HomeMy WebLinkAboutTuluksak Correspondence 1989NA Yupiit School District AD fre? | ‘ P.O. Box 100
Akiachak, Alaska 99551
(907) 825-4428 or 825-4127
RECEIVED
APR 2 7 1992
ALASKA ENERGY AUTHORITY
April 22, 1992
Sue White
Alaska Energy Commission
P.O. Box 190869
Anchorage, Alaska 99519-0869
Dear Sue:
The purpose of this letter is to request that you send an engineer from your
organization to inspect the recently completed electrification and waste heat
recovery project at Tuluksak Schools.
Mr. Bob Shipley of Community and Regional Affairs suggested that I contact you
and request that an engineer come out and complete an inspection of the electrical
and waste heat recovery work just completed in Tuluksak. After inspection, the
engineer needs to write a status report for me so I can file a claim for payment of funds from community and regional affairs.
Please give this request your immediate attention.
Professionally yours,
bh phmer—
And Doha
Superintendent
LLD:ar
cc: Ivan M. Ivan, Representative
Lyman Hoffman, Senator
Yaw 0
&
{ yy
Cha WW
Serj l- itis 1989.
The Honcrable Mayor John Peter
City of Tuluksak
General Delivery
Tuluksaks Alaska 9797679
Subject: Generator and equipment prices.
Dear Mayor Peter:
4s requested during the meeting of April 3> I have investigated
the prices for a suitable back up generator set and same spare
equipment.
it appears that the electrical loads in Tuluksak are very !ighti
the highest reading which I have seen is SO kw. I would strangly
Suggest that we instal! a temperary; recording kw-meter on the
power plant prior to purchasing any new generator. Currently we
have such a meter installed on the power house in Akiaks and once
we are done with it there, I will be happy ta install Pi be
Tuluksak.
It would appear that a 100 kw generator or similar would be more
than sufficient as a stand-by machine in Tuluksak. Such a unit
can be purchased for approximately $20,000, and it we include
freight and installation» $25,000 would be a reasonable figure.
Please note that the Power Authority will be happy to provide
bidding and selection services for you at no cost tao you. That
way you will be assured that you get the right equipment at the
right price.
As far as transformers, conductors» suy wire» and other spare
parts is concerned, $10,000 should buy you a reasonable stock af
relevant spareparts. Again» we would be happy to assists you with
selecting relevant spare parts. We are currently in the process
o¢ setting up contracts with vendors for a variety of equipment,
and it may be advantageous far you to utilize the discounts that
these contracts wil! provide for.
It the City of Tuluksak elects not to purchase whalesale pawer
from the Yupiit School District, l would recommend that the
Detroit generator be equipped with a new engine in arder ta give
the City tree operable generators. The price of the right engine
would be approximately $10,00C.
in other words, a total of $45,000 should enable you to get the
power plant into a shapes, which wil! allow for reasonable
reliability. However, it should be noted that a couple of problems remain ta be salvedi the fue! tank is not diked
sufficient!y» and the power plant is somewhat of a tire hazard.
If there is anything else | can do for yours please do nat
hesitate to contact me. a
Sincerely,
Peter
Rural
N. Hansen
Systems Engineer. 3
a baa Tuilicisarmute IRA council 3
: General Delivery es gs
#3 Tuluksak, Alaska 99679. Telephone (907) 695-6313
ae
Resolution 89-10-7
Where as, Tuluksak, City Council, with the consent of its
“Council members turn over.Certificate of Conveyance _ over to Sate IRA Council.
miaiear mate: IRA: Council; accept the> Certificate.
onveyanceturn, over: ‘by: Tuluksak: City, counci
to its community member j
accepted: “‘to,mainta n°and: provide Village “Powe
Now thereiors Be it. Boaolved:. that: the Partificaty of Convey-'
- 4 ance. ‘accepted: by® Tulkisarmute IRA Council, be’ ap- :
proved and -aCcepted. ‘by Alaska Public Utilities Can to _ Provide service to” the’ community . eM : ‘
Motion Passed and ‘Approved by Tuluksak City Council, ea
“ Tulkisarmute - IRA Council, on this 7th ey Of .3 ee oe
‘October, 1989s - ; Se =
0 ,Mayor Oy Ailes,’ a Lied wick
uksak City Council Tulkisarmute IRA’Council
Tulkisarmute IRA Council
Secretary Work ding , Secretary
STEVE COWPER, GOVERNOR
DEPT. OF COMMUNITY & REGIONAL AFFAIRS Ural Development Division 949 E. 36th Ave. #402
Anchorage, AK 99508
(907) 563-1073
Telefax: (907) 563-1734
November 9, 1989
Mr. Roger Helmer
Assistant Superintendent
Yupiit School District
Box 100
Akiachak AK 99551
Dear Mr. Helmer:
This letter is in reference to the requested amendment to ECM number 22 as contained in contract number 2192104 relating to the Tuluksak Elementary School. (submitted by Peter Hansen on behalf of the Yupiit School District)
The amendment appears to conform to the initial approved concept with the added advantage of increased generation
efficiency. Therefore the amendment is approved as requested contingent upon the following conditions:
1. The total cost charged to contract 2192104 to emplement ECM number 22 shall not exceed $125,755.00.
2. The total design cost charged to contract 2192104 to
emplement ECM number 22 shall not exceed $14545.00
3. The total combined cost charged to contract 2192104 for
design and installation shall not exceed $25,000.
Please note, seperate accounting must be maintained for design
cost. I mention this because according to Peter Hansen design
cost were included as part of the installation cost in the
amendment request.
This letter of approval becomes part of contract 2192104 and
should be filed accordingly.
If you have any questions please contact me at 273-9456 or FAX 563-1734,
Sincerely:
_—_ fa
Toy C. Owen Jr. ICP Program Manager
cc
Ala Authority
tco/1614P
Adams, Morgenthaler and Company
TING ENGINEERS 3333 DENALI, SUITE 201
— ANCHORAGE, AK 99503
(907) 279-0431
FAX (907)272-5593
July 27, 1989
Mechanical Piping Contractors
P.O. Box 771396
Eagle River, AK 99577
ATTN: Mr. Ralph Fuller
RE: Tuluksak Water System (89128)
SUBJ: Letter from Alaska Energy Authority Dated July 10, 1989
Gentlemen:
This letter is in regard to the letter from Mr. Donald L. Shira, Director of Program Development and Facilities Operations for Alaska Energy Authority to yourself which offers comments on our design drawings for the above noted project. We would like to offer the following concerning Mr. Shira's comments.
Drawing M2
Mr. Shira's Comment:
1. This drawing offers no information to substantiate the need for 67 gpm pressure pumps with 140 ft. of head capacity. In order to reduce system wide voltage drops in connection with the start of these pumps, it is important to size these pumps as small as possible and to install reduced voltage motor starters.
AMC Response:
Water demand load calculations are typically not included on project construction drawings. The demand calculations were based on actual fixture counts and UPC sizing methods. The pump head was established using estimated flow rates, actual site specific routing lengths and branch pipe sizes of existing service lines to be connected.
AN ALASKAN CORPORATION
Mechanical Piping Contractors
July 27, 1989 page 2
Mr.
Mr.
Please note on Sheet E-1, Detail 1, the note identifying Pumps 1A and 1B states to provide Cutler-Hammer Type 515 solid state reduced voltage combination starters for Pumps 1A and 1B. These starters are easily field adjustable to provide the desired starting characteristics. Also please note that per Note at right side of Sheet E-1 time delay relays are being provided for Pumps 1A, 1B, 2, the Filtration System Circulation Pump and the Ozone System to prevent these loads from all coming on-line at the same time. These loads will be sequentially started with a minimum separation of 15 seconds.
Shira's Comment:
It would be prudent to utilize two or three smaller pressure pumps with independent controls adjusted to activate the pumps at different pressure levels.
Response:
Additional pumps will add to the first cost of the system and increase the overall maintenance requirement of the system. In addition a compromise in system reliability maybe realized with the added mechanical equipment. We feel the electrical design pointed out in AMC response #1 above is an excellent system of protecting the overall power quality in the village.
Shira's Comment:
Considering the real cost of power in rural communities it would be prudent to preheat the water with heat from the school's heating system prior to transfer to the high school and consequently utilize electric heat tracing for emergencies only. System peak loads are typically encountered during periods of extreme cold and any addition of load during such periods is highly undesirable.
Response:
The type of heat tracing used is the self-limiting type, i.e., during higher ambient temperatures its resistance increases reducing the amount of energy required. During cold periods the heat trace's resistance decreases increasing the tapes output as required. The heat trace design is a very cost effective way of protecting the utilidor water piping.
Mechanical Piping Contractors July 27, 1989
page 3
Mr. Shira's Comment:
4. This drawing offers no information on the proposed ozone treatment system; the appropriateness of system sizing cannot be verified.
AMC Response:
System sizing of the ozone has been prepared by registered engineers at Kramer Chin and Mayo (KCM) specializing in water treatment systems. Sizing calculations are not typically part of a construction drawing presentation.
Drawing El
Mr. Shira's Comment:
5. This drawing offers no information in reference to the types of equipment included in the ozone treatment system or the inrush currents which can be expected. Also, no information is offered concerning estimated power consumption per gallon or per year.
AMC Response:
Supplementary information provided by Mechanical Piping Contractors to the Yupiit School District describes the treatment system in greater detail. Estimated power consumption was also included.
Mr. Shira's Comment:
6. General Comments: The design as presented may be one solution to the water problems encountered in Tuluksak; however, no information has been offered to substantiate that it is the best solution. It is obvious that this system will have very significant impacts on the power system in Tuluksak, and depending on the usage pattern by the ozone treatment system, it is conceivable that this system will cause the quality of power to deteriorate. It is simply not desirable to instantaneously add loads of this magnitude to a system where the total load at times will be 50 kw or less.
System peak loads can be expected to increase by 25 kw not counting motor starting peaks, and this necessitates the continuous operation of an additional 25 kw of spinning
Mechanical Piping Contractors
July 27, 1989
page 4
capacity. As total run time will be limited, the overall load factor of the electrical system will be reduced resulting in reduced fuel efficiency and increased operations and maintenance cost per kilowatt-hour produced.
In order to avoid a situation where a water system problem is simply changed to a power system problem, it is recommended that alternative and less power consuming solutions be investigated prior to the final selection of a system concept.
Response:
As noted in our response to Comment Number 1 reduced voltage starters are utilized for Pumps 1A and 1B to minimize starting peaks and the loads noted are sequenced on to minimize their impact on the power system. Please keep in mind that the pumps and any appurtenances would be required for any type water systen.
The appropriateness of an ozone treatment system has been reviewed and confirmed by the design engineers at KCM. Ozone treatment reportedly shows significant potential improvement above the standard chemical treatment system in Tuluksak (and other sites) which has not been in compliance with drinking water standards for many years. If this all comes down to a question of safe reliable water versus a few incremental kw of power, our vote is for the water systen.
Please contact us at your convenience if we may offer further comments.
Sincerely,
ADAMS, MORGENTHALER AND COMPANY
Boyd Morgenthaler, P.E. Mechanical Engjfeer
89128/let90727
Pye
¢
P.O. Box v. State Capitol
Juneau, Alaska 99811 JOBS BILL CAPITALWPROJECT REQUEST
PROJECT NAME: Electrical Upgrade Project
Official Business
LOCATION: Tuluksak ELECTION oDIsTRict: 24
FUNDING:
General Funds $_150,000 Other Funds (specify type) $
APPROPRIATION METHOD (select one): (a) To a State Agency:
(b) As a Municipal Grant: city of Tuluksak (All municipal grants go through the Department of Adminstration. Specify which city or borough is to be recipient.)
(c) As an Unincorporated Community Grant:
(All unincorporated community grants go through the Department of ) Community and Regional Affairs. Specify community)
PROJECT DESCRIPTION:
Replace existing untreated non-standard poles with utility grade treated poles, transfer existing transformers and install new lines, add yard poles and building service masts, install additional transformers, tightening and addition of anchors, install Street lights, inspect and correct safety problems and demolish old distribution system. HOW PROJECT MEETS JOBS BILL CRITERIA: Local labor will perform the work (approximately $65,000 labor costs). Project is a number one priority for safety reasons. It can be completed the summer of 1988. The electrical system will be brought up to Rural Electrification Administration and National Electrical Safety Code standards. Neutral impact or reduction in operating costs. Current system is dangerous to the health and safety of the community.
.
REQUESTING LEGISLATORS’ SIGNATURES: SoG ah
Date: Retum completed forms to your respective Finance Committee,Senator Rick Halford in room 516, or Representative Pat Pourchot in room 511.
STANDARD AGREEMENT FORM
FOR MUNICIPAL GRANTS
1G"
This agreement is executed between the State of Alaska, Department of
Administration (Hereinafter called the "State"), and Tuluksak (Hereinafter
called the “Grantee"),
WITNESSETH that: Whereas, the Grantee is willing to undertake the performance of this grant
under the terms of this agreement;
Whereas, the municipality has the authority under the State law or local
charter to provide the services for which funds were appropriated;
Whereas, the State has the authority to enter into this agreement by
AS 37.05.315;
Whereas, funding for this grant lapses
X on lapse date October 30, 1989
upon completion of the project;
Whereas, the grant #7/88-660 of $150,000 is for the purpose of Electrical
System Safety Upgrade (please, provide further explanation and details in the
space provided);
Crna #7/s6-bbo oF *50,100.00 wite be sed. To prrchase
electrical moter: als AZ Umves Trans tevmers STreT
Lights, and Other tle crivel matiriels t> meet i
Safety upgrade needs of the QiTy oF ToLoles 2
phlhe PMs
Page 1 of 4
1/1K2/0715-86/1
(Rev. 7/87)
asineinaAnr Ars1
City Of Tuluksak
General Delivery ¢ Tuluksak, Alaska 99679
Phone 907-695-6212
ait feselalcn NO F4-1
hie xe Che gerd eseloten by the Ot -
Counerd | RA Comune , Tulhrsarsnmd tne, ark
the yapeef Scheuf Malic tL > AgromnenT
prepecal te the vibfage Ragidork GY Trlubs sh,
Crank est Coun l, GitthisasmnrAe LHe.
ec The fraticf detdetD ela, eo
Tikuberal’ anf
WHEREAS, the purchase of electricity from the Yupiit School
District would be beneficial to the City of Tuluksak and its
citizens.
THEREFORE BE IT RESOLVED, that the City Council of Tuluksak agrees
to enter into a Power Sales Agreement contract with the Yupiit
School District as appended to this resolution.
4
Passed this 234 day of Al py. / , 1989 at Tuluksak, Alaska.
<7 / ) . Ans let SNe
founcil Member J
CL tun be we + Vite Prosi dent
Council Member
—— Council Member
Zz 6H S. Yeh tf Lj, begs sfm
Council Member
Ltr, 2M Cheyer. ncil Member
Abstd Sy vesidals 7
fRO ot?
sd. p5o
oD ho 30 —~ pha. ACD ND Ty
a, AO Dodd [RO Oo \ c Ces Ky Benne
cA - DrniT lo yo oky / CPR
3. @ 4 ~ of po “Ae 1 4 A. Ao | Y\ ai”
> we >
TULUKSAK PROJECT AGREEMENT
THIS AGREEMENT, entered into this /2 day of » 1989,
between the CITY OF TULUKSAK (the City), and the ALASKA POWPR AUTHORITY
(the Power Authority), outlines the responsibilities of the parties and
the procedures to be followed in connection with the upgrade and
completion and the future operation of the Tuluksak Power Distribution
and Generation System Upgrade, Project (the Project). This Agreement
represents the entire agreement between the parties and may only be
modified by the mutual consent of both parties in writing.
Article A. ALASKA POWER AUTHORITY COVENANTS
The Power Authority will:
1. On behalf of the City, engage an accounting firm that will
receive funds for the Project, disburse funds for the payment of
obligations, and provide record and bookkeeping services associated with
administration of the Project, including preparation of all federal,
State and other reports related to payroll, such as taxes, insurance,
unemployment, pension, health and welfare fund contributions. The Power
Authority will serve as liaison between the City and the bookkeeping
firm in providing approved invoices and time sheets for payment. The
fees charged by the accounting firm for this service are to be paid from
the funds described in Paragraph 2 below.
2. Request of the Department of Administration (DOA), on behalf
of the City, that the DOA forward the remaining balance of $120,000 of
Grant No. 7/88-660 (Encumbrance No. 2280451) to the accounting firm
described in Paragraph 1 above for the purpose of meeting expenditures
related to the Project. A copy of the DOA grant agreement appears in
Appendix A.
3. Expend funds from the Rural Technical Assistance Program (SLA
88, CH 173, PG 38, LN 20, LC 81824108) to cover Power Authority expenses
incurred in performance of this Agreement, including the following:
(i) Direct and indirect labor expense.
(ii) Non-personal services costs distributed on the basis of direct
labor hours according to Power Authority standard accounting procedures.
(iii) Travel expenses incurred for transportation, food, lodging,
and related incidental travel costs.
4. Provide advice and assistance to the City on administrative,
management, and technical matters relating to the completion of the
Project, as described in the project request at Appendix A; serve as the
City's agent for the design and construction management of the Project;
perform a final inspection of the Project upon completion; and issue a
notice of Project completion.
5410/956/(1)
Tuluksak Project _reement
Page 2 of 7
5. On behalf of the City, negotiate a pole sharing agreement with
United Utilities, Inc., to allow the City's conductors, transformers,
and hardware to be suspended from United Utilities' poles for the life
of Project facilities. This pole sharing agreement will be negotiated
in accordance with the guidelines established by the Alaska Public
Utilities Commission. If a mutually acceptable pole sharing agreement
cannot be negotiated, the Power Authority may terminate this Agreement
in accordance with the provisions of Article C, Paragraph 2.
6. Assist the City with operational difficulties of the Project,
if needed, for one year after completion. This covenant pertains only
to items that would normally be covered by a contractor's warranty and
does not include items normally considered as routine maintenance. The
Power Authority will have sole discretion over whether assistance is
needed and when assistance will be provided under this paragraph.
Article B. CITY OF TULUKSAK COVENANTS
The City will:
1. Obtain all titles, easements and other approvals necessary to
provide clear title and to establish the City's legal right and author-
ity to construct, maintain, and operate the Project and its facilities
and provide the Power Authority with proof of such titles, easements and
other approvals from Tuluksiarmute, Inc.
2. Ensure that the Power Authority and its contractors and
consultants have reasonable access to Project facilities, records, and
materials previously purchased for the Project during construction of
the Project and to Project facilities and records over the life of
Project facilities for performance analysis and testing.
3. Designate the Power Authority as its agent in the design and
construction management of the Project and delegate to the Power
Authority full authority over all decisions in connection with construc-
tion, start-up, and run-in of the Project, including approval of plans
and specifications; choices of scheduling, manpower, methods, procure-
ment, materials, and procedures for the Project; performance of final
inspection; and issuance of a notice of Project completion.
4, Authorize the Power Authority, on behalf of the City, to
procure the bookkeeping services described in Article A, Paragraph 1,
and authorize the bookkeeping service to perform the services described
therein, on the City's behalf, including payment of invoices and time
sheets approved by the Power Authority.
5. By virtue of authorizing the bookkeeping service to perform,
in accordance with Paragraph 4 above, accept responsibility for all
grant funds disbursed under this Agreement, including, where applicable,
payment of all payroll and other taxes and Workman's Compensation. In
addition, the City will accept responsibility for acquisition of
appropriate general liability insurance coverage.
5410/956/ (2)
Tuluksak Projeci jreement
Page 3 of 7
6. Authorize the Power Authority to request funding for the
Project from the DOA as described in Article A, Paragraph 2 and ensure that said funds are expended only for the purposes provided for under this Agreement and in accordance with the DOA grant agreement in
Appendix A,
7. Account for the funds received from the DOA as contributions-
in-aid of construction and, therefore, refrain from including those
funds or property acquired with those funds in future rate base calcu- lations.
8. Except for sales taxes in force at the time of entering into
this Agreement, refrain from levying any taxes or fees or any require-
ments for licenses, permits, or certificates of any kind, for any
purpose, from any vendor, consultant, contractor, or any other entity
involved with the Project. The City agrees to give full and final
authority to the Power Authority to resolve any dispute between the City
and any other entity involved with the Project over the applicability of
this paragraph in any given situation.
9. Authorize the Power Authority to negotiate a pole sharing
agreement with United Utilities, Inc. on behalf of the City, as
described in Article A, Paragraph 5.
10. Refrain from asserting tribal sovereignty as a defense against
enforcement of the City's obligations under this Agreement.
11. Upon receipt of a notice of Project completion from the Power
Authority, adopt a resolution accepting the Project as completed.
12. Upon completion of the Project, authorize the Power Authority
to reimburse its costs, described in Article A, Paragraph 3, from any
remaining balance of the funds described in Article A, Paragraph 2.
After the Power Authority has reimbursed its costs, any remaining
balance of funds will be returned to the DOA.
13. Upon completion of the Project, accept responsibility for
operation and maintenance of Project facilities, select qualified
personnel to be trained to operate and maintain the facilities, and
operate and maintain the system in accordance with prudent utility
standards and REA guidelines and in compliance with National Electrical
Code (NEC) and National Electrical Safety Code (NESC) rules for the life
of Project facilities.
Article C. MUTUAL COVENANTS
The Power Authority and the City agree to the following:
1. Indemnification.
(a) The Power Authority and the City shall indemnify, save
harmless and defend the other party to this Agreement, its officers,
5410/956/(3)
Tuluksak Projec greement
Page 4 of 7
agents, servants, and employees from all liability, including costs and expenses, for all actions or claims resulting from injuries or damages sustained by any person or property arising directly or indirectly as a result of any error, omission or negligent act of the indemnifying party, its officers, agents, servants, or employees or anyone directly
or indirectly employed by it in the performance of this Agreement. Any labor provided by the City for work on the Project shall be considered
the officers, agents, servants, or employees of the City for purposes of construing these indemnification provisions.
(b) All actions or claims, including costs and expenses, resulting
from injuries or damages sustained by any person or property arising directly or indirectly from the City's performance of this Agreement which are caused by the joint negligence of the Power Authority and the City shall be appropriated on a comparative fault basis. Any such joint negligence on the part of the Power Authority must be a direct result of
active involvement by the Power Authority.
2. Rights to Terminate this Agreement. The City acknowledges the right of the Power Authority to terminate this Agreement without payment of any damages to the City if it is determined by the Power Authority to
be in the best interest of the State to do so, if funds are no longer available, if the City and United Utilities, Inc. are unable to negotiate a pole sharing agreement as described in Article A, Paragraph 5, or for cause. For the purposes of this paragraph, “cause” is defined as the provision of incorrect or misleading information by the City or the City's failure to provide information that, in the opinion of the Power Authority, is a material fact that would have influenced Power
Authority actions. Under these conditions, the City waives any right of
recourse and will reimburse the Power Authority for all expenses incurred in performance under this Agreement and for all costs, including attorneys' fees, incurred by the Power Authority to perfect its claim or to collect its expenses.
3. Availability of Funding. The City acknowledges that this Agreement is subject to availability of money from the State of Alaska or other sources to finance performance under this Agreement. If funding is withdrawn, reduced, or limited in any way after the effective date of this Agreement and before the completion of performance, the
Power Authority may terminate the Agreement without incurring any damages. The Power Authority may, in its discretion, renegotiate the terms of this Agreement to comply with any new funding limitations or conditions.
4. City Not Being Agents of the Power Authority. It is agreed that the City, its officers, agents, servants and employees shall act in an independent capacity and not as agents of the Power Authority in the performance of this Agreement.
5. Disputes. Either party to this Agreement may bring an action
against the other party in the superior court for the State of Alaska to resolve a dispute arising under this Agreement. Any lawsuit involving this Agreement shall be heard by the superior court, Third Judicial
5410/956/(4)
Tuluksak Projec: jreement
Page 5 of 7
District at Anchorage. All legal costs, including attorneys' fees not otherwise provided for in this Agreement, shall be allocated pursuant to Alaska Civil Rule 82.
6. Rights of Other Parties. It is the intent of the parties that this Agreement confer no rights to any third parties.
7. Binding Effect. This Agreement and all of its terms
covenants, conditions and appendices represent the entire agreement and shall extend to and be binding upon the respective heirs, executors,
administrators, grantees, successors and assigns of the parties to this
Agreement.
8. Severability. If any section, paragraph, clause or provision
of this Agreement shall be finally adjudicated by a court of competent
jurisdiction to be invalid or unenforceable, the remainder of this Agreement shall be unaffected by such adjudication and all the remaining
provisions of this Agreement shall remain in full force and effect as if
such section, paragraph, clause or provision or any part thereof so
adjudicated to be invalid had not been included herein.
9. Declaration of Public Benefit. The parties acknowledge that
the Project is to be constructed for the benefit of the general public
and will not deny any person use of Project facilities or use of power
produced from Project facilities due to race, religion, color, sex, or national origin.
10. Declaration of Cooperation. The parties agree to make
reasonable and cooperative efforts to complete the Project by the third
quarter of 1989. Until the Power Authority issues a notice of Project
completion, project meetings between the parties to this Agreement will
be held at the request of either party within 14 calendar days after
receipt of such request by the other party. All such meetings will be
held in Tuluksak unless another location is mutually agreed upon by the
parties.
ll. Notices. Any notice required of either party shall be in
writing and, unless receipt of such notice is expressly required by the
terms of this Agreement, shall be deemed served when deposited in the
mail in a sealed envelope, with sufficient first class postage affixed,
and addressed to the appropriate party. The notices shall be sent to
each party's place of business, which in the case of the Power Authority
shall be:
Robert E. LeResche, Executive Director
Alaska Power Authority
P.O. Box 190869
Anchorage, Alaska 99519-0869
(907) 561-7877
5410/956/(5)
Tuluksak Projec jreement
Page 6 of 7
and in the case of the Grantee shall be:
THIS AGREEMENT has been reviewed, agreed to, and executed by the
following parties:
ALASKA POWER AUTHORITY
Robert E. LeResche ate
Executive Director
STATE OF ALASKA )
) ss.
THIRD JUDICIAL DISTRICT )
The foregoing Agreement was acknowledged before me this day of
, 1989, by Robert E. LeResche, the Executive Director
of the Alaska Power Authority, an Alaskan Corporation, on behalf of the
corporation.
Notary Public, State of Alaska
My commission expires:
Approved:
Assistant Attorney General ate
5410/956/(6)
Tuluksak Project .reement
Page 7 of 7
CITY OF TULUKSAK
Date
STATE OF ALASKA
ss.
THIRD JUDICIAL DISTRICT )
The foregoing Agreement as acknowledged before me this 2 day of 1989. OY ieee a ae Mayor yo Tuluksak, on
Notary Public, Stat
My commission exp
5410/956/(7)
: DAPCGLM:MIS:APA
: Bob
: Brent
: Village of Tuluksak/Organization
BACKGROUND
On Feb. 2,1989 APA staff met with representatives of the Village
of Tuluksak to discuss: 1) their request for technical assistance
to repair/upgrade Tuluksak electric system utilizing a direct
grant to the community and 2) resolution of the long recurring PCE
problems resulting from the Village lack of basic compliance with
the administrative procedures of the progam.
ISSUE
During the meeting we were informed that the day to day control of
the Village electric utility d/b/a Tuliksarmute, Inc. has been
transfered to all effects to the Elders Council of the tribal
village.
Officially Tuluksak is an incorporated second class city,
governed by a city council and an elected mayor. However, these
administrative entities have been inactive for several months.
Because of concern in dealing with the appropriate legal entity
today I called C&RA, Div. of Municipal Assistance (DMA); their
Bethel office is familiar with the political conflicts in this
village.
Mike Black, DMA/Anchorage, advised me that upon written request
his office can provide us with a complete statewide list of
villages experiencing similar conflicts; this will assist us in
preventing that program funds be inadvertently made available to
non recognized entities.
I am interested in following up this matter. Wuold you please let
me know if you agree or disagree.
Gloria
Feb. 10,1989
April 12, 1989
The Honorable John Peter Mayor
City of Tuluksak General Delivery Tuluksak, Alaska 99679
Subject: Generator and Equipment Prices
Dear Mayor Peter:
As requested during the meeting of Apri} 3, I have investigated the prices for a suitable back-up generator set and some spare equipment.
It appears that the electrical loads in Tuluksak are very light; the highest reading which I have seen is 50 KW. I would strongly suggest that we install a temporary, recording KW-meter on the power plant prior to purchasing any new generator. Currently we have such a meter instal- led on the power house in Akiak, and once we are done with it there, I will be happy to instal] it in Tuluksak.
It would appear that a 100 KW generator or similar would be more than sufficient as a stand-by machine in Tuluksak. Such a unit can be purchased for approximately $20,000, and if we include freight and installation, $25,000 would be a reasonable figure. Please note that the Alaska Power Authority will be happy to provide bidding and selection services for you at no cost to you. That way you will be assured that you get the right equipment at the right price.
As far as transformers, conductors, guy wire, and other spare parts is concerned, $10,000 should buy vou a reasonable stock of relevant spare parts. Again, we would be happy to assist you with selecting relevant spare parts. We are currently in the process of setting up contracts with vendors for a variety of equipment, and it may be advantageous for you to utilize the discounts that these contracts will provide for,
If the City of Tuluksak elects not to purchase wholesale power from the Yupik School District, I would recommend that the Detroit generator be equipped with a new engine in order to give the City tree operable enerators. The price of the right engine would be approximately 10,000.
x
5499/956/1
vage z
In other words, a total of $45,000 should enable you to get the power plant into a shape, which will allow for reasonable reliability. However, it should be noted that a couple of problems remain to be solved; the fuel tank is not diked sufficiently, and the power plant is somewhat of a fire hazard.
If there is anything else I can do for you, please do not hesitate to contact me.
Sincerely,
Peter N. Hansen Rural Systems Engineer
PNH: aa
_
5499/956/2
7/10/89.
Mr. Ralph Fuller
Mechanical Piping Contractors
P.O.Box 771396
Eagle River, Ak. 99577
Reference: Our phone conversation of 7/6/89
Subject: Proposed water system for Tuluksak schools.
Dear Mr. Fuller:
Alaska Energy Authority staff has reviewed the proposed project
design as presented (Drawings Ml, M2, amd El) and can offer the
following comments in reference to the projects impact on
Tuluksak's electrical system:
Drawing M2:
1.
This drawing offers no information to substantiate the need for 67
gpm pressure pumps with 140 ft. of head capacity. In order to
reduce system wide voltage drops in connection with the start of
these pumps, it is important to size these pumps as small as
possible and to install reduced voltage motor starters.
2.
It would be prudent to utilize two or three smaller pressure pumps
with independent controls adjusted to activate the pumps at
different pressure levels.
3.
Considering the real cost of power in rural communities it would
be prudent to pre-heat the water with heat from the school's
heating system prior to transfer to the high school and
consequently utilize electric heat tracing for emergencies only.
System peak loads are typically encountered during periods of
extreme cold and any addition of load during such periods is
highly undesireable.
4
This drawing offers no information on the proposed ozone treatment
system; the appropriateness of system sizing cannot be verified.
Drawing El:
5.
This drawing offers no information in reference to the types of
equipment included in the ozone treatment system or the in-rush
currents which can be expected. Also, no information is offered concerning estimated power consumption per gallon or per year.
6. General comments:
The design as presented may be one solution to the water problems
encountered in Tuluksak; however, no information has been offered to substantiate that it is the best solution. It is obvious that this system will have very significant impacts on the power system in Tuluksak, and depending on the usage pattern by the ozone treatment system, it is conceivable that this system will cause the quality of power to deteriorate. It is simply not desireably to instantaneously add loads of this magnitude to a system where the total load at times will be 50 kw or less.
System peak loads can be expected to increase by 25 kw not counting motor starting peaks, and this necessitates the continous operation of an additional 25 kw of spinning capacity. As total run time will be limited, the over all load factor of the electrical system will be reduced resulting in reduced fuel efficiency and increased operations and maintenance cost per kilowatthour produced.
In order to avoid a situation where a water system problem is simply changed to a power system problem, it is recommended that alternative and less power consuming solutions be investigated prior to the final selection of a system concept.
If you have any questions, please do not hesitate to contact me in writing or at 261 7261 during normal business hours.
Sincerely,
Donald L. Shira
Director/Program Development & Facilities Operations.
ec: Mr. Roger Helmer, Yupiit School District.
Mr. Boyd Morgenthaler, Adams, Morgenthaler And Company
Mr. David D. Adams, Adams, Morgenthaler And Company.
[oe 7 - EYR
7/10/89 /'
Mr. Brad Raphel, Superintendent
Yupiit School District
Box 100
Akiachak, Alaska
99551
Reference: Letter from Mechanical Piping Contractors of 7/8/89
Subject: Allegations made by Mr. Fuller in reference to
statements made by me.
Dear Mr. Raphel:
The Alaska Energy Authority has received a letter from Mechanical Piping Contractors in which Mr. Fuller alleges that I made a number of derogatory and racial comments during a recent phone conversation with him. I am greatly disturbed that Mr. Fuller alleges that I have made racial comments refearding Alaskan
Natives , and Eskimos in particular. As you know, I work almost
exclusively in the villages around Alaska, and I can not accept
leaving even a hint of such allegations unanswered. I have attached a copy of Mr. Fuller's letter, and in the following I will offer my comments to each of the paragraphs in the letter.
As stated in paragraph two of the letter, I received a call on 6/27 from Mr. Fuller. During the conversation Mr. Fuller told me about the power requirements for the proposed system, and when I questioned Mr. Fuller about the size of the system, Mr. Fuller told me that the size was mandated by the Uniform Plumbing Code
(UPC). I told Mr. Fuller that UPC does not mandate but merely
recommends water system sizes and I suggested that the Department
of Environmental Conservation (DEC) be contacted in order to determine how DEC interpretes the code. Mr. Fuller then proceeded to give me the name and phone number of the DEC official with whom he had been dealing. To set the record straight, I made a call to this DEC official on 6/27 and not 6/28 as alleged by Mr. Fuller, and I did not inquire about a variance as I was told by the DEC official that UPC makes recommendations only and that DEC reviews
each case on its own merits. I did not in any way tell the DEC
official that I felt that the system would not work; on the contrary, I asked her to tell me what she knew about ozone systems as I had never seen one! At this time I had not yet received any drawings of the system and consequently I had no opinion in reference to the system being overdesigned or not. However, as I
also had stated to Mr. Fuller earlier, I was concerned about the size of the system as this would have significant impacts on the power system in Tuluksak.
On 6/29 a set of blue prints were delivered to my office; this set included 3 drawings produced by Adams, Morgenthaler & Company and did not include any of the Ozone Water Filtration System.
On 6/30 I received another call from Mr. Fuller. During this
conversation Mr. Fuller complained about the frustrations
experienced during the development of a project to the point where
it is ready for construction and we agreed that the actual
construction was more fun than the design and review stage. In no
way what so ever did I at any point of time make any derogatory
comments to Mr. Fuller in regards to his background, occupation,
or personality. As I had not yet seen Mr. Fuller's design
drawings, I still had no opinion about the system being over
designed and I certainly made no statements as to whether’ the
system would work or not. We discussed the appropriateness of
installing a computer controlled system and I explained to Mr.
Fuller that such systems frequently experienced problems in the villages due to surges and spikes in the electrical power systems. I also explained to Mr. Fuller that even though the Yupiit School
District has a very capable maintenance crew stationed in
Akiachak, a simpler system was likely to be more reliable as
weather conditions frequently makes travel between the villages impossible. I made it clear to Mr. Fuller that I disagreed with
his assessment regarding the ability of locals to mix and add
chemicals to a simpler system. Such systms work well throughout
Rural Alaska and I saw no reason that they would not work in
Tuluksak.
In reference to Mr. Fuller's allegation that I made a comment
about Eskimos and what they do and deserve, I can only say that I believe that my all-out efforts during the past 6 years including
nights, weekends, and vacations on projects in native villages should speak for themselves. I have spent hundreds of
uncompensated hours working with local construction crews,
operators and community leaders in order to develop and design
appropriate and reliable systems which can be constructed,
operated, maintained, and repaired by local crews at a cost which can be afforded by local communities. Needless to say, if I
harbored or expressed any racial and derogatory opinions as
alleged by Mr. Fuller, I would be in a different line of work.
On page 2 Mr. Fuller alleges that he questioned why I contacted
DEC. As previously stated, the name and number of the DEC official
was provided to me by Mr. Fuller. Contrary to the statement made by Mr. Fuller, I also did not state that the system is over-built;
as far as I know, the system has not been built at all! Without
using the term quoted by Mr. Fuller, I did however suggest, that I
would have preferred to see other options studied in some detail before a concept was selected and a detailed design developed.
Let me finally emphasize that I have not at any time used terms
such as "dumb" or "stupid" about Mr. Fuller or any of the
engineers with whom Mr. Fuller has associated or about any design
presented to me by any of these individuals.
Regardless of the opinions expressed by Mr. Fuller, I will continue to promote the design, installation, and operation and
maintenance of appropriate solutions, systems, and technology in
Rural Alaskan communities. It is my belief that the most important measure of appropriateness is the extent to which local
communities can afford, construct, operate, maintain, and repair such solutions, systems, and technology with local forces and
local resources.
If you have any questions, please do not hesitate to contact me at 261 7221.
Sincerely,
Peter N. Hansen, P.E.
Alaska Energy Authority
ec: Mr. Willie Kasaylie, Yupiit School Board
Mr. Mike Williams, Vice-President, Yupiit School Board
Mr. Brad Raphel, Superintendent, Yupiit School District
Mr. Roger Helmer, Business Manager, Yupiit School District
Mr. Pat Rausch, Adams, Morgenthaler & Company
Mr. Pat Cusick, Adams, Morgenthaler & Company
Mr. Boyd Morgenthaler, Adams, Morgenthaler & Company
Mr. Wayne Daley, Kramer, Chin & Mayo, Inc.
Mr. Ralph Fuller
JUN 28 ’89 99:51 ADAMS, MORGENTHALER & CO 272-5593 P.1/3
(ieee [s Ce-240)
ADAMS, MORGENTHALER ' JOB NO. ‘Sze AND COMPANY cone Teles,
PM
FAX TRANSMISSION
TO: ALASKA dew Aut Hoe! =
TELEPHONE NO. 2 Xo! - QOS DATE: -27
ATTENTION OF: $2, PETE HANSON
SUBJECT: Te Ke
COVER SHEET + PLUS _<— PAGES
MESSAGE OR ADDITIONAL INFORMATION
vam Pebih EZ acl OPERATOR INITIALS 442
ADAMS, MORGENTHALER AND COMPANY TEL: (907)279-0431 3333 DENALI, SUITE 201 FAX: (907)272-5593 ANCHORAGE, AK 99503 TYPE: RICOH FAX20
, : : TI 0 272-5593 Pury ReQ’Z, » JUN 28 789 @9:52 ADAMS, MORGENTHALER & C 5 Kens ee
+ a
Adams, Morgenthaler and Company
3333 DENALI, SUITE 201 CONSULTING ENGINEERS Dee an nic aaes
June 27, 1989 (907) 279-0431 FAX (907) 272-5593
Alaska Power Authority
701 E. Tudor Ra.
Anchorage, AK 99503
ATTN: Mr. Peter Hanson
RE: Tuluksak School Water System Upgrade (89128)
SUBJ: Tuluksak School System Power Generation
Gentlemen:
We have been working with Mr. Ralph Fuller on the Tuluksak School Water System Upgrade. We have defined the electrical requirements for the new water treatment. equipment. Please include the additional load requirements in your generator upgrade project.
New Panel "WI", 120/208V, 3 Phase, 4 Wire, 225 Amp Lug, 10000 AIc surface mount. + TCL @ 100% 26.7 KVA, 74 Amps + TDL per NEC 28.3 KVA, 79 Amps
In addition to the new equipment we anticipate reusing the existing 1/2. hp well pump and well heat trace. Two (2) 1/2 hp booster pumps will be eliminated. All other existing loads are expected to remain. Please send written confirmation that the above requirements will be met.
Sincerely,
ADAMS, MORG R AND COMPANY
Leh | Od)
Patrick Rausch Mechanical Engineer
Attachments
89128: let90627
BAA AL REZ AR ONDER Ares
PANEL__NT z
B 120/208 VOLTS 3 PHASE 4 WIRE 225 AMP LUG 10,000 A.1.C. SURFACE MOUNT a
nei T f) Hip AMD abc i! y fi a
m E10 Vaan : eee alien 5
§ ----* § 17 a Em j *---- 3 . = 9 --*--10 9 lia = 11--~-*12 . 13*----14 i a 15--*--16 sh 17----*18 3 ee | 23----*24 TATA FOOT TOL “| 25*----26 iT 2)7--*--28 29----*30 31*----32. 33--*--34
Et 35----*36 37*----38 39--*--40 + i. 41-~--*42
TCL @ 100% KVA "ANPS RENARKS TOL PER NET __KVA AMPS eve'd
Adams, Morgenthaler and Company
CONSULTING ENGINEERS on ee
June 27, 1989 (907) 279-0431 FAX (907) 272-5593
RE Alaska Power Authority CE l VE D 701 E. Tudor Rd. JUN A Anchorage, AK 99503 297
SKA Powe 4 UTHORITY ATTN: Mr. Peter Hanson
RE: Tuluksak School Water System Upgrade (89128)
SUBJ: Tuluksak School System Power Generation
Gentlemen:
We have been working with Mr. Ralph Fuller on the Tuluksak School Water System Upgrade. We have defined the electrical requirements for the new water treatment equipment. Please include the additional load requirements in your generator upgrade project.
New Panel "WT", 120/208V, 3 Phase, 4 Wire, 225 Amp Lug, 10000 AIC surface mount. - TCL @ 100% 26.7 KVA, 74 Amps - TDL per NEC 28.3 KVA, 79 Amps
In addition to the new equipment we anticipate reusing the existing 1/2. hp well pump and well heat trace. ‘Two (2) 1/2 hp booster pumps will be eliminated. All other existing loads are expected to remain. Please send written confirmation that the above requirements will be met.
Sincerely,
ADAMS, MORGENT R AND COMPANY fa
/ « thick Kaquaol
Patrick Rausch
Mechanical Engineer
Attachments
89128:let90627
AN ALASKAN CORPORATION
rr er er
PANEL__ WT
120/208 VOLTS 3 PHASE 4 WIRE 225 AMP LUG 10,000 A.I1.C. SURFACE MOUNT
CIRCUIT DESCRIPTION KVA | AMP abc | AMP
1 3
= -- 5 oooat 6
7 9 a 3
PMP-2 FILTRATION OZONE SYSTEN VIA TRANSFORM
ARCTIC PIPE HEAT TRAC! (GLC BREAKER) ARCTIC PIPE HEA! (GLCB BREAKER,
25*----26 27--*--28 29----*30 31*----32 33--*-- 34 35----*36 37*----38
1 39--*--40 4j----*42
TCL @ 1008 KVA TDL PER NEC $F KVA
AMPS REMARKS AMPS Ni hols}
7/10/89.
Mr. Ralph Fuller
Mechanical Piping Contractors
P.0.Box 771396
Eagle River, Ak. 99577
Reference: Our phone conversation of 7/6/89
Subject: Proposed water system for Tuluksak schools.
Dear Mr. Fuller:
Alaska Energy Authority staff has reviewed the proposed project design as presented (Drawings Ml, M2, and El) and can offer the following comments in reference to the projects impact on Tuluksak's electrical system:
Drawing M2:
i
This drawing offers no information to substantiate the need for 67 gpm pressure pumps with 140 ft. of head capacity. In order to reduce system wide voltage drops in connection with the start of these pumps, it is important to size these pumps as small as possible and to install reduced voltage motor starters.
2.
It would be prudent to utilize two or three smaller pressure pumps with independent controls adjusted to activate the pumps at different pressure levels.
a
Considering the real cost of power in rural communities it would be prudent to pre-heat the water with heat from the school’s heating system prior to transfer to the high school and consequently utilize electric heat tracing for emergencies only. System peak loads are typically encountered during periods of extreme cold and any addition of load during such periods is highly undesireable.
4
This drawing offers no information on the proposed ozone treatment system; the appropriateness of system sizing cannot be verified.
Drawing El:
5.
This drawing offers no information in reference to the types of equipment included in the ozone treatment system or the in-rush
currents which can be expected. Also, no information is offered
concerning estimated power consumption per gallon or per year.
6. General comments:
The design as presented may be one solution to the water problems
encountered in Tuluksak; however, no information has been offered
to substantiate that it is the best solution. It is obvious that
this system will have very significant impacts on the power system
in Tuluksak, and depending on the usage pattern by the ozone
treatment system, it is conceivable that this system will cause
the quality of power to deteriorate. It is simply not desireably
to instantaneously add loads of this magnitude to a system where
the total load at times will be 50 kw or less.
System peak loads can be expected to increase by 25 kw not
counting motor starting peaks, and this necessitates the continous
operation of an additional 25 kw of spinning capacity. As total
run time will be limited, the over all load factor of the
electrical system will be reduced resulting in reduced fuel
efficiency and increased operations and maintenance cost per
kilowatthour produced.
In order to avoid a situation where a water system problem is
simply changed to a power system problem, it is recommended that
alternative and less power consuming solutions be investigated
prior to the final selection of a system concept.
If you have any questions, please do not hesitate to contact me -in—
—writimg=or at 261 7261,during normal—business hours.—
Sincerely,
Donald L. Shira
Director/Program Development & Facilities Operations.
ec: Mr. Roger Helmer, Yupiit School District.
Mr. Boyd Morgenthaler, Adams, Morgenthaler And Company
Mr. David D. Adams, Adams, Morgenthaler And Company.
July 10, 1989
Mr. Ralph Fuller
Mechanical Piping Contractors
P.0. Box 771396
Eagle River, AK 99577
Subject: Proposed Water System for Tuluksak Schools
Reference: Our Phone Conversation of 7/6/89
Dear Mr. Fuller:
Alaska Energy Authority staff has reviewed the proposed project design as presented (Drawings Ml, M2, and E1) and can offer the following
comments in reference to the projects impact on Tuluksak's electrical
system:
Drawing M2:
I.
4.
This drawing offers no information to substantiate the need for
67 gpm pressure pumps with 140 ft. of head capacity. In order to
reduce system wide voltage drops in connection with the start of
these pumps, it is important to size these pumps as small] as possible and to install reduced voltage motor starters.
It would be prudent to utilize two or three smaller pressure pumps
with independent controls adjusted to activate the pumps at differ-
ent pressure levels.
Considering the real cost of power in rural communities it would be
prudent to pre-heat the water with heat from the school's heating
system prior to transfer to the high school and consequently
utilize electric heat tracing for emergencies only. System peak
loads are typically encountered during periods of extreme cold and
any addition of load during such periods is highly undesirable.
This drawing offers no information on the proposed ozone treatment
system; the appropriateness of system sizing cannot be verified.
Drawing E1:
S. This drawing offers no information in reference to the types of
equipment included in the ozone treatment system or the in-rush
currents which can be expected. Also, no information is offered
concerning estimated power consumption per gallon or per year.
6177/DD54(1)
rage <
6. General Comments:
The design as presented may be one solution to the water problems
encountered in Tuluksak; however, no information has been offered to substantiate that it is the best solution. It is obvious that this system will have very significant impacts on the power system
in Tuluksak, and depending on the usage pattern by the ozone
treatment system, it is conceivable that this system will cause the quality of power to deteriorate. It is simply not desirable to
instantaneously add loads of this magnitude to a system where the total load at times wil? be 50 kw or less.
System peak loads can be expected to increase by 25 kw not counting
motor starting peaks, and this necessitates the continuous opera-
tion of an additional 25 kw of spinning capacity. As total run time will be limited, the overall load factor of the electrical
system will be reduced resulting in reduced fuel efficiency and
eon operations and maintenance cost per kilowatthour pro-
duced,
In order to avoid a situation where a water system problem is
simply changed to a power system problem, it is recommended that alternative and less power consuming solutions be investigated prior to the final selection of a system concept.
If you have any questions, please do not hesitate to contact me at
261-7261.
Sincerely,
Donald L. Shira
Director of Program Development
and Facilities Operations
PNH:DLS: it
cc: Mr. Roger Helmer, Yuptit School District
Mr. Boyd Morgenthaler, Adams, Morgenthaler and Company
Mr. David D. Adams, Adams, Morgenthaler and Company
6177/DD54(2)
Adams, Morgenthaler and Company
CONSULTING ENGINEERS 3333 DENALI, SUITE 201 on ANCHORAGE, AK 99503 June 27, 1989 (907) 279-0431 FAX (907) 272-5593
Alaska Power Authority
701 E. Tudor Rd.
Anchorage, AK 99503
ATTN: Mr. Peter Hanson
RE: Tuluksak School Water System Upgrade (89128)
SUBJ: Tuluksak School system Power Generation
Gentlemen:
We have been working with Mr. Ralph Fuller on the Tuluksak School Water System Upgrade. We have defined the electrical requirements for the new water treatment equipment. Please include the additional load requirements in your generator upgrade project.
New Panel "WI", 120/208V, 3 Phase, 4 Wire, 225 Amp Lug, 10000 AIC surface mount. - TCL @ 100% 26.7 KVA, 74 Amps + TDL per NEC 28.3 KVA, 79 Amps
In addition to the new equipment we anticipate reusing the existing 1/2. hp well pump and well heat trace. Two (2) 1/2 hp booster pumps will be eliminated. All other existing loads are expected to remain. Please send written confirmation that the above requirements will be met.
Sincerely,
ADAMS, MORGENT: RR AND COMPANY “pes Litt: Keurcld
Patrick Rausch
Mechanical Engineer
Attachments
89128: let90627
AN ALASKAN CORPORATION