HomeMy WebLinkAboutLarsen Bay Electric Furnace 1991_FROM: Marchegiani, Eric
TO: Sieczkowski, Stan DATE: 12-16-91
TIME: 11:57 AM
cc: Khan, Afzal
Marchegiani, Eric
Petrie, Brent
SUBJECT: larsen bay electric furnace
PRIORITY:
ATTACHMENTS:
In an effort to make sure that you have all the facts on the above subject, I
decided that I should put together what information I have collected so it
does not get lost and then I have to generate it again.
Generally what we need to know is what is the break even point of the oil
fired furnaces that are located in the School and the Village offices. In my
opinion the only thing that we can displace is the oil which runs
approximately $1.35/gal to residential customers. This could be less if one
purchased the oil in quantity. Then what we wish to do is convert what the
cost of fuel is to convert it to the cost per KWH. The following are the
assumptions:
Use #2 fuel which has an energy rating of approximately 140,000 BTU/gal
Price of #2 fuel oil at $1.35/gal
1 KWH = 3413 BTU
Assume fuel oil furnace efficiency = 0.80 PWNEB Then, $/KWH ($1.35/gal) (1/140,000 BTU/gal) (3413BTU/KWH) (1/0.80) =
$/KWH $0.04/KWH
Depending upon the assumptions, I would guess the break even point may vary
between $0.03/KWH and $0.04/KWH.
KKRKKKRKKEKRK KKK ERK EEK KKK ERK RK KKK RR ERK EKER KRKKRKKKKKKKKKKKKKRKKEE
Presently the school furnace is a Weil McLain, 542,000 BTU/hr oil fired
furnace. We checked with a local vendor here in town and found that a
comparable electric furnace would be a Weil McLain, CE-128-W, 436,864 BTU/hr,
3 phase, with 8 elements each at 16kw, with a cost of approximately $3,800.
The City furnace is a Burnham, 150,000 BTU/hr oil fired furnace. The
comparable electric furnace would be a Weil McLain CE-48-W, 164,000 BTU/hr, 3
phase, with 3 elements, each at 16kw for a cost of approximately $2,900.
A rough estimate of the cost to install the above electrical furnaces
including all expenses is as follows:
Parts/Equipment etc
School
Furnace $3,800
Plumbing Parts $1,000
Electrical Meter/Conduit/wiring $3,000
Load Management Modules (8 at $200) $1,600
Village Building
Furnace $2,900
Plumbing Parts $1,500
Electrical Meter/Conduit/wiring $2,500
Load Management Modules (3 at $200) $0,600
Travel
Airfare $1,600
Per Diem $2,000
Freight $1,500
Labor (Including overhead)
Plumber (7 days,10hr/day) $4,200
Electrician (7 days,10hr/day) $4,200
Manager (7 days,10hr/day) $5,500
Engineering (3 days at 8hr/day) $2,000
Contracts
Thompson & Howe Site Visit $3,000
Total $40,900
This total is substancially higher than what we originally estimated but I
believe it includes all of the major expenses that would be necessary to
complete the work. We might be able to trim it some and get the costs down to
approximately $30,000 but I think between $35,000 and $40,000 is more likely.
If one were able to obtain approximately $0.04/kwh; it take approximately
1,022,000 KWH to break even with the investments. Given the information I
have been able to gather we have run approximately 150,000 KWH into the load
dump over the past five months. This works out to be approximately 30,000 KWH
per month. This would relate to approximately 360,000 KWH per year or it
would take approximately three years to exceed the 1,022,000 KWH to break
even. We need to look at this closer. It is unlikely that we would be able
to use all of this energy since the furnaces do not come on and run
continuously, during the summer the school is not open, and the Village
probably does not use much heat during the summer therefore one might wish to
assume that we would only be able to use 1/3 of this energy; in which case it
would take approximately 9 years to recoup our investiment not including any
interest or rate of return during that period.
All of the above does not consider that an agreement will need to developed
and negotiated with both the Kodiak School District and the City of Larsen BAy
concerning the arrangement of purchase of surplus energy.
Please review the above information, and discuss more indepth with Brent and
advise me as to how you wish for me to proceed. As of the present I am
assuming that nothing will move forward until someone decides where the money
would come from along with beginning negotiations with the School District and
the City of Larsen Bay. Please note no funding was included for negotiations
in the above budget.
ERIC
DEC 13 ’91 11:53 PSI — ANCH ATTN STEVE FROM “IN Well-McLal
. : ; HEATING CAPACITY; aR Dea eda at em ea ee) ees. WATER: 164,000 to
436,864 BTU/Hr. STEAM: 55,000 to 327,648 BTU/Hr.
CE WATER BOILER CE STEAM BOILER 7 well: MoLain ae: CE — Bole is designed pn — oi = i: a sieeve. someon or foe ‘or hot water or steam heating systema in homes, apart- emall area, aa) value ving space, No flue or ven ments, commercial and institutional buildings. The CE is necessary. Standard components are used, and electri- ia factory assembled and wired with all controls; before cal connections are required only for power supply, cir- shipping, each boiler {is factory inspected and tested with culator, and thermostat. Piping is the same as for any hot all components. water or steam boiler, and two or more units may be The CE is designed for fast, low-cost installation for new headered together for multiple applications, heating aystems or for replacement of older boilers, The
DESIGN AND CONSTRUCTION FEATURES
yf of the unit facilitate wall mounting. Elements are easily Agi. —- removed through the aide plate on the right side of the jac!
HEATING ELEMENTS = Incoloy-sheathed, low-watt-density elements resist the corrosive effects of all chemicals found in domestic water syatems. | FACTORY-WIRED CONTROLS All controly are factory { wired and standard electrical components are used, The componentized control system provides the advantage of | easier replacement at lower unit cost, INTERNAL FUSING The CE Boiler ig supplied with a rate fuse for each element leg. This safety feature i eliminates the need for additional external sub- using. aoe CONTACTORS ca res a lege 0! ower source on a ++ Open 8 of each element when the thermostat is satisfied. si CAST IRON CONSTRUCTION The one-piece cast iron OPERATING SEQUENCE The CE control system uses boiler section is built in accordance with the Tequirements heavy-duty contactors and time-delays to sequence the heat- erm
of the ASME boiler = rn — code. Large water ing elements.
pe (ory meatal otmemigg Siatigk sonateee tees On a call for heat, the firat contactor instantly energizes the ly temperature. The internal baffling system assures first heating element and the first time-delay, Additional ele- p= steam and a steady water level, Thecastingis insulated nents are sequenced in intervals az long aa there is a call for with fiberglass to reduce heat logs. A built-in air separator eat. . , lel at the top of the casting diverts air bubbles to the automatic The elements remain energized until the thermostat is satie- ait vent or expansion tank , . , no separate air eliminating fied or the boiler water temperature reaches the o erating device is necessary. control setting. When either condition occurs, the first ele- HEAVY-DUTY JACKET The steel jacket is finished in at. ‘Ment energized is immediately de-energized, tractive blue hammerloid with a hinged front door to per- If the boiler water temperature exceeds the high-limit setting, mit access to all internal components. Brackets on the back all elements are immediately de-energized
Before purchasing this appliance, read Important energy cost and efficiency information avaliable from your retailer,
C13 ’91 11:54 PSI - ANC ——?P . 2/2, @UsTeD] oo: CH)
{evs No. of Circuits
ie on pena teat nip prescribed by the United States Department of Energy, rounded to nearest 1,000 BTU) Hr, NOTE, Baptog in atte Inad to the pe A apacg si Shoukd be added {eo the building |oss to determine total heating requirement, Syriac neon reat supe wis he baller. Mini it r hn '
ap curain cee 1c a HS neato ae only, Cengult national or local etsetrical code ‘manuals for temperature ratings of conductors other than 90°C. yaa eh onl oe os
fae shee ree Goren ne zea) eae: Seam—7.0 -“. ES orn treited a8 Re Sn rue
Steere ae
WATER . WATER "WATER /STEAM LEFT SIDE 0S FRONT RIGHT SIDE
"a4 minimum wall clearance required for lament romavel, eo vist vate ,
oFANDARD FQUIPMENT
pci path Wal Mountin i For Water Boilers Fer Steam Bollers , Lowel & rt ASME Satety Relief Valve ASME Vaive fA Nol ee om rDenalty Elements Corbina Pesur and igh Limi researc Control Borie re Att ns “mmermrens = eet ny
asi core iayR ela lays = Low Wat Cutoff (CE-128-W only) ge Cd setante Pat Conger Relay aid : te and of cantinead Improvement In products and pertormance, Weil-McLain reserves the right to change specifications without notice. WEIL McLAIN s:.:i:a0. van { Michigan City, Indiana 46360 @ A Marley Company InCanege WyianCanasa (TO .7EE. 120 Eat: Srampion Gownoner 162 Forn Na. C-523R6(382)
Litho In U.8.A.
FROM 12.13.1991 11152 ae |
PSC hoe f Farris Bo'foe tremace — ECA Lidctor! Farmee f
bes |- LAW ~ rmnufictnmwry
Ylarre PA Je into. ag foVows cd
Mt umier Pee Beam = 1S ps,"
LAde-. 50 ps.
Yun, relief ule cap- oy (4/ke,
OR MOH
Bor'for- S2e- BL. 976 Ws
Input FS 749 mad
rapape o'l- Stoo or
Fr outa p_ 62Y arp
19S0 4. FE
Stam - YORe/
Mitem- — py2
Ftegry -
Presyuve Veyse /s Ln. - Mma fe terywedh vn £7. wap fs Pees
4
rare We 1, <Q .
eee Fp rs AL Alas miter ¢ Aasoe +e
F¥ol Pemed Kd.
youd / FF 2ZO-N Anes, IK a1 509 2a ald, - 1RI-A-O
Shige mp, jay-
v5; xr ,,
Sem,
; "79349 )25
ee Lor x, Ths. POD treo
You, 160 ps,' “yrtisde, Tegel Ls loo “2
water me iy»
Lr 37 b
“Of . 4
57! J _ Ate a 1S
“ 35 =
ae ? ae ih Zz, Meter “ 30 pies’
TO, we hy “/
+ ee END eee
moec:
Mike L)i150n @ Ap Sot Ceeg
Weil MeClyx Bakers
-Ebectert mu HS
Ce aCER > papueee version
Z prarm Un 24%, ow BM