Loading...
HomeMy WebLinkAboutBradley Lake Hydro Plant Operators Report 3-30-2010Date: March 30", 2010 To: Bradley Lake Project Management Committee Bradiey Lake Hydro Piant Operators Report January thru March 2010 The plant is in good condition and is operating reliably. The lake level is currently 1135 ft and is steadily trending lower, but is still higher than the historical average. According to the snow reports, the snow water content this year is about 85% of the historical yearly average. The following is a report of the events and activities have occurred since the last BPMC meeting on December 29", 2009: Events / Emergent Issues Islanded operations due to transmission line repair work on the Kenai Peninsula. Units have responded properly with no problems. Work / Activities Performed Prepared and submitted FY2011 Budget. Performed snow clearing operations (snow plowing, sanding, etc.) We have had to spend a lot of time on snow clearing this month due to the blizzards in the Kachemak Bay area. We have received quite a bit of snow this month. Completed installation of the new station batteries and battery racks. Batteries are in service and supplying plant loads. Cathodic Protection system for the gate shafts has been commissioned and the engineer has visited the site for as-built drawings. Work Management software replacement — Received quotes from vendors. Reviewing software via web demos. Expect to make selection and start software conversion soon. Transmission Line Frost Jacking Repairs of structures 12-1 BS, 12-1 BD, 12-2 BS, 12-2 BD, 12-3 BS, and 12-3 BD are in progress and expected to be completed by the end of the week. The repairs have been performed without any outages. We have been received regular reports from the contractor. We inspected the project work on March 17". They have been able to add and drive additional piles to meet resistance criteria and some piles have been able to be driven to refusal. We are scheduled to perform an inspection of the project on Friday April 2m Document Control Project — The initial phase of the project is complete. We have implemented a new EDMS system and all Bradley Lake personnel have been trained. All of the current drawings have been converted to electronic format and loaded into our new EDMS system. The final phase of the project is to convert the manuals and load into EDMS. We estimate 3 months to complete. Following this phase, the project will be complete and we will shift to normal maintenance of the drawings and manuals. Duplex Modifications - RFPs have been sent out. Contractors have performed a visit to the project and bids are due in a week. Eagle Lake Communications Building —- Received additional quotes for hut removal and transport to Homer. The estimated cost was lowered to $3,000. We have been waiting for DNR permits for moving equipment across DNR land. DNR notified us last week that the land has been transferred to the borough and we expect to receive a permit to remove the hut soon. If the permit is received soon, we will be able to complete before thaw. Oil Storage Room Halon System replacement — Obtained quotes from vendors. Waiting on an additional quote. Transformer Containment Grating installation: most of the large rocks (approximately 3 inch) have been removed from all 3 containments in preparation for the grating installation. Finalized the design for the grating layout. Grating material is on-site, but additional grating is needed and will be procured. Expect completion of the work by June. Received new excavator and brush cutter, but the brush cutter is not cutting the alder brush properly. Continuing work with vendor to correct issues. — Safety Training - Operators completed Crane Operator and Rigging training. Training is scheduled for Confined Space Rescue and Fall Protection. Purchasing gas cylinders in lieu of renting cylinders. Purchased HP Nitrogen Cylinders, Oxygen, and Acetylene cylinders. This provides a cost savings potential of greater than $10,000 per year. Replaced fire protection water pressure control valve with new valve. Still having problems with the valve controlling pressure properly. Working with vendors to correct issues. Upcoming Activities Annual Maintenance Outage and Gate Testing. Runway Culvert Replacement project to bid. Expect to start work mid July. Complete configure gate house alarms to the plant annunciator and CEA SCADA. Replace Air Monitors in the Gate Houses. New monitors are have been upgraded to include Hydrogen Sulfide sensors. Awaiting arrival of cables. Order new small forklift. Order spare facilities transformer.