Loading...
HomeMy WebLinkAboutCopper Valley Electric Association 3-1991COPPER VALLEY ELECTRIC ASSOCIATION, INC. P.O.BOX 45 GLENNALLEN, ALASKA 99588-0045 Glennallen (907) 822-3211 Valdez (907) 835-4301 Telefax # (907) 822-5586 . RECEIVED MAR 02 1991 March 6, 1991 ALASKA ENERGY AUTHORITY! Mr. Rick Collins Valdez Terminal Manager Alyeska Pipeline Service Co. Post Office Box 300 Valdez, Alaska 99686 Dear Mr. Collins: The following is Copper Valley Electric Association's (CVEA) preliminary proposal to extend service to the Alyeska Terminal in Valdez, Alaska. This proposal is to be used as a basis for beginning discussions on an Alyeska intertie to the Solomon Gulch Project. It is our hopes that Alyeska can work jointly with CVEA, the Alaska Energy Authority, and the City of Valdez to bring this project to fruition. No single project that CVEA has studied has the potential to benefit the Association and the local communities as much as this project. We look forward to a mutually beneficial relationship with Alyeska through this project. This proposal is intended to establish some preliminary parameters for an energy exchange scenario. As you are aware, a final agreement must have CVEA Board, Alaska Energy Authority, and ultimately the Alaska Public Utilities Commission approval. If you have any questions concerning this proposal, please do not hesitate to call Mike Easley, Manager of Engineering, or me. Sincerely, R.D. (Doug) BurSey General Manager SERVING MEMBER-OWNERS IN THE COPPER RIVER BASIN AND VALDEZ COPPER VALLEY ELECTRIC ASSOCIATION, INC. Ronald D. Bursey, General Manager Glennallen, Alaska PERMANENT SERVICE TO ALYESKA TERMINAL ‘Valdez, Alaska March, 1991 Report Prepared by: Michael E. Easley, PE Section I. Il. Ill. IV. V. Vi. Vil. VIII. IX. TABLE OF CONTENTS Introduction System Overview Impacts to Alyeska Proposed Additions Cost Analysis Project Estimate Solomon Gulch Hydro Substation Solomon Gulch Substation Estimate 24.9 KV Distribution Line 24.9 KV Distribution Line Estimate Alyeska Terminal Substation Alyeska Terminal Substation Estimate 13.8 KV Distribution Line 13.8 KV Distribution Line Estimate Q > o a CVEA/Alyeska Dispatch Model System One Line CVEA Reliability Comparison Proposed One Line Plan View Solomon Gulch Substation Additions Agency Correspondence Structure Drawings Alaska Energy Authority Correspondence City of Valdez Correspondence oO Alyeska Permanent Service March 1991 Page 1 1. INTRODUCTION In February of 1991, Copper Valley Electric Association (CVEA) was requested by Alyeska to estimate costs to provide temporary service to the Valdez terminal facilities. CVEA was informed that the cost of providing this temporary service ($760,848) exceeds the cost of providing on site temporary generation (reported to be $450,000). . Based upon this information, CVEA has investigated its options in providing a permanent interconnection to Alyeska. Unlike a temporary service, CVEA would be able to share a portion of the costs under a permanent scenario. CVEA has been developing a long range planning strategy in an attempt to stabilize or even reduce ever increasing electrical rates. A connection to Alyeska in which energy was exchanged between the two systems would serve to benefit all the parties involved. CVEA would propose an energy exchange agreement with Alyeska and the Alaska Energy Authority (AEA). In this scenario Alyeska would be furnished with 7MW of power during the periods of excess Hydro capacity. This is typically June through August. In return, CVEA would take 4 MW of power during periods of limited Hydro capacity. This is typically October through April. The arms length arrangement between CVEA and Alyeska would involve AEA facilities. AEA wholeheartedly supports the tie. It also provides Alyeska with the comfort of removing any possible Alaska Public Utilities Commission (APUC) involvement. A graphical representation of this energy dispatch is shown in Exhibit 1. This energy exchange program would enable CVEA to eliminate the use of costly oil fired generation and would allow Alyeska to receive power at no cost during the summer months. This would be especially beneficial during the times Alyeska may require additional temporary on site generation for turbine maintenance. The most beneficial aspect of this arrangement is that Alyeska would have a completely independent source of stand by generation. Since CVEA has almost 30 MW of capacity and a load less than one third of its capacity, Alyeska would have almost 20 MW’s of stand by power at its disposal. The information presented in the remainder of this proposal will provide preliminary details concerning CVEA’s existing system, the proposed facilities, and the proposed energy exchange scenario. Alyeska Permanent Service March 1991 Page 2 ll. SYSTEM OVERVIEW CVEA has 29.65 MW of generation at its disposal. Of this approximate 29.65 MW’s of generation, 12 MW is Hydro, 7.64 is Glennallen Diesel, and 10.01 is Valdez Diesel. Each of these power plant facilities are interconnected through a distribution and transmission system. CVEA utilizes a 106 mile, 138 KV transmission line to interconnect the Valdez and Glennallen systems. A complete one-line diagram of the CVEA system is provided as Exhibit 2. CVEA maintains a high degree of system reliability through an aggressive maintenance program and continued improvement in control equipment, including relaying and System Control And Date Acquisition (SCADA) systems. CVEA has upgraded all of its SCADA equipment and transmission relays to current state of the art systems. CVEA has achieved statewide recognition for system reliability as mentioned in several Alaska Energy Authority Studies (see Exhibit 3). Alyeska Permanent Service March 1991 Page 3 Ill. IMPACTS TO ALYESKA Providing an interconnection to Alyeska is an important goal for CVEA. (AEA and CVEA are considered as a unit and hereafter referred to only as CVEA.) It is an opportunity to further the Association’s goals of providing service to its members. Alyeska and CVEA share a major concern for the Valdez and Copper Basin areas. As CVEA is concerned for its members, Alyeska is concerned for its employees and the . community in which they live. The direct benefits related to the energy exchange are relatively easy to quantify, yet the benefits to the various communities from this project are less easily quantified but could actually outweigh the direct benefits. Reliability is of high concern to CVEA, especially when considering current world events. The varied power plant locations, as well as the excess capacity, establishes a high reliability component in relation to generation resources. During the summer each year, CVEA has an excess of Hydro energy, resulting in the ability to serve the Alyeska and CVEA load from the Hydro. The diesel generation resources can also be utilized to meet energy requirements in the unlikely event either one or both of the Hydro units were to experience problems. In essence, CVEA has four independent generation sources available, of which any two could carry the entire CVEA and Alyeska loads. The transmission and distribution systems are also important components of the electrical system. The proposed line route following the existing pipeline route is free from avalanche hazards. Exposure to weather related outages would be virtually nonexistent due to the length and location of this line. This situation serves to enhance the reliability of the system. The weakest link in the service to the Terminal becomes the distribution line from the Hydro to the Terminal. The security of this line could be an issue; however, CVEA feels that the location of the proposed line on the pipeline corridor will ensure adequate security through pipeline patrols. It should be just as secure as any exposed portion of the pipeline. Even if the line were to experience a problem, CVEA crews are available on a 24 hour basis to make repairs. Typically, crews are able to restore power within hours, even when pole replacement is necessary. Generation related outages are typically restored within 30 minutes. This time frame would be reduced for the Alyeska load, since Alyeska would be given top priority. When considering the varied generation sources, the historical performance of the CVEA system, and secure routing, CVEA feels the proposed line is a viable source of dependable power. Historical performance can also be measured through Alyeska Permanent Service March 1991 Page 4 documentation established to satisfy the United States Air Force during their investigation in connection with the Over the Horizon Backscatter facility (OTH-B). Service performance was 99.1 percent or CVEA service was available 99.1 percent of the time. CVEA chose not to continue pursuing the OTH-B service because direct benefits to CVEA members in rate reductions were not significant, even though secondary benefits may have been realized. Alyeska Permanent Service March 1991 Page 5 IV. PROPOSED ADDITIONS Service to Alyeska requires substation additions to the Solomon Gulch Hydro, 2.8 miles of 25 KV distribution line, a 24.9 KV Wye/13.8 KV Delta substation, and 1.5 miles of 13.8 KV distribution line. A one-line diagram of the proposed additions is provided as Exhibit 4. The additional bay required at the Hydro substation will include adequate protective systems to insure that system disturbances will not damage equipment at Solomon Gulch or at the Alyeska Terminal. Protection systems, at a minimum, should be designed for a radial feed distribution line; however, the need of the Alyeska system to operate in parallel with the CVEA system during project energization and de- energization requires the use of sync check capabilities, and possibly SCADA control, of one or more breakers or reclosers. Energy exchanges will be metered at the Solomon Gulch location. The 24.9 KV distribution line required to deliver power from the Solomon Gulch Hydro to the Alyeska Terminal will be 336.4 MCM ACSR. This conductor is capable of delivering up to 21 MW’s of three phase power. Its choice as a conductor is primarily made upon its mechanical and loading characteristics. There will not be any pole grounds installed along the length of the distribution circuit. This will preclude the chance of coupling with the corrosion protection systems of the pipeline. It is desireable to leave the various ground systems independent of each other; therefore, a fourth wire will not be necessary on the distribution line. The stepdown substation necessary at the Alyeska Terminal site will transform the voltage from 24.9 Wye to 13.8 Delta. The 24.9 system will be an ungrounded Wye system to eliminate the possibility of ground fault contributions between the facilities. The desire to keep the systems ungrounded is warranted when considering coupling of the ground and corrosion control systems and fault current contributions. Operating in an ungrounded system does complicate the transformer selection. When operating in a grounded system, the transformer windings never see a voltage in excess of the nominal phase to neutral voltage; however, in an ungrounded system, the winding voltages can approach the phase to phase voltage levels. This precludes the use of standard transformers with reduced voltage windings. Common to the industry are 13.8 to 24.9 generator step up transformers; however, the typical transformer size for this type of application is in the order of 50 MW. This proposal includes the purchase of four (4) 2500 KVA transformers with full voltage windings. Alyeska Permanent Service March 1991 Page 6 This proposal includes a 13.8 KV distribution line to be located entirely on Alyeska property. It is proposed to be primarily an overhead line with one section of . underground. The line will begin at the substation and will proceed to the existing 13.8 KV main distribution bus. Alyeska may desire to locate this circuit in above ground ducts; however, CVEA is not prepared to operate or maintain a facility of this nature. Estimates are provided for the various portions of the system required to provide service. A proposed system one line is shown in Exhibit 4, and a plan view of the entire project is shown in Exhibit 5. Alyeska Permanent Service March 1991 Page 7 V. COST ANALYSIS CVEA Engineering has reviewed the project requirements to prepare an Engineer’s Estimate for the completion of the work. Careful review was made of site conditions, as well as general system requirements. CVEA has prepared an estimate for this project of $760,848 which includes estimated installation costs and a 10% contingency. The estimate further assumes that Alyeska will provide the excavation for the proposed underground cable. CVEA would be prepared to pay for one-half of this project’s cost. This would mean that Alyeska would pay $380,424. This appears to be less than the costs of providing temporary on site generation. Alyeska would gain by having permanent service during plant shutdowns. Timing of outages for Alyeska generation could be lengthened to reduce overtime costs. Alyeska could gain a permanent source of standby generation for costs less than that of providing a one time temporary service. The additional benefit is that under the energy exchange proposal, Alyeska is able to utilize energy with little or no cost. Since Alyeska would be providing a small energy requirement to CVEA over several months, it would be able to do so with only incremental costs. During the summer when GVEA was providing a large block of power to Alyeska, significant reductions could be made in the amount of on-site generation required. The energy provided to CVEA would be incrementally inexpensive, while the energy provided by CVEA would offset more expensive power. This scenario can be viewed as an energy banking arrangement. The project banks excess Hydro energy during the summer months, and Alyeska banks energy during the winter months. Under this scenario, this type of energy exchange is exempt from regulation under AS 42.05.711. Energy in to and out of this banking pool would be netted each year. The excess energy, if any, will be 6.4 cents per kwh to Alyeska, and Alyeska would be paid 5.4 cents per kwh for excess flows to CVEA. The 1 cent difference is the cost of Solomon Gulch operations and losses. A cost summary follows which breaks down the costs into the various stages of the project. The following sections of this proposal provide a detail description of the individual stage, as well as a detailed estimate of the work. Alyeska Permanent Service March 1991 Page 8 SOLOMON GULCH TO ALYESKA DISTRIBUTION LINE ESTIMATE FOR ENTIRE PROJECT STATION ADDITIONS SOLOMON GULCH TOTAL 2.8 MILES DISTRIBUTION LINE 24.9 KV, WYE TOTAL TERMINAL SUB. 24.9 WYE/13.8 DELTA TOTAL 1.5 MILES DISTRIBUTION LINE 13.8 KV, DELTA TOTAL PROJECT TOTAL CVEA PARTICIPATION ALYESKA PARTICIPATION $ 53,350. $294,877. $277,530. $135,091. 760,848. $380,424. $380,424. Alyeska Permanent Service March 1991 Page 9 VI. SOLOMON GULCH HYDRO SUBSTATION Modifications required at the Hydro will be completed on the west end of the substation. The recommended method is to add a breaker (or OCR) in the spare bay. New bus will be installed over the existing bus and routed to the west end of the existing steel. Attachments will be made to the existing steel, and a span to a wooden dead-end structure will be installed. Protection for a radial distribution feeder is typically fuses; however, in this case, sync capabilities are required, so a breaker will be added to ensure adequate system protection. Meters will need to be able to measure IN/OUT KWH, KW, KVAR. JEM | electronic metering will be used. The drawings found in Exhibit 6 indicate the proposed changes required in order to provide for the additional bay. Alyeska Permanent Service March 1991 Page 10 SOLOMON GULCH TO ALYESKA DISTRIBUTION LINE ESTIMATE FOR SUBSTATION ADDITIONS (SOLOMON GULCH) ITEM QTY COST EXTENDED BREAKER or OCR 1 $25,000. $25,000. BUSWORK 1 ; 5,000. 5,000. RELAYING 7 10,000. 10,000. MOBILIZATION 1 2,500. 2,500. ENGINEERING 1 6,000. 6,000. TOTAL $48,500. ADD CONTINGENCY 10% 4,850. STATION ADDITIONS SOLOMON GULCH TOTAL $53,350. Alyeska Permanent Service March 1991 Page 11 Vil. 24.9 KV DISTRIBUTION LINE The 2.8 miles of distribution line would begin on the west side of the Hydro facility. It would then proceed adjacent to the Penstock. The routing would follow the penstock to the crossing of the pipeline, where the line would then run parallel with the pipeline to the terminal facilities. There is considerable rock in the area. In lieu of using explosives to open holes, it is proposed that pole sockets be installed. This . consists of a pipe anchored to the rock in which the butt of the pole is placed. Line construction would consist of REA approved VC-1 series assemblies. Crossarms will be ten foot in length. This has an additional advantage of being a RAPTOR safe design. The base poles would be 40 feet in length. Anchors would be rock anchors and plate anchors as required. Spans would average 275 to 350 feet in length. Conductor will be 336.4 ACSR. This conductor has adequate amperage. Right of way clearing would be limited to danger trees. A right of way permit will be required from the State of Alaska to allow CVEA the use of the pipeline corridor for the distribution line. State Agencies have been contacted, and the ability to utilize this route seems likely. A copy of the correspondence relating to the right of way is found in Exhibit 7. Structure drawings can be found in Exhibit 8. Alyeska Permanent Service March 1991 Page 12 SOLOMON GULCH TO ALYESKA DISTRIBUTION LINE ESTIMATE FOR 2.8 MILES DISTRIBUTION LINE 24.9 KV UNGROUNDED WYE ITEM QTY COST EXTENDED 40-2 POLES 30 $ 905. $27,150. 45-2 POLES 20 1,376. 27,520. VC1-A POLE TOP 40 205. 8,200. VC7 POLE TOP 5 300. 1,500. VC8 POLE TOP 5 400. 2,000. GUYS 40 80. 3,200. ANCHORS 40 400. 16,000. VM-F1 30 2,000. 60,000. 336.4 ACSR 50,000 2 100,000. PUSH SUPPORTS 10 750. 7,500. CLEARING 1 2,000. 2,000. MOBILIZATION 1 / 5,000. 5,000. ENGINEERING 1 8,000. 8,000. TOTAL $268,070. ADD CONTINGENCY 10% 26,807. 2.8 MILES DISTRIBUTION LINE 24.9 KV, WYE TOTAL $294,877. Alyeska Permanent Service March 1991 Page 13 Vill. ALYESKA TERMINAL SUBSTATION The Terminal substation consists of a step down transformer to transform voltage from 24.9 KV Wye to 13.8 KV Delta. It is proposed that the transformation be accomplished through the use of three 2500 KVA single phase transformers. The substation structure will be constructed of wood poles and crossarms. The transformers will be placed on concrete foundations. The high side of the transformer bank will be . protected by fuses, and the low side will be protected with an OCR. The OCR will be remotely operated via CVEA SCADA. It is assumed that Alyeska will provide cable pairs for the communication circuit. It will also have sync capabilities. Metering will be accomplished with IN/OUT KWH, KW, KVAR quantities recorded with a JEM electronic meter. : The substation site will have to be 70’ x 100’. A fence will also be installed in accordance with the latest NESC codes. It will be 7’ high and topped with three strands of barb wire. Alyeska Permanent Service March 1991 Page 14 SOLOMON GULCH TO ALYESKA DISTRIBUTION LINE ESTIMATE FOR TERMINAL SUBSTATION 24.9 WYE/13.8 DELTA ITEM QTY COST EXTENDED STRUCTURE/FENCE 1 $30,000. $30,000. DISCONNECT SWITCH “ 1,200. 4,800. OCR 1 20,000. 20,000. HIGH SIDE FUSES 1 5,000. 5,000. METERING 1 6,000. 6,000. TRANSFORMERS a 40,000. 160,000. GROUND GRID 1 3,000. 3,000. SITE/FOUNDATIONS 1 15,000. 15,000. MOBILIZATION 1 2,500. 2,500. ENGINEERING 1 6,000. 6,000. TOTAL $252,300. ADD CONTINGENCY 10% 25,230. TERMINAL SUBSTATION 24.9 WYE/13.8 DELTA TOTAL $277,530. Alyeska Permanent Service March 1991 Page 15 IX. 13.8 KV DISTRIBUTION LINE The 13.8 KV distribution line will carry power from the Alyeska Terminal substation to the 13.8 KV main distribution bus. It will be mainly overhead, but it will have one section of underground in an area frequented by large cranes. Standard CVEA practice is for consumers to open ditches for underground . installations. This estimate assumes Alyeska will provide the ditch for underground facilities. The line will generally follow on the north side of the access road that runs between the crude oil storage tanks and the ballast tanks. It will proceed down to near the end of the tank farm and on to its terminus at the Alyeska 13.8 KV switchgear building. This line may be replaced by Alyeska with cable trays at some future date. CVEA would be willing to remove the line, at Alyeska’s expense, if the replacement occurs. Alyeska Permanent Service March 1991 Page 16 SOLOMON GULCH TO ALYESKA DISTRIBUTION LINE ESTIMATE FOR 1.5 MILES DISTRIBUTION LINE ITEM 40-2 POLES 45-2 POLES VC1-A POLE TOP VC7 POLE TOP VC8 POLE TOP GUYS ANCHORS VM-F1 336.4 ACSR PUSH SUPPORTS CLEARING URD CABLE MOBILIZATION ENGINEERING 1.5 MILES DISTRIBUTION LINE 13.8 KV DELTA TOTAL 13.8 KV DELTA QTY 15 10 21 24 24 24,000 1500 ADD CONTINGENCY 10% COST $ 905. 1,376. 205. 300. 400. 80. 400. 2,000. 2. 750. 2,000. 10. 2,500. 3,000. TOTAL EXTENDED $13,575. 13,760. 4,305. 600. 800. 1,920. 9,600. 4,000. 48,000. 3,750. 2,000. 15,000. 2,500. 3,000. $122,810. 12,281. $135,091. KW (Thousands) ALYESKA DISPATCH MODEL POSITIVE TO ALYESA, NEGATIVE TO CVEA La tt er 1 oF NRW FP ITI DN CO WO = Se ee ee ee 1/1/90 ALYESKA GEN. 2/26/90 4/23/90 $j --|_ _____— 6/18/90 8/13/90 ——— CVEA DIESEL \ en 10/8/90 12/3/90 1/28/91 —— SOLOMON EXCESS Stattow srevice veev7eray, ‘atta STATION scAVICE a oa srevreray ——— L ee J oo +--+ - +--+ - - 5 - - - + - = - - = = - - -- = == 1 ree ee ' | om Fees averonr lenertorve rey | it or os Sey FE. muon a4 Diesel ears Durante war fe i —s or i a. PH ssowva 3] rarerme te re aorwet t}e— f{—__- tone mivee uRP [ts] ey Z we bod 2 i s00nve roy sxe <boves 3 q ! fay ieee ut —s ROM Ive CURD, wv Shere eee 1 z wast se temeyeanrirny e Zi een ee me a wee a a a a a em mm mm mr ee ee er re Sg tome: vanes su9e : reer VE Re faye stevie twun)| | PaRaaee- - - = ---- = -- ----- ce sye 0 Parvintt ' ner caer anv Bo ors sw 1 Dewama vie see arene: " eno oerrarce| |, 3 raarai | Bae Ta rrarees. MAIN POVER TRawsr. ran 73 WA tn i202 4i6- 2aoKV co eva TATION POWER Fon won 1m roan, =——jf—— rome. TOM POINT FOR hom FORILE er eve 4 jaarea sr ayy tmawsromen rao Pu me.ey Isvenes eva ciara vate Sst eee femal Moste Crergy Authority 1 1D Rene Crpcaaey oe CY 0 bo oem Cant Tee Reet ene Pane ETP me rev tery sa v* Srartow SOLOMON GULCH HYDROELECTRK PROJECT SPREE SYSTEM ONE-LINE PUGRAM i wa: lili} WM eS SS — poner — oi: = 300 KVA, 3¢ e4.9KV — 460V STA. SERVICE fea ae ~ VFDA SERVICE ER TRANSF. OA S456 IKV Ge) | || Lica MEALS SUBSTATI S414 GENERATOR 9 14.4/24,9KV 6.0 MW,8PF = SS cio ee 34,60 Hz,4.16KV 3 @) - TO MEALS SUBSTATI 5 CB TRANSF, 2£4.9Y/13.8A 7.5 MVA,OA = 6, 4 ACSR DISTRIBUTION FACILITIES N GULCH HYDRUELECTRIC ENERATING PLA SOL _1LIN COPPER VALLEY ELECTRIC ASSOCIATION INC. CLENNALLEN 822-2211 VALDEZ 835< 4301 MN GULCH ONE-LINE DIAGRAM, F E GLENNALLEN, AK. 99588 VALDEZ, AK. 99686 ALYESKA COPPER VALLEY GLENNALLEN 822-3211 P.O. BOX 45 GLENNALLEN, AK. 99588 OLOMON , LAKE ELECTRIC ASSOCIATION — INC. VALDEZ 835-4301 P.O. BOX 927 VALDEZ, AK. 99686 [18 al ALLISON See ei ee ene eee 13.8KV DISTRIBUTION ! ALY ESKA F PROPOSED ELEVATION SIDE VIEW DE VIEW PLAN VIEW SCALE: i’=8’-uU" REVISIONS ENGINEERING KECORD I SOLOMON GULCH COPPER VALLEY ELECTRIC ASSOCIATION, INC. SUBSTATION DETAILS DESIGNER FTSPERSON P.O. BOX 45 5 . Trai GLENNALLEN, ALASKA 99588 PROPOSED ADDITIONS FOR ALYESKA TIE ee DRAWING NUMBER CHECKED APPROVED Pee eee Pir nak teres UVALDE VeL ULL VAT COPPER VALLEY ELECTRIC ASSOCIATION, INC. PO BOX 45 = GLENNALLEN. ALASKA 99588-0045 ; Glennalien (907) 822.3211 Veldez (907) 835-4301 ® Telefax # (907) 822-5586 February 1, 1991 Mr. Mike Sullivan State of Alaska Department of Natural Resources Division of Land and Water Management Pouch 7-005 3601 C Street Anchorage, AK 99510-7005 Subject: Permit for Right-of-Way on State Land between Solomon Gulch Hydro and the Alyeska Pipeline Terminal Dear Mr. Sullivan: Copper Valley Electric Association, Inc. (CVEA) is proposing to construct a 24.9 KV distribution line between the Solomon Gulch Hydro facility and the Alyeska Pipeline Terminal. This line would provide electrical service to the Pipeline Terminal. We have discussed this project with Dennis Prendeville, of Alyeska. He has indicated that they will be able to issue a letter of nonobjection. The proposed distribution line would parallel the Pipeline and be located approximately 75' north of the Pipeline centerline. We would propose to follow the edge of the cleared right-of-way to preclude any timber clearing, with the exception of a few danger trees that could fall into the line. The line would originate at the Solomon Gulch powerhouse and would follow on the west side of the Penstock to the point where the Penstock crosses the Pipeline. It would then turn and follow the Pipeline until it reaches the Alyeska Pipeline property. The project presents several benefits to CVEA, and therefore the residents of Valdez and the Copper Basin. The pote-tial increase in electrical sales of otherwise spilled Hydro energy will help reduce the impact of high fuel costs associated with the Gulf War. The potential for future energy exchanges could reduce the electrical rates for our consumers as much as three to five cents. This is quite a benefit to our members who currently pay almost 20 cents per kwh. SERVING MEMBER-OWNERS IN THE COPPER RIVER BASIN AND VALDEZ Permit for Right-of-Way February 1, 1991 Page 2 At this early point, I am hoping for a quick assessment as to the "permitability" of this project. We have a need to begin construction in April 1991 and are concerned with timing of the right-of-way permit. We would certainly be able to meet with you in person, if such a meeting would be a means to help the permitting process. I certainly appreciate your assistance with this project, and I hope to be hearing from you soon. THU bebe Michael E. Eas Manager, Engineering Services Attachment cc: File c:\wp\me\91-009. jw Notes: |. See drawing VE5-1 for crossorm loading limitations. 2 Designate os VC7-I for assembly with three crossarms. ITEM|NO. MATERIAL Iirem|no | MATERIAL | | d_|13 |Wosher, squore, 2 U4" [[n_| 3 [Bot, double orming, 5/8"x req'd. length |_| | 2 |Crossorm, 3 V2"x 4 V/2"x 8-0" o | 1 |Bolt, eye, 5/8"x reqd. length CU | 4 |Broce, wood, 28" | oo | 2 |Nut, eye, 5/8" pa i .| 4 |Bolt, carrioge, 378" x 4 V2" co | 3 [Deodend cssembly, prima: Screw, log, V/2"x 4" cc Deodend assembly, neutral Pe Insulator, suspension, 10" | [lek | |Locknuts Bolt,eye, double arming 5/8" 44/249 KV, 3- PHASE ; CROSSARM CONSTRUCTION- DEADEND (SINGLE ) Jonl,1963 Position of Guy when req'd. Specify VCIA for PLAN offset neutral assembly TEM | NO. MATERIAL litem NO. MATERIAL co | 3 |msulotor, pin_type ll cu_| 2 |Broce, wood, 28" pe Pin, pole top, 20" i__| 2 [Bon __corrioge, 3/8" 4V2 Bolt, machine, 5/8'x req'd. length j | |Screw, og, V2"x 4", (VCl only) pe Wosher, $4 vore 2 1/4" |_|Bolt, single upset, insulated (VC! only) -— itpeeeeate —t fet bee ees pat Crossorm, 3 V2" x 4 We'x 8'-0' Bracket, offset, insulated (VCIA only) ps “ 14.4/24.9 KV, 3-PHASE CROSSARM CONSTRUCTION- SINGLE PRIMARY SUPPORT O° TO 5* ANGLE Cl,VCIA i oy’ + SECTION X-X ‘PLAN a MATERIAL : MATERIAL | bo | 2 |Shackle, anchor m [ca |6 peadend assembly, primary LU ossarm, 342" x 4¥2"x8'- 0" + ee 2 Deadend assembly, neutral SANIT insulator, suspension, 10" | race, wood ma a span HE E i "x req'd leng —] pee 14.4/249 KV.,3- PHASE CROSSARM CONSTRUCTION-DEADEND (DOUBLE) ALIN iii Pal iB NOTES: |. When two guys ore ottoched to one anchor rod use 3/4"x 8-O" twin thimble type eye rod. 2. Spacing between anchors shall be sufficient to provide maximum holding power for each anchor. 3. For loose soils, concrete or other pole footings are recommended. 4. Refer to Owgs. VE3-2 and VE3-3 for details of Wrapped guy when used in place of through bolt type guy shown in this drawing. 5. Arcing horns shown dotted may be installed as required for pole protection. For detoils of arcing horns refer to drawing VMIO- 14. 6. Other occepted and equivalent Item u deadend moterial moy be substituted for 3-bolt clamps shown. , * 8 * i a a fn A ergo rT aod 3/8" Strand 7/16" Strand I'- 6" MATERIAL Bolt, machine, 5/8"x req'd. length wire, S.M.,7 strand sher, square, 2 1/4" Clomp, guy bond, os required Deadend for guy strond, heavy duty onnectors, as req'd. Guy ottechment,(heavy duty for VE6- Jumpers, OS required ocknuts 14.4/249 KV DOUBLE DOWN GUY VEI-3 This may be substituted for wrapped type guy _Moximum ofter provided guy tension strain Is opplied will not exceed 8500 Ibs. Other accepted and equivolent (item u) dead-end material may be substituted for the ones shown. ASSEMBLY UNIT VEI-1 VEI-2 VEI-3 V4" Guy Wire| 3/8" Guy Wire | 716" Guy Wre MATERIAL _ [N& REQ'D. |N& REQ'D. | N& REC'D. Bot, machine, 5/8"x required length p | Connectors, os required Deadend for strand Guy wire, S.M., 7 Strond : req'd. length Clomp, anchor rod bonding Hlelel> |e Nn itr = Light Dut reqd. TT Pe CUT) 14.4/24.9 KV. SINGLE DOWN GUY, THROUGH BOLT TYPE | | OO faaeel ___ [WELWEFBVERS Approx. ofter stroin is opplied Size of hole to be some os onchor Approx. ofter strain is applied SCREW FI-IC, FI-2C, FI-3C, FI-IS, Fl-2S, Fl-3S, FI-4S Approx.after strain is Size of hole to be some os un- expanded anchor. EXPANDING Fl-1, Fl-2, FI-3,-Fl-4 Note: Projection of anchor rods above earth Approx. after strain is applied PLATE moy be increased to a mox. of !2"in FI-IP, FIl-2P, FI-3P, FI-4P cultivoted fields or other locations where necessory to prevent burying of the rod eye. ASSEMBLY UNIT ( Sto'e oO ACHkO DS | Woe’. mcKe Governs’ Alaska Energy Authority APydlic Corporation February 8, 1991 Mr. rag Bursey Copper Valley Electric Association, Inc. P.O. Box 45 Glennallen, Alaska 99588-0045 Dear Mr. Bursey: The Solomen Guich-Alyeska 24,9 kV Intertie line appears to be a good project to pursue and construct. I agree that this has benefits for both systems, even though Alyeska is requesting temporary service for June 1991. As we discussed, Copper Valley Electric Association, Inc. (CVEA) wil} provide the proposal to Alyeska and coordinate the project. If Alyeska accepts the proposal, CVEA will then hire a consultant agreeable to AEA to design the project from the Solomon Gulch Hydroelectric Plant to the Alyeska Pipeline terminal. The construction of the line will be under CVEA control. The Authority will want to approve the design for the Solomon Gulch substation modification and concur with the remainder of the project so all involved and effected by this project will understand what is to be installed and how it works. As stated, the project needs to provide for reliability as well as capacity, and insure that Solomon Guich Hydro and the terminal are protected from inadvertent system problems to the best of our capability. Remy Williams will be the contact for the Energy Authority for this project, assisted by Afzal Khan and myself. We will be available to help where we can. I hope this project moves ahead and succeeds so long-term goals can be realized. Sincerely, Stanley EY Sieczk , Director Facilities Operations & Engineering SES: jd cc: Brent N. Petrie, Alaska Energy Authority Afzal Khan, Alaska Energy Authority Remy Williams, Alaska Energy Authority G PO.BoxAM Junedu. Alaske 99841 (907) 465-3575 oe FO Pan 190869 704 Eost Tudor Road )=Anchorage Alaska 99549-0869 (907) 561-7877 February 8, 1991 Mr. Doug Bursgey, General Manager Copper Valley Electric Association, Inc. Post Office Box 45 Glennallen, Alaska 99588 SUBJECT: Alyeska Temporary Service Dear Mr. Bursey: : The City of Valdez has no objections to Copper Valley Electric Association (CVEA) routing a distribution line across City property to serve the Alyeska Terminal. We hope your project becomes a reality since electrical sales of this nature serve to benefit the entire CoOp membership and ultimately the City of Valdez. It is very encouraging to see Alyeska and CVEA working together to reach a common goal. We hope this relationship continues to improve in future dealings. If we may be of further assistance, please do not hesitate to call. Sincerely, be Griffin City Manager DG:blp P.O. BOX 307 * VALDEZ, ALASKA 89686 TELEPHONE (907) 835-4313 » TELEX 25-381 » TELECOPIER (907) 835-2982