HomeMy WebLinkAboutBPMC August 23, 1991 1FILE COPY
i a
v
BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE
August 23, 1991
1. CALL TO ORDER
Chairman Kelly called the Bradley Lake Project Management Committee to
order at 10:00 a.m. in the Training Room at Chugach Electric Association in
Anchorage, AK, to conduct the business of the Committee per the agenda
and the public notice.
2. ROLL CALL
Alaska Energy Authority
Charlie Bussell, Designated Representative
Brent N. Petrie, Designated Alternate
Chugach Electric Association, Inc.
David L. Highers, Designated Representative
Joe Griffith, Designated Alternate
Golden Valley Electric Association, Inc.
Mike Kelly, Designated Representative and Chairman
City of Seward
E. Paul Diener, Designated Representative
Homer Electric Association, Inc.
Norman L. Story, Designated Representative
Matanuska Electric Association, Inc.
James D. Hall, Designated Alternate
Municipal Light and Power
Thomas Stahr, Designated Representative
91Q3/D1475(1)
* Bradley Lake Project nmittee Meeting Minutes August 23, 1991
Page 2
Others Present:
Ron Saxton, Representing Ater, Wynne, Hewitt, Dodson & Skerrit
Robert Hufman, Purchasing Utilities
Dave Burlingame, Chugach Electric Association, Inc.
David Eberle, Alaska Energy Authority
John Cooley, Chugach Electric Association, Inc.
Tim McConnell, Municipal Light and Power
Moe Aslam, Municipal Light and Power
Dave Fair, Homer Electric Association, Inc.
Dave Calvert, City of Seward
Penny Haldane, Alaska Energy Authority
3. PUBLIC COMMENT
There was no public comment.
4. AGENDA COMMENTS
The agenda was modified to include:
11. Old Business
135) | | 1¢ Section 31 Costs
D. Approval of SVS Contract Award.
5. APPROVAL OF MINUTES
Hearing no objection, the minutes from July 2, 1991 were approved as
corrected.
6. TECHNICAL COORDINATING SUBCOMMITTEE REPORT
Dave Burlingame reported on the Technical Coordinating
Subcommittee (TCS) meeting August 15, 1991. All SWEC sponsored tests
and other utility required tests have been completed. These tests identified
some problems; subsequent tests of the solutions have proved satisfactory.
91Q3/3D1475(2)
Bradley Lake Project nmittee Meeting Minutes
August 23, 1991 Page 3
The plant operated at a level of 103 MW for 10-15 minutes, 90 MW for 1
hour, and survived a 90 MW load rejection of electrical power plus over
50 MW water waste. In terms of water load rejection it rejected 120 MW.
The plant output is now considered firm and all participants are starting to
schedule Bradley accordingly.
At the last Bradley Lake Project Mangement Committee (BPMC) meeting
the TCS was directed to perform an energy study evaluating how the
minimum operating restrictions would affect the available energy of the plant.
AEA completed those studies and found approximately 1% difference even
after the utility revised energy forecasts were used.
The Kenai import study is not critical at this time and is currently on hold till
more studies are completed by PTI. The Bradley Lake Operating Manuals
are expected to be ready for review/adoption at the next BPMC meeting and
will be placed on the agenda as new business.
Overall, the plant is doing well. John Cooley had a question on the efficiency
and Dave Burlingame said that this is still an outstanding item that will be
addressed by Fuji next week.
In response to Chairman Kelly's question, Dave Burlingame reported that a
full reservoir is expected around September 15. Therefore, the minimum
operating level will not be a problem in the coming months.
Moe Aslam commented that recent work evaluating the disturbances on
July 20 and August 3rd, has increased the level of confidence in PTI.
Chairman Kelly thanked Dave and his subcommittee for the good work and
the helpful report.
INSURANCE SUBCOMMITTEE REPORT
Brent Petrie reported that the quotes on property and boiler insurance
premiums were $110,000 less than budgeted. The recommendation of this
subcommittee is to keep the budget as is until June 30, 1992, and apply any
overage to the next 12 month premium payment. This will improve the
current cash flow situation. Hearing no objection, it was agreed to treat the
premium payments in this manner.
91Q3/JD1475(3)
Bradley Lake Project nmittee Meeting Minutes
August 23, 1991 Page 4
Brent also reported that the insurance subcommittee is preparing an
application for business interruption insurance. The premium costs will be
based on information provided in the application documents and is not known
at this time. This will be an action item for a future meeting.
BUDGET SUBCOMMITTEE REPORT
Ron Saxton provided the Budget Subcommittee report in Ken Ritchey's
absence. The payment levels were finalized and billed at a higher level for 4
months and a lower lever for the remaining 6 months. The BPMC is
requested to begin thinking about the next budget, since the budget
preparation process will begin in the next 6-8 weeks. The last thing to report
is that there will be more cushion than originally anticipated due to Section 31
costs and the insurance expense. Mr. Saxton suggested that as a conservative
approach, this cushion should be held till the following year when an
adjustment would be made, although it is possible that a mid-year revision
could occur if things go well.
After additional discussion on Chugach and Homer rates, Chairman Kelly
asked that concurrence on the elements be reached and distributed prior to
the next meeting. These will be new business items at the next meeting.
OPERATION AND DISPATCH SUBCOMMITTEE REPORT
John Cooley reported that this subcommittee had not met since the last
BPMC meeting. At the October 25, 1991, BPMC meeting; Stan Sieczkowski
stated that the operation and dispatch subcommittee had met on
July 25, 1991. Brent Petrie reported that Stan was weathered in at Wrangell,
but had the documents with him and they were close to completion. Stan had
expected that Brad Evans would be at the meeting today to provide a
committee report. The committee will meet before the next meeting, review
the final documents, and present them to the BPMC at the next meeting.
Motion - Interim approval by the BPMC of the Agreement for the Dispatch of
Electric Power and for Related Services ("Dispatch Agreement") by and among
Chugach Electric Association, Inc. and Alaska Energy Authority. Motion by
E. Paul Diener, second by Tom Stahr. Under discussion, Tom Stahr
commented that any dispute between Chugach Electric and the AFA that
required arbitration or resolution in the Courts would first be presented to the
BPMC. Tom Stahr's comment is included in the motion. The motion passed
unanimously.
91Q3/3D1475(4)
Bradley Lake Project mmittee Meeting Minutes
August 23, 1991 Page 5
10.
11.
REVIEW OF PROJECT STATUS
Dave Eberle reported that all testing is now completed and the plant is in the
utility's control for firm power. Commercial operation is set for September 1
and the dedication will be on September 6.
The water levels are doing well. Current level is 1,162 feet with 18 feet before
spill. Estimated water levels are above the historical average. Dispatchers
have been told that 63 GWH's must be used between now and December 1 or
spill will occur. The utilities are scheduling accordingly.
Dave Eberle reported that the SVS bids were opened (low bid ASEA Brown
Boveri $14.2 million) and that all bidders were considerably higher than the
engineer's estimate of $9.2 million or the budget amount of $9.3 million. The
notice of intent to award was issued to determine if there would be a protest
(none were received). Options for revising the scope of work have been
discussed, but no substantial changes have been identified.
Chairman Kelly asked Dave Eberle if the contingency funds would be
adequate to cover the cost overruns. Dave replied that after allowing for the
$5 million for SVS, $2-2.5 million would remain. Two possible needs for these
remaining funds would be site rehabilitation costs not quantified yet and any
additional SVS costs. SVS is expected to be on line for commercial operation
in January 1993.
OLD BUSINESS
Dave Burlingame requested that the previous tabled motions requesting
funds for transfer tripping be considered. Installation of transfer tripping will
prevent the need to take the tieline out of service when output of Bradley
Lake reaches 65 MW. Chugach does not want to take the line out of service.
Motion - Approval of costs to install transfer tripping not to exceed $35,000
for Chugach Electric and $62,000 for Homer Electric. Motion by
Dave Highers, second by Tom Stahr. Both Homer and Chugach assured that
all costs are strictly related to Bradley Lake. The motion passed unanimously.
91Q3/JD1475(5)
Bradley Lake Project mmittee Meeting Minutes August 23, 1991 Page 6
12. NEW BUSINESS
A.
91Q3/JD1475(6)
Dispatch Agreement
John Cooley reported on the Scheduling and Allocation Agreement.
After discussion it was determined that this agreement was approved
at the July 2, 1991 meeting subject to the completion of Exhibits A
and B.
The dispatch services agreement between Chugach and the Alaska
Energy Authority is awaiting comments from AFA. This final will be
distributed to all utilities prior to the next BPMC meeting.
Chairman Kelly has asked that all related documents (SWEC report
discussing the parameters of operating Bradley) also be redistributed.
It is expected that these agreements will also go to the Operation and
Dispatch Subcommittee at the same time.
Approval of Committee Expenses
Chairman Kelly recommended that only reviewed expenses would be
considered. Expenses received but not reviewed would be held for
consideration at the next BPMC meeting.
Brent Petrie received a request with back-up documentation for
Ater, Wynne, Hewitt, Dodson & Skerrit cost reimbursement of
$17,480.33.
Motion - Approval of $17,480.33 expense. Motion by Charlie Bussell,
seconded. The motion passed unanimously.
Section 31 Costs
Motion - Section 31 balances will be allocated to ongoing BPMC costs
or to defray budget expenses. Motion by Charlie Bussell, second by
Tom Stahr. Discussion on documentation for Gloria resulted in the
recommendation that a certifying block be added for each expenditure
approved. This motion passed unanimously.
Bradley Lake Project nmittee Meeting Minutes
August 23, 1991 Page 7
D. Approval of SVS Contract Award.
Motion - Approval to issue SVS contract award and notice to proceed.
Motion by Dave Highers, second by E. Paul Diener. This motion
passed unanimously.
E. Further Business
Dave Eberle reported that he had received a bill from HEA for
standby spinning during testing. It was decided that these and other
related bills would be placed on the agenda as new business (Power
generation expenses related to testing) at the next meeting.
13. COMMUNICATIONS
A. Schedule Next Meeting
October 25, 1991 (Friday)
10:00 a.m.
Chugach Electric Association Training Room
15. ADJOURNMENT
There being no further business the committee adjourned at 11:43 a.m.
“Wy An
Mike Kelly, Chairman
Attest:
Charlie Bussell, Secretary
91Q3/JD1475(7)