HomeMy WebLinkAboutBPMC Meeting October 9, 1992 1RECORD UOPY FILE NO FRO, 3 =) mind (of9/42 BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE “ APPROVED MEETING MINUTES October 9, 1992 1. CALL TO ORDER Chairman Highers called the Bradley Lake Hydroelectric Project Management Committee to order at 10:15 a.m. in the Training Room at Chugach Electric Association in Anchorage, Alaska to conduct the business of the Committee per the agenda and the public notice. 2. ROLL CALL Alaska Energy Authority Ron Garzini, Designated Alternate Representative Chugach Electric Association David L. Highers, Designated Representative and Chairman Golden Valley Electric Association Mike Kelly, Designated Representative City of Seward Paul Diener, Designated Representative Homer Electric Association Norm Story, Designated Representative Matanuska Electric Association Ken Ritchey, Designated Representative Municipal Light & Power Tom Stahr, Designated Representative Others Present: Ron Saxton, Ater, Wynne, Hewitt, Dodson & Skerritt David Burlingame, Chugach Electric Association Tom Lovas, Chugach Electric Association e:\dburger\word\minutes\pme\10-92 BPMC Meeting Minutes October 9, 1992 Page 2 of 10 John Cooley, Chugach Electric Association Gene Bjornstad, Chugach Electric Association Bradley Evans, Golden Valley Electric Association Bob Hufman, AEG&T Dave Fair, Homer Electric Association Dave Calvert, City of Seward Tim McConnell, Municipal Light & Power Bob Price, Municipal Light & Power Stanley E. Sieczkowski, Alaska Energy Authority Larry Wolf, Alaska Energy Authority Denise Burger, Alaska Energy Authority Dennis Lewis, Petersburg Municipal Power & Light 3. PUBLIC COMMENT There being no public comment, the meeting continued to the next agenda item. 4. AGENDA COMMENTS Item 12 B, APPROVAL OF UTILITY AGREEMENTS, was removed from the agenda. 5. APPROVAL OF MINUTES - August 24, 1992 Mr. Stahr objected to the inclusion of Attachment 2, Bradley Lake Operations and Dispatch Summary of Meeting on August 18, 1992 for Bradley Project Managers' Committee, as part of the approved permanent record of the August 24, 1992 PMC meeting. Mr. Stahr took exception to the following statement contained in paragraph eight: "After a lengthy discussion of scheduling procedures, it was the consensus of the committee that Bradley was agreed to, by the managers, to be operated as an energy project." Mr. Stahr firmly stated that he was not a part of that consensus and that the utilities had purchased a lot more than energy (i.e. capacity and spin.) Mr. Kelly, offering his comments on behalf of the remaining utility managers, agreed that the language used in the summary was incorrect. Mr. Stahr moved that the Bradley PMC meeting minutes of August 24, 1992 be approved with the exception of the August 18, 1992 O&D Meeting Summary (Attachment 2). The motion was seconded by Ron Garzini. Mr. Ritchey ¢:\dburger\word \minutes \pmo\10-92 BPMC Meeting Minutes October 9, 1992 Page 3 of 10 questioned whether the Bradley PMC had the authority to approve the O&D Subcommittee meeting summary. Mr. Saxton clarified that if the summary was an accurate account of the O&D Subcommittee meeting, then the PMC should not change it, but if the summary was inaccurate, then the O&D Subcommittee, itself, should change it. Mr. Saxton stated that the Bradley PMC had the right to disagree with the summary. Responding to Mr. Saxton's comments, Mr. Sieczkowski confirmed that the relationship of energy and capacity was discussed at the O&D Subcommittee meeting and that the summary reflected the discussion. With the understanding that the BPMC record will reflect the managers' disapproval of the O&D Subcommittee statement, the August 24, 1992 BPMC meeting minutes were approved by acclamation. 6. TECHNICAL COORDINATION SUBCOMMITTEE REPORT Dave Burlingame distributed a report (synopsis) of the TCS meeting held October 8, 1992 (Attachment 1). Mr. Burlingame informed the PMC that the DECnet had been installed but had not yet been put into operation. Mr. Burlingame noted that the SVC work was on schedule (the transformer, reactors, and buswork had been installed.) The contractor has tentatively requested an outage of the 115 kV transmission system October 16, 1992 to hook up the SVC. It was reported that the reservoir water elevation was significantly lower than projected for this time. Mr. Burlingame explained that AEA had uncovered a potential error in the lake level survey which, if verified, contributed to the lower than anticipated lake level. It was noted that AEA would be issuing a revised allocation schedule. Because of the discrepancies between the results of the actual SVC simulator tests and the Power Technology Incorporated (PTI) prediction, Mr. Burlingame stated that Stone & Webster Engineering Corporation (SWEC) had been requested to analyze both the ABB simulator test data and PTI studies. It was noted that the TCS utility representatives objected to the conclusions of SWEC's analysis due to the fact that SWEC used outdated PTI data. SWEC will continue to investigate the problem. ¢:\dburger\word\minutes\pme\10-92 BPMC Meeting Minutes October 9, 1992 Page 4 of 10 Mr. Burlingame reported that the TCS had developed possible short term and long term solutions to the unstable Kenai oscillation problem.! The TCS approved the implementation of two procedures to resolve the problem when the Kenai was exporting more than 10 megawatts of power: (1) to automatically place the unit into deflector mode via SCADA and, (2) to disable the gain acceleration function within the governor. Mr. Burlingame noted that the second procedure would slow the needle response time (allowing more time for system response) resulting in the waste of some water. Mr. Burlingame reported that no short term solution to the unstable oscillation problem had been identified for when the Kenai was importing power, or exporting less then 10 megawatts of power. SWEC is investigating possible short term solution options using the Bradley governor and is concurrently investigating long term solutions. It was noted that when the Kenai is importing more than 5 megawatts of power and is islanded, the unstable oscillation will cause the Kenai to go through all three stages of load shed (effectively resulting in only one stage of load shed.) De BUDGET SUBCOMMITTEE REPORT Mr. Ritchey reported that there had been no official Budget Subcommittee meetings. However, the RFP for the construction cost audit was nearly ready to issue and the proposals were expected by the first of November 1992. Mr. Ritchey noted that the subcommittee would be reviewing a proposal for the audit of yearly operating expenses. Mr. Saxton stated that the PMC had authorized the expenditure of funds for the construction cost audit, but not the yearly operating cost audit. Mr. Ritchey clarified that funds for the yearly operating cost audit had already been approved as part of the fiscal year budget and that no additional approval was needed. Mr. Saxton recommended that the PMC address the upcoming fiscal year budget at the next meeting. 8. AGREEMENT SUBCOMMITTEE REPORT Mr. Sieczkowski distributed the Agreement List and Assignment Schedule, Updated October 8, 1992 (Attachment 2). Mr. Sieczkowski reported that HEA and ABA met October 2, 1992 and discussed the Soldotna Substation Agreement and Transmission Facilities Maintenance Agreement. New drafts of the agreements developed at that meeting were currently being reviewed by HEA, CEA, AEA, and the Agreement Subcommittee members. The ! Unstable oscillations are those oscillations which grow in magnitude once started and do no subside until either corrective action has been taken or the system has suffered considerable loss of load and/or generation to obtain stability. ¢:\dburger\word\minutes\pme\10-92 BPMC Meeting Minutes October 9, 1992 Page 5 of 10 Agreement Subcommittee was expected to meet later this month to review the draft agreements. The SVC Maintenance Agreement was currently being reviewed by the Energy Authority's attorney. In response to inquiry by Mr. Lovas, Mr. Sieczkowski noted that AEA was presently awaiting receipt of a revised draft of the Transmission Interconnect Agreement from HEA. 9. OPERATION AND DISPATCH SUBCOMMITTEE REPORT A summary of the October 2, 1992 O&D Subcommittee meeting was distributed (Attachment 3). Mr. Sieczkowski highlighted the following topics: Request for installation of kW metering on the station service system for better accounting of energy flows. Annual maintenance of both units scheduled for November 9 - 19, 1992 Modification of the fish water bypass release software program to improve system response time (in order to avoid violation of FERC minimum flow requirements.) Exhibit B, Allocation and Scheduling Procedures acted upon by the O&D Subcommittee will be presented under "NEW BUSINESS." Amendment to Allocation and Scheduling Procedures acted upon by the O&D Subcommittee will be presented under "NEW BUSINESS." Notification by CEA of a formal agreement between CEA and HEA for the purchase of scheduling rights (originally misstated as capacity and allocation at the October 2, 1992 O&D Subcommittee meeting.) In response to the CEA / HEA agreement, Mr. Sieczkowski stated the O&D Subcommittee requested clarification of whether HEA still had voting rights on the Subcommittee since HEA was no longer a scheduling utility. Chairman Highers pointed out that the Power Sales Agreement included all Bradley Lake participants (as opposed to scheduling utilities.) Mr. Saxton stated that the contract did not specify anything about the subcommittees, giving the PMC the authority to make those rules. Mr. Stahr stated that the utilities had purchased capacity and energy, not water allocation, further explaining that water allocation was an operational procedure. Mr. Story took exception to the language in the last paragraph on page 1 of the October 2, 1992 O&D meeting summary where it stated that CEA had purchased HEA capacity and water e:\dburger\word\minutes\pmo\10-92. BPMC Meeting Minutes October 9, 1992 Page 6 of 10 allocation. Mr. Story explained that, rather, CEA had purchased HEA scheduling rights. Mr. Stahr expressed concern over potential impact (if any) of the CEA / HEA agreement on the rights of the other purchasing utilities. Mr. Stahr suggested that the Bradley PMC assure the prevention of any infringement on another utility's rights or provide a mechanism for review of such agreements by all of the participating utilities. Mr. Kelly brought attention to the responsibility for spinning reserve, noting that CEA had originally taken the position that HEA was required to provide spinning reserve. Mr. Kelly raised the question of a utility's responsibility to carry spinning reserve if the utility assigned its scheduling right. Mr. Fair noted that the spinning reserve issue to which Mr. Kelly referred was a temporary Intertie Operating Committee (IOC) arrangement that would dissolve on January 1, 1993. Mr. Fair informed the PMC that HEA was preparing a letter explaining the HEA agreement with CEA. Mr. Fair explained that the agreement was a scheduling agreement and did not impact the "rights, obligation, cost, payment, etc. in relation to AEG&T's share of Bradley Lake associated HEA participation." Mr. Fair reiterated that HEA had only sold its right to schedule, noting HEA purposely avoided a power sale, kilowatt hour sale, or kilowatt sale. Mr. Kelly again questioned HEA's spinning reserve requirement stating that the issue of spinning reserve was "hooked" to the issue of scheduling and participant voting rights. Mr. Fair stated that HEA's spinning reserve requirement was taken care of by the agreement with CEA.? Mr. Fair further stated that HEA had no intent to modify its participation in the Bradley Lake Project. Mr. Kelly stated that if HEA was no longer obligated to spin, it would have an impact on the other participants. Mr. Lovas clarified that CEA's agreement with HEA pooled the resources of both utilities similar to its agreements with SES and MEA. Mr. Burlingame re-focused the discussion on the question raised at the October 2, 1992 O&D Subcommittee meeting regarding Bradley Lake participant voting rights. Mr. Burlingame phrased the following question: "Does CEA have the right to schedule 57% of the project, or does CEA 2 Mr. Stahr later stated that, by his interpretation of the Alaska Intertie Agreement, only utility participants had spinning reserve obligations (i.e. Eklutna and AEA have no spin obligations.) Mr. Lovas also confirmed this interpretation, stating that the generating utility (representing a pool of resources) was responsible for the spin obligation (i.e. CEA picked up the spin requirement for HEA.) e:\dburger\word\minutes\pmc\10-92 BPMC Meeting Minutes October 9, 1992 Page 7 of 10 schedule 31% + 12% + 13% + 1% of the project?" Mr. McConnell noted that it depended on which way CEA dispatched, explaining that if all the water of all the participants was depleted in proportion to their project share, there was no difference. If CEA however used all of one utility's share but still claimed 57% (for apportioning spin), there would be a "dramatic difference." Mr. Burlingame stated that the Allocation and Scheduling Procedure does not state that CEA must draw all shares down equally and pointed out that there were no operating restraints defined in the Allocation and Scheduling Procedure. Mr. Burlingame stated each utility would incur spinning reserve obligation if the participant shares were treated in an additive manner (i.e. 31%, 12%, 13% and 1%.) Mr. Kelly expressed concern over the possibility that utilities could avoid the spinning reserve requirement. Mr. Lovas noted that the combined spinning reserve obligation was not reduced, and that it was an allocation problem as opposed to an electrical problem. It was the general consensus of the PMC that a determination of the effect of the CEA / HEA agreement could not be made without further review of the actual contract or a contract summary. Mr. Lovas informed the Committee that the scheduling agreement would become public information within the next few days when it was filed as part of (APUC) Docket U 92-25. Mr. Stahr moved that no change be made to the voting rights and membership in the PMC subcommittees, and that the "status quo" be maintained. The motion passed by a. unanimous roll call vote. Mr. Kelly asked Mr. Saxton to research answers to the following questions: i Does Bradley require spin? 2: Do the arrangements between SES and MEA and CEA effect their spin requirement? 3. Does the new HEA / CEA arrangement effect their spin requirement? Mr. Fair pointed out that there is no spinning reserve obligation imposed by any of the Bradley Lake agreements, stating that it was an IOC issue. Mr. Burlingame clarified that, for now, CEA was carrying the extra spin. Mr. Burlingame, referring to the motion, asked if the "status quo" meant that CEA then operated 57% of the project. Mr. Burlingame explained that CEA ¢:\dburger\word\minutes\pme\10-92 BPMC Meeting Minutes October 9, 1992 Page 8 of 10 11, would provide some water allocation to each participant that CEA scheduled for and would carry each participants spin obligation. Mr. Burlingame added that the water share of participants CEA scheduled for would not be depleted in proportion to their project share. Mr. McConnell noted that if the water was depleted at rates determined by CEA, entitlement to capacity and entitlement to spin changes dramatically. Mr. Burlingame disagreed, stating that CEA had never operated according to proportion of share. Mr. Stahr recommended that spin obligation and the selling of spin also be researched. Chairman Highers, citing the need to have several questions answered, asked Mr. Saxton to provide this information to the PMC. To ensure a response to all issues, Mr. Saxton responded with a plan to first put together a list of the questions that had been raised for review by the managers. A. BRADLEY SCHEDULING VS. SPIN REQUIREMENT This item was included in the discussion of Item 9, OPERATION AND DISPATCH SUBCOMMITTEE REPORT. REVIEW OF PROJECT STATUS In the absence of Dave Eberle, Mr. Wolf noted that information regarding project status was presented in the TCS report to the Committee (Item 6). OLD BUSINESS A. SPINNING RESERVES/UNDER FREQUENCY LOAD SHEDDING - UPDATE Mr. Lovas reported that the ASCC had met the day before and was continuing to make progress in its discussions of spinning reserve and load shed. The ASCC discussed the use of utility staff to perform technical studies and concluded that it was more timely and cost effective than using consultants. Mr. Lovas informed the PMC that the Intertie Subcommittee was close to finalizing a load shedding schedule proposal and that the ASCC had approved a $159,000 budget for the Reliability Criteria Subcommittee's work. e:\dburger\word \minutes \pme\ 10-92 BPMC Meeting Minutes October 9, 1992 Page 9 of 10 13. | NEW BUSINESS A. APPROVAL OF COMMITTEE EXPENSES Noting that documentation of the current expenses had been submitted to Brent Petrie, Mr. Saxton stated that future Committee expenses should be forward to Ken Ritchey (Chairman of the Budget Subcommittee). Mr. Saxton presented the following expenses to the PMC for approval: Homer Electric: $228.84 for TCS work $544.87 for PMC related activities Ater Wynne: $23,760 for July, August, and September legal expenses Mr. Saxton noted that the remainder of Section 31 funds would be depleted and a portion of these expenses would come directly from the Committee budget. Mike Kelly moved to approve the submitted expenses. The motion, seconded by Norm Story, was approved by unanimous roll call vote. APPROVAL OF UTILITY AGREEMENTS Deleted from the agenda. APPROVAL OF AMENDED ALLOCATION AND SCHEDULING PROCEDURES Mr. Sieczkowski distributed a revision to Section 5 of the Allocation and Scheduling Procedure (Attachment 4) and recommended action by the PMC. Additionally, Mr. Sieczkowski distributed a copy of the Exhibit B language to the Allocation and Scheduling Procedure (Attachment 5) and recommended that the PMC review it for consideration at the next meeting. Mr. Kelly moved that the Section 5 revision be approved. Ken Ritchey seconded the motion.? Mr. Stahr asked if the proposed amendment would result in increased lead time on the scheduling. In response to Mr. Sieczkowski's answer that it would, Mr. Stahr expressed his opposition, stating that there was too much lead time now. 3 No action was taken on this motion. e:\dburger\word\minutes \pme\10-92 BPMC Meeting Minutes October 9, 1992 Page 10 of 10 Mr. Burlingame disagreed and pointed out daily changes could still be made to the schedule. Mr. Kelly motioned, seconded by Mr. Stahr to table the previous motion until the next PMC meeting and allow CEA to implement the revised procedure in the manner described until then. The motion was approved by a unanimous roll call vote. HISTORICAL REVIEW OF PMC ACTIONS Mr. Saxton noted that a list of PMC actions delegating assignments to various subcommittees had been prepared and previously distributed to the utility managers (Attachment 6). It was noted that the subcommittees had not been given any authority to act independently of the PMC. 14. COMMUNICATIONS Mr. Kelly informed the PMC that Mr. Brad Evans had been appointed GVEA's alternate representative to the PMC. A. SCHEDULE NEXT MEETING Friday, November 20, 1992 10:00 a.m. CEA Training Room 15. ADJOURNMENT There being no further business before the committee, the meeting adjourned at 11:45 .m. Gut Go tor— ttest: ie Ronald A. Garzini, Designated Alternate Representative e:\dburger\word\minutes \pme\10-92 10. 11. 12. BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE October 9, 1992 Chugach Electric Association, Inc. Training Room 10:00 a.m. CALL TO ORDER 10:00 a.m. ROLL CALL PUBLIC COMMENT AGENDA COMMENTS APPROVAL OF MEETING MINUTES - August 24, 1992 TECHNICAL COORDINATING SUBCOMMITTEE REPORT BUDGET SUBCOMMITTEE REPORT A. Bradley Lake Construction Cost Review - Update B. FY93 Budget, AEA Administrative Costs - Update AGREEMENTS SUBCOMMITTEE REPORT OPERATION AND DISPATCH SUBCOMMITTEE REPORT A. Bradley Scheduling vs. Spin Requirements REVIEW OF PROJECT STATUS OLD BUSINESS A. Spinning Reserves/Under Frequency Load Shedding Update NEW BUSINESS A. Approval of Committee Expenses (nest wot.) — 8 Aiea ot ily Agremcnty— 13. 14, Cc. Approval of Amended Allocation & Scheduling Procedures D. Historical Review of PMC Actions COMMUNICATIONS A. Schedule Next Meeting ADJOURNMENT RECORD VOPY FILE NO RO 3-b! ww 10/9 /4a Highers Burlingame Ritchey Sieczkowski Sieczkowski Kelly Eberle Lovas Petrie Sieczkowski Sieczkowski Saxton BRADLEY LAKE FY93 BUDGET FERC ACCOUNT Acct. ACCOUNT DESCRIPTION COMMENT TOTAL HYDRAULI ay POWER GENERATIO 535 Operation Supervision and Engineering _ Supervision, Engineering and Administrative Support - 3.2 FTE 257,926 257,926 537 Lea Operation Expenses Inspection of Three Diversions 6,000] ‘Snow measurement, SCS 20,000] Siesmic Monitoring, UAF 50,000 Climatologic - NOAA Weather Service 5,460 Semi-Annual Dam Settlement Survey 2,000 Conservation Studies for Fish and Game 18,000) 101,460 538 Electric Operation Expense SCADA Technical Maintenance 25,000 Powerplant Operations - .4 FTE 42,000, ‘Supplies 15,000 82,000 539 Hydraulic Power Generation Operation Expense Mechanical vibration and balance testing, consumables such as oil and filters, die checks 20,000 20,000 and pressure nitrogen cylinder recharges. 540.1 Transportation Helicopter Transportation for Project Facility Inspections 91,000) Barge Rental to Transport Materials and Dock Fees 27,500 Project Site Contract Transportation - Scheduled Fixed Wing Service to Site 70,000: Commercial Transportation 14,400 |Safety Technical and-Operations Training 14,000 |Maintenance Management System Software Upgrade Modification and Training _ 4,000 |Communications Divcom Maintenance Fee 40,000 | Project radios, pagers, and telephones 6,000 | 266,900 542 Maintenance of Structures Routine Supplies, Materials and Maintenance Items 60,000: 60,000: Page i\ of 3 FY93BUDB.XLS 1:41 PM 8/24/92 T LN3WHOVLLY BRADLEY LAKE FY93 BUDGET RODIN DESCRIPTION 544 Maintenance of Electric Plant Electrical Spare Parts Contract Labor for Testing Protective and Revenue Meters, Generators, Transformers, 70,000) 545 Maintenance of Misc. Hydraulic Plant _} 45,000 545.1 __|Maintenance of Hydraulic Plant 392,000 547 Fuel Stock Fuel for Bradley Vehicles, Loaders, Graders 40,000 556 |System Control and Load Dispatching Labor - CEA 1 FTE Training - CEA Dispatchers Economic Dispatch Program (10 yr. Armortization ) - CEA Bradley Junction Substation Switchyard Inspection and Tests - HEA Maintenance of Overhead Lines ADMINISTRATIVE, GENERAL AND EXPENSES ‘Transmission Line Inspection and Maintenance - HEA 39,000 Administration and General Expenses |a. Bradley PMC Costs | _ PMC Travel Cost 6 PMC Meetings each year in Anchorage Subcommittee Travel Cost 12 Subcommittee Meeting each year Meeting General Expenses PMC Adminstrative Support Litigation Expenses 81,000 b. Administration Expe AEA Administrative and General Costs Page of 3 396,011 FY93BUDB.XLS 1:43 PM 8/24/92 BRADLEY LAKE FY93 BUDGET ACCOUNT DESCRIPTION Contract Services a, Legal Attorney Fees (AEA & Utilities) 10,000 b. Project Audit Professional Audit Services 15,000 25,000 Insurance a, Property $IM Deductible 160,824 b. Boiler and Machinery $50K Deductible 50,000: c. General Liability One-Sixth of AEA State Policy Premium 10,000 d, Watercraft & Aviation One Sixth of AEA State Policy Premium 10,000) e. Directors and Officers Liability Liability Insurance for the Directors and Officers of the PMC 15,000 245,824 928 Regulatory Commission Expenses a, FERC Land Use Fees FY92 Billing $97,000 Administrative Fees Estimate USGS Streamgaging Five Year Inspection Engineering Consultant (est. $75,000 in FY96) b. Permitting AEA Permits Specialist TOTAL FY93 BRADLEY O&M BUDGET Page3 of 3 FY93BUDB.XLS 1:43 PM 8/24/92 ATTACHMENT 2 Bradley Lake Operations and Dispatch Summary of Meeting on August 18, 1992 for Bradley Project Manager's Committee Correspondence - received for discussion of Scheduling Procedures, Spinning Reserve, Bradley Lake Project Summary Reports, Operational Procedures and Allocation Update. Operation - the lake elevation was 1139.2 ft. on August 17. Inflow is beginning to slow down. 45,680 MWH was delivered during July. The communication, DECNet and SCADA systems were being worked on by project and contract personnel. There was an outage on August 13. Unit one tripped off-line. This problem was detected when the project was islanded. Load changes, under this condition, greater than 1/2 MW/minute creates problems in the system. This problem is being investigated. Increased unit start-stops have caused other control problems to surface that previously were not detected in the synch circuits. The Division of Information will be requested to initiate the dispatcher ring down circuit upon receipt of approval and transfer of funds. The storing water criteria need committee review and input and will be presented at the next meeting for discussion. After a lengthy discussion of scheduling procedures, it was the consensus of the committee that Bradley was agreed to, by the managers, to be operated as an energy project. The declared capability versus project capacity causes difficulty at times in scheduling, therefore, this philosophy may need to be revisited if capacity becomes an issue. To accomodate the scheduling issue, there were two motions passed which are summarized: 1. Utilities scheduling above their 9OMW sfare willbe cut back proportionately to 9OMW for unit trips or system emergencies. Under normal load changes, the approved schedule will not be allowed to change; 2: The utilities will submit a weekly schedule by Tuesday, reviewed on Wednesday, confirmed by Thursday and implemented on Saturday at 0001 hours. Spinning reserve calculation methods were discussed. Chugach Electric Association (CEA) provided an example of a proposed method. The discussion addressed the issue of being able to use an utilities capacity when they committed that capacity to another utility. This led to an unresolved problem in the O&D. There was a motion to refer this issue to the Bradley PMC. The method suggested by CEA to calculate the spinning reserve was accepted by the O&D noting that the method of calculation only was approved. Annual maintenance on the Bradley units was discussed and the schedule will be coordinated with the participating utilities. The next meeting is set for September 15, 1992. 92Q3\IT3449(1) Page | of | ATTACHMENT 1 CHUGACH ELECTRIC ASSOCIATION, INC. Anchorage, Alaska October 8, 1992 TO: Bradley Lake PMC FROM: David W. Burlingame, TCS Secretary SUBJECT: TCS Meeting Report The following is a synopsis of the TCS meeting held on October 8, 1992. SCADA SubCommittee has reviewed the DECNET installation at Bradley Lake. SWEC is waiting for the final points list to be received from Golden Valley and AML&P prior to implementing. SWEC has requested Landys & Gyr investigate alternative methods of supplying HEA with requested information other than the present design. Svc Project Status - The transformers at both sites are installed, reactors installed, switches and buswork installed and the valves are on-site. The Daves Creek SVC is tentatively scheduled to be connected to the power system October 16, 1992. The SVC is not scheduled to begin any testing until November. Bradley Lake Water Elevation - The water elevation is down significantly and project allocations are expected to be adjusted downward. SWEC/AEA found an error in the field survey which resulted in the water elevation at the dam being reported 2' lower than it actually is. svc Simulator Studies - SWEC presented an analysis of the analog and digital simulator studies ABB performed at AEA's request. The studies were performed due to the apparent discrepancy between the stability numbers found by ABB in their initial tests and the PTI numbers we are operating under. The utilities objected to the SWEC conclusion as SWEC was using numbers from a superseded PTI study and the not the numbers currently in use. SWEC will investigate further. SWEC was requested to run an additional case to ascertain the stability limit after the SvC's are installed as this now appears to be in question. Kenai Oscillations - SWEC presented its findings an the cause of the Kenai oscillations and the recommended short term solutions. The committee accepted two of the recommendations with motions as follows: Motion 1 - Move to put one Bradley Lake unit in deflector automatically as soon as possible via Chugach's SCADA control upon detection of islanding to prevent or mitigate Kenai frequency oscillations. The above action has previously been implemented by Chugach and according to the SWEC studies, should prevent oscillation during those times when the Kenai is exporting more than 10 MW of power. Motion 2 - Move to disable the gain acceleration function within the Bradley governor to allow more time before the needle valve and deflectors equalize and begin the Kenai system frequency oscillations. The above action will be implemented by SWEC as soon as possible. The only detriment to the above is a small amount of water that is wasted on overfrequency conditions since it slows down the time it takes for the needles to close and match the deflectors, ie the units are running on their deflectors for a slightly longer period of time. The committee has not been able to identify any short term solutions which mitigate the Kenai loadshedding during import conditions. SWEC estimates that any import more than 5 MW will result in total Kenai loadshedding. SWEC was asked to investigate the possibility of automatically tripping a unit to deflector control on overfrequency as opposed to waiting for SCADA control. This may help the Kenai avoid further loadshedding during import conditions. SWEC recommended disabling AGC control for Bradley Lake during transient period immediately after islanding. Chugach will investigate and implement if possible. SWEC will investigate the possible long term solutions including the installation of a new governor control mode at Bradley Lake, new intertie, batteries, surge tanks etc. ATTACHMENT 2 BRADLEY LAKE AGREEMENTS SUBCOMMITTEE AGREEMENT LIST AND ASSIGNMENT SCHEDULE UPDATED: October 8, 1992 COMPLETION Organiz- AGREEMENTS DRAFT DATE DATE RESPONSIBILITY ation Dispatch Agreement 3-6-91 2-19-92 Tom Lovas CEA between AEA and CEA 6-19-91 S. Sieczkowski AEA 9-4-91 Maintenance S. Sieczkowski AEA Agreement between Sam Mathews HEA AEA and Maintenance Contractor Transmission Facilities 04/05/89 Sam Mathews HEA Maintenance 08/06/89 S. Sieczkowski AEA Agreement between 09/13/91 AEA and HEA 11/08/91 03/03/92 05/15/92 08/21/92 10/05/92 Allocation and 09/15/89 7/2/91 S. Sieczkowski AEA Scheduling Procedures 10/90 O&D Members Utilities Exhibit A 12/91 3/92 Exhibit B 10/92 12/91 Exhibit C 11/91 12/91 Exhibit D 11/91 Deleted Transmission 06/21/91 Sam Mathews HEA Interconnect 11/08/91 Stan Sieczkowski AEA Agreement between 03/02/92 AEA and HEA 05/18/92 Communications 9/92 Afzal Khan AEA Equipment MOU between AEA and Div of Infor Soldotna #1 Dispatch Done + Sam Mathews HEA Agreement between CEA and HEA Transmission 3/7/89 Sam Mathews HEA Capability Agreement between HEA and CEA, ML&P, AEG&T, GVEA 4 Dare not avai bole bradagre/ds9/91 10. Ly; 12. 13. 14, 15. AGREEMENTS Power Sales Agreement between AEA, & CEA, GVEA, ML&P, AEG&T, HEA, City of Seward Wheeling of Electric Power (Services Agreement) between CEA & HEA, GVEA, MEA ML&P, AEG&T, Seward Static Var Compensator Systems at Daves Creek and Soldotna Maintenance Agreement between AEA and CEA Daves Creek Substation Soldotna Substation Right of Entry Agreement between AEA and HEA Power Revenue Bond Resolution DRAFT DATE 1/92 2/92 8/91 11/8/91 3/2/92 8/91 11/08/91 03/02/92 03/27/92 05/18/92 08/06/92 08/21/92 10/02/92 COMPLETION DATE 12/8/87 12/8/87 3/92 9/7/89 RESPONSIBILITY Afzal Khan D. Burlingame S.Sieczkowski D. Burlingame S. Sieczkowski Sam Mathews D. Burlingame AEA ORGANI ZATION AEA CEA AEA CEA AEA HEA CEA ATTACHMENT 3 BRADLEY LAKE HYDROELECTRIC PROJECT OPERATION AND DISPATCH SUBCOMMITTEE OCTOBER 2, 1992 MEETING SUMMARY BRADLEY PR‘ T OPERATION The Chugach Electric Association (CEA) dispatcher was requested to provide the generation schedule to the plant maintenance personnel. This will assist in maintenance scheduling to reduce conflicts and enable maintenance to be coordinated with dispatchers. Additional KWH metering on the station service system is desired for Bradley energy accountability. The weather station communications are still being put into service because new crystals were required. Deflector mode operating tests are scheduled for November 7 and 8, 1992. This is part of the investigation to determine why the oscillation occurred after islanding on the Kenai. Annual maintenance of the project units is scheduled for November 9-19, 1992. The fish releases require close monitoring. A software revision is necessary to prevent dropping below minimum required flows, Because of the four hour time lag from release at the dam and the recording of the flow at the lower Bradley River Gaging Station. Alaska Energy Authority (AEA) utilities and Division of Information Services (DIS) are working to complete installation of project communications. There is still a gap in direct communications from the dispatcher's with personnel in the field. This needs to be resolved so the switchmen can be contacted directly by the dispatchers. Homer Electric Association (HEA), CEA, AEA and DIS are working to correct this problem. COMMITTEE DI ION AND ACTION: The committee took action to recommend "Approval of the Allocation and Scheduling Procedures, Exhibit B Language, Presented in the CEA September 12, 1992 Memo as Modified." (Copy attached) The "Storing Water Criteria" proposal was presented and discussed. A discrepancy arose when the generation projections were presented. There was a substantial acre-foot storage accounting error in addition to a two foot transducer level indication error detected this past week. This discrepancy will be resolved and the projections updated for the dispatchers. The committee is to review the Storing Water Criteria proposal and discuss at the next meeting. Operating the Bradley Lake units in condenser mode was discussed. The consensus of the committee was to continue operating the system without running the unit in condenser mode unless requested by a utility. The project will continue to be operated according to established procedures and approved criteria. CEA and HEA have formalized an agreement for CEA to purchase HEA capacity and water allocation. Discussion followed and it was noted that clarification was needed from the Bradley Project Management Committee (BPMC) regarding HEA's spinning reserve obligation. 92Q4\NK3718(1) Page | of 2 Summary of October 2, 1992 Operation & Dispatch Subcommittee Meeting October 8, 1992 Another issue arose when this was discussed. "Since CEA has HEA's capacity and water allocation, and is therefore no longer a scheduling utility, does HEA have the right to vote on issues within the Operation and Dispatch subcommittee." This issue needs clarification from BPMC. SS:nk Attachment as Stated. 92Q4\NK3718(2) Page 2 of 2 DATE: TO: FROM: SUBJECT: ATTACHMENT 4 Alaska Energy Authority MEMORANDUM October 8, 1992 Bradley Lake Hydroelectric Project Project Management Committee Stanley E. Sieczkowski eal Director Facilities Operation and Engineering Alaska Energy Authority Revised Allocation and Scheduling Procedure The following revision to the Bradley Lake Allocation and Scheduling Procedure was approved for recommendation to the Bradley PMC at the August 18, 1992 Operations and Dispatch Subcommittee meeting: "In the interim, Section 5, Project Scheduling, (b), Hourly Schedules of the Allocation and Scheduling Procedures, revised November 19, 1991 shall be changed to: The utilities' weekly schedule shall be submitted to the dispatcher no later than 1400 hours on Tuesday; a preliminary summary of schedule requests shall be distributed to all utilities no later than 1400 hours on Wednesday for review; the schedule shall be confirmed by the dispatcher no later than 1400 hours on Thursday; and implemented at 0001 hours on Saturday. (The energy week is established to be Saturday to Friday.)" The motion passed by unanimous roll call vote. DB:SES:db ce: Ronald A. Garzini, Alaska Energy Authority Brent N. Petrie, Alaska Energy Authority DATE: TO: FROM: SUBJECT: Alaska Energy Authority MEMORANDUM October 8, 1992 Bradley Lake Hydroelectric Project Project Management Committee Stanley E. Sieczkowski - Director Facilities Operation and Engineering Alaska Energy Authority Exhibit B - Allocation and Scheduling Procedure Exhibit B of the Bradley Lake Allocation and Scheduling Procedure was approved for recommendation to the Bradley PMC at the October 2, 1992 Operations and Dispatch Subcommittee meeting. Attached is a copy of the approved Exhibit B for your consideration. DB:SES:db cc: Ronald A. Garzini, Alaska Energy Authority Brent N. Petrie, Alaska Energy Authority ATTACHMENT 5 10/06/92 16:55 39077624540 CEA DISPATCH CTR Hoo2 Exhibit B The following sections are intended to replace the existing schedule B in the Allocations and Scheduling Procedures Turbine Operation The following schedule shall be used to determine the operation of the Bradley Lake generators, assuming both units are available for operation: Plant Schedule (MW) Speed Mode Condense Mode Notes Schedule< 10 MW no units none, one or both units #1 10 MW<schedule <20 MW one unit one unit #2 20 MW <schedule < 30 one unit one unit/no unit #3 Schedule > 30 MW both units no units Notes #1 - If any participant could utilize the spinning reserve from a unit or a second unit in the condense mode, one or both units will be operated in condense. If no utility requests the additional spinning reserve, only one unit will be operated in condense if required for voltage control unless a unit is changed to condense to avoid a shutdown. Notes #2 - depending on spin requirements, either one unit will be operated alone in the speed mode or both units will be operated, ene in speed and one in the condense mode. A utility can request the unit be operated in the condense mode as opposed to altering its schedule if in conflict with the minimum 4 hour down time. Note #3 - any scheduling utility can require both units to he Placed on-line between 20 and 30 MW if desired by that utility, although it would be possible to operate one unit in speed and one unit in condense mode at these levels to obtain the entire spinning reserve allocation for the plant, the more efficient operation would be for both units to be operated above 10 MW each in speed mode. 10/06/92 16:55 39077624540 CEA DISPATCH CTR oo03 Minimum Unit Shut Down Each unit scheduled for shutdown shall be shut down for a minimum of 4 hours. Operation of a unit in the condense mode will not constitute a shut down and does not have a 4 hour minimum time associated with it. The following criteria shall generally govern the operation of the plant during islanded and non-islanded conditions; Islanded Operation Unscheduled Tslanding If the Kenai is operating with only Bradley Lake or Bradley Lake and Cooper Lake prior to islanding, one Bradley Lake unit will automatically be placed in deflector by the Chugach scada system upon detection of islanding. The unit will remain in deflector until a Kenai area gas turbine has been synchronized with the islanded Kenai system. After a gas turbine has been synchronized with the Kenai system the unit will be changed to the speed mode from the deflector mode. During load restoration on the Kenai, one unit may be placed in deflector control to aid the gas turbine in load pickup and frequency restoration. The unit will be returned to speed mode after restoration has been completed. Scheduled Islanding Prior to scheduled islanding a Kenai area gas fired generator will be synchronized with the Kenai system. Bradley generation will remain in the speed mode. on - Ss While running islanded, a gas-fired generator shall be operated in conjunction with Bradley Lake. The Bradley Lake units shall he operated in the speed mode. If an on-line gas-fired turbine suffers a forced outage and it is the only gas-fired unit on-line in the islanded system , one Bradley Lake unit shall be placed in deflector mode and operated in deflector until a gas-fired generator is placed on-line in the islanded area. 10/06/92 16:56 9077624540 CEA DISPATCH CTR @oo4 Interconnected Operation - Steady State While Bradley Lake is interconnected to the Anchorage system, its normal mode of operation shall be the speed mode for both units. During times of system load restoration, one Bradley Lake unit may be placed in the deflector mode if the amount of load to be restored will not exceed the export or operating limits of the Kenai systen. ATER WYNNE HEWITT DODSON & SKERRITT ATTORNEYS AT LAW MEMORANDUM TO: Bradley PMC Representatives FROM: Ron Saxton DATE: October 6, 1992 RE: Duties Assigned to Subcommittees ATTACHMENT 6 Suite 1800 222 SW. Columbia Portland, Oregon 97201-6618 (503) 226-1191 Fax (503) 226-0079 In response to a request at our last BPMC meeting to outline the assignments delegated to the various subcommittees, I had my legal assistant (Liz Westby) review the BPMC meeting minutes from 1989 to present and prepare the attached list of tasks. Note that some of the tasks have been completed, but are included on the list for your reference. Distribution: BPMC Utility Managers Paul Diener, City of Seward Ken Ritchey, MEA Dave Highers, CEA Norm Story, HEA Mike Kelly, GVEA Tom Stahr, ML&P ACA j= ae. \>ReV t ot teal Seattle, Washington Washington, D.C. San Francisco, California (206) 623-4711 (202) 785-0303 (415) 421-4143 Fax (206) 467-8406 Fax (202) 785-8676 Fax (415) 989-1263 Affiliated offices in Anchorage, Fairbanks and Juneau, Alaska TO: Ron Saxton FROM: Liz Westby DATE: October 6, 1992 RE: Duties Assigned to the Bradley Lake PMC Subcommittees The following are tasks assigned to the Bradley Lake PMC Subcommittees (as referenced in the meeting minutes). AGREEMENTS SUBCOMMITTEE Tasks: e Look at other agreements for consolidation and coverage. (Minutes 7/2/91, p. 4) e Review Dispatch Agreement. (Minutes 11/19/91, p. 3) e Update Allocation and Scheduling Agreement Exhibits C and D. (Minutes 1/13/92, p. 3) e Work on Maintenance and Right of Way Agreements with Homer, (Minutes 1/13/92, p. 3) e Review and follow-up on: - Allocation and Scheduling Agreement Exhibit A - Dispatch Agreement - Transmission Facility Maintenance - Facilities Interconnected Dispatch - Communications MOU - SVCS Draft Agreement - Daves Creek Substation ~ Soldotna Substation (Minutes 3/26/92, p. 4) BUDGET (AND FINANCE) SUBCOMMITTEE Tasks: Develop draft definitions of Project (construction) costs versus utility costs. (Minutes 7/28/89, p. 4) Establish uniform accounting procedures for utility cost reimbursement. (Minutes 7/28/89, p. 4) Review issues: - cash flow timing; ~ budget revisions subsequent to budget adoption; - reserve accounting; ~ AEA staffing and overhead costs; - transmission costs; - environmental studies costs; - Intertie budget component. (Minutes 2/27/90, p. 3-4) Review issues: ~ HEA Transmission Line Maintenance; - AEA Costs; - CEA Software; ~ Dispatching labor costs. (Minutes 5/17/90, p. 4-5) Review of CEA and HEA Wheeling Agreement costs, and insurance. (Minutes 5/17/90, p. 6) Address the sinking fund payment that SWEC came up with for the scheduled maintenance and replacement of equipment. (Minutes 7/17/90, p. 8) Look at Homer Electric O&M expenses for the transmission line. (Minutes 7/2/91, p. 3) Analysis and discussion of (1) payments to the trustee to eliminate the cashflow problem, and (2) timing of payments. (Minutes 7/2/91, p.4) Prepare FY93 budget. (Minutes 11/19/91, p. 2) Resolve wheeling issue with HEA. (Minutes 1/13/92, p. 2) INSURANCE SUBCOMMITTEE Tasks: Review need for formal risk assessment of Bradley Lake Project required by insurers in order to develop quotes for property insurance. (Minutes 5/4/89, p. 3) Inventory types of insurance required, such as business interruption Insurance. (Minutes 6/8/89, p. 5) Review of possibility of pooled insurance coverage with the Alaska Intertie and/or Four Dam Pool. (Minutes 10/19/89, p. 5) Prepare insurance alternatives for the budget. (Minutes 11/30/89, p. 3) Consideration of errors and omissions insurance for SWEC. (Minutes 11/30/89, p. 3) Review Stone & Webster Risk Management Report. (Minutes 4/6/90, p. 3) Review property insurance premium quotes from the Division of Risk Management. (Minutes 11/28/90, p. 2) Look (to Corroon & Black) for a provider interested In providing boiler and machinery as well as business interruption insurance. (Minutes 6/6/91, p. 5) Look at coverage of debt service payment and operation and maintenance debt service for at least one year. (Minutes 6/6/91, p. 5-6) Request quotes on insurance premiums. (Minutes 10/25/91, p. 3) Review shop and crew facilities insurance coverage. (Minutes 4/28/92, p. 2) Review options and present recommendations for the level and types of insurance, including an option of not renewing the insurance (self-insurance), extra insurance, and not increasing the contingency fund. (Minutes 4/28/92, p. 3) OPERATING AND DISPATCH AGREEMENT SUBCOMMITTEE Engage services of a consultant to assist with drafting language for the Allocation and Scheduling Agreement. (Minutes 5/4/89, p. 6) Draft Bradley Lake Allocation and Scheduling Agreement. (Minutes 10/19/89, p. 5) Develop agreements and distribute to members. Agreements include: - Dispatch Agreement between AEA and CEA = Maintenance Agreement between AEA and Maintenance Contractor - Transmission Facilities Maintenance Agreement between AEA and HEA - Participants Allocation & Scheduling Agreement - Substation Maintenance Agreement between AEA and HEA - Joint Operations Agreement between CEA and HEA ~ Communications Equipment Agreement between AEA and Division of Telecommunications - Soldotna #1 Dispatch Agreement between CEA and AEG&T (Minutes 7/28/89, p. 4) Select a representative to review and provide comments on the Four Dam Pool draft technical standards. (Minutes 7/28/89, p. 6) Review of presentations on project hydrology, turbine efficiencies and reservoir model for forecasting reservoir inflow and utility demands. (Minutes 1/18/90, p. 5) Review of draft Dispatch Agreement. Work on 2 issues: (1) spinning reserve, and (2) losses on the Homer transmission system. (Minutes 2/27/90, p. 4) Review results of SWEC model on spill allocation. (Minutes 4/6/90, p. 5) Discuss the Allocation and Scheduling Draft Agreement, the operation of the transmission line after Homer Electric has completed their construction. (Minutes 3/5/91, p. 5) Determine the allocation method to be used for Bradley Lake power prior to commercial operation. (Minutes 3/5/91, p. 6) offs TECHNICAL COORDINATING SUBCOMMITTEE Develop a method for tracking and accounting for costs associated with dispatching during generation tests from Bradley Lake. (Minutes 6/6/91, p. 2) Discuss load restoration procedures, loss and billing procedures. (Minutes 6/6/91, p. 4) Develop procedures to allow the Bradley participants to readily note or record Chugach's service needs for Kenai area combustion turbine versus those conditions of providing combustion turbine to support the operation of Bradley Lake. (Minutes 7/2/91, p. 3) Review comments on Dispatch Agreement and reservoir model. (Minutes 11/19/91, p. 3) Meet and discuss maintenance and outage schedule with dispatchers. (Minutes 11/19/91, p. 3) Continue work on Allocation and Scheduling Agreement, Dispatch Agreement, Transmission Maintenance Agreement, Facilities Interconnected Agreement. (Minutes 2/28/92, p. 3) Participate in National Weather Service demonstration (to aid in allocation). (Minutes 2/28/92, p. 4) Review of SCADA communications problem. (Minutes 3/26/92, p. 5) Review and make recommendations on Bradley Lake project start-up charges. (Minutes 3/26/92 p. 7) Discussion of common ring-down circuit and communications problems. (Minutes 6/16/92, p. 5) Develop draft operation and maintenance definitions and responsibilities. (Minutes 8/29/88, p. 4) Appoint a member to serve on the Power Authority Configuration Control Board. (Minutes 9/27/88, p. 2) =5 Meet with SEI regarding their assessment of reliability of the Bradley Junction to Fritz Creek transmission line. (Minutes 1/20/89, p. 2) PTI presentation on Phase II Stability and Reliability. (Minutes 3/3/89, p. 2) Review bids for SCADA system. (Minutes 3/3/89, p. 2) Make presentation to PMC regarding proposed PTI 115 kv additions. (Minutes 4/6/89, p. 2) Review scope of work for system stability studies prepared by SWEC and proposal from PTI to complete additional stability work. (Minutes 6/8/89, p, 3) Review of software program DECNET. (Minutes 6/8/89, p. 3) Continue review of stability issues (Woodward governor). (Minutes 7/28/89, Pp. 2) Work on surge tank analysis. (Minutes 7/28/89, p. 3) Review and presentation of Load Acceptance Analysis report prepared by SWEC. (Minutes 1/18/90, p. 2) Prepare testing procedures prior to commercial operation. (Minutes 1/18/90, p. 3) Study of microwave link between Divcom and CEA main headquarters. (Minutes 1/18/90, p. 8) Provide an opinion on test period power agreement, interim operational period. (Minutes 7/17/90, p. 7) Approve SCADA point list. (Minutes 9/21/90, p. 2) Review, approve SWEC's recommendation on the installation of the braking resistor, installation of digital stabilizers on the units, installation of one SVS at the Daves Creek side and in Soldotna. (Minutes, 11/28/90, p. 2) Review how the project should be operated under different scenarios and define certain operation constraints. (Minutes 11/28/90, p.2 ) abe Review overfrequency tripping for Cooper Lake to try and control the frequency during times of high Kenai energy export. (Minutes 3/5/91, p. 2) Determine the maximum Kenai import (i.e. minimum Bradley Lake operating limit without a gas turbine on-line, assuming that any single contingency event will not result in more than a reasonable loss of load (and define "reasonable."). (Minutes 3/5/91, p. 3) Review of PTI study of operating restraints for the testing and commissioning phase. (Minutes 6/6/91, p. 2) TCS work with SWEC to gather all operating restrictions and recommendations relating to Bradley Lake within the past 2-3 years into one document for reference. (Minutes 6/6/91, p. 3) Develop operating scenarios with 80 MW and 90 MW caps. (Minutes 6/6/91, p. 7) Set the operating criteria for Bradley based on Homer Electric and Seward being subject to no more than stage two load shedding for any single contingency event, using interim operating criteria until such time as the final operating conditions are adopted by the PMC. (Minutes 7/2/91, p. 3) Oversee SWEC sponsored tests and other utility required tests. (Minutes 8/23/91, p. 3) Review Bradley Lake Operating Manuals. (Minutes 8/23/91, p. 3) Review of PTI Bradley Lake/Kenai Operating Guidelines. (Minutes 11/19/91, p. 2) Review of Bradley Lake Dispatcher Guidelines Summary. (Minutes 1/13/92, p. 4) Report on results of exciter tests. (Minutes 2/28/92, p. 2) Appoint a representative to accompany the tunnel inspectors. (Minutes 3/26/92 p. 7) Expansion of Bradley Lake Operating Conditions, interim operating levels. (Minutes 4/28/92, Attachment A, p. 2) a .., 16788792 18:27 & 503 226 3879 ATER WU t 82 » 1992 As Submitted fo After Wynne PROJECT COSTS UNREIMBURSED BRADLEY LAKE COSTS COSTS INCURRED July through ay} i a al Hl lols R=91% 503 226 0079 10-08-92 05:35PM POO2 #23 e16=a 6L00 922 €0S WdS€:S0 26-80-01 €c# €00d a a SECTION 31 OR OPERATING BUDGET COSTS &2(a) BPM ORGANI- ZATION =) 23,760.58 | 21760.50 BPMC LEGAL Cs ee ee APPROVED AT BPMC MEETING __(0/9/ 7 SIGNED: [Nash FE Dbghe CHEGACH: No costs submited. GVEA: No costs submitied. inclucies cost information ffrough April, 1992. HOMER: Inctudes cost information from May through Septernber, 1992. MATANUSKA: No costs submiited. Cost form ciaims zero expenses itrough May 15, 1992. MLEP: Mo costs submitted. SEWARD: No costs submilted. includes cost information through April, 1992. ATER WYNNE: Inclucies legol fees and costs fom July through September 1992. reayemec 87:8 76788781 620e 9z7z ses & a yale £8 R=91% 10788792 18:28 S 503 226 6879 ATER & Porward completed chart to: Ron Saxton Atar 222 sW Columbia, Ste. 1800 Portland, OR 97201 UNREIMBURSED BRADLEY LAKE COSTS UTILITY _Ater Wynne ss MONTH July - September, 1992 RETURN NO LATER THAN PROJECT COSTS 1990 FINANCE TEAM PARTICIPATION All travel-related expanses for members of the Finance Taam for trip and meetings associated ‘with the second financing. LECAL EXPENSES FOR PINANCING EFFORTS Legal fees of the Committees atterney rolating to the second finansing effort OPINIONS OF COUNGEL Scope of work on 1990 second financing effort to be determined later, TCC EXPENSES Travel and meeting expenses associated with your utility’s participation on the Technical Coordinating Committes. Do not include amounta for staff time. SECTION 31 OR OPERATING BUDGET COSTS BPMC ORGANIZATION (a) BPMC-approved costs for conducting Committee meetings and general business. (b) Legal expenses for representation of Committee. PREPARED BY Liz Westby = = ~=~=—=»- APPROVED BY 4 503 .226 0079 10-08-92 05:35PM P0004 #23 “wit ee R=91% 10708792 16129 & 503 226 0079 ATER E Porward completed chart to: Sena copy tor Lin westhy iTaeka anaryy htcnority Scott vies etal. Jetcrage, aiuaxa vva.s-0503 . Part innn. OR Nigh eat T UNREIMBURSED BRADLEY LAKE COSTS UTILITY Momet Electric Accociation, Inc. MONTHS. May, June, July, August & Sept., 1992 RETURN NO LATER THAN PROJECT COSTS Al 1990 FINANCE TEAM PARTICIPATION All travel-related expenses for meubers of tha Pinance Team for trips and meetings associated with the second #innanaing. LEGAL EXPENSES FOR FINANCING FFFORTS Legel eee of the Committee alvoracy Saxton will provide talating to the second financing ta ARA effort. = eel 1990 OPINIONS OF COUNSEL Scope of vork on 199M aannnd fLnanciag None unti] requseted OtforL Lu be determined lates, by AHA May -0- | TCC EXPENSES June -0- Travel and meeting expenses associated Tuly = $114.45 with your ucility’s partdeipacion on Aug. ~- $114.39 the Technical Coordinating Committee. Scpt. - -0- Be act inejun amounts for atafft tina. SECTION 31 COSTS ioe $15.39 BPMC ORGANIZATION $117.48 (a) M¥NC-approved Lusts for sendueting $ 99.00 Committee meetings and geussal busiowse. : ae Leqel expenses for representation Gaxteo vill provide of Comittas, ‘April Charges not previously submi' te ABA rte , PREPARED BY Corel A Mashagited—- NPPROVED BY eb fbr Carol A. Wumbyrd 9 “Yela/pe— Rick Eckert Admin. /Races Analyst Manager. Accnunring & Rates 503 226 0079 10-06-92 05:35PM POOS #23 d Bradley Lake PROJECT MANAGEMENT COMMITTEE MEETING RECORD VOPY —Oclidseh) FY, 1992 FILE NO (Date) ; Pep) 3-} 7 (Location) / 16 PLEASE SIGN IN No. NAME REPRESENTING 1 e lyolF AER 2 | Abe'm SY y HEA | 3 Dawe Fare HLA 4| J304 Hutma— AEG iz s| DAVs CacvuérRe SLS 6 “‘Rewores fuwny Ged 1 | om SAL Ll EP 8 | Tin ME Conn-el) Miy¢pr 9 | Lob /rice MLE 10 “ie * <l| GvEA uff | hoa ¢ hengeeLk 12 | Ren Lyle Darchuing VA tay 13 | Om LOVAS - HOC ACH- 14 | Geve ‘eens7Tad Che gee | 15_| Mines LS epoch 17 92Q2\IT9884 RECORD VCOPY FILE NO Alaska Energy Authority r BRADLEY PMC VOTING oe 9 (gor 0 = MAJORITY YOTING METHOO A: REQUIRING 4 YEAS W/ 51% OF UTILITIES, WITH NO APA VOTE; 1) PROCEDURES FOR SCHEDUUNG, PRODUCTION AND DISPATCH OF PROJECT POWER. 2) ESTABUSHMENT OF PROCEDURES FOR USE OF EACH PURCHASER'S WATER ALLOCATION (APA ASSENT REQUIRED FOR FERC UCENSE REQUIREMENTS). 3) SELECTION AMONG ALTERNATIVE METHOOS THAT (0 NOT INVOLVE APA FOR FUNDING REQUIRED PROJECT WORK. VOTING METHOD C: UNANIMOUS VOTE BY ALL (INCLUDING APA): ADOPTION OF PROCEDURES FOR DISPUTE RESOLU- TION. MAJORITY VOTE (INCLUDING APA). ELECTION OF OFFICERS. VOTING METHOO §: REQUIRING 4 YEAS W/ 51% OF UTILITIES, AND APA CONCURRENCE; 1) ARRANGING OPERATION AND MAINTENANCE OF PROJECT. 2) ADOPTION OF BUDGET OF ANNUAL PROJECT costs. 3) ESTABUSHMENT OF FY ESTIMATED ANNUAL PAY- MENT OBUGATION AND SCHEDULE OF EACH PUR- CHASER. 4) DETERMINATION OF ANNUAL PROJECT COSTS AFTER EACH FY. 5) EVALUATION OF NECESSITY FOR AND SCHEDUUNG OF REQUIRED PROJECT WORK. 6) DETERMINATION OF APPROPRIATE AMT. OF IN- SURANCE. 7) ADOPTION OF ADO'L MIN. FUNDING AMTS. FOR RENEWAL AND CONTINGENCY RESERVE FUND ABOVE THAT REQ. BY BOND RES. 8) SELECTION AMONG ALT. METHOOS THAT INVOLVE APA FOR FUNDING REQ. PROJECT WORK. pour Cree O27 sk le Wel sake | || ate a eae he V CITY OF SEWARD 01% iat REM / MATANUSKA ELEC ASSOC 14% eee | idl / CHUGACHELECASSOC 30% rg // HOMER ELEC ASSOC wm WL) “ GOLDEN VALELECASSOC 17% MLL Ce / MUNI LIGHT & POWER snes a VET] VL] Ae ll dae ek / ALASKA ENERGY AUTH 291 %ugze™'* Poo a A 9) ADOPTION_OR AMENOMENT OF PROCE- DURAL COMMITTEE RULES (EXCEPT Dis- PUTE RES) 10) ADOPTION OF PROJECT MAINTENANCE SCHEDULES. 11) DETERMINATION OF RULES, PROCE- DURES AND ACCOUNTS NECESSARY TO MANAGE PROJECT WHEN NO BONDS OUT- ‘STANDING. 12) EVALUATION AND APPROVAL OF OPTION- AL PROJECT WORK AND COMPENSATION FOR SUCH WORK 13) APPUCATION OF INSURANCE CLAIMS PROCEEDS NOT GOVERNED BY BOND RESOLUTION. 14) APPROVAL OF PROCEDURES ANO ANY INOMOUAL UTILITY AGREEMENTS RELATING TO ELECTRIC POWER RESERVES FOR PROJECT. 15) APPROVAL OF CONSULTANTS. Mr. Everett P. Diener City of Seward 5th & Adams P.O. Box 167 Seward, Alaska 99664 Mr. David L. Highers Chugach Electric Association 560I Minnesota Drive P.O. Box 196300 Anchorage, Alaska 99519-6300 Mr. Michael P. Kelly Golden Valley Electric Association 758 Illinois P.O. Box 1249 Fairbanks, Alaska 99707 Mr. Fred Arvidson Perkins Coie 1029 W. 3rd Avenue, Suite 300 Anchorage, Alaska 99501 Mr. James Hall Matanuska Electric Association 163 Industrial Way P.O. Box 2929 Palmer, Alaska 99645-2929 Mr. S.C. Mathews Homer Electric Association 3977 Lake Street Homer, Alaska 99603 Mr. Ron Saxton Ater Wynne Dobson & Skerritt 225 S.W. Columbia, Suite 1800 Portland, OR 97201-6618 90Q1D0068L(1) Distribution List Bradley Lake Hydroelectric Project Project Management Committee October 9, 1992 Mr. Ken Ritchey Matanuska Electric Association 163 Industrial Way P.O. Box 2929 Palmer, Alaska 99645-2929 Mr. N. L. Story Homer Electric Association 3977 Lake Street Homer, Alaska 99603 Mr. Thomas R. Stahr Municipal Light and Power 1200 E. Ist Avenue Anchorage, Alaska 99501-1685 Mr. Eugene N. Bjornstad Chugach Electric Association 560I Minnesota Drive P.O. Box 196300 Anchorage, Alaska 99519-6300 Mr. John Cooley Chugach Electric Association 5601 Minnesota Drive P.O. Box 196300 Anchorage, Alaska 99519-6300 Mr. Bob Hansen Golden Valley Electric Association 758 Illinois P.O. Box 1249 Fairbanks, Alaska 99707 Mr. Kurt Dzinich 4511 N. Riverside Drive Juneau, Alaska 99801 Mr. Robert Hufman Utilities Consulting Services 1018 Galena Street Fairbanks, Alaska 99709 Mr. David Burlingame Chugach Electric Association, Inc. P.O. Box 196300 Anchorage, Alaska 99519-6300 Mr. Tom Lovas Chugach Electric Association, Inc. P.O. Box 196300 Anchorage, Alaska 99519-6300 90Q1\D0068L(1) Distribution List Bradley Lake Hydroelectric Project Project Management Committee October 9, 1992 Lapaeive Research Agency Box Y Juneau, Alaska 99811-3100 Mr. Hank Nikkels Anchorage Municipal Light & Power 1200 East 1st Street Anchorage, Alaska 99501 Mr. Bob Orr Golden Valley Electric Association 758 Illinois P.O. Box 1249 Fairbanks, Alaska 99707 DATE: TO: FROM: SUBJECT: RECORD VOPY Alaska Energy Authority — =i no MEMORANDUM “ September 28, 1992 Bradley Lake Hydroelectric Project Project Management Committee Brent N. Petrie 8, Ge Secretary Project Management Committee Meeting October 9, 1992 The next meeting of the Bradley Lake Project Management Committee is scheduled Friday, October 9, 1992. The meeting will begin at 10:00 a.m. in the Training Room at Chugach Electric Association, Anchorage. The following items are enclosed for your information and review: ° PMC Meeting Agenda - October 9, 1992 ° Draft Minutes - August 24, 1992 PMC Meeting Approved Minutes - July 23, 1992 PMC Meeting ° Memorandum - August 21, 1992 Bradley Lake Seismic Data Collection (w/attachments) Please provide any comments regarding the upcoming October 9, 1992 PMC meeting agenda items to Chairman Highers. DB:BNP:db ue Dist. ae eegiee Aw Se DRE DATE: TO: FROM: SUBJECT: Alaska Energy Authority MEMORANDUM August 21, 1992 Bradley Lake Project Management Committee Ronald A. Garzini Interim Executive Director Rac Alaska Energy Authority Bradley Lake Seismic Data Collection As requested by the Project Management Committee (PMC) during the July 23 meeting, the Alaska Energy Authority recently met with the University of Alaska Geophysical Institute regarding seismic monitoring at Bradley Lake. During our meeting of August 6, 1992, Larry Wolf and I discussed with University representatives, Dr. Niren Biswas and Syun Akasofu, the project's seismic monitoring requirements and how the Institute could continue to support those needs. For the benefit of the PMC members to better address this issue, I believe it would be helpful to first explain the various seismic monitoring requirements at Bradley Lake. Design/Construction Requirements During the design/construction period, the seismic monitoring requirements at the project site consisted of data collection and analysis for purposes of establishing baseline historical records and verifying engineering design criteria for the project features. This task was initially being accomplished by the USGS until 1987 when the USGS began scaling back its data colleeticn efforts in Alaska. At that time the Energy Authority entered into a Reimbursable Services Agreement (RSA) with the University's Geophysical Institute to continue these services. The University purchased and installed seismic motion monitoring equipment onsite and interfaced this equipment with their state-wide database in Fairbanks. Utilizing the information collected, the University then provided a summary report of this data annually to the Energy Authority. Operational Requirements Now that project construction has been completed, the seismic monitoring requirements have changed. The primary emphasis is to support operational needs which consist of two basic elements. First, is a FERC requirement that we monitor the dam site for seismic events of 5.0 Richter scale or greater. 92Q3\JD3409(1) Page 1 Memorandum to Bradley Lake Project Management Committee Subject: Bradley Lake Seismic Data Collection August 21, 1992 2 Project Maintained System An alternative means of fulfilling the project's seismic monitoring requirements would be the purchase and installation of seismic equipment which would be entirely operated and maintained by onsite personnel. The proposed monitoring system (see attached Stone & Webster letter dated June 5, 1992) would provide for operator alarm via the SCADA network for earthquakes over 5.0, and would also automatically record and store the seismic information. In the event this seismic data base was needed to support future engineer studies, it could easily be analyzed by the Geophysical Institute or through the use of an engineering consultant. This project data base could also be made available to the Institute for their state-wide research effort. The estimated cost for the initial equipment purchase, installation and operator training is $30,000. The subsequent annual maintenance of the system is estimated at $5,000 per year. The only additional cost would be the cost of data analysis if and when it became necessary. Summary The seismic monitoring requirements at Bradley Lake can be accomplished using either of the two methods outlined above. The Energy Authority's previous intent to discontinue the services of University's Geophysical Institute was based primarily on economics and system reliability. However, we recognize that beyond the operational requirements there may be additional scientific benefits in monitoring the site for induced earthquake activity during the initial years of operation and being part of the Institute's state-wide seismic data collection and research program. For this reason, the Energy Autherity is willing to extend the RSA agreement with the University to continue seismic data collection services related to monitoring and analyzing seismic activities for a period of three years. The Energy Authority, for reliability reasons, will also be installing and maintaining a separate monitoring device for the operator alarm function. We recommend that after the three year period, the Bradley PMC review the University's seismic data collection program to determine whether or not continuation of program is in the project's best interest. I must also point out that the current FY93 budget allowance for seismic data collection is only $20,000. To fund the University's program and install the additional monitoring device, the total budget requirement for this year will be approximately $50,000. Therefore, with the PMC concurrence, a $30,000 increase in this budget item will be made. Unless I am advised otherwise, we will proceed as outlined above. DE:RAG;jd 92Q3\JD3409(3) Page 3 Memorandum to Bradley Lake Project Management Committee Subject: Bradley Lake Seismic Data Collection August 21, 1992 (Whenever these occur, we must inspect the project features for damage and report to FERC). Second, is the desire to record ground motion data during such events so that the data would be available to support any future engineering/design analysis which may become necessary. In addition to these operational needs, but of a lesser importance, is the interest in continuous seismic monitoring and analysis for induced earthquakes caused by the variation in reservoir levels. Monitoring Alternatives 1. Continued use of Geophysical Institute The Energy Authority's original plan to meet the seismic monitoring during construction and to support the long term operational requirements of the project, was to utilize the service of the University's Geophysical Institute. Although several factors (and in particular increased costs) induced us to re-evaluate this alternative, the University remains a possible option for accomplishing the work. The Institute can continue to record and store the Bradley Lake information in their state-wide data base, analyze the data, and report annually to the Energy Authority. Although this analysis would have the added benefit of identifying any reservoir induced earthquake activity, the report itself would be of little or no benefit to project operations unless there was a significant event over 5.0 on the Richter scale. In questioning the Institute regarding possible cost reductions, they advised us that analyzing data on an "as-needed basis only" would not be feasible, because the data for Bradley would be difficult to retrieve from the Institute's computer data base after an extended period of time. The Institute's projected annuai cost for providing the data collection and analysis service is $38, [00 (see attached University of Alaska letter dated March 6, 1991). Technically, the University's onsite equipment could also be equipped to provide the alarm signal for earthquakes over 5.0. However, based on our experience to date, we would recommend the installation of a separate monitoring device for this purpose. This added device would be maintained by onsite project personnel and would therefore be much more reliable and immediately responsive to any significant events. Alarming via the Institute's equipment may not be responsive to our needs as their equipment is sometimes inoperable for extended periods of time due partly to the accessibility of their personnel. The fact that the Institute is not manned on a continuous basis, and the relatively complex nature of their equipment increases the system reliability problems. The estimated cost for purchase and installation of the additional monitoring device is approximately $10,000. Annual maintenance cost is projected to be approximately $1,000 per year. 9203\JD3409(2) Page 2 STONE & WEBSTER ENGINEERING CORPORATION ReCOKD COPY 7677 EAST BERRY AVENUE FILE NO A ENGLEWOOD, COLORADO 80111 - 2137 ADORESS ALL CORRESPONDENCE TO P.O. BOX 5406, DENVER, COLORADO 80217-5406 W.U. TWX: 910 935-0105 TELEPHONE: 303 741-7700 FAX: 303-741-7670 W.U. TELEX: 45-4401 RCA TELEX: 289251 303-741-7671 BOSTON MA NEW YORK NY CHATTANOOGA. TN OAK RIOGE TN CHERRY HILL NJ PORTLAND ME CHICAGO. IL PORTLAND. OR DALLAS Tx RICHLAND WA DECATUR AL RICHMOND VA DENVER CO PLEASANTON. CA FT LAUDERDALE. FL TAMPA FL HOUSTON. TX WASHINGTON OC -. THORITY Mr. D. R. Eberle ‘ June 5, 1992 Project Manager Alaska Energy Authority J.O. No. 15800.50 701 East Tudor Rd. WP 20A Anchorage, AK 99503 SWEC/AEA/2866 SEISMIC MONITOR BRADLEY lY In reference to our letter of May 20, 1992 (SWEC/AEA/2857), attached is the information we received from Kinemetrics/Systems regarding the seismic monitoring system for the Bradley Lake Dam. We recommend this system for the Bradley Lake Project, which may already be in place and the property of AEA. The training package available from Kinemetrics may be purchased separately as indicated in the quote from Kinemetrics. The Operations personnel at the Bradley Lake Project are well qualified to receive this training and then will be able to preform the necessary calibration and maintenance required for the equipment, as well as, retrieve the data from the seismic monitors. The data retrieval and maintenance is about the same complexity as other project equipment and should be done easily by the current personnel. Actual analysis of the data needs to be performed by qualified personnel when a significant seismic event occurs. We can provide this service to you, or there are several qualified organizations within Alaska that can perform this analysis. Regarding the gate closing logic, as mentioned in our above referenced letter, the trigger switches available with these monitors have not demonstrated reliable enough operation for automatic power tunnel gate closure or unit shutdown applications. We recommend that the trigger switch be used for an alarm with the operators determining the need to retrieve data, shutdown units, or close the gate. — WM 000869. wpt/BLO0S : 1889 + STOWE @ WEBSTER : LLY Ys 1989 £o f Mr. D. R. Eberle June 5, 1992 Page 2 Messrs. John Yale and Jonathan Hodges plan to investigate the existing seismic equipment currently at Bradley Lake during their next visit to the site for testing of the DECnet and the remote RTUs. Once we have determined what equipment is presently on site, we will advise you of additional equipment and installation work recommended for an operational system. If you have any questions or comments, please call. nil Hedger Theodore Critikos Project Manager Attachments TC/JH/swg ce: Mr. Larry Wolf CORRESPONDENCE DISTRIBUTION 1D00869.wpf/BLOOS KKK —— May 7, 1992 KINEMETRICS Jim Meisenheimer Stone & Webster P.O. Box 5406 Denver, Colorado 80217-5406 Subject: Bradley Reservoir, SSA-1 Replacement System Refernence: Our telecon, May 4 1992 Dear Jim, The budgetary numbers you requested for two solid state accelero- graphs and training follow. As we discussed, the new generation of solid state accelerographs are intended to be less subject to the skills of the technician performing the preventative maintenance activity. If a board is not functioning, someone with a general knowledge of the instrument could be reasonably expected to swap boards and send the faulty board to Pasadena for repair. Operation and maintenance level training for the solid state accelerographs could be provided in two days for two to three students. Three days would be required for four to six students. The SWS-1 Strong Motion Analysis software package can be taught in one day. However, I recommend that the processing of any strong motion data be performed by or, at least reviewed by, an engineer or scientist experienced in this work prior to publication of the processed data. Thank you for your interest in Kinemetrics products and services. Please feel free to contact me should you have any questions or comments regarding this proposal. Sincerely, Noted J. K.MEISENHEIMER Mly 19 ‘92 Rod Merril Manager of Services RAM: 1lpc enclosures: noted cc: John Diehl, Vice-President, Kinemetrics, Inc. Mel Lund, Vice-President, Kinemetrics, Inc. KINEMETRICS/SYSTEMS, 222 VISTA AVENUE, PASADENA, CA 91107 - (818) 795-2220 - TELEX 67-5402 KMETICS PSD - FAX (818) 795-0868 KKK ae KINEMETRICS PROPOSAL INVOICE TO: SHIP TO* Stone & Webster Please Advise P.O. Box 5406 Denver, Colorado 80217-5406 Attn: Jim Meisenheimer Customer RFP No.: Verbal/Meisenheimer Date: 4/MAY/92 FOB: Jobsite Proposal No.: K2-022 Date: 7/MAY/92 CIF/CF: --- Payment Terms: Net 30 days Delivery: Hardware 90 days ARO, Training Representative 30 days after shipment. Quotation Validity: 120 days Approved by: Item Qty Type Description 1s 2 Model: SSA-1 Solid State Accelerograph $ 13,000.00 2g full-scale, 0.5 Mbyte CMOS RAM. Unit price is $6,500.00 as Lot Memory expansion to 1 Mbyte total per 750.00 accelerograph. Unit price is $375.00. 35 Lot Communications and Utility Software N/C QuickTalk (QTSSA) Communications Software “ Package, 2 disks including; QuickLook (QLSSA) for SSA, ASCII file converter, and related utility programs. Supplied with each SSA-1 order. 4. ak Model OM-PCB-251 Omega Receiver Option, 1750500 includes: antenna, 50’ coax and PA-12 pre- amp. Additional coax cable, 50 ft, $80.00. SPARES AND SUPPLIES S- ak Analog to Digital Converter Board 875.00 6: £ I/O Processor Board 630.00 oe 1 Data RAM Controller Board 465.00 8. a Data Storage Module, 1 Mbyte 970.00 O42 1 Power Supply and Sequencer Board 650.00 KINEMETRICS/SYSTEMS, 222 VISTA AVENUE, PASADENA, CA 91107 - (818) 795-2220 - TELEX 67-5402 KMETICS PSD - FAX (818) 795-0868 Quotation KMS K2- Stone & Webster May 7, 1992 Page 2 of 3 11.1-Lot 72 11.2 Lot 72 12:.1; Lot 72 022 Description Price Subtotal, hardware $ 19,090.00 SWS-1 Strong Motion Analysis 1,500.00 Software package; will run on any 100% IBM compatible PC operating with 8087 math co- processor and EGA graphics, PC-DOS (MS- DOS) Version 3.1 or compatible. Suggested hardware is: Compaq DeskPro 386/20e or equiv. 40 Mbyte hard disk 4 Mbytes RAM 1 Serial Port 1 Parallel Port 80387 Coprocessor VGA monitor and adapter Dot matrix printer (Epson) w/ cable MS-DOS Version 3.3 On-site training for installation, maint- 7,055.00 enance and operation of Kinemetrics Model SSA-1 units. Price includes all student course materials and instructor expenses (i.e. airfare, hotel, meals, ground transportation, etc.). Optional SWS-1 training to plant $ 1,200.00 engineers including; data retrieval, data reduction, and data analysis. Analysis includes differentiating seismic from non- seismic events, filter selection criteria and analyis of sample data. Pe 1 ese assumes training provided immediately following delivery of Item 11.1 and requires one (1) additional day on-site. Optional factory training per Item 11.1. $1000/student, minimum three and maximum six students. Price includes all student course materials. Student expenses not included. Quotation KMS K2-022 Stone & Webster May: 7, 1992 Page 3 of 3 Item Qty Type Description Price 12752 Lor F2 Optional factory SWS-1 training per Item 11.2. No charge if provided in conjunction with factory SSA-2 training. Otherwise, $600/student, minimum three and maximum six students. Subtotal, on-site SSA-2 and analysis soft- S) 1 9i:755,,.00 ware training; includes analysis software package. TOTAL, hardware, software and training $ 28,845.00 SCOPE OF WORK Kinemetrics shall provide a three day training course per blocks 1 through 12 of the attached SSA-1 Course Outline. Kinemetrics shall supply the course materials for the students (6 max.) in attendance plus one (1) extra set. DELIVERY SCHEDULE Not currently scheduled. December, January, February, June, July and August are months in which training can be provided. INCLUSIONS The firm, fixed price includes the following: All mobilization labor including travel planning, preparation of special test equipment, file search to determine original system specifications. All portal-to-portal travel labor, including overtime charges, for the Instructor/Field Engineer (based in Pasadena, California). All on-site labor, including any overtime charges, for the scheduled duration of the work. All portal-to-portal travel and living expenses including air and ground transportation, parking, lodging and meals for the instructor. Air freight fees for shipment of all training materials. COURSE OUTLINE OPERATION AND MAINTENANCE OF THE MODEL SSA-1 SOLID-STATE ACCELEROGRAPH KINEMETRICS/SYSTEMS 222 No. Vista Avenue Pasadena, California 91107 (818) 795-2220 REV.E, 2-18-91 COURSE NAME: Operation and Maintenance of the Page 2 Model SSA-1 Solid-State Accelerograph Instructor References: Operating Instructions: Model SSA-1 Solid State Accelerograph Service Information Manual: Model SSA-1 Solid State Accelerograph Interface Manual: SSA-1 Operating Instructions: QL16 Quick-look* Display Utility All Acceptance Test Procedures for SSA-1. All Schematic diagrams All wiring diagrams Training Materials Required: 1 SSA-1 for each three students 1 IBM-compatible computer for each three students Computer/SSA interconnect cables/MS-DOS** Crosstalk***program on diskette Quick-look program on diskette Standard SSA-1 Support Software Operating Instructions: Model SSA-1 Solid-State Accelerograph Operating Instructions: QL16 Quick-look Display Utility SSA-1 Interface Manual Classroom Requirements: Whiteboard with markers Tables and workbenches Typical shop support such as small tools, test lead, and instrumentation including voltmeters and oscilloscopes. Prerequisites Anyone may attend this course. A working knowledge and background in analog electronics, digital electronics, and microprocessors is recommended in order for the student to understand the theoretical portions of the course. Evaluation This course does not include formal testing and evaluation of students. Each student is, however, expected to report promptly for classes, attend all designated blocks of instruction and actively participate in laboratory portions of the course. Class Size Kinemetrics will try to accommodate any number of students that the customer wishes to have attend this course. Experience has shown, however, that six students is the optimum number and about ten students is the practical maximum. *Quicklook is a Trademark of Kinemetrics/Systems **MS-DOS is a trademark of Microsoft ***Crosstalk is a trademark of Microsuff COURSE NAME: Operation and Maintenance of the Page 3 Model SSA-1 Solid-State Accelerograph Training Objectives: This course may be tailored and priced to meet the requirements of Customer’s formal task analysis and specific requirements. In the absence of such input, the standard course is designed to meet the following objectives. At the completion of the course, the student will be able to: 1. sy | ae Identify the major assemblies of the SSA-1 and describe their purposes and relationships. Install the SSA-1 in a typical field or structural situation including physical attachment and electrical interconnection. Using a "laptop" computer and commercially available communications software, establish communication with the SSA-1. Set header parameters. Perform, display and interpret functional tests. Retrieve EQ records. Scale dominant frequencies and peak acceleration levels of earthquake using Quick-look. Perform field exchanges of malfunctioning boards. Have sufficient background in SSA-1 theory that, given the trainee’s existing skills in analog and digital electronics, laboratory repair to the component level may be performed in an efficient manner. COURSE NAME: Operation and Maintenance of the Page Model SSA-1 Solid-State Accelerograph Presentation: This course is divided into four sections. The customer may select one or more sections for presentation. Each section is divided into blocks of instruction lasting about 3-1/2 hours per block. BLOCK 1: INTRODUCTION Introductions Preview of class, etc. Comparison of SSA-1 to previous designs SSA-1 concept and construction Typical Applications BLOCK 2: PORTABLE COMPUTERS PC-compatible laptop computers Keyboards, disk drives, floppy and hard MS-DOS; booting up, copying files, Crosstalk, Etc. Includes time for students to practice with computers. BLOCK 3: INSTALLATION Physical installation - mounting SSA-1 Electrical connections a. power b. signal c. interconnection with computer d. modems, extended interconnect option, etc. e. balancing accelerometers f. connecting batteries, etc. BLOCK 4: BASIC OPERATIONS Establishing communication with SSA-1 Basic commands and setting parameters Performing functional test Standard maintenance program Using Quick-look to evaluate functional tests. BLOCK 5: BASIC OPERATION (continued) Expanded discussion of commands and parameters. Retrieval and proper handling of earthquake records. Scaling frequencies and acceleration levels using Quick-look. Students practice with computers and SSA-1’s. COURSE NAME: Operation and maintenance of the BLOCK 6: BLOCK 7: BLOCK 8: BLOCK 9: BLOCK 10: BLOCK 11: BLOCK 12: Model Solid-State Accelerograph TRIAXIAL AND UNIAXIAL FORCE BALANCE ACCELEROMETERS Theory of operation Construction, acceptance Testing anc Calibration Trouble shooting Malfunctions Students Test and Calibrate Acclerometers Page 5 OVERVIEW: SSA-1 CHASSIS, POWER SUPPLY, AND TRANSITION BOARD Lecture on theory of operation and signal/power path. Discussion of construction, acceptance testing and calibration. Discussion of possible malfunctions and troubleshooting. Students examine and test chassis as time permits. OVERVIEW: A TO D CONVERTER Lecture on design, theory of operation and signal path. Discussion of construction, acceptance testing and calibration. Discussion of possible malfunctions and troubleshooting. Students examine and test A to D converter as time permits. OVERVIEW: 3 POLE FILTER Lecture on design, theory of operation and signal path. Discussion of construction, acceptance testing and calibration Discussion of possible malfunctions and troubleshooting. Students examine and test filter as time permits. OVERVIEW: I/O PROCESSOR Lecture on design, theory of operation and signal path. Discussion of construction, acceptance testing and calibration Discussion of possible malfunctions and troubleshooting. Students examine and test I/O processor as time permits. OVERVIEW:DATA RAM CONTROLLER AND DATA STORAGE MODULE Lecture on design, theory of operation and signal path Discussion of construction, acceptance testing and calibration Discussion of possible malfunctions and troubleshooting. Students examine and test controller and data storage module as time permits. OVERVIEW: RADIOS AND TIMING DEVICES Lecture on design, theory of operation and signal path. Discussion of construction, acceptance testing and calibration Discussion of possible malfunctions and troubleshooting. Students examine and test various timing options for the SSA-1 as time permits. COURSE NAME: Operation and Maintenance of the Model SSA-1 Solid-State Accelerograph BLOCKS 13 SWS-1 SEISMIC WORKSTATION and 14: Lecture on design, application and operation Software and hardware requirements Discussion of operation of SWS-1 Students process sample earthquake records. BLOCKS 15 SWS-1 SEISMIC WORKSTATION and 16: in depth discussion and study of SWS-1 programming. BLOCKS 17 to SSA-1 CALIBRATION 25:(1 week) BLOCK 26+: SSA-1 TROUBLESHOOTING BLOCK 27+: INDEPENDENT STUDY AND PRACTICE Students utilize training aids and test equipment for self-paced practice any desired level of operation or testing. Kinemetrics instructors are made available to assist and answer questions. This block may be repeated as many times as desired by Customer. Page 6 Solid State Accelerographs Domestic INSTRUMENTS List 3-1 SYSTEMS SERVICES Model Part Number Description Price SSA-1 107200 Solid State Accelerograph, 2g, .5 Mbyte CMOS RAM 6,500.00 SSA-1 with 1g, 1/2g, 1/4g full-scale optional sensors 6,500.00 SSA-1 without FBA deck, for use with FBA-23 5,760.00 (includes option P/N 107315) SOFTWARE 300130 QuickTalk for the SSA (QTSSA) Communications Software No Charge Package, 2 disks. Includes: QLSSA (QuickLook for SSA), ASCII file converter, and related utility programs. This software is supplied with each SSA-1 order. OPTIONS 107354-01 Memory Expansion to 1 MByte Total (in place of .5 MByte) 375.00 107354-02 Memory Expansion to 2 MBytes Total (in place of .5 MByte) 1,345.00 107354-03 Memory Expansion to 3 MBytes Total (in place of .5 MByte) 2,315.00 107354-04 Memory Expansion to 4 MBytes Total (in place of .5 MByte) 3,285.00 107305 Additional 3-Pole Filter Board 200.00 107310 Provision for Fourth Channel FBA-11 Input 95.00 107315 Provision for Extemal FBA-23 140.00 TCG-1A 107215-01 Time Code Generator (standard accuracy) 980.00 TCG-2 107210 Time Code Generator (high accuracy) 1,225.00 86-4 107220-04 WWVB Receiver, mounted in accelerograph 645.00 A60-FS 790011 Antenna for WWVB Receiver 325.00 86-5 107220-05 DCF-77 Receiver, mounted in accelerograph 790.00 A77.5-FS 790029 Antenna for DCF-77 Receiver, with 50 ft. coax 325.00 OM-PCB-251 107335 Omega Receiver Option, includes antenna, 50 ft. coax and 1,750.00 PA-12 pre-amp Additional coaxial cable, 50 ft. 80.00 SPARES 107300 Analog to Digital Converter Board 875.00 107325 I/O Processor Board 630.00 107340-01 Data RAM Controller Board 465.00 107350-01 Data Storage Module, 1 MByte 970.00 107350-02 Data Storage Module, .5 MByte 595.00 Prices are FOB Factory, Pasadena, California. Effective October 1, 1991. Printed in the U.S.A. Subject to change without notice. ee UU aaa ESSIEISS ESSE SSISSESSSSSSISSS SSSI nan KINEMETRICS INC, 222VISTAAVENUE, PASADENA, CALIFORNIA 91107 U.S.A. (818) 795-2220 TELEX 67-5402 KMETRICS PSD FAX (818) 795-0868 Solid State Accelerographs Domestic List 3-2 KKK SYSTEMS KINEMETMIC S&S Model Part Number Description Price 107290 Power Supply and Sequencer Board 650.00 107240 FBA Accelerometers and Deck Plate 1,840.00 (specify full-scale range: 1/4g, 1/2g, 1g, or 2g) 700181 Charger, battery (110/220 Vac) 45.00 ACCESSORIES Portable PC: NEC MultiSpeed HD, with 640kB RAM, 3.5" 3,075.00 720kB floppy disk drive, 20MB Fixed Drive, EL backlit screen, cigarette lighter adapter and carrying case. (For additional computer hardware, see price list 21) Extended Interconnect System, consists of: 1,030.00 ¢ Interface Box interconnect cable, SSA-1 to Box 700302 Cable, Box to Box, bulk, per foot 1.80 107375 Extender Board Assembly for SSA-1 115.00 107395 External Mounting Kit, including 3 hold down clamps, bolts, 45.00 concrete anchors and sealing plug for internal hole 700170-02 Internal Anchor Kit, including bolt, thread seals, washer and 4.00 concrete anchor XCELITE P4 7/16" Nut Driver for installation 8.00 TDC-1 790012 Time Display Controller for TCG-1 1,155.00 TDC-2 790013 Time Display Controller for TCG-1, with reference, TCG-1B 4,675.00 500305-02 Cable, local interconnect, SSA-1/2, 3 ft. 130.00 107393 Cable, SSA-1/2 to Modem RS-232C interface, 25 ft. 110.00 107392-01 Cable, SSA-1/2 to PC RS-232C interface, 25 ft. 145.00 107316 Cable, FBA-23 to SSA-1, with connectors, 10 ft. 210.00 840356 Additional cable, per foot 2.50 104022 Cable, FBA-11 to SSA-1, with connectors, 10 ft. 150.00 700277 Additional cable, per foot 1.50 SUPPLIES 103413 Battery Set, rechargeable, 12V ( 2 of LCR12V6.5P) 100.00 700300 Memory or Clock Back-up Battery, Lithium 15.00 700049 Desiccant 3.00 Prices are FOB Factory, Pasadena, California. Effective April 1, 1991. Printed in the U.S.A. ‘Subject to change without notice. KINEMETRICS/SYSTEMS, 222 VISTA AVENUE, PASADENA, CA 91107 - (818) 795-2220 - TELEX 67-5402 KMETICS PSD - FAX (818) 795-0868 Solld State Accelerographs Domestic | INSTRUMENTS List 3-3 KKK J SYSTEMS KINEMETRICS SERVICES Model Part Number Description Price SSA-2 108000 Solid State Accelerograph, with Internal Triaxial 3,850.00 Accelerometers, 256kB CMOS RAM (Specify full scale sensitivity: 2g, 1g, or 1/2g) SSA-2 without internal accelerometers, for use with FBA-23 3,350.00 (includes option P/N 108080) SOFTWARE 300130 QuickTalk for the SSA (QTSSA) Communications Software No Charge Package, 2 disks. Includes: QLSSA (QuickLook for SSA), ASCII file converter, and related utility programs. This software is supplied with each SSA-2 order. OPTIONS 108006 FBA accelerometers (in place of standard accelerometers), add 400.00 108094-01 Memory Expansion to .5 MByte (in place of 256kBytes) 230.00 108094-02 Memory Expansion to 1 MByte (in place of 256kBytes) 685.00 108094-03 Memory Expansion to 2 MBytes (in place of 256kBytes) 1,675.00 108080 Provision for External FBA-23 130.00 108065 Provision for Local Interconnect 130.00 108070-01 Provision for Extended Interconnect of SSA-1/2 665.00 (installed internal to SSA-2) 108070-02 Provision for Extended Interconnect of SSA-1/2 and SMA-1s 785.00 (installed internal to SSA-2) E 108100-01 Transient Protection Box with additional TransZorb protection 400.00 for Extended Interconnect 700302 Cable, Extended Interconnect to Extended Interconnect, per ft. 1.80 TCG-1A 108090-01 Time Code Generator (standard accuracy) 980.00 TCG-2 108088 : Time Code Generator (high accuracy) 1,225.00 86-4 108092-04 WWVB Receiver, mounted in accelerograph 645.00 A60-FS 790011 Antenna for WWVB Receiver, with 50 ft. coax 325.00 86-5 108092-05 DCF-77 Receiver, mounted in accelerograph 790.00 A77.5-FS 790029 Antenna for DCF-77 Receiver, with 50 ft. coax 325.00 OM-PCB-252-0 108085 Omega Receiver Option, includes antenna, 50 ft. coax and 1,750.00 PA-12 pre-amp Additional coaxial cable, 50 ft. 80.00 Prices are FOB Factory, Pasadena, California. Effective October 1, 1991. Printed in the U.S.A. ‘Subject to change without notice. KINEMETRICS INC. 222 VISTAAVENUE, PASADENA, CALIFORNIA 91107 U.S.A. (818) 795-2220 TELEX 67-5402 KMETRICS PSD FAX (818) 795-0868 Solid State Accelerographs Domestic . List 3-4 SYSTEMS KINEMETRICS Model Part Number Description Price ACCESSORIES Portable PC: NEC MultiSpeed HD, with 640kB RAM, 3.5" 3,075.00 720kB floppy disk drive, 20MB Fixed Drive, EL backlit screen, cigarette lighter adapter and carrying case. (For additional computer hardware, see price list 21) 107392-01 Cable, SSA-1/2 to PC RS-232C interface, 25 ft. 145.00 107393 Cable, SSA-1/2 to Modem RS-232C interface, 25 ft. 110.00 500305-02 Cable, local interconnect, SSA-1/2, 3 ft. 130.00 108003 Cable, FBA-23 to SSA-2, with connectors, 10 ft. 210.00 840356 Additional cable, per foot (for cable lengths less than 1000 ft.) 2.50 700045 Additional cable, per foot (for lengths from 1000 to 3000 ft.) 4.10 TDC-1 790012 Time Display Controller for TCG-1 1,155.00 TDC-2 790013 Time Display Controller for TCG-1, with reference, TCG-1B 4,675.00 SUPPLIES 840301 Battery, rechargeable, 12V (LCR12V6.5P) 50.00 700300 Clock or Memory Back-up battery, Lithium 15.00 700049 Desiccant 3.00 SPARES | 108020 Data Processor Board 1,280.00 108030 Analog to Digital and Power Supply Board 1,380.00 108035-01 256kByte Memory Board 305.00 108035-02 512kByte Memory Board 535.00 108035-03 1 MByte Memory Board 990.00 Prices are FOB Factory, Pasadena, California. Effective April 1, 1901. Printed in the U.S.A. Subject 10 change without notice. SS SSS KINEMETRICS/SYSTEMS, 222 VISTA AVENUE, PASADENA, CA 91107 - (818) 795-2220 - TELEX 67-5402 KMETICS PSD - FAX (818) 795-0868 Solid State Accelerographs Domestic List 3-5 KKK SYSTEMS KINEMETRICS Model Part Number Description Price SENSORS Extemal Force Balance Accelerometers:(Specify full scale range) FBA-11 105000 Uniaxial Force Balance Accelerometer 1,030.00 FBA-23 105610 Triaxial Force Balance Accelerometer 2,945.00 FBA-13DH 105085 Triaxial Downhole Accelerometer Package 6,970.00 Options for FBA-13DH: 105080 Yoke Adapter (one per FBA-13DH) 250.00 102516 Vulcanization of mating connector to cable (required for each 365.00 FBA-13DH) *Note: To complete downhole cable assembly, add: Cable, waterproof to 1000 psi, per foot 6.45 105060 Orientation Poles: Master Pole (one per order) 400.00 105071 Orientation Poles: 10 foot extension pole 100.00 105075 Clamp, loading pole (one per order) 415.00 105058 Wellhead Box (one per FBA-13DH) 380.00 107625 EPRI/YOUD Wedging System (requires yoke adapter and 1,420.00 orientation poles for installation, one per FBA-13DH) 107635 Wedging System Tamping Sleeve (one needed per order) 450.00 3/16 retrieval cable, per foot 1.95 Prices are FOB Factory, Pasadena, California. Effective April 1, 1901. Printed in the U.S.A. Subject to change without notice. ———— — ——————————————_————————————— KINEMETRICS/SYSTEMS, 222 VISTA AVENUE, PASADENA, CA 91107 - (818) 795-2220 - TELEX 67-5402 KMETICS PSD - FAX (818) 795-0868 . te Te IIS ITS March 6, 1991 Mr. David R. Eberle Project Manager Alaska Energy Authority P.O. Box 190869 701 East Tudor Road Anchorage, Alaska 99519 Re: Proposal GI 91-25 Earthquake Monitoring for the Bradley Lake Hydroelectric Project Dear Mr. Eberle: I could not write to you any earlier as I had to look over significant amount of paperwork to respond to your letter of January 31, 1991. However, I have addressed your inquiries as follows: (1) The Geophysical Institute of the University of Alaska Fairbanks has a yearly budget of about $12M per year of which 70 to 80% is derived mostly from federal grants and contracts issued to individual faculty for specified research projects. The remaining 20 to 30% is appropriated by the State of Alaska which is mostly for library maintenance, emergency support for salary, etc. Thus, the Geophysical Institute has no flexibility to support any specified project, like the seismic monitoring for the hydroelectric project or any part of it from its own resources. (2) The Office of Naval Research (ONR) has been designated by the federal government to set rates for the University overhead (OH) charges across the nation. It varies from 80 to 30% depending on the local costs. Our OH rate has been set by ONR to 45.5%; we have to apply it uniformly to all grants, contracts, RSA, etc., whether we like it or not. (3) The minimum requirement for the location of an earthquake is 5 to 6 station data gathered around the foci. This is because the location is an iterative least squares regression process. Accordingly, you have supported such an effort for the assessment of background seismicity of the hydroelectric project site by the U. S. Geological Survey. I was approached by your office te handle the earthquake monitoring project during and post reservoir impoundment phases. Being a member of a state University, I felt obligated to undertake the task, though it has nominal direct research component. I hoped to work closely with your office to establish a reliable and efficient system and once that system is established, to reduce the cost of operation to a minimum. Geophysical Institute, University of Alaska Fairbanks, Alaska 99775-0800 PHONE: 907-474-7558 TELEX: 35414 GEOPH INST FBK FAX: 907-474-7290 TELEMAIL: GEOPH.INST.FBK Established by Act of Congress, dedicated to the maintenance of geophysical research concerning the Arctic regions Geophysical Institute, University of Alaska (4) For the purpose mentioned in (3), I have taken the following steps: (a) establish a calibrator station near the reservoir to monitor in real-time both the weak and strong ground motions, (b) establish a strong motion station at the gate site as stipulated by the project for providing warning to the personnel at the site following a strong nearby earthquake, (c) locate routine earthquakes in and around the reservoir site using a similar seismic coverage as used by USGS to establish the background seismicity. Use the data from the calibrator station under (a) to estimate magnitude precisely, and (d) archive the data gathered under this project separately, and if required by the Alaska Energy Authority (AEA), transmit the data for strong earthquakes on diskette. (5) For the last ten years or so, our seismology program involved with projects costing $6 to $7M; about half of this amount has been invested for the acquisition of hardware. A significant amount of the above figure has been utilized for the development of computer programs for data acquisition, reduction, etc. These activities are an ongoing part of our operation as everyday we discover a new problem, a phenomenon common to all laboratories of our kind. However, on the basis of the last two fiscal years budget, our per station cost (station installation, maintenance, data telemetry, data acquisition, data reduction and reporting) is around $17K and with 45.5% OH, it is averaging around $25K. (6) For the last year or so, every project has been asked to cover student tuition cost; this is again not an individual campus decision, rather a national policy. Accordingly, we had to incorporate student tuition with the budget of the current RSA. I must point out here that every Principal Investigator, like myself, invariably wants to keep the budget to a minimum just to be competitive with others, yet tries to maintain the best standard of the output of the contract to preserve his or her professional status among the colleagues. (7) The last eruption of the Mt. Redoubt volcano completely saturated our data acquisition system and caused considerable interruption in routine recording of earthquake data. To avoid similar problems in the future, with the consent from your office, I have diverted a part of the budget of the last RSA (1988- 1989) to acquire data acquisition-computer peripherals dedicated to the project. (8) The budget submitted with the renewal RSA (GI 91-25) are for the following reasons: (a) Task 1 deals with a one time procurement for the expansion of the data recording system. The volume of the daily digital data for the five stations used for the project, including the calibrator station near the dam site is very large. I am hoping that the proposed addition will alleviate the current memory problem. (b) Task 2a deals with the elimination of some residual problems with the field sites. I draw your attention under materials and travels. The insistence of your office for arranging these items from Anchorage is an inefficient way of solving technical problems. We are constantly faced with the problems of adapting microelectronics to Alaskan environmental conditions. Consequently, unpredictable failure of components at field sites is not uncommon. After a few Geophysical Institute, University of Alaska attempts, we have always solved these problems. From my past experience of operating seismic stations in Alaska, I must say that I would require another two field seasons (Summer 1991 and 1992) to eliminate all component failure at the field sites. After that, I will be in a position to reduce the cost to a minimum under this task, as shown under (10). (c) Task 2b deals with the following: We routinely locate the earthquakes across the state without examining the details. The works under this task begin after that. We sort the data between longitudes 147°W to 154°W and latitudes 58.5°N to 61°N for detailed analysis (rescale, relocate, recompute magnitudes, determine source mechanisms for larger events and clustering of epicenters and hypocenters, etc.). Graduate student assistance is the most economical technical assistance available in a University system as 30% of his/her cost is shared by the institution plus the reliability of work output is an asset to the project. If we hire assistance from other sources, the cost will be twice than that incurred for a graduate assistant. As a matter of fact due to the utilization of graduate assistance, it has been possible for me to meet the project obligation by devoting 2-3 hours a week and about 2-3 weeks/yr. for the preparation of the annual report for your project. However, I had to spend 3 months for the preparation of the last annual report (a copy enclosed for your review), though the RSA was budgeted a month of my salary. This was again due to the interruption of our routine operation caused by the Redoubt eruption. (9) The cost benefit of the project shared by your organization and the University of Alaska Fairbanks may be summarized as follows: Alaska Energy Authority (AEA) (i) For the purpose of earthquake monitoring, hardware standardized and/or developed by the Geophysical Institute (GI) over many years at large cost could be adapted for the Bradley Lake Project (BLP) at nominal cost to AEA. (ii) Services of well equipped electronic and machine shops, manned by highly skilled workers have been used at various phases of BLP on the basis of hourly charge to AEA. Similarly, assistance of highly trained computer programmers is being used from time to time for BLP. These services would not be available to other organizations at the same rate charged to AEA by the Geophysical Institute. (iii) The Geophysical Institute as an integral part of the University of Alaska Fairbanks (UAF), a state University system, has been able to obtain access to dedicated data circuit for BLP at nominal cost. Moreover, we are able to telemeter the data in real-time from Bradley Lake to Fairbanks, using the facilities of the State Communication Division at no cost. This is saving BLP approximately $20K per year. Geophysical institute, University of Alaska Gadbiesiial Tati aD (i) GI is able to advance its image to the citizens of Alaska as an active participant in a project which is going to serve the most important population center of the state. (ii) GI has been able to acquire a set of state-of-the-art seismographic system and it is gaining experience in operating it under Alaskan environmental conditions. (iii) The graduate students in the seismology program get an opportunity to engage in technical reviews of literature and discussions on the phenomenon of induced seismicity. (10) Maintenance Budget Estimate Principal Investigator, 1 month $ 7K Reserve for annual, sick leave, etc. 1.4K Staff Benefits (Social Security, Retirement, etc.) 1.7K Graduate Asst. (1/2 time), 12 months 7.6K Office supplies, replacement of equipment parts at the field and recording sites 1.5K Preparation of annual report 2K Usage of Institute's computer peripherals (printer, plotter, etc.) 2K Electronic shop charges for the maintenance of the field site, including site visit if necessary 3K Subtotal $26.2K Indirect Costs (45.5% TMDC) -LLOK TOTAL $38.1K Geophysical Institute, University of Alaskz If you have any further inquiries on the above project, please feel free to pass them on to me or call me at 474-7373. Sincerely, Niren N. Biswas Professor of Geophysics NNB:mkw Enclosures: as stated.