HomeMy WebLinkAboutRed Devil Status Reports, Trip Reports, & Field Notes 1985ALASKA POWER AUTHORITY
334 WEST 5th AVENUE - ANCHORAGE, ALASKA 99501 Phone: (907) 276-0001
October 8, 1985
Mr. Ken Selby
Selby Consulting Service
6421 Reed Lane
Anchorage, Alaska 99502
Subject: Red Devil Loan Application
Dear Ken:
Qur Planning directorate has reviewed the Middle Kuskokwim Electric
Cooperative's (MKEC) application and has the following comments:
1)
2)
The cost estimate presented seems very preliminary.
In order to establish a more accurate estimate of project
costs, we feel that either a firm bid for construction of the
entire project should be solicited from a contractor or that a
cost estimate should be prepared by a Professional Engineer.
An example of our concern is in the amounts allocated for
administration (seems excessive) and engineering (seems low).
The operating budget includes no provision for unscheduled repairs.
Only $1,640 has been budgeted annually for parts; this amount
seems only adequate to cover expenses such as filters and
lubrication, with no provision for repairs.
Written commitments to purchase power should be obtained from Targe customers.
The economic feasibility of the project is largely dependent
upon the purchase of power by the Kuspuk School District and
the Vanderpool Road House, which account for almost 83% of
projected revenues. Written commitments from these future
customers would help assure that the project is feasible.
Generators may be too large.
One 40kW and one 50kW unit have been proposed for Red Devil.
Based on the projected system's loads (110,000 kwh), we feel
these units may be too large, resulting in poor fuel efficien- cy.
1453/460
Mr. Ken Selby
October 8, 1985
Page 2
Our staff will be happy to meet with you to discuss these problems
and to help identify solutions to them.
Sincerely, Ze
Ernie Whitney
Auditing Manager
EW: it
cc: R.E. Etheridge, Alaska Power Authority
i rit
Susan White, Alaska Power Authority
1453/460
To:
Thru:
From:
ALASKA POWER AUTHORITY
Memorandum Ernie Whitney November 19, 1985 Auditing Manager
Edwin L. Morris
Assoc. Exec. Diréctor/Planning
} § Brent N. Petrie ®e
Director/Systems Planning
Peter N. Hansen BM The Middle Rural Systems Engineer Kuskokwim
Electric
Cooperative
(MKEC) Loan
Application
I have reviewed the Middle Kuskokwim Electric Cooperative (MKEC) loan application for a $250,000 loan from the Power Project Loan Fund.
The loan cannot be considered secured by assets once the project has been completed. Only a small fraction (10%) of the funds could be recovered through the sale of salvageable materials such as generators in case of an economic failure of the project. Additionally, the generators should not be expected to last until the loan has been repaid. Due to the small size of the generators it will not be realistic to expect more than 10 years of service from these units. It does not appear that MKEC has sufficient collateral located in other villages served by MKEC in order to secure this loan.
The security of the loan depends entirely on the future operation of the project. The current management of MKEC seems very capable of operating a small rural utility and thus the proposed system can be expected to be in operation as long as sufficient loads exist in Red Devil. At the present time the loads must be considered marginal for the operation of a utility. In the loan application budget assumes that the School will use 57% of the power produced by the utility and provide 51% of the cash flow for the utility. Another 22% will be used by the local Road House/Store which in return is expected to provide 20% of the cash flow for the utility. Thus, the budget is very sensitive to any fluctuation in the amount of power purchased by these two customers. The School presently has an enrollment of 10 students with an average attendance of six students. Earlier plans to close the School seem to have been at least temporarily suspended.
The loan application only identifies 11 residential customers who are scattered over a fairly large area on both sides of the river. This explains the relatively high cost of the project.
1957/497
Ernie Whitney
November 19, 1985
Page 2
My conclusion must be that from a purely economic stand point the project is questionable. The loan can not be considered secured through assets. The loan can be expected to be repaid only through continued operation of the utility. This operation obviously depends on the presence of the School and the Road House/Store. The argument has been presented that the availability of firm power in Red Devil will help stabilize the community and provide the basis for slow but steady growth. The stabilization of the community could provide the basis for keeping the School in operation thereby securing the feasibility of this project. This argument could be expected to be correct; however, it can not be substantiated at the present time.
I am under the impression that the proposed river crossing and the distribution system on one side of the river will serve only three residential consumers. The river crossing is a very costly element of the project. MKEC should be required to investigate the feasibility of deleting the river crossings from the project.
No recommendation is made concerning the MKEC loan application for $250,000 for the electrification of Red Devil.
EW/fs
1957/497
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE - ANCHORAGE, ALASKA 99501 Phone: (907) 276-0001
July 10, 1985
Mr. Max Gifford
Administrative Assistant
Office of Senator John C. Sackett c/o 1024 West Sixth Avenue
Anchorage, Alaska 99502
Dear Max:
This is in follow-up to our phone conversation regarding a possible electrification loan for the Village of Red Devil. As I indicated, the Power Authority administers two loan funds from which Red Devil might be interested in pursuing financing.
Both the Power Project Loan Fund and the Rural Electrification Revolving Loan Fund (RERLF) are available for application to rural communities. Power Project Loan Fund monies provide financing for a wide range of energy projects, including construction and equipping of small-scale power production facilities (power plant and generators, fuel storage, etc.). The attached statutes and administrative regulations define and provide guidelines on the applicable uses and terms of these loans. The RERLF provides 2 percent financing for rural utilities for the purposes of paying capital improvement costs which extend the electric utility's transmission and distribution system to new customers. Loan proceeds from this fund may not be used for construction of elec- tric power generation facilities. A copy of the statutes and administrative regulations applicable to this fund are also attached.
Considering the provisions of the above two loan funds, it appears that the Power Project Loan Fund is most appropriate to Red Devil's immediate electrification needs. A loan from the RERLF would be a consideration after power generation facilities are constructed and in operation. A legislative grant to the village through the Power Authority, for the extension of electrical lines is another sug- gested means for providing future funding. Should a power project loan be desired by the village, a decision will have to be reached as to what entity will assume obligation for the loan. Power Authority statutes provide that the Power Authority may make loans to a number of qualified borrowers, including electric utilities, regional electric authorities, village corporations and councils, etc. In Red Devil's case, the village council or Middle Kuskokwim Electric are the two appropriate entities; considering Red Devil's small population and limited revenues, Middle Kuskokwim would
82/365
Mr. Max Giffo..
July 10, 1985
Page 2
appear to be in a better financial position to assume debt
repayment on a power project loan.
At this time, to include Red Devil within their service area,
Middle Kuskokwim would have to file an application of amendment to
their Certificate of Public Convenience and Necessity with APUC. I
spoke with APUC and was advised that Middle Kuskokwim had recently
filed for their Certificate of Public Convenience and certification
approval date is anticipated towards the end of August.
The village of Red Devil should address their desire and need for
electrification financing to the Power Authority as soon as pos-
sible. Communication between the Village of Red Devil and Middle
Kuskokwim Electric should also be initiated, if the village so
desires, in the very near future, as the certification amendment
process does take time. The General Manager of Middle Kuskokwim is
Dennis Thomas of Crooked Creek.
Max, I hope the information I have provided is helpful. At this
time, the loan scenario is the only way we could finance Red
Devil's system. Please let the village know that we are interested
in hearing from them on their intentions. I wish there was an
easier way, unfortunately the project coordination and loan process
will be time consuming, but it is a means for funding. For your
information, Clarrisa Quinlan (344-2631) has been assisting with
Middle Kuskokwim's application for certification, and has been
advising the utility on an informal basis.
On a closing note, if Red Devil so desires, we may be in the
position to offer them technical assistance as far as surveying
their power needs and providing a recommendation on the most
appropriate generation facilities to accommodate these needs.
If I can be of further assistance, please give me a call.
Sincerely, eer
Susan White
Special Assistant
to the Executive Director
SW/amh
ee Pot. Heath
82/365
A)
ALASKA POWER AUTHORITY
334 WEST 5th AVENUE - ANCHORAGE, ALASKA 99501 Phone: (907) 276-0001
October 8, 1985
Mr. Ken Selby
Selby Consulting Service
6421 Reed Lane
Anchorage, Alaska 99502
Subject: Red Devil Loan Application
Dear Ken:
Our Planning directorate has reviewed the Middle Kuskokwim Electric
Cooperative's (MKEC) application and has the following comments:
1) The cost estimate presented seems very preliminary.
In order to establish a more accurate estimate of project
costs, we feel that either a firm bid for construction of the
entire project should be solicited from a contractor or that a
cost estimate should be prepared by a Professional Engineer.
An example of our concern is in the amounts allocated for
administration (seems excessive) and engineering (seems low).
2) The operating budget includes no provision for unscheduled repairs.
Only $1,640 has been budgeted annually for parts; this amount
seems only adequate to cover expenses such as filters and
lubrication, with no provision for repairs.
3) Written commitments to purchase power should be obtained from Targe customers.
The economic feasibility of the project is largely dependent
upon the purchase of power by the Kuspuk School District and
the Vanderpool Road House, which account for almost 83% of
projected revenues. Written commitments from these future
customers would help assure that the project is feasible.
4) Generators may be too large.
One 40kW and one 50kW unit have been proposed for Red Devil.
Based on the projected system's loads (110,000 kwh), we feel
these units may be too large, resulting in poor fuel efficien-
cy.
1453/460
Mr. Ken Selby
October 8, 1985
Page 2
Our staff will be happy to meet with you to discuss these problems
and to help identify solutions to them.
Sincerely, ZL
Ernie Whitney
Auditing Manager
EW: it
cc: R.E. Etheridge, Alaska Power Authority
Ed Morris, Alaska Power Authority
Peter Hansen, Alaska Power Authority
Susan White, Alaska Power Authority
1453/460