HomeMy WebLinkAboutMetlakatla Waste Heat Project Agreements, Contracts, & Budget 1988Version: 88/3/16/1200
METLAKATLA WASTE HEAT SYSTEM FEASIBILITY ANALYSIS
TABLE OF CONTENTS:
EXECUTIVE SUMMARY 1.0
Introduction and Background
Conclusions RR NP FACILITY DESCRIPTION i) ° General
Power plant
The School facilities
The Loussac Activity Center
The Council Chambers
The Clinic
The Youth Center
The Head Start Building
The Townhall
The Senior Center
The Low Income Housing NNNNNNNNNM FPOWOONDUNFWNHEH NN PR WASTE HEAT SYSTEM CONCEPTS Ww Oo General 3.1
Concept Al 3.2
Concept A2 3.3
Concept A3 3.4
Concept Bl 3.5
Concept B2 3.6
COST ESTIMATES 4.0
General 4.1
Concept Al 4.2
Concept A2 4.3
Concept A3 4.4
Concept Bl 4.5
Concept B2 4.6
ECONOMIC ANALYSIS 5.0
General 5.1
Concept Al 5.2
Concept A2
Concept A3
Concept Bl
Concept B2
CONCLUSIONS
General Discussions
Conclusions aann ana DAuFw NO
1.0 EXECUTIVE SUMMARY
1.1 Introduction and Background
In the fall of 1987 Metlakatla Light and Power (ML&P) requested
that the Alaska Power Authority investigate the feasibility of
utilizing waste heat from its power plant for heating public
buildings in Metlakatla including the local schools. Power
Authority staff made a visit to Metlakatla where the facilities
were audited for compatibility with waste heat recovery systems.
Based on the information gathered, five concepts for waste heat
recovery systems were developed. For each concept a preliminary
cost estimate and the pay back time were calculated with a Lotus
1-2-3 program using relevant climatic and statistical data. This
program simulates the operation of a waste heat recapture system
over the life span of the project.
This study does not include detailed engineering data such as
soils conditions, local availability of skilled labor and local
experience in undertaking construction projects. Thus, the cost
estimates should be used with great caution. The economic
analysis of system performance over the life span of the project
is fairly accurate, provided that prudent maintenance is
performed on the system.
1.2 Conclusions
It is expected that the City would realize substantial savings in
fuel and some savings in maintenance expenses from this project.
Also, it is expected that ML&P would realize some savings from
reduced station service loads. Maintenance savings have not been
quantified and consequently have no effect on the calculated pay-
back time. Annual operations and maintenance costs have been
estimated at 2% of the capital cost of the project. No technical
obstacles should prevent the installation of a waste heat
recapture system utilizing waste heat from the power plant in a
number of buildings. Provided that operational procedures are
not changed drastically in the power plant, installation of a
waste heat recapture system appears technically feasible.
However, due to the relatively low price of fuel, and due to the
length of the necessary distribution system, the economical
feasibility appears unsatisfactory at this time. The five
concepts show pay-back times of approximately 24, 22, 18, 26, and
30 years, when an annual fuel price escalation of 2% is used in
conjunction with a real interest rate of 4% and a fuel cost of
0.80$/gallon.
In accordance with the feasibility outlined above, it is
recommended that the project be postponed until such times when
the potential fuel savings will provide for a pay back time of no
more than 10 years. As an alternative means of reducing
operating costs for some of the buildings involved, it is
recommended that these buildings be audited for potential energy
efficiency improvements. Especially the Loussac Activity Center
has a great potential for efficiency improvements. Pump and fan
operating costs can be greatly reduced through optimization and heating costs can be reduced through a connection to the oil
fired heating system installed in the high school. Also, it should be noted that the current plans for electric heating
systems in the planned senior citizen center and low inclome housing unit will provide for very high future operating costs.
Such plans appear to ignore economic realities and they should be
changed.
2.0 FACILITY DESCRIPTION
2.1 General
This facility description is limited to facilities and items that can be considered relevant in connection with waste heat recovery in Metlakatla.
2.2 Power Plant.
The power plant is a well built and well maintained facility incorporating a 4,000 kw Caterpillar 3612 generating set. Waste
heat recapture equipment has already been incorporated into the
power plant with a horizontal core radiator providing automatic
back up cooling capacity in case the waste heat recovery system is unable to utilize all the heat generated.
2.3 The School Facilities
The school facilities to be connected to a potential waste heat recovery system include the upper and lower elementary schools, the junior high school, and the high school. These buildings all incorporate heating systems, which with some modifications will be able to accomodate waste heat. Such modifications may include
the addition of additional radiation surface, installation of heat exchangers, and replacement of some controls. Annual fuel consumption for these buildings has been estimated at 34,349
gallons.
2.4 The Loussac Activity Center
The heating system in this building is all electric with an estimated electrical consumption for heating purposes of 570,000
kwh. This has been converted to a fuel consumption of 19,500 gallons for the purpose of this study and consequently has been
assigned a value of $15,600 using a fuel price of $0.80 per
gallon. While it may be argued that the cost of the electric power used for heating is far higher, the actual value of the
heat consumed is only $15,600. This is due the fact that the
activity center could be provided with oil based heat either
through the installation of a single boiler in the building or through an interconnection to the high school's oil fired heating
system. Both conversions would be relatively inexpensive and
should be considered independent of this study.
2.5 The Council Chambers
It has been estimated that this building will use waste heat according to an estimated annual fuel consumption of 3,500
gallons.
2.6 The Clinic
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 1,500
gallons.
2.7 The Youth Center
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 1,500
gallons.
2.8 The Head Start Building
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 1,500
gallons.
2.9 The Town Hall
The utilization of waste heat in the town hall would include the
installation of separate unit heaters connected directly to the
waste heat system. The existing heating system would serve as
back up to supply heat at times when the waste heat system did not have sufficient capacity. It has been estimated that this
building will use waste heat according to an estimated annual
fuel consumption of 5,000 gallons.
2.10 The Senior Center
The connection of this building to waste heat will require the
installation of a water based heating system to replace the
planned all electric heating system. The feasibility of
installing all electric heat in a new building in Metlakatla must
be questioned. While the initial installation costs will be
lower for an all electric heating system, even the most basic
life cycle cost analysis would reveal that the cost of electric
heating over the life of the building will be several times the
cost of any other means of heating. The value of heat provided
for this building has been estimated to be equivalent to 8,000
gallons of fuel per year.
2.11 The Low Income Housing
The connection of this building to waste heat will require the
installation of a water based heating system to replace the planned all electric heating system. The feasibility of
installing all electric heat in a new building in Metlakatla must
be questioned. While the initial installation costs will be
lower for an all electric heating system, even the most basic
life cycle cost analysis would reveal that the cost of electric
heating over the life of the building will be several times the
cost of any other means of heating. The value of heat provided
for this building has been estimated to be equivalent to 8,000
gallons of fuel per year.
3.0.0 WASTE HEAT SYSTEM CONCEPTS
3.1.0 General
Waste heat system concepts that have been investigated in this
study are described here. This study does not attempt to
investigate all possible waste heat system concepts for use in
Metlakatla, but concentrates on alternatives found reasonable as a result of the Power Authority’s experience with waste heat
recapture systems.
Based on the field date collected, it seems clear to Power
Authority staff that several details are pre-determined. Thus the
differences between the concepts are limited to pipe routings,
the number of buildings connected and to some extent the method
of connection. All concepts studied would involve a system using the existing installation of exhaust gas and jacket water waste
heat equipment in the power plant. Heat would be delivered to
the user buildings through a constant output temperature,
variable flow, water based system, which feeds into an underground distribution network. The network would consist of
pre-insulated pipe using a steel carrier pipe, high density
urethane foam insulation and high density polyethylene jacket
pipe. In buildings with hydronic type heating systems, a large flat plate heat exchanger would transfer heat to the boiler
return line in the existing heating system. A simple control
valve would maintain a pre-set temperature in the existing
heating system by limiting the flow in the waste heat recovery system. With this concept the boiler would function as an
automatic back up heat source in case insufficient heat was
available from the power plant.
It is not recommended that heat is metered as "Btu-meters" have proven to be expensive and and somewhat unreliable. As all
buildings are supported by the same entity which owns Metlakatla Power and Light, metering will not be necessary. If the display
of in-kind contributions to user entities are needed, such
displays can reasonably be based on estimates of the amounts of
heat delivered.
3.2.0 Concept Al
This concept provides heat for all the above mentioned buildings through district heating lines extending from the power plant
along Walden Pt. Road, Atkinson Street, past the Head Start
Building to the school complex. From here branch lines will
connect to the proposed low income housing building and along
Hillcrest Street and across to the new senior citizen complex.
The main pipe run will most likely be 4" diameter with 2" service
lines to the three school boiler rooms and to the activity
center, the senior citizen complex, and to the low income housing
building. The pipe to the council chambers will also be of 2"
diameter and 1" service lines will be installed to all other
users. See also attached map A.
3.3.0 Concept A2
This concept will be identical to concept Al with the only
difference being the deletion of the connection to the low income
housing.
3.4.0 Concept A3
This concept will be identical to concept A2 with the only
difference being the deletion of the connection to the senior
citizen center.
3.4.0 Concept Bl.
As it has been described for concept Al, this concept will also
provide heat to the school facilities, the activity center, the
council chambers, the clinic, the youth center, the head start
building, the townhall, the senior citizen center, and to the low
income housing units. As it can be seen from map B, the main
line will extend from the power plant across the south end of the
chip dump to Airport Road and from there along the new road past
the proposed low income housing units to the corner of Skater
Lake Road and Eighth Avenue. From here a branch line along Skater
Lake Road and Hillcrest Street will connect to the proposed
senior citizen center and another branch will supply the school
facilities, the activity center, and the town hall. Another branch line will supply the council chambers along with the
clinic, the head start building, and the youth center.
3.5.0. Concept B2.
This concept is identical to concept Bl with the only difference
being the deletion of the connection to the senior citizen
center.
4.0 COST ESTIMATES
4.1 General
The cost estimates presented in this report are based on _ the following assumptions:
a.
System design follows Alaska Power Authority standards.
b.
Construction is performed by City of Metlakatla crews on a "force
account" basis with the Alaska Power Authority providing basic
engineering, some supervision and inspection, and _ start-up
assistance.
c.
All lines will be buried in existing roads where ever possible
and these roads will be re-established according to their prior state.
d.
Labor rates of approximately $15/hour have been used for cost
estimating purposes.
Note that all cost estimates are based on preliminary designs only and consequently the cost estimates should be used with
great caution.
4.2 Concept Al.
Cost estimate:
Power plant work $ 5,000
District heating piping 414,533
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., Senior C., and Low inc. 24,000
Townhall installation 5,500
Net construction $ 516,033
Job indirects, 30% 154,810
10
Construction cost $ 670,843
Overhead, 10% 67,084
Net project cost $ 737,927
Contingency, 15% 110,689
Total cost estimate $ 848,616
4.3 Concept A2.
Cost estimate:
Power plant work $ 5,000
District heating piping 353,578
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., and Senior C. 16,000
Townhall installation 5,500
Net construction $ 447,078
Job indirects, 30% 134,123
Construction cost $ 581,201
Overhead, 10% 58,120
Net project cost $ 639,321
Contingency, 15% 95,898
Total cost estimate $ 735,219
4.4 Concept A3.
Cost estimate:
Power plant work $ 5,000
District heating piping 274,705
11
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch. 8,000
Townhall installation 5,500
Net construction $ 320,466
Job indirects, 30% 96,140
Construction cost $ 416,606
Overhead, 10% 41,661
Net project cost $ 458,267
Contingency, 15% 68,740
Total cost estimate $ 527,007
4.5 Concept Bl.
Cost estimate:
Power plant work $ 5,000
District heating piping 439,759
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., Senior C., Low in. 24,000
Townhall installation 5,500
Net construction $ 541,259
Job indirects, 30% 162,378
Construction cost $ 703,637
Overhead, 10% 70,364
Net project cost $ 774,001
Contingency, 15% 116,100
12
Total cost estimate $ 890,101
4.6 Concept B2.
Cost estimate:
Power plant work $ 5,000
District heating piping 427,753
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., Low in. 16,000
Townhall installation 5,500
Net construction $ 521,253
Job indirects, 30% 156,376
Construction cost $ 677,629
Overhead, 10% 67,763
Net project cost $ 745,392
Contingency, 15% 111,809
Total cost estimate $ 857,201
13
5.0 ECONOMIC ANALYSIS
5.1 General
The economic analysis for the waste heat recapture system
concepts addressed in this report was performed using the LOTUS
1-2-3 software and the following methodology:
Based on actual power production figures for the diesel generator
together with specific technical data for the generator the
available waste heat was calculated for each hour during the year.
Based on heating degree variations for Metlakatla together with
fuel consumption data and operational characteristics provided by
the City of Metlakatla the actual heat demand was calculated for
each hour of the year.
Comparing the available heat and the demand showed how much
waste heat was actually utilized. At this point the estimated
heat loss for the district heating lines was also taken into
account. The waste heat utilized was added up hour by hour for
the entire year.
With a set of assumptions for load growth over the next 20 years,
the same operation was done for each of the next 20 years and the
annual fuel savings were derived. Based on current fuel cost and
estimated fuel cost escalation together with the cost estimates
presented in this report, a cash flow analysis and a pay _ back time were calculated for each of the concepts. Generally
speaking, the pay back time indicates the period of time during
which the project will have to operate as intended in order to
pay off the initial investment. In this study, a discount rate of
4 percent has been used. The discount rate is approximately equal
to the difference between the interest rate and the inflation
rate.
The annual operations and maintenance cost for each concept has
been estimated at 2% of the construction cost for general
operation and maintenance. (This item will be discussed in
greater detail is subsequent sections.)
Pay back times are based on the assumption that basic engineering
and construction management is provided by the Alaska Power
Authority and that all construction efforts are undertaken by the
City of Metlakatla on a "force account" basis.
5.2 Concept Al.
With the assumptions made, Concept Al shows a pay back time of 24 years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
14
heat recapture concept would have annual operation and
maintenance expenses of $16,972. Operation and maintenance
expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
5.3 Concept A2.
With the assumptions made, Concept A2 shows a pay back time of 22 years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $14,704. Operation and maintenance
expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
5.4 Concept A3.
With the assumptions made, Concept A3 shows a pay back time of 18
years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $11,847. Operation and maintenance
expenses for the boiler systems could be expected to decrease significantly due to the systems being idle.
5.5 Concept Bl.
With the assumptions made, Concept Bl shows a pay back time of 26
years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $17,802. Operation and maintenance
expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
5.6 Concept B2.
With the assumptions made, Concept B2 shows a pay back time of 30 years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $17,144. Operation and maintenance
expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
15
6.0 CONCLUSIONS
6.1 General Discussion
The power plant in Metlakatla is very well suited for the utilization of waste heat.
District heating lines would be installed preferably in existing roads in order to avoid some of the very difficult soils conditions found around Metlakatla. It should be noted that no
soils conditions have been investigated in detail, and
consequently it cannot be guaranteed that it will even be
possible to install a line through areas such as the chip dump. The cost estimates shown do not reflect any ripping of rocky soils nor do they include back filling with suitable
replacement materials.
The existing heating systems in the school can be modified for
the utilization of waste heat. All systems seem to be capable of
operating on medium grade heat, which is what is available from
the power plant. Tie-ins in the existing boiler rooms would be fairly easy, as sufficient floor space is available and relatively simple heating systems are in place.
All heating systems have been reviewed for compatibility with
waste heat recapture systems, and it appears that no major
technical obstacles will prevent the utilization of waste heat in
the buildings addressed in this report.
6.2 Conclusion
It is expected that the City would realize substantial savings in
fuel and some savings in maintenance expenses from this project. Also, it is expected that the power plant would realize some
savings from reduced station service loads. Maintenance savings
have not been quantified and consequently have no effect on the calculated pay-back time. Annual operations and maintenance
costs have been estimated at 2% of the capital cost of the
project. No technical obstacles should prevent the installation
of a waste heat recapture system utilizing waste heat from the power plant in a number of buildings. Provided that operational
procedures are not changed drastically in the power plant,
installation of a waste heat recapture system appears technically
feasible.
The concepts are similar in the sense that cost estimates are
dominated by the cost of the distribution system. While it may
be possible to reduce the cost of the distribution system through efficient installation techniques, it would not be prudent to base the cost estimates and thereby the project on such hopes.
From the anticipated time of start up of all concepts, the plant
will be capable of providing all the heating needs for all
buildings connected.
16
Due to the relatively low price of fuel, and due to the length of the necessary distribution system, the economical feasibility
appears unsatisfactory at this time. The five concepts show pay-
back times of approximately 24, 22, 18, 26, and 30 years, when an
annual fuel price escalation of 2% is used in conjunction with a
real interest rate of 4% and a fuel cost of .80$/gallon.
With the pay back times listed above, the project does not appear
to be feasible at this time. Even if a fuel cost of $1.60 was
used, the best alternative (A3) would show a pay back time of 7
years.
In accordance with the feasibility demonstrated above, it is
recommended that the project be postponed until such times when
the potential fuel savings will provide for a pay back time of no
more than 10 years. As an alternative means of reducing
operating costs for some of the buildings involved, it is
recommended that these buildings be audited for potential energy
efficiency improvements. Especially the Loussac Activity Center
has a great potential for efficiency improvements. Pump and fan
operating costs can be greatly reduced through optimization and
heating costs can be reduced through a connection to the oil
fired high school heating system.
17
Version: 88/3/16/1200
METLAKATLA WASTE HEAT SYSTEM FEASIBILITY ANALYSIS
TABLE OF CONTENTS:
EXECUTIVE SUMMARY 1.0
Introduction and Background
Conclusions BPR Nr FACILITY DESCRIPTION ND °o General
Power plant
The School facilities
The Loussac Activity Center
The Council Chambers
The Clinic
The Youth Center
The Head Start Building
The Townhall
The Senior Center
The Low Income Housing NNMONNNNNNND NN PR: : FPODCMYNDAUEWNHE WASTE HEAT SYSTEM CONCEPTS Ww °o General
Concept Al
Concept A2
Concept A3
Concept Bl
Concept B2 WWWWWW DAUFWNrR COST ESTIMATES oO General
Concept Al
Concept A2
Concept A3
Concept Bl
Concept B2 PREEEHE FF DUPWNeE ECONOMIC ANALYSIS 5.0
General
Concept Al awn el
Concept A2
Concept A3
Concept Bl
Concept B2
CONCLUSIONS
General Discussions
Conclusions wan ano Le el Aufw
1.0 EXECUTIVE SUMMARY
1.1 Introduction and Background
In the fall of 1987 Metlakatla Light and Power (ML&P) requested
that the Alaska Power Authority investigate the feasibility of
utilizing waste heat from its power plant for heating public
buildings in Metlakatla including the local _ schools. Power Authority staff made a visit to Metlakatla where the facilities
were audited for compatibility with waste heat recovery systems.
Based on the information gathered, five concepts for waste heat
recovery systems were developed. For each concept a preliminary
cost estimate and the pay back time were calculated with a Lotus
1-2-3 program using relevant climatic and statistical data. This
program simulates the operation of a waste heat recapture system
over the life span of the project.
This study does not include detailed engineering data such as
soils conditions, local availability of skilled labor and local
experience in undertaking construction projects. Thus, the cost
estimates should be used with great caution. The economic
analysis of system performance over the life span of the project
is fairly accurate, provided that prudent maintenance is
performed on the system.
1.2 Conclusions
It is expected that the City would realize substantial savings in
fuel and some savings in maintenance expenses from this project. Also, it is expected that ML&P would realize some savings from
reduced station service loads. Maintenance savings have not been
quantified and consequently have no effect on the calculated pay-
back time. Annual operations and maintenance costs have been
estimated at 2% of the capital cost of the project. No technical
obstacles should prevent the installation of a waste heat
recapture system utilizing waste heat from the power plant in a
number of buildings. Provided that operational procedures are not changed drastically in the power plant, installation of a
waste heat recapture system appears technically feasible.
However, due to the relatively low price of fuel, and due to the length of the necessary distribution system, the economical
feasibility appears unsatisfactory at this time. The five
concepts show pay-back times of approximately 24, 22, 18, 26, and
30 years, when an annual fuel price escalation of 2% is used in conjunction with a real interest rate of 4% and a fuel cost of
0.80$/gallon.
In accordance with the feasibility outlined above, it is
recommended that the project be postponed until such times when the potential fuel savings will provide for a pay back time of no more than 10 years. As an alternative means of reducing
operating costs for some of the buildings involved, it is recommended that these buildings be audited for potential energy
efficiency improvements. Especially the Loussac Activity Center
has a great potential for efficiency improvements. Pump and fan
operating costs can be greatly reduced through optimization and heating costs can be reduced through a connection to the oil fired heating system installed in the high school. Also, it should be noted that the current plans for electric heating
systems in the planned senior citizen center and low inclome
housing unit will provide for very high future operating costs.
Such plans appear to ignore economic realities and they should be
changed.
2.0 FACILITY DESCRIPTION
2.1 General
This facility description is limited to facilities and items that
can be considered relevant in connection with waste heat recovery
in Metlakatla.
2.2 Power Plant.
The power plant is a well built and well maintained facility
incorporating a 4,000 kw Caterpillar 3612 generating set. Waste
heat recapture equipment has already been incorporated into the
power plant with a horizontal core radiator providing automatic
back up cooling capacity in case the waste heat recovery system
is unable to utilize all the heat generated.
2.3 The School Facilities
The school facilities to be connected to a potential waste heat
recovery system include the upper and lower elementary schools,
the junior high school, and the high school. These buildings all
incorporate heating systems, which with some modifications will
be able to accomodate waste heat. Such modifications may include
the addition of additional radiation surface, installation of
heat exchangers, and replacement of some controls. Annual fuel
consumption for these buildings has been estimated at 34,349
gallons.
2.4 The Loussac Activity Center
The heating system in this building is all electric with an
estimated electrical consumption for heating purposes of 570,000
kwh. This has been converted to a fuel consumption of 19,500
gallons for the purpose of this study and consequently has been
assigned a value of $15,600 using a fuel price of $0.80 per
gallon. While it may be argued that the cost of the electric
power used for heating is far higher, the actual value of the
heat consumed is only $15,600. This is due the fact that the
activity center could be provided with oil based heat either
through the installation of a single boiler in the building or
through an interconnection to the high school's oil fired heating
system. Both conversions would be relatively inexpensive and
should be considered independent of this study.
2.5 The Council Chambers
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 3,500
gallons.
2.6 The Clinic
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 1,500
gallons.
2.7 The Youth Center
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 1,500
gallons.
2.8 The Head Start Building
It has been estimated that this building will use waste heat
according to an estimated annual fuel consumption of 1,500
gallons.
2.9 The Town Hall
The utilization of waste heat in the town hall would include the
installation of separate unit heaters connected directly to the waste heat system. The existing heating system would serve as
back up to supply heat at times when the waste heat system did not have sufficient capacity. It has been estimated that this building will use waste heat according to an estimated annual
fuel consumption of 5,000 gallons.
2.10 The Senior Center
The connection of this building to waste heat will require the installation of a water based heating system to replace the planned all electric heating system. The feasibility of installing all electric heat in a new building in Metlakatla must be questioned. While the initial installation costs will be lower for an all electric heating system, even the most basic life cycle cost analysis would reveal that the cost of electric heating over the life of the building will be several times the cost of any other means of heating. The value of heat provided
for this building has been estimated to be equivalent to 8,000 gallons of fuel per year.
2.11 The Low Income Housing
The connection of this building to waste heat will require the installation of a water based heating system to replace the planned all electric heating system. The feasibility of installing all electric heat in a new building in Metlakatla must
be questioned. While the initial installation costs will be lower for an all electric heating system, even the most basic life cycle cost analysis would reveal that the cost of electric heating over the life of the building will be several times the cost of any other means of heating. The value of heat provided for this building has been estimated to be equivalent to 8,000 gallons of fuel per year.
3.0.0 WASTE HEAT SYSTEM CONCEPTS
3.1.0 General
Waste heat system concepts that have been investigated in this study are described here. This study does not attempt to
investigate all possible waste heat system concepts for use in
Metlakatla, but concentrates on alternatives found reasonable as a result of the Power Authority's experience with waste heat recapture systems.
Based on the field date collected, it seems clear to Power Authority staff that several details are pre-determined. Thus the differences between the concepts are limited to pipe routings, the number of buildings connected and to some extent the method of connection. All concepts studied would involve a system using the existing installation of exhaust gas and jacket water waste heat equipment in the power plant. Heat would be delivered to the user buildings through a constant output temperature,
variable flow, water based system, which feeds into an underground distribution network. The network would consist of pre-insulated pipe using a steel carrier pipe, high density urethane foam insulation and high density polyethylene jacket pipe. In buildings with hydronic type heating systems, a large flat plate heat exchanger would transfer heat to the boiler return line in the existing heating system. A simple control valve would maintain a pre-set temperature in the existing heating system by limiting the flow in the waste heat recovery system. With this concept the boiler would function as an automatic back up heat source in case insufficient heat was
available from the power plant.
It is not recommended that heat is metered as "Btu-meters" have proven to be expensive and and somewhat unreliable. As all buildings are supported by the same entity which owns Metlakatla Power and Light, metering will not be necessary. If the display of in-kind contributions to user entities are needed, such
displays can reasonably be based on estimates of the amounts of heat delivered.
3.2.0 Concept Al
This concept provides heat for all the above mentioned buildings through district heating lines extending from the power plant
along Walden Pt. Road, Atkinson Street, past the Head Start Building to the school complex. From here branch lines will connect to the proposed low income housing building and along Hillcrest Street and across to the new senior citizen complex. The main pipe run will most likely be 4" diameter with 2" service lines to the three school boiler rooms and to the activity
center, the senior citizen complex, and to the low income housing building. The pipe to the council chambers will also be of 2" diameter and 1" service lines will be installed to all other
users. See also attached map A.
3.3.0 Concept A2
This concept will be identical to concept Al with the only
difference being the deletion of the connection to the low income
housing.
3.4.0 Concept A3
This concept will be identical to concept A2 with the only
difference being the deletion of the connection to the senior
citizen center.
3.4.0 Concept Bl.
As it has been described for concept Al, this concept will also
provide heat to the school facilities, the activity center, the
council chambers, the clinic, the youth center, the head start
building, the townhall, the senior citizen center, and to the low
income housing units. As it can be seen from map B, the main
line will extend from the power plant across the south end of the
chip dump to Airport Road and from there along the new road past
the proposed low income housing units to the corner of Skater Lake Road and Eighth Avenue. From here a branch line along Skater
Lake Road and Hillcrest Street will connect to the proposed senior citizen center and another branch will supply the school
facilities, the activity center, and the town hall. Another branch line will supply the council chambers along with the clinic, the head start building, and the youth center.
3.5.0. Concept B2.
This concept is identical to concept Bl with the only difference being the deletion of the connection to the senior citizen center.
4.0 COST ESTIMATES
4.1 General
The cost estimates presented in this report are based on _ the
following assumptions:
a.
System design follows Alaska Power Authority standards.
b.
Construction is performed by City of Metlakatla crews on a "force
account" basis with the Alaska Power Authority providing basic
engineering, some supervision and inspection, and start-up
assistance.
c.
All lines will be buried in existing roads where ever possible
and these roads will be re-established according to their prior state.
d
Labor rates of approximately $15/hour have been used for cost
estimating purposes.
Note that all cost estimates are based on preliminary designs
only and consequently the cost estimates should be used with
great caution.
4.2 Concept Al.
Cost estimate:
Power plant work $ 5,000
District heating piping 414,533
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., Senior C., and Low inc. 24,000
Townhall installation 5,500
Net construction $ 516,033
Job indirects, 30% 154,810
10
Construction cost $ 670,843
Overhead, 10% 67,084
Net project cost $ 737,927
Contingency, 15% 110,689
Total cost estimate $ 848,616
4.3 Concept A2.
Cost estimate:
Power plant work $ 5,000
District heating piping 353,578
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., and Senior C. 16,000
Townhall installation 5,500
Net construction $ 447,078
Job indirects, 30% 134,123
Construction cost $ 581,201
Overhead, 10% 58,120
Net project cost $ 639,321
Contingency, 15% 95,898
Total cost estimate $ 735,219
4.4 Concept A3.
Cost estimate:
Power plant work $ 5,000
District heating piping 274,705
11
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch. 8,000
Townhall installation 5,500
Net construction $ 320,466
Job indirects, 30% 96,140
Construction cost $ 416,606
Overhead, 10% 41,661
Net project cost $ 458,267
Contingency, 15% 68,740
Total cost estimate $ 527,007
4.5 Concept Bl.
Cost estimate:
Power plant work $ 5,000
District heating piping 439,759
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., Senior C., Low in. 24,000
Townhall installation 5,500
Net construction $ 541,259
Job indirects, 30% 162,378
Construction cost $ 703,637
Overhead, 10% 70,364
Net project cost $ 774,001
Contingency, 15% 116,100
12
Total cost estimate $ 890,101
4.6 Concept B2.
Cost estimate:
Power plant work $ 5,000
District heating piping 427,753
School facilities installation 41,000
LAC installation 12,500
Clinic, Youth Center, and Head Start 13,500
Council Ch., Low in. 16,000
Townhall installation 5,500
Net construction $ 521,253
Job indirects, 30% 156,376
Construction cost $ 677,629
Overhead, 10% 67,763
Net project cost $ 745,392
Contingency, 15% 111,809
Total cost estimate $ 857,201
13
5.0 ECONOMIC ANALYSIS
5.1 General
The economic analysis for the waste heat recapture system
concepts addressed in this report was performed using the LOTUS
1-2-3 software and the following methodology:
Based on actual power production figures for the diesel generator
together with specific technical data for the generator the
available waste heat was calculated for each hour during the
year.
Based on heating degree variations for Metlakatla together with
fuel consumption data and operational characteristics provided by
the City of Metlakatla the actual heat demand was calculated for
each hour of the year.
Comparing the available heat and the demand showed how much
waste heat was actually utilized. At this point the estimated
heat loss for the district heating lines was also taken into
account. The waste heat utilized was added up hour by hour for
the entire year.
With a set of assumptions for load growth over the next 20 years,
the same operation was done for each of the next 20 years and the
annual fuel savings were derived. Based on current fuel cost and
estimated fuel cost escalation together with the cost estimates
presented in this report, a cash flow analysis and a pay back
time were calculated for each of the concepts. Generally
speaking, the pay back time indicates the period of time during
which the project will have to operate as intended in order to
pay off the initial investment. In this study, a discount rate of
4 percent has been used. The discount rate is approximately equal
to the difference between the interest rate and the inflation
rate.
The annual operations and maintenance cost for each concept has
been estimated at 2% of the construction cost for general
operation and maintenance. (This item will be discussed in
greater detail is subsequent sections.)
Pay back times are based on the assumption that basic engineering
and construction management is provided by the Alaska Power
Authority and that all construction efforts are undertaken by the City of Metlakatla on a "force account" basis.
5.2 Concept Al.
With the assumptions made, Concept Al shows a pay back time of 24
years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
14
heat recapture concept would have annual operation and
maintenance expenses of $16,972. Operation and maintenance
expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
5.3 Concept A2.
With the assumptions made, Concept A2 shows a pay back time of 22 years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $14,704. Operation and maintenance expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
5.4 Concept A3.
With the assumptions made, Concept A3 shows a pay back time of 18 years. All heating needs for the buildings can be met during the first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $11,847. Operation and maintenance
expenses for the boiler systems could be expected to decrease significantly due to the systems being idle.
5.5 Concept Bl.
With the assumptions made, Concept Bl shows a pay back time of 26 years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste heat recapture concept would have annual operation and
maintenance expenses of $17,802. Operation and maintenance expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
5.6 Concept B2.
With the assumptions made, Concept B2 shows a pay back time of 30 years. All heating needs for the buildings can be met during the
first year of operation and it is anticipated that this waste
heat recapture concept would have annual operation and
maintenance expenses of $17,144. Operation and maintenance
expenses for the boiler systems could be expected to decrease
significantly due to the systems being idle.
15
6.0 CONCLUSIONS
6.1 General Discussion
The power plant in Metlakatla is very well suited for the
utilization of waste heat.
District heating lines would be installed preferably in existing
roads in order to avoid some of the very difficult soils
conditions found around Metlakatla. It should be noted that no
soils conditions have been investigated in detail, and
consequently it cannot be guaranteed that it will even be
possible to install a line through areas such as the chip dump.
The cost estimates shown do not reflect any ripping of rocky
soils nor do they include back filling with suitable
replacement materials.
The existing heating systems in the school can be modified for
the utilization of waste heat. All systems seem to be capable of
operating on medium grade heat, which is what is available from
the power plant. Tie-ins in the existing boiler rooms would be
fairly easy, as sufficient floor space is available and
relatively simple heating systems are in place.
All heating systems have been reviewed for compatibility with
waste heat recapture systems, and it appears that no major
technical obstacles will prevent the utilization of waste heat in
the buildings addressed in this report.
6.2 Conclusion
It is expected that the City would realize substantial savings in
fuel and some savings in maintenance expenses from this project.
Also, it is expected that the power plant would realize some
savings from reduced station service loads. Maintenance savings
have not been quantified and consequently have no effect on the
calculated pay-back time. Annual operations and maintenance
costs have been estimated at 2% of the capital cost of the
project. No technical obstacles should prevent the installation
of a waste heat recapture system utilizing waste heat from the
power plant in a number of buildings. Provided that operational
procedures are not changed drastically in the power plant,
installation of a waste heat recapture system appears technically
feasible.
The concepts are similar in the sense that cost estimates are dominated by the cost of the distribution system. While it may
be possible to reduce the cost of the distribution system through
efficient installation techniques, it would not be prudent to
base the cost estimates and thereby the project on such hopes.
From the anticipated time of start up of all concepts, the plant
will be capable of providing all the heating needs for all
buildings connected.
16
Due to the relatively low price of fuel, and due to the length of
the necessary distribution system, the economical feasibility
appears unsatisfactory at this time. The five concepts show pay-
back times of approximately 24, 22, 18, 26, and 30 years, when an
annual fuel price escalation of 2% is used in conjunction with a
real interest rate of 4% and a fuel cost of .80$/gallon.
With the pay back times listed above, the project does not appear
to be feasible at this time. Even if a fuel cost of $1.60 was
used, the best alternative (A3) would show a pay back time of 7
years.
In accordance with the feasibility demonstrated above, it is
recommended that the project be postponed until such times when
the potential fuel savings will provide for a pay back time of no
more than 10 years. As an alternative means of reducing
operating costs for some of the buildings involved, it is
recommended that these buildings be audited for potential energy
efficiency improvements. Especially the Loussac Activity Center
has a great potential for efficiency improvements. Pump and fan
operating costs can be greatly reduced through optimization and
heating costs can be reduced through a connection to the oil
fired high school heating system.
17