Loading...
HomeMy WebLinkAboutGlennallen Waste Heat Recovery Report & Concept Design 1990 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN Prepared for Alaska Energy Authority 701 East Tudor Road Anchorage, Alaska 99519 Prepared by Fryer/Pressley Engineering, Inc. 560 East 34th Avenue, Suite 300 Anchorage, Alaska 99503 JANUARY 15, 1990 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1989 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY 1 2.0 INTRODUCTION 2 3.0 DESCRIPTION OF SITE VISIT 4 4.0 POWER PLANT DESCRIPTION 5 5.0 POTENTIAL WASTE HEAT USER BUILDING DESCRIPTIONS 9 6.0 RIGHT-OF-WAY/EASEMENT 25 7.0 CONCEPT DESIGN 26 8.0 ECONOMIC DATA 49 9.0 FAILURE ANALYSIS 52 10.0 CONCLUSIONS AND RECOMMENDATIONS 62 APPENDICES 1. Calculations 2. Contact Names 3. Cost Estimates 4. Raw Data ii LIST OF FIGURES AND TABLES Glennallen Power Generation - 1988 Power Plant Photographs School Building Photographs School Building Fuel Oil Inventory and Use Apartment Building Photographs Apartment Bullding Fuel Oll Use Post Office Photographs Post Office Fuel Oil Use Figure 1 - Legend Figure 2 - System Schematic Figure 3 - System Site Plan Figure 4 - Power Plant Floor Plan Figure 5 - Power Plant Cooling Schematic Figure 6 - Old School Floor Plan. Figure 7 - Old School Boiler Schematic Figure 8 - Weir Building Gym Floor Plan Figure 9 - Weir Building Gym Boiler Schematic Figure 10 - New School Floor Plan Figure 11 - New School Boiler Schematic Figure 12 - Apartment Floor Plan Figure 13 - Apartment Boiler Schematic Figure 14 - Post Office Floor Plan Figure 15 - Post Office Boiler Schematic Figure 16 - Arctic Pipe/Trench Cross Section til GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN i 13 21 23 24 27 28 31 32 33 37 38 39 4) 42 JANUARY 15, 1989 1.0 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 EXECUTIVE SUMMARY A potential for waste heat recovery exists in the community of Glennallen. Glennallen Is located on the Glenn highway, approximately 190 miles from Anchorage by road. The heat energy could be recovered from the diesel engine-generator sets operated by Copper Valley Electric and circulated to user buildings in the community. Five possible waste heat users have been identified: the Old School Building, the Weir Building Gym- nasium, the New School Building, the Post Office, and an apartment building (Highlander Apartments). It appears as if the most economical system will provide heat to all five buildings: the Apartment building, Post Office, the Old School Building, the Weir Building Gym, and the New School Building. A summary of the construction cost estimates along with design and SIA costs is included in the Cost Estimate Appendix. If the system is installed con- necting all of the buildings, the following are the estimated results: Estimated Project Cost $647 303 Total Fuel Oil Savings 57,544 gallons Total Annual Dollar Savings $52,816 Page 1 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 2.0 INTRODUCTION 2.1 2.2 2.3 Objective The objective of the field investigation and report is to ascertain the viability of waste heat recovery and use in the community of Glennallen. It has been estab- lished that there is a potential source and use for the heat energy, and that the community is interested in pursuing the matter. Methodology The approach for investigation and analysis has been as follows: 1 Pre-site visit information gathering: this has consisted of contact with the community officials, owners/operators of potential user buildings, and contact with the local utility. The site visit was coordinated with the local building owners/operators. 2. Field Investigation: a visit was made to the community to view the site. Photographs of the potential user buildings were taken as well as of the electrical generation buildings and equipment. Sketches were made of the equipment and piping connections. The project was discussed with local interested parties. 3. Office Analysis: additional information was collected regarding weather and historical electrical energy production. This was used in a model to predict the system performance and the amount of energy recovered. 4, Report Preparation: a draft version report was prepared for the expected audience - users and agencies with an interest. Community Description Glennallen is a community of 909 persons located on the Glenn Highway, 2 miles west of the Junction of the Glenn and Richardson Highways in the Copper River Basin. The community is 155 air miles northeast of Anchorage. Most of the terrain Is relatively level with small hills away from the highway. See Figure 3 in Section 7 for a partial community site plan. Page 2 2.4 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Applicable Codes and Regulations The most recently State of Alaska-adopted editions (1985 for all except as noted) of the following codes and regulations have been used in the preparation of the concept design. These are listed below: Uniform Plumbing Code (UPC - 1979) Uniform Mechanical Code (UMC) Uniform Building Code (UBC) Uniform Fire Code (UFC) National Electrical Code (NEC - 1987) National Fire Protection Association (NFPA) Codes Page 3 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 3.0 DESCRIPTION OF SITE VISIT 3.1 3.2 Field Notes Contact names are included as part of the Appendix at the end of this report. They include both field contacts and contacts made by phone. Field Contacts The following people were contacted in the field: Dave Bruno, Service Oil and Gas Charles Mason, Principal at Glennallen High School Leland Dischman, Superintendent - Copper River School District Loreen Kramer, Business Manager - Copper Valley School District Jasper Hall, Branch Manager - National Bank of Alaska Elaine Seager, Postmaster - Glennallen Post Office Lowell Highbargin, Power Production - Copper Valley Electric Page 4 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 4.0 POWER PLANT DESCRIPTION 4.1 Narrative Description The power plant Is located approximately one block from the Glenn Highway. The power plant facilities include the large engine building, another building for the smaller back-up engines, and a maintenance shop. On adjacent properties Is the Manager’s house and then the administrative offices. On the side of the power plant main buildings away from the highway are the remote radiators and fuel oil storage tanks. There are two each 20,000 gallon tank for storage of #4 fuel oll and two each 10,000 gallon tank for #2 fuel oil. The electric utility, Copper Valley Electric, provides power for Glennallen and vicinity. The utility is also intertied with power production facilities in Valdez. Most of Valdez's power requirement is satisfied by Solomon Gulch hydroelectric facility. Excess power from that facility is also used in Glennallen and environs. In the summer when power production from Solomon Gulch Is at its peak and all of the Glennallen load can be supplied ie the intertie, the diesel generators In Glennallen are shut down. The two main generators at the Glennallen plant are 2600 KW Enterprise diesel engine/generator sets. The units are fired with fuel oll #4 (also known as HAGO). This fuel is a high viscosity residual fuel oil from the North Pole refinery. The fuel is kept heated to 140 degrees F in exterior fuel tanks. Other smaller generators are kept in an adjacent building and are used for emergency purposes and for peak loads. These generators use fuel oil #2 which are kept heated to 100 degrees F in exterior tanks. The two main engines are connected to a cooling header. A number of small connection have been made fo this header for the purposes of plant and plant outbuilding uses. These connections Include one to heat the #4 fuel oil, one for the #2 fuel oll, one each to the maintenance shop, Manager's house, and ad- ministrative offices. The cooling piping extends to connections to two each horizontal core remote radiators outside. Separate radiators are used for the smaller generators. The power plant building appears to be in excellent condition as are the genera- tors. There is more than sufficient space for equipment should a waste heat sys- tem be installed. Page 5 4.2 4.3 44 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Floor Plan and Schematics See the Figures 4 and 5 for a simple floor plan and schematic of the system (located in Section 7). Photographs See the attached copies of the original color photographs. Available Load Information Refer to the attached Table indicating historical power production. This Informa- tion is from Copper Valley Electric Association for the year 1988. Figures for other years are also available. Page 6 TABLE 1 GLENNALLEN POWER GENERATION 1988 1,454,200 rB 1,339,200 MAR 1,325,680 APR 2,329,420 MAY 885,260 JUNE 488,200 JULY 94,600 AUG 25,084 SEP ; 0 OCT 169,400 NOV 962,200 DEC 1,643,600 ANNUAL 10,716,844 ** Power provided by Solomon Gulch. Page 6A 1230 * PHOTO 1: POWER PLANT Back side of building PHOTO 2; POWER PLANT Exterior of Maintenance Shop Page 7 PHOTO 3: POWER PLANT Engine Number 1 PHOTO 4: POWER PLANT Existing Waste Heat Recovery Piping Page 8 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 5.0 POTENTIAL WASTE HEAT USER BUILDING DESCRIPTIONS 5.1 5.2 General During the site visit, all buildings within a reasonable distance of the power plant, and with a significant heating load were considered. The buildings were visited and information about them gathered. The information is presented below. Photographs accompany each building description. Plans and schematics can be found in Section 7. Old School General The old school is a slab-on-grade structure of wood and steel. It is currently used mostly for elementary school activities. The building has classrooms, a gym/multipurpose room, and some administrative space. The school area is ap- proximately 24,000 square feet. The building was built beginning in 1961 . Addl- tions were constructed up through 1972. It is in good general condition. Heating Energy Use A single mechanical room in the school building houses three fuel-oil fired boilers which provide all of the heating for the school. Domestic hot water is produced using a shell-and-tube heat exchanger and water from the boiler. In addition, another shell-and-tube heat exchanger is used for heating an outbuilding used as a wood shop. Refer to Table 2 for the yearly fuel oil use for the building. The yearly figures were provided by the School District. Monthly figures were estimated based on average degree days for the area. Page 9 5.3 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Weir Building Gym General This building is immediately adjacent and connected to the new school. It was built in approximately 1977, 10 years before the new school to serve as a full size gymnasium. When the new school was constructed, it was built as an “addition” to the existing gym. The new school is sometimes referred to as the "Weir" build- Ing because of its shape. Estimated area is 15,000 square feet. The gymnasium Is a wood and steel structure supported on piles. The major function of the building is as a gymnasium and multipurpose room. Some other smaller rooms included as part of this construction are the locker rooms, a boiler room, and some storage areas. Heating Energy Use A single fuel-oil fired boiler serves only the gymnasium/multipurpose room. The boiler capacity is 1257 MBH net output. Domestic water Is produced using a heat exchanger connected to the boiler hydronic system. Refer to Table 2 for the yearly fuel oil use for the building. The yearly figures were provided by the School District. Monthly figures were estimated based on average degree days for the area. Page 10 PHOTO 5: OLD SCHOOL Exterior Elevation from New School PHOTO 6: OLD SCHOOL Back side of building Page 11 PHOTO 7: OLD SCHOOL Existing Boiler PHOTO 8: OLD SCHOOL Existing Piping at Pumps TABLE 2 SCHOOL BUILDING FUEL OIL USE - 1988 BUILDING: OLD SCHOOL YEARLY FUEL USE: 26,700 REDUCTION FOR DHW: 0% HEATING DOM. WATER |NETHEATING |TOTAL USE DEGREE DAYS) HEATING USE (GALLONS) |(GALLONS) ZALLON JAN 2191 0 4483 4483 FEB 1759 0 3600 3600 MAR 1559 0 3191 3191 APR 1057 0 2163 2163 MAY 678 0 1387 1387 JUNE 0 0 0 0 JULY 0 0 0 0 AUG 0 0 0 0 SEP 682 0 1394 1394 OCT 1182 0 2419 2419 NOV 1777 0 3635 3635 DEC 2164 0 4427 4427 13,049 0 26,700 26,700 BUILDING: WEIR BLDG. GYM YEARLY FUEL USE: 8,382 REDUCTION FOR DHW: 0% HEATING DOM. WATER |NETHEATING |TOTAL USE DEGREE DAYS/HEATING USE (GALLONS) |(GALLONS) ALLO JAN 2191 0 1407 | 1407 FEB 1759 0 1130 1130 MAR 1559 0 1002 1002 APR 1057 0 679 679 MAY 678 0 436 436 JUNE 0 _0 0 0 JULY 0 0 0 0 AUG 0 0 0 0 SEP 682 0 438 438 OCT 1182 0 759 759 NOV 1777 0 1141 1141 DEC 2164 0 1390 1390 13,049 0 8,382 8,382 Page 13 TABLE 2 (continued) SCHOOL BUILDING FUEL OIL USE - 1988 BUILDING: NEW SCHOOL YEARLY FUEL USE: 15,450 REDUCTION FOR DHW: 10% HEATING DOM. WATER |NETHEATING |TOTAL USE DEGREE DAYS en oa USE (GALLONS) |(GALLONS) JAN 2594 FEB 2083 MAR 1846 APR 1252 MAY 803 JUNE 0 JULY 0 AUG 0 SEP 807 OCT 1400 NOV 2104 DEC 2562 15,450 Page 14 PHOTO 9: WEIR BLDG. GYM Exterior Elevation PHOTO 10: WEIR BLDG. GYM Existing Boller Page 15 5.4 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 New School Building General As mentioned above, the new school is built immediately adjacent to the Weir building gymnasium. The new school is sometimes referred to as the "Weir" bulld- ing because of its shape. The construction took place in two phases. The first phase was completed in 1987 and included the auditorium, commons area, kitchen (for the multipurpose building), and the administration area. The second phase took place in 1988 and consisted mostly of classroom space. The addition Is of identical construction and Is essentially an indistinguishable part of the main structure. The first phase is approximately 15,000 square feet; the second phase Is 17,000 for a total of 32,000 square feet. A third phase of construction is planned but no date has been set. The planned addition is expected to include a new home economics lab and wood shop. The existing building Is In excellent condition. Heating Energy Use Both phases and the ‘planned third phase are (will be) heated from a single mechanical room in the first phase of construction. Three identical hydronic boilers are used. Each is rated at 480 MBH. They are in excellent condition. The fuel oil use reported for two years appears to be lower than expected. The average Is for approximately 50,000 BTU/square foot per year. Actual use may be higher but the recorded fuel use figures were used in the calculation process. Page 16 PHOTO 11: NEW SCHOOL Exterior Front Elevation from New School PHOTO 12: NEW SCHOOL Back side of building Page 17 PHOTO 13: NEW SCHOOL Existing Bollers PHOTO 14: NEW SCHOOL Utilidor under Boiler Room Page 18 5.5 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Apartment Building General The apartment building, sometimes referred to as the Highlander Apartments, is located across the street from the power plant. The building is a wood frame structure with two occupied floors, and a unfinished basement. The building is currently owned by the local branch of the National Bank of Alaska. A sale toa private individual may occur soon. There are twelve rental units in the building, each at about 780 square feet. The gross building area is estimated at 10,000 square feet. The building is currently occupied by renters. Heating Energy Use The building is heated by one two-section oll-fired boiler rated at approximately - 500 MBH. Hot water is produced by individual electric water heaters in the units. The fuel use was estimated based on the fuel oil deliveries by Service Oil and Gas. These figures however show only delivered fuel which may or may not coin- cide with actual use. The figures for approximately two years were used to deduct probable use. The estimated use Is shown In the attached Table 3. Page 19 PHOTO 15: APARTMENT BUILDING Exterior Elevation PHOTO 16; APARTMENT BUILDING Existing Boiler System Page 20 TABLE 3 APARTMENT FUEL USE: 1987 - 1989 nahn GALLONS OF — fia FUEL USED APSED PER DA 1/21/87 9/16/87 54 37 8/87 145 31 2/9/88 185 17 2/10/88 1 476 2/18/88 8 33 2/25/88 7 28 wares 7 23 910/88 6 24 9/17/88 7 23 yeses 8 22 4888 14 18 4/15/88 7 17 5/5/88 20 11 8/12/88 7 20 8/27/88 16 5 22/88 26 12 78/88 26 6 8/12/88 31 5 /2a/88 11 82 913/88 21 24 10/10/88 27 37 4 15 27 16 28 24 19 31 28 46 JAN 1180 0 1180 FEB 1200 0 1200 MAR 713 0 713 APR 510 0 510 MAY 372 0 ~ 372 JUNE 270 0 270 JULY 248 0 248 AUG 341 0 341 SEP 630 0 630 OocT 760 0 760 NOV 1050 0 1050 DEC 1902 0 1902 8576 0 8576 Page 21 5.6 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Post Office General The building was built in the early 1970’s. It measures approximately 40 feet by 26 feet for an area of 1040 square feet. It is a wood and steel structure built on a pile foundation. Its only use Is as a post office. Portions of the building are acces- sible at ail time for mail box pick-up. the building is in good condition. Heating Energy Use The building is heated by a single fuel-oil fired boiler. Terminal heating units in- Clude finned tube, unit heaters, and one hydronic coil in a single air handler. Domestic hot water Is produced in an electric water heater. The estimates of fuel oil use is based on the fuel oil deliveries. Since the tank Is continually topped off at each delivery, it ls considered a reasonable method of estimating actual use. The estimated use follows In Table 4, Page 22 PHOTO 17: POST OFFICE Exterior Elevation PHOTO 18; POST OFFICE Existing Boiler System Page 23 TABLE 4 POST OFFICE FUEL USE - 1988 & 1989 11/1/88 11/2/88 FUELOIL j|NUMBER DELIVERED |OF DAYS APSED GALLONS OF FUEL USED 563 12/2/88 38 12/21/88 880 46 1/23/89 982 30 1/26/89 934 311 2/13/89 064 59 3/2/89 664 37 3/21/89 530 28 3/31/89 455 46 4/18/89 648 36 5/11/89 330 11 6/6/89 300 12 7/24/89 170 4 10/17/89 569 85 7 11/20/89 1942 34 57 12/6/89 897 16 56 12,618 EST. FUEL NET HEATING OIL USE USE (GALLONS) GALLONS JAN 1642 90 1552 FEB 1652 90 1562 MAR 1110 90 1020 APR 705 90 615 MAY 345 90 255 JUNE 240 90 150 JULY 120 90 30 AUG 165 90 75 SEP 400 90 310 OCT 992 90 902 NOV 1710 90 1620 DEC 1767 90 1677 10,848 1,080 9,768 Page 24 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 6.0 RIGHT-OF-WAY/EASEMENT 6.1 Narrative Description The issue of right-of-ways and easements were addressed by a review of the in- formation available in Anchorage for the Glennallen site. This information in- cluded a review of available aerial photos, U.S. Geological Survey information, plats, and Alaska Department of Community and Regional Affairs data. The only aerial photos available were taken in August 1983 and therefor do not include the new construction at the high school. The only other local source for informa- tion was the Anchorage Recorder's Office. The office had information available from 1963, 1964, and 1974. Complete plats were not available but information was found for the Apartment, Post Office, and power plant properties. Since Glennallen has its own recording district, additional information might be ob- tained through searching of their archives. Right-of-way Information on the plats was limited. An easement is shown on the north side of the Post Office property, and an easement runs through the center of the apartment building (north and south). The legal descriptions of the properties are as follows: School: Township 4 North, Range 2 West, Copper River Meridian. Section 23 East 1/2 Northeast 1/2 Southeast 1/4 containing 20 acres more or less. U.S. Post Office: Tract A, Section 3 of Heintz Subdivision, Plat #74-442 of Chitina recording District. Apartment Building: Lots 1, 2, 3, 15, 16, 17 Block 4, Section 2, Heintz Sub- division. PowerPlant: Lot 1, Co-op Subdivision, Plat #67-239 Chitina recording District. Page 25 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 7.0 CONCEPT DESIGN 7.1) System Narrative In keeping with the previous AEA recommendations, the current concept design includes one flat plate heat exchanger at the power plant. The flow will be without any booster pump on the engine side of the system. Since the actual operating point of the engine-mounted pump is not known it is assumed that there is some allowance for a low pressure drop heat exchanger. On the primary loop, a main circulation pump will be designed for the pressure drop of the furthest connected building. In addition, an air separator, and ex- pansion tank, and a glycol make-up system Is required. The pump’s design flow rate will be for the maximum heat available at a 20 degree temperature drop. The piping to each of the connected buildings will be through arctic pipe buried underground to protect it from damage from passage of vehicles. Two separate arctic pipes are envisioned, one for supply to the building, and one for return to the power plant. See the attached Figure 2 for the system schematic. Balancing valves are used at the connection to existing piping for two reasons. The first is to allow balancing of the flow to the heat exchanger; the second is to provide a means of measuring the flow rate at that point in the piping. All connections to the user buildings will be using flat plate heat exchangers. This will limit problems associated with damage of distribution piping and intercon- nection of systems. Precautions must be taken to prevent overcooling of the generator jacket water and to prevent building system boilers from heating the waste heat distribution system. Each of these issues can be addressed with controls and valving. They can also be automated to some degree but the solutions must be carefully balanced with the need for system simplicity. Page 26 BALANCE VALVE GATE VALVE 2-WAY CONTROL VALVE 3—-WAY CONTROL VALVE CHECK VALVE STRAINER UNION CIRCULATING PUMP THERMOMETER EXPANSION TANK a im Is ‘ O : + LOW WATER CUTOFF FLOW ARROW PIPE DOWN PIPE UP NEW RETURN LINE NEW SUPPLY LINE EXISTING RETURN LINE EXISTING SUPPLY LINE NEW EQUIPMENT/VALVES IN THIS COLOR EXISTING EQUIPMENT/VALVES IN THIS COLOR NOORVIK SYMBOL LEGEND DWN BY: MD. CKD BY: TW FRYER/PRESSLEY ENGINEERING Dare $60 EAST 24th AVENUE, SUITE 300 (007)561-1666 1/15/90 Page 27 82 ebeg £0966 VXSVIV ‘SDVYOHONY 006 ZLINS SANA! ONIYAANIONGA AMISSHAd / MARTA 3 : 3 Tre Lsva 099 dj QILVWSHOS WALSAS AYSA00SY LVSH ALSVM N3ATIVNNST9 BOILER ee OFFICE ENERATOR 1 GENERATOR 2 HEAT EXCHANGER (TYP.) POWER PLANT _| ALL PIPING SHOWN RUN QUTSIDE | BUILDINGS IS IN ARCTIC a” BOILER| BOILER BOILER [ New senor | GLENNALLEN WASTE HEAT RECOVERY i BOILER’ | APARTMENT BUILDING __| BOILER | WEIR BUILDING GYM Li 7.2 7.3 74 7.5 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Site Plan/Routing The routing will be as shown on the attached plan. The concept 1A Is for con- nection only to the apartment building. Concept 1B also connects to the Post office. Concept 2A Is connection only to the Old School. Concept 2B continues on and connects to both the New School and the Weir Building Gym. The rout- ing Is shown on Figure 3. Generator Room Plans/Schematics See the attached Figures 4 and 5 for the design concept for changes to the power plant. User Building Plan/Schematics See the attached Figures 6 through 15 for proposed changes to each of the potential user buildings. Arctic Pipe/Utilidor Section A cross section of the anticipated trench and arctic pipe configuration is shown In the Figure 16, Page 29 oe ebeg $0966 VHSVIV ‘SDVEOHONY 006 ZLINS ZNNFAY Nive Lsva 099 ONIYHANIONG ATISSHUd/ MqANd * 3 : 3 QNILNOY 3dld/NV1d 3LIS d CONCEPT 1A: 2-1/2” CONCEPT CONCEPT 1B: 3° in oie POWER PLANT CO-OP ROAD ov] EON BLACKBURN oe i ORIVE CONCEPT 2A: 4” CONCEPT 2B: 5” NORTH 1st. AVE. BUILDING LOCATIONS SHOWN ARE APPROXIMATE BASED ON AERIAL PHOTOS AND A SITE VISIT. PROPERTY LINES ARE BASED ON PLAT INFORMATION 2B: 3° OBTAINED FROM THE ANCHORAGE RECORDER'S OFFICE. NEW SCHOOL (PHASE |!) >, a 7 < NEW SCHOOL (PHASE Il! — FuTuRe)N——~— © APPROX. SCALE: 1"=280' NEW SCHOOL (PHASE 1) CONCEPT WEIR BLDG. GYM SMALL GENERATORS UP OFFICE | SHOP REMOTE RADIATOR _| (TYP. OF 2) GENERATOR GENERATOR 0s) ap) APPROX. SCALE: 1”=30' POWER PLANT FIP Foor pian . ERYER/PRESSLEY ENGINEERING ANCHORAGE, ALASKA 99603 (907)561-1666 Page 31 ze ebeg PLANT OFFICE OFFICE /MANAGER'S HOUSE SMALL PLANT/SHOP FUEL OIL #4 HEATING FUEL OIL #2 HEATING dj GENERATOR #2 > FROM ARCTIC PIPING TO ARCTIC PIPING Tre Lsva 099 CIRC. PUMP AIR SEPARATOR VASVIV ‘XOVEOHONY GENERATOR #1 LNV1d Y3MOd werner e ee eee ee ee ew ew ew ew ew ew ee Jd LOW WATER TO HX UNDER LOADING &” Nee WORK ml VALVE DOCK, PREHEATS FUEL iia i TO RADIATORS \—8-><1- 6" ’ Y bikie TO RADIATORS ‘\—883—><1-— 6 TO ELEC. = |§ ge ><} 5 BOILER QILVWSHOS WALSAS ONMO09 YOLVYANS9 ry < =a] ~~ i) vu 3] A nn c ie3| K< fe Zi a — za eS 3 v Zz, QR APPROX. SCALE: 1”°=38' DWN BY: OLD SCHOOL N FIP Foor pian 7 BE . FRYER/PRESSLEY ENGINEERING a 660 EAST 34th AVENUE SUITE 300 1/15/90 ANCHORAGE, ALASKA 99603 (907)561-1666 Page 33 r : ; YOM MIN ee L__ + XH MHG (907)561-1666 ddid IWIN OL ddld DWOYV WON YZDNVHOXZ LV3H VENUE SUITE 300 ANCHORAGE, ALASKA 99603 XH MH OL OLD SCHOOL BOILER SCHEMATIC . FRYER/PRESSLEY ENGINEERING F|P XH LV3H3Nd THY? g XH dOHS GOOM OL Page 34 @ WEIR BUILDING GYM FLOOR PLAN APPROX. SCALE: 1°=16' = 2S 9 co a ir we 9 a DWN BY: WEIR BUILDING GYM n FIP FLoor pian 7 WE . FRYER/PRESSLEY ENGINEERING a ANCHORAGE, ALASKA 99603 (907)561-1666 Page 35 YOM MIN Te eee et a et ddid SWOYY OL Adid SLOYY WON ANVL ‘“dX3 OL VENUE SUITE 300 (907)561—1666 WEIR BUILDING GYM BOILER SCHEMATIC FIP ; FRYER /PRESSLEY ENGINEERING ANCHORAGE, ALASKA 99603 Page 36 DWN BY: | NEW SCHOOL FLOOR PLAN . F P — . ERYER/PRESSLEY ENGINEERING — [oi 560 EAST 34th AVENUE SUITE 300 1/15/90 ANCHORAGE, ALASKA 99603 (907)561-1666 Page 37 OWONY WON OUIYY OL S3NOZ ONUV3H OL YSONVHOXI 1V3H S3NOZ ONUV3H OL A>NVL ‘dX3 SUITE 300 ANCHORAGE, ALASKA 99603 (907)561-1666 NEW SCHOOL BOILER SCHEMATIC . FRYER /PRESSLEY ENGINEERING FIP Page 38 [| gone a VESTIBULE (TYP.) qm BOILER ROOM ACCESS APARTMENT BUILDING FIP sasement PLAN . ERYER/PRESSLEY ENGINEERING ANCHORAGE, ALASKA 99603 (907)561-1666 1/15/90 Page 39 % TO 3 ZONES % TO 3 ZONES TO 5 ZONES + TO 3 ZONES r=— NEW WORK ATW AIT ae WaT a TMT TIC TORT 44 1 1 1 § 1 | S ! 1 4 O I | x zs = ' ' 1 YS 1 ! 1 i ~ 1 | did OU9WW 1 >is GHi-pg P| | 3dld QUOYY WOU G palili te | 1 1 1 1 I ! 4 FROM ZONES APARTMENT BUILDING FIP oer scHematic . ERYER/PRESSLEY ENGINEERING ANCHORAGE, ALASKA 99603 (907)561-1666 Page 40 BOILER ROOM APPROX. SCALE: 1-1/2°=10' DWN BY: POST OFFICE n FIP tL00r pian oD Fi E|. FRYER/PRESSLEY ENGINEERING [ome— ANCHORAGE, ALASKA 99603 (907)561-1666 1/15/90 Page 41 ddild IWOYV OL ddid ILOYY WON -+><t—4 S3NOZ OL (907)561-1666 NHY NI 1109 SNULVSH OL S3NOZ WOU 5 NHV NI 109 ONILV3H WONS FRYER/PRESSLEY ENGINEERING POST OFFICE BOILER SCHEMATIC Stee A= F|P Page 42 BACKFILL, COMPACT TO 95% WASTE HEAT SUPPLY AND RETURN PIPING. * <2 <3 ‘ OOOg . . CSR | 0. SOOTY |. RD | CS ARCTIC PIPE AND TRENCH P cross SECTION FRYER/PRESSLEY ENGINEERING DATE 660 EAST 34th AVENUE SUITE 300 ANCHORAGE, ALASKA 99603 (907)561-1666 Page 43 BEDDING. BEDDING, COMPACT TO 95%. 6" MIN. BEDDING. DWN BY: MD CKD BY: in) 1/15/90 7.6 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Outline Specifications The outline specifications for the major components of the system are shown below. 18010 GENERAL CONDITIONS The system shall be balanced by the Contractor to the flow specified In the construction documents. 15050 BASIC MATERIALS AND METHODS Valves: Valves for isolation use shall be gate type rated for 150 psig. Piping: Piping inside buildings shall be type "L" copper or steel schedule 40 with dielectric unions at connection points of dissimilar metals. 15120 ARCTIC PIPE Arctic Pipe: Carrier pipe shall be schedule 40 steel. Insulation shall be foamed polyurethane with no voids. Thickness of insulation to be mini- mum of 2 inches. Jacket pipe shall be steel or high density polyethylene. Arctic pipe system shall include kits or fittings for take-off connections to main loop that provide water-tight seal. 15250 MECHANICAL INSULATION Piping insulation: Pipe Insulation shall be fiberglas with an all-service Jacket. Minimum insulation thickness shall be 1-1/2 inches. 15750 HEAT TRANSFER Heat Exchangers: Heat exchangers shall be plate and frame type with minimum 20 gage stainless steel plates, painted steel frame with head and end support, top carrying bar, and bottom guiding bar. Ports shall be International pipe thread. Capacity shall be as specified. Accept- able manufacturers are Bell & Gossett, APV, Tranter, and Alfa Laval. Page 44 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Circulation Pumps: The primary loop circulation pump shall be a base- mounted centrifugal pump capable of 450 GPM at 106 feet of head. All pumps shall be compatible with a glycol heating fluid. 15900 CONTROLS Sequence of Operation: All of the pumps shall be manually switched. 16010- GENERAL This Section of the Division 16 Specifications will include the following sub- headings with appropriate explanations of the requirements covered in each. GENERAL AND SPECIAL CONDITIONS Refers the Contractor to the Project Specifications’ General and Special Conditions. DRAWINGS Explains the nature of the Drawings and how the information depicted on the Drawings should be used and interpreted when viewed in the context of the entire set of Contract Documents. DEFINITIONS Defines some of the major terms used in writing the Specifications. SUBMITTALS AND APPROVALS Defines the acceptable information considered to constitute the material submittals required for verifying the actual equipment and materials proposed for use in the Project's electrical systems. Page 45 16020- 16021- GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 PRODUCT DELIVERY, STORAGE AND HANDLING Directs caution in the storage and handling of materials to ameliorate their possible damage prior to their installation. JOB CONDITIONS Advises the Contractor to visit the site to acquaint himself with the actual conditions at this Project’s location. PRODUCTS Establishes general criteria and standards of quality for the Project which apply to all of the materials proposed for the Project. This sub-section also requires all electrical materials to be labeled for their intended use and environment by UL. : CLEANING The Contractor is required to clean all surfaces of equipment and remove debris and unused materials in this sub-section. WORK INCLUDED This area of the Division 16 Specification lays out the generalized descrip- tions of the electrical systems and work required in this Project. It also covers which area of the Specifications will define the requirements for equipment or installations which must be coordinated with other building trades. - WORK NOT INCLUDED This Section deals with those items which will definitely be. provided within other areas of the Project's various disciplines. An example of such an item would be the motors provided on a fan unit (obviously specified in Division 15) which is specified complete with a motor starter, disconnect or other accessories normally found in Division 16. Page 46 16032- 16111- 16120- 16131- 16147- GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 MANUALS AND AS-BUILT DRAWINGS Sub-paragraphs describing the required contents of the Operation and Maintenance Manuals, defining the periods of instruction for the Owner's designated personnel and the updating of information necessary to prepare record drawings of this Project’s final configuration are con- tained in this Section. CONDUIT All types of raceways and their associated appurtenances will be covered in this Section of Division 16. Galvanized rigid steel conduit, PVC-coated galvanized rigid steel conduit, intermediate metallic con- duit, electrical metallic tubing, flexible metal conduit and liquid-tight flexible conduit will be specified. Fittings, couplings, grounding and where each type of raceway may be used will be specified. WIRES AND CABLES Building wires and cables for the distribution, feeders and branch circuits required for this Project are defined in this Section. This Section typically covers only wire with voltage ratings below 600 V. PULL BOXES AND JUNCTION BOXES The various types of pull boxes and Junction boxes which will be allowed and/or required for installing the systems defined within Division 16 are specified in this Section. DEVICE PLATES AND COVERS Surface mounted boxes shall be galvanized steel plates. Weatherproof installations will have gasketed metal plates. Page 47 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 16155- MOTOR STARTERS This Section will specify the motor contactors and controllers required by mechanical equipment. All controllers will be specified to have integral thermal overloads for motor overload protection. Combination starters utllizing circuit breakers or motor circuit protectors and that are UL listed for the application, will be acceptable. Combination starters utilizing fuses will not be allowed. 16161- GROUNDING This Section expands on the National Electrical Code requirements. 16164- BRANCH CIRCUIT PANELBOARDS Branch circuit breakers required to connect new equipment to existing panelboards will be specified in this Section. All circuit breakers will be bolt-on molded case circuit breakers of the rating and configuration necessary to serve general branch circuits and other defined loads. 16170- MOTOR AND CIRCUIT DISCONNECTS Unfused switches will be specified. Disconnects for motor applications will be required to be horsepower rated. Other disconnects will be specified to have ratings as necessary for the application. Enclosures will be NEMA 1 except where otherwise required. 16190- SUPPORTING DEVICES This Section will contain the requirements for hardware, anchors and fas- teners used to support raceways, equipment and any other electrical apparatus. Page 48 8.0 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 ECONOMIC DATA 8.1 8.2 Current Fuel Oil Costs Fuel oil costs for Copper Valley School District were $.913/gallon for fuel oll (#1). The fuel is purchased based on a negotiated rate. Fuel oil costs for the Post Office (#1 only) is currently $0.91/gallon while the Apart- ment building, using #2 fuel oil is currently paying $0.957/gallon. Displaced Costs Due to Heat Recovery The calculations that model the waste heat system are shown in the Appendix at the end of this report. These calculations essentially make comparisons of the waste heat available to the waste heat demand of the connected buildings. These comparisons are made for each hour of an average day of each month of the year. Since it may not be economically feasible to connect all of the potential build- ings, the calculations were made in a logical order of building connections, that is, the nearest building was modeled as being connected first. In this proposed order, the high school was connected first, then the Community building, and last the Treatment plant. The results of the calculations based on the most recent fuel oil costs were as fol- lows: CONCEPT GALLONS SSAVINGS 1A 6,905 $6,608 1B 15,430 $14,366 2A 38,316 $35,A33 2B 57,544 $52,844 Page 49 8.3 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Summary Cost Estimate The assumptions for the cost estimate was that bidding would take place In April of 1990. Prevailing local wages as defined by the Department of Labor were used. The cost estimate is presented with costs identified for the total project, but broken out separately to show the component costs for the work at the power plant, for the arctic pipe, and for each of the connected buildings. Since there can be much more energy demand than is available with the con- nected buildings, the cost estimate Is organized in an additive alternate form. Energy Authority SIA (Supervision, Inspection, and Administration) costs are in- cluded in the figures shown below. CONCEPT = COST 1A $255,309 . 1B $289,770 2A $458,120 2B $647,603 Page 50 8.4 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Estimated Component Life and Maintenance Costs The following estimates of maintenance cost were made based on the in- cremental cost of technician who Is already on-site. Assumptions were made for each of the pieces of equipment regarding frequency of inspection and repair. The total yearly maintenance cost will depend on the scope of installation. The costs for all buildings connected Is shown. ttem Life (yrs) Maint. Cost ($/Yp Heat Exchangers 20 $126 (each, 6 total) Circulation pumps 16 $112 (each, 2 total) Arctic Pipe 16 $700 (total Interior piping 16 $70 (each location, 6 total) Interior valves 15 $140 (each location, 6 total) Expansion Tank 16 $70 (each, 2 total) Air Separator 15 $35 (each, 2 total) Glycol 15 $300 (total TOTAL (base bid) $3450/year Page 51 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 9.0 FAILURE ANALYSIS 9.1 General The purpose of this section is to analyze the reliability if the various components of the proposed waste heat recovery system. The analysis of the system will help guide the direction of the design to avoid systems with increased failure rates and repair costs and reduced waste heat recovery effectiveness. 9.2 Identification of Major Components The following components are those whose failure Is likely In the normal course of operation and whose failure could affect the operation of the generator or waste heat recovery systems. A brief description of the component follows the identification. Circulation pump(s): This is the pump (centrifugal) that will be used to cir- culate fluid from the heat exchanger In the power plant to the user buildings through the arctic pipe. This discussion.also applies to booster pumps (in-line type) that can be used In the user buildings to help overcome the additional pressure drop of the waste heat recovery system heat exchanger. A pump may also be used on the generator side of the system to help overcome the added pressure drop of the heat exchanger or the case where hydronic coils have been added to an all air system. Jacket Water Heat Exchanger: This component is the device used to transfer heat from one liquid to another. In the design presented here, it is a flat plate, or plate and frame type heat exchanger. The device consists of vertical plates separated by gaskets with the fluid of one system flowing in alternate plates heating (or cooling) the other fluid. There are no moving parts during operation. Stack Gas Heat Exchanger: This Is a device similar in concept to the jacket water heat exchanger with the exception that the-fluids being considered include both a liquid (the waste heat recovery transfer medium) and a gas - the exhaust gases from the engine. Although there are no moving parts, the heat exchanger surface is subject to very high temperatures from the exhaust gases (to 1400 degrees F). Radiator(s): These devices are part of the generation system rather than the waste heat recovery portion. They are used to provide cooling for the engines by transferring heat from the engine coolant to the atmosphere. In conjunction Page 52 9.3 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 with the waste heat recovery system, they would be used only when cooling Is required beyond the cooling that has occurred through the use of waste heat by the recovery system. Control Valve(s): Control valves are used to maintain a setpoint tem- perature at a specific location in a piping system. In the case of the generation system, they often are the self-contained type as manufactured by Amot. The valve operator movement is based on the expansion of wax in the valve case. Alfematives are an electrically operated valve to serve the same function. Exterior piping (arctic pipe): The arctic pipe is a pipe-within-a-pipe system used for transferring fluid between locations. The center pipe, or carrier pipe is used for fluid transfer. The carrier pipe is insulated to reduce heat transfer. Outside the insulation Is a second pipe called the jacket. This is used to protect the insulation. Interior piping/valves: This portion of the system is found at the power plant or at the user buildings. Its purpose Is to transfer and control the fluid to the com- ponents of the system. Failure Mode and Impact For each of the components Identified above, the likely mode or modes of failure is discussed. These failure modes have been surmised based on conversations with equipment manufac- turers and based on engineering experience and judgment. In addition, the impact of failure on the generation and the waste heat recovery system is gaged as is the environmental effects. Recommended immediate actions by the system caretaker are also noted. Circulation pump(s) Failure Mode: The pump assembly can fail by the failure of its in- dividual components. These include shaft seals, shaft bearings, motor, impeller, or casing. Impeller or casing failure is not expected to occur before the life of the com- ponent has been reached. This life is expected to be 15 years. Generator Operational Impact: Since failure of a booster pump used on the gener- ator side of the system could result in a high-temperature shut-down of the engine, its use Is not recommended. The likely reason for addition of a booster pump Is to over- come additional pressure drop imposed by the system by new heat recovery equip- Page 53 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 ment. To avoid the need for the pump, the system should be designed to keep addi- tional pressure drop below the maximum rated pressure drop of the engine mounted pump. Waste Heat System Operational Impact: Where only a single circulation pump has been installed for heat transfer services, Its failure Could result In complete suspension of heat recovery. Shaft seal and shaft bearing failures in their early stages would have little effect on operation but could eventually reduce heat recovery to zero after complete failure. When duplex pumps have been installed, the heat recovery will be affected only until the standby pump can be put into service which can occur minutes after the failure is noted. Environmental Impact: Minor - a shaft seal failure could result in a slow fluid leak that could reach the ground outside. Required Immediate Actions: If no significant loss of fluid has occurred (due to shaft seal failure), replacement of the pump will restore the system to service. The pump should be Isolated with the valves on either side of the pump, fluid checked and proper fluid level restored as needed, and the back-up pump (if installed) started. Jacket Water Heat Exchanger Failure Mode: Since there are no moving parts, the failure of this component can occur from failure of the gaskets, or failure on the frame or plates. Since the plates are generally of stainless steel, failure is unlikely during the rated life of the equipment - or approximately 20 years. The frame Is also unlikely to fail during the 20 year life. The only probable failure during the life would be the gaskets, probably exhibited as a slow leak that worsens with time. Generator Operational Impact: If the gaskets failed serving the generator cooling system fluid, enough fluid could leak out to cause a low water shut-down of the engine. Waste Heat System Operational Impact: Similar to the scenarios above, if fluid from the waste heat system were to leak from failed gaskets, the system could be in- capacitated. Page 54 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Environmental Impact: A major loss of the fluid, most likely an ethylene glycol mix- ture could have some environmental impacts. Ethylene glycol is toxic. The problem could be reduced by using propylene glycol which is potable. The problem that often results when using propylene glycol is failure of operating or maintenance personnel to use compatible glycol for system make up. Required Immediate Actions: If an engine side gasket has failed, the heat ex- changer should be bypassed and manual shut-off valves used on the leaking side. If the leak occurs on the waste heat side, isolation valves should be closed and the circulation pump shut off. Stack Gas Heat Exchanger Failure Mode: Three mechanisms can lead to this component failure. The first Is through operational wear. This wear is caused by the passage of hot exhaust gases over the heat exchanger surface. The failure through this mechanism determines the life of the equipment which is approximately 5 years. Two other forms of failure can occur: the first Is through thermal shock by passage of relatively cold fluid into the exchanger which has been heated to the exhaust gas temperature. Sudden contraction will destroy the heat exchanger. The second type of failure could occur if the heat exchanger is kept at too low of a temperature allowing sulfuric and hydrochloric acids to form from the exhaust gases. Rapid corrosion would result in the heat exchanger failure. Generator Operational Impact: If the heat exchanger Is located away from the generator, its failure would probably not release glycol onto the engines surface. Since the flow path of the exhaust gases would not be any more restricted after failure, no significant backpressure is expected to develop. If the stack gas heat exchanger is used to heat fluid after passing through the main jacket water heat exchanger, no loss of en- gine coolant will occur. However, to avoid pipe contamination, the generator should be shut down. If available or designed, a bypass-.device that allows exhaust gases to fol- low a path away from the heat exchanger would allow generator operation with a damaged or missing heat exchanger. Waste Heat System Operational Impact: Tne waste heat system would be disabled by a sudden stack gas heat exchanger failure. Environmental Impact: The loss of fluid to the environment could represent a problem as outlined in previous discussions. Page 55 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Required Immediate Actions: After failure of the stack gas heat exchanger, the exchanger should be isolated with valves and a bypass mechanism used for the stack gases. Fluid snould be added to make up for losses, and lost fluid collected where pos- sible. Radiator(s) Failure Mode: The main component of the radiators Is the heat exchanger for cooling of the liquid. The heat exchanger is expected to last the life of the radiator or 15 years. The other modes of failure are similar to for circulation pumps: shaft bearings or motors, or controls. The controls in this case are assumed to be variable speed controls for the fan motor. Generator Operational Impact: Failure through leakage would drain the fluid and cause a low water shutdown of the generator. Failure of the fan-related hardware would result in insufficient cooling and a high-temperature shut down. Waste Heat System Operational Impact: Tnere would be no effect on the waste heat system until generator shut down. At that time of course, no more heat would be avail- able for recovery. Environmental Impact: The only environmental impact would be if a leakage failure occurred which Is not the highest probability failure. Required Immediate Actions: The radiator should be isolated and an altemate radiator used for cooling until repairs can be made. Control Valve(s) Failure Mode: The valve casing is expected to last the life of the valve or 20 years. The most likely failure before the life is reached is that of leaking seals or seats, or failure of the operating mechanism. The seal or seat failure will normally result in a low-loss leak of fluid until repaired. The control mechanisms that can be used In this instance include Amot type operators which use the expansion characteristics of wax to operate the valve or electric motor driven operators. Although Amot-type operators fail less fre- quently than electric motor operators, they have the disadvantages of less control (which means less heat recovery) and do not indicate current control position. Page 56 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Generator Operational Impact: Failure of the operators will normally result in loss of control. Often time these failures can occur at a mixing condition which may not im- mediately cause a system failure. The extreme cases would result in overheating. Waste Heat System Operational Impact: As discussed above, a failure in a mixing mode may not cause complete failure, but it is possible. Environmental Impact: Minor - only small leaks normally develop through seal and seat failures, Required Immediate Actions: The valve should be isolated as soon as the seat or seal failure is discovered. If the failure is an electric operator, the valve could be manually positioned to an acceptable position until the operator can be replaced. When an Amot-type valve Is used, manual bypass valves can be used. Exterior piping (arctic pipe) Failure Mode: The only failure mode likely to interfere with the system operation would be a fluid leak at a joint. Generator Operational Impact: None. Waste Heat System Operational Impact: —_A significant leak would shut down the sys- tem. Environmental Impact: The leaking fluid could drain the entire piping system. Required Immediate Actions: The pump would be turned off, the system drained as much as possible, and the leaking line Isolated as close to the leak as possible. Interior piping/valves Failure Mode: Interior piping joints will normally last the length of the pipe life - about 20 years - unless physically damaged. The valves may suffer the same failures as men- tioned above for control valves. Generator Operational Impact: A fluid leak would generally be small but it is pos- sible that enough fluid would leak until a low water shut down occurred. Waste Heat System Operational Impact: Same as for Generation system effect. Page 57 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Environmental Impact: Minor. Required Immediate Actions: Isolate the leaking valve, shut off pump if fluid loss is significant. 9.4 Failure Frequency and Cost Frequencies of failure have been estimated based on conversations with manufacturers and on engineering Judgment. Assumptions made regarding the repair include: On-site operator's skill are that of a "caretaker." Skilled preventive maintenance is performed 3 times yearly. A one day weather delay is included for all winter repair trips. Travel to site for repair is via jet, and then charter. Skilled mechanics are mobilized from Anchorage, Fairbanks, or Juneau as ap- propriate. Costs are based on $43/hour labor costs. Travel time is 12 hours round trip. Travel cost Is $600 round trip. Subsistence costs are $100 per day. OQRONn> Ps FP Circulation pump(s) Most common failure: Shaft.seal, shaft bearings, or motor. Frequency of Occurrence: 0.1 per year Repair Cost: $1900/occurrence Estimate of Down Time: 2 days after discovery Effects of System Life on Frequency: Increase in probability only. Jacket Water Heat Exchanger Page 58 Most common failure: Frequency of Occurrence: Repair Cost: Estimate of Down Time: GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Gasket failure. 0.1 per year $1900/occurrence 9 days Effects of System Life on Frequency: Increasing probability. Stack Gas Heat Exchanger Most common failure: Frequency of Occurrence: Repair Cost: Estimate of Down Time: Operator error - damage to heat exchanger 1 per year $6600/occurrence 30 days Effects of System Life on Frequency: No effect due to frequent expected replacement Radiator(s) Most Common failure: Frequency of Occurrence: Repair Cost: Estimate of Down Time: Motor failure 0.1 per year $1800/occurrence 5 days Effects of System Life on Frequency: Increased probability. Control Valve(s) Page 59 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Most common fallure: Electric operator (seal for Amot valve) Frequency of Occurrence: 0.33/year (0.1 for Amot valve) Repair Cost: $1800/occurrence Estimate of Down Time: 3 days Effects of System Life on Frequency: Increasing likelihood due to wear Exterior piping (arctic pipe) Most common failure: Accidental damage Frequency of Occurrence: 0.1 per year Repalr Cost: $1800/occurrence Estimate of DownTime: 21 days Effects of System Life on Frequency: None Interior piping/valves Most common failure: Valve seat/seal failure Frequency of Occurrence: 0.25 per year Repair Cost: $1800/occurrence Estimate of Down Time: 2 days Effects of System Life on Frequency: Increased likelinood due to wear Page 60 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 95 Design Decisions Impact on current concept design from the above failure analysis Includes the recommenda- tion that stack gas heat exchangers not be used In a location where the operator is a not a skilled maintenance person. This recommendation is due to the sensitivity of the equipment to operator error and the delay that could be encountered in returning the system to service. Other recommendations include design of duplex pumps so that damaged pumps will not halt service for any length of time. This type of approach can also be extended to spare parts stock so that some failures may be attended to during the preventive maintenance visits to reduce costs. To avoid compromising the reliability of the generation system, booster pumps of the generator side should be avoided. A way to avoid the need for the pumps Is to design the heat ex- changer and piping system to be as low as possible and to be less than the maximum recom- mended external pressure drop as listed by the engine manufacturer. Although the failure rate of the electric motor operators on control valves is higher than for self- contained Amot-type valves, the additional control and heat recovery may provide incentive for their use. To keep an increased level of reliability of building heating systems, it is also recommended that any building connected the waste heat recovery system use a heat exchanger. In the event of a distribution piping failure, the building’s heating system would continue to operate without in- terruption. Page 61 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 10.0 CONCLUSIONS AND RECOMMENDATIONS The final economics will be completed by the Alaska Energy Authority so a definitive conclusion Is not made at this tine concerming the feasibility of a waste heat installation at Glennallen. Some conclusions that can be made are that the project is technically feasible, that the people and agencies in the community seem quite enthusiastic about the project, and that if the economics prove acceptable, a waste heat system for the community can be recommended. Two graphs follow this page that illustrate the current waste heat situation in Glennallen. The first graph entitled "Heat Available Vs. Heat Required" shows the relationship be- tween these two quantities for each month of a year. The lowest line represents the heat available from the power plant in terms of equivalent gallons of fuel oil. Each of the other three lines represent a construction option: the concept 1B, the concept 2A, and the concept 2B. The second graph Is entitled "Fuel Oll Displaced” and shows the amount of recovered energy in equivalent gallons of fuel oil for each of the three construction options for the year. A similar shape as was shown in the previous graph is displayed. Page 62 e9 ebeg GLENNALLEN WASTE HEAT RECOVERY HEAT AVAILABLE VS. HEAT REQUIRED FUEL OIL EQUIVALENT (GALLONS) 70,000 MIN ag tart Fea ai gh mec ae Rapti heel al ate etialckei etches ae AO, O00 bonne orn cnn RL espe cenenenenennnenennnannnnnnnnnenenetety 30,000 ; 20,000 4 ONO geen gee neering ste i —z JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC MONTH OF THE YEAR LEGEND —— HEAT AVAILABLE —— HEAT REQ. - 1A+1B —*— HEAT REQ. - 1A+1B+2A —8— HT. REQ.-1A+1B+2A+2B 1/26/90 vg ebed GLENNALLEN WASTE HEAT RECOVERY FUEL OIL DISPLACED FUEL OIL EQUIVALENT (GALLONS) 12,000 10,000 8,000 6,000 4,000 2,000 0 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC MONTH OF THE YEAR LEGEND ES Alt. 1A+1B 4 Alt. 1A+1B+2A HH Alt. 1A+1B+2A+2B 1/26/90 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 APPENDIX 1 Calculations Zz Contact Names 3. Cost Estimates 4, Raw Data GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Calculations GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 WASTE HEAT RECOVERY CALCULATION METHOD Input Before the calculation of recovered waste heat can take place, the user must input in- formation about power production, fuel use, and system heat loss. The information Is for each month of a year. The year is assumed to be either an average year or a represen- tative year. The power production information must include the amount of power produced for each month of a year and the amount of heat rejected to the Jacket water for each KWH of power produced. The power production is from historical records and the heat rejection data is from the manufacturer of the engine/generators being used for power production. The fuel use data Is for each of the potential waste heat user buildings. It is fuel oll use for each month of the “average” year. It Is also assumed that the fuel oil use reported here is only for heating energy that can be displaced by waste heat recovery. It would not include fuel oil used by a separate fuel oil-fired water heater. The information ideally should be based on historical information but can also be estimated on a monthly basis for yearly fuel oll use. The system heat loss is a number that represents the energy that Is rejected to the jacket water, but is lost or used before It can be used by the end user buildings. Examples of this system loss can include: heat loss of the generator cooling system piping, heat loss from the arctic pipe, and heat recovery in the power plant for space heating or fuel oil heating. This figure must be estimated based on available information. Assumptions The most important assumptions made in this model are the diurnal variation of the heat demand, and the power production. The figures shown in the calculations represent a ‘typical’ pattern for rural environments. Tne heating demand follows an approximate sine curve with minimum demand at solar noon, and maximum demand at solar mid- night. The diurnal variation for power plant production is less regular. The variation as- sumed has peaks in the moming (around 8:00) and near noon and at 6:00 pm. The lowest power production occurs near midnight. GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 When calculating the energy demand for the buildings based on their fuel oil use, it is as- sumed that each gallon of fuel oil corresponds to 100,000 BTU. This represents ap- proximately a 71% efficient boiler or fumace. Actual efficiencies will vary. Calculations The heat available is calculated by dividing the monthly power production by the num- ber of days in the month - yielding the power production on an average day, then by multiplying that figure by the hourly power production variation for each hour. This is the power produced for each hour of the average day of the month. This figure Is multiplied by the manufacturer's factor for heat rejected to the jacket water. The result is the gross heat available at the power plant on an hourly basis. The system heat loss is subtracted from the gross amount, leaving the amount available for building use. The heat required by the buildings is accomplished in a similar manner. The sum of all the buildings fuel use is multiplied by 100,000 BTU/gallon and adjusted to yield the hourly heat demand for the average day of the month. The heat recovered Is just the smaller number of the heat avallable and the heat demand; if the heat available is larger than the heat demand, all of the heat available will be used. If the reverse Is true and much more heat Is available, then all of the bulld- ing heat demand requirements will be met. The number of gallons displaced also as- sumes that each 100,000 BTU corresponds to one gallon of fuel oil. GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 1 CONCEPT 1A WASTE HEAT UTILIZATION SIMULATION WORK SHEET. Location: GLENNALLEN Date: December 26, 1989 Heat rate: 2730 Btu/kwh produced System loss: 625,000 Btu/hour (FOR ALL SYSTEMS CURRENTLY CONNECTED) Total generation: 10,716,844 kwh/year UAL Local degree days 1784 1846 = 2089 1418 944 683 263 356 = 811 1054 «1787 2894 15,849 Assumed diurnal heat Power plant monthly generation: demand variation: 2---------------- JAN FEB MAR APR MAY JUN JUL AUG SEP ocT NOV DEC CHECKSUM Fraction:8.13569 8.12496 8.12376 8.21736 8.0826 9.0455 6.0088 0.6623 6 8.0158 6.8897 8.15336 1 Winter Summer Hour Kwh: 1454288 1339200 1325688 2329420 885260 488200 94600 25084 B 169408 962208 1643600 10,716,844 Diurnal 8.0494 0.0494 1 variation 8.038 8.038 68.038 8.038 8.045 0.045 06.045 6.045 0.045 0.045 0.058 0.038 6.0477 6.0477 2 9.036 8.036 0.036 0.036 6.040 0.040 0.040 0.040 0.040 0.040 0.036 0.036 6.0460 9.0460 3 6.034 8.034 0.034 0.054 6.036 0.036° 0.036 0.036 8.036 0.036 9.034 0.034 9.0443 8.0443 4 6.034 8.034 8.034 0.034 0.035 0.035 0.035 0.055 0.035 0.035 0.034 0.034 8.0428 6.0428 5 8.033 8.033 0.033 8.033 0.035 0.035 8.035 0.035 0.035 9.035 0.033 0.033 0.0414 8.0414 6 0.034 0.034 6.034 6.034 6.038 0.038 6.038 0.038 6.038 8.038 0.034 0.034 6.0401 8.0401 7 0.038 6.038 6.038 6.038 0.038 0.038 0.038 0.038 8.038 0.038 0.038 0.038 9.0398 0.0398 8 8.042 8.042 6.042 0.042 0.040 0.040 0.040 0.040 6.040 0.040 0.042 0.042 0.0381 6.0381 9 6.042 8.042 8.042 8.042 0.045 0.045 6.045 6.045 0.045 0.045 0.042 0.042 8.0374 0.0374 at) 8.047 8.047 6.047 8.047 0.047 6.047 6.047 0.047 0.047 6.047 0.047 0.047 9.0378 8.0370 " 6.048 8.048 8.048 8.048 0.040 0.040 0.040 0.040 0.040 6.040 0.048 0.048 6.0367 9.0367 12 6.047 0.047 0.047 8.047 0.048 6.048 0.048 6.048 6.048 6.048 0.047 0.047 9.0367 9.0367 13 6.045 8.045 0.045 0.045 8.050 0.050 6.050 8.050 8.058 0.050 9.045 0.045 6.0378 8.0378 14 0.047 8.047 0.047 0.047 6.052 0.052 0.052 8.052 8.052 6.052 8.047 0.047 6.0374 0.0374 15 8.048 8.048 0.048 8.048 0.050 0.050 6.050 6.058 0.050 8.050 0.048 0.048 6.0381 0.0381 16 8.048 8.048 0.048 0.048 0.050 0.050 0.050 0.050 0.050 8.050 d.048 0.048 6.0398 9.0390 17 6.049 0.049 8.049 0.049 6.045 0.045 6.045 8.045 0.045 0.045 0.049 0.049 6.0401 0.0401 18 8.046 8.046 0.046 8.046 0.047 6.047 0.047 6.047 6.047 8.047 0.046 0.046 8.0414 6.0414 19 9.043 8.043 8.043 0.043 0.050 6.050 0.050 8.050 0.050 0.050 0.043 0.043 0.0428 6.0428 26 9.038 9.038 8.038 8.038 0.045 6.045 6.045 6.045 6.045 6.045 0.038 0.038 8.0443 8.0443 ra 6.038 8.038 8.038 8.038 0.041 6.041 6.041 6.041 6.041 8.041 0.038 0.038 9.0460 8.0460 22 8.041 8.041 6.041 8.041 0.041 6.041 6.041 6.041 0.041 6.041 0.041 0.041 6.6477 8.0477 23 8.045 8.045 6.045 8.045 0.041 6.041 0.041 6.041 0.041 0.041 6.045 0.045 8.0494 8.0494 24 6.040 8.040 6.040 9.040 8.043 0.045 0.043 6.043 0.043 0.043 6.040 0.040 Building use per month, gallons of fuel oil BUILDING 1A - APARTMENT BUILDING 1188 1266 713 518 372 276 248 341 630 766 «61058 1382 8,576 BUILDING 1B ~ POST OFFICE a a 8 a a 8 8 6 6 a 0 a a BUILDING 2A - OLD SCHOOL 8 6 6 a a 8 8 8 a 8 8 6 0 BUILDING 2B - NEW SCHOOL 8 6 6 8 8 8 6 6 6 6 6 6 a BUILDING 2B - WEIR BUILDING GYM 8 8 8 8 8 8 8 8 6 6 6 8 4 BUILDING 6 8 a 4 8 8 8 6 8 a a 8 a 6 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION BUILDING 7 BUILDING 8 BUILDING 9 PAGE 2 11881288 3 518 Heat available per hour by month JAN FEB MAR APR 1 4334194 3942815 3895988 7318919 2 4873184 3781646 3657966 6980818 3 3812174 3461276 3426623 6482717 4 3812174 3461276 3426823 6482717 5 3681669 3341092 3301052 6273666 6 3812174 3461276 3420623 6482717 7 4334194 3942015 3895988 7318919 8 4856215 4422753 4371793 8155121 9 4856215 4422753 4371793 8155121 18 5588741 5823676 4966658 9260374 11 5639246 5143861 5885621 9489424 12 5588741 5823676 4966658 9200374 13 5247738 4783307 4728767 8782273 14 5588741 5823676 4966658 9200374 15 5639246 5143861 5885621 9489424 16 5639246 5143861 5685621 9409424 17 5769751 5264846 5284592 9618475 18 5378235 4983492 4847678 8991323 19 4986728 4542938 4498765 8364172 28 4334194 3942815 3895988 7318919 21 4334194 3942015 3895988 7318919 22 4725718 43062569 4252822 7946871 23 5247738 4783307 4728787 8782273 24 4595205 4182384 4133851 7737620 1E+O8 «1E+88 = 1E+08 «= -2E+08 Heat demand by hour by month JAN FEB MAR APR Oryaue un — a MAY 3E+86 3E+06 2E+06 2E+06 2E+06 2E+06 2E+06 SE+O6 3E+86 SE+06 3E+O6 SE+O6 3E+O6 4E+06 SE+O6 3E+O6 SE+O6 3E+O6 SE+O6 3E+O6 SE+O6 SE+O6 SE+O6 3E+O6 7E+87 MAY 191684. 194932. 115822. 82846.4 60429. 184964. 188899. 111762. 79942.4 58310. 178371. 181394. 187778. 77892.5 56232. 172625. 174948. 183944. 74349.8 54231. 166045. 168859. 100330. 71765.4 52346. 160543. 163264. 97006.2 69387.3 50611. 155621. 158259. 94032.2 67260.0 49860. 151371. 153936. 91464.8 65423.1 47728. 9 147871. 158378. 89349.6 63910.7 46617. 18 145188. 147649. 87728.4 62751. 45771. 11 143371. 145801. 86630.5 61965.7 45198. 12 142454. 144869. 86076.4 61569.3 44909. 13 142454. 144869. 86076.4 61569.3 44909. 14 143371. 145861. 86630.5 61965.7 45198. JUN 1E+06 1E+86 952261 soee4e 908448 1E+86 1E+06 1E+86 1E+06 1E+06 1E+06 1E+06 2E+06 2E+06 2E+06 2E+86 1E+06 1E+06 2E+06 1E+86 1E+O6 1E+06 1E+06 1E+06 3E+87 3 eS etaiefeelelala ale lcle elelialelalerare a lavarate El alalalalalalatataaie/elalalaleralalarararararatr JUN JUL AUG 43859. 42322. 40813. 39361. 37993. 36734. 35608. 34635. 33835. 33221. 32805. 32595. 32595. 32805. 40286. 38873. 37488. 36154. 34897. 33741. 32766. 31813. 31878. 30514. 30132. 29939. 29939. 30132. 55393. 53451. 51546. 49712. 47984. 46394. 44971. 43743. 42732. 41957. 41431, 41166. 41166. 41431. 638 768 SEP OCT 6 59115. 6 6 59115. 6 89528. 6 6 6 184723 6 135128 ® 165533 6 135128 ® 135128 6 59115. 6 89528. ® 135128 6 59115. 6 28710. 6 1E+86 SEP OCT 182339 123457 98752. 119129 95232. 114883 91843. 118795 88651. 186944 85713. 103400 83085. 1006236 88816. 97493. 78948. 95239. 77516. 93511. 76545. 92341. 76056. 91758. 76056. 91758. 76545. 92341. CONCEPT 1A a 8 a 8 4 a 8 a a 6 6 a 1058 1302 8,576 NOV-DEC 3E+06 4980097 2E+86 4685092 2E+06 4398087 2E+86 4396887 2E+06 4242584 2E+86 4390087 3E+86 4980097 3E+86 5570107 3E+06 55761087 3E+06 6307620 4E+06 6455123 3E+86 6307628 3E+O6 6612615 3E+06 6307620 4E+86 6455123 4E+06 6455123 4E+06 6602625 3E+O6 6160117 3E+86 5717610 3E+86 4980097 3E+06 4980097 3SE+06 5422605 3E+06 6012615 3E+06 52751082 ANNUAL TE+O7? «= 1E+88 2. 504E+10 NOV DEC 170566 211582. 164587 204088. 158728 196812. 153073 189818. 147752 183212. 142856 177141. 138476 171711. 134694 167621. 131588 163160. 129193 168199. 127576 158194. 126766 157183. 126768 157183. 127576 158194. GLENNALLEN WASTE HEAT RECOVERY ESTIMATION 15 16 17 18 19 RSRsees wCoaranueun = Baste = PRQBRERSSIAG 145188. 147871. 151371. 155621. 160543. 166845. 172825. 178371. 184964. 191684. 147649. 158378. 153936. 158259. 163264. 168859. 174948. 181394. 188899. 194932. PAGE 3 87728.4 62751.8 45771. 89349.6 63910.7 46617. 91464.8 65423.1 47720. 94032.2 67260.0 49868. 97006.2 69387.3 50611. 180330. 71765.4 52346. 183944. 74349.8 54231. 187778. 7092.5 56232. 111762. 79942.4 58318. 115822. 82846.4 60429. 33221. 33835. 34635. 35608. 36734. 37993. 39361. 40813. 42322. 43859. 30514. 31078. 31813. 32786. 33741, 34897. 36154. 37488. 38873. 40286 3879826 3944773 2343852 1676528 1E+06 887573 815253 Heat delivered by hour by month JAN 191684. 184964. 178371. 172625. 166045. 160543. 155621. 151371, 147871. 145188. 143371. 142454. 142454. 143371. 145188. 147871. 151371. 155621. 160543. 166845. 172625. 178371. 184964. 191684. FEB 194932. 188899. 181394. 174948. 168859. 163264. 158259. 153936. 150378. 147649. 145881. 144869. 144869. 145801. 147649. 150378. 153936. 158259. 163264. 168859. 174948. 181394, 188899. 194932. MAR APR MAY 115822. 82846.4 60429. 111762. 79942.4 58318. 187778. 77692.5 56232. 103944. 74349.8 54231. 100330. 71765.4 52346. 97006.2 69387.3 58611. 94032.2 67260.0 49060. 91464. 65423.1 47720. 89349.6 6391.7 46617. 87728.4 62751.8 45771. 86630.5 61965.7 45198. 86076.4 61569.3 44909. 86076.4 61569.3 44989. 86630.5 61965.7 45198. 87728.4 62751.8 45771. 89349.6 63918.7 46617. 91464.8 65423.1 47728. 94032.2 67260.0 49060. 97006.2 69387.3 58611. 188338. 71765.4 52346. 183944. 74349.8 54231. 187778. 77892.5 56232. 111762. 79942.4 58310. 115822. 82846.4 60429. 3879826 3944773 2343852 1676528 FUEL OIL CONSUMPTION DISPLACED JAN 1188 FEB 1268 MAR APR MAY 713 518-372 41957. 42732. 43743. 44971. 46394. 47984. 49712. 51546. 53451. 55393. 77516. 78948. 86816. 83885. 85713. 88651. 91843. 95232. 98752. 182339 93511. 95239. 97493. 106238 103400 106944 118795 114883 119129 123457 1E+86 2E+06 2E+06 g & 43859. 42322. 40813. 39361. 37993. 36734. 35608. 34635. 33835. 33221. 32805. 32595. 32595. 32805. 33221. 33835. 34635. 35608. 36734. 37993. 39361. 40813. 42322. 43859. 1E+86 887573 JUN JUL 276 AUG 6 § § 59115. 59115. 89528. 6 91758. 91758. 92341. 93511. 95239. 59115. 89520. 103400 8 59115. SEP 28710. 1E+O6 ocT 388 129193 131568 134694 138476 142856 147752 153073 158728 164587 170566 168199. 163160. 167821. 171711. 177141. 183212. 189818. 196812. 204088. 211582. CONCEPT 1A ANNUAL, SE+O6 4280078 857600000 Nov 170566 164587 158728 153873 147752 142856 138476 134694 131588 129193 127576 126768 126768 127576 129193 131588 134694 138476 142856 147752 1530873 158728 164587 170566 DEC 211582. 204088. 196812. 189818. 183212. 177141, 171711. 167021. 163168. 168199. 158194. 157183. 157183. 158194. 166199. 163160. 167821. W71711. 177141, 183212. 189810. 196812. 204088. 211582. ANNUAL. BE+O6 4280078 690491322. NOV 1058 DEC 1302 ANNUAL 6,965 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 1 CONCEPT 1B WASTE HEAT UTILIZATION SIMULATION WORK SHEET. sassseass Location: GLENNALLEN Date: December 26, 1989 Heat rate: 27308 Btu/kwh produced System loss: 625,008 Btu/hour (FOR ALL SYSTEMS CURRENTLY CONNECTED) Total generation: 10,716,844 kwh/year ANNUAL Local degree days 1784 1846 = 2089 1418 944 605 263 0-356 811 1854 «1787 = 2894 15,049 Assumed diurnal heat Power plant monthly generation: demand variation: —aare cee reccenene JAN FEB MAR APR MAY JUN JUL AUG SEP ocT NOV DEC CHECKSUM Fraction:8.13569 8.12496 6.12378 6.21736 6.0826 6.0455 6.6088 6.6023 6 6.6158 6.0897 0.15336 1 Winter Summer Hour Kwh: 1454208 1339280 1325680 2329420 885268 488200 94608 25084 8 169400 962200 1643600 10,716,844 Diurnal 9.0494 9.0494 1 variation 8.038 8.038 9.038 8.038 0.045 6.045 0.045 8.045 0.045 0.045 0.058 0.038 9.0477 0.0477 2 0.036 8.056 8.036 8.056 0.040 0.040 0.040 0.040 0.040 0.040 9.036 0.036 8.0460 9.0460 3 8.034 8.034 8.034 8.034 0.036 0.036 6.036 8.036 0.036 0.036 0.034 0.034 8.0443 8.0443 4 8.034 8.034 8.034 8.034 0.035 6.035 6.035 6.055 0.035 6.035 0.034 0.034 8.0428 6.0428 5 6.033 9.033 0.033 0.033 0.035 6.035 0.035 0.035 6.035 6.035 0.033 0.033 6.0414 8.0414 6 9.034 8.054 8.034 8.054 0.038 0.038 0.038 8.058 0.038 0.038 0.034 0.034 6.0401 9.0401 7 0.038 0.038 0.038 0.038 0.038 0.038 6.038 0.058 6.058 6.038 0.038 06.038 9.0398 0.0398 8 0.042 0.042 6.042 8.042 0.040 6.040 0.040 0.040 0.040 6.040 0.042 0.042 9.0381 9.0381 9 8.042 8.042 6.042 9.042 0.045 0.045 6.045 6.045 0.045 6.045 0.042 08.042 0.0374 6.0374 16 6.047 8.047 8.047 8.047 0.047 0.047 6.047 0.047 6.047 6.047 0.047 0.047 9.0378 6.0370 " 0.048 6.048 0.048 0.048 0.040 0.040 0.040 6.040 0.040 6.040 0.048 0.048 6.0367 9.0367 12 0.047 6.047 6.047 0.047 6.048 0.048 06.048 6.048 0.048 6.048 0.047 0.047 9.0367 0.0367 13 9.045 0.045 0.045 0.045 0.050 0.050 8.050 0.050 6.050 8.050 0.045 0.045 9.0378 0.0370 14 0.047 0.047 0.047 0.047 6.052 8.052 8.052 0.052 6.052 6.052 0.047 0.047 8.0374 9.0374 15 8.048 8.048 6.048 6.048 6.050 0.050 0.050 6.050 6.050 6.050 0.048 0.048 6.0381 9.0381 16 8.048 8.048 8.048 8.048 0.050 6.050 0.050 0.050 0.050 8.050 0.048 0.048 6.0398 9.0390 17 9.049 6.049 6.049 8.049 0.045 6.045 0.045 6.045 0.045 0.045 0.049 0.049 0.0401 0.0401 18 8.046 8.046 6.046 0.046 0.047 6.047 6.047 6.047 6.047 0.047 0.046 0.046 0.0414 0.0414 19 0.043 8.043 0.043 0.043 0.050 0.050 0.050 0.058 6.050 0.050 0.043 6.043 9.0428 0.0428 26 8.038 8.038 8.038 8.038 0.045 8.045 6.045 0.045 0.045 0.045 0.038 0.038 0.0443 6.0443 21 8.038 8.038 8.038 8.038 8.041 0.041 0.041 6.041 6.041 6.041 8.038 9.038 0.0460 0.0460 22 6.041 8.041 6.041 8.041 8.041 0.041 6.041 6.041 6.041 6.041 0.041 0.041 0.0477 6.0477 23 8.045 6.045 6.045 6.045 0.041 6.041 6.041 6.041 0.041 6.041 6.045 0.045 6.0494 8.0494 24 8.048 8.040 0.040 8.040 0.043 0.043 0.043 0.043 6.043 0.043 0.040 0.040 Building use per month, gallons of fuel oil BUILDING 1A - APARTMENT BUILDING 1186 =: 1208 113 518 «372 278 24834 630 «= 768 |= 1058 = 1302 8,576 BUILDING 1B - POST OFFICE 1552 1562 1628 615 255 158 30 6 310 962 «1620 1677 9,768 BUILDING 2A - OLD SCHOOL 8 8 8 8 0 a a 8 8 8 8 8 8 BUILDING 2B - NEW SCHOOL 6 8 8 6 6 6 8 6 6 6 8 6 0 BUILDING 2B - WEIR BUILDING GYM a 6 8 a a 8 6 6 6 8 8 a 4 BUILDING 6 6 8 8 8 6 8 6 6 a a 8 a 6 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION BUILDING 7 BUILDING 8 BUILDING 9 PAGE 2 aaoes aesacs seasa saaaos 2732-2762, 1733 1125 aeoas 627 Heat available per hour by month JAN FEB MAR APR 1 4334194 3942815 3895988 7318919 2 4073184 3701646 3657966 6900818 3 3812174 3461276 3426823 6482717 4 3812174 3461276 3420023 6482717 5 3681669 3341092 3301052 6273666 6 3812174 3461276 3426623 6482717 7 4334194 3942015 3895908 7318919 8 4856215 4422753 4371793 8155121 9 4856215 4422753 4371793 8155121 18 5508741 5823676 4966658 9200374 11 5639246 5143861 5885621 9409424 12 5588741 5823676 4966658 9200374 13 5247738 4783307 4728787 8782273 14 5588741 50623676 4966650 9200374 15 5639246 5143861 5885621 9409424 16 5639246 5143861 5885621 9409424 17 5769751 5264046 5204592 9618475 18 5378235 4983492 4847678 8991323 19 4986728 4542938 44908765 8364172 28 4334194 3942015 3895988 7318919 21 4334194 3942815 3895988 7318919 22 4725718 4302569 4252822 7946071 23 5247738 4783307 4728787 8782273 24 4595205 4182384 4133851 7737620 1E+O8 = 1E+08 = 1E+08 = 2E+08 Heat demand by hour by month JAN FEB MAR APR 1 443797. 448678. 281515. 182749. 2 428248. 432943. 271647. 176343. 3 412974. 417589. 261963. 170057. 4 398281. 402655. 252643. 164007. "5 384437. 388658. 243861. 158306. 6 371698. 375788. 235781. 153060. 7 360302. 364259. 228552. 148367. 8 350462. 354311. 222318. 144315. 9 342360. 346128. 217171. 148979. 18 336148. 339840. 213230. 138421. 11 331941. 335586. 210561. 136689. 12 329818. 333440. 209215. 135814. 13 329818. 333440. 269215. 135814. 14 331941. 335586. 210562. 136689. MAY 3E+06 3E+06 2E+06 2E+06 2E+06 2E+06 2E+06 3E+86 SE+06 3E+06 3E+06 3E+06 3E+O6 4E+06 3E+06 3E+06 3E+O6 SE+O6 3E+O6 3E+06 SE+06 3E+06 3E+06 SE+O6 TE+O7 MAY 1061852 98282. 94778. 91406. 88229. 85305. 82690. 80431. 78572. 77146. 76181. 75694. 75694. 76181. 428 JUN 1E+06 1E+06 952261 988448 908448 1E+O6 1E+O6 1E+86 1E+06 1E+06 1E+06 1E+06 2E+06 2E+06 2E+06 2E+06 1E+06 1E+06 2E+06 1E+66 1E+06 1E+06 1E+06 1E+86 3E+87 JUN 68226. 65834. 63488. 61229. 59100. 57142. 55390. 53877. 52632. 51677. 51030. 50704. 50704. 51030. 278 JUL 45159. 43576. 42023. 40527. 39119. 37822. 36663. 35662. 34837. 34205. 33777. 33561. 33561. 33777. os eligi i nity eee = ms Aas B 416 aaaeeeaaneamnauacameseeank AUG 67576. 65287. 62883. 60646. 58538. 56598. 54863. 53364. 52131. 51185. 50544, 56221. 50221. 50544, 948 = 1662 6 59115. 8 8 59115. 8 89520. 6 4 8 104723 8 135128 B 165533 8 135128 ® 135128 6 59115. 6 89528. ® 135128 6 59115. 6 28710. 8 1E+06 SEP OCT CONCEPT 13 ao aaa ea saan 2678 = 2979 18,344 NOV DEC 3E+06 4980097 2E+06 4685092 2E+06 4390087 2E+06 4390087 2E+06 4242584 2E+86 4390087 3E+06 4980097 3E+06 5570187 3E+06 5570107 3E+O6 6307620 4E+06 6455123 BE+O6 6307620 3E+O6 6012615 BE+O6 6307620 4E+06 6455123 4E+06 6455123 4E+06 6602625 3E+O6 6160117 3E+06 5717618 3E+06 4980097 3E+O6 4980097 BE+O6 5422605 3E+O6 6012615 3E+86 5275102 ANNUAL. 7E+O7 «= 1E#08 2. 504E+10 NOV DEC 152697 269982 433725 483920. 147344 260518 418522 466958. 142892 251231 403682 450311. 137836 242293 389243 434290. 132273 233878 375713 419194. 127898 226121 363263 405303. 123969 219188 352126 392877. 120583 213282 342589 382147. 117796 208273 334591 373313. 115658 204494 328528 366539. 114211 261935 324488 361952. 113488 208643 322333 359637. 113488 200643 322333 359637. 114211 201935 324408 361952. GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 3 CONCEPT 1B 15 336148. 339840. 213230. 138421. 77146. 51677. 34205. 51185. 115658 204494 328520 366540. 16 342360. 346120. 217171. 140979. 78572. 52632. 34837. 52131. 117796 208273 334591 373313. 17 358462. 354311. 222318. 144315. 80431. 53877. 35662. 53364. 120583 213202 342509 382147. 18 368303. 364259. 228552. 148367. 82698. 55398. 36663. 54863. 123969 219188 352126 392878. 19 371698. 375780. 235781. 153060. 85305. 57142. 57822. 56598. 127898 226121 363263 405383. 20 384437. 388658. 243861. 158306. 88229. 59108. 39119. 58538. 152273 233878 375713 419194. 21 398282. 402655. 252643. 164007. 91406. 61229. 40527. 60646. 137837 242293 389243 434298. 22 412974. 417589. 261963. 178057. 94778. 63488. 42825. 62883. 142892 251231 403682 458311. 23 428248. 432943. 271647. 176343. 98282. 65834. 43576. 65207. 147344 260518 418522 466958. 24 443797. 448670. 281515. 182749. 161852 68226. 45159. 67576. 152697 269982 433725 483920. ANNUAL. 8980933 9679552 5696989 3696224 2E+86 1E+06 913872 1E+M6 SE+O6 SE+O6 9E+06 9792899 1834400008 Heat delivered by hour by month JAN FEB MAR APR MAY = JUN 1 443797. 448670. 281515. 182749. 101852 68226. 2 428240. 432943. 271647. 176343. 98282. 65834. 3 412974. 417589. 261963. 178057. 94778. 63488. 4 398281. 482655. 252643. 164007. 91486. 61229. 5 384437. 388658. 243861. 158306. 88229. 59100. 6 371698. 375780. 235781. 153060. 85305. 57142. 7 360302. 364259. 228552. 148367. 82698. 55398. 8 350462. 354311. 222310. 144315. 80431. 53877. 9 342360. 346120. 217171. 148979. 78572. 52632. 18 336148. 339840. 213230. 138421. 77146. 51677. 11 331941. 335586. 210561. 136689. 76181. 51030. 12 329818. 333440. 209215. 135814. 75694. 50704. 13 329818. 333448. 209215. 135814. 75694. 58704. 14 331941. 335586. 210562. 136689. 76181. 51030. 15 336148. 339840. 213230. 138421. 77146. 51677. 16 342360. 346120. 217171. 148979. 78572. 52632. 17 350462. 354311. 222318. 144315. 88431. 53877. 18 360303. 364259. 228552. 148367. 82690. 55390. 19 371698. 375788. 235781. 153860. 85305. 57142. 28 384437. 388658. 243861. 158306. 88229. 59100. 21 398282. 402655. 252643. 164007. 91406. 61229. 22 412974. 417509. 261963. 170057. 94778. 63488. 23 428240. 432943. 271647. 176343. 98282. 65834. 24 443797. 448670. 281515. 182749. 181852 68226. 8980933 9879552 5696909 3698224 2E+06 1E+06 AUG =6SEP) = OCT:~—S ss NOV. —s«EC a 0 59115. 433725 483920. 6 6 418522 466958. a 6 403682 450311. 8 6 389243 434290. 6 8 375713 419194. 6 8 363263 405303. 6 6 352126 392877. 8 6 8 342509 382147. 6 8 59115. 334591 373313. 6 8 89528. 328520 366539. 6 6 6 324408 361952. 6 6 8 6 6 6 6 4 8 8 a 8 a 6 6 104723 322333 359637. 6 135128 322333 359637. ® 165533 324408 361952. 8 135128 328520 366540. 8 135128 334591 373313. 8 59115. 342509 382147. ® 89528. 352126 392878. 8 135128 363263 405303. 6 59115. 375713 419194. 6 ® 389243 434290. 8 ® 403602 450311. 6 8 418522 466958. 6 28710. 433725 483920. ANNUAL. O 1E+86 9E+86 9792899 1542976554 Dm Eveiale Gis ere @ ele GWe = 6c a eG ele eee & FUEL OIL CONSUMPTION DISPLACED JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC ANNUAL 27320-2762) 1733') “1125 «627 4208 6 6 6 382 2678 2979 15,438 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 1 CONCEPT 2A WASTE HEAT UTILIZATION SIMULATION WORK SHEET. seeeeesssaseceresessecessseesssseesecesess222 Location: GLENNALLEN Date: December 26, 1989 Heat rate: 2730 Btu/kwh produced System loss: 625,006 Btu/hour (FOR ALL SYSTEMS CURRENTLY CONNECTED) Total generation: 18,716,844 kwh/year . ANNUAL Local degree days 1784 1846 2089 1418 944 603 263 356 811 1854 «1787 2094 15,049 Assumed diurnal heat Power plant monthly generation: i demand variation: Smeemmeunrnnecnionien JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC CHECKSUM Fraction:8.13569 8.12496 8.12378 6.21736 6.6826 6.8455 6.6088 6.0623 6 6.0158 6.0897 8.15336 1 Winter Summer Hour Kwh: 1454288 1339208 1325688 2329428 885260 488208 94608 25084 6 169408 962208 1643608 10,716,844 Diurnal 8.0494 9.0494 1 variation 8.038 8.058 6.038 0.038 6.045 0.045 6.045 0.045 6.045 0.045 0.038 0.038 6.0477 6.0477 2 9.036 8.056 0.036 0.036 0.040 0.040 6.040 0.040 6.040 6.046 0.036 0.036 0.0460 0.0460 3 6.054 8.034 6.034 8.034 6.036 6.036 6.036 0.036 6.036 6.036 0.034 6.034 9.0443 6.0443 4 0.034 6.034 6.034 6.034 6.035 6.035 6.035 6.635 6.035 6.035 6.034 6.034 8.0428 9.0428 5 6.035 6.033 6.033 6.033 6.035 8.035 8.055 0.035 8.035 8.055 6.033 0.033 0.0414 6.0414 6 6.034 9.034 8.034 0.034 6.038 6.038 6.038 0.038 0.038 9.038 6.034 0.034 6.0401 6.0401 7 6.038 8.038 8.058 8.058 0.038 6.038 6.038 9.038 6.038 6.038 0.038 0.038 6.0598 9.0398 8 6.042 8.042 8.042 0.042 0.040 0.040 0.040 0.040 0.040 6.040 0.042 0.042 6.0381 6.0381 9 6.042 8.042 6.042 0.042 0.045 6.045 8.045 0.045 06.045 0.045 6.042 0.042 9.0374 8.0374 18 9.047 8.047 6.047 6.047 6.047 6.047 6.047 0.047 6.047 6.047 0.047 0.047 6.0370 0.0370 1 6.048 0.048 0.048 0.048 6.040 0.040 6.040 0.040 6.040 0.040 0.048 0.048 6.0367 6.0367 12 9.047 8.047 6.047 6.047 6.048 6.048 6.048 0.048 6.048 6.048 0.047 6.047 9.0367 6.0367 13 6.045 6.045 0.045 6.045 0.050 6.050 8.050 0.056 0.050 8.050 0.045 0.045 6.0376 6.0370 14 6.047 8.047 6.047 6.047 6.052 6.052 6.052 0.052 6.052 8.052 0.047 0.047 6.0374 6.0374 15 8.048 6.048 6.048 6.048 6.050 6.050 0.058 0.058 6.050 8.058 0.048 6.048 6.0381 98.0381 16 0.048 8.048 6.048 0.048 0.050 6.050 0.050 0.050 6.050 0.058 0.048 0.048 6.0390 6.0390 17 8.049 8.049 6.049 8.049 6.045 6.045 6.045 0.045 0.045 6.045 0.049 0.049 0.0401 6.0401 18 0.046 0.046 6.046 0.046 6.047 6.047 8.047 0.047 0.047 0.047 0.046 0.046 6.0414 6.0414 19 6.043 8.043 8.043 8.043 6.058 0.050 6.050 6.050 0.058 6.050 0.043 0.043 6.0428 6.0428 28 0.058 8.038 6.038 6.038 6.045 8.045 0.045 0.045 6.045 0.045 0.038 0.038 0.0443 0.0443 21 8.058 8.038 6.038 6.038 6.041 6.041 6.041 6.041 6.041 0.041 6.038 6.038 6.0460 6.0460 22 6.041 8.041 6.041 6.041 6.041 6.041 6.041 6.041 6.041 8.041 0.041 6.041 0.0477 6.0477 23 6.045 8.045 0.045 6.045 6.041 6.041 6.041 0.041 8.041 6.041 8.045 0.045 9.0494 8.0494 24 6.040 8.046 8.040 8.040 0.043 6.043 6.043 0.043 0.043 6.043 0.040 0.040 Building use per month, gallons of fuel oil BUILDING 1A - APARTMENT BUILDING 1186 1208 713 516 372 276 248 341 630 766 «1058 1382 8,576 BUILDING 1B - POST OFFICE 15521562, 1828 615 255 = 158 38 % 3186 982 1626 1677 9,768 BUILDING 2A - OLD SCHOOL 4483 = 3600) = 31912163 1387 6 6 6 1394 2419 3635 4427 26,699 BUILDING 2B - NEW SCHOOL 6 6 a 8 6 8 4 6 6 8 8 6 g BUILDING 2B - WEIR BUILDING GYM 6 6 6 a a 8 6 a 6 6 a 6 a BUILDING 6 8 a 6 6 8 6 4 6 6 6 8 6 4 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION BUILDING 7 BUILDING 8 BUILDING 9 PAGE 2 7215 = 6362 4924 «= 3288 2014 Heat available per hour by gonth JAN FEB MAR APR 1 4334194 3942015 3895968 7318919 2 4873184 3781646 3657966 6900818 3 3812174 3461276 3420623 6482717 4 3812174 3461276 3426823 6482717 5 3681669 3341892 3301052 6273666 6 3812174 3461276 3420023 6482717 7 4334194 3942815 3895988 7318919 8 4856215 4422753 4371793 8155121 9 4856215 4422753 4371793 8155121 18 5588741 5823676 4966650 9200374 11 5639246 5143861 5885621 9409424 12 5588741 5823676 4966658 9200374 13 5247738 4783367 4728787 8782273 14 5508741 5823676 4966658 9208374 15 5639246 5143861 5885621 9489424 16 5639246 5143861 5885621 9409424 17 5769751 5264846 5284592 9618475 18 5378235 4985492 4847678 8991323 19 4986728 4542938 4498765 8364172 20 4334194 3942015 3895988 7318919 21 4334194 3942815 3895988 7318919 22 47257168 4382569 4252822 7946871 23 5247738 4783387 4728767 8782273 24 4595205 4182384 4133851 7737828 1E+O8 = 1E+08 = 1E+08 = 2E+08 Heat demand by hour by month JAN FEB MAR APR 1 1172834 1833469 799874. 534116. 2 1138958 997243. 771836. 515393. 3 1898633 961692. 744321. 497820. 4 1051831 927477. 717848. 479337. 5 1015269 895238. 692887. 462675. 6 981627. 865573. 669928. 447344. 7 951532. 839836. 649389. 433629. 8 925544. 816121. 631653. 421786. 9 984148. 797254. 617851. 412036. 18 887742. 782788. 605855. 404559. 11 876632. 772992. 598273. 399496. 12 871825. 768047. 594446. 396941. 13 871025. 768047. 594446. 396941. 14 876632. 772992. 598273. 399496. MAY SE+O6 SE+O6 420 JUN 1E+06 1E+06 2E+86 952261 28+06 908448 2E+66 908448 2E+06 2E+06 SE+O6 SE+O6 SE+06 3E+06 SE+O6 SE+O6 4E+06 SE+O6 SE+O6 3E+06 3E+06 SE+06 SE+O6 SE+O6 3E+06 SE+O6 3E+06 TE+87 MAY 1E+86 1E+06 1E+06 1E+06 1E+06 1E+06 1E+O6 2E+06 2E+06 2E+06 2E+06 1E+86 1E+06 2E+06 1E+06 1E+06 1E+06 1E+O6 1E+86 3E+87 JUN 327162 68226. 315694 65834. 304440 63488. 293689 61229. 283403 59100. 274812 57142. 265611 55390. 258357 53877. 252384 52632. 247885 51677. 244703 51038. 243138 58704. 243138 58704. 244703 51038. Eheim res lea] ee ele mle we teres ech enhee) m erento eee JUL 45159. 43576. 42823. 40527. 39119, 37822. 36663. 35662. 34837. 34205. 33777. 33561. 33561. 33777. 416 ea Wansstmt em [a Uewsd me elfen tuo ta ences exe cence el ew fem fey copter AUG 67576. 65287. 62883. 60646. 58538. 56598. 54863. 53364. 52131. 51185. 50544. 50221. 50221. 50544. 2334 «= 4081 8 59115. 6 6 59115. 6 89528. 6 6 6 104723 8 135128 6 165533 6 135128 8 135128 6 59115. 6 89520. 6 135128 6 59115. 6 28710. 6 1E+06 SEP OCT 379144 662934 365854 639696 352811 616891 348259 594944 328432 574263 317549 555235 387813 538212 299406 523513 292485 511411 287178 562131 283584 495847 281778 492675 281778 492675 283584 495847 6305 = 7406 NOV-DEC 3E+06 4980097 2E+86 4685092 2E+06 4396087 2E+06 4390087 2E+06 4242584 2E+86 4390087 3E+06 4980097 3E+06 5570107 3E+06 5570107 SE+06 6307620 4E+06 6455123 3E+06 6307620 3E+O6 6012615 3E+O6 6307620 4E+06 6455123 4E+86 6455123 4E+06 6602625 3E+O6 6166117 3E+O6 5717610 3E+06 4980097 3E+86 4980097 SE+86 5422605 3E+86 6012615 3E+06 5275102 TE+O7 «= 1E+08 NOV-DEC 1E+06 12030608 988308 1160898 953075 1119505 919168 1879676 887217 1042146 857818 1067613 831519 976721. 888809 950046. 798111 928683. 775775 911243. 766066 899839. 761166 894084. 761166 894884. 766066 899839. CONCEPT 2A 45,243 ANNUAL, 2.504E+10 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION 15 887742. 782788. 605855. 16 964148. 797254. 617051. 17 925544. 816121. 631653. 18 951532. 839836. 649389. 19 981627. 865573. 669928. 26 1815269 895238. 692888. 21 1851831 927478. 717840. 22 1898633 961692. 744321. 23 11308951 997243. 771836. 24 1172834 1833469 799874. 2E+87 «= 2E+07 «= 2E+87 Heat delivered by hour JAN FEB MAR 1 1172834 1833469 799874. 2 1138958 997243. 771836. 3 1898633 961692. 744321. 4 1851831 927477. 717848. 5 1815269 895238. 692887. 6 981627. 865573. 669928. 7 951532. 839836. 649389. 8 925544. 816121. 631653. 9 984148. 797254. 617051. 16 887742. 782788. 605855. 11 876632. 772992. 598273. 12 871825. 768047. 594446. 13 871825. 768047. 594446. 14 876632. 772992. 598273. 15 887742. 782788. 605855. 16 984148. 797254. 617851. 17 925544. 816121. 631653. 18 951532. 839836. 649389. 19 981627. 865573. 669928. 26 1815269 895238. 692888. 21 1851831 927478. 717848. 22 1898633 961692. 744321. 23 1138951 997243. 771836. 24 1172834 1833469 799874. 2E+87 «= 2E+07 = 2E+017 FUEL OIL CONSUMPTION DI: JAN FEB MAR 7215 = 6362, 4924 PAGE 3 404559. 412036. 421786. 433629. 447344. 462675. 479337. 497628. 515393. 534116. 247885 51677. 252384 52632. 258357 53877. 265611 55398. 274812 57142. 283483 59108. 293689 61229. 304448 63488. 315694 65834. 327162 68226. 34205. 51185. 34837. 52131. 35662. 53364. 36663. 54863. 37822. 56598. 39119. 58538. 40527. 60646. 42823. 62883. 43576. 65287. 45159. 67576. 1E+87 =7E+86 1E+86 913872 1E+06 by month APR 534116. 515393. 497628. 479337. 462675. 447344, 433629. 421786. 412036. 484559. 399496. 396941. 396941. 399496. 404559. 412036. 421786. 433629. 447344. 462675. 479337. 497828. 515393. 534116. 1E+O7 7E+06 1E+06 SPLACED APR 3288 MAY = JUN 327162 68226. 315694 65834. 304446 63488. 293689 61229. 283483 59100. 274812 57142. 265611 55398. 258357 53877. 252384 52632. 247805 51677. 244703 51838. 243138 56764. 243138 50704. 244763 51038. 247885 51677. 252384 52632. 258357 53877. 265611 55396. 274812 57142. 283403 59108. 293689 61229. 304448 63488. 315694 65834. 327162 68226. MAY JUN 2014 428 Slolalalalalelalsiclalata alalaleleletatelalarate ts Sialtalalalaliolalalalalalalalalalajfalalalelwlulalat JUL = AUG 6 6 287178 562131 775775 911243. 292485 511411 798111 928683. 299486 523513 888809 950046. 387813 538212 831519 976721. 317549 555235 857818 1687613 328432 574264 887217 1042146 348259 594944 919168 1879676 352811 616891 953075 1119585 365854 639696 988308 1160890 379144 662934 1E+86 1203060 SE+86 1E+87 2E+07 © 2E+07 ocT NOV DEC 59115. 1E+86 1203060 6 988368 1160898 ® 953875 1119505 6 919168 1879676 6 857818 1007613 6 831519 976721. 6 888809 950046. 6 59115. 798111 928883. 6 89528. 775775 911243. 6 ® 766066 899839. 6 184723 761166 894684. 8 135128 761166 894884. 8 165533 766066 899839. 6 135128 775775 911243. 6 135128 798111 928083. 8 59115. 888809 950046. 6 89528. 831519 976721. 8 135128 857818 1687613 6 59115. 887217 1642146 4 6 919168 1679676 6 8 953875 1119585 6 ® 988308 1160890 6 28710. 1E+66 1203060 6 1E+06 2E+07 2E+07 mlalelalalavarats SEP OCT NOV DEC 6 382 6305 7406 CONCEPT 2A ANNUAL 4504300000 6 887217 1042146 - ANNUAL 3831576554 ANNUAL 38,316 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 1 CONCEPT 2B- WASTE HEAT UTILIZATION SIMULATION WORK SHEET. Location: GLENNALLEN Date: December 26, 1989 Heat rate: 2738 3tu/kwh produced System loss: 625,008 Stu/hour (FOR ALL SYSTEMS CURRENTLY CONNECTED) Total generation: 16,716,844 kwh/year . ANNUAL, Local degree days 1784 1846 2089 1418 944 603 263 (356 811 1854-1787 2094 15,049 Assumed diurnal heat Power plant monthly generation: demand variation: ac atecaeeeaiiaeammaaiae JAN FEB MAR APR MAY JUN JUL AUG SEP ocT = NOV DEC CHECKSUM Fraction:8.13569 6.12496 6.12376 8.21736 6.0826 0.0455 0.0088 6.6023 6 8.0158 6.0897 8.15336 1 Winter Summer Hour Kwh: 14542008 1339208 1325688 2329428 885260 488200 94608 25084 8 169408 962208 1643600 10,776,944 Diurnal 0.0494 0.0494 1 variation 9.038 9.058 6.038 6.038 6.045 6.045 6.045 6.045 0.045 6.045 0.038 6.038 0.0477 6.0477 2 0.036 6.036 0.036 06.036 0.040 0.040 0.040 6.040 6.040 0.040 0.036 0.036 6.0460 0.0460 3 9.034 6.034 6.034 6.034 0.036 0.036 0.036 0.036 0.036 0.036 6.034 9.034 0.0443 0.0443 4 9.034 0.034 0.034 0.034 0.035 0.035 0.035 6.035 0.035 8.035 0.034 0.034 6.0428 9.0428 5 9.033 8.033 0.033 0.033 0.035 0.035 0.035 6.035 8.035 6.035 0.033 0.033 9.0414 8.0414 6 6.034 0.034 0.034 0.034 0.038 6.038 0.038 0.038 0.038 8.038 0.034 6.034 0.0401 0.0401 7 0.038 6.038 06.038 06.038 0.038 0.038 6.038 6.038 9.038 6.038 0.038 0.038 6.0398 6.0398 © 8 0.042 6.042 6.042 0.042 0.040 0.040 0.040 6.040 6.040 6.040 0.042 0.042 8.9381 9.0381 9 0.042 6.042 8.042 6.042 0.045 0.045 6.045 6.045 6.045 0.045 0.042 0.042 0.0374 0.0374 10 0.047 6.047 6.047 0.047 0.047 6.047 6.047 0.047 6.047 6.047 6.047 0.047 6.0376 0.0376 "1 6.048 6.048 0.048 0.048 0.040 0.040 0.046 6.040 0.040 6.040 0.048 0.048 9.0367 6.0367 12 0.047 0.047 0.047 0.047 0.048 0.048 6.048 0.048 6.048 6.048 0.047 0.047 0.0367 6.0367 13 6.045 6.045 6.045 6.045 6.050 0.050 0.050 6.050 6.050 6.050 6.045 9.045 0.0378 0.0376 14 0.047 6.047 0.047 8.047 0.052 6.052 6.052 6.052 6.052 6.052 0.047 0.047 6.0374 0.0374 15 6.048 8.048 8.048 8.048 0.050 6.050 6.050 6.050 0.050 6.050 0.048 6.048 6.0381 6.0381 16 0.048 6.048 0.048 0.048 0.050 0.050 0.050 0.050 0.050 0.050 0.048 0.048 6.0398 0.0398 17 0.049 6.049 6.049 0.049 0.045 0.045 6.045 6.045 6.045 0.045 0.049 0.049 6.0401 0.0401 18 0.046 8.046 0.046 6.046 0.047 0.047 0.047 0.047 6.047 0.047 0.046 0.046 6.0414 6.0414 19 0.043 8.043 0.043 0.043 0.050 0.050 0.050 6.050 8.058 9.050 0.043 0.043 0.0428 8.0428 26 8.038 8.038 0.038 8.038 8.045 0.045 6.045 6.045 6.045 0.045 0.038 0.038 8.0443 0.0443 2 6.038 6.0358 6.038 6.038 0.041 6.041 0.041 6.041 06.041 6.041 6.038 9.038 0.0468 0.0468 22 0.041 0.041 0.041 8.041 0.041 6.041 0.041 6.041 0.041 0.041 0.041 6.041 0.0477 6.0477 23 0.045 0.045 0.045 0.045 0.041 0.041 8.041 0.041 0.041 0.041 0.045 0.045 0.0494 6.0494 24 0.040 0.040 0.040 6.040 6.043 0.043 0.043 0.043 0.043 6.043 6.040 0.040 Building use per month, gallons of fuel oil BUILDING 1A - APARTMENT BUILDING 1188 1208 713 518 372 278 248 341 638 768 81058 1302 8,576 BUILDING 1B - POST OFFICE 1552 1562 1028 615 255 158 38 6 310 982 ©1628 1677 9,768 BUILDING 2A - OLD SCHOOL 4483 3600 3191 2163 = 1387 a a 6 1394 2419 3635 4427 26 ,699 BUILDING 2B - NEW SCHOOL 2423 1912 1675 1688 631 6 6 6 635 «1228 «=—:1932 2398 13,906 BUILDING 2B - WEIR BUILDING GYM 8 a a 8 6 6 a a 6 6 a a 0 BUILDING 6 8 6 8 8 8 6 4 8 6 6 8 a a GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 2 BUILDING 7 4 a a 2 6 4 a a 6 6 6 6 a BUILDING 8 a a 6 6 6 0 a a 6 8 6 a g BUILDING 9 6 a 0 6 a 4 6 6 8 a a 6 a 6 6 8 4 4 6 6 6 6 4 4 6 a TOTAL 9638 8274 6599 4368 «2645 420 278 416 2969 5389 8237 9796 58,949 Heat available per hour by month JAN FEB MAR APR MAY JUN AUG SEP ocT NOV DEC 1 4334194 3942815 3895908 7318919 3E+06 1E+06 659115. 3E+66 4980097 2 4073184 3701646 3657966 6900818 SE+06 1E+06 6 6 2E+06 4685892 3 3812174 3461276 3426823 6482717 2E+66 952261 6 8 2E+86 4396087 4 3812174 3461276 3420823 6482717 2E+66 908448 6 8 2E+86 4390887 5 3681669 3341892 3301052 6273666 2E+06 988448 4 8 2E+86 4242584 6 3812174 3461276 3420023 6482717 2E+06 1E+06 a 8 2E+06 4390087 7 4334194 3942015 3895908 7318919 2E+06 1E+06 a 0 3E+06 4980097 8 4856215 4422753 4371793 8155121 SE+06 1E+06 a B 3E+06 5570107 9 4856215 4422753 4371793 8155121 SE+86 1E+06 18 5508741 5023676 4966658 9200574 SE+06 1E+06 11 5639246 5143861 5085621 9409424 SE+06 1E+06 12 5508741 5823676 4966650 9200574 SE+06 1E+06 13 5247730 4783307 4728787 8782273 3E+06 2E+06 14 5588741 5823676 4966658 9200374 4E+86 2E+06 15 5639246 5143861 5885621 9409424 3E+06 2E+06 16 5639246 5143861 5885621 9409424 3E+06 2E+06 17 5769751 5264046 5284592 9618475 3E+66 1E+06 18 5378235 4983492 4847678 8991525 3E+06 1E+06 19 4986726 4542938 4498765 8364172 3E+06 2E+06 28 4334194 3942015 3895988 7318919 3E+86 1E+06 21 4334194 3942815 3895988 7318919 SE+06 1E+86 22 4725718 4302569 4252822 7946071 3E+06 1E+06 23 5247730 4783307 4728707 8782273 3E+O6 1E+06 24 4595205 4182384 4133851 7737020 3E+06 1E+06 1E+88 «= 1E+88 «= 1E+88 «=. 2E+08 «= 7E+07 = SE+O7 659115. 3E+06 5576187 6 89520. 3E+66 6307620 6 8 4E+86 6455123 6 104723 3E+86 6307628 0 135128 3E+66 6012615 ® 165533 3E+06 6307628 ® 135128 4E+86 6455123 6 135128 4E+86 6455123 659115. 4E+86 6602625 8 89520. 3E+86 6160117 6 135128 3E+86 5717618 859115. 3E+86 4980097 8 6 3E+06 4980097 8 6 3E+06 5422605 6 6 3E+06 6012615 ® 28710. 3E+06 5275102 ANNUAL 6 1E+06 7E+87 1E+88 2.504E+10 Ea kb@eee heme eh eee eee eee geek Heat demand by hour by month JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 1565636 1344062 1071968 709555. 429664 68226. 45159. 67576. 482296 862415 1E+#6 1591302 1518756 1296949 1034393 684683. 414683 65834. 43576. 65287. 465398 832185 1E+86 1535522 1456898 1250713 997517. 660275. 399823 63488. 42023. 62883. 448799 802518 1E+#6 1480782 1405866 1286217 962028. 636784. 385598 61229. 40527. 60646. 432832 773967 1E+86 1428100 1356225 1164288 928588. 614649. 372195 59188. 39119. 58538. 417787 747063 1E+06 1378458 1311285 1125788 897818. 594282. 359862 57142. 37822. 56598. 403943 722389 1E+#6 1332781 1271883 1891195 876292. 576062. 348829 553908. 36663. 54863. 391559 700164 1E+06 1291921 1236368 1861393 846523. 560329. 339382 53877. 35662. 53364. 380865 681041 1E+86 1256636 1207787 1036857 826954. 547376. 331458 52632. 34837. 52131. 372068 665298 1E+06 1227587 1185871 1818843 811949. 537444. 325444 51677. 34205. 51185. 365309 653226 1E+06 1205312 1171838 1805302 801788. 530718. 321371 51038. 33777. 50544. 360737 645051 1E+86 1190228 1163548 998872. 796659. 527323. 319315 50704. 33561. 58221. 358438 648925 994405 1182615 1163548 998872. 796659. 527323. 319315 50704. 33561. 58221. 358438 648925 994405 1182615 1171838 1805382 801788. 538718. 321371 51038. 33777. 50544. 360737 645051 1E+86 1198228 oryranaueun — FUSzZSwo GLENNALLEN WASTE HEAT RECOVERY ESTIMATION 15 16 RPRRBNRRS COryranueun = Sartrannzrunsta RSSB28B PAGE 3 1185871 1818843 811949. 537444. 325444 51677. 34205. 51185. 365309 653226 iE+06 1287787 1836857 826954. 547376. 331458 52632. 34837. 52131. 372068 665298 1E+66 1236368 1861393 846523. 560329. 339382 53877. 35662. 53364. 380865 681041 1E+06 1271883 1891195 876292. 576862. 348829 55398. 36663. 54863. 391559 706164 1E+06 1311285 1125708 897818. 594282. 359862 57142. 37822. 56598. 483943 722389 1E+06 1356225 1164288 928588. 614649. 372195 59108. 39119. 58538. 417787 747063 1E+06 1485066 1206217 962628. 636784. 385598 61229. 40527. 68646. 432832 773967 1£+06 1456898 1258713 997517. 668275. 399823 63488. 42823. 62883. 448799 882518 1E+06 1518756 1296949 1834393 684683. 414683 65834. 43576. 65207. 465390 832185 1E+06 1565636 1344062 1871968 709555. 429664 68226. 45159. 67576. 482296 862415 1E+06 3E+O7 «6 SE+07 «=. 2E+07 = 1E+87 SEG «= 1E+86 913872 1E+06 1E+87 2E+07 3E+07 Heat delivered by hour by month JAN FEB MAR APR MAY JUN JUL AUG) =6SEP) OCT) = NOV 1565636 1344062 1071968 709555. 429664 68226. 4 6 859115. 1E+06 1518756 1296949 1834393 684683. 414603 65834. 6 6 6 8 1E+86 1456898 1258713 997517. 668275. 399823 63488. 6 6 6 6 1E+66 1405866 1286217 962828. 636784. 385598 61229. 6 6 6 6 1E+06 1356225 1164288 928588. 614649. 372195 59108. 6 6 6 6 1E+86 1311285 1125788 897818. 594282. 359862 57142. 8 6 6 6 1E+86 1271883 1891195 878292. 576062. 348829 55398. 4 4 a 8 1E+06 1236368 1861393 846523. 560329. 339382 53877. 6 6 6 6 1E+66 1287787 1836857 826954. 547376. 331458 52632. 6 6 659115. 1E+06 1185871 1818843 811949. 537444. 325444 51677. 4 6 6 89528. 1E+06 1171838 1605382 881788. 538718. 321371 51030. 6 6 6 6 1E+06 1163548 998872. 796659. 527323. 319315 56764. 6 6 6 184723 994405 1163548 998872. 796659. 527323. 319315 58764. 6 6 6 135128 994405 1171838 1685382 881788. 530718. 321371 51638. 6 6 ® 165533 1E+06 1185871 1818843 811949. 537444. 325444 51677. 8 6 6 135128 1E+06 1287787 1836857 826954. 547376. 331458 52632. 6 6 6 135128 1E+66 1236368 1861393 846523. 560329. 339302 53877. 6 6 859115. 1E+06 1271883 1891195 876292. 576062. 348829 55390. 6 8 6 89520. 1E+66 1311285 1125768 897818. 594282. 359862 57142. 6 6 6 135128 1E+06 1356225 1164288 928588. 614649. 372195 59160. 8 8 859115. 1E+06 1405866 1286217 962828. 636784. 385598 61229. 6 6 6 6 1E+06 1456898 1258713 997517. 668275. 399823 63488. 6 6 6 6 1E+06 1518756 1296949 1034393 684683. 414603 65834. 6 6 6 B 1E+86 1565636 1344862-1071968 789555. 429664 68226. 6 6 6 28710. 1E+06 3E+O7 «= SE+07 «= 2E+07 = 1E+07 -SE+06 1E+06 6 6 8 1E+06 3E+07 FUEL OIL CONSUMPTION DISPLACED JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV 9638 8274 6599 4368 2645 428 8 6 6 382 8237 1205312 1227587 1256636 1291921 1332782 1378458 1428108 1488782 1535522 1591382 3E+87 DEC 1591382 1535522 1488782 1428188 1378458 1332781 1291921 1256636 1227587 1285312 1198228 1182615 1182615 1198228 1205312 1227587 1256636 1291921 1332782 1378458 1428108 1488782 1535522 1591382 3E+87 DEC 9796 CONCEPT 28- ANNUAL 5894900000 ANNUAL 5035876554 ANNUAL 58,359 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION PAGE 1 CONCEPT 23+ WASTE HEAT UTILIZATION SIMULATION WORK SHEET. Location: GLENNALLEN Date: December 26, 1989 Heat rate: 2738 Btu/kwh produced System loss: 625,000 Btu/hour (FOR ALL SYSTEMS CURRENTLY CONNECTED) Total generation: 18,716,844 kwh/year ANNUAL Local degree days 1784 1846 2089 1418 944 603 263-356 811 1054 «1787 2094 15,049 Assumed diurnal heat Power plant monthly generation: demand variation: See JAN FEB MAR APR MAY JUN JUL AUG SEP ocT Nov DEC CHECKSUM Fraction:8.13569 8.12496 8.12378 6.21736 6.6826 8.0455 8.6088 8.0823 6 8.0158 8.0897 8.15336 1 Winter Summer Hour Kwh: 1454208 1339208 1325688 2329428 885260 488200 94608 25084 B 169408 962200 1643600 18,716,944 Diurnal 9.0494 8.0494 1 variation 6.038 6.038 08.038 08.038 0.045 0.045 0.045 0.045 0.045 6.045 0.038 0.038 6.0477 6.0477 2 0.036 0.036 0.036 0.036 0.040 0.040 0.040 0.040 6.040 0.040 0.036 0.036 6.0460 0.0460 3 0.034 0.034 6.034 6.034 0.036 0.036 0.036 6.036 8.036 0.036 0.034 0.034 9.0443 8.0443 4 6.034 0.034 0.034 0.034 0.035 0.035 8.035 0.055 0.035 8.035 0.034 0.034 6.0428 6.0428 2 6.033 6.033 6.033 6.033 6.035 0.035 6.035 06.035 6.035 0.035 6.033 0.033 9.0414 8.0414 6 6.034 6.034 0.034 6.034 6.038 6.038 0.038 0.038 8.038 8.038 0.034 6.034 0.0401 6.0401 7 6.038 6.038 0.038 6.038 6.038 0.038 6.038 6.038 6.038 6.038 0.038 06.038 6.0398 6.0398 8 6.042 6.042 6.042 6.042 6.040 0.040 6.040 0.040 0.040 0.040 6.042 0.042 0.0381 0.0381 9 6.042 6.042 6.042 0.042 0.045 0.045 0.045 0.045 6.045 0.045 0.042 06.042 6.0374 0.0374 18 6.047 6.047 0.047 06.047 6.047 6.047 0.047 0.047 6.047 0.047 0.047 6.047 6.0378 6.0378 " 6.048 0.048 0.048 6.048 0.040 0.040 0.040 0.040 6.040 6.040 0.048 06.048 9.0367 9.0367 12 0.047 6.047 0.047 6.047 6.048 0.048 0.048 6.048 0.048 0.048 0.047 6.047 6.0367 6.0367 13 6.045 6.045 6.045 9.045 8.050 0.050 6.050 0.050 6.056 6.050 0.045 06.045 6.0378 6.0378 14 6.047 6.047 6.047 6.047 6.052 6.052 6.052 0.052 6.052 6.052 0.047 06.047 6.0374 6.0374 15 6.048 6.048 6.048 0.048 6.050 0.050 0.050 6.050 0.050 0.050 0.048 0.048 6.0381 6.0381 16 6.048 6.048 6.048 6.048 8.050 0.050 6.050 6.050 6.050 0.050 0.048 0.048 6.0390 6.0398 17 8.049 8.049 8.049 8.049 8.045 6.045 0.045 8.045 0.045 0.045 6.049 0.049 6.0401 6.0401 18 6.046 6.046 0.046 0.046 0.047 0.047 0.047 6.047 6.047 6.047 0.046 0.046 6.0414 6.0414 19 0.043 0.043 6.043 0.043 6.050 6.058 0.050 0.050 0.050 0.050 0.043 98.043 6.0428 6.0428 20 9.038 8.038 0.038 6.038 6.045 0.045 0.045 6.045 6.045 0.045 6.038 9.038 0.0443 6.0443 21 6.038 6.038 0.058 0.038 0.041 6.041 6.041 6.041 6.041 0.041 0.038 0.038 0.0466 6.6468 22 6.041 6.041 6.041 6.041 6.041 6.041 6.041 6.041 6.041 6.041 0.041 6.041 6.0477 6.0477 23 6.045 6.045 0.045 6.045 0.041 0.041 0.041 0.041 6.041 0.041 6.045 6.045 6.0494 6.0494 24 6.040 0.040 6.040 8.040 0.043 0.043 6.043 6.043 0.043 0.043 0.040 0.040 Building use per month, gallons of fuel oil BUILDING 1A - APARTMENT BUILDING 1188 12066 713 510 372 278 248 341 630 766 «1058 1382 8,576 BUILDING 1B - POST OFFICE 1552 1562 1620 615 255 158 B) ry 310 902 «1620 1677 9,768 BUILDING 2A - OLD SCHOOL 4483 3600 =—-3191 2163 = 1387 6 a 6 1394 2419 3635 4427 26,699 BUILDING 2B - NEW SCHOOL 2423 1912 1675 1088 631 8 6 8 635 1228 1932 2390 13,986 BUILDING 2B - WEIR BUILDING GYM 1407 1138 10082 679 436 4 6 6 438 7591141 1398 8,382 BUILDING 6 a 6 8 a a 6 8 8 6 6 4 4 8 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION BUILDING 7 BUILDING 8 BUILDING 9 PAGE 2 eoaan aoan ese aa Bases 11045 94847681 5847 3081 Heat available per hour by month JAN FEB MAR APR 1 4334194 3942815 3895988 7318919 2 4073184 3761646 3657966 6960818 3 3812174 3461276 3420623 6482717 4 3812174 3461276 3428623 6482717 5 3681669 3341892 3301852 6273666 6 3812174 3461276 3426623 6482717 7 4334194 3942815 3895908 7318919 8 4856215 4422753 4371793 8155121 9 4856215 4422753 4371793 8155121 10 5508741 5823676 4966650 9200374 11 5639246 5143861 5085621 9409424 12 5508741 5823676 4966656 9200374 13 5247738 4783307 4728767 8782273 14 5588741 5023676 4966650 9200374 15 5639246 5143861 5885621 9409424 16 5639246 5143861 5085621 9409424 17 5769751 5264046 5204592 9618475 18 5378235 4903492 4847678 8991323 19 4986728 4542938 4490765 8364172 26 4334194 3942015 3895988 7318919 21 4334194 3942815 3895988 7318919 22 4725718 4382569 4252822 7946071 23 5247738 4783307 4728787 8782273 24 4595205 4182384 4133851 7737020 1E+88 = 61E+88 = 1E+88 =. 2E+08 Heat demand by hour by month JAN FEB MAR APR 1794194 1527624 1234737 819855. 1731303 1474876 1191456 791117. 1669583 1421526 1148981 762914. 1618184 1378953 1188104 735771. 1554213 1323297 1069586 710196. 1582713 1279448 1034144 686662. 1456642 1248223 10062438 665610. 1416859 1206358 975860. 647432. 1384185 1178463 952528. 632465. 18 1358998 1157888 935236. 620989. 11 1341983 1142599 923532. 613217. 12 1333399 1135291 917625. 689295. 13 1333399 1135291 917625. 609295. 14 1341983 1142599 923532. 613217. COrnnuneun = MAY 3E+O6 3E+06 420 JUN 1E+O6 1E+86 2E+86 952261 2E+06 908448 2E+06 908448 2E+06 2E+06 SE+O6 3E+06 3E+O6 3E+06 3E+06 SE+O6 4E+06 3E+06 SE+O6 3E+06 3E+O6 3E+O6 3E+06 3E+06 3E+O6 3E+06 3E+O6 TE+O7 MAY 1E+06 1E+06 1E+06 1E+06 1E+06 1E+06 1E+06 2E+06 2E+06 2E+06 2E+06 1E+06 1E+06 2E+06 1E+06 1E+06 1E+06 1E+06 1E+06 3E+O7 JUN 500498 68226. 482946 65834. 465729 63488. 449168 61229. 433547 59100. 419181 57142. 486329 55390. 395232 53877. 386095 52632. 379898 51677. 374345 51030. 371951 50764. 371951 50704. 374345 51030. 278 cada cece senna cc ence e manne le JUL 45159. 43576, 42023. 40527. 39119. 37822. 36663. 35662. 34837. 34205. 33777. 33561. 33561. 33777. 416 | et le tls deacetylase wasted! cn, a | AUG 67576. 65207. 62883. 60646. 58538. 56598. 54863. 53364. 52131. 51185. 50544. 56221. 50221. 50544. eaaas saan 3407 ©6068 Bea Saaoan- 89528. a 104723 135128 165533 135128 8 135128 8 59115. 6 89520. ® 135128 6 59115. a a 4 a 6 4 @ 59115. 8 8 4 4 8 8 ® 28710. B 1E+06 SEP OCT 553446 985710 534047 951158 515008 917250 496686 884617 479421 853867 463534 825573 449323 800263 437052 778406 426948 760412 419201 746614 413955 737278 411307 732554 411387 732554 413955 737278 6 8 a a 6 8 a 4 9378 =—11186 NOV-DEC 3E+06 4980097 2E+06 4685092 2E+86 4398087 2E+06 4390087 2E+06 4242584 2E+06 4390087 3E+06 4980097 3E+06 5570107 3E+06 5570107 BE+O6 6307620 4E+06 6455123 3E+O6 6307628 3E+06 6012615 3E+06 6307620 4E+06 6455123 4E+06 6455123 4E+06 6602625 3E+06 6160117 3E+06 5717618 3E+06 4980097 3E+06 4980097 3E+86 5422605 3E+O6 6012615 BE+O6 5275102 TE+O7 «= 1E+08 NOV-DEC 2E+06 1817699 1E+86 1753405 1E+86 1698897 1E+06 1630748 1E+06 1574054 1E+86 1521896 1E+06 1475237 1E+86 1434946 1E+06 1481775 1E+06 1376339 1E+86 1359115 1E+86 1350421 1E+06 1350421 1E+86 1359115 CONCEPT 23+ a aan 67,331 ANNUAL 2.504E+10 GLENNALLEN WASTE HEAT RECOVERY ESTIMATION 15 16 17 18 19 21 22 24 woaranuetun = 18 11 12 13 14 15 16 17 18 19 PERRBER PAGE 3 1358991 1157888 935236. 620989. 1384185 1178463 952520. 632465. 1416859 1286358 975061. 647432. 1456642 1248223 1002438 665611. 1582713 1279449 1854144 686663. 1554213 1323297 1869586 710196. 1618184 1378953 1188184 735772. 1669583 1421526 1148981 762914. 1731383 1474876 1191456 791117. 1794195 1527624 1234737 819855. 4E+07 3E+87 2E+87 = 2E+87 Heat delivered by hour by month JAN 1794194 1731303 1669583 1616184 1554213 1582713 1456642 1416859 1384105 1358998 1341983 1333399 1333399 1341983 1358991 1384105 1416859 1456642 1582713 1554213 1610184 1669583 1731383 1794195 4E+07 FEB MAR APR 1527624 1234737 819855. 1474876 1191456 791117. 1421526 1148981 762914. 1378953 1168184 735771. 1323297 1869586 716196. 1279448 1034144 686662. 1248223 1082438 665610. 1286358 975060. 647432. 1178463 952528. 632465. 1157888 935236. 620989. 1142599 923532. 613217. 1135291 917625. 609295. 1135291 917625. 689295. 1142599 923532. 613217. 1157888 935236. 620989. 1178463 952528. 632465. 1286358 975861. 647452. 1248223 1002438 665611. 1279449 1034144 686663. 1323297 1869586 716196. 1378953 1108184 735772. 1421526 1148981 762914. 1474876 1191456 791117. 1527624 1234737 819855. 3E+O7 2E+87 = 2E+87 FUEL OIL CONSUMPTION DISPLACED JAN 11045 FEB 9404 MAR APR 7601 5047 379898 51677. 386095 52652. 395232 53877. 406330 55398. 419181 57142. 433547 59180. 449168 61229. 465729 63488. 482946 65834. 500498 68226. MAY JUN 508498 68226. 482946 65834. 465729 63488. 449168 61229. 433547 59100. 419181 57142. 406329 55398. 395232 53877. 386095 52632. 379898 51677. 374345 51030. 371951 58704. 371951 50704. 374345 51030. 379898 51677. 386095 52632. 395232 53877. 406330 55390. 419181 57142. 433547 59108. 449168 61229. 465729 63488. 482946 65834. 500498 68226. 1E+87 1E+06 MAY JUN 3081 = 428 34205. 34837. 35662. 36663. 37822. 39119, 40527. 42823. 43576. 45159. a ia ee ae ele ee ee oe eee ee el ee ee JUL 6 51185. 52131. 53364. 54863. 56598. 58538. 60646. 62883. 65207. 67576. 1E+87 1E+06 913872 1E+06 AUG 6 a e.etee Bie e Gee Bae wee eS eee ee eee Be 419281 746614 426948 760412 437052 778406 449323 800263 463534 825573 479421 853867 496686 884617 515008 917258 534047 951158 553447 985710 1E+87 2E+07 § § 8 59115. 6 8 59115. 6 89520. 4 6 6 104723 8 135128 8 165533 8 135128 8 135128 6 59115. 6 89520. 6 135128 6 59115. 6 28718. 6 1E+06 SEP OCT 6 382 1E+86 TE+66 1E+06 1E+06 1E+06 1E+06 1E+06 1E+06 1E+06 2E+06 3E+87 2E+06 1E+06 1E+06 1E+86 1E+06 1E+06 1E+86 1E+06 1E+06 1E+86 1E+06 1E+66 1E+06 1E+06 1E+06 1E+86 1E+06 1E+06 1E+6 1E+86 1E+06 1E+66 1E+66 2E+06 3E+O7 9378 1376339 1401775 1434947 1475237 1521896 1574054 1630748 1698897 1753405 1817899 4E+07 DEC 1817899 1753405 1696897 1630748 1574054 1521896 1475237 1434946 1401775 1376339 1359115 1350421 1350421 1359115 1376339 1481775 1434947 1475237 1521896 1574054 1630748 1698897 1753405 1817899 4E+87 DEC 11186 CONCEPT 2B+ ANNUAL, 6733100008 ANNUAL 5754376554 ANNUAL 57,544 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Contact Names The following people were contacted in the field: Dave Bruno, Service Oil and Gas (822-3375) Charles Mason, Principal at Glennallen High School (822-3232) Leland Dischman, Superintendent - Copper River School District (822-3234) Loreen Kramer, Business Manager - Copper Valley School District (822-3234) Jasper Hall, Branch Manager - National Bank of Alaska (822-3214) Elaine Seager, Postmaster - Glennallen Post Office Lowell Highbargin, Power Production - Copper Valley Electric (822-3211) GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Cost Estimates SIMPLE ECONOMIC SUMMARY COST SUMMARY CONCEPT 1A 1 CONCEPT 1B $289,770 CONCEPT 2A $458,120 CONCEPT 2B $647,603 CONCEPT 2A ONLY $338,991 CONCEPT 2B ONLY $528,473 FUEL OIL SAVINGS SUMMARY CONCEPT $0.91 ine $0 i ‘% bee k SAVINGS CONCEPT 1A $6,608 CONCEPT 1B $14,366 CONCEPT 2A $35,443 CONCEPT 2B $52,816 CONCEPT 2A ONLY $21,244 CONCEPT 2B ONLY $38,799 SIMPLE PAYBACK SUMMARY CONCEPT COST SAVING SAVING: PAYBACK CONCEPT 1A $255,399 CONCEPT 1B $289,770 20. ° CONCEPT 2A $458,120 12.9 CONCEPT 2B $647,603 12.3 CONCEPT 2A ONLY $338,991 16.0 CONCEPT 2B ONLY $528,473 13.6 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE FRYER/PRESSLEY ENGINEERING 560 EAST 34TH AVENUE ANCHORAGE, ALASKA Anchorage, Alaska (907) 337-2767 GLENALLEN WASTE HEAT RECOVERY TABLE OF CONTENTS Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. General Requirements Concept 1A Distribution Piping Apt. Building Connection Concept 1B Distribution Piping . . . Post Office Connection Concept 2A Distribution Piping . . . Old School Connection Concept 2B Distribution Piping New School Connection Weir Building Gym Connection Page i BS SSS SSS SSS SSS SS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SSS SS SSS SSS sss Ss SSS Sass sss se SsSS SSS sass SSS SSS SSS SSTqS GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE: SUMMARY OF COSTS Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. 05-Jan-90 SeSsessS ss SSSS SSS SSeS SSS SSS SSS SS SSS SS SSS SS SSS SSS SSS SSS SSS SSS SSH S SSS SS SSS HSH SSS SSS SHS HSS SHH SSS SS SS SHS SS SS SSS SSS SSS SS SS SSS SHS SSSSSS DESCRIPTION ESTIMATED COST OF CONSTRUCTION LINE GENERAL REQUIREMENTS $101,957 POWER PLANT $29,305 CONCEPT 1A DISTRIBUTION PIPING $52,240 APT. BUILDING CONNECTION $12,959 CONCEPT 1B DISTRIBUTION PIPING $65,495 POST OFFICE CONNECTION $13,184 CONCEPT 2A DISTRIBUTION PIPING $113,055 OLD SCHOOL CONNECTION $16,445 CONCEPT 2B DISTRIBUTION PIPING $88,410 10 NEW SCHOOL CONNECTION $28,984 11 WEIR BUILDING GYM $28,362 ll WCONDUS WHE — CSCeUMNADUFSF WHE SUBTOTAL: $550,396 <<<<< BOND AND ALL RISK INSURANCE COVERAGE: 1.6% $8, 806 UNASSIGNED CONTINGENCY: 15.0% $82,559 TOTAL ESTIMATED COST - BASIC BID: : $641,762 <<<<<< Summary Sasatscsasessesss ess asssesSe eae esses ssssSsSSeses5 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE cecccoces + LABOR W/O O’HEAD WITH O’HEAD ? WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS cost AND PROFIT AND PROFIT 2 2 GENERAL REQUIREMENTS 3 4 ROOM & BOARD 388 Mandays $85.00 $32,980 $32,980 5 FREIGHT 55 Tons $300.00 $16,500 1.714 94.3 $4,022 $20,522 6 EXPEDITING 2 Months 88.000 176.0 $7,508 $7,508 7 SUPERVISION 2 Months 129.900 259.8 $11,083 $11,083 8 FINANCING 1 Job $5,000.00 $5,000 $5,000 9 MEETINGS i Allow $1,000.00 $1,000 16.000 16.0 $683 $1,683 10 SUBMITTALS ‘ 1 Allow $200.00 $200 16.000 16.0 $683 $883 11 SITE FACILITIES 12 Equipment 2 Months $1,500.00 $3,000 $3,000 13 office 2 Months $2,500.00 $5,000 $5,000 14 Electricity 2 Months $500.00 $1,000 $1,000 15 16 17 i8 i9 20 21 22 23 24 www e eee Pee mec c cree erm e erence ere r meee e eee reer sere esas see ee esse essen sess esses see saeeseeseessesssesssasesseeeeasesssssssesessescees 25 SUBTOTAL: GENERAL REQUIREMENTS 7680 562.1 $23,979 $88,659 26 BD na nn nn nn nn nn nn nn en ne nn nnn nn nnn ne nn en eee e enn oo eee eneneee oa nee en ne ne ee ee ee eee ee eee eee eee eee ee 28 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $74,382 $27,575 $101,957 29 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR BO nnn nn on nw nw nw on on nn on on ons nn nn neem wn ren nn nnn ces nc csc nneccc ces ons cece cess cesses seesesenenseses= Page 1 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE secrete et LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT i cc ee et ee eee eect nto enernscs emienima ge bbdmeneicnecneanibtunicnrismndaedll adbcdieh dase thaaed edited gaeaaeaatanelatascictliieelaaieslaiisaidediansndicedetiti 31 32 POWER PLANT 33 34 DEMOLITION 1 JOB $500.00 $500 24.000 24.0 $1,024 $1,524 35 PIPING 36 Piping 6" 100 LF $42.00 $4,200 0.600 60.0 $2,560 $6,760 37 Pipe Fittings 6" 10 EA $60.00 $600 2.000 20.0 $853 $1,453 38 39 VALVES 40 Gate 6" 5 EA $240.00 $1,200 6.000 30.0 $1,280 $2,480 41 Bal. Valve 6" 2 EBA $140.00 $280 6.000 12.0 $512 $792 42 Check Valve 6" 1 EA $220.00 $220 6.000 6.0 $256 $476 43 44 EQUIPMENT 45 Heat Exchanger, Flat 1 EA $5,250.00 $5,250 16.000 16.0 $683 $5,933 46 Plate Type . 47 Air Separator 1 EA $200.00 $200 2.000 2.0 $85 $285 48 Circ Pump 450 GPM 1 EA $1,500.00 $1,500 8.000 8.0 $341 $1,841 49 50 51 ALLOWANCE FOR ELECTRICAL CONNECTIONS 1 JOB $1,250.00 $1,250 20.000 20.0 $853 $2,103 52 53 SE ccccccccccccccccccccccccccccccccccccccsccce ee mmm mere mercer ener caren reece ease eee eeassesesesesssesssessseseerssesssessssssessesee 55 SUBTOTAL: POWER PLANT $15,200 $8,447 $23,647 56 , 57 58 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $17,480 $11,825 $29,305 59 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR G0 nnn nnn nn nn enn nee ee eee nee ee eee eee ee ster c tere cerns Deemer etme ww tee ewe ete tem wee en ewe ese mene www e emt eset essere ese ses eens ner ennn Page 2 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 ee ee ee ee MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Panaascwcnsccces Siiaack) | Geta aie 2 ere are + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS cost AND PROFIT AND PROFIT 62 CONCEPT 1A 64 WEW BURIED HRS & HRR 65 TRENCHING 675 LF $3.90 $2,633 0.060 40.5 $1,728 $4,360 66 BACKFILL W/ORIGINAL MATERIAL - 675 LF $2.00 $1,350 0.060 40.5 $1,728 $3,078 67 No Cost Of Material 68 Importation Included 69 BEDDING 675 LF $2.00 $1,350 $1,350 70 2-1/2" ARCTIC PIPE 1,350 LF _ $16.00 $21,600 0.171 231.4 $9,873 $31,473 71 + PRE-FAB PIPE ELLS 8 EA $75.00 $600 0.667 5.3 $228 $828 72 «PIPE ANCHORS 16 EA $35.00 $560 1.000 16.0 $683 $1,243 BA) ie © icin W viele 801 « Si eISis ©: Sinie © wile © bisie SSIs SS S116 © © Sleio [0:6 SEIS © SIKIS @ witis © Sinle W sleIo 6H BISIIS @ Slelole S Biola W Sivie © Slew S HIwie[w HIS 6 wine @ Siow wwiejeicis © 0151616 BILE © HSIoM NISC © cieiere 85 SUBTOTAL: CONCEPT 1A $28,093 333.8 $14,238 $42,331 88 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $32,306 $19,934 $52,240 89 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR Page 3 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Hee cence eee e eee e eee a eee + LABOR W/O O’HEAD WITH O’HEAD a WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT ee in steamers tbe ceoiieaeaiceasies 91 92 APT. BUILDING CONNECTION 93 DRAIN & FILL SYSTEM 1 Job $500.00 $500 48.000 48.0 $2,048 $2,548 94 BALANCING . 1 Job 24.000 24.0 $1,024 | $1,024 95 INSULATION 100 LF $2.00 $200 0.074 7.4 $316 $516 96 PIPING 2-1/2" 100 LF $6.33 $633 0.255 25.5 $1,088 $1,721 97 ELLS & MISC FITTINGS 2-1/2" 12 EA $8.00 $96 1.000 12.0 $512 $608 98 VALVES 2-1/2" 4 EA $92.00 $368 2.000 8.0 $341 $709 99 EQUIPMENT 100 Heat Exchanger, Flat Plate Type 1 EA $2,437.50 $2,438 8.000 8.0 $341 $2,779 101 MISCELLANEOUS 102 Housekeeping pad 9 SF $3.13 $28 0.222 2.0 $85 $113 103 104 105 106 107 108 109 110 111 i122 113 115 SUBTOTAL: APT. BUILDING CONNECTION $4,263 -9 $5,755 $10,017 116 VD o-oo nnn nn nnn nn nn nnn nnn nnn nn nn nn nn nn nnn nn nn nnn nnn nn nnn nn nn enn nn nnn nee nnn nee nnn neers esr rnscrces 118 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $4,902 $8,057 $12,959 119 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 120-2 - o-oo nn nn nn nn nn nn nn nn nn nn nn nn nn nn nn nn nn nnn nnn nn nn nn nee nn ee eee neee wen ence renner ee- Page 4 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE sew eccccccocs celal ieee HP Hoc wccascasccccce + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT saunesnsensuensussnesennenses aneusnanenenen SSUES SAAAeSEs 121 122 CONCEPT 1B 123 124 NEW BURIED HRS & HRR 125 TRENCHING 790 LF $3.90 $3,081 0.060 47.4 $2,022 $5,103 126 BACKFILL W/ORIGINAL MATERIAL - 790 LF $2.00 $1,580 0.060 47.4 $2,022 $3,602 127 No Cost Of Material 128 Importation Included 129 BEDDING 790 LF $2.00 $1,580 $1,580 130. 2-1/2" ARCTIC PIPE *(790)LF $16.00 ($12,640) 0.171 (135.4) ($5,777) ($18,417) 131 3" ARCTIC PIPE 2,370 LF $18.00 $42,660 0.171 406.3 $17,332 $59,992 132 PRE-FAB PIPE ELLS 6 EA $75.00 $450 0.667 4.0 $171 $621 133 PIPE ANCHORS . 12 BA $35.00 $420 1.000 12.0 $512 $932 134 135 136 137 138 139 140 141 142 143 145 SUBTOTAL: CONCEPT 1B $37,131 381.7 $16,281 $53,412 146 147 148 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: , $42,701 $22,794 $65,495 149 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 150) ------------ == 2 2 ee ne ne ee ene eee ee eee eee ee eee eee eee ee ce ese ceeene a ee cee nee eee eee renee eres Page 5 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE do ccceeee oceeee ween pe wcccccewcwccses + LABOR W/O O’HEAD WITH O’HEAD * WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT meen ss ties saslavecenana ee/ad FEE ENR IESS SE-IIISI SEVIS SS EDIE CSTD IDUISIDED SPSS GSTS SSG SESSSSSSONSR SST SISSDSOSNGN ES NDGNSSCND SSs LENS SSL OEDIPUS ANNO ar ar eeSO TEDL S 151 152 POST OFFICE CONNECTION 153 DRAIN & FILL SYSTEM 1 Job $500.00 $500 48.000 48.0 $2,048 $2,548 154 BALANCING 1 Job 24.000 24.0 $1,024 $1,024 155 INSULATION 100 LF $2.00 $200 0.074 7.4 $316 $516 156 PIPING 2-1/2" 100 LF $6.33 $633 0.255 25.5 $1,088 $1,721 157 ELLS & MISC FITTINGS 2-1/2" 12 EA $8.00 $96 1.000 12.0 $512 $608 158 VALVES 2-1/2" 5 EA $92.00 $460 2.000 10.0 $427 $887 159 EQUIPMENT 160 Heat Exchanger, Flat Plate Type 1 EA $2,437.50 $2,438 8.000 8.0 $341 $2,779 161 MISCELLANEOUS 162 Housekeeping pad 9 SF $3.13 $28 0.222 2.0 $85 $113 163 164 165 166 167 168 169 170 171 172 173 175 SUBTOTAL: POST OFFICE CONNECTION $4,355 136.9 $5,840 $10,195 176 LDD nn nn nn nn nnn en nn ne re ene eee nner n eee eneee eed 178 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: ‘$5,008 , $8,176 $13,184 179 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 180-22 nn nn nn nn nn ne nn nen nn nee ene eee eee eer rrr reer weeeeeeee Page 6 GLENALLEN WASTE HEAT RECOVERY . CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves Inc. DATE: 05-Jan-90 Sosaeasesaseeeesaeeeessesssssssssssesssssessessessssensss55554555255882825555555555 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Home w ecco ccce eeceee poem ewww wwe wenn ne + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS cost AND PROFIT AND PROFIT 181 182 CONCEPT 2A 183 184 NEW BURIED HRS & HRR 185 TRENCHING 1,125 LF $3.90 $4,388 0.060 67.5 $2,880 $7,267 186 BACKFILL W/ORIGINAL MATERIAL - 1,125 LF $2.00 $2,250 0.060 67.5 $2,880 $5,130 187 No Cost Of Material 188 Importation Included 189 BEDDING 1,125 LF $2.00 $2,250 $2,250 190 4" ARCTIC PIPE 2,250 LF $24.00 $54,000 0.229 514.3 $21,939 $75,939 191 PRE-FAB PIPE ELLS 6 EA $75.00 $450 0.667 4.0 $171 $621 192 PIPE ANCHORS 12 EA $35.00 $420 1.000 12.0 $512 $932 193 194 195 196 197 198 199 200 201 202 203 ri) re ere errr rrr rer circ rrr rrr rrr rrr rrr rect rer rrr rr rrr rrrer rrr ree rere rere eee ere ee eT Tee ee 205 SUBTOTAL: CONCEPT 2A $63,758 665.3 $28,381 $92,139 206 . ° 207 208 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $73,321 $39,734 209 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR ee weet ee ene eee eee e+e eee eee ee eee ee eee ee eee ee eee eeee atte eee ene eee eee e eee eee Page 7 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 :=susan gD GSenGDENGD GES aS}0S =D=E=ESE=DSSEDDEEGSEDCSUNEESEAEESSESSUSSEE MEESGSEDEESUS SOGOU IDES USSDESDUESS 2 SS US SPSS UES MESS SSS OS STUDD STS SEDI IDO PEE SDSS DISS SEDED SDSS RUSS SPEDE USS DURDEN SD URDESIDO ASUS RENOD ED MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Hare eee eee eee eeee + -+ LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT ee Saeassssasssassesesssassessasssasesesssassssssssssesssssssssssaseassesesssssse552222522522=5=5 211 212 OLD SCHOOL CONNECTION 213 DRAIN & FILL SYSTEM 1 JOB $500.00 $500 48.000 48.0 $2,048 $2,548 214 BALANCING 1 JOB 24.000 24.0 $1,024 $1,024 215 INSULATION 100 LF $2.00 $200 0.074 7.4 $316 $516 216 PIPING 4" 100 LF $17.00 $1,700 0.400 40.0 $1,706 $3,406 217 + PIPE FITTINGS 218 Ells & Misc Fittings 4" 12 EA $25.00 $300 1.500 18.0 $768 $1,068 219 VALVES 4" 5 EBA $140.00 $700 3.000 15.0 $640 $1,340 220 EQUIPMENT 221 Heat Exchanger, Flat Plate Type 1 EA $2,437.50 $2,438 8.000 8.0 $341 $2,779 222 MISCELLANEOUS 223 Housekeeping pad 9 SF $3.13 $28 0.222 2.0 $85 $113 224 225 226 227 228 229 230 231 232 233 BSH nc 0 0c occ 0 000 00000 008 800808058 8800000850080 0650060000088 0 8000506000800 5 co 00 oOo eS Oo cece cece hese sereccecccccvcccctcseeseeses 235 SUBTOTAL: OLD SCHOOL CONNECTION $5,866 162.4 $6,928 $12,794 236 ZED nnn nn rr nn enn re rn nn nn nn rn nn en nn nn nn ee ene ee ee eee ee een eee eee eee ee ee eee eee een erence ree 238 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $6,745 $9,699 239 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 240 mn nnn nn nn en rn ee ne rn en ne nn nee nnn ne en ee en nee en eeee sete cece cere se rrr eee renee nec e snes Page 8 GLENALLEN WASTE HEAT RECOVERY “ CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Gra s, Inc. DATE: 05-Jan-90 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Sea ett estate aes rete tee ie) ease. sae ee see ae + LABOR W/O O’HEAD WITH O’HEAD # WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT ‘guns pence ukcncasCUUs aGEDULS SNS SSE SUORSE x cus SSE OOS Sees ADI Se SS sO a SS SS TS Se 2 UO DUD GS a nw SSD UD SUSE L/D EDERLAD EDEN tr S-ST ONDUCDUDUDEDEEDADUIDE MENDES UDOT TSR COURTS OOD 241 242 CONCEPT 2B 243 244 WEW BURIED HRS & HRR ‘ 245 TRENCHING 844 LF $3.90 $3,292 0.060 50.6 $2,160 $5,452 246 BACKFILL W/ORIGINAL MATERIAL - 844 LF $2.00 $1,688 0.060 50.6 $2,160 $3,848 247 No Cost Of Material 248 Importation Included 249 BEDDING 844 LF $2.00 $1,688 $1,688 250 4" ARCTIC PIPE 338 LF $24.00 $8,112 0.229 77.3 $3,296 $11,408 251 5” ARCTIC PIPE 1,350 LF $26.00 $35,100 0.229 308.6 $13,164 $48,264 252 PRE-FAB PIPE ELLS 6 EA $75.00 $450 0.667 4.0 $171 $621 253 PIPE ANCHORS 12 BA $35.00 $420 1.000 12.0 $512 $932 254 255 256 257 258 259 260 261 262 263 B40 <20% Sie 1o Je [a *1s16/5 © slaks (ole) cle eloiale ol lols © | alc inlaipinlgiaiviole(a i cleis © civic minlela!g elsiale © #)s/s\e1> vivisis @ siols w clele ini vicle ls s'slcle w visio viele sfelele sleiein'= =| sisie © Eibisio ale 8Is[6'w oicie ie isis © MNCIE 265 SUBTOTAL: CONCEPT 2B $50,750 503.1 $21,463 $72,212 266 267 rn nnn nnn nn nn enn nn nnn nn nn nn nn nn ene nen nn nnn nnn nn nen rene ne nee ne ene 268 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $58,362 $30,048 269 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 2T0 wn nnn nen eee enn nn ee ee eee nee eee eee ee eee we ee ee eee eee ee ee ee ee ee ee ee eee eee wee eee ene eee eee e ee eee weer e cen cece wren ew eees Page 9 GLENALLEN WASTE HEAT RECOVERY . CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 are ea rT eet ere en cipceccssri oteenterig eevee tins: tarabee moan aots tare oneness ade ibe st asta mses ime ee hen es ete peta nen eee st sees eee sccnmnasdi oer cenmnensicadacatadsatared MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL Cost LINE Powcccccce wwccccccce HP pec w www www emcees + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT Pas peeeneses escaetemucisusandicis oo areenmapur ureremertastrantoes aberasaserareperares eeanenen rere seer ox caetass an paeeme a ae aaa acon ee a a tee ee eats ciuisboenampiabiadameniaaiciaes 271 272 NEW SCHOOL CONNECTION 273 DRAIN & FILL SYSTEM 1 JOB $500.00 $500 48.000 48.0 $2,048 $2,548 274 BALANCING 1 JoB 24.000 24.0 $1,024 $1,024 275 INSULATION 350 LF $2.00 $700 0.074 25.9 $1,105 $1,805 276 PIPING 4" 350 LF $17.00 $5,950 0.400 140.0 $5,972 $11,922 277 PIPE FITTINGS 278 Ells & Misc Fittings 4" 12 BA $25.00 $300 1.500 18.0 $768 $1,068 279 VALVES 4" 5 EBA $140.00 $700 3.000 15.0 $640 $1,340 280 EQUIPMENT 281 Heat Exchanger, Flat Plate Type 1 BA $2,437.50 $2,438 8.000 8.0 $341 $2,779 282 MISCELLANEOUS 283 Housekeeping pad 9 SF $3.13 $28 0.222 2.0 $85 $113 284 285 286 287 288 289 290 291 292 293 2984 wleisisle citi cici= =! store oiclsigis sieicia-eitiels tae Zisis s Sisisle © sshoie s sieie o's lois s\sioMeleie)= o v:0[ois © siciele[< siew © sicio in sinle @ bivle® © Sisigipidic = slale visinw © wjelewie'b seis 5 6 3160 bila Bs10is les Sis 295 SUBTOTAL: NEW SCHOOL CONNECTION $10,616 280.9 $11,983 $22,599 296 297 298 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $12,208 $16,776 $28,984 299 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR B00 - nn nnn nnn nnn nn nn nn nn nn ne ee ee wenn nen ewe ene eeeee weeeeee were tre reece eee ee eee Page 10 GLENALLEN WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 05-Jan-90 MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Hoc e ence ween seen eens + Heeecccecccsccoss + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT ee ee sesame 2s seesaen sam umamennsmenesinie Sein of exudes cavemen Sa enistonece passes si ii i caceicloaae e 301 302 WEIR BUILDING GYM 303 DRAIN & FILL SYSTEM 1 JoB $500.00 $500 48.000 48.0 $2,048 $2,548 304 BALANCING 1 JOB 24.000 24.0 $1,024 $1,024 305 INSULATION 400 LF $2.00 $800 0.074 29.6 $1,263 $2,063 306 PIPING 3" 400 LF $17.76 $7,104 0.320 128.0 $5,460 $12,564 307 PIPE FITTINGS . 308 Ells & Misc Fittings 3" 12 EA $17.40 $209 0.500 6.0 $256 $465 309 VALVES 3" 5 EA $88.00 $440 1.500 7.5 $320 $760 310 EQUIPMENT 311 Heat Exchanger, Flat Plate Type 1 EA $2,437.50 $2,438 8.000 8.0 $341 $2,779 312 MISCELLANEOUS 313 Housekeeping pad 9 SF $3.13 $28 0.222 2.0 $85 $113 314 315 316 317 318 319 320 321 322 323 325 SUBTOTAL: WEIR BUILDING GYM $11,518 253.1 $10,797 $22,316 326 327 328 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $13,246 $15,116 $28,362 329 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 3300 ---- 2-22-22 ee ee ee ee nee ee wee cece eeee Pr re en ee eee eee een eeese SHES LES USS SS TSK SRS SES Page 11 GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Raw Data POWER PLANT Generators: Enterprise 2600 KW using HAGO Radiators: Young, model not available Operating Conditions during site visit: Not recorded, avail. from CVEA Min. Return Temp to Generator: Not available. Engine Design Flow and Max External Pressure: Not available. USER BUILDINGS Old School Boiler(s): | 2 ea. Birchfield Type 8 3967 & 1 ea. Type 24060 Boiler Supply Setpoint Temp.: 180 Actual Boiler Return/Supply Temp.: Not recorded. Cire Pump(s): P-1 1,5 HP P-2. 1/4HP P-3 B&G 189105, 1/3 HP P-4 B&G 189105, 1/4 HP P-5 Gone Circ Pump(s) Pressure: Not available. GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 New School Boiler(s): 3 ea. Weil-Mclain BL-876-SW, 480 MBH net IBR Boiler Supply Setpoint Temp.: 180 Actual Boiler Return/Supply Temp.: Not recorded. Cire Pump(s): CP-1 Grundfos CP8 KU 8-20 CP-2 Grundfos UPS 50-160 Circ Pump(s) Pressure: Not recorded. Weir Building Gym Boiler(s): American Standard Model PF 509, 1257.4 MBH Boiler Supply Setpoint Temp.: 180 Actual Boiler Return/Supply Temp.: Not recorded. Circ Pump(s): Pacific Pumping Co., 100 GPM @ 25’ Cire Pump(s) Pressure: Not recorded. Apartment Building Boiler(s): Hydrotherm, two sections, two burners, no model No. Boiler Supply Setpoint Temp.: 180 Actual Boiler Return/Supply Temp.: Not available. Circ Pump(s): B&G 189105 Circ Pump(s) Pressure: Not available. GLENNALLEN WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN JANUARY 15, 1990 Post Office Boiler(s): Burnham P5-505, 683.5 MBH net IBR Boiler Supply Setpoint Temp.: 180 Actual Boiler Return/Supply Temp.: Not available. Circ Pump(s): Grundfos Circ Pump(s) Pressure: Not available. EEFE CONSULTING ENGINEERS 560 E. 34th Avenue, Suite 300 SHEET NO: l ar 2 Ph. (607) 561-1666 CALCULATED BY. TS cave! /2/4> FAX (907) 561-7028 CHECKED OY nee DATE. seace_CulMArc Ey WASTE NEAT 2Ecwezy OVERHEAD HEAT WOSSES Besieecy 6 Miter valves tn Era vits race will be constent hk. loss de dvebing Flees. the ava’ able huat, These. losees foil inte the _fallening rote geries : (, Breede Ponser plant - hoeb ecbar gots, PD, Vales, ok 2. Uetecuhien yn - atc Pipex : 3 . e Kouser pier "wate an re shop, fe tanks. PAGT LL - INCIDE ForeR PLANT eee TE | Desurne ot loss in esvivaleyd te (06. fee} of vriesulakd 6" PL | ; v r _ 100 {es ak wrreulewd 12 Pipiry (esting) with Aa fluid Keng, o 10°F, pare bevy, of Bo °F. . fon AcyZAe fordame tals Gis8) b" sheel 2 33t. Gs [he] f+ 2 Bo. mai tz theek 2 fod Bh)he/FE 2 F014 meet PRooUCT 2041 (AEBS) Ine. Groton, Masa 01471 FFG CONSULTING ENGINEERS 560 E. 34th Avenue, Suite 300 SHEET NO: Zz or Ph. (07) Reisen caccutaten sy_____ TS pare__! /2/40 FAX (907) 561-7028 CHECKED BY ate SCALE LENNALLEN WASTE Ar PEcorez' papel. kel Polen baer (e abcd celle og opel sepa A® El th Toa gind Ba Lites feel Ay Jenks aie? 4a £ 7 4" lens 2 tens Dt © UE GIB + 080 FP Q oar 5 Ae Twv-0 1 e+ I4o' Fo ~ he Ely inside Nusa f\m ® Lo 2 d+ Cree s4o= 1s) mat. Cenc) - av 7 = 300 WBN fe Z PRODUCT 204-1 (WEBS) Ine, Groton, Mase, 01471.