HomeMy WebLinkAboutBradley Lake Hydroelectric Project 01-17-2003Martin River Airstrip Access Road, Maintenance versus Removal
AERIAL PHOTOS OF MARTIN RIVER AIRSTRIP AND ACCESS ROAD
Kachemak Bay ¢ Aone Intersection with Bradley
Lake Dam Access Road
Battle Creek Bridge
Low Water Crossing
at end of Airstrip
Low Roadway Section
Battle Creek Slough Bridge
Low Water Crossing
Martin River Emergency Airstrip
Kachemak Bay
Old Gravel Borrow Area,
Now Unattended Fish
Ponds
Martin River Dike
Rev 01/17/03 Page 6 of 6 AEA
Martin River Airstrip Access Road, Maintenance versus Removal
Cost Considerations
A definitive cost comparison of a one-time effort to remove the road and airstrip versus
long term, annual maintenance costs (plus some cost for rehabilitation of the site
following failure of the dike) is of value in determining the best course of action. Costs
stated in the following paragraphs have not been definitively estimated but are based on
order-of-magnitude cost parameters.
The estimated cost to remove all the Martin River Access Road roadway embankment
and bridges is around $200,000 to $300,000 depending on the level of restoration
required along the road and at the bridges.
Removal of the Airstrip would not be necessary as the runway is literally a graded
gravel surface at the general elevation of the surrounding flood plain. Rendering the
runway “unusable” and formally closing it with appropriate “Closed Runway” signage
would cost in the range of $10,000 to $30,000.
Remedial work required to restore the Martin River road, low water crossings and
bridges to fully serviceable condition using construction materials available at the
project storage yard would cost in the range of $100,000 to $200,000 and an additional
$80,000 to $100,000 to replace decks and abutment timber walls at the two bridges.
Experience the past decade would indicate awards from injury and death settlements
related to aircraft crashes range form $250,000 to well over $1,000,000. This potential
liability should be considered when determining whether the Martin River Airstrip
Access Road and Airstrip are taken out of service.
The estimated costs above can be refined when a program scope is better defined.
Costs of mobilization and demobilization and equipment utilization by a contractor can
be spread over a number of the tasks noted above, resulting in a lesser cost for a
particular task.
Rev 01/17/03 Page 5 of 6 AEA
Martin River Airstrip Access Road, Maintenance versus Removal
e One time cost for removal and restoration will be large.
Pros-
e Following removal no additional burden on project staff to monitor and maintain
features.
e Environmental, safety and security liabilities eliminated.
Discussion of Alternatives
Restoring the Martin River Airstrip Access Road and Airstrip to fully serviceable
condition compliant with the FERC license for the Bradley Lake HEP requires remedial
work on bridges, low water crossings and the roadbed. The developing subsidence and
sinkholes in the roadbed of the Battle Creek Bridge approaches needs to be corrected
and the approaches regarded. In addition, the Battle Creek Bridge waterway approach
channel requires reconstruction of the guide dike on the left bank upstream side. The
remnant dike has lost nearly all of its material and the creek is eroding the road
embankment along the bridge approach.
The low water crossing in the Battle Creek flood plain and the low water crossing at the
east end of the airstrip need regarding and reconstruction to allow vehicle and
maintenance equipment access to the airstrip and to restore the eroded roadbed.
Battle Creek Slough Bridge is apparently in serviceable condition but the approaches
need sub-grade repairs and re-grading.
The Martin River Airstrip Access Road requires re-grading and some reconstruction in
the area where it traverses the tidal flat between Battle Creek and Battle Creek Slough.
This area has been damage by ice and the creek high flows resulting from the
November 2002 storms.
The Martin River Airstrip needs re-grading and brush and trees that encroach into the
aircraft operations safety area and safety surface along, and at each end of, the runway
need to be trimmed or removed to below the safety surface.
Signage indicating the airstrip is a restricted-use private airstrip needs to be installed at
the airstrip.
A security plan for the Martin River Airstrip and Access Road needs to be formalized
consistent with the recently mandated National Dam Safety Act.
Rev 01/17/03 Page 4 of 6 AEA
Martin River Airstrip Access Road, Maintenance versus Removal
Given the above concerns it is recommended that AEA evaluate the current status of
this project feature and make a decision as to whether it is in the Bradley Lake HEP’s
best interest to:
1.) Increase the maintenance and monitoring effort expended on this feature to
ensure it does not represent an environmental, safety or security liability for the
project, or,
2.) Abandon the feature and remove the roadway, bridges and airstrip. This would
require obtaining a license amendment prior to removing the road and airstrip.
Evaluation Factors
The listing presented below indicates the readily apparent pros and cons of retaining or
removing the Martin River access road and airstrip from the Bradley Lake HEP based
on subjective and qualitative factors presently known.
Retain the Martin River Road and Airstrip -
Cons-
e Un-maintained or poorly maintained road/airstrip are potential environmental and
safety liabilities. Cost of a single litigated loss in a small aircraft crash on the
airstrip could run to over one million dollars.
e Un-monitored airstrip is a potential security risk. A determined vandal could take
the project out of service for several days to weeks.
e Annual maintenance costs to maintain facility in environmentally compliant and
safe condition could be substantial.
e Eventual loss of these features is highly probable in the near future, with
associated costs (unknown) to clean up area following flooding of the Martin
River.
Pros-
e Airstrip remains available if case of an actual need for a secondary landing site
ever occurs.
e Noneed to file a second license amendment.
Removal of the Martin River Road and Airstrip -
Cons-
e Will require non-capacity amendment of project with associated (minimum) risk of
opening up project to regulatory scrutiny.
Rev 01/17/03 Page 3 of 6 AEA
Martin River Airstrip Access Road, Maintenance versus Removal
river to reclaim the flood plain in the delta that was isolated by constructing the
temporary dikes during construction of the Bradley Lake HEP.
Restoration of the Martin River Airstrip access road after Bradley Lake HEP
construction required submittal of an application for a non-capacity amendment to the
project license from the Federal Energy Regulatory Commission (FERC) as well as
permits from the U.S. Army Corps of Engineers (USACE) and the Alaska Department of
Fish and Game (ADF&G).
Concerns
There are several concerns related to the Martin River Airstrip Access Road and
Airstrip. The concerns include project license compliance, project facilities security,
liability related to unknown third parties for a variety of reasons, and project operation
and maintenance costs,.
The license-related concern is that since both the Martin River Road and Airstrip are
permitted and licensed components of the Bradley Lake HEP. It is AEA’s responsibility
to maintain both these features in good condition. Failure to do so could result in
citations from the FERC, USACE or ADF&G.
The security concern is related to the difficulty in monitoring the Martin River airstrip,
which is relatively remote and not visible from the power plant area. Small fixed wing or
rotary wing aircraft landing there are difficult to see unless a staff person is actually at
the airstrip or is driving by the area at the time the intruding aircraft is landing or taking
off. This clearly represents an un-controlled entry point to the project and a potential
security risk to the Bradley Lake HEP as a whole. The security risk ranges from
personal injury to persons attempting to access project facilities for various “innocent”
reasons to persons performing acts of vandalism with the intent to render the project
inoperable.
The third party liability concern is related to potential liability in the case of persons
injured or killed in unauthorized use of the airstrip. The airstrip is commonly used by
local hunters and guides even though the use is not authorized. This represents a
potential liability to AEA and HEA that could run to several million dollars in a legal
action should an unauthorized user of the airstrip be injured or killed when using the
airstrip.
Maintenance of the road and structures and airstrip in serviceable condition will be a
sustained annual cost if license compliance is maintained. Some years, major
maintenance or replacement will increase the cost and the question is “is it worth the
maintenance costs to keep this project feature when it has never been used by the
project’? There are practical alternatives available, such as using helicopter or boat
transport or simply delaying the departure and arrival of personnel undergoing shift
change.
Rev 01/17/03 Page 2 of 6 AEA
Bradley Lake Hydroelectric Project
Martin River Airstrip Access Road
Maintenance versus Removal
Background
The Martin River road was restored in 1996 in order to provide access to the Martin
River Airstrip and thus provide aircraft carrying project staff with an alternative landing
site, to be used in cases when weather conditions precluded safe landing and takeoff
from the primary airstrip. See Aerial Photos of the facilities in question at the end of this
document.
The Martin River Airstrip is located along the East side of the Martin River delta down
stream from the gravel borrow area used during the construction of the Bradley Lake
Hydroelectric Project (Bradley Lake HEP).
The gravel borrow area was temporarily diked-off from the river but the temporary dikes
were left in place after Project construction was completed to function as fish rearing
ponds in cooperation with ADF&G. This was an event of opportunity for ADF&G and
the department agreed at the time that there would be no liability for dike maintenance
or pond operation accruing to AEA and that when the dike finally is breached by the
river, it would not be reconstructed.
Water from the Martin River percolates through the dike into the ponds, flows through
the ponds and exits to the North across the access road at the East end of the airstrip.
The Martin River Airstrip Access Road has two bridges and two low-water crossings
and traverses the tidal flat/ Battle Creek flood plain to the East of the Airstrip. At times
the road is impassable due to flooding and/or high tide.
Existing Conditions
It is reported that since restoration of the Martin River road, the Airstrip has never been
used for the intended purpose. In the winter, the road is not maintained open due to a
lack of need for the airstrip in winter and due ice from tidal flooding. Maintenance of the
road has been a problem because of changing stream flow conditions related to
aggradation of the Martin River stream channel in the river delta/tidal flat adjacent to the
Martin River dike, which, when combined with the effects of high tides and ice
movement on the tidal flats along the course of this restored road results in flooding and
erosion of the roadway.
Specifically, the low water crossings, approved by the Federal Energy Regulatory
Commission (FERC) and the Alaska Department of Fish and Game (ADF&G), have
continually deteriorated since construction and granular material from the roadbed has
been eroded and carried onto the adjacent Kachemak Bay tidal flats. In addition, it
appears probable that continued aggradation of the streambed along the Martin River
dike, if left un-checked, will eventually result in breaching of the dike. This will allow the
Rev 01/17/03 Page | of 6 AEA