Loading...
HomeMy WebLinkAboutBradley Lake BPMC Meeting Operators Report 03-08-2012Unit Statistics: Bradley Lake BPMC Meeting March 8th, 2012 - July 17%, 2012 Operators Report Generation Unit 1 Unit 1 Unit 2 Unit 2 Total (MWhrs) Availability (MWhrs) Availability (MWhrs) March 15,600 99.56% 16,270 97.88% 31,870 April 14,080 97.67% 15,160 94.54% 29.240 May 14,510 96.47% 14,120 96.77% 28,630 June 16,720 100.00% 13,890 100.00% 30,610 Hydraulics Avg. Lake Level (ft) Usage (ac ft) Fishwater (ac ft) March 1,128.08 33,099 2,407.1 April 1,115.36 30,742 1,250.3 May 1,105.97 30,374 1,166.2 June * 1,108.84 32,463 24.1 Current Status: e Lake level as of July 13 was 1,126.3 feet. The minimum lake level for the water year was reached on May 224 with a level of 1,103.56 feet. e Emerson DCS project has progressed from design, kickoff, FAT, to installation currently. Issues were identified during the FAT with regards to DNP 3.0 protocol. These issues were worked out at Nikiski and the installation at Bradley is very similar. e VA Tech Governor communications upgrade is scheduled for next week while both Units are offline. e Review of our monthly electrical and hydraulic report identified problems that have been resolved with the implementation of a new report and format. e Worked with HEA Linemen’s group on updated procedures and information due to the upcoming removal of the Bradley Junction switches. The largest concern was to have a point where an air break can be seen in the insulated substation for LOTO purposes. This can be done externally on the disconnect switches but not on the breakers. e Completed Fish Water flow ramp up in May without any issues. e Conducted review of trainee applications, aptitude tests, and phone interviews. Andrew Carey was selected for the position. He started on April 30th as an Operator Trainee. Bradley Lake Operator Report Page 1 Work with ML&P Auditors on questions, data requests, and other reviews. Their final report showed Bradley in compliance with no findings. Completed maintenance work on Airport and Barge Dock buildings. Replacing rotted wood, broken windows, rusted-out doors, repainting, and roof repairs. Installed “Ice Crickets” on the Warehouse/Shop, and Crew Quarters buildings to stop damage that has been occurring due to ice sliding off the roofs. Delayed installation of a PD Monitoring system due to vendor pricing, installation labor, and adequate time before outage for delivery. They also have a newer system coming out this fall that has many features we would like to have incorporated into our system. ProComm completed the wireless canopy modules configuration. The first three links are up and running. Which are the ones need to carry RTU information to the DCS. The rest of the links will be installed after the current outage. Ed Parvin from the USGS on site for flow testing and coordination of signals between fish water flow monitor signals and the Below the Dam gauging site. Worked with the USGS for new certified flow curve equations. The reason for the change is that the new DCS does not use matrix style lookup tables like the old SCADA system did. The Kenai Peninsula Borough has put into place new waste disposal rules. We have been working with their Environmental Coordinator to get approval for Bradley. We have approval for all of our wastes except the Incinerator ash. We have to have the ash tested for residual hydrocarbons and trace contaminants before they will accept it. Work on the Overhead Crane controls replacement started on June 17*h and that portion was completed on the 26». The load cells require custom pins to be manufactured and will be installed when received. Load testing and certification of the crane will occur in August. The outage started on July 8». We were delayed 2 days due to difficulties in getting people and materials on site. The barge delivery was delayed 5 days. Also, the 4 of July holiday made it more difficult to get people here to get things started. We are working closely with KECO to regain schedule wherever possible. Annual gate testing for FERC is scheduled on July 19%. Sherwin Williams out of Anchorage will be on site on July 24 to work on the Diversion Tunnel re-coating project. Training & Safety: Qualified Substation Operator annual training completed. First Aid and CPR annual training. Fire Extinguisher inspections completed. Annual Vibration survey completed. Completed annual fire extinguisher inspections. Bradley Lake Operator Report Page 2 BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE REGULAR MEETING AGENDA Friday, August 31, 2012 — 9:00 a.m. (via electronic media at the Alaska Energy Authority’s Aspen Room 813 West Northern Lights Boulevard, Anchorage, AK) Dial 1-800-315-6338, Enter Code 3074# CALL TO ORDER ROLL CALL (for Committee members) PUBLIC ROLL CALL (for all others present) PUBLIC COMMENT AGENDA COMMENTS / MOTION FOR APPROVAL APPROVAL OF MEETING MINUTES -— July 17, 2012 NEW BUSINESS A. Selection of Auditor (Action Item) COMMITTEE REPORTS / COMMENTS A. Operators Report B. Update on Battle Creek Diversion Project C. Next Meeting Date ADJOURNMENT Evans Cunningham Jorgensen Carey Evans CHECKLIST FOR BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE MEETINGS Meeting Date: 8/3) [lo Ten tet Meeting Location: As pe db Poon CONFIRMED/DATE Secure Meeting Date with Bryan Carey *3065 Secure Meeting Date with Chairman — “Only May Post to the State of Alaska’s Online Notice System 3.4/1), r Sherrie can do this Send email and fax to all members with meeting date/time/location (ask for documents to be emailed for packet inclusion — including action items with their motions) If their designee will attend instead, they need to send me an email stating so! N Secure meeting room for use (block out 30 minutes prior to meeting to allow for set-up time x Schedule a teleconference line with GCI (1-800-770-2121) provide them with a reference project (BPMC) and code (your | phone extension number) Barun k Draft Agenda for Bryan Carey's review Send Draft Agenda by email to Chairman for review and approval Emotes Gy hy ites Gather documents from members Email packet to members including all attachments (teleconference information/agenda/draft of previous meeting minutes/motions/general handouts) (SEND IN PDF FORMAT!) Print 5 extra copies of the full packet of information and bring to the meeting for those who did not bring their copy SN wi Ni \ \ Log on to the boardroom computer 30 minutes prior to meeting Page 1 of 1 H:\AEA Projects\Bradley Lake ProjectiBPMC\BPMC Meetings\Meeting Setup Folder\CHECKLIST for BPMC Meetings.doc