Loading...
HomeMy WebLinkAboutS. Intertie Phase 1 6-14-1996 landPROJECT NO: 120293-01 ) YY, ISSUED TO. MoO ronan QR DMT SUED TO" CHUGACH ELECTRIC ASSOCIATION, INC. CONTRACT NO. 95-208 SOUTHERN INTERTIE ROUTE SELECTION STUDY PHASE 1 June 14, 1996 FINAL LANDS / REGULATORY SECTION REPORT FOR INFORMATION CONTACT: = Randy Pollock, P.E. ™ Frank Rowland =» Tim Ostermeier, P.E. POWER ENGINEERS, INC. @ P.O. BOX 1066 @ HAILEY, IDAHO 83333 (208) 788-3456 @ FAX (208) 788-2082 SOUTHERN INTERTIE ROUTE SELECTION STUDY PHASE I LAND / REGULATORY SECTION REPORT TABLE OF CONTENTS INTRODUCTION 1 OVERVIEW 1 PROJECT REVIEW PROCESS 2 e Federal 2 e National Environmental Policy Act (NEPA) 3 e Section 404 and Related Permit Requirements 6 e EPA-Related Requirements 6 e Federal Aviation Administration, U.S. Forest Service, and Bureau of Land Management 7 e State of Alaska 7 e Division of Governmental Coordination 7 ¢ Municipality of Anchorage 9 e Kenai Peninsula Borough 10 CORRIDOR-SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS 10 e Quartz Creek 12 e Enstar 12 e Tesoro 12 e Klatt Corridor 13 PRIVATE LAND EASEMENT ACQUISITION 13 APPENDIX A — CORRIDOR-SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS APPENDIX B — LIST OF ACRONYMS APPENDIX C — SAMPLE RIGHT-OF-WAY PROCEDURES MANUAL HLY 24-057 (06/96) Final 120293-01/ab i LAND/REGULATORY SECTION REPORT INTRODUCTION This section provides a description of the compliance requirements anticipated for the Southern Intertie Project prior to its construction and operation. The section describes the permits, clearances and other authorizations, and their associated procedures required by federal, -envirenmental-and- -other-administrative-regulations, state statutes, and local ordinances that may apply to the construction and operation of the line and the acquisition of its right-of-way. These permitting and right-of-way acquisition processes apply generally to the entire study area. The specific application of individual permits, easements, or other authorizations would be known only when a preferred alternative is selected through the appropriate federal, state, and local approval processes. Federal, State of Alaska, and local permits and authorizations are summarized in Appendix A. In addition, Table 1, located in the Private Land and Easement Acquisition Section, summarizes private lands within each alternative corridor and its sub-links that would require the acquisition of transmission line easements. In order to better understand the relationship between the following text and the project study area, refer to the Alternative Corridor Map, and the Jurisdiction/Ownership Map, found in the pocket inside the back cover of this report. Also described in this section are the agency review processes for obtaining the necessary permits and approvals and a description of permitting constraints relative to each of the alternative corridors under consideration. Specific permit conditions and monitoring are not discussed as they cannot be known until a final centerline is identified. Because it is not now known which potential permits would be required for the ultimately selected route, individual permit application forms have not been included with this report. However, these forms are readily available once a route is approved and their use determined. OVERVIEW There are currently three major alternative transmission line corridors under consideration (see Alternative Corridor Map). The three major alternative corridors are referred to as: e Tesoro Route (TE), which roughly parallels the existing Tesoro Pipeline Route along the western coast of the Kenai Peninsula e Enstar Route (EN), which roughly parallels the existing Enstar Pipeline route through the Kenai National Wildlife Refuge HLY 24-057 (6/96) Final 120293-01/ab 1 e Quartz Creek Route (QC), which follows the existing Quartz Creek transmission line that parallels the Seward and Sterling highways. The TE and EN routes would require the construction of an electrical submarine cable; the QC route may or may not. The QC alternative has an optional route that deviates from the existing transmission line at the intersection of the Seward and Hope highways. This alternative segment follows an existing electrical distribution line north to Snipers Point located on the south shore of the Turnagain-Arm -Fwe eptions-exist-for-crossing-the Furnagain-Arm~at-this point: an aerial crossing at Bird Point (QC.D.1.A), and a submarine crossing (QC.D.1.B). Both optional routes at this location intersect the existing QC Transmission Line directly north of Bird Point. In addition to describing the general permitting and right-of-way acquisition process, this report section describes the relationship between the National Environmental Policy Act (NEPA) and other federal and state permits that would be required for the three study corridors. Again, note that potentially required federal, state and local permits are summarized in Appendix A. Note also, because of the number of acronyms associated with agency permitting, an acronym glossary is included as Appendix B. HLY 24-057 (6/96) Final 120293-01/ab 2 PROJECT REVIEW PROCESS The majority of all federal, state and local permitting processes require public review and solicit public comment. Permits often require public notification that a proposed project is available for review while other permits, primarily local government permits, often require public hearings within the community potentially being affected. An example of a permit requiring public notice and hearings is the U.S. Army Engineer District (USAED) Section 404 Permit. FEDERAL REQUIREMENTS Federal permitting requirements described in this section include: National Environmental Policy Act (NEPA) National Pollutant Discharge Elimination System (NPDES) - administered by the Environmental Protection Agency (EPA) Spill Prevention, Control and Countermeasure (SPCC) - administered by the EPA Section 106 - administered by the State Historic Preservation Office (SHPO) Section 404 - administered by the USAED Section 7 - administered by the U.S. Fish and Wildlife Service (USFWS) Special Use Permits - administered by the U.S. Forest Service (USFS) Grant of Right of Way - administered by the Bureau of Land Management (BLM) National Environmental Policy Act (NEPA) NEPA (Public Law 91-190, 42 USC 4321 et seq.) establishes policy, sets goals, and provides means for carrying out the policy of protecting the nation’s environment. In 1978, the Council on Environmental Quality (CEQ) issued regulations for implementing the procedural provisions of NEPA (40 CFR Parts 1500-1508). Because the Southern Intertie Project includes a federal action that could significantly affect the human environment, it requires consideration under NEPA. “Federal actions” include projects and programs entirely or partially “financed, assisted, conducted, regulated, or approved by federal agencies.” The Southern Intertie Project would involve federal lands and numerous permits and approvals from federal agencies. An EIS is required when potential significant impacts and/or public controversy have been identified at the onset of the project. An environmental assessment (EA), is typically prepared when the potential for significant impacts is either not anticipated or unknown. Agency representatives indicate that an EIS will be required and that the Rural Utility Service (RUS) will, most likely, be the lead federal agency. The final determination as to the level of study required (EA versus EIS) will be decided upon by the lead federal agency. HLY 24-057 (6/96) Final 120293-01/ab 3 The federal NEPA process is illustrated in Figure 1. NEPA required the designation of a federal lead agency to oversee preparation of the EA/JEIS and to issue the Record of Decision on the proposed project. If there is a potential interest on the part of other federal agencies with jurisdiction to participate in the NEPA process, the lead agency must consider their involvement as a cooperating agency. Agencies may request that the lead agency designate them as cooperating agencies. In this role, cooperating agencies are invited to participate in determining the direction of the study and assist in providing information and staff to support the efforts associated with the NEPA process. For the Southern Intertie Project, a variety of agencies may need to be considered as cooperating agencies, such as the USFWS, USFS, and USAED. The lead agency would take the lead in developing a Memorandum of Understanding for the purpose of defining and clarifying the roles and responsibilities of the agencies, project proponent, and third- party contractor. The third-party contractor in this case is environmental consultant conducting the environmental studies and preparing the EA/EIS under the direction of the lead federal agency. typical EA/EIS document will have the following major sections: e Executive Summary — adequately and accurately summarizes the document and stresses major conclusions, areas of controversy, and issues to be resolved e Purpose and Need - briefly specifies the underlying purpose and need for the project e Alternatives Including the Proposed Action - presents the environmental impacts of and alternatives to the proposed project, in comparative form, providing a clear choice among options for the lead agency e Affected Environment - succinctly describes the environment of the area(s) potentially affected or created by the proposed project and alternatives under consideration e Environmental Consequences - includes a discussion of the anticipated environmental impacts of the alternatives including the proposed action and any adverse environmental effects that cannot be avoided or mitigated to insignificance e Consultation and Coordination - identifies the agencies and individuals which aided in the environmental analysis and documentation e List of Preparers - includes the names and qualifications of the persons who are primarily responsible for the document e Appendices - present supporting information, materials and studies developed as part of the environmental analysis HLY 24-057 (6/96) Final 120293-01/ab 4 FEDERAL PROCESS NATIONAL ENVIRONMENTAL POLICY ACT (NEPA) Proposed Action Identified Scoping/Determine Issues and Concerns Determination of ; Significance No Significant i Effects Expected to Occur | ; Significant Effects Significance of Effects Will Occur is Uncertain Conduct Required * me Prepare Draft EIS ~ MAT Environmental Studies | Finding of No 5 Categorical Exclusion Significant Impact i Sn Fos) — Implementation and Monitoring Prepare Final EIS : Sanaa NO NANTES Record of Decision : Lo. emsessy * Federal, state, and local permitting studies can be started in conjunction with the NEPA process once a preferred alternative is identified. FIGURE 1 Section 404 and Related Permit Requirements Federal permits anticipated for the Southern Intertie Project include: USAED Section 404 Permit, which is required when the proposed project includes the potential for filling, construction, or placement of structures in wetlands and waters of the United States. USAED Section 10 Permit, which would be required for the construction of a structure in, or over navigable waters of the United States. Section 106 Consultation, required by the National Historic Preservation Act, which would assess the potential impacts to cultural resources along the various alternative corridors. The consultation would be conducted by Alaska's SHPO in the Office of History and Archaeology in conjunction with the review of the Section 404 Permit by federal resource agencies. In the unlikely event that a Section 404 Permit process would not be required, the Section 106 Consultation would be conducted under the guidance of appropriate federal agencies. However, all routes appear to require Section 404 permitting due to associated wetlands. Section 7 Consultation with the USFWS regarding threatened and endangered species, which occurs automatically with the initiation of a Section 404 Permit and review. As with the Section 106 Consultation, if a Section 404 Permit process would not be required, Section 7 Consultation would be conducted under the guidance of appropriate federal agencies. EPA-Related Requirements The EPA would probably require the following permits to be obtained: A National Pollutant Discharge Elimination System (NPDES) General Permit for storm water. This permit, which applies to non-point sources associated with construction activities, may be required depending upon the extent of construction and development of additional facilities. The general NPDES permit would apply to construction of a transmission line and substation facilities due to the need to clear right-of-way and the potential need for above-ground facilities at the marine crossing locations. The General Permit would also necessitate the creation of a Storm Water Pollution Prevention Plan required during the construction phase of the project. SPCC Plan for the storage of large amounts of fuel (greater than 1,320 gallons). This would be required in the event that equipment fuel is stored onsite during the construction phase of the project, as well as for oil-filled equipment such as some types of submarine cable and associated pumping facilities, oil-filled reactors, and power transformers. HLY 24-057 (6/96) Final 120293-01/ab 6 Federal Aviation Administration, U.S. Forest Service, and Bureau of Land Management e A Notice of Proposed Construction to the Federal Aviation Administration (FAA) would also be required if the proposed route would potentially interfere with existing flight patterns or flight management areas. In addition, the FAA will require that the proposed project be evaluated for a hazard determination. A hazard determination is the potential hazard that any new construction could cause to existing flying conditions. e The BLM handles lands selected under the Alaska Native Claims Settlement Act (ANCSA) and Native Allotments under the Alaska Native Allotment Act of 1906 for all lands that have not been transferred and are held in trust for allottees. The BLM would review a request for right-of-way on, or lease of, trust properties. e The USFS will also require a Special Use Permit for the construction and installation of the proposed project on National Forest Lands. STATE OF ALASKA REQUIREMENTS State of Alaska permitting requirements described in this section include: e Review processes directed by the Division of Governmental Coordination (DGC) e Review permits by the Alaska Department of Natural Resources (ADNR) e Review and consultation during the federal permitting requirements that affect state lands Division of Governmental Coordination The lead coordinating agency for the state’s permitting review of the project within the state’s coastal zone will be the Division of Governmental Coordination (DGC) of the Office of Management and Budget. The DGC’s authorities come from Alaska State Statute (A) 46 and A6 Alaska Administrative Code (AAC) 50. The extent of the coastal zone is defined by each local Coastal District. The Municipality of Anchorage (MOA) and Kenai Peninsula Borough coastal districts both manage lands within the existing project study area. DGC is directed by the Alaska Coastal Zone Management Act and the Alaska Coastal Zone Management Program (ACMP) to coordinate the state’s review of projects requiring more than one state agency’s permit or federal permits requiring state concurrence. DGC coordinates permitting by initially holding “pre-application” meetings and reviewing permit application packets for completeness. Once the packet is considered complete, DGC starts the state’s 50-day review by supplying the review packet, including applications, to state agencies and local coastal district reviewers. The USAED also receives notice that the state’s review has begun. HLY 24-057 (6/96) Final 120293-01/ab 7 Upon completion of the state’s review, DGC issues a “Consistency Determination” which precipitates the issuance of state permits and also allows any federal permits to be finalized. Issuance of federal permits in the state’s coastal zone requires concurrence on the part of the state that the project is consistent with the ACMP. DGC may extend the review time frame if there are information requests from reviewers. Chugach Electric Association personnel who have had experience with this process indicate that if a project generates significant controversy, agencies may request additional information that can extend their review to 90 days or more. The USAED coordinates the federal review of a project if a Section 404 or Section 10 permit is required. The USAED then issues the 404 permit after receiving notice that the state has found the project consistent with the ACMP. Additional State of Alaska permits may be required from the Alaska Department of Environmental Conservation (ADEC), Alaska Department of Fish & Game (ADF&G), and the Alaska Department of Natural Resources (ADNR). ADEC permits include Water Quality Certification, Air Quality Permits, and approval of oiling to control dust or burning of slash from cleared areas (i.e., rights-of-way). The range of ADEC permits are generally required under A 46 and A1l8 AAC. These include: e A Wastewater Discharge Permit for any direct discharges of wastewater to waters of the United States. e A Certificate of Reasonable Assurance (Section 401) is necessary when any federal permit is issued under the Federal Clean Water Act. In this case, the USAED Section 404 Permit will trigger the need for State certification. e An Air Quality Permit to Construct and Operate may be required if more than 100 tons of criteria pollutants are emitted. This would typically only occur if construction activities would generate considerable dust. The most likely air pollutant would be particulate matter emitted during ground disturbing activities (i.e., right-of-way clearing and access road construction). If road dust is to be controlled by oiling during construction, ADEC may require a Surface Oiling Permit. e A Burn Plan when more than 16 hectares (99.5 acres) of land are to be cleared and the slash burned during the construction phase of the project. ADF&G permits would include: e A Fish Habitat Permit under A 16.05.840, A 16.05.870, and A 5 AAC 95 from the ADF&G, which would be required for any structures placed below the ordinary high water line for equipment crossing fish-bearing streams. HLY 24-057 (6/96) Final 120293-01/ab 8 e The fording of equipment through state waters must be approved by ADF&G. e Activities in any Special Management Areas managed by the ADF&G are controlled through A 16.20 and 5 AAC 95. ADNR has four divisions with regulatory powers over a project of this type. The authority stems from A 38 and 11 AAC. The approvals required from ADNR include e Written approval from the Division of Forestry to burn material from areas cleared during the fire season. A Burn Plan would need to be submitted prior to approval. e A Temporary Water Use Permit to secure temporary (during construction) use of state waters is required from the Division of Mining and Water Management. e A Material Sale for the use of state materials, such as sand and gravel, would be conducted by the Division of Land (DOL). e ALand Use Permit and right-of-way would have to be issued by DOL for any use of or construction on state lands. The Alaska Department of Transportation/Public Facilities (ADOT/PF) would require: e A Utility Permit and right-of-way Encroachment Permit for any transmission line structures crossing or potentially affecting ADOT/PF rights-of-way. MUNICIPALITY OF ANCHORAGE Permits and approvals within the Municipality of Anchorage (MOA) are primarily covered by the existing federal and state requirements previously described. MOA General Permits may be require to projects that cross designated wetlands that could be developed. A Conditional Use Permit amendment to the Utility Corridor Plan would be required for transmission or substation type facilities located within the MOA for areas not zoned industrial and not routed within the identified corridors. Industrial zoning exempts these facilities from the Conditional Use Permit requirements. Routing opportunities within the corridor will be compared against the Municipality’s Utility Corridor Plan. Although the currently adopted plan incorporates future transmission line locations, construction and operation of the Southern Intertie Project would require approval by the MOA Planning and Zoning Commission and the Municipal Assembly regardless of the location of the line. Both the Planning and Zoning Commission and the Municipal Assembly require public hearings on the proposed amendment. Final approval is issued by the Municipal Assembly pending review of the HLY 24-057 (6/96) Final 120293-01/ab 9 amendment and the completion of the public hearing process. KENAI PENINSULA BOROUGH Construction and operation of the project would require compliance with the requirements of the Federal Emergency Management Agency (FEMA). Compliance with FEMA specifically relates to the construction and placement of transmission line facilities within coastal bluff areas and special hazard areas as defined by FEMA and the Kenai Peninsula Borough (borough). In addition, the borough will require compliance with the Coastal Management Program and requirements for temporary fuel storage locations. Additional right-of-way and transmission line easements, permits, and approvals may be required pending the identification of the exact location of the transmission line. Similar to the MOA, the borough requires compliance with all federal and state permits and approvals. HLY 24-057 (6/96) Final 120293-01/ab 10 CORRIDOR-SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Three alternative corridors have been identified within the regional study area. The individual corridors have been divided into segments called links. The Alternative Corridor Map illustrates the individual corridors and related links. The anticipated permitting requirements and authorizations are similar for all of the corridors under consideration. However, the extent and proximity of regulated areas vary between the identified potential routes. Appendix A summarizes the potential permit requirements for the alternative corridors under consideration at this time. In addition, for all submarine crossings a plat showing the location of the UG submarine cable must be submitted to the U.S. Coast Guard after installation. HLY 24-057 (6/96) Final 120293-01/ab ll Quartz Creek (QC) The QC corridor alternative maximizes the use of existing transmission line right-of-way through federal, state and local management areas. As noted in Appendix A, the QC corridor would require a variety of federal, state-and local permits prior to construction and operation of the proposed project. This corridor is the only alternative under consideration that crosses National Forest land and would be subject to the applicable Special Use Permits. There are three-options-in the-vicinity of Turnagain Arm (refer to Alternative Corridor Map, page 11). They are Alternative Routes QC.D-I.10, QC.D.1.A, and QC.D.1.B. All three options would require similar permitting considerations, however, the potential for the placement of dredge and fill material is potentially higher with the two marine crossing options. In addition, a Section 10 Permit would be required for the placement of structures within Turnagain Arm. This route will also require coordination and review with the Chugach State Park Board of Directors, the National Park Service regarding Land & Water Conservation Fund (LWCF) lands, the ADOT/PF when crossing roads or potentially sharing right-of-way, and the USFWS regarding right-of-way permits on the Kenai National Wildlife Refuge, specifically, Title 11 of the Alaska National Interest Lands Conservation Act (ANILCA) as it pertains to conservation units. Enstar (EN) The majority of the land portion of the EN alternative corridor is within the Kenai National Wildlife Refuge and would require compliance with Title 11 and 22g of ANILCA and considerable consultation with the USFWS for final approval. Title 22g regulates use on private in holdings within the Refuge, specifically regarding the reallocation of lands for specific uses (i.e., transmission line corridors vs. wildlife habitat). Title 11 pertains to transportation or utility system within or crossing conservation easements. In addition, local permits would be required within the Soldotna and MOA areas. This corridor also potentially affects three important wildlife habitat areas (Anchorage Coastal Wildlife Refuge, Potter Marsh and Chickaloon Bay) at the marine crossing. This crossing would require considerable consultation with the ADF&G, USFWS and USAED. The National Park Service would administer the LWCF process if State Park Lands along the Kenai River would be crossed. Tesoro (TE) The Tesoro alternative corridor would specifically require a Notice of Proposed Construction or Alteration to the FAA. This is primarily due to the location of aviation navigation equipment on Fire Island and its relative close proximity to the Anchorage International Airport. In addition, the LWCF requires the approval of the National Park Service for the construction of utilities within State Park Lands. This regulation also HLY 24-057 (6/96) Final 120293-01/ab 13 prohibits the construction of overhead transmission lines within State Park Lands funded through LWCF appropriations. The BLM would oversee any permitting issues that would occur on native allotments potentially crossed near Point Possession. Compliance with Title 11 of ANILCA could be required if the route crosses the refuge at either Captain Cook SRA or Point Possession. : Klatt Corridor This corridor presents two alternative routes that deviate from either the Tesoro Corridor or the Enstar Corridor. Both would make-a landfall near Klatt Road in Anchorage. On the Alternative Corridor Map, the Klatt alternatives are designed as AN.70 and AN.80. No additional permitting would be required beyond that identified for the other three corridors. HLY 24-057 (6/96) Final 120293-01/ab 14 PRIVATE LAND EASEMENT ACQUISITION All proposed corridors contain private lands from which transmission line easements and/or access easements would be required. The Land Jurisdiction/Ownership map provides a visual display of the extent of private lands affected by the study corridors. In addition, Table 1 shows the lineal distance of private lands crossed by each corridor segment. Note that a corridor reference line is shown in the center of each corridor. For purposes of this report, the reference line has been used to quantify the amount of private land crossed by that corridor or corridor sub-link. Upon further study and impact analysis, a final route may be chosen within the corridor that differs greatly from the present reference line. Therefore, the right-of-way acquisition requirements could vary greatly from one side of the corridor to the other. Many distribution lines exist by permit or easement rights that would not provide for the addition of transmission facilities, without getting further permission from the affected property owners or Agencies.. Additional property would have to be acquired to allow for expansion of the University Substation. Lands would also have to be acquired to accommodate submarine cable terminal facilities. It is recommended that additional examination of ownership be conducted during the next phase of this project for lands surrounding International Substation, Bernice Lake Substation, and Soldotna Substation. However, it appears from discussions with respective utility personnel that these facilities have sufficient utility- owned land for expansion purposes. An examination of the land ownership at substations and submarine cable landfall locations reveals the following: e University Substation Large acreages immediately to the east of the ; substation are owned by the State of Alaska and the Municipality of Anchorage. e International Substation These lands are owned by CEA. e Bernice Lake Substation These lands are owned by Homer Electric Association, Inc. e Soldotna Substation Adjacent lands appear to owned by Homer Electric; however, this needs verification. e Fire Island landfall Fire Island is owned by the Cook Inlet Regional Corporation (CERI), an Alaska Native Corporation. e Point Campbell landfall These lands are owned by the Municipality of Anchorage. e Point Woronzof landfall These lands are owned by the Municipality of Anchorage and by the Anchorage International Airport. e Point Possession landfall These lands are owned by the Point Possession HLY 24-057 (6/96) Final 120293-01/ab 15 Native Group, an Alaska Native Corporation. There are also certified native allotments in this area. e Potter Marsh landfall These lands are owned by the State Department of Natural Resources, Division of Parks and Recreation. Also, very close to landfall are lands owned by the Alaska Railroad Corporation. e Kenai Peninsula landfall These lands are owned by the U.S. Fish and for the Enstar Route Wildlife Service, Kenai National Wildlife Refuge. e Bird Point Crossing These lands are owned by the Department of - North side Natural Resources and the Alaska Railroad. There are also State mining claims in this area e Bird Point Crossing Lands on the east side of Six Mile Creek are - South side owned by the U.S. Forest Service, Chugach National Forest. Lands in the area are also in the Sunrise Subdivision. Note that a cemetery is also in the area. Lands on the southwest side of Six Mile Creek are owned by Chugach National Forest and by the Alaska Department of Transportation. Subsequent to earlier efforts to identify private lands within the Base Routes and their alternatives, additional research has been conducted to better understand the extent of unpatented mining claims within the study corridors. Within the Tesoro and Enstar Base Routes and their alternatives there are no mineral claims, except on the north side of the Bird Point landfall, where there are State mining claims. Unpatented claims are interspersed throughout the Quartz Creek Base Route. It is estimated that 1-2% of the lands along this route may contain unpatented mining claims. It is estimated that the impact upon the right of way budget to appropriately deal with these mineral interests would range from $10,000 - $20,000. Refinements of private land ownership information, such as developing ownership lists and determining mineral rights holders, would be conducted in a subsequent project phase. Easement acquisition would not commence until a route has been authorized and the appropriate centerline surveys completed. Specific procedures for right-of-way easement acquisition would be developed prior to beginning acquisition activities. However, to serve as a suggested approach, a sample right-of-way Procedures Manual is included with this report as Appendix C. Project-specific procedures will be developed at the appropriate time. Also, legal documents to be used for Project easement acquisition will have to be developed. “For the purpose of this study, it has been assumed that Chugach will take the easements and maintain the associated records.” HLY 24-057 (6/96) Final 120293-01/ab 16 The following table (Table 1) summarizes the land ownership status of each corridor link and shows total miles of private land within each of the three primary corridors: Tesoro, Enstar and Quartz Creek. Note that miles of private land are totaled for the core route only within each corridor. Numerous alternative sub-routes are possible in the vicinity of Anchorage, Captain Cook State Park, Soldotna, and for the submarine cable crossings and Bird Point area. This data has been obtained via an examination of federal, state, borough, and municipality land status mapping to determine the gross land ownership status of the project study area. In some cases, the data is incomplete. However, there is reason to believe the lands are privately owned. In those instances, a title search would have to be conducted to verify ownership. Upon final route approval, a detailed title search will be conducted to determine parcel-by-parcel ownership of the project centerline. The time periods included in this report are based on estimates provided by federal, state, and local agency representatives contacted during the preparation of the report. The time frames are intended to provide the reader with an estimate of the time required to complete the various permits, provided all the requested information is included int he permit applications. HLY 24-057 (6/96) Final 120293-01/ab 17 TABLE 1 CORRIDOR LANDOWNER STATUS TESORO ALTERNATIVE ROUTE OWNERSHIP SUMMARY LINK CODE TOTAL OWNERSHIP PRIVATE LOCATION LENGTH (MI) LAND (MI) TE.A.10 Syl STATE Submarine Pt. Woronzof - Fire mew e | Bae t TE.E.50 9.1 STATE - Submarine Fire Island - Pt. TE.G.H.80 Private, NATIVE, 5.2 | Tesoro Pipeline aio Ee A 4.0] Private, Borough, 0.8 TE.1.115 3.9] Private, Borough, 1.0 | Tesoro Pipeline TE.J.K.120 3.4| Private, STATE 1.8 | Tesoro Pipeline TE.J-K.130 2 Private 12 a Submarine Alternatives Woronzof - Fire 5.6 STATE Island 3.9] Private, Municipal | not established | Anchorage/ AAT Kincaid Park 32 STATE Submarine Pt. Campbell - Fire Island 9.4 STATE Submarine Pt. Campbell - Possession Pt. SES) STATE Submarine Pt. Campbell - Possession Pt. 27.6 Submarine Pt. HLY 24-057 (06/96) Final 120293-01/ab 18 TABLE 1 (CONTINUED) CORRIDOR LANDOWNER STATUS Captain Cook Alternatives ] 3.8 | Near Tesoro Pipeline TE.G.H.90 TE.I.100 TE.K.140 Private, STATE, Native TE.K.150 TE.K.160 TE.K.170 Total HLY 24-057 (06/96) Final 120293-01/ab 19 TABLE 1 (CONTINUED) CORRIDOR LANDOWNER STATUS ENSTAR ALTERNATIVE ROUTE OWNERSHIP SUMMARY LINK CODE TOTAL OWNERSHIP PRIVATE LOCATION LENGTH (MI.) LAND (ML) EN.A.20 3.8 Private 3.8 | Alaska Railroad EN.A.50 3.2 Private 3.2 | Alaska Railroad EN.A.60 0.4 Private 0.4 | Alaska Railroad EN.B.20 2.3| Private, STATE 2.0 | Alaska Railroad EN.C.10 7.8 STATE - Submarine Potter - Burnt Island EN.D.E.20 38.5 FEDERAL, - ENSTAR Pipeline Borough QC.M.1.20 10.2] Private, Borough, 6.9 | Pipeline STATE QC.M.1.30 5.9 Private, Native 0.6 | Transmission Line QC.M.1.50 Private, Native Road, Total EN.A.30 QC.M.1.10 ees ieeeeereerres QC.M.1.40 5.0 Total 19.3 EN.A.10 5.3 Transmission Line Priate, Native, Borough 19.1 Soldotna Area Alternatives 6.2 0.4 Private, Native Transmission Line Private Private 10.2 bn Anchorage Area Alternatives 5.3 International & New Seward Highway O’Malley Private New Seward Highway Private 2.8 | Old Seward Highway 11.1 HLY 24-057 (06/96) Final 120293-01/ab 20 TABLE 1 (CONTINUED) CORRIDOR LANDOWNER STATUS OWNERSHIP SUMMARY LINK CODE TOTAL OWNERSHIP PRIVATE LENGTH (ML.) LAND (ML) QC.C.D-1.10 38.7] Private, STATE, 23 aL QC.M.1.20 10.2] Private, aan STATE ERT QC.M.1.50 47 Private, Native EXISTING QUARTZ CREEK TRANSMISSION LINE LOCATION Tudor/Existing Quartz Creek Transmission Line Quartz Creek Pipeline | ———_—0.6 | Transmission Line Transmission Line Total 139.1 28.1 Bird Point Alternative QC.D.1.A,B 4.2 STATE, FEDERAL QC.D.2.10 9.6 Fe 13.8 | Total Aerial and Submarine Bird Pt. - Snipers Pt. Distribution Line HLY 24-057 (06/96) Final 120293-01/ab 21 TABLE 1 (CONTINUED) CORRIDOR LANDOWNER STATUS ANCHORAGE AREA OWNERSHIP SUMMARY LINK CODE TOTAL OWNERSHIP PRIVATE LOCATION LENGTH (ML) LAND (ML) ania AN.20 iin Private 0.8 | Section Line [3 Private 0.9 | New Corridor CNMI MMM 40 Private 0.5 | New Seward Highway Private 1.0 | O’Malley Rd. Private 0.8 | Old Seward Highway STATE 11.1 | Submarine crossing to Pt. Possession 3 STATE, .3 | Submarine FEDERAL crossing to ENSTAR Corridor 0.5 1.0 11.1 ni HLY 24-057 (06/96) Final 120293-01/ab 22 APPENDIX A CORRIDOR-SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS HLY 24-057 (06/96) Final 120293-01 /ab Action Requiring Permit CORRIDOR SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Permit Approval or TABLE 1 Estimated Permitting/ Authorization |_| Submarine Permit required for discharge of wastewater from a Crossing & point source into federal- and state-owned waters. Substation The permit is also required for storm water runoff. Facilities A Storm Water Pollution Prevention Plan is required for construction activities in order to be covered under the EPA’s General Permit for storm water discharges. Environmental Protection Agency National Pollutant Discharge Elimination (NPDES) Permit for Storm Water Discharges Federal Water Pollution Control Act, 40 CFR 125 All alternative corridors under consideration Applies specifically to substation/ switching stations Issue Approval or Review Agencies Review Relevant Legislation Corridor Affected Comment Time Period Contact Federal Wetlands/ A Section 404 Permit is required when wetlands are U.S. Army Engineer Section 404 Permit Clean Water Act, 33 All alternative corridors | The ENSTAR Route 90 - 120 days Georgina Akers, Unit Waterways affected by the discharge of dredge or fill material, District, Alaska USC 1344, Section 404 | under consideration initially appears to cross Coordinator or transmission line construction activities. more wetlands than other USAEDA Regulatory Branch routes PO Box 898 Anchorage, AK 99506-0899 (907)753-2724 Wetlands/ A Section 10 Permit is required for the construction | U.S. Army Engineer Section 10 Rivers and Harbor Act, All submarine crossings 90 - 120 days Georgina Akers, Unit Waterways or placement of any structures in or above navigable | District, Alaska 33 USC 403, Section and the aerial crossing Coordinator waters of the United States. 10 at Bird Point USAEDA Regulatory Branch PO Box 898 Anchorage, AK 99506-0899 (907)753-2724 Agency review of Jackie Poston, Environmental Submarine Crossing & Substation Facilities Plans are required for oil storage facilities storing in excess of 660 gallons in a single container above ground; in excess of 1,320 gallons in aggregate in tanks above ground; or in excess of 42,000 gallons below ground. Environmental Protection Agency Spill Prevention Control and Countermeasure Plans Cultural Resources The Advisory Council on Historic Preservation protects properties of historical, architectural, archaeological, and cultural significance at the national, state and local level by reviewing and commenting on Federal actions affecting National Register and eligible properties. A Section 7 consultation is required to assure protection of endangered or threatened species and wildlife. Sensitive Plant and/or Wildlife Species Federal Water Pollution Control Act, 40 CFR 112 All alternative corridors under consideration Advisory Council on Historic Preservation Concurrence that proposed actions do not adversely impact National Register and eligible properties U.S. Fish and Wildlife Service Section 7 consultation (in conjunction with Section 404 or 10 Permitting) National Historic Preservation Act, Section 106 Fish and Wildlife Protection Act, Section 7 All alternative corridors under consideration All alternative corridors under consideration Applies specifically to cooling fluid reservoirs for submarine cable crossing. This permit could General Permit Engineer applicability is 30 - U.S. Environ. Protection Agency 60 days Alaska Operations Office 222 W 7th Ave #19 Anchorage, AK 99513-7588 (907) 271-3541 30 - 90 days Matt Carr, Environmental Protection Specialist U.S. Environ. Protection Agency Alaska Operations Office potentially be avoided by 222 W 7th Ave #19 placing the storage tanks Anchorage, AK 99513-7588 underground. (907) 271-3616 Potential to identify sites is equal among all alternatives No threatened and endangered species have been identified within the study area. In conjunction with Section 404 or 10 Permitting - up to 120 days Judith Bittner, State Historic Preservation Officer DNR/SHPO 3601 C Street, Suite 1278 Anchorage, AK 99510-7001 (907) 269-8715 In conjunction with Section 404 or 10 Permitting - up to 120 days Anne Rappaport, Field Supervisor USFWS Ecological Services 605 W 4th Ave, Rm 62 Anchorage, AK 99501 (907) 271-2787 |__| Right-of-Way Right-of-Way Non-recreation use in a Land & Water Conservation Funded (LWCF) recreation area requires “Conversion of Use” approval. Nonprohibited conversions of use are approved by the National Park Service and the Department of the Interior. Right-of-Way Grant and temporary Use Permit would be required for obtaining right-of-way on BLM.-, BIA-, and ANCSA-selected lands. i & DNR Parks & (administers State side of LWCF for non-Federal land managed to acquire/develop public outdoor recreation areas) Bureau of Land Management on Indian Affairs National Park Service Outdoor Recreation behalf of Bureau of Land & Water Conservation Fund Act P.L. 88-578, Section 6(3) Tesoro Route and potentially the existing Quartz Creek Route “Conversion of Use” approval Grant Right-of-Way and Temporary Use Permit Federal Land Policy Tesoro Route and Management Act of 1976 (P.L. 94-579) USC 1761-1771 and 43 CFR 2800 Applies to Captain Cook State Park. Regulations prohibit overhead power lines in LWCF areas; buried power lines are permitted. Grant Right-of-Way would require concurrence by ANCSA allottee Approximately 6 - 8 weeks TABLE 1 CORRIDOR SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Estimated Permitting/ Action Requiring Permit Permit Approval or Authorization Issue Approval or Review Agencies Review Relevant Legislation Corridor Affected Comment Time Period Contact Aviation A notice to the FAA, for the review and approval, Federal Aviation Notice of Proposed FAR Part 77 Potentially the Tesoro A hazard determination will 90 days minimum Jack Schommer, Air Space & will be required to address concerns and effects of Administration Construction or Alteration Route pending require public review of the Procedures the proposed project on the safe and efficient use of and a Hazard identification of exact proposed project Air Traffic Division AAL 532 navigable air space. Determination (Form transmission line 222 W. 7th Ave, Box 14 7460-1) location Anchorage, AK 99513 t— (907) 271-5903 Right-of-Way Right-of-Way Permit would be required for USS. Fish and Right-of Way Permit 50 CFR 25, 26, 29, & All with the possible The Tesoro Route may Approximately two Lucy Blix, Realty Specialist obtaining right-of-way within a National Wildlife Wildlife Service 36 exception of the Tesoro | avoid USFWS lands if the years USFWS Div. of Realty Refuge. Route final route goes through the 1011 E Tudor Rd Captain Cook State Anchorage, AK 99503 Recreation Area (907) 786-3566 Right-of-Way Right-of-way permit would be required for U.S. Fish and Right-of-Way Permit Title 11 of ANILCA All with possible Two years Sharon Janis obtaining right-of-way within a conservation unit. Wildlife Service exception of Tesoro Chief, Division of Realty Route USFWS 1011 E. Tudor Road Anchorage, AK 99503 (907) 786-3490 Right-of-Way Special Use Permit would be required for obtaining Chugach National Special Use Permit for use | 36 CFR 251 Existing Quartz Creek Approximately 4 Leo Keeler, Realty Specialist right-of-way on National Forest land. Forest of Forest Lands Transmission Line and weeks USFS Bird Point alternative following Chugach National Forest, completion of Supervisor’s Office NEPA analysis 3301 “C” Street, Suite 300 Anchorage, AK 99503-3998 (907) 271-2547 Joy Bryan-Dolsby, Grant Administrator DNR/Parks & Outdoor Recreation 3601 “C” Street, Suite 1200 Anchorage, AK 99503-5921 (90) 269-8692 Approximately 4 - 6 weeks Robert Rinehart, Realty Specialist BLM Division of Lands Anchorage District Office (041) 6881 Abbott Loop Rd Anchorage, AK 99507 907) 267-1213 Action Requiring Permit CORRIDOR SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Permit Approval or TABLE 1 Estimated Permitting/ Authorization Right-of-Way A Land Use Permit is required for use of state lands along the proposed right-of-way. A right-of-way permit is required for construction of transmission lines or other improvements that cross state lands. Department of Natural Resources, Division of Lands Land Use Permit, Tideland Use or Lease, Right-of- Way AS 38.05, 11 AAC 58, 62, 96 All alternative corridors under consideration 50 day consistency review and up to 6 to 9 months for Title 38 review Issue Approval or Review Agencies Review Relevant Legislation Corridor Affected Comment Time Period Contact State of Alaska Wetlands/ Permitting of projects requiring more than one State | Division of Coastal Consistency Alaska Coastal Zone All alternative corridors Approximately 50 Faye Heitz, Project Review Waterways agency permit or Federal permit (requiring State Governmental Review/Determination Management Act: AS under consideration days Coordinator concurrence) must be coordinated by DGC for the Coordination 46, 6 AAC 50 Office of Management and State’s review. Budget Division of Governmental Coordination 3601 “C” Street, Suite 370 Anchorage, AK 99503-5930 (907) 269-7470 Wetlands/ ADEC must issue a 401 Certificate to accompany Department of Certificate of Reasonable Clean Water Act, 13 All - It is assumed 401 Approximately 50 Tim Rumfelt, Environmental Waterways any Federal permit issued under the Federal Clean Environmental Assurance (401) USC 1344, 18 AAC 15. | certification would be days Specialist Water Act. For example, a U.S. Army Corps of Conservation complete pending DEC/Southcentral Regional Engineers Section 404 Permit would trigger the issuance of a Section Office need for a State certificate. 404 Permit 555 Cordova Street Anchorage, AK 99501 907) 269-7500 Cultural In accordance with information provided by the Department of Section 106: Concurrence | National Historic All alternative corridors Approximately 50 Judith Bittner, State Historic Resources Advisory Council on Historic Preservation, SHPO Natural Resources, with the Advisory Council | Preservation Act, under consideration days Preservation Officer will provide a determination regarding a project's State Historic on Historic Preservation Section 106; DNR/SHPO potential impacts on known cultural resources. Preservation Office Alaska Historic 3601 C Street, Suite 1278 Preservation Act, Anchorage, AK 99510-7001 AS 41.35.010-240 (907) 269-8715 State Parks A Special Use Permit is required for Park lands Department of Parks Special Use Permit AS 41.20, 11 AAC 12 All alternative corridors | Applies to Captain Cook, Approximately 50 Chris Degernes, Kenai Area along the Right-of-Way. Natural Resources, under consideration Chugach, Kenai River, and days Superintendent Division of Parks Potter’s Marsh State Parks. DNR/Parks & Outdoor Quartz Creek Corridor Recreation would require review by the Frontier Building Chugach State Park Board 3601 “C” Street, Suite 1200 of Supervisors. Anchorage, AK 99503-5921 (907) 269-8700 Alice Iliff, Natural Resource Officer Regional Office, DNR/Land Frontier Building Southcentral District Office 3601 “C” Street, Suite 1080 Anchorage, AK 99503-5937 907) 269-8549 TABLE 1 CORRIDOR SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Action Requiring Permit Permit Approval or Estimated Permitting/ Authorization Issue Approval or Review Agencies Review Relevant Legislation Corridor Affected Comment Time Period Contact Existing Approval is required before construction on Department of Utility Permit on State AS 19.25, 17 AAC 15 ENSTAR and Quartz Potentially more 6 weeks Rick Pettit, Utility Permit Facilities ADOT/PF managed state lands or for structures Transportation and Right-of-Way Creek involvement along Quartz Officer crossing ADOT/PF right-of-ways. Public Facilities Creek Corridor DOT&PF Design & Construction 4111 Aviation Dr. Anchorage, AK 99502 (907) 266-1541 Construction ADEC must authorize plans and specifications for Department of Air Quality Permit Clean Air Act, 40 CFR All alternative corridors Approximately 50 Bill MacClarence construction that would be undertaken and must Environmental 60, AS 46.03 and 18 under consideration days DEC/Southcentral Regional assess emission standards and possible air Conservation AAC 50 Office contamination resulting from that construction. 555 Cordova Street Road dust, wind-blown contaminants, emissions Anchorage, AK 99501 from generators could cause this permit to be (907) 269-7500 required. Construction Control of road dust. To control and legalize Department of Surface Oiling Permit AS 46.03, 18 AAC 75 All alternative corridors | Applies to access roads 30 - 50 days DEC/Southcentral Regional surface oiling in order to prevent water pollution. Environmental under consideration Office Conservation 555 Cordova Street Anchorage, AK 99501 (907) 269-7500 Construction A General Waterway/Waterbody Application must Department of Fish & | Fish Habitat Permit AS 16.05.840, AS All alternative corridors | Construction access Approximately 50 Don McKay be submitted to ADF&G if heavy equipment usage Game 16.05.870, and 5 AAC under consideration days ADF&G/Habitat and Restoration or construction activities disturb the natural flow or 95 Division bed of any stream, river, or lake. These permits also 333 Raspberry Road stipulate how stream water withdrawals may be Anchorage, AK 9958-1599 conducted. (907) 267-2284 Sensitive Plant | A Special Areas Permit Application must be Department of Fish & | Special Areas Permit AS 16.20 and 5 AAC Potentially the Tesoro Applies to the Anchorage Approximately 50 Don McKay and/or Wildlife | submitted for activities conducted in legislatively- Game 95 and ENSTAR Routes Coastal Wildlife Refuge days ADF&G/Habitat and Restoration Species designated State game refuges, critical habitat areas, Division and State game sanctuaries. 333 Raspberry Road Anchorage, AK 9958-1599 Ee (907) 267-2284 Construction ADNR must approve any plan to burn materials Department of Burn Permit AS 41.15, 11 AAC 92 All alternative corridors | Applies to potential burning | Approximately 10 John McClair, Fire Management during fire season. The permit is issued by the State | Natural Resources, under consideration of slash in cleared right-of- days Officer Forester or local rangers after review of burn plan. Division of Forestry way DNR/Forestry Kenai-Kodiak Area Office HC 1 Box 107 Soldotna AK 99669 (907) 262-7559 Action Requiring Permit CORRIDOR SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Permit Approval or TABLE 1 Estimated Permitting/ Authorization 404 Permits and platting requirements for right-of- way easements. | Right-of-Way The Kenai Peninsula Borough will require Conditional Use Permits, concurrence with Section 404 Permits and platting requirements for right-of- way easements. Zoning Changes Planning Department Right-of-Way Platting Conditional Use Permit Kenai Peninsula Borough AS 29 All alternative corridors under consideration All alternative corridors determined once more specific routing alternatives have been identified maximum Land Use Permit - one month maximum Issue Approval or Review Agencies Review Relevant Legislation Corridor Affected Comment Time Period Contact Construction This permit is required if water withdrawals will Department of Water Rights or AS 46.15, 11 AAC 93 All alternative corridors | Applies during construction | Temporary Water Kellie Litzen occur during construction. The permit lasts for the | Natural Resources, Temporary Water Use under consideration Use - 50 days, DNR/Water length of a temporary project. Division of Mining Water Rights - upto | 3601 “C” Street, Suite 822 and Water one year Anchorage, AK 99503 (907) 269-8642 Right-of-Way Approval would be required to locate a transmission | Alaska Railroad Leasing of ARRC lands, 45 USC Sec. 1201 et All alternative corridors Approximately 30 - Mike Fretwell, Land Use line within, cross, or parallel a railroad Right-of- Corporation Alaska Railroad Permit seq., AS 42.40 under consideration 60 days Coordinator Way and Construction 43 USC 975 Alaska Railroad Corporation 327 W. Ship Creek Ave Anchorage, AK 99501 907) 265-2465 Right-of-Way Approval would be required to locate a transmission | Cook Inlet Region, Leasing of Right-of-Way Not applicable Tesoro Corridor Approximately 60 - Mike Franger, Land Manager line across Cook Inlet Region, Inc. lands Inc. 90 days Cook Inlet Region, Inc. 2525 C Street, Suite 500 Anchorage, AK 99509 (907) 274-8638 Municipality of Anchorage Right-of-Way The Municipality of Anchorage will require Planning Department | Land Use Permit AS 29 Specific permitting Conditional Use Thede Tobish Conditional Use Permits, concurrence with Section Conditional Use Permit under consideration requirements will be Permit - 90 days Municipality of Anchorage Department of Community Planning & Development PO Box 196650 Anchorage, AK 99519-6650 (907) 343-4261 Specific permitting requirements will be determined once more specific routing alternatives have been identified Platting - 60 day minimum, 90 day maximum Permitting Right-of- Way - 30 day maximum Conditional Use Permit - 45 day smaximum Harriet Wegner, Environmental Planner Kenai Peninsula Borough 144 N. Binkley Street Soldotna, AK 99669 (907) 262-4441 X298 TABLE 1 CORRIDOR SPECIFIC ENVIRONMENTAL PERMITS AND AUTHORIZATIONS Estimated Permitting/ Action Requiring Permit Permit Approval or Authorization Approval or Review Agencies Review Relevant Legislation Corridor Affected Comment Time Period Contact Other Right-of-Way Approval would be required to locate a transmission | Alaska Railroad Leasing of ARRC lands, 45 USC Sec. 1201 et All alternative corridors Approximately 10 Mike Fretwell, Land Use line within, cross, or parallel a railroad Right-of- Corporation Alaska Railroad Permit seq., AS 42.40 under consideration days Coordinator Way and Construction 43 USC 975 Alaska Railroad Corporation 327 W. Ship Creek Ave Anchorage, AK 99501 (907) 265-2465 Right-of-Way Approval would be required to locate a transmission | Cook Inlet Region, Leasing of Right-of-Way Not applicable Tesoro Corridor Approximately 60 - Mike Franger, Land Manager line across Cook Inlet Region, Inc. lands Inc. 90 days Cook Inlet Region, Inc. 2525 C Street, Suite 500 Anchorage, AK 99509 907) 274-8638 APPENDIX B LIST OF ACRONYMS HLY 24-057 (06/96) Final 120293-01 /ab ACMP ADEC ADF&G ADNR ADOT/PF ANCSA ANILCA BLM CEQ DGC DOL EA EIS EPA FAA FEMA FERC FPC LWCF MOA NEPA NPDES RUS SHPO SPCC USAED USFS USFWS LIST OF ACRONYMS Alaska Coastal Zone Management Program Alaska Department of Environmental Conservation Alaska Department of Fish and Game Alaska Department of Natural Resources Alaska Department of Transportation/Public Facilities Alaska Native Claims Settlement Act Alaska National Interest Lands Claims Act Bureau of Land Management Council on Environmental Quality Division of Governmental Coordination Division of Land Environmental Assessment Environmental Impact Statement Environmental Protection Agency Federal Aviation Administration Federal Emergency Management Agency Federal Energy Regulatory Commission Federal Power Commission Land Water Conservation Fund Municipality of Anchorage National Environmental Policy Act National Pollutant Discharge Elimination System Rural Utilities Service State Historic Preservation Office Spill Prevention, Control and Countermeasure U.S. Army Engineering District U.S. Forest Service U.S. Fish and Wildlife Service HLY 24-057 (06/96) Final 120293-01/ab APPENDIX C RIGHT-OF-WAY PROCEDURES MANUAL *SAMPLE* RIGHT-OF-WAY PROCEDURES MANUAL INTRODUCTION There are as many right-of-way acquisition policies and procedures as there are organizations that require right-of-way services. As a member of POWER’s Public Utility Department (CLIENT) right-of-way staff, you are an extension of (Client’s) Right-of Way Department. Therefore, the right-of-way procedures you use are those of the CLIENT. In developing a successful right-of-way program, the CLIENT is committed to effective and productive communications with landowners. It has been our experience in the past that no system better represents the utility and landowner’s interest as well as the individual face-to-face approach. After each landowner is contacted, he or she will be have details -- how much the transmission line will affect their property and land uses. It is the CLIENT’s intent to compensate landowners fairly and equitably with easement payments and to expeditiously investigate damage claims and ensure fair settlements. Frequent and open communications are essential for effective right-of-way services. This means being open and fair to landowners and to your co-workers. POWER expects the right-of-way staff to share information, including the day-to-day “war stories” that can be invaluable in your landowner relations. Keep in mind that there is nothing to be gained and a great deal to lose by holding your cards too close to your chest. HLY 24-051 (06/96) Final 120293-01/ab 1 PERSONAL AFFAIRS First and foremost, POWER is concerned for the well-being of our employees. We hope that you will be open and honest with any concerns that you may have regarding POWER policies, your working environment, or other POWER employees or subcontractors. In addition, should there be some element of your personal life for which you feel POWER may provide some assistance, feel free to discuss your options with (POWER). As employees of POWER and agents of the CLIENT, your conduct should be beyond reproach. Any misconduct on your part is damaging to you, POWER, and the CLIENT. Your personal business conduct in some instances becomes company business. For instance, irresponsibility in financial matters or behavior unbecoming a professional soon become common knowledge in a small town. Your life is your own, unless your actions jeopardize the CLIENT’s reputation and POWER is forced to become involved. The use of alcoholic beverages during working hours or illegal drug use at any time is strictly prohibited and is grounds for immediate dismissal. A number of employees have their families accompany them on assignment. POWER has no objection to this whatsoever; however, we do insist that no member of the family accompany an agent to the field to negotiate with the landowner. It goes without saying that first impressions are important. Develop a habit of dressing and presenting yourself appropriately for the occasion. HLY 24-051 (06/96) Final 120293-01/ab 2 1.0 INTRODUCTION 1.0 Introduction The following procedures are established to provide the right-of-way staff with guidance and task control for all aspects of right-of-way services during pre-construction, construction, post-construction, and record closing phases for the CLIENT’s projects. This portion of the Procedures Manual describes procedures for completing time cards and expense reports, equipment and supplies inventory and accounting, and internal control and reporting of personnel hours worked, project expense, and schedule. 1.1 Project Numbers Time Card and Expense Report project number entries will use the following numbers. Personnel will use the task/subtask number that most closely matches the activity conducted for a particular day or portion thereof. Time cards should reflect full hour increments only. Project Number : TASK ___ RIGHT-OF-WAY ACQUISITION 24.0_.01 Title Search 24.0_.02 Property Appraisals 24.0_.03 Right-of-Entry Permits 24.0_.04 Public Meetings 24.0_.05 Prepare Easements 24.0_.06 Procure Easements 24.0_.07 Support Condemnation Efforts 24.0_.08 Participate in Condemnation 24.0_.09 Management and Administration Activities 24.0_.10 Support Condemnation Appeals 24.0_.11 Participate in Appeal Hearings 24.0_.12 Construction Support 24.0_.13 Settle Damage Claims 24.0_.14 Procure Permits 24.0_.15 Permit Data 24.0_.16 Fee Purchases 24.0_.17 Legislative Liaison 24.0_.18 Field Office Expense HLY 24-051 (06/96) Final 120293-01/ab 3 2.0 _ORGANIZATION 2.1 Project Personnel Organization The Project Personnel Organization Diagram, Figure 2.1, is included in this section. It indicates the key personnel and their organizational relationships. Figure 2.2 lists key personnel locations, telephone numbers, and addresses. The CLIENT has contracted POWER to perform as their agents for environmental studies, public involvement, right-of-way acquisition, preliminary and detail design and engineering, surveying, and construction management. Except for questions regarding CLIENT policy, we are hired to be the day-to-day problem-solvers. POWER’s Project Right-of-Way Manager, and the Project Right-of-Way Services Supervisor, should be consulted regarding questions that may require consultation with the CLIENT’s Right-of-Way Manager, . The primary interface with the Manager will be Frank, and secondarily (the Project Right-of-Way Services Supervisor). Right-of-Way Agents should not contact the Manager directly, except in cases of emergency when neither nor (the Project Right- of-Way Services Supervisor) can be reached. Keep in mind that this chain of command is designed to place the process of problem solving upon POWER’s shoulders by encouraging our staff to communicate with each another, and to keep and (the Project Right-of-Way Services Supervisor) apprised of on-going conditions of each of your files, as well as any issues or concerns relative to your work. 22 Communications The Project Personnel Organization Diagram (Fig. 2.1) indicates the line of communication for the project. Any contact by Right-of-Way Agents with the CLIENT personnel should first be cleared through and (the Project Right-of-Way Services Supervisor) or . In addition, there will be communications with outside agencies and other third parties. When POWER personnel are involved in those communications, they will prepare documentation consisting of memoranda, as described in this section, and make entries in the landowner or permit Contact Diary which is described in other sections. Communications shall be documented according to the judgment of the involved individuals; however, all landowner and agency communications or attempted communications will be documented in the case file Contact Diary (Figure 2.3). Conversations recorded on the Contact Diary Form that affect or may have influence on the engineering or construction of the transmission line shall be distributed to (the CLIENT’s Right-of-Way Manager, and the Project Manager). HLY 24-051 (06/96) Final 120293-01/ab 4 (Insert Figure 2.1-Organization Diagram) HLY 24-051 (06/96) Final 120293-01/ab 5 Figure 2.2 — Key Personnel Listing PROJECT POWER Engineers, Inc., Hailey, Idaho 3940 Glenbrook Drive P.O. Box 1066 Hailey, ID 83333 Main Switchboard 208/788-3456 Project Permitting & Right-of-Way Manager 208/788-0437 FAX 208/788-3017 HLY 24-051 (06/96) Final 120293-01/ab 6 2.2.1 Telephone Memoranda Memoranda of telephone conversations shall be prepared by POWER on the standard form (Figure 2.3) for field office retention as follows: e Original is retained in POWER’s applicable field office landowner or permit case file for transmittal to CLIENT at completion of the Project. HLY 24-051 (06/96) Final 120293-01/ab 7 (Insert Figure 2.3 — sample telephone record sheet) HLY 24-051 (06/96) Final 120293-01/ab 8 797) Memorandum of Conferences and Meetings POWER shall prepare a “Memorandum of Conference and Meeting” between the CLIENT and POWER, and other third parties, in accordance with the following format: Memorandum of Conferences and Meetings CLIENT/PROJECT POWER Project # (Date) (Subject) Meeting Held in Attending: Information on conferences and meetings shall include the organizations represented, and their addresses; attendees, including their names, titles, and telephone numbers; subjects discussed; results of the meeting, potential issues, and action items needing attention by the CLIENT and/or POWER and/or other organizations. Memoranda will be distributed to each meeting participant and a copy retained in the permanent project meetings record file in the field office. HLY 24-051 (06/96) Final 120293-01/ab 9 (Insert Expense Reporting Form) HLY 24-051 (06/96) Final 120293-01/ab 10 3.0 STATUS REPORT 3.1 Right-of-Way Status Report POWER’s Right-of-Way Status Report shall be used to enter basic parcel data for each parcel to be affected, as well as specific data relative to acquisition requirements and status of parcel-by-parcel activity. See Figure 3.1 for report format. Status reporting procedures are as follows: Each Right-of-Way Agent will be supplied with a hard copy status report for that section of the project on which they are currently working. Agents shall make hand-written entries of changes in the status of those report fields for which changes have occurred during the week. Each Friday by 10 a.m. the Agents will submit their weekly marked-up status sheets to the POWER Staff Assistant. The Staff Assistant will electronically compile all entries into the weekly updated report. Distribution of hard copy reports will then be made by the Staff Assistant by 10 a.m. Central Time Monday as follows: 4 Copy to the Supervisory Right of Way Agent Mw Copies to each Agent One copy faxed to the CLIENT Project Manager for distribution to the CLIENT Staff 4 One copy faxed to for distribution to POWER Staff 3.2 Final Status Report Each Right-of-Way Agent will ensure the accuracy and complete nature of their assigned parcel casé files. They will in turn assure that all final entries are made on the Status Report and will assure their accuracy and complete nature. HLY 24-051 (06/96) Final 120293-01/ab ll (Insert sample of Status Report) HLY 24-051 (06/96) Final 120293-01/ab 12 4.0 TITLE REPORTS 4.1 Title Searches & Reports 4.1.1 On Private Land POWER will obtain, as available, the current surface owner, address, legal description, last deed of record or the type of transaction, leasehold interest, contracts to purchase, deeds of trust and mortgages (name, address, and telephone number of mortgagee, amount of mortgage, and date), as well as prepare a Section Plat showing tract plotted according to description. The abstract and title search shall be carried back 25 years, or two transactions, whichever is longer, See Figure 4.1, “Limited Title Search.” Mortgage subordinations will not be required, unless otherwise requested on a case-by-case basis by CLIENT. 4.1.2 On Site Land POWER will obtain, as available, the name and address of lessee on commercial leases, grazing leases, and agricultural leases. Similarly, POWER will obtain the name and address of contract purchasers. HLY 24-051 (06/96) Final 120293-01/ab 13 Figure 4.1 Limited Title Search HLY 24-051 (06/96) Final 120293-01/ab 14 5.0 EASEMENT DOCUMENT PREPARATION 5.1 Easement Preparation POWER’s survey contractor, will prepare documents for the new easements. Each new document will include a written description and a plat of the easement which will be provided by the survey contractor. The documents will be formatted in accordance with the CLIENT’s requirements as follows: The surveyor shall complete the Easement Document Form provided by the CLIENT, in accordance with this section of the Survey Procedures Manual and any additional examples provided by the CLIENT. All documents shall be developed with as much consistency and uniformity as possible. Each Easement Document Form must be completed using methods that will eliminate the possibility of errors within the document. The Land Surveyor shall be responsible for placing the Parcel Number, Landowners Name(s) and the Legal Descriptions on the Easement Document Form approved by the CLIENT. When the Legal Description requires more area than is provided on the form, a second sheet will be used. The plat shall be the second sheet of the Easement Document. For all easements that require and Easement Area or Easement Strip Plat, a statement shall be placed in location for the Legal Description on the Easement Document Form stating, “See Sheet of Sheets of this Easement Document for the Electric Transmission Line Easement Description” or “See Sheet of ___— Sheets of this Easement Document for the Electrical Transmission Line Easement Area or Easement Strip Plat.” Three (3) copies of each Easement document shall be prepared. Whenever a plat is used as a part of the Easement Document, three (3) copes of the plat shall also be provided. The surveyor shall promptly transmit all completed Easement Document Forms to the Supervisory Right-of-Way Agent. When successful easement negotiations have been completed, the Agent will secure three fully executed counterparts of the document, notarizing each copy. One copy will be left with the landowner. A second copy will be recorded within twenty-four hours and retained in the permanent case file in the Office. The third copy will also be retained in the case file as a backup. HLY 24-051 (06/96) Final 120293-01/ab 15 Schl General Easement Document The general easement document is titled EASEMENT FOR ELECTRIC TRANSMISSION LINE and will generally be used for all new easements for the parcels both with or without structures, as well as for parcels with only as overhang. See Figure 5.1. S162 Consent for Lessee Use this form (See Figure 5.2) to obtain lessee or tenant consent. This form is intended to form a bridge between the fee owner of the property and the tenant. It is used to assure the fee owner that the tenant agrees to the project, and that the tenant will be compensated for any damages that may occur as a result of construction or maintenance. Any dispute between the owner and the tenant about who should receive the easement payment must be a matter to be resolved between those two parties, and should not become an element of easement negotiations between the CLIENT and the fee owner. Payment to the tenant for the consent to construct as indicated in the last paragraph of the form shall be one dollar ($1.00) and serves as the contractual consideration. No additional payment for the tenant/lessee signature will be made. (Note: the following forms have not been approved for use as of 9/14/94) S123 Access Road Easement Document. The title of this form is Access Road Easement (Figure 5.2). This form is used for a roadway easement when the Exclusive general easement document is insufficient. In this instance, the insufficiency occurs when access to the CLIENT facilities is via land not encumbered by the basic easement itself; that is, access is from neighboring land, etc. 5.1.4 Temporary Work Space Agreement. The title of this form is Temporary Work Space Agreement. This form is used exclusively for construction work space on lands adjacent to the right-of-way not granted by the easement agreement. Communication (with the contractor) is essential to determine specific areas for which this agreement will be necessary. See Figure 5:3) HLY 24-051 (06/96) Final 120293-01/ab 16 5.1.6 Right-of-Way Construction Conditions. It is the CLIENT’s policy to include any special conditions or stipulations relative to a specific parcel within the construction specifics. In this way, the easement document remains unencumbered, and specific landowner issue are cleared through the construction process. Therefore, special conditions should be noted on the comments portion on the Right-of-Way Status Report and incorporated into the Conditions Summary for the construction specifications. The following right-of-way conditions and stipulations are not voluntary measures. They are intended to demonstrate some willingness to accommodate specific landowner concerns should easement negotiations become stalled over resolution of non-monetary issues. Every attempt shall be made to acquire the Standard Form Easement agreement without additional construction obligations. In no event shall a landowner be given a copy of or allowed to read the following pre-approved right-of-way conditions. The following construction conditions are approved for all right-of-way agents in the field. There is no need to obtain clearance before committing to a landowner for any condition listed in this section. e Grantee agrees to H-brace all fences prior to cutting and return all fences to condition equal to or better than that which existed prior to construction. ¢ Grantee shall remove all construction waste and debris after completion of construction activities. e Grantee shall construct erosion control structures necessary to prevent and control erosion which is attributable to construction, operation, and maintenance activities. e Grantee shall restore all access roads disturbed by construction to a condition equal to or better that that which existed prior to construction. Restoration shall include final grading where necessary. ¢ Grantee shall re-seed disturbed areas along the right-of way with a seed mix native to the area or a specified by the Grantor. e Grantee shall restore the property after construction to as close to the original condition as it practicable. e Grantee shall protect all survey monuments located within the right-of-way. In the event survey monuments are disturbed and/or destroyed, it shall be the responsibility of the Grantee to re-establish said survey monument in conformity with survey standards then currently established for the State of HLY 24-051 (06/96) Final 120293-01/ab 17 e Grantee shall notify Grantor of the construction schedule a minimum of hours prior to the initiations of construction activities on the Grantor’s land. Grantor may be contacted at (telephone number). The following right-of-way conditions require the approval of the Right-of-Way Manager and/or the Field Right-of Way Supervisor prior to inclusion in a right- of-way and easement contract. Approval shall be on a case by case basis and approval in one circumstance shall not constitute approval for future circumstances. e Grantee shall indemnify and hold harmless Grantor from and against any and all loss, damage, or injury which may result from the construction operation and maintenance of the transmission line; provided however, that said loss, damage, or injury does not arise out of or result from the actions of the Grantor, his agents or employees. e Grantee shall fertilize disturbed soils within the right-of-way as recommended by the Soil Conservation Service or with a fertilizer specified by the Grantor. e Grantee shall compensate Grantor for all livestock losses which are caused by construction activities. Grantor shall keep sufficient records so as to allow independent verifications of all such claimed losses. e Grantee shall erect temporary fencing as necessary to control livestock and maintain the livestock a safe distance from the construction activities. e Grantee shall provide to Grantor, within one (1) year following the transmission line being placed in service, an as-built survey plan of the permanent transmission line easement. e During the period of construction, Grantee shall reimburse Grantor for the reasonable cost of alternate pasturing which may be required due to the conflicts in construction schedule and the sensitive livestock operation. Reimbursement shall include associated transportation costs for the movement of livestock. e Following construction, grantee shall scarify disturbed portions of the right-of- way to minimize soil compaction and enhance revegetation efforts. e Following right-of-way clearing, trees 4 inches in diameter or greater shall be cut into (4 foot to 8 foot) lengths and stacked along the edge of the right-of-way. Remaining slash and brush shall be clipped, burned, redistributed along the right- of-way, or disposed of after construction to assist restoration efforts. e Vehicle travel shall be limited to 25 miles per hour on access roads and along the right-of-way. HLY 24-051 (06/96) Final 120293-01/ab 18 Grantee shall install a fence or other barrier to prevent unauthorized access along the right-of-way. Where gates are installed, the Grantor and Grantee shall have keys to any locks which may be installed. NOTE: Right-of-Way Agents shall in no event commit the construction contractor or CLIENT to unrelated property improvements or repairs, or otherwise restrict the contractor’s ability to conduct normal construction sequence without the prior approval of the CLIENT. In the event the Grantee fails to initiate construction activities within the right of way and Easement within a period of years from the execution date hereof, said right-of-way agreement and easement shall become null and void. The following conditions are prohibited for all purposes. Right-of-Way personnel shall not inquire to obtain approval. The CLIENT shall not survey property boundaries or establish property corners, except under circumstances authorized in above sections. Clauses which prohibit the CLIENT from clearing certain trees within the right- of-way areas. Clauses restricting construction to specific item frames. Open-ended clauses in favor of the landowner/e.g., “construction shall be to the Grantor’s satisfaction.” Any terms obligating the CLIENT to pay an annual or other periodic rent. No indemnification clauses for the Grantor’s own negligence. No favored nation clause, i.e., no clause stating that the sum to be paid to a particular landowner for the easement shall be equal to the highest sum paid to other landowners. Each negotiation is discrete and stands on its own. The CLIENT shall not pay a landowner’s legal fees, except for the additional one-time payment of $100.00 that is intended for a legal review of the easement document. HLY 24-051 (06/96) Final 120293-01/ab 19 Sol) Distribution of Completed Documents. POWER will distribute the easement documents as follows: e Original to be maintained in Project Case File, by the CLIENT Right-of-Way Manager. e Copy to be maintained in Project office case file. HLY 24-051 (06/96) Final 120293-01/ab 20 Figure 5-1 Exclusive Right-of-Way and Easement HLY 24-051 (06/96) Final 120293-01/ab 21 Figure 5-2 Consent of Lessee HLY 24-051 (06/96) Final 120293-01/ab 22 Figure 5.3 Access Road Easement (Suggested format only. DO NOT USE WITHOUT PRIOR APPROVAL FROM THE RIGHT-OF-WAY SUPERVISOR) The undersigned, hereinafter referred to as Grantor, for and in consideration of Ten Dollars ($10.00) and other considerations paid to the Grantor by the CLIENT, hereinafter called the Grantee, the receipt of which is hereby acknowledged, does hereby grant, sell, and convey unto said Grantee its successors and assigns, a perpetual right-of-way feet in length and feet in width on which to construction, maintain and use a roadway overall and across the following described lands approximately along the line designated by survey heretofore made the following described lands approximately along the line designated by survey heretofore made the following described lands approximately along the line designated by survey heretofore made or hereafter to be made by the Grantee, through and over the said property situated in County, State of Subdivision Section Township Range It is understood and agreed that this road right-of-way does not and shall not extend generally for the use of the public, but is limited to and for the use of the Grantor and CLIENT, its successors and assigns, for its agents an employees, and for persons, firms, and corporations doing work for the said CLIENT, it’s successors and assigns. For the consideration, the Grantor(s) hereby waive(s) any claims for damages for the opening, repairing, maintaining and using of said roadway. Grantor represents and warrants that it is the owner in fee simple of the said described land. The rights herein granted are subject to outstanding easements of record in said County. Witness the execution this day of ,19___, by (CLIENT) (Grantor) HLY 24-051 (06/96) Final 120293-01/ab 23 Figure 5.4 Temporary Access and Agreement (Suggested format only. DO NOT USE WITHOUT PRIOR APPROVAL FROM THE RIGHT-OF-WAY SUPERVISOR.) The undersigned, hereinafter referred to as Grantor, for and in consideration of Ten Dollars ($10.00) and other considerations paid to Grantor by CLIENT, hereinafter called Grantee, the receipt of which is hereby acknowledged, does hereby give and grant unto Grantee, its agents, contractors, and employees, the right and privilege of using an existing road for the period of construction and restoration for ingress and egress to and from Grantee’s proposed pipeline, right-of-way and easement, over and across the hereinafter described lands. Description of property situated in County, State of Subdivision Section Township Range Grantee hereby agrees that after construction is completed on its electrical transmission line, it will restore or pay for the restoration of said road and thereafter have no further rights of interest therein. WITNESS THE EXECUTION HEREOF, this By by: CLIENT Grantor 19 day of LOTT HLY 24-051 (06/96) Final 120293-01/ab 24 Figure 5.5 Temporary Working Space Agreement (Suggested format only. DO NOT USE WITHOUT PRIOR APPROVAL OF THE RIGHT OF WAY SUPERVISOR.) The undersigned hereafter referred to as Grantor, for and in consideration of Ten Dollars ($10.00) and other consideration paid to Grantor by CLIENT, hereinafter referred to as Grantee, the receipt and sufficiency of which is hereby acknowledged, does hereby grant and convey unto Grantee, its agent, contractors and employees, the right and privilege of using as temporary working space a parcel of land, described as follows: County, State of It is understood and agreed by Grantor and Grantee that said working space is to be used in connection with the construction of Grantee’s electric transmission line. Upon completion of the above described work Grantee’s interest in said land shall revert to Grantor, except as provided by separate instrument. Damage if any caused by Grantee’s use of said land will be corrected or paid for by Grantee, provided that Grantee shall not be held liable for damage of any kind which arises due to the negligent act or willful misconduct of the Grantor, its successor’s, assigns, permittees, agents or contractors. WITNESS THE EXECUTION HEREOF, this day of 19 GRANTOR: BY: HLY 24-051 (06/96) Final 120293-01/ab 25 6.0 _PROPERTY VALUATION 6.1 Property Valuation POWER has contracted with to conduct project-area comparable sales research and individual parcel appraisals. Sales Report books by individual project county, and individual parcel appraisals will be made available to Right-of-Way Agents as follows: First third (beginning at ) by (date), Second third by (date), and the final third by (date). An important requirement for determining a tract’s before and after value will be the location of structures in the tract. It is imperative that the results of the Agent’s review of the structure location with the landowner, and any subsequent structure relocation be immediately communicated to the appraiser and to the design engineer. The parcel appraisal will provide the basis for the individual easement values. The appraisals will give before project and after project values. The Right-of-Way Agent will apply the before value to the CLIENT’s easement payment formula to determine the easement value. Under no circumstance shall offers by made to any property owner or tenant prior to the CLIENT’s concurrence with the basis of the offers. HLY 24-051 (06/96) Final 120293-01/ab 26 7.0 PRELIMINARY STRUCTURE REVIEW 71 Preliminary Structure Review POWER’s design engineers will conduct a preliminary structure spotting process whereby structure locations will be shown on preliminary plan and profile drawings and on full-size section photos. Upon receipt of these materials, the Right-of-Way staff will commence individual landowner review meetings to discuss the structure locations. It is imperative that the landowners understand the value to them to allow this meeting and review to take place. Without the benefit of knowing if any on the ground obstacles exist that may affect structure placement, such as a center pivot irrigation system, a well, grain bins or their structures, the designer must assume that the location is unencumbered. The on-site review is intended to provide the landowner an opportunity to discuss with the Agent the right of way layout. The Agent should include in his exhibits to show the landowner, the appropriate plan and profile drawing, the section photo, and the landowner questionnaire. The Agent has some latitude to make minor adjustments in the structure location in order to accommodate a landowner concern. Under most circumstances those adjustments will be limited to: A. In-line = 30 feet B. Sidewise = 10 feet Should an unusual circumstance warrant a longer distance move, the design engineer will be consulted immediately, and may elect to visit the site. In all cases the result of each structure review, including responses to the questionnaire will be conveyed to the design engineer on a weekly basis. This response will be made whether or not structure location changes have been made. HLY 24-051 (06/96) Final 120293-01/ab 27 8.0 _EASEMENT PAYMENT POLICY & PROCEDURE 8.1 Easement Payment Policy After final structure and right of way locations have been determined, land appraisals completed, and easement descriptions written, and prior to easement acquisition, easement payment will be determined for each easement parcel using the following factors: The appraised value of the parcel. The limited rights being obtained The impair of structure on existing land use. Any special consideration; i.e., creation of an uneconomic remainder, effect on improvements that may require them to be relocated. GOP The total easement payment will typically include the following elements: A. Payment for _ percent of the fee value of the land area within the boundaries of the easement. Base this percentage on the ”Before” value according to the parcel appraisal. B. Payment of $ for each transmission structure located on the parcel. The purpose for the structure payment is to compensate landowners for any additional cost which may be incurred due to the presence of the structure including: a. Loss of net income from cropland removed from production due to the inability to operate various types of farm equipment directly under and immediately adjacent to the lattice structure. b. Loss of time due to the inconvenience of maneuvering farm equipment around structure bases. c. The cost (labor and materials) of applying persistent herbicides to the area removed from production under and adjacent to structures. C. In addition to the above, each landowner who voluntarily signs an easement contract will be paid $ for expenses that might be incurred by the landowner for legal review of the easement document. D. As an option to a one-time lump sum payment, the CLIENT will consider deferred annual payments for a period up to five years based on a fixed 4% simple interest rate on the unpaid balance. Interest would be paid annually and all payment would be paid out of the CLIENT’s general reserves. If special circumstances warrant, the CLIENT will discuss deferred payment over a period for time greater that five years (but not exceed ten years). HLY 24-051 (06/96) Final 120293-01/ab 28 8.2 Easement Payment Procedure Upon conclusion of an easement acquisition, and obtaining fully executed and notarized easement documents (three copies) the Right-of-Way agent will immediately complete a Special Payment Request (see Figure 9.1 below). The request form will be sent to the CLIENT, attention to (the CLIENT Project Manager) for review and payment. The CLIENT typically processes these payment within 2-3 weeks. This schedule will be explained to the landowner. If a landowner contacts the Agent about not receiving payment, the Agent will contact (the CLIENT Project Manager), or a designated CLIENT Accounting person for information with which to follow-up with landowner. HLY 24-051 (06/96) Final 120293-01/ab 29 Figure 8.1 HLY 24-051 (06/96) Final 120293-01/ab 30 9.0 _DAMAGE CLAIMS 9.1 Damage Claim Investigation All landowner claims of damages resulting from project-related activities will be immediately investigated by the appropriate Agent. Various data sources are available to determine a credible resolution to the claim: A. Soil Conservation Service - County Agent caf 9.2 Payment for Damages The CLIENT’s damage claim payment policy is as follows: A. For damages valued at less that $50.00, pay $50.00 B. For damages valued at $51-100, pay $100.00 C. For damages valued at over $100.00, pay actual value. In the circumstance of multiple year crop losses, caused by ongoing construction activities, multiple payment will be made (i.e., construction interferes with growth or harvest of one crop year, and extends into next planting season). All damages will be calculated on an “actual loss basis.” Damage that results from maintenance work in future years will be paid for by the CLIENT immediately after it occurs. 9.3 Damage Payment Procedure Payment for damages will be processed using the Special Payment Request as described in Section 8.2. The damage claim will be documented using the Construction Damage Inventory Form (see Figure 9.1) This is multi-copy form that includes a section for landowner and tenant acknowledgment of the receipt of damage settlement payment and the release of the CLIENT from any further liability relative to the inventory of damages on that particular claim. The Agent will distribute copies of the form according to instructions on the form. HLY 24-051 (06/96) Final 120293-01/ab 31 (Insert Figure 9.1) HLY 24-051 (06/96) Final 120293-01/ab 32 10.0 CONDEMNATION PROCEDURES 10.0 CLIENT Eminent Domain Policy* *(Varies from state to state. The following is an example only.) Eminent domain is the right, granted by state law, permitting the condemnation of land by the CLIENT for facilities which will benefit the general public. Condemnation or eminent domain proceedings are started when the landowner and the CLIENT cannot reach a settlement, or when the landowner is unable to grant a prior easement because of a defect in the land title. The court of the county of the condemnation action appoints three appraisers to determine the value the landowner will be paid for the easement. Once the CLIENT has paid this amount of money to the court which is then turned over the landowner, the CLIENT is allowed to proceed with construction. Both landowner and the CLIENT have the right to appeal this award to the higher court if they are dissatisfied. Right-of-Way Agents will be prepared to support the CLIENT’s legal staff during condemnation actions. This will include ensuring that all case file documentation is complete, legible, and professionally presentable as evidence. NOTE: Be sure to determine when possession of the property is granted for purposes of survey and construction. HLY 24-051 (06/96) Final 120293-01/ab 33 ae 11.0 Records Close-Out Files Quality Check Upon completion of the project, Right-of-Way Agents will conduct a final quality check of each file under their respective responsibilities. Each file will be checked as to the following items prior to its being transmitted to (the CLIENT Project Manager), CLIENT: ae be ES Oe Ae OF 10. 11. 12. Project Name Legal description of parcel, including county, section, township, and range, and the surveyors easement description. Current owner(s) of record, including address and phone number. Easement grantor Recorded date of easement Recording information Fully executed and notarized easement document. Other fully executed instruments as appropriate to the parcel: a. Right of Entry b. Consent of Lessee ( Construction Damage Inventory d. Temporary Access Agreement e. Permanent Access Agreement Copy of Request for Special Payment Title Report Verify that the Grantor signature(s) on documents agree with Title information. Assure that document amendments or alternations are initialed and fully executed. Upon completion of the quality check, Agents will assemble file in appropriate containers and transmit to (the CLIENT Project Manager), CLIENT. Such transmittal shall be by personal hand delivery. HLY 24-051 (06/96) Final 120293-01/ab 34