Loading...
HomeMy WebLinkAboutNoorvik Waste Heat Recovery Report & Concept Design 1989‘AS oan Alaska Energy Authority e > LIBRARY COPY ss NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN Prepared for Alaska Energy Authority 701 East Tudor Road Anchorage, Alaska 99519 Prepared by Fryer/Pressley Engineering, Inc. 560 East 34th Avenue, Suite 300 Anchorage, Alaska 99503 DECEMBER 15, 1989 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY 2.0 INTRODUCTION 3.0 DESCRIPTION OF SITE VISIT 40 POWER PLANT DESCRIPTION 5.0 POTENTIAL WASTE HEAT USER BUILDING DESCRIPTIONS 6.0 —RIGHT-OF-WAY/EASEMENT 7.0 | CONCEPT DESIGN 8.0 |= ECONOMIC DATA 9.0 | CONCLUSIONS AND RECOMMENDATIONS APPENDICES 1 Calculations 2. Contact Names 3. Cost Estimates 10 21 41 WAS oz\| c.2 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 LIST OF FIGURES AND TABLES Power Plant Photographs Noorvik Power Generation - 1988 Noorvik High School Fuel Oil Inventory and Use Noorvik High School Photographs Community Building Photographs Community and Treatment Buliding Fuel Oll Use Treatment Building Photographs Figure 0 - Drawing Legend Figure 1 - System Schematic Figure 2 - System Site Plan Figure 3 - AVEC Module Pian Figure 4 - AVEC Module Schematic Figure 5 - High School Plan Figure 6A - High School Fan Room Schematic Figure 6B - High School Schematic Figure 7 - Community Bullding Module Plan Figure 8 - Community Bullding Module Schematic Figure 9 - Treatment Building Plan Figure 10 - Treatment Bullding Schematic Figure 11 - Arctic Pipe/Trench Cross Section NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 7,8 1A 12, 13 15, 16 17 18, 19 22 23 25 27 28 31 32 33 1.0 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 EXECUTIVE SUMMARY A potential for waste heat recovery exists at the community of Noorvik. Noorvik is lo- cated on the banks of the Kobuk River, approximately 520 air miles north-northwest of Anchorage. The heat energy could be recovered from the diesel engine-generator sets operated by AVEC and circulated to user buildings in the community. Three possible waste heat users have been identified: the high school, the Community building, and the Water/Wastewater Treatment building. It appears as if the most economical system will provide heat only to the high school since It Is closest to the power plant and can use almost all of the available heat. A sum- mary of the construction cost estimates along with design and SIA costs Is Included in the Cost Estimate Appendix. If only the base bid system Is installed connecting only to the high school, the following are the estimated results: Estimated Project Cost $283,316 Total Fuel Oil Savings 16432 gallons Total Annual Dollar Savings $17,750 Sigh Page 1 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 2.0 INTRODUCTION 2.1 2.2 2.3 Objective The objective of the field investigation and report Is to ascertain the viability of waste heat recovery and use in the community of Noorvik. It has been estab- lished that there is a potential source and use for the heat energy, and that the community |s Interested in pursuing the matter. Methodology The approach for investigation and analysis has been as follows: 1. Pre-site visit Information gathering: this has consisted of contact with the community officials, owners/operators of potential user bulldings, and contact with the local utility. The site visit was coordinated with the local building owners/operators. 2. Field Investigation: a visit was made to the community to view the site. Photographs of the potential user buildings were taken as well as of the electrical generation bulldings and equipment. Sketches were made of the equipment and piping connections. The project was discussed with local interested parties. 3. Office Analysis: additional information was collected regarding weather and historical electrical energy production. This was used in a model to predict the system performance and the amount of energy recovered. 4, Report Preparation: a draft version report was prepared for the expected audience - users and agencies with an interest. Community Description Noorvik is a community of 384 persons located on the banks of the Nazuruk Channel of the Kobuk River. The community Is 33 miles northwest of Selawik. Most of the community follows the terrain of the river bank. A small hill is located at the west end of the community. See Figure 1 in Section 7 for a community site plan. Page 2 2.4 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Applicable Codes and Regulations The most recently State of Alaska-adopted editions (1985 for all except as noted) of the following codes and regulations have been used in the preparation of the concept design. These are listed below: Uniform Plumbing Code (UPC - 1979) Uniform Mechanical Code (UMC) Uniform Building Code (UBC) Uniform Fire Code (UFC) National Electrical Code (NEC - 1987) National Fire Protection Association (NFPA) Codes NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 3.0 DESCRIPTION OF SITE VISIT 3.1 Field Notes Contact names are included as part of the Appendix at the end of this report. They include both field contacts and contacts made by phone. 3.2 Field Contacts The following people were contacted in the field: Cheryl Sampson, City Administrator Flora Carter, AVEC plant operator Donna Zabel, High School Principal’s Secretary David Denig-Chakroff, AEA Susan White, AEA Page 4 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 4.0 POWER PLANT DESCRIPTION 41 4.2 43 Narrative Description The site Is located on the road between the airstrip and the community Itself. The site consists of one module for switchgear and instrumentation, three separate modules each housing one generator and remote radiator, two small structures used for storage, and fuel oll storage tanks. Each of the modules Is an "ATCO" prefabricated unit, approximately 10 feet wide by 24 feet long. Inside each of the generator modules Is an engine/generator set housed in a room approximately 17.5 feet long and the width of the module. In the at- tached room at the north end of the modules, separated by a door, Is the remote radiator, cooling piping, and heat exchanger. The heat exchanger Is a shell and tube type. The heat transferred from the cooling system is used to heat the modules themselves using a unit heater in each module. No pump was found for circulation of this heating fluid. A 3/4" pair of lines runs interconnected between all of the modules, running through a small wooden utllidor between the modules. The line serves unit heaters located in each of the three modules. Cooling is accomplished through wall mounted axial fans. A single control sys- tem controls both the heating and cooling based on a thermostat located in the space. The power plant uses two Caterpillar 3412 engine/generators rated at 340 KW and one Caterpillar 0342 rated ar 185 KW. The D342 Is rarely used. There are no immediate plans for changes to the generating system. Part of the long term plan Is to replace the D342 (within 10 years). Floor Plan and Schematics » See the Figures 3 and 4 for a simple floor plan and schematic of the system (located in Section 7). Photographs See the attached copies of the original color photographs. Page 5 44 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Avallable Load Information Refer to the attached Table Indicating historical power production. This informa- tion is from AVEC for the year 1988. Figures for other years are also available from AVEC. Page 6 PHOTO 1: AVEC MODULES East Elevation of Module No. 1 PHOTO 2: AVEC MODULES Exterior of Modules 2 and 3 PAGE 7 PHOTO 3: AVEC MODULES Heat Exchanger Piping PHOTO 4: AVEC MODULES Generator Number 1 PAGE 8 NOORVIK POWER GENERATION 1988 MONTH PRODUCTION HOURS/ AVG. LOAD (KWH) MONTH (KW) JAN 88, 988 726 122 FEB 99, 206 696 143 MAR 199, 000 744 134 APR 95, 600 728 133 MAY 87, 208 744 117 JUNE 70,909 726 97 JULY 70,000 744 94 AUG 78, 980 74h 195 SEP 70,400 729 98 ocT 192,499 744 138 NOV 196, 49 728 148 DEC 115,206 744 155 ANNUAL 1, 082, 488 8768 124 Page 9 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 5.0 POTENTIAL WASTE HEAT USER BUILDING DESCRIPTIONS 5.1 5.2 General Three buildings were identified by Peter Hansen of the Alaska Energy Authority as having the most economic potential for waste heat use. These three buildings are the Noorvik High School, the Community Building, and the Water/Wastewater Treatment Building. The three buildings were visited and information about them gathered. The information is presented below. Photographs accompany each building description. Plans and schematics can be found in Section 7. Noorvik High School General Tne building is a wood and steel structure on piles with approximately 20,000 square feet of conditioned space. The building is used mostly for educational purposes although there is some use of the gym and kitchen area for special events. The main portion of the building was constructed approximately 15 years ago. An addition was made 9 years ago which added the shop. science, and junior high reading areas. The building appears to be in good condition. Heating Energy Use The original portion of the school is heated through indirect fuel oil-fired furnaces located in a fan room above the administrative area, adjacent to the gym- nasium. Two fuel oil-fired water heaters are also located in this space. The equipment appears to be in good condition. Tne space added 9 years ago is heated separately through the use of two boilers located in the addition. The equipment appeared to be in good condi- tion. No fans were found other than make-up air units for welding exhaust which did not appear to receive more than very occasional use. Page 10 5.2 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 See the attached Table showing the approximate fuel use for 1988. The fuel use shown is from school records of the current fuel oil inventory. 10% of the fuel use was assumed to be for domestic water heating purposes and was deducted from the total. The actual inventory figures were averaged where more than one month of fuel use was known, and adjusted for gaps in the records. Noorvik Community Building General The building is a wood frame structure on piles two stories in height. A portion of the building is open from the bottom floor to the roof. The building has ap- proximately a 3200 square feet footprint, with an estimated 4400 conditioned square feet. It is used for community administrative spaces and for meeting pur- poses. The building is in fair condition. Heating Energy Use Two different methods of heating are available to the Community Building. One indirect fired unit heater is located in the main meeting room (which is open to the second floor). It is more economical to use this system, but is noisy, does not distribute the heat throughout the spaces well, and can be uncomfortable for those in the meeting room. The means for water heating in the space is not known and its use would be quite small, only for one lavatory and one sink. The second form of heating available is through the use of the hydronic boilers located in a small module adjacent to the Community Building. The boilers heat water which is zoned in the boiler room, and then piped over to the Community Building through a small wooden utilidor attached to the underside of the build- ings. See the attached Table outlining the fuel use for the buildings (for the Com- munity and the Treatment buildings). The figures shown were provided by the community office in terms of yearly fuel use. The monthly use was calculated based on the heating degree days for the area. Page 11 NOORVIK SCHOOL FUEL OIL INVENTORY (INCLUDES ELEM. SCHOOL ) DATE FUEL ON HAND USE COMMENT (GALLONS ) (GALLONS) 6/30/89 45,388 a 5/31/89 45, 388 3,459 4/39/89 48,838 5,214 3/31/89 54,952 2,380 2/28/89 56,432 22,464 11/38/88 78,896 7,978 16/31/88 85, 966 11,871 USE ADJUSTED FOR DELIVERY 7/31/88 51,837 (4,684)46, 999 GALLONS DELIVERED 4/39/88 47,153 4,684 FUEL NUMBER SUSPECT 3/31/88 51,837 5,598 2/29/88 57,345 4,824 1/31/88 62,169 16,955 11/38/87 78,224 5,749 9/30/87 83,964 (37,864) 7/31/87 46, 908 g 6/30/87 46,908 SINCE FUEL USE IN INVENTORY INCLUDES BOTH HIGH SCHOOL AND ELEMENTARY SCHOOL, USE WILL BE APPORTIONED AT 56% OF THE TOTAL. THIS IS BASED ON CONVERSATIONS WITH THE SCHOOL DISTRICT AND MAINTENANCE PERSONNEL . IN ADDITION, 19% OF HIGH SCHOOL USE DEDUCTED AS BEING FOR DOMESTIC WATER HEATING. NORMALIZED MONTHLY USE MONTH TOTAL USE H.S. HEATING (GALLONS ) (GALLONS ) JAN 7758 3,918 FEB 4824 2,431 MAR 2388 1,280 APR 5214 2,628 MAY 3456 1,759 JUNE 2 6 JULY g g AUG g g SEP 5671 2,858 ocT 6208 3,125 NOV 7876 3,563 DEC 8628 4,846 ANNUAL 58,595 25,588 Page 11A PHOTO 5: HIGH SCHOOL Exterior Elevation PHOTO 6: HIGH SCHOOL Exterior Elevation PAGE 12 PHOTO 7: HIGH SCHOOL Boiler Room PHOTO 8: HIGH SCHOOL Fan Room 5.3 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Noorvik Water/Wastewater Treatment Plant General The building is on piles, and is constructed of wood and steel with a metal roof. The actual age is unknown and the condition of the building Is good. The size of the building is estimated at 50 feet by 100 feet, for a 5000 square foot area. The building houses the equipment used for water and wastewater treatment. In addition, a 100,000 gallon water storage tank Is located in the space. A portion of the building Is also used for an apartment by a private individual. Heating Energy Use Besides the energy required for space heating of the building, energy Is also con- sumed for the purpose of keeping the utilidor temperature high enough to prevent freezing. This purpose is accomplished through the use of glycol heat trace lines. The glycol is heated In the treatment building for circulation through the utilidor. The heating energy Is used via two hydronic boilers located In the treatment building. The boilers also have small domestic water heat exchangers located in the casing. The hot water is used for the apartment and other uses around the building. The hydronic system serves four unit heaters located at the corner of the building, and is also used to heat the glycol utilidor circulation system through shell and tube heat exchangers also located within the building. Page 14 PHOTO 9: COMMUNITY BUILDING Exterior Elevation PHOTO 10: COMMUNITY BUILDING Utility Module PAGE 15 PHOTO 11: COMMUNITY BUILDING Utilidor Between Buildings PHOTO 12: COMMUNITY BUILDING Interior of Main Meeting Room PAGE 16 COMMUNITY BUILDING FUEL USE FOR 1988 - AS AN AVERAGE YEAR COMMUNITY BUILDING 7615 GALLONS TOTAL MONTH DEG.. DAYS USE (GALLONS) HEAT REQ. (MBTU/DAY) JAN 1784 993 99273 FEB 1846 934 93416 MAR 2689 1957 195766 APR 1418 718 71753 MAY 944 478 47768 JUNE 693 395 39513 JULY 263 133 13398 AUG 356 188 18914 SEP 811 416 41938 ocT 1954 533 53334 NOV 1787 964 99425 DEC 2994 1968 195959 ANNUAL 15,949 7,615 761,596 WATER/SEWER TREATMENT BUILDING 14,589 GALLONS TOTAL MONTH DEG.. DAYS USE (GALLONS) HEAT REQ. (MBTU/DAY) JAN 1784 1719 171892 FEB 1846 1779 177866 MAR 2689 2613 261279 APR 1418 1366 136627 MAY 944 916 96956 JUNE 693 581 58169 JULY 263 253 25341 AUG 356 343 34361 SEP 811 781 78141 ocT 1954 1916 191555 NOV 1787 1722 172181 DEC 2994 2918 261761 ANNUAL 15,949 14,568 1,458,688 Page 17 ema a PHOTO 13: TREATMENT BUILDING Exterior View PHOTO 14: TREATMENT BUILDING Wastewater Treatment Equipment PAGE 18 PHOTO 15: TREATMENT BUILDING Boilers and Piping PHOTO 16: TREATMENT BUILDING Utilidor Heating System PAGE 19 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 6.0 RIGHT-OF-WAY/EASEMENT 6.1 Narrative Description The issue of right-of-ways and easements were not addressed as part of this report. Page 20 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 7.0 CONCEPT DESIGN 7.) System Narrative In discussion with Peter Hansen of the Alaska Energy Authority, Mr. Hansen recommended some general guidelines for the design of the waste neat recovery systems. His recommendations were the following: 1, Use flat plate heat exchangers in series, one for each of the generators that may be used. 2. Connect the High School system using another flat plate heat exchanger. Connections to the other two buildings can be direct, with no neat ex- changer. 3: System design should be for at least a 15 degree F temperature drop to keep flow rates as low as possible. In keeping with the above recommendations, the current concept design in- cludes two flat plate heat exchangers at the AVEC modules. The two heat ex- changers are for each of the normally used engine/generator sets. The flow will be in series through the two heat exchangers without any booster pump on the engine side of the system. Since the actual operating point of the pump is not known it is assumed that there is some allowance for a low pressure drop neat exchanger. One the primary loop, a main circulation pump will be designed for the pressure drop of the furthest connected building. In addition, an air separator, and ex- pansion tank, and a glycol make-up system is required. The pump’s design flow rate will be for the maximum heat available at a 20 degree temperature drop. Tne piping to each of the connected buildings will be through arctic pipe buried underground to protect it from damage from passage of vehicles. Two separate arctic pipes are envisioned, one for supply to the building, and one for return to the AVEC plant. See the attached Figure 1 for the system schematic. Page 21 oe] BALANCE VALVE GATE VALVE a1 2—WAY CONTROL VALVE 3—WAY CONTROL VALVE = CHECK VALVE a STRAINER UNION CIRCULATING PUMP i] THERMOMETER L ; —i + EXPANSION TANK c+—— _LOW WATER CUTOFF —e— FLOW ARROW —) PIPE DOWN ———© PIPE UP NEW RETURN LINE Se ~NEW SUPPEY EINE a EXISTING RETURN LINE EXISTING SUPPLY LINE ——-————--— NEW EQUIPMENT/VALVES IN THIS COLOR ——————_—_——— _ EXISTING EQUIPMENT/VALVES IN THIS COLOR NOORVIK SYMBOL LEGEND FRYER/PRESSLEY ENGINEERING 560 VENUE ANCHORAGE ALASKA $0603" ” (907)5e1-1060 12/15/89 PAGE 22 €¢ A9Vd x ef re be : “3 8 yy av Ki rl od i Uo a fs na Y ce by K rs iz a e 2 tl tl = z a dj4 AY3A003Y LVSH SLSVM YIAXOON GENERATOR 1 | GENERATOR 2 HEAT EXCHANGER TYP.) AVEC MODULES ALL PIPING SHOWN RUN OUTSIDE BUILDINGS IS IN ARCTIC ioe COMMUNITY BLDG NOORVIK WASTE HEAT RECOVERY HYDRONIC HEATING COILS IN FURNACES JS7 7” J) 7) howe pose nse HIGH SCHOOL /| //\ //| tte [Faleel | - ii} von an TREATMENT PLANT 7.2 7.3 74 75 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 At the connection to the high school connection will be to the fan room where the flat plate heat exchanger will be used for the circulating system serving new single-row heating coils in the existing furnaces and the hydronic system at the existing boilers. The coil design will be for a single row coil with wide fin spacing to minimize the air pressure drop and its effect on air flow to the rooms. The connection to the Community and the Treatment building will be with a heat exchanger to reduce the potential problems with building system overpressuriza- tion and loss of heating fluid in the event of a pipe leak. The piping will be con- nected into the return lines of the boilers and circulated with the existing in-line circulating pumps. Precautions must be taken to prevent overcooling of the generator jacket water and to prevent building system boilers from heating the waste heat distribution system. Each of these issues can be addressed with controls and valving. They can also be automated to some degree but the solutions must be carefully balanced with the need for system simplicity. Site Plan/Routing The routing will be as shown on the attached plan. Essentially, a direct line-of- sight connection is envisioned first from the AVEC plant to the high school, then from the high school to community building, and then to the treatment plant. The routing is shown on Figure 2. Generator Room Plans/Schematics See the attached Figures 3 and 4 for the design concept for changes to the AVEC modules. User Building Plan/Schematics See the attached Figures 5 through 10 for proposed changes to each of the potential user buildings. Arctic Pipe/Utilidor Section A cross section of the anticipated trench and arctic pipe configuration is shown in the Figure 11. Page 24 a SOC=,1 STIS ‘XOUdEY YSN NEO NOORVIK SITE PLAN . FRYER i. oO a ee [oa] fl [2] & oO a fz fa — n vn [2] 2 a. PAGE 25 76 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Outline Specifications The outline specifications for the major components of the system are shown below. 15010 GENERAL CONDITIONS The system shall be balanced by the Contractor to the flow specified in the construction documents. 15050 BASIC MATERIALS AND METHODS Valves: Valves for isolation use shall be gate type rated for 150 psig. Piping: Piping inside buildings shall be type “L" copper with dielectric unions at connection points of dissimilar metals. 15120 ARCTIC PIPE Arctic Pipe: Carrier pipe shall be schedule 40 steel or type “L" copper. In- sulation shall be foamed polyurethane with no voids. Thickness of Insula- tion to be minimum of 2 inches. Jacket pipe shall be steel or high density polyethylene. Arctic pipe system shall include kits or fittings for take-off connections to main loop that provide water-tight seal. 15250 MECHANICAL INSULATION Piping Insulation: Pipe Insulation shall be fiberglas with an all-service Jacket. Minimum insulation thickness shall be 1-1/2 Inches. 15750 HEAT TRANSFER Heat Exchangers: Heat exchangers shall be plate and frame type with minimum 20 gage stainless steel plates, painted steel frame with head and end support, top carrying bar, and bottom guiding bar. Ports shall be international pipe thread. Capacity shall be as specified. Accept- able manufacturers are Bell & Gossett, APV, Tranter, and Alfa Laval. Page 26 7 POSSIBLE LOCATION OF REMOTE HEAT EXCHANGER > / FUTURE EQUIPMENT RADIATOR — eet ee ee - LOUVER, TYP. i |e ¢ 5 7. | eae \\ SHEET METAL UNIT HEATER o A HOOD, TYP. | ENGINE | | | | it ETE ! | aS x \ { i GENERATOR | yt AESSERESAEEE APPROX. SCALE: 1”=4’-0" AVEC MODULE OW BE MD. FIP reicat Plan ae TW FRYER/PRESSLEY ENGINEERING DATE: 560 EAST 34th AVENUE SUITE ANCHORAGE ALASKA $9503" ~° (907)se1-1606 12/4/89 PAGE 27 oO =|| 2 ' a a : ow Oo %& eon c) Oo Lt qo); 2 E 1 = < ° 2 tS Sa ' 25 Y Ge |) 1 | ee ! Oo 1 Ma) I Ss Ce 1 1 = T ' A v ! a ee BY | || |e | lt | 26 Lb I aS) © > oc: : eae = 7 Ss \ poy 5 So 1 ow ><}-— > \=S= 1 > Qqa<g 1 ex mn i ‘ a | 1 a S ea + — &- 5 i ene A i Sy | — ! ! ' Neal || <S i (\3 ! + } j = \ v ery } 4 | = A 1 y | \ =e 7 | |g 1 i esn il I fe L 1 | ; A y 1 - i & i wi ee) A ; ETS ie alae 1 | i> VU Oo i 1 oo ! ><} Ls 1 i fl ; = 1 cH NG) qd | | (aot Tala iit im | 1x SS SS ee! | I | 1 ' ' I NEW WORK ———= GENERATOR ENGINE AVEC MODULES DYN BY: MOD. F|P pipinc piAcRAM ye if) . FRYER/PRESSLEY ENGINEERING DATE ANCHORAGE ALASKA’ 80603" (907)8e1-1680 12/4/89 PAGE 28 6¢ 39Vd dj NV1d 40014 ‘TOOHOS HOIH MIANOON soses 00€ ZLINS @ANAY TIVE LSVE 09S ONIMGTANIDNG AWISSAYd/MAANA = a & ‘ S a o RESOURCE ROOM Tth & 8th SCIENCE READING /ENGLISH UBRARY ENGLISH HOME EC. 7 Sc a = SOCIAL J opp 7 “STORAGE STUDIES | UPSTARS TM a [Srorace HMM s— es bu ROOM upsTAIRS /& ~ 3” SUPPLY & / 2 RETURN PIPES & FROM FAN ROOM / S PENTHOUSE ABOVE] KITCHEN GYM /S /& fe /& /€ APPROX. SCALE: 1°=25' BOILER ROOM 0€ 39d WYYOVIG INidld d a SSINGOW SAV ©0966 VXSVIV ‘ZDVEOHONY OOF ZLINS ZANZAY ive Lsva 099 DNINAANIDNG AWISSHYd/ HAAN NEW WORK ———~ 9991-199(406) 1 1 ! 1 ! ' ! ! | | ! | ! | | ' ' | | ! | ' HEAT EXCHANGER 71 ape 7 sorrie A FROM COILS/BOILER ROOM | 3” ae Ctopay LY | +-+eHti+4 To COILS/BOILER ROOM | ! | \ ore. PUMP A | = TANK & GLYCOL MAKE-UP | v | | | | | | | | FROM EXISTING Ae | | | THERMOSTAT OY PET A | i J \ | coi | FROM ‘TO ep | | ARCTIC ARCTIC a cee (ea PIPING PIPING 1-1/4 COIL PIPING — TYPICAL OF 5 be 3DVd FROM CLASSROOMS Sede tecle le | fy eel lil H d|i 4] | —~q- ah | A Y TO CLASSROOM A +2" -2" a pie 1-1/4" WVYYOVIA ONidid WOON Y3dI08 IOOHOS HOIH €0966 VXSVIV XSVYOHINY OO ZLINS ZNNZAY Nive Leva 099 ONIMAANIONG AWISSHUd/ AANA 4 ‘ FROM TO pO) t<t 1 COMMON ~— COMMON TO EXP. TANK ' SUPPLY RETURN ! GLYCOL MAKEUP Cee ow x) - L a 7 ———- NEW WORK 1-1/4") 3 ? 3 TO SHOP 3/4" 1-1/4" CP-5 CP-6 Te Or 1-1/4" eH OL pe BOILER CP-7 CP-8 1-1/4" WORKSHOP /STORAGE BOILER ROOM 7 BOILERS POSSIBLE LOCATION OF | NEW EQUIPMENT | OLD ENGINE /GENERATORS APPROX. SCALE: 1”=8'-0" DWN BY: MD CKD BY: TJ COMMUNITY BUILDING MODULE FIP pun Et FRYER/PRESSLEY ENGINEERING 560 EAST 34th AVENUE SUITE 300 ANCHORAGE, ALASKA 99503 DATE: 12/4/89 (907)561—1666 PAGE 32 €€ 3d ©0966 VXSVIV ‘ZDVHOHONY OOG ZLINS UNNZAY Tire Leva 099 DNIMGANIONG ABISSHUd/YaAMA dj WVYOVIG ONIdid ONIGTINE ALINNWWOO TO ARCTIC PIPE RETURN LOW WATER CUT-OFF snnceaaarmins - 4 PIPE SUPPLY | (ew worn -| { ARCTIC | 4 EA. SUPPLY A LINES ~~~ pos —_— TO PUMP, THEN TO 4 ZONES W/ZONE VALVES, 1 ZONE TO UNIT HEATER — 4 FROM HEAT EXCHANGERS TO 2 EA. SHELL & TUBE HEAT EXCHANGERS ON DETROIT DIESEL GENERATORS EXISTING UTILIDOR UNDER MODULE TO/FROM CITY HALL. APARTMENT AREA = CR {> Boiers f7 / L- 4-~ possiBle LOCATION / FOR NEW EQUIPMENT / \ WATER STORAGE | TANK / NOTE: NOT ALL EQUIPMENT SHOWN ON PLAN APPROX. SCALE: 1”=20'-0" TREATMENT BUILDING FIP pian FRYER/PRESSLEY ENGINEERING 560 EAST 34th AVENUE SUITE 300 ANCHORAGE, ALASKA 99603 (907)561-1666 12/4/89 PAGE 34 S€ 3DVd £0966 VXSVIY ‘ADVEOHINY OO€ ZLINS INNAAY Nive Leva 099 ONINHANIONA AWISSHUNd/YdANA WYYOVIG ONidid d a ‘O018 LNSWLV3YL YALVMSLSVM/YaLvM 1-1/2") 1-1/2", 1-1/2" 1-1/2" 1-1/2" _4 3/4” TO APT. W/ SEPARATE PUMP 10 TO TO TO TO AND ZONE VALVES. HX#1 HX#2 HX#3 HX#4 = -HX#5 Ll. | - | : | Lo 4 1-1/2” RUN TO 3 OR 4 UNIT aortic aI . ihaJ«,:dnen “ on —f rd fir Tt . Leryn HEATERS IN SERIES. —— 4 3/4” TO FINNED TUBE +9" RETURNS FROM ALL ZONES 4 = 10. COMMON [ ab Get Ss ReTURN ' Ave (1-1/2 = TO COMMO EXTROL MOD. 90 a { pao c+ tae qu Nr -{}+—if HEAT EXCHANGER r = = TUBE HEATER =| 35-S-29 ——-~ [ | LAG BOILER LEAD BOILER BACKFILL, COMPACT WASTE HEAT SUPPLY AND RETURN PIPING. | BEDDING. LI |_——— BEDDING, COMPACT TO 95%. | 6” MIN. | BEDDING. ARCTIC PIPE AND TRENCH P cross SECTION FRYER/PRESSLEY ENGINEERING 560 EAST 34th AVENUE SUITE 300 ANCHORAGE, ALASKA 99603 (907)561-1666 PAGE 36 15900 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Hydronic Coils: Coils shall be copper tube coils with aluminum fins, one row deep, and 8 fins per inch. Coils shall be designed for approximately 3000 CFM at 0.05 inches water column air pressure drop, 6.4 GPM at 30 degree temperature drop, and a water pressure drop of 5 feet or less. Circulation Pumps: The primary loop circulation pump shall be a base- mounted centrifugal pump capable of 100 GPM at 106 feet of head. The pump at the high school shall be an in-line centrifugal pump capable of 64 GPM at 20 feet of head. All pumps shall be compatible with a glycol heating fluid. CONTROLS Sequence of Operation: All of the pumps shall be manually switched. At the high school, each of the five thermostats shall be connected to new control valves at each of the respective coils. When the thermostats call for heat, the coils’ valves will open and the oil burners will fire (note that other, more efficient options are available which require additional controls). No other controls are expected to be necessary. 16010- GENERAL This Section of the Division 16 Specifications will include the following sub- headings with appropriate explanations of the requirements covered in each. GENERAL AND SPECIAL CONDITIONS Refers the Contractor to the Project Specifications’ General and Special Conditions. DRAWINGS Explains the nature of the Drawings and how the information depicted on the Drawings should be used and interpreted when viewed in the context of the entire set of Contract Documents. Page 37 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 DEFINITIONS Defines some of the major terms used in writing the Specifications. SUBMITTALS AND APPROVALS Defines the acceptable information considered to constitute the material submittals required for verifying the actual equipment and materials proposed for use in the Project’s electrical systems. PRODUCT DELIVERY, STORAGE AND HANDLING Directs caution in the storage and handling of materials to ameliorate their possible damage prior to their installation. JOB CONDITIONS Advises the Contractor to visit the site to acquaint himself witn tne actual conditions at this Project's location. PRODUCTS Establishes general criteria and standards of quality for the Project which apply to all of the materials proposed for the Project. This sub-section also requires all electrical materials to be labeled for their intended use and environment by UL. CLEANING The Contractor is required to clean all surfaces of equipment and remove debris and unused materials in this sub-section. 16020- WORK INCLUDED This area of the Division 16 Specification lays out the generalized descrip- tions of the electrical systems and work required in this Project. It also covers which area of the Specifications will define the requirements for equipment or installations which must be coordinated with other building trades. Page 38 16021- 16032- 16111- 16120- 16131- NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 WORK NOT INCLUDED This Section deals with those items which will definitely be provided within other areas of the Project’s various disciplines. An example of such an item would be the motors provided on a fan unit (obviously specified in Division 15) which is specified complete with a motor starter, disconnect or other accessories normally found in Division 16. MANUALS AND AS-BUILT DRAWINGS Sub-paragraphs describing the required contents of the Operation and Maintenance Manuals, defining the periods of instruction for the Owner’s designated personnel and the updating of information necessary to prepare record drawings of this Project’s final configuration are con- tained in this Section. CONDUIT All types of raceways and their associated appurtenances will be covered in this Section of Division 16. Galvanized rigid steel conduit, PVC-coated galvanized rigid steel conduit, intermediate metallic con- duit, electrical metallic tubing, flexible metal conduit and liquid-tight flexible Conduit will be specified. Fittings, couplings, grounding and where each type of raceway may be used will be specified. WIRES AND CABLES Building wires and cables for the distribution, feeders and branch circuits required for this Project are defined in this Section. This Section typically covers only wire with voltage ratings below 600 V. PULL BOXES AND JUNCTION BOXES The various types of pull boxes and junction boxes which will be allowed and/or required for installing the systems defined within Division 16 are specified in this Section. Page 39 16147- 16155- 16161- 16164- 16170- NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 DEVICE PLATES AND COVERS Surface mounted boxes shall be galvanized steel plates. Weatherproof installations will have gasketed metal plates. MOTOR STARTERS This Section will specify the motor contactors and controllers required by mechanical equipment. All controllers will be specified to have integral thermal overloads for motor overload protection. Combination starters utilizing circuit breakers or motor circuit protectors and that are UL listed for the application, will be acceptable. Combination starters utilizing fuses will not be allowed. GROUNDING This Section expands on the National Electrical Code requirements. BRANCH CIRCUIT PANELBOARDS Branch circuit breakers required to connect new equipment to existing panelboards will be specified in this Section. All circuit breakers will be bolt-on molded case circuit breakers of the rating and configuration necessary to serve general branch circuits and other defined loads. MOTOR AND CIRCUIT DISCONNECTS Unfused switches will be specified. Disconnects for motor applications will be required to be horsepower rated. Other disconnects will be specified to have ratings as necessary for the application. Enclosures will be NEMA 1 except where otherwise required. 16190- SUPPORTING DEVICES This Section will contain the requirements for hardware, anchors and fas- teners used to support raceways, equipment and any other electrical apparatus. Page 40 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 8.0 ECONOMIC DATA 8.1 8.2 8.3 Current Fuel Oil Costs Fuel oil costs for High School were $1.08/gallon for fuel purchased in 1989, and $.80/gallon for fuel purchased in 1988. The fuel is purchased through the Bureau of Indian Affairs (BIA) and is lower in price than what is available to other con- sumers in the community. Fuel oil costs for the community of Noorvik, for both the Community building and the Treatment building have been $1.41/gallon. Displaced Costs Due to Heat Recovery The calculations that model the waste heat system are shown in the Appendix at the end of this report. Tnese calculations essentially make comparisons of the waste heat available to the waste heat demand of the connected buildings. These comparisons are made for each hour of an average day of each month of the year. Since it may not be economically feasible to connect all of the potential build- ings, the calculations were made in a logical order of building connections, that is, the nearest building was modeled as being connected first. In this proposed order, the high school was connected first, then the Community building, and last the Treatment plant. The results of the calculations based on the most recent fuel oil costs were as fol- lows: High school only 16A32 gallons saved ($17,750) H.S. & Comm. bidg. 17,957 gallons saved ($19,900) All three buildings 19,269 gallons saved ($21,750) Summary Cost Estimate Tne assumptions for the cost estimate was that bidding would take place in April of 1990. Prevailing local wages as defined by the Department of Labor were used. The cost estimate is presented with costs identified for the total project, but broken out separately to show the component costs for the work at the AVEC plant, for the arctic pipe, and for each of the connected buildings. Page 41 8.4 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Since there can be much more energy demand than is available with the con- nected buildings, the cost estimate is organized in an additive alternate form. Tne base estimate assumes connection to just the high school and the additional cost for connection to the Community building and the Treatment building are shown separately. Energy Authority SIA (Supervision, Inspection, and Administra- tion) costs are included in the figures shown below. High school only $261,522 (base bid) H.S. & Comm. bidg. $94,194 (additive alt. #1) All three buildings $20,443 (additive alt. #2) Estimated Component Life and Maintenance Costs The following estimates of maintenance cost were made based on the in- cremental cost of technician who is already on-site. Assumptions were made for each of the pieces of equipment regarding frequency of inspection and repair. The total yearly maintenance cost will depend on the scope of installation. The costs for both the base bid and alternate #2 are shown. ttem Life (yrs) Maint, Cost ($/Yn Heat Exchangers 20 $126 (each, 4 total) Circulation pumps 15 $112 (each, 2 total) Arctic Pipe 16 $210 ¢total) Interior piping 16 $70 (each location, 5 total) Interior valves 15 $140 (each location, 5 total) Expansion Tank 15 $70 (each, 2 total) Air Separator 16 $35 (each, 2 total) Glycol 16 $180 (total) Coils 20 $105 (total) TOTAL (Alternate #2) $2483/year TOTAL (base bid) $1811/year Page 42 9.0 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 CONCLUSIONS AND RECOMMENDATIONS The final economics will be completed by the Alaska Energy Authority so a definitive conclusion cannot be made at this time concerning the feasibility of a waste heat instal- lation at Noorvik. Some conclusions that can be made are that the project is technically feasible, that the people and agencies in the community seem quite enthusiastic about the project, and that if the economics prove acceptable, a waste heat system for the community can be recommended. Two graphs follow this page that illustrate the current waste heat situation in Noorvik. The first graph entitled "Heat Available Vs. Heat Required" snows the relationship be- tween these two quantities for each month of a year. The lowest line represents the heat available from the power plant in terms of equivalent gallons of fuel oil. Each of the other three lines represent a construction option: the base bid, the alternate #1, and the alternate #2. As the graph demonstrates, the waste heat available is less than the heat energy required by the high school alone in all months except for the summer months. The second graph is entitled “Fuel Oil Displaced" and shows the amount of recovered energy in equivalent gallons of fuel oil for each of the three construction options for the year. A similar shape as was shown in the previous graph is displayed. If either of the additive alternates are accepted, only a small amount of additional energy would be saved since the school is using all of the available waste heat except during the sum- mer. Page 43 vr e6dd NOORVIK WASTE HEAT RECOVERY HEAT AVAILABLE VS. HEAT REQUIRED FUEL OIL EQUIVALENT (GALLONS) 38 >----- ee 0 T T I ai = = Ti 1 T = ji JAN FEB MAR APR MAY JUNE JULY AUG SEP OCT NOV DEC LEGEND "= HEAT REQ. - BASE BID —-— HEAT AVAILABLE | —4— HEAT REQ. - ALT. #2 12/15/89 Sv eBbd 2500 2000 1500 - 1000 500 - 0 12/15/89 NOORVIK WASTE HEAT RECOVERY FUEL OIL DISPLACED FUEL OIL EQUIVALENT (GALLONS) JAN FEB MAR APR MAY JUNE JULY AUG SEP OCT NOV DEC MONTH OF THE YEAR LEGEND” ee MMM BASE BID) W4 ALTERNATE 41. ‘HEH ALTERNATE #2 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 APPENDIX 1, Calculations 2. Contact Names 3. Cost Estimates NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Calculations NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 WASTE HEAT RECOVERY CALCULATION METHOD Input Before the calculation of recovered waste heat can take place, the user must input in- formation about power production, fuel use, and system heat loss. The information is for each month of a year. The year Is assumed to be either an average year or a represen- tative year. The power production information must include the amount of power produced for each month of a year and the amount of heat rejected to the jacket water for each KWH of power produced. The power production Is from historical records and the heat rejection data is from the manufacturer of the engine/generators being used for power production, The fuel use data Is for each of the potential waste heat user buildings. It Is fuel oll use for each month of the “average” year. It is also assumed that the fuel oll use reported here Is only for heating energy that can be displaced by waste heat recovery. It would not include fuel oil used by a separate fuel oil-fired water heater. The information ideally should be based on historical information but can also be estimated on a monthly basis for yearly fuel oll use. The system heat loss is a number that represents the energy that is rejected to the jacket water, but is lost or used before It can be used by the end user buildings. Examples of this system loss can include: heat loss of the generator cooling system piping, heat loss from the arctic pipe, and heat recovery in the power plant for space heating or fuel oil heating. This figure must be estimated based on available information. Assumptions The most important assumptions made in this model are the diumal variation of the heat demand, and the power production. The figures shown in the calculations represent a ‘typical’ pattem for rural environments. The heating demand follows an approximate sine Curve with mininum demand at solar noon, and maximum demand at solar mid- night. The diurnal variation for power plant production Is less regular. The variation as- sumed has peaks in the moming (around 8:00) and near noon and at 6:00 pm. The lowest power production occurs near midnight. NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 When calculating the energy demand for the buildings based on their fuel oll use, It is as- sumed that each gallon of fuel oll corresponds to 100,000 BTU. This represents ap- proximately a 71% efficient boiler or fumace. Actual efficiencies will vary. Calculations The heat available is calculated by dividing the monthly power production by the num- ber of days in the month - yielding the power production on an average day, then by multiplying that figure by the hourly power production variation for each hour. This is the power produced for each hour of the average day of the month. This figure Is multiplied by the manufacturer's factor for heat rejected to the jacket water. The result is the gross heat available at the power plant on an hourly basis. The system heat loss is subtracted from the gross amount, leaving the amount available for building use. The heat required by the buildings is accomplished in a similar manner. The sum of all the buildings fuel use Is multiplied by 100,000 BTU/gallon and adjusted to yield the hourly heat demand for the average day of the month. Tne heat recovered Is just the smaller number of the heat available and the heat demand; if the heat available Is larger than the heat demand, all of the heat available will be used. If the reverse is ttue and much more heat Is available, then all of the build- ing heat demand requirements will be met. The number of gallons displaced also as- sumes that each 100,000 BTU corresponds to one gallon of fuel oil. NOORVIK WASTE HEAT RECOVERY ESTIMATION ASSUMED DIURNAL HEAT DEMAND VARIATION BASED ON KOTZEBUE WEATHER INFO: AVG. YEARLY TEMP = 21 DEGREES AVG. RANGE = 13 DEGREES Hour Sine Avg. temp. Temp. diff. Normalized Function (deg. F) (based on 65 d) Factor 1 %.28 14.5 58.5 9.9494 2 G.14 16.3 48.7 $.6477 3 G.27 18.8 47.8 9. B469 4 9.48 19.7 45.3 G.8443 5 G.52 21.3 43.7 9.9428 6 .63 22.7 42.3 9.8414 7 6.73 24.6 41.6 9.0481 8 G.82 25.1 39.9 6.9398 9 %.89 26.8 39.6 $.9381 19 %.94 26.7 38.3 9.6374 11 $.98 27.2 37.8 6.6378 12 1.96 27.5 37.5 . 9367 13 1.96 27.5 37.5 9.9367 14 $.98 27.2 37.8 9.8376 15 G.94 26.7 38.3 6.8374 16 9.89 26.8 39.6 %.9381 17 G.82 25.1 39.9 %.9396 18 9.73 24.8 41.6 9.6481 19 .63 22.7 42.3 6.9414 26 %.52 21.3 43.7 6.9428 21 G.49 19.7 45.3 9.9443 22 $.27 18.9 47.9 6.9468 23 9.14 16.3 48.7 6.9477 24 -6. 88 14.5 59.5 6.9494 1621.9 1.6968 The heat demand variation is based on a sine function that models the daily temperature vaiations. The average temperatures are for each hour of the average day. NOORVIK WASTE HEAT RECOVERY ESTIMATION PAGE 1 WASTE HEAT UTILIZATION SIMULATION WORK SHEET. Location: NOORVIK Date: December 14, 1989 Heat rate: 2468 Btu/kwh produced System loss: 54,006 Btu/hour (approx. 38 BTU/FT arctic pipe) Total generation: 1,682,488 kwh/year Local degree days: 1784 1846 2689 1418 944 683 263 356 Assumed diurnal heat Power plant monthly generation: demand variation: oneo-------------- JAN FEB MAR APR MAY JUN JUL AUG Fraction:8.6813 6.6916 6.8923 6.6683 6.6805 6.6646 6.6646 6.6726 Winter Summer Hour Kwh: 88666 99288 166688 95608 87208 70688 70088 78066 Diurnal 6.6494 8.8494 1 variation 8.038 6.638 6.638 6.638 6.645 6.645 6.045 6.645 6.6477 6.6477 2 6.036 6.636 6.036 6.036 6.046 6.646 6.046 6.046 6.0468 68.0468 3 6.034 6.634 6.634 6.034 6.636 6.636 6.036 6.636 8.8443 8.8443 4 6.634 6.034 6.634 6.834 6.035 6.635 6.635 6.035 6.6428 6.6428 5 6.033 6.633 6.653 6.633 6.635 6.655 6.635 6.635 6.0414 6.0414 6 6.634 6.034 6.654 6.034 6.638 6.638 6.658 6.038 6.0461 6.6461 7 6.638 6.038 8.058 8.038 6.038 6.058 6.638 6.038 6.0398 6.8398 8 6.842 6.042 6.042 6.042 6.046 6.646 6.040 6.648 6.0381 9.8381 9 6.042 8.8642 6.642 6.042 6.645 8.845 6.645 6.045 6.0374 6.8374 16 6.047 6.047 6.047 6.047 6.047 6.647 6.047 6.647 6.0378 68.0378 1 6.048 6.048 6.048 6.048 6.040 6.040 6.040 6.040 6.0367 6.8367 12 6.047 6.047 6.647 6.047 6.048 6.648 6.048 6.048 6.6367 6.0367 13 6.045 6.045 6.645 6.645 6.650 6.658 6.058 6.656 6.0376 8.8378 14 6.647 6.647 6.647 6.647 6.052 6.652 6.652 6.652 6.0374 8.8374 15 6.048 6.048 6.648 6.648 6.658 6.056 6.056 6.656 6.0381 8.8381 16 5.648 6.048 6.048 6.048 6.050 8.058 6.058 6.058 6.6598 8.8598 17 6.049 6.649 6.649 6.649 6.645 6.645 6.645 6.645 6.6401 6.6481 18 6.046 6.646 6.646 6.646 6.047 6.647 6.047 6.647 6.0414 6.8414 19 6.645 6.643 6.643 6.045 6.658 6.656 6.058 6.656 6.8428 6.8428 26 6.658 6.658 6.658 6.658 6.645 6.645 6.645 6.645 6.0443 8.8445 ai 6.658 6.058 6.658 6.058 6.041 6.641 6.641 6.641 6.6466 6.8468 22 6.041 6.041 6.641 6.641 6.641 6.641 6.641 6.641 6.0477 6.6477 23 6.045 6.045 6.645 6.045 6.041 6.041 6.641 6.841 6.0494 8.8494 24 6.046 6.046 6.046 6.048 6.0435 6.043 6.643 6.643 Building use per month, gallons of fuel oil BUILDING 1, HIGH SCHOOL 3918 = 2431 1288 = 2628 )=—:1759 6 6 6 BUILDING 2, COMMUNITY BUILDING 6 6 6 6 6 6 6 6 BUILDING 3, TREATMENT BUILDING 6 6 6 6 6 6 8 6 BUILDING 4 6 6 6 6 6 6 6 6 BUILDING 5 6 6 6 6 6 6 6 6 BUILDING 6 6 6 6 6 6 6 6 6 811 SEP 6.8656 76408 6.845 6.846 6.836 6.635 8.635 6.638 6.638 6.048 6.645 6.647 6.848 6.648 6.656 6.652 6.056 6.058 6.045 6.647 6.656 6.645 6.641 6.641 6.641 6.843 2858 1054 ocT 1787 NOV 6.6946 6.6983 162488 6.845 6.646 6.836 6.635 6.635 6.638 6.38 6.848 6.045 6.647 6.048 6.648 6.656 6.652 6.058 6.656 6.645 6.647 6.656 6.645 6.641 6.641 6.041 6.645 3125 186488 6.638 6.036 6.834 6.654 6.633 6.034 6.638 6.642 6.642 6.647 6.048 6.647 6.645 6.647 6.648 8.648 6.649 6.846 6.643 6.658 6.638 6.641 6.845 6.646 3563 2094 DEC 6.1864 115266 6.838 8.636 8.834 6.834 6.633 6.034 6.838 6.642 8.642 6.647 8.648 8.047 8.845 6.647 6.648 6.648 6.649 6.646 6.645 6.638 6.638 6.641 6.645 6.646 4846 CONCEPT 1 ANNUAL, 15,049 CHECKSUM 1 1,682,408 25,508 maaan NOORVIK WASTE HEAT RECOVERY ESTIMATION BUILDING 7 6 6 BUILDING 8 6 6 BUILDING 9 6 6 6 6 TOTAL 3918 2431 PAGE 2 6 8 6 6 6 6 6 8 6 6 6 6 1266 ©2628 = 1739 Heat available per hour by month JAN FEB 1 289826 243464 2 195948 227751 3 182855 212898 4 182855 212898 5 175112 264272 6 182055 212898 7 209826 243484 8 237597 274718 9 237597 274718 16 272311 313842 11 279254 321668 12 272311 313842 MAR = APR- MAY. 245882 232611 255585 236623 217526 221187 214244 262441 193668 214244 262441 186788 286355 194899 186788 214244 262441 267428 245882 232611 267428 277366 262781 221187 277366 262781 255585 316888 366493 269345 324698 368855 221187 316868 386495 276224 JUN 194528 166967 144816 139293 139293 155861 155861 166967 194528 205566 166967 211688 JUL 194528 166967 144816 139293 139293 155861 155861 166987 194528 285566 166987 211888 13 258426 298189 361829 285468 289984 222134 222134 14 272311 313842 316888 366493 363743 233179 15 279254 321668 324698 368635 289984 222134 16 279254 321668 17 286197 329495 18 265368 366615 324698 368635 289984 332587 315577 255585 388919 292956 269345 222134 194528 205566 233179 222134 222134 194528 285566 19 244548 282536 285258 276323 289984 222134 222134 28 269826 243484 21 269826 243484 22 238654 266883 23 258426 298189 24 223712 259857 245862 232611 255585 245862 232611 228667 269471 255238 228867 361629 285468 228667 261581 247696 241826 194528 172429 172429 172429 183475 194526 172429 172429 172429 183475 GE+86 7E+86 TE+O6 GE+86 GE+I6 4E+86 4E+86 Heat demand by hour by month JAN FEB 1 635156 394961 2 612892 381859 3 591843 367474 4 576615 354406 5 556261 342681 6 531969 336746 7 515668 328686 8 561577 311858 9 489982 384641 18 481891 299115 11 475676 295376 12 472831 293488 13 472631 293486 14 475676 295376 MAR APR” MAY. 194932 426963 282498 188699 411938 272588 181394 397253 262876 174948 383128 253518 168859 369882 244785 163264 357549 236597 158259 346587 229543 153936 337121 223879 158378 329328 217923 147649 323352 213968 145861 319385 211291 144869 317263 289939 144869 317263 289939 145881 319385 211291 Sl eforel ay ove ere laverearaus 8 AUG 222923 192153 167538 161384 161384 179846 179846 192153 222923 235238 192153 241384 253692 266066 234826 366162 340546 373171 253692 253692 222923 235236 253692 222923 198367 198367 198387 216615 SE+O6 4E+86 7E+86 7E+86 8E+86 AUG 6 2858 3125 3563 4846 SEP OCT NOV DEC 195946 389558 264998 291372 168169 269155 248281 273195 145952 236846 231412 255617 148398 228761 231412 255817 140398 228761 223617 245928 157861 252998 231412 255617 157661 252998 264998 291372 168169 269155 298568 327727 195948 369556 298568 327727 267849 325768 348548 373171 168169 269155 348934 382268 212683 333786 340546 373171 223712 349944 323751 354994 223712 349944 348934 382268 223712 349944 348934 382266 195948 3869556 357329 391349 267649 325788 332145 364882 223712 349944 386962 336816 195948 369558 264998 291372 173723 277234 264998 291372 173723 277234 296173 318639 173723 277234 323751 354994 184832 295392 281779 389556 SEP ocT NOV DEC 6 464265 567637 578788 657248 6 447991 489843 558588 6342108 6 432626 472386 538589 611681 6 416658 455575 519428 589842 8 462167 439739 581372 569338 6 388841 425167 484759 556473 6 376928 412132 469897 533596 6 366626 406876 457663 519623 6 358158 391669 446497 587625 6 351651 384584 438396 497825 6 347251 379692 432989 491594 6 345629 377263 436148 488456 6 345629 377263 436148 488456 6 347251 379692 432989 491594 CONCEPT 1 aa aes 25 508 ANNUAL 2.17E+89 NOORVIK WASTE HEAT RECOVERY ESTIMATION 15 481891 299115 16 489982 384641 17 561577 311856 18 515668 326666 19 531969 338746 26 556261 342881 21 576615 354481 22 591843 367474 23 612892 381859 24 635156 394961 1E+87 = 8E+66 PAGE 3 147649 323352 213968 158378 329328 217923 153936 337121 223688 158259 346587 229345 163264 357549 236597 168859 369882 244785 174946 383128 253518 181394 397253 262876 188899 411938 272588 194932 426983 282496 4E+86 SE+B6 6E+86 Heat delivered by hour by month JAN FEB 1 209826 243404 2 195948 227751 3 182855 212898 4 182855 212898 5 175112 284272 6 182855 212898 7 209826 243404 8 237597 274716 9 237597 274716 16 272311 299113 11. 279254 2953768 12 272311 293488 13 258426 293488 14 272311 295376 15 279254 299113 16 279254 384641 17 286197 311858 18 265368 366615 19 244548 282536 26 289826 243464 21 289826 243464 22 236654 266883 23 258426 298189 24 223712 259057 GE+O6 6E+86 MAR = APR” MAY. 194932 232611 255585 188899 217526 221187 181394 262441 193668 174948 262441 186788 168859 194899 186788 163264 262441 267428 158259 232611 267428 153936 262781 221187 156378 262781 217923 147649 386493 213968 145881 368635 211291 144869 386495 269939 144869 285488 289939 145881 366493 211291 147649 368835 213968 158378 368635 217923 153936 315577 223688 158259 292958 229343 163264 276323 236597 168859 232611 244785 174948 232611 228867 181394 255238 228867 188899 285488 228867 194932 247696 241826 4E+86 G6E+86 SE+B6 FUEL OIL CONSUMPTION DISPLACED JAN FEB 1726 1946 MAR «APR MAY 1266 ©1982 1596 Wee erele oleiclela ela elale ele ele alajals Sa eee otal olclaiercialetatatelatetara: = 6 351652 384584 438396 497825 6 358156 391689 446497 587825 6 366626 466876 457863 519823 6 376926 412132 469897 533596 6 388841 425167 484759 558473 6 482167 439739 5861372 569338 6 416658 455575 519428 589842 6 432626 472381 538589 611661 6 447991 489843 558568 634218 6 464265 567637 578788 657248 6 9E+86 1E+87 1E+87 1E+87 AUG =SEP) OCT = NOV_—s«éEC 195948 389558 264998 291372 168169 269155 248281 273195 145952 236848 231412 255617 148398 228761 231412 255617 140398 228761 223617 245928 157661 252998 231412 255617 157861 252998 264998 291372 168169 269155 298568 327727 195948 369558 298568 327727 267649 325768 340546 573171 168169 269155 348934 582266 212683 333786 346546 373171 223712 349944 323751 354994 234826 366162 348548 373171 223712 349944 348934 382268 223712 349944 348934 382260 195948 389558 357329 391349 267649 325768 332145 364682 223712 349944 366962 336816 195946 389556 264996 291372 173723 277234 264996 291372 173723 277234 296173 318639 173723 277234 323751 354994 184832 293392 281779 369558 4E+06 7E+86 7E+O6 8E+86 JUL = =AUG SEP OCT NOV DEC 6 6 1366 ©2167 2162-2373 CONCEPT 1 ANNUAL 2.55E+89 ANNUAL 1.64E+89 ANNUAL 16,432 NOORVIK WASTE HEAT RECOVERY ESTIMATION PAGE 1 WASTE HEAT UTILIZATION SIMULATION WORK SHEET. Location: NOORVIK Date: December 14, 1989 Heat rate: 2466 Btu/kwh produced System loss: 54,068 Btu/hour (approx. 38 BTU/FT arctic pipe) Total generation: 1,682,488 kwh/year Local degree days: 1784 1846 2689 1418 944 663 263 356 811 Assumed diurnal heat Power plant monthly generation: demand variation: a = JAN FEB MAR APR MAY JUN JUL AUG SEP Fraction:6.6813 6.6916 6.6923 6.6883 6.6805 6.6646 6.6646 6.6728 6.6656 Winter Summer Hour Kwh: 88688 99288 188088 95666 87286 76008 76000 78008 76488 Diurnal 6.6494 6.6494 1 variation 8.038 8.058 6.638 6.058 6.045 6.645 6.045 6.645 6.645 6.0477 8.6477 2 6.636 6.036 6.036 6.036 6.046 6.048 6.046 6.048 6.048 6.6466 8.8468 5 6.634 6.634 6.054 6.634 6.636 6.036 6.636 6.036 6.836 8.0443 68.8443 4 6.034 6.034 6.034 6.034 6.035 6.835 6.035 6.635 8.635 6.0428 6.6428 5 6.633 6.633 6.653 6.633 6.635 6.635 6.635 6.635 8.635 6.0414 6.0414 6 6.654 6.634 6.654 6.634 6.638 6.638 6.838 6.638 6.038 6.0461 6.0481 7 6.038 6.658 6.638 6.038 6.658 6.638 6.638 6.638 6.638 6.6398 + 6.8398 8 6.842 6.642 6.642 6.042 6.046 6.648 6.646 6.048 6.646 6.6381 6.6381 9 6.642 6.842 6.642 6.642 6.645 6.645 6.645 6.645 6.845 6.8374 «8.0374 16 6.647 6.647 6.647 6.647 6.647 6.647 6.647 6.647 6.647 6.6578 6.6378 WV 6.048 6.048 6.648 6.048 6.046 6.046 6.040 6.046 6.6468 6.6367 6.6367 12 6.047 6.047 6.047 6.047 6.048 6.048 6.648 6.048 6.648 6.6367 6.0367 13 6.645 6.045 6.645 6.645 6.056 6.056 6.056 6.656 6.656 6.6378 6.63768 14 6.647 6.647 6.647 6.647 6.652 6.652 6.652 6.652 6.852 6.6374 «6.8374 15 6.648 6.048 6.648 6.048 6.656 6.058 6.656 6.656 6.656 6.0381 6.6381 16 6.048 6.048 6.048 6.048 6.056 6.058 6.056 6.050 6.858 6.0396 §=6.0398 17 6.649 6.649 6.649 6.049 6.645 6.045 6.645 6.645 6.845 6.0401 6.6461 18 6.646 6.046 6.646 6.046 6.647 6.047 6.647 6.647 6.647 6.6414 6.8414 19 6.643 6.645 6.643 6.643 6.056 6.056 6.058 6.656 6.656 6.0428 6.6428 26 6.658 6.638 6.658 6.638 6.645 6.645 6.645 6.645 6.645 6.0443 8.8443 21 6.658 6.658 6.658 6.658 6.641 6.641 6.641 6.641 6.641 6.0466 6.6468 22 6.041 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.6477 6.6477 23 6.645 6.045 6.645 6.045 6.641 6.641 6.641 6.641 6.641 6.8494 8.8494 24 6.646 6.046 6.646 6.646 8.645 6.645 6.843 6.643 6.845 Building use per month, gallons of fuel oil BUILDING 1, HIGH SCHOOL 3916 «2431 1288 = 2628 )=—:1739 6 6 6 2858 BUILDING 2, COMMUNITY BUILDING 963 934 «1857 718 478 365 133 186 416 BUILDING 3, TREATMENT BUILDING 6 6 6 6 6 6 6 6 6 BUILDING 4 6 6 6 6 6 6 6 6 6 BUILDING 5 6 6 6 6 6 6 6 6 6 BUILDING 6 6 6 6 6 6 6 6 6 6 1054 ocT 6.6946 162466 6.845 6.046 6.636 6.635 6.635 6.638 6.638 6.646 6.645 6.647 6.848 6.648 6.658 6.652 6.658 6.658 6.645 6.647 6.658 6.645 6.641 6.641 6.641 6.645 3125 533 1787 NOV 6.6983 186406 6.638 6.636 6.634 6.034 6.853 6.034 6.638 6.642 6.642 6.647 6.848 6.647 8.845 6.647 6.648 6.648 6.649 6.646 6.645 6.638 6.638 6.641 6.645 6.646 3563 alelalans 2094 DEC 6.1864 1152668 6.838 6.836 6.034 6.834 6.833 6.634 6.038 6.642 6.842 6.647 6.648 6.847 6.845 6.647 6.848 6.648 6.649 6.846 6.843 6.638 6.638 6.641 6.645 6.646 4846 1666 ANNUAL 15,849 CHECKSUM 1 1,682,408 25,580 7,615 NOORVIK WASTE HEAT RECOVERY ESTIMATION BUILDING 7 BUILDING 8 BUILDING 9 PAGE 2 eaaeae aan aoa aaaea aaan maaan aaan 4813 3365 2257 «3346 = 2217 305 Heat available per hour by month JAN FEB MAR APR MAY 209826 243484 245882 232611 255585 195948 227751 236623 217526 221187 182855 212898 214244 282441 193668 182855 212898 214244 262441 186788 175112 284272 286355 194899 186788 182855 212898 214244 262441 267428 269826 243484 245882 232611 267428 237597 274718 277368 262781 221187 237597 274716 277366 262781 255585 1B 272311 313842 316888 366493 269345 11 279254 321668 324698 368835 221187 12 272311 313842 316888 366493 276224 13 258426 298189 381629 285488 289984 14 272311 313842 316888 366493 363745 15 279254 321668 324698 388835 289984 16 279254 321668 324698 388835 289984 17 286197 329495 332587 315577 255585 JUN 194528 166967 144816 139293 139293 155861 155861 166987 194528 Cory nuewn = aaa a 133 JUL 194528 166987 144816 139293 139293 155861 155861 166967 194528 1868 AUG 222923 192153 167538 161384 161384 179846 179846 192153 222923 8 8 6 8 6 8 8 8 6 6 6 8 8 8 6 8 3268 «63658 «04467 5186 SEP OCT NOV DEC 195948 389556 264998 291372 168169 269155 248281 273195 145952 236848 231412 255617 148398 228761 231412 255617 148398 228761 223617 245928 157661 252998 231412 255617 157661 252998 264998 291372 168169 269155 298568 327727 195946 369558 298568 327727 285566 285566 235238 267649 325788 340548 373171 166987 166987 192153 168169 269155 348934 382266 211888 211688 241384 212683 333786 348548 373171 222134 222134 253692 223712 349944 323751 354994 233179 233179 266866 234826 366162 346548 373171 222134 222134 253692 223712 349944 348934 382268 222134 222134 253692 223712 349944 348934 382268 194526 194528 222923 195948 389558 357329 391349 18 265368 386615 388919 292958 269345 285566 285566 235236 267649 325788 332145 364882 19 244548 282536 285258 276523 289984 26 289826 243484 245882 232611 255585 21 289826 243464 245882 232611 228667 22 238654 266883 269471 255238 228667 23 258426 298189 361629 285488 228867 172429 24 223712 259857 261581 247696 241826 183475 GE+86 7E+B6 TEH06 GE+O6 GE+O6 4E+86 194528 172429 172429 Heat demand by hour by month JAN FEB MAR APR MAY = JUN 1 781843 546624 366636 543537 366138 49545. 2 754437 527463 353784 524485 347514 47888. 3 727542 588659 341172 565787 335125 46164. 4 761658 498563 329834 487793 323283 44464. 5 677268 473516 317597 476837 311968 42918. 6 654826 457826 367673 455235 361631 41496. 7 634756 443784 297658 441278 292383 48224. 8 617414 431664 289529 429226 284398 39125. 9 683141 421685 282836 419384 277823 38221. 16 592197 414633 277784 411696 272782 37527. 11 584786 468852 274228 466543 269368 37857. 12 581845 486237 272474 485943 267645 36828. 13 581845 486237 272474 465943 267645 36828. 14 584786 468852 274228 466543 269368 37857. 194528 172429 172429 172429 183475 4E+66 JUL 21665. 26847. 26184. 19389. 18715. 18695. 17546. 17661. 16666. 16364. 16159. 16856. 16856. 16159. 222134 222134 253692 222923 198387 198387 198387 218615 SE+O6 AUG 29239. 28214. 27269. 26241. 25328. 24489. 23738. 23698. 22556. 22147. 21876. 21736. 21738. 21876. 223712 349944 386962 336816 195948 389558 264998 291372 173723 277234 264998 291372 173723 277234 298173 318639 173723 277234 323751 354994 184832 293392 281779 3869558 4E+86 7E+86 7E+86 8E+06 SEP OcT NOV DEC 536867 594228 725637 829439 512258 573391 766262 860365 493997 552958 675246 771832 476422 533277 651217 744373 459861 514746 628588 718498 444623 497684 667751 694698 436992 482426 589119 673392 419221 469258 573629 655608 489529 458482 559782 639859 462898 458685 549625 628248 397866 444452 542746 628386 394526 4416869 539275 616418 394526 441689 539275 616418 39766 444452 542746 628386 CONCEPT 2 ea ae 33,115 ANNUAL 2.1 7E+89 NOORVIK WASTE HEAT RECOVERY ESTIMATION PAGE 3 15 592197 414633 277764 411696 272782 37527. 16 685141 421685 282836 419384 277823 38221. 17 617414 431664 289529 429226 284398 39125. 18 634756 443784 297658 441278 292383 46224. 19 654826 457826 387673 455235 361631 41496. 26 677268 473511 317597 476837 311968 42918. 21 761658 498563 329834 487793 323203 44464. 22 727542 568659 341172 505787 335125 46104. 23 754437 527463 353784 524485 347514 47808. 24 781843 546624 366636 543537 368138 49545. 2E+87 «1E+87 7E+86 1E+87 7E+66 1E+86 Heat delivered by hour by month JAN FEB MAR APR MAY JUN 1 289826 243484 245862 232611 255585 49545. 2 195948 227751 236623 217526 221187 47868. 3 182655 212898 214244 262441 193668 46164. 4 182855 212898 214244 282441 186788 44464. 5 175112 264272 266355 194899 186788 42918. 6 182855 212898 214244 262441 267428 41496. 7 209826 243484 245862 252611 287428 46224. 8 237597 274716 277366 262781 221187 39125. 9 237597 274718 277366 262781 255585 38221. 16 272311 313842 277764 366493 269345 37527. 11 279254 321668 274228 368835 221187 37657. 12 272311 313842 272474 386495 267645 36826. 13 258426 298189 272474 285488 267645 36828. 14 272311 313842 274228 366493 269368 37857. 15 279254 321668 277764 368635 272782 37527. 16 279254 321668 282836 368635 277823 38221. 17 286197 329495 289529 315577 255585 39125. 18 265368 366615 297658 292958 269345 46224. 19 244548 282536 285256 278523 289984 41496. 26 289826 243484 245862 232611 255585 42918. 21 269826 243484 245862 232611 228867 44464. 22 230654 266883 269471 255238 228667 46164. 23 258426 298189 361629 285488 228867 47868. 24 223712 259857 261581 247696 241826 49545. GE+O6 TE+86 GE+O6 GE+86 6E+06 FUEL OIL CONSUMPTION DISPLACED JAN FEB MAR APR MAY 1726 «1989 1982 1982 1758 = 385 16364. 16666. 17661. 17546. 18895. 18715. 19389. 20104. 20847. 21685. 437212 21685. 26847. 26184. 19389. 18715. 18895. 17548. 17661. 16666. 16364. 16159. 16056. 16656. 16159. 16364. 16666. 17661. 17546. 18895. 18715. 19389. 26164. 26847. 21685. 133 22147. 22556. 23696. 23738. 24489. 25328. 26241. 27289. 28214. 29239. 591715 26241. 28214. 29239. JUN JUL AUG 186 482698 458685 549625 628248 489529 458482 559782 639859 419221 469258 573629 655868 438992 482426 589119 673392 444623 497684 667751 694698 459861 514748 628588 718498 476422 533278 651217 744373 493997 552958 675248 771832 512258 573391 766282 880365 538867 594228 725637 829439 1E+87 =1E+87 1E+87 2E+87 SEP OCT NOV DEC + 195948 369558 264998 291372 + 168169 269155 248281 273195 145952 236846 231412 255617 + 148398 228761 231412 255617 + 148398 228761 223617 245928 + 157661 252998 231412 255817 + 157661 252998 264998 291372 + 168169 269155 298568 327727 195948 389558 298568 327727 + 267649 525768 340548 373171 + 168169 269155 348934 382268 + 212683 333786 340548 373171 + 223712 349944 323751 354994 + 234826 366162 340546 373171 + 223712 349944 348934 382260 + 223712 349944 348934 382268 + 195948 369558 357329 391349 . 267649 325768 332145 364682 + 223712 349944 386962 336816 - 195948 389558 264996 291372 173723 277234 264998 291372 + 173723 277234 296173 318639 173723 277234 323751 354994 184832 293392 281779 369556 1E+86 437212 591715 4E+86 7E+86 7E+66 S8E+86 SEP OCT NOV DEC 1366 ©2167-2162) 2373 ANNUAL 3.31E+89 ANNUAL 1. 8BE+89 ANNUAL 17,957 NOORVIK WASTE HEAT RECOVERY ESTIMATION PAGE 1 CONCEPT 3 WASTE HEAT UTILIZATION SIMULATION WORK SHEET. Location: NOORVIK Date: December 14, 1989 Heat rate: 2488 Btu/kwh produced System loss: 54,668 Btu/hour (approx. 38 BTU/FT arctic pipe) Total generation: 1,682,408 kwh/year ANNUAL Local degree days: 1784 1846 2689 1418 944 683 263 356 811 1654 «1787 2894 15,049 Assumed diurnal heat Power plant monthly generation: demand variation: oo---------------- JAN-FEB MAR APR MAY JUN JUL AUG SEP ocT NOV DEC CHECKSUM Fraction:8.6813 6.6916 6.6923 6.6883 6.6805 6.0646 6.6646 6.6728 6.6656 6.0946 6.6983 6.1064 1 Winter Summer = Hour Kwh: 88008 99208 100008 95608 87206 76600 70006 78088 76406 182400 186408 115208 1,682,408 Diurnal 6.0494 8.8494 1 variation 8.038 6.038 6.038 6.038 6.645 6.045 6.045 6.045 6.045 6.045 6.038 6.038 6.6477 6.6477 2 8.036 6.056 8.036 6.036 6.048 6.046 8.040 6.046 6.048 6.046 6.036 0.036 6.0460 6.0468 3 6.034 6.034 6.034 6.034 6.036 6.036 6.036 6.036 6.036 6.036 6.034 6.034 6.0443 8.0445 4 8.034 6.054 6.034 6.034 6.035 6.055 6.035 6.055 6.635 6.035 6.634 6.034 6.0428 6.6428 5 6.633 6.033 6.653 6.633 6.055 6.035 6.835 6.035 6.035 6.035 6.033 6.033 6.8414 6.8414 6 6.034 6.634 6.634 6.034 6.038 6.638 6.038 6.038 6.038 6.038 6.034 6.034 6.6401 6.6481 it 6.838 6.638 6.838 6.638 6.038 6.038 6.038 6.638 6.638 6.038 6.838 6.638 6.0598 8.6398 8 8.042 6.042 8.042 6.042 8.048 6.646 6.040 6.046 6.646 6.048 6.042 6.642 6.0381 8.8381 9 6.042 6.042 8.042 6.042 6.045 6.645 6.045 6.045 6.645 06.045 6.642 6.642 6.0374 6.0374 16 6.047 6.047 6.047 6.047 6.647 6.047 6.047 6.647 6.647 6.047 6.647 6.047 6.0570 6.0378 11 6.048 6.048 6.648 6.048 6.048 0.040 0.040 6.046 6.046 6.040 6.848 0.648 6.6367 6.0367 12 6.047 6.647 6.047 6.047 6.048 6.048 6.048 6.048 6.648 6.048 6.647 6.047 6.8367 6.8367 13 8.845 6.045 6.645 6.645 6.058 8.056 6.056 6.058 6.658 6.058 6.045 8.645 6.6376 6.6378 14 6.647 6.647 6.647 6.647 6.652 6.052 6.852 6.652 6.0652 6.652 6.647 6.647 6.0374 8.8374 15 6.048 6.648 6.648 6.648 6.058 6.058 6.058 6.056 6.058 6.658 6.048 6.648 6.0381 6.6381 16 6.848 6.648 6.048 6.648 6.058 6.056 6.658 6.056 6.058 6.056 6.048 6.648 8.0598 8.6398 17 6.849 6.049 6.049 6.649 6.645 6.645 6.045 6.045 6.645 6.045 6.049 9.049 6.6461 6.8461 18 6.846 6.646 6.646 6.646 6.647 6.647 6.647 6.647 6.647 6.047 6.646 8.046 6.8414 6.8414 19 6.645 6.045 6.643 6.043 6.056 6.058 6.058 6.056 6.656 6.056 8.043 6.043 6.6428 6.6428 26 6.638 6.658 6.638 6.638 6.645 6.645 6.645 6.645 6.045 6.845 6.638 6.638 8.8443 8.8443 a1 6.638 6.638 6.658 6.638 6.041 6.641 6.041 6.641 6.041 6.841 6.638 6.638 6.8466 986.8468 22 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.641 6.041 6.8477 = 8.6477 23 6.045 6.045 6.045 6.045 6.041 6.641 6.641 6.641 6.041 6.041 8.845 6.645 8.6494 8.8494 24 6.046 6.640 6.040 6.048 6.0435 6.043 6.043 6.643 6.643 6.043 6.648 0.048 Building use per month, gallons of fuel oil BUILDING 1, HIGH SCHOOL 3918 «24311288 = 2628 )=—-:1739 6 6 6 2858 3125 3563 4046 25,5008 BUILDING 2, COMMUNITY BUILDING 983 934 1657 718 478 305 133 1860418 533 964 = 1868 7,615 BUILDING 3, TREATMENT BUILDING 1719 1779-2813 1366 918581 253 3430-781 18161722 2818 14,581 BUILDING 4 8 6 6 6 8 8 6 6 6 6 8 6 6 BUILDING 5 6 6 6 6 6 6 6 6 6 6 6 6 6 BUILDING 6 6 6 6 6 6 8 6 6 6 6 6 6 8 NOORVIK WASTE HEAT RECOVERY ESTIMATION BUILDING 7 BUILDING 8 BUILDING 9 PAGE 2 6532 5144 4278 «4712-3127 Heat available per hour by month JAN FEB MAR APR MAY 1 289826 243484 245882 232611 255585 2 195948 227751 238623 217526 221187 3 182855 212898 214244 262441 193668 4 182855 212698 214244 262441 186788 5 175112 264272 286355 194899 186788 6 182855 212898 214244 262441 287428 7 209826 243404 245882 232611 287428 8 237597 274718 277368 262781 221187 9 237597 274716 277366 262781 255585 18 272311 313842 316888 366495 269345 11 279254 321668 324698 388635 221187 12 272311 313842 316868 366493 276224 13 258426 298189 361629 285488 289984 14 272311 313842 316888 366493 363743 15 279254 321668 324698 368635 289984 16 279254 321668 324698 388835 289984 17 286197 329495 332587 315577 255585 18 265368 386815 388919 292958 269345 19 244548 282536 285258 276523 289984 26 269826 243484 245862 232611 255585 21 289826 243484 245882 232611 228067 22 238654 266883 269471 255238 228867 23 258426 298189 361629 285488 228867 24 223712 259857 261581 247696 241826 GE+86 7E+86 7E+86 GE+66 6E+86 Heat demand by hour by month JAN FEB MAR APR OMAY 1 1E+86 835612 693636 765436 567962 2 1E+86 866321 669322 738605 496157 3 987389 777576 645461 712274 472685 4 952261 749913 622497 686934 455866 5 919168 723845 686859 663856 440626 6 888762 699868 588949 641685 425459 7 861456 678465 563138 621438 412396 8 837928 659875 547758 684458 461133 9 818558 644621 535695 596484 591868 16 863785 632924 525386 579778 584758 11 793647 625683 518811 572514 379935 886 JUN 194526 166967 144816 139293 139295 155861 155861 166967 194528 205566 166967 211688 222134 222134 1945268 172429 172429 172429 183475 4E+86 JUN 143925 138886 133929 129164 124674 126543 116847 113656 111629 169614 1676568 386 JUL 194528 166967 144816 139293 139293 155861 155861 166967 194526 205566 166987 211688 523 AUG 222923 192153 167538 161384 161384 179846 179846 192153 222923 235236 192153 241384 4049 4674 «6189 SEP 195948 168169 145952 148398 146398 OcT NOV 309558 264998 269155 248281 236848 231412 228761 231412 228761 223817 157861 252998 231412 157861 252998 264998 168169 269155 298568 195948 369558 298568 267649 325768 346546 168169 269155 348934 212663 333786 340546 222134 253692 223712 349944 323751 233179 233179 266886 234826 366162 346548 222134 222134 253692 223712 349944 348934 222134 222134 253692 223712 349944 348934 194526 194528 222923 195948 369558 357329 205566 205566 235236 287649 525768 332145 222134 194526 172429 172429 172429 183475 4E+86 JUL 62763. 60565. 58348. 56272. 54316. 52516. 56986 . 49516. 48371. 47493. 46899. 12 788571 621865 515492 568852 377564 166961 46599. 13 788571 621865 515492 568852 377564 166961 46599. 14 793647 625083 518811 572514 379935 167656 46899. 253692 222923 198387 198387 198367 216615 SE+O6 84958. 81986. 79057. 76245. 73594. 71156. 68974. 67696. 65539. 64356. 63545. 63138. 63138. 63545. 223712 349944 386962 195946 369558 264998 173723 277234 264998 173723 277234 296173 173723 277234 323751 184832 293392 281779 4E+86 TE+86 7E+86 SEP OCT NOV 657736 759263 1E+86 634688 732649 976125 612854 766538 935541 596279 681394 962257 569761 657768 876894 556881 635914 842036 533992 616418 816226 519468 599583 793928 567486 585722 775575 498194 575894 761582 491959 567897 751972 488812 564265 747162 488812 564265 747162 491959 567897 751972 7124 DEC 291372 273195 255617 255617 245928 255817 291372 327727 327727 373171 382268 373171 354994 373171 382268 382268 391349 364682 336816 291372 291372 318639 354994 369556 BE+B6 DEC 1E+B6 TE+B6 1E+66 1E+86 1E+86 969246 9395368 913871 892744 876546 865576 866639 866639 865576 47,616 ANNUAL 2.17E+89 NOORVIK WASTE HEAT RECOVERY ESTIMATION PAGE 3 15 883785 632924 525386 579778 384758 16 818558 644621 535895 596484 391868 17 837929 659875 547758 664458 481133 18 861456 678483 563138 621438 412396 19 888782 699868 588949 641685 425439 26 919168 723845 686859 663856 440628 21 952261 749913 622497 686934 455866 22 987389 777576 645461 712275 472683 23 1E+86 886321 669322 738685 498157 24 1E+86 835612 693636 765436 567962 2E+87 «2E+87 1E+67 2E+87 1E+87 Heat delivered by hour by month JAN FEB MAR APR MAY 1 289826 243484 245862 232611 255585 2 195948 227751 238623 217526 221187 3 182055 212898 214244 262441 193668 4 182055 212698 214244 282441 186788 5 175112 284272 286355 194899 186788 6 182855 212898 214244 262441 267428 7 269826 243464 245862 232611 267428 8 237597 274716 277366 262781 221187 9 237597 274716 277366 262781 255585 16 272311 313842 316868 366493 269345 11 279254 321668 524698 368655 221187 12 272311 313842 316868 366495 276224 13 258426 298189 361629 285488 289984 14 272311 313842 316868 366495 383745 15 279254 321668 324698 368835 289984 16 279254 321668 324698 368855 289964 17 286197 329495 332587 515577 255585 18 265368 386615 388919 292956 269345 19 244548 282536 285258 278523 289984 26 289826 243484 245862 232611 255585 21 289826 243464 245882 232611 228667 22 238654 266883 269471 255238 228667 23 258426 298189 381629 285488 228867 24 223712 259057 261581 247696 241826 GE+86 7E+86 7E+66 GE+86 6E+66 FUEL OIL CONSUMPTION DISPLACED JAN FEB MAR APR OMAY 1726 ©1989 2868 1982 1786 189814 47493. 111829 48371. 113656 49516. 116847 56966. 128543 52516. 124674 54316. 129164 56272. 133929 58348. 138886 68585. 143925 62763. SE+O6 1E+86 JUN «JUL 143925 62763. 138888 68585. 133929 58348. 129164 56272. 124674 54316. 120543 52516. 116847 56966. 113656 49516. 111829 48371. 169614 47493. 167658 46899. 186961 46599. 186961 46599. 1867656 46899. 189614 47493. 111629 48371. 113656 49516. 116847 58966. 128543 52516. 124674 54316. 129164 56272. 133929 58348. 138886 68585. 143925 62765. 64358. 65539. 67698. 68974. 71156. 73594. 76245. 79657. 81988. 84958. 2E+86 AUG 84958. 81988. 79057. 76245. 73594. 71156. 68974. 67696. 65539. 64358. 63545. 63138. 63138. 63545. 64356. 65539. 67696. 68974. 71156. 73594. 76245. 79857. 81988. 84958 498194 575894 761582 567406 585722 775575 519488 599583 793928 533992 616418 816228 556881 635915 842836 569761 657768 876894 598279 681394 962257 612854 766538 935541 634688 732649 978125 657736 759263 1E+86 1E+87 9 2E+87 9 2E+87 SEP OCT NOV 195948 369558 264998 168169 269155 248261 145952 236846 231412 148398 228761 231412 140398 228761 223617 157661 252998 231412 157661 252998 264998 168169 269155 298568 195946 369558 298568 267849 325768 340546 168169 269155 348934 212663 333786 340546 223712 349944 323751 234826 366162 340548 223712 349944 348934 223712 349944 348934 195948 369558 357329 267649 325768 332145 223712 349944 366962 195948 3695568 264996 173723 277234 264996 173723 277234 296173 173723 277234 323751 184832 293392 281779 SE+O6 1E+66 2E+86 4E+86 7E+86 7E+86 JUN JUL 886 0386 AUG 523 SEP OCT NOV 1366 «2167 «2162 876546 892745 913871 939531 969246 1E+66 1E+66 1E+66 1E+66 1E+B6 2E+87 DEC 291372 273195 255617 255617 245928 255617 291372 327727 327727 373171 382266 373171 354994 373171 382268 382266 391349 364682 336816 291372 291372 318639 354994 389556 SE+86 DEC 2373 ANNUAL 4. 76E+89 ANNUAL 1. 93E+89 ANNUAL 19,269 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Contact Names The following people were contacted In the field: Cheryl Sampson, City Administrator - 636-2 100 Flora Carter, AVEC plant operator - 636-2108 Donna Zabel, High School Principal’s Secretary - 636-2160 David Denig-Chakroff, Director of Rural Programs AEA - 561-7877 Susan White, AEA - 561-7877 In addition, the following people were contacted from Anchorage: John Lyons, AVEC 561-1818 Dan Coffey, Maintenance Director NW Arctic School District, 442-3476 Paul Weisner, Assistant Maintenance Director NW Arctic School Dist., 442-3476 NOORVIK WASTE HEAT RECOVERY REPORT AND CONCEPT DESIGN DECEMBER 15, 1989 Cost Estimates NOORVIK WASTE HEAT PROJECT COST SUMMARY BASE BID ESTIMATED CONSTRUCTION COST DESIGN COST (18% OF CONST. COST) SIA (26% OF CONST. COST) ESTIMATED PROJECT COST ADDITIVE ALTERNATE #1 ESTIMATED CONSTRUCTION COST DESIGN COST (18% OF CONST. COST) SIA (26% OF CONST. COST) ESTIMATED PROJECT COST ADDITIVE ALTERNATE #2 ESTIMATED CONSTRUCTION COST DESIGN COST (18% OF CONST. COST) SIA (26% OF CONST. COST) ESTIMATED PROJECT COST $217,935 $21,794 $43,587 $283,316 $78,495 $7,859 $15,699 $192,644 $17, 636 $1,764 $3, 467 $22,147 RUNNING TOTAL $217,935 $239,729 $283,316 $283,316 $361,811 $369,669 $385,359 $487, 463 $584,439 $596,142 $589,549 $531,696 SaessssssesesseseeeeeesssseSSSeSSSSS SSS S SSS SSS S SSS SSS SSS SSS SSS SHS SSS SHS SS SSS SHS SHH SHS SSS SH SHH SHS SSS SS SSS SS SSS SSS SSS SSSSSSSSSs== NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE: SUMMARY OF COSTS Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. 13-Dec-89 DESCRIPTION ESTIMATED COST OF CONSTRUCTION LINE 1: GENERAL REQUIREMENTS $50, 766 1 2: AVEC PLANT $33,247 2 3: ARCTIC PIPE $69,930 3 4: HIGH SCHOOL CONNECTION $41,339 4 SUBTOTAL: $195,282 <<<<< BOND AND ALL RISK INSURANCE COVERAGE: a CONTINGENCY: $3,125 $19,528 TOTAL ESTIMATED COST - BASIC BID: $217,935 <eKeek <Smeaaaeeeeses ALTERNATES: COST COST PLUS CONTINGENCY & INSUR. Al: EXTEND SYSTEM TO COMMUNITY CENTER General Requirements $16,322 $18,242 Arctic Pipe $47,650 $53,254 Community Center Connection $6,263 $7,000 TOTAL: $70,236 $78,495 A2: EXTEND SYSTEM TO WASTE TREATMENT PLANT General Requirements $3,983 $4,452 Community Center Connection $11,260 $12,585 TOTAL: $15,244 $17,036 TOTAL ALTERNATES: $95,532 <<<<< SSS Saas ss SBS SSS SS SSSA ASSS SSS SS SHA L SSSA AAS SSS SSH THVT ASSVSAAS VHS HHS HS ASBS SSS SSS SSS SSS SSS SS SSSSH SHS TH SSS SAASs TOTAL ESTIMATED PROJECT COST: $313,467 Summary NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Henne eee e eee e eee e ee Ho tence eee eee e eee + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT aeeeeae =: oe: ecassces: = 2 01 - GENERAL REQUIREMENTS 3 4 Room & Board 120 Mandays $75.00 $9,000 $9,000 5 Freight 13 Tons $900.00 $11,700 1.714 22.3 $951 $12,651 6 Air Freight 3,000 Pounds $0.65 $1,950 0.001 4.3 $183 $2,133 7 Expediting 1 Months 88.000 88.0 $3,754 $3,754 8 Supervision 1 Months 129.900 129.9 $5,542 $5,542 9 Financing i; Job $2,500.00 $2,500 $2,500 10 Meetings 1 Allow $1,000.00 $1,000 16.000 16.0 $683 $1,683 11 Submittals 1 Allow $200.00 $200 16.000 16.0 $683 $883 12 site Facilities 13 Equipment 2 Months $1,500.00 $3,000 $3,000 14 Office i: Months $2,500.00 $2,500 $2,500 15 Electricity 1 Months $500.00 $500 $500 16 17 18 19 20 21 22 23 24 cc ccc cc ccc ccc ccc cece ccccccccccces ce w cece wc ccnee pec cece ewer cee ccene emcee cece cece cece ccc ccccccserecrescscsccccscccessecscesseeese 25 SUBTOTAL: GENERAL REQUIREMENTS $32,350 276.5 $11,794 $44,144 26 27 28 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $37,203 $13,563 $50,766 29 LABOR RATE FOR THIS DIVISION: VARIES BO wenn nn nnn nnn nn nn rn nn re tr tr nn nn nn ne rrr rr rrr errr rrr Page 1 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 13-Dec-89 eee eeeeeeneeseessescesneseseeeeeneneneneee seen eeesssseeseseseesess esses ssesssesssssssS sees see eesssesessssSss ee seeSeeeSsseseessess MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Herre renee reer Bo Bee ee ee ene eee eee + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT weeeeeeeeeeseeeeeseee sees nese eeneeeeeeeee sess esc esse sesee sess seesesssesessseasesssassessesessessseessssseesseessessssssssssesess 31 32 AVEC PLANT 33 34 Demolition 1 JOB $500.00 $500 24.000 24.0 $1,024 $1,524 35 PIPING 3" 140 LF $17.76 $2,486 0.320 44.8 $1,911 $4,398 36 PIPE FITTINGS 37 Ells 38 aP 20 EA $17.40 $348 0.500 10.0 $427 $775 39 Tees 40 3° 14 EA $37.70 $528 0.500 7.0 $299 $826 41 VALVES 42 Gate 3" 21 EA $88.00 $1,848 1.500 31.5 $1,344 $3,192 43 EQUIPMENT 44 Heat Exchanger, Flat 3 EA $3,250.00 $9,750 8.000 24.0 $1,024 $10,774 45 Plate Type 46 47 55 Gal. Glycol Mixing Tank 1 EA $200.00 $200 1.000 1.0 $43 $243 48 Expansion Tank 1 EA $1,490.00 $1,490 4.000 4.0 $171 $1,661 49 Glycol Hand Pump 1 EA $45.00 $45 0.250 0.3 $11 $56 50 51 Circulating Pump 2 EA $700.00 $1,400 4.000 8.0 $341 $1,741 52 In-line 53 Allowance For Electrical Connections 1 JOB $1,250.00 $1,250 20.000 20.0 $853 $2,103 SE cccccccee a 5) bia iS © Sle W Sze © Sie & H4 © ©: SHS is fo She =: one iw: ota: dl one: ols (8 ONS 1G Bi S00 9) Sie Ge! ote Sits 55 SUBTOTAL: AVEC PLANT 174.6 $7,446 $27,292 56 oF 58 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $22,822 $10,425 $33,247 59 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 60 — Page 2 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 13-Dec-89 eeeeeee=: eee Soseseeesesas: Sasnesess== onan mea Seseesseesesssseesesssesces MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE He cc creer cect eeeccen HF tee nce ecw ee cerns + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT eeueeeeee eee esesseeses ses see eee eneeee eee eee seeEseee sess ses SSE sees ese sss sss Sees SSeS SSeS SEs SsSSSee esse Ses Sess eee eseeeeEssSSseS 61 62 ARCTIC PIPE 63 64 New buried 3" HRS & HRR 65 Trenching 850 Lin.Feet $3.90 $3,315 0.060 51.0 $2,176 $5,491 66 Backfill W/Original Material - 850 Lin.Feet $2.00 $1,700 0.060 51.0 $2,176 $3,876 67 No Cost Of Material 68 Importation Included 69 Bedding 850 Lin.Feet $2.00 $1,700 $1,700 70 3" Arctic Pipe 1,700 Lin.Feet $18.00 $30,600 0.171 291.4 $12,432 $43,032 71 Pre-Fab Pipe Ells 20 Each $75.00 $1,500 0.667 13.3 $569 $2,069 72 Pipe Anchors 10 Each $35.00 $350 1.000 10.0 $427 $777 73 74 75 76 7 78 79 80 81 82 83 84 . : 85 SUBTOTAL: ARCTIC PIPE $39,165 416.8 $17,779 $56,944 86 87 88 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $45,040 $24,891 $69,930 89 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 90 Page 3 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 13-Dec-89 =m SSE SE a SEEN eee eR EERE See see Ese EE SEs ERE see ee EE sees esse sess see SSeS SSS esses AEE EEE EEsSESssE MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Henne enn e ee ence ee- Se + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS cost AND PROFIT AND PROFIT Saeessseeesscessesssessecesssseeeeneeeeeeseseesessesessessesesssssesseseseseseessssesessessssssssasesssessssessssseeeseeeesesssssessssssss 91 92 HIGH SCHOOL CONNECTION 93 94 Drain & Fill System 1 Job $500.00 $500 48.000 48.0 $2,048 $2,548 95 Balancing 1 Job 24.000 24.0 $1,024 $1,024 96 97 INSULATION 98 Pipe Insulation 550 Lin.Feet $1.65 $908 0.074 40.7 $1,736 $2,644 99 100 PIPING 101 102 ae 300 LF $8.88 $2,664 0.213 64.0 $2,730 $5,394 103 1-174" 250 LF 104 PIPE FITTINGS 105 Ells 106 107 ae 10 EA $6.19 $62 0.500 5.0 $213 $275 108 Tees 109 110 ae 2 EA $13.87 $28 0.500 1.0 $43 $70 111 112 VALVES 113 Gate 114 = to BY 2° 2 EA $65.00 $130 1.000 2.0 $85 $215 116 1-174" 15 EA $35.00 $525 1.000 15.0 $640 $1,165 127 Flow Control Valve 5 EA $175.00 $875 2.000 10.0 $427 $1,302 118 119 120 Page 4 eeeeeceeoes: NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 13-Dec-89 Saeeeseesesseeeesesesessees nese sees eee eee sess seeese esses sess sees sse ses se sess eeseesesessessessessasssessesse se ssssSeseaeeesessssescsess MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Hence nee e eee ee eee Ho teen eee rene ee eee + LABOR W/O O’HEAD WITH O’HEAD ¢ WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT 121 EQUIPMENT 122 Fan Coils 5 EBA $2,400.00 $12,000 16.000 80.0 $3,413 $15,413 123 124 125 Allowance For Electrical Connections 1 JOB $1,000.00 $1,000 16.000 16.0 $683 $1,683 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 DOE, a io. o50'n: are 0 fe 9 vfs 0] ste fe 91050) wie @ oFe 9 Sve © o:= este owls iw vie wieie oie we eiv ei Bie wets a) ee. efele ei ete.e) wie cl gie weve wie © aise e7e 9 cles oFe le cies. alaw oe ie. ote a) ole ei vie wie. vneie is a10 6 0 66 B bie OFS SSIs Sis 145 SUBTOTAL: HIGH SCHOOL CONNECTION $18,691 305.7 $13,041 $31,732 146 147 148 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $22,429 $18,910 $41,339 149 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 150 Page 5 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Inc. DATE: 13-Dec-89 Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Grav Sass sssenes: a a = MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE He ween eee eee eee eee + tee eee - eee ee eee + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT 151 152 ALTERNATE NO. 1 153 General Requirements 154 Room & Board 42 Mandays $125.00 $5,250 $5,250 155 Freight 8 Tons $900.00 $7,200 1.714 13.7 $585 $7,785 156 Misc. Costs 1 Allow $200.00 $200 16.000 16.0 $683 $883 ST) [eeiclsieis siete ot = akotorsteteisiers 5 a\efols efola'cfoie close’ stole clea) oferaiaie aera stare efole alela' e\evere) slate elele elale sie/elaie, aisle eters hele oiele isle) a Sale e) ofp isielojelstete'!stelsisin== R oreipists aials ie 158 SUBTOTAL: General Requirements $12,650 29.7 $1,268 $13,918 159 160 161 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $14,548 $1,775 $16,322 162 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 163-2 nn ene nn ee ee eee e ee eee 164 Arctic Pipe 165 New buried 2" HRS & HRR 166 Trenching 630 Lin.Feet $3.90 $2,457 0.060 37.8 $1,613 $4,070 167 Backfill W/Original Material - 630 Lin.Feet $2.00 $1,260 0.060 37.8 $1,613 $2,873 168 No Cost Of Material 169 Importation Included 170 Bedding 630 Lin.Feet $2.00 $1,260 $1,260 171 2" Arctic Pipe 1,260 Lin.Feet $14.00 $17,640 0.171 216.0 $9,215 $26,855 172 Pre-Fab Pipe Ells 24 Each $75.00 $1,800 0.667 16.0 $683 $2,483 273. Pipe Anchors 12 Each $35.00 $420 1.000 12.0 $512 $932 LIA, Reece oc ous sees Bean sea se preted kell ote tote etelotetels olete cletsiaiete «iafatate eistaretcie’e aye) stay! slave’ oiate isis Sia Te STs (ol ois leteTo fal olaleraia eres ie) ot-ini oe oi ots @ af e Seles) Sele ote oi cie ele arais ie ee 175 SUBTOTAL: Arctic Pipe $24,837 319.6 $13,634 $38,471 176 WDD - 2 enn nnn nn nn nn en nn nn nn nnn nn en ne nnn nn nnn nnn en en ne nn nnn nn ee nn ne en en nn en eee eee 178 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $28,563 $19,088 $47,650 179 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 180 onan nn nn a nn nn eee eee een eee nee ene ee ence enn nen neenees Page 6 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 13-Dec-89 sesessasss CESS ASS SAA SSeS EEE SSeS eee Sees See Ses Sees Sess eee Se se Sees Sees eee eeeeeeE sess MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE Henne eee ee eee ee ee + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS TOTALS cost AND PROFIT AND PROFIT 182 Community Center Connection 184 INSULATION 185 Pipe Insulation 80 Lin.Feet $1.65 $132 0.074 5.9 $253 $385 188 PIPING 189 1-172" 80 Lin.Feet $5.32 $425 0.213 17.1 $728 $1,153 192 PIPE FITTINGS 193 Ells & Misc Fittings 194 1-172" 12 Each $3.15 $38 0.250 3.0 $128 $166 195 Tees 196 a" 2 Bach $45.00 $90 0.500 1.0 $43 $133 199 VALVES 200 Gate 201 1-172" 5 Each $23.00 $115 1.000 5.0 $213 $328 Page 7 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DATE: 13-Dec-89 ne neeeee ese see eee enone seee ee eee eeneneseneen esses ese sesssnseee sss sees ee ese seeseesssesesssseesss esses ssseesesssseseseees MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST come || |) i Wi i} Oo Ot oO OW I ae cl ce eral eel) operate pare ier talon + LABOR W/O O’HEAD WITH O’HEAD # | WORK DESCRIPTION QUANTITY UNITS TOTALS COST AND PROFIT AND PROFIT 211 EQUIPMENT 212 Heat Exchanger, Flat Plate Type 1 Each $2,437.50 $2,438 8.000 8.0 $341 $2,779 215 MISCELLANEOUS 216 Housekeeping pad 9 Sq.Feet $3.13 $28 0.222 2.0 $85 $113 221 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $3,756 $2,508 $6,263 222 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 235 SUBTOTAL: ALTERNATE NO. 1 $40,753 391.3 $16,693 $57,446 238 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $46,866 $23,370 $70,236 239 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR Page 8 NOORVIK WASTE HEAT RECOVERY Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Grav: Inc. MATERIAL COST LABOR HOURS CONCEPTUAL ESTIMATE 13-Dec-89 TOTAL COST TOTAL TOTAL COST GIMB erm w ere www eoenn Hee w cree cee ee eens + LABOR W/O O’HEAD WITH O’HEAD + WORK DESCRIPTION QUANTITY UNITS IT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT ——— ee Sacnonessesssessssesesssssess 243 ALTERNATE NO. 2 244 245 General Requirements 246 Room & Board 12 Mandays $125.00 $1,444 $1,444 247 Freight 1 Tons $900.00 $900 1.714 auw $73 $973 248 Misc. Costs 1 Allow $200.00 $200 16.000 16.0 $683 $883 249 cc cccccccces weer cere ere ccccccce eee rece cecccccces eee c ccc cccccccce sce c ec ccceee cee eee eee eee ceeeee occ rccccccccccceccecccce se eeee 250 SUBTOTAL: General Requir $2,544 17.7 $756 $3,299 251 252 ww nn nr nnn rr re ee een nnn tne tener n tennant ttre nen sssscne 253 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $2,925 $1,058 $3,983 254 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 255 wwe nnn ew nn mw nme cee ww weer mw www www ne enter cnn eer nnn etre nn etree tte en nem e nee nner n enn n erent nme n nnn n nnn ns ensseessenes 256 257 Treatment Plant Connection 258 259 INSULATION 280 Lin.Feet $1.65 $462 0.074 20.7 $884 $1,346 260 261 262 PIPING 1-1/2" 280 Lin.Feet $5.32 $1,488 0.213 59.7 $2,548 $4,037 263 264 265 PIPE FITTINGS 266 Ells & Misc Fittings 10 Each $3.15 $32 0.250 2.5 $107 $138 267 Tees 2 Each $45.00 $90 0.500 1.0 $43 $133 268 269 270 Page 9 NOORVIK WASTE HEAT RECOVERY CONCEPTUAL ESTIMATE 13-Dec-89 Prepared for FRYER/PRESSLEY ENGINEERING by Clark-Graves, Inc. DAT MATERIAL COST LABOR HOURS TOTAL TOTAL COST TOTAL COST LINE fi ctelorele wlpteieieimreisinimininrare Cheese eee + LABOR W/O O'HEAD WITH O’HEAD # WORK DESCRIPTION QUANTITY UNITS UNIT TOTAL UNITS TOTALS COST AND PROFIT AND PROFIT 271 VALVES 5 Each $23.00 $115 1.000 5.0 $213 $328 272 273 EQUIPMENT 274 Heat Exchanger, Flat Plate Type 1 Each $2,437.50 $2,438 8.000 8.0 $341 $2,779 275 276 MISCELLANEOUS 277 Housekeeping pad 9 Sq.Feet $3.13 $28 0.222 2.0 $85 $113 278 279 cece eee eeee Cece c cece cece cece ese re nr ec cence cece eeseeennsseseceeeeeeesscssccces Cece cece cc cccccccccccesccccccs eccccece eee eee eeeee 280 SUBTOTAL: Treatment Plant Connection $4,653 99.0 $4,221 $8,874 281 282 nn nn a nn nn nn nn ee ee nn nnn nn en nr nn nn nn nn nr tn nnn nr ne rn ren nner tern rrr e ss ersrsee 283 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $5,350 $5,910 $11,260 284 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR 285 enn n nm n een ewww www ewe n mene seeeee wt nn ee ee ne en ee ene nt en errr r nnn n nnn srsssss 286 287 288 289 290 291 292 293 294 eoee 295 SUBTOTAL: ALTERNATE NO. 2 $7,196 116.7 $4,977 $12,173 296 297 298 DIVISION SUB-TOTAL WITH OVERHEAD AND PROFIT: $8,276 $6,968 $15,244 299 LABOR RATE FOR THIS DIVISION: $42.66 PER HOUR B00 ----- ~~ nn nn en nn rn er rn nr ne rn er tr nt tr rn en nt er nn rn rn eer errr rer rrr rrr rr rrr rrr rss Page 10