HomeMy WebLinkAboutS Intertie Status report 7-1997CHUGAC,. ELECTRIC
ASSOCIATION, INC.
EGEIVE
July 11, 1997 JUL 16 1997
Alaska Industrial Development Alaska Industrial Development and Export Authority and Export Authority
480 West Tudor Road
Anchorage, Alaska 99503
Attention: Mr. Dennis V. McCrohan, P.E., Deputy Director, Energy
Subject: Southern Intertie - Status Report
Dear Mr. McCrohan:
In response to your letter of June 20, 1997, we have prepared the enclosed status report for the
Southern Intertie. Please, review the document and let us know, if additional information is
required.
If you so desire, Dora Gropp, our Project Manager, is prepared to make a brief presentation
and/or is available to answer questions at AIDEA’s Board of Directors meeting. Please, contact
her direct at 762-4626, or e-mail to dora_gropp@chugachelectric.com to discuss her
participation.
Sincerely,
dpa EA
Sr Eugene N. Bjornstad
General Manager
i
Enclosures
C3 IPG Utility General Managers, w/
Steve Haagenson, GVEA, w/
Lee Thibert, w/
Mike Massin, w/
Dora Gropp, w/
Don Edwards, w/
W.0.#E9590081, Sec., 2.2.2.1
RF
5601 Minnesota Drive * P.O. Box 196300 * Anchorage, Alaska 99519-6300
Phone 907-563-7494 * FAX 907-562-0027
Il.
CHUGACH ELECTRIC ASSOCIATION, INC.
Anchorage, Alaska
July 11, 1997
SOUTHERN INTERTIE
W.O. E9590081
STATUS REPORT
INTRODUCTION
The Southern Intertie is a new proposed transmission line between the Anchorage area
and the Kenai Peninsula.
Chugach Electric began project activities on behalf of the Intertie Participant Group (IPG)
in mid 1995 with a Route Selection Study. This study was performed by Power Engineers
with Dames and Moore as a sub contractor for environmental work and completed in June
of 1996. It resulted in the identification of three possible corridors for the proposed
transmission line, but did not establish a preferred route.
The IPG then authorized Chugach Electric to take the project to the environmental
permitting phase with the originally selected consultants. The Rural Utility Services
(RUS), as the federal lead agency, published a Notice Of Intent (NOI) to prepare an
environmental impact statement (EIS) for the project in October 1996. Scoping meetings
were held in Anchorage, Kenai/Soldotna, and Cooper Landing in November 1996 and
Community Working Groups were formed in Anchorage and on the Kenai Peninsula to
assist with impact assessment, mitigation and route selection. Other agencies with
jurisdiction over various aspects of the project were invited to join RUS in the EIS
process. The EIS preparation is now under way with RUS as the lead agency and the US
Fish and Wildlife Service (USFWS) and the US Forest Service (USFS) as cooperating
agencies. Chugach’s consultant will prepare an Environmental Analysis (EVAL), which
RUS - most likely with assistance from a consultant - will use to prepare the EIS. We
expect that a preferred alternative will be selected by September of this year. Extended
review and public comment periods between the release of the draft EIS (DEIS) and the
final decision are required by the various agencies involved. The final EIS and a Record
Of Decision (ROD) are therefore not expected to be available before February of 1999.
PROJECT DESCRIPTION
The Route Selection Studies identified three corridors for the new transmission line.
These corridors,” Tesoro”, “Enstar” and “Quartz Creek” as well as a sub-alternative within
the Quartz Creek corridor, “Hope”, are shown on the map below:
CADATA\ANNALISA\WPDOCS\E9550061 \PHIBKAIDASTAT. WFD
SOUTHERN INTERTIE
STATUS REPORT Page 2 of 4 July 11, 1997
ROUTES: pCHORAGE GENERATION ~ 806M T - Tesoro mn
E - Enstar
Q - Quartz Ck
H - Hope
SOLDOTNA
KENAI GENERATION 244.N
Estimated construction costs for these routes at two different voltage levels and two
different submarine cable configurations are shown in the following table:
Cost - 1996 $
Quartz Creek’
138kV $108-$126' $96-$107!
$$ millions $85 to $95
$89 to $104? $85 to $917
230kV
$$ millions $120 to $139 $109 to $119 $100 to $116
Line Length
Base Route 62 miles 77 miles 140 miles
Note 1: Submarine Cable: 4 - 1 phase SCFF
Note 2: Submarine Cable: 2 - 3 phase Flat SCFF
Note 3: Includes Hope Route Alternative
Major project facilities consist of overhead lines, underground and submarine cables with
the associated terminal stations. Refinements are still under way as to structure types to
be used as well as cable design.
IDATA\ANNALISA\WPDOCS 9590081 PHI BAIDASTAT.W
SOUTHERN INTERTIE
STATUS REPORT Page 3 of 4 July 11, 1997
The final route selection will be greatly influenced by reliability considerations and
regulatory constraints.
The Quartz Creek Route is the only all overland route and follows the existing
transmission line. It traverses the Chugach National Forest and Chugach State Park.
Reliability concerns associated with simultaneous avalanche and other hazard exposure of
two transmission lines and regulatory constraints in regard to rights of way may make this
route not viable.
The ENSTAR Route follows the existing pipeline and traverses the Kenai National
Wildlife Refuge. It will have to be permitted under ANILCA regulations. Routing in the
Anchorage area leads through residential and commercial neighborhoods and will require
special consideration in regard to alignment and structure configuration and placement. It
also includes about 9 miles of submarine and 5 to 6 miles of underground cable, which
increase construction costs. The general location of the submarine crossing has been
investigated and found to be feasible.
The TESORO Route follows the pipeline corridor near the west coast of the Kenai
Peninsula. This corridor traverses Captain Cook State Park, private and state lands as
well as a native allotment. The submarine crossings from Pt. Possession to Pt.
Campbell/Pt. Woronzof is 13 to 14 miles long and makes up 50% of the overall
construction costs. These submarine cable portions would be located in a zone of very
high tidal currents and rocky bottom conditions and difficult to protect from
environmental hazards.
lil. BUDGET
Costs to complete the EIS process are estimated at $5,009,916, of which $2,760,091 have
been spent as of June 1997. Funds for the project are presently committed as follows
(without allocated contingencies):
Task Commi Spent
Routing Studies (complete) $ 814,995 $ 814,995
Environmental Analysis (55% spent) $3,146,470 $1,762,822
Agency Reimbursements (22% spent) $ 155,554 $ 34,954
Economic Feasibility Update (0% spent) $ 45,000 $ 0
Project Management (33% spent) $ 440.000 $ 147.320
Total $4,602,019 $2,760,091
(CNDATA\ANNALISA\WPDOCS\ESS90081\PHIE\AIDASTAT. WPD
SOUTHERN INTERTIE
STATUS REPORT Page 4 of 4 July 11, 1997
IV. SCHEDULE
The project phases are anticipated to be accomplished according to the following
milestones:
Environmental Process 1996 to 1999
Pre-Construction Activities 1999 to 2001
Construction 2001 to 2003
In Service 2004
A more detailed schedule, which shows the major tasks associated with the EIS process is
attached.
(CNDATA\ANNALISA\WPDOCS\E9S50081 PHIBAIDASTAT. WFD.
CHUGACH ELECTRIC ASSOCIATION ANCHORAGE - KENAI INTERTIE 6/20/97
PHASE IB
1995 1996 [ 1997 1998 1999 2000
1D__| Task Name % Comp. | Act. Cost ar res [aa a2TasTa4]arfa2[as[a4s{arfaz[as[as ai [a2Tas[a4[ai[a2 esloul ct 1 | ENVIRONMENTAL & ENGINEE 38% | $2,749,112.84 i i
2 PROJECT MANAGEMENT 20%| $80,005.50
3 ROUTE SELECTION STUD 100% | $871,650.00
4 EIS & PREL.ENGINEERIN 50% | $1,762,503.34
5 SCOPING 97%| $364,715.78
6 INVENTORY 90%| $608,790.98
7 IMPACT/MITIGATION 62%| $374,486.81 a0 | an
8 ALTERN.SELECTION 12%| $36,414.49 an a 8/29
9 DRAFT EIS 9%| $36,689.76 " é :
10 FINAL EIS 0% $0.00
"1 STUDIES 58%| $62,069.07
12 ENG.FIELD WORK 91%| $184,406.25
13 PREL. ENGINEERING 50%| — $94,930.20
4 AGENCIES 20%| $34,954.00
15 USFS 20%| $34,954.00
16 USFWS 20% $0.00
Task Summary Qe olled Up Progress Project: ANCHORAGE - KENAI INTE a Date: 6/20/97 Progress Rolled Up Task
Milestone a Rolled Up Milestone <> C:\WINPROJ\SOUTHTIE\PH_IB.MPP Page 1