HomeMy WebLinkAboutCopper Valley Intertie Memorandums 1992-1993WALTER J. HICKEL, GOVERNOR
DEPT. OF COMMUNITY & REGIONAL AFFAIRS
DIVISION OF ENERGY
MEMORANDUM
November 23, 1993
To: Robert E. Harris
Director
From: Richard Emerman ( ja
Senior Economist 7 |
Subject: | Copper Valley Intertie Feasibility Study -- Issuance of Draft Report
According to our contractor for the Copper Valley Intertie Feasibility Study, R.W.
Beck & Associates (Beck), the draft report is 99% complete -- with about one more
day’s work it would be ready to go to the printer. Preliminary copies of all significant
segments of the draft report have been provided to Copper Valley Electric
Association (CVEA) over the past several weeks. Some segments, such as the load
forecast and environmental analysis, were first provided to CVEA two months ago,
which in turn submitted detailed comments back to Beck and to the Division of
Energy. A brief chronology explaining how we got into the position of providing
advance drafts to CVEA is attached.
According to the attached letter from Beck to Clayton Hurless of CVEA, a meeting
on December 1, 1993 is planned between Beck and CVEA to discuss additional
CVEA comments and questions about the preliminary drafts. Although Beck is
ready to issue the formal draft report right now, they are continuing to operate under
instructions that CVEA is to be given full opportunity to present their views and
arguments prior to general release of the draft report.
After discussing this with Ike Waits and Dennis Meiners, I believe we should instruct
Beck to issue the formal draft report to the public as soon as possible, and cancel
their meeting of December 1 with CVEA. The reason, as suggested at the end of the
attached chronology, is that we have gone beyond the normal pre-draft consultation
practice whereby informed parties are asked to review and comment on the accuracy
of segments with which they may be uniquely familiar. Instead, we have reached a
point where it could reasonably be argued that CVEA, as a committed intertie
advocate, has been given an unfair opportunity to influence the content and
conclusions of the draft report before any other party has an opportunity for review
and comment. This would not be consistent with the even-handed public process
envisioned by the statutes under which this study is being conducted, nor would it be
consistent with the general policy of the Department.
Robert E. Harris
November 23, 1993
Page 2
To minimize any further perception that one side of the intertie debate has been
accorded an advantage in the study process, I recommend immediate release of the
draft report. At that time, CVEA and all other interested parties will have equal
opportunity for review and comment prior to preparation of the final report.
Attachments
cc: Dennis Meiners
Ike Waits
-81 39 mh BECK/SEATTLE CONSULT FAX NO. 208 44. 4864 EF
RW, BECK
AND ASSOCIATES
2101 Fourch Avcnuc Suite 600 @ Seatrle, Washington 95121-2375 e USA
Telephone (206) 441-7500 @ Fax (206) $41 4962
WS-1559-HA1-AJ November 19, 1993
Mr. Clayton Hurless
General Manager
Copper Valley Electric Association, Inc.
P.O, Box 45
Glennallen, Alaska 99588-0045
Upcoming Meeting to Discuss Report
Dear Clayton:
We look forward to meeting with you and other Copper Valley Electric
Association representatives in our office at 1.00 p.m. on December 1st to discuss the preliminary
draft of the Intertie feasibility report. In recent telephone discussions with Mike Easley, several
important comments and questions have been raised regarding the basic assumptions used in
our analysis. We would like to discuss these issues more thoroughly with you so that
appropriate adjustments can be made. I would expect that after our discussions we would be
in position to make final adjustments in the cost estimate, load forecast, economic analysis and other elements of the study and proceed with completion of the draft report. Since it may be
useful to spend more than just Wednesday afternoon reviewing and discussing the analysis and
report, we are prepared to carry the meeting over to Thursday, December 2nd, if necessary. Paul
Dorvel will be on vacation November 29th and 30th but the rest of us will be available
throughout the weck of November 29 through December 3 if your schedule changes.
If you should have any questions or require additional information please call either me at (206) 727-4418 or Paul Dorvel at (206) 727-4632.
Very tnily yours,
R. W. BECK AND ASSOCIATES
ohn L. Heberling
Executive Engineer
JLH:
G Paul Dorvel Mike Easley
Dave Helsby
Dick Emerman
Boston, MA @ Columbus, NE @ Denver, CO w Indimapolis, INw Mingcapolix, MN
Noshville, TN @ Orlando, Fl. @ Phocuia, AZ @ Sacramento, CA @ Seattle, WA
November 22, 1993
To:
From:
Robert E. Harris oa
Director ;
Richard Emerman / . / \
Senior Economist {
Subject: Copper Valley Intertie Feasibility Study -- Brief Chronology
As the feasibility study manager, I have afforded Copper Valley Electric Association
(CVEA) the opportunity to review and comment on segments of the feasibility study
draft prior to its general distribution. This has created at least the perception that
CVEA, as an intertie advocate, has been given an unfair advantage relative to other
interested parties in influencing the content and outcome of the draft report. Ike
Waits suggested this morning that it would be useful to set down a chronology that
indicates how we got into this situation, so a chronology with regard to the issue is set
down below.
1? The Alaska Energy Authority (AEA) included an FY 94 capital budget
request for $500,000 (later reduced to $425,000) to conduct the feasibility
study. If approved, the study could not have begun until July 1, 1993 (i.e. the
beginning of FY 94).
I met with Clayton Hurless, General Manager of CVEA, during the fall of
1992 to discuss options for proceeding with a feasibility study. He did not
want to wait until July 1, 1993, but wanted instead for the study to begin as
soon as possible.
The reason he wanted a feasibility study conducted was to demonstrate to the
legislature that the Copper Valley intertie had gone through (or was going
through) the same process that the Railbelt and Tyee-Swan interties had gone
through. He expressed the belief that this would increase the chances that the
legislature would include funds for a Copper Valley intertie within an overall
intertie package.
At my meeting with Clayton Hurless in fall 1992, I presented him with two
options:
A. He could conduct the study himself (or hire a consultant himself), and
present the study to the legislature in support of his request for State
funds. I told him this would not be recommended if he anticipated
getting the funds through AFA because I felt that the legislature --
particularly the House as it had been organized for a number of years -
- would be unlikely to accept his study in fulfillment of AEA’s statutory
review process. However, he could seek to have funds appropriated to
CVEA as a grant, perhaps through the Dept. of Administration or
through AIDEA or some other way. The legislature had appropriated
millions to AIDEA for the Healy Coal Plant, and other major requests
(such as Seward transmission line) had been appropriated as named
recipient grants through, I believe, the Dept. of Admin. These had not
required an AEA feasibility study.
B. If he felt that AEA would be the most likely conduit for Copper Valley
intertie funds, then the feasibility study should be conducted by AEA
to satisfy AEA’s statutory project review process. However, I told him
that an AEA study would be managed and controlled by AEA
independent of CVEA. He felt that appropriation through AEA was
the most likely path at that point and he therefore initiated the process
to develop an MOA under which CVEA would pay AEA to do the
study.
On October 13, 1992, I submitted the attached memo to Ron Garzini and
Brent Petrie stating my views on the proposed arrangement that CVEA
would pay AEA to conduct the feasibility study. My position was that we
should not share management responsibility with CVEA, and that generally
we should proceed as if the study were funded by State appropriation.
On November 6, 1992, CVEA submitted the attached draft agreement to
AEA. It contained numerous statements that implied a favorable posture
regarding the outcome of the proposed feasibility study, e.g.
"G. AEA and CVEA agree that preliminary studies conducted by Power
Engineers, Inc. relative to contructing a 138K V transmission line from
O'Neill Substation to Pump Station 11 Substation are indicative that it
is the option that would provide the most benefits to CVEA’s long-
term power requirments (sic) and rate reduction program."
"K. | AEA and CVEA agree that time is of the essence and, in order to
expedite the project construction to the extent possible, it would be
beneficial to both parties for CVEA to advance funds to AEA to
conduct the necessary additional studies to meet AEA’s statutory
requirments (sic) for establishing the project’s feasibility."
I redrafted the proposed agreement in a manner that deleted language
suggesting favorable judgment of the study outcome in advance of the study
process. See attached the final MOA dated January 6, 1993.
The study proceeded along for a few months. Numerous contacts with CVEA
occurred -- for example, I met with Clayton Hurless, his staff, and Beck staff
in Seattle in April to go over route alternatives in detail. Beck was in frequent
contact with CVEA staff on study issues.
In early summer 1993, I met with Ron Garzini and Clayton Hurless in
Garzini’s office -- Brent Petrie came in mid-way through the meeting. The
re 10.
1.
feasibility study had been underway since March 1993 and Clayton Hurless
had expressed objections to the way the study was going. Ron Garzini stated to me that he wanted to establish a new management relationship among
CVEA, AEA, and our study contractor R.W. Beck; that he wanted to ensure
that CVEA had full opportunity to make their views known on all
assumptions and significant elements of the study before any general release.
He wanted us to go forward in a cooperative manner.
On June 14, 1993, Garzini, Petrie, Hurless, and myself met with Beck in
Beck’s Seattle office. Beck stated that they had been in frequent contact with
CVEA staff up to that point on significant aspects of the study. Garzini
restated, however, that he wanted a new management relationship in which
CVEA was accorded full opportunity to express their views on all significant
aspects of the study, and that they should be more closely consulted and
included in the study development.
I don’t remember exactly when the verbal commitment was made to provide
CVEA with advance copies of the draft segments in order to get their
comments and consider revisions prior to general release. But it was around
this time and it was in the context of the "new relationship" that Garzini
wanted.
Up to a point, there is nothing unusual in providing certain segments of a
draft to the appropriate party in advance of general release to check its
accuracy. For example, Beck provided a copy of its write-up on Petro Star
future loads to the Petro Star site manager along with a request to check its
accuracy. Sending segments of drafts to the affected utility -- for example, to
check the accuracy of data used to establish labor or fuel costs, or generator
efficiencies -- is not controversial. The issue of fairness arose when subjects
such as the intertie environmental analysis, cost estimate, and regional load
forecast were sent as well. This went beyond input material that can simply
be checked for accuracy. And it could be argued that other parties have
comparable interest in, and understanding of, such issues as the intertie
environmental impact, intertie construction costs, or the modeling of future
economic and population growth in the region, and that these other parties
should have equal opporunity to review and comment.
October 13, 1992
To: Ron Garzini
Brent Petrie
in
From: Dick pena j, Wy
Subject: | Copper Valley Role in Intertie Feasibility Study
If Copper Valley pays for the study, I believe that the study outcome will ca
influenced and that we should try to minimize that influence.
As you know, whenever a supplicant for State funds conducts or commissions a study
on the project for which funding is sought, there is a strong tendency for cost
estimates to be low, problems underestimated, and benefits exaggerated. If we buy
into it, we increase the chance that AEA will have to come back to the Legislature
sometime in the future for more money, and with less credibility.
The situation with Kennecott is different because Kennecott is not asking for any
State money. Because Kennecott would bear the entire cost of the Greens Creek
intertie, their concern is much different than Copper Valley’s. The choices for the
preliminary cost estimate work for Greens Creek were Beck and HDR. When I told
Kennecott that Beck tended to be more "conservative" than HDR (i.e. their
estimates tended to be somewhat higher in my experience), Kennecott replied that
they would be much more comfortable with the more conservative firm. What they
didn’t want was extra cost surprises down the road.
Because Copper Valley’s interest is much different, I am uncomfortable with having
them play any significant role in the study. Assuming they pay for the study, I would
limit their participation to:
ie Review the RFP and give us their comments on it.
2; Review the proposals and give us their comments -- specifically which firms
would be acceptable and which would not.
35 Provide system data to the study team as they would whether or not they were
paying for the study.
4. Review the draft report and provide written comments, again as they would
whether or not they were paying for the study.
5: Participate in the public meeting process -- i.e. Clayton Hurless should be at
the front table for all public meetings on this subject.
Beyond that, I would not share management responsibilty with Copper Valley, or
give the consultant any impression that their job is to satisfy Copper Valley in this
assignment. I would not create a joint management or supervisory committee as we
did with Kennecott.
COPPER VALLEY ELECTRIC ASSOCIATION, INC. =
P.O.BOX45 GLENNALLEN, ALASKA ggsa8-008b& CEIVED
Glennallen (907) 822-3211 NOV 2 1992 Valdez (907) 835-4301 Telefax # (907) 822-5586 ALASKA ENERGY AUTHORITY
November 6, 1992
Mr. Ron Garzini, Executive Director
Alaska Energy Authority
P. O. Box 190869
Anchorage, Alaska 99519-0869
Subject: Memorandum of Understanding of OPS-11 Line
Enclosed is a draft of the Memorandum of Understanding (MOU) for the OPS-11
Line. It should be self-explanatory.
Please review the MOU and forward your comments.
Your truly,
Clayton Hurless
General Manager
Enclosure
cc: Dick Emmerman
c:\wp\cdh\92-174.jw
SERVING MEMBER-OWNERS IN THE COPPER RIVER BASIN AND VALDEZ
DRAFT
GZ0amn ") MEMORANDUM OF UNDERSTANDING = “°F 4200"
REGARDING THE STUDY AND PRELIMINARY COST OF RIGHT-OF-WAY
SELECTION AND ACQUISTION TO FACILITATE THE CONSTRUCTION OF
A 138KV TRANSMISSION LINE FROM O’NEILL SUBSTATION NEAR
SUTTON, ALASKA, TO PUMP STATION ELEVEN SUBSTATION NEAR
GLENNALLEN, ALASKA (OPS-11 LINE).
THIS MEMORANDUM OF UNDERSTANDING dated the of November, 1992, by
and between the ALASKA ENERGY AUTHORITY (AEA) and COPPER VALLEY ELECTRIC
ASSOCIATION INC. (CVEA).
WITNESSETH:
A. AEA desires to fulfill its statutory duty of providing residents of the State of Alaska with
a long-term economical and reliable supply of power;
B. CVEA owns and operates an electric utility system serving the Copper Basin and Valdez
areas of the State of Alaska and is engaged in the business of providing electric service
to approximately 8,000 Alaskan residents;
c AEA has constructed a significant number of generation and transmission facilities in the
State of Alaska;
D. AEA has the desire to further expand and improve the transmission and generation
infrastructure within the State of Alaska;
E. AEA and CVEA have been working together to find an economically feasible method to
reduce CVEA’s dependency on expensive diesel generated power and to provide CVEA
the opportunity to begin the process of reducing its extremely high retail rates;
F. AEA and CVEA have studied a number of different projects, such as raising the
Solomon Gulch dam and spillway to facilitate increased water storage in Solomon
Reservoir, tapping Allison Lake to provide supplemental generation and water supply for
the Solomon Gulch project, and developing Silver Lake as a new project. Each of these
projects would provide an increment of additonal energy, but none would eliminate the
necessity to continue running the diesel genertors during low inflow periods;
G: AEA and CVEA agree that preliminary studies conducted by Power Engineers Inc.
relative to constructing a 138KV transmission line from O’Neill Substation to Pump
Station 11 Substation are indictative that it is the option that would provide the most
benefits to CVEA’s long-term power requirments and rate reduction program.
DR md Se
Memorandum of Understanding
AEA and CVEA
Page 2
H. AEA and CVEA also agree that further studies are required to verify and expand the
NOW,
1.1
1.2
L3
scope of the preliminary findings to meet AEA’s statutory requirements for establishing
feasibilty for the proposed project;
AEA has included $500,000 in its FY 94 budget request to the 1993 Alaska Legislature
to conduct the necessary studies for the OPS-11 line, and such funds will not be available
until July 1, 1993;
CVEA has paid for the preliminary studies and, through December 31, 1992, will have
expended approximatley $100,000;
AEA and CVEA agree that time is of the essence and, in order to expedite the project
construction to the extent possible, it would be beneficial to both parties for CVEA to
advance funds to AEA to conduct the necessary additional studies to meet AEA’s
statutory requirments for establishing the project’s feasibility;
THEREFORE, the parties agree as follows:
ARTICE I
OBLIGATIONS OF THE ALASKA ENERGY AUTHORITY (AEA)
AEA will submit a request to the 1993 Alaska Legislature in the amount of $500,000 to
fund the necessary studies, right-of-way selection, public involvement meetings, and
other preliminary engineering work required to construct a 126-mile, 138K V transmission
line beginning at the O’Neill Substation near Sutton, Alaska (owned by Matanuska
Electric Association) and terminating at Pump Station 11 Substation near Glennallen,
Alaska (owned by AEA and operated under contract by CVEA).
Upon receiving authorization by the Alaska Legislature to fund the work described in the
above paragraph 1.1, AEA will refund to CVEA all funds advanced from the date of this
agreement through June 30, 1993; and to the extent adequate funds are remaining in the
authorization after payment to CVEA of all funds advanced under this agreement and the
payment of all other costs associated with completing the tasks as outlined in the attached
AEA estimate of costs (Exhibit A), AEA will refund to CVEA the costs of the
preliminary studies that were conducted prior to this agreement in an amount not to
exceed $110,000.
AEA will conduct the work covered by this agreement in a timely manner and will keep
CVEA informed on the status of the various contracts that will be required to complete
the work.
DRE: ons sy “hy Memorandum of Understanding
AEA and CVEA
Page 3
1.4 If the work provided for in this agreement concludes that the OPS-11 is feasible and is
the best long-term economic solution to providing an adequate and reasonably priced
source of wholesale power to CVEA, AEA shall use its best efforts to obtain adequate
funding for the construction of the project in a manner that will produce the maximum
benefit possible to the member-owners of CVEA.
1.5 On completion of the work provided for in this agreement and the decision to proceed
with the construction of the OPS-lI line, AEA will enter in good faith negotiations with
CVEA and other interested parties to determine the most cost- and time-efficient method
for construction. Possible methods could include but are not be limited to contracting
with CVEA, another utility, or a consortium of utilities to provide the design,
right-of-way acquistion, construction, and construction management for the project.
ARTICLE I
OBLIGATION OF COPPER VALLEY ELECTRIC ASSOCIATION (CVEA)
2.1. CVEA will advance funds not to exceed $260,000 to AEA to conduct the work described
in paragraph 1.1 of Article I of this agreement and further described in Exhibit A
attached to this agreement beginning on the effective date of this agreement and ending
on June 30, 1993.
2.2. CVEA will provide the coordination with Matanuska Electric Association and other
interested organizations for the conducting of public involvement meetings and other
activities relative to securing land holder and agency permission for rights-of-way in the
most cost- and time-efficient manner possible.
2.3. CVEA will cooperate with AEA in all ways possible to assure that the work is completed
at the earliest date possible consistent with performing the work to the standards required
to meet AEA’s statutory requirements.
ARTICLE I
GENERAL PROVISIONS
3.1 This Memorandum of Understanding will be effective when approved by each
organization’s Board of Directors, and the Resolution effecting such approval has been
transmitted to the other party. Such resolutions will become a part of this agreement and
shall be attached hereto.
Memorandum of Understanding
AEA and CVEA
Page 4
3.2 Subsequent to the effective date of this MOU, should any provision contained herein be
determined to be unlawful or unenforcible, all other provisions shall remain in effect as
if the unlawful or unenforcible provision were not in the agreement.
IN WITNESS WHEREOF, the Alaska Energy Authority and Copper Valley Electric Association
have caused this Memorandum of Understanding to be executed the day and year first above
written.
ALASKA ENERGY AUTHORITY COPPER VALLEY ELECTRIC
ASSOCIATION, INC.
BY: BY:
Ay MEMORANDUM OF AGREEMENT
REGARDING THE FEASIBILITY STUDY OF A 138 KV TRANSMISSION LINE
FROM O’NEILL SUBSTATION NEAR SUTTON, ALASKA, TO PUMP STATION
ELEVEN SUBSTATION NEAR GLENNALLEN, ALASKA (OPS-11 LINE). Khy
‘ 73 OY
THIS MEMORANDUM OF AGREEMENT dated the (-' of _ VMAuUaru ___, 1997, &
by and between the ALASKA ENERGY AUTHORITY (AEA) and COPPER VALLEY
ELECTRIC ASSOCIATION, INC. (CVEA).
WITNESSETH:
A. The primary mission of AEA is to facilitate the development of energy systems that will
satisfy the requirements of Alaska consumers at the lowest cost over the long run;
B. CVEA owns and operates an electric utility system serving the Copper Basin and Valdez
areas of Alaska and is engaged in the business of providing electric service to
approximately 8,000 Alaskan residents;
Cc AEA has constructed a significant number of generation and transmission facilities in
Alaska;
D: AEA and CVEA have been working together to find an economically feasible method to
reduce CVEA’s dependency on expensive diesel generated power and to provide CVEA
the opportunity to begin the process of reducing its high retail rates;
E: AEA and CVEA have studied a number of different projects, such as raising the
Solomon Gulch dam and spillway to provide increased water storage in Solomon
Reservoir, tapping Allison Lake to provide supplemental generation and water supply for
the Solomon Gulch project, and developing Silver Lake. Each of these projects would
provide an increment of additional energy, but none promises to eliminate the necessity
of diesel generation in the future.
F. In 1989, AEA issued a reconnaissance study for the “Northeast Intertie," a proposed
230 kv transmission line from Sutton to Glennallen, then north to the Fairbanks area;
iG. The proposed 138 kv line between Sutton and Glennallen, to be evaluated in the
feasibility study that is the subject of this Memorandum of Agreement, is a scaled down
version of the Sutton-Glennallen portion of the Northeast Intertie. Consequently, AEA’s
reconnaissance study requirements for the proposed 138 kv line between Sutton and
Glennallen (the "OPS-11" line) have been satisfied by completion of the 1989 Northeast
Intertie study;
Memorandum of Agreement
AEA and CVEA
Page 2 of 4
NOW,
Tl
1.2
L.3
For the OPS-11 line, the next step in AEA’s project review process is a feasibility study
conforming to AEA’s statutory requirements;
AEA has included $500,000 in its FY 94 capital budget request to conduct a feasibility
study, plan of finance, and independent cost estimate for the OPS-11 line. If this request
is ultimately approved by the Governor and the Legislature, the funds will not be
available for expenditure until July 1, 1993;
CVEA prefers that the project evaluation process begin as soon as possible and asked
AEA to estimate the amount that would be spent on the required feasibility study prior
to July 1, 1993, if funding were available now. In response, AEA estimated that
$260,000 would be spent prior to July 1, 1993, and an additional $165,000 would be
spent after July 1, 1993, to complete the feasibility study and also the plan of finance and
independent cost estimate (see Exhibit A). The parties anticipate that all tasks in
Exhibit A will be complete by December 31, 1993, provided timely provision of
adequate funds.
THEREFORE, the parties agree as follows:
ARTICLE I
OBLIGATIONS OF THE ALASKA ENERGY AUTHORITY (AEA)
AEA will continue to support a request in the FY 94 capital budget of not less than
$425,000 to fund the feasibility study, plan of finance, and independent cost estimate for
the OPS-11 line. Further, AEA will support the use of a portion of this request to
reimburse CVEA for all funds advanced to AEA for the OPS-11 feasibility study under
the terms of this Memorandum of Agreement.
If the Legislature specifically appropriates funds to reimburse CVEA for funds CVEA
advances to AEA for the OPS-11 feasibility study from the date of this agreement
through June 30, 1993, CVEA will be reimbursed in accordance with the appropriation.
If the Legislature does not specifically appropriate funds to reimburse CVEA for such
feasibility study costs, CVEA will not be reimbursed. The parties are cognizant of and
have read the Alaska Department of Law memorandum (Exhibit B) indicating that
legislative intent to refund these costs to CVEA must be clearly expressed in the
appropriation in order for reimbursement to occur.
AEA will conduct the work covered by this agreement in a timely manner and will keep
CVEA informed on the status of contracts required to complete the work.
Memoranduin of Agreement
AEA and CVEA
Page 3 of 4
1.4
i)
1.6
AEA will submit invoices to CVEA on a monthly basis for reimbursement of costs
covered by this agreement. At the conclusion of work covered by this agreement, AEA
will refund to CVEA any funds remaining from CVEA’s initial advance payment.
If the work provided for in this Memorandum of Agreement concludes that the OPS-11
line is feasible and is the best long-term economic solution to providing an adequate and
reasonably priced source of power to CVEA, AEA shall use its best efforts to obtain
adequate funding for construction of the project.
On completion of the feasibility study, plan of finance, and independent cost estimate,
AEA will enter into good faith negotiations with CVEA to determine the most cost- and
time-efficient method for project construction consistent with State procurement law.
ARTICLE II
OBLIGATIONS OF COPPER VALLEY ELECTRIC ASSOCIATION, INC. (CVEA)
2.1
2:2
2.3
3.1
3.2
CVEA will advance funds not to exceed $260,000 to AEA to conduct the work described
and scheduled in Exhibit A to occur before July 1, 1993. CVEA shall pay such funds
within two weeks of receipt of monthly invoices from AEA and will make an advance
payment of $20,000 to AEA upon execution of this agreement.
CVEA will participate with AEA and others in the public involvement meetings and will
assist in other activities such as land holder and agency right-of-way discussions.
CVEA will cooperate with AEA in all ways to assure that the work is completed in a
timely fashion and consistent with AEA statutory requirements.
ARTICLE I
GENERAL PROVISIONS
This Memorandum of Agreement will be effective when approved by each organization’s
Board of Directors and the Resolution effecting such approval has been transmitted to the
other party. Such resolutions will become a part of this agreement and shall be attached
hereto.
Subsequent to the effective date of this Memorandum of Agreement, should any provision
contained herein be determined to be unlawful or unenforceable, all other provisions shall
remain in effect as if the unlawful or unenforceable provision were not in the agreement.
Memorandum of Agreement
AEA and CVEA
Page 4 of 4
IN WITNESS WHEREOF, the Alaska Energy Authority and Copper Valley Electric Association
have caused this Memorandum of Agreement to be executed the day and year first above
written.
ALASKA ENERGY AUTHORITY COPPER VALLEY ELECTRIC
ASSOCIATION, INC.
STATE OF ALASKA )
THIRD JUDICIAL DISTRICT )
_The foregoing Mem ate of Agreement was acknowledged before me this (a bay of _< ae , 199236¥ RONALD GARZINI, Executive Director of the ALASKA
ENERGY A ORITY, on behalf of the Authority.
Notary Public f He for the State of Alaska
My commission expires: (ZAI/IID
STATE OF ALASKA )
) ESS;
THIRD JUDICIAL DISTRICT )
The foregoing Memorandum,of Agreement was acknowledged before me this (ot say
of eee 5 19923 CLAYTON HURLESS, General Manager of COPPER
VALLEY ELE C ASSOCIATION, INC., on behalf of said corporation.
Notary Public hd for the State of Alaska
My commission expires: _D( tober (> 199.)
COPPER VALLEY ELECTRIC ASSOCIATION, INC.
RESOLUTION 92-28
AEA/CVEA MEMORANDUM OF AGREEMENT
OPS-11 INTERTIE LINE
WHEREAS, the Copper Valley Electric Association Board of
Directors has identified the need for rate relief for its
membership, and alternatives have been studied to fulfill this
need; and
WHEREAS, the Board of Directors has identified the most
reasonable solution is to become interconnected to the Railbelt
System; and
WHEREAS, Copper Valley Electric Association has begun
preliminary studies of an intertie line from O'Neill Substation to
Pump Station 11 Substation, the purpose of which is to connect
CVEA's system to the Railbelt system; and
WHEREAS, the Alaska Energy Authority has indicated
studies cannot continue until the next fiscal year when funds are
appropriated; and
WHEREAS, the Board of Directors has identified the need
to continue the studies in a timely manner; now, therefore
BE IT RESOLVED, that Copper Valley Electric Association
and the Alaska Energy Authority enter into a Memorandum of
Agreement which allows for Copper Valley Electric Association to
forward funds in the amount of $260,000 to the Alaska Energy
Authority to continue preliminary studies of the OPS-11 line; and
BE IT FURTHER RESOLVED, the Board of Directors approves
the Memorandum of Agreement and authorizes the General Manager to
execute the document on behalf of Copper Valley Electric
Association.
Approved and signed this 16th day of December, 1992, in Glennallen,
Alaska. VY i. ppt
Robert E. Sunder, President
(seal)
ALASKA ENERGY AUTHORITY
BOARD OF DIRECTORS MEETING
JANUARY 22, 1993
RESOLUTION 1993-03
RESOLUTION OF THE ALASKA ENERGY AUTHORITY APPROVING A MEMORANDUM
OF AGREEMENT WITH COPPER VALLEY ELECTRIC ASSOCIATION FOR A
FEASIBILITY STUDY OF A SUTTON-GLENNALLEN INTERTIE
WHEREAS, the Alaska Energy Authority completed a
reconnaissance study in 1989 of a transmission line between
Sutton and Glennallen; and
WHEREAS, the Alaska Energy Authority Board of Directors has
approved the inclusion of $425,000 in the FY94 capital budget
request to conduct a feasibility study of a transmission line
between Sutton and Glennallen; and
WHEREAS, Copper Valley Electric Association has requested
that the Sutton-Glennallen intertie feasibility study begin as
soon as possible; and
WHEREAS, Copper Valley Electric Association has agreed to
pay the expected costs of the feasibility study incurred through
June 30, 1993; and
WHEREAS, the Legislative Budget and Audit Committee approved
the request of the Energy Authority to receive and expend the
funds that Copper Valley Electric Association has agreed to pay;
NOW THEREFORE BE IT RESOLVED BY THE ALASKA ENERGY AUTHORITY
AS FOLLOWS:
Section 1. That the Alaska Energy Authority Board of
Directors approves the Memorandum of Agreement between the Alaska
Energy Authority and Copper Valley Electric Association regarding
the Sutton-Glennallen feasibility study and the provision of
funds not to exceed $260,000 by Copper Valley Electric
Association. :
an vens_5/ Rey Attn ae
Nays OO
ABSENT 2) funs/ Mag)
93Q1\JD4148(1) Page 1
and the resolution was declared adopted on the aane day
of , 1993.
ALASKA ENERGY AUTHORITY
By:
hairma
By:
Secretary
Approved at Sinu ary 4a, 1992 Board Meeting.
Corporate Seal Goes Here
93Q1\JD4148(2) Page 2
m XHIZIT A
October 20, 1992
Cost estimate for Copper Valley Intertie Feasibility Study
Note: It is assumed that both the "Northern Suggested Route" (near the road) and
the "NEICR" route up Boulder Creek (or a comparable route away from the road)
will be reviewed, refined, and compared in the feasibility study. Also assumed that
the study begins in mid-January.
Public meetings would be held at the start. Both route alternatives would be
reviewed and refined in the winter, including flyovers of both routes and limited
ground review of accessible portions. Preliminary environmental impact
comparisons would be conducted. Another set of public meetings would follow to
share information and discuss results.
After June 30, any remaining route alternatives would again be reviewed and
refined, including flyover and ground review as appropriate. Thus both summer and
winter conditions will be accounted for in the route selection, feasibility design, and
environmental analysis. Public meetings would again follow the summer review.
Before 6/30 After 6/30 Total
Electrical system studies $30,000 $30,000
Route selection 25,000 15,000 40,000
Feasibility design 25,000 5,000 30,000
Cost estimate : 20,000 20,000
Environmental studies 60,000 40,000 100,000
Load forecast 25,000 25,000
Economic evaluation of alternatives 40,000 10,000 50,000
Plan of finance 25,000 25,000
Independent cost estimate 25,000 25,000
Public comment process 20,000 10,000 30,000
AEA costs 35,000 15,000 50,000
TOTAL $260,000 $165,000 $425,000
MEMORANDUN, costars c.ate of Alaska a FROM
Ronald A. Gar2ini ree Novenber 9, i392
Executive Director
Alaska Energy Authority 5 feu 269-5166
sugect Sutton-Glennallen y Intertie
ST: James F. Klas
Assistant Attorrey General
Transportation Section, Anchorage
This memorandum is in response to the request of your
office of November 2, 1992 regarding the plan for Copper Valley
Electric Association (CVEA) to advance the Energy Authority costs
for phase 1 of the Sutton-Glennallen Intertie Feasibility Study.
I have researched the proposal and find no law to
prohibit such an arrangement. This appears to be a conditional
gift which the AEA has the power to accept under AS 44.83.080(5).
The AEA furthermore has the power to perform the feasibility
studies under AS 44.83.080(13) and to enter into a Memorandum of
Agreement (MOA) for this study under AS 44.83.080(14).
State funds may not be spent without an appropriation
pursuant to Article IX, section 13 of the state constitution, but
this requirement is being met in this instance through your
Legislative Revised Program Request (RPL) dated October 26, 1992
which if approved will result in an appropriation for the stated
purposes.
However, the AEA and CVEA should understand that absent
specific legislative direction or clear intent, costs are not
ordinarily reimbursable from an appropriation where the costs are
incurred prior to an appropriation being passed. Past attorney
general opinions have noted that only in exceptional circumstances
may grant money be used to reimburse for costs incurred prior to
the date of the legislative appropriation. See, for example, the
attached attorney general opinions dated August 7, 1985, file No.
366-527-85, and March 24, 1986, file No. 663-86-0412. The
reasoning employed in these AG opinions applies to capital budget
appropriations as well.
Whether CVEA can be reimbursed out of a future state
appropriation would be determined from the language of the
appropriation. Without specific language in the appropriation
making clear the legislative intent to reimburse CVEA out of the
appropriation it is very probable that the reimbursement to CVEA
would not be allowed. Furthermore, the MOA with CVEA should
reflect that the $260,000 conditional gift can only be refunced <5
CVEA if the appropriation from the legislature clearly reflects
that legislative intent.
JFK: bb
att
KEPOR!I: MEDIA CONTACE
DEPARTMENT OF COMMUNITY AND REGIONAL AFFAIRS
Please return completed form to: Annette Barril Secretary II
: 7 Office of the Commissioner
From: helen Efren Date (2) (ELF 3
7) i Fa ?
Contacted by: Like O vd te Telephone
Leh - LhLi News Newspaper/TV/Radio Station:
“Contact Narrative:
SCO CY CG
(continue on back if necessary)
Action Required or Taken:
Follow-up Response Necessary? Yes No x
If yes, when, what type, and person responsible:
cc: Division Director
Deputy Director
Date In Received By
2/6/87
December 16, 1993
Contact narrative:
I received a phone call today from Peter Goodman, reporter for the Anchorage
Daily News working out of their Palmer office. Points in the discussion included:
1 He said he had been out in Glennallen during this last week and had talked
with a number of people, including Mr. Randy Maag, Engineering Manager
of the Petro Star refinery. Randy Maag sent our study contractor a letter in
early November stating that the refinery planned a very significant expansion
in its power requirements over the next 10 years -- an assumption which can
make a significant difference in the economic analysis of the intertie.
Apparently, Randy Maag eventually told the reporter that the expansion
plans were fairly speculative -- more speculative than they seemed to be in his
letter. So the reporter asked whether I felt we might be misled by speculative
projections of major expansions at the refinery to make the intertie look
better. He also asked whether I felt a good decision could be made on the
intertie when so little was known about such a major assumption. I said it
would be good to know more about it than we do, but that at this point we
proposed only to lay out in the draft study what we had been told to this point.
The reporter also said that he was presently planning to do a story on the
subject of the Sutton-Glennallen intertie sometime next week, and that he
plans to come in and look at our files in accordance with his previous request
under public information laws.
He asked about changes that Beck might now be making in the draft report
relative to the content of the preliminary working drafts that are in our files. I
said that the cost estimate was coming down, but I declined to give him a
number until Beck puts it in writing. I also said that there will be changes in
the load forecast, and discussed my direction to Beck to create essentially two
"Mid" cases; one with limited expansion of the Petro Star refinery, and one
with the full expansion described in Randy Maag’s letter.
A Fax From The Department of Community & Regional Affairs a Division af Ene
BOM BESTS Ts Anchorage, AK 99519-0869 7oL Eade PEGE RLS ot Floor Anchorage, AK 99503
Main Telephone Number (907) $61-7877
ore
Deliver Fax ro: ee.
Company Name:
Company Address:
Nyeermber: (907) $61-8F584
a, Zana
Fax Phone #: 2ZVG-— S272 Sender: a eee
Sender's Phone *#
# of Pages Sent:
Date Fax Sent: *
SS you aon eo ecaive —
SPECIAL INSTRUCTIONS TO FAX RECIPIENT:
Unctuding this cover shaw@) SS
Sadee signe att:
TRANSMISSION REPORT
THIS DOCUMENT WAS CONFIRMED
(REDUCED SAMPLE ABOVE - SEE DETAILS BELOW)
*k COUNT **
TOTAL PAGES SCANNED >: 2
TOTAL PAGES CONFIRMED : 2
yee SEND eek
[No. | REMOTE STATION START TIME [DURATION|#PAGES | MODE | RESULTS
1 12-14-93. 14:41 1'22"| 27 2 | COMPLETED
| | | 9600
TOTAL 0:01°22" 2 NOTE: \o. : OPERATION NUMBER 48 : 4800BPS SELECTED EC : ERROR CORRECT G2 : G2 COMMUNICATION PD : POLLED BY REMOTE SF : STORE & FORWARD RI: RELAY INITIATE RS : RELAY STATION MB : SEND TO MAILBOX PG : POLLING A REMOTE MP : MULTI-POLLING = RM : RECEIVE TO MEMORY
A Fax From The Department of Community & Regional Affairs Division of Energy
Mailing Address: Physical Address:
P.O. Box 190869 701 East Tudor Road, 2nd Floor
Anchorage, AK 99519-0869 Anchorage, AK 99503
Main Telephone Number (907) 561-7877
Deliver Fax to:
Company Name: g :
Company Address: fieboré
Fax Phone #: ee Sf eZ
Sender: A ! Exner
Sender's Phone # S6/- 7572
# of Pages Sent: 2
. } (Including this cover sheet) Date Fax Sent: hh Fass
If you don't receive all of this lease call: iy Anchorage: (967) SIRS
SPECIAL INSTRUCTIONS TO FAX RECIPIENT:
WALTER J. HICKEL, GOVERNOR
DEPT. OF COMMUNITY & REGIONAL AFFAIRS
DIVISION OF ENERGY
December 14, 1993
Mr. Peter Goodman, Reporter
Anchorage Daily News
800 West Evergreen, Suite 205
Palmer, AK 99645
VIA FAX: = 746-5171
Dear Mr. Goodman:
Following receipt of your fax dated December 10, 1993, requesting access to our files
on the Sutton-Glennallen intertie feasibility study, I called you and left a message on
your phone recorder. Since I have not yet heard back from you, I am following up
with this fax reply.
The files are available for public review at our office during regular business hours.
Should you request copies of file materials following your review, we will copy them
for you and charge the agency’s standard duplication fees. I would prefer that you
review the materials first and then select whatever you want us to copy. Unless I
hear otherwise from you, I will assume that you will come to our offices first to review
the files before we copy and mail anything to you pursuant to your December 10
request.
I will be in the office during the week of December 13, but will then be on vacation
for the last two weeks of December. Should you wish to come in to review the files
during the week of December 20, please contact Irene Tomory, Administrative
Assistant. Should you wish to review the files during the December 27-29 period,
please contact Terri Ganthner, Administrative Assistant.
Sincerely,
Mk {prove
Richard Emerman
Senior Economist
701 East Tudor Road, P.O. Box 190869, Anchorage, AK 99519-0869
ws KEPORI: MEDIA CONTACT
DEPARTMENT OF COMMUNITY AND REGIONAL AFFAIRS
Divisrn ¢ 4 Erryy
Please return completed form to: Annette Barril
Secretary II
Dy ~ Office of the Commissioner
From: hihi Eneman Date PES A £ TS
A: Fae CQ cac ry ty Telephone
eer
Lhivh, Nex
Contact Narrative:
Contacted by:
(continue on back if necessary)
Action Required or Taken: ACHE
Follow-up Response Necessary? Yes No
If yes, when, what type, and person responsible:
cc: Division Director
Deputy Director
Date In Received By
2/6/87
(2/0/53
Contact Narrative:
Reporter inquired about the status of the Copper Valley intertie feasibility study. He had in his possession at least one memo I had written on the subject, and possibly
more. For example, a memo he specifically referred to was one I wrote to Garzini
and Petrie in late 1992 before the study began, in which I suggested that there was a
potential for bias in the feasibility study because the intertie applicant (CVEA)
would be paying for it, and that we needed to be especially careful to maintain an
arms length relationship. My assumption is that he obtained these memos from Mr.
Chris Rose, a lawyer who obtained them from our files a couple of weeks ago
pursuant to a formal request under the Public Records Act.
The main thrust of his questioning was whether I felt the study turned out to be
objective and fair. The main thrust of my reply was that I believed the State (i.e.
AEA, DCRA, and myself) and our contractor had been successful in maintaining our
neutrality and objectivity throughout the study process, making adjustments only in
response to those criticisms from CVEA that we believed had merit and rejecting the
others. However, I also confirmed that we had much more comment from and
interaction with CVEA than with any of the other interested parties, and that I
wondered whether the study would have been at least somewhat affected if we had
been in contact primarily with an advocate of one of the intertie alternatives instead
of with CVEA. I said that perhaps we would have been more forcefully confronted
with different perspectives and arguments, and that this might have made a
difference.
Additional Note: I heard yesterday from Robert Harris that a question had been
raised about whether I had spoken recently with a reporter from Palmer. It has been
several months since anyone from Palmer has called me, and I have never initiated a
contact with the media myself. However, I would not be surprised if the file memos I
referred to above have been distributed to a number of people and/or organizations,
including media people and potential intertie opponents. The gist of the memos
copied by Mr. Chris Rose was that the study might be perceived to be biased because
the study process has, to this point, allowed CVEA considerably more opportunity
than any other party to comment on and argue for changes in the analysis and
preliminary drafts.
ff Arron
REPURI: MEDIA CUNITAL!
DEPARTMENT OF COMMUNITY AND REGIONAL AFFAIRS
Please return completed form to: Annette Barril
Secretary II
Office of the Commissioner
From: Ki Mac Entoonte Date fz G3
Contacted by: ppec boxed mary Telephone 2YE-2Y320
(Seuspaps}/1V/Radio Station: Yuete Cope 4, S Ve As J J) fel ra we.
Contact Narrative:
_Ste_atbehod,
(continue on back if necessary)
Action Required or Taken:
Follow-up Response Necessary? Yes No
If yes, when, what type, and person responsible:
cc: Division Director
Deputy Director
Date In Received By
2/6/87
12/13/93
Contact Narrative:
I received the attached fax this morning requesting access to Sutton-Glennallen
intertie feasibility study files in accordance with public information statutes. I called
back and left a message on his recorder saying that he could come in and look
through the files, and that we would then copy requested material.
As of noon today, he has not indicated whether or when he will come in.
Anchorage Daily News
12/10/93 — Page t 300 West Evergreen, Suite 205 i
Palmer, Alaska 99645
Phone: 746-2430
Fax: 746-5171
Oecember 10, 1993
Mr. Richard Emmerman
Project Manager for Feasibility Study for
Sutton to Glennallen Intertie
Department of Community and Regional Affairs
Anchorage, Alaska
i Desr Mr; Ermerrnan:
i
Under all applicable state and federal open record laws, | hereby request copies of any
and all correspondence between R.W. Beck Inc. and Copper Valley Electric Association
related to the feasibility study on the proposed Sutton to Glennallen Intertie as well as
copies of apy existing drafts of that feasibility study.
! {f the mass of paper involved is large enough to make mailing or faxing impractical, |
request that you allow me to visit your office and provide me with access to the relevant
files.
Thank you for your time. | !
\ . | Sincerely,
| Puls rde
Peter S. Goodman
Reporter
Street Address: 1001 Northway Drive, Anchorage, Alaska 99508
Mailing Address: P.O. Box 14-9001, Anchorage, AK 99514-9001 (907) 267-4200