Officer (SHPO), Alaska Heritage Research Group (AHRG) was contracted in 1986 to complete cultural resources studies along a realigned seg- ment of the power transmission line corridor near Caribou Lake (figure 1). The intent of the cultural resources study was to locate and evaluate any archaeological and historical properties which might be located within a segment of the right-of-way designated by the SHPO as having potential for containing significant cultural sites. On June lOth, a two ma~-day field effort, augmented by literature research, covered approximately 3500 meters (11,250 feet) of 152.5 meter (500 foot) wide transmission line right-of-way (ca. 131 acres or 53 hectares). Field research was completed by AHRG archaeologists Glenn Bacon and Howard Maxwell under State Antiquities Permit AK86-S. Physical Settina The survey area (figure 2) is located just south of Caribou Lake along a linear segment of power transmission line right-of-way located within Section 25 (Township 3 South, Range 11 West, Seward Meridian) -1- .1 .... ... '"'. ~,i:t:~t'> .. ~-:..-..~ ...... "" ....... .:.• ... ~· ........... :,.~.; .. · ~ ...... -~.-,:-.. o-.. •• :::.;....,,.... _ _.1 ... Modified from Mobley et al. 1985 FIGURE 1 PROJECT LOCATION }. ~0 KILOMETERS 20 MILES NORTH \ :>. -c -Q > r "a c , IIJ { IIJ ' G) \. ... • c ' ... I i G) :>. CD > • G) ... ) :I ::I rn ., + / c , c . r N 10 .; w a: ::;) 5:! u. s-a •1Aop1es sasn :d•w •••q and Sections 29 and 30 (Township 3 South, Range 10 West, Seward Merid- ian). From wet tundra, this segment of transmission line rises a little more than 15 meters (50 feet) to an elevation of 415 meters (1350+ feet), drops again to cross wet tundra, and then climbs to cross up and over a taiga covered hill reaching almost 460 meters (1500 feet) lying off the south shore of Caribou Lake (figures 3-5). The Bradley Lake transmission line corridor intersects the Fritz Creek to Soldotna power transmission intertie corridor approximately four miles west of the survey area. Cultural Settin& Background research previously completed by Alaska Heritage Research Group (Mobley et al. 1985) for the Fritz Creek to Soldotna Power transmission line corridor indicates that the prehistory of the Kenai Peninsula is poorly known. The Cook Inlet region appears to have been populated in early post':"'glacial times (approximately 10,000 years ago), but little is known of these early people except that they manufactured specialized "core and microblade" stone tools. Following a 3,000 year gap in the archaeological record, people carrying equip- ment representative of the early Norton tradition are thought to have occupied the western portion of the upper inlet area. By 1500 years ago, the Norton sphere of influence was greatly reduced in the Cook Inlet region, but the Kachemak cultural tradition was expending north- ward from its hearth in the lower Cook Inlet -Kodiak region. The late prehistoric period witnessed greater influence from interior de- rived Athabascan groups (Reger 1981:206). -4- Figure 3. Approximate Line of Survey Figure 4. View Eastward Toward Base of Rill South of Caribou Lake Figure 5. Example of Tree Stump and Nearby Ground Disturbance The historic period for the western Kenai Peninsula began in 1786, when the first Russian settlement was established at English Bay. A year later Fort Georgievsk was founded at the mouth of the Kasilof River. Information on Russian activities in the interior of the Kenai Peninsula is fragmentary, but suggests that archaeological remains are potentially present near the survey area (Mobley et al. 1985:2lff). After the Alaska Purchase in 1867, life on the western Kenai Pen- insula continued essentially unchanged for more than a decade. The U.S. Army occupied a post at Kenai only briefly, from 1869 to 1870; and the Russian trading stations, acquired by the Alaska Commercial Company, continued to operate in much their former manner despite occasional fierce competition from rival firms. From the 1880s on- ward, however, new industries and employment opportunities attracted a growing number of visitors, seasonal workers, and settlers to the area. The first cannery on the western peninsula was built at Kasilof in 1882, and a number of other canneries soon followed. Tall swamp spruce, ideal for pilings and fish traps, were harvested along the Kasilof and Kenai Rivers and elsewhere. Archaeological evidence of this activity might consist of isolated hand tools and sled parts as well as small camps; however it is unlikely that such poles were cut as far inland as the survey area. In the late 1890s news of gold strikes attracted many to the Kenai Peninsula's mountainous interior. There is no record of pros- pecting in the hills between Tustumena Lake and Kachemak Bay, though -7- some likely occurred. Archaeological evidence of prospecting, in the form of tools, prospect holes, and small camps, could be present near the survey area. Others were drawn to the Kenai Peninsula in the 1890s by the coal seams which were readily visible along the coast on the north side of Kachemak Bay. The earliest coal mining there was on Fritz Creek, where the Alaska Coal Company drove a tunnel in 1888. Since coal mines required tidewater access in order to be economically viable in the region, and no coal deposits are known near Caribou Lake, it is unlikely that evidence of early coal prospects will be found as far inland as the survey area. As the outside world grew more familiar with Alaska, fame of the Kenai Peninsula's game resources spread. From the turn of tne century onward, professional guides and their clients stalked trophy sheep, moose, and brown and black bear in the Kenai Mountains between Skilak and Tustumena lakes and in the valleys south of Tustumena Lake to Kachemak Bay. Fur trapping was long the major winter occupation of many permanent residents of the western Kenai Peninsula. Though writ- ten records are scarce, this activity may have extended into the sur- vey area. Evidence of fur trapping in the form of cabins, caches, and traps may be preserved near the survey area. The general homestead laws, extended to Alaska in 1903, attracted new settlers to the western peninsula. In the early 1920s, there was intensive homesteading in the Kachemak Bay area along the benches above the beach. Many homesteaders around Homer found fox farming profitable throughout the 1920s, but a great decline in the fur market in the 1930s forced most to seek other sources of income. A second -8- period of intensive homesteading occurred in the Kachemak Bay area in 1941-1950, when the hills above Homer and the Fox River flats were settled. In 1947 construction began on the Sterling Highway, which was completed in 1950 and linked Homer with Anchorage. METHODS Proiected 1mpacts Direct impacts of the project will include surface and subsurface disturbance along the transmission line right-of-way, which will be brushed prior to tower erection. Towers will be transported by heli- copter, although tracked vehicles·may be used in the right-of-way as well. Access roads and marshalling yards were not surveyed as a part of the effort reported here. Suryey Methods The survey methods used for the project were selected as an efficient means of locating sites and a suitable means for declaring linear alignments devoid of significant cultural resources. Two sur- vey methods were used in the field: pedestrian and aerial survey. The pedestrian survey was implemented by walking parallel zig-zag tran- sects, spaced approximately 150 meters apart along the proposed trans- mission line right-of-way. Augmenting the pedestrian survey, judge- mentally placed shovel test units were excavated. The aerial survey was implemented with a helicopter and involved low altitude visual in- spection of the surveyed alignment. -9- Navigation. Since the transmission corridor was not marked on the ground at the time of the survey, the field archaeologists relied on 1:12,000 scale blueline photomosaic maps (map pocket) furnished by Stone and Webster, to determine the boundaries of the survey area. Ground navi- gation was enabled by checking position using a combination of U.S. Geological Survey topographic maps (1:63,360 scale), blueline mosiac aerial photographs (1:12,000 scale), and compass bearings. Shovel Probes. Shovel probes were excavated to depths of approximately 50 em or less depending on subsurface conditions. Areas insulated by surface moss or shaded by trees were generally found to be frozen within 30 em of the surface. Wet tundra areas with a high water table were not tested. Probes were placed approximately every 100 meters along the surveyed corridor segment. RESULTS Aerial Inyestiaations The helicopter aerial reconnaissance of the survey area revealed several cleared areas in the taiga forest cover of the large hill located just south of Caribou Lake. In addition, all-terrain vehicle (ATV) tracks were noted along the base this hill. No architectural features, such as cabins or caches, were noted. -10- Surface Inyestiaations The surface survey revealed numerous cut tree stumps along the eastern end of the survey area. These stumps varied in diameter from approximately 45 em (c. 18 in.) to less than 20 em (c. 8 in.). Micro- topographic and vegetative disturbance near these stumps revealed the locations of narrow logging trails, which in turn led to larger trails leading toward Caribou Lake. The larger trails evidence recent ATV traffic. Subsurface Inyestiaations Approximately seventy shovel probes were attempted during the course of the survey. Only a few of these located fully thawed ground enabling deep tests. However, despite the limitations imposed by partially frozen ground conditions, it is possible to generalize sur- face sediment characteristics on the basis of completed tests. A typical section exposed a thick organic mat (c. 20 em thick) overlying an organic rich forest brown (lOYR) soil (c. 30 em thick), which in turn overlies a pebbly organic soil grading to gravel. No evidence of buried cultural deposits were discovered during subsurface testing. CONCLUSIONS A review of pertinent literature did not reveal the presence of significant historic or prehistoric properties within the survey area. Additionally, the only culturally derived remains discovered within the survey area were cut tree stumps and recent trails. These are not -11- known to be associated with any historically significant person or event, and do not independently meet National Register eligibility criteria (cf. 36 CFR Part 800, Appendix A). Thus, on the basis of data revealed through literature research and field investigations, it is concluded that the proposed realignment for a segment of the Brad- ley Lake power transmission line corridor does not appear to represent a threat to any cultural property listed in or eligible for inclusion in the National Register of Historic Places. Mobley, 1985 REFERENCES CITED Charles M.; Glenn H. Bacon, Katherine Arndt, and James A. Ketz 1984 an4 1985 Cultural Resources Suryey Beport for the Fritz Creek to Soldotna Transmission Line Project. Research report from Alaska Heritage Research Group to Commonwealth Associates Inc. for the Homer Electric Association. Reger, Douglas D. 1981 A Hodel for Culture History in Upper Cook Inlet. Alaska. unpublished Ph.D. dissertation, Department of Anthropology, Washington State University, Pullman. -12- MAPS .. I I ! i I ! I I .. I I '"'' I L I 1. t. I I + 12 OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT J ; 6 --1------ 7 I I I I i t I I I I I I I I I 5 + 2 140 000 !!!._ ----+-------- 1 I I I 8 PROPOSED "' 0 8 0 I"' TRANSMISSION LINE ROUTE FOR lNFORr~A TlON ONLY BRADLEY LAKE HYDROELECTRIC PROJECT ~ g r DRAWING NUMBER g l SWB9 -220 - 1 _'··· ______ j'L_"' -----1-....l..----~ LAND OWNERSHIP IN FORMAT ION '<5 DENOTE ·y IPRIVATEi REI 4 •• E SOU' RANGE ON oSE MAPS REPRESENT LOCATIONS BASED ON AVAILABLE OATA. 3. OWNERSIP FOR PRIVATE PARCELS IS OSTENSIBLE ONLY, AND MAY NOT REFLECT CURRENT OWNER. 4. CM·I a CM·2 ARE CONTROL MONUMENTS SET BY AOL. PREPARED BY' I DATE: I Tn• Droftin9 Company Feb., 1986 SHEET I OF :5 \~"'"" 6 '\ \:, ..... ,, ...... ' I I I OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT I s 4 I I I . I ZI40~00N I + I I I I -·+---------+---------+ '"" .. '""',~,! ..... ,, .,.:OR INFPRMATION ONLy i L''"z~~o~.. , 7 '~j , ' S TRANSM I ==~~:O~~~ E ROUTE ... ;;,.,,_ .... ~. I ' BRADLEY LAKE HYDROELECTRIC PROJECT LAND OWNERSHIP IN FORMAT 10 N I I I . I 'M 6 ·e. I ~ OVERSIZED MAP - NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT I -----+----- 1 I I I - I I I I I (\j I 1'0 I I I I I I I I -------+--. -·-----t---- 1 I + I I \ I I ' .. I I \ \~! N i~ I I q-' -"· ~+J ' ~ l FOR INFORMATION I ONLy ~ _ ~~ I; I PROPOSED .,-z \? -~ Q I "'uc ....... IL~~ f---------+--TRANSMISSION LINE ROUTE I I I 1'0 I BRADLEY LAKE HYDROELECTRIC PROJECT LAND OWNERSHIP INFORMATION PREPARED BY: OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT . l . ;Y . '-, ) 111. f ..... ~.,~ ROUTE MAP ALASKA POWER AUTHORITY FOR: /A Stone&: 'Webster ~.....--.~ ANCHORAGE, ALASKA OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT BRADLEY ROUTE MAP UNES BRADLEY LAKE HYDROELECTRIC POWER PRO.ECT ALASKA POWER AUTHORITY I'REPARED fOil: /A Stooe&~ 6!!A &oli-n .. ~ ALASKA DRAWING NUMHfl: OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT BRADLEY ROUTE MAP BRADLEY LAKE HYDROELECTRIC POWER PROJECT ALASKA POWEft AUTHOIUTY I'IIEI'AIIED FOil: A~~ AHCHOIIAGE.ALASKA .. OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT BRADLEY LAKE HYDRoELECTRIC PROJECT ALASKA POWI!A AUTHORITY PROJECT BOUNDARY .KEY MAP ~-------~------.--------~ ~ · · sTONE • .weaamt HIBtT~~'~ Pl.ATE 11 /b. ENGINEERING CORPORATION EX i ,_,.. : . ~ -~ ~ ' ' " ' ______ __... __ ....._.__..._ ___ --1 ~I I I J ' J I J ' OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY . PROJECT BOUNDARY .. TRANSMISSION LINE ' .. ~ STONE & WEBSTER ENGINEERING CORPORATION EXHIBIT G PLATE 2 . . OVERSIZED MAP NOT MICROFILMED MAP LOCATED IN ORIGINAL· REPORT . BRADLEY LAKE HYDROELECTRIC PROJECT ALASKA POWER AUTHORITY 1 PROJECT BOUNDARY' l TRANSMISSION LINE I ~ STONE & .WEBSTER E BIT G ··-~ ENGINEERING CORPORATION XHI ·PLATE 3 .. _________________ _____.