Loading...
HomeMy WebLinkAboutS Intertie Grant 1996Southern Intertie Environmental Budget Power Engineers Chugach Electric Federal Lead Agency Feasibility Analysis Total Base Amount $3,043,423 400000 100000 200000 $3,743,423 Sheet1 Contingency $304,342 $40,000 $10,000 $20,000 $374,342 Page 1 Total $3,347,765 $440,000 $110,000 220,000 $4,117,765 Dhavne ALASKA INDUSTRIAL DEVELOPMENT AND EXPORT AUTHORITY RESOLUTION NO. G96-09 A RESOLUTION OF THE ALASKA INDUSTRIAL DEVELOPMENT AND EXPORT AUTHORITY AUTHORIZING THE DISBURSEMENT OF A PORTION OF GRANT PROCEEDS IN CONNECTION WITH A PROPOSED INTERTIE BETWEEN ANCHORAGE AND THE KENAI PENINSULA, AND TAKING RELATED ACTIONS RELATED TO INTERTIE PROJECTS WHEREAS, the Alaska Industrial Development and Export Authority ("Authority") is administering grants made available for the development of the power transmission intertie between Anchorage and the Kenai Peninsula (the "Southern Intertie") ; WHEREAS, in Resolution G95-20 the Authority approved the disbursement of up to $900,000 of grant funds for certain preliminary project development tasks ("Phase I Work") ; WHEREAS, Chugach Electric Association, on behalf of the participating utilities, has completed the Phase I Work contemplated under Resolution G95-20 and is now requesting funding to proceed into the Environmental Impact Statement analysis and preliminary engineering with respect to the Southern Intertie ("Phase II Work") ; WHEREAS, the Authority has reviewed the Phase I Work and found it to be complete; WHEREAS, the Authority recommends, and the participating utilities concur, that the analysis for the Environmental Impact Statement should include a cost-benefit analysis of the proposed Intertie; WHEREAS, the Authority estimates the cost of the work proposed by Chugach Electric Association for the next phase of project development will be $4,200,000; WHEREAS, the Authority finds it reasonable and in the public interest to release an additional $4,200,000 in grant funds, subject to such reasonable terms and conditions the Authority may impose, to facilitate continued development of the Project; NOW, THEREFORE, BE IT RESOLVED: a The Executive Director is authorized to release up to $4,200,000 of grant funds to undertake Phase II Work, providing that the participating utilities agree in writing that the Environmental Impact Statement analysis will include a cost- benefit evaluation of the Southern Intertie. au The Executive Director may impose reasonable terms and conditions relating to the release of the Phase II funds authorized in Section 1. Ce The Executive Director of the Authority is directed to monitor progress of the utilities with respect to the RESOLUTION NO. G96-09 PAGE 2 resolution of the core development issues related to the Intertie Projects and report to this Board with respect to such progress. 4. The Executive Director is authorized and empowered to take any and all actions appropriate and consistent with this Resolution. DATED at Anchorage, Alaska this 21st day of May, 1996. ea es Chairman (S E A L) ATTEST Secretary PAGE 3 RESOLUTION NO. G96-09 Quality § vives ) (907) 274-1056 Date 2 4 4986 PENINSULA CLARTON Client No.__ eA More reliable power goal of intertie plan AICE 302 ¥2I0A By KIRSTEN SCHULTZ Peninsula Clarion A plan to connect Anchorage and Kenai Peninsula electric utili- ties will raise rates, but the projec- t's managers say it should eliminate some outages and keep costs down in the long run. The Southern Intertie Project, which has been in the works since 1993, would connect Homer Electric Association customers with those in Anchorage and the Matanuska-Susitna Valley. It's designed to improve electri- cal service by sharing power between those areas. If Chugach Electric Association’s Beluga Power Plant goes down, for exam- ple, then the HEA-operated Bradley Lake hydroelectric facility near Homer could pick up the slack. There already is a transmission line connecting the peninsula to Anchorage, but it was built more than 30 years ago and only can carry about 70-or-so megawatts. The new intertie would bump that total up to 120 megawatts. Phil Steyer, a spokesperson for Chugach Electric, compares the intertie with an extra car idling in the driveway for back up. “We need to strengthen that elec- trical structure,” Steyer said. “The power line between the Kenai and Southcentral is not that reliable.” The current line was constructed in areas prone to avalanches, and so sometimes goes down in the winter. The new intertie would take advantage of an abundance of. power on the Kenai Peninsula. The peninsula is home to four different power plants, which are able to pro- duce 247 megawatts of electricity. So far, the line to Anchorage hasn't been strong enough to run any high- er than 75 megawatts and there aren’t enough HEA customers on the Kenai to use the difference. “We've got extra power ava able here that we can’t run,” Stey said. “We're constrained in o ability to use power.” The intertie, said Steyer, wou beef up Anchorage’s ability to dre on peninsula power — two of t four peninsula power plants a owned by Chugach’s 54.000 mer bers. But what about customers her Most outages on the Keni arer See INTERT :k pa q) VAAN neyuniT \ ...Intertie 210E 392 Y2dA Continued from page 1 caused by disconnections in the line from Anchorage. They're caused by something much less technical — falling trees. According to Don Stead, man- ager of power production with HEA, the majority of peninsula out- ages over the last year were caused by trees or branches falling on or touching power lines. There are some cases where a stronger intertie would have been helpful. In October of 1992, for example, a heavy snowstorm cut the peninsula off from Anchorage, causing brown-outs here. Steyer said the new intertie wouldn’t guarantee outage-free ser- vice, but it would help stop certain types of outages. “It will reduce out- ages related to the existing intertie.” The new intertie also will improve reliability on the Kenai, Steyer said. Power can flow either way, so ifthe Kenai does experience a shortage of some kind, more elec- tricity from Anchorage can be shut- tled down here. “That same power line can just as easily flow south,” he said. What’s. more important, Steyer said, is HEA’s ability to buy power at cheaper rates. HEA buys almostall ofits power from Chugach, but gets electricity at different rates depending on where it comes from. Sometimes, Steyer said, getting power from Chugach’s Beluga plant north of Tyonek isa better deal for HEA than buying it down the road from Chugach’s Bernice Lake facility north of Nikiski. Even though rates will go up ini- tially, power bills will be lower in the long run, said HEA board mem- ber Ron Rainey. “T think it’s very good for HEA,” he said. “It ties resources together.” If everyone is linked, Steyer said, everyone is sharing the cost of infrastructure. If the peninsula was separate from everyone else, power costs would be much higher. “Putting the line in ultimately keeps costs lower,” Styler said. While rates definitely won’t go down, the intertie should keep rates from rising as quickly. But because the project still is in the planning stages, there are sever- al unknowns. Planners say they aren’t sure how much the project will cost, exactly how much it will raise rates or even where the line will be built. Customers of the participating electric cooperatives, including HEA, will end up paying for some of the project. The state is kicking in $46.8 million, but project man- agers won’t know the total bill until a site for the intertie is selected. Some site ideas for the Anchorage-peninsula: intertie should be picked by the end of June. According to Dora Gropp, man- ager of transmission and special projects at Chugach, the intertie’s three-year construction schedule should start in 1999 at the earliest. Currently, the intertie project committee, made up of representa- tives from seven different utilities, is taking public comment before it draws up a list of possible routes. A public meeting will be held from 5:30 to 9 p.m. on Feb. 1 in Soldotna in the Kenai Peninsula Borough Assembly chambers. The event will include an open house, in which engineers and utility repre- sentatives will answer questions. A formal presentation will be at7 p.m. Tim Tetherow, project manager with Dames & Moore, the intertie’s engineering firm, said he is looking for ideas on where the line should be built and what obstacles the intertie should avoid. The intertie itself won’t have “big lattice tower structures,” Tetherow said. - Instead, it will have either 80-by- 60-foot steel towers, which look like an “X,” or 20-by-50-foot wood- en frames, in the shape of an “H.” Tetherow said the committee is trying toconsider the recreation and visual impacts of the intertie. It is looking at running the intertie along already existing structures, like pipelines. But where the line actually runs isn’t up to the utilities. A federal agency, which has yet to be namc will oversee the project and ma the final decision. A similar project, connecti Healy with Fairbanks, is furth along. Its budget is ‘set at $70 millic including a $43.2 million gra from the state. Fairbanks Municipal Utiliti also won’t know how much mon will be added to 4 typical cu tomer’s monthly bill until a budg is worked out before constructi: starts next fall, at the earlie: Participating cooperatives ha until right before construction decide if they want to sign on to tl project. Once the Fairbanks-"" * ' inte tie and the Anchorag ‘insu intertie have both been vusn, mo residents in Alaska would be co nected to the same power grid. Cope fae Ts anDi™M . Dew G. € — Bee oe ALASKA INDUSTRIAL DEVELOPMENT > AND EXPORT AUTHORITY {= ALASKA Me ENERGY AUTHORITY 480 WEST TUDOR ANCHORAGE, ALASKA 99503 907 / 269-3000 FAX 907 / 269-3044 July 31, 1996 Qcop eed Se ea Eugene N. Bjornstad fF @ [E " VW f D same, 1 osc General Manager Chugach Electric Association, Inc. r P.O. Box 196300 Anchorage, Alaska 99519-6300 Alaska Industria! Development and Export Authority Subject: Southern Intertie Funding Conditions Dear Gene: As previously discussed AIDEA will release grant funds for the Southern Intertie to Chugach Electric Association (CEA) in advance of expenditures under certain conditions. Those conditions are as follows: 1. CEA will document the reasons for, the amount requested and the cash flow needed for release of grant funds. AIDEA, in its sole discretion and subject to Board approval, will determine the timing and amounts of any release of grant funds. 2: All grant funds shall be segregated from other CEA funds by placing the grant funds in separate specified interest bearing accounts (“grant accounts”). The funds and interest earned on the funds may only be used for project expenditures. 3. All earnings on the grant funds shall remain in the grant accounts and shall not be disbursed without prior budget approval by AIDEA. CEA shall provide monthly reports on the grant accounts’ activity, including interest earned, amounts expended and available balances. 4. The funds shall be invested to earn the maximum interest possible considering the project cash flow needs. Eugene Bjornstad July 31, 1996 Page 2 5. CEA shall monthly provide reports on the scope of work, project budget, expenditures, progress, schedules and any exceptions to the budget and schedules. (Updates in the format of those reports currently being provided to AIDEA will satisfy these requirements.) AIDEA approval is required prior to the expenditure of funds in excess of budgeted amounts or use of contingency funds. The audit requirements of 2 AAC 45.010 apply. The audit for each preceding calendar year shall be submitted to AIDEA no later than April 15 each year. In the event the project is terminated and funds remain, the funds shall be returned to AIDEA. The release of funds under this procedure does not constitute a waiver of the general procedure established in Section 4.03 of the Gran Administration Agreement. If the above conditions are acceptable to CEA, please note your acceptance in the space provided below and return a signed copy to AIDEA. AIDEA will wire funds to the grant account(s) designated by CEA based on approved individual requests. Sincerely yo 1 William R. Shell Executive Director Chugach Electric Association, Inc. agrees to the above conditions. = Eugene Mpc jornstad General Manager Chugach Electric Association, Inc. 4 ~ SENT’ BY: 8-15-96 + 9:24AM ; CHUGACH ELEC XY f i#1/ 93 ) wes a, Dgin I G, Chugach Electric Assn. PO Box 196300, Anchorage, Alaska 99519-6300 Z Date: 08/15/96 Number of pages including cover sheet: 3 FAX Valerie Walker Phone; 907-269-3000 Fax phone: 907-269-3044 CC: Phone: 907-762-4778 Fax phone: 907-562-0027 REMARKS: ®& Urgent O Foryourreview [] Reply ASAP OO Please comment Valerie, Attached is a signed copy of the agreement for release of the Southern Intertie Grant Funds. The agreement was signed approximately 10 days ago, but evidently got lost in the mail. R¢gards, ike Cunnin; Controller SENT’ BY: 8-15-96 ; 9:24AM ; CHUGACH ELEC" 'C> 1# 2/3 ALASKA INDUSTRIAL DEVELOPMENT ‘call > 4 Re ee = ee i ENERGY AUTHORITY 480 WEST TUDOR July 31, 1996 ANCHORAGE, ALASKA. 99503 907 / 269-3000 FAX 907 / 269-3044 Eugene N. Bjornstad a fl General Manager Chugach Electric Association, Inc. P.O. Box 196300 Anchorage, Alaska 99519-6300 Subject: Dear Gene: Southern Intertie Funding Conditions As previously discussed AIDEA will release grant funds for the Southern Intertie to Chugach Electric Association (CEA) in advance of expenditures under certain conditions. Those conditions are as follows: Ue CEA will document the reasons for, the amount requested and the cash flow needed for release of grant funds. AIDEA, in its sole discretion and subject to Board approval, will determine the timing and amounts of any release of grant funds. All grant funds shall be segregated from other CEA funds by placing the grant funds in separate specified interest bearing accounts (“grant accounts”), The funds and interest earned on the funds may only be used for project expenditures. All earnings on the grant funds shall remain in the grant accounts and shall not be disbursed without prior budget approval by AIDEA. CEA shall provide monthly reports on the grant accounts’ activity, including interest earned, amounts expended and available balances. The funds shall be invested to earn the maximum interest possible considering the project cash flow needs. SENT BY: for 8-15-96 ; 9:24AM ; CHUGACH ELE™™""C> Eugene Bjornstad July 31, 1996 Page 2 Ss CEA shall monthly pravide reports on the scope of work, project budget, expenditures, progress, schedules and any exceptions to the budget and schedules. (Updates in the format of those reports currently being provided to AIDEA will satisfy these requirements.) AIDEA approval is required prior to the expenditure of funds in excess of budgeted amounts or use of contingency funds. The audit requirements of 2 AAC 45.010 apply. The audit for each preceding calendar year shall be submitted to AIDEA no later than April 15 each year. In the event the project is terminated and funds remain, the funds shall be returned to AIDEA. The release of funds under this procedure does not constitute a waiver of the general procedure established in Section 4.03 of the Gran Administration Agreement. lf the above conditions are acceptable to CEA, please note your acceptance in the space provided below and return a signed copy to AIDEA. AIDEA will wire funds to the grant account(s) designated by CEA based on approved individual requests. Sincerely yo William R. Shell Executive Director Chugach Electric Association, Inc. agrees to the above conditions. Eugen ey Gee ornstad General Manager Chugach Electric Association, inc. 1# 3/3 April 29, 1996 Southern Intertie Status The 1993 legislation appropriated $46,800,000 as a grant for the Southern Intertie. Subsequently, AIDEA authorized by Resolution GS 95-20, $900,000 of the grant funds for Route Selection studies. Phase 1A Route Selection of the Southern Intertie is essentially completed. A Final Report will be issued in May 1996. The prime participants in the work were Chugach Electric Association (CEA), Power Engineers, and Dames and Moore. The objectives of Phase 1A were to identify the most viable routes for the Intertie, the most significant environmental constraints, and major technical concerns. These objectives have been accomplished. Public meetings have been held with effected communities. The work is within budget and expected to be completed for a total cost of less than $900,000. The major results of Phase 1A were: ils The three (3) most viable routes were identified. These are the Tesora Corridor, the Enstar Corridor, and the Quartz Creek Corridor. Each has minor variations to the routing. 2 The estimated cost of the total project, depending upon the final routing, varies from $85 to 135M. 3. The major technical issue appears to be the feasibility and location of a submarine cable crossing of the Turnagain Arm or Cook Inlet, depending on the route selection. The termination facility for the submarine cable of the Intertie in the Anchorage Bowl and subsequent routing to the connecting substation is of lesser technical and economic importance but raises considerable local Anchorage concern. CEA is now proposing to start the next phase which includes the environmental impact statement and preliminary engineering. The next phase is to analyze the three routes using the Environmental Impact Statement (EIS) process. CEA has assumed that an EIS will be required. All three routes will be analyzed in parallel. This is a conservative and reasonable approach. It is anticipated that the Rural Utility Service (RUS) will be the lead review agency for the EIS. The preliminary engineering include system and configuration studies, hydrographic and geotechnical studies, preliminary engineering of the submarine cables, cable transition site selection, and substation design. This stage is anticipated to start in May 1996. The completion milestone would be the receipt of the EIS Record of Decision (ROD) for the preferred route. This is scheduled for June 1998. Funding for this phase will be provided by the State grant and is estimated to be about $3,500,000. A new AIDEA resolution will be required to authorizing use of these grant funds. Considerations include: 1. For some AIDEA projects a reimbursement agreement is required which requires the developer to refund all State moneys if the project does not proceed. Since the project is funded by a State grant and since there was no reimbursement agreement on the Northern Intertie, it would seem unreasonable to impose such a reimbursement requirement on the Southern Intertie. However, the Southern Intertie will be controversial due to Federal and State land and National Wildlife crossings. Due to the nature of the Southern Intertie project, project completion is not assured. Significant grant funds would be at risk. 2s AIDEA must release the $3,500,000 funding prior to start of this stage in May 1996. While it might be prudent to release the funds in stages, depending upon completion of milestones, the project approach is not conducive to a definitive scope with milestones. The plan must be flexible and easily altered so as to be responsive to the environmental concerns raised in the review and hearing processes. Ultimately the only milestone of consequence is the ROD. 3. During the public meetings there were several comments regarding the feasibility of the Intertie and what effect it would have on rate payers, particularly in the CEA territory. While this was addressed in the late 1980’s and early 1990's in several reports, these reports and the data base used for the reports is considerably out of date. AIDEA suggested to CEA that such an economic feasibility analysis be added to this next stage to reaffirm the project viability. CEA agreed to consider this request. 4. The 1993 legislation contemplated a Southern Intertie ownership structure where the Intertie would be owned by CEA for the benefit of the participating utilities. Subsequently, the Participating Utilities agreed that both the Northern and Southern Intertie ownership would be shared. Ownership agreements were formed but many issues remain unresolved. While the Northern Intertie has completed most of their environmental work and preliminary engineering, ownership issues including cost and benefit sharing remain to be resolved. AIDEA placed a condition that no funds for procurement or construction would be released on the Northern Intertie until these issues were resolved. On the Southern Intertie, the ownership issues will not arise until the Northern Intertie ownership is resolved. There currently are no significant ownership issues but may arise once procurement and construction starts or if the Northern Intertie ownership structure changes. AIDEA should decide an approach on the Southern Intertie regarding the timing for a resolution of ownership issues. Please let me know if any additional information is needed. ALASKA INDUSTRIAL DEVELOPMENT % AND EXPORT AUTHORITY =, ALASKA im ENERGY AUTHORITY ———————————————— _—_ 480 WEST TUDOR ANCHORAGE, ALASKA 99503 907 / 269-3000 FAX 907 / 269-3044 MEMORANDUM TO: William R. Snell Executive Director FROM: Dennis V. McCrohan, P. WA Deputy Director - Energy DATE: April 15, 1996 SUBJECT: Southern Intertie Stage 2 | have reviewed the Southern Intertie status for the upcoming meeting. The objectives of the next stage of the project are to obtain the ROD, define a preferred corridor, develop a reasonable cost estimate but not necessarily a definitive construction cost estimate, and develop an implementation schedule. The status is: 1. Power is asking to proceed with the full EIS analysis for all three favored corridors. These are Turnagain Arm/Bird Point, Enstar Corridor, and Tesora Corridor. 2 Environmental activities will include the field reconnaissance data collection. No met stations or permanent facilities are envisioned. The environmental work will be data review and correlation, analysis, and modeling of impacts. 3. Preliminary engineering is expected to be limited to underwater cable routing and associated geotechnical analysis and drilling, and some definition of onshore facilities such as underground corridors in Anchorage and onshore underwater cable terminals. Preliminary engineering would be providing a definition for the environmental analysis and to produce a conceptual cost and schedule for each corridor. 4. Anticipated schedule for this stage is 30 months commencing in June 1996. The estimated cost is $3.5M which is consistent with the overall project budgets. Memorandum April 15,1996 Page 2 5. The EIS scope includes the scoping meetings with the agencies and the numerous general public information and comment meetings. 6. Land acquisition activities are limited to definition of land parcels and requirements to gain access for necessary environmental reconnaissance work. The scope of work appears quite reasonable and prudent for this stage of the project. While the release of funds might be staged, the scope does not lend itself to interim measurable milestones nor staging. The only possible reduction could be the elimination of a corridor such as the Turnagain Bird Point corridor. So, | believe that a full release of the $3.5M is appropriate. Any reimbursement agreement would be contrary to policies set for the Northern Intertie and might be opposed by the IPG on the grounds of fairness. My main concern which is not related to the environmental current scope comes from the comments in the Anchorage public meeting on the Southern Intertie, our HCCP experience relative to project benefits, and our experience on the Sutton Glennallen Intertie. In simple terms, the first attack of the opponents to the Intertie was that the Intertie is not justified economically. The impacts to the ratepayer are not quantified. There is no clear reason why the Intertie is being built. These criticisms will persist and cannot be solved by environmental studies. In my review of the past reports it is evident that the Southern Intertie achieves its economic benefits from reliability considerations such as reduced outages and reduced spinning reserve which the utilities tend not to carry anyway. These are qualitative and very subjective. The capital cost estimates thus have a very large effect on the benefit cost ratio of the project. Some of the previous reports show benefit cost ratios as low as .6 for the Southern Intertie. These reports are outdated. The fact is that no recent assessment of benefit costs has been made. | believe CEA is greatly exposed to criticism that the Intertie will not provide any benefits and will simply add cost to the CEA ratepayers. | would strongly recommend that an economic benefit cost review be undertaken as soon as possible on the project. In private discussions with Power Engineers, they concur that the economic benefits must be re-done and had recommended a new analysis to CEA. To date, CEA has not responded but Power feels that the IPG opposes such evaluation. Please let me know if any additional information is needed. cc: Daniel W. Beardsley DVM:ks h\all\dvm\aidea\ceat ALASKA INDUSTRIAL DEVELOPMENT * oo = ALASKA @@E _=ENERGY AUTHORITY 480 WEST TUDOR ANCHORAGE, ALASKA 99503 907 / 561-8050 FAX 907 /561-8998 January 18, 1996 Mr. Eugene N. Bjornstad General Manager Chugach Electric Association, Inc. P.O. Box 196300 Anchorage, Alaska 99519-6300 Subject: Southern Intertie Audit Dear Mr. Bjornstad: As requested by your letter of January 11, 1996 AIDEA, as the grant administrator for the Southern Intertie, waives the requirement for Chugach Electric Association to obtain an audit under the terms of the Grant Administration Agreement, Section 5, 2 AAC 45.010 and AS 37.05.030. Staff consulted with the Department of Administration and the Office of Management and Budget concerning the applicability of a waiver. Since Chugach only expended $72,000 within calendar year 1995, and AIDEA did not make any reimbursement for those expenditures within that calendar year, the grant expenditures and disbursements for the Southern Intertie did not exceed $150,000, the threshold for an audit. Sincerely, Executive Director WRS:bijf h:all\beardsle\dword\aea\ipglt002.doc cc: Gary Anderson, Office of Management & Budget Dave Calvert, IPG Chairman bec: Dennis V. McCrohan, Deputy Director - Energy Valorie F. Walker, Deputy Director - Finance Dan Beardsley, Contracts Manager Why an Intertie? 3) Slo LV The electric utilities serving the interior and southcentral ari Jntertie Participants Group (IPG). The seven utilities that f 4) Fda connected to provide efficient service to customers in the region. The proposed Soutnern Intertie will provide an additional connection between IPG utilities to improve reliability of service and efficient distribution of power. Project Overview The existing transmission line between Kenai and Anchorage is prone to outages and is limited in its capacity to transfer energy; installation of a second line will improve reliability and increase the transmission capability of the electrical system. The proposed Southern Intertie Project will specifically provide a more efficient distribution of electricity between the Bradley Lake Hydroelectric Project on the Kenai Peninsula and the rest of the Alaska Railbelt. Study Approach On behalf of the IPG, Chugach Eleccric Association is directing engineering and environmental studies for the proposed project. These studies are being performed by POWER Engineers, Dames & Moore and other local consultants. The project team is beginning a transmission line siting study, and input from the public, special interest groups, and public agencies is a critical part of the planning process. This is the first of several opportunities for public involvement in a two part process. Two open houses will be held to explain the project and the process (see schedule below). At the same time, the public will have an opportunity to comment on che values and criteria that will be used to help identify route alternatives that will be studied during the next step of the planning process, The next step is to conduct engineering and environmental studies to determine the feasibility of alternatives indentified. Siting Process Open House You are invited to open houses at the locations listed below. Representatives from Chugach Electric Association, POWER Engineers and Dames & Moore will be available to answer questions and describe the project in detail. In addition, a formal presentation will be conducted at 7:00 p.m. which will focus on the current phase of the project. Anchorage Soldotna Loussac Library Kenai Peninsula Borough Assembly Chambers Assembly Chambers 3600 Denali Street 144.N. Binkley Road January 31, 1996 February 1, 1996 5:30 - 9:00 PM 5:30 - 9:00 PM If you have any comments or questions, or know of someone who would like more information on the project please contact: Dora Gropp Niklas Ranta Chugach Electric Association Inc. or Dames & Moore 800-478-7484 800-909-6787 907-762-4626 907-562-3366 7 = len, DON 06.. 4