DRAFT BOARD MEETING MINUTES
Wednesday, March 4, 2020
Anchorage, Alaska
1. CALL TO ORDER
ALASKA
ENERGY
AUTHORITY
Chair Pruhs called the meeting of the Alaska Energy Authority to order on March 4, 2020 at
10:02 a.m. A quorum was established.
2. ROLL CALL: BOARD MEMBERS
Members present: Chair Dana Pruhs (Public Member); Vice -Chair Bernie Karl (Public
Member); Julie Anderson (Commissioner DCCED); Anna MacKinnon (SOA-DOR), Albert
Fogle (Public Member); Bill Kendig (Public Member); and Julie Sande (Public Member).
3. ROLL CALL: STAFF, PUBLIC
Staff present: Curtis Thayer, Brenda Applegate, Kirk Warren, Tim Sandstrom, Linda Senn,
Amy Adler, Brandy M. Dixon, TW Patch, Bryan Carey, Karsten Rodvik, Alan Fetters, and
Ashton Doyle (AEA).
Others present: Ladonna Lindley (Accu-Type Depositions); Ceal Smith (ALICE); Elwood
Brehmer (Alaska Journal of Commerce); Tim Bradner (Alaska Legislative Digest); Chad
Stovall, Tom Wolf (Denali Commission); Stefan Saldanha (Department of Law); Steve Noble
(DOWL); Wescott Bott (HDR); Kerry Williams (Quadrigs); Melissa Heuer, and Mike Wood
(Susitna River Coalition).
4. AGENDA APPROVAL
MOTION: Mr. Kendig made a motion to approve the agenda as presented. Motion
seconded by Mr. Fogle.
The motion to approve the agenda as presented passed without objection.
5. PUBLIC COMMENTS
Mike Wood, President of the Board for the Susitna River Coalition, provided members a
document entitled Setting the Record Straight, which primarily responds to AEA's
presentation given in February to the Senate Community & Regional Affairs Committee. The
Susitna River Coalition has been active since 2010 in opposition to the Susitna hydro -electric
project. The Coalition has 14,000 members and works to maintain the accuracy of
information given to the public and to the Legislature.
813 West Northern Lights Boulevard, Anchorage, Alaska 99503 I P 907.771.3000 1 Toll Free 888.300.8534 1 F 907.771.3044 1 WWW.AKENERGYAUTHORITY.ORG
REDUCING THE COST OF ENERGY IN ALASKA
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 2 of 10
Mr. Wood informed the main focus of questionable misinformation is contained on Slides 14
and 15 of AEA's presentation. He inquired as to method for determining the cost of
approximately $50 million to reach the end of the license status.
Chair Pruhs explained the public comment period is for comments only. Any questions asked
will be answered by staff at a later time outside of this forum. Chair Pruhs expressed
appreciation to Mr. Wood for his appearance and travels from Talkeetna. Mr. Wood noted he
looks forward to working with members again, but hopes it will not be necessary. He
encouraged active consideration of the new hydro -technology available in the state. Mr.
Wood expressed he does not support going back in time with the Susitna hydro project. He
noted the past project manager, Wayne Dyok, and others indicated in 2015 it would take at
least $100 million to finish the last season of studies.
Mr. Wood outlined $220 million has been spent in the 1980's and $192 million has been
spent between 2010 and 2014. At least $100 million, if not more, is expected to be needed.
He explained FERC discussed the State needs to show a reasonable financial commitment to
restarting this project. Mr. Wood requested to be informed of any such movement by the
State and the explanation of the $50 million expected permitting costs.
Chair Pruhs directed staff to keep Mr. Wood informed as the cost of the permitting becomes
more defined. He communicated AEA values the organization and will continue to provide
information.
6. PRIOR MINUTES - January 15, 2020
MOTION: Mr. Kendig made a motion to approve the Minutes of January 15, 2020.
Motion seconded by Mr. Fogle.
The motion to approve the Minutes of January 15, 2020 passed without objection.
7. NEW BUSINESS
Presentation by Denali Commission on "Roadbelt Inter -tie"
Curtis Thayer, Executive Director, introduced Chad Stovall, Chief Operating Officer, and Tom
Wolf, Energy Program Manager, of the Denali Commission to discuss their presentation
entitled Road Belt Inter -Tie. Mr. Stovall expressed appreciation to AEA for their long-
standing partnership and collaboration. He noted it is a priority to Denali Commission to
support the mission of the State.
Mr. Wolf discussed the Denali Commission has funded a study to further develop the
feasibility of a conceptual electric power intertie route from Sutton to Glennallen to Tok to
Delta. The study is expected to be completed by the middle of June. The purpose and need is
to reduce the power cost for those rural communities along the roadbelt, to support regional
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 3 of 10
economic opportunities, to increase Department of Defense facility resilience, and to
increase electric reliability throughout the road system.
Mr. Wolf described the map of the current concept. The intertie would cover approximately
380 miles. The study will be conducted in one phase. Each of the communities in the project
area is electrified by its own diesel -powered microgrid and are paying higher costs. The
served population for the study line is approximately 3,000 people. Mr. Wolf discussed the
possible economic and natural resource development benefits, including renewable
resources, from less expensive electric power, including the specific benefits to the military.
Mr. Wolf explained the affected communities have been working for several years in
planning to move the project forward. It is a high priority in many comprehensive economic
development strategies, including Copper Valley, Ahtna Tribal, Tanana Chiefs, and Fairbanks
North Star Borough. In 2019, the Senate/House Joint Resolution 10 passed, which urged
congressional delegation to pursue development of the project. Denali Commission has
contracted with engineering firms to prepare the Roadbelt Intertie Reconnaissance Report,
which will address possible line corridors, mitigation areas, transmission planning,
renderings of typical installations, design and construction estimates, description of
anticipated environmental permit requirements, and qualitative cost/benefit analysis.
Public awareness presentations will be delivered during the study time. Public support is
high in the service areas.
Mr. Wolf informed discussions are occurring with AEA and AIDEA regarding the types of
support that can be provided, including technical assistance and reviews, economic analyses,
and financing and ownership plans. Development of an MOU will be drafted for approval by
AEA and AIDEA.
Vice -Chair Karl expressed support for the study, development, and partnering with Denali
Commission.
Chair Pruhs asked for Copper Valley Electric's response to the study. Mr. Wolf informed
Copper Valley Electric has provided resolutions in favor of the study. He noted Alaska Power
and Telephone, Golden Valley Electric, and Matanuska Electric Association have provided
support for the development of the project. Mr. Wolf discussed the possibilities of line
structure. Chair Pruhs encouraged the study to determine ways to keep costs of transmission
as low as possible and asked if a Transco could be utilized. Mr. Thayer agreed.
8. OLD BUSINESS
8A. Updated AEA Organization Chart
Mr. Thayer advised the organizational chart includes AEA, AIDEA, shared services, and
vacant positions. It is reviewed with the Board quarterly before it is provided to Juneau. He
discussed AEA, with the help of the Denali Commission, was able to hire a fourth circuit rider
position to assist in rural Alaska. It is possible funding from the Denali Commission could
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 4 of 10
provide a fifth circuit rider position. Mr. Thayer informed there have been no major electrical
emergencies this winter. He discussed the addition of TW Patch, Director Planning, and
described the work the planning group is conducting.
8B. Battle Creek Update
Mr. Thayer noted Battle Creek will also be discussed during executive session. He welcomed
Bryan Carey to provide the public update. Mr. Carey discussed the contractor has been
working through the winter at the site. The last concrete pour of the winter on the main wall
was conducted last week. The process of placing the rip -rap in front of and behind the wall
is ongoing. Afterward, the cofferdam will be removed. Additional snow will be cleared in
April and the HDPE fusing will begin in May.
Mr. Carey informed the contract value is within 1% of its initial value. He showed pictures of
the project. Mr. Carey described the technology used to monitor the temperature
requirements of the concrete pours and insulation. He discussed the logistics of bringing the
pipe to the site and the risks of damage in transit, as well as during installation. There are
quality control measures, and it is possible for damage to occur on the bottom of the pipe
that cannot be observed.
Mr. Carey explained the fusing will occur on the road alongside the ditch where the pipe will
be laid. Approximately 2,000 eco blocks and sufficient bedding will be used to line the pipe.
Mr. Carey informed he was onsite in October and is expected to return to the worksite in
early June. The construction administrator from the engineering firm is onsite at all times,
and additional personnel attend during the concrete pours.
Mr. Kendig reported he is a member of the MEA Board, which presents a conflict of interest.
He requested advice from Stefan Saldanha regarding his attendance in any portion of the
executive session. Mr. Saldanha informed the executive session does involve the Board in
which Mr. Kendig is a member. Mr. Kendig recused himself from the executive sessions.
MOTION: A motion was made by Ms. Sande to go into Executive Session to discuss
confidential financial information related to the Battle Creek diversion project. These
are matters, the immediate knowledge of which would clearly have an adverse effect
upon the finances of AEA. Motion seconded by Mr. Fogle.
The motion was approved without objection.
9. EXECUTIVE SESSION 10:46 a.m. - Discuss confidential matters related to
Bradley Lake, Battle Creek and the SQ Line.
The Board reconvened its regular meeting at 11:13 am. Chair Pruhs advised the Board did
not take any formal action on matters discussed while in executive session regarding Bradley
Lake and Battle Creek.
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 5 of 10
Chair Pruhs noted he will entertain a motion to go into executive session to discuss
confidential information related to the SQ Line.
MOTION: A motion was made by Mr. Kendig to go into Executive Session to discuss
confidential financial information related to Soldotna Quartz Creek Transmission
Line. These are matters, the immediate knowledge of which would clearly have an
adverse effect upon the finances of AEA. Motion seconded by Mr. Fogle.
The motion was approved without objection.
EXECUTIVE SESSION 11:14 a.m. - Discuss confidential matters related to the SQ Line.
The Board reconvened its regular meeting at 11:46 am. Chair Pruhs advised the Board did
not take any formal action on matters discussed while in executive session.
10. DIRECTOR COMMENTS
10A. Hydro Update
Mr. Thayer gave an update on the six current hydro projects. Bradley Lake is approximately
15 to 20 feet over its normal levels for this time of year. The utilities are trying to draw the
power to avoid spillage. The bonds for Bradley Lake get paid off July 1, 2021, which will
trigger effects for the $12.5 million dollars to ultimately return to the general fund for the
Railbelt Energy Fund. The funds are subject to appropriation by the Legislature and may not
be available until FY23 or FY24. Discussions will occur with utilities to develop a strategy for
moving forward regarding the bonds and to create a master plan for the Railbelt. Staff will
communicate the developments as they unfold.
Ms. MacKinnon requested additional information regarding the term in the Power Sales
Agreement. Mr. Saldanha explained the term in the Power Sales Agreement is linked to the
longest debt, which is the Battle Creek debt, July 1, 2050.
Mr. Thayer continued the hydro update discussing Hiilangaay. The project will begin
quarterly payments for their loan on April 1, 2020. He noted the status of Gunnuk Creek,
Thayer Creek, and Five Mile Creek are included in the handout.
1013. AEA Annual Report
Mr. Thayer informed the AEA Annual Report has been shared with the Board and provided
to the Governor and Legislature, by statute. He expressed appreciation to employees and
directors for their input of information.
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020 Page 6 of 10
10C. Rural Power Systems Inventory & Assessment
Mr. Thayer requested Tim Sandstrom, Director of Rural Programs, and Alan Fetters, Program
Manager, provide an update on the rural power systems inventory and assessment
requested by Board members. Mr. Sandstrom explained the inventory and assessment is
required by regulation to prioritize the assistance for power system upgrades. The
assessments are conducted on an interim basis. The last assessment was completed in 2012,
at a cost of $500,000. The current effort is underway, and is expected to cost approximately
$757,000.
Mr. Sandstrom advised new survey technology and a three-dimensional imaging system has
been introduced to eliminate the need for the high -cost interim inventory assessments. Mr.
Fetters described the new iterative process will enable the collection of more information on
a consistent and current basis, as staff or contractors visit communities. He highlighted the
equipment that is used, including the advanced capability of the camera. Mr. Fetters gave a
virtual tour of the Tuluksak plant utilizing the new technology. Additionally, a pilot of several
powerhouses has been conducted in preparation for the inventory and assessment. The full
breadth of the process takes approximately three hours to complete.
Mr. Fetters noted two of the three generators at Tuluksak are running. He is not fully aware
of the status and reason the third generator is dysfunctional. Questions would have to be
directed to the current project manager. Mr. Fetters assumes the third generator was
operated without oil because of its condition. He believes it will be replaced.
Vice -Chair Karl inquired if the waste heat is being captured yet. Mr. Thayer indicated the
waste heat has not yet been captured. Mr. Sandstrom informed the waste heat is too far away
from existing facilities for use. It has been stubbed out for possible use for a small shack
nearby. Waste heat affects PCE. Ms. Sande noted a larger conversation regarding waste heat
remains to be addressed. Commissioner Anderson informed the waste heat study is ongoing.
Mr. Kendig asked if Tuluksak has updated their PCE paperwork. Mr. Thayer indicated those
issues have been resolved. Tuluksak is a success story. He advised the Tuluksak School
District had a recent power outage and enlisted a contractor to make repairs.
Mr. Sandstrom reviewed the requirement is to provide a rank listing of prioritization of the
projects for the Rural Power System Upgrade projects. The information will also be used to
inform the maintenance and improvement projects list. A two-year to five-year plan is being
developed and will be presented to the Board at a later meeting.
Ms. Sande requested additional information regarding cost. Mr. Fetters informed the
competitive RFP was awarded to CRW Engineering. The total cost for 183 facilities was
$757,000, at a cost of $3,500 to $4,500 per survey.
Chair Pruhs commented for the record that he, Mr. Thayer, Vice -Chair Karl, and Mr.
Sandstrom visited Tuluksak less than six months ago. He reported on the three dead
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 7 of 10
generators inside the building and two or three dead generators outside the building.
Tuluksak had no money and no fuel in the tanks. The school district would not sell the
community power or fuel. The progress made from his visit until now is substantial. Chair
Pruhs agreed additional work is necessary, but he is highly encouraged by the response of
the community and the success of the program. He believes the success of Tuluksak can be a
model for other utilities.
Vice -Chair Karl echoed the comments by the Chair. He added his support for saving energy
using the waste heat from the boilers and the rejection heat from the radiators. He
complimented staff on their efforts and encouraged them to pursue a waste heat project to
continue to reduce the cost for the community.
Ms. MacKinnon inquired if staff is reviewing other programs that are deploying resources in
the same community to address the same issues. Mr. Sandstrom noted that discussion is a
good segue into the next agenda item.
101). Coast Guard Bulk Fuel Inspections
Mr. Sandstrom discussed the Coast Guard has increased their inspection effort for the
approximately 400 facilities outside of Southeast Alaska. Two hundred of the facilities were
inspected last year at a cost of about $700,000, and similar efforts will occur this year. AEA
intends to leverage the Coast Guard's effort to develop an inventory and assessment of bulk
fuel in coordination with DCRA, Denali Commission, and others.
Ms. MacKinnon asked if Tuluksak was inventoried by the Coast Guard. Mr. Sandstrom
clarified the distinction between the Coast Guard's purview of bulk fuel facilities and the
Tuluksak powerhouse that was reviewed previously. The Coast Guard did not inspect the
powerhouse facility. Ms. MacKinnon asked if the Coast Guard inspected the fuel tank in
Tuluksak. Mr. Fetters does not have that information with him, but the information is
accessible and he will provide it to Ms. MacKinnon. Mr. Fetters noted the Coast Guard is
primarily concerned with spill prevention and does not routinely inspect tanks. Ms.
MacKinnon commented the issue regards the multitude of financing structures deployed
from different state and federal sources into one community to provide energy. She noted
the amount of funds and resources deployed is unknown, and it is unknown how long the
deployment will remain operable for producing energy.
Ms. MacKinnon expressed the goal for all communities throughout Alaska is to have lower
cost of energy and investment. She noted some of the smaller communities have needed
additional assistance like maintenance and support, which was not provided. This is an
opportunity to bring together and braid the many resources available to support this
community and other communities with a safety net.
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
10E. 5.5 Mile Update
Page 8 of 10
Mr. Thayer advised negotiations are ongoing with MEA regarding a new 10-year right-of-
way lease agreement for transmission of power over AEA's 5.5 miles of line within the Healy
to Willow line.
10F. Tuluksak Update
Discussed in previous agenda items.
10G. PCE Report
Mr. Thayer advised the completed PCE Report is in the process of being submitted to the
Legislature. Mr. Patch stated he is available to answer questions. He informed preliminary
discussions have begun regarding scoping, funding, authorization and composition of a blue
ribbon panel, if requested by the Legislature or the Governor. Mr. Patch advised the PCE
program is expanding technology and is testing a developed electronic portal for the delivery
of information from the 196 PCE communities. Once successful testing and performance is
complete, specifically selected communities will be trained to utilize the portal. Additional
evaluation of the portal program will continue with the intent to gain confidence in the
program and to provide additional training sessions to another group of communities. The
hope is every community will be utilizing the portal program by the end of the year.
10H. Community Outreach Schedule
Mr. Thayer discussed the provided AEA community outreach efforts.
10I. Dashboard and Loan Report
Mr. Thayer reviewed the provided Dashboard and Loan Reports. There are currently 20
loans outstanding, with one delinquency. Included in the report is the Power Fund cash flow
forecast identifying the communities who hold loans. The information provided includes the
principal loan amount, committed date, payment schedule, and payment year. There are
several pending applications.
10J. Denali Commission Report
Mr. Thayer informed the total funding of the Denali Commission partnership is $26.5 million,
of which the total spending is approximately $19 million. The four circuit riders provided to
rural Alaska are paid for by the Denali Commission. The intent is to add a fifth circuit rider.
Circuit rider funds are annual.
Chair Pruhs inquired regarding the current Trump Administration attempting to delete the
Denali Commission. Mr. Thayer noted the Denali Commission has been in jeopardy of
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 9 of 10
deletion for the last three years. He noted Senator Murkowski is number three on the
Appropriations Committee and Mr. Thayer does not see the Denali Commission being
negatively affected. There is no contingency plan. The Denali Commission has a three-year
wind -down that is currently in the President's budget.
Chair Pruhs requested Mr. Thayer give a future presentation to the Board showing the Denali
Commission's funding and how it is used for operating and organizational funding. Mr.
Thayer agreed. He noted the Denali Commission awards are primarily capital funding.
10K. VW Settlement Update
Mr. Thayer provided an update on the VW settlement. AEA received $8.1 million, which has
been delineated to specific areas, including replacement of school diesel engines, public
transit bus replacement in Juneau, and electric vehicle charging infrastructure. The line item
of marine engines for $800,000 had little interest, and has been transferred to the school bus
replacement, which was originally underrepresented. AEA intends to complete the
competitive bid process for additional funding from the VW settlement.
10L. Articles of Interest
Mr. Thayer provided a list of articles of interest when AEA was mentioned in the news.
10M. Legislative Presentations
Mr. Thayer explained AEA's legislative presentations have been provided to members.
Follow-up questions by the Committee and response letters were also included.
Mr. Thayer informed the Regulatory Commission of Alaska (RCA) was previously scheduled
to give a presentation at today's meeting regarding their role in regulating utilities. Due to
recent merger activity, Chairman Robert Pickett requested to postpone the presentation
until the April 15, 2020 meeting.
Mr. Thayer expressed appreciation to the Board for their positive comments during his
evaluation. He acknowledged the areas where improvements can be made.
10N. Next Regularly Scheduled AEA Board Meeting Wed. April 15, 2020
The next scheduled AEA Board meeting is Wednesday, April 15, 2020.
11. BOARD COMMENTS
Ms. Sande expressed appreciation to Mr. Thayer and staff particularly for the community
outreach efforts and for their attendance at the Southeast Conference.
Alaska Energy Authority
Board Meeting Minutes
March 4, 2020
Page 10 of 10
Vice -Chair Karl expressed his support for additional focus on waste heat utilization. He
strives for excellence. He congratulated Mr. Thayer for his efforts and encouraged his firm
determination.
Chair Pruhs expressed appreciation to Mr. Thayer and staff. He welcomed Ms. MacKinnon to
the Board.
12. ADJOURNMENT
There being no further business of the Board, the AEA meeting adjourned at 12:29 p.m.
01
Q_/•�_ T4TF =
Curtis W. Thayer, Executive Director/Secretary r978
Alaska Energy Authority '