HomeMy WebLinkAboutCEA System disturbance Nov 14-1993Vile
ey aley pitehoe
CHUGACH ELECTRIC ASSOCIATION, INC.
Anchorage, Alaska
November 23, 1993
TO: File 1051 ee
FROM: Daniel C. Rogers, Manager, Facilities nisin IO
SUBJECT: System Disturbance of 11/14/93 - ML&P 34.5 kV PT Failure
Oo VI OF EVENTS
On November 14, at 19:32:15, AML&P experienced a 34.5 kV PT
failure at Plant 1. ‘Primary protection reportedly was not in
service, and the fault was cleared by second or third stage backup _
overcurrent, in approximately 2.5 seconds. Estimated fault current
was 14,000 Amps.
At approximately 19:32:17, Eklutna Unit 1, Beluga Unit 8,
Teeland Breaker 538, 1310, and Douglas Bl tripped. Maximum
frequency was 60.93 Hz; minimum was 59.24 Hz. None of the
interconnected systems experienced first = loadshedding.
ANALYSIS LE twhy not |
System Operations:
There were a number of items that could have contributed
to a complete collapse of the Anchorage and Kenai systems.
These are addressed in D. Burlingames memo of 11/17/93
(attached) .
Teeland 538/Douglas Bl/Teeland SVC trips:
The Teeland SVC and Teeland 538 tripped out on
overvoltage. As can be seen from the Teeland DSM plots, the
svc attempted to support the Voltage during the fault. At the
time of clearing, the capacitively supported Voltage rose to
17.6 kV on the SVC (13.8 kV) bus, thus tripping the Svc and
538 on overvoltage. Future controls upgrades for the SVC can
alleviate this problem by blocking capacitive reactive power
during the fault interval.
Beluga Unit 8 trip:
Beluga Unit 8 tripped on loss of excitation. The loss of
excitation relay is sensitive to power system swings. This
sensitivity can be lessened by the installation of a
supervisory timer. This protection improvement, along with a
number of others, was identified to be installed in units 3
and 8 in 1994. Based on discussions with the plant, we will
attempt to cut the timer in, hot, after generation schedules
allow, approximately December 18. This will fix the loss of
excitation tripping, but will leave the rest of the problems
identified in the protection system until the 1994 project.
Interconne.ted flows:
As can be seen on the attached DSM plots from the AML&P
230 yard, P_ "leaned" on CEA based on the predisturbi e
schedule, while attempting to restore lqad, its She system
frequency was just at nominal, and the Kenai tie was 14 MW
over the stability limit of the line. The flow out of Daves
Creek reached a peak of 104 MW (143% of the recommended
stability limit), which resulted in a calculated Girdwood
voltage, at the station, of 92%. See D. Burlingames memo for
details.
Attachments
dcr e:\outdata\931114\931114.out
cc: Facilities Outage Book
D. Burlingame
M. Massin
T. Newton
931114 19:32:13 teeland 230 KV bus voltage
cycles
280.0 -
~ 229.9 kV @ 199 cy
ng —— 262.4 kV @ 363 cy
240.0 [_ 229.1 kV @ 472 cy
Z 200 -
_* 203.6 KV @ 228 cy
200.0 -
— 181.2kV @ 244 ¢
193.6 kV @ 203 cy
0.0 500, 0 1000.0 1500.0 2000.0 + ~—«-2500.0 += 3000.0-«SS—t«800.0
93111 4 19:32:13 teeland SVC reactive power _
20.0 fe 14.8 MVAr @ 199 cy
-13.9 MVAr @ 252 cy 10.0
0 MVAr @ 367 cy
0.0 7 ea ee am Pat Par or e Sia aaa (as ed Koa 1
-10.0 -
-20.0 - /, 30.3 MVAr @ 358-364 cy
-30.0 - cs
~~ -48.7 MVAr @ 353 cy
49.0 | 15-4 MVAr @ 208 cy
0.0 | 500. 0 1000. 0 1500. 0 2000. 0 2500. 0 3000. 0 3500. 0
18.0 -
16.0 +
14.0 -
12.0 -
—.- 13.9 KV @ 199 cy
Pe
17.6 KV @ 359 cy
13.9 k V @ 481 cy
p+
13.1 KV @ 228 cy
—~12.3 KV @ 251 cy
12.1 kV @ 203 cy
0.
T r
0 500. 0 1000. 0 1500. 0 2000. 0 2500. 0 3000. 0 3500. 0
1931114 19:32:13 teeland 538 MW
6.0 -
4.0 -
2055
0.0 4
0.0 500. 0 1000. 0 1500. 0 2000. 0 2500. 0 3000. 0 3500. 0
cycles
931114 19:32:13 amlp frequency Hertz
60.93 Hz @ 306 cy 61.0 /
931114 19:32:13 amlp frequency - Hz
60.5 | _, 60.00 Hz @ 3799 cy
59.92 Hz @ 950 cy ———
a 60.0 ~—— / ——|
59. 5
a a, 59.24 Hz @ 471 cy 59,98 Hz @ 197 cy
0.0 500. 0 1000. 0 1500. 0 2000. 0 2500. 0 3000. 0 3500. 0
Cycles
931114 19:32:13 amlp auto power
16.1 MW @ 195 cy
27.0 SS
“26.1 MW @ 375 cy
_- 0.7 MW @ 1047 cy
0.0 ms
= | ! il
\ 14.4 MW @ 258 cy
-27.0
-2.3 MW @ 3799 cy
931114 19:32:13 amlp auto power - Mil
-§3.9 4
0.0 475.0 950. 0 1425.0 1900. 0 2375. 0 2850. 0 3325. 0
Cycles
9314 14 19:39:19 amlp frequency - Hz
59. 90
59.88 -
59. 86 il _/ 58.78 Hz @ 2648 cy Hertz 59. 82
59. 80
59.78 ~ 931114 19:39:19 amlp frequency - Hz. t T T T T T a
0.0 500. 0 1000. 0 1500. 0 2000. 0 2500. 0 3000. 0 3500. 0
Cycles
931114 19:39:19 amlp auto power - MW
—— 21.3 MW @ 3799 cy
2k
15.26 MW @ 0 cy
20. 3
ie
13.5 7 |
68 4 931114 19:39:19 amlp auto power - MW
0.0 475.0 950. 0 1425. 0 1900. 0 2375. 0 2850. 0 3325. 0
Cycles
931114 19:47:14 amlp frequency
59. 870
B59. 860 HTT I
|
Hl il { 1
AANA
59. 850
931114 19:47:14 amlp frequency - Hz
0.0 500. 0 1000. 0 1500. 0 2000. 0 2500. 0 3000. 0 3500. 0
Cycles
CHUGACH ELECTRIC ASSOCIATION, INC.
Anchorage, Alaska
November 19, 1993
TO: Gene Bjornstad, Executive Manager, Operating Divisions
FROM: David W. Burlingame, Manager, Power cxf
SUBJECT: AML&P 34.5 kV Fault November 14, 1993
The following is a preliminary review of the events surrounding the above disturbance:
19:32:15 AML&P experiences a fault on their 34.5 kV system. Due to clearing problems, the
fault is present for 2.5 seconds. Prior to fault, AML&P is receiving 18.8 MW from the CEA
system on a scheduled interchange.
19:32:20 Eklutna unit 1 tripped, Teeland breaker 538 tripped (intertie breaker feeding
Douglas), Teeland breaker 1310 tripped (Teeland SVC breaker), Douglas breaker B1 tripped
(breaker feeding intertie), Beluga unit 8 tripped. AML&P contributes 19 MW of spin into the
Chugach system. Interchange between the two utilities is 2.6 MW. (AML&P contribution is
essentially their Bradley power)
19:32:48 Frequency restored to normal
19:32 - 19:36 unable to contact AML&P Dispatch
19:37 - Chugach Dispatch contacts AML&P Dispatch and asks if the Intertie 538 was the
problem, AML&P states no the problem was in their 34.5 kV system. Chugach states they
believe they have enough generation to cover loss of unit 8. (neither Chugach or AML&P the
Eklutma operator were aware that Eklutna 1 had also tripped) AML&P has reduced their
contribution to 9 MW.
19:38:55 Frequency dips below 59.90 and begins to fall. AML&P (the Eklutna operator)
still has not voided the Eklutna schedules and is apparently not on flat frequency control (which
would have in effect canceled Eklutna scheduled). AML&P contributing 15.5 MW to the
Chugach system.
Chugach begins attempts to contact AML&P Dispatch to request generation assistance (Due to
the frequency decay, assistance should have been automatic)
19:39:47 AML&P appears to return to tie-line bias or takes some other action, begins to
increase energy take from the Chugach system
19:41:03 AML&P appears to incorrectly return to the pre-disturbance schedule, taking 19.0
MW from the Chugach system. Frequency 60.0 Frequency excursions begin to occur. wn
19:44:22 IGT unit 2 start command given, Beluga unit 1 attempted to start
19:45:03 AML&P off original schedule, taking 21.8 MW from Chugach, frequency decay
begins again. Daves Creek line to 86 MW.
19:46:03 AML&P taking 24 MW frum Chugach. Frequency decay to 59.96 Daves Creek
tie loading 89.0 MW.
19:47:03 AML&P taking 27.7 MW from Chugach, frequency decay to 59.88. Daves Creek
tie loading to 92.1 MW
19:47 Chugach contacts AML&P and asks for generation assistance, AML&P states they
have 50 MW of spin and Chugach requests 30 MW. Chugach — to manually drop load
in the Anchorage area to avoid overloading the Kenai tie-line.
19:48:03 AML&P taking 31.1 MW from Chugach system. Frequency 59.86. Daves Creek
tie loading to 94.4 MW
19:49:03 AML&P taking 32 MW from Chugach system. Frequency 59.87. Daves Creek
tie 96.3 MW. Tie peaks out at 104 MW.
19:50:03 AML&P begins reducing take from Chugach system to 26.7 MW. Frequency
recovers to 60 Hz. Daves Creek loading decreases to 93 MW.
19:52:07 AML&P increases take from Chugach to 36.2 MW. Frequency 60 Hz. Daves
Creek tie loading increases to 94 MW
19:53:03 AML&P increases take from Chugach system to 41 MW, frequency 60 Hz, Daves
Creek tie loading 93 MW.
19:53 IGT start sequence failed, Beluga unit 1 starts aborted after three attempts,
Chugach contacts AML&P and asks why no generation has been delivered
19:54 AML&P calls to say their generation is now beginning to pick up and notifies
Chugach that they are beginning to pick up load. Chugach requests a delay as there is still 88
MW flowing north from Daves Creek. (AML&P closing into a fault at this level would most
likely result in an unstable situation) ACE indicates AML&P begins restoring load, Kenai line
loading increases to 93 MW. AML&P take from Chugach system 31.8 MW, Daves Creek tie
89.4 MW.
20:00:03 AML&P returns to pre-disturbance schedule, ie is not contributing to the Chugach
system, but is no longer leaning on the system.
20:04 MEA Dispatch inquires as to the problem with the intertie since they cannot reach
AML&P on the phones an
20:06 GVEA Dispatch inquires as to what is the status of the Intertie since AML&P
won’t answer phones
20:08 AML&P (Eklutna Dispatcher) notifies Chugach of unit trip and asks what
schedule to travel to, does not revise Eklutna schedule. Chugach requests not to return to
schedule until 8 is loaded.
20:09 Chugach notifies AML&P to begin moving toward schedule
20:12:34 AML&P closes Teeland Breaker 538 without notifying Chugach or MEA, and
without the SVC.
20:16:57 AML&P closes Teeland breaker 1310 without notifying Chugach or MEA
20:18:24 AML&P closes into a fault on the Intertie without notifying Chugach or MEA
20:19:41 AML&P closes into a fault on the Intertie without notifying Chugach or MEA
20:34 Chugach Dispatcher explains to AML&P dispatcher that we were close to losing
the Kenai, AML&P responds that he was not watching the system, he was trying to get
downtown back on.
The events surrounding this outage are important, especially in light of the discussions involving
the controller duties. It would appear the system was near collapse. At the time of the event
the Soldotna SVC was operating with a failed capacitor. Total collapse of the Chugach system
could have been instituted by several actions of the AML&P Dispatcher, if Teeland breaker 538
had been closed 10 minutes earlier, the Douglas load itself would have put the Kenai tie line into
voltage collapse, resulting in separation and total collapse. AML&P Dispatcher could have
closed into a fault on either the 138 kV Intertie or the SVC 5 minutes earlier and sent the system
unstable. AML&P Dispatcher could have restored load in the AML&P system at the peak of
the intertie loading and sent the system into voltage collapse. If we had been unable to contact
ee ee eo erae paitzike toe decreasing generation would have
collapsed the system. When airbanks Intertie for faults, collapse could occur
anytime the Kenai is loaded above 75 MW. The Chugach system could have also collapsed due
to the failure of one additional capacitor at the Soldotna SVC.
It should be noted, that the AML&P dispatcher is probably the most qualified Dispatcher at
AML&P and one of the most qualified dispatchers in the state, however, AML&P only operates
with one dispatcher 24 hours per day. This dispatcher simply cannot perform all of the required
duties of the Southern Controller and the Ekluta Dispatcher while also performing duties for
AML&P.
I would recommend we have an outage committee meeting as soon as possible to discuss these
events. yy
BOferbesdL POF Yser iris
Py
OUTAGE 11/10/93 1932 HOURS
31. 33.2384. 4 30 pAl 4432.45. 47. 49° SL 53255 57 591 3 5887 32 34 36 38 40 42 44 46 48 30 52 34 36 58 0 2 4 6
_»_ UNIT 7MW'S _4— NET INTERCHANGE
CHUGACH cLECTRIC
ASSOCIATION, INC. —— \a-24-43 4 DAVID L. HIGHERS
General Manager Q December 27, 1993
Emmis Cay Jock EWUcUW se; |]
William R. Snell |
Executive Director DEC 30 i935
Alaska Industrial Development & Export Authority
480 West Tudor Road
Anchorage, AK 99503-6690
Alaska Industrial Development
and Export Authority
Re: _ Existing Intertie
Dear Riley:
As you are aware, the Alaska Energy Authority is the owner of the existing intertie transmission
line between Anchorage and Healy and is a party to the Alaska Intertie Agreement.
The utility participants have asked me to propose to you that AEA consider transferring the
ownership of this line to the utilities. We believe this makes sense for the State and would
simplify a number of issues.
First, the State's interest in this line is very limited, and is all risk. Unlike Bradley Lake (with
outstanding bonds) or the Four Dam Pool (where the State collects debt service which can be
reappropriated for other purposes), the existing intertie does not involve the payment of any funds
to the State for bond or other State purposes. The utilities pay all of the operating costs and their
responsibility for insurance, repairs, etc.
The State's involvement does result in some risks and uncertainty for the State. As has been
discussed at numerous meetings with the AEA, the correct reading of the contract actually results
in the requirement to treat AEA as a "utility participant" which would owe a share of the utility
expenses. This has been true since the date the AEA signed the Bradley Lake Power Sales
Agreement and leaves the State with a financial exposure for the last three years, as well as one
for future years. This result is possibly unintended, but is nonetheless the inescapable conclusion
from application of contract provisions. AEA has not addressed how it intends to fulfill this
obligation. In addition, because the State is the owner, it is almost certainly true that anyone
asserting liability claims against the line would include the State as a defendant, thereby exposing
the State to such risks.
5604 Minnesota Drive ¢ P.O. Box 196300 » Anchorage, Alaska 99519-6300
cc. E, Wowhrokr Phone 907-563-7494 ¢ FAX 907-562-0027
h. Beardscey
William R. Snell
December 27, 1993
Page Two
After significant reflection on these issues, we believe they are most easily resolved by a transfer
of the ownership of the line to the utilities and a release of the State from any of its obligations
under the Alaska Intertie Agreement.
We would like to discuss these issues with you at your earliest convenience. Please feel free to
contact Ron Saxton for any explanation you may wish about the workings of the Alaska Intertie
Agreement and the mechanics of how such a transfer might occur.
Thank you for your cooperation.
Sincerely,
ACH, ELECTRIC ASSOCIATION, INC.
David L. Higher:
General Manager
i ' J 01/19/94 07:53 S 27+ GVEA | @oo1/o04 ! | |
CHUGACH ELECTRIC ASSOCIATION, INC. be Le | Anchorage, Alaska Ext BW vSrdho
December 27, 1993
TO: Jim Hall, Matunuska Electric Association
Brad Evans, Golden Valley Electric Association
FROM: David W. Burlingame, Chugach Electric Associatio
SUBJECT: Stevens - Douglas Losses
Enclosed is a loss table which depicts the total line losses which occur between Stevens and
Douglas Substation.
The losses would have to be automatically applied via SCADA and would roll forward for every
hour. The losses would be applied in the same ratio as the Stevens load was to the total line
flow for the past hour. For instance, at a total line flow of 70 MW, with a Stevens load of 1.5
MW, Stevens losses would be (1.5/70) X 0.37 = .008 MW. Since the losses appear so small,
we would probably not make economy energy adjustments until the adjustment for the end of
the month meter correction is done.
Chugach’s (and GVEA’s if desired) SCADA system would calculate the losses every hour and
keep a rolling total. The total would be zeroed out the end of each month and added to the
MEA energy metered at Douglas station.
The transformer losses would need to be recorded by biasing the MEA mete: at Stevens
Substation.
Since the losses between Douglas and Stevens are so small and the use infrequ-ut, I would
propose the existing loss tables be used for flows North to South until we have rea‘i:n to change
them.
Please advise if the proposed loss tables are acceptable.
01/19/94 07:55 io +++ GVEA {002/004
CHUGACH ELECTRIC ASSOCIATION, INC.
Anchorage, Alaska
December 27, 1993
TO: Dave Burlingame, Manager, Power Control
FROM: Alice M. Mullins, Planning Engineer (42.2. YZ. Whe
SUBJECT: Intertie Loss Table for Stevens Substation
I have produced the attached loss table to document losses on the 138 kV line section from
Douglas to MEA’s proposed Stevens Substation.
Losses were calculated by running PSS/E for varying line flows from 0 to 70 MW south to
north in 10 MW increments as measured at Douglas looking toward Stevens. The line
impedance between Douglas and Stevens was calculated based on the impedance shown for
the Douglas-Cantwell line in the Alaska Railbelt Data Book and on GVEA’s system one-line
diagram and assumes that Stevens Substation will be located 26 miles from Douglas. A
voltage schedule of 140 kV was modeled as you suggested.
Losses were calculated at 1 MW intervals by a simple I?R calculation. For this calculation, a
constant VAR flow of 12 MVAR north to south was assumed based on observation of PSS/E
results.
PSS/E tabular output for the cases is available upon request.
4379.AMM:BM
Attachment
cc: John Cooley, Tom Lovas, RF
RECEIVED
DEC 27 4993
Power Gaius
Centor
01/19/94
ae
07:55 S 27% GVEA
Douglas-Stevens Line Losses
MW Losses
MW Losses
Stevens MW/| Calculated
Flow by Excel by PSS
i [0.0109
0.0153
9 0.0165 [00178]
0.031 = 2 ° ag id x 0.0371
20 t i BRR i 2 3S 2 >
003/004
01/19/94 07:56 Se 27+ GVEA 004/004
-
Douglas-Stevens Line Losses
Ny sie Municipal Light & Power
1200 East First Avenue
Anchorage, Alaska 99501-1685
(907) 279-7671, Telecopiars: (907) 263-5204, 277-9272
DATE: December 6, 1993
TO: Brad Evans, GVEA
Sam Matthews, HEA
Dennis McCrohan, AIDEA/AEA
Vince Mottola, FMUS
Ken Richie, MEA
TTA
FROM: ML&P, Southern Operator, Alaska Intertie / yr w
SUBJECT: CEA Ultimatum
I am forwarding the attached ultimatum from CEA. 2G ean response to the letter I sent to each of you, "Proposal for Expediting the Stevens Substation", December 2, 1993.
Mr. Burlingame's attached memo makes it obvious to me that the
CEA agenda is removal of ML&P as Southern Operator of the
Intertie, and not the betterment of MEA's ratepayers who would be
well served by bringing the substation on line as soon as prudently possible and as ML&P proposes.
Please keep in mind, the CEA ultimatum is delivered in the teeth
of the Intertie Agreement, a contract they signed which clearly
directs hourly Intertie accounting by each of the Operators for
their respective Groups (Paragraphs &.4.3 and 8.4.4 among
others). By issuing the attached ultimatum, CEA in fact is
holding the Stevens Substation hostage to the outcome of a legal
battle which if need be can occur quite apart from the Stevens
on-line date.
Over the years we have all been on the receiving end of such CEA
ultimatums. This one appears to me to be particularly mean
spirited in that they would defy a contract and deprive MEA
ratepayers in an attempt, destined to be futile, to eliminate
contractual Intertie oversight.
I would submit that for the sake of the Stevens ratepayers, and
of our future dealings with CEA (with or without contracts) their
"ultimatum" modus operandi be quashed. I once again request your
good office and support in ML&P's attempt to expedite the Stevens
Substation.
Attachment: CEA Letter, December 3, 1993
cet PR, Suere 5 Ss eczKouse] Putting Energy Into Anchorage
’. ee
_ iC Whfez
Frc”
CHUGACH ELECTRIC ASSOCIATION, INC.
Anchorage, Alaska
December 3, 1993
TO: Tin McConnell, AML&P
FROM: David W. Burlingame, Manager, Power conmaege™ :
SUBJECT: — Stevens Substation - Your Proposal dated December 2, 1993
It would appear your proposal requires more work from Chugach than is required to operate the
system. It would also appear that your proposal is based on the assumption that AML&P will
continue to performs duties as it interprets the contract.
We disagree with the continuation of those duties which serve no useful purpose and are not in
the best interest of the operation of the Intertic.
Should your insert Northern Controller in each place as opposed to Southern we wiil support it.
We will not , however support any action which perpetuates the cost inefficiencics presently in
place.
We do not feel the recording of hourly loads serves any us¢ful purpose in the interim and are
not required for reconciliation between the effected utilities.
.. File
CHUGACH E-ECTRIC ft ote
ASSOCIATION, INC.
4c Own Oe 60° 19-24-43 DE NINE DAVID L. HIGHERS
General Manager
December 27, 1993
Well $e a SHAG yy
D)fbliuzi i}
William R. Snell Mae 4qah i J
Executive Director DEG S.Y Hus
Alaska Industrial Development & Export Authority ‘staid niostiid: Geudlanewen!
480 West Tudor Road ; : d Expert Autt Anchorage, AK 99503-6690 anal Expert Aothority
Re: Existing Intertie
Dear Riley:
As you are aware, the Alaska Energy Authority is the owner of the existing intertie transmission
line between Anchorage and Healy and is a party to the Alaska Intertie Agreement.
The utility participants have asked me to propose to you that AEA consider transferring the
ownership of this line to the utilities. We believe this makes sense for the State and would
simplify a number of issues.
First, the State's interest in this line is very limited, and is all risk. Unlike Bradley Lake (with
outstanding bonds) or the Four Dam Pool (where the State collects debt service which can be
reappropriated for other purposes), the existing intertie does not involve the payment of any funds
to the State for bond or other State purposes. The utilities pay all of the operating costs and their
responsibility for insurance, repairs, etc.
The State's involvement does result in some risks and uncertainty for the State. As has been
discussed at numerous meetings with the AEA, the correct reading of the contract actually results
in the requirement to treat AEA as a “utility participant" which would owe a share of the utility
expenses. This has been true since the date the AEA signed the Bradley Lake Power Sales
Agreement and leaves the State with a financial exposure for the last three years, as well as one
for future years. This result is possibly unintended, but is nonetheless the inescapable conclusion
from application of contract provisions. AEA has not addressed how it intends to fulfill this
obligation. In addition, because the State is the owner, it is almost certainly true that anyone
asserting liability claims against the line would include the State as a defendant, thereby exposing
the State to such risks.
5601 Minnesota Drive « P.O. Box 196300 « Anchorage, Alaska 99519-6300
Phone 907-563-7494 « FAX 907-562-0027
William R. Snell
December 27, 1993
Page Two
After significant reflection on these issues, we believe they are most easily resolved by a transfer
of the ownership of the line to the utilities and a release of the State from any of its obligations
under the Alaska Intertie Agreement.
We would like to discuss these issues with you at your earliest convenience. Please feel free to
contact Ron Saxton for any explanation you may wish about the workings of the Alaska Intertie
Agreement and the mechanics of how such a transfer might occur.
Thank you for your cooperation.
Sincerely,
ACH,ELEGTRIC ASSOCIATION, INC.
David L. Higher
General Manager
TO:
FROM:
SUBJECT:
FROM CHUGACH ELECTRIC T0 cc 998 PUU2/007 on a CHUGACH ELECTRIC ASSOCIATION, INC.
Anchorage, Alaska
November 17, 1993
,
Riley snell, Executive Director \
AIDA ”
David L. Highers, General Manager }.
ML&P Southern Intertie Route Proposal
The attached, for your information, is a new and different southern intertie route proposal faxed to me by ML&P. I don't
know where this leaves us on the wheeling issue, but it confirms
my views that routing decisions cannot be made intelligently at
this time.
11-17-93 12:21PM FROM CHUGACH ELECTRIC TO 5618998 003/007
NOV-17-93 WED 10:50 MLQP GEhenm MANAGER FAX NO, 907263620¢ P.O
WW ~ AW
ey Municipality of Anchora: Municipal Light & Power
Tom Fink, Mayor 1200 East First Avenue
Anchorage, Alaska 99501-1685 1907) 279-7671, Telacopiers: (90?) 276-296 1. 277-9272
TRANSMITTAL SWEET
VUNICIPAL LIGHT & POWER
ADMINISTRATIVE OFFICES PAX #: (907) 263-5204
DATE: 11/17/93
TO: SEE DISTRIBUTION BELOW
PROM: TOM STAHR, GENERAL fANAGER, ML&P
SUBJECT: LEAST COST TESORO/FIRE ISLAND INTERTIE ROUTE
THIS OOCUMENT CONTAINS 5 SHERTS (INCLIIRING THR COVFR SHRRT). TF YOU WISI
TO VERIFY RECEIPT OF THIS DOCUMENT OR YOU 01D NOT RACEIVE ALL SREETS INDICATED
PLEASE CALL __ Anne AT (907) 279-7671, ext. __520]_. MANY THANKS!
ERIC REDMANN/HELLER EHRMAN/206-447-0849
RON SAXTON/ATER WYNNE/503=226=0079
GVEA/KELLY/ 451-5633 CEA/HIGHERS/562-0027
Putting Energy Into Anchorage
R=-93% 9072635204 Li-17-93 10:56AM POOL #20
12.21TM PRUM UlUVAUD CLEVIRIY iV
NOV-17-93 WED 10351 ML&P Gris MANAGER FAX NO. 907263520. P, 02
R“93%
LEAST COST TESORO-FIRE ISLAND-ML&P ROUTE
The Enstar ML&P route | previously sent intormation on was developed afler Rick Redman had indicated there were serious probloms with tho Fire Island route. Now that the Fire Island rota has bean rehabilitated we have developed a ML&P Fire Island route. This is based on one of the alternatives Power Engineers had developed in 1987. Fortunately this route is less expensive than the Fire Island -voronzof route wnicn previously appeared least costly,
This route starts at the HEA 118kV line near Bernice Station and then generally follows the Tesoro pipeline route to Point Possession and then crosses Tummaguin Anm to the south end of Fire island, It then goes north on Fire Island Untill It reaches the place clusesl lo Point Campbell
and then crosses to the mainland a littlo north of Point Campbell. Then it follows, more or less, the south Intamational Airport boundary till It goes underground for the North-South runways. It then follows Raspbery Road to Arctic Blvd, extended to tle Into the ML&P line at International Airport Read.
Tha HFA line from Soldotna Station to Bemice is one of the HEA lines leased lo CEA on a long term lease. Fortunately the lease is very explicit as to the cost elements so the cost of this line segment can be easily determined. Since regulatory practice fs to allow 8 relurn on invesiment
but not a mark-up on expenses, and the appropriate TIER te alroady In the base jease rate CEA pays it is extremely unilkely CEA would be allowed ta racover more than it's expenses on this line segment. Preferably the IPG should acquire this line segment for incorporation in to the Southem Intertie. Redman in nis tour proposals has Indicated this possibilily. | have not
attempted to quantify the cast of acquiring or the annual lease costs of this link because only HFA has the necessary data. Nor have | tried to allocate usage between CEA and the intertie.
At the ML&P end of the line | did not snow the auto-transformer station nor did | hiclude it’s cost in the cost estimate, There aro sovoral reasons for this . One Is that the line segment
immediately north of Intemational Airport Raad is to a considerable extent over insulated for 1415KV so with little or no work can be used for 138kV. Anather reason Is that it would be preferable but not essential to the MLAP system to have separate breakers for each fine direction leaving 36th and Arctio Blvd which would require a station closer to that location. As for enst sharing between MLA&P and the Intertie Doug Rosenber is presenting fo the Attarneys a proposal which would essentially hold other IPG participants harmless from any costs in excess
of the lowest cost route.
Clearty this route could just as easily terminate at CEA’s international Station and there would also be unquantified termination costs there because they would need one more breaker and a
haif section and a complete additional 136kV Station bay. But again the principal applies there is n0 Justification for a CEA whooling charge because an altemative exists which requires no wheeling payments to CEA and It's cost is not higher. Emo with a new intertie the value of CEA wheeling to Anchorage Is zero. Wheeling on to the north from Anchorage as previously detailed
shduid not exceed 2.8 mitis/kWh.
9072635204 Li-t7-93 10:56AM FoO2 #20
!
‘
Tote da-1c: Cre
NOV-17-93 WED 10:52
R=93%
he iG H KI rRI{ FRUM CHUGAUH ELECTRIC
ML&P GENkkAL MANAGER
TO 9618998 005/007
FAX NO. 907263520,
Preliminary Cost Estimate For Tesoro/Fire Island Route to ML&P Ststem at Arctice & International
Link Miles
3.2A 11.50
343 24.75
3.22 4.7
3.6 2.8
3.0 3.90
Bernice Lake
3.7 1.0
3.25 4.0
3.41 6.8
3.42 3.2
Bescription
Steel Single Pole
Steel X Structure
Steel X Structure Fire Island
Steel Single Pole
Steel slngle role
Substation
Subtotal
R/W & Acquistion
Design 44% eM 4%
Subtotal 1
Underground Cable
Underground cable
Submarine Cable & 2 Tern
Submarine Cable &
2 Term
Subtotal 2
Utility Admin 1% (Sub 1 & 2)
AEA Admin Contingency 10% (Sup 12 & 2)
Estimated Total
9072635204
gost
3,392,736.
9,210,447.
2,350,000.
826,056.
365,U6U.
2,300,000.
16,964,299,
2,750 000. 758,572 758,572.
23,231,443,
2,209,038.
8,073,954.
23,056,800.
13,141,995.
46,491,787.
697,132.
250,000.
6,971,323.
77,631,685.
11-17-93 10:56AM
P, 03
POO3 #20
- NOV-17-93 WED 10:52
-
MLAP GEnsxAL MANAGER FAX NO, 90728352. P, 04
Anchorage-Kanai New 138 KV Intertie Tesoro/Fire Island Route
Loa
Reference ML&P Link
System No.
PEI/MLAP =. 4987/1993 3.8
PEI 1987 a7
PEI/ML&P 1987/1993 DG
D&L/ML&P 1993 3.42
D&L/ML&P 1993 3641
DEL 1993 3.41
D&L 1993 a3
D&L 1993 3.2B
D&L 1993 3.2A
138KV
R=94%
atin
Description
3.0 Miles O/H
Single pola steel
1,0 Mile use
2.8 Miles O/H
single pole steel
3.2 Miles
submarine +2
terminals
4.7 Miles (Fire Island) steel X structure
6.8 Miles
submarine + 2
tearminale
24.75 Miles
Steel *X Structure
4.0 Miles U/G
11.5 Miles Single steel pole
Bernice Substation
Existing 115KV 0/H
Soldotna Substation
9072635204 $1-37-93 10:56AM vooa #20
Oc 900d Wyo Fiat: IAT Ep 5 sled nel n 2 | »N@GE9CL06 ‘ON X¥d SIOVNVH TWYANAD d BIH ES'01 aM €6-L1-AQN. :