HomeMy WebLinkAboutReconnaissance Study Of Energy Requirements & Alternatives-Finding and recommendations 1980RECONNAISSANCE STUDY OF ENERGY
REQUIREMENTS AND ALTERNATIVES FOR ELIM, KALTAG, SAVOONGA AND WHITE MOUNTAIN
FINDINGS AND RECOMMENDATIONS
Funding was made available to the Power Authority in July of 1980 to conduct reconnaissance studies of energy requirements and alternatives in 29 selected Western Alaskan villages. Holden & Associates was the engineering firm selected to conduct the reconnaissance studies for the villages of Elim, Kaltag, Savoonga, and White Mountain.
STUDY DESCRIPTION:
The purpose of the study was to identify and assess the present and future power needs of each community and to assess the power project alternatives
available to that community. It will serve as the basis for recommending more detailed data collection activities, resource assessments or detailed feasibility studies of one or more specific power project alternatives. The study includes the following items:
1. An assessment of existing demographic and economic conditions, power facilities, heating facilities, and preparation of an energy balance
that characterizes total energy use in terms of energy forms entering
the area, end uses and waste heat.
2. A 20 year energy requirements forecast which addresses economic
activity, planned capital projects and electrical and heating end uses.
The forecast includes electrical energy, heating energy and peak loads.
3. A resource and technology assessment. This includes an energy resource
assessment for those resources available to each individual village, a
brief description of the full range of alternative electrical energy
technologies, and a determination of which technologies are available
to each village.
‘4. Formulation of a number of energy plans for each individual village
incorporating those technologies previously determined to be available
to each village. The plans include a base case plan which consists of
the continuation of existing practices.
5. Economic, environmental and technical evaluation of each plan.
6. Recommendation of the preferred energy alternatives for each individual
village and required subsequent resource assessments and feasibility
studies.
Paae 1 ‘ pet
FINDINGS:
Elim - The existing electrical energy requirements and peak demand are approximately 249,819 kwh/yr and 82 kw respectively. These requirements are expected to increase to 654,293 kwh/yr and 213 kw by the year 2001. Existing heating energy requirements are 13,400 MBTU/yr. This requirement is expected to increase to 20,900 MBTU/yr by the year 2001. Existing power generation
for the village is by one 250 kw, one 105 kw, and one 50 kw diesel generators,
all owned by AVEC. The school district owns two standby diesel generators
which supply power to the school during AVEC outages. Also, a Single 1 kw
wind generator has been installed for use by the National Guard Armory.
Most residential space heating is by woodstove. The remainder of the village
heating requirements is accomplished by the use of fuel oil.
The lowest cost energy plan available to Elim consists of continued diesel
electric generation with the implementation of an increased conversion
efficiency system, waste heat recovery for the school buildings, heavy
utilization of woodstoves and weatherization measures. All plan components
have been proven and demonstrated in an Alaskan village environment with the
exception of the increased conversion efficiency component which would
require pre-packaged load sharing and sequencing systems. The second lowest
cost alternative is the base case plan of continued diesel electric generation with a continuation of the existing proportion of fuel oil and wood for
space heating purposes and none~~ the “lowest cost plan" improvements.
Development of hydroelectric energy on Quiktakik Creek with supplemental
diesel electric generation and maximum utilization of woodstoves and weatheri-
zation measures was found to be the highest cost alternative and, therefore
dropped from further consideration.
The harvest and transportation of wood required for space heating could have
significant environmental impacts due to access trails and clear cutting.
Also, development of the hydroelectric project could have significant adverse
environmental impacts. Community preferences at Elim include hydroelectric
power and weatherization of older homes.
Kaltag - The existing electrical energy requirements and peak demand are
approximately 240,654 kwh/yr and 88 kw respectively. These requirements are
expected to increase to 609,060 kwh/yr and 224 kw by the year 2001. Existing
heating energy requirements are 17,100 MBTU/yr. This requirement is expected
to increase to 32,000 MBTU/yr by the year 2001. Existing power generation
for the village is by one 250 kw, one 105 kw and one 50 kw diesel generators,
all owned by AVEC. The school district owns two standby diesel generators
which supply power to the school during AVEC outages. Also, one small
privately owned generator is operated in Kaltag. Most residential and a
portion of the commercial and public facility space heating is by woodstove.
The remainder of the village heating requirement is accomplished by the use
of fuel oil.
The lowest cost energy plan available to Kaltag consists of continued diesel
electric generation with the implementation of an increased conversion
efficiency system, waste heat recovery for the school buildings, heavy
Page 2
utilization of woodstoves and weatherization measures. All Plan components have been Proven and demonstrated in-an Alaskan village environment with the exception of the increased conversion efficiency component which would require pre-packaged load sharing and sequencing systems. The second lowest cost alternative is the base case plan of continued diesel electric generation with a continuation of the existing proportion of fuel oil and wood for Space heating purposes and none of the “lowest cost plan" improvements. A plan including development of a hydroelectric project on the south tributary
of the Kaltag River was considered, but found to be too expensive and dropped from further consideration.
The harvest and transportation of wood required for space heating could have
significant environmental impacts due to access trails and clear cutting.
Also, development of the hydroelectric projects could have significant
adverse environmental impacts. Community preferences at Kaltag include
hydroelectric power, weatherization of residential housing, energy education
and wood fired electric generation if hydroelectric is not feasible. One
resident suggested mechanization of wood transportation.
Savoonga - The existing electrical energy requirements and peak demand are
approximately 652,574 kwh/yr and 192 kw respectively. These requirements
are expected to increase to 1,516,831 kwh/yr and 444 kw by the year 2001.
Existing heating energy requirements are 34,100 MBTU/yr. This requirement
is expected to increase to 65,300 MBTU/yr by the year 2001. Existing power
generation for the village is by one 250 kw, one 300 kw and one 100 kw
diesel generators, all owned by AVEC. The Bureau of Indian Affairs owns two
standby diesel generators which provide power to the Bureau of Indian
Affairs and Bering Strait REAA schools during AVEC outages. Nearly all
village space heating is accomplished by the use of fuel oil. A few homes
are equipped with woodstoves which utilize the scarce amounts of driftwood
found on St. Lawrence Island.
The lowest cost energy plan available to Savoonga consists of continued
diesel electric generation with a 25% insertion of wind power, waste heat
recovery for the school buildings, heavy utilization of cdéal for space
heating and weatherization measures. All plan components have been proven
and demonstrated in an Alaskan village environment with the exception of the
increased conversion efficiency component and the wind energy conversion
systems. The increased conversion efficiency component would require pre-
packaged load sharing and sequencing systems. Wind generators show promise
as a future means of offsetting a portion of the villages electrical energy
requirements and may someday help to satisfy a portion of the space heating
requirement through resistive heating. However, wind generation systems
greater than 4 kw in size have not proven themselves as yet. Not one system
of the size deemed necessary to supply an economical portion of Savoonga's
overall electric energy requirements has been successfully installed in
Alaska. Two occurrences of coal have been identified on St. Lawrence Island.
One source is reported to be used for residential heating. No information
exists on the grade or tonnage of this coal, but if of inferior quality or
inadequate supply, the possibility of barging in coal from other localities
may be available. The second lowest cost plan consists of all the “lowest
(2D cost plan" components minus the wind energy conversion system and coal space heating. The highest cost alternative is the base case plan of continued . diesel electric generation with continued use of fuel oil for space heating and none of the “lowest cost plan" improvements.
Environmental impacts of the plans are expected to be minimal. The ex- traction of coal could have adverse impacts on fish, wildlife and vegeta-
tion. Emissions from coal heaters could be detrimental, however, due to the small size of the community and the continuous movement of air in the area
impacts should be minimal. Community preferences at Savoonga include
weatherization programs, wind power, energy education and development of
alternative heating fuels.
White Mountain - The existing electrical energy requirements and peak demand
are approximately 76,000 kwh/yr and 25 kw respectively. These requirements
are expected to increase to 137,790 kwh/yr and 45 kw by the year 2001.
Existing heating energy requirements are 8,200 MBTU/yr. This requirement is
expected to increase to 17,100 MBTU/yr by the year 2001. There are no
centralized power generating facilities in White Mountain. The Bering
Strait School District owns two 85 kw and one 35 kw diesel generators which
supply power to the school, health clinic and store. In addition, there are
six small gasoline generators which supply power to private residences and a
church. White Mountain will be electrified by the Bering Strait School
District power generation system this year. Most village space heating is
accomplished by the use of fuel oil. Some residences are equipped with
woodstoves, however.
The lowest cost energy plan available to White Mountain consists of diesel
electric generation with the implementation of an increased conversion
efficiency system, waste heat recovery for the school buildings, heavy
utilization of woodstoves and weatherization measures. This plan assumes
the community will be electrified by the school district as planned. All
plan components have been proven and demonstrated in an Alaskan village
environment with the exception of the increased conversion efficiency compo-
nent which would require pre-packaged load sharing and sequencing systems.
The second lowest cost alternative is the base case plan of continued diesel
electric generation from the school district generators with a continuation
of the existing proportion of fuel oil and wood for space heating purposes
and none of the "lowest cost plan" improvements. Development of a hydro-
electric project on Eagle Creek with maximum utilization of woodstoves and
weatherization measures was the highest cost plan and therefore dropped from
further consideration. The need for a wide pad crawler tractor for the
transportation of wood was also identified.
The harvest and transportation of wood required for space heating could have
significant environmental impacts due to access trails and clear cutting.
Also, development of a hydroelectric project on Eagle Creek could have
significant adverse environmental impacts. Community preferences at White
Mountain included completion of the electrification project by the school
district, implementation of a weatherization program, mechanization of the
current wood transportation system, implementation of a grant or low cost
loan program to assist in the purchase of woodstoves, and a higher degree of
energy efficiency in new homes.
SDD RECOMMENDATIONS:
It is the recommendation of the Power Authority that Elim, Kaltag and Savoonga continue to use diesel generation to satisfy their electric energy requirements and that White Mountain proceed with planned centralized diesel electrification of the community by the school district. A study should be conducted to determine the feasibility/final design of a waste heat recovery
system to supply heat to the school buildings in all four villages. At White Mountain, installation of the system should coincide with the scheduled
remodeling of the elementary school to reduce costs.
A demonstration project to determine the feasibility of increasing con-
version efficiencies of diesel electric generators utilizing load sharing
and sequencing systems as mentioned earlier, and perhaps other systems
suggested by different consultants, should be conducted. Such systems would
require pre-packaged load sharing and sequencing systems which are commer-
cially available from United States manufacturers, but are relatively complex
for village use and may have difficulties functioning in extreme temperature
variations. If proved feasible, a re-assessment of the technologies appli-
cation to each of the four villages should be made.
If the appropriate type and size of wind generator proves itself in the
Alaskan environment and becomes commercially available in the future,
feasibility studies should be conducted at Savoonga to determine if such
units would be a viable conservation measure to work in conjunction with the
diesel generators. Wind anemometers should be installed if the wind gener-
ators prove themselves feasible to further assess wind potential. Also, an
assessment should be made of coal resources on St. Lawrence Island for space
heating purposes and for potential coal fired binary cycle electrical power
generation. The assessment should be made in conjunction with a larger
regional study, if possible, and should address importation of coal in the
event local sources are inadequate.
A demonstration project to determine the feasibility of utilizing coal and
wood fired binary cycle electrical generation facilities should be conducted
at an optimal location within Alaska. The demonstration project should also
address co-generation for district heating. If determined feasible in the
Alaskan environment and the appropriate type and size of unit becomes com-
mercially available, site specific feasibility studies of using the binary
cycle systems in each of the four villages should be conducted.
The Power Authority also recommends conducting energy audits of all building
stock and the implementation of cost effective weatherization programs and
other conservation measures. Increased use of woodstoves should be encouraged
as part of this program in Elim, Kaltag and White Mountain. | The residents
of White Mountain should be provided a crawler tractor to aid in the harvest
of wood. The estimated costs of these various programs are summarized
below:
Page 5
Waste Heat Recovery Feasibility/
Village Name Final Design Study Energy Audits
Elim $ 15,000 $ 14,000 Kaltag 21,000 14,000
Savoonga 21,000 33,000
White Mountain 5,000 7,500
The estimated cost of the St. Lawrence Island coal resource assessment is
$100,000, the estimated cost of the crawler tractor to aid in the harvest
of wood at White Mountain is $120,000, the estimated cost of the increased
conversion efficiency demonstration project is $200,000, and the esti-
mated cost of the wood and coal fired binary cycle demonstration project is
$3,000,000.
J RY Lt
Eric P. Yould
Executive Director
Page 6
of ALASKA FUEMORAMOY 4G
ae
TO: TP Yould, Executive Director 71 Uwoe* Alaska Power Authority FILENO
TELEPHONE NO: ORT
MA: i { | ; SUBJECT: ag Ronald DO. Lehr, Director) ; A.(3) & -. otudy
Division of Budget and Management
Office of the Governor
FRO.
In accordance with AS44.83.179, Budget and Management has completed a review of a
reconnaissance study for Kaltag, Savoonga, White Mountain and Elim. We find that
the study complies with statutory requirements and provides justification for
captial expenditures to improve the energy utilization of each village.
An attached memo gives a more detailed review of the reconnaissance study.
ot ey SNIP ATEN EM ORAMOUK
C Tn ; DATE 10 Crete Yould, Executive Director i (ows
Alaska Power Authority FILENO.
{ TELEPHONE NO OR
fi f
2 SUBJECT: 2 *0™: Ronald D. Lehr, Directonl- it A. (3) er _. otudy
Division of Budget and Management
Office of the Governor
i,
In accordance with AS44.83.179, Budget and Management has completed a review of a
reconnaissance study for Kaltag, Savoonga, White Mountain and Elim. We find that
the study complies with statutory requirements and provides justification for
captial expenditures to improve the energy utilization of each village.
An attached memo gives a more detailed review of the reconnaissance study.
Ronald D. Lehr, Director September 2, 1981
Division of Budget and Management
Office of the Governor
George Matz, Program Analyst APA Reconnaissance Study
Division of Budget and Management
Office of the Governor
The Alaska Power Authority (APA) has submitted to Budget and Management a copy of Reconnaissance Study of Energy Requirements and Alternatives for Kaltag, __ Savoonga, White Mountain, Elim, and a letter of findings and recommendations. . According to AS44.83.179, Budget and Management is to review the reconnaissance study and determine its compliance with the requirements of AS44.83.177.
Funding for this reconnaissance study was provided by CH54/SLA80 which allocated
$50,000 to each village.
The reconnaissance study includes a detailed survey of all reasonable power
sources which are available to each community at this time. The economic merits
and the environmental impacts of each source of power are presented. The study
includes the present and projected electrical energy demand for each community
including net energy balance. A model was developed to project increases in
population and electrical consumption. Although there may not be a sufficient
data base to use such a model on a village basis, it may prove useful for rural
regional studies. The assumptions used to determine saturation rates, etc., were
reasonable. Residents of each community have had an opportunity to participate
in public meetings and several public agencies have provided comments.
The study is adequate and complete and approval is recommended. The APA
recommendations are consistent with the reconnaissance and are also endorsed.
One negative comment about the reconnaissance study concerns its' organization.
Information was often fragmented and frequently redundant. From a reviewers
standpoint, it would have been easier to have information presented on a village
by village basis. For instance the resource and technology assessment for a
village should be followed by its energy plan and its recommendations.
The reconnaissance study and the APA make recommendations for each village. It
should be noted that many of the projects being recommended are funded by
CH90/SLA81. Section 6 provides funding for power project feasibility studies,
preconstruction, design and engineering for a number of villages including Elim
and Kaltag. Section 28 provides $5,000,000 for the acquisition and installation
of two organic Rankine Cycle generators in Northwest Alaska. Section 31
allocates $170,000 to White Mountain for electrification. Section 42
appropriates $100,000 to the Department of Natural Resources for a coal resource
investigation on St. Lawrence Island where Savoonga is located. Section 48
Ronald D. Lehr, Director September 2, 1981
Division of Budget and Management
Office of the Governor
George Matz, Program Analyst APA Reconnaissance Study
Division of Budget and Management
Office of the Governor
The Alaska Power Authority (APA) has submitted to Budget and Management a copy of
Reconnaissance Study of Energy Requirements and Alternatives for Kaltag, Savoonga, White Mountain, Elim, and a letter of findings and recommendations. .
According to AS44.83.179, Budget and Management is to review the reconnaissance
study and determine its compliance with the requirements of AS44.83.177.
Funding for this reconnaissance study was provided by CH54/SLA80 which allocated
$50,000 to each village.
The reconnaissance study includes a detailed survey of all reasonable power
sources which are available to each community at this time. The economic merits
and the environmental impacts of each source of power are presented. The study
includes the present and projected electrical energy demand for each community
including net energy balance. A model was developed to project increases in
population and electrical consumption. Although there may not be a sufficient
data base to use such a model on a village basis, it may prove useful for rural
regional studies. The assumptions used to determine saturation rates, etc., were
reasonable. Residents of each community have had an opportunity to participate
in public meetings and several public agencies have provided comments.
The study is adequate and complete and approval is recommended. The APA
recommendations are consistent with the reconnaissance and are also endorsed.
One negative comment about the reconnaissance study concerns its' organization.
Information was often fragmented and frequently redundant. From a reviewers
standpoint, it would have been easier to have information presented on a village
by village basis. For instance the resource and technology assessment for a
village should be followed by its energy plan and its recommendations.
The reconnaissance study and the APA make recommendations for each village. It
should be noted that many of the projects being recommended are funded by
CH90/SLA81. Section 6 provides funding for power project feasibility studies,
preconstruction, design and engineering for a number of villages including Elim
and Kaltag. Section 28 provides $5,000,000 for the acquisition and installation
of two organic Rankine Cycle generators in Northwest Alaska. Section 31
allocates $170,000 to White Mountain for electrification. Section 42
appropriates $100,000 to the Department of Natural Resources for a coal resource
investigation on St. Lawrence Island where Savoonga is located. Section 48
appropriates $400,000 for a Bering Straits wind project for a number of villages
including White Mountain and Savoonga. Also, White idountian has previously
received $5,000 for a generator hook-up (Chp. 50/SLA80) and $50,000 for a
generator (Chp. 173/SLA80).
tone of the recommended projects would be subject to the project review process
(AS44.87.181 or AS44.83.183). However, if State funding is expected for project
construction budgetary approval is needed which generally requires similar
justification.
Ae OG
<< appropriates $400,009 for a Bering Straits wind project for a number of villages including White Mountain and Savoonga. Also, White ifountian has previously received $5,000 for a generator hook-up (Chp. 50/SLA80) and $50,000 for a generator (Chp. 173/SLA80).
None of the recommended projects would be subject to the project review process (AS44.87.181 or AS44.83.183). However, if State funding is expected for project construction budgetary approval is needed which generally requires similar justification.