Loading...
HomeMy WebLinkAboutS. Intertie Phase 1 March 11-1996CHUGACH ELECTRIC i Fey ECEWE()) A bar MAR 15 1996 fe 13, 1996 3) — ry Alaska industrial Development Alaska Industrial Development 4) (ond and Export Authority and Export Authority 480 West Tudor Road Anchorage, Alaska 99503 Attention: Mr. William R. Snell, Executive Director Subject: Southern Intertie - Route Selection Services Draft Economic Section Report Enclos€d is one Copy of subject report for your information. A copy of the report has also been sent toall IPG Technical Committee members for review. Should you wish to provide separate comments or have questions, please, don’t hesitate to contact me or our Project Manager, Dora Gropp at 762-4626 by March 27, 1996. Sincerely, . -Bjo * General Man ENB/ :ahw CAANNALISATWPD: 1\BNBOS96.LTR (CAANNALISATWPD: NBNBLTR.DAT Enclosure: Draft Economic Section Report dated March 11, 1996. cc? Lee Thibert Michael Massin Dora Gropp W.0.#E9590081, Sec., 2.1.2.1 RF 5601 Minnesota Drive * P.O. Box 196300 * Anchorage, Alaska 99519-6300 Phone 907-563-7494 * FAX 907-562-0027 PROJECT NO.: 120293-01 Q My TLWER ISSUED TO: INEERS COPY NO: CHUGACH ELECTRIC ASSOCIATION, INC. CONTRACT NO. 95-208 SOUTHERN INTERTIE ROUTE SELECTION STUDY PHASE 1 MARCH 11, 1996 DRAFT ECONOMIC SECTION REPORT FOR INFORMATION CONTACT: =» Larry Henriksen, P.E. => Tim Ostermeier, P.E. = Randy Pollock, P.E. POWER ENGINEERS, INC. @ P.O. BOX 1066 @ HAILEY, IDAHO’ 83333 (208) 788-3456 @ FAX (208) 788-2082 SOUTHERN INTERTIE ROUTE SELECTION STUDY PHASE 1 DRAFT ECONOMIC SECTION REPORT TABLE OF CONTENTS ECONOMIC SUMMARY AND REPORT OVERVIEW Introduction Summary of Estimates Tesoro Route Introduction Route Descriptions and Cost Estimate Summary Enstar Route Introduction Route Descriptions and Cost Estimate Summary Quartz Creek Route Introduction Route Descriptions and Cost Estimate Summary OVERHEAD TRANSMISSION LINE Introduction Tesoro Route Enstar Route Quartz Creek Route SUBMARINE & UNDERGROUND TRANSMISSION CABLE Introduction Submarine Cable Land/Underground Cables PEI-HLY 55-0198 120293-01 (3/96) ab 1 SUBSTATIONS Introduction Bernice Lake Substation International Substation University Substation Soldotna Substation Point Woronzof Substation REACTIVE COMPENSATION Introduction Shunt Capacitor Banks Shunt Reactors Static Var Compensators Series Capacitor Banks Battery Energy Storage ENVIRONMENTAL PERMITTING Introduction Environmental Impact Statement Pre-Construction / Monitoring RIGHT-OF-WAY & PERMIT ACQUISITION Introduction Permits Right-of-Way Acquisition APPENDICES Appendix - A Overhead Transmission Line (Detailed Estimates) Appendix - B Submarine & Underground Transmission Line (Detailed Estimates & Supporting Data) Appendix - C Substation (Drawings & Detailed Estimates) Appendix - D Reactive Compensation (Drawings & Detailed Estimates) PEI-HLY 55-0198 120293-01 (3/96) ab 2 REPORT SUMMARY AND ECONOMIC SECTION REPORT OVERVIEW INTRODUCTION The purpose of the Economic Section Report is to provide cost estimates for the Southern Intertie Project Alternatives. The alternatives have been previously identified in the Draft Design Section Report and Draft System Studies Report, which were previously issued for review and-comment.. The-three primary. alternatives. are referred.to as-Tesoro Route, Enstar Route, and Quartz Creek Route. Based on the results of the preliminary design efforts and environmental evaluations, each corridor has a base route identified. These base routes are potential routes that have attributes that may allow the route to be ultimately permitted under an environmental assessment (EA) or environmental impact statement (EIS) process. The cost estimates for the environmental permitting efforts are based on the preparation of an EIS. For purposes of this report, the base routes will be the baseline estimates. Multiple alternatives to each of the base routes are also provided. Refer to the alternative corridor map in the map pocket for the locations of the routes. When referring to the map and in the route tables, please note for the link designations, the first two letters of each route delineate the overall route or area for a routing opportunity as follows: TS Tesoro Route Qc Quartz Creek Route EN Enstar Route AN Anchorage Municipal Area This Economic Section Report provides an overview of the project cost estimates, a summary of the estimates, and a detailed breakdown of the various costs. The report is organized as follows: - e Report Summary and Economic Section Overview - Introduction - Economic Section Report Overview - Summary of Estimates - Summary of estimates in 1996 dollars for each preferred base route and local alternatives inclusive of submarine, underground and overhead transmission, substations, reactive compensation, environmental permitting, rights- of-way, engineering and construction management - Tesoro Route - Detailed description of the base route and local alternatives - Enstar Route - Detailed description of the base route and local alternatives - | Quartz Creek Route - Detailed description of the base route and local alternatives Overhead Transmission - Cost estimate breakdown by link Underground Transmission - Cost estimate breakdown by link Substations - Cost estimate breakdown by substation alternative Reactive Compensation - Cost estimate breakdown by device and application PEI-HLY 55-0198 120293-01 (03/96) ab 1 e —_ Environmental Permitting - Cost estimate breakdown for EIS, associated studies, and Pre- construction surveys e Rights of Way - Cost estimate breakdown by right-of-way and related permitting Appendices A-D - Supporting detailed documentation for transmission, substation and reactive compensation estimates. SUMMARY OF ESTIMATES The Southern-Intertie has numerous.technical challenges regardless-of the route.. The following discussions reflect some of the more economically significant assumptions applied to the cost estimates. OVERHEAD LINES @ The overhead transmission structure types are steel guyed-X and single pole steel structures in accordance with the Design Section Report and detailed in Appendix A in this document. SUBMARINE CABLES ® The submarine cable estimates were performed based on double armor for the entire circuit length and embedding the cables. The decision to double armor and embed is based on the operating environment in the Turnagain Arm and discussions with Pirelli. Additional discussion on this information is presented in the “Submarine and Underground Transmission Cable” section of this document, Appendix B, and in the previously submitted Design Section Report. The recommended cable system at 138kV, except for the Bird Point crossing, is 2 - 3 phase flat type SCFF cables. Since this system provides for two completely independent 3 phase circuits, embedment of the cables may not be as important, since if one circuit fails, the line could continue to operate on the other circuit. Since embedment is estimated to add $14 per cable foot (0.7 - 2.5$M) to the installation cost, site specific Geotechnical investigation is recommended prior to finalizing a decision regarding embedment. At 230kV, 4 - 1 phase SCFF cables are estimated, with embedment. ®& The Bird Point Alternative was estimated using a different technology than the SCFF type submarine cable. We anticipate that it will be possible to set up in the Turnagain Arm and directionally drill towards either shore to place an HPGF type of cable system. PEI-HLY 55-0198 120293-01 (03/96) ab 2 ® After additional geotechnical investigations have been performed and the submarine, installation actually bid, we anticipate up to a 10% reduction (0.9 - 3.0 $M) in the cable material price. LAND UNDERGROUND CABLES > All anticipated underground high voltage cable installations are assumed to be XLPE type. This is reliable type of technology and has the lowest costs. SUBSTATION @ The substation estimates are based on the Design Section Report and the General Arrangements located in Appendix C of this document. @ The termination points for the Southern Intertie were selected for estimating purposes. Actual final terminal (substation) locations may vary in the Anchorage area. REACTIVE COMPENSATION @ Reactive compensation will be required for all scenarios of the Southern Intertie to facilitate steady state power transfer, dynamic stability during system disturbances and to control capacitance of high voltage submarine/underground cables. Additionally, construction of the new transmission facility will require compensation of the existing 115kV Intertie for the same reasons. Our cost estimates include appropriately sized devices for both new and existing facilities. The high voltage underground or submarine type of cables require shunt connected reactors. Generally speaking, the higher the voltage and the longer the cable run, the larger the reactor has to be to control the (higher) capacitance. Also, the existing 115kV Intertie would require shunt connected capacitor banks augmented by a Static Var Compensator (SVC) or a Thyristor Controlled Series Capacitor (TCSC) Bank. Estimates are provided for both scenarios; however, the TCSC offers superior steady state and dynamic capabilities and is the preferred choice. It should be noted, a significant capital cost savings of approximately $3M can be made by eliminating the TCSC, if it is determined that some underfrequency load shed can be tolerated. The extent of load shed is highly dependent on the generation mix at the time of a system disturbance and on the ability to be able to very quickly provide transfer trip of at least one Bradley Lake unit. PEI-HLY 55-0198 120293-01 (03/96) ab 3 ® The reactive compensation estimates are based on the previously submitted System Studies and Design Section Report and information detailed in Appendix D. ENVIONMENTAL PERMITTING @ Each of the three major potential route for the project present significant challenges to successfully securing a permitted route based on meetings with the public, affected agencies and a review of previous study correspondence. It has not yet been determined whether an EA {Environmental Assessment) or an Environmental Impact Statement (EIS) level of effort will be required to comply with NEPA (National Environmental Policy Act) requirements. Cost estimates included in this report are based on an EIS level of effort. ®@ As compared to the effort required for a typical EIS, the project will require additional studies or effort in the following areas (please refer to the Environmental Permitting Section for more detail): Anchorage Urban Study - Additional Data Collection Additional Public and Agency Meetings to Facilitate the Decision Process Additional Mitigation Studies PRE-CONSTRUCTION SURVEYS @ Prior to construction and potentially before agency approval on the selected alternative, a number of compliance studies are required. These include Section 106 (cultural) and Section 107 (biology). In addition, a Construction, Operation and Maintenance (COM) Plan would be prepared. The final element of environmental studies includes preparation of EAs (if needed) as well as other permits (e.g. Section 404). PEI-HLY 55-0198 120293-01 (03/96) ab 4 RIGHT-OF-WAY AND RIGHT-OF-WAY ACQUISITION r To secure the requisite project right-of-way, two major acquisition processes will occur: e Permit acquisition to secure CEA’s transmission line rights to exist on local, state, and federally administered lands; and e Private land easement acquisition to secure CEA’s rights to exist on private lands crossed by the transmission line. . The variation of project right-of-way and permit acquisition costs among the three primary ° alternatives-is a direct function of the agency lands crossed that require-permitting, as well as the amount of private land crossed by the route. The direct cost of subsequent land value of the lands encumbered by the easement on those parcels. Indirect costs are directly related to the number of parcels to be acquired, and the labor and expense costs associated with easement acquisitions. FIBER OPTICS Consideration for the installation of a fiber optic cable as part of the project was not requested until after the preliminary design was complete. The preliminary design and design criteria as presented in the Design Section Report do not provide for fiber optics. However, based on our experience with similar projects, we have estimated the cost of adding a fiber over the various routes and have summarized those costs below. Costs for the addition of fiber optics to the Project are not included in the overall Project costs as summarized elsewhere in this Report. If the addition of fiber optics is desired to be added to the Project, it is recommended that it be included in the requirements for the final design. Submarine Cable 500 - 1,200 5 Underground (Land) Cable 0 - 0 Overhead Transmission 1,800 - 4,000 i Total F.O. costs, depending on route 2.4M - 5.3M PEI-HLY 55-0198 120293-01 (03/96) ab 5 COST ESTIMATE SUMMARY TABLES The following tables summarizes the base routes and alternatives by overall corridor and voltage. Refer to the applicable section for detailed breakdowns of summarized costs. The following acronyms are used. *OH - High Voltage (138kV.or 230kV) Overhead Transmission Line * SUB - Submarine Type Cable (138kV or 230kV) *UG - High Voltage (138kV or 230kV) Land Underground Type Cable *SS_ - Substation (138kV or 230kV) *RC_ - Reactive Compensation (115kV, 138kV, or 230kV) ENV - Environmental Permitting (includes EIS) ROW - Right-of-Way and Permit Acquisition PCS - Environmental Pre-Construction Surveys * Inclusive of labor, material, engineering design and construction management. PEI-HLY 55-0198 120293-01 (03/96) ab 6 SUMMARY OF COSTS 138KV SYSTEM (MILLIONS OF DOLLARS) Southern Intertie Project - Phase 1 Route Selection RC Diff. From Total SM Base Route QUARTZ CREEK BIRD A (OH)* BIRD B (SUB) SOL B SOL C Local Alternatives: Anchorage Area Local Alternative: Captain Cook State Park Local Alternatives: Soldotna Area Local Alternatives: Bird Point Area awn PEI-HLY 55-0198 120293-01 (03/96) ab 7 SUMMARY OF COSTS 230KV SYSTEM (MILLIONS OF DOLLARS) outhern Intertie Project - Phase 1 Route Selection | (Sather intertieProject= Phase LRowteSeection fei ere bre ral Pre i fee ree Base Route [awk [oa] Or] ma, wr] ee] 23] wo] ap ee ac a 22 | os _| act ae 2 | | [ane Cee [es pecrowe | 0] oo] oo] a] oo] as] os] ap ms ie A rs > Local Alternatives: Anchorage Area © Local Alternative: Captain Cook State Park 7 Local Alternatives: Soldotna Area * Local Alternatives: Bird Point Area PEI-HLY 55-0198 120293-01 (03/96) ab 8 TESORO ROUTE INTRODUCTION The Tesoro Route starts near Anchorage at Point Woronzof Substation. Significant substation modifications, including additional reactors would be required. The base route departs the Point Woronzof Substation via submarine cable and crosses to Fire Island. The cable makes landfall on the north end of the island, goes to overhead construction, then back to submarine type cable on the south end. -It again makes landfall near Point.Possession-on-the Kenai Peninsula. At-this point, the line has a small reactor station and proceeds down the coastline to Bernice Lake Substation via overhead with the exception of Captain Cook State Park, which is estimated as underground. ROUTE DESCRIPTIONS AND COST ESTIMATE SUMMARIES The following tables more fully describe the base route for Tesoro in addition to the identified alternatives and their associated costs. Also, please refer to the Alternative Corridors Map located in the map pocket at the back of this report to assist the reader in identifying specific links that constitute the route and alternatives: PEI-HLY 55-0198 120203-01 (03/96) ab 1 TABLE TE 01 TESORO ROUTE ae N/A Point Woronzof 138kV: New 5 Breaker Ring Bus, arrangement. 230kV: New 230kV line terminal, 230/138kV 200 MVA autotransformer, new 138kV 5 Breaker Ring Bus, Reconfigure Reactive Point Woronzof 138kV: 1-30 MVAR reactor Compensation 230kV: 1-75 MVAR reactor Transition to submarine cable from _ | Substation. TE.A.10 From: Point Woronzof Submarine cable. To: Fire Island 138kV: 2-3 phase SCFF cables. New route. 230kV: 4-1 phase SCFF cables. Transition North end Fire Island: new site Transition from submarine cable to Facility overhead. TE.D.40 From: North end, Fire Island Overhead line on guyed X steel To: South end, Fire Island structures. Line Design 3. New route. Route follows eastern side of | . island to avoid aviation navigation facilities. ransition South end Fire Island: new site Transition from overhead to fers submarine cable. TE.E.50 From: South end, Fire Island Submarine cable. To: Point Possession 138kV: 2-3 phase SCFF cables. New route. Proposed route located on west side of depression on the inlet floor. |230kV: 4 - 1 phase SCFF cables. PEI-HLY 55-0198 120203-01 (03/96) ab 2 TABLE TE 01 TESORO ROUTE Reactive N/A Point Possession: new site sea ‘1-10 and 1-30 MVAR Compensation rs. : 230kV: 1-10 and 1-40 MVAR reactors. Transition from submarine cable to overhead transmission. TE.G-H.80 : Point Possession Overhead line on guyed X steel To: Links TE.G-H.90, and TE.1I.130,} structures. Line Design 3. | north of Captain Cook State Transition N/A North end of Captain Cook State Park: Facility new site Recreation Area. Parallels Tesoro pipeline. Could follow east side of existing Tesoro pipeline. Separation requirements are not known at this time. From: Link TE.I.130 north of Captain | Overhead line on guyed X steel Cook i i To: North boundary of Captain Cook State Recreation Area Parallels Tesoro pipeline, could follow the east side of the existing Tesoro pipeline. Transition from overhead to underground. PEI-HLY 55-0198 120203-01 (03/96) ab 3 TABLE TE 01 TESORO ROUTE Link/Substation Link Code | Total Length Location : Type of Facility ae ome | eT TE.1.100 From: Northern boundary of Captain Underground line through the Cook State Recreation Area. Captain Cook State Recreation Area. To: Southern boundary of Captain 3 - 1 phase XLPE cables. . Cook State Recreation Area Parallels Tesoro pipeline or roadway. Could follow the Tesoro pipeline or park access road. Separation requirements from the pipeline and actual location are currently unknown. Transition N/A South end of Captain Cook State Park: Transition from underground to Facility new site overhead. TE.J-K.110 From: Southern boundary of Captain Overhead line on guyed X steel Cook State Recreation Area. structures. Line Design 3. To: Link TE.J-K.120. Near Bernice Lake Substation Overhead/underground transition Parallels Tesoro pipeline. Would follow | facility located at the north end. the east side of the Tesoro pipeline. Separation requirements are currently unknown. TE.J-K.120 1.0 From: Link TE.J-K.110. Tesoro Pipeline| Overhead line on guyed X steel To: Bernice Lake Substation structures. Line Design 3. _ | Could parallel pipeline, North Kenai roadway, and/or transmission line. | f Bernice Lake Substation 138kV: Expand 115kV, new 115kV 3 Breaker Ring Bus, 138/115kV, 200 MVA autotransformer. 230kV: Expand 115kV, new 115kV 3 Breaker Ring Bus, 138/115kV, 200 MVA autotransformer. 1-20 MVAR shunt Capacitor Bank & 0-40 MVAR Thyristor Controlled Series Capacitor (TCSC) Bank. PEI-HLY 55-0198 120203-01 (03/96) ab 4 Cost Estimate for the Tesoro Route 230kV 138kV Estimated Estimated Cost Cost Overhead Lines Go3Milesyf 193 ____183] Submarine Cable (142 Miles) 2.1] #44 [and Underground Cable Miles) 17] 93] Substations: Point Woronzof Reactive Compensation: Point Possession Portage Right of Way and Penniting Petre cree rey ert pes Pre-Construction Surveys Pear eat rors IEE ac Eo 230KV 138KV EngnesingSuveyEIS Spon |r| Si [Construction Management [47] 38 PEI-HLY 55-0198 120203-01 (03/96) ab 5 TABLE TE 02 TESORO ROUTE - ANCHORAGE AREA UDF TICS AUN EVOL gee TL TUT TL Link Code Location Type of Facility (Miles) TE.A.10 | 5.1 _| Please see previous description. Please see previous description. Please see previous description. Please see previous description. TE.E.50 [{ 9.1 _| Please see previous description. Please see previous description. UME CE EEC EC AD EA SCA: (DO lk IE Cost Estimate for Tesoro Route - Anchorage Area Base Route OUI UTE VA OCT Lee Cost Item Estimated - Estimated Cost Cost (Overhead Lines emi Teri eee LLP Lee CL Submarine Cable ___(42Miles) [atid SCT Cid UndergroudLines__@Mile) |__—~+4| «dCi SSCS ae IDVOO TO et TILT ITH PEI-HLY 55-0198 120203-01 (03/96) ab 6 TABLE TE 03 TESORO ROUTE ANCHORAGE AREA ALTERNATIVE A = ee (Miles) 138kV: 2 -.3-_phase SCFF cables. 230kV: 4-1 phase SCFF cables. Overhead/submarine transition facilities at both ends. |TE.D.40 | 4.4 | Please see previous description. _| Please see previous description. | |TE.E.5O | _9.1_| Please see previous description. _| Please see previous description. | Underground Lines (0 Miles) TOTAL PEI-HLY 55-0198 120203-01 (03/96) ab 7 TABLE TE 04 TESORO ROUTE ANCHORAGE AREA ALTERNATIVE B Link Code | Total Length Location Type of Facility gale GEER ee ee TE. From: Point Woronzof Underground line. 3 - 1 phase XLPE To: Point Campbell cables. Submarine/underground transition facility at Point Campbell. Submarine cable. New route. From: Point Campbell To: Fire Island 138kV: 2-3 phase SCFF cables. New route. 230kV: 4 - 1 phase SCFF cables. Submarine/underground and submarine/overhead transition | 4.4 __| Please see previous description. Please see previous description. | 9.1 _| Please see previous description. Please see previous description. SE 2006 CE | ES | TET S| Submarine Cable (12.3 Miles) Underground Lines (3.9 Miles) Overhead Lines Gamay] = par PEI-HLY 55-0198 120203-01 (03/96) ab 8 TABLE TE 05 TESORO ROUTE ANCHORAGE AREA ALTERNATIVE C a ee oie) Please see previous description. Please see previous description. From: Point Campbell Submarine cable. To: Links TE.F.70 and AN.70 138kV: 2-3 phase SCFF cables. Generally follows the Tesoro pipeline across the inlet. 230kV: 4-1 phase SCFF cables. Underground/submarine facility located at Point Campbell. From: Links TE.F.60 and AN.70 Submarine cable. To: Point Possession and Link TE.G-H.80 138kV: 2-3 phase SCFF cables. Generally follows the Tesoro pipeline 230kV: 4-1 phase SCFF cables. across the inlet. Submarine/overhead transition facility located at Point Possession. Cost Estimate for Tesoro Route - Anchorage Area Alternative C ATR Ta aT Cost Item Estimated Difference Cost From Overhead Lines C2) MR TATE Submarine Cable (14.9 Miles) ; Underground Lines G.9 Niles PEI-HLY 55-0198 120203-01 (03/96) ab 9 TABLE TE 06 TESORO ROUTE ANCHORAGE AREA ALTERNATIVE D Link Code | Total Length Location Type of Facility noc me Eee | eee From: International Substation Overhead line on single pole To: — Links AN.20 and AN.40 near structures. Line Design 2. Minnesota and O’Malley Parallels west side of Minnesota Drive. From: Links AN.10 and AN.40 (near | Overhead line on single pole Minnesota and Klatt Road) structures. Line Design 2. To: Links AN.30 and AN.60 (near the new Klatt Road) New route. From: Intersection of Links AN.20 and | Overhead line on single pole AN.60 structures 0.4 mile along Klatt Road. To: — Links AN.70 and AN.80 Line Design 2. Parallels Klatt and Victor Roads. Underground line 0.4 mile along Victor Road to the submarine Transition station at Klatt and Victor transition area. Roads. 138kV: 3-1 phase XLPE cables. 230kV: 3-1 phase XLPE cables. From: Link AN.30 near Victor Road, | Submarine cable. south Anchorage To: Links TE.F.60 and TE.F.70 138kV: 2-3 phase SCFF cables. New route. 230kV: 4-1 phase SCFF cables, overhead. Submarine transition at Klatt and Victor Roads. TE.F.70 | 5.5 __| Please see previous description. Please see previous description. iT coal tte tet 21.8 ete | ie etisalat tetas | tebe ftntleltefetaetntareoeae | PEI-HLY 55-0198 120203-01 (03/96) ab 10 Cost Estimate for Tesoro Route - Anchorage Area Alternative D PEI-HLY 55-0198 120203-01 (03/96) ab 11 TABLE TE 07 TESORO ROUTE CAPTAIN COOK AREA BASE ROUTE Total Length (Miles) [| _4.6 | Please see previous description. _‘| Please see previous description. _| [| _4.9 __| Please see previous description. _| Please see previous description. __| eat tate ete lated Link/Substation Inf : Location Cost Estimate for Tesoro Route - Captain Cook Area Base Route eee eee enn en ROC isa Cost Item Estimated Difference Estimated Difference Cost From Cost From Base Route Base Route PEI-HLY 55-0198 120203-01 (03/96) ab 12 TABLE TE 08 TESORO ROUTE CAPTAIN COOK AREA ALTERNATIVE A (Miles) TE.1.130 13.8 From: Intersection of Links TE.G-H Overhead line on guyed X steel 80 and TE.G-H.90 structures. Line Design 1. To: Intersection of Links TE.J- , K.110 and TE.J-K.120 A new route designed to avoid conflicts with Captain Cook Recreation Area. Cost Estimate for Tesoro Route - Captain Cook Area Alternative A Overhead Lines (13.8 Miles) ) Submarine Cable (0 Mil Underground Lines (0 Miles) | _______0.9 Right of Way (Entire Route) res PEI-HLY 55-0198 120203-01 (03/96) ab 13 ENSTAR ROUTE INTRODUCTION The base Enstar Route starts at the International Substation in the Anchorage area and proceeds via overhead until it gets near Rabbit Creek where it transitions to underground with a reactive compensation station. The underground continues to about Potters where it transitions into _ submarine type cable to cross the Turnagain Arm. The submarine cable makes landfall on the Kenai Peninsula near the Burnt Island Creek area. The submarine cable is then transitioned into underground type of cable to a point near Big Indian Creek. At Big Indian Creek there would be a transition station with reactors and go back to overhead construction the rest of the way to the terminus at Soldotna. ROUTE DESCRIPTIONS AND COST ESTIMATE SUMMARIES The following tables more fully describe the base route for Enstar in addition to the identified alternatives and their associated costs. Also, please refer to the Alternative Corridors Map located in the map pocket at the back of this report to assist the reader in identifying specific links that constitute the route and alternatives: PEI-HLY 55-0198 120293-01 (03.96) ab 1 TABLE EN 01 ENSTAR ROUTE Link Code Total Location Type of Facility ‘Length (Miles) Substation N/A International Substation 138kV: One bay extension to future 138kV breaker and one half yard. 230kV: One by extension to future 138kV breaker and one half yard, 1- 230/138kV, 200 MVA autotransformer and new 230kV line terminal. EN.A.20 3.8 From: International Substation Overhead line on single pole To: Links AN.50, EN.A.30 and EN.A.50 (Minnesota and O’Malley Road) Parallels east side of the Alaskan Railroad. structures. Line Design 2. EN.A.50 3.2 From: Links EN.A.20, AN.50 and EN.A.30 O’Malley Road and Reactive N/A | Compensation Alaskan Railroad | To: Links EN.A.60 and EN.B.80 Transition Potter: new site Facility Overhead line on single pole structures. Line Design 2. (Rabbit Creek) Parallels east side of the Alaskan Railroad new Site 138kV: 1-22 MVAR reactor Rabbit Creek area: 1-60 MVAR reactor 230kV: Transition from overhead to underground. Underground line. 3 - 1 phase XLPE cables. From: Link EN.A.40 and EN.A.60 (Rabbit Creek) To: Potter Marsh and Link EN.B.90 Parallels east side of the Alaskan XLPE underground to submarine cable type. PEI-HLY 55-0198 120293-01 (03.96) ab 2 TABLE EN 01 ENSTAR ROUTE ee Link Code Total Location Type of Facility ‘Length (Miles) EN.B.90 71.9 From: Potter Marsh and Links _ Submarine cable. ; EN.B.70 and EN.B.80 To: Burnt Island/Chickaloon Bay, _| 138kV:. 2 -3 phase SCFF cables. Links EN.D.100 and AN.80 230kV: 4-1 phase SCFF cables. Generally parallels the existing Enstar pipeline. ransition Burnt Island Creek: new site Submarine cable type to XLPE may underground type cable. EN.D.100 From: Links AN.80 and EN.B.90, Underground cable. 3 - 1 phase near Burnt Island XLPE cables. To: Link EN.E.110 near Big Indian Creek Underground/submarine and underground/overhead transition Parallels the west side of the existing facilities located at the north and Enstar pipeline adjacent to the right-of- | south ends respectively. way. Right-of-way separation is currently unknown Reactive Big Indian Creek Area: new site 138kV: 1-22 MVAR reactor. Compensation 230kV: 1-60 MVAR reactor. Transition from underground to overhead. EN.E.110 33.7 From: EN.D.100, near Big Indian Overhead line on guyed X steel Creek structures. Line Design 1. To: QC.M.1.20 and QC.M.1.30 near Naptowne Parallels the west side of the existing Enstar pipeline adjacent to the right-of- way. Right-of-way separation is currently unknown. PEI-HLY 55-0198 120293-01 (03.96) ab 3 TABLE EN 01 ENSTAR ROUTE east of Soldotna -Links QC.M.L70 and QC.M.I.50 north of Mackey Lakes. Parallels the south side of the existing Quartz Creek transmission line adjacent to the right-of-way. Right-of-way separation is 100’ centerline to centerline. From: Link QC.M.130 and QC.M.1.50 north of Mackey Lakes. Links QC.M.1.60 and QC.M.1.80 north of the Sterling Highway. Q.C.M.1.70 To: Parallels north, west and southern sides of the Quartz Creek transmission line. Transmission line separation is 100’ centerline to centerline. Q.C.M.1.80: From: QC.M.1.60 and QC.M.1.70 north of Mackey Lakes To: Soldotna Substation Parallels west side of the existing Quartz Creek Transmission line. Transmission line separation is 100’ centerline to centerline. Will need to cross to east side of Soldotna Substation. Substation Soldotna Substation PEI-HLY 55-0198 120293-01 (03.96) ab 4 structures. Line Design 1 — 7.8 miles. Line Design 2 — 5.0 miles. Overhead line on guyed X steel structures. Line Design 1. Overhead line on single pole steel structures. Line Design 2. 138kV: One bay extension to existing 115kV breaker and one half layout, 138/115kV, 200 MVA autotransformer, 138kV line terminal. 230kV: One bay extension to existing 115kV breaker and one half layout. 230/115kV, 200 MVA autotransformer, 230kV line terminal. TABLE EN 01 ENSTAR ROUTE ee ee Link Code Total Location Type of Facility Length (Miles) Reactive N/A Portage Substation: new site on existing | 1 - 20 MVA Shunt Capacitor Bank Compensation 115kV Intertie and a 0 - 40 MVAR TCSC Bank. fro Ss 766] CCS ST TTTTTTCTC~SY Cost Estimate for the Enstar Route a EL Cost Item Estimated Estimated Cost Cost Overhead Lines GliMiey| 80S Submarine Cable C9Mile)| 383] 243 Underemd Lins ile] Teal 85 Big Indian Creek Portage Environmental Pemniting [23 23 Right of Way and Penniting Tat Pre-Construction Surveys Pe rors | ne) 230KV 138KV Engineering Survey/EIS Suppor |______sa[______43 [Construction Management [__48| 40 PEI-HLY 55-0198 120293-01 (03.96) ab 5 TABLE EN 02 ENSTAR ROUTE - ANCHORAGE AREA BASE ROUTE EN.A20 ——— Please see previous description ee eo B. Cost Estimate for Enstar Route - Anchorage Area Base Route Lian ZO Ta Cost Item Estimated Estimated Difference Cost Cost From Base Route Overhead Lines ge A A TT Edam ab TT cS ANTE ne SOT NTN TE nT [and Underground Cable@3 Miles] 6a] | sa] rors | ws gl se]! PEI-HLY 55-0198 120293-01 (03.96) ab 6 TABLE EN 03 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE A From: International Substation Overhead line on single pole To: Links EN.A.30 and EN.A.40 structures. Line Design 2. (near O’Malley Road) ; Parallels north side of International Airport Road and west side of the New Seward Highway. Follows existing toad rights-of-way. From: Links EN.A.10 and EN.A.30 (near O’Malley Road) To: EN.A.60 and EN.B.70 near Rabbit Creek Overhead line on single pole structures. Line Design 2. Parallels west side of the New Seward Highway and follows existing road right-of-way. From: Links EN.A.40 and EN.A.60 (near Rabbit Creek) To: Intersection of Links EN.B.80 and EN.B.90 at Potter Marsh Underground line. 3 - 1 phase XLPE cables. Overhead/underground and underground/submarine transition facilities located at north and south ends respectively. Parallels west side of the Old Seward Highway and follows existing overhead distribution line adjacent to and outside of existing road right-of-way, within distribution line right-of-way. EN.B.70 |EN.B.90_| EN.B.90 Total 719 Please see previous description. Please see previous description. ELTA TAA ALT ST Pe eT 7 SU 7 9 HE ini PEI-HLY 55-0198 120293-01 (03.96) ab th Cost Estimate for Enstar Route - Anchorage Area Alternative A PC 80KV | Item | raat a Cost Cost Overhead Lines Gamespy] = Per Submarine Cable (TMi) 383] 00 Land Underground Cable @-8Miles| 7a] oa} 57 TOTAL HI PEI-HLY 55-0198 120293-01 (03.96) ab 8 Link Code TABLE EN 04 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE B Total Length From: International Substation To: Links AN.20 and AN.40 near Minnesota and O’Malley’ Parallels west side of Minnesota Drive. From: Links AN.10 and AN.40 near Minnesota Drive To: Links AN.60 and AN.30 near Klatt Road New route. From: Intersection of Links AN.20 and AN.60 near Klatt Road To: Links AN.70 and AN.80 southern Anchorage near Victor Parallels Klatt and Victor Roads. Road From: Links AN.30 and AN.70 southern Anchorage at Victor Road Links EN.C.90 and EN.D.100, Burnt Island near Chickaloon PEI-HLY 55-0198 120293-01 (03.96) ab 9 Overhead line on single pole structures. Line Design 2. Overhead line on single pole structures. Line Design 2. Overhead line on single pole structure along Klatt Road. Line Design 2. Underground cable along Victor Road. 138kV: 3-1 phase XLPE cables. 230kV: 3-1 phase XLPE cables. Overhead/underground transition at Klatt and Victor Roads. Submarine cable. 138kV: 2-3 phase SCFF cables. 230kV: 4-1 phase SCFF cables. Underground/submarine transition facilities located at south end. Cost Estimate for Enstar Route - Anchorage Area Alternative B ORCS, TR TORY Cost Item Overhead Lines (4.1 Miles) i a Ei Submarine Cable (113Miles)| 327] aa] 33.1] 86) Land Underground Cable (0.8 Miles) Gol —+id4| 6H) TOTAL PEI-HLY 55-0198 120293-01 (03.96) ab 10 TABLE EN 05 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE C ae “ofl From: International Substation Overhead line on single pole To: Links AN.20 and AN.40 (near | structures. Line Design 2. O'Malley Road) Parallels west side of the Minnesota Drive. From: Links AN.10 and AN.20 near Overhead line on single pole Minnesota and Klatt Roads structures. Line Design 2. To: Links AN.50 and AN.60 near Minnesota and O’Malley Roads Parallels southwest side of Minnesota Drive. : Links AN.40 and AN.60 near Overhead line on single pole Minnesota and O’Malley Roads | structures. Line Design 2. Links EN.A.20 and EN.A.50 near O’Malley Road and the Alaskan Railroad Parallels south side of O’Malley Road. From: Links AN.50 and EN.A.30 near | Overhead line on single pole O’Malley Road and the Alaska | structures. Line Design 2. Railroad To: Links EN.A.60 and EN.B.80 near Rabbit Creek Parallels east side of the Alaskan Railroad. From: Links EN.A.60 and EN.A.50 Underground line. 3 - 1 phase near Rabbit Creek XLPE cables. To: Links EN.B.70 and EN.B.90 near Potter Marsh Underground/submarine transition facilities located near Potter Marsh. Parallels east side of the Alaskan Railroad. PEI-HLY 55-0198 120293-01 (03.96) ab 11 TABLE EN 05 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE C (Miles) bl 7a From: Links EN.B.70 and EN.B.80 Submarine cable. near Potter Marsh To: AN.80 and EN.D.100 near Burnt Island 138kV: 2 - 3 phase SCFF cables. 230kV: 4- 1 phase SCFF cables. Generally follows the Enstar pipeline. Underground/submarine transition facilities and both ends. Submarine Cable (7.9 Miles) Land Underground Cable (2.3 Miles) rors | ws od ses]! PEI-HLY 55-0198 120293-01 (03.96) ab 12 TABLE EN 06 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE D ——, (Miles) |AN.10 | 2.9 _| Please see previous description. Please see previous description. |AN.40 {| 0.5 _| Please see previous description. Please see previous description. |AN.50 | _'1.0__| Please see previous description. Please see previous description. EN.A.30 From: Links EN.A.20 and AN.5O near | Overhead line on single pole O’Malley Road and Minnesota | structures. Line Design 2. To: Links EN.A.10 and EN.A.40 near O’Malley Road eT cock NNT EA 8 £2 ec FA | ace Parallels south side of O’Malley Road. Cost Estimate for Enstar Route - Anchorage Area Alternative D Overhead Lines (7.4 Miles) Submarine Cable (7.9 Miles) ‘Land Underground Cable (2.8 Miles), PEI-HLY 55-0198 120293-01 (03.96) ab 13 TABLE EN 07 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE E ee | Miles) EN.A.10 Please see previous description. Please see previous description. EN.A.40 Please see previous description. Please see previous description. EN.A.60 - From: Links EN.A.30 and EN.B.70 Overhead line on single pole near O’Malley Road and Seward | structures. Line Design 2. Highway To: Links EN.A.50 and EN.B.80 |EN.B.80__| _2.3___| Please see previous description. _| Please see previous description. —_| RS a ee ee near Rabbit Creek Parallels New Seward Highway; the specific crossing of the New and Old Seward Highway interchange has yet to be determined. st Estimate for Route - Anchorage Area Alternative E TRV Cost Item Estimated Difference Estimated Cost From Cost Base Route Overhead Lines rw! SES Submarine Cable (79s) 38300] aes Cand Underground Cable @3Miles| afoot soo rome | on!) PEI-HLY 55-0198 120293-01 (03.96) ab 14 TABLE EN 08 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE F . (Miles) Please see previous description. Please see previous description. }AN.40 | ~——_—~0.5__| Please see previous description. Please see previous description. |AN.SO.[ 1.0 __| Please see previous description. Please see previous description. From: EN.A.20 and EN.A.50 near the | Overhead line on single pole Railroad structures. Line Design 2. To: EN.A.10 and EN.A.40 at New Seward Highway Parallels south side of O’Malley Road in between the Alaskan Railroad and the New Seward Highway. Please see previous description. Please see previous description. uM 0.4 eu K} Please see previous description. Please see previous description. EN.B.80 Please see previous description. Please see previous description. a Please see previous description. Please see previous description. Ht ee ee ee Cost Estimate for Enstar Route - Anchorage Area Alternative F 230kV 138kV Difference Estimated From Cost Overhead Lines (7.8 Miles) A Submarine Cable (7.9 Miles) ; Land Underground Cable (2.3 Miles), TOTAL PEI-HLY 55-0198 120293-01 (03.96) ab 15 TABLE EN 09 ENSTAR ROUTE - SOLDOTNA AREA BASE ROUTE see caer ERIN caad NRA ce (Miles) [QC.M.1.30[ 12.8 _| Please see previous description. Please see previous description. QC.M.1.70| 6.8 —_| Please see previous description. Please see previous description ee M.1.80 | oe Please see previous description. Please see previous description. Cost Item TOTAL PEI-HLY 55-0198 120293-01 (03.96) ab 16 TABLE EN 10 ENSTAR ROUTE - SOLDOTNA AREA ALTERNATIVE A (Miles) From: Links EN.E.110 and Overhead line on guyed X steel QC.M.1.30 east of Naptowne structures. Line Design 1. To: Links QC.M.1.40 and : QC.M.1.10 Parallels north side of the Enstar pipeline. Separation requirements are currently unknown. From: Links QC.M.1.10 and Overhead line on guyed X steel QC.M.1.20 structures. Line Design 2. To: Links QC.M.1.50 and QC.M.1.60 Parallels north side of the Enstar pipeline. Separation requirements are currently unknown. From: QC.M.1.40 and QC.M.1.60 To: QC.M.1.30 and QC.M.1.70 Overhead line on guyed X steel structures. Line Design 1. Parallels north side of the Enstar pipeline. Separation requirements are currently unknown. QC.M.1.70| 6.8 —_| Please see previous description. Please see previous description. QC.M.1.80{ 0.8 _| Please see previous description. Please see previous description. [Total wags | 20 |e | PEI-HLY 55-0198 120293-01 (03.96) ab 17 Cost Estimate for Enstar Route - Soldotna Area Alternative A ET RV TsaRV Overhead Lines (20.1 Miles) Submarine Cable (0.0 Miles) and Underground Cable (0.0 Miles) PEI-HLY 55-0198 120293-01 (03.96) ab 18 TABLE EN 11 ENSTAR ROUTE - SOLDOTNA AREA ALTERNATIVE B Link/Substation Information ai (Miles) From: Links QC.M.1.40 and Overhead line on guyed X steel QC.M.1.50 west of Mackey structures. Line Design 1. Lakes To: Links QC.M.1.70 and QC.M.1.80 north of Sterling Highway Parallels existing underground pipeline. Follows existing pipeline right-of-way, transmission line separation is currently unknown. PEI-HLY 55-0198 120293-01 (03.96) ab 19 TABLE EN 12 ENSTAR ROUTE - SOLDOTNA AREA ALTERNATIVE C Link/Substation Information Hae arn -(Miles) QC.M.1.20 Please see previous description. Please see previous description. From: Links QC.M.1.20 and Overhead line on guyed X steel i QC.M.1.40 near Naptowne structures. Line Design 1. r To: Links QC.M.2.05 and QC.M.2.10 north of Sterling Highway Parallels existing Quartz Creek Transmission Line. Transmission line separation is 100' centerline to centerline. From: Links QC.M.1.10 and Overhead line on steel structures. QC.L.120 To: Soldotna Substation Line Design 1 — 10.6 miles. Parallels existing overhead transmission | Line Design 2 — 3.0 miles. line . Transmission line separation is 100" centerline to centerline. Overhead Lines Submarine Cable 0. 0 a Land Underground Cable (0.0 Miles) Right of Way (Entire Route) PEI-HLY 55-0198 120293-01 (03.96) ab 20 UARTZ CREEK INTRODUCTION The base Quartz Creek Route starts at University Substation in Anchorage and, essentially, follows the existing 115kV intertie all the way to the Kenai Peninsula where it would terminate at Soldotna Substation. At Bird Point, alternative routes crossing the Turnagain Arm from Bird Point to the Snipers Point area and proceeding south along Sixmile Creek to rejoin the existing line near Hope Junction-have been estimated. The crossing-of the Turnagain Arm.at Bird point has been estimated for both overhead and submarine crossing alternatives. The submarine crossings has been estimated using directional boring techniques to enable the installation of an HPGF cable system. ROUTE DESCRIPTIONS AND COST ESTIMATE SUMMARIES The following tables more fully describe the base route for Quartz Creek Route in addition to the identified alternatives and their associated costs. Also, please refer to the Alternative Corridors Map located in the map pocket at the back of this report to assist the reader in identifying specific links that constitute the route and alternatives: PEI-HLY 55-0198 120293-01 (03/96) ab 1 TABLE QC 01 QUARTZ CREEK ROUTE Link Code | Total-Length Substation 138kV: One by extension of existing main and transfer layout. 230kV: New 230kV 4 Breaker Ring Bus. Connect to existing 230/138kV transformers. Qc.A.10 i From: University Substation Overhead line on guyed X steel To: Link QC.B.20 near Campbell structures. Line Design 2. Creek Could parallel south side of existing Quartz Creek transmission line along 5 Tudor Road, then follow either side through Powerline Pass. Transmission line separation id 100' centerline to : centerline with potential crossovers. From: Link QC.A.10 near Campbell Overhead line on steel structures. Creek To: Link QC.C.30 near Indian Line Design 2 — 1.0 mile. Could parallel either side of existing Line Design 4 — 10.1 miles. transmission line. Transmission line separation is 100' centerline to centerline. From: Link QC.B.20 near Indian Overhead line on guyed X steel To: Link QC.D.40 near Bird Point | structures. Line Design 1. Could parallel either side of the existing transmission line. Transmission line separation is 100' centerline to centerline. From: Links QC.D.1.A.10 and Double circuit steel lattice. Line QC.D.1.B.10 near Bird Point Design 6. To: Links QC.E.50 near Girdwood Rebuild and double circuit existing transmission line for approximately 6.5 miles. PEI-HLY 55-0198 120293-01 (03/96) ab 2 TABLE QC 01 QUARTZ CREEK ROUTE Link/Substation Inf P Link Code | Total Length Location Type of Facility (Miles) QC.E.50 From: Link QC.D.40 near Girdwood Overhead line on guyed X steel To: Link QC.F.60 near Portage structures. Line Design 1. Could parallel either side of the existing transmission line. Transmission line separation is 100' centerline to centerline. Overhead line on guyed X steel structures. Line Design 5. From: Link QC.E.50 near Portage To: Link QC.G.70 near Ingram Creek Could parallel either side of the existing transmission line. Transmission line separation is 100' centerline to centerline. From: Link QC.F.60 near Ingram Creek To: Link QC.H.80 near Turnagain Pass Overhead line on guyed X steel structures. Line Design 4. Could parallel either side of the existing transmission line. Transmission line separation is 100' centerline to centerline. From: Link QC.G.70 Overhead line on guyed X steel To: Link QC.1.90 structures. Line Design 4. Could parallel either side of the existing transmission line. Transmission line separation is 100' centerline to centerline. From: Link QC.H.80 near Turnagain Pass To: Link QC.J.100 near Hope Junction Overhead line on guyed X steel structures. Line Design 4. Could parallel either side of the existing transmission line. Transmission line separation is 100' centerline to centerline. PEI-HLY 55-0198 120293-01 (03/96) ab 3 TABLE QC 01 QUARTZ CREEK ROUTE Li From: Link QC.1.90 near Hope Junction To: Link QC.K.110 near Daves Creek Overhead line on guyed X steel structures. Line Design 4. Parallel western side of the existing transmission line. Transmission line separation is 100' centerline to centerline. From: Link QC.J.100 near Daves Creek To: Link QC.L.120 near Daves Creek Overhead line on guyed X steel structures. Line Design 1. Parallel western side of the existing transmission line. Transmission line separation is 100' centerline to centerline. From: Link QC.K.110 near Hideout Hill To: Link QC.M.1.15 near Naptowne Overhead line on guyed X steel structures. Line Design 1. Parallels northern side of the existing transmission line. Transmission line separation is 100' centerline to centerline. PEI-HLY 55-0198 120293-01 (03/96) ab 4 TABLE QC 01 QUARTZ CREEK ROUTE Link/Substation Information Link Code Total Location Type of Facility Length (Miles) QC.M.1.15 From: Link QC.L.120 near Naptowne | Overhead line on guyed X steel To: Link QC.M.1.20 and EN.E.110 north of Naptowne Parallels eastern side of the existing Quartz Creek transmission line. Transmission line separation is 100' centerline to centerline. 1.8 QC.M.1.30 12.8 From: Link EN.E.110 east of Soldotna | Overhead line on steel structures. To: — Links QC.M.I.70 and Line Design 1. QC.M.I.50 north of Mackey QC.M.1.70 QC.M.1.80 Lakes PEI-HLY 55-0198 120293-01 (03/96) ab 5 Line Design 1 — 7.8 miles. Parallels the south side of the existing Quartz Creek transmission line adjacent to the right-of-way. Right-of-way separation is 100' centerline to centerline. Line Design 2 — 5.0 miles. From: QC.M.1.30 and QC.M.1.50 To: QC.M.1.60 and QC.M.1.80 Overhead line on guyed X steel structures. Line Design 1. Parallels south side of the existing Quartz Creek transmission line. From: QC.M.1.60 and QC.M.1.70 Overhead line on single pole steel To: Soldotna Substation structures. Line Design 2. Parallels east side of the existing Quartz Creek transmission line. Cross to east side Soldotna Substation Soldotna Substation 138kV: One Bay extension to existing 115kV Breaker and one half layout, 138/115kV, 200 MVA autotransformer, 138kV line terminal. 230kV: One Bay extension to existing 115kV Breaker and one half layout. 230/115kV, 200 MVA autotransformer, 230kV line terminal. TABLE QC 01 QUARTZ CREEK ROUTE Li ion Infc Type of Facility Link Code Total = (Miles) Reactive N/A Toul a Portage Substation: new site on existing | 1-20 MVAR Shunt Capacitor Bank 115kV Intertie & 0-40MVAR TCSC Bank. Cost Estimate for the Quartz Creek Route ev TaaRV Cost Item Estimated Estimated Cost Overhead Lines (140.7 Miles) 86.0 80. Submarine Cable (0.0 Miles) Underground Lines Reactive Compensation: Portage Environmental Permitting ad : § a an oo Right of Way and Permitting 0.5 Pre-Construction Surveys TOTAL pas] a 230KV 138KV Engineerng/SuveyES Suppor [at S—=*S [Construction Management [saa PEI-HLY 55-0198 120293-01 (03/96) ab 6 TABLE QC 02 QUARTZ CREEK ROUTE - SOLDOTNA AREA BASE ROUTE Link/Substation Infi i Link Code Total Location Type of Facility Length (Miles) . FOCM.115 [1.8 | Please see previous description. | Please see previous description. | | 6.8 | Please see previous description. | Please see previous description. | OC.M.1.80 | 0.8 | Please see previous description. Please see previous description. | 2 Cost Estimate for Creek Route - Soldotna Area Base Route iv TAK Overhead Lines (22.2Miles) Submarine Cable PEI-HLY 55-0198 120293-01 (03/96) ab 7 TABLE QC 03 QUARTZ CREEK ROUTE QUARTZ CREEK/SOLDOTNA ALTERNATIVE A Link Code Total Length Location Type of Facility (Miles) Parallels north side of an existing Overhead line on guyed X steel transmission line. Transmission line structures. Line Design 1. separation is 100' centerline to centerline. OC Ef OE __ | Fieaes poe prevoes ceecripece.__} Fea ene previows deecripocm,_| From: QC.M.1.40 and QC. ™. 1.50 Overhead line on guyed X sical To: QC.M.1.70 and QC.M.1.80 structures. Line Design 1. QC.M.1.60 Parallels Enstar pipeline route. Transmission line separation is currently unknown. QC.M.1.80 | 0.8 _| Please see previous description. Please see previous description. A ES = A eT Cost Estimate for Creek Route - Soldotna Area Alternative A 230kV 138kV Estimated Difference Estimated Difference Cost From Cost From Base Route Base Route ae eM Se AL backs Can Tn OoMen (mT mi moe nee mmm mm TOO Land Underground Cable @.0Miles|_—______ oof oof oof 0} I 02 oa 2) Rc a ef ETT one es ee PEI-HLY 55-0198 120293-01 (03/96) ab 8 TABLE QC 04 QUARTZ CREEK ROUTE SOLDOTNA ALTERNATIVE B Link/Substation Information Link Code | Total Lengt! Location Type of Facility ao. QC.M.2.05 a Please see previous description. Please see previous description. Parallels existing transmission line Overhead line on steel structures. transmission line separation is 100° centerline to centerline. Line Design 1 — 10.6 miles. Line Design 2 - 3.0 miles. Cost Estimate for Creek Route - Soldotna Area Alternative B ew TBR Estimated Difference Estimated Difference Cost From Cost From (Overhead Lines U7 6Miley[ 9. Submarine Cable (0.0Milesy[ 0.9 [Land Underground Cable (0.0Miles| 0.0 Right of Way (entireroute) ‘| ____ 03 TOTAL PEI-HLY 55-0198 120293-01 (03/96) ab 9 TABLE QC 05 QUARTZ CREEK ROUTE SOLDOTNA ALTERNATIVE C | 4.0 _| Please see previous description. From: Links QC.M.2.05 and QC.M.2.10 To: Links QC.M.1.20 and QC.M.1.40 New route. From: QC.M.1.10 and QC.M.1.20 To: QC.M.1.50 and QC.M.1.60 Parallels northern side of the existing Enstar pipeline. Separation requirements are currently unknown. From: QC.M.1.40 and QC.M.1.60 To: QC.M.1.30 and QC.M.1.70 Parallels northern side of the existing Enstar pipeline. Separation requirements are currently unknown. From: QC.M.1.30 and QC.M.1.50 To: QC.M.1.60 and QC.M.1.80 Parallels south side of the existing Quartz Creek transmission line. From: QC.M.1.60 and QC.M.1.70 To: Soldotna Substation Parallels east side of the existing Quartz Creek transmission line. PEI-HLY 55-0198 120293-01 (03/96) ab 10 Please see previous description. Type of Facility Overhead line on guyed X steel structures. Line Design 1. Overhead line on single pole steel structures. Line Design 2. Overhead line on guyed X steel structures. Line Design 1. Overhead line on guyed X steel structures. Line Design 1. Overhead line on single pole steel structures. Line Design 2. ‘ost Estimate for Creek Route - Soldotna Area Alternative Overhead Lines : S) Submarine Cable .0 Miles) Land Underground Cable (0.0 Miles) PEI-HLY 55-0198 120293-01 (03/96) ab 11 TABLE QC 07 QUARTZ CREEK ROUTE - BIRD POINT AREA BASE ROUTE Link/S tion Information Location Type of Facility Link Code | Total Length (Miles) 1QC.D.40 [6.5 _| Please see previous description. Please see previous description. QC.E.50 | __9.1 __| Please see previous description. Please see previous description. [QC.1.90 | 11.5 ___| Please see previous description. | Please see previous description. | A Cost Estimate for Creek Route - Bird Point Area Base Route 230kV 138kV Cost Item Estimated Estimated Difference Cost Cost From Base Route 26.9 Overhead Lines (38.8 Miles Submarine Cable (0.0Miles)[ ==—s«. PT [and Underground Cable @.0Miley]_______oof |__| Reactive Compensation: Portage TOTAL PEI-HLY 55-0198 120293-01 (03/96) ab 12 TABLE QC 08 QUARTZ CREEK ROUTE - BIRD POINT ALTERNATIVE A (AERIAL) Link/Substation Information Link Code | Total Length Location Type of Facility (Miles) QC.D1A.10 From: QC.C.30 and QC.D.40 Steel towers located on both shore To: QC.D.2.10 landings with a single steel tower located in the Arm. New route. Aerial crossing of the Turnagain Arm from the base of Alpenglow Mountain to Bird Point. From: QC.D1A.10 Overhead line on guyed X steel To: QC.1.90 and QC.J.100 structures. Parallels existing distribution line and also will require approximately 2 miles new right-of-way. Transmission line separation is 100’ centerline to centerline. Creek Route -Bird Point Area Alternative A (Aerial 230kV 138kV [a Item Estimated Difference Estimated Cost From Cost Overhead Lines (12.0 Miles) ary[__163| a0 Swinatne Case — foosaiey| ———— vo ——va] ——0g} ——v0 Land Underground Cable (0.0 Miles) OM 00 oof ____00} i ion: : 0.0) 6.0) Portage Reactive Compensation: Cost Estimate for PEI-HLY 55-0198 120293-01 (03/96) ab 13 TABLE QC 09 QUARTZ CREEK ROUTE - BIRD POINT ALTERNATIVE B (SUBMARINE) Type of Facility Bird Point area: new site 138kV: 10 MVAR reactor. Compensation 230kV: 22 MVAR reactor. Transition from overhead to submarine or pipe type cable. From: QC.C.30 and QC.D.40 Submarine cable. To: QC D.2.10 QC.DIB.10 138kV: 1-3 phase HPGF. New route from Bird Point to Six Mile Creek. 230kV: 4 - 1 phase SCFF cables. Overhead/submarine transition facilities located at both ends of the cable. Submarine: 4.0 miles. Overhead: 1.5 miles. Line Design 4. QC.D.2.10 Please see previous description. Please see previous description. Reactive Six Mile Creek area: new site 130kV: 10 MVAR reactor. Compensation 230kV: 22 MVAR reactor. Transition from submarine or pipe type cable to overhead. PEI-HLY 55-0198 120293-01 (03/96) ab 14 Cost Estimate for Creek Route -Bird Point Area Alternative B (Submarine PEI-HLY 55-0198 120293-01 (03/96) ab 15 OVERHEAD TRANSMISSION LINE INTRODUCTION This section contains spreadsheet which documents overhead line cost estimates. These estimates are based on the preliminary designs presented in the Draft Design Section Report for this project. The estimates are organized by route and local alternatives similar to the route estimates contained in an earlier section of this report. Please refer to the route sections for link descriptions. The per mile line costs have been adjusted in some cases to allow for conditions not anticipated in the per mile line estimate. These cases include: e Link TE.D.40 across Fire Island. Costs have been increased because of access. e Links QC.C.30, QC.E.40, and QC.F.50 have been reduced because a reduced clearing effort is anticipated in these areas. e Links QC.D.40 contains a line item for temporary installation and removal of a line during construction of the double circuit steel line. Please note that guyed X structures were selected for cost estimating because they were practical for the locations in which they were applied and have costs which are comparable to wood pole H-frame and guyed vee structures. The type of structure chosen for final design will be determined after a detailed investigation of the route, agency requirements, and other factors. PEI-HLY 55-0198 120293-01 (03/96) ab 1 Tesoro Route Overhead Lines TABLE OHO01 - COST ESTIMATING INFORMATION TESORO ROUTE - OVERHEAD LINES Fea al lanl} a $2,247 a See en TEGHa— | 238 | 3 | $s4oat s46ay siiosof s44o[ $440 [$10,471 G-H.90 | 2.2 [3 | $968 JKu0 [4.9 | $2,275 I-K.120 | 1 | SUB TOTALS $17,057 $16,164 ENGINEERING 7.00% $1,194 $1,131 CONSTRUCTION MGMT. 6.00% $1,023 $970 TOTALS $19,275 $18,265 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th 1 r:/WAR/CHUGACH/SIP102.XLS TABLE OHO1 TABLE OH02 - COST ESTIMATING INFORMATION TESORO ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES TESORO ROUTE - ANCHORAGE AREA BASE ROUTE & ALTERNATIVES A, B & C 230KV 138KV BA ADJU ADJU LINK LINK | LINE COST le ae LINK COST a LINK —_ MILES] DESIGN| (PER MILE) | (PER MILE PER MILE peue | 66) 3 a ee a seo — saa] 184] $2,129 | SUB TOTALS $2,247 $2,129 ENGINEERING 7.00% $157 $149 CONSTRUCTION MGMT. 6.00% $135 $128 TOTALS $2,539 $2,406 TESORO ROUTE - ANCHORAGE AREA ALTERNATIVE D 230KV 138KV ADJU ADJU LINK LINK | LINE COST LINK COST COST a LINK — MILES| DESIGN| (PER MILE PER MILE) | (PER MILE AREA eR ee SOR SORE Se eSNG eee Ee AN.20_ | 08 | 2) | sse1f $561] $449 | $536] $536 [$429 | AN 30] 04 TT $561 $561 [$225 $536 $536 $214 SUB TOTALS $2,302 $2,196 ENGINEERING 7.00% $161 $154 CONSTRUCTION MGMT. 6.00% $138 $132 TOTALS $2,601 $2,482 DIFFERENCE FROM ANCHORAGE BASE ROUTE $62 $76 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS TABLE OH02 TABLE OH03 - COST ESTIMATING INFORMATION TESORO ROUTE - CAPTAIN COOK ALTERNATIVES - OVERHEAD LINES TESORO ROUTE - CAPTAIN COOK AREA BASE ROUTE COST COST COST LINK | LINK LINE bi PER LINK Ape ae MILES| DESIGN Reg sl gant eee sary eet ste el TEV in49-[ 3 | sues | sue | sa73 | sua | sua] 3] SUB TOTALS $3,296 $3,124 ENGINEERING 7.00% $231 $219 CONSTRUCTION MGMT. 6.00% $198 $187 ( a TOTALS $3,725 $3,530 TESORO ROUTE - CAPTAIN COOK AREA ALTERNATIVE A 138KV COST COST | COST | ADJUSTED | COST LINK |LINKM] LINE lps PER LINK hia oe PER LINK IDENT | ILES | DESIGN SUB TOTALS $6,281 ENGINEERING 7.00% $440 CONSTRUCTION MGMT. 6.00% $377 TOTALS $7,097 DIFFERENCE FROM CAPTAIN COOK BASE ROUTE $3,373 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th t:/WAR/CHUGACH/SIP102.XLS 3 TE.1.130 es a a $6,281 eel _ $5,742 | $5,742 $402 $344 $6,488 $2,958 TABLE OH03 Enstar Route Overhead Lines TABLE OH04 - COST ESTIMATING INFORMATION ENSTAR ROUTE - OVERHEAD LINES 230KV Ser BA ADJUST! LINK LINK | LINE COST cOsr a LINK COST COST ae LINK IDENT _ | MILES] DESIGN] (PER PER MILE PER MILE, EN.A.20 a a EN ASD p32 [2 [sent S61 797] 536 536f 1,714 ENETIOW[ 337 [1 | a85]_ass] 15338] a6] are 14a cm] 78-| 1] 435] ass] 3.350] aio] sie] — 3.943 QC.M.1.30 | 5.0 | 2 | | S61] 2,807] 536] 536 2,678 | 455] | 4G] 46] 2,829] L561) SUB TOTALS $29,170 $26,952 ENGINEERING 7.00% $2,042 $1,887 CONSTRUCTION MGMT. 6.00% $1,750 $1,617 TOTALS $32,962 $30,456 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 4 TABLE OH04 TABLE OH05 - COST ESTIMATING INFORMATION ENSTAR ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - ANCHORAGE AREA BASE ROUTE ater SST ADJU ADJU OST LINK LINK | LINE COST ea LINK COST aa PER LINK | IDENT __| MILES} DESIGN| (PER MILE PER MILE)| (PER MILE EN.A.20_ sa] 2 soar | 50] $2,134 $536 $e] sie | $2,036 EN.A5O_ [3.2 [ 2 [$561 $561] __ $1,797 | $536 $536 SUB TOTALS $3,930 $3,750 ENGINEERING 7.00% $275 $262 CONSTRUCTION MGMT. 6.00% $236 $225 TOTALS $4,441 $4,237 ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE A Ses 138KV ADJU O BA ADJUSTED O LINK LINK | LINE COST ay PER LINK COST PER LINK IDENT _ | MILES} DESIGN] (PER MILE)} (PER MILE PER MILE) ENAIO [57 | 2 | ss6if $561] $3,200] $536 =ss56 [| $506 [ST ENA40 [26 [2 | ss61f_ 8561] $1,460] $536 | $536] $1,393 SUB TOTALS $4,660 $4,446 ENGINEERING 7.00% $326 $311 CONSTRUCTION MGMT. 6.00% $280 $267 TOTALS $5,266 $5,024 DIFFERENCE FROM ANCHORAGE BASE ROUTE $825 $787 NOTE: A 10% contingency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 5 TABLE OH05 TABLE OH05 - COST ESTIMATING INFORMATION ENSTAR ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE B 230KV 138KV ADJUSTED ‘0 BA ADJU D OST LINK LINK | LINE COST COST PER LINK COST PER LINK — MILES] DESIGN] (PER MILE)} (PER MILE PER MILE) AN.IO [29 [2 [S561 $561] $1,628 Sse [5590] [$1,553 | JAN.20_ | 08 | 2 | S561] $561] $449 | $536{ $536 | $429 | JAN.30_ ff 04 [2 fT ss61f S561] $225] $536] 8536 [$214 | SUB TOTALS $2,302 $2,196 ENGINEERING 7.00% $161 $154 CONSTRUCTION MGMT. 6.00% $138 $132 TOTALS $2,601 $2,482 DIFFERENCE FROM ANCHORAGE BASE ROUTE ($1,840) ($1,755) NOTE: A 10% contingency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) Ih r:/WAR/CHUGACH/SIP102.XLS 6 TABLE OH05 TABLE OH05 - COST ESTIMATING INFORMATION ENSTAR ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE C 230KV 138KV BA ADJUSTED O BA ADJUSTED O LINK LINK | LINE COST COST PER LINK COST COST PER LINK IDENT _ | MILES} DESIGN| (PER MILE)| (PER MILE) PER MILE)| (PER MILE AN IO _{_2.5 | 2} _Ss6i |_s561 | _51,628 | $536] $536 | $1,553 | ANA OS td $561] $561] $281] $536] $536 [$268 | ra 50 $561 $536 $536 EN.A.50 $561 $1797) | es $536) ee $5361) S714 SUB TOTALS $4,267 $4,071 ENGINEERING 7.00% $299 $285 CONSTRUCTION MGMT. 6.00% $256 $244 TOTALS $4,822 $4,600 DIFFERENCE FROM ANCHORAGE BASE ROUTE $381 $363 NOTE: A 10% contingency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 7 TABLE OH05 TABLE OH0S5 - COST ESTIMATING INFORMATION ENSTAR ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE D 230KV Sern ADJU ADJU LINK COST “COST a LINK COST eal eh LINK eN __|MILES} DESIGN] (PER MILE)| (PER MILE oie PER MILE )j_ __—_—*{(PERMILE)|(PERMILE)| SUB TOTALS $4,155 $3,964 ENGINEERING 7.00% $291 $277 CONSTRUCTION MGMT. 6.00% $249 $238 ————e (sa SS TOTALS $4,695 $4,479 DIFFERENCE FROM ANCHORAGE BASE ROUTE $254 $242 NOTE: A 10% contingency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 8 TABLE OH05 TABLE OH05 - COST ESTIMATING INFORMATION ENSTAR ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE E 230KV 138KV BA ADJUSTED O BA ADJUSTED OST LINK LINK | LINE COST COST PER LINK COST COST PER LINK IDENT _ | MILES} DESIGN| (PER MILE)} (PER MILE: PER MILE)} (PER MILE EN.A1O | 5.7 | 2 T ss61f $561] $3,200 $536] $3,053 EN.A40 | 26 [ 2 [ ssoit ss61[ si460[ $536 [$536 |] $1,393 EN.A6O | 04 [2 [ ssoit $561] $225 $536 SUB TOTALS $4,885 $4,660 ENGINEERING 7.00% $342 $326 CONSTRUCTION MGMT. 6.00% $293 $280 TOTALS $5,520 $5,266 DIFFERENCE FROM ANCHORAGE BASE ROUTE $1,079 $1,029 NOTE: A 10% contingency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) Ih r:/WAR/CHUGACH/SIP102.XLS 9 TABLE OHO05 TABLE OH0S - COST ESTIMATING INFORMATION ENSTAR ROUTE - ANCHORAGE ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - ANCHORAGE AREA ALTERNATIVE F 138KV BASE ADJU D O BASE AD ‘ED OST LINK LINK | LINE COST COST PER LINK COST PER LINK IDENT _| MILES} DESIGN] (PER MILE)| (PER MILE PER MILE)| (P ANIO | 29 | 2 | S$561] $561] $1,628 $536] $1,553 JAN40 | 0.5 [2 | $561 | $561 [$281 $536 | $536 N AN.SO_ | 1 [2 Serf S561 ser $536 [$536 | $536 | ENA3O | 04 | 2 | sse1f sso1] $225] $536] $536 | $214 | ENA4O | 26 [| 2 | sse1f sse1t si4oo] $536 [$536 [$1,393 | ENACO | 04 | 2 | 561 $561] $225] $536] $536] $214 | SUB TOTALS $4,380 $4,178 ENGINEERING 7.00% $307 $292 CONSTRUCTION MGMT. 6.00% $263 $251 TOTALS $4,949 $4,721 DIFFERENCE FROM ANCHORAGE BASE ROUTE $508 $484 NOTE: A 10% contingency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th 1:/;WAR/CHUGACH/SIP102.XLS 10 TABLE OH0S5 TABLE OH06 - COST ESTIMATING INFORMATION ENSTAR ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - SOLDOTNA AREA BASE ROUTE COST COST COST COST LINK LINK LINE = PER LINK hie PER LINK IDENT MILES | DESIGN Se as $3,550 ae aa $3,245 ADJUSTED QC.M.1.30] 5.0 | 2 | ss61_ $561] $2,807 $2,678 | $455 | | $561 | SUB TOTALS $9,902 $9,181 ENGINEERING 7.00% $693 $643 CONSTRUCTION MGMT. 6.00% $594 $551 TOTALS $11,189 $10,375 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS ll TABLE OH06 TABLE OH06 - COST ESTIMATING INFORMATION ENSTAR ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - SOLDOTNA AREA ALTERNATIVE A 230KV 138KV COST | ADJUSTED | COST COST LINK ——— LINE pesopes Reyne PER LINK aoe | IDENT | ES ___| DESIGN |_ MILE) |(PERMILE)|___ ADJUSTED} COST SUB TOTALS $9,903 $9,212 ENGINEERING 7.00% $693 $645 CONSTRUCTION MGMT. 6.00% $594 $553 TOTALS $11,191 $10,410 DIFFERENCE FROM SOLDOTNA BASE ROUTE $2 $35 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 12 TABLE OH06 TABLE OH06 - COST ESTIMATING INFORMATION ENSTAR ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - SOLDOTNA AREA ALTERNATIVE B ADJUSTED COST COST COST COST LINK a LINE oe PER LINK Ai PER LINK IDENT DESIGN P SEM aE as ose SL ie are __ $1,331 | IQCM.1.40] 63 | 2 | $561_ | $561] $3,537 | $536 $3,375 Q |_ $416 | SUB TOTALS $7,446 $6,965 ENGINEERING 7.00% $521 $488 CONSTRUCTION MGMT. 6.00% $447 $418 TOTALS $8,413 $7,871 DIFFERENCE FROM SOLDOTNA BASE ROUTE ($2,775) ($2,504) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) Ih r:/WAR/CHUGACH/SIP102.XLS 13 TABLE OH06 TABLE OHO06 - COST ESTIMATING INFORMATION ENSTAR ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES ENSTAR ROUTE - SOLDOTNA AREA ALTERNATIVE C 230KV 138KV COST | ADJUSTED | COST COST |ADJUSTED| COST LINK | LINKMIL| LINE (PER COST PER LINK| (PER COST |PERLINK IDENT ES DESIGN | MILE PER MILE MILE PER MILE QCM.1.20] 3.2 [| 1 | 455 45ST as6f 416 4] 1,331 IQCM.1.10] 08 | 1 | 455 | 45sf 36446 Tato 333] IQCM.2.10[ 106 | 1 | 455 [455] 4.824] 416 IQCM.2.10] 30 | 2 | 561 [ 56if 1,684] 536 | SUB TOTALS $8,329 $7,681 ENGINEERING 7.00% $583 $538 CONSTRUCTION MGMT. 6.00% $500 $461 TOTALS $9,412 $8,680 DIFFERENCE FROM SOLDOTNA BASE ROUTE ($1,777) ($1,695) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 14 TABLE OH06 Quartz Creek Route Overhead Lines TABLE OH07 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE BA ADJUSTED “OST BASE ADJUSTED OST LINK LINK | LINE COST COST PER LINK COST COST PER LINK IDENT _ | MILES} DESIGN| (PER MILE) | (PER MILE PER MILE) | (PER MILE QC.A1O | 71 [2 fT $561 | $561 $536| $536 | $3,803 | Q 2 igcB.20 | 10 [ 2 | ssoif $soitSsei [$536] 8536] $536 | igc.B.20 | 101 | 4 | $565[ $565] $5,704 S541 S541 | «$5,466 | gc.c.30_ | 62 [ 1 | s45s[ $425] $2,636, Salo T8386] $2,394 | igcD.40 | 65 | 1 | $455[ $501] $3,254] S416 | $458 [$2,975 | ec.p.40 | 65 | 6 | ss24] $824] $5,356 $824] $824] $5,356 | QC ESO. | 91 [ 1 | $455[ $425] $3,869[ S416 T8386] $3,513 | Qcr6o | 43 | 5 | s46s[ $435] $ig71 [$426] $396 [$1,701 | igc.G.70 | 37 [ 4 | $565] $565] $2089] S541 8541] ‘$2,002 | igcHso | 37 [ 4 | $565] $565] $2,089] $541] 8541] ‘$2,002 | gcr90 fs [4] $565[ $565] $6,494] S541 S541] $6,224 | gcjioo | 210 [ 4 | $s65[ $565] silsso] $541 $541] $11,365 | QcKiio | 219 [ 1 [ $45sT $455] $9,967] Sao [S416] $9,112 | QcLi20 | 124 [ 1 | $45s[ sass] $5,644] S46] S416] ($5,159 | IQCM115 [| 18 [ 1 | $455[s45s[ssig[S4io | S46 | ($749 | Qc.M.130 [78 [ 1 | $455[ $455] $3,550[ S416 [S416] $3,245 | 1QC.M.1.30 | 50 | 2 | $s61[ $561] $2,807] $536] $536 | —*$2,678 | igcM.170 [| 68 [ 1 | $455[ $455] $3,095] S46 | S416 | $2,829 | jQcM.i8so [os [2 J] sseif sse1f 4498536 $536] —_—$429 | SUB TOTALS $76,100 $71,538 ENGINEERING 7.00% $5,327 $5,008 CONSTRUCTION MGMT. 6.00% $4,566 $4,292 TOTALS $85,994 $80,838 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 15 TABLE OH07 TABLE OHO08 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - SOLDOTNA AREA BASE ROUTE STS 138KV ADJUST! ADJU LINK LINK | LINE COST coer a LINK COST eee LINK IDENT _ | MILES] DESIGN| (PER MILE)| (PER MILE PER MILE)| (PER MILE)| ____| QcM.i30 | 78 | 1 | sass] _sass[ $3,550] sai6 [$416 | _ $3,245 1QC.M.1.30 [5.0 [| 2 | ssf $561 | __ $2,807 | $536] $536 | __ $2,678 | QCM.1.70 | 68 | 1 | _s4ss| _sass| $3,095] _$ai6| $416 | $2,829 | QcM.i8o [08 | 2 [ ss61f $561 $449] $536 | $536] $429 | SUB TOTALS $10,721 $9,930 ENGINEERING 7.00% $750 $695 CONSTRUCTION MGMT. 6.00% $643 $596 TOTALS $12,114 $11,221 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 16 TABLE OH08 TABLE OH08 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - SOLDOTNA AREA ALTERNATIVE A STISTES 138KV ADJU ADJU D OST LINK LINK | LINE COST a LINK COST COST PER LINK IDENT _ | MILES} DESIGN] (PER MILE PER MILE)} (PER MILE i9CM205 {40 | 1 7 $455] sess] Sisait sein | S4iG | $1,664 | pect fos ff ess |__siss f_siea {sie [sti |] cee Leo | 63} 2 t _sseh) S86} 53.537 | $536 [$3,375 | |__«$455 | | $561 | $53 6 SUB TOTALS $8,174 $7,631 ENGINEERING 7.00% $572 $534 CONSTRUCTION MGMT. 6.00% $490 $458 TOTALS $9,236 $8,623 DIFFERENCE FROM QUARTZ CREEK BASE ROUTE ($2,878) ($2,598) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 17 TABLE OH08 TABLE OH08 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - SOLDOTNA AREA ALTERNATIVE B 7 BA ADJUSTED O BA AD TED OST IDENT _ | MILES} DESIGN] (PER MILE)} (PER MILE) PER MILE)} (PER MILE QCM.2.05 [| 40 [ 1 [ 45s[ 455] 1821] 46] 416] 1,664 QC.M.2.10 | 106 [ 1 | 45sf455[ 4 gat atef a6] 4,410) (gc.M.2.10 [| 30 [ 2 | Seif Soi] os4t 536] 536] ~—S—«a1,607] SUB TOTALS $8,329 $7,681 ENGINEERING 7.00% $583 $538 CONSTRUCTION MGMT. 6.00% $500 $461 TOTALS $9,412 $8,680 DIFFERENCE FROM QUARTZ CREEK BASE ROUTE ($2,702) ($2,541) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 18 TABLE OH08 TABLE OH08 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - SOLDOTNA ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - SOLDOTNA AREA ALTERNATIVE C SOSTES 138KV_ ADJU ADJU: LINK LINK | LINE COST ee Eo LINK COST ae =e LINK IDENT _ | MILES] DESIGN] (PER MILE)| (PER MILE PER MILE)| (PER MILE gcm2.05 [40 T 1 [ s4ss[ sass] siszit s4io[ S416 [$1,664 | QCM.i10 [os | 1 | _sass[_sass|___$36a| sais | __sai6| _$333 QCM.140 | 63 | 2 | ssoi] $561} $3,537] $536] $536] $3,375 | QcM.150 [3.0 | 1 | $455[ $455] $1365] $416 [$416 | $1,248 | QCM.1.70 | 68 | 1 | $455] $455] $3,095] $416 | $416 | $2,829 | QcM.i8so [08 [| 2 | ss6if $561] $449] $536] $536 $429 | SUB TOTALS $10,631 $9,878 ENGINEERING 7.00% $744 $691 CONSTRUCTION MGMT. 6.00% $638 $593 TOTALS $12,014 $11,162 DIFFERENCE FROM QUARTZ CREEK BASE ROUTE ($101) ($59) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th t:/WAR/CHUGACH/SIP102.XLS 19 TABLE OH08 TABLE OH09 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - BIRD POINT ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - BIRD POINT AREA BASE ROUTE 138KV COST | ADJUSTED} COST | COST LINK LINK | LINE | (PER COST |PERLINK| (PER ENT__| MILES | DESIGN | MILE) | (PER MILE MILE SUB TOTALS $25,022 $23,773 ENGINEERING 7.00% $1,752 $1,664 CONSTRUCTION MGMT. 6.00% $1,501 $1,426 TOTALS $28,275 $26,864 NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 20 TABLE OH09 TABLE OH09 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - BIRD POINT ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - BIRD POINT AREA ALTERNATIVE A (AERIAL) COST COST COST LINK Se LINE (PER PER LINK Aken IDENT DESIGN | MILE QC.D.1.A.10 Soe SSS $3,338| $3,338] $9,681] $3,338] $3 = = $3,338] $9,681 | QCDIA1O | 15 | 4 | $565] $565] $847] $541 $541] $812 | QCD.2.10 | 82 7 4 | s565f $565] $4631] $541 $5417 $4,438 | COST PER LINK. SUB TOTALS $15,159 $14,931 ENGINEERING 7.00% $1,061 $1,045 CONSTRUCTION MGMT. 6.00% $910 $896 TOTALS $17,129 $16,872 DIFFERENCE FROM BIRD POINT BASE ROUTE ($11,146) ($9,992) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th r:/WAR/CHUGACH/SIP102.XLS 21 TABLE OH09 TABLE OH09 - COST ESTIMATING INFORMATION QUARTZ CREEK ROUTE - BIRD POINT ALTERNATIVES - OVERHEAD LINES QUARTZ CREEK ROUTE - BIRD POINT AREA ALTERNATIVE B (SUBMARINE) COST LINK rer LINE (PER IDENT DESIGN | MILE QCDIBIOT 15 [4 J $565] $565] $847 aaa | $541 $812 | gcp210 [82 | 4 | sses[ $505 s4o31] Si] Sal] 94,438 SUB TOTALS $5,478 $5,250 ENGINEERING 7.00% $383 $367 CONSTRUCTION MGMT. 6.00% $329 $315 TOTALS $6,190 $5,932 DIFFERENCE FROM BIRD POINT BASE ROUTE ($22,086) ($20,932) NOTE: A 10% contigency has been included in the "BASE COST (PER MILE)". PEI-HLY 120293-01 (6:51 PM3/11/96) th 1:/WAR/CHUGACH/SIP102.XLS 22 TABLE OH09 UNDERGROUND AND SUBMARINE CABLE INTRODUCTION Based on information obtained to date, the best choice available for submarine cable design in the harsh environment of the Turnagain Arm is a SCFF' cable with the exception of the Bird Point Crossing. For the Bird Point Alternative, we recommend using directional drilling to install a HPGF” cable system. We recommend that XLPE’ submarine cable not be considered because of the challenging cable operating environment of the Turnagain Arm. However, we do recommend using XLPE type cable for all land-based underground applications. Of the SCFF cable types, the least expensive is the flat three-phase SCFF cable configuration. This cable presents some unique capabilities, such as two completely redundant three-phase circuits, which may alter the recommendation for embedment pending additional geotechnical evaluation. As a result of our preliminary engineering investigations completed during Phase I of the Project, we are providing cost estimates based on the use of the following cable types: 2 - 3 phase flat SCFF cables, submarine type 4-1 phase SCFF cables, submarine type 3 - 1 phase XLPE cables SUBMARINE CABLE The cost estimates have been made assuming that double-armored cables will be embedded into the Arm’s bottom using a water jet assisted cable plow. The decision to use this method for the estimates is based on our current level of information about the potential crossings and the recommendations of Pirelli-Jacobson’s Brian Jacobson (see letter in Appendix B). We have also provided a non-embedded cost estimate for each of the cable types we considered by reducing each embedment estimate by $14.00 per cable foot. The embedment cost is for embedment only and the associated mobilization and demobilization of all required equipment is covered separately. ' SCFF - Self-Contained Fluid-Filled ? HPGF - High-Pressure Gas-Filled > XLPE - Cross-Linked Polyethylene PEI-HLY 55-0198 120293-01 (03/96) ab 1 There are possible exceptions to using embedment for selected portions of each alternative. Geotechnical and bathymetric evaluations could indicate that there may be areas where embedment is not needed. It may further indicate that additional armoring (rock armoring) is justified along part of the route where it is not feasible to embed the cables. Since significant field work is required and this data is not yet available, we have opted to consider direct embedment of double-armored cable along the entire route of each alternative to calculate the estimates. Based on the available information at this time, the reasons to embed cables are: e Scouring and abrasion of armor in the Point MacKenzie-Point Woronzof cable field has damaged armor on some of the existing cables, causing them to leak and subsequently be taken out of service. e Pirelli-Jacobson recommends the embedment of armored cables due to the environment, based on their experience in the area. e Embedment may reduce the risks of cables being damaged by anchors and moving boulders and changing Turnagain Arm bottom profile. e Buried armor suffers significantly less corrosion and wear. To determine areas where embedment is not practical or is unnecessary, we recommend that further evaluations of the sea bottom’s surface and subsurface be conducted. These include evaluations by side-scan sonar, sub-bottom sonar, geotechnical drilling, and investigation of the bathymetry of the Turnagain Arm. These evaluations will help determine where rock armoring is necessary along portions of each link. The reasons not to embed cable in certain areas include: e The bottom is too steep to use the embedding plow. e The bottom is so soft that the cable will embed itself. e Severe currents in the Arm cause the bottom to shift enough to uncover the embedded cable in a short time. e —_ Bottom conditions are too hard (rocky) to embed cable. e The additional cost of embedding already-protected (armored) cables may be considered excessive. ° Ice scour and/or boulder movement is so severe that embedment at a depth of 10 feet is not sufficient to prevent damage. Should the non-embedded approach be selected for part or all of an alternative’s length, the addition of rock armor over the double armor of the cables should be considered. Rock armor is an additional layer of armor consisting of wires that are typically larger in diameter than the wires of the underlying armor. The rock armoring is applied with a shorter lay than the normal armor wires. Its purpose is to provide additional protection against damage by external forces, such as anchors or boulders, and to support the cables when laid over obstructions or when bottom shifts suspend the cable over a portion of its route. This additional armor may double the weight of the cable and makes the cable stiffer and more difficult to handle. Rock armoring may be applied to selected sections of a continuous cable. PEI-HLY 55-0198 120293-01 (03/96) ab 2 The cost estimates are based on a 1,000-foot spacing of cables along the bottom. The Coastal Pilot (reference the Design Section Report) identifies an anchorage just north of Point Possession, near several of the possible cable routes. A final decision on the spacing should be made after the recommended geotechnical and bathymetric evaluations are completed. However, the actual spacing is expected to have little impact on the overall cost of the cable’s installation. Soil thermal resistivity studies conducted during the recommended geotechnical work may allow us to refine our judgment on using the 1,000 kCMIL copper cable selected for these estimates. These studies will also better define the shore landing conditions and the spacing of the cables. Better knowledge of these latter conditions may also allow us to refine the cable conductor size. LAND UNDERGROUND CABLES All estimates for cables installed on land have been made using a manhole and duct system which is typical and usual for this type of application. Additionally, estimates assume that cross bonding of the cable’s sheaths as described in the Preliminary Design Report. XLPE is the preferred insulation for land-based cables. This insulation material has proven reliability, is readily available, has the lowest losses and least maintenance requirements, and is the lowest capital cost. COST ESTIMATE SUMMARY Each of the following estimates is a compilation of the individual links and assumptions used to make up the cable costs of a particular route or local alternative. All cost estimates are in millions of dollars. Additionally, the following assumptions were used: e ___ Landfalls were assumed to be within 1,000 feet from water’s edge. e Geotechnical estimates includes marine survey, soil borings and soil thermal resistivity testing. e Labor and expenses related to installation techniques are included in the labor item on the mobilization/demobilization line item. e _ Burial conditions for embedment costs are assumed to be without boulders or other significant obstructions. Other items included in the section are a material pricing summary and a spreadsheet detailing the methodology to determine installation costs per cable foot. For additional detail by link and cable type, please refer to the Appendix B. PEI-HLY 55-0198 120293-01 (03/96) ab 3 TESORO ROUTE SUBMARINE CABLES i g ea) an Oa Sy] R Sle > ms omen © g\< I ¢ oO Z/RisI2 <l</5|8 BIE|E|e <|3|=|S Ole w Ow Z< Da as & o Ak TESORO ROUTE UNDERGROUND LAND CABLES = a ALF : o a S < ~ oo = Q > CAPTAIN COOK 9.3 1.6 a 2 & 7 ” B a on Pa) Oo z\< 3 2183 <\< F) 10.3 230KV 10.3 0.0 0.0 DIFFERENCE FROM BASE ENSTAR ROUTE SUBMARINE CABLES 250KV BASE ANCHORAGE ALTERNATIVES rouTe|BASE] A | B | c | D | E | F [ROUTE|BASE] A | B | C | ENB90 | 383] 383] 383] | 383] 383] 383] 383] 245] m45[ 245| [245] Pepe g emer ae 383 | 0.0 > 38.3 AT 24.5 DIFFERENCE FROM BASE DIFFERENCE FROM BASE MATERIAL SUMMARY _JARMOR [NOTES VOLTAGE TYPE TYPE _| (sce below) 138 SCFF {DOUBLE] 1,2 _ 138 [3P SCFF [FLAT] DOUBLE l 138 XLPE DOUBLE] 1,2 138 HPGF DOUBLE] 0 230 SCFF DOUBLE] 0 L1. 230 XLPE 1 | pouBie) 3 Le LAND CABLES _ am ; i 138 XLPE 38 | 1 suanl 230 XLPE 5a tt t NIA 3 eee ee SPLICES = 7 TYPE 138 3-1/C XLPE TO 3-1/C SC 138 138 138 138 230 230 CL 138 9s77 | [38 | (63065) 0 138 | 11230 | oO] 138 i 13000, | 4 230 22000 4 230 —|25000 | 4 GROUNDING BOXES | _ SHEATH GRC YUNDIN X- BONDING NOTES _ 0|ACTUAL PRICE 1|AVERAGED PRICE FROM ESTIMATES RI 2|DOUBLE ARMORED PRICE CALCULATED AT 120% © “S 3 4 3|230 kV PRICES CALCI ILATED | AT 1409 6 OF 1 38 PRICES BASED ON OTHER JOB EXPE! | | | I] | | This table and its accompaning notes is the method used to > penerate material c detailed estimates. used in the — | Page 1 INSTALLATION SUMMARY AVERAGE COST PER INSTALLATION COSTS PT. P-F.I. PT.W PT.P-PT.C ENSTAR —_— BIRD PT. DISTANCE (LINEAR) ae 73920 76560 44880 = 10500 —__ $/PHASE FOOT $ PHASE FOOT |S PHASE FOOT $/PHASE FOOT ————— fo SUPPLIER 34) 9.300.000 45| 5,800,000 138 14] 3,800,000) 14| 1,600,000 38) 13,100,000) $8] 7,400,000 176 | 74 66 PHASE FOOT EMBEDDED —— +—-1—— {USED FOR ESTIMATING PURPOSES} This table is a summary of the methods used to arrive at the $53.00 per phase foot used to estimate the cost of embedding a submarine cable. Also, it develops the $14.00 per cable foot used for the embedment allowance . Page 1 SUBSTATIONS INTRODUCTION Modifications will be required to existing substations to terminate the proposed Southern Intertie. For the purposes of this report, alternate substation estimates have been prepared to include the University, Point Woronzof and International substations in the Anchorage area and the Soldotna and Bernice Lake substations on the Kenai Peninsula. This section will present the applicable substation cost estimates for the modifications necessary to terminate the Southern Intertie. Cost estimates for each substation are based on the conceptual general arrangement drawings contained in Appendix C and other applicable information as contained in the System Studies and Design Section Reports. Equipment vendors were contacted for equipment prices and shipping costs and constraints. The equipment prices used in preparing the estimates are based on this vendor information and are f.o.b. site. Future plans and additions for the substations were considered and accommodated in these estimates to the extent possible. The preliminary designs have also considered the addition of switches where appropriate to allow future expansion with minimal outages. Additional land purchase and/or expansions of the existing fence will be required for all proposed substation modifications except for the 138kV options at University Substation. Land purchase prices are included in the right-of-way Section and were not included in the substation estimates. The following tables summarize the substation estimates by route, inclusive of labor, material, engineering, construction management, and 10% contingency. PEI-HLY 55-0198 120293-01 (03/96) ab 1 Substation Cost Summary by Route 138kV Option 230kV Option TESORO ROUTE Point Woronzof* $3,743,532 $6,586,193 Bernice Lake $3,573,337 $4,088,579 Total $7,316,869 $10,674,772 ENSTAR ROUTE International $850,977 $3,482,885 Soldotna $3,143,384 $3,655,477 57138362 QUARTZ CREEK ROUTE Substation 138kV Option 230kV Option University $557,232 $2,473,180 Soldotna $3,143,384 $3,655,477 Total $3,700,616 $6,128,657 * Contains reactive compensation component for submarine cable for Anchorage area. PEI-HLY 55-0198 120293-01 (03/96) ab BERNICE LAKE SUBSTATION GENERAL The cost estimates for the Bernice Lake Substation are based on a new 115kV three breaker ring bus. The bus has been designed to not alter the existing access. The existing 115kV circuit breaker and voltage transformers will not be reused due to the length of outage required to perform the required modifications. The existing 115kV deadend structure and disconnect switch will be left in place and reused is shown in Figure SS-09, Appendix C. The existing yard must be expanded to the east for the addition of the Southern Intertie. Homer Electric Association (HEA) owns the property east of the substation to North Kenai Road. This area is adequate for the required modifications. 138kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 09. The proposed arrangement requires that additional property, approximately 215 x 185 feet in size, be included in the substation fence. Refer to the more detailed cost estimates contained in Appendix C and the Design Section Report for more information on the specific equipment required. 230kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 10, Appendix C. The proposed arrangement requires that additional property, approximately 235 x 185 feet in size, be included in the substation fence. Refer to the more detailed cost estimates contained in Appendix C and the Design Section Report for more information on the specific equipment required. PEI-HLY 55-0198 120293-01 (03/96) ab 3 COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 138 KV Option, Bernice Lake Substation Summ: UNIT COSTS TOTAL | HRS | UNIT _| | HRS | UNIT | [EQUIPMENT | 28 | $1,473,650] 1336 | $133,600] $1,920,400] 1800 | $180,000 | __ $2,100,400 | [FOUNDATIONS | 188 | $1500] 36 [$3,600] $47,000] 1128 | $112,800[—_—*$159,800 | ICABLE& CONDUIT | 2070 [8153 0.96 [soe $54,600] 340 | $33,990] «$88,590 | 49215 0.25 | $2st $89,275 [1189 [$118,925 [$208,200 | ICONTROLHOUSE | S| $111,500] 208 [$20,800] $192,500] 232 [$23,200 ——_—*$215,700 | TESTING 15 $3,000] 104 | $i04o0[ $3,000 [186 | SUB TOTALS $2,378,075 5153 $515,315 $2,893,390 ENGINEERING 6.50% $188,070 CONSTRUCTION MG 7.00% $202,537 CONTINGENCY 10.00% $289,339 TOTAL $3,573,337 PEI-HLY 120293-01 (6:34 PM3/9/96) ss COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 230 KV Option, Bernice Lake Substation Summ: EXTENDED COSTS DESCRIPTION , TERIAL MATERIAL foo $2,286,700 EQUIPMENT $1,786,268 | 1352 $135,173 183: $183,800 $2,470,500 $18,087 $6,780 $108,300 36 1314 $186,150 $15 $88,590 ISITEWORK | 51650] $25 1253 $219,750 ICONTROLHOUSE |S $20,800 232 $215,700 TESTING TS $10,400[ $3,000 | SUB TOTALS $2,763,750 __ 5468 $546,840 $3,310,590 ENGINEERING 6.50% $215,188 CONSTRUCTION MG 7.00% $231,741 CONTINGENCY 10.00% $331,059 TOTAL $4,088,579 PEI-HLY 120293-01 (6:34 PM3/9/96) ss INTERNATIONAL SUBSTATION GENERAL The cost estimates for International Substation are based on CEA plans to build a 138kV breaker-and-a-half station to the south of the existing 138kV station. If the new station is not built at the time it is needed for the Southern Intertie, additional work will need to be done to the existing substation. The bay for the Southern Intertie can still be built in the location shown on Figures SS-11 and SS-12, Appendix C, but a strain bus would need to be constructed to connect the bay to the existing substation. Additional costs would be incurred for site work, fencing, grounding, control building, etc. that would not be necessary if the new station were in place. These costs have not been estimated. 138kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 11. Cost estimates for the 138kV option assume that the proposed 138kV breaker-and-a- half station is in place. The general arrangement drawing of the proposed station furnished by CEA shows a bay designated for a future 138kV transmission line. As shown of Figure SS-11, this bay will be used for the Southern Intertie. 230kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 12. Cost estimates for the 230kV option assume that the proposed 138kV breaker-and-a- half station is in place. The general arrangement drawing of the proposed station furnished by CEA shows a bay designated for a future 138kV transmission line. As shown of Figure SS-12, this bay will be used to connect to a 230/138kV autotransformer via an overhead strain bus. The 230kV portion of the station will be constructed adjacent to the proposed station and will require that additional property, approximately 250 x 55 feet in size, be included in the substation fence. PEI-HLY 55-0198 120293-01 (03/96) ab 4 COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 138 KV Option, International Substation Summ: UNIT COSTS TOTAL | HRS [UNIT | | HRS [UNIT | STRUCTURES | 6 [$15,767] 57_—T$5,733 7 $40,900 160 | $16,000 «$56,900 | [FOUNDATIONS | 76 $1000] 24 | $2,400T $19,000 456 [ $45,600|—«$64,600 | [CABLE & CONDUIT 1375 [$123 0.78 [$78 $34,425 207 | $20,650[ ——«$55,075 | SITEWORK | to00 | ST ooo Tso 84.3751 43 84,250 $8,625 | ICONTROLHOUSE | 3 | $29,333[ 8 TESTING CT 8 83,000 80_ | SUB TOTALS $502,150 1869 $186,900 $689,050 ENGINEERING 6.50% $44,788 CONSTRUCTION MG 7.00% $48,234 CONTINGENCY 10.00% $68,905 TOTAL $850,977 PEI-HLY 120293-01 (6:34 PM3/9/96) ss COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 230 KV Option, International Substation Summ UNIT COSTS TOTAL QTY. MATERIAL COST | HRS | UNIT | | HRS [UNIT __| [EQUIPMENT | 7_—| $1,778,790 | 1072 [$107,181] $2,110,100] 1376 [$137,600] __ $2,247,700 | STRUCTURES] 20 87,492 65 [$6,500] $76,300] 292 [$29,200] ——$:105,500 | [FOUNDATIONS _ | 194 ‘| $1250T 30 [$3,000] $48,500] 1164 | $116,400[_— $164,900 | ICABLE& CONDUIT | 2475 [$153 0.96 [ s96[ $68,800] 416 [$41,550] —_— $110,350 | SITEWORK_ id 4000 $24] 0.24 [saat $27,100] 344 [$34,400] «$61,500 | ICONTROLHOUSE | 4 | $27,000f 8 T ssoot 108,000] 32 | 83,200] «$111,200 | [TESTING CT tt 83,000 96 | 160 | $16,000[ $19,000 | SUB TOTALS $2,441,800 3784 $378,350 $2,820,150 ENGINEERING 6.50% $183,310 CONSTRUCTION MG 7.00% $197,411 CONTINGENCY 10.00% $282,015 TOTAL $3,482,885 PEI-HLY 120293-01 (6:34 PM3/9/96) UNIVERSITY SUBSTATION GENERAL The cost estimates for University Substation are based on the future plans for the station and proposed changes to the 230kV portion of the station. The design takes advantage of unassigned future positions where possible. 138kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 13, Appendix C. Cost estimates for the 138kV option assume that the future 138kV bay shown on the general arrangement drawing furnished by CEA can be used for the Southern Intertie. 230kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 14, Appendix C. Cost estimates for the 230kV option assume that an entirely new 230kV station will be built to the east of the existing station. Proposed changes to the 230kV portion of the station completely utilize all available land within the existing fence. Future plans include the addition of another 230kV line to ML&P Plant No. 2 and a 230/115kV autotransformer. The configuration of the proposed 230kV additions is not easily adaptable to accommodate the future additions. For this reason, a ring bus expandable to a breaker and half has been proposed as shown on Figure SS-13. PEI-HLY 55-0198 120293-01 (03/96) ab 5) COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 138 KV Option, University Substation Summ UNIT COSTS EXTENDED COSTS TOTAL . MATERIAL LABOR MATERIAL LABOR COST 2 DESCRIPTION Q | HRS | UNIT __| | HRS [UNIT __| [EQUIPMENT | 10s $134,900] 436 | $43,600 $177,400] 504 [$50,400] $227,800 | ISTRUCTURES | tS] $15,700] 57 $5,714] $28,900] 112 $11,200 $40,100 | [FOUNDATIONS | 53 | $1,000] 24 [$2,400] $13,250] 318 | $31,800] $45,050 | ICABLE& CONDUIT 480 | SIS] 0.73 [ $73[ $11,250] 67 $6,675] $17,925 | ISITEWORK_ df 000 | S14 0.19 ESR Ea | 80 SUB TOTALS $328,675 1225 $122,525 $451,200 ENGINEERING 6.50% $29,328 CONSTRUCTION MG 7.00% $31,584 CONTINGENCY 10.00% $45,120 TOTAL $557,232 PEI-HLY 120293-01 (6:34 PM3/9/96) ss COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 230 KV Option, University Substation Summ UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL LABOR MATERIAL LABOR COST | HRS | UNIT _| | HRS | UNIT _| EQUIPMENT 3119 $311,941 $502,200 $374,600 $876,800 STRUCTURES $20,943 $8,171 $50,400 $174,500 CABLE & CONDUIT $123 $78 $110,425 $178,175 5 . FOUNDATIONS 284 $1,000[ 24 | $2,400 | $71,000 SITE WORK $256,500 $427,500 CONTROL HOUSE $29,333] 8 | $800 | $88,000 | 80 TESTING $3,000] $3,000 [108 | $10,800 $13,800 SUB TOTALS $1,069,725 9329 $932,850 $2,002,575 ENGINEERING 6.50% $130,167 CONSTRUCTION MG 7.00% $140,180 CONTINGENCY 10.00% $200,258 TOTAL $2,473,180 PEI-HLY 120293-01 (6:34 PM3/9/96) ss SOLDOTNA SUBSTATION GENERAL The cost estimates for Soldotna Substation are based on the availability of the 115kV breaker-and-a-half arrangement for expansion. A 115kV additional bay must be constructed since the bays for the Fritz Creek line and the SVC cross over to the adjacent bay before exiting the station. An additional disconnect switch has been included to accommodate future expansion. The general arrangement drawings furnished by CEA show an area designated for a future 230kV yard. This area was utilized for the Southern Intertie. 138kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 15, Appendix C. Cost estimates for the 138kV option assume that an entirely new 138kV station will be built in the area designated for future 230kV on the general arrangement drawing furnished by CEA and will require that additional property, approximately 150 x 120 feet in size, be included in the substation fence. 230kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 16, Appendix C. Cost estimates for the 230kV option assume that an entirely new 230kV station will be built in the area designated for future 230kV on the general arrangement drawing furnished by CEA and will require that additional property, approximately 170 x 120 feet in size, be included in the substation fence. PEI-HLY 55-0198 120293-01 (03/96) ab 6 COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 138 KV Option, Soldotna Substation Summa: UNIT COSTS TOTAL DESCRIPTION QTY. COST | HRS | UNIT | | HRS [UNIT | $15,883 | 58 | $5,767[ $60,400] 238 | $23,800[ «$84,200 | [CABLE& CONDUIT sd «3350 ss $153] 096 | $96] $82,300] 498 [ $49,800] —*$132, 100 | [CONTROLHOUSE “(| 4 | $27,000] ~—8 | S800 ~~ $108,000] 32 ~*~ 83,200] ~—S——«S$111,200 | TESTING sc CCTCC—C‘i;CSCLC CTS 83,000] = 96 ~—|$9,600[ $3,000] 160 [ —$i6,000f ——_—«$ 19,000 | SUB TOTALS $2,115,350 4299 $429,900 $2,545,250 ENGINEERING 6.50% $165,441 CONSTRUCTION MG 7.00% $178,168 CONTINGENCY 10.00% $254,525 TOTAL $3,143,384 PEI-HLY 120293-01 (6:34 PM3/9/96) ss COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 230 KV Option, Soldotna Substation Summa: UNIT COSTS TOTAL QTY. |MATERIAL| LABOR MATERIAL COST | HRS [UNIT | | HRS | UNIT | $152,981 ISTRUCTURES_ | 27_:*|$20,558[ 79 [$7,867 $66,800] 266 | $26,600] ——_—~$93,400 | [FOUNDATIONS | 198 | $1,250 30 | $3,000] $49,500] 1188 [$118,800] —_—*$168,300 | ICABLE& CONDUIT 3350 [$153] 0.96 [$96] $82,300] 498 | $49,800] —*$132,100 | ISITEWORK_ «24950 $25[ 0.27 [$27] $45,550] 625 | $62,450] ——*$:108,000 | [CONTROLHOUSE | 4 | 827,000 8800 | | 32_ | $3,200 $111,200 | [TESTING CCC—=~‘dE:CiLSCaE's—s«$3,000 [96] —_—$9,600| | 160 [$16,000 | SUB TOTALS $2,499,650 4603 $460,250 $2,959,900 ENGINEERING 6.50% $192,394 CONSTRUCTION MG 7.00% $207,193 CONTINGENCY 10.00% $295,990 TOTAL $3,655,477 PEI-HLY 120293-01 (6:34 PM3/9/96) ss POINT WORONZOF SUBSTATION GENERAL The cost estimates for the Point Woronzof Substation are based on a new five-breaker ring bus. This bus has been designed to not alter the existing access. The existing station does not currently have circuit breakers to sectionalize the lines. The addition of the Southern Intertie requires the construction of a switching station for proper sectionalizing and protection. Insulators will be installed in the existing strain bus and the lines reconnected to the new station via a combination of rigid bus and strain bus as shown on Figures SS-17 and SS- 18, Appendix C. Shunt reactors, circuit switchers, and a switching structure are included in the cost estimates for the station. Costs for cable terminations are included in the submarine cable section. The existing yard must be expanded to the north to accommodate the new ring bus, the Southern Intertie termination equipment, and required reactors. 138kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 17. Cost estimates for the 138kV option assume that an entirely new 138kV station will be built to the north of the existing station. and will require that additional property, approximately 190 x 300 feet in size, be included in the substation fence. 230kV OPTION A General Arrangement Drawing showing the proposed additions is shown in Figure SS- 18. Cost estimates for the 230kV option assume that an entirely new 230kV station will be built to the north of the existing station and will require that additional property, approximately 200 x 340 feet in size, be included in the substation fence. PEI-HLY 55-0198 120293-01 (03/96) ab 7 COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 138 KV Option, Pt. Woronzof Substation Summ UNIT COSTS TOTAL QTY. MATERIAL] LABOR__ [MATERIAL COST | HRS | UNIT | | HRS [UNIT | EQUIPMENT | 50_| $763,767] 2755_| $275,500] $1,472,600 | 3434 | $343,400] —_—‘$1,816,000 | ISTRUCTURES | 46 816,325] 55 $5,493] $131,500] 484 | $48,400] —_—$179,900 | ee eS a ee CABLE & CONDUIT 3150 $89 ISITEWORK sf 68050 $24 0.24 | $24] $113,250] 1508 | $150,750| —«$264,000 | [CONTROLHOUSEsd|;sd'Cd | 208 | $20,800[ $348,500] 280 | $28,000] ——*$376,500 | | 103 [| $10,320[ $3,000] 280 [$28,000], —_—$31,000 | SUB TOTALS $2,215,900 8153 $815,300 $3,031,200 ENGINEERING 6.50% $197,028 CONSTRUCTION MG 7.00% $212,184 CONTINGENCY 10.00% $303,120 TOTAL $3,743,532 PEI-HLY 120293-01 (6:34 PM3/9/96) ss COST ESTIMATING INFORMATION SUBSTATION COST SUMMARY 230 KV Option, Pt. Woronzof Substation Summai UNIT COSTS TOTAL QTY. JMATERIAL[____ LABOR _ [MATERIAL COST | HRS [UNIT | | HRS | UNIT | $314,187 STRUCTURES —CiédL;:CAK_—sédT;SCsé$117,42657_—sdT $5,742 | $143,300] 520 | —$52,000[ __—‘ $195,300 | 362 | $2,000] 48 =| $4,800] $90,500] 2172 | —$217,200[ _—_—‘$307,700 | ISITEWORK ——C*«d 79605 $24] 0.24 [$24] $133,575| 1771 | _$177,075| __ $310,650 | 208 TESTING C~—“‘dE:SCBS=CdTCSC«83,000] = '109 ‘| ‘$10,927 | SUB TOTALS $4,380,375 9526 $952,575 $5,332,950 ENGINEERING 6.50% $346,642 CONSTRUCTION MG 7.00% $373,307 CONTINGENCY 10.00% $533,295 TOTAL $6,586,193 PEI-HLY 120293-01 (6:34 PM3/9/96) ss REACTIVE COMPENSATION INTRODUCTION As previously stated and defined in the Systems Studies and Design Section Reports, Reactive Compensation will be required for all scenarios of the Southern Intertie Project. This section presents the cost estimates for each of the possible transmission line routes. Equipment vendors and turnkey/manufacturer’s were contacted to obtain equipment prices, shipping costs and related construction costs. The pricing information is used in preparing the estimates in this section. Land acquisition and/or new right-of-way will be required for all installations involving submarine/underground reactor installations. For the compensation of the existing 115kV line, additional property will be required adjacent to the existing right-of-way. Significant land acquisitions would be required both in the Anchorage area and on the Kenai Peninsula to accommodate Battery Energy Storage (BES) systems. Summary estimate sheets for all reactive compensation scenarios are provided at the end of this section. Detailed estimates and associated general arrangements are provided in Appendix D. The following tables summarize the reactive compensation estimates by base route. One alternative estimate to the Quartz Creek route is also included as the underground Bird Point Crossing requires additional compensation beyond the base route. No other routes require additional compensation due to routing alternatives. PEI-HLY 55-0198 120293-01 (03/96) ab 1 Reactive C ion § Substation Location 138kV 230kV TESORO ROUTE $2,122,055 $5,953,644 $8,075,699 $2,648,797 $5,953,644 $8,602,441 Point Possession* ENSTAR ROUTE Rabbit Creek $1,353,062 $1,708,626 Big Indian Creek $1,353,062 $1,708,626 Portage** $5,953,644 $5,953,644 Total $8,659,768 $9,370,896 QUARTZ CREEK ROUTE $5,953,644 $5,953,644 $5,953,644 $5,953,644 QUARTZ CREEK - BIRD POINT ALTERNATIVE Bird Point $1,228,212 $1,649,010 Snipers Point (Six Mile Cr.) $1,228,212 $1,649,010 595,64 595,64 * Reactive Compensation for the Anchorage area is included with Point Possession Substation Costs. ** — New site to provide for compensation of existing 115kV intertie. PEI-HLY 55-0198 120293-01 (03/96) ab 2. SHUNT CAPACITOR BANKS The cost estimates are inclusive of utilizing shunt connected capacitor banks in 20 MVAR blocks. These are primarily for improving steady-state system operating conditions. As determined in the Systems Studies, the shunt banks must be augmented by a fast-acting device (Static Var Compenstors [SVC] or Thyristor Controlled Series Capacitors [TCSC]) on the existing 115kV Intertie. Accordingly, estimates for the shunt banks are included with either an SVC or TCSC. A general arrangement showing 2-20 MVAR banks with a 0-20 MVAR SVC is shown on Figure RC-01 and detailed in Table RC-01 in Appendix D. The configuration with the 0-40 MVAR TCSC is provided with a single 20 MVAR Shunt Capacitor Bank. Refer to Figure RC-02 and Table RC-02 in Appendix D. SHUNT REACTORS The cost estimates for the shunt reactor installations are provided for both 138kV and 230kV scenarios. In general, the reactors are placed at the terminus of the submarine/underground cables. The following table summarizes the required shunt reactor installations. Associated Associated # Locations Figure Table Quartz Creek 10 MVAR - 2 sites RC-03 RC-03 Enstar 138 22 MVAR - 2 sites RC-03 RC-04 Route Voltage Reactor Size & (KV) Quartz Creek 230 22 MVAR - 2 sites RC-04 RC-05 Enstar 230 60 MVAR - 2 sites RC-04 RC-06 Tesoro 138 10 + 30 MVAR - | site RC-05 RC-07 30 MVAR - 2nd site 230 30+40 MVAR - | site RC-06 75 MVAR - 2nd site Tesoro RC-08 Refer to Appendix D for all associated Reactive Compensation Figures and Detailed Estimates (Tables). PEI-HLY 55-0198 120293-01 (03/96) ab 3 STATIC VAR COMPENSATORS The cost estimate provided for the SVC is included with the shunt connected Capacitor Bank, Figure RC-01 and Table RC-02 in Appendix D. The SVC operation for dynamic control is augmented by the more economical 20 MVAR shunt banks for the steady-state support. As described in the Systems Studies and Design Section Reports, the SVC provides dynamic stability during system disturbances. Significant control issues would have to be addressed to coordinate with the existing SVC installations. SERIES CAPACITOR BANKS The cost estimate provided for the Series Bank is included with a 20 MVAR shunt connected Capacitor Bank, Figure RC-02 and Table RC-02 in Appendix D. As with the SVC, a portion of the var support is more economically provided by standard shunt banks. Normally (mechanically) switched series capacitors can not be utilized for the Southern Intertie application due to response time and Subsynchronous Resonance considerations. A more detailed description and discussion is provided in the System Studies Report. Accordingly, this estimate included a TCSC Bank. This device provides sub-cycle response time and mitigates SSR concerns typically associated with series compensation. TCSC provides the best overall technical solution considering both steady-state and dynamic system requirements. BATTERY ENERGY STORAGE BES has the unique capability of providing full power circle operation. More detailed operational information is provided in the System Studies and Design Section Reports. Estimates for two systems (Anchorage and Kenai) project were provided by vendors. Together the BES systems estimates varied between $41 million and $51 million. These are rough budgetary numbers only. Significantly more study work would be required to refine the BES capacity specifications which could significantly influence the capital cost. Accordingly, detailed cost estimates are not available for this option. PEI-HLY 55-0198 120293-01 (03/96) ab 4 SUMMARY The following tables provide a cost estimate summary for each reactive compensation installation or applicable combination of installations for the Southern Intertie. Additional detail can be found in Appendix D. PEI-HLY 55-0198 120293-01 (03/96) ab 5 SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE TOTAL DESCRIPTION COST EQUIPMENT $2,290,100 STRUCTURES $120,750 FOUNDATIONS $252,750 CABLE & CONDUIT $133,375 SITE WORK $258,513 CONTROL HOUSE $408,000 TESTING $115,000 $3,578,488 ENGINEERING 6.50% $232,602 CONSTRUCTION MG 7.00% $250,494 CONTINGENCY 10.00% $406,158 TOTAL $4,467,742 Apply to the existing 115kV Intertie, new site at Portage as an alternate SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE TOTAL $4,768,637 ENGINEERING 6.50% $309,961 CONSTRUCTION MG 7.00% $333,805 CONTINGENCY 10.00% $541,240 — SSS TOTAL = $5,953,644 Apply to the existing 115kV Intertie, new site Portage,. Applicable to all base estimates. SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 138 KV, 10 MVAR REACTOR TOTAL DESCRIPTION COST $100,875 $17,000 $69,205 $146,000 $17,000 $983,750 ENGINEERING 6.50% $63,944 CONSTRUCTION MG 7.00% $68,862 CONTINGENCY 10.00% $111,656 SSS TOTAL = $1,228,212 Quartz Creek, 138kV, Bird Point Alternative: * | Site at Bird Point * | Site at Snipers Point (Six Mile Creek) SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 138 KV, 22 MVAR REACTOR TOTAL $1,083,750 ENGINEERING 6.50% $70,444 CONSTRUCTION MG 7.00% $75,862 CONTINGENCY 10.00% $123,006 TOTAL = $1,353,062 Enstar, 138kV * | Site at Rabbit Creek (North of Potter's Marsh) * | Site at Big Indian Creek (on the Kenai) SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 230 KV, 22 MVAR REACTOR TOTAL DESCRIPTION COST $868,650 $73,800 $135,750 $4,200 $75,393 $146,000 $17,000 81,320,793 | ENGINEERING 6.50% $85,852 CONSTRUCTION MG 7.00% $92,455 CONTINGENCY 10.00% $149,910 TOTAL = $1,649,010 Quartz Creek, 230kV, Bird Point Alternative * | Site at Bird Point * | Site at Snipers Point (Six Mile Creek) SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 230 KV, 60 MVAR REACTOR TOTAL $1,368,543 ENGINEERING 6.50% $88,955 CONSTRUCTION MG 7.00% $95,798 CONTINGENCY 10.00% $155,330 TOTAL — $1,708,626 Enstar Route, 230kV, Base route: * | Site at Rabbit Creek (North of Potters Marsh) * | Site at Big Indian Creek (on the Kenai) SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 138 KV, 10+30 MVAR REACTORS TOTAL DESCRIPTION COST $125,625, $34,000 $80,708 $146,000 $88, He 31,699,683 ENGINEERING 6.50% $110,479 CONSTRUCTION MG 7.00% $118,978 CONTINGENCY 10.00% $192,914 TOTAL = $2,122,055 Tesoro Route, 138kV, Base route: * | Site, Point Possession, new site * Additional 30MVAR at Point Woronzof Substation SUMMARY - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 230 KV, 30+40 MVAR REACTORS TOTAL DESCRIPTION COST TESTING $22,000 2,121,584 ENGINEERING 6.50% $137,903 CONSTRUCTION MG 7.00% $148,511 CONTINGENCY 10.00% $240,800 TOTAL = $2,648,797 Tesoro Route, 230kV, Base route: * | Site, Point Possession, new site * Additional 75MVAR at Point Woronzof Substation ENVIRONMENTAL PERMITTING INTRODUCTION The proposed Environmental Impact Statement (EIS) cost is estimated at $2.5 million for the Southern Intertie Project. This estimate is based on previous EISs successfully completed by Dames & Moore with similar issues. Initially, we estimated the cost based on estimated miles of alternatives. The three primary routes (Tesoro, Enstar, and Quartz Creek) equal approximately 275 miles total. There are approximately an additional 145 miles of local alternatives within the three primary routes. Accordingly, a total of approximately 420 miles of alternatives are to be evaluated in the EIS. For major EISs in rural areas, costs typically average approximately $4,500 to $5,000 per mile of alternative. Using this average per mile cost, we estimated the overall costs to be approximately $1.9 to $2.1 million. In addition, the Southern Intertie Project has a number of significant issues that will require additional studies or effort. These are: e Urban Anchorage: Typical urban studies vary in cost from $250,000 to $750,000. Because the Municipality of Anchorage has prepared a plan for utilities, we do not anticipate maximum costs for this study. Estimated additional cost is between $250,000 to $300,000. e The National Environmental Policy Act (NEPA) requires all alternatives to be evaluated equally. However, the level of data currently existing for the potential alternatives is inconsistent. For example, the Forest Service’s data are the most complete and are at the level of detail desired for a transmission line project EIS. For the remainder of the study area, data gaps exist for soils, vegetation, visual concerns, etc. An additional $150,000 to $200,000 is anticipated for data collection. e Typically, after completing the initial feasibility or alternative identification studies, a solution for most utility projects becomes obvious. However, for the Southern Intertie Project, a combined least-impact and least-cost preference has not yet appeared because of agency issues and submarine crossing conditions. This will result in a difficult decision process with numerous decision meetings with the client, agencies and interested parties, graphics, and data management. Estimated additional cost ranges between $100,000 and $150,000. PEI-HLY 55-0198 120293-01 (03/96) ab 1 The difficulties or agencies with significant issues are as follows: - State Parks - Forest Service - US. Fish and Wildlife Service - Corps of Engineers (404 permits) - Native Corporation Lands and Private Lands (Soldotna and Kenai areas) The primary concerns include visual, wilderness, recreation/tourism, and wildlife habitat. The concern of federal and state agencies is the management of these resources and the potential impact of the transmission line on them. Since there is no clear resolution of these issues for the primary routes, we will need to conduct major mitigation studies in locally sensitive areas. Visual analysis will include numerous simulations and visibility analyses. Typical wilderness studies will include user identification and areas of potential impact prior to making mitigation recommendations. The level of analysis for recreation and tourism will be generally confined to mitigation of visual and physical impacts, while wildlife habitat may be somewhat more complex. The cost for additional visual and recreation/tourism analyses is estimated to be $100,000 to $150,000. The following table summarizes the overall environmental cost estimates. Urban Study 250,000 300,000 Additional Data Collection Decision Process Additional Mitigation Studies 100,000 150,000 Total Estimated Cost Range’ $2,500,000 $2,900,000 Anticipated Cost ($) Potential Cost ($) 150,000 100,000 200,000 150,000 ' Estimated costs do not include client, legal counsel, or agency involvement (cost reimbursement). PEI-HLY 55-0198 120293-01 (03/96) ab 2 Additionally, pre-construction surveys, monitoring during construction, and compliance planning are needed”. Their cost is estimated as follows: The work in preparing the EIS is detailed in the following sections. ENVIRONMENTAL IMPACT STATEMENT The general technical approach, including the environmental studies and preparation of the EIS, is described below. It is important to note that we are assuming an EIS will be required, although there is always the potential to complete an environmental assessment (EA). Typically, this kind of work can be organized into seven main groups of activities, as shown below. Terminology may vary depending upon the lead agency. 1) Work Scope 2) Scoping 3) Inventory 4) Impact Assessment and Mitigation Planning 5) Preferred Route(s) Selection 6) Draft EIS (DEIS) 7) Final EIS (FEIS) A geographic information system (GIS) will be used to assist in the environmental analysis. This system will provide the ability to summarize the voluminous environmental data, assist reviewers and decision makers in identifying and assessing specific impacts, and compare routing alternatives. GIS applications will include: e __ Digitizing of resource inventory data as collected and recorded on maps by resource principal investigators e Conversion of mapped resource data to a digital database format > These estimated costs are not based on a final route and will need to be reviewed during the EIS phase. > Cultural and biological surveys may be required during the EIS phase. PEI-HLY 55-0198 120293-01 (03/96) ab 3 e Development of impact assessment models to evaluate how construction and operation of the proposed project would affect resource values and features e Data report and presentation graphics, inventory and impact maps at various sizes and scales WORK SCOPE Dames & Moore would assist in the identification of a federal lead agency, including preparation of documents (e.g. preliminary right-of-way application, etc.), and initial agency meetings. The project’s preparation plan required at the initiation of an EIS will contain the overall scope of work, including management structure and responsibilities, technical approach for the environmental studies, methods for conducting the resource studies, and schedule. This preparation plan will be approved by the agencies. A public involvement program would also be developed and is expected to include the agency interdisciplinary team, newsletters, public open houses, working groups, and perhaps a project information line. In addition, we will assist the lead federal agency in preparing the Federal Register notice. SCOPING Several agency and public scoping meetings would be conducted. Prior to initiating the environmental process, the project team will meet with other federal agencies, which have the potential to become cooperating agencies for the EIS, to inform them of the project, discuss their issues and concerns, and invite their participation in the project. Follow-up meetings with the agencies will be conducted during scoping and throughout the project. The lead federal agency will execute interagency agreements with the cooperating agencies. The lead federal agency would prepare a Notice of Intent to prepare the EIS for publication in the Federal Register and establish the dates and locations for the public scoping meetings. Public scoping meetings would be conducted at various locations within the study area. The purpose of the meetings is to introduce and describe the project, explain the purpose of and need for the project, describe the environmental studies and public planning to be conducted as part of the environmental process, and solicit comments. The lead federal agency would conduct all scoping meetings. CEA, or its representative (e.g. engineering consultant), will participate by presenting the project description and purpose and need. Dames & Moore will present status of initial studies and will prepare displays, including project map and flip chart visual aids, handouts, and sign-in sheets. Dames & Moore will document and summarize the proceedings and prepare a report on the scoping process and results. Potential changes to the scope of work will be documented. A project mailing list would be established and maintained throughout the project. Dames & Moore would prepare fact sheets to send to all addresses on the mailing list and would prepare PEI-HLY 55-0198 120293-01 (03/96) ab 4 news releases for all media within and nearby the study area, including newspapers and radio and television stations. A plan of development describing what can be expected for construction, operation, and maintenance will likely need to be prepared early on, depending on the lead agency’s requirements. INVENTORY Specific to the alternative corridors, available resource data previously not obtained through secondary sources (i.e., existing maps, databases, published and unpublished reports) and agency contacts will be researched and secured. The collection of data will be systematic and well documented. Dames & Moore will provide the resource study team with corridor base maps and a data documentation packet of standard forms to record the data sources. For example, information about the original scale and sources of data, assumptions used during collection, formats, dates, and additional sources will be part of the data documentation. Important to this procedure is the documentation of variations in data resolution and accuracies in order to understand any limitations of the data. These procedures will provide a means to ensure the applicability of the data and the validity of their sources. Preliminary base data initially will be developed for each alternative corridor based on refinement of the secondary data, supplemented by aerial photo interpretation and additional map studies. Environmental data will then be reviewed in the field, verified, and mapped in final form supported by graphs and tables as appropriate. The environmental resources to be addressed, at a minimum, include: Air Resources Earth Resources Water Resources Biological Resources Land Use Visual Resources Socioeconomics Electrical Effects Cultural Resources (prehistory, history, Native American concerns) It is important to note that the inventory study area or corridor widths will vary by resource depending on the needs and concerns for each resource study. For example, visual resources may be affected up to two miles from an assumed centerline, while effects to earth and water resources may be evaluated approximately one-half mile from the assumed centerline. PEI-HLY 55-0198 120293-01 (03/96) ab 5 Once plots have been completed for each resource study, the resource study teams will input and verify data at an appropriate scale. A refined database for corridor level assessment will be constructed. Corridor base maps created on GIS/Computer-Aided Drafting and Design (CADD) will include roads and other features that allow registration. Dames & Moore will digitize all maps, provide check plots to scale, complete all editing changes, correct maps and cut into grid cells. Each corridor may be subdivided at an appropriate size and, when complete, will serve as the maps for digitizing. Each resource study team will be responsible for checking the accuracy and edge matching of data sets within the corridors. As necessary, corridor information will be produced on an overall map or separately. Technical reports will be produced and given to the lead and cooperating agencies as documentation for the EIS. Presentation maps will be prepared at the appropriate scale. IMPACT ASSESSMENT AND MITIGATION PLANNING The objective of the impact assessment and mitigation planning process (IA/MPP) is to conduct an interdisciplinary analysis of the potential environmental impacts and plan effective mitigation within the alternative corridors. Concurrent with the refinement of the environmental database, we will implement the IA/MPP. The methodology will be reviewed by the ID team, which includes the project participants, so that pertinent issues and concerns are addressed. The ID team will meet at key times during this task to understand the methodology and results. Potential environmental consequences (impacts) are based on the environmental effects that would result from the construction and operation of the transmission line along the alternative routes. Through the use of the [A/MPP, the potential direct, indirect, and cumulative impacts, the interrelationships (cause and effect) of impacts (beneficial, adverse, direct, indirect, local, or regional) will be determined. Determining impact significance is probably the most important and difficult part of impact assessment and will be determined through a systematic process of defining criteria for “thresholds” beyond which impacts are considered significant. Criteria for thresholds will take into account the magnitude, incidence, intensity, duration, and interrelationships of impacts and regulations. The criteria will be developed based on data collected, issues and concerns expressed, and relevant agency policy. Requirements for access involves where and to what extent roads would have to be built or upgraded to construct the proposed project facilities for each alternative corridor. Dames & Moore will assist POWER in determining where existing roads are sufficient or would require upgrading, and where new access roads would have to be constructed. Potential vegetation clearing will also be estimated. Specific impacts of each resource will be documented in the technical reports. The technical reports will be accompanied by data tables that indicate the location and description of specific resource features and values, initial impact levels of these resources, mitigation measures PEI-HLY 55-0198 120293-01 (03/96) ab 6 recommended to reduce impacts, and residual impacts expected following mitigation. The technical reports will be reviewed and approved by the ID team. PREFERRED ROUTE(S) SELECTION Ranking the alternatives and selecting the “environmentally preferred” alternative or alternatives (or corridor) are the final steps before the preparation of the EIS. Ranking and comparing the alternatives are important in understanding the relative impacts of each. A multi-objective decision-making process will be used to evaluate and compare the environmental considerations inherent to the study area. Each resource study team (e.g. land use, biological, etc.) will conduct comparisons or rankings of the alternative corridors. These comparisons will be used to synthesize “cross discipline” rankings of all alternative corridors. The purpose of rankings is to develop an environmental ordering of all corridors under consideration. This comparison of corridors uses information and judgments rendered within each resource study. These data are organized around goals, of which the most important for the EIS is the identification of the environmentally preferred alternative or alternatives. All corridors will be ranked in order of environmental preference. Routing preference will be based on review of generalized impact levels, significant unavoidable adverse impacts, and other pertinent descriptive and impact data. Agency and public comments received through the public contact and information program also will be considered. The lead agency and cooperating agencies will identify the agency-preferred alternative or alternatives for inclusion in the EIS. Critical information from the project proponent is typically considered by the lead agency in its decision. DRAFT EIS (DEIS) The format of the DEIS will be in accordance with the Council on Environmental Quality regulations 40 CFR 1502.10 for preparation of an EIS. A preliminary DEIS will be prepared for review and approval by the lead and cooperating agencies. The schedule for preparing the preliminary DEIS will be carefully synchronized with the schedule of the environmental studies in order to ensure its timely completion and submission. For example, the chapter on the affected environment will be written after the resources inventory material has been developed. The chapter on environmental consequences will be completed after the impact analysis has been determined. Other special sections and appendices will be compiled throughout the preparation of the preliminary DEIS. The preliminary DEIS will be reviewed by the lead agency, CEA, and cooperating agencies. Review comments will be returned for incorporation by Dames & Moore into the final DEIS. Review meetings will be scheduled to clarify all comments on the report. Dames & Moore will then finalize the DEIS for final approval by the lead agency and CEA. PEI-HLY 55-0198 120293-01 (03/96) ab 7 Dames & Moore will revise the report, if needed, and submit the final camera-ready DEIS to the lead agency. The lead agency will file the DEIS with the EPA, prepare and issue the Federal Register Notice of Availability, and distribute copies of the DEIS to interested parties. During the DEIS review period, the lead agency, with assistance from Dames & Moore, will conduct public hearings to receive comments on the adequacy of the DEIS, make arrangements for the hearings, prepare notices and media releases, and conduct the proceedings. The representatives of the Dames & Moore project team will attend the public hearings and provide input as needed. Preparation of the environmental presentation materials by Dames & Moore will be closely coordinated with the preparation of technical and engineering information by POWER. FINAL EIS (FEIS) Following the public review period, the comments received will be reviewed by the lead agency, cooperating agencies, CEA, and Dames & Moore. The responsibility for developing appropriate responses for inclusion in the FEIS will be assigned by the lead agency. Presumably, Dames & Moore will prepare responses to all comments on the environmental studies while those related to the purpose of and need for the project, system planning, and engineering design will be completed by CEA. Following the development of the responses, the comments and their corresponding responses will be incorporated into the preliminary FEIS and submitted to the lead agency, cooperating agencies and CEA for review. Based on the comments from the review, Dames & Moore will prepare the FEIS for final approval by the lead agency. The lead agency will file the FEIS with the EPA and prepare and issue the Federal Register Notice of Availability. Dames & Moore will also prepare and issue media releases and newsletters, and distribute the FEIS to interested parties. At the close of the FEIS review period, the lead agency will prepare and issued the Record of Decision. A plan amendment may be required by a land managing agency, such as the Forest Service or Bureau of Land Management. Plan amendments are typically required when a preferred route does not utilize an existing or planned utility corridor documented in the Forest Plan or Resource Management Plan (Bureau of Land Management). PRE-CONSTRUCTION / MONITORING Prior to construction and potentially before agency approval on the selected alternative, a number of compliance studies are required. These include Section 106 (cultural) and Section 107 (biology). In addition, a Construction, Operation and Maintenance (COM) Plan would be prepared. The final element of environmental studies includes preparation of EAs (if needed) as well as other permits (e.g. Section 404). PEI-HLY 55-0198 120293-01 (03/96) ab 8 RIGHT-OF-WAY AND PERMIT ACQUISITION INTRODUCTION In order to secure a right-of-way along an approved route, significant permitting and acquisition of private easements will be required. Because of the complexity of local, state, and federal agency permits, as well as the need to resolve concerns of private landowners, the right-of-way acquisition process will require close coordination among project team groups, i.e., CEA personnel, project management, Dames & Moore, design staff, and the right-of-way personnel. Therefore, costs for right-of-way acquisition do not accrue only to right-of-way personnel. For detailed information about the project land status and anticipated permitting process refer to the Draft Lands/Regulatory Section Report. Cost information presented here was derived from researching the land status and property values along the core route for each of the three primary study corridors and their local alternatives. While the permitting requirements may not vary for a route selected anywhere within the boundaries of a study corridor, the number of private parcels may vary from one side of the corridor to the other, thereby affecting the cost of easement acquisition. PERMITS The three primary study alternatives, as well as their local alternatives, have many common permit requirements. Costs presented for permitting include title services, appraisals, and the assembly of exhibits and submission of the permit applications. Also included are costs to track the permit through the approval and granting process. Costs for conducting the appropriate environmental compliance associated with permits are covered in the costs for the EIS and pre-construction monitoring. Anticipated permit applications required include: Kenai Peninsula Borough Right-of-Way Permit Alaska Department of Fish and Game Title 16 Stream Crossing Permit Alaska Department of Fish and Game Title 16 Waterways Permit Alaska Department of Natural Resources Right-of-Way Permit Alaska Division of Governmental Coordination Coastal Zone Consistency Permit Bureau of Land Management Grant of Right-of-Way Alaska Department of Natural Resources Tidelands Lease Municipality of Anchorage Right-of-Way Easement PEI-HLY 55-0198 120293-01 (03/96) ab 1 e State of Alaska (DNR), Division of Parks and Outdoor Recreation Right-of-Way Permit Corps of Engineers 404 and Section 10 Permit State of Alaska, Mental Health Trust Lands Permit Alaska Department of Transportation and Public Facilities Utility Permit U.S. Forest Service Special Use Permit Alaska Railroad Corporation Crossing and/or Easement Permit Kenai River Special Management Area Permit Alaska Department of Natural Resources Tidelands Right-of-Way Permit RIGHT-OF-WAY ACQUISITION Land Field Services of Anchorage researched public records to determine estimates of parcels crossed by the various routes. Those sources were also used to gain a planning- level estimate of land values that could be used to derive easement costs. These data sources included: e Municipality of Anchorage Assessor and Recorder records for plats and assessed value; e Motznik Title Service for urban area land values; e Kenai Peninsula Land Management Officer, Assessor; and GIS Manager for maps, plats, parcel and cost information; and e Land Field Services, via past CEA project work, with an extensive in-house data base for lands crossed by the Quartz Creek 115kV Line. An individual parcel-by-parcel examination of location and cost relative to each specific route link was beyond this phase’s work scope and, accordingly, was not conducted. In- depth title searches and appraisals would be conducted for each parcel affected by the ultimately selected route within which right-of-way acquisition would occur. In some cases, particularly in the Anchorage area, the nature of readily available parcel information is such that parcel counts may be incomplete. Again, after a route selection process is complete, this would require an in-depth title search to provide the level of detail necessary to proceed with easement and permit acquisition. The records examinations described above reveal parcel counts for the core, or primary routes as follows: e Tesoro Route - 105 parcels between Point Woronzof and Bernice Lake; e Enstar Route - 58 parcels between the International Substation and the Soldotna Substation; e Quartz Creek Route - 93 parcels between University Substation and Soldotna Substation PEI-HLY 55-0198 120293-01 (03/96) ab 2 In our analysis, it has been assumed for the links that parallel an existing road, highway, railroad, or other identified public utility corridor, the transmission line would be sited within the existing utility corridor. The rationale for this assumption is based on constraints of the Alaska eminent domain statutes. Those proceedings do not allow a utility to condemn private lands if a public utility corridor is available for the proposed use. Therefore, in those cases, right-of-way acquisition costs would accrue to permitting only, with no costs required for acquiring private lands. An examination of land status in the vicinity of landfall alternatives for submarine cable shows that nearly all are owned or administered by federal or state agencies. Therefore, the costs for reactive compensation stations site acquisition is covered within the appropriate permitting process. If an alternative landfall is chosen in the Klatt Road area, it is likely that private property would have to acquired for the landfall facilities. It is estimated that land values in that area are $152,000 per acre. Costs for acquiring this site are included in the costs for this alternative. As it may become desirable to expand the University Substation, an examination of land status to the east of the substation was made. A suitably sized parcel is privately owned in that area. Land values in this vicinity are currently approaching $200,000 per acre. Approximate land values in other project areas are as follows: Soldotna, $10,000/acre Point Possession, $20,000/acre north of Captain Cook State Park, $3,000/acre south of Captain Cook State Park, $5,000/acre rural lands along the Quartz Creek Route, $1,000/acre These costs form the basis for the direct cost of purchasing the easement. In the case of CEA’s easement payment policy, the landowner would receive 100% of the fee value of his property for the area encumbered by the easement. Costs for acquiring private rights-of-way include: title services appraisal services ($750/parcel) easement surveys and descriptions ($600/parcel) document preparation negotiation recording file transfer/close-out PEI-HLY 55-0198 120293-01 (03/96) ab 3 The above listed costs form the basis for determining the indirect cost of right-of-way acquisition. Essentially, these costs are associated with the labor and expense of acquiring the easements. It is estimated that the total indirect cost per parcel for acquiring easements on this project would be $3,350. The total cost for right-of-way acquisition for each primary route and local alternative includes direct, indirect, and permitting costs. PEI-HLY 55-0198 120293-01 (03/96) ab +t TESORO Base Route Submarine Alternatives TE.A.20 TE.B.15 TE.C.30 Anchorage Area Alternatives A B c Captain Cook Alternative ENSTAR Bae Route Soldotna Area Alternatives A B Cc Anchorage Area Alternatives A B PEI-HLY 55-0198 120293-01 (03/96) ab R/W Direct $_ | R/W Indirect $ 521,900 461,750 All Public Lands All Public Lands All Public Lands Within Public Utility Corridor Within Public Utility Corridor Within Public Utility Corridor 129,684 168,200 327,272 390,000 930,000 Within Public Utility Corridor Within Public Utility Corridor Within Public Utility Corridor Within Public Utility Corridor Permits 31,820 Total Cost ($) * 1,015,470 384,210 461,272 424,500 990,300 384,210 384,210 384,210 384,210 QUARTZ CREEK Base Route 205,200 Bird Point Alternatives Overhead 22,330 Underground 13,332 Soldotna Area Alternatives A 1,066,560 B 690,840 Cc 509,040 311,550 44,290 14,740 117,920 76,380 56,280 Total Cost ($) * 29,380 546,130 536,792 498,244 1,184,480 767,220 565,320 * The Total Cost represents the cost to acquire permits and right of way for the entire route, substation-to-substation. PEI-HLY 55-0198 120293-01 (03/96) ab 6 Appendix A TABLE OH10 - COST ESTIMATING INFORMATION 230 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ Extended | Extended L&M LINE DESIGN 1 Material | Labor | Material | Labor Total Lot $52,800 $52,800 el le ell $43,740 | __$65,610 9 $2,160 | $2,484 | $19,440 $22,356 230kV Tangent Suspension PTA 4.5 | $1,200] $1,800 [ _ $5,400 $8,100 | $13,500 Tangent Screw Anchor 4.5 $900 $6,750 Tangent Driven Pile Anchor 4.5 | $1,080| $2,052] $4,860 $9,234 Light Angle Foundation 1 230kV Light Angle Suspension PTA Light Angle Screw Anchor Light Angle Driven Pile Anchor [Heavy Angle Steel Pole $2,052 $18,900 ‘Heavy Angle Foundation $4,140 230kV Heavy Angle PTA 0.5 $1,350 $2,025 $15,750 $11,610 g $1,688 Angle Driven Pile Anchor $2,052 $5,481 [Deadend (30°-90°) Steel Pole $16,800 $25,200 $10,500 [Deadend (30°-90°) Foundation $3,600 $4,140 $5,805 230kV Deadend (30°-90°) PTA [Double Deadend Steel Pole 0.25 | $19,200 | $28,800 $3,600 $5,805 [Mob/Demob ot 821,673 [$21,673 | TOTAL CONSTRUCTION ** $148,015 $307,121 $455,136 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r:\WAR\CHUGACH\CH_OHEST.XLS TABLE OH10 TABLE OH11 - COST ESTIMATING INFORMATION 138 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ Extended | Extended L&M LINE DESIGN [Clearing (per Mile) 80°ROW* [| Alot | $42,240 | $42,240] $42,240 | Soe occ ec ce eee ce ce eee ec ee | fTangentFoundation | 82,160 $2,484] $19,440] $22,356 |_ $41,796 | Tangent Screw Anchor | 4.5 [$200] $1,500] $900] $6,750 |_ $7,650 | Light Angle Foundation | 1 $2,160 $2,484] $2,160] $2,484 | __$4,644 | Light Angle Screw Anchor | 0.5 [$200 $1,500] $100] $750 |__—$850 | Heavy AngleFoundation | «1.5 | $3,600 $4,140] $5,400] _ $6,210 | _$11,610 | 138kV Heavy AnglePTA | 0.5 | $1,200] $1,800] sooo] ___—$900|_ $1,500 | 1.75 | $1,080 | _$2,052] $1,890] __$3,591| __$5,481 | Deadend (30°-90°) Steel Pole | 0.25 | $16,800] $25,200] $4,200] _$6,300|_$10,500 | Deadend (30°-90°) Foundation | 0.75 | $3,600] $4,140 $2,700] _$3,105|_ $5,805 | [138KV Deadend (30°-90°) PTA 0.25 | $2,400] $3,600] sooo] __—$900|_ $1,500 | [Deadend (30°-90°) Driven Pile Anchor | 1.63 |_$1,080 | _$2,052] $1,760] _$3,345 | __$5,105 | Double Deadend Steel Pole | 0.25 | $19,200] $28,800] $4,800] _ $7,200 | _$12,000 | 138KV Double DeadendPTA | 0.25 | $2,400] $3,600] sooo] ___—$900|_ $1,500 | Conductor Cd S84] $1,800] $3,000] $28,512] $47,520 | _ $76,032 | [Mob/Demob tot PO 819,812] $19,812 | TOTAL CONSTRUCTION ** $137,350 ___ $278,703 __ $416,053 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r:\WAR\CHUGACH\CH_OHEST.XLS TABLE OH11 TABLE OH12 - COST ESTIMATING INFORMATION 230 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ Extended | Extended L&M LINEDESIGN2 | Nate | Meat | tatoe_| Matera | tater | Toxt_| Clearing (per Mile) 70’ ROW * ilo] ss: $36,960 | sd $36,960] $36,960 (ERRESRRESEUR NESE ggg EVs Ev env TPE ESTATES, EESEEEEE] EEESRERENESN CEEREESEEESESE| EEGOEESSERETEND ESELEOPRESETETE] [SUEREESEERIED 9.5 230kV Tangent BracedPostPTA_ | 9.5_| $2,400 $2,880 $22,800| _ $27,360 | __ $50,160 | Light Angle Single Steel Pole ———s|_—1_—(| $8,190 | $12,285[ $8,190[ $12,285 | $20,475 | Light Angle Foundation —s—ss| = 1_~|_~—$1,800] $2,700] $1,800] $2,700 __ $4,500 | 230KV Light Angle Braced PostPTA | _1 | $2,400] $2,880] $2,400] $2,880 __$5,280 | Heavy Angle Single Steel Pole | 1.5 | $14,664] $21,996 | $21,996 | $32,994] $54,990 | Heavy AngleFoundation |S | $2,250 $3,375 [$3,375] $5,063 | __ $8,438 | 230kV Heavy AnglePTA |S | $1,350] $1,620] $2,025] $2,430 | $4,455 | Deadend (0°-90°) Steel Single Pole ___—|_2 | $17,862 | $26,793 | $35,724 | _ $53,586 | __ $89,310 | 230kV Deadend (0°-90°) PTA [2 | $2,700[ $3,240] $5,400] $6,480 | __ $11,880 | IMoby/Demob fre ee [ not fe] $11,009) |" $11,009) TOTAL CONSTRUCTION ** $207,417 $354,059 $561,476 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r:\WAR\CHUGACH\CH_OHEST.XLS TABLE OH12 TABLE OH13 - COST ESTIMATING INFORMATION 138 KV SINGLE CIRCUIT OVERHEAD LINE Oy/ Extended | Extended | L&M LINE DESIGN 2 Material | Labor | Material | Labor Total Clearing (per Mile) 70' ROW * [ito] | $36,960 | $36,960 | __ $36,960 | Te ae a a ee Se ight Angle Single Steel Pole__| 1 | $8190] 12285] $8,190] 12.285 | $20,475 | Light Angle Foundation | 1] $1,800 | $2,700] $1,800 | $2,700] $4,500 | Heavy Angle Foundation | 15 |_ $2,250] $3375] $3,375] $5,063 | _ $8,438 15.84 ed eG TOTAL CONSTRUCTION ** $197,300 $338,377 _ $535,677 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r\WAR\CHUGACH\CH_OHEST.XLS TABLE OH13 TABLE OH14 - COST ESTIMATING INFORMATION 230 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ ee eee Extended | Extended L&M LINE DESIGN 3 Material | Labor | Material | Labor Total Clearing (per Mile) 100' ROW * | itot] i $52,800 | $52,800] $52,800 | Lab eM Eee eee eee ea [Tangent Steel Pole (Guyed X-Frame) _|_4.5 | $12,960] $15,552 [$58,320] $69,984 [$128,304] Tangent Foundation || $2,160] $2,484 | $19,440] $22,356] $41,796 | 4.5 [Light Angle Steel Pole (Guyed X-Frame) | _0.5_| $14,400 | _$17,280 | __$7,200| __$8,640 | _$15,840 | Light Angle Foundation | 1 | $2,160] $2,484 | $2,160] $2,484 $4,644 | 230kV Light Angle Suspension PTA __|_0.5 | $1,350] $2,025] $675 [__—$1,013 | __ $1,688 | Ci Ansan eh cE Light Angle Driven Pile Anchor 0.5 $1,080 $2,052 $540 $1,026] $1,566 | Heavy Angle Foundation |S | $3,600] $4,140] $5,400[ _—$6,210|_ $11,610 | 0.5 {| $1,350[ _$2,025| $675] $1,013 | _ $1,688 | 1.75 |__$1,080 $3,591 $16,800 | $20,160] _ $4,200 $5,040 [Deadend (30°-90°) Foundation | 0.75 | $3,600] $4,140] $2,700[__$3,105|_ $5,805 | 230kV Deadend (30°-90°) PTA 0.25 | $2,700 1.63 $175 $1,250 $285 $2,038 $2,323 [Double Deadend Steel Pole | 0.25 | $19,200] $23,040] $4,800] $5,760 | _ $10,560 | [Double Deadend Foundation | 0.75 | $3,600] $4,140] $2,700] $3,105] $5,805 | 0.25 | $2,700] $4,050] $675[ $1,013 |__ $1,688 | 1.63 | __$175 1.63 |_ $1,080 [Conductor CCCSC*d;'*S.84|_ $1,800 epee peo UID PTET rrr coe [PT EOP TTL ee TOTAL CONSTRUCTION ** $162,395 $301,875 _ $464,270 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh 5 r\WAR\CHUGACH\CH_OHEST.XLS TABLE OH14 TABLE OH15 - COST ESTIMATING INFORMATION 138 KV SINGLE CIRCUIT OVERHEAD LINE nite seat | ator | Maal | “ate LINE DESIGN 3 Material Tater Total [Clearing (per Mile) 80.ROW* [Alot | $42,240 | $42,240] $42,240 | Hee eg Tangent Foundation | 82,160 $2,484] $19,440] $22,356] $41,796 | [138kV Tangent Suspension PTA [4.5 [$1,050] $1,575] ___$4,725|__$7,088 | _ $11,813 | Light Angle Foundation | 1 [$2,160 $2,484] $2,160] $2,484] $4,644 | Heavy AngleFoundation | 1.5 | $3,600] $4,140 $5,400[ $6,210 | _ $11,610 | 138kVHeavy AnglePTA | 0.5 | $1,200] $1,800] S600 | ___—$900| _ $1,500 | [Heavy Angle Driven Pile Anchor [1.75 | $1,080] $2,052] $1,890 $3,591] _$5,481 | [Double Deadend Foundation | 0.75 | $3,600 $4.140[ $2,700] $3,105 _ $5,805 | {138kV DoubleDeadendPTA | 0.25 | $2,400 $3,600[ S600 | —_—s900 | _ $1,500 | Double Deadend Driven Pile Anchor | 1.63 | $1,080 $2,052| $1,760 $3,345 _$5,105 | Mob/Demob tot 820.950] $20,950 TOTAL CONSTRUCTION ** $156,800 __$283,151_ $439,950 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (4:08 PM3/11/96) 120293-06 Irh r:\WAR\CHUGACH\CH_OHEST.XLS TABLE OH15 TABLE OH16 - COST ESTIMATING INFORMATION 230 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ eee Extended | Extended L&M LINE DESIGN 4 Material | Labor -| Material | Labor Total Clearing (per Mile) 100' ROW * | Liot{ | $52,800 | $52,800] $52,800 | ee [Tangent Driven Pile Foundation-1/25' | 4 | $1,800] $2,070] $7,200] $8,280 [$15,480 | [Tangent Anchor Bolt Foundation- 4/6" | 4 [| $500] $2,500[ $2,000 [$10,000 | _$12,000 | 230kV Tangent SuspensionPTA [4 [$1,200] $1,800[ $4,800 $7,200 | $12,000 | Tangent Plate Anchor__— | 5.6 [Stoo] $1,250] ss60 | $7,000 | $7,560 | Light Angle Driven Pile Foundation -1/2| 2 | $1,800] $2,070] $3,600 [$4,140 [$7,740 ] Light Angle Anchor Bolt Foundation- 4/6] 2 | $500] _$2,500| $1,000] __$5,000|_$6,000 | 230kV Light Angle SuspensionPTA | 2 | $1,350] $2,025] _$2,700| $4,050 | __$6,750 | Light Angle Anchor Bolt Anchor-1/8'_| 1.2 [ $200] $1,250[ $240 _$1,500 [$1,740 | Light Angle Plate Anchor | 2.8 | $100] $1,250[ $280 $3,500 | _$3,780 | Heavy Angle SteelPole | 0.5 | $12,600] $18,900] $6,300 | __$9,450 | $15,750 | Heavy Angle Plate Anchor | 2.45 | $100] $1,250] $245 | $3,063 | $3,308 | Deadend (30°-90°) Steel Pole | 0.5 | $16,800] $25,200] $8,400 $12,600 | $21,000 | Deadend (30°-90°) Driven Pile Foundatio $2,880 $3,312 $2,160 $2,484 [Deadend (30°-90°) Anchor Bolt Foundatiol 0.75 | _$500|__ $2,500] $375 |__—$1,875 | _ $2,250 | 230KV Deadend (30°-90°) PTA | 0.5 | $2,700] $4,050] $1,350 $2,025] __ $3,375 | [Deadend (30°-90°) Plate Anchor | 4.55] $100| $1,250] $455 |___—$5,688 | __ $6,143 | Dose Deion Dvr Pic Fanaa | 15-[ $2580 Double Deadend Driven Pile Foundation - $2,880 $3,312 $4,320 [Double Deadend Anchor Bolt Foundation] 1.5 | _$500| $2,500] $750 |__—$3,750|__ $4,500 | 230kV Double Deadend PTA 1 $4,050 $6,750 [Double Deadend Anchor Bolt Anchor - 1/| 3.9 $4,875 $5,655 [Double Deadend Plate Anchor 9.1 $11,375 $12,285 Conductor 15.84 $28,512 $47,520 $76,032 Mob/Demob 1 lot | | «$26,882 | $26,882 TOTAL CONSTRUCTION ** $173,687 $390,836 $564,523 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r\WAR\CHUGACH\CH_OHEST.XLS TABLE OH16 TABLE OH17 - COST ESTIMATING INFORMATION 138 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ Extended Extended L&M | MNEDESIGN4 —_| sate isecia!|_tator_| Maint | Later | Teal [Clearing (per Mile) 80'ROW* | lot | | $42,240 [$42,240] $42,240 | DE ES eS $14,940 $2,070 $2,500 $1,575 | _$1,250[ $480] $3,000] $3,480 | $1,250 $20,610 $2,070 $2,500|_$1,000[ $5,000] _ $6,000 | $1,200 $200 $12,600 $2,880 | $2,500 $375] $1,875] $2,250 | ‘angent Steel Pole (Guyed X-Frame) ‘angent Driven Pile Foundation - 1/25' ‘angent Anchor Bolt Foundation - 4/6' 38kV Tangent Suspension PTA ‘angent Anchor Bolt Anchor - 1/8' ‘angent Plate Anchor ight Angle Steel Pole (Guyed X-Frame ight Angle Driven Pile Foundation - 1/ ight Angle Anchor Bolt Foundation - 4) 138kV Light Angle Suspension PTA ight Angle Anchor Bolt Anchor - 1/8' ight Angle Plate Anchor [Heavy Angle Steel Pole [Heavy Angle Driven Pile Foundation - 2. -4 $9,960 $1,800 $5 $1,050 4 s — ayy = 2.4 $13,740 $1,8 Nn 3 N Lk N — o ~ wn 8 s/s 3|3/8 8 0.75 im 8 z z 2 : : 3 eit. Ss $1,200| _$is00[ $600 $900 | _ $1,500 | s200[ $1,250] $210] $1,313 | _ $1,523 | 2.45 $16,80 Deadend (30°-90°) Driven Pile Foundatio | 0.75 | _$2,88 $5 138kV Deadend (30°-90) PTA | 05 | $2,400| $3,600| $1,200] _—‘$1,800| _$3,000 | $200 Double Deadend Steel Pole | 1 | $19,200] $28,800] $19,200 | $28,800 | $48,000 | $2,880 | $2,500] $750] $3,750] $4,500 | [138kV Double DeadendPTA |_| $2.40 s200] $1,250] $780] $4,875] $5,655 | [Double Deadend Plate Anchor |_9.1_ | | $1,250] $910 [$11,375 [$12,285 | 15.84| $1,800 [Mob/Demob tot 825,71 | 825,71 | TOTAL CONSTRUCTION ** $169,022 __ $372,167 __ $541,189 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r:\WAR\CHUGACH\CH_OHEST.XLS TABLE OH17 TABLE OH18 - COST ESTIMATING INFORMATION 230 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ Extended | Extended [ L&M | —_LINEDESIGNS | site| Mart|_tator_|_ ar [Clearing (per Mile) 100'ROW* ss [ 1iot[ | $52,800 [$52,800] $52,800 | Ee a a | er Ya | ea Ta | Lee] SL | Tae Tangent Foundation 30kV Tangent Suspension PTA 4. Tangent Screw Anchor . angent Driven Pile Anchor . ight Angle Steel Pole (Guyed X-Frame) ight Angle Foundation 230kV Light Angle Suspension PTA | $1,350] $2,025] $675] $1,013 | __ $1,688 | eat An Dan Pe Anca ——[-0-[-teo-| srr [ssa ne | a Light Angle Driven Pile Anchor _—si|_(0.5 | $1,080 $2,052 $540 $1,026 $1,566 Heavy Angle SteelPole —s|_«(0.5_| $12,600] $18,900[ $6,300] $9,450 | $15,750 | Heavy Angle Foundation —s|s«i1S | $3,600] $4,140[ $5,400] $6,210] $11,610 | 230kV Heavy AnglePTA |S | $1,350] $2,025] $675] $1,013 | $1,688 | [Heavy Angle Driven Pile Anchor __—[_1.75 | $1,080| _$2,052[__—$1,890[ $3,591 | —_$5,481 | [Deadend (30°-90°) Steel Pole | 0.25 | $16,800] $25,200[ _—$4,200| _—$6,300 | __ $10,500 | [Deadend (30°-90°) Foundation | 0.75 | $3,600] $4,140[ _$2,700[ $3,105 | $5,805 | 230kV Deadend (30°-90°)PTA_——s| 0.25 | $2,700] $4,050[ $675 | $1,013 | —_—$1,688 | [Deadend (30°-90°) Driven Pile Anchor_| 1.63 | $1,080| $2,052 [__—$1,760[__—$3,345 | _$5,105 | [Double Deadend Foundation | (0.75 | $3,600] $4,140] $2,700] _—$3,105|__ $5,805 | [Conductor CCSCSCSC*«d «S84 $1,800] $3,000 $28,512 $47,520] $76,032 | ateagp ee ccf msl Ce LL fn TOTAL CONSTRUCTION ** $151,795 $313,264 $465,059 >| > Minin * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Irh r\WAR\CHUGACH\CH_OHEST.XLS TABLE OH18 TABLE OH19 - COST ESTIMATING INFORMATION 138 KV SINGLE CIRCUIT OVERHEAD LINE Qty/ Extended Extended L&M LINE DESIGN 5 Material | Labor | Material | Labor Total [Clearing (per Mile) 80'ROW* | tot | | $42,240 | $42,240] $42,240 | pone ee Py Tangent Foundation $2,484 $19,440 $22,356 | $41,796 $200 $1,500 $900 $6,750 $7,650 Light Angle Foundation |S} | $2,160[ $2,484 [| $2,160] $2,484] $4,644 | lLight Angle Screw Anchor __————s«d|«S | $200] 81,500] $100] $750] $850 | 0.5 [138kV-Heavy AnglePTA sd] (0S | $1,200[ $1,800] $600] $900 | _—$:1,500 | 1.75 0.25 | $2,400] $3,600] $600] $900 | __—$1,500 | [Deadend (30°-90°) Screw Anchor | 1.63 | $250] $1,750] $408 | $2,853 | _ $3,260 | 15.84 Tot | ——L ———=|__ $20,285 | $20,285 | TOTAL CONSTRUCTION ** $141,130 $284,845 $425,975 * Clearing costs can be reduced in segments QC.C, QC.D,QC.E, & QC.F ** Estimates include a 10% contigency in the line items. PEI-HLY (3:57 PM3/11/96) 120293-06 Ith 10 r:\WAR\CHUGACH\CH_OHEST.XLS TABLE OH19 TABLE OH20 - COST ESTIMATING INFORMATION BIRD POINT TO GRIDWOOD DOUBLE CIRCUIT OVERHEAD LINE LINE DESIGN 6 0 Unit $ Item $ 0 Unit $ Item $ Conductor (ft) 205,920 $2.25 $463,320 | 205,920 | $5.00] _ $1,029,600 Tower (Ib) 1,120,000] $1.20] $1,344,000 [1,120,000] _ $1.50 | $1,680,000 Str. Removal (ea) | 16 | $2,000 | $32,000] 16 | $12,000 $192,000 WireRemove(ft) | —s| ~—Sss| ~SSCSCSCSC*d:«é002,960 | __$.1.000 $102,960 Hardware (set) | 16 | $6,000 | $96,000 $6,000 $96,000 Foundations (set) | 16 _| $5,000 $15,000 SUB TOTALS $2,015,320 $3,340,560 TOTAL $5,355,880 COST PER MILE $823,982 NOTE: Construction labor and material costs include a contingency. PEI-HLY (3:39 PM3/11/96) 120293-06 pe r:/WAR/CHUGACH/OHBIRDPT.XLS 1 TABLE OH20 TABLE OH21- COST ESTIMATING INFORMATION TURNAGAIN ARM OVERHEAD LINE CROSSING $225,000 | 45,000 | $6.00 Tower A (Ib) __—'{_15,000 | _ $1.50 | $22,500 | 15,000 $2.00 $30,000 Tower Bib) __—_—*|_ 500,000 |__ $1.50 _ $750,000 | 500,000 | $2.00 | __ $1,000,000 | Hardware (set) _—|_—9~—«|_—«$6,000| = $54,000 9 =| $6,000[ $54,000 | Anchors(set) «| 6 ~_—*|_—- $3,000 _—$18,000[ 6 __—*|_ $10,000] $60,000 | SUB TOTALS $4,219,500 $4,964,000 CONTINGENCY 10.00% $496,400 TOTAL $9,679,900 COST PER MILE $3,337,897 PEI-HLY (3:39 PM3/11/96) 120293-06 pc r:/WAR/CHUGACH/OHBIRDPT.XLS 2 TABLE OH21 Appendix B o- RECEIVED COPY FEB 2 0 1998 fimewi JACOBSON, INC. 5355 - 28TH AVE. NW. * SEATTLE, WA 98107 + (206) 782-1618 (20o-2T2- Gr2Ur 6-2 February 16, 1996 cc”. File JOBNO. PHASE SVC TASK SUB TASK Bit @ Taek He. [FE FEB 2€ i996 peep Power Engineers Inc. ; Chus 3940 Glenbrook Drive FIKE NAME P.O. Box 1066 sitet Hailey, Idaho 83333 Attn: Mr. Jack Hand Re: Submarine Cable Circuit Turnagain Arm - Cook Inlet, Alaska Dear Jack, We have completed our rough estimate of installation costs for (4) single conductor 138kV oil filled submarine cables at (4) crossings in Turnagain Arm - Cook Inlet Alaska. We believe it would be in the customers best interest to embed these cables under the sea bed for the total length of the crossing. The embedment of the cables is based upon a jetting method utilizing high pressure water being applied to a cable burial machine. The cable is laid through the sled and is placed at a pre-determined depth via a “stinger” located on the burial machine. It is also recommended that double armor be applied to the outer sheath of the cable for added protection and longer life. The armor should be the same lay for ease of handling. We have broken our estimate into two categories including just laying the cables on the sea bed and laying and burial of the cables. ; We appreciate the opportunity to work with you and should you have any questions please do not hesitate to contact us. Best regards, Pirelli Jacobson, Inc. BJ/sk enclosure TURAGAIN ARM 138KV INTERTIE SUBMARINE CABLE INSTALLATION ESTIMATE PT. POSSESSION PT. POSSESSION ENSTAR FIRE ISLAND PT. CAMPBELL PT. WORNSOFF Transport & Lay (4)cables $10,000,000 $9,300,000 $8,000,000 Includes: Marine Survey, Directional Drill and conduits at each land fall $5,800,000 Bury to 2-3 m. in jettable $4,200,000 $3,800,000 $2,500,000 material below seabed $1,600,000 $7,400,000 Total Lay & Embed $14,200,000 $13,100,000 $10,500,000 ESTIMATE INCLUDES: . Marine Survey - For cable routing ° Excavation from H.W.M. to terminal ° Conduits for each cable to a maximum of 1000' offshore ° Cable transit from factory to Anchorage . All marine equipment and manpower for installation works ° Installation of (4) 138kV FF D.A. submarine cables . Cable burial to 2 - 3 meters in jettable material ESTIMATE DOES NOT INCLUDE: . Termination & Testing of cables . Sub-station-work (other than cable pull in) . Any material ie: cables, accessories, splices, terminations, pump station, etc. Estimate all in 1996 dollars Jil / NIL (EES 200s t4e 521 Fs Pou vo sy 54 NU Ue Ve LEFEFEEEEE EE AEEEEEEEEEEEEEEEFEEEEEEFETEEEALE ETAT EEE EEE thee tt sesneareneninerarnisrseiaanereseehee GD) E NY JACOBSON INTERNATIONAL, INC. FAX 200-744-2701 PHONE 206-7448765 HOME 205-446-3768 DATE: 2 - S- IAS FAX REF #: | GE, ATIN: Tack Pe av FROM: =) / No. PAGES (INCLUDING THIS COVER) 2—- If you have any problem with this transmission, please call 206-744-9765 retell etetieccankeetantecertasnisintesieteninsietoeetentastecantniaanhantr tu liertnkernkaetesiesiisiansinisesiieniadiatinatasiaasiaieanasiasaaiasaia OT ee eee arias \2O2UTD- &22-02-Y, JOSRU. PRASE “SYS” THER” “Sua Tasn | reco FEB 05 1995 acco: tw tee Eé ares LT 4) INTL TEL: 206-744-2791 Feb 05 96 15:41 No.002 P.01 Pn a INSTALLATION PRICING TESORO AND ENSTAR CABLE ROUTES The pricing for these crossings is predicated on the following assumptions: e Arock free right-of-way in which to pull the trencher. « Soils that are considered jetable, such as silt, sand, consolidated sands, gravel, and clay. ' « Burial depth not to exceed 3 meters. e Vehicular access to both shore ends. e One cable loaded on barge at a time, total of 4 cables to be installed. « Cable delivered Anchorage area with 45 days of standby for delivery vessel. Tesoro pricing: in thousands Mobilization $2,000 Shore ends 900 Lay and bury 64 days at $ 80,000. 5,120 Load and refurbish equipment 16 days at $ 80,000 1,280 Risk 3,000 Profit 20% on $12,300,000 _2,480 Total $ 14,760 Total estimate for the installation and burial of 4 cables in the Tesoro route is $ 14,760,000.00 US dollars. Enstar pricing: Mobilization $2,000 Shore end south 450 Lay and bury 56 days at $ 80,000. 4,480 Load and refurbish equipment 12 days at $ 80,000. 960 Risk 2,500 Shore end bore under tracks and rip rap north 750 Profit 20% on $ 11,140,000 2.228 Total $13,368 Total estimate for the installation and burial of 4 cables in the Enstar route Is $ 13,368,000.00 US dollars. ne ey eouo 1Oceuce Pees P.O. Box 5147 Pleasanton, CA 94566-9998 Phone 510-426-4718 Fax 510-426-0323 Facsimile Cover Sheet To: Jack Hand UN Company: Power Engineers Inc. [| Ol Phone: 208-788-3456 f Bi Fax: 208-788-2082 yee le ! ad yr From: Steve Kanty fe a Company: Isberg & Associates Inc. f Hf ; Phone: 510-426-4718 Jac’ Fax: 510-426-0323 Date: 01/11/96 Pages including this cover page: Three Subject: Alcatel Wire & Cable Kenai Submarine Transmission Project _ Jack, as promised the following pages provide brief details of the LPOF Submarine cable costs that Alcatel would provide on this project. | hope this will be sufficient to get you to the next stage of the project. Obviously once the route has been selected and load determined we can be much more specific. As | mentioned in our recent conversation, some key individuals from Alcatel France will be attending the ICC in Houston and | have extended an invitation, on your behalf, for them to visit Hailey. | look forward to working with you on this project. ALC ATE! High Voltage Systems __" CABLE Lor PR Option 1 Cable 1x630mm2 Cu LPOF 132/280 (245) kV SSWA Cable laying (not embedded) + Accessories + Packaging + Transportation Option 2 Cable 1x500mm2 Cu LPOF 132/230 (245) kV OSWA Cable laying (not embedded) + Acoessaries + Packagin + Transportation 3 The estimated prices quoled by us are subject to the following general. qualifications: qi Delivery: to @ advised once more precise requirements are defined, 2. Prices only valid for above quantity and exclude any taxes or duties. More specitic prices can be given once more precise requirements ate defined. Approved by: OY OK Cam Dowlat Director-High Voltage Systems, Enel! Cable Gross Section Drawings tie iva a gids YHINTLINLoSO 6D s4 Pru 4600 | Sccuce fax: duig por: 32 4 APSC6SIG. ALCATEL URsLs ! mi ‘i s 7 ar wre ew met ee ieee tee ps a, Nominal Diameter. pad nt ALCATEL CABLE FRANCE USINE DE CALAIS . 500-mii Tam? r OF. AS2/Z30 pkV. Double steel wires _armoured submarine cable JAN-11-13 Si J Se f— 11-1356 85:48 FROM ISEERG & ASSOC. r setter 12087652082 P.ag Tax tip eer: 33 1 47566515 ALCATEL CABLE ' wee we ane wee ue. Ny TT | ' COPPER CONDUCTOR oe CONDUCTOR SCREEN ; INSULATION ¥ : INSULATION LEAD ALLOY SHEATH METALLIC - __ REINFORCEMENT, yk BEDDING rE SHEATH ANTI-IEREDD TAPE _ BEDDING . QALVANIZED STFEI. ey , WIRES: ARMOUR eee te ; \ ‘ POLYPROPYLENT: “YARN AND i FLUS 7 COM: 1D ALCATRL CABLE . FRANCE USINEDE CALAIS. | KENAL INTERTIE 630 mnt? Copper O.F. . 132/230 (245) kV Single stee! wires armoured submarine cable TOTAL P.@4 Ate Te Nests are aS Job Pr Sve Task Sub. aga From: Oheiede - 22619 aaa Time P O WE. R TELEPHONE RECORD Follow Up: Two AK for Th 89: ae ? HAD ower Cable Consultants, Inc. Fax Number: 208-788-2082 Total # of Pages: 2 From: Torben Aabo Date: February 27, 1996 2 LPL sano 220 Sweetman Road, Ballston Spa, New York 12020-3211 phone 518-384-1613 » fax 518-359-9517 TELEFAX Please deliver to: Mr. Bill Riall, Power Engineers, Hailey, ID SFOS ESO OE SSS ES SSDS ESET EFSF ESET OTEESESSSS SESE SRESES FOE ESSERE SSE OFSHESES OES EEE ESESESESSSECSSESE SOS EAGREETSSSETSESOS CONFIDENTIALITY NOTE: The information contained in this facsimile message is legally privileged and confidential information intended only for the use of the individual or entity named above. If the reader of this massage is not the intended recipicnt, you are hereby notified that any dissemination, distribution or copy of this fax is strictly protubited. If you have received this fax in crror, picase immodiately notify the sender at the telephone number provided above and return the original messagp to us at the address above via the United States Postal Service. Thank you. POR OHREHSESESESESO TEESE EST ESESSEOEOOESEE SET EETOSEEESEHHEHESETEEESSSEEEEDEETEESEOSESEESHEEDEHESSSEETOEDREURYOSHOTREUE Dear Bill: The attached is the Alcatel Norge estimated costs. | have summarized it in the table below. Note the cost for the transition joints. I believe it is for the lot of 3 single phase joints. Item Cost WD SCFF, 138kV Submarine cable $4 03/ft. £ XLPE, 138 kV Submarine cable $93.23/ft. a XLPE, 138 kV Land cable $58.88/ft. Transition joint, XLPE/SCFF $48,300 each (set SCFF Terminations $11,230 each L XLPE Terminations $8,855 each Transportation and laying of Submarine cable $14,490,000 Aot | still have one outstanding request (from Japan). Please call me if you have any questions. Regards, Vt Torben Aabo ae 4- et rm | en mownice RABEL NORGE APS + 5183999517 NR.Sd9 Soai/net v KABEL NORGE TELEFAX toe Offen Bo 136, Okern N-0809 Osio, Nerway Telephone: +472263 88 20 Telefon: +47 22 63 81 20 To: Power Cable Consuttants Inc. Pax ne.: 518 399 9517 Att: Torben Aabo Ret.: 138 KV subm. cables in Alasko. Frem: Bertram C. Middelthon Sender's direct faxie.: 9 +47 47 22 63 74 Sender's direct tei, ne. +47 47 22 63 8B Dave: 12 Fab 1996 Ne. of pages, inal. this: ia Wany port of this tronentusion le arising or illegibie, please guntuct tut. +47 67 33 63 00 82 Referring te your fax of Fabrvary 7, 1996, we have the pleasure of indicating the following budget prices. - Qil-filled submarine cable 1000 kemil (500 mm2) NOK 2100,-./meter ax works 02 if + XLPE submarine able 1000 kemil ($00 mm2) NOK 1900,-./meter ox works 7 72,95 ~ XLPE land cable 1000 kemit NOK 1200,-./meter ex works 53% #5 Bb - Transition joint NOK 300 000,-. each - ¥¥.30u - Tarminatioon for oll-filled cable NOK 70 000,-. each + // 230 - Termination for XLPE cable NOK 55 000,-. each - 3 555 - Transportation and laying cost for submarine coble NOK 90.000.000,-. . ; , 450. MN t The prices ore to be understood as fairly opproximate figures based on 1995 cost levels and the very limited information given to us. We hope to have served you with the above estimates. ards / Middelthon 2/29 /% Truutey Stes (NOK $0, /L/0 \oern \Jetater\he-pe-us.dec Received: 02/27/96 07:32:00 From: 22637444 82/06/1996 18:59 5183999517 AABO PAGE @1 - Power Cable COPY Consultants, Inc. Terbes Asbo 220 Sweetman Road, Ballston Spa, New York 120203211 phone 518-384-1613 ° fax 518-399-9517 TELEFAX Please deliver to: r. Bill Riall, Power Engineers, Hailey, ID | °=0'0 FEB 0 1598 EGO Fax Number: 208-788-2082 Total # of Pages: 6 From: Torben Aabo Date: February 6, 1996 CAR a ew ATeNs Ess Oe oem HeeeeeeSECESEKERAE AERA HRAER SHEERS ESET THESE HSOSON ESET EPEERE RETEST EERE SOOT OS HER TORTOHSTETEERERSE CONFIDENTIALITY NOTE: The information conmined in this facsimile message is legally privileged and confidential informauon intended only for the use of the individual or entity named above. If the reader of this message is not the intended recipient, you are hereby notified that amy dissemination, distribution or copy of this fax is strictly prohibited If you have received this fax in error, please inumediatety notify the sender at che telephous aumber provided above and rerum the origins! message to us at the address above via the United States Postat Service. Thank you. SOS SOR EHTETE STORE TERRE COEETERSESEEHEES SHEER SHESERENSERURONETES YS ESHEETS EESETES FOO FERETUIRGTRORNOOHESH SONS EES ES TEESE Dear Bill: Jay requited that | fax you the cost information I used for the development of the Chugach cable cost. 3 I have attached the information received from manufacturers. I have promise from several other manufacturers to supply costs. I will discuss the data with you as soon as | get it. The following costs were given to me verbally from SILEC: e XLPE land cable: $23/ft ¢ Splices: $7,000 each e Link boxes: $5,000 each e Grounding boxes: $3,000 each Please call me at 518-384-1613 so we can discuss how to present the data in an appendix to the report. Regards vt. Torben Aabo 7 Vel UOi L550 44645 9 -e esse { Bi7ee/so 69S KT ENGINEERING % 0215183999517 A NR.329 S@01 ys ‘ v TELEFAX IN FALE Jenoincenine Fax No. +45 43 96 07 74 Phone No. +45 43 48 20 10 COMPANY: Power Cable Consultants, Inc. FAX: 00 1 518 399 9517 ' ATT: Mr. Torben Aabo REF: MKI-0238/1k3 Cos DATE: 1 February 1996 i FROM: Martin KX. Jensen PAGE: 1 OF 2 (Inclusive of this cover) (IF YOU DO NOT RECEIVE ALL PAGES, PLEASE CALL IMMEDIATELY) Dear Mr. Aaho, Re: Alaska Project Reference is made to previous correspondence on the above subject plus latest pleasant telephone conversation of today. As requested, we take pleasure in indicating xough budget estimate prices for the cables discussed in our telefax of 18 January 1996, ref. MKJ-0206/1kj. Cable type: NKT flat type oil-filled (SCOF) 145 kv 3x500 mm? Cu submarine cable. Design details acc. to NKT document No. K 96003. 2,650.0 g 92 fete, Cable type: 145 kV 1x500 mm? XLPE-Cu-LRT Submarine cable. 11) Design deteils acc. to NKT document No. K 96004, a 200.8 #221 huh a he Sel DHKE ArOs3 (I= 5,29) Bas dbs Lss0 iu.os QLog5 5551! ARDS real Gl Wied OY 59 NKT ENGINEERING 9 8815183999517 ; NR,329 S82 Journal: MKJdJ-0236 NH T 7 UNGINZERING Date : 1 February 1996 Ref. MKJ/1kj Page : 2 of 2 Underground/land cables: Cable type: 145 kV 1x500 mm? XLPE~Cu-LRT unarmoured underground cable. Design details acc. to NKT document No. K 96005. $ 7 y2 = 5 : 8 LY Virele a e iti sald : A xyough budget estimate for suitable transition joint for interconnection of three-core flat type oil-filled cable with 3 single core 500 mm’? XLPE cables, both 145 kv 57 @e voltage level, will amount to approx. ? s67iy Kindly observe that all the above-mentioned budget prices are Ex Works our factory. Hoping that the forwarded is in accordance with your wishes, we trust this will assist you in the further investigations of &@ possible submarine cable project. Best regards, NKT Engineering Laugh, Martin/K. Jensen Svend O. Olsen 3AN-89-1996 16:27 FROM PIJRELLI JACOBSON INC To 15183999517. FACSIMILE PIRELLI JACOBSON, INC. Date: January 9, 1996 Fax Reference Number: PJI-8051-PM To: POWER CABLE CONSULTANT Attn: TORBEN AABO From: PIETRO MONDINI Pages (including this cover): 4 Ifyou haveany probleats with this tremmniselon, plecee call us at (206) 788-1618 / evr (208) 789-2881 RE: 115/138KV SUBMARINE CABLE FOR ALASKA. REGARDING YOUR FAX DATED JANUARY 9. 1996 Dear Mr. Aabo, In order to respond to your fax in dus time, I will submit a rough estimate of a similar cable with a slight difference in the cross section (750 MCM instead of 1000 MCM). The cable that we propose will be SCFF (self contained Suid filled) cable as per attached cable technical data with double armor. AS REE Oe Sorte PELE AS , The cable will have a polypropylene yarn serving and it will be mamufactur¥d th 8 continuous length. The budgetary price for the cable ex-factory Naples (Italy) is $160 USD / ft. To the above cost, you will have to add the import duties and the transportation cost. Please also note that we have proposed a double armor cable because as you mentioned in some areas there is rocky hard bottom and the cable burial is questionable from s technical and econoraical point of view. We have to inform you that our company owns different burial machines that use the jetting method but all are usable in sandy/mud bottoms, ie. jettable bottorn, and we do not have available machine for trenching in rocky bottom. Should you require an estimate for construction, please keep in mind the above. 5955 2th Avenue N.W."**Seatile, WA 98107" USA. Received: 01/09/96 07:37:24° From: 206 789 2851 B2ido+lsso 10:55 5a SIISSCL I | JPN-89-1996 16:27 FROM PIRELLI JACOBSON INC TO 15183999517 - P.@2 Power Cable Consultant Mr, Torben Aabo January 9, 1996 pias Tis wv Fae Raft PT-8051-PM a Sai ete imine aaa trata ame. estion i would be to Is the cable on the sea bottom and have only the shore end ete raha it tA (hice backhoe excavation) unless it is feasible to find a suitable route that is entirely jettable. Please comment if any- wes Pietro Mondini Vice President Pirelli Jacobson, Inc. Receiwed: 01/09/36 07:37:24 From: 206 789 2851 LEDEZSEB0G UTE BZ'9T:EO 96/20/20 ‘pentecey ELECTRICAL SERVICES AND CONSTRUCTION OPERATION 1225 Westfield Avene, Clark, NJ 07066 Breet Tel.: (908) 382-3776 Fax: (908) 382-3437 Rare eee i PO NO. OF PAGES: >t FROM: OK LY TO: Tae a. bo FAX NOW 7 3-3 iis 717 REF.; - ees KLE cade S$ 4 w ry i. LAO The 4 he aL x4 spiadquce . KG GL Zh 1@ = 3vd WWD ---- ITGUd 4EPECBERSE 2:Gt 9661/28/28 5 UdsdorL3s0 solss Dsos3I354¢ mADU reac oda Power Cable CO Py Consultants, Inc. Torben Aabo 220 Sweetman Road, Ballston Spa, New York 12020-3211 phone 518-384-1613 * fax 518-399-9517 TELEFAX Please deliver to: Mr. Bill Riall, Power Engineers, Hailey, a 7 20ctJor Ww o7 Total # of Pages: 3 ! ° ] Fax Number: 208-788-2082 1 aw. meet | lacoo | FEB 08 {9 De, Lact tet From: Torben Aabo Date: February 8, 1996 CAFE CERT EReesesseecesoUseRULEEUSSSETeTseCunSEEETS DET eEHeDeeseT Ee EEHEEserese oes eERnTEeESESsEraesseseseceasuescegess CONFIDENTIALITY NOTE: The informmtion contained in this facsirnile message is legally privileged and confidential imformation intended only for the use of the individual or entity named above. Lf the reader of this moasage is not the intended recipient, you are hereby noufied that ary dissermnation, distribution or copy of this fax is stricdy prohibited If you have received thus fax in error, please immediately noufy the sender at the telephone number provided above and retum the original message to us at the address above via the United States Postal Service. Thank you. RHEEEDAEE OO CEDAORESS ODE HEOTE EER EEODEATES ESSE SCRE STNTENAERETER ESSE STS OSSSOOEREESE SE RESR ESOS TOR TICENNENS FES eREEEERESSS Dear Bill: Attached please find additional costing for XLPE terminations and the three-conductor flat cable. Also attached is a drawing of the cable. You may want to use this to replace Figure 6.3, which at the moment is a drawing of a two-conductor cable. I was promised additional cost data on the SCFF cable by Friday.... Please call me at 518-384-1613 so we can discuss how to present the data in an appendix to the report. i Regards, C TO he ro Torben Aabo Pay ; fille 4 Received: 02/08/96 10:27:08 From: +45 43 96 07 74 bZ/da/1l3so 1335 5163995517 AKBO PAGE 682 08/02/96 16:22 NKT ENGINEERING + 6815183999517 NR.471 S@@i TELEFAX TAD EEE Benaneenine Fax No. +45 43 96 07 74 ' Phone No. +45 43 48 20 10 COMPANY: Power Cable Consultants, Inc. FAX: 00 1 nie 399 9517 ATT: Mr. Torben Ambo REF: MNKJ-0260/1k4 co: DATE: & February 1996 FROM: Martin K. Jengen PAGE: 1 OF 1 (Inclusive of this cover) (IF YOU DO NOT RECEIVE ALL PAGES, PLEASE CALL IMMEDIATELY) Dear Mr. Aabo, Be: Alaska Project Reference is made to your fax of February 7, 1996, ' Prices for terminations for flat type M@llerhe} cable is very much depending on how the cable system will look, in particu- lar lay-out of terminating point etc. However, in order to give you an idea of the total project costs involved, we can inform you of the following rough budget prices as follows: 1) Complete termination for 3-core flat type Mellerhej cable with splitter box and connecting tubes, built up as 3 separate porcelain insulators placed on one common steel atructure. Budeet orice: Dkk 250,000.00 per 3 phase termination $6 5,06 2) Porcelain cable termination for termination of XLPE- t 2 Temeinnhe, cables (underground as well as submarine cables). b : .0 — B/S, UB 2ath Both the above prices are excl. installation, furthermore, we take pleasure in fcrwarding the enclosed drawing of Sur’ Plat type submarine’cabte-furAC=porpose, see Journal No. Al057. ; Two prints of the same have been airmailed to your address by express mail. mm DK OFO,1989 Cy. 5.37?) Best regards, NKT Engineering Martin W. Jensen PL LO 96 EP GP+ WOT BO'LZ°0T 96/80/70 :peatecey f ' | | | | NKT ¢ ENGINEERING AC Flat type submarine cable Straaded copper comdactor, Carbomized paper. Paper im scdaticn. Carbouized paper und screen of Al-foil. CX EX XN) PSN Lead alloy sheath FSS OSS - aS Layer of agghalt and two layers of Oil-inpregaated paper. Tyo layers of copper tapes. Comragated bronze tape on cach side. Copper wire. Asphalt, pol ypropyieee yarn, asphalt, bmpregasied crepe paper, seffsdhoxi we PB-ape, asphalt, polypropytene yarn and asphalt. Galvanized sicel wires. ‘Asphalt, polypropylene yarn, sapinali, Polypropyieas yarn taphak aed chalk. Journal 00: Al0S7 Edision: 0 Date: 08.02.96 enor ne neat ora ra cal Lonesre spot ose Migr rE ey eg Bie ae ea 22:91 96-20-80 LISEEESBTISTAS < ONIYTSNISNS LN ZB0S5 TLP°YN £9 RANG now Power Cable - Consultants, Inc. Torhes' Ashe 220 Sweetman Road, Ballston Spa, New York 12020-3211 phone 518-384-1613 * fax 518-399-9517 TELEFAX COPY Please deliver to: Mr. Bill Riall, Power Engineers, Hailey, ID Fax Number: 208-788-2082 Total # of Pages: 2 From: Torben Aabo Date: February 21, 1996 SEES U SS ESOS TSS SSESF TT EAEESUSSSES COSTE SSS SHS SLE CEEESREEES EES ESOS HESS ETE ET ORRSERSSS 9944998909955 50 CEREERREESEERED CSS 98 CONFIDENTIALITY NOTE: The information contained in this facsimile message is legally privileged and confidential information intended onty for the use of the individual or entity naoved above. If the reader of this messagr is not the intended recipient. you arc hereby notified that any disscrmination, distribution or copy of this fax is strictly prohibited [f you have received this fax in error, please immediately notify the sender at the telephone qumber provided above and retum the original message to 1s at the address above via the United Staiss Postal Service. Thank you. PCCM AHO SESS LE TEETSS > EEEROERESET SSO SSS TET EUEES PRRORERSEHETOS CETSOTS ONS HESTHSSEERCS ERED ERSESEHSSEEEHOEEOTOTEGENESS Dear Bill: The attached is a summary of the cost information I received from Nokia Cable. The submarine cable manufacturers are very slow in putting their costs together. Re wv Torben Aabo eae a1. L, Ea. Jl a , Power Cable Consultants, Inc. Chugach Cost Summary Submitted by Nokia Cables USA, Inc. 1,00 kcmil XLPE - Reduced insulation 1,000 kcmil XLPE - Full AEIC insulation Outdoor terminations Transition joint XLPE/SCFF XLPE Splice - Field molded XLPE X-bonded Splice - Field molded XLPE pre-molded XLPE pre-molded - X-bonding [Linkbox $27.75/f $32.56/ft $8,898 cach Link box Grounding box Note: These costs include delivery to Alaska and delivery duties paid (DDP) The costs are based on single circuit, 5 miles long Torben Aabo February 21, 1996 xipe-chu.cst Power Cable COPY Consultants, Inc. = Torben Aabo 220 Sweetman Road, Ballston Spa, New York 12026-3211 phone $18-384-1613 * fax 518-399-9517 TELEFAX = 2047) 7 2 Please deliver to: Mr. Bill Riall, Power Engineers, Hailey, ID Fax Number: 208-788-2082 Total # of Pages: 1 From: Torben Aabo Date: February 26, 1996 C8988 ORREREOEEEESE SES SRTTEETES ESE ESSOSETERE HERON ESSE Es EE SEREHNGHENSESSSOTSS EER PCERERESEESSSOSSERSESERELEOEEEKEESEE CONFIDENTIALITY NOTE: The information contained in this facsimile message is logally privileged and confidential information intended onty for the usc of the individual or entity named above. If the reader of this message is not the intended recipient, you arc hereby noufied that any disscrrnation, distribution or copy of this fax is stnctly prohibited If vou have reccived this fax in error, please immediately noufy the sender ot the telephone mumber provided above and return the original message to us at the address above via the United States Postal Service. Thank you. AOOEFOTS OOo SNPRRAEE OSS E DEST SERED ESEREEHS TOSSES OO RTERTS SHES ESTOONETRONR ESE SEEOESS EROFENAHSEHE SER ESSE CEST OREEEEES Dear Biil: NKT informed me that the cost of double armoring the 138 kV Flat Type SCFF cable will increase the cost in the order of 15 to 20 %. Based on this information, the cable cost for one foot of cable would be $173 to $180,_ NKT has not and do not have plans to research the development and testing of a 230 kV Flat Type SCFF cable construction. The NKT research efforts will continue to be in the HVDC area, focusing on voltages up to 600 kVDC. Regarding the other cable costs [ have promised you, I have made inquiries to the manufacturers again. Regards, D Torben Aabo TABLE UG04 - COST ESTIMATING INFORMATION LINK TE.A.10 COST SUMMARY 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. [MATERIAL LABOR |MATERIAL CABLE (ft) 107,712 $143 $53 $15,402.816 $5,708,736 | $21,111,552 TRENCH/BACKFILL (ft) 8,000 $0 $40 $0 $320,000 $320,000 GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 | $0 $290,000 $290,000 |SPLICE (1-PHASE) (ea) 0 $0 $0 | $0 $0 $0 | TERMINATIONS (1-PHASE) 8 $25.000 $4.000 | $200.000 $32,000 $232,000 ARRESTERS (ca) 8 L $3,000 $1,000 $24.000 $8,000 $32.000 MANHOLES (ea) 0 $0 | $0 $0 | $0 $0 SHEATH GROUNDING (ea) 8 $1,000 | $1,000 $8.000 | $8.000 | $16,000 SUBSTATION TERMINATION STRUCTURE 2 $13.000 | $7.000 $26.000 | $14,000 | $40,000 TRANSITION SITE (CIVIL: FIRE ISLAND) 1 $50,000 | $50,000 $50,000 | $50,000 | $100,000 | TRANSITION STRUCTURE (FIRE ISLAND) 1 $40,000 $20,000 $40,000 | $20,000 $60,000 TRANSITION FOUNDATION (FIRE ISLAND) 1 $200 $25,000 $200 | $25,200 HYDRAULIC RESEVOIRS 4 $35,000 $20,000 $140,000 $220,000 MOB/DEMOB 1 $250,000 $2,000,000 $250,000 $2,000,000 $2,250,000 SUB TOTALS ~ $16.141.016 $8,555,736 $24,696,752 ENGINEERING $550,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $740,903 TOTAL EMBEDED $26,025,155 LESS $14/CABLE FT. $1,507,968 TOTAL NON-EMBEDED $24,517,187 PEI-HLY 120293-01 (8:25 AM3/11/96) mh r:/WAR/CHUGACH/TESORO/2TEA10.XLS 1 TABLE UG04 TABLE UG09 - COST ESTIMATING INFORMATION LINK TE.E.50 COST ESTIMATE 4-230.KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS | TOTAL DESCRIPTION QTY. [MATERIAL LABOR [MATERIAL LABOR COST {CABLE (ft) [192,192 $143 | $53 $27,483,456 $10,186,176 | $37,669,632 TRENCH/BACKFILL (ft) [8,000 $0 | $40 $0 $320,000 $320,000 GEOTECH: Marine Survey, Strength/Thermal | LOT $0 | $290,000 $0 $290,000 $290,000 SPLICE (1-PHASE) (ea) 0 $0 | $0 $0 $0 $0 | TERMINATIONS (1-PHASE) | 8 $25,000 | $4,000 $200.000 $32,000 $232,000 | ARRESTERS (ea) 8 $3,000 | $1,000 $24,000 $8,000 $32,000 MANHOLES (ea) 0 $0 | $0 $0 $0 zt SHEATH GROUNDING (ca) I 8 $1,000 | $1,000 $8,000 $8,000 $16,000 SUBSTATION TERMINATION STRUCTURE 2 $13,000 | $7,000 $26,000 $14,000 $40,000 TRANSITION SITE (CIVIL: FIRE ISLAND) 1 $50.000 $50,000 $50,000 $50,000 $100,000 TRANSITION STRUCTURE (FIRE ISLAND) 1 | $40,000 $20,000 $40,000 ~ $20,000 $60,000 TRANSITION FOUNDATION (FIRE ISLAND) | $200 $25,000 | $200 $25,000 | $25,200 HYDRAULIC RESEVOIRS 4 $35,000 $20,000 | $140,000 $80,000 $220,000 MOB/DEMOB . 1 $250,000 $2,000,000 | $250,000 $2,000,000 $2,250,000 | SUB TOTALS $28,221,656 $13,033,176 $41,254,832 ENGINEERING . $550,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $1,237,645 TOTAL EMBEDED ~~ $43,079,977 | LESS $14/CABLE FT. $2,690,688 TOTAL NON-EMBEDED $40,389,289 PEI-HLY 120293-01 (8:27 AM3/11/96) mh : r:/WAR/CHUGACH/TESORO/2TEES0.XLS 1 TABLE UG09 TABLE UG26 - COST ESTIMATING INFORMATION LINK TE.F.60 COST ESTIMATE 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS DESCRIPTION | QTY. [MATERIAL LABOR [MATERIAL LABOR [CABLE (ft) | 198,528 $143 $28,389,504 $10,521,984 | $38,911,488 | TRENCH/BACKFILL (ft) | _ 8,000 $0 $40 $0 $320,000 $320,000 |GEOTECH: Marine Survey, Strength/Thermal | LOT _| $0 $290,000 $0 $290,000 $290,000 |SPLICE (1-PHASE) (ea) 0 | $0 $0 $0 | TERMINATIONS (1-PHASE) 4 | $25,000 $4,000 $100,000 $16,000 $116,000 | ARRESTERS (ca) : 4 | $3,000 | $1,000 $12,000 $4,000 $16,000 | MANHOLES (ea) 0 | $0 | $0 | $0 $0 $0 | SHEATH GROUNDING (ea) | 4 | $1.000 | $1,000 | $4.000 | $4.000 $8,000 SUBSTATION TERMINATION STRUCTURE 1 | $13,000 | $7.000 | $13,000 $7,000 $20,000 HYDRAULIC RESEVOIRS 2 | $35,000 $20,000 | $70.000 $40,000 $110,000 | MOB/DEMOB 1 | $250,000 $2.000,000 | $250,000 $2,000,000 $2,250,000 SUB TOTALS $28,838,504 $13,202,984 $42,041,488 ENGINEERING $550,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $1,261,245 TOTAL EMBEDED $43,890,233 LESS $14/CABLE FT. $2,779,392 TOTAL NON-EMBEDED $41,110,841 PEI-HLY 120293-01 (8:27 AM3/11/96) mh 1 TABLE UG26 r:/(WAR/CHUGACH/TESORO/2TEF60.XLS TABLE UG29 - COST ESTIMATING INFORMATION LINK TE.F.70 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System | UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION aa ieee | LABOR [MATERIAL LABOR COST CABLE (ft) 58,080 | $180 $53 | $10,454,400 $3,078,240 $13,532,640 TRENCH/BACKFILL (ft) 4,000 | $0 $40 $0 $160,000 $160,000 GEOTECH: Marine Survey, Strength/Thermal LOT | $0 | $290,000 $0 $290,000 $290,000 SPLICE (3-PHASE) (ea) 0 | $55,270 | $50,000 $0 $0 $0 TERMINATIONS (3-PHASE) 2 | $65,065 | $50,000 | $130,130 $100,000 $230,130 ARRESTERS (ea) 6 | $2.000 | $1,000 | $12,000 $6,000 $18,000 MANHOLES (ea) o | $0 $0 | $0 $0 $0 SHEATH GROUNDING (ea) 2 | $1.000 $1,000 | $2,000 $2,000 $4,000 SUBSTATION TERMINATION STRUCTURE 2 $13.000 | $7,000 | $26,000 $14,000 $40,000 HYDRAULIC RESEVOIRS 0 $0 $0 | $0 | $0 MOB/DEMOB 1 amet $2,000,000 | $250,000 $2,000,000 $2,250,000 SUB TOTALS $10.874,530 $5,650,240 $16,524,770 ENGINEERING $500,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $578,367 TOTAL EMBEDED $17,640,637 LESS $14/CABLE FT. $813,120 TOTAL NON-EMBEDED $16,827,517 PEI-HLY 120293-01 (8:00 PM3/10/96) mh r:/WAR/CHUGACH/KLATTPP/TEF70.XLS 1 TABLE UG29 TABLE UG31 - COST ESTIMATING INFORMATION LINK TE.F.70 COST ESTIMATE 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. MATERIAL LABOR MATERIAL LABOR COST CABLE (ft) 116,160 $143 $53 $16,610,880 $6,156,480 | $22,767,360 TRENCH/BACKFILL (ft) 8,000 $0 $40 | $0 $320,000 $320,000 GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 $0 $290,000 $290,000 SPLICE (1-PHASE) (ea) 0 $0 $0 $0 $0 | TERMINATIONS (1-PHASE) + $25,000 $4,000 $100,000 $16,000 $116,000 | ARRESTERS (ea) + $2,000 $1,000 $8,000 $4,000 $12,000 | MANHOLES (ca) 0 $0 $0 $0 | $0 | SHEATH GROUNDING (ea) 4 $1.000 $1,000 | $4.000 | $4,000 $8,000 | SUBSTATION TERMINATION STRUCTURE + $13,000 $7,000 $52,000 | $28,000 $80,000 | HYDRAULIC RESEVOIRS 2 $35,000 $20,000 $70,000 $40,000 $110,000 | MOB/DEMOB 1 $250,000 $2,000,000 $250,000 $2,000,000 $2,250,000 | SUB TOTALS $17,094,880 $8,858,480 $25,953,360 ENGINEERING j $550,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $778,601 TOTAL EMBEDED $27,319,461 LESS $14/CABLE FT. $1,626,240 TOTAL NON-EMBEDED $25,693,221 PEI-HLY 120293-01 (8:27 AM3/11/96) mh r:/WAR/CHUGACH/KLATTPP/2TEF70.XLS 1 TABLE UG31 TABLE UG07 - COST ESTIMATING INFORMATION LINKTE.E.50 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL MATERIAL LABOR COST CABLE (ft) 96,096 $180 $17,297,280 $5,093,088 $22,390,368 TRENCH/BACKFILL (ft) 4,000 $0 GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 $290,000 SPLICE (3-PHASE) (ea) 0 $55,270 $0 TERMINATIONS (3-PHASE) 4 [ $65,065 $260,260 $200,000 $460,260 ARRESTERS (ea) 12 $2,000 $24,000 $12,000 $36,000 MANHOLES (ea) $0 $0 SHEATH GROUNDING (ea) $1,000 $4,000 $4,000 $8,000 SUBSTATION TERMINATION STRUCTURE $13,000 $26,000 $14,000 $40,000 HYDRAULIC RESEVOIRS MOB/DEMOB ENGINEERING LAND SURVEY CONSTRUCTION MGMT. PEI-HLY 120293-01 {7:43 PM 3/10/96) br r:/WAR/CHUGACH/TESORO/TEESO.XLS TRANSITION SITE (CIVIL: FIRE ISLAND) TRANSITION STRUCTURE (FIRE ISLAND) TRANSITION FOUNDATION (FIRE ISLAND) $50,000 $40,000 $200 $0 $25,000 $0 —lofel—[—[rlelo $2,000,000 2 $250,000 SUB TOTALS $17,951,740 LOT 3.50% TOTAL EMBEDED LESS $14/CABLE FT. TOTAL NON-EMBEDED $50,000 $50,000 $20,000 $40,000 $20,000 | __ $25,000 | $2,000,000 $7,868,088 $250,000 $100,000 $60,000 $25,200 $2,250,000 $25,819,828 $500,000 $37,500 $903,694 $27,261,022 $1,345,344 $25,915,678 TABLE UGO7 TABLE UG02 - COST ESTIMATING INFORMATION LINK TE.A.10 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL COST DESCRIPTION QTY. LABOR MATERIAL LABOR [CABLE (ft) 53,856 $53 $9,694,080 $2,854,368 $12,548,448 TRENCH/BACKFILL (ft) 4,000 $40 $0 $160,000 $160,000 $290,000 | | (Eton GEOTECH: Marine Survey, Strength/Thermal $0 $290,000 $0 $290,000 SPLICE (3-PHASE) (ea) 0 | $55,270 $50,000 $0 $0 TERMINATIONS (3-PHASE) 4+. | $65,065 $50,000 $260.260 $200,000 $460,260 ARRESTERS (ea) 12 $2.000 $1,000 | $24,000 | $12,000 $36,000 MANHOLES (ea) 0 $0 | $0 | $0 $0 SHEATH GROUNDING (ea) 4 $1,000 $1,000 | $4,000 | $4,000 $8,000 SUBSTATION TERMINATION STRUCTURE 2 $13,000 $7,000 $26,000 | $14,000 $40,000 TRANSITION SITE (CIVIL: FIRE ISLAND) 1 $50,000 | $50,000 $50,000 | $50,000 | $100,000 [TRANSITION STRUCTURE (FIREISLAND) | ___1 $40,000 | $20,000 $40,000 | $20,000 | $60,000 TRANSITION FOUNDATION (FIRE ISLAND) | 1 $200 | $25,000 $25,000 $25,200 HYDRAULIC RESEVOIRS (toss $0 $0 $0 $0 [MOB/DEMOB [1 _[{___ $250,000 | __ $2,000,000 $250,000 | $2,000,000 $2,250,000 SUB TOTALS $10,348,540 $5,629,368 $15,977,908 ENGINEERING $500,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $559,227 TOTAL EMBEDED $17,074,635 LESS $14/CABLE FT. $753,984 TOTAL NON-EMBEDED $16,320,651 PEI-HLY 120293-01 (7:49 PM 3/10/96) br r:/WAR/CHUGACH/TESORO/TEA10.XLS 1 TABLE UG02 TABLE UG24 - COST ESTIMATING INFORMATION LINK TE.F.60 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System UNIT COSTS TOTAL DESCRIPTION MATERIAL MATERIAL LABOR COST CABLE (ft) $17,867,520 $5,260,992 $23,128,512 TRENCH/BACKFILL (ft) $0 $160,000 GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 $0 $290,000 $290,000 SPLICE (3-PHASE) (ea) 0 $55,770 | $50,000 | $0 | $0 $0 TERMINATIONS (3-PHASE) 2 L $65,065 $50,000 | $130,130 $100,000 $230,130 ARRESTERS (ea) 6 $2,000 $1,000 | $12,000 $6,000 MANHOLES (ea) 0 $0 SHEATH GROUNDING (ea) 2 $1.000 SUBSTATION TERMINATION STRUCTURE 1 $13,000 $7.000 $13.000 $20,000 HYDRAULIC RESEVOIRS 0 $0 $0 $0 $0 MOB/DEMOB 1 $250,000 $2,000,000 $250,000 $2,000,000 $2,250,000 SUB TOTALS $18,274,650 $7,825,992 $26,100,642 ENGINEERING $500,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $913,522 TOTAL EMBEDED "$27,551,664 LESS $14/CABLE FT. $1,389,696 TOTAL NON-EMBEDED $26,161,968 PEI-HLY 120293-01 (8:04 PM 3/10/96) br r:/WAR/CHUGACH/TESORO/TEF60.XLS 1 TABLE UG24 TABLE UGS5 - COST ESTIMATING INFORMATION LINK AN.70 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System q| UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL MATERIAL COST CABLE (ft) 117,216 $53 | $21,098,880 $6,212,448 $27,311,328 TRENCH/BACKFILL (ft) 4,000 $40 $0 | $160,000 $160,000 GEOTECH: Marine Survey, Strength/Thermal LOT $290,000 $0 $290,000 $290,000 | SPLICE (3-PHASE) (ea) 0 $55,270 $0 $0 $0 TERMINATIONS (3-PHASE) 2 $65,065 $50,000 $130,130 $100,000 $230,130 ARRESTERS (ea) 6 $1,000 $12,000 $6,000 $18,000 MANHOLES (ea) 0 $0 $0 | $0 | $0 $0 SHEATH GROUNDING (ea) 4 $1,000 $1,000 | $4,000 | $4,000 $8,000 SUBSTATION TERMINATION STRUCTURE 1 $13,000 $7,000 | $13,000 | $7,000 $20,000 HYDRAULIC RESEVOIRS | 0 $0 $0 | $0 | $0 $0 MOB/DEMOB 1 $250,000 $2,000,000 | $250,000 | $2,000,000 | $2,250,000 | SUB TOTALS $21,508,010 $8,779,448 $30,287,458 ENGINEERING $500,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $1,060,061 TOTAL EMBEDED $31,885,019 LESS $14/CABLE FT. $1,641,024 TOTAL NON-EMBEDED $30,243,995 PEI-HLY 120293-01 (8:07 PM3/10/96) mh r:/WAR/CHUGACH/KLATTPP/AN70.XLS 1 TABLE UGS55 TABLE UGS7 - COST ESTIMATING INFORMATION LINK AN.70 COST ESTIMATE 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL MATERIAL COST [CABLE (ft) 234,432 $143 | $53 | $33,523,776 | __ $12,424,896 TRENCH/BACKFILL (ft) 8,000 $0 | $40 | $0 GEOTECH: Marine Survey, Strength/Thermal LOT $0 | $290.000 | $0 SPLICE (1-PHASE) (ea) 0 $0 | $0 | $0 $of ss $0] TERMINATIONS (1-PHASE) 4 $25,000 | $4,000 | $100,000 $16,000 |ARRESTERS (ea) 4 $2,000 | $1,000 $8,000 MANHOLES (ca) 0 $0 | $0 $0 $0 SHEATH GROUNDING (ea) | 4 | $1,000 | $1,000 $4,000 {SUBSTATION TERMINATION STRUCTURE _| 1 | $13,000 | $7.000 $13,000 $7,000 $20,000 |HYDRAULIC RESEVOIRS | 2 | $35,000 | $20,000 $70,000 $40,000 $110,000 |MOB/DEMOB | | | $250,000 | __ $2,000,000 $250,000 $2,000,000 |__ $2,250,000 SUB TOTALS $33,968,776 $15,105,896 __ $49,074,672 ENGINEERING $550,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $1,472,240 TOTAL EMBEDED $51,134,412 LESS $14/CABLE FT. $3,282,048 TOTAL NON-EMBEDED $47,852,364 PEI-HLY 120293-01 (8:24 AM3/11/96) mh r:/WAR/CHUGACH/KLATTPP/2AN70.XLS 1 TABLE UG57 TABLE UG62 - COST ESTIMATING INFORMATION LINK AN.80 COST ESTIMATE 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. MATERIAL MATERIAL LABOR COST CABLE (ft) 238,656 $143 $34,127,808 $12,648,768 $46,776,576 TRENCH/BACKFILL (ft) 8,000 | $0 $40 $0 $320,000 $320,000 GEOTECH: Marine Survey, Strength/Thermal | LOT | $0 $290,000 $0 $290,000 $290,000 SPLICE (1-PHASE) (ea) | 0 | $0 $0 $0 $0 TERMINATIONS (1-PHASE) | 8 | $25,000 $4,000 $200,000 $32,000 $232,000 ARRESTERS (ea) | 8 | $2,000 $1,000 $16,000 $8,000 $24,000 MANHOLES (ea) | 0 | $0 $0 $0 $0 $0 SHEATH GROUNDING (ea) | 8 | $1,000 $1,000 $8.000 $8,000 $16,000 HYDRAULIC RESEVOIRS | 4 | $35,000 $20.000 | $140,000 $40,000 $180,000 [MOB/DEMOB | 1 | $250,000 $2.000,000 | $250,000] _ $2,000,000 $2,250,000 SUB TOTALS $34,741,808 $15,346,768 $50,088,576 ENGINEERING $1,100,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $1,502,657 TOTAL EMBEDED $52,728,733 LESS $14/CABLE FT. ‘ $3,341,184 TOTAL NON-EMBEDED $49,387,549 PEI-HLY 120293-01 (8:24 AM3/11/96) mh r:/WAR/CHUGACH/KLATTBI/2AN80.XLS 1 TABLE UG62 TABLE UG60 - COST ESTIMATING INFORMATION LINK AN.80 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System UNIT COSTS | EXTENDED COSTS DESCRIPTION QTY. |MATERIAL LABOR {MATERIAL CABLE (ft) [119,328 $180 $53 $21,479,040 $6,324,384 $27,803,424 TRENCH/BACKFILL (ft) | 4,000 $0 $40 | $0 $160,000 $160,000 |GEOTECH: Marine Survey, Strength/Thermal | LOT $0 $290,000 | $0 $290,000 |SPLICE (3-PHASE) (ca) [| 0 $55,270 $50,000 $0}| STE $0) | See SO} | TERMINATIONS (3-PHASE) 4 $65,065 $50,000 $260,260 $200,000 $460,260 ARRESTERS (ca) 12 $2,000 | $1,000 $24,000 $12,000 $36,000 MANHOLES (ea) 0 $0 | $0 $0 $0 $0 SHEATH GROUNDING (ca) 4 | $1,000 | $1.000 $4,000 $4,000 $8,000 HYDRAULIC RESEVOIRS | 0 | $0 | $0 $0 $0 $0 [MOB/DEMOB | 1 [ $250,000 | _ $2,000,000 $250,000 $2,000,000 $2,250,000 SUB TOTALS $22,017,300 $8,990,384 $31,007,684 ENGINEERING * $1,000,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $1,085,269 TOTAL EMBEDED $33,130,453 LESS $14/CABLE FT. $1,670,592 TOTAL NON-EMBEDED $31,459,861 PEI-HLY 120293-01 (8:14 PM 3/10/96) br r:/WAR/CHUGACH/KLATTBI/2AN80.XLS 1 i TABLE UG60 TABLE UG36 - COST ESTIMATING INFORMATION LINK EN.B.90 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL LABOR LABOR COST DESCRIPTION QTY. |MATERIAL CABLE (ft) 83,424 $15,016,320 $4,421,472 $19,437,792 TRENCH/BACKFILL (ft) 4.000 Rm $160,000 $160,000 GEOTECH: Marine Survey, Strength/Thermal LOT $290,000 $0 $290,000 $290,000 SPLICE (3-PHASE) (ea) | 0 $55,270 $50,000 $0 $0 TERMINATIONS (3-PHASE) | 4 | $65,065 $50,000 | $260.260 $200,000 $460,260 ARRESTERS (ea) | 12 $2,000 | $1,000 | $24.000 | $12,000 | $36,000 MANHOLES (ea) | 0 | $0 | $0 | $0 | $0 | $0 |SHEATH GROUNDING (ca) 4 $1,000 | $1,000 | $4.000 | $4,000 | $8,000 |SUBSTATION TERMINATION STRUCTURE 2 $13.000 | $7,000 | $26.000 | $14,000 | $40,000 HYDRAULIC RESEVOIRS 0 $0 $0 $0 MOB/DEMOB 1 $250,000 $2,000,000 $250,000 SUB TOTALS $15,580,580 $7,101,472 $22,682,052 ENGINEERING $1,000,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $793,872 TOTAL EMBEDED $24,513,424 LESS $14/CABLE FT. $1,167,936 TOTAL NON-EMBEDED $23,345,488 PEI-HLY 120293-01 (8:18 PM 3/10/96) br r:/WAR/CHUGACH/ENSTAR/2ENB90.XLS 1 TABLE UG36 TABLE UG38 - COST ESTIMATING INFORMATION LINK EN.B.90 COST ESTIMATE 4-230-KV Single Phase SCFF Cable System DESCRIPTION |CABLE (ft) UNIT COSTS EXTENDED COSTS TOTAL MATERIAL LABOR LABOR COST QTY. 166,848 $143 $53 $23,859,264 $8,842,944 $32,702,208 $40 $0 $320,000 $320,000 | TRENCH/BACKFILL (ft) 8.000 |GEOTECH: Marine Survey, Strength/Thermal LOT | __ $290,000 ss $0 | ~——$:290,000[ —_- $290,000 | SPLICE (1-PHASE) (ea) 0 je 180 fe S080) TERMINATIONS (1-PHASE) 8 $200,000 $32,000 $232,000 ARRESTERS (ca) | 8 $24,000 $8,000 | $32,000 MANHOLES (ea) | 0 $0 | $0 SHEATH GROUNDING (ca) | 8 $1,000 | $1,000 | $8,000 $8,000 $16,000 | SUBSTATION TERMINATION STRUCTURE __| 2 $13,000 | $7,000 | $26,000 | $14,000 $40,000 HYDRAULIC RESEVOIRS | 4 $35,000 | $20,000 $140,000 | $80,000 MOB/DEMOB | I $250,000 | __ $2,000,000 $250,000 | __ $2,000,000 SUB TOTALS $24,507,264 $11,594,944 $36,102,208 ENGINEERING $1,100,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% : $1,083,066 TOTAL EMBEDED "$38,322,774 LESS $14/CABLE FT. $2,335,872 TOTAL NON-EMBEDED $35,986,902 PEI-HLY 120293-01 (8:24 AM3/11/96) mh r:/(WAR/CHUGACH/ENSTAR/2ENB90.XLS 1 TABLE UG38 TABLE UG47 - COST ESTIMATING INFORMATION LINK QC.D.1.B.10 COST ESTIMATE 2 - 138 KV Three Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. ae | LABOR COST CABLE (ft) 42,240 | $180 | $7,603,200 $2,238,720 $9,841,920 TRENCH/BACKFILL (ft) 4,000 | $0 | $40 $0 | $160,000 $160,000 GEOTECH: Marine Survey, Strength/Thermal Lona] $0 | $290,000 $0 | a i$0) SPLICE (3-PHASE) (ea) 0 | $55,270 | $50,000 $0 | $0 TERMINATIONS (3-PHASE) 4 | $65.065 $50,000 $260,260 | $200,000 $460,260 ARRESTERS (ca) 12 | $2,000 $24,000 | $12,000 $36,000 MANHOLES (ea) 0 $0 | $0 $0 | $0 SHEATH GROUNDING (ea) 4 $1,000 $1.000 $4.000 | $4.000 $8,000 SUBSTATION TERMINATION STRUCTURE 2 $13,000 $7,000 $26,000 | $14,000 $40,000 HYDRAULIC RESEVOIRS 0 $0 $0 $0 | $0 MOB/DEMOB I $250,000 $2,000,000 | $250,000 | _ $2,000,000 $2,250,000 SUB TOTALS $8.167,460 $4,628,720 $12,796,180 ENGINEERING $1,000,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $447,866 TOTAL EMBEDED $14,281,546 LESS $14/CABLE FOOT $591,360 TOTAL NON-EMBEDED _ $13,690,186 PEI-HLY 120293-01 (8:22 PM3/10/96) mh r:/WAR/CHUGACH/BIRD/2QCD1B10.XLS 1 TABLE UG47 TABLE UG49 - COST ESTIMATING INFORMATION LINK QC.D.1.B.10 COST ESTIMATE 138 KV Three Phase High Pressure Gas Filled Cable System DESCRIPTION MATERIAL UNIT COSTS MATERIAL EXTENDED COSTS TOTAL ] COST CABLE (ft) | 63,360 $1,077,120 $316,800 $1,393,920 | DIRECT DRILLING (ft) | 21,120 $6,336,000 $6,336,000 |GEOTECH: Marine Survey, Strength/Thermal | LOT $290,000 $0 $290,000 $290,000 |SPLICE (3-PHASE) (ea) | 5) $5,500 $20,000 $27,500 $100,000 $127,500 | TERMINATIONS (3-PHASE) 6 | $13,000 $8,000 $78,000 $48,000 $126,000 ARRESTERS (ea) 6 | $2,000 $1,000 $12,000 $6,000 $18,000 COATED PIPE 21120 | $35 $10 $739.200 $211,200 $950,400 CATHODIC PROTECTION 2 | $35,000 $20,000 $70,000 $40,000 $110,000 SUBSTATION TERMINATION STRUCTURE 2 | $13,000 | $7.000 $26.000 $14,000 $40,000 |MANHOLES (ea) 4+ | $30.000 | $20,000 $120,000 $80,000 $200,000 PRESSURIZATION SYSTEM | 1 $50,000 | $20,000 $50,000 $20,000 $70,000 MOB/DEMOB | 1 $250,000 | $2,000,000 $250,000 | $2.000,000 $2,250,000 SUB TOTALS $2,449,820 $9,462,000 $11,911,820 ENGINEERING $1,000,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $416,914 TOTAL $13,366,234 PEI-HLY 120293-01 (8:22 PM 3/10/96) br r:/WAR/CHUGACH/BIRD/2QCD1B10.XLS 2 TABLE UG49 TABLE UGS0 - COST ESTIMATING INFORMATION LINK QC.D.1.B.10 COST ESTIMATE 4 - 230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS |] TOTAL DESCRIPTION QTy. [MATERIAL LABOR —_|MATERIAL LABOR | COST CABLE (ft) | 84,480 $143 | $53 $12,080,640 $4,477,440 | $16,558,080 TRENCH/BACKFILL (ft) 8,000 $0 | $40 $0 $320,000 | $320,000 GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 $0 $290,000 | $290,000 SPLICE (1-PHASE) (ea) 0 $0 $0 $0 $0 $0 TERMINATIONS (1-PHASE) 8 $25,000 $4,000 $200,000 | $32,000 $232,000 ARRESTERS (ea) 8 | $3,000 $1.000 $24.000 | $8,000 $32,000 |MANHOLES (ca) 0 | $0 $0 $0 | $0 | $0 SHEATH GROUNDING (ea) 8 | $1,000 $1,000 $8.000 | $8,000 | $16,000 SUBSTATION TERMINATION STRUCTURE 2 | $13,000 $7,000 $26,000 | $14,000 | $40,000 HYDRAULIC RESEVOIRS 4 | $35,000 $20,000 $140,000 | $80,000 $220,000 MOB/DEMOB | 1 | $250,000 $2,000,000 $250,000 | $2,000,000 $2,250,000 SUB TOTALS $12,728,640 $7,229,440 $19,958,080 ENGINEERING $1,100,000 LAND SURVEY $37,500 CONSTRUCTION MGMT. 3.00% $598,742 TOTAL EMBEDED $21,694,322 LESS $14/CBLE FT. $1,182,720 TOTAL NON-EMBEDED $20,511,602 PEI-HLY 120293-01 (8:25 AM3/11/96) mh r:/WAR/CHUGACH/BIRD/2QCD1B10.XLS 1 TABLE UGS50 TABLE UG33 - COST ESTIMATING INFORMATION LINK TE.I.100 COST ESTIMATE Single Circuit 138 KV Single Phase XLPE Cable System UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. |MATERIAL] LABOR [MATERIAL CABLE (ft) 72,864 $38 $5 | $2,768,832 | $364,320 | $3,133,152 CONCRETE (cu yds) 3598 $120 $150] —__$431.774 | $539,718 [$971,492 TRENCH/BACKFILL (ft) 24,288 $0 $40 | $0] $971,520 | $971,520 CONDUIT (fi.) 97,152 $2 $1] $194.304 $97,152 | $291,456 GROUNDING CONDUCTOR 24.288 $2 $1 $48,576 $24,288 $72,864 GEOTECH: Strength/Thermal -| 1 $0 $50,000 $0 $50,000 $50,000 SPLICE (1-PHASE) OPEN SHEATH (ca) 18 $9.950 | _$5.000 $179.100 $90,000 | $269,100 SPLICE (1-PHASE) CLOSED SHEATH (ca) 36 $7.725 $5.000 $278.100 | $180,000 TERMINATIONS (1-PHASE) 6 $8.877 | $4,000 $53.262 $24,000 ARRESTERS (ea) 6 $2.000 | __$1.000 $12.000 $6,000 $18,000 MANHOLES (ca) 18 $25,000 | _$12.000 $450.000 [ $216,000 | $666,000 GROUNDING X-BONDING 12 $6,350 | $2,000 | $76,200 $24,000 | __ $100,200 GROUNDING LINK BOXES 2 $2,250 TRANSITION SITE (CIVIL) 2 $50,000 | $50,000 : TERMINATION STRUCTURES (ca) 2 $40,000 | _$20.000 | , i TERMINATION FOUNDATIONS (cu yds) 26 $200 | $25,000 | : PAVEMENT RESTORATION (sq yds) 0 $0 $0 MOB/DEMOB 1 $50,000 SUB TOTALS $4,681,848 $2,830,998 $7,512,846 ENGINEERING 6.50% $488,335 LAND SURVEY LOT $92,000 CONSTRUCTION MGM 7.00% $525,899 CONTINGENCY 10.00% * $861,908 TOTAL — $9,480,989 PEI-HLY (3/11/9610:05 AM) 120293-01 br 5 r:/WAR/CHUGACH/KLATTPP/TEI100.XLS 1 TABLE UG33 TABLE UG34 - COST ESTIMATING INFORMATION LINK TE.I.100 COST ESTIMATE Single Circuit 230 KV Single Phase XLPE Cable System DESCRIPTION UNIT COSTS MATERIAL] LABOR [MATERIAL COST EXTENDED COSTS TOTAL CABLE (ft) 72,864 $5 [ _$3.861.792 | $364,320 | $4,226,112 CONCRETE (cu yds) 3598 $150 $431,774 | $539,718 | $971,492 TRENCH/BACKFILL (ft) 24.288 $30 $0 | $728,640 | $728,640 CONDUIT (fi.) 97.152 $1 $194,304 $97,152 | $291,456 GROUNDING CONDUCTOR 24.288 =o $48,576 $24,288 $72.864 GEOTECH: Strength/Thermal at $50.000 $0 $50,000 $50,000 SPLICE (1-PHASE) OPEN SHEATH (ca) 18 $16.745 | $15.000 $301.410 | $270,000 | $571.410 36 $13.000 | $15,000 $468.000 | $540,000 TERMINATIONS (1-PHASE) 6 $22.000 $4.000 $132.000 ARRESTERS (ca) 6 $3.000 $1.000 $18,000 MANHOLES (ea) 18 $25,000 | _ $12,000 $450,000 GROUNDING X-BONDING 12 $6,350 $2,000 GROUNDING LINK BOXES 2 $2,250 $2,000 $4,500 TRANSITION SITE (CIVIL) 2 $50,000 ERMINATION STRUCTURES (ea) 2 $49,000 | $20,000 x TERMINATION FOUNDATIONS (cu yds) 26 $200 | $25,000 3 PAVEMENT RESTORATION (sq yds) 0 $0 $0 $0 go] $0 | MOB/DEMOB 1 $0 { $50,000 $0 SUB TOTALS $6,171,756 _ $3,128,118 $9,299,874 ENGINEERING 6.50% $604,492 LAND SURVEY LOT $92,000 CONSTRUCTION MGM 7.00% $650,991 CONTINGENCY 10.00% $1,064,736 , TOTAL $11,712,093 PEI-HLY (3/11/9610:05 AM) 120293-01 br r:/WAR/CHUGACH/KLATTPP/TEI100.XLS TABLE UG34 TABLE UG16 - COST ESTIMATING INFORMATION LINK TE.B.15 COST ESTIMATE Single Circuit 138 KV Single Phase XLPE Cable System $15,000 UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL] LABOR pisaise LABOR COST CABLE (ft) 61.776 $38 $5 | $2,347,488 | _$308.880 | $2,656,368 CONCRETE (cu yds) 3051 | $120 | $150 $366.070 | $457.587 | $823.657 TRENCH/BACKFILL (ft) 20.592 | $0 | $40 $0 | $823.680 $823.680 CONDUIT (ft.) 82.368 | $2 $1 $164.736 $82,368 | $247,104 GROUNDING CONDUCTOR 20.592 $2 $1 $41,184 $20,592 $61.776 GEOTECH: Strength/Thermal $0 $40.000 $0 $40,000 $40.000 $179.100 $270,000 $449.100 SPLICE (1-PHASE) CLOSED SHEATH (ca) $15,000 $278.100 | $540,000 $818,100 | | SPLICE (1-PHASE) OPEN SHEATH (ea) | | : | TERMINATIONS (1-PHASE) 6 $8.877 | __ $4.000 $53,262 | __ $24,000 $77,262 ARRESTERS (ea) 6 $2,000 | _ $1,000 $12.000 | $6,000 $18,000 MANHOLES (ca) 18 $25,000 | $12,000 $450,000 | $216,000] $666,000 GROUNDING X-BONDING 12 $6.350 | $2,000 $76.200 | _ $24,000 | __ $100,200 GROUNDING LINK BOXES 2 $2,250 | $2,000 $4,000 $8,500 TRANSITION SITE (CIVIL) 2 $50,000 | $50,000 $100,000 | $100,000 | $200,000 TERMINATION STRUCTURES (ca) 2 $40,000 | $20,000 $80.000 $40,000 | $120,000 TERMINATION FOUNDATIONS (cu yds) 26 $200 | $25,000 $5,200 $50,000 PAVEMENT RESTORATION (sq yds) 9152 $10 $91,520 $91.520 MOB/DEMOB 1 | $50,000] $0 |__$50,000 | __ $50,000 | SUB TOTALS $4,249,360 $3,148,627 _ $7,397,987 ENGINEERING 6.50% $480,869 LAND SURVEY LOT $78,000 CONSTRUCTION MGM 7.00% $517,859 CONTINGENCY 10.00% $847,471 TOTAL $9,322, 186 PEI-HLY (3/11/9610:06 AM) 120293-01 br r:/WAR/CHUGACH/KLATTPP/TEBI5.XLS TABLE UG16 TABLE UGI17 - COST ESTIMATING INFORMATION LINK TE.B.15 COST ESTIMATE Single Circuit 230 KV Single Phase XLPE Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION MATERIAL] LABOR [MATERIAL LABOR COST CABLE (ft) $53 $5] $3.274.128 | $308,880 | $3,583,008 CONCRETE (cu vds) $120 | $150 $366.070 | $457,587 | $823,657 TRENCH/BACKFILL (fi) 20,592 $0) $40 $0 | $823,680 | $823,680 CONDUIT (fi.) 82,368 $2 $1 $164.736 $82,368 | $247,104 GROUNDING CONDUCTOR 20.592 | $2 $1 $41,184 $20.592 $61.776 GEOTECH: Strength/Thermal $0 | $40.000 $0 $40,000 $40,000 SPLICE (1-PHASE) OPEN SHEATH (ea) $16.745 | $5.000 | $301,410 $90.000 | $391,410 SPLICE (1-PHASE) CLOSED SHEATH (ca) $13.000 | $5.000 $468.000 | $180,000 | $648,000 TERMINATIONS (1-PHASE) $22.000 | $4.000 $132.000 $24.000 | $156,000 ARRESTERS (ca) $3,000 | _ $1,000 $18,000 $6,000 $25,000 | $12,000 $450,000 | $216,000 GROUNDING X-BONDING $2,000 $76,200 $24.000 | $100,200 TRANSITION SITE (CIVIL) 2 $50.000 | $50,000 $100,000 | $100.000 | $200,000 TERMINATION STRUCTURES (ea) $20.000 $80,000 $40,000 | $120,000 TERMINATION FOUNDATIONS (cu yds) $25.000 $5,200 $50,000 $55,200 PAVEMENT RESTORATION (sq yds) $10 $91,520 $91,520 | $183,040 MOB/DEMOB $50,000 $0 | $50,000 $50,000 SUB TOTALS $5,572,948 $2,608,627 $8,181,575 ENGINEERING 6.50% $531,802 LAND SURVEY LOT $78,000 CONSTRUCTION MGM 7.00% $572,710 CONTINGENCY 10.00% $936,409 TOTAL __ $10,300,496 PEI-HLY (3/11/9610:06 AM) 120293-01 br r:/WAR/CHUGACH/KLATTPP TEBI5.XLS TABLE UGI17 TABLE UG40 - COST ESTIMATING INFORMATION LINK EN.D.100 COST ESTIMATE Single Circuit138 KV Single Phase XLPE Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL | LABOR |MATERIAL LABOR COST CABLE (ft) $38 $3.190.176 $419,760 | $3,609,936 CONCRETE (cu yds) 4146 $120 TRENCH/BACKFILL (ft) 27,984 $0 CONDUIT (fi.) 111,936 $2 $497.479 $40 $1 $223,872 $621,849 $1,119,360 $111,936 $1,119,328 $1,119,360 $335,808 GROUNDING CONDUCTOR $2 $55,968 $27.984 $83,952 GEOTECH: Strength/Thermal $0 | $52.800 $52.800 $52.800 SPLICE (1-PHASE) OPEN SHEATH (ca) $9.950 $5.000 $179,100 $90,000 $269,100 SPLICE (1-PHASE) CLOSED SHEATH (ca) TERMINATIONS (1-PHASE) ARRESTERS (ca) $5.000 $4,000 $1,000 $278. 100 $53.262 $12,000 $180,000 $24,000 $6,000 $458.100 $77,262 $18,000 $2,000 MANHOLES (ca) $12.000 $450.000 $216,000 $666,000 GROUNDING X-BONDING $2,000 | $76.200 $24,000 $100,200 GROUNDING LINK BOXES $2,000 $4,500 $4,000 $8,500 TRANSITION SITE (CIVIL) ; $100,000 $100,000 $200,000 TERMINATION STRUCTURES (ea) | 2 | $40,000] $20.000 $80,000 $120,000 $50,000 f TERMINATION FOUNDATIONS (cu yds) $200 | $25,000 $5,200 $55,200 PAVEMENT RESTORATION (sq yds) ee $0 so{ sof 80 | MOB/DEMOB | 1 | sof $50,000[ $0 $50,000 $50,000 SUB TOTALS $5,205,857 $3,137,689 $8,343,546 ENGINEERING 6.50% $542,331 LAND SURVEY LOT $100,000 CONSTRUCTION MGM 7.00% $584,048 CONTINGENCY 10.00% $956,992 TOTAL $10,526,917 PEI-HLY (3/11/9610:07 AM) 120293-01 br r:/WAR/CHUGACH/KLATTBVEND100.XLS 1 TABLE UG40 TABLE UG41 - COST ESTIMATING INFORMATION LINK EN.D.100 COST ESTIMATE Single Circuit 230 KV Single Phase XLPE Cable System UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. [MATERIAL | LABOR |MATERIAL LABOR CABLE (fi) 83.952 $53 $5 $4,449,456 $419,760 CONCRETE (cu yds) 4146 $120 $150 $497.479 $621,849 | $1,119,328 TRENCH/BACKFILL (fi) 27.984 $0 $30 $0 $839,520 $839,520 CONDUIT (fi.) 111.936 $2 $1 $223.872 $111,936 $335,808 GROUNDING CONDUCTOR 27.984 $2 $1 $55,968 $27.984 $83,952 GEOTECH: Strength/Thermal 1 $0 | $52.800 $0 $52.800 $52,800 SPLICE (1-PHASE) OPEN SHEATH (ca) 18 $16.745 | $15.00 $301.410 $270,000 [$571,410 SPLICE (1-PHASE) CLOSED SHEATH (ca) 36 $13,000 | $15,000 $468.000 $540,000 | _$1.008.000 TERMINATIONS (1I-PHASE) 6 $22.000 | $4.00 $132,000 $24,000 $156,000 ARRESTERS (ca) 6 $3,000 | $1.000 $18,000 $6,000 $24,000 MANHOLES (ea) $25.000 | _$12.000 $450.000 $216,000 $666,000 GROUNDING X-BONDING $6.350 | _$2.000 $76,200 $24,000 $100,200 GROUNDING LINK BOXES $2,250 | $2,000 $4,500 $8,500 | TRANSITION SITE (CIVIL) $50,000 | $50.000 $100,000 [TERMINATION STRUCTURES (ea) $40.000 | $20,000 $80,000 $40,000 $120,000 TERMINATION FOUNDATIONS (cu yds) 26 $200 | $25,000 $5,200 $50,000 $55,200 PAVEMENT RESTORATION (sq yds) 0 $0 $0 $0 $o] ss MOB/DEMOB 1 $0 | $50,000 $0 $50,000 SUB TOTALS $6,862,085 $3,397,849 _ $10,259,934 ENGINEERING 6.50% $666,896 LAND SURVEY LOT $100,000 CONSTRUCTION MGM 7.00% $718,195 CONTINGENCY 10.00% $1,174,503 TOTAL $12,919,528 PEI-HLY (3/11/9610:07 AM) 120293-01 br r:/WAR/CHUGACH KLATTBI/END100.XLS TABLE UG+41 TABLE UG42 - COST ESTIMATING INFORMATION LINK EN.B.80 COST ESTIMATE Single Circuit 138 KV Single Phase XLPE Cable System UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. [MATERIAL] LABOR |MATERIAL LABOR CABLE (fi) 36.432 $1,384.416 | _ $182,160 | $1,566,576 CONCRETE (cu yds) 1799 $215.887 | _ $269.859 | $485,746 TRENCH/BACKFILL (ft) 12.144 $0 | $485,760 | $485,760 CONDUIT (ft) 48.576 $97.152 $48.576 | _ $145,728 GROUNDING CONDUCTOR 12.144 $24,288 $12,144 $36,432 GEOTECH: Strength/Thermal $25.000 $0 $25.000 $25,000 SPLICE (1-PHASE) OPEN SHEATH (ca) 12 $5,000 $119.400 $60,000 | $179,400 SPLICE (1-PHASE) CLOSED SHEATH (ca) 12 $5.000 $92.700 | $60,000 | _ $152,700 | TERMINATIONS (1-PHASE) 6 $4,000 $53.262 $24.000 $77,262 ARRESTERS (ca) 6 $2.000 | __$1.000 $12.000 $6,000 $18,000 | MANHOLES (ca) 8 $25,000 | _ $12,000 $200.000 | __ $96,000 | __ $296,000 GROUNDING X-BONDING 4 $6.350 | _$2.000 $25,400 $8,000 sao] GROUNDING LINK BOXES 2 $2,250 | $2,000 $4.500 $4.000 | __ $8.500 TRANSITION SITE (CIVIL) 2 $50,000 | _$50.000 $100,000 | $100,000 | $200,000 TERMINATION STRUCTURES ,a) 2 $40,000 | $20,000 $80.000 | : TERMINATION FOUNDATIONS (cu yds) 26 $200 | _$25,000 $5,200 | ___ $50.000 $55,200 PAVEMENT RESTORATION (sq yds) 0 $0 $0 $0 $0 $0 | MOB/DEMOB 1 $0 | $50,000 $0] $50,000 | $50,000 | SUB TOTALS $2,414,205 $1,521,499 $3,935,704 ENGINEERING 6.50% $255,821 LAND SURVEY LOT $46,000 CONSTRUCTION MGM 7.00% $275,499 CONTINGENCY 10.00% $451,302 ee TOTAL $4,964,327 PEI-HLY (3/11/9610:08 AM) 120293-01 br r:/WAR/CHUGACH ENSTAR/ENB80.XLS TABLE UG42 TABLE UG43 - COST ESTIMATING INFORMATION LINK EN.B.80 COST ESTIMATE Single Circuit 230 KV Single Phase XLPE Cable System DESCRIPTION UNIT COSTS EXTENDED COSTS QTY. EEE LABOR |MATERIAL $182,160 CABLE (ft) 36,432 $53 $5 | $1,930,896 $2,113,056 CONCRETE (cu yds) 1799 | $120 $150 $215.887 | $269.859 $485,746 TRENCH/BACKFILL (ft) 12,144 | $0 $40 $0 | $485,760 | $485,760 CONDUIT (fi.) 48.576 $2 $1 | $97.152 $48,576 $145,728 | GROUNDING CONDUCTOR [12.144 $2 $1 $24.288 $12,144 $36,432 GEOTECH: Strength/Thermal 1 $0 $25.000 $0 $25,000 $25,000 [SPLICE (1-PHASE) OPEN SHEATH (ea) 12 $16.745 | $15,000 $200.940 | $180,000 $380,940 SPLICE (1-PHASE) CLOSED SHEATH (ea) 12 $13.00 | $15,000 $156.000 | $180,000 $336.000 TERMINATIONS (1-PHASE) 6 $22.000 $4.000 $132.000 $24.000 $156,000 ARRESTERS (ea) 6 $3.000 $1.000 $18.000 $6,000 $24,000 MANHOLES (ea) 8 $25.000 | _$12.000 $200.000 $96,000 $296,000 GROUNDING X-BONDING 4 $6,350 $2.000 $25.400 $33,400 GROUNDING LINK BOXES 2 $2,250 $2.000 $4.500 $8,500 TRANSITION SITE (CIVIL) 2 $50,000 | _$50.000 $100,000 | $100,000 $200.000 TERMINATION STRUCTURES (ca) 2 $40,000 | $29.000 $80,000 $40,000 TERMINATION FOUNDATIONS (cu yds) 26 $200 | $25,000 $5.200 $55,200 PAVEMENT RESTORATION (sq yds) 0 $0 $0 $0 MOB/DEMOB 1 $0 | $50,000 $50,000 $50,000 SUB TOTALS $3.190,263 $1,761,499 $4,951,762 ENGINEERING 6.50% $321,865 LAND SURVEY LOT $46,000 CONSTRUCTION MGM 7.00% $346,623 CONTINGENCY 10.00% $566,625 ; TOTAL $6,232,875 PEI-HLY (3/11/9610:08 AM) 120293-01 br r:/WAR/CHUGACH/ENSTAR/ENB80.XLS TABLE UG43 TABLE UG44 - COST ESTIMATING INFORMATION LINK EN.B.70 COST ESTIMATE Single Circuit 138 KV Single Phase XLPE Cable System PEI-HLY (3.11/9610:08 AM) 120293-01 br r:/WAR/CHUGACH/ENSTAR/ENB70.XLS UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL] LABOR |MATERIAL COST CABLE (fi) 44,352 $5 $1,685,376 $221,760 | $1,907,136 CONCRETE (cu yds) 2190 $150 $262.819 $328,524 $591,343 TRENCH/BACKFILL (ft) | 14.784 $0 | $40 $0 $591,360 | _$591.360 CONDUIT (ft.) [59.136 $2 $1 $118,272 $59,136 $177.408 GROUNDING CONDUCTOR 14.784 $2 $1 $29.568 $14.784 $44.352 GEOTECH: Strengtl/Thermal | $0 | _$30.000 $0 $30.000 $30.000 [SPLICE (1-PHASE) OPEN SHEATH (ca) 12 $9.950 $5.000 $119,400 $60.000 $179.400 SPLICE (1-PHASE) CLOSED SHEATH (ea) 12 $7.725 $5,000 $92.700 $60.000 | $152.700 | TERMINATIONS (1-PHASE) | 6 $8.877 $4.000 $53,262 $24.000 $77.262 ARRESTERS (ea) | 6 $2.000 $1,000 $12,000 | $6,000 $18,000 MANHOLES (ea) 8 $25,000 $12.000 $200,000 | $96,000: $296,000 GROUNDING X-BONDING 4 $6,350 $2.000 $25.400 | $8,000 $33,400 GROUNDING LINK BOXES 2 $2.250 $2.000 $4.500 | $4,000 $8.500 TRANSITION SITE (CIVIL) 2 $50,000 | $50,000 $100,000 $100.000 $200,000 TERMINATION STRUCTURES (ea) 2 7 $40.000 $20.000 $80.000 $40,000 TERMINATION FOUNDATIONS (cu yds) 26 | $200 | $25.000 $50,000 $55,200 PAVEMENT RESTORATION (sq yds) 0 | $0 $0 $0 $0 | MOB/DEMOB 1 | $0 | $50,000 $50,000 $50.000 SUB TOTALS $2,788,497 $1,743,564 $4,532,061 ENGINEERING 6.50% $294,584 LAND SURVEY LOT $56,000 CONSTRUCTION MGM 7.00% $317,244 CONTINGENCY 10.00% $519,989 TOTAL $5,719,878 TABLE UG44 TABLE UG45 - COST ESTIMATING INFORMATION LINK EN.B.70 COST ESTIMATE Single Circuit 230 KV Single Phase XLPE Cable System UNIT COSTS MATERIAL} LABOR EXTENDED COSTS MATERIAL LABOR TOTAL COST DESCRIPTION CABLE (ft) E $5 [ $2.350,656 | _$221.760 | $2,572,416 CONCRETE (cu yds) 2190 $120 $150 $262.819 | $328.524] $591.343 | TRENCH/BACKFILL (ft) 14.784 $0 $40 $0 [| $591,360 | $591,360 CONDUIT (fi.) 59.136 | $2 $1 | $118.272 $59,136 | _$177.408 GROUNDING CONDUCTOR 14.784 $2 $1 $29.568 $14.784 $44.352 GEOTECH: Strength/Thermal 1 $0 $25.000 $0 $25.000 $25.000 SPLICE (1-PHASE) OPEN SHEATH (ea) 12 $16.745 | $15.000 $200.940 | $180.000 | $380.940 {SPLICE (1-PHASE) CLOSED SHEATH (ca) 12 $13,000 | $15.000 $156.000 | $180,000 | $336.000 TERMINATIONS (1-PHASE) | $22.000 | $4.000 | $132.000 | $24.000 | $156.000 ARRESTERS (ea) $1.000 | $18.000 | $6.000 | $24.000 MANHOLES (ea) $12.000 | $200.000 $96.000 | _ $296.000 GROUNDING X-BONDING $2.000 $25,400 $8.000 $33.400 $4.500 | $4.000 $100,000 | $100,000 $40.000 $50.000 $0 $50,000 $8.500 | $200,000 $120,000 $55,200 GROUNDING LINK BOXES TRANSITION SITE (CIVIL) $50.000 $20.000 $25.000 $0 $50,000 PAVEMENT RESTORATION (sq yds) _ MOB/DEMOB $0 SUB TOTALS $3,683,355 $1,978,564 $5,661,919 ENGINEERING 6.50% $368,025 LAND SURVEY LOT $56,000 CONSTRUCTION MGM 7.00% $396,334 CONTINGENCY 10.00% $648,228 TOTAL _ $7,130,506 PEI-HLY (3/11/9610:08 AM) 120293-01 br r: WAR/CHUGACH ENSTAR ENB70.XLS 2 TABLE UG45 TABLE UGS2 - COST ESTIMATING INFORMATION LINK AN.30 COST ESTIMATE Single Circuit]38 KV Single Phase XLPE Cable System UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. CABLE (ft) 6.336 $5 $240,768 $31,680 CONCRETE (cu yds) 313 50 $37.546 $46,932 $84,478 | TRENCH/BACKFILL (fi) 2.112 $40 CONDUIT (ft.) 8.448 $1 $16.896 $8.448 $25,344 GROUNDING CONDUCTOR 2.112 $2 $I $4.224 $2,112 $6.336 GEOTECH: Strength/Thermal | $0 | $15,000 $0 $15.000 $15,000 SPLICE (1-PHASE) OPEN SHEATH (ca) 3 $9.950 | $5,000 $29.850 $15.000 sr SPLICE (1-PHASE) CLOSED SHEATH (ea) 0 $7.725 | $5,000 $0 $0 $0 TERMINATIONS (1-PHASE) 6 $8.877 | _$4.000 $53.262 $24.000 | $77,262 ARRESTERS (ca) 6 $2.000 | $1,000 $12.000 $18,000 MANHOLES (ea) 1 $25,000 | $12.000 $25.000 $12,000 $37.000 GROUNDING X-BONDING 0 $6.350 $0 $0 $0 | GROUNDING LINK BOXES 1 $2,250 $2,250 $2,000 $4,250 TRANSITION SITE (CIVIL) 2 $50.000 | $50,000 $100.000 $100,000 $200,000 TERMINATION STRUCTURES (ca) 2 $40.000 | $20,000 $80.000 | __ "$40,000 $120,000 TERMINATION FOUNDATIONS (cu yds) 26 $200 | $25,000 $5,200 $50,000 $55,200 PAVEMENT RESTORATION (sq yds) 0 $0 $0 $0 MOB/DEMOB 1 $0 | $50,000 $50,000 $50,000 SUB TOTALS $606,996 $487,652 $1,094,648 ENGINEERING 6.50% $71,152 LAND SURVEY LOT $16,000 CONSTRUCTION MGM 7.00% $76,625 CONTINGENCY 10.00% $125,843 TOTAL $1,384,268 PEI-HLY (3/11/9610:08 AM) 120293-01 br rt, WAR/CHUGACH KLATTBIAN30.XLS 1 TABLE UGS52 TABLE UGS3 - COST ESTIMATING INFORMATION LINK AN.30 COST ESTIMATE Single Circuit 230 KV Single Phase XLPE Cable System | UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. |MATERIAL | LABOR [MATERIAL CABLE (ft) $31,680 $367,488 CONCRETE (cu yds) 313 $120 $46.932 $84,478 TRENCH/BACKFILL (ft) 2.112 $0 $63,360 $63,360 CONDUIT (ft.) 8.448 $2 $1 $16.896 $8,448 $25,344 GROUNDING CONDUCTOR [2.4112 $2 $1 $4.224 $2,112 $6,336 GEOTECH: Strength/Thermal 1 $0 | $15,000 $0 $15,000 $15,000 SPLICE (1-PHASE) OPEN SHEATH (ca) 3 $16.745 | $15.000 $50.235 $45.000 $95,235 SPLICE (1-PHASE) CLOSED SHEATH (ca)_| 0 $13,000 | $15,000 $0 $0 $0 TERMINATIONS (1-PHASE) 6 $22.000 | $4,000 $132.000 $24,000 $156.000 ARRESTERS (ca) 6 $3.000 | $1,000 $18.000 $6,000 $24,000 MANHOLES (ea) 1 $25,000 | $12,000 $25,000 $12,000 $37.000 GROUNDING X-BONDING 0 $6,350 | $2,000 $0 GROUNDING LINK BOXES 1 $2,250 | $2,000 $2,250 $2.000 TRANSITION SITE (CIVIL) $50,000 $100.000 $200,000 TERMINATION STRUCTURES (ea) 2 $40,000 | $20,000 $80,000 $40.000 TERMINATION FOUNDATIONS (cu yds) 26 $200 ; PAVEMENT RESTORATION (sq yds) 0 $0 Tl ee a MOB/DEMOB 1 $0 | $50,000 SUB TOTALS $807,159 $496,532 $1,303,691 ENGINEERING 6.50% $84,740 LAND SURVEY LOT $16,000 CONSTRUCTION MGM 7.00% $91,258 CONTINGENCY 10.00% $149,569 TOTAL | $1,645,258 PEI-HLY (3/11/9610:08 AM) 120293-01 br r:‘WAR/CHUGACH’/KLATTBI/AN30.XLS TABLE UGS53 TABLE UG12 - COST ESTIMATING INFORMATION LINKTE.A.20 COST ESTIMATE 2-138. KV Three Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL LABOR = [MATERIAL COST CABLE (ft) 59,136 $180 $53 $10,644,480 | $3,134,208 | $13,778,688 TRENCH/BACKFILL (ft) 4,000 $0 $40 $0 $160,000 | $160,000 GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 | $0 $290,000 | $290,000 SPLICE (3-PHASE) (ea) 0 $55,270 $50,000 | $0 $0 | $0 TERMINATIONS (3-PHASE) 4 $65,065 $50,000 | $260,260 $200,000 | $460,260 | ARRESTERS (ea) 12 $2,000 $1,000 | $24,000 $12,000 | $36,000 MANHOLES (ea) 0 $0 $0 | $0 $0 $0 SHEATH GROUNDING (ea) 4 $1,000 $1,000 $4,000 $4,000 $8,000 SUBSTATION TERMINATION STRUCTURE 2 $13,000 | $7,000 $26,000 $14,000 $40,000 TRANSITION SITE (CIVIL: FIRE ISLAND) 1 $50,000 $50,000 $50,000 $50,000 $100,000 TRANSITION STRUCTURE (FIRE ISLAND) 1 $40,000 $20,000 $40,000 $20,000 $60,000 TRANSITION FOUNDATION (FIRE ISLAND) 1 $200 $25,000 $200 $25,000 $25,200 HYDRAULIC RESEVOIRS 0 $0 $0 $0 $0 $0 MOB/DEMOB 1 $250,000 $2,000,000 $250,000 $2,000,000 $2,250,000 SUB TOTALS $11,298,940 $5,909,208 $17,208,148 ENGINEERING ; $500,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $602,285 TOTAL EMBEDED "$18,347,933 LESS $14/CABLE FT. $827,904 TOTAL NON-EMBEDED $17,520,029 PEI-HLY 120293-01 (7:52 PM 3/10/96) br r:/WAR/CHUGACH/TESORO/TEA20.XLS 1 TABLE UG12 TABLE UG14 - COST ESTIMATING INFORMATION LINK TE.A.20 COST ESTIMATE 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL LABOR [MATERIAL COST CABLE (ft) 118,272 $143 $53 $16,912,896 $6,268,416 TRENCH/BACKFILL (ft) 8.000 $0 $40 | GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 | $290,000 $290,000 SPLICE (1-PHASE) (ea) 0 $0 $0 | $0 $0 TERMINATIONS (1-PHASE) 8 $25,000 $4,000 | $200,000 $32,000 $232,000 ARRESTERS (ea) 8 $3,000 $1,000 $24,000 $8,000 $32,000 MANHOLES (ea) | 0 $0 $0 $0 | $0 SHEATH GROUNDING (ea) | 8 | $1,000 $1,000 $8,000 $8,000 | $16,000 SUBSTATION TERMINATION STRUCTURE _ | 2 | $13,000 $7,000 $26,000 | $14,000 $40,000 | TRANSITION SITE (CIVIL: FIRE ISLAND) | 1 | $50,000 $50,000 $50.000 | $50,000 $100,000 | TRANSITION STRUCTURE (FIRE ISLAND) | 1 | $40,000 $20,000 $40,000 $20,000 $60,000 TRANSITION FOUNDATION (FIRE ISLAND) _| I | $200 $25,000 $200 HYDRAULIC RESEVOIRS | 4 | $35,000 $20,000 $140,000 MOB/DEMOB | 1 | $250,000 $2,000,000 | __$250,000 SUB TOTALS $17,651,096 $9,115,416 $26,766,512 ENGINEERING $550,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.00% $802,995 TOTAL EMBEDED $28,157,007 LESS $14/CABLE FT. $1,655,808 TOTAL NON-EMBEDED $26,501,199 PEI-HLY 120293-01 (8:26 AM3/11/96) mh r:/WAR/CHUGACH/TESORO/2TEA20.XLS 1 TABLE UGI4 TABLE UG19 - COST ESTIMATING INFORMATION LINKTE.C.30 COST ESTIMATE 2-138 KV Three Phase SCFF Cable System UNIT COSTS | EXTENDED COSTS | TOTAL DESCRIPTION QTY. |MATERIAL LABOR MATERIAL LABOR COST CABLE (ft) 33,792 $53 $6,082,560 $1,790,976 $7,873,536 | TRENCH/BACKFILL (ft) 4,000 $40 $0 $160,000 $160,000 | GEOTECH: Marine Survey, Strength/Thermal LOT $0 $290,000 $0 $290,000 $290,000 | SPLICE (3-PHASE) (ea) 0 $55,270 | $50,000 $0 L $0 $0 | TERMINATIONS (3-PHASE) 4 $65,065 | $50,000 $260,260 $200,000 $460,260 ARRESTERS (ea) 12 $2,000 | $1,000 $24,000 $12,000 $36,000 |MANHOLES (ea) 0 $0 | $0 $0 $0 | $0 SHEATH GROUNDING (ea) 4 $1,000 | $1,000 $4,000 $4,000 | $8,000 SUBSTATION TERMINATION STRUCTURE 2 $13,000 | $7,000 $26,000 $14,000 | $40,000 TRANSITION SITE (CIVIL: FIRE ISLAND) 1 $50,000 | $50,000 $50,000 $50,000 $100,000 TRANSITION STRUCTURE (FIRE ISLAND) 1 $40,000 $20,000 $40,000 | $20,000 $60,000 TRANSITION FOUNDATION (FIRE ISLAND) 1 $200 $25,000 $200 ___ $25,000 HYDRAULIC RESEVOIRS 0 $0 $0 $0 $0 MOB/DEMOB cl 1 $250,000 . $2,000,000 $250,000 $2,000,000 | $2,250,000 SUB TOTALS $6,737,020 $4,565,976 $11,302,996 ENGINEERING $500,000 LAND SURVEY LOT $37,500 CONSTRUCTION MGMT. 3.50% $395,605 TOTAL EMBEDED $12,236,101 LESS $14/CABLE FT. $473,088 TOTAL NON-EMBEDED $11,763,013 PEI-HLY 120293-01 (7:56 PM 3/10/96) br r:/WAR/CHUGACH/TESORO/TEC30.XLS 1 TABLE UG19 TABLE UG21 - COST ESTIMATING INFORMATION LINK TE.C.30 COST ESTIMATE 4-230 KV Single Phase SCFF Cable System UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL LABOR [MATERIAL LABOR COST |CABLE (ft) 67,584 $143 $53 $9,664,512 $3,581,952 | $13,246,464 | |_TRENCH/BACKFILL (ft) 8,000 | $0 | $40 | $0 $320,000 $320,000 GEOTECH: Marine Survey, Strength/Thermal LOT $0 | $290,000 | $0 $290,000 $290,000 SPLICE (1-PHASE) (ea) $0 | $0 | $0 $0 TERMINATIONS (1-PHASE) $25,000 | $4,000 | $200.000 $32,000 $232,000 ARRESTERS (ea) $3.000 | $1,000 | $24,000 $8,000 $32,000 MANHOLES (ea) $0 | $0 | $0 $0 $0 SHEATH GROUNDING (ea) $1,000 | $1,000 | $8,000 $8,000 $16,000 SUBSTATION TERMINATION STRUCTURE $13,000 | $7.000 | $26,000 $14,000 $40,000 TRANSITION SITE (CIVIL: FIRE ISLAND) $50,000 | $50,000 | $50,000 $50,000 $100,000 TRANSITION STRUCTURE (FIRE ISLAND) $40,000 | $20,000 $40,000 $20,000 $60,000 —fel—l|—l—lrloalolalaleo TRANSITION FOUNDATION (FIRE ISLAND) $200 | $25,000 $200 $25,000 $25,200 HYDRAULIC RESEVOIRS $35,000 $20,000 $140,000 $80,000 $220,000 MOB/DEMOB _ $250,000 $2,000,000 i $250,000 $2,000,000 $2,250,000 SUB TOTALS $10,402,712 $6,428,952 $16,831,664 ENGINEERING $550,000 LAND SURVEY LOT ' $37,500 CONSTRUCTION MGMT. 3.00% $504,950 TOTAL EMBEDED $17,924,114 LESS $14/CABLE FT. $946,176 TOTAL NON-EMBEDED $16,977,938 PEI-HLY 120293-01 (8:26 AM3/11/96) mh r:/WAR/CHUGACH/TESORO/2TEC30.XLS 1 TABLE UG21 Appendix C FIGURE SS-09 138KV OPTION BERNICE LAKE POWER PLANT SITE PLAN anon CORRECTIONS 5601 Minnesota Drive ASBOLT 73 WA WPUR_& COUPMONT RISTALLATION f P.O. Box 196300 Anchorage, Alaska 99519-6300 BLPP-E-0010 FIGURE SS-10 230KV OPTION PROJECT: RECORD REWSON ENG. /DESIGN.: 0. © RECORO UPOATE = =a == ‘ 5601 Minnesota Drive ASBULT 75 MA XFUR_& CQUPMENT INSTALLATION ‘ P.O. Box 196300 Anchorage, Alaska 99519-6300 BLPP-E-0010 TABLE SS01 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, Bernice Lake Substation TOTAL DESCRIPTION QTY. JMATERIAL| LABOR $100 [MATERIAL| LABOR _'|_— COST | HRS | UNIT | HRS | UNIT | Q Circuit Breakers 4 $100,000 | __ 60 Disconnect Switches 1 $10,000 | __24 Instrument Transformers and Misc. Equipment 12 $4,250]. 4 | $400] $51,000] 48 | $4,800] — $55,800 | | 138/115 kV 150/200 MVA Autotransformer__|__1__‘| $1,300,000 [120 [$12,000 | $1,300,000] 120 | __ $12,000 |_ $1,312,000 | | Demolition, Removal, Modifications —s|| LOT [| _—s— $0] _120 [| $12,000] _—s— $0] 120 | $12,000] _ $12,000 | STRUCTURES Deadend Structures Switch Stands Bus and Inst. Transformer Supports FOUNDATIONS 2 $11,500] 40 | $4,000 $23,000 80 $8,000 $31,000 ul $1,200 | _ $33,000 $46,200 | 66 | $6,600 Circuit Breakers 12 [| _$250[ 6 =| 72 | $250] 6 26 $26,400 Bus and Inst. Transformer Supports 4 $250] 6 | $600] $10,000| 240 $24,000 $34,000 | $250] 6 | $000] $11,000] $264| $26,400 $37,400 | $250] 6 | $600] $4,000] 96 $9,600 $13,600 $250 6 $600 $8,000 $192 $19,200 $27,200 Autotransformer and Oil Containment Control House _ Deadend Structures 32 CABLE & CONDUIT Cassano Gessner} Sioa 55] — sr | tu | — | a Instrument Transformers 390 siof oos | —-$5t— $3,900] 20 [$1,950] $5,850 | | Autotransformer ss Ci‘“‘(R«CSO CT CS30] (0.18 [ S18] $4,500] 27 *| $2,700] __—$7,200 | ighting 600 os | ss $5] 48007 30 | $3,000] ‘$7,800 | 300 . e | 0.016 | $69,500 | _ $104,250 [ Fencing C—“‘“C;SCC(*’:COOUS: «T_~$15.81[ 0.166 [ $17[_—_—89,725] 102 ~ [$10,225 $19,950 | PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SSO01 TABLE SS01 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, Bernice Lake Substation CONTROL HOUSE UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. /MATERIAL MATERIAL a [Grounding C—“‘CSC(#d’#«#SWOON*T_~—C«$8.00|_ 0.07 $7] $44,800 392 $39,200 | Prefabricated Control Building & Accessories [| 1 [| $72,000] 160 | $16,000[ _ $72,000] 160 | $16,000] _$88,000 | Lor [| $12,500[ 40 | $4000] $12,500[ 40 | $4,000| $16,500 | Control, Relay, Metering, & Comm. Panels 4 $27,000] 8 $800 | $108,000 | 32 TESTING Lor | ___—ssof —36_~| 3,600] so] 36 | 83,600] $3,600 | Get ake} 4 | no] an] | Circuit Breaker $0 12 $1,200] ss $0 48 $4,800] $4,800 | | Control, Relay, Metering, &Comm. Panels | _4 [ —s$0{_ 12, ~*~ i200] SO] 48 84.800] $4,800 | so] 16 | $ieoo] $0] 16 =| $1,600[ _—$1,600 | Mobilization/Demobilization/Report $3,000 SUB TOTALS $2,378,075 _5153__ $515,315 _ $2,893,390 - ENGINEERING 6.50% $188,070 CONSTRUCTION MGMT. 7.00% $202,537 CONTINGENCY 10.00% $289,339 TOTAL $3,573,337 PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS01 TABLE SS02 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 230 KV Option, Bernice Lake Substation UNIT COSTS EXTENDED COSTS DESCRIPTION . JMATERIALTLABOR $100 __ [MATERIAL LABOR | HRS [UNIT __| | HRS | UNIT _| ——————— a = See Disconnect Switches $11,818] 25 $27,200 Instrument Transformers and Misc. Equipment | 12 [ $4,750] 4 48 $4,800 | 230/115 kV 150/200 MVA Autotransformer__[__1_[ $1,600,000| 130 | $13,000 | $1,600,000] 130 | $13,000 | _ $1,613,000 | | Demolition, Removal, Modifications | LOT [| _—$0{ 120 [| $12,000] $0] 120 | $12,000] _$12,000 | STRUCTURES Deadend Structures 2 $13,750 | 50_| $5,000] $27,500] 100 | $10,000] _ $37,500 | | Switch Stands CST] _83,091 | 12.7273] $1,273 | $34,000] 140 | $14,000] $48,000 | |_Bus and Inst. Transformer Supports | 13, [| $1,246[ 5508] $16,200] 66 [$6,600] $22,800 | FOUNDATIONS | Circuit Breakers T8250] S600 $3,500] 84 J $8,400] $11,900 | | Switch Stands T8250] 6 $600] $12,000] 288 | $28,800 [$40,800 | | Bus and Inst. Transformer Supports | 43, =| $2506 = T8600] $10,750] 258 [$25,800 | $36,550 | |_Autotransformer and Oil Containment _—|_58_[ $2506 | sooo | $14,500] $348 | $34,800 [$49,300 | | ControlHouse TG T8250] 6 S600 | $4,000] 96 [$9,600 [$13,600 | | Deadend Structures S| 4 T$250] 6 YT S600] 10,000 $240 $24,000 [$34,000 | CABLE & CONDUIT | Circuit Breakers | 630 =| S30 0.8 TP sis] $18,900] 113 [$11,340] $30,240 | j—fenl Trsformers SR Sa Fs fs Autotransformer | 150 [| $30f ois [sis] $4,500 27 [$2,700 | $7,200 | | Yard Lighting & Convenience Outlets _——|_ 600 _[ $80.05 [ss] $4g00] 30 [$3,000 [$7,800 | | Precast Cable Trench (ft) S| 300 ‘[ 87ST os | $50] $22,500] 150 [$15,000 [$37,500 | [a ee ee ee Se eee 45,000 | _ $0.81] 0.016 | _$2]_ $36,250] 725 [$72,500 $108,750 | | Fencing 50 815.77 0.165 | $17] __$10,250[ 108 [$10,750 $21,000 | PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS02 TABLE SS02 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 230 KV Option, Bernice Lake Substation UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. [MATERIAL[LABOR $100 |MATERIAL LABOR | HRS | UNIT _| $8.00 CONTROL HOUSE SUB TOTALS $2,763,750 5468 $546,840 _ $3,310,590 ENGINEERING 6.50% $215,188 CONSTRUCTION MGMT. 7.00% $231,741 CONTINGENCY 10.00% $331,059 TOTAL $4,088,579 PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS02 ij LEGEND et 6 = mom we i N | \ me rent | ° ‘unUTY POLE 1 © vorr rat ! \ rt wow : FENCE ; + e STORM ORAM MANHOLE | My © exes nee ! i suntan seven azsnout i } Se SAMTARY SEWER MANHOLE vel soma ‘ i Canes rover homer | 6 woot Secure. | t La 2 ee emacs oxen i kd een . i i Ts tt | OODEN FENCE wre 4 manOroUse SOK STRAIN BUSES Sir) (=) bra ay Pama Semel SALE 1 = 30! e & = a — aon oe zé coum 5 a 1 a z z = = ome le e 3 i é ae i sl] 3 5 sromsce yao 1 a in oon 5 Fy ¥ | STORAGE z 3 wc. 3 ieee ill 4 — FIGURE SS-11 y 4 TT 138KV OPTION \ \ PROJECT: RECORD RESON WHT apy | wo | RECORD Tose a ENG: DE RIOR: i. GUM ANE Od eee ae INTERNATIONAL SUBSTATION * CONSTRUCTION REWSON oa Dee STA 34.5/138kV SWITCHYARD 7 | resus Fon conseonanon 5601 Minnesota Drive GENERAL ARRANGEMENT - ALTERNATE #1 P.O. Box 196300 t anchor eget Alaska {4 [0/94/2006 fas 3 nS WO: INSS~S-0013 34.SKV SMTOHYARD PROPERTY UNE Tate 20 FIRE HYDRANT _—Z unuTy Poe UoHT POLE RAILROAD STORM DRAM MANHOLE LECTRIC MANHOLE SANITARY SENER CLEANOUT Coa Be 2 GEERATORB.. 3 y SANITARY SEWER MANHOLE ASPHALT a ~ it ——— ma © © . 9 Cy ° MONUMENT Ee re 9g ——=—— _ unoencrounn ELECTRICAL UNDERGROUND ELECTRICAL : tl Ta hs ; a ma ae —— Oy if SCALE: 1° = 30° 8; Ez! | lat z So 3! a oe t t z z! “oe = rae CTY Te"? eoce oF PaEUENTA | i i NL me. c anv mevoreo w T ‘STORAGE YARD - al 5 r 1 Soh & wee | q : FIGURE SS-12 4 1 230KV OPTION mT ay Tone, | em Loom Dig ese: gagmaR eee wg a ame ae SUBSTATION 34.5/138kV SWITCHYARD ry CECH AIOE GEER | oe ; ; : 5601 Minnesota Drive GENERAL ARRANGEMENT - ALTERNATE #1 ‘ — P.0. Box 196300 Anchorage, Alaska [64 [0/04 [20088 fs. + 99519-6300 = ra INSS-S-0013 TABLE SS03 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, International Substation UNIT COSTS QTY. |MATERIAL | LABOR EXTENDED COSTS DESCRIPTION $100 Bim Seka ————————}3-}- “ite "557000 Disconnect Switches 5 $10,000 $62,000 Ba Fling. and Me SRD Bus, Fittings, and Misc. LOT $35,450 584 $58,400 $35,450 584 $58,400 $93,850 STRUCTURES a {asta i] stant —st8900| ts | 6 | $3,000 $1,200 $18,000 | 72 $7,200 Bus and Inst. Transformer Supports 9 $1,267{ 5 | $533] $1400] 48 [ $4,800[ $16,200 | FOUNDATIONS Circuit Breakers 6 $250 | 6 $600] $1,500] 36 ~~ $3,600] _—$5, 100 | Switch Stands Sa rn Bus and Inst. Transformer Supports 30 $250] 6 | $s600| $7,500] 180 | $18,000] $25,500 | Deadend Structures | 16 | $250] 6 | sooo] $4,000] $96[ $9,600] $13,600 CABLE & CONDUIT Crombie fn $14,400 Instrument Transformers | 400 | —ssi0f 005 | $5] $4,000 $2,000 $6,000 Yard Lighting & Convenience Outlets | joo [ $8 00s | st sgo0] 5 $500 | _$1,300 | Precast Cable Trench (ft $5,625, $3,750 $9,375 Control, Relay, Metering, & Comm. Panels $29,333] 8 | $800 $2,400 $90,400 Physical Check Out & Misc. Systems er a ee $2,800 $0] 28 $2,800 $2,800 | Instrument Transformers CCi‘dCS CSC] CSOT $200 $o] 6 $600 PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS03 TABLE SS03 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, International Substation UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL] LABOR __ $100 LABOR COST | HRS _| eR | CircuitBreaker ss C“‘CS;OCL Os OC2C~UC«CL:~SCOOC‘#SSO YT 2_—sd| $1,200] ~~ ST 24 [$2,400 $2,400] Control, Relay, Metering, & Comm. Panels Rae a AE $4,800 $4,800 Mobilization/Demobilization/Report $3,000 $2,600 SUB TOTALS $502,150 _ 1869 $186,900 $689,050 ENGINEERING 6.50% $44,788 CONSTRUCTION MGMT. 7.00% $48,234 CONTINGENCY 10.00% $68,905 TOTAL $850,977 PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS03 TABLE SS04 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION Qty. [MATERIAL[LABOR $100 __ [MATERIAL LABOR cost | HRS [UNIT | EQUIPMENT é Disconnect Switches 25 $2,514 $90,000 | 176 $17,600 | Instrument Transformers and Misc. Equipment | 6 | __$5,500| 4 | 230/138 kV 150/200 MVA Autotransformer___|__1_| $1,600,000 | _130_| _$13,000 | $1,600,000 | _130_| _$13,000 | _$1,613,000 | LOT STRUCTURES | Deadend Structures | 3 813,000 | 46.6667] $4,667 | $39,000] 140 | $14,000] $53,000 | | Switch Stands 883,125 13 $1,300] $25,000] 104 [$10,400 $35,400 | | Bus and Inst. Transformer Supports] 9 [$1,367] 5 T8533 $12,300] 48 [$4,800 T $17,100 | FOUNDATIONS | CircuitBreakers_ TT 8250f 6 S600 82,750] 66 86,6007 $9,350 | | Switch Stands CE 8H 8250 6 | S600 89,000] 216 | $21,600] $30,600 | [Bus and Inst. Transformer Supports | 33 | $250 6 | sooo] $8,250] 198 | $19,800] $28,050 | Autotransformer and Oil Containment | 58_| $250] 6 | $600] $14,600] 348 | $34,800] $49,300 [ Deadend Structures ——SSSSSC*dT ~~~ «S250 6 | $600] $14,000] 336 CABLE & CONDUIT | CircuitBreakers 275 T8307 0.18 [818] $38,250] 230 [$22,950] $61,200 | | Instrument Transformers | 500 | S10 0.05 [SS] $5,000] 25 $2,500| ‘$7,500 | | Autotransformer CT 450 ST S30 0.18 [sis $13,500] 81 [$8,100] $21,600 | | Yard Lighting & Convenience Outlets {|_(100_| $8] 0.05 [Sst S800] 5 | S500] $1,300 | $11,250 SITE WORK Site Preparation, Access, and Surfacing $0.75 | 0.015 $2 $9,000 | 180 | $18,000 $27,000 Fencing $15.00 | 0.150 $15 $4,500 $4,500 $9,000 Grounding 1,700 $8.00 $7 $13,600 { 119 | — $11,900 | $25,500 PEI-HLY 120293-01 (1:45 PM3/11/96) ss 12,000 w ag o TABLE SS04 TABLE SS04 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL[LABOR $100 _|MATERIAL LABOR COST | HRS | UNIT _| | HRS [UNIT _ | CONTROL HOUSE Control, Relay, Metering, & Comm. Panels | 4 __$27,000[_8 [| _—$800 $108,000 $3,200 TESTING Physical Check Out & Misc. Systems | Lor [sof 28 [$2,800T S028 [$2,800 $2,800 |_Instrument Transformers | TSO 2 s200{ Sot 6 | $600 $600 | Circuit Breaker SO S200 8036 83,600 $3,600 Control, Relay, Metering, & Comm. Panels | 4 [| SOT 12, T1207 S048 $4,800 $4,800 230/138 kV Autotransformer pt fof 6 fT siooof sot 16 [$1,600 $1,600 Mobilization/Demobilization/Report $3,000 $2,600 $3,000 $2,600 $5,600 SUB TOTALS $2,441,800 3784 $378,350 $2,820,150 ENGINEERING 6.50% $183,310 CONSTRUCTION MGMT. 7.00% $197,411 CONTINGENCY 10.00% $282,015 SS SS TOTAL $3,482,885 PEI-HLY 120293-01 (1:45 PM3/11/96) ss TABLE SS04 © 1060R HOKD * 2 ¥ 28 § lip PANT Nae DY) ees sew came vo we mas He (ee a a4 Juul Sean el ora cr ; TF ate ii | Aye ie a AH) WH ; 7 T i ; | | I ster | aL fy iil! 7 rt ar ' y+ = . ° AN Tired SERMCE POND sero e GATE | | i 1 | —; «1. | oe ee on coer ree / ia = a FIGURE. $S-I3 138KV OPTION SITE PREPARATION 5601 Minnesota Drive UNIVERSITY SUBSTATION . 2 = 4 : le $ = PROJECT: = an NG./EsiGN.: SCOTT GIRARD _____wo. 70/es| v7 ° i F a MES) P.0. Box 196300 F Anchorage, Alaska {A feomahranl 8201 Sfonshapt 2/270 = \ bree i 99519-6300 3 WE = PREVI RFERENG - / ec UVSS-S-0034/E9520113 a : c:\projects\120293\uvs34_1.dgn Mar. 8, 1996 15:33:27 TO MP PLANT NO. 2 —_—_—— SOUTHERN INTERTIE —_—_— FIGURE SS-14 230KV OPTION ¢:\projects\120293\uvs34_2.dgn Mar. 8, 1996 15:29:10 TABLE SS05 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, University Substation UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION : TERIAL | LABOR $100 COST HRS UNIT : | CircuitBreakers CdS $100,000 , $100,000 | __60 : $106,000 Disconnect Switches 3 $10,000 $2,400 $30,000 722 A $37,200 Instrument Transformers and Misc. Equipment $4,500 $400 $27,000 24 $2,400 $29,400 6 Bus, Fittings, and Misc. $20,400 $34,800 $20,400 | 348 $34,800 $55,200 Deadend Structures 1 $11,500] 40 $4,000 $11,500 , $15,500 Switch Stands 3 $3,000 | 12 $1,200 $9,000 : ; $12,600 Bus and Inst. Transformer Supports $1,200 5 $514 $8,400 | 36 $3,600 $12,000 FOUNDATIONS Circuit Breakers $250 $600 $750 18 $1,800 $2,550 Sch Sn aa fg of or | | sf a Bus and Inst. Transformer Supports 132 $13,200 $18,700 Deadend Structures i $96 $9,600 $13,600 CABLE & CONDUIT | CircuitBreakers ss C“‘SSC#*i;:S«O225:«dTC S30 0.18 | S18] $6,750T 41 ; $10,800 | Instrument Transformers Cd 225 | SOT 0.05 | SS] $2,250] T8125 $3,375] | Precast CableTrench (ft) Ss CE 380 ST 875 05 P50 82,2507 15 [$1,500] $3,750 | SITE WORK Site Preparation, Access, and Surfacing : : ing . ; $4,000 CONTROL HOUSE Control, Relay, Metering, & Comm. Panels $800 | $88,000 | 24 R $90,400 Physical Check Out & Misc. Systems Instrument Transformers oc $1,200] Sof 12 $1,200 $1,200 PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS05 TABLE SS05 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, University Substation UNIT ST ASOR S100 EXTENDED COSTS TOTAL DESCRIPTION MATERIAL | LABOR -LABOR _$100_| MATERIAL LABOR COST | HRS [UNIT _| | HRS [UNIT _| Control, Relay, Metering, & Comm. Panels a ee $1 a a on ee $3, ‘o0 $3,600 Mobilization/Demobilization/Report $3,000] 26 | $2,600 $3,000] 26 | $2,600 $5,600 SUB TOTALS $328,675 1225 $122,525 $451,200 ENGINEERING 6.50% $29,328 CONSTRUCTION MGMT. 7.00% $31,584 CONTINGENCY 10.00% $45,120 TOTAL $557,232 PEI-HLY 120293-01 (6:34 PM3/9/96) ss TABLE SS05 TABLE SS06 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE UNIT COSTS EXTENDED COSTS [SUNITCOSTS TOTAL DESCRIPTION QTY. Cost [ HRS [UNIT _| UNIT | Disconnect Switches. SSC™~—CSS SST =~ (812,727] 31d 83,091 | $140,000] 340] $34,000[ $174,000 | | Instrument Transformers and Misc. Equipment | 12 | $2,750[__5__ | _—$500| $33,000 60 | $6,000] $39,000 | Lor | _—- sof 200 | $20000[ sof 200 [$20,000] $20,000 | | Deadend Structures Ci‘“‘;SSC*rT SOC: C«dY~S«816,000T 60 $6,000] $32,000] 120 | $12,000] $44,000 | | SwitchStandsC—~—“—~s~—s~s—s—C—sssCsTCSCSCSTCS«83,500 16 T1600] $31,500] 144 | $14,400] $45,900 | | Bus and Inst. Transformer Supports ———sd| = 42—«T CS S1443[ 6 T8571 $60,600] 240 | $24,000] $84,600 | FOUNDATIONS | Circuit Breakers SC—~—“C—~é‘“;**~é*s*dCSCSCSdECsC*‘ STG S60 $5,000 120 YT $12,000] $17,000 | | SwitchStands CC‘ CSSCOC*'LCOO4 ~=@:~SS250[ 6 | S600] $13,500] 324 | $32,400] $45,900 | | BusandInst. Transformer Supports | «162_—«| =~ $250 6 iT S600] $40,500 972 | $97,200] $137,700 | | DeadendStructures CS CTS S250 TS S600[ $12,000 288 [ $28,800] $40,800 | CABLE & CONDUIT ; | CircuitBreakers CC‘ 200O*T~CS$30] 0.18 [ $18 $60,000 360 | $36,000] $96,000 | [Instrument Transformers Ss|«000 |S S| 0.05 [$5 $10,000T s0_[ $5,000] $15,000 | | YardLighting & Convenience Outlets ss] —-600:~«[ SB] 0.05 | SS] $4,8007 30 [| $3,000] _$7,800 | | PrecastCableTrench(®) CCAS ST SST OS TSO $35,625] 237.5 [$23,750] $59,375 | SITE WORK Site Preparation, Access, and Surfacing [120,000] $0.77] 0.015 | $2] $92,500] 1,850_| $185,000] $277,500 | [ Fencing 200 [$15.42] 0.158 | $16] $18,500] 190 | $19,000] _ $37,500 | $60,000 CONTROL HOUSE Control, Relay, Metering, & Comm. Panels $29,333] 8 | $800 $90,400 PEI-HLY 120293-01 (1:48 PM3/11/96) ss TABLE SS06 TABLE SS06 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. {MATERIAL | LABOR $100 MATERIAL LABOR COST [ars [unit TESTING Physical Check Out & Misc. Systems Lor | _—s of 28 | $2,800[ ss S028: | $2,800 $2,800 |_Instrument Transformers | 3 TSO 2 s200{ S06 $600 $600 | Circuit Breaker TT SOT 200 soa $1,200 $1,200 Control, Relay, Metering, & Comm. Panels | 3 [sof 12 =| $1,200{ ss $o[ 36 | $3,600 $3,600 Mobilization/Demobilization/Report LOT $3,000 $2,600 $3,000 $2,600 $5,600 SUB TOTALS $1,069,725 9329 $932,850 $2,002,575 ENGINEERING 6.50% $130,167 CONSTRUCTION MGMT. 7.00% $140,180 CONTINGENCY 10.00% $200,258 TOTAL $2,473,180 PEI-HLY 120293-01 (1:48 PM3/11/96) ss TABLE SS06 138KV OPTION FIGURE SS-15 HEA SOLDOTNA SUBSTATION 5601 Minnesota Drive P.O. Box 196300 Anchorage, Alaska 99519-6300 ° 1si7ae ; 1Sae-TSVF CO APPROVED | APPROVED 2 SCADA RT INSTALLATION (SE HT. E-3) ty reteset ain | Iegecent 230KV OPTION FIGURE SS-16 HEA SOLDOTNA SUBSTATION 5601 Minnesota Drive P.0. Box 196300 Anchorage, Alaska 99519-6300 9° sessesbesstss55525- 23 aR IOS 1 2 SCADA RTU NSTALLATION [DRAWN TO CAD FROM COFFUAN ENGR... DWC. E: TABLE SS07 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, Soldotna Substation UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL[ LABOR $100 |MATERIAL LABOR COST | HRS | UNIT | | HRS | UNIT | EQUIPMENT Circuit Breakers 60 $300,000 | _180 $18,000 | _ $318,000 Disconnect Switches $70,000 | 168 | $16,800 $86,800 Instrument Transformers and Misc. Equi $27,000 | 24 | _$2,400] $29,400 | 138/115 kV 150/200 MVA Autotransformer $1,300,000 | 120 $12,000 | $1,300,000 $12,000 | $1,312,000 Bus, Fittings, and Misc. LOT $81,200 [ 1304 $130,400 [ $81,200 [1304 $130,400 $211,600 STRUCTURES IsTRUGTURES Ml MM MIM MISTI II MM IM Ms IS I] Deadend Structures [1 | $i1,500T 40 $4,000 | $11,500 40 | $4,000T $15,500 | Switch Stands | 8 | $3,000] 12 $1,200 $24,000[ 96. | $9,600 $33,600 $100,000 |_BusandInst. Transformer Supports | 18 [$1,383] 6 $567] $24,900] 102 [$10,200 [$35,100 | FOUNDATIONS [ssn eso] — arom | 9s [ st a00| a0 Switch Stands 32 $250| 6 $600 | Bus and Inst. Transformer Supports | 66 (| $2506 =| $600 $16,500] 396 | $39,600 | $56,100 | Autotransformer and Oil Containment | 44 | $250{_ 6 | s6o0{ $11,000] $264 $26,400 [$37,400 | Deadend Structures | i6 [ s2sof 6 | sooo] s40o0[ $96] $9,600 [$13,600 | CABLE & CONDUIT | CircuitBreakers 1250 $30 0.8 J sis] $37,500 225 [$22,500 $60,000 | |_Instrument Transformers | 700 | $10 | 0.05 [ss $7,000 35 $3,500 [$10,500 | | Autotransformer | 600 | $30 0.18 | sis] $18,000 [108 | $10,800 [$28,800 | |_Yard Lighting & Convenience Outlets | 600_ [$8 | | _$15,000[ 100 _[ $10,000] $25,000 ] SITE WORK Site Preparation, Access, and Surfacing 20,000 $0.88 | 0.018 $2 $17,500 $35,000 $52,500 $16.67 |_ 0.183 $18 $5,000 $5,500 $10,500 $8.00 $19,200] 168 | $16,800[ $36,000 | PEI-HLY 120293-01 (4:39 PM3/11/96) ss TABLE SS07 TABLE SS07 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, Soldotna Substation UNIT COSTS DESCRIPTION $100 CONTROL HOUSE Control, Relay, Metering, & Comm. Panels 4 $27,000[ 8 | $800 | $108,000 $3,200 | $111,200 TESTING Physical Check Out & Misc. Systems | Lor | So 28 | 82,8007 S028 [$2,800 Sheet — ett Circuit Breaker 3 sof 12 [ si200[ sof 36 '[ $3,600] $3,600 | | Control, Relay, Metering, &Comm.Panels__| 4 | So{ 12 [ $1,200] so] 48 [$4,800] $4,800 | | 138/115kV Autotransformer__— | 1 CT SOT 6 = Si600 $0 | | 16 | Mobilization/Demobilization/Report $3,000 $3,000 SUB TOTALS $2,115,350 4299. $429,900 __$2,545,250 ENGINEERING 6.50% $165,441 CONSTRUCTION MGMT. 7.00% $178,168 CONTINGENCY 10.00% $254,525 TOTAL $3,143,384 PEI-HLY 120293-01 (4:39 PM3/11/96) ss TABLE SS07 TABLE SS08 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL[LABOR $100 __ [MATERIAL LABOR COST | HRS [UNIT _| EQUIPMENT instrument Transformers and Mise. Equipment | 6 | $5500] 4 | $400] _$33,000[ 24 | $2,400] $35,400] 230/115 kV 1507200 MVA Autotransformer | 1 | $1,600,000 | 130 | $13,000 | $1,600,000 | 130 | _ 813,000 | $1,613,000 | Bus, Fittings, and Mise. STRUCTURES | Deadend Structures | 1] 816,000] 60 | 86,000 16000] 60 | 86,000] $22,000 Switch Stands SCS 8 | 83,125] 13] 81,300] $25,000 | 104] 810,400] $35,400 | Bus and inst. Transformer Supports] 18 | $1,433| 6 | $567] $25,800] 102 | $10,200] $36,000 FOUNDATIONS Circuit Breakers] 11] 50] 6 | sooo] 82750] 66] $6,600] $9,350 Switch Stands] 36 | 8250 6 | 000] $9,000 | 216 | $21,600] $30,600, [Bus and Inst. Transformer Supports | 69 | _s2s0[ 6 | sooo] _817,250| 414 | __sai,400| $58,650] [autotransformer and Oil Containment] 58 | 8250 6 | 000] $14,500 348_| 34,800] $49,300, Deadend Structures _——=——SSCSC~dCi | 82st 6 | S000] $6,000] 144 | 14,400] $20,400 CABLE & CONDUIT F Circuit Breakers] 1250] 80] 018 [| S18] 897300] 205 | 822,500] 860,000] [instrument Transformers | 700 | $10] 005_| ss] 7,000] _35_| $3,500] $10,500, autotransformer] 600 $30] 0.18 | $18 | 818,000 | 108] — $10,800 ] $28,800, [Yard Lighting & Convenience Outlets] 600_| _$8| 0.05 | ss] 4,00] 30 | $3,000] $7,800] [Precast Cable Trench (RY) | 200] $75] 05 | $50 | 815,000 | 100] $10,000 | $25,000, ITE WORK $19,000 | Fencing 850 $16.43] 0.179 Tis] $5,750] 63 | $6,250] $12,000 $8.00 $18,200 PEI-HLY 120293-01 (1:50 PM3/11/96) ss TABLE SS08 TABLE SS08 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE UNIT COSTS EXTENDED COSTS TOTAL LABOR $100 LABOR COST HRS UNIT DESCRIPTION CONTROL HOUSE Control, Relay, Metering, & Comm. Panels | 4 | $27,000] 8 | TESTING $800] $108,000] 32 $3,200 Lor | ___—sSof 28 [82,800 S028 [$2,800] $2,800 | | Sof 2 fT sz00f SO S600 $600 | | Of 2 | st200] S036 | 83,600] $3,600 | | sof 12 [_si200f So 48 | 84,800] $4,800 | | soft 6 = sisoof sof i6_ | $i,600[ $11,600 | Mobilization/Demobilization/Report SUB TOTALS $2,499,650 4603 $460,250 —_ $2,959,900 ENGINEERING 6.50% $192,394 CONSTRUCTION MGMT. 7.00% $207,193 CONTINGENCY 10.00% $295,990 TOTAL $3,655,477 PEI-HLY 120293-01 (1:50 PM3/11/96) ss TABLE SS08 MAX AMPACITY 450 AMPS, 1. ELEVATIONS SHOWN ARE BASED ON AN ASSUMED ELEVATION OF 100.00 ON THE CONCRETE BASE OF STRUCTURES AT LAND CABLE NO. 1 TERMINATION 2. 397.5 AAC +112 COORDINATE POINT NUMBER + 98.95 ELEVANON FIGURE SS-17 138KV OPTION SITE PLAN 5601 Minnesota Drive P.O. Box 196300 Anchorage, Alaska 99519-6300 PwSS-S-0002 FIGURE SS-18 230KV OPTION SITE PLAN PT, WORONZOF SUBSTATION +112 COORDINATE POINT NUMBER + 98.95 ELEVATION PwsS-S-0002 P.O. Box 196300 Anchorage, Alaska fp __ CONSTRUCTION BASELINE “BT 5601 Minnesota Drive 99519-6300 ee rigeyt ms ———————_—--- 7 -_---— Ra a \ \ =} -=--- = Jepseuye “™ basa yt Pt pe APPROMD nit ot ee Ow Fone RECORD RESON SOUT Ee a TABLE SS09 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, Pt. Woronzof Substation UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION . /MATERIAL MATERIAL LABOR COST | HRS | UNIT | R 2 | HRS [UNIT _| EQUIPMENT Circuit Breakers 6 $91,667 55 $5,500 Disconnect Switches Instrument Transformers and Misc. Equipment 30 $4,500 4 $400 [38kVReactor | 85250007 80 | $8,000] $525,000] 80 | $8,000 $533,000 | STRUCTURES | Deadend Structures TST 812,200T 38 $3,800] $61,000 190, | $19,000] $80,000 | Bus and Inst. Transformer Supports 28 $1,125 FOUNDATIONS Circuit Breakers and Circuit Switchers 23 | s2sof 6 [S600] $5,750] 138: T $13,800[ $19,550 | Switch Stands 52 ee ee Bus and Inst. Transformer Supports 82 $250] 6 | $600[ $20,500] 492' | $49,200 | $69,700 | | Reactor and Oil Containment | 38 | $2507 6 dT S600 | $9,500] $228] $22,800] $32,300 | | ControlHouse CT T8250 6 S600 | $4,000 96 7 [$9,600] $13,600 | | Deadend Structures | 2 T8250 6 | S600 $18,000] $432 [$43,200] $61,200 | CABLE & CONDUIT ae et Breakers [1,000 | $28f 0.17 | $17] $28,000 168 [$16,800] $44,800 | | Instrument Transformers | 950 ~T S10 0.05 T $5[ $9,500] 48 [$4,750] $14,250 | |_ Yard Lighting & Convenience Outlets [| 600_[ $8{ 0.05 | $5[ $4,800] 30 [$3,000] —_—$7,800 | |_PrecastCableTrench(ft) | 400 *T 875 05 T sso[ $30,000] 200 [$20,000] $50,000 | |_ Site Preparation, Access, and Surfacing | 60,000 | __—$0.75[ 0.015 | $2] $45,000 900 | $90,000] $135,000 | [| Fencing C*dE:CiSSV_“ | $15.00] 0150 | Sis] $32s0[ 83 [ $3,250] $16,500 | PEI-HLY 120293-01 (4:28 PM3/11/96) ss TABLE SS09 TABLE SS09 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 138 KV Option, Pt. Woronzof Substation UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL] LABOR $100 _ [MATERIAL LABOR COST | HRS | UNIT | | HRS’ | UNIT $8.00 $52,500 | _ $112,500 CONTROL HOUSE Prefabricated Control Building & Accessories | 1 | _$72,000[ 160 [| $16,000] _$72,000[ 160. | $16,000] _ $88,000 | AC & DC Station Service LOT $12,500] 40 | $4,000] $12,500] 40 | $4,000 $16,500 Control, Relay, Metering, &Comm.Panels | _10 [ $26,400[ 8 | $soo | $264,000] 80. [$8,000 | $272,000 | Physical Check Out & Misc. Systems LoT | _—s sof = 36 ~«~«d[)~— $3,600] ~—ss S036 —C*”' $3,600 $3,600 | Instrument Transformers CT SS CT CSOT CT S200 CSOT 30 ~~] ~——_—«$3,000 | CircuitBreaker CT STS S200] SOT 60 | 86,000| _ $6,000 | Control, Relay, Metering, &Comm. Panels {_10_ [$0 112 [| $ii20[ SO] 112 | __‘ $11,200 $11,200 230/115 kV Autotransformer } i [sof 6 T sisoof sof 16 | $1,600] _—$1,600 | Mobilization/Demobilization/Report $3,000] 26 | $2,600[ ‘$5,600 | SUB TOTALS ; $2,215,900 8153: _ $815,300 _ $3,031,200 ENGINEERING 6.50% $197,028 CONSTRUCTION MGMT. 7.00% $212,184 CONTINGENCY 10.00% $303,120 TOTAL $3,743,532 PEI-HLY 120293-01 (4:28 PM3/11/96) ss TABLE SS09 TABLE SS10 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 230 KV Option, Pt. Woronzof Substation UNIT COSTS TOTAL HRS | HRS | UNIT | Circuit Breakers 6 $106,667 | 63.3333 $640,000 $38,000 $678,000 Instrument Transformers and Misc. Equipment 30 $4,700 4 $141,000 | 230/115 kV 150/200 MVA Autotransformer__ | __1_| $1,600,000 | __130 | 230kVReactor ss C“‘CSN!OC*'YS OFC ~ $800,000( 100 [ $10,000[ $800,000[ 100, | _$10,000| _ $810,000 | | 230kV Circuit Switcher sss Ci] SC S| =~ 860,000] 40 | $4,000 _ $60,000] 40. | $4,000 __ $64,000 | $143,900 $278,000 [$421,900 STRUCTURES $66,000 Bus and Inst. Transformer Supports 27 $1,159 $31,300 $44,500 FOUNDATIONS $5,000 $17,000 $600 $16,000 $38,400 $54,400 $600 $21,250 $51,000 $72,250 | 6 | $600 | $18,250| 438 | | $43,800] $62,050 |___ $600 | _ $3,000 | ControlHouse ss C—“‘“‘CSN!CLSCOUG C[ C$250[ 6 ~~ S600 $4,000] 96 [$9,600] _—$13,600 | | Deadend Structures CC“‘C‘dC «SC722:«CO<C(T;“CO;*~C‘QSSOT =~ SSN] $18,000] 432 [| $43,200[ _ $61,200 | CABLE & CONDUIT | CircuitBreakers ss C“‘(CS™;C*LS«(C9SO:«*SYTSCCti‘SHOT_ LIB | $18] $28,500] 171 [$17,100] $45,600 | is_[ a8 Sta Autotransformer 150 $30 | 0.18 $18 $4,500 | _27 $2,700 200 PEI-HLY 120293-01 (4:28 PM3/11/96) ss TABLE SS10 TABLE SS10 - COST ESTIMATING INFORMATION SUBSTATION COST ESTIMATE 230 KV Option, Pt. Woronzof Substation UNIT COSTS TOTAL DESCRIPTION MATERIAL LABOR TERIAL} COST gig cc $5 $4,800 | 30 $3,000 $7,800 } $30,000 $20,000 $50,000 SITE WORK ; . $52,500 ; . $9,075 [91 $9,075 $18,150 CONTROL HOUSE 160 $16,000 $72,000 : $16, 00 $88,000 ROR DC Staion See or tain oot a0] eons 500 [a0 $e 000 S60, F cecieireiaer RCearee x Coane Paes TTT af reese eho pe coe eee 1 Physical Check Out & Misc. Systems LOT $0 36 $3,600 $0 Instrument Transformers 15 $0 2 $200 $0] 30. | $3,000 $3,000 Circuit Breaker 6 $o] 12 $1,200 | 72° | $7,200 $7,200 | CircuitSwither CT CSOT S500] S80 | __ $600[ $600 | | Control, Relay, Metering, &Comm.Panels | _ 11 | $0. | 11.2727] $1,127| S80 2 a tf SUB TOTALS $4,380,375 9526 _‘ $952,575 __ $5,332,950 ENGINEERING 6.50% $346,642 CONSTRUCTION MGMT. 7.00% $373,307 CONTINGENCY 10.00% $533,295 TOTAL $6,586,193 PEI-HLY 120293-01 (4:28 PM3/11/96) ss TABLE SS10 Appendix D TABLE RCO1 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE W) = V UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL LABOR MATERIAL LABOR COST | HRS | UNIT _| | HRS [UNIT | EQUIPMENT ‘ [115 kV, 1200A, SFO Circuit Breaker (ea) | 3] 8100000 60 | 86000] $300,000| 180 _[ $18,000] $318,000 TIS KV. Disc. Sw.1200A (ea) | 3 | _ $10,000 8 | $800] — $30,000 | 24 | 2,400. | $32,400 TISKV, Dise. Sw.1200A (ea) | 2] $1,000 8 | soo] $2,000] 16] 81,600] $3,600, TiiskV,CcvT(ea)———SSCSCSCS 3 | 86,000 4 | $400] $18,000 12 | 1,200 | $19,200 | 115 KV Class Surge Arrestor(ea) | 6 | $7,000 4 | 8400] $42,000] 24 | 2,400] $44,400 | 115 KV Station Post Insulators (ea) | 18] $400 4 | sao] $7200] 72_| 7,200] $14,400 | L1skVReactors ————SSSSCSCSC*iC | 89,000 8 | $800] $54,000] 48 | $4,800] $58,800 ] 115/15 KV 60 MVA Transformer (ea) | 1 _} $500,000 | 100 | 810,000 | $500,000 | 100] — $10,000. | $510,000 [Aluminum Tubular bus w/Fitings (R) | 1800_| _$35[ 05 | $50] — $63,000 | 900 | $90,000 | $153,000 15 kV Class Surge Arestor(ea) | 9 | $6 000[ 4] 8400] 854,000 | 36 | $3,600 | $57,600 [3Phase-20 MVAR Shunt Cap Banks | 2 | $125,000| 40] $4,000] $250,000 | 80] $8,000 | $258,000, Psvecaps Ss SSSSSSC*d C3 825,000 16 | 81,600] — $75,000] 48] 4,800 | $79,800 TsvCReaciors | 3] $8,000| 16 | $1,600] $24,000] 48 | $4,800 | $28,800 | Lot | i2,000[ 40 | $4,000] — $12,000, 40 | 4,000 | $16,000, [Cooling EquipmenControls | LoT_| _ $75,000] 160_| 816,000 $73,000 | 160 | $16,000 | $91, 000 LoT_| —s10,000[ 40 | $4,000 ] $10,000 | 300] [$50,000 | $275,000 | [Fire Protection ___—————*dY CLOT] — $10,000] 40 | $4,000] — 10,000] 40 | — $4,000] $14,000 STRUCTURES (Tapered Tube) | 40 | 500 $50,000 3 0 6 4 [ 11SKVT.0.Tower, 12,000# (@) | 1] Si6o00] 40 | ‘4000 si6o00] 40 | 4000] $00,000, 115 kV, Disc. Sw.,2500# (ea) | 3 | _ $3,000] 12] 1,200] $9,000] 36] $3,600 | $12,600 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO1 TABLE RCO1 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE ITE WORK ~ Vv. UNIT. COSTS TOTAL DESCRIPTION QTY. |MATERIAL MATERIAL pees UNIT ee aS oT [TIS KV Inst. Transformer Support, 7007 (ea) | 3 | S800] 4 | S400] $2,400] 12 | $1,200] $3,600 TIS KV Cap Rack Support, 2000# (ea) | 6 | $2,000 4 | 400] $12,000] 24 | $2,400] $14,400 15 kV Inst. Transformer Support, 600# (ea) 5 $750 4 $400 15 kV Three Phase Bus Support, 1000# (ea) FOUNDATIONS [_1IS kV Breaker, (I) 6x6x2 Slab 3eyea | 9 | $250] 5 | $500] S220] 45 | 94500] 96,750] 15 & 115 kV Three Phase Bus , 2 cy ea. 32 SOND pa SS ee 115 kV Disc. Switch, 2 cy ea. 6 s250[_ 5 [soot $1,so0T 30 [$3,000 [$4,500 | | USKVCapRackiscyea | 24 T8250 5 T8500 $6,000] 120 | $12,000] $18,000 | 115/15 kV Transformer 15'x12'x3', 20 cy ea. | MISKVT.O.Tower,6cyea | 1282505 T 8500 $3,000] 60 | $6,000] $9,000 | | Microwave Tower, 6cy | 188250 5 T8500 $4,so0[ 90 $9,000] $13,500 | [IS KV Disc. Switch, 2cyea ‘| 4 | 820] 5 | $500] 81,000] 20 | $2,000] 3,000 | SVC YardEquipment, 100cy | 100 «| $250 5 [8500 $25,000] 500 | $50,000] $75,000 | | SVC Exchangers 25'x10'xI',9cy | 9 $250] 5 s500 $2,250 45 [$4,500] $6,750] 16500 | $40.02 $2 $50 $5 $15,120 $21,420 $7 [$2] [$50 | 0.008 | SI] $20,640 $75,680 [85 | | $7 F Site Preparation, Site Plus 20 Gqh) | 68800 | 8030] 0.008 | $20,680 ] [575,680 [815,120 P$21,420 | 200 | 850.00 1 | —_s100| $10,000 | 200 | $20,000 | $30,000 PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO1 TABLE RCO! - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 40 MVAR SHUNT CAPS WITH 0-20 MVAR SVC UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTy. [MATERIAL LABOR MATERIAL LABOR COST UNIT | HRS | UNIT Crushed Rock, 6" (sq ft) 51766 $0.30] 0.005 | _—s $1 { $15,530 | 258.83: $25,883 $41,413 CONTROL HOUSE j Prefabricated Control Building, 30'x70' $320,000 $30,000 | $320,000 $30,000 $350,000 Building Aux Systems | 1 [ $50,000[ 80 | $8,000 $50,000 [ 80 | $8,000 $58,000 Testing/Commisioning $35,000 $80,000 $35,000 $80,000 $115,000 SUB TOTALS $2,786,715 $7,918 $791,773 $3,578,488 ENGINEERING 6.50% $232,602 CONSTRUCTION MGMT. 7.00% i $250,494 CONTINGENCY 10.00% $406,158 . TOTAL $4,467,742 PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO1 TABLE RC02 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 20 MV. ~ EXTENDED COSTS UNIT COSTS TOTAL DESCRIPTION MATERIAL COST EQUIPMENT { |_115 kV, 1200A, SF6 Circuit Breaker(ea)___|_1__|_$100,000{ __60_| _$6,000| $100,000] 60 _| $6,000] _ $106,000 | | 115kV, Disc. Sw.,1200A(ea)_ | 4 10,0001 8 | $800] $40,000] 32_ | $3,200] $43,200 | | iskv,ccvr¢a) CT 386,000T 4 S400 18000] 12 | $1,200] $19,200 | TISKV Station Post Insulators ea) | 12_| S400] 4 | 400] $4,800] 48 | 4,800] $9,600 | 115kVDeadend Assembly | 682,500] 3 | $300] $15,000] 18 [$1,800] $16,800 | | 115kVBus/Fittings/Jumpers | 600 | $35] 0.5 | $50] $21,000 300 | $30,000] $51,000 | | 3Phase-20MVARShuntCapBanks ||| $125,000[ 40 $4,000T $125,000] 40 [$4,000 $129,000 | | 1ISkV AirCoreReactors | 389,000 8 $800] $27,000] 24 [$2,400] $29,400 | | Microwave/Communications | “LOT | $12,000| 40_[| $4,000 $12,000 40 | $4,000[__$16,000 | [Piping for TCSC Cooling | Lot | 840,000 | 160 $16,000 | $40,000] 160 $16,000] $56,000 | HeatExchangers CT 4 810,000[ 40 [$4,000] $10,000] 160 [$16,000 $26,000 | |_115kV TCSC Platform w/BusEquipment___|_3_| $1,850,000 |_1000_| $100,000 | $1,850,000 | 3000 | $300,000 [ $2,150,000 | | TCSC Controls/instrumentation/Design | LOT | $750,000| 1000 | $100,000 [$750,000 [_1000_| $100,000 [$850,000 | | Cooling EquipmentControls | LOT [$75,000] 160 | $16,000 $75,000[ 160 [$16,000 | $91,000 | STRUCTURES (Tapered Tube) |_115KV T.O.Tower, 16,000# (ea) | 3 $16,000] _60_ | $6,000 $48,000] 180 [$18,000] $66,000 | |_115kV, Disc. Sw.,2500#(ea) | tT 83,000{ 60 | $6,000[ $3,000 60 [$6,000] $9,000 | [1ISKV Reactor Support, 20007 (ea) | 1 | $2,500] 12 | _si,200| 2,500] 12] 81,200] $3,700] | 115 kV Bus Support, 700#(ea)_ | 6 S1,000T 12 [$1,200 $6,000f 72 | $7,200[ $13,200 | | TCSC Supporting Insulators | 18 | $2,000[ 8 | ssoot $36,000] 144 [$14,400 $50,400 | | TCSCSteel Platforms | 3 815,000[ 40 $4,000] $45,000] 120 [$12,000] $57,000 | | TCSC Tension Insulators | 24 | 8750] 4 $400] $18,000] 96 [$9,600 | $27,600 | [$11,100 PEI-HLY 120293-01 (4:12 PM3/10/96) to . t:/WAR/CHUGACH/0198RC_B.XLS TABLE RC02 TABLE RC02 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE AR 4 UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. {MATERIAL LABOR MATERIAL LABOR COST 3 FOUNDATIONS { TIS KV Breaker, () 6xOK? Seb, Seyen [3 950] 5 _] 3 $500 | __$500 TiS kV Cap Rack (12) @ 1Seyen. | 18 | 250] 5 | 8500] $4,500 90 | $9,000 $13,500 ss Transformer, (I) @2eyea | 2 | 250] 5 | ss00| _$500[ 10_| 1,000] $1,500] HTS KV T.O. Tower, @)6cyea | 18 | 8250] 5 | _8500[ 4,500] 90 | 9,000 | $13,500 [Microwave Tower, @)@6cy | 18 | $250] 5 | 8500| 4,500] 90 | 9,000 | $13,500 | C115 KV Bus Suppor, (6)@ISeyea | 9 | 250] 5 | ss00] $2,250] 45_| 84,500] $6,750 Cast in Place Trenches, 60 7400 | 60_| soo] 0.14 | sia] 824,000] 84] sao] $04,840 | Bypass Breaker, 3) @ 3 ey@ay | 9 | sso] 5 | soo] $2,250] 45_| _$4,500| $6,750 Platform SSS 250 5 | 8500] $8,000] 160 | $16,000] $24,000 | TB.U. Generator, dey —SSCid SY 250 5 | 8500] $1,000] 20 | $2,000] $3,000] CABLE & CONDUIT [ Controi Cabling (R) | 10000] $4] 003 | $3] $40,000] 300_| $90,000] $70,000] LOT | 850,000 60 | $6,000 | $50,000] 60 | $6,000] $56,000 | Site Preparation, Site Plus 20'(q 8) PAceessRoad _———S~s S| $50.00 1 | $100] $2,500] 50 | $5,000] $7,500, Crashed Rock oq) | 33696] s02s] o0oa | so] $8,424 | 194.784] 813,478 | $21,902, CONTROL HOUSE Prefabricated Control Building, 24'x48' $184,000 $30,000 | $184,000 $30,000 $214,000 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS . TABLE RCO02 TABLE RC02 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. {MATERIAL LABOR MATERIAL LABOR COST |_LABOR__| |_—LABOR _ | HRS [UNIT _| | HRS | UNIT _| Building Aux Systems $50,000] 80 | $8,000 $50,000] 80 | $8,000 $58,000 Testing/Commissioning $20,000 $80,000 $20,000 $80,000 $100,000 SUB TOTALS $3,803,719 9649.18 $964,918 — $4,768,637 ENGINEERING 6.50% $309,961 CONSTRUCTION MGMT. 7.00% $333,805 CONTINGENCY 10.00% $541,240 TOTAL $5,953,644 PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RC02 TABLE RC03 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE D V. 138 KV, 10 MVAR REACTOR TOTAL DESCRIPTION QTY. [MATERIAL] LABOR _ [MATERIAL COST PAY RST ONT [ARS [UNIT _ EQUIPMENT 138 kV, Disc. Sw. (ea) |__$i0,000] 8 | soo] $10,000T 8 [$800 $10,800 | Pe emu OP | ce Et Son cTeT TT eso |e | 138kV Station ServicePT | 825,000 5 $500 $25,000 5 T8500] $25,500 | | 138kV Reactor, 1OMVAR_ Tt $350,000 100 [$10,000] $350,000] 100 [$10,000 [$360,000 | |_138kV Deadend Assembly (ea) |_| $2,000] 40 | $4,000] $2,000 40_[ $4,000 $6,000 | |_138kV Station Post Insulator(ea) | 12 | S400 | 4 S400 84,800] 48 $4,800 [$9,600 | | 138kV Bus/Fittings | 870 SGT 035 [$35] $5,920 129.5 [$12,950] $18,870 | |_138kV Surge Arrestors(ea) | 386,000] 4 S400 i800 12 [$i,200 [$19,200 | |_Microwave/Communications | 1 | 812,000] 40 T $4,000T $12,000 40 [_$4,000[ $16,000 | STRUCTURES (Tapered Tube) : |_138KV T.O.Tower, 12,0004 (ea) | 2 | $12,000 40 [$4,000] $24,000 80 [$8,000 [$32,000 | | _138kV, Disc. Sw.,2700#(ea) TT 83,3007 12 $1,200 $3,300 12 $1,200 [$4,500 | |_138 kV Three Phase Bus Support, 2000# (ea) | 2 | $2,000] 8 [soo] $4,000[ 16 [$1,600[ $5,600 | |_138kV Inst. Support, 1200#(ea) | tT $2007 4 S400 si200f 4 s400 $1,600 | |_138 kV Switch Rack, 15,000#(ea) |] 1 $15,007 30 T $3,000T $15,000] 30 [$3,000] $18,000 | FOUNDATIONS [138 KV Three Phase Bus Support, 2ey | 8 | $250] 5 | $500] $2,000] 40 | $4,000] $6,000 138 kV 10 MVAR Reactor, 15x12x2, 13 oy | Microwave Tower,6cy TT 8250s Tss00T$4,so0] 90 [$9,000 | $13,500 | PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS TABLE RC03 DESCRIPTION TABLE RCO03 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 138 KV, 10 MVAR REACTOR | HRS | UNIT _| UNIT COSTS EXTENDED COSTS Qty. [MATERIAL LABOR MATERIAL LABOR | HRS | UNIT _| TOTAL COST 138 kV Circuit Breaker, 3 cy ea. P| 3 fT s2sof 5 | S500 750] 15 {| $1500] $2,250 | p 4 [| s2sof 5 | 8500] $1,000] 20 | $2,000] $3,000 | B. U. Generator, 4 cy Control Enclosure, 16'x16'x1', 9cy | 9 | $250 5 Oil Containment, 25cy ABLE & CONDUIT |) 25 [ s2sof 5 $500 $2,250 45: $4,500 $500 $6,250 125 $12,500 $6,750 | ControlCabling(f) CT 500 TSH 830] $2,000] 150 |] $15,000] __ $17,000 | SITE WORK Site Preparation, Site Plus 20' (sq ft) Fence Grounding, 4/0 Cu, 20 ft. grid (ft) Access Road Crushed Rock, 6" (sq ft) 24500 $0.30 470 $12.00 0.008 |S $7,350] 196 | $19,600| $26,950 | 1550 $6.00 50 $50.00 14946 $0.25 | 0.004 .05 $9,300 | 77.5 $7,750 $17,050 | sioo | _$2,500[_50_[_$5,000[ _ $7,500 | | SOT $3,737 | 59.784] $5,978] $9,715 | CONTROL HOUSE Prefabricated Control Building, 16'x16' LOT $100,000 $8,000] $100,000] 80 | $8,000 $108,000 Building Aux Systems $30,000] 80 | $8,000 $30,000] 80 | $8,000 $38,000 TESTING/COMMISSIONING Testing/Commissioning $5,000 $12,000 $5,000 $12,000 $17,000 SUB TOTALS $774,372 2093.78 __ $209,378 _ $983,750 ENGINEERING 6.50% $63,944 CONSTRUCTION MGMT. 7.00% $68,862 CONTINGENCY 10.00% $111,656 TOTAL $1,228,212 PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO03 TABLE RC04 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE T 138 KV, 22 MVAR REACTOR UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL LABOR MATERIAL LABOR COST EQUIPMENT 31,500 $106,000 [$500] $10,000 | 8 __| $100,000] 60_| $6, 5 $25,000 $500 $25,500 $450,000] 100 _[ $10,000 $460,000 $2,000 $6,000 12 $400 $4,800 | 48 $4,800 $9,600 0.35 $5,920 $18,870 3 4 $18,000 $19,200 40 $12,000 $16,000 138 kV, Disc. Sw. (ea) 138 kV, Circuit Breaker (ea) 138 kV Station Service PT 138 kV Reactor, 22 MVAR 138 kV Deadend Assembly (ea) 138 kV Station Post Insulator (ea) 138 kV Bus/Fittings 138 kV Surge Arrestors (ea) Microwave/Communications w > o STRUCTURES (Tapered Tube) . |_138KV T.O.Tower, 12,000# (ea) | 2 812,000 40 [$4,007 $24,000T 80 [$8,000] $32,000 | |_138kV, Disc. Sw.,2700#(ea) TT 83,3007 12 $1,200 $3,300 12 [$1,200 [$4,500 | |_138kV Three Phase Bus Support, 2000#(ea) | 2 | $2,000] 8 [ ssoof $4,000] 16 [$1,600] $5,600 | |_138kV Inst. Support, 1200#(ea) | tT S1200T 4 S400 si.200f 4 sa00 $1,600 | [138 KV Switch Rack, 15,000# (ea) | 1 | 815,000] 30 | $3,000[ 815,000] 30 | 83,000 | $18,000 FOUNDATIONS |_138kV, Disc.Sw,2cy TT 8250 5 8500 si,000 20 [$2,000 [$3,000 | |_138kV Three Phase Bus Support, 2cy | 8] $250, 5 $500 $2,000 40 [$4,000 $6,000 | 138 kV 22 MVAR Reactor, 15'x12'x2', 13 cy | Microwave Tower,6cy | 8 T8250 5 TT s500T 84,500 90 TT $9,000 [$13,500 | PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RC04 TABLE RC04 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE D. V. 138 KV, 22 MVAR REACTOR UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION MATERIAL MATERIAL COST pe as one aft B. U. Generator, 4 cy 4 $250 Control Enclosure, 16'x16'x1', Icy 9 $250 4 Oil Containment, 25cy CABLE & CONDUIT Control Cabling (ft) Site Preparation, Site Plus 20" (sq ft) | 24500 | _ $0.30] 0.008 [| Si] $7,350] 196 J $19,600] $26,950 | 470 | $12.00] 005 [ss] $5,640] 23.5 [$2,350 $7,990 | Grounding, 4/0 Cu, 20 ft. grid (ft) | AccessRoad ST 50.00T 1 si00T $2,500] 50_ [$5,000 [$7,500 | Crushed Rock, 6" (sq ft) | 14946 | $0.25] 0.004 [Soy $3,737] 59.784] $5,978 |] $9,715 | CONTROL HOUSE |_ Prefabricated Control Building, 16x16 | LOT | $100,000] _80_[ $8,000] $100,000[ 80 [$8,000 [$108,000 | | Building Aux Systems| Ct 830,000T 80 $8,000[ $30,0007 80 [$8,000 $38,000 | SUB TOTALS $874,372 2093.78 $209,378 _$1,083,750 ENGINEERING 6.50% $70,444 CONSTRUCTION MGMT. 7.00% $75,862 CONTINGENCY 10.00% $123,006 TOTAL $1,353,062 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS : TABLE RC04 TABLE RC05 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 230 KV, 22 MVAR REACTOR TOTAL DESCRIPTION ev. ar | ___ LABOR __|MATERIAL| LABOR. _—«|_—s COST a a EQUIPMENT | 230 KV, Disc. Sw.(ea) | tT $10,000] 28 $2,800 $10,000 28 T$2,800T $12,800 | |_230kV, Circuit Breaker(ea) | tT $140,000T 80 $8,000 | $140,000[ 80 [$8,000 [$148,000 | |_230kV Station ServicePT | tT $30,000 16 [$1,600] $30,000[ 16 [$1,600] $31,600 | | 230kV Reactor, 22MVAR_ | $575,000 120 | $12,000] $575,000] 120 [$12,000 [$587,000 | |_230 kV Deadend Assembly (ea) |_| $3,000 40 | $4,000T $3,000 40 [$4,000 [$7,000 | |_230 kV Station Post Insulator(ea) | 12 | S400 4 Tsao $4.800] 48 $4,800 [$9,600 | |_230kV Surge Arrestors(ea) | 3 88,000T 4 s400 $24,000 12 $1,200 | $25,200 | |_Microwave/Communications Tt 812,0007 40 T$4,000[$12,000[ 40 [$4,000 $16,000 | STRUCTURES (Tapered Tube) |_230 kV T.O.Tower, 12,000# (ea) | 2 $12,000 60 T$6,000T$24,000[ 120 JT $12,000T $36,000 | |_230 kV, Disc. Sw. 3000#(ea) | 83,500 16 Tsi6o0 | $3,500[ 16 [$1,600 [$5,100 | |_230 kV Three Phase Bus Support, 2000#(ea) [2 [$2,000] 6 [| s600[—$4,000[ 12 $1,200] $5,200, |_230kV Inst. Support, 1000#(ea) | tT Sitoof 4 sa00sit0o[ 4 [$400] ‘$1,500 | |_230 kV Switch Rack, 18,000#(ea) Tt $20,000T 60 [$6,000] $20,000T 60 [$6,000 [$26,000 | FOUNDATIONS | 230KV T.O.Tower,8cy 32 T8250] ST 8500 $8,000 160 [$16,000] $24,000 | |_230kV, Disc.Sw.3cy T8250 5 S500 81,500 30 $3,000 [$4,500 | |_230kV Three Phase Bus Support, 3cy [|_ 12, «| $2sof 5 [s500[ $3,000 60 | $6,000] —_$9,000 | | 230KV Inst. Transformer, 3cy | 3 | S250f 5 Tsso0] 8750s $1,500, $2,250 230 kV 22 MVAR Reactor, 18153, 30ey | 30 | $250] 5 | $500] $7,500] 150 | $15,000] $22,500 |_230kV Switch Rack, cy 32 sss T s500 [$8,000] 160 [$16,000 | _ $24,000 | Microwave Tower, 6 cy | is [ s2sof 5 T sso0T$4,so0[ 90 [$9,000 [$13,500 | PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RC05 TABLE RCOS5 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE Vv. 230 KV, 22 MVAR REACTOR UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL MATERIAL COST 230 kV Circuit Breaker, 5 cy (ea) $3,750 | B.U.Generator,4cy TT 8250] 58500] $1,000| 20 [$2,000] $3,000 | Control Enclosure, 16'x16'x1', 9cy } 9 | $250 $500 $2,250 $4,500 $6,750 Oil Containment, 30 cy $250 $15,000 | $22,500 CABLE & CONDUIT Control Cabling (ft) | 600 | $4] 003 | 3] 82,400] 18 [$1,800 $4,200 SITE WORK Site Preparation, Site Plus 20' (sq ft) 0.008 $8,100 $29,700 $12.00 $2,500 Grounding, 4/0 Cu, 20 ft. grid (ft) $10,200 $18,700 $50.00] 1 [ sioo{ $2,500] s0_| $5,000 Crushed Rock, 6" (sq ft) 0.004 | $0 | $4,228 | 67.648 $10,993 CONTROL HOUSE Prefabricated Control Building, 16'x16' $100,000] 80 | $8,000 | $100,000] 80 | $8,000] $108,000 Building Aux Systems Yi [$30,000] 80 [ $8,o00[ $30,000[ 80 | $8,000 TESTING/COMMISSIONING Testing/Commissioning $5,000 $12,000 $12,000 $17,000 SUB TOTALS $1,078,028 2427.65 $242,765 _ $1,320,793 ENGINEERING 6.50% $85,852 CONSTRUCTION MGMT. 7.00% $92,455 CONTINGENCY 10.00% $149,910 TOTAL $1,649,010 PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO05 TABLE RC06 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE NV. 230 KV, 60 MVAR REACTOR UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL LABOR MATERIAL LABOR COST | | a rn | a rn EQUIPMENT [230 KV, Disc. Sw. (ea) 810,00 | 38 [92,800] $10,000 28 | $9,800 | 810,800 [a0ny, ceeukBsertey— 1 fsa sof sepoo | stanano {tf ston srstgon 230 kV Station Service PT $30,000 | 16 $1,600] $30,000] 16 | $1,600] $31,600 | [330 kV Reactor, 60 MVAR| 1} $625,000 | 120 | 812,000 | $625,000 | 120 | $12,000 | $637,000, [330 kV Deadend Assembly (ea) [1 | $3,000] 40 | $4000] $3,000] 40 | $4,000] $7,000 [230 kV Station Post Insulator (ca) | 12_| sao 4 | sao0] _sa,g00] 48_| 4,800] $9,600, T‘Microwave/Communications | 1 | 812,000| —40_| 4,000] 12,000 40 | $4,000 | $16,000 | STRUCTURES (Tapered Tube) | 230 kV T.O.Tower, 12,0004 (ca) | 2 [$12,000] 60 | $6,000] $24,000 120 | $12,000] $36,000 | | 230 kV, Disc. Sw. 3000#(ea) | tf 83,500] 16 | $i600T $3,500] 16 | $i,600] $5,100 | |_230 kV Three Phase Bus Support, 2000# (ea) | 2 | $2,000] 6 [ sooo[ $4,000[ 12 [$1,200] $5,200 | [230KV Inst. Support, 1000# (ea) ————Ss| 1 (| _Si,t00[ 4 | 400] si,100] 4 | $400] $1,500 230 kV Switch Rack, 18,000# (ea) 1 $20,000[ 60 | $6,000] $20,000] 60 | $6,000] — $26,000 | 230 kV T.O.Tower, 8 cy $500 | _$8,000[ 160 [$16,000] $24,000 | 230 kV, Disc. Sw., 3 cy 6 $250 230 kV Three Phase Bus Support, 3 ey a 230 kV Inst. Transformer, 3 cy 3 $250 | 230kV SwitchRack,8cy | 32 | S250 5 | s500] $8,000] 160 | $16,000] $24,000 | | Microwave Tower,6cy dT 18 T8250] 5 Ts500T$4,so0f 90 [$9,000] $13,500 | PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS ‘ TABLE RC06 TABLE RC06 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 230 KV, 60 MVAR REACTOR UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. [MATERIAL] LABOR _ [MATERIAL LABOR COST | HRS | __UNIT_| | HRS [UNIT _| 230 kV Circuit Breaker, 5 cy (ea) ; 5 [| s2sof 5 | 8500] 1,250{ 25 | $2,500 $3,750 | B.U.Generator,4cy CT 250 5500 $1,000] 20 | _ $2,000 $3,000 Control Enclosure, 16'x16'x1', 9cy | 9 | $250 $500 $250 $500 $750 Oil Containment, 35 cy $250 $500 $8,750 $17,500 $26,250 CABLE & CONDUIT Control Cabling (ft) | 600 [ $4f_ 003 | s3___—$2,400 $1,800 $4,200 SITE WORK : Site Preparation, Site Plus 20 (qf) $0.30 $8,100 $12.00 $2,500 | $8,500 Grounding, 4/0 Cu, 20 ft. grid (ft) 1700 $10,200 $8,500 $18,700 | AccessRoad | 5 T5000] 1 | S100 $2,500 $5,000 $7,500 Crushed Rock, 6” (sq ft) $0.25] 0.004 | So] $4,228 $6,765 | _$10,993 CONTROL HOUSE Prefabricated Control Building, 16'x16' $100,000] 80 | $8,000 | $100,000] 80 | $8,000 Building Aux Systems | 1 [$30,000] 80 | $8,000 $30,000] 80 | $8,000 $38,000 TESTING/COMMISSIONING Testing/Commissioning $5,000 $12,000 $5,000 $12,000 $17,000 SUB TOTALS $1,127,278 2412.65 $241,265 $1,368,543 ENGINEERING 6.50% $88,955 CONSTRUCTION MGMT. 7.00% ; $95,798 CONTINGENCY 10.00% , $155,330 TOTAL $1,708,626 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS TABLE RC06 TABLE RC07 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE TOTAL UNIT COSTS EXTENDED COSTS DESCRIPTION QTY. [MATERIAL| LABOR _ [MATERIAL COST a as To EQUIPMENT | 138kV, Disc. Sw.(ea) 28100007 8 $800 $20,000T 16 [$1,600] $21,600 | | 138KV, Circuit Breaker(ea) | 2 | $100,000| 60 | $6,000 $200,000 120 | _ $12,000 | _$212,000 [138KV Station ServicePT sd | _$25,000[ 5 | ss00| $25,000] 5 | $500] $25,500 | | 138kV Reactor, 1OMVAR | St $350,000] 100 | $10,000] $350,000 | 100 [$10,000 | $360,000 | | 138kV Reactor, 30MVAR__— | $425,000] 100 [$10,000] $425,000 | 100 [$10,000 | $435,000 | |_138kV Deadend Assembly (ea) | tT $2,000] 40 [$4,000] $2,000 40 $4,000 $6,000 | [138KV Station Post Insulator(ea) [| 9 | $400] 4 | S400] $3,600] 36 | $3,600] $7,200 |_138kV Surge Arrestors(ea) | $7,000] 4 S400] $42,001 24 [$2,400] $44,400 | |_Microwave/Communications | 1 | $12,000] 40 [$4,000 $12,000 40 [$4,000] $16,000 | STRUCTURES (Tapered Tube) . |_138KV T.O.Tower, 10,000# (ea) | 2 | $10,000] 40 [$4,000] $20,000T 80 [$8,000 [$28,000 | |_138kV Three Phase Bus Support, 2000#(ea) | 1 | $2,000] 8 [ ssoo[_$2,000[ 8 S800 $2,800 | |_138kV Inst. Support, 1200# (ea) | tT 81,200T 4 S400 $i200f 4 s400 [$1,600 | |_138 kV Switch Rack, 15,000#(ea)_ | 815,000] 30 [T $3,000T $15,000 30 [$3,000 $18,000 | FOUNDATIONS |_138KV, Disc.Sw.2cy TT 82505 8500 [$2,000 40 [$4,000] $6,000 | |_138kV Three Phase Bus Support, 2cy | 4_ | $250] 5 $500 $1,000 20 [$2,000 $3,000 | 138 kV 30 MVAR Reactor, 18'x15'x3', 30 cy 150 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO7 TABLE RCO7 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE E +. TOTAL DESCRIPTION MATERIAL CARS [UNIT ARS [UNIT Microwave Tower, cy] 18 [| s250| —s_| $500] 4,500 | 90 | $9,000 | $13,500 138 KV Circuit Breaker, Seyea | 6 | 8250] 5 | $500[ 81,500] 30 | $3,000[ $4,500 YB-U. Generator, dey ———SSC~i iY sf 5] $500] 1,000] 20 | $2,000] 3,000] Control Enclosure, 16x1GXP, Sey 9 [8250] 5 | 8500 $2,250 45 | $4,500 | $6,750 | CABLE & CONDUIT F Control Cabling (@) | 1000 |] 03 [| so] sooo] 300 | $30,000] $34,000 SITE WORK Site Preparation, Ste Plus 20 qf) [29400 | s0.03] 0008 |__| S080] 2352 | W03520] S040 | Grounding, 470 Ca, 20 Ri ard (8) 2500 TAceessRoad————SSSSC~*t SS $50.00 1 | 8100] $2,500] 50] $5,000] $7,500, Crushed Rock oq) | 18656 | s02s] o0oa | so] $4,064] Ta.ora | $7,462] 812,126, CONTROL HOUSE : | Prefabricated Control Building, 16x16 LOT] $100000| #0 | 88000] 8100000] 80 | 8,000] $108,000 | Building Aux Systems| 1 | _ $30,000] 80 | $8,000 — $30,000] 80 | $8,000 $38,000 TESTING/COMMISSIONING SUB TOTALS $1,353,551 3461.32 $346,132 $1,699,683 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO7 TABLE RCO07 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE + UNIT COSTS EXTENDED COSTS TOTAL DESCRIPTION QTY. |MATERIAL LABOR MATERIAL LABOR COST Pars [UNIT [ARS [UNIT ENGINEERING 6.50% : $110,479 CONSTRUCTION MGMT. 7.00% $118,978 CONTINGENCY 10.00% : $192,914 TOTAL $2,122,055 PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS . TABLE RCO7 TABLE RCO08 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE 4h TOTAL DESCRIPTION QTY. MATERIAL] LABOR __—+|_— COST See ee a | 230KV, Circuit Breaker(ea)———s—SSSC*d|~S 2 ~—«d|~=(8140,000| 80 $8,000] $280,000] 160 | $16,000] $296,000 | | 230KV Station ServicePT S| St} S| ~$30,000T 8 [$800] $30,000] 8 | $800] $30,800 | | 230kV Reactor, 30MVAR_T SL $525,000] 100 | $10,000] $525,000 | 100_| $10,000] _ $535,000 | [230KkV Reactor, 40MVAR_ | StS $575,000 100 | $10,000] $575,000[ _100_| $10,000] $585,000 | | 230kV Deadend Assembly (ea) ——Ss—sd|_ =~ SC|~—$2,000] 40 $4,000] $2,000] 40_—| $4,000] $6,000 | | 230KV Station PostInsulator(ea) —ss—sd|_ = =| ~SS S400 4 | S400] 83,600] 36 | $3,600] $7,200 | [230KkV Surge Arrestors(ea) SCT S| 87,000] 4 | S400] $42,000 24 [$2,400] $44,400 | | Microwave/Communications _———s| 3S| S| = $12,000 40 [$4,000] $12,000] 40 | *$4,000[ $16,000 | STRUCTURES (Tapered Tube) | 230kV T.O.Tower, 12,000# (ea) _—Ss—s|_ 2 ~—CdT $12,000 60 | $6,000] $24,000] 120 | $12,000] $36,000 | | 230KV, Disc. Sw. 3000#(ea) | =O TS 83,500] 16 = $1,600] $7,000] 32_ | $3,200] $10,200 | [230 kV Three Phase Bus Support, 2000#(ea) [1 [$2,000] 6 [| $600{__—$2,000] 6 | $600] $2,600 | | 230kV Inst. Support, 1000#(ea)———Cs| ST CT S00] 4 | S400TSitoof 4 | $400] $1,500 | 230 KV Switch Rack, 18,000#(ea)__—s—sd|_ 1 T—$20,000] 60 [$6,000 $20,000] 60 | $6,000] $26,000 | FOUNDATIONS , | 230kVT.O.Tower,8cy Ss] 32ST S250 5 T8500] $8,000] 160 [$16,000] $24,000 | | __ $3,000] 60 _[ $6,000{ __ $9,000 | | 230kV Three Phase Bus Support, 3cy | 6 T8250 5 230 kV 30 MVAR Reactor, 18'x15'x3', 30cy_| 30 | __$250 | 230 kV 40 MVAR Reactor, 20x15'x3, 33cy [33] $250 | PEI-HLY 120293-01 (4:12 PM3/10/96) to r:/WAR/CHUGACH/0198RC_B.XLS TABLE RCO8 TABLE RC08 - COST ESTIMATING INFORMATION REACTIVE COMPENSATION COST ESTIMATE [S30 KV Switch Rack Bey ———~dY(C «dT SSS —«SS0O YT 88000] 160] $16,000| 924,000] | Microwave Tower, Gey] 18 | 250] 5 | 8500] 4,500] 90 | $9,000| $13,500 [Control Enclosure, 16x16xT, Sey | 9 | 8250] 5 | $500] _82.250| 45 | 84,500 $6,750 Foi Containment, 35ey | 35] sso] 5 | 8500] 88,750] 175 | $17,500 | $26,250 CABLE & CONDUIT Control Cabling (ft) SITE WORK | S4f_ 03 | $30] _—$4,000T 300 J $30,000] $34,000 | F Site Preparation, Ste Pls 20GqA) | 32850] 8030] 0008 | Si] 99855] 2008 | sv6280| 990,155) FAccessRoad _——SSSSSCS~*d C80 | _850.00[ 1 | S100] $2,500 50 | $5,000 $7,500] Crushed Rock, © Ga) 21392 | s025[ 0004 | so] $5348 | 85.568 | 88,557 | $13,905] CONTROL HOUSE | | Prefabricated Control Building, 16x16 | LOT [| $100,000] 80 | $8,000] $100,000] 80 | $8,000 | —s108,000, [Building Aux Systems___—_—_—~——~|_1 | $30,000] 80 | $8,000] — $30,000] 80 | 8,000] $38,000, TESTING/COMMISSIONING Testing/Commissioning $8,000 | 140 | $14,000 $8,000]. 140 [ $14,000 $22,000 SUB TOTALS $1,795,237 3263.47 __ $326,347 __ $2,121,584 ENGINEERING 6.50% . $137,903 CONSTRUCTION MGMT. 7.00% $148,511 CONTINGENCY 10.00% $240,800 TOTAL $2,648,797 PEI-HLY 120293-01 (4:12 PM3/10/96) to t:/WAR/CHUGACH/0198RC_B.XLS : TABLE RCO08 1 1 2 I 3 I 4 | 5 6 7 280-0" i‘ r e —. . mee . ° = - - . : - { 30 Bus SUPPORT aieckee OIL CONTAINMENT HEAT EXCHANGERS CIF REQUIRED) — ae oO) { 30 Slat 20 MVAR | SHUNT CAP SO 6 lo FILTER CAPACITORS BANK l x | AND REACTORS 1S A eS 175-0" © 9 CAPACITOR AREA 50-0" 115KV T.0. TOWER 6° INTERIOR FENCE WITH OUT BARBED WIRE REACTOR AREA TSC SUBSTATION AND SVC CONTROL BUILDING 30° x 70° Ha | SHUNT CAP LAYOUT APPLICABLE FOR THE FOLLOWING LOCATION BANK : an { ¢ EXISTING 115KV INTERTIE. NEW SITE NEAR PORTAGE i | a ut VILLA : au : ut . AECL x : : : ete me UE HL iH : Ls THIS DRAWING WAS PREPARED BY POMK OSGN TO 3/96 SOUTHERN INTERTIE zi oon ch ono te POWER EXISTING INTERTIE fs mo toa SCALE: 1” = 20'-0" EORIACERSUS: ts PaOUDITED URLSS waITTEn PURaSStOH TSSUED WITH REPORT 3240 GLENBROOK ORI VE 40 MVAR SHUNT CAPACITOR Se ee REV REVISIONS OATE | DRN |OSGN| CKD [APPD REFERENCE DRAWINGS For 11017 Dw one BANK WITH +/- 20 MVAR SVC [cranteo. B-MAR-1996 15136 JOB NUMBER 120293.02 FIGURE NO |REV RC-01 |A\ ‘fusz.tb! | re0l.agn | TO LINE VOLTAGE INSULATED 3 20MVAR SHUNT CAPBANK © PLATFORMS CAPS RACKS (TYP) AL PI DISC SW. AND BYPASS DISC SW DISC SW. AND BYPASS DISC SW T.0. TOWER. ISOLATING. G 1.0. TOWER» ISOLATING, ¢ 1.0. TOWER |< LAYOUT APPLICABLE FOR THE FOLLOWING LOCATION ¢ EXISTING 115KV INTERTIE. NEW SITE NEAR PORTAGE VISKV LINE 115KV LINE } THYRISTOR HOUSING 5" REACTORS. (TYP) BYPASS. BREAKER (ONE PER PHASE) PIPING AND CABLE TRENCH HEAT EXCHANGERS (TYP) CONTROL /COOL ING BUILDING [| (24"-0" x 48'-0") NOTES 1. BUS CONNECTIONS ON PLATFORM ARE NOT SHOWN. 20'-0" DRIVE GATE Tile Daavine ¥iS PREPIRED BY PORT TWO] 02/96 SOUTHERN INTERTIE encinetrs, Inc. FOR & SPECIFIC PROUECT tcw__| 02/96 taxi ro cosioeat ion SFI EXISTING INTERTIE 120293.02 cust OF WIS ORABING OR ANT In CATION SCALE TIN SSIIO EO: PORTAGE SUB DRAWING NO p TSSUED_WITH REPORT Rae ENBaRO’ BS55s 4OMVAR THY CONTROLLED SERIES ey cous en Penen se fomee 5 ae | REVISIONS REFERENCE DRAWINGS FOR 11417 ec wy CAPS (TCSC)_& ZOMVAR SHUNT CAP BANK RCc-— Touantose tsr37 | turener ] reo8-aon | STATION SERVICE PT LAYOUT APPLICABLE FOR THE FOLLOWING LOCATIONS QUARTZ CREEK CORRIDOR - BIRD POINT - 138KV 10MVAR QUARTZ CREEK CORRIDOR - SNIPERS POINT - 138KY 10MVAR SUBLARINE ENSTAR CORRIDOR - POTTERS MARSH - 138KV 22MVAR eae ENSTAR CORRIDOR - BURNT ISLAND CREEK - 138KV 22MVAR OVERHE AD TRANSMISSION LINE CABLE TERMINATION STRUCTURE WITH JACK BUS FOR 4TH CABLE BACK-UP GEN 16° x 16° CONTROL ENCLOSURE MICRO WAVE TOWER y OIL CONTAINMENT 20'-0" DRIVE GATE NOTES 1. REACTOR SIZE SHOWN TYPICAL FOR PRIMARY VOLTAGE ONLY. SIZES WILL VARY SLIGHTLY WITH MVAR RATING. cin ene Ins TON 1 SCCIIC POC. To SOUTHERN INTERTIE JOB NUMBER TAKING INTO CONSIDERATION THE SPECIFIC Le 120293.02 pest or ns main chs Oa UNDERGROUND TO OVERHEAD FIGURE NO |REV SCALE: 1” = 20'-0" TRANSITION SITE TSSUED FOR APPROVAL BasceENBANOY SESS WITH REACTOR HAILEY. IDAHO 63333 REVISIONS REFERENCE DRAWINGS FOR 11x17 DwG OY O-MAR-1996 10141 STATION SERVICE PT LAYOUT APPLICABLE FOR THE FOLLOWING LOCATIONS © QUARTZ CREEK CORRIDOR - BIRD POINT - 230KV 22MVAR © QUARTZ CREEK CORRIDOR - SNIPERS POINT - 230KV 22MVAR SUBMARINE © ENSTAR CORRIDOR - POTTERS MARSH - 230KV GOMVAR CABLE ROUTE © ENSTAR CORRIDOR - BURNT ISLAND CREEK - 230KV GOMVAR OVERHEAD TRANSMISSION LINE CABLE TERMINATION STRUCTURE WITH JACK BUS FOR 4TH CABLE BACK-UP GEN 16’ x 16° CONTROL ENCLOSURE J MICRO WAVE TOWER aaa eae DARA EBAREN 20°-0" DRIVE GATE OIL CONTAINMENT NOTES 1. REACTOR SIZE SHOWN TYPICAL FOR PRIMARY VOLTAGE ONLY. SIZES WILL VARY SLIGHTLY WITH MVAR RATING. incense In. FORD SPECIFIC PROICT, Two SOUTHERN INTERTIE JOB NUMBER Lo 120293.02 TAKING INTO CONSIDERATION THE SPECIFIC fs sono ee a UNDERGROUND TO OVERHEAD S [cURETNOTMIREY JRCUSE OF THIS DRAWING OR say INF OFDAT ON] 1” = 20'-0" TRANSITION SITE CONTAINED IM THIS DRAWING FOR any PURPOSE 1S PROVIBITED UNLESS. WRITTEN PERS TSSUED FOR APPROVAL ioe enanae oes WITH REACTOR aon PORER Ma POMER'S CLIENT I'S REVISIONS REFERENCE DRAWINGS FOR 11x17 Dw OMY B-MaR-1996 Tora? THIS DRAWING WAS PREPARED BY POWER JEMGIMEERS. INC. FOR A SPECIFIC PROUE TAKING INTO CONSIDERATION THE SPECI OF Te PRO ax UM IOUE REQUIRE REUSE OF THIS DRAWING OR [CONTAINED IH THIS ORAWING FOR amy PURPOSE 1S PROMIBITED UNLESS WRITTEN PERMISSION | FROM BOTH POWER AMD PORER'S CLIENT I'S) OVERHE AD TRANSMISSION ————=y LINE STATION SERVICE PT CABLE TERMINATION STRUCTURE WITH JACK BUS FOR 4TH CABLE UNDERGROUND OR SUBMARINE CABLE ROUTE 170'-0" LAYOUT APPLICABLE FOR THE FOLLOWING LOCATION © TESORO CORRIDOR - POINT POSSESION - 138KV 1-10MVAR AND 1-30MVAR REACTOR NOTES 1. REACTOR SIZE SHOWN TYPICAL FOR PRIMARY VOLTAGE ONLY. SIZES WILL VARY SLIGHTLY WITH MVAR RATING. 2. 1-30MVAR REACTOR WILL ALSO BE ADDED AT PT. WORONZOF SUBSTATION. SOUTHERN INTERTIE JOB NUMBER 120293.02 GR DOWER UNDERGROUND TO OVERHEAD SCALE: 1” = 20-0" TRANSITION SITE FCs eis 3940 GLENBROOK ORI VE HAILEY, IDAHO 63333 WITH REACTORS } + + MICRO WAVE TOWER OIL CONTAINMENT 20'-0" DRIVE GATE = - = 7 — —— 4 TWO 03/96 LCM 03/96 TSSUED_FOR APPROVAL T REV REVISIONS DATE | ORN |DSGN| CKD REFERENCE DRAWINGS FOR 11x17 DwG OMY RC-05 |A B-MAR-1996 10112 fulsz.tb! | _rc05.dgn STATION | LAYOUT APPLICABLE FOR THE FOLLOWING LOCATION SERVICE ay ¢ TESORO CORRIDOR - POINT POSSESION - 230KV 1-30MVAR AND 1-40MVAR REACTOR OVERHEAD TRANSMISS JON Cie UNDERGROUND OR ‘> SUBMARINE A CABLE ROUTE 3 CABLE TERMINATION STRUCTURE WITH JACK BUS FOR 4TH CABLE 16° x 16° CONTROL ENCLOSURE MICRO WAVE TOWER 20'-0" DRIVE GATE OIL CONTAINMENT NOTES REACTOR SIZE SHOWN TYPICAL FOR PRIMARY VOLTAGE ONLY. SIZES WILL VARY SLIGHTLY WITH MVAR RATING. 1-75MVAR REACTOR WILL ALSO BE ADDED AT PT. WORONZOF SUBSTATION. TAKING INTO CONSIDERATION THE SPECIFIC racine rae | SOUTHERN INTERTIE | cine Ins TORK SCIFI FOIE, SOUTHERN INTERTIE JOB NUMBER 120293.02 XO UNIQUE REQUIREMENTS OF THE PROKCT. UNDERGROUND TO OVERHEAD fem nr Fined : 3940 GLENBROOK DRIVE TRANSITION SI TE ee Me ae ie manne WRESS TICK PUMA . WITH REACTORS = cmented ape | REVISIONS REFERENCE DRAWINGS Oe ee ae RC-06 |A (B-MAR-1996 10141