HomeMy WebLinkAboutBPMC Meeting January 18, 1990 3STONE & WEBSTER ENGINEERING CORPORATION 9”
a 800A STREET, SUITE 211, ANCHORAGE, ALASKA Pr o- 3-
ADDRESS ALL CORRESPONDENCE TO P.O. BOX 104479. ANCHORAGE, ALASKA 99510
apavai TELEPHONE 907-276-1583 iN NEW YORK TELECOPY 907-277-7092
CHERRY HILL. NJ. OENVER HOUSTON DALLAS PORTLANO. OREGON RICHLANO. WA WASHINGTON. 0.c.
Mr. D. R. Eberle January 17, 1990
Project Manager
Alaska Energy Authority J.O. No. 15800.55
701 East Tudor Rd. WP 25A
Anchorage, AK 99503 SWEC/AEA/2499
TRANSMISSION SYSTEM CAPABILITIES AND RELIABILITY
BRADLEY LAKE HYDROELECTRIC PROJECT
In association with the Bradley Lake Project, SWEC and PTI have
recently completed several studies involving, in part, the analysis
of the existing Kenai to Anchorage transmission systems. These
studies involved: (1) Kenai Export Limits, (2) Load Acceptance
Analysis and, (3) the ongoing Bradley Lake/Kenai Transmission
System Stability Analysis. Although none of these studies were
directed specifically at the question of the feasibility of a new
transmission line from Kenai to Anchorage, we believe»that»the
results of these studies strongly suggest that a_ second
AmDDERAABL Ee line from the goigotna.. substation to. the University
sation, (plan line being studied by the
, ™ S Qeiritie ustified. The primary erred of the new line
would be inngaad.reliability.g? servi pal Peninsula and
increased. power export capabilities fr aes o Anchorage.
As a result of performing the Kenai Export Limits study and other
studies we have determined that it is possible to improve the
stability of the existing system using stability aids. However,
this should not be construed to suggest that a more reliable system
will be obtained once the stability aids are installed. The
customary economic life for this type of transmission line is
between 30 and 40 years. Even though some of the existing line
conductors have been restrung, this is an "old" line. A 25 year
old single transmission line will still be the same line after the
stability aids are installed. The existing line will be stable,
but it will still be the cause of relatively frequent customer
outages. The number of customer outages can be expected to be over
12 annually.
With the existing line and a new line in service, there will be a
second line available to maintain the system interconnection if one
line trips. Thus there will be a reduction in the frequency of
separations of electrical service between Kenai and Anchorage. The
sar «stop yo) Nepsten - so 1989
new line will provide an improvement in the supply of reliable
power from Kenai to the Anchorage area, and reduce significantly the frequency and duration of Kenai electric customers outages.
It would take more study to determine the change in outage
duration, but the number of customer outages could be reduced: from
over 12 to less than one annually. PTI has advised that "a new
line would fix the long and unreliable Soldotna to University
line." This existing line has historically experienced outages
well above the traditionally accepted design criteria of one event
per 100 miles per year.
Current transmission planning practice is to determine the most
effective transmission upgrade, starting with the least costly
approach that meets stability criteria, then building on it or
considering other more costly alternatives until a balance is
reached between cost (equipment, O&M, losses) and reliability. The
recent SWEC/PTI studies have shown that with modern technology, low
cost stability aids can provide stable operation right up to (or
above) the transmission line thermal limits. Voltage problems, if
any, are similarly solvable. Our studies performed to date do not
quantitatively address the effect on reliability, the consequences
of increasing power transfers, and the associated losses. Even
though reliability issues were not studied, there are some obvious
benefits to improve the reliability of the interconnection between
Soldotna and Anchorage by the installation of a second transmission
line between Kenai and Anchorage. It is our understanding that
Decision Focus is studying the reliability aspect. We endorse that
this study is prudent and necessary.
If we can be of further assistance please advise.
N.A/ Bishop
Deputy Project Manager
NAB/JM
| 1889+ srofsrer +1989 A
BRADLEY LAKE PROJECT SYSTEM CHECKOUT & STARTUP SEQUENCE
wOleEs:
1. EVP.S - ELECTRICAL TEST PROCEDURES 2. MIPS - MECHANICAL TES PROCEDURES, 2. TIPS . WIS TRUMENT TEST
PROCEDURES 4. PTP'S - PREOPERA TIONAL ‘TEST PROCEDURES §. SIPS - STARTUP TEST PROCEQURES
eo /1 pit 3G SE:p t O6. 6B NOL P9SS SEZ 406 NOTLbxOdHOD “T31H EE 'd
1 , ) oa “4 ud
ot Tw) \ January 16, 1990
Bradley Lake Hydroelectric Project Gr
Proposed Start-Up and Testing Sequence
1991 May 1 * Sept. 1 **
Construction Pre-Operational Start-Up Testing System Operational Commercial
Testing Testin (Commissioning) Turnover Test Period Operations
(est. 8 weeks) (up to 60 days)
** No later than September 1, 1991 * No earlier than May 1, 1991
@ Contractor System @ CM/Contractor Power Scheduled
@ Engineer/Owner Owner/Utilities @ Units Operated on
Check-outs Verify Initial Perform Integrated Acceptance Testing and Dispatched on Commercial Basis
(meggering, flushing, Operation of System Operations Test Basis
etc.) Individual Plant (Turbine/Gen. Unit
Systems Testing, On-Line
Testing, etc.)
@ Operations by @ Operations by Operations by Operations by @ Operations by @ Operations by
Contractors Contractors Owner Under Owner/Utilities Owner/Utilities Owner/Utilities
Engineer's
Direction
Contractors Craft @ Final Acceptance @ Project Declared
Support on Stand- from Contractors Commercially
By Operational at End of Test Period
Intermittent On-Line Scheduled Commercial >
Test Power Test Power Power
Interim Power Project Power >
Sales Agreement Sales Agreement
Construction Period Warranty Period ¢ - 7 a (1-5 Years)
BRADLEY LAKE HYDROELECTRIC PROJECT
INTERIM POWER SALES AGREEMENT
Proposed Definitions
Operational Test Period: A planned functional test period following the
final acceptance testing and turn over of the project work from the
construction contractors to the owner, wherein project power would be
scheduled and dispatched on a test basis to verify and demonstrate that
the project is fully operational and capable of generating power on a
commercial basis. The operational test period shall begin no earlier
than May 1, 1991, and shall end after a period of 60 calendar days or on
September 1, 1991, whichever comes first. At the conclusion of the
operational test period, and provided the project is capable be
generating a minimum of 90 MW, the project shall be declared
commercially operational.
Interim Power Sales Period: The period prior to the commercial operation
date, wherein test power from the project may be available to the
purchasers on an intermittent, interruptable or scheduled basis.
9 eer a
Revised: January 11, 1990
J.0. No. 15800.52, WP22B
RISK ASSESSMENT EVALUATION
BRADLEY LAKE HYDROELECTRIC PROJECT
Ne Introduction —— Is eis -
The Energy Authority wishes to make a risk assessment evaluation for the
Bradley Lake Hydroelectric Project, which is scheduled for startup in
1991. This assessment is to be similar to that made by Stone & Webster for
five major electric systems (Solomon Gulch, Swan Lake, Terror Lake, Tyee
Lake and the Anchorage-Fairbanks Intertie) and is to provide the basic
information needed by the Energy Authority in order to include the Bradley
Lake Project in its overall risk management program.
Stone & Webster Engineering Corporation proposes to perform the work under
a separate Work Package for Task 22, Miscellaneous Engineering and Design
of our current Bradley Lake professional services contract. We would
utilize the services of Stone & Webster Management Consultants, Inc.
(SWMCI) for certain parts of the work. SWMCI took the lead in the 1988
risk assessment evaluation of the Energy Authority's five major electric
systems.
2. Objective
The Bradley Lake risk assessment evaluation will estimate the value, in
1991 dollars, of the losses from insurable risks that could be reasonably
expected over the 30 year life of the bonds issued for this project. The
risks will include a number of perils which are as follows:
Earthquake
Flood
Wind
Fire and Lighting
Other Perils - Natural
- All others
7845R/0349R/CM -1-
The results of the study are intended to be used by the Energy Authority,
its financial consultants and the State Division of Risk Management to
formulate the optimum overall risk management program.
a Approach
The approach for the Bradley Lake risk assessment will be similar to that
used by Stone & Webster for the Energy Authority's five major electric
systems..
The methodology for the Bradley Lake study will differ as listed below from
the previous study due to the project not yet being in operation and Stone
& Webster's intimate knowledge of the design basis:
he Site familiarization visits will not be required.
Project cost estimates rather than completion cost reports will be
used to develop repair or replacement estimates for damaged
structures and equipment.
Data obtained in the literature search for the major electric
systems evaluation will provide the data base needed for certain
parts of the Bradley Lake evaluation.
Property insurance evaluation would be done only if the Energy
Authority requires more analysis than was provided in Section 5.9
of the major electric systems risk assessment report.
Attachment A presents the study methodology in more detail.
4. Work Tasks
The work will be subdivided into four tasks as described below.
7845R/0349R/CM -2-
Task 1 - Engineering analysis
The analysis will estimate the direct annual property damage that could be
reasonably expected over the 30 year project bonding period resulting from
the following perils:
. Earthquake
° Flood
e Wind
e Fire
e Other perils as follows:
a. Natural: Ice, hail, subsidence, landslide, avalanche, snow, rain,
tsunami, volcanic eruption and lighting.
b. Man-made: Pollution, toppling, electrical overload, explosion,
sonic boom, chemical leakage, vibration, carelessness, vandalism,
sabotage and others.
The probability of occurrence of the various perils will be obtained from
design criteria or where necessary predicted for use in the risk assessment.
Task 2 - Risk Assessment
The risk assessment will use appropriate statistical methods to estimate
single-year losses from all perils. This calculation will be based on the
probability of occurrence of various categories of perils and the loss
expected from the occurrences, as determined by the engineering analysis.
Probable single-year losses will be totaled over the 30 year period,
present worthed, and levelized to produce a value that represents the
probable loss that could occur in any one year during the period. The
results will be presented in spread sheet format.
7845R/0349R/CM -3-
Task 3 - Draft Repo. ~.
A comprehensive risk assessment report will be provided setting forth our
findings and recommendations. The report will include an executive
summary, appendices of mathematical calculations and reference data.
Attachment B is the proposed outline. Eight copies of the Draft Report
will be provided for Energy Authority's review.
Task 4 - Final Report
The draft report will be revised to incorporate the Energy Authority's
comments. One reproducible original and 10 copies of the final report will
be provided.
5. Staffing
The proposed Bradley Lake Risk Assessment Study team consists of personnel
who worked on the Risk Assessment Evaluation of five major electric systems
prepared for the Energy Authority by Stone & Webster in March 1988 plus
members of the Bradley Lake design team. This combination of experience
will contribute to an efficient and cost effective study effort.
The work will be under the general responsibility of Ted Critikos, Bradley
Lake Project Manager. Norm Bishop would support requirements for technical
information on the project design. Jim Galambas, who led the five major
electric system risk assessment evaluation, is the proposed Study Manager.
He will be responsible for day-to-day oversight of the work. Other
principal contributors and their areas of responsibility are listed below.
Name Responsibility
*% Leslie A. Buttorff Statistical Analysis
we * Kenneth G. Laurence Engineering Analysis
we x Charles C. Clark Cost Estimates
yw Robert Joyet Geology and Seismicity
we = = John B. Yale Electrical and Controls
we James B. Nowak Mechanical and Fire Protection
% Robert L. Stinnett Structures
we Charles F. Giuliani Structures
* Major Power Systems Risk Assessment Team we Bradley Lake Design Team
7845R/0349R/CM =4—
The proposed organization is shown on Figure 1. As noted above, all of the
personnel have experience either on the Energy Authority's major electric
systems risk assessment or on the Bradley Lake Project.
6. Schedule
The Risk Assessment Evaluation can be completed within twelve weeks after
authorization, assuming an allowance of two weeks for review of the draft
report by the Energy Authority and discussion of comments. Figure 2 shows
the proposed schedule.
7845R/0349R/CM -5-
ATTACHMENT A
METHODOLOGY
The study methodology is designed to develop the value of the reasonably
expected annual losses expressed in 1991 dollars. These potential
disbursements estimated at low, likely, and high ranges will be based on
the results of the peril probability analyses and by the structural, .
civil, electrical and mechanical engineering analyses directed to assess
property damage loss to the Bradley Lake Project resulting from:
1. Earthquake
2. Flood and Tsunami
3. Wind
4. Fire and Lightning
5. Other Perils - Natural
- All Others
Analysis will be performed to estimate the total risk to the Energy
Authority. Losses will be expressed in 1991 dollars, escalated for each
year of the study and discounted to present value utilizing capital
budgeting techniques recommended and approved by the Energy Authority. The
results will be based upon probability theory and the best information
available at the time of the study. Notwithstanding the value of the
losses determined by this study, there is always the possibility that a
major event will occur sometime within the study period causing
catastrophic losses far in excess of those estimated on a probabilistic
basis in this study.
The step-by-step procedure used to accomplish the study objective is
outlined below and further elaborated in the following text.
1. Obtain project data (descriptions, background studies, design
criteria, drawings, maps) from SWEC files.
2. Identify all major structures, facilities and equipment, and relevant
perils.
7845R/0349R/CM -6-
3. Organize evaluation team effort and assign damage assessment
responsibilities.
4. Review project data.
5. Utilize evaluation data from the previous risk assessment of the
Energy Authority's five major electric systems for documented damage
incidents to hydroelectric facilities from natural and inherent perils
and loss statistics and documentation from fire and other perils using
power and insurance industry sources.
6. Review and tabulate design criteria for each structure.
7. Assign discrete ranges of peril magnitude and corresponding
probability to each structure under consideration.
8. Assess low, likely and high levels of damage for each range of peril
magnitude.
9. Estimate dollar cost of each damage level and corresponding downtime
for repair or replacement.
10. Tabulate peril magnitudes, probabilities, loss estimates and downtime
estimates for each structure.
11. Compute annual probable loss from each peril extended over the study
period and present worth to 1991 the low, likely and high loss.
The following paragraphs present greater details on the above study
procedure outline.
Data
The project data will be obtained largely from the Stone & Webster's files
and will consist mostly of site data, project specifications, drawings,
geotechnical studies, design criteria and Federal Energy Regulatory
Commission (FERC) License documents.
7845R/0349R/CM Fon
Identify Project Facilities
The major structures, facilities and equipment for the Bradley Project will
be listed and the perils to which the project would be susceptible will be
identified in a tabular form. Table 1 is an example of the type of
tabulation that will be developed.
TABLE 1
Facilities and Perils
Structure/ Subsi-
Facility/ Earth- Snow/ dence/
Equipment quake Flood Wind Fire Tsunami Avalanche Ice Landslide Other
Dam/Spillway
Power Intake
Power Tunnel
Penstock
Powerhouse
Machinery &
Equipment
Switchyard &
Equipment x x x x xX x
Transmission X
Line D4 OG OG OO OOS o > * Pe Damage Assessment
The assessment of the type and magnitude of damage to each structure will be
made by experienced engineers in the geotechnical, civil, structural,
electrical or mechanical disciplines, as appropriate.
The evaluation of peril magnitude/probabilities for earthquake, flood and
tsunami will be developed from the Bradley Lake background studies and design
criteria.
Other peril magnitude/probabilities will be obtained from published
meteorological data, utility forced outage/loss records and insurance industry
sources.
7845R/0349R/CM -8-
Document Review
The engineer responsible for damage assessment of each structure or peril
magnitude/probability evaluation will review the appropriate documents and
drawings to extract information pertinent to his portion of the work.
Evaluation Data
A literature search was previously carried out during the five major electric
systems risk assessment for documented incidents of damage or failure to dams,
powerhouses and associated facilities, their cause and the remedial action
taken to return them to service. Evaluation data resulting from this will be
used and the documents will be listed in a Bibliography.
Fire, lightning and all other perils are not amenable to the kind of
probability evaluation which will be applied to the natural perils.
Statistical loss data obtained from the literature and from direct contacts
with utilities and agencies during the five major electric system's risk
assessment will be used for evaluating these perils.
Design Criteria
Pertinent design criteria for the Bradley Lake Project will be collected and
summarized. The assumption will be made that all structures, facilities and
equipment have been designed and constructed to the specified criteria, and
that the design criteria were appropriately developed.
Design criteria reviews will be carried out for the purpose of identifying the
peril magnitudes which may be damage causing and to differentiate between
these and the threshold magnitudes actually used for design and for which it
is assumed no damage will occur.
In essence, this assessment will estimate the "residual risk" to the project
which has been defined by the United States Bureau of Reclamation (USBR) as -
"The risk of adverse consequences that remains after the design loading
conditions have been selected, appropriate designs prepared to accommodate the
loading conditions, and safety precautions established."
7845R/0349R/CM -9-
In addition, the ri 2ws will identify those poten 1 natural hazards for
which no design criteria are stated. The need to consider their effects in
the assessment will be evaluated and, if so, the magnitudes to be included
will be estimated.
Design Factors of Safety will be evaluated for applicability to threshold
peril magnitude values and for a range of loss values.
Damage Losses
The risk assessment will adopt a qualitative quasi-engineering approach as
distinct from the actuarial approach preferred and most often used by
insurance companies. The actuarial approach relies on historical loss data
from many events which have occurred and the law of large numbers to
evaluate the risk of future loss occurring from specific perils.
Unfortunately, we do not have the benefit of extensive historical,
documented natural peril loss data for hydroelectric facilities and must
utilize engineering judgment in estimating damage loss from perils which
have statistically determined probabilities of occurrence in given
magnitudes. The repair or replacement cost estimates used in this study
will be based on replacement "in kind" costs. The annual value of probable
loss is equivalent to the total area under the curve of damage cost versus
probability of occurrence for each peril considered. In this approach
probable annual loss estimates will be assessed by summing the incremental
damage which potentially could occur due to a series of discrete ranges of
peril magnitudes.
The total single year loss from all perils is obtained by summing the
individual peril loss totals. It is assumed that this estimated value of
total probable loss is for the entire study period, adjusted for forecasted
escalation of labor and materials. The present worth of the estimated
probable loss is then computed using an appropriate discount rate to
provide the cumulative 1991, present worth of losses that are levelized
over the study period so that an "average" loss number can be presented.
7845R/0349R/CM -10-
"Average" is in té.uws of a cost that represents tne repair or replacement
cost over the study period. A more detailed description of this
methodology will be presented in the Risk Assessment Section of the report.
7845R/0349R/CM -l1l1-
actachment B
REPORT CONTENTS
1.0 Executive Summary
1.1 Introduction
1.2 Engineering Analysis
1.3. Risk Assessment
1.4 Conclusions and Recommendations
2.0 Introduction
2.1 Background
2.2 Objectivity
2.3 Methodology
2.501 Data
3.2 Identify Project Facilities
-3.3 Damage Assessment
-3.4 Document Review
2
2
2
2.3.5 Literature Search
2.3.6 Other Perils
2.3.7 Design Criteria
2 -3.8 Damage Losses
3.0 Engineering Analysis
3.1 Overview
3.2 Earthquake
3.3 Flood
3.3.1 General
3.3.2 Tsunami Flood
3.3.3 Landslide Induced Wave in Bradley Lake
3.4 Wind
3.4.1 General
3.4.2 Transmission Line
3.5 Other Perils
3.5.1 Internal Failure
3.5.2 Snow/Avalanche
3.5.3 Subsidence, Landslide and Rockfall
3.5.4 Volcanic Eruption
7845R/0349R/CM -12-
Attachment B
REPORT CONTENTS
3.5.5 Ice
3.5.6 Fire and Lightning
3.6 Cost Estimates
4.0 Risk Assessment
4.1 Data Base
4.2 All Other Perils - Average Number of Occurrences
4.3 Fire and Lightning - Average Number of Occurrences
4.4 Insurance Observations
4.5 Loss Severity
4.6 Fire and Lightning - Losses
4.7 All Other Perils - Losses
4.8 Probability Analyses
4.8.1 Natural Perils
4.8.2 Fire, Lightning and AOP
4.9 Insurance Review
4.9.1 Property Insurance
4.9.2 Boiler and Machinery Insurance
4.9.3 Policy Gaps
5.0 Conclusions and Recommendations
5.1 Conclusions
5.2 Recommendations
Exhibits
Appendices
7845R/0349R/CM -13-
Figure 2
—WEEK
| Auth.
|
|
Pa tlo2to3to4testoetisrmt 8 9 tf wy wm tow dt
|
|
|
|
1. Engineering Analysis |
2. Risk Assessment |
3. Draft Report ee |
Report Review/Discussion See
4. Final Report (eee
Progress Report Kf x
SCHEDULE
RISK ASSESSMENT
BRADLEY LAKE HYDROELECTRIC PROJECT
8013R/CM
8013R/CM
| |
| Alaska Energy|
| Authority |
IEEE
|
|
WEEEEEULE |
| |
| Ted Critikos |
| Project Manager |
| |
|
|
EE Eee
| |
| James E. Galambas |
| Study Manager| HOSES ER EL
| | | PERE Eee
| |
| Leslie A. Buttorff |
| Statistical Analysis |
| | EEE | SE | |
| Kenneth G. Laurence |
| Engineering Analysis |
Figure 1
JE ECEEEEVEL EE LELEEE || EEE EEE EE
|
| | | | | | | es | | PECUEELUE EEEEEELEEEY | | nl | | | | | Charles C. Clark | | | M. Gene Yow | | John B. Yale | | | Cost Engineer | | | Geotechnical Engineer | | Electrical Engineer |
| eee eee) | eee EEE EEE LT EEE PEELE EEL | |
| |
PUEEEEEEEEE EEE EEE PE
|
| James B. Nowak
| Mechanical Engineer |
Eee
|
| Robert C. Stinnett |
| | Structural Engineer HEEEEEEE ELLER EELS |
PROPOSED ORGANIZATION
BRADLEY LAKE HYDROELECTRIC PROJECT
RISK ASSESSMENT
1001 FourTH AVENUE PLAZA (Szarirst Bipa.), SUITE 8200
SEATTLE, WASHINGTON 98154
(206) 623-471
1225 lorH STREET, N.W.
Lrinpsay, HART, NEIL & WEIGLER LAWYERS
SvuITE 1800
222 S.W. CoLuMBIA
PORTLAND, OREGON 97201-6618
TELEPHONE (503) 226-1101
TELECOPIER (503) 226-0079
TELEX 494-7032
JEFFERSON PLACE 350 N. 9TH, SUITE 400 BorseE, IDAHO 83702 (208) 3936-8844
345 CALIFORNIA STREET
Su1TE 200 SuirE 2200
WasutncrTon, D.C. 20036 San FRANCISCO, CALIFORNIA 94104
(202) 303-4460 (415) 984-5858 January 9, 1990
RECEIVED
VIA FEDERAL EXPRESS JAN 11 1990
a =
Brent Petrie
Alaska Energy Authority
P.O. Box 190869
Anchorage, Alaska 99519-0869
Dear Brent:
Here are the two documents we talked about. I will be
talking to Mike about how we wish to proceed with the budget
discussion at the BPMC meeting, etc.
Very truly yours,
(oe
Ronald L. Saxton
Encls.
cv |p a
Brea & Ze Ue RLS\der351. ltr
A, r Dor Cue
Pa vet ins (
G | DAC NON,
Alaska Energy Authority
MEMORANDUM
TO: Bradley Lake
aga Wie baw x a Vie ine
FROM: Bre s KAS vert
Alternate Secretary, PMC
DATE: January 3, 1990
SUBJECT: January 18, 1990 Meeting
Enclosed for your review is a copy of the draft agenda for the
January 18, 1990 meeting of the PMC. Please provide any
corrections or additions to Chairman Kelly. Also enclosed for
your review is a copy of the draft meeting minutes of the
November 30, 1989 meeting. The minutes will be considered at
the next meeting.
Enclosed for your record is a copy of the executed October 19,
1989 Project Management Committee meeting minutes.
Enclosures: as stated
i wee
Alaska Energy Authority
MEMORANDUM
TO: Bradley Lake
3 Sie, of ee
FROM: BYré ; yee “
Alternate Secretary, PMC
DATE: January 3, 1990
SUBJECT: January 18, 1990 Meeting
Enclosed for your review is a copy of the draft agenda for the
January 18, 1990 meeting of the PMC. Please provide any
corrections or additions to Chairman Kelly. Also enclosed for
your review is a copy of the draft meeting minutes of the
November 30, 1989 meeting. The minutes will be considered at
the next meeting.
Enclosed for your record is a copy of the executed October 19,
1989 Project Management Committee meeting minutes.
Enclosures: as stated
a January 3, 1990
* nN 10.
11
12.
13.
14,
15.
BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE
January 18,1990 AGENDA
Chugach Electric Association
Anchorage, Alaska
. CALL TO ORDER 9:00 a.m. Kelly
ROLL CALL
PUBLIC COMMENT
. MODIFICATION OF AGENDA
. APPROVAL OF MINUTES
November 30, 1989
BOND FINANCE TEAM REPORT Petrie
. TECHNICAL COORDINATING SUBCOMMITTEE REPORT Yerkes
INSURANCE SUBCOMMITTEE REPORT Saxton
BUDGET AND FINANCE SUBCOMMITTEE REPORT Saxton
Presentation of Standardized FY Budget Format Petrie
. OPERATING AND DISPATCH AGREEMENT SUBCOMMITTEE REPORT Shira
. REVIEW OF PROJECT STATUS Eberle
. OLD BUSINESS
Report on Surge Tank Analysis SWEC, PTI
. NEW BUSINESS
Schedule Next Meeting
Date, Location, Time
COMMUNICATIONS
. ADJOURNMENT
BPMC Minutes, November 30, 1989
page 1 of 8
BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE
NOVEMBER 30, 1989
MINUTES OF MEETING
1. CALL TO ORDER
Chairman Kelly called the Bradley Lake Project Management Committee Meeting
to order at 9:15 a.m. in the Training Room of Chugach Electric Association,
Anchorage.
2. ROLL CALL
The roll was called and a quorum established. In attendance were the
following representatives:
Alaska Energy Authority
Brent Petrie - Alternate
Chugach Electric Association
Tom Lovas - Alternate
City of Seward
None present.
Golden Valley Electric Association
Michael Kelly - Representative
Homer Electric Association
Kent Wick - Representative
Sam Matthews - Alternate
Matanuska Electric Association
Ken Ritchey - Representative
Myles Yerkes - Alternate
Municipal Light and Power
Thomas Stahr - Representative
John Cooley - Alternate
Others present:
Don Shira - Alaska Energy Authority
Dave Eberle - Alaska Energy Authority
Ron Saxton - PMC Utilities
Marcey Rawitscher - Alaska Energy Authority
Joe Griffith - Chugach Electric Association
Dan Bloomer - Chugach Electric Association
Denise Burger - Alaska Energy Authority
3. PUBLIC COMMENT
There being no public comment, Chairman Kelly continued on to agenda item 4.
BPMC Minutes, November 30, 1989
page 2 of 8
4. MODIFICATION OF AGENDA
Mr. Petrie requested an item, 8.d., Stone and Webster Errors and Omission
Insurance be added to the agenda. There being no objection, item 8.d. was
added to the agenda.
5. APPROVAL OF MINUTES
The minutes of the October 19, 1989 meeting were approved as written.
6. BOND FINANCE TEAM REPORT
Mr. Petrie reported that closure of the first bond issue was completed. Mr.
Petrie explained there is some question of possible tax liability (loss of
tax exemption) should the Bradley Lake Project become commercially
operational significantly earlier than originally anticipated (September
1991). Mr. Saxton and Ms. Rawitscher further defined the tax issue stating
that interest is capitalized up to October 1991 but cannot be capitalized
more than a short period of time after commercial operation begins without
exceeding the 5 percent limit for non-project costs and threatening the
entire transaction. An additional potential problem could also surface if
commercial operation began before July 1, 1991, in that the bond resolution
would require the final O&M budget to be in place a year earlier (April 1,
1990 rather than April 1, 1991.) Mssrs. Wick and Yerkes explained that the
SCADA process and Stability Problem may result in an extended test period,
which could delay commercial operation. Mr. Saxton suggested that the test
period be defined, which may require an arrangement between the utilities
and the Energy Authority. Mr. Griffith suggested discussions with the IRS
may be appropriate, however Mr. Petrie commented that such action was
premature. Mr. Petrie reiterated Mr. Saxton’s suggestion to establish a
definition for "test period" and address arrangements for the use of power
generated during the test period. Mr. Petrie further recommended that Bond
Counsel, Ron Saxton, Dave Eberle and the Technical Coordinating Subcommittee
(TCS) work together to formulate acceptable definitions and solutions to
present at the January PMC meeting. Mr. Eberle added it may be necessary to
redefine "commercial operation." After further discussion Chairman Kelly
summarized by stating the consensus was a preference to stay with the
current schedule, with commercial operation after July 1, 1991. Ms.
Rawitscher will also be consulting with the tax lawyer on 12/1/89 to
determine if it is possible to redefine interest dollars. Mr. Ritchey
suggested that the budget process might begin now to avoid a possible bind
later. Mr. Petrie commented that a dry run of the budget process has
already begun and, if necessary, could be nearing completion by the April
1990 date. Chairman Kelly stated that no action was required at this time
and further discussion on the issue should be included in the next PMC
meeting after additional information was available.
7. TECHNICAL COORDINATING SUBCOMMITTEE REPORT (TCS)
Mr. Yerkes stated that due to a delay by Power Technologies Inc. (PTI) on
the Surge Tank Analysis there is no information to report on this item. The
TCS is scheduled to meet December 14, 1989 and expects to review the draft
report at that time. Mr. Yerkes noted that there was a proposal to reduce
the amount of lining in the power tunnel, however upon review by the
BPMC Minutes, November 30, 1989
page 3 of 8
contractor, the savings were determined to be insignificant. (Further
discussion by Mr. Eberle under item 11.)
8. INSURANCE SUBCOMMITTEE REPORT
Mr. Saxton stated the Insurance Subcommittee was directing its emphasis
toward preparation of insurance alternatives for the dry run budget.
a. Report on Collective Business Interruption Insurance
Not addressed at this time.
b. Report on Pooled Insurance Coverage
Mr. Saxton commented steady progress was being made on the possibility
of pooling with the Four Dam Pool.
c. Risk Assessment
Mr. Petrie stated the Energy Authority was proceeding to use Stone &
Webster Engineering Corporation (SWEC) to update estimated damage
costs. After discussing the option and added expense (increased amount
of time as well as dollars) of hiring an independent consultant, Risk
Management agreed that SWEC could best make the required estimates for
the necessary “modified risk assessment." The contract does require
the retention of an independent consultant for this purpose after
project commercial operation begins. Other options for insurance were
discussed, Mr. Petrie noting the possibility of self insurance. There
being no objection, the PMC supported AEA’s approach to proceed with
finalizing a work order for SWEC to perform the task.
d. SWEC Errors and Omissions (E&0) Insurance
Mr. Petrie stated that E&0 insurance had become an issue the Energy
Authority felt should be presented to the PMC for consideration as it
would be classified a project cost. Mr. Eberle gave a brief history of
the attempts to attain E&O insurance beginning in 1985, stating it was
generally not obtainable at all until recently. Mr. Eberle described
the proposed coverage as $850,000 for a $10 million policy with
$500,000 deductible, pointing out that the deductible was per
occurrence and that any problem areas discovered to date would be
excluded from coverage. Mr. Eberle noted that given the advance stage
of construction, the proposed policy may not be worth the expense. Mr.
Eberle suggested self insurance might be an alternative option to
consider at this point. Mr. Saxton stated that funds could possibly be
made available for this purpose through the issue of additional bonds.
After further comments, Mr. Ritchey motioned, seconded by Mr. Stahr, to
approve the purchase of E&O insurance. Without further discussion, the
motion was defeated in a roll call vote, the vote being as follows:
Messrs. Ritchey, Kelly, Highers, Wick, Petrie, Lovas voting NO; Mr.
Stahr voting YES; City of Seward representative ABSENT.
BPMC Minutes, November 30, 1989
page 4 of 8
9. BUDGET AND FINANCE SUBCOMMITTEE REPORT
Mr. Saxton reported the committee has identified a detailed list of the
components and sources of the budget, however would like to continue working
on it before presenting it to the PMC. Mr. Saxton identified one item for
the PMC to consider; the benefit of handling the Chugach and Homer Electric
wheeling agreements by the PMC. Chairman Kelly commented there seemed to be
notable benefit to design these agreements under the umbrella of the PMC.
Mr. Lovas stated that Chugach Electric has already performed a substantial
amount of work in regard to the rates and scheduling and would not want to
relinquish it to the PMC, rather would prefer to use the PMC to review that
work. Mr. Saxton stated it was the committee's intention to finalize the
budget items and to present it to the PMC at the January meeting, beginning
the gathering of necessary information after that time.
10. OPERATING AND DISPATCH AGREEMENT SUBCOMMITTEE REPORT
Mr. Shira distributed copies of minutes for the November 1, 1989 meeting
held at the project site (attachment 1). An additional meeting was held
November 28, 1989. Mr. Shira stated the committee, working with Frank
Moolin & Associates (FMAA) is making good progress on discussions of
resolutions for several issues (detailed in the November 1, 1989 meeting
minutes.) Chairman Kelly requested continued reports on subcommittee
progress at future PMC meetings.
Mr. Petrie noted that the Operating and Dispatch Agreement Subcommittee has
had need for the services of a consultant. Mr. Petrie suggested that the
PMC consider allocating $100,000.00 under Section 31 Costs for continuing
consulting needs, as he felt it was to the benefit of the purchasers. Mr.
Lovas concurred that some further mechanism should be provided for the
committee to retain consultant services to alleviate the necessity for the
committee to request funds from the PMC for each task. Mr. Petrie offered
the service of AEA as a vehicle for the contracting, as a matter of
convenience to the utilities. Chairman Kelly expressed potential concerns
he had heard regarding the performance of the current consultant (FMAA).
Mr. Shira commented that, in general, FMAA was performing well and
recommended FMAA be allowed to continue. Mr. Wick motioned to extend the
contract with FMAA for an amount up to $25,000. An amendment offered by Mr.
Lovas to increase the amount to $100,000 died for lack of a second. The
original motion, having been seconded, passed by a unanimous roll call vote
of all those representatives present. Mr. Petrie requested clarification
for the source of these dollars, stating preference for Section 31 as
utility costs. After some discussion, it was concluded that until the
initial O&M agreement has been finalized, such costs should be project
costs.
Mr. Shira expressed his appreciation for the contribution that Marvin Riddle
of GVEA made toward developing the Technical Standards for the Four Dam
Pool, noting after the first of the year, work would begin on the Technical
Standards for Bradley Lake.
11. REVIEW OF PROJECT STATUS
Mr. Eberle reported that the project is about 61 percent complete overall.
\
BPMC Minutes, November 30, 1989
page 5 of 8
All tunneling is now complete with the exception of a 15 foot rock plug
which will remain in place until the tunnel is ready to be watered-up. The
hydrotest of the penstock and manifold is scheduled within the next few
days. Mr. Eberle explained the test would be performed to the extreme of
150 percent of working pressure, about 950 psi. Lining has begun in the
upper tunnel to be followed by the lower tunnel and vertical shaft this
winter. Mr. Eberle added that the powerhouse is enclosed and Unit 2 spiral
case for the turbine has been embedded in concrete. Two major shipments for
the Turbine/Generator Components are arriving this month. After earlier
shipping problems, Mr. Eberle stated Fuji is taking several measures to
insure the safe arrival of these shipments. Mr. Eberle suggested the PMC
schedule a meeting at the Project site later this winter or early next
spring to review the project status. In response to a question on the
progress of the transmission line, Mr. Eberle stated currently work is being
done on the foundations. Most of the pilings in the Fox River Valley have
been driven and the contractor is preparing to move onto the Caribou Lake
plateau.
Mr. Wick updated the PMC regarding HEA’s progress on their portion of the
transmission line. At present, HEA is working south from Bradley Junction
to Fritz Creek and has approximately one mile of poles in place on the
thirteen mile segment. Mr. Wick noted that mechanical problems with the
only helicopter of proper size available in the state may require that the
poles be hauled in overland. However, Mr. Wick still anticipates this work
will be done by Summer 1990.
Mr. Eberle referenced Mr. Yerkes earlier comment on the tunnel lining,
explaining the original design was for 100 percent tunnel lining. The
better than anticipated geology (rock quality) provided an opportunity to
consider deleting some of the liner in hopes of a significant ($2 to $3
million) financial savings. The contractor's estimated cost difference
however showed little or no savings due mostly to the added cost of ending
and restarting the sections of lining. Mr. Eberle stated the result of the
review was to continue with the original plan for full tunnel lining.
12. OLD BUSINESS
a. Report By Power Technologies, Inc. (PTI)
In reference to the PTI Surge Tank Analysis report previously mentioned
by Mr. Yerkes, Mr. Eberle added that he expects to receive the rough
draft by December 7, 1989. The TCS will review the draft report at
their December 14, 1989 meeting and completion of the final report is
anticipated by the next PMC meeting.
b. Report on the Four Dam Pool FERC Fee Appeal
Mr. Saxton noted that FERC has denied the request by the Alaska Energy
Authority and the Four Dam Pool utilities for exemption from annual
fees and a motion for reconsideration has been filed. FERC initially
denied the request stating that although the Energy Authority was not
earning a profit on the sale of the power, it felt the utility
companies were. Therefore, the utilities did not meet the required
non-profit standard. Mr. Saxton does not expect a positive result on
the motion and anticipates the Four Dam Pool to decide next year on
BPMC Minutes, November 30, 1989
page 6 of 8
whether or not to continue this process in court. Mr. Saxton noted
that if there is a judicial appeal, Bradley Lake may be requested to
(or desire to) participate in some way.
c. Review of Reimbursable Cost Items by Utilities from Grant Funds or
Bond Proceeds
Mr. Ritchey motioned that the list of utility costs prepared by Mr.
Saxton be released to all PMC members at this time. Mr. Wick seconded
the motion. Without discussion, all members present unanimously
approved the motion. Prior to passing out the prepared list, Mr.
Saxton noted that all costs reported were not entirely comparable. Mr.
Saxton reminded the PMC that the purpose for gathering together these
(Section 31) costs was to provide the utilities the opportunity for
reimbursement from the tax exempt bond proceeds. Mr. Saxton warned the
committee that there is current debate on whether there is sufficient
money to reimburse all expenses and recommended that as a group the PMC
decide which costs are appropriate. Mr. Saxton distributed copies of
the list of utility cost items titled "Unreimbursed Bradley Lake Costs,
Project Costs" and a second list titled "Section 31 Costs" (Attachment
2) explaining that there were substantial differences of dollar amounts
among the utilities. Mr. Saxton noted discrepancies in legal fees were
probably due to the amount of legal work each utility required. Mr.
Saxton also addressed discrepancies in the TCS cost amounts stating he
had received detailed billing from HEA and clarified their cost did not
include any staff labor. Responding to a question from Chairman Kelly,
Mr. Saxton stated the money for these reimbursements was coming out of
the second bond issue and this current review of the costs would help
determine how to size it. Again Mr. Saxton expressed doubt that all
Section 31 costs could be reimbursed. Ms. Rawitscher requested the
committee address the costs of issuance (items Al, A2, and A3 of
"Unreimbursed Bradley Lake Costs, Project Costs".) Mr. Petrie
motioned, seconded by Mr. Stahr, that the Committee approve the costs
of bond issuance, items Al, A2, and A3. Mr. Stahr verified ML&P legal
expenses (A2). Mr. Ritchey suggested that the actual cost of in-house
legal service be included in this item. There being no objection, the
motion passed unanimously by a roll call vote of all those
representatives present.
Mr. Saxton suggested further discussion of TCS cost items. Mr. Wick
clarified HEA’s TCS expenses stating that approximately $18,000 was
paid to Black & Veatch for studies on the impact of the Bradley Lake
project and approximately $8,000 was paid to Gilbert Commonwealth for
evaluation of stability problems. Mr. Wick stated those expenditures
were necessary to HEA because of its proximity to the project.
Chairman Kelly recommended item AS, TCS expenses, be included in the
previous motion approving items Al, A2, A3. There were no objections,
however discussion between Mr. Eberle and Mr. Matthews resulted in the
determination that the ($18,000) Black & Veatch cost was not a TCS
related expense, but rather an O&M cost. Mr. Petrie and Mr. Lovas
recommended that the original motion for approval be amended to exclude
the ($18,000) Black & Veatch cost. By consensus, the original motion
was made to read: Mr. Petrie motioned, seconded by Mr. Stahr, that
the committee approve the costs of bond issuance, items Al, A2, A3 and
BPMC Minutes, November 30, 1989
page 7 of 8
Ms.
the TCS costs, item A5 (having been determined to exclude the Black &
Veatch cost.) Further discussion by committee members resulted in the
reclassification of HEA’s Black & Veatch cost as a Section 31 cost.
Chairman Kelly noted, as a general guideline, future studies to be
considered for reimbursement should be approved by the PMC in advance.
There was no objection.
Section 31 Costs
Mr. Stahr motioned, seconded by Mr. Lovas, that the Section 31 costs be
approved (as adjusted to include the $18,864.29 HEA Black & Veatch cost
previously removed from item A5 of Project Costs.) Concern was
expressed by Mr. Ritchey about the negotiation costs. Mr. Saxton
stated that 97 percent to 99 percent of the listed amounts were actual
attorney fees. Mr. Lovas requested that CEA'’s footnoted cost of
$22,700 (in-house attorney fees) be included as part of item Bl,
Negotiation Costs. There being no objection or further discussion, the
motion was passed unanimously by a roll call vote of all those
representatives present. Mr. Petrie requested the Chairman provide a
letter to the Energy Authority clarifying the revised numbers for
"Section 31 Costs" and "Unreimbursed Bradley Lake Costs, Project
Costs."
d. Reconsideration of DFI Surge Tank and Intertie Study Costs
Mr. Petrie distributed a letter stating the Energy Authority's position
after further review of these two items (attachment 3). Mr. Petrie
stated the Energy Authority was now agreeable to include the DFI Surge
Tank Study (for $10,000) as a project cost. The motion to include the
DFI Surge Tank Study was made by Mr. Petrie and having been seconded,
passed by a unanimous roll call vote of all those representatives
present. It was determined that ARECA should be reimbursed $10,000 for
the DFI Surge Tank Study.
Rawitscher requested clarification regarding the source of the
compensation amount of $600,000 to HEA for the Fritz Creek - Soldotna
Transmission Line. Chairman Kelly recommended a review of past meeting
minutes to clarify how that cost was intended to be handled.
13. NEW BUSINESS
a. Contingency Plan for early Bradley on-line
b. Disposition of Bradley Test Power
Chairman Kelly noted that these items had been discussed earlier
(reference item 6, Bond Finance Team Report.) Mr. Saxton stated his
understanding was that the project would not be going on line (as
commercially operable) before July 1991. Mr. Eberle added that in the
most optimistic scenario, the earliest the project could produce 90
mega watts would be April or May of 1991, however the test period could
extend to July 1991.
BPMC Minutes, November 30, 1989
page 8 of 8
14.
c. Benefits of Coordinated Dispatch
Chairman Kelly stated a meeting had taken place between Mr. Brooks,
Dr. LeResche, and the railbelt managers at Chugach’s office. The goal
being to obtain money through the legislature from the Railbelt Energy
Fund, it was determined to send a memorandum of understanding between
the Energy Authority and utilities to work toward coordinated dispatch
to optimize savings. In addition, it was decided an effort should be
made to assure the legislature that this was a one time request for
funds. Chairman Kelly stated a third concept discussed was a 2 mil
usage toll on the line to produce a repayment stream to the Energy
Authority. Mr. Lovas noted that CEA had agreed to prepare the frame
work of a wheeling agreement, extension intertie agreement at that
meeting. Currently, this work is in the initial draft stage.
d. Schedule Next Meeting
The next meeting was scheduled for Wednesday, January 17, 1990,
9:00 a.m. in the training room at Chugach Electric.
COMMUNICATIONS
There being no communications or further comments at this time, Chairman
Kelly continued to item 15.
15. ADJOURNMENT
All business before the committee being complete, the meeting adjourned at
11:51 a.m.
Chairman Kelly
Attest:
Alaska Energy Authority, Secretary
Approved at BPMC meeting held , 1990
ATTACHMENT #1
BRADLEY LAKE OPERATION AND DISPATCH COMMITTEE
Meeting Minutes
November 1, 1989
A meeting was held November 1 at the Bradley Lake Hydroelectric Project to visit the
site and to further discuss the Bradley Lake Allocation and Scheduling Agreement.
Present at the meeting were:
Don Shira (chairman) - AEA
John Cooley - AML&P
Dave Fair - CEA
Doug Hall - AML&P
Mike Hubbard - FMAA
Afzal Kahn - AEA
Jerry Mackey - CEA
Sam Matthews - HEA
Marvin Riddle - GVEA
John Zidalis - AEA
After the site visit was completed, the agreement was discussed. Mike Hubbard gave
a quick overview of the agreement that was distributed October 6.
Dave Fair stated that CEA's legal department had reviewed the draft and had
numerous comments. While he recognized that the agreement was not ready for this
type of review, he was concerned by one of Eric Redman's comments that the
concepts of rule curves and base energy content curves may be in conflict with the
Power Sales Agreement. Dave had not talked to Eric, so he did not know what the
exact problem, if any, was. No one else at the meeting understood the concern either,
and Dave said he would try and get more details.
Everyone recognized that the agreement will need to be reviewed by the attorneys; but
in the interest of getting things down on paper, the following was agreed to:
+ The parties to the agreement should be those of the Power Sales Agreement.
* CEA will be scheduling MEA and SES Bradley output, and this should be set
forth in the agreement. It was felt that there should be just one rule curve and
one energy content curve for all three utilities unless the three utilities agree
otherwise.
* In the event that a conflict between the Scheduling Agreement and other
agreements arises, the language in the other agreements should prevail.
¢ Language on the ability for two or more utilities to coordinate their take of
Bradley power should be deleted as it was felt that the language could be
confusing. Deletion of the language will not negate any rights of transfer, but
will require that a utility laying off its Bradley power still participate fully in the
regulation studies and scheduling process.
* The requirement that each utility must take its monthly firm energy established during the regulation study was felt to be too restrictive. After some discussion, it was decided that the requirement should be on an annual basis.
+ Project spill due to transmission limitations should be treated as in the Services Agreement.
* During the course of operation, there will be periods of time when some utilities do not want to schedule any Bradley power. The available power
could then be utilized by the other utilities as long as their available water is
greater than their Energy Content Curve. If there is a conflict for the available
excess Capacity, it will be prorated on a Project Percentage Share basis.
+ Losses over HEA's system were discussed. The PTI studies will be
investigated to determine if a loss factor can be utilized that will reflect actual
conditions. The PTI load studies should be on a monthly basis, with and
without Bradley Lake, and include the second line from Bradley Lake. The
consensus of the group was to try and utilize a single loss factor instead of
reading meters, etc.
* Spinning reserves still need to be addressed in the agreement, but the issue
was deferred until efficiency curves and other data was available.
Frank Moolin's budget was also discussed. The bulk of the original budget was for
Don Gregg's services and that amount for Frank Moolin was for the development of the
initial draft. Don Shira indicated that Mike Hubbard had submitted a new budget for
continued services through June 1990. Mike told the group that he saw his effort to be
fairly concentrated at first but would taper off as the agreement got to the stage where
the attorneys worked on it. During that stage, he saw his role as somewhat of a liaison
between the technical and legal arenas. He also indicated that there had to be some
flexibility on the budget as it was dependent on the length of time all parties could come to an agreement.
The utility representatives instructed Don Shira to augment Frank Moolin's budget for
the month of November, and the full PMC would take up the long-term budget and
source of funding at their next meeting.
Mike Hubbard will get the next draft out within a couple weeks; and the next meeting
was scheduled for 9:30 a.m., November 28, at AEA.
The meeting adjourned at 3:30 p.m.
LL aM.
Donald L. Shira, Chairman
Anchorage Municipal Light &
Power
1200 East 1st Avenue
Anchorage, Alaska 99501
—, Dear Mr. Gootey: Sohn
After our meeting on November 1, 1989 at Bradley Lake, Chugach has
expressed some concerns that we are getting ahead of ourselves in the drafting of contract language. Consequently, they have requested that our meeting on November 28, 1969 be devoted to discussing the basic issues to be developed in a contract. Accordingly, Mike Hubbami. dee
developed the attached paper which identifies and discusses sc
these issues.
If you have any questions or comments, please do not hesitate
at 261-7261. 1 look forward to meeting with you on November 2
$1 ty.
j oor
Donald L. Shira, Directer Facilities Operations & Engineering
DASi@e
J
7038/1018(1)
DISTRIBUTION LIST
November 13, 1989
7038/1018
Mr. John Cooley
Anchorage Municipal Light &
Power
1200 East lst Avenue
Anchorage, Alaska 99501
Mr. Dave Fair
Chugach Electric Association, Inc.
P.0. Box 196300
Anchorage, Alaska 99519-6300
Mr. Mike Hubbard
Frank Moolin and Associates
P.O. Box 7044
Anchorage, Alaska 99501
Mr. Saii Mathews
Homer Electric Association, Inc.
3977 Lake Street
Homer, Alaska 99603
Mr. Marvin Riddle
Golden Valley Electric
Association, Inc.
P.O. Box 1249
Fairbanks, Alaska 99707
BRADLEY LAKE HYDROELECTRIC PROJECT
SCHEDULING AND ALLOCATION AGREEMENT
MAJOR ISSUES
RULE CURVE/OPERATING CURVE
The rule curve and operating curve provide the basis of reservoir management. The rule
curve provides assurance that an amount of firm energy can be provided each year
during a period of time with runoff conditions similar to those of the critical period. In
a multi-year critical period, the reservoir would neither drain or completely refill at
the end of the first year.
oe The operating curve is based on providing firm energy but attempts to attain a full
reservoir at the end of the water year (September 30). It is usually the rule curve in
the early part of the water year but is updated as runoff conditions are known with more
certainty. The revised operating curve may be above or below the rule curve depending
on runoff conditions. In addition to providing a guide for reservoir refill, it also helps to
lessen the chance of spill (and therefore provide secondary generation).
ISSUE - Should such curves be established and used, or should each utility be allowed to
draw its share of water as it sees fit?
ADVANCE ENERGY
Even if operating curves are utilized, a utility may want to schedule energy that would
take it below its operating/rule curve. This deficit could be paid back over any one of
numerous time periods.
ISSUE - Should a utility be allowed to schedule and take advance energy? If so, over
what time period should it be paid back and should there be a maximum deficit?
DEFICIT CURTAILMENTS
Even if advance energy is not allowed, actual operations may result in deficits.
ISSUE - In the event that deficits occur, to what extent should operations be curtailed
during the following accounting period?
SUBMISSION OF LOADS/COORDINATION OF MAINTENANCE
The Regulation Study that establishes firm energy amounts, the rule curve and the
operating curve is based in part on power requirements submitted by the utilities.
Since the most beneficial use of Bradley Lake will come from coordinating thermal
maintenance, the power requirements should be net of some level of expected thermal
generation. If too much thermal generation is subtracted, initial simulation runs may
show spill, and the optimization process may be lengthy. :
ISSUE - What process will minimize the effects on everyone's behalf yet still develop
credible results?
RESERVES/MINIMUM SCHEDULING
During the course of operations, Bradley Lake will undoubtedly be utilized for spinning
reserves. However, this may require the operation of two units when one would
otherwise suffice.
ISSUE - Shall the use of Bradley Lake for spinning reserves be curtailed in any way or
should some sort of compensation for any efficiencies be required?
HEAD LOSS/EFFICIENCIES
As the reservoir elevation is drawn down, generation efficiency decreases. Therefore a
utility scheduling generation during periods of high reservoir elevation will obtain more
energy per unit of water than a utility scheduling during low reservoir conditions.
ISSUE - Should those participants scheduling power during high reservoir conditions be
required to compensate the participants scheduling power during low reservoir
conditions?
LOSSES ON HOMER TRANSMISSION
ISSUE - Shall losses over HEA's transmission system be metered or shall a factor (or set
of factors) be utilized? What loss factor shall apply to the Bradley - Bradley
Junction portion?
ATTACHMENT #2
UNREIMBURSED BRADLEY LAKE costs!
AS OF NOVEMBER, 19897
PROJECT COSTS?
CATEGORY CHUGACH GVEA AEG&T HOMER MEA ML&P aos | __ $$} S E
Al
FINANCE TEAM
ACTIVITIES 0.00 1,396.00 0.00 0.00 0.00 2,057.00 3,453.00
A2
BPMC LEGAL AND
FINANCE 16,172.80 8,990.80 13,725.60 a=) Ses 13,778.80 532.00 53,200.00
aS
1989 UTILITY a
OPINION LETTERS >
OUTSIDE 7,174.01 4,879.00 2,016.65 1,331.84 8,114.00 11,216.05 2,449.50 37,181.05
ms 8 PTI STUDY
AS
tcc
EXPENSES? 0.00 7,629.00 0.00 40,376.87 3,018.00 411.00 51,434.87
A6
INSURAN'
STUDI zs
a7
STABILITY
rl
einvile STUDY
ag DFI SURGE ,, TANK STUDY
A10 OFI IWJERTIE
sry
22,894.80 15,742.25 41,708.71 11,132.00 24,994.85 5,449.50 | 145,268.92 UTILITY TOTAL
EGW\egw082.doc
1. Only unreimbursed costs are included in this chart. The utilities were instructed not to include those
amounts for which they have received reimbursement.
2. The utilities were contacted October 27, 1989 for their final revisions to the chart. Chugach and GVEA
responded 11/1, Seward 11/2, Homer and AEG&T 11/14. MEA confirmed in early November that they were still
sorting their data. ML&P was contacted by phone on several occasions. The data presented here was given
from Claudette Petty, ML&P accountant, and has not been verified by Tom Stahr.
3. These items are treated as "Project" costs, eligible for 50% grant funds.
4. ALL travel and associated costs for members of the Finance Team for all financing trips and meetings.
5. All legal fees and costs for work on finance activities. Includes legal representation through bond
sale and preparation of opinion letter for BPMC.
6. ALL legal fees and costs associated with each utility's 1989 opinion of counsel.
7. Chugach has also paid approximately $2,419.20 to $4,200 in “in-house” attorney fees for the preparation
of the opinion letter.
8. Final figures not yet available.
9. All travel and other costs associated with meetings of the Technical Coordinating Committee.
10. Studies yet to be completed. Final amount to be forecasted.
11. Final figures not available.
12. Final figures not available.
13. Final figures not available.
14. Final figures not available.
EGW\egw082.doc
SECTION 31 COSTS 4
r TT eT LL a 1 CATEGORY CHUGACH GVEA AEG&T HOMER MEA ML&P SEWARD TOTAL
— ——— $$$
B1
NEGOTIATION
costs’ 3
OUTSIDE 285,643.71 391,876.25 0.00 64,535.62 63,097.00} 194,469.00 {11,672.50 |1,011,294.08
B2
BPMC 4
ORGANIZATION 49,131.26 27,313.10 41,696.93 — a 41,858.55 1,616.16 161,616.00
B3
BPMC FUTURE
COSTS
6 SMITH BARNEY 16,382.52 9,107.39 13,903.58 — —- 13,957.46 538.89 53,889.84
fa
Utility Total | 351,157.49 428,296.74 55,600.51 64,535.62 63,097.00 250,285.01 13,827.55 | 1,226, 799.92
nd a es j
\section 31 costs paid from bond proceeds, but not eligible for 50% grant contribution.
2
approval of the Power Sales Agreement, Chugach Services Agreement and Homer Transmission Agreement.
3, ‘Chugach paid approximately $22,700.16 to $39,410.00 for “in-house” attorney fees during the
negotiation process.
‘ALL costs including legal fees associated with individual utilities negotiating, amending or obtaining
4epmc costs (including legal costs) for organizing the Committee and conducting Committee meetings and
general business.
510 be determined by the Utility Participants and AEA.
Scosts associated with the Smith Barney review of financing activities.
EGW\egw082.doc
ATTACHMENT #3
State of Alaska N Steve Cowper. Governor
Alaska Energy Authority
A Public Corporation
November 30, 1989
Mr. Michael P. Kelly
Chairman, Bradley Lake
Project Management Committee
Golden Valley Electric Association
P.O. Box 1249
Fairbanks, AK 99707
Subject: Reconsideration of DFI Surge Tank
and DFI Intertie Study Costs
Dear Mike:
The October 19, 1989 Bradley Lake Project Management Committee (BPMC)
considered two actions to categorize certain costs incurred by Decision
Focus, Inc. (DFI) for “Surge Tank Analysis" and "Intertie Study Costs"
(see pages 7-8 of draft BPMC 10/19/89 minutes) as project costs. The
Energy Authority vetoed each action by noting no to each proposal, but
was asked to reconsider and respond at the next BPMC meeting.
Upon reconsideration of the costs of the DFI "Surge Tank Analysis" of
$10,000, we would not object to their inclusion as project costs, since
the analysis deals with spinning reserve benefits which were substan-
tially directed at operating parameters of Bradley Lake. The study
suggested possible benefits that might be realized by varied needle
valve opening and closing times on the project turbines.
We will not approve DFI Intertie Study as a project cost as the study
deals with technical and economic issues substantially beyond the scope
of the Bradley Lake Hydroelectric Project, namely a new transmission
line between Anchorage and the Kenai Peninsula and a new transmission
line between Healy and Fairbanks and the utilization of virtually all
existing Railbelt generation resources. The feasibility of these
projects depend on dispatch, fuel costs, reliability, and stability of
numerous components in the Railbelt energy supply system beyond Bradley
Lake.
Sincerely, Gurl beet
Brent N. Petrie
Alaska Energy Authority
Alternate Representative
Bradley PMC
BNP: it
— PO.BoxAM Juneau, Alaska 99814 (907) 465-3575
% PO. Box 190869 701 East Tudor Road Anchorage, Alaska 99519-0869 (907) 561-7877
7158/1017(1)
BRADLEY PMC (BRADOCT19.CHP) Page 1 of 8
MEETING MINUTES
BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE
October 19, 1989
1. CALL TO ORDER
Chairman Kelly called the Bradley Lake Project Management Committee to order at 9:05 a.m. in the Training Room of
Chugach Electric Association in Anchorage, Alaska to conduct the business of the Committee per the agenda and the public
notice.
2. ROLL CALL
The roll call was taken and a quorum was established. In attendance were the following:
Designated Representatives Designated Alternates Representing
Brent N. Petrie Alaska Energy Authority
Ken Ritchey Myles Yerkes Matanuska Electric Association
Dave Highers Tom Lovas Chugach Electric Association
Michael Kelly Golden Valley Electric Association
Thomas Stahr John Cooley Municipal Light and Power
Kent Wick Sam Mathews Homer Electric Association
Everett Paul Diener City of Seward
Representatives Absent Alternates Absent Representing —ssisiygw
Robert E. LeResche Alaska Energy Authority
Robert Hansen Golden Valley Electric Association
Fred Arvidson City of Seward
Others Present Representing
Dave Eberie Alaska Energy Authority
Ron Saxton PMC Utilities
Julie Becker Alaska Energy Authority
Marnie Isaacs Alaska Energy Authority
Joe Griffith Chugach Electric Association
3. PUBLIC COMMENT
There being no public comment, Chairman Kelly proceeded to agenda item 4.
BRADLEY PMC (BRADOCT19.CHP) Page 2 of 8
MEETING MINUTES
4. Modification of Agenda
Review of Reimbursable Cost Items by the Utilities from Grant Funds or Bond Proceeds was added under item 12., Old
Business.
5. APPROVAL OF MINUTES
August 21, 1989
The following clarifications were made to the draft August 21, 1989 meeting minutes:
"by Eric Wohlforth” was inserted between "It was noted" and "that Section 31 costs..." in the next to the last paragraph on
page 4 of 6, and "should" was a fae Sete to" in the one line — ne "Mr. Saxton said that...” on page
6. BOND FINANCE TEAM REPORT
Chairman Kelly reported that an enviable interest rate in the investment community had been secured for the Bradley bond
financing and that the closing in New York, which some of the members (i.e., Messrs. Highers and Wick) had participated
in, had gone smoothly. Mr. Wick said that a blended interest rate of 7.28% had been secured.
Chairman Kelly expressed specific appreciation to Ms. Isaacs, Alaska Energy Authority, for her work relative to the investor
tour.
7. TECHNICAL COORDINATING SUBCOMMITTEE REPORT
a. Report on Four Dam Pool Technical Standards
Mr. Yerkes reported that this issue had previously been assigned to the Operating and Dispatch Agreement Subcommittee
and that this Subcommittee had requested that Mr. Riddle, GVEA, be the lead person in reviewing the Four Dam Pool
technical standards on behalf on the Bradley Lake PMC.
b. Report on Stability/Islanded Condition
Mr. Yerkes distributed copies of the following three graphs entitled:
1) Costs vs. Needle Opening Time depicting needle opening time in seconds versus order of magnitude costs,
2) Present Value of Bradley Lake Spinning Reserves showing Bradley Lake spinning reserves in MW versus the value in
1989 dollars, and
BRADLEY PMC (BRADOCT19.CHP) Page 3 of 8
MEETING MINUTES
3) Present Value of an Optimized Coordination System demonstrating Bradley Lake spinning reserves in MW versus
value in 1989 dollars.
Discussion on Graph 1; Costs Vs. Needle Opening Time
Mr. Yerkes reported that the Technical Coordinating Subcommittee met on October 5, 1989 and that Stone and Webster
Engineering Corporation (SWEC) made a presentation to the Subcommittee on surge tanks at that time. Mr. Yerkes noted
that the presentation by SWEC was summarized on the hand-out entitled Costs Vs. Needle Opening Time, which depicts
costs ranging from $32 Million for a pressurized surge tank to $15 Million for a surge tank in the power tunnel with
corresponding governor needle opening times in terms of spinning reserves ranging from 4 to 23 seconds. Mr. Eberle noted
that the needle opening time of 4 seconds on the graph might be misleading in that a needle opening time of 4 seconds was
in the realm of what had never been done before for units of this size (10 seconds has been achieved). It was noted that
without a surge tank, there would be a 90 second needle opening time from no load to full load. Mr. Yerkes added that
Power Technologies Incorporated (PTT) has begun base runs of a system model with and without a surge tank to see how
real performance would be affected and that the results of their analysis showing costs and benefits are scheduled to be
available in 2-3 weeks (i.e., around mid November, 1989).
Mr. Eberle was asked, if the decision was made to install a surge tank, when would he recommend installation. Mr. Eberle
responded that he would recommend doing it after construction was completed, since it would take a year for the design
work and it would be too expensive to maintain existing construction contracts during this year delay. Mr. Eberle said that
during a retrofit with surge tanks, the project would need to be shut down; however, this would probably be scheduled
during summer months when the current plan by the utilities calls to use the project as little as possible.
Mr. Saxton said that if a surge tank was installed after completion of the project work, it might be considered as optional
project work, which would mean that only those parties who voted in favor of it would share the cost and benefits (reference
Section 4.d of Power Sales Agreement).
Discussion on Graph 2; Present Value of Bradley Lake Spinning Reserves
Mr. Yerkes said that DFI, who is already doing the Intertie Study, had been asked to do a study of the possible benefits of
Bradley Lake spinning reserves, and that the benefits ($50 to $100 Million) were reflected on Graph 2, Present Value of
Bradley Lake Spinning Reserves.
Discussion on Graph 3; Present Value of an Optimized Coordination System
Mr. Yerkes said that the generation schedules for a typical year were used to develop Graph 3; Present Value of an
Optimized Coordination System. It was noted that the value of an optimized coordinated system was substantial, ranging
from $70 to $90 Million.
General Surge Tank Discussion
Mr. Stahr said that it was his understanding, although he hadn’t actually reviewed it, that spinning reserve values were part
of the project benefits or deliverables in the Bradley Lake License Application. Mr. Stahr said that there were literally
hundreds of millions of dollars of potential benefits in spinning reserve and that he thought that those benefits were what
the utilities had originally agreed to.
Mr. Eberle noted that to date no one, including Decision Focus, has defined spinning reserve.
BRADLEY PMC (BRADOCT19.CHP) Page 4 of 8
MEETING MINUTES
Mr. Eberle explained that the PTI studies presently being performed are focusing on the ability of Bradley Lake with and
without a surge tank to prevent load shedding due to frequency delay in the 1 to 3 second time frame. Mr. Stahr stated that
spinning reserve values are not simply limited to avoiding load shedding, and there is significant value for spinning reserves
beyond the initial response time. Mr. Eberle asked, if Bradley can’t respond quickly enough to avoid loss of load and prevent
collapse of the system, does it really matter if the generation comes on, for instance, in 30 seconds or 60 seconds and how
do you differentiate the relative benefits of faster response times once you are beyond the ability to avoid load shedding.
Mr. Saxton said that two issues are raised by the surge tank issue:
1) _ the timing of any financing, particularly more favorable tax exempt financing, and
2) how does it affect the date at which the utilities accept the project as commercially operable.
Chairman Kelly asked the utilities whether or not they felt the surge tank issue would affect the date at which they accepted
the project as commercially operable. The consensus was that they wanted to keep the project on its current schedule,
while concurrently investigating any benefits of a surge tank and that this would be a separate issue which would not affect
acceptance of the project as commercially operable.
The consensus was that PTI be invited to the next PMC meeting to review this issue. Mr. Yerkes asked for an Energy
Authority commitment to possibly expand the scope of the current review of this issue; Mr. Eberle concurred however he
said that PTI might not be the appropriate party to do so.
SCADA/Decknet Discussion
Mr. Yerkes said that the SCADA supplier had originally quoted $20,000 for a Decknet option; however, following review
and clarification of the requirements by the Technical Coordinating Subcommittee, the system is now being quoted at
$200,000. It was noted that control of the plant would be exercised through CEA’s RTU and that this Decknet system is
informational. It was further noted that the utilities would be able to receive this information through CEA; however, some
of the members had expressed the preference for receiving the information directly through a system such as Decknet. The
consensus was that direct access was preferred if the cost was $20,000; however, not at the $200,000 quote.
Stability
Mr. Yerkes reported that Southern Engineers had said that a second transmission line was necessary for reliability/stability;
however, that it was the Energy Authority's position based upon PTI’s work under Phase II that additions to the existing
line could provide this reliability. Mr. Yerkes said that $7 Million had been budgeted in the Bradley Lake project budget
for this "band-aid fix" and that PTI had been working for the Energy Authority on this issue. Mr. Yerkes said that an
additional intertie would require additional funding from the Railbelt Energy Fund.
Mr. Yerkes said that the static var system proposed as the stability fix would not be on-line until one year after commercial
operation and that this might result in some operational restriction on peak capacity during that year.
8. INSURANCE SUBCOMMITTEE REPORT
a. Report on Collective Business Interruption Insurance
Mr. Saxton reported that the Insurance Subcommittee will meet to consider collective business interruption insurance in
November.
BRADLEY PMC (BRADOCT19.CHP) Page S of 8 MEETING MINUTES
b. Report on Pooled Insurance Coverage
Mr. Saxton said that pooled insurance coverage with the Alaska Intertie and/or Four Dam Pool is being analyzed. Mr. Saxton said that the Alaska Intertie insurance issue, which allows self insurance in the Amendment, must be resolved before
the Committee can move ahead with the Bradley insurance issue. There was no objection expressed, therefore, to
considering the Alaska Intertie insurance issue before this group.
Mr. Saxton noted that during a recent meeting with REA, the attorney for REA said that REA will never accept REA
cooperatives being self insured or contracting with others who are self-insured because they do not feel it provides enough
security to REA securities. Mr. Saxton said that REA had been provided with an unexecuted copy of the revised Alaska
Intertie Insurance Agreement, as the original document is currently being circulated for signature. Mr. Saxton was asked
to check on whether Fairbanks Municipal Utility System was going to sign the Amendment. Mr. Saxton said that once the
document was signed, it must be formally filed with REA.
c. Report on Risk Assessment
Mr. Saxton reported that the Insurance Subcommittee will meet to consider this issue in November.
9. BUDGET AND FINANCE SUBCOMMITTEE REPORT
Mr. Saxton said that per the terms of the Power Sales Agreement, the first Bradley Lake annual budget is to be completed
by April 1, 1991. Mr. Saxton with the Energy Authority said that development of the initial budget may be cumbersome
and recommended that the PMC do a "dry run" budget during the beginning of 1990. It was noted that this might require
a full day PMC meeting in order to price items out. No objection was expressed to this recommendation and Mr. Petrie
said that the Energy Authority would develop and circulate standardized categories of expenses/accounts, in order for the
utilities budgets to be consistent and in the same format.
10. OPERATING AND DISPATCH AGREEMENT SUBCOMMITTEE REPORT
Mr. Cooley distributed the September 27, 1989 Bradley Lake Operating and Dispatch Committee meeting minutes.
Mr. Cooley reported that Mr. Gregg, a consultant, had been working on reservoir management and scheduling problems
and that Mr. Hubbard had subsequently developed the first draft of the Bradley Lake Allocation and Scheduling Agreement.
Mr. Cooley said that the agreement allows each utility to have its own flexibility and that it has a rule curve, subdivided to
each utility's proceeding year. Mr. Cooley said that the allocation of losses on the HEA system remains to be resolved and that Mr. Gregg is no longer available as a consultant due to health considerations. The Bradley Lake Operation and
Dispatch Subcommittee may require an additional consultant to complete this work.
11. REVIEW OF PROJECT STATUS
Mr. Eberle reported that excavation of the lower tunnel was completed September 5, 1989. The vertical shaft is 60%
complete, with completion scheduled for the end of October, 1989 and lining scheduled to begin November, 1989. The
dam, including the face, has been completed. The spillway is 40% complete. The roof has been placed on the powerhouse.
Construction of the transmission line is underway and should be completed by December of 1990. Mr. Eberle said that the
critical areas of the penstock are being repaired and that a study of the non-critical areas showed that these areas should
not go into fatigue. The entire penstock and manifold will be hydrostatically tested. Mr. Eberle reported that assuming
that no problems are revealed in the hydrostat testing scheduled for November, the project is projected to be on-line 4-6
months early. Mr. Eberle was asked what the worst case impact to the project schedule would be if problems are revealed
BRADLEY PMC (BRADOCT19.CHP) Page 6 of 8 MEETING MINUTES
in penstock welding. Mr. Eberle responded that under a worst case scenario a new penstock would take one year; however,
since this item is not on the critical path and the project is otherwise 6 months ahead of schedule, the project would be
delayed 6 months.
Mr. Eberle reported that the camp population is approximately 260 and that the winter low population will be approximately
180.
Mr. Wick reported that the HEA Board of Directors had previously agreed to split the lower portion of the transmission
line work between Irby and HEA. The HEA portion, Bradley junction south, will commence this winter, with completion
scheduled during the early portion of next summer (June-July, 1990). The Irby portion is scheduled for the winter of 1990-91.
12. OLD BUSINESS
Review of Reimbursable Cost Items by the Utilities by Grant or Bond Proceeds
Mr. Saxton reviewed that the PMC had previously adopted categories of costs from bond proceeds and grant funds
(reference page 3 of 6 of August 21, 1989 meeting minutes). Mr. Saxton said that the problem at this time is that the utilities
have not accounted for these costs in terms of the reimbursement categories. Mr. Saxton said that the PMC needs to
consider the following three issues:
1) Identification of costs incurred by the utilities in terms of the reimbursement categories,
2) Estimates of future costs and tracking of such costs in terms of these categories, and
3) Consideration of the process for approval of such costs.
Mr. Saxton said that Ms. Rawitscher, Alaska Energy Authority Finance Manager, had directed the trustee to hold some of
the bond proceeds for reimbursement of costs incurred by the utilities and that reimbursement could proceed as soon as
invoices had been approved. Mr. Saxton noted that reimbursement of some of the costs may be delayed until the final bond
issuance.
Project Costs
Mr. Saxton noted that the PMC had previously agreed that the following costs be treated as Project Costs (i.e., eligible for
50% grant funds), and asked that the utilities provide amounts expended for each of these items, with the understanding
that back-up documentation with a fair degree of accuracy should be available:
1) Finance Team Costs (expenses)
a. This would include direct out-of-pocket travel costs to New York for the trip in 1988. Mr. Saxton said that all of
these costs have probably been reimbursed previously, and
b. Out-of-pocket expenses for the trip to New York for the October 5, 1989 closing, which should be directly submitted
to the Alaska Energy Authority, and
c. Direct out-of-pocket expenses for Finance Team meetings in Seattle and Anchorage during the past year;
documentation for these costs should be submitted to Mr. Saxton.
2) Legal costs for finance, which Mr. Saxton already has.
BRADLEY PMC (BRADOCT19.CHP) Page 7 of 8
MEETING MINUTES
3) Legal costs for individual 1989 utility opinion letters (probably August, 1989 costs).
4) PTI Study Costs, including utility out-of-pocket expenses (i.c., travel, hotel, meals) for review of this study which was
coordinated through the Technical Coordinating Subcommittee. It was noted that the members had previously agreed not
to include overhead costs, which would be individually absorbed by the utilities.
5) Technical Coordinating Subcommittee meeting expenses (exclusive of labor) from inception to date plus estimates of
future costs.
6) Insurance Studies; estimate by Messrs. Petrie and Saxton of Probable Loss Analysis, which has not yet been done.
7) SCI Study; direct expenses associated with utility representatives’ participation.
8) Allocation Study.
Mr. Saxton summarized that the utilities needed to submit their costs for items 1,4,5,7, and 8.
Discussion ensued regarding categorization of the cost of the surge tank analysis by DFI in the amount of $10,000. The
consensus was that Mr. Saxton would research this item for consideration at the next meeting.
Section 31 Costs
Mr. Saxton said that the following Section 31 costs (possibly paid from bond proceeds, but not eligible for 50% grant
contribution) had been agreed to:
9) Negotiating Costs for the Power Sales Agreement, Services Agreement and Homer Agreement. Mr. Saxton said that it
had been agreed that this item included work done by attorneys/other outside consultants, as well as in-house travel, lodging
and meals. It had previously been agreed that staff time was not eligible for reimbursement. Mr. Saxton said that a policy
decision regarding whether or not the costs for the in- house attorneys utilized by CEA and ML&P would be treated as
outside costs. Mr. Saxton suggested that they should be; however, no action was taken at this time. Mr. Saxton said that
the intent is to try to pay some of these costs from the short- term bond funds; however, it is likely that these costs will not
be reimbursed until late Spring of 1990.
10) Bradley PMC Costs, including out-of-pocket expenses, such as Committee member air- fare.
The members agreed that Mr. Saxton should share the numbers for expenses submitted with the other members in order
to avoid internal inequity.
Other Costs
= Smith- — hoe Mr. ro = that the deer aaeaey would not _— to this i item as a project cost. Mt
12) DFI Intertie (Decision Focus, $250,000). Mr. Petrie motioned that the DFI Intertie cost be treated as a Section 31 cost.
The motion died for lack of a second. (see below for subsequent action).
BRADLEY PMC (BRADOCT19.CHP) Page 8 of 8 MEETING MINUTES
Mr. Saxton asked the members to identify any other expenses or costs to be incurred prior to commercial operation for
classification. No additional items were identified at this time.
Chairman Kelly said that the Budget and Finance Subcommittee should come up with a standard approach for members
to use in maintaining their costs in these classifications.
The consensus was that the General Managers were to review the costs identified by their accounting staffs and telecopy
them to Mr. Saxton. Mr. Saxton was asked to address any questions raised by his review of the costs submitted to the
individual utilities, prior to distributing the costs to the PMC for consideration (approval) at the next meeting.
13. NEW BUSINESS
a. Report by Power Technologies, Inc.
This item was deferred to the next meeting with the understanding that Messrs. Yerkes and Eberle would coordinate this
and consider the appropriateness of other reports (i.e., by SWEC).
b. Schedule Next Meeting
The next meeting was scheduled for November 30, 1989 beginning at 9:00 a.m. in the Training Room of Chugach Electric
Association.
14. COMMUNICATIONS
Mr. Saxton reported that the Four Dam Pool appeal of Federal Energy Regulatory Commission fees was scheduled for
action by FERC on October 25, 1989 and that he would provide a report on this at the next PMC meeting.
15. ADJOURNMENT
‘ee, the PMC adjourned at 12 noon.