HomeMy WebLinkAboutBradley Lake BPMC Meeting Operators Report 07-17-2012Bradley Lake BPMC Meeting July 17, 2012 - August 29th, 2012 Operators Report Unit Statistics: Generation Unit 1 (MWhrs) Unit 2 (MWhrs) Total (MWhrs) July 7,970 7,360 15,330 Hydraulics Avg. Lake Level (ft) Usage (ac ft) | _Fishwater (ac ft) July 1129.88 13,013.65 | 955.65 Current Status: Lake level as of August 29 was 1,153.8 feet. Annual Gate Testing completed on July 19. Sherwin Williams out of Anchorage inspected the Diversion Tunnel piping and recommended a coating applicable for the area. We have materials on order and will start the project as soon as they arrive. Unit #2 came back on line on July 29th. Unit # 1 came back on line on July 31st. There have been several issues with the interfacing the new control system with existing equipment both at the plant and with remote Dispatch. Currently both units can run from Dispatch but only up to 38 MWs each. They can be run manually from the site to full load. In remote control as soon as we transition to 6 needle control we are seeing stability issues. We are working with VA Tech / Andritz Hydro for the governor and Emerson Ovation for the DCS to resolve these issues. The SVC at Soldotna has been down causing Bradley to be limited to only one unit on line at a time due to voltage limitations. The SVC was returned to service late on the 28th allowing both units to be run at Bradley. R&M Consultants have been on site doing their work for the Battle Creek project. We have provided support for their activities and are continuing to do so. Training & Safety: Emerson Ovation Operator training completed. Bradley Lake Operator Report Page 1 Kimberly Lomen From: Kimberly Lomen Sent: Monday, August 27, 2012 2:54 PM To: Ambrose, Harvey; Brian Bjorkquist; Bryan Carey; Carrie Buckley; Christel Petty; Cunningham, Mike; Dale, Henri; Dawn Baham; Day, Bob; Divina Portades, CEA; Zoerb, Don; Evans, Brad; Foutz, John; Gamble, Teresa; Gary Dixon, Swalling & Assoc.; Gary Kuhn; Janorschke, Brad; Jean Schroeder, HEA Secretary; Jeff Estes, City of Seward; Jeff Warner; Jim Kingrey, HEA; Joe Griffith, MEA; Kelli L. Veech; Kimberly Lomen; Kirk Gibson, McDowell Rackner & Gibson PC; Larry Jorgensen; Lynn Ragle, Swalling & Associates, CPA; May Clark; Moira Halbert; Newton, Brian; Owens, Connie; Pattie Worrell, MEA Secretary; Posey, Jim; Rick Miller, AML&P; Sara Fisher-Goad; Shelby Weems; Susan Redlin, Exec. Secretary, GVEA; Wick, Burke Subject: Packet Information for the August 31 meeting attached Attachments: Agenda 8-31.pdf; BMPC July 17 2012 Final Draft .pdf; Proposal for Audit and Motion 7A.pdf Importance: High Good Afternoon, Attached are the following documents for the August 31, 2012 BPMC meeting. e Agenda e July 17, 2012 meeting minutes e Motion 7A - Auditor Selection The Operator’s report will be distributed at the meeting. If you are unable to attend in person please dial 1-800-315-6338 enter code 3074#. Please call or email if you have any questions. Thank you, Kim Lomen Administrative Assistant State of Alaska Alaska Energy Authority Email: klomen @ aidea.com Phone: 907-907-771-3991 Fax: 907-771-3044 813 West Northern Lights Blvd Anchorage, Alaska 99503 BRADLEY LAKE PROJECT MANAGEMENT COMMITTEE MEETING REGULAR MEETING (via electronic media at the Alaska Energy Authority’s Aspen Room) Anchorage, Alaska July 17, 2012 DRAFT MINUTES 1. CALL TO ORDER Chair Brad Evans called the regular meeting of the Bradley Lake Hydroelectric Project Management Committee to order at 9:00 on Tuesday, July 17, 2012, from the AEA Aspen Conference Room, Anchorage, Alaska to conduct the business of the Committee per agenda and public notice. 2. ROLL CALL Roll was called by May Clark. The following members were present: John Foutz City of Seward Joe Griffith Matanuska Electric Association Brad Evans Chugach Electric Association Harvey Ambrose Homer Electric Association Henri Dale Golden Valley Electric Richard Miller Anchorage Municipal Light & Power Bryan Carey Alaska Energy Authority 3. PUBLIC ROLL CALL May Clark AEA Kim Lomen AEA Brian Hickey Chugach Burke Wick CEA Bob Day MTA Rick Miller ML&P Jeff Warner ML&P Jim Strandberg AEA Lee Thibert CEA Sara Fisher-Goad AEA Larry Jorgensen HEA (teleconference) Page 1 of 4 BPMC Draft Minutes 7/17/2012 4. PUBLIC COMMENT There were no public comments. 5. AGENDA COMMENTS/MOTION FOR APPROVAL The agenda was approved as amended. 6. Approval of Meeting Minutes — March 16, 2012 The March 16, 2012 meeting minutes were approved as amended. 7. New Business 7A. Review of the O&M Services Agreement Mr. Griffith said that there are a series of new issues in the Railbelt, such as determining how to support the Susitna-Watana project and the Unconstrained Bradley Lake project. One factor is the O&M services agreement and who runs Bradley Lake. Mr. Griffith suggested that Mr. Gibson review the agreements. The O&M Service Agreements, which were signed in 1980, may need changes so the committee can fully understand the conditions the project is currently operating under when changes occur at end of 2014. There have been many changes in 20 years so the language of the agreement must be reviewed. A task force must consider the contractual good faith dealing concept; the prudent utility practice; and the obligations and duties of all the agencies involved. Chair Evans said that if there were no more comments he moved to close the discussion and that he would create a task force by Chair edict. He would also consult the BMPC attorney regarding the creation of an ad hoc committee or write a resolution to review the original agreements. 7B. Update on the Battle Creek Diversion Project. Mr. Carey said there had been a workshop with agencies on the environment flows. In early May, Alaska Department of Fish and Game and U.S. Fish and Wildlife reviewed cross sectional transacts of Battle Creek at a low flow rate. Fish and Game has performed two in-stream flow reviews and came to a similar conclusion. Chairman Evans asked if the different agencies reviewing the resources in terms of water flow and salmon spawning would have to consolidate their finds. Mr. Carey said that once the draft conditions are completed by Fish and Game and federal agencies, there will be an opportunity to negotiate Page 2 of 4 BPMC Draft Minutes 7/17/2012 conditions for the final license application. After the negotiations are complete, the final license application will be submitted. Mr. Carey said that once the license amendment is received in summer of 2013, the project can go to bid and a site visit will be conducted for the bidders. The successful contractor will have the winter months to gather their equipment and have it mobilized for construction in the 2014 calendar year. However, there will be additional funding needed to cover the increased cost of helicopter drilling. AEA is waiting on additional information from the environmental licensing consultant, but the amount needed will be between $250,000 and $500,000. Originally the project started out with $6 M and $3 M was used to fund the Battle Creek design and licensing. Both the RE fund and BPMC contributed $500,000 bringing the total budget to $4 M, of which roughly $3.4 M has been obligated. There is currently $600,000 of unobligated funding. The cost of additional engineering and licensing to bid is greater than the unobligated amount. Of the $3.4 M between $1.5 M and $2 M has been used for helicopter drilling. The costs for geotechnical work and engineering design amount to about 80% of the original budget. Ms. Fisher-Goad said relocation of existing funds may be the quickest way to obtain the funds needed for 2012. But Mr. Gibson must be consulted to find out the current status of the grants and determine the most logical solution. 7C. Election of Officers MOTION: Mr. Griffith moved for election of Committee Officers with current slate. Mr. Posey seconded the motion. A roll call vote was taken: City of Seward: Yes Matanuska Electric Association: Yes Chugach Electric Association: Yes Homer Electric Association: Yes Golden Valley Electric Association: Yes Anchorage Municipal Light & Power: Yes Alaska Energy Authority: Yes The motion passed unanimously. 8. Committee Reports/Comments 8A. Operator’s Report —Larry Jorgensen Page 3 of 4 BPMC Draft Minutes 7/17/2012 Mr. Jorgenson said the Lake level as of July 13 was 1,126.3 feet. Mr. Posey asked if annual gate testing was being done to determine if there was any erosion of pipe in the project. Mr. Jorgenson said the lower region is re-enforced steel to guard against erosion. Trash collection is done in the penstock at the end of the year to determine if any erosion has occurred and there has not been any substantial trash in the past. There is a large rock trap by the turbines that any eroding concrete would have to jump and that is not likely to happen. There were no other meeting comments. Meeting summary/assignments: e Creation of a task force to review past O&M Agreements. Update language in the agreements and determine the duties and obligations of all participating agencies. e Creation of a special purpose committee work with AEA to cover upcoming funding shortfall. 8B. Next Meeting Date Based on issues raised in the July 17, 2012 meeting the next meeting should be help by mid- September. 9. Adjournment The meeting adjourned at 10:00 a.m. BY: Brad Evans, Chair ATTEST: Alaska Energy Authority, Secretary Page 4 of 4 BPMC Draft Minutes 7/17/2012