Alaska Power Authority Metering Audit 1985
RECEIVED BY ALASKA POWF® ATITHORITY 86 JAN 28 AIO :11 ALASKA POWER AUTHORITY 1985 Substation Metering Audit December 2nd to 21st, 1985 Contract #APA 85-R-016 Utility Systems & Applications, Inc. 4160 S.E. International Way, D-107 Portland, Oregon 97222 ALASKA POWER AUTHORITY Metering Audit Summary Utility Systems and Applications, Inc. provided testing, calibration and verification for metering points at Alaska Power Authority facilities in Wrangell, Petersburg, Ketchikan, Tyee and Swan Lake, Solomon Gulch, Meals Substation, Pump Stations 1l and 12, Kodiak and Terror Lake, Alaska. The following report, along with the audit sheets for each metering point, detail our findings, observations and recommendations. I. METER AUDIT CRITERIA AND PROCEDURE Each metering point was tested and evaluated in a standard manner, which included some or all of the following procedures and techniques. A. Meter _Test.and Calibration 1. Each KWH meter was isolated from its circuit and "as found" tested for Full Load, Light Load, Power Factor and Balance, In addition, those meters equipped with demand registers were checked for Demand Zero Point, Demand Rise Rate and Demand Reset Time. 26 Each meter was adjusted and necessary to operate within the following tolerances where possible. a. Full Load and Light Load: at least plus or minus 0.3% accuracy b. Power Factor: at least plus or minus 0.75% Cre Balance: no more than 0.5% variation among elements Due to defects, some meters could not be adjusted to meet the above tolérances; this is discussed in Section II A of this report. B. Magnetic. Tape Recorder, Packages The KWH and QH meters associated with these packages were tested as noted in Section A above. In addition, the pulse initiators were checked for proper operation and the pulse per revolution rate was checked against nameplate rate. The pulse values were also calculated and marked in the appropriate place on the recorder face plate. Magnetic. Tape Recorder. Metering. Packages Most packages do not have provision for testing (test switch) and on one, the test switch is incorrectly wired and cannot be used in testing. In these packages, it is not possible to seal the individual meters because they do not have individual glass covers. If you were to seal the package cover, the Magnetic tapes would be inaccessible for monthly changes. Norms! proce 1s 7 reseal methly, C.~'t de ie Jes Oose os AVA Cinrot ge fo ses mdhy/, : Pulse values on all the magnetic tape recorder packages are 100 KWH or Q-Hour per pulse. Some meters have to turn 15 disk revolutions for one pulse. These are very low pulse rates which give a demand definition of 400 KW. Pulse rates could be ten times as fast and still not be close to tape saturation. This would greatly improve demand definition. Ops preblex Because the meters in these packages do not have separate covers, dirt is a problem. There is no way to prevent heavy contamination. An additional digital recording package should be considered at Bailey Substation. Gaek L. vb lan Demand_Definition.of.mechanical..Demand.Register special register ratios have been ordered to give multipliers of 1,000 on many of the meters. As a result, many of these have poor demand definition and cannot be read closer than 500 KW. Const [ena bl erm III. oe @ RECOMMENDATIONS The following is a review of the recommendations listed on the Audit Test Sheets. A. Wrangellsubstation 1. Verify accuracy class of all current transformers, If magnetic tape package C.T.s are not 0.3 accuracy class, they should be replaced. Fae One of the switchboard meters should be returned to the factory for rebuilding. ops Install test switch for remote magnetic tape recorder package. Increase pulse initiator output by at least a factor of 10. B. Wrangell_Switchyard 1. 2. 3 The C.T. ratio should be verified. The metering is three wire and should be replaced with four wire metering. Register demand definition is poor and a magnetic tape could be installed to improve this. c. Petersburg.Substatian 1. 2. Two meters have incorrect demand register scale plates. One switchboard meter has the incorrect cover, which makes it impossible to reset the demand without removing the cover. This allows dirt to contaminate the meter. The metering is three wire, but should be four wire. The metering on the magnetic tape package should be changed to four wire as it appears this is the billing meter. (This will require installation of three P.T.s). Consideration should be given to installing four wire metering on the other two circuits also. The customer will have line to ground loads in the future. None of the current transformers are 0.3 accuracy class and should at least be replaced on the magnetic tape package metering. By The "Out" meter is wired for "In" power. 6. A test switch should be installed to enable convenient testing for the magnetic tape package. Ure The pulse rate should be increased at least a factor of 10 on the magnetic tape package in order to improve demand definition. 8. Remote the recorder from the metering package. Tyes Tie C.T. ratio and accuracy class needs to be verified as C.T.s were inaccessible on the station service metering. 2. The generator C.T.s are not 0.3 accuracy class and are relay class. 5 The station total metering is three wire but the system is four wire. This metering should be changed to four wire for best accuracy. 4. The test switch should be rewired to enable easier testing for the magnetic tape metering package. Se The pulse rate to the magnetic tape should be increased by at least a factor of 10 to improve demand definition. 6. Remote the recorder from the metering package. Swan.Lake 1. The potential transformer should be disconnected from the metering circuit for both station service meters. They are not necessary and create inaccuracies inthe registration. 2. Install test switches or "slide" kits to enable easier testing of station service meters. Sie Station service C.T.s are not 0.3 accuracy class. 4. Due to loading of P.T.s and wire length, a separate potential cable should be run to the generator meters. oe @ Soelomen.Gulch 1. Replace the Fuji meters with magnetic suspension type. 2. Verify C.T. ratio and accuracy class. 3% Change metering to four wire WYE. 4. Change instrument transformers to revenue class. Meals.Substation Le Correct the wiring on the 25 KV busp meter. 2 Verify C.T. and P.T. ratio and quality. Pump..Station #11 1. Replace meter demand register on circuit #1. 2 replace C.T.s with metering quality ones that are 0.3 accuracy class. 36 Rewire one meter. Terrar.lake l. Install test switch on the "Line Out" meters. ie Remote the recorder from the metering package. Ste Replace instrument transformers with 0.3 accuracy class ones. 4. Change metering to four wire WYE scheme. Se Install detent on Port Lyons "Line Out” meter. Airport. Substation. Kadiak 1. 2. 3. Change metering to four wire WYE configuration. “Change instrument transformers to 0.3 accuracy class. “Verify C.T. ratio and accuracy on three installations. Iv. @ @ L. Swampy.Acres 1. Verify C.T. ratios and quality. De Change instrument transformers to 0.3 accuracy class. 3. Change metering to four wire WYE. 4. Change meter register on Airport "Line In" meter. CONCLUSION Many of the installations are in considerable error and, due to the large amounts of power they meter, should be repaired. Those installations where billing occurs should definitely be brought into plus or minus 0.3 accuracy. The meters themselves, with a coupled of exceptions, were left better than plus or minus 0.3% accuracy. If demand is to be billed in the future, magnetic tape recorder packages or similar devices should be installed to provide suitable demand definition. lity Systems & Applications, Inc. us, Uti SBA January 23, 1986 Mr. Harry L. Beck Operations Engineer Alaska Power Authority 334 West 5th Avenue Anchorage, Alaska 99501 Subject: Meter audit of December 2nd through 20th, 1985. Attached you will find the documents pertaining to our audits of the metering at Alaska Fower Authority's facilities at Wrangell, Petersberg, Ketchikan, Tyee, Swan Lake, Solomon Guicr, Meals Substation, Pump Stations 11 and 12, Kodiak and Terror Lake. The information is divided into two sections: a general report and the individual audit reports. We would be happy to submit a proposal to make any or all of the changes recommended. Our travel was restricted due to the weather and short daylight hours for flying. Because of this we would recommend that future visits be done in summer months if possible. We appreciate the opportunity to meet your metering requirements and look forward to assisting you in the future. Sincerely, ey Y7 a Bob G. Fisher Superintendent of Technical Services BGF:ckh Enclosures 4160 S.E. International Way * D 207 + Portland, Oregon 97222 (503) 659-3441 THE WATTS DOCTOR TABLE OF CONTENTS I. METER AUDIT CRITERIA AND PROCEDURE Il GENERAL COMMENTS Il. RECOMMENDATIONS IV. CONCLUSION V. INDIVIDUAL SITE AUDIT SHEETS APPENDIX DAILY WORK LOG I. METER AUDIT CRITERIA AND PROCEDURE ALASKA POWER AUTHORITY Metering Audit Summary Utility Systems and Applications, Inc. provided testing, calibration and verification for metering points at Alaska Power Authority facilities in Wrangell, Petersburg, Ketchikan, Tyee and Swan Lake, Solomon Gulch, Meals Substation, Pump Stations 11 and 12, Kodiak and Terror Lake, Alaska. The following report, along with the audit sheets for each metering point, detail our findings, observations and recommendations. I. METER AUDIT CRITERIA AND PROCEDURE Each metering point was tested and evaluated in a standard manner, which included some or all of the following procedures and techniques. A. Meter Test.and Calibration iL Each KWH meter was isolated from its circuit and "as found" tested for Full Load, Light Load, Power Factor and Balance. In addition, those meters equipped with demand registers were checked for Demand Zero Point, Demand Rise Rate and Demand Reset Time. 2. Each meter was adjusted and necessary to operate within the following tolerances where possible. a. Full Load and Light Load: at least plus or minus 0.3% accuracy b. Power Factor: at least plus or minus 0.75% Cc. Balance: no more than 0.5% variation among elements Due to defects, some meters could not be adjusted to meet the above tolerances; this is discussed in Section II A of this report. B. Magnetic. Tape Recorder, Packages The KWH and QH meters associated with these packages were tested as noted in Section A above. In addition, the pulse initiators were checked for proper operation and the pulse per revolution rate was checked against nameplate rate. The pulse values were also calculated and marked in the appropriate place on the recorder face plate. Identification Where necessary, the meters were given additional identification markings and the dial multiplier was calculated and marked on the multiplier tag. Current Transformer and Potential Transformer Ratio and Quality Veification. Where possible, each C.T. and P.T. was visually inspected and nameplate data checked for ratio and quality. Current_Transformer..Burden. Checked The burden test is basically a proof test to determine how well the C.T. can provide constant current with increasing loads. "Good" C.T.s are those in which little current drop occurs when high resistance (up to 6 ohms) is inserted into a C.T. secondary circuit. "Bad" C.T.s show a sharp drop at low currents with small additions of load. This test also indicates whether there are any "shorts" in the C.T. secondary circuit. Phase Angle. Analysis Where there was sufficient loading, phase angle readings were taken to verify correctness of wiring and power load factor. In addition, the meter disk was timed and KW demand calculated and compared to actual load current and phase angle. Meter.Seals Each meter, except those in the magnetic tape packages, was sealed with a pressed lead seal. The seal mark number pressed into these lead seals is "87". IL GENERAL COMMENTS II. GENERAL COMMENTS A. Meter Tests The Fuji Meters at Solomon Gulch are of obsolete design and were considerably out of calibration. On one of them, we could not adjust the Light Load. Some meters do not have enough adjustment left to fully bring them into 0.3 accuracy. Several other meters have little or no adjustment left. Due to this problem, many of these meters should be returned to the factory for rebuilding. (See Audit Summary dated June 8, 1984.) Current..Transformer.Quality Several installations did not have 0.3 metering accuracy class current transformers for the KWH metering. The C.T.s that are in service are relay class and may not be close to ratio at metering currents. Unnecessary..Potential.Transformers The two station service meters at Swan Lake were connected to the secondary of the P.T.s (277 to 120), but these are 277 volt meters. Improper.Metering Several installations were metered three phase three- wire, but should be three phase four-wire. These occur at Wrangell Switchyard, Petersburg, Tyee, Solomon Gulch, Terror Lake, Kodiak Airport Substation, and Swampy Acres. SIn".and"Qut" Metering Some installations have "In" and "Out" metering, but the "Out" meter is wired the same as the "In" meter. They are at Petersburg and Tyee. There is no "Out" metering at Bailey Substation, so when Ketchikan feeds power to Swan Lake, this power cannot be registered. Magnetic Tape Recorder. Metering. Packages Most packages do not have provision for testing (test switch) and on one, the test switch is incorrectly wired and cannot be used in testing. In these packages, it is not possible to seal the individual meters because they do not have individual glass covers. If you were to seal the package cover, the Magnetic tapes would be inaccessible for monthly changes. Pulse values on all the magnetic tape recorder packages are 100 KWH or Q-Hour per pulse. Some meters have to turn 15 disk revolutions for one pulse. These are very low pulse rates which give a demand definition of 400 KW. Pulse rates could be ten times as fast and still not be close to tape saturation. This would greatly improve demand definition. Because the meters in these packages do not have separate covers, dirt is a problem. There is no way to prevent heavy contamination. An additional digital recording package should be considered at Bailey Substation. Demand_Definition.of.mechanical..Demand..Register special register ratios have been ordered to give multipliers of 1,000 on many of the meters. As a result, many of these have poor demand definition and cannot be read closer than 500 KW. Gencvat: hs Me fering c7's Fugposed fo have O'3 accucacy class Rel aT. = (Cece 2 ia @ 4oo:S 2.07’ neat notte be Changed - 8. Ultoupert Sy h . 1. CT has Relay Crk cdee @ yoo: CT has meter wil 0.380.) 8 2.0 2. eterna ig not evificek Sar Retey shag Lise aX Wraupet Sue rh aa : €. Retasbary Sue. 2, We. hue wan hd o449 Der 4. To be verif-ed Il, RECOMMENDATIONS IV. CONCLUSION ELE. RECOMMENDATIONS The following is a review of the recommendations listed on the Audit Test Sheets. A. Wrangell substation 1. Verify accuracy class of all current transformers. If magnetic tape package C.T.s are not 0.3 accuracy class, they should be replaced. One of the switchboard meters should be returned to the factory for rebuilding. Install test switch for remote magnetic tape recorder package. Increase pulse initiator output by at least a factor of 10. B. Wrangell_Switchyard 1. 2. 3. The C.T. ratio should be verified. The metering is three wire and should be replaced with four wire metering. Register demand definition is poor and a magnetic tape could be installed to improve this. C. Petersburg.Substation 1. Two meters have incorrect demand register scale plates. One switchboard meter has the incorrect cover, which makes it impossible to reset the demand without removing the cover. This allows dirt to contaminate the meter. The metering is three wire, but should be four wire. The metering on the magnetic tape package should be changed to four wire as it appears this is the billing meter. (This will require installation of three P.T.s). Consideration should be given to installing four wire metering on the other two circuits also. The customer will have line to ground loads in the future. None of the current transformers are 0.3 accuracy class and should at least be replaced on the magnetic tape package metering. 5. The "Out" meter is wired for "In" power. 6. A test switch should be installed to enable convenient testing for the magnetic tape package. Te The pulse rate should be increased at least a factor of 10 on the magnetic tape package in order to improve demand definition. 8. Remote the recorder from the metering package. Tyee vs C.T. ratio and accuracy class needs to be verified as C.T.s were inaccessible on the station service metering. Ze The generator C.T.s are not 0.3 accuracy class and are relay class. Se The station total metéring is three wire but the system is four wire. This metering should be changed to four wire for best accuracy. 4. The test switch should be rewired to enable easier testing for the magnetic tape metering package. OS The pulse rate to the magnetic tape should be increased by at least a factor of 10 to improve demand definition. 6. Remote the recorder from the metering package. Swan.Lake 1. The potential transformer should be disconnected from the metering circuit for both station service meters. They are not necessary and create inaccuracies inthe registration. Ze Install test switches or "slide" kits to enable easier testing of station service meters. Se Station service C.T.s are not 0.3 accuracy class. Ae Due to loading of P.T.s and wire length, a separate potential cable should be run to the generator meters. Soglomon..Gulch Le Replace the Fuji meters with magnetic suspension type. 2. Verify C.T. ratio and accuracy class. 3. Change metering to four wire WYE. 4. Change instrument transformers to revenue class. Meals. Substation de Correct the wiring on the 25 KV buss meter. 2. Verify C.T. and P.T. ratio and quality. Pump..Station #11 1. Replace meter demand register on circuit #1. 2 replace C.T.s with metering quality ones that are 0.3 accuracy class. 3. Rewire one meter. Terror.Lake l. Install test switch on the "Line Out" meters. 26 Remote the recorder from the metering package. 3 Replace instrument transformers with 0.3 accuracy class ones. 4. Change metering to four wire WYE scheme. Sis Install detent on Port Lyons "Line Out" meter. Airport.Substation,.. Kodiak Zs Change metering to four wire WYE configuration. die Change instrument transformers to 0.3 accuracy class. 36 Verify C.T. ratio and accuracy on three installations. IV. L. Swampy_Acres Le. Verify C.T. ratios and quality. 2. Change instrument transformers to 0.3 accuracy class. 3. Change metering to four wire WYE. 4. Change meter register on Airport "Line In" meter. CONCLUSION Many of the installations are in considerable error and, due to the large amounts of power they meter, should be repaired. Those installations where billing occurs should definitely be brought into plus or minus 0.3 accuracy. The meters themselves, with a coupled of exceptions, were left better than plus or minus 0.3% accuracy. If demand is to be billed in the future, magnetic tape recorder packages or similar devices should be installed to provide suitable demand definition. V. INDIVIDUAL SITE AUDIT SHEETS TEST CARD - FILE # 1985-1 *#** CUSTOMER SERVICE INFORMATION *** Test Date: 12-02-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Substation Breaker T-51 Line | Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12,470 ***METER INFORMATION *** Meter #!->! Voltage: 120 Kh:!-3 Test Amps: 2-5 Manuf: Westinghouse Wire: 4 Rr: 46 8/27 M. Factor: 5/6 Type: D4B-3FM Phase: 3 Gr: 100 Form: 9B Demand Register Type: Mark Ia Intervals! > Full Scale: 4-32 *** METER TEST DATA *** As Found Full Load: 92!% Light Load: -0-14% EFF; 914% pp; -0.5% Bal: 9-36% As Left Full Load: 2!% Light Load: ~9-14% EFF; 09-14% — pp; -0.5% Bal: 09-36% Demand Test:Correct Reset Motor Time:!?> Min Creep Test: No Creep Measured PF: 93% *** METER DATA *** Correct Meter Application: Y°S Meter Condition: 6°04 As Found Readings: KwH!68 Kw 08 KVAR- 12 Month Peak KW: Meter Defects: None None Meter Adjustments: Multiplier: !000 Socket Bypass Condition: Test Switch - Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 100/300 5 on 100 Tap C.T. Burden Test: Fair - No Drop | ohm @ 2.3 amps Potential Transformer: GE JVM-5 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: nae ee = Instrument Wiring: — Current Circuit Wire Size:! Length: n Condition: °°4 *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN 120.8 Ven 119.9 Von 120.4 c 4 Wire Van VBN Von B Cc 3 Wire v AB Vac Vo A *** PHASE ANGLE *** nN WYE Vanl, 16-3 Vantn 21-0 Von 26.2 Delta V,-I Vee Vanl ACA BC'B CNC BNeutral lf Center Tip 1985-1 Wrangell Substation Breaker T-51 Line | Page 2 ***COMMENTS*** CT nameplate date was not available to varify accuracy class and ratio. ***R ECOMMENDATIONS*#** Varify accuracy class of current transformers. TEST CARD - FILE # 1985-2 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-02-85 Rate Schedule: Alaska Power Authority Customer: wrangell Substation - Breaker T-52, Line 2 Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12,470 ***METER INFORMATION *** Meter # 1-52 Voltage: 120 Kh:1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: - Rr: 46 8/27 M. Factor: 5/6 Type: D4B-3FM Phase: 3 Gr: 100 Form: 9B Demand Register Type: Mark Ia Interval: 15 Full Scale: 4.32 *** METER TEST DATA *** As Found Full Load: -9-16% Light Load: 0.14% EFF: -0.1% PF: -0.12% — Bals 1.07% As Left Full Load: -9-39% Light Load: 0.0% EFF: 0.31% PF:-0.28% Bal: 0.07% Demand Test:Correct Reset Motor Time:!5 Min Creep Test: No Creep Measured PF: 84.7% ##* METER DATA *** Correct Meter Application: Yes Meter Condition: Fair As Found Readings: KWH 4728 KW 0.28 KVAR- 12 Month Peak KW: Meter Defects: Can not bring full load into 0.3 accuracy Meter Adjustments: Balance Light Load Multiplier: 1900 Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: !00/300 to 5 on Tap C.T. Burden Test: Fair No Drop 0.6 ohms @ 0.9 amps Potential Transformer: GE JVM-6 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct _ Instrument Wiring: Correct Current Circuit Wire Size: !2 Length: 15' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 121-8 Yan 120.6 Yon 121.8 c 4 Wire VAN VBN Von B Cc 3 Wire VaB Vac Von *** PHASE ANGLE *** N WYE Vania 23-5 YVenlg 48 VYente 24.8 ie YaciA “ac's Yenic 8 Neutral If Center fie 1985-2 Wrangell Substation - Breaker T-52, Line 2 Page 2 ***COMMENTS*** Could not bring full load into 0.3 accuracy. F.L. adjustment has run to it's stop. CT accuracy class could not be varified. ***RECOMMENDATIONS*** Meter should be returned to the factory to replace damping magnet. Varify accuracy class of current transformers. TEST CARD - FILE # 1985-3 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-02-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Substation - Breaker T-53, Line 3 Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter # T-53 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 46 8/27 M. Factor: 5/6 Type: D4B-3FM Phase: 5 Gr: 100 Form: 9B Demand Register Type: Mark Ia Interval: 15 Full Scale: 4.32 #*# METER TEST DATA *** As Found Full Load: 9-47% Light Load: 90-10% EFF: 0.38% pF; -0.24% Bal: 0.24% As Left Full Load: 0.27% Light Load: -0-04% EFF: 0.21% pp; -0.42% Balz 0.24% Demand Test: Correct Reset Motor Time: !5 Min Creep Test: No Creep Measured PF: 92.5% +#* METER DATA *** Correct Meter Application: Correct Meter Condition: Good As Found Readings: KWH 5842 Kw 0.75 KVAR - 12 Month Peak KW: Meter Defects: None Meter Adjustments: Full Load Multiplier: 1000 Socket Bypass Condition: Good Test Switch *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 100/300 to 5 on 100 Tap C.T. Burden Test: Fair No Drop 0.6 ohms @ 1.6 amps Potential Transformer: GE JVM-5 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 12 Length: 15! Condition: Good *#** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** se YAN 121.5"BN 120.4.CN 121.4 c 4 Wire VAN VBN Von B Cc 3 Wire VaB Vac Von *** PHASE ANGLE *** " WYE Vania. 20.3"BN'B_ 20.9 “cNIc 25.5 — VAC'A Yac's Yen'c B Neutral If Center The 1985-3 Wrangell Substation - Breaker T-53, Line 3 Page 2 ***COMMENTS*** CT's are not 0.3 accuracy class for metering. As per Winston Davies. ***RECOMMENDATIONS*** Replace current transformers with 0.3 accuracy class. TEST CARD - FILE # 1985-4 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-02-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Substation - Main KWH Meter "IN" Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter # 150-KWH Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 15 35/81 M. Factor: 5/18 Type: WRP-23-KWH phase: 3 Gr: 100 Form: - Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** As Found Full Load: 9-15% Light Load: -0-84% EFF: -0.05% pF: -0.12% Bal: 0.30% As Left Full Load: 918% Light Load: 09-12% EFF: 0.17% pF: -0.02% Bal: 0.30% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Dirty As Found Readings: KWH 22013) Kw N/A KVAR N/A 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 1000 Socket Bypass Condition: | No Test Switch *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 300/600 to 5 on Tap C.T. Burden Test: Potential Transformer: GE JVM-5 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct _ Instrument Wiring: Correct Current Circuit Wire Size: !? Length: 2° Condition: Good *** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE Van 120-8 Vpy 120-1 Von 121.0 = 4 Wire VAN Ven Von B c 3 Wire VaB Vac VoA #4 PHASE ANGLE *** N WE Vania Yen's Yonlc Delta V,_I Von) Var! ACA BCB CNC B Neutral If Center fip 1985-4 Wrangell Substation - Main KWH Meter "IN" Page 2 ***COMMENTS*** There is no test switch for this metering package making it difficult and time consuming to test. Each month the package must be opened to change the tape. This allows a large amount of contamination to enter the meter as they do not have individual glass covers. Pulses from this meter are recorded on "B" channel of the tape recorder. Pulse MP = 1250/81 which gives a KWH/Pulse of 100. Demand definition is 400 KW. Could not varify accuracy class of current transformers. ***RECOMMENDATIONS*** Install test switch. Change pulse initiator to an MP 125/81 giving a demand definition of 40 KW. Varify accuracy class of current transformers. Move recorder out of metering package to eliminate the need to open it each time the tape is changed. TEST CARD - FILE # 1985-5 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-02-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Substation - Main QH meter "IN" Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter # 150-QH Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 15 35/81 | _M. Factor: 5/18 Type: WRP-23QH Phase: 3 Gr: 100 Form: N/A Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** As Found Full Load: 9-96% Light Load: 0-10% EFF: 0.07% PF: 0.26% Bals 0.30% As Left Full Load: = 9:06% Light Load: 09-10% EFF: 0.07% PF: 0.26% Bal: 0.30% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Dirty As Found Readings: KWH N/A Kw N/A KVAR QH 18028 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1000 Socket Bypass Condition: No Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 300/600 to 5 on 300 Tap C.T. Burden Test: Potential Transformer: GE JVM-5 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: C°rrect Instrument Wiring: Correct Current Circuit Wire Size: !? Length: 29' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 120-8 Vay 120.1 Von 121.0 oH 4 Wire VAN VBN Von B ¢ 3 Wire Vv AB Vac Vo A *** PHASE ANGLE *** . WYE Vala Ven'a Von!c Delta V,_I Vent Vet ACA BCB CNC B Neutral If Center fis 1985-5 Wrangell Substation - Main QH meter "IN" Page 2 ***COMMENTS*** Pulse value is 100 QH/pulse and is fed to channel "O" of the recorder. See file 1985-4 for other comments. ***RECOMMENDATIONS*** Change pulse initiator to increase pulse rate. See file 1985-4. TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-03-85 Rate Schedule: 1985-6 Alaska Power Authority Customer: Petersburg Substation T-61, Line | Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter # 69-980-624 Voltage: 120 Kh: | 2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: ¢ 17/18 M. Factor: 1/12 Type: D4B-2FM Phase: 3 Gr: 190 Form: [5B Demand Register Type: Mark Ia Interval: 15 Full Scale: 28.8 *** METER TEST DATA *** As Found Full Load: 0.2% Light Load: _9.92% EFF: 0.16% PF: 9 08% Bal: . 0.15% As Left Full Load: 0.2% +=Light Load: -9.92% EFF: 0,.16% PF? -o.03% Balt 9.159 Demand Test: Correct Reset Motor Time: |5 Min Creep Test: No Creep Measured PF: 7 *** METER DATA *** Correct Meter Application: No Meter Condition: Gooq As Found Readings: KWH 4538 KW 0.1 KVAR _ 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1000 Socket Bypass Condition: = Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw WA159-C 300 Tap C.T. Burden Test: Did not perform - not enough load Potential Transformer: GE JVM-6 200:5 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: Length: Condition: **#* REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN YBN YcN - 4 Wire Van Ven Yon 6 7 3 Wire Vaan 114.7%BC 115.5 “CA *#* PHASE ANGLE *** . WYE Vaal, Ven'p Yonic pete VA AK Yac'a Yonic ONeutral If Center tp 1985-6 ; Petersburg Substation T-61, Line | Page 2 *** COMMENTS*** Load was not sufficient to perform burden and phase angle test. Current transformers are not 0.3 metering accuracy class. Service is 4 Wire WYE - metering is 3 Wire. ***RECOMMENDATIONS*** Change current transformers to 0.3 accuracy class and rewire for 3 element 4 Wire metering. TEST CARD - FILE # 1985-7 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-03-85 Rate Schedule: Alaska Power Authority Customer: Petersburg Substation T-62, Line 2 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter #f ©9-980-622 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 6 17/18 — M. Factor: 1/12 Type: D#B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark Ia Interval: 14 Full Scale: 28.8 *** METER TEST DATA *** As Found Full Load: 913% Light Load: -9-!2% EFF: 0.08% pF; -0.04% Bal: 0.35% As Left Full Load: 0.13% Light Load: -0.12% EFF; 0.08% pF. -0.04% Bale 0.35% Demand Test: Correct Reset Motor Time: !> Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: N° Meter Condition: Good As Found Readings: KWH 9234 Kw 4.0 KVAR - 12 Month Peak KW: Meter Defects: Wrong Demand Scale Plate Meter Adjustments: None Multiplier: Weg Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw WAC159C C.T. Burden Test: Good No Drop 2 ohms Potential Transformer: GE JVW-6 200:1 1.7 amps *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct = Instrument Wiring: Correct Current Circuit Wire Size: !° Length: 100 Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** we VAN YBN Von oc 4 Wire VAN VBN Von B Cc 3 Wire VaB 114.9 Vac Von LSet + PHASE ANGLE *** N wen Fa Yen's Venice Delta Vacla 48.5 Vac!n 350.3 Vonlc o.—sal pares A. 1985-7 Petersburg Substation T-62, Line 2 Page 2 ***COMMENTS*** The meter demand scale plate is wrong for this register, full scale should read 28.8 instead of 2.88. Current transformers are not 0.3 accuracy for revenue metering. Service is 4 Wire WYE metered 3 Wire. ***RECOMMENDATIONS*** Demand scale plate should be changed. Three element metering should be incorporated. Change CT's to 0.3 accuracy class and install a 4 Wire meter. TEST CARD - FILE # 1985-8 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-03-85 Rate Schedule: Alaska Power Authority Customer: Petersburg Substation - Main KWH Out, T-60 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter # ©9-980-623 Voltage: 120 Khz 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 6 17/18 = M. Factor: = 1/12 Type: D4B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark Ia Interval: 15 Full Scale: 28.8 *** METER TEST DATA *** As Found Full Load: ~9-4% Light Load: -2-68% EFF: -0-86% pF: -0.6% Bal: 0.3% As Left Full Load: ~9-3!% Light Loas!8% EFF: -0-21% pF; 0.18% Bal: 0.3% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: #*#* METER DATA *** Correct Meter Application: No Meter Condition: Fair - Dirty As Found Readings: KWH 4675 Kw 3-5 KVAR - 12 Month Peak KW: Meter Defects: No Fast Adjustment Left On - Full Load Meter Adjustments: Light Load Multiplier: 1000 Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw WACI59C 300:5 C.T. Burden Test: Gooc No Drop 2 ohms @ 1.4 amps Potential Transformer: GE JVW-6 200:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Incorrect Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 1° Length: 100' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** “ VAN VBN Yon 11) 4 kag VAN VBN Von B Cc 3 Wire VaB 114.7 Vac 115.6 Vor **#* PHASE ANGLE *** " we OV an'Aa Yen's Yonlc Delta V,_I 50.2 Va nll 349.8 Vaal AG A BCB CNC B Neutral If Center ip 1985-8 Petersburg Substation - Main KWH Out, T-60 Page 2 ***COMMENTS*** This system is 4 Wire, metered 3 Wire. CT's are not 0.3 metering accuracy. Wrong demand reset cover. Meter found unsealed. Meter full load adjustment is run to it's high end and meter is not within 0.3 accuracy. Meter is wired for in megawatts, but is label main out. ***RECOMMENDATIONS*** Replace meter cover and register scale plate with proper scale plate. Rewire for "OUT" power. Change to 4 Wire metering. Change current transformers to 0.3 accuracy and change PT's for 4 Wire metering. TEST CARD - FILE # 1985-9 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-03-85 Rate Schedule: Petersburg Substation Main Power IN T-60 KWH 3 Phase 4 Wire WYE 14.4/24.9 Customer: Service Type and Voltage: ***METER INFORMATION *** Meter ¢69-983-852 Voltage: Lae Kh: |-2 Test Amps: 2+) Manuf: Westinghouse Wire: 3 Rr: © 17/18 M. Factor: 1/12 Type: ¥RPa2 Phase: 3 Gr: 100 Form: 5B Demand Register Type: - Interval: ~ Full Scales ~ *** METER TEST DATA *** As Found Full Load: °°" Light Load: “04% Epp; ~9-01% pp, 018% pay, 0.2% As Left Full Load: 99% = Light Load: “994% Epp; -0:01% pp, 018% pay, 0.2% Demand Test: Reset Motor Time: Creep Test: Measured PF: ##* METER DATA *** Correct Meter Application: na Meter Condition: V'Y Dirty As Found Readings: KWH 24705 KW KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1000 Socket Bypass Condition: None *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: See 1985-8 C.T. Burden Test: See 1985-8 Potential Transformer: See 1985-8 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct = Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 100 Condition: Good *** REVENUE CHANGE *** *#* VOLTAGE MEASUREMENTS *** WYE VAN VBN Von c 4 Wire VAN Ven Von B CG 3 Wire Vv AB Vac Vo A *#* PHASE ANGLE *** = WYE Vanla Yen'a Von! — Vacia ‘ac's Yenic B Neutral lf Center fir 1985-9 Petersburg Substation Main Power IN T-60 KWH Page 2 ***COMMENTS*** Installation has no test switch making it difficult and time consuming to test. Each month the package must be opened to change the tape. This allows large quantities of contamination to enter the meters. Service is 4 Wire, metered 3 Wire with an MP of 125/18; the pulse rate is 100 KWH/Pulse on channel "B", and 100 QH/Pulse on channel "C". Demand CT's are not 0.3 accuracy. ***RECOMMENDATIONS*** Rebuild system using a test switch and 4 Wire meters. Remote recorder eliminating contamination problem. Use MP of 25/36 to give demand definition of 40 KW. Change CT's to class 0.3 accuracy. TEST CARD - FILE # 1985-10 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-03-85 Rate Schedule: Alaska Power Authority Customer: Petersburg Substation Main Power IN T-60 QH Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 ***METER INFORMATION *** Meter # ©9-683-852 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse wire: 3 Rr: 617/18 M, Factor: 1/12 Type: WRP-22 Phase: 3 Gr: 100 Form: 5B Demand Register Type: *** METER TEST DATA *** As Found Full Load: 9-28% Light Load: 09-08% EFF: 0.24% pr; 0.08% Bal: 0.25% Interval: ~ Full Scale: - As Left Full Load: Light Load: EEF: PE: Bal: Demand Test: Reset Motor Time: Creep Test: Measured PF: #4 METER DATA *** Correct Meter Application: N° Meter Condition: Very Dirty As Found Readings: KWH 18257) Kw KVAR 12 Month Peak KW: Meter Defects: Meter Adjustments: Multipli = 1000 Socket Bypass Condition: None *** INS) UMENT TRANSFORMER DATA *** Current Transformers: 5° Test File 1985-8 C.T. Burden Test: See Test File 1985-8 Potential Transformer: 5€ Test File 1985-8 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: ©°'rect Instrument Wiring: Correct Current Circuit Wire Size: Length: Condition: *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN VBN Von c 4 Wire VAN Van Von B Cc 3 Wire VaB Vac Voa *** PHASE ANGLE *** N wre Van's Vania Von! Delta V, I vant Val ACA BCB CNC B Neutral If Center fhe 1985-10 Petersburg Substation Main Power IN T-60 QH Page 2 ***COMMENTS*** See File 1985-9 ***RECOMMENDATIONS*** See File 1985-9 TEST CARD - FILE # 1985-11 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-04-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Switchyard - "OUT" meter Service Type and Voltage: 3 Phase 4 Wire WYE 40 KV/69 KV ***METER INFORMATION *** Meter # 69-980-621 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 3 17/36 M. Factor: 1/24 Type: D4B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark Ia Interval: 15 Full Scale: 57.6 *** METER TEST DATA *** As Found Full Load: 9-08% Light Load: -0.42% EFF: -0.02% PF: -0.5% Bal: 0.15% As Left Full Load: 0.13% Light Load: 0.06% EFF: 0.12% PF: -0.3% Bal: 0.15% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 6322 KW 4.8 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 1000 Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Square D IK 650-4015-002 200/400:5 on 200 (not varified) C.T. Burden Test: Good No Drop 6 ohms @ 0.73 amps Potential Transformer: Square DV2-350-69 350/600 on 600 Tap *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 1° Length: 150 Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Ves ti a = 4 Wire VAN Van Von 8 c 3Wire Van 113.6¥EaC 113.5%eq 114.3 *** PHASE ANGLE *** N Wee Vesta Ven'B VYonlc Delta Vaca 27.5¥acly 327.3 Venlc 8 Neutral If Center Tap 1985-11 Wrangell Switchyard - "OUT" meter Page 2 ***COMMENTS*** CT ratio could not be verified. Demand definition is 500 KW. Service is 4 Wire WYE, but the metering is 3 Wire. ***RECOMMENDATIONS*** Verify CT ratio. Replace metering with 4 Wire. Instrument transformers exist to do this. Install mag tape to suitable demand definition. TEST CARD - FILE # 1985-12 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-04-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Switchyard - IN meter from mill Service Type and Voltage: 3 Phase 4 Wire WYE 14400/24940 ***METER INFORMATION *** Meter # 69-780-385 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 15 35/81 M. Factor: 5/18 Type: D4B-3FM Phase: 3 Gr: 100 Form: 9B Demand Register Type: Mark Ia Interval: 15 Full Scale: 12.96 *#** METER TEST DATA *** As Found Full Load: 09-53% Light Load: -0.02% EFF: 0.42% PF: -0.08% Bal: 0.57% As Left Full Load: 0.28% Light Load: 0.24% EFF: 0.27% PF: -0.38% Balz 0.43% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 9713 KW 0.22 KVAR - 12 Month Peak KW: Meter Defects: None Meter Adjustments: Balance Full Load Multiplier: 1000 Socket Bypass Condition: | Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 120:5 Bushing CT's on Line Breaker (not varified) C.T. Burden Test: Could not burden (no load) Potential Transformer: Westinghouse 120 ratio *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Circuit Grounding: Instrument Wiring: C@n't varify Current Circuit Wire Size: !4/10 Length: 155" Condition: Good *** REVENUE CHANGE *** ** VOLTAGE MEASUREMENTS *** WYE VAN VBN Von co 4 Wire VAN Ven Von B Cc 3Wire Van Vac Win *** PHASE ANGLE *** N WYE Vania Vania Vonic _— Vacia ‘c's Vente B Neutral If Center fhe 1985-12 Wrangell Switchyard - IN meter from mill Page 2 ***COMMENTS*** This is a new installation that is not yet energized. Current circuit is #14 in the panel and #10 to the breaker. All current circuit should be #10. The current transformers used on this installation are the bushing CT's on the breaker. They are not class 0.3 accuracy suitable for revenue metering. The wiring appears to be correct as marked, but we're unable to confirm this as the system is not energized. ***RECOMMDENATIONS*** Install current transformers of metering quality (0.3 accuracy class). TEST CARD - FILE # 1985-13 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-04-85 Rate Schedule: Alaska Power Authority Customer: Wrangell Switchyard - OUT meter from mill Service Type and Voltage: 3 Phase 4 Wire WYE 14400/24940 ***METER INFORMATION *** Meter # 1-54 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4aw Rr: 46 8/27 M. Factor: 5/6 Type: D4B-3FM Phase: 3 Gr: 10 Form: 9B Demand Register Type: Mark Ia Interval: 15 Full Scale: 4.32 *** METER TEST DATA *** As Found Full Load: 9-35% Light Load: -0-01% EFF: 0.28% PF: 0.02% Bal: 0.8% As Left Full Load: ~-9-12% Light Load: -0-02% EFF: -0.13% PF: -0.42% Bal: 0.26% Demand Test: Correct Reset Motor Time: 15 Min 6 Sec Creep Test: No Creep Measured PF: - *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 4462 Kw 0.03 KVAR 12 Month Peak KW: Meter Defects: Detent was not working properly Meter Adjustments: Balance Multiplier: 3000 Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-12 C.T. Burden Test: See File 1985-12 Potential Transformer: See File 1985-12 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-12 Circuit Grounding: S€¢ File 1985-12 _ Instrument Wiring: S¢¢ File 1985-12 Current Circuit Wire Size: 14/10 Length: 155' Condition: Good *** REVENUE CHANGE *** ** VOLTAGE MEASUREMENTS *** ala VAN VBN Von c 4 Wire VAN VBN Von B Cc 3 Wire Vv AB Vac Vo A #44 PHASE ANGLE *** “ Wve. Vania Yen's Yenc a VACIA Yac's Yenc B Neutral If Center The 1985-13 Wrangell Switchyard - OUT meter from mill Page 2 *** COMMENTS*#** Adjusted detent. See file 1985-12. ***RECOMMENDATIONS*** See file 1985-12. TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** pe Test Date: 12-05-85 Rate Schedule: Alaska Power Authority Customer: Tyee Power House Generator #2 Station Service Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 ***METER INFORMATION *** Meter # 69-981-220 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 86 29/36 M. Factor: T1T2: Type: D4B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark Ia Interval: 15 Full Scale: 2.304 ##* METER TEST DATA *** As Found Full Load: 0.09% Light Load: 0.36% EFF: 0.14% PF: -0.08% Bals 0.05% As Left Full Load: 0.06% Light Load: -0.06% EFF: 0.04% PF: - Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 00549 KW 0 KVAR 0 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 1000 Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 1200:5 (not verified) C.T. Burden Test: Could not perform - No load Potential Transformer: Westinghouse PPW 4 to 1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 12 Length: = 10' Condition: *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE tom Yen eg 4 Wire VAN Ven Von B 3 Wire Van 119.¥ Bc 119.%cCA 119.2 *** PHASE ANGLE *** ' ae YAK Yen's Venic Delta Vacla a Ved: 8 0.12% Balz 0.05% Good Neutral If Center fip 1985-14 Tyee Power House Generator #2 Station Service Page 2 ***COMMENTS*** Service was not loaded so could not perform CT burden test or phase angle test. See file 1985-15. ***RECOMMENDATIONS*** See file 1985-15. TEST CARD - FILE # = 1985-15 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-05-85 Rate Schedule: Alaska Power Authority Customer: Tyee Power House Generator #1 Station Service Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 ***METER INFORMATION *** Meter # 69-981-219 Voltage: 120 Kh: 1.2 Test Amps: 25 Manuf: Westinghouse Wire: B Rr: 86 29/36 M. Factor: 7 5/72 Type: D4B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark Ia Interval: 15 Full Scale: 2.304 *** METER TEST DATA *** As Found Full Load: 0.26% Light Load: 0.06% EFF: 0.22% PF: -0.22% Bal: 0.1% As Left Full Load: 0.26% Light Load: 0.06% EFF: 0.22% PF: -0.22% Bal: 0.1% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *#* METER DATA *** Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 01617. KW _ 0.222 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1000 Socket Bypass Condition: | Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 1200:5 (not verified) C.T. Burden Test: Good No Drop @ 3 ohms 0.99 amps Potential Transformer: Westinghouse PPW 4:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: !2 Length: 10 Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Vv Vv. Vv AN BN CN ie 4 Wire VAN Ven Von 8 ¢ 3Wire Van 120.1¥BC 119.8%CA 118.9 *** PHASE ANGLE *** - WYE Vaal, Ven'p Vonlc Delta V,-,lI G53 I Ven! A ACA 5.¥aclp 340.1"CN'C BNeutral If Center Tap 1985-15 Tyee Power House Generator #1 Station Service Page 2 ***COMMENTS*** Service is 4 Wire WYE metered 3 Wire. If all loads are not connected line to line errors could result due to unmetered leg. CT's were not accessible to verify the ratio and accuracy class. ***RECOMMENDATIONS*** Verify CT accuracy and ratio. Change to 4 Wire metering. TEST CARD - FILE # 1986-16 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-05-85 Rate Schedule: Alaska Power Authority Customer: Tyee Power House Generator Unit #1 Service Type and Voltage: 3 Phase 3 Wire 13.8 KV ***METER INFORMATION *** Meter # 69-980-614 Voltage: 120 Khs 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 4 49/144 M. Factor: 5/96 Type: D4B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark la Interval:15 Full Scale: 46.08 *** METER TEST DATA *** As Found Full Load: 90-14% Light Load: 0.36% EFF: 0.18% PF: -0.18% Bal: 0.05% As Left Full Load: 9-26% Light Load: 0.16% EFF: 0.24% PF: 0.18% Bal: 0.05% Demand Test: Correct Reset Motor Time:15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 5069 KW 0.30 KVAR 12 Month Peak KW: Meter Defects: Detent not engaged properly Meter Adjustments: Light Load Multiplier: 1000 Socket Bypass Condition: Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: RISHO KOGYO ER-48 800:5 C400 C.T. Burden Test: Not performed - no load/not energized Potential Transformer: RISHO KOGYO RP172-M 120-1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: !0 Length: 100' a *##* REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Vv Vv Vv ~ AN BN CN c 4 Wire Vax Ven Von B c 3Wire Van a Yor *** PHASE ANGLE *** N WYE Vania Vana Von!c Delta Vacla Vaply Tradl B Neutral If Center Ths 1986-16 Tyee Power House Generator Unit #1 Page 2 *** COMMENTS*#** Generator #1 was off line so could not burden or phase angle CT's. CT's are relay class C400 and not 0.3 accuracy metering class. Relays are also in the metering circuit. ***RECOMMENDATIONS*** 0.3 accuracy CT's should be installed. TEST CARD - FILE # 1985-17 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-05-85 Rate Schedule: Alaska Power Authority Customer: Tyee Power House Generator #2 Service Type and Voltage: 3 Phase 3 Wire Delta 13.8 KV ***METER INFORMATION *** Meter #69-980-618 Voltage: 120 Kh: |.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 4 49/144 M. Factor: 5/96 Type: D4B-2FM Phase: 3 Gr: 100 Form: 5B Demand Register Type: Mark Ia Interval: 15 Full Scale: 46-08 *** METER TEST DATA *** As Found Full Load: 9 !9% Light Load: 09-30% EFF; 09-21% pp; 0.5% —§ Bal: 0.28% As Left Full Load: 919% Light Load: 9:30% EFF: 09-21% pp; 0.5% — Bal; 0-28% Demand Test: Correct Reset Motor Time: !> Min Creep Test: No Creep Measured PF: **#* METER DATA *** Correct Meter Application: Yes Meter Condition: As Found Readings: KWH 6604 Kw 7-4 KVAR N/A 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1900 Socket Bypass Condition: Test Switch Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: RISHO KOGYO ER-48 80025 C.T. Burden Test: No Drop @ 6 ohms and 1.66 amps Potential Transformer: RISHO KOGYO RP172-m 120:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: !° Length: 100" Condition: G°0d *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN VBN Von ce. 4 Wire VAN Ven Von B Cc 3 Wire VaB 111.9 Vac 111.6 Voa 111.7 ++ PHASE ANGLE *** N WYe Vania Van's Ven! Delta Vv — I i Sel 321.4 VA. ACA BCB eh B Neutral lf Center Tur 1985-17 Tyee Power House Generator #2 Page 2 ***COMMENTS*** CT's are relay class C400 and not 0.3 accuracy metering class. Relays are also in the metering circuit. ***RECOMMENDATIONS*** Install 0.3 accuracy CT's. TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-95-35 Rate Schedule: 1985-18 Alaska Power Authority Customer: Tyee Power House Switchyard KWH IN Service Type and Voltage: 3 phase 4 Wire WYE 39/69 KV ***METER INFORMATION *** Meter # 69-980-619 Voltage: 120 Kh: | > Test Amps: 2.5 Manuf: . Westinghouse Wire: 3 Rr= 3 17/36 M+ Factor: 1/24 Type: = D4B-2FM Phase: 3 Grz 109 Form: 5B Demand Register Type: Mark Ia Interval: |5 Full Scale: 57.6 *** METER TEST DATA *** As Found Full Load: 0.21% Light Load: 0,93% EFF: 0.18% PF: 0.0% Bal: 09.1% As Left Full Load: 0.21% Light Load: 9.93% EFF: 0.18% PF: 0.0% Bal: 0.1% Demand Test: Correct Reset Motor Time: [5 Min Creep Test! No Creep Measured PF: *** METER DATA *** Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 3748 KW 6.8 KVAR _ 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1000 Socket Bypass Condition: Test Switch Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: West BYM 200/400 on 200 tap C.T. Burden Test: Good - No Drop | ohm @ 1.2 amps Potential Transformer: Square D U2-350-69 350/600 on 600 tap *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 300! Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** = VAN VBN Von co 4Wire Vax Sec Von 8 Cc 3Wire Van 115.4%BC 14.s%CA 115.8 *** PHASE ANGLE *** N WYE Vanla Vania Vente Delta Vacla —i2./BclaB_ 315.8% cnic Bscuunl if Genter fie 1985-18 Tyee Power House Switchyard KWH IN Page 2 ***COMMENTS*#** This meter is wired for "OUT" power not "IN" power as it is marked. When used for "OUT" power it could be in error because the system it is trying to meter is 4 Wire WYE. The meter is 3 Wire. When used for "IN" the accuracy would be correct as the secondary transformer connection is Delta. This meter is in the same circuit as those in file 1985-19 & 20. ***RECOMMENDATIONS**#* Consider changing to 4 Wire metering. TEST CARD - FILE # 1985-19 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-05-85 Rate Schedule: Alaska Power Authority Customer: Tyee Power House Switchyard Kwh Out Service Type and Voltage: 3 Phase 4 Wire WYE 39/69 KV ***METER INFORMATION *** Meter #Kwh-Out Voltage: 120 Khs 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 2 Rr: 3 17/36 M. Factor: 1/24 Type: WRP-22 Phase: 3 Gr: 100 Form: 5B Demand Register Type: N/A Interval: N/A Full Scale: N/A *#** METER TEST DATA *** As Found Full Load: 09-08% Light Load: -0-88% EFF: -0.11% PF 0.12% Bal: 0.6% As Left Full Load: ~-9-3% Light Load: -0-16% EFF: -0.27% PF: -0.5% Bal: 0.45% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: *#* METER DATA *** Correct Meter Application: No Meter Condition: Dirty As Found Readings: KWH 48797 KW - KVAR - 12 Month Peak KW: Meter Defects: None Meter Adjustments: Balance - Light Load Multiplier: 1900 Socket Bypass Condition: *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: West BYM 200/400 on 200 tap C.T. Burden Test: Good No Drop | ohm @ 1.2 amps Potential Transformer: Square D U2-350-69 350/600 on 600 tap *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 19 Length: 300' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van Ven Yon co 4 Wire VAN VeBN Von B Cc 3Wire Van 115.6 Vac 114.8 Veg 115.8 *** PHASE ANGLE *** " WYE Vania Yen'a Ven! Delta V,_I 12.8 Val 315.8 Von} acla Bc!a 8 Von!c 8 Neutral If Center Tap 1985-19 Tyee Power House Switchyard Kwh Out Page 2 ***COMMENTS*** This metering could be in error. It is a B wire meter on a 4 Wire WYE system. The MP = 125/36 giving a 100 Kwh/Pulse on channel B and 100 QH/Pulse on channel C. The metering package must be opened each month to change the mag tape. This brings in a large amount of dirt to contaminate these meters. The test switch is improperly wired to use for testing. ***RECOMMENDATIONS*** Change to 4 Wire metering. Install a pulse initiator with an MP of 25/72 to bring demand definition to 40 KW. Remote the recorder so as to not contaminate the meters. Rewire the test switch. TEST CARD - FILE # 1985-20 *#** CUSTOMER SERVICE INFORMATION *** Test Date: 12-05-85 Rate Schedule: Alaska Power Authority Customer: Tyee Powerhouse Switchyard - Q-Hour Out Service Type and Voltage: 3 Phase 4 Wire WYE 39/69 KV ***METER INFORMATION *** Meter # QH-Out Voltage: 120 Kh: 1.2 Test Amps: Zed Manuf: Westinghouse Wire: 3 Rr: 3 17/32 M. Factor: 1/24 Type: WRP-22 Phase: 3 Gr: 100 Form: 5B Demand Register Type: Interval: Full Scale: *** METER TEST DATA *** ; As Found Full Load: 9-93% Light Load: 0-46% EFF: 0.12% PF: 0.34% Bal: 0.01% As Left Full Load: 992% Light Load: 0-14% EFF: 0.04% PF: 0.12% Balz 0.01% Demand Test: Reset Motor Time: a at = Creep Test: No Creep Measured PF: : *** METER DATA *** Correct Meter Application: No Meter Condition: Dirty As Found Readings: KWH KW KVAR QH 02642 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 1000 Socket Bypass Condition: *##* INSTRUMENT TRANSFORMER DATA *** Current Transformers: West BYM 200/400 07 200 Tap de ele tes See File 1985-19 Potential Transformers Square D U2-350-69 350/600 on 600 Tap *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-19 See File 1985-19 See File 1985-19 Circuit Grounding: Instrument Wiring: Current Circuit Wire Size: ™ Length: 30" Condition: *** REVENUE CHANGE *** *#* VOLTAGE MEASUREMENTS *** ate VAN VBN Von ar 4 Wire VAN Van Von B Cc 3Wire Van 1156 Vg. 148 Veg 115.8 *#* PHASE ANGLE *** N WYE Vania a Van's Von!c Delta Vv, I Sue. | | ise wot ACA BCB CNC B Neutral If Center ie 1985-20 Tyee Powerhouse Switchyard - Q-Hour Out Page 2 ***COMMENTS*** See File 1985-19 ***RECOMMENDATIONS*** See File 1985-19 TEST CARD - FILE # — 195-2) ##* CUSTOMER SERVICE INFORMATION *** Test Date: 12-06-85 Rate Schedule: Customer: Bailey Substation - Swan Lake Line Alaska Power Authority Service Type and Voltage: 3 Phase 3 Wire 34.5 KV Delta ***METER INFORMATION *** Meter # 30-979-663 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: G.E. Wire: 2 Rr: 5 5/9 M. Factor: 1/30 Type: DS-63 Phase: 3 Gr: 50 Form: 5B Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** As Found Full Load: Light Load: 0.0% EFF: -0.14% PF: -0.12% Bal: 0.15% As Left Full Load: -0.18% Light Load: 0.0% EFF: -0.14% PF: -0.12% Bals 0.15% Demand Test: N/A Reset Motor Time: N/A Creep Test: | Good - No Creep Measured PF: Yes *** METER DATA *** Correct Meter Application: | Good Meter Condition: Good As Found Readings: KWH 98036 KW N/A KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 1000 Socket Bypass Condition: | Test Plug - Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: GE MRB CT 500 to 5 Tap, C200 ratio not verified C.T. Burden Test: Good - No Drop @ 4 ohms and 2.64 amps Potential Transformer: JV1-200 300-1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: !0 Length: 100! Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VaN VBN Von c 4 Wire Van Van Von ) Cc 3 Wire Vag 112.6¥ ac 112.2Voq 112.1 *** PHASE ANGLE *** . WYE Vania Yen's Yonic Delta Val, 39.0 acly Venlc VBCIC 39.4 BNcawal if Genter fap 1985-21 Bailey Substation - Swan Lake Line Page 2 ***COMMENTS*** The CT's are relay class C 200 and not suitable for 0.3 accuracy metering. There is "IN" metering only (power from Swan Lake), but no "OUT" metering (power to Swan Lake in the event Swan Lake not running). CT ratio could not be verified. ***RECOMMENDATIONS*** Install 0.3 metering accuracy CT's and verify ratio. Consider installing "OUT" metering. An electronic "IN" and "OUT" meter could be used with a mag tape recorder. TEST CARD - FILE # 1985-22 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-07-85 Rate Schedule: Alaska Power Authority Customer: Swan Lake Power House - Generation Unit #1 Service Type and Voltage: 3 Phase 3 Wire 13.8 KV ***METER INFORMATION *** Meter # 30-978-486 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: G-E. Wire: 3 Rr: 166 2/3 M. Factor: 1 Type: DS-63 Phase: 3 Gr: 50 Form: 5B Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** As Found Full Load: ~9-06% Light Load: -0-06% EFF: -0.06% PF: -0.36% Bal: 0.30% As Left Full Load: ~9-6% Light Load: -0-06% EFF: -0-06% pF; -0.36% Bal: 0.30% Demand Test: N/A Reset Motor Time: N/A Sena Creep Test: Good - No Creep Measured PF: *** METER DATA *** Correct Meter Application: Y&S Meter Condition: Good As Found Readings: KWH 92350 Kw N/A KVAR 12 Month Peak KW: Meter Defects: No Defects Meter Adjustments: None Multiplier: 19200 Socket Bypass Condition: Test Plug *** INSTRUMENT TRANSEORMER, RATA Current Transformers: C.T. Burden Test: Good No Drop 4 ohms @ 1.54 amps Potential Transformer: Balteau Stand, Inc. - V102-110 120 to 1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct = Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 150' Condition: Good **#* REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** hediias VAN YBN Yon c 4Wire Van Naas Mein B C a Wie “ap 148 “eG: 1150 “ea 108 === PHASE: ANGLE => N YE VA A Yen's Yen!c Dele Vadis sae Sarda: igh Mend b Neutral If Center The 1985-22 Swan Lake Power House - Generation Unit #1 Page 2 ***COMMENTS*** There is approximately 0.5 volt drop on the potential transformer circuit caused by loading of the PT's and PT circuit. ***RECOMMENDATIONS*** Run seperate potential leads from PT's to KWH meter. TEST CARD - FILE # 1935-23 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-07-85 Rate Schedule: Alaska Power Authority Customer: Swan Lake Powerhouse - Generation Unit #2 Service Type and Voltage: 3 Phase 3 Wire 13.8 ***METER INFORMATION *** Meter # 320-978-435 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: G-E- Wires 3 Rr: 166 2/3. M. Factor: 1 Type: DS-63 Phase: 3 Gr: 50 Form: 5B Demand Register Type: N/A / Interval: N/A Full Scales N/A *** METER TEST DATA Es dalad As Found Full Load: ~-9-06%] Light Load: -0-04% EFF: -0.06% PF: -0.22% Bal: 0.0% As Left Full Load: ~9-96% Light Load: -9-04% EFF: -0.06% PF: -0.22% Bal: 0.0% Demand Test: N/A Reset Motor Time: N/A ede Creep Test: G0od - No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 92930 Kw N/A KVAR N/A 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 19200 Socket Bypass Condition: Test Plug *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: G-E+ JCS-O 800 to 5 C.T. Burden Test: No Drop @ 5 ohms and 1.73 amps Potential Transformer: Balteau Stand, Inc. V1-02-110, 120 to 1 *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: —— _ Instrument Wiring: Compe! Current Circuit Wire Size: !° Length: = Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** = VAN YBN Von c 4 Wire VAN Ven Von B Cc 3 Wire Van 114.3 Vac 114.7 YCA 114.6 *** PHASE ANGLE *** “ WE Yan's Yen's Venlc Delta Vacla 42.1 Vac!a 341.5 Vonlc 8 Neutral If Center eg 1985-23 Swan Lake Power House - Generation Unit #2 Page 2 ***COMMENTS*** See Test File 1985-22 ***RECOMMENDATIONS*** See Test File 1985-22 TEST CARD - FILE # 1985-24 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-07-85 Rate Schedule: Alaska Power Authority Customer: Swan Lake Powerhouse - Station Service #2 Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 Volts ***METER INFORMATION *** Meter #20-975-323 Voltage: 277 Kh:3.6 Test Amps: 2.5 Manuf: G-E- Wire: 4 Rr: 55 5/9 M. Factor: | Type: DS-55 Phase: 3 Gr: 50 Form: 6B Demand Register Type: N/A Interval:N/A Full Scale: N/A **#* METER TEST DATA *** As Found Full Load: 9-!16% Light Load: 9-27% EFF: 0.18% PF: 0.11% 0.33% As Left Full Load: 916% Light Load: 9-27% EFF: 0.18% PF: 0.11% — Bals 0.33% E Demand Test: N/A Reset Motor Time: N/A : Creep Test: Good - No Creep Measured PF: 94.1% *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 9555 Kw N/A KVAR - 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier:°/6 Socket Bypass Condition: No Bypasses *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Abbott 806-122 1200 to 5 C.T. Burden Test: Good - No Drop @ 5 ohms Potential Transformer: G.E. JAV-O 2.4 to 1, 0.6 amps *** PROPERLY APPLIED METER CIRCUITS #** Socket Wiring: cee Circuit Grounding: ©OTe*t Instrument Wiring: are Current Circuit Wire Size: !? Length: 10" Condition: Good *#** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** as VAN YBN Von 114.4 co 4 Wire VAN VBN Von B C 3 Wire VaB Vac Vou *** PHASE ANGLE *** " WYE Vania Veni Vente Delta Vacla 32.2 Vac!a 7.1 Von 8 Neutral If Center Te 1985-24 Swan Lake Powerhouse - Station Service #2 Page 2 ***COMMENTS*** This meter is rated 277 volts but is driven by 120 volts causing a 1.12% over registration. The 2.4 to 1 PT's should not be used for this meter. There is no test switch or provision for testing the meter without disconnecting wires and shunting the CT's with jumpers. This is very time consuming and difficult to test. Current transformers are not 0.3 metering accuracy and are designed for relay application. Ratio could vary as much as plus or minus 10%. ***RECOMMENDATIONS*** Remove PT's from the metering circuit. Meter multiplier will become 240. Install "slide" kit or test switch to provide a location for entering the circuit for test. TEST CARD - FILE # 1985-25 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-07-85 Rate Schedule: Alaska Power Authority Customer: Swan Lake Powerhouse - Station Service #1 Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 volts ***METER INFORMATION *** Meter # 309-975-265 Voltage: 277 Kh: 3.6 Test Amps: 2.5 Manuf: G-E- Wire: 4 Rr: 555/9 M. Factor: 1 Type: DS-5S Phase: 3 Gr: 50 Form: 6B Demand Register Type: N/A Interval: N/A Full Scale: 9 N/A *** METER TEST DATA *** As Found Full Load: 919% Light Load: 9-46% EFF: 0.21% PF: -0.13% Bal: 0.30% As Left Full Load: ~7-°1% Light Load: 9-11% EFF: 0.01% pF; -0.21% Balz 0.30% Demand Test: N/A Reset Motor Time: N/A Creep Test: Good No Creep Measured PF: No Load *** METER DATA *** Correct Meter Application: N° Meter Condition: Good As Found Readings: KWH !828 Kw N/A KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: *”° Socket Bypass Condition: No Bypasses *** INSTRUMENT TRANSFORMER DATA *#** Gurrentclransfocmers: Abbott 806-122 1200 to 5 C.T. Burden Test: No Load - Could not test Potential Transformer: GE. JVO-O 2.4 to 1 *##* PROPERLY APPLIED METER CIRCUITS *** S et Wiring: No Load - Could not check Circuit Grounding: No Load - Could not check - ' Instrument Wiring: No Load - Could not check PT's not necessary Current Circuit Wire Size: |? Length: wa Condition: G0°d *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** Wik VAN YBN Yon — 4 Wire VAN VBN Von 2 Cc 3 Wire v AB Vac Vo A + PHASE ANGLE *+* " WYE Vanla Yen's Yonlc Delta Vacla Vacln Vonlc B Neutral If Center hs 1985-25 Swan Lake Powerhouse - Station Service #1 Page 2 *** COMMENTS*** See Test File 1985-24 with the exception that this meter is 0.84% over-registering. ***RECOMMENDATIONS*** See Test File 1985-24. TEST CARD - FILE # 1985-26 *#** CUSTOMER SERVICE INFORMATION *** Test Date: 12-12-85 Rate Schedule: Alaska Power Authority Customer: Solomon Gulch - Generation Unit #2 Service Type and Voltage: 3 Phase 4 Wire WYE 2400/4160 ***METER INFORMATION *** Meter # 15870 Voltage: 120 Kh: 105/208 Test Amps: 5 Manuf: Fuji Wire: 3 Rr: 238 2/21 M. Factor: 5/416 Type: D-16PWK 8T Phase: 3 Gr: | Form: Demand Register Type: Interval: Full Scale: *** METER TEST DATA ** As Found Full Load: 993% Light Loads -0-6% EFF: 0.10% PF: -0.66% Bal: 0.30% As Left Full Load: ~9-92% Light Load: 09-06% EFF: 0.0% PF: -0.28% ~ Balz 0.36% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: No Load *** METER DATA *** Correct Meter Application: No Meter Condition: Obsolete As Found Readings: KWH 4493 KW KVAR 12 Month Peak KW: Meter Defects: Obsolete Meter Adjustments: Light Load Multiplier: !00 Socket Bypass Condition: Test Plug Good *#*#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: !299 to 5 Fuji CEPB-6 C.T. Burden Test: No Load - Could not perform Potential Transformer: 4160 to 120 Riosho Kogyo RPG-175 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Incorrect Not Grounded Not Verified Circuit Grounding: Instrument Wiring: Current Circuit Wire Size: 12 Length: 150' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN YBN. Von c 4 Wire VAN Ven Von B Gc 3 Wire VaB Vac Vor *** PHASE ANGLE *** " WYE Vanla Vania Vonic —_ Vacia ‘ac's Yenc B Neutral If Center fap 1985-26 Solomon Gulch - Generation Unit #2 Page 2 ***COMMENTS*** This generator was off line at the time of test so could not phase angle or burden CT's. Meter has ball jewel disk suspension. Could not verify instrument transformers as to metering class (0.3 accuracy) or ratio. Current circuit is not grounded. This is a 4 Wire WYE circuit metered 3 Wire. ***RECOMMENDATIONS*** Meter should be changed to a state of the art 4 Wire WYE magnetic suspension meter. Verify CT's and PT's. Ground current return at current transformers. TEST CARD - FILE # 1985-27 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-12-85 Rate Schedule: Alaska Power Authority Customer: Solomon Gulch - Generation Unit #1 Service Type and Voltage: 3 Phase 4 Wire WYE 2400/4160 ***METER INFORMATION *** Meter # 19869 Voltage: 120 Kh: 105/208 Test Amps: 5 Manuf: Fuji Wire: 3 Rr: 238 2/21 M. Factor: 5/416 Type: D-l16PWK8T Phase: 3 Gr: | Form: Demand Register Type: Interval: Full Scale: *** METER TEST DATA *** As Found Full Load: 99% Light Load: -0-74% EFF: -0-15% PF: -0.14% Bal: 0.84% As Left Full Load: ~9-95% Light Load: ~9-08% EFF; -0.06% PF: 0.36% Balz 0.48% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: *###* METER DATA *** Correct Meter Application: N° Meter Condition: Obsolete As Found Readings: KWH 2074 KW KVAR 12 Month Peak KW: Meter Defects: Obsolete Meter Adjustments: Balance - Light Load Multiplier: 100 Socket Bypass Condition: Test Plug *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Fuji CEPB-6; 1200 to 5 C.T. Burden Test: Good No Drop 6 ohms @ 2.23 amps Potential Transformer: 4160 to 120 Risho Kogyo RPG-175 #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect Not Grounded Instrument Wiring: Correct Current Circuit Wire Size: 12 Length: 150' Condition: Good *** REVENUE CHANGE *** #* VOLTAGE MEASUREMENTS *** wve VAN VBN Von cc” 4 Wire Vay Ven Von B Cc 3 Wire Vag 122.4 %ac 123.0 YCA 122.0 *** PHASE ANGLE *** N WYE VYanla Ven'p Von! Delta Vaclg 32.1 %pclp 327.4 Yenic 8 Neutral If Center te 1985-27 Solomon Gulch - Generation Unit #1 Page 2 ***COMMENTS*** See File 1985-26 except this generator was on line. ***RECOMMENDATIONS*** See File 1985-26. TEST CARD - FILE # 1935-28 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-12-85 Rate Schedule: Alaska Power Authority Customer: Solomon Gulch - Line Meter Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter #272311 Voltage: 120 Khz 42/83 Test Amps: 5 Manuf: Fuji Wire: 3 Rr: 595 5/21 M.Factor: 5/166 Type: O-!6WTER Phase: 3 Gr: | Form: Demand Register Type: Interval: Full Scale: *** METER TEST DATA *** As Found Full Load: 9-45% Light Load: -1-73% EFF: 0.01% PF: -0.8% Bal: 3.91% As Left Full Load: 921% Light Load: -0-41% EFF: 0.09% PF: -0.07% Balz 0.24% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: ##* METER DATA *** Correct Meter Application: No Meter Condition: Obsolete - Poor As Found Readings: KWH 7635 KW KVAR 12 Month Peak KW: Meter Defects: Can't adjust light load obsolete meter Meter Adjustments: Balance Full Load Multiplier: 90° Socket Bypass Condition: Good - Test Plug *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Parallel 400:5 Siemens-Allis BCM15-1 C.T. Burden Test: Good No Drop 2 ohms @ 1.24 amps Potential Transformer: 24900:120 ratio test 8% low *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect CT return is not grounded Instrument Wiring: Not Verified Current Circuit Wire Size: 12 Length: 200' Condition: Good *** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYeE VAN VBN Yon oe) 4 Wire VAN VBN Yon B Cc 3 Wire Van 129.4 Yac 129.6 YCA 129.1 *** PHASE ANGLE *** N WYE Vanla Vania Venic Delta Vacl, 30.9 Yacla 329.3 Venic 8 Neutral If Center Tc 1985-28 Solomon Gulch - Line Meter Page 2 ***COMMENTS*** This meter is an obsolete ball jewel suspension. The service is 4 Wire WYE and the meter is 3 Wire. If the circuit loading is unbalanced meter error will result. The current transformers are only relay accuracy and fall below metering quality. The meter light load adjustment is ineffective and cannot be properly adjusted to bring it into 0.3 accuracy. CT's are paralleled for totalizing of both exit circuits. This will also add to metering error. Both circuit secondary's are not the same length. ***RECOMMENDATIONS*** Replace meter with a state of the art electronic totalizing meter capable of metering 4 Wire WYE. Install 0.3 accuracy instrument transformers ground current returns at CT's. TEST CARD - FILE # 1985-29 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-12-85 Rate Schedule: Alaska Power Authority Customer: Solomon Gulch - Substation Service Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 ***METER INFORMATION *** Meter # 774785 Voltage: 120 Kh: 5/12 Test Amps: 5 Manuf: Fuji Wire: 3 Rr: 750 M. Factor: 1/32 Type: FDI3HVR Phase: 3 Gr: | Form: Demand Register Type: N/A Interval: N/A Full Scales N/A ##* METER TEST DATA *** As Found Full Load: 3-77% Light Load: 452% EFF: 3.92% PF: 3.52% Bal: 6.14% As Left Full Load: ~9-11% Light Load: 9-0% EFF: -0.09% DPF: -0.28% Bal: 0.449% Demand Test: N/A Reset Motor Time: N/A Reda Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: No Meter Condition: Obsolete As Found Readings: KWH 78264 kw KVAR 12 Month Peak KW: Meter Defects: Obsolete Meter Adjustments: Balance, Full Load & Light Load Multiplier: Socket Bypass Condition: Good Test Plug *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 400:5 Abbott C.T. Burden Test: Good No Drop 6 ohms Potential Transformer: 480/120 Abbott *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct I Instrument Wiring: Correct Current Circuit Wire Size: 12 Length: 200' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** vie VAN YBN Yon c 4 Wire Vv AN Van Von B Cc omer | Nam |teie "ee | [30 “oa, beg “+ PHASE ANGLE #*** nN FEE) Tan A Yen's Vonlc TT VAciA aa “ac! Piel Yenc 8 Neutral If Center The 1985-29 Solomon Gulch - Substation Service Page 2 ***COMMENTS*** This service is 4 wire WYE but metered 3 wire. This is a ball jewel suspension that has been obsolete for 30 years. ***RECOMMENDATIONS*** Change meter to 4 wire WYE with magnetic suspension. TEST CARD - FILE # 1985-30 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-13-85 Rate Schedule: Alaska Power Authority Customer: Solomon Gulch - Fish Plant Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 ***METER INFORMATION *** Meter ## 67-884-907 Voltage: 240 Kh: 43.2 Test Amps: 30 Manuf: Westinghouse Wires 4 Rr: 2 17/54 M. Factor: 1 Type: D4S-8M Phase: 3 Gr: 100 Form: 14S Demand Register Type: Mark Ia Interval: 15 Full Scale: 72 *** METER TEST DATA *** As Found Full Load: -9-19% Light Load: -0-46% EFF: -0-24% pp; -1.09% Bal; 0.25% As Left Full Load: 0.0% Light Load: 0-22% EFF; 0.04% pr; -0-51% pal; 0-25% Demand Test: Correct Reset Motor Time: 1% Min | Sec Creep Test: No Creep Measured PF: *#* METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 28215 Kw 34 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Full Load, Light Load - Power Factor Multiplier: | Socket Bypass Condition: No Bypass *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: N/A C.T. Burden Test: N/A Potential Transformer: N/A *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct 7 Instrument Wiring: N/A Current Circuit Wire Size: N/A Length: N/A Condition: N/A *#*#* REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE YAN 282. BN 234 YCN 284.9 c 4 Wire Van, VN t.. B Cc 3 Wire VaB Vac Vou *** PHASE ANGLE *** N WYE Vanta Van's Von! Delta Vacl, Tapia oat 6 Neutral If Center Te 1985-30 Solomon Gulch - Fish Plant Page 2 ***COMMENTS*** None ***RECOMMENDATIONS*** None TEST CARD - FILE # 1985-31 **#* CUSTOMER SERVICE INFORMATION *** Test Date: 12-13-85 Rate Schedule: Alaska Power Authority Customer: Meals Substation KWH "In" circuit #4 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter # ©6-487-826 Voltage: 120 Kh:1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rrz55 5/9 M. Factor: | Type: D4B-3FM Phase: 3 Gr: 100 Form: B Demand Register Type: Mark Ia Intervals! 5 Full Scale: 3.6 *## METER TEST DATA *** . As Found Full Load: 36% Light Load: 90-06% EFF: 0.30% PF: 0.48% Bal: 0.30% As Left Full Load: ~9-15% Light Load:-9-24% EFF: -0-17% PF: 0.0% Balz 0.30% Demand Test:G00d Reset Motor Time:Good ae Creep Test: Good Measured PF: ### METER DATA *** Correct Meter Application: Yes Meter Condition:Good As Found Readings: KWH 2015 Kw 0-00 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Full Load, Light Load Multiplier: — Socket Bypass Condition: Test Switches Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw-Edison 300 to 5 C.T. Burden Test: Potential Transformer: Electomagnetic Industries BPO4-150; 120 to 1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding:Correct =i Instrument Wiring:Correct Current Circuit Wire Size: 10 Length: 175' Condition: Good *##* REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** blebs VAN YBN Yon — 4 Wire v AN VBN Von B Cc 3 Wire v AB Vac Vo A e* PHASE ANGLE *** N wre Vania Yen'B Yoni = YaciA ‘ac's Yenic B Neutral If Center fig 1985-31 Meals Substation KWH "In" circuit #4 Page 2 ***COMMENTS*** The demand pointer counter weight was bent causing inaccurate demand readings above 1.1 This was corrected. Meter had been sealed with line pliers. ***RECOMMENDATIONS*#** None TEST CARD - FILE # 1985-32 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-13-85 Rate Schedule: Alaska Power Authority Customer: Meals Substation - KQH "In" circuit #4 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter # 66-491-285 Voltage: 120 Khz 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 55 5/9 M. Factor: 1 Type: D4B-3F Phase: 3 Gr: 100 Form: B Demand Register Type: N/A Interval: N/A Full Scale: N/A *#** METER TEST DATA *** . As Found Full Load: 9-15% Light Load: -0-6% EFF: 0.0% PF: -0.06% Bals 0.60% As Left Full Load: 9-03% Light Load: -0-01% EFF: 0.02% PF: -0.18% Bals 0.46% Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: ### METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH KW KVAR KQH 0012 12 Month Peak KW: Meter Defects: None Meter Adjustments: Balance Light Load Multiplier: 729° Socket Bypass Condition: Test Switch Good *#*#* INSTRUMENT TRANSFORMER DATA *** ° Current Transformers; McGraw-Edison 300 to 5 C.T. Burden Test: Potential Transformer: Electromagnetic Industries BP04-150; 120 to 1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: 9 Correct Circuit Grounding: COTe*t Instrument Wiring: Coron Current Circuit Wire Size: 10 Length: 175' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** _—— VAN VBN Von c 4Wire Van Ven Von B Cc 3Wire Van Vac Non *** PHASE ANGLE ** N WYE Vana Ven'p Von!c Delta Vacla Yec'a Vonlc 8 a Neutral If Center Tap 1985-32 Meals Substation - KQH "In" circuit #4 Page 2 ***COMMENTS*** Pulse initiator not connected. Meter was sealed with line pliers. ***RECOMMENDATIONS*** None TEST CARD - FILE # 1985-33 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-13-85 Rate Schedule: Alaska Power Authority Customer: Meals Substation - KQH "Out" circuit #4 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter # 66-491-286 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 55 5/9 M. Factor: | Type: D4B-3F Phase: 3 Gr: 100 Form: B Demand Register Type: N/A Interval:N/A Full Scales N/A *** METER TEST DATA *** As Found Full Load: 9-42% Light Load: -0-04% EFF: 0.33% PF: 0.44% Bal: 0.17% As Left Full Load: 92% Light Loads -0.28% EFF: PF: 0.18% | Balz 0.17% Demand Test: N/A Reset Motor Time: N/a Cee tae Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Ys Meter Condition: Good As Found Readings: KWH KW KVARKQH 0607 12 Month Peak KW: Meter Defects: None Meter Adjustments: Full Load Multiplier: 720° Socket Bypass Condition: Test Switches *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw-Edison 300 to 5 C.T. Burden Test: Good No Drop 3 ohms @ 1.7 amps Potential Transformer: Electromagnetic Industries BP04-150; 120 to | *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: COrTeCt ' Circuit Grounding: ©°Te*t Instrument Wiring: Correct Current Circuit Wire Size:10 Length: 175' Condition: Gooq *** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE vi Vv, Vv ~ AN BN CN c 4 Wire VAN Van Von B CG 3 Wire VaB Vac Vor *** PHASE ANGLE *** nN wre a A Van's Venlo Delta Vacla Vacln Neale 8 a Neutral If Center Tap 1985-33 Meals Substation - KQH "Out" circuit #4 Page 2 ***COMMENTS*** Pulse initiator is not hooked up. Meter had been sealed with linemen's pliers. ***RECOMMENDATIONS*** None TEST CARD - FILE # 1985-34 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-13-85 Rate Schedule: Alaska Power Authority Customer: Meals Substation - KWH "Out" Circuit #4 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter i 65-487-831 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 55 5/9 M. Factor: 1 Type: D4B-3FM Phase: 3 Gr: 100 Form: B Demand Register Type: Mark la Interval: 15 Full Scale: 3.6 *+* METER TEST DATA *** As Found Full Load: 9:!7% Light Load: -0-54% EFF: 0.03% pF; -0.24% Bal: 0.7% As Left Full Load: —9-28°% Light Load: -0-22% EFF: 0.18% PF: 0.30% Bal: 0.3% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: 91.7% *** METER DATA *** Correct Meter Application: Y&S Meter Condition: Good As Found Readings: KWH 4479 Kw 0-70 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Full Load, Balance, Light Load Multiplier: 7200 Socket Bypass Condition: Good - Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current liranstocmers: McGraw-Edison 300 to 5 C.T. Burden Test: Potential Transformer: Electromagnetic Industries BP04-150; 120 to 1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 175' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** _ VAN YBN Von c 4 Wire VAN Ven Yon B Cc 3 Wire VaB Vac Vou *** PHASE ANGLE *** N WYE Vania 21.5 Yan’a 23.8 Vente 25.2 Delta V,_I v1 Val ACA BCB CNC BNeutral If Center fic 1985-34 Meals Substation - KWH "Out" Circuit #4 Page 2 ***COMMENTS*** None ***RECOMMENDATIONS*** None TEST CARD - FILE # 1985-35 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-13-85 Rate Schedule: Alaska Power Authority Customer: Meals Substation 25KV Buss Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 ***METER INFORMATION *** Meter # 66-487-830 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 55 5/9 M. Factor: 1 Type: D4B-3FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: 15 marked Pall Scale: 3.6 *** METER TEST DATA *** As Found Full Load: ~0-17% Light Load: -0-34% EFF: -0-20% pp; -0-12% Bal: 05% As Left Full Load: —-9-92% Light Load: 9-06% EFF: 09-03% pp; -0.06% pai; 0.2% Demand Test: Correct Reset Motor Time: !> Min Creep Tests No Creep Measured PF: *** METER DATA *** Correct Meter Application: Y€S Meter Condition: Good As Found Readings: KWH 39300 Kw 0-18 KVAR 12 Month Peak KW: Meter Defects: Wrong information on register name plate Meter Adjustments: Balance - Light Load Multiplier: Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Could Not Verify Breaker Bushing C.T. Burden Test: Good - No Drop @ 4 ohms and 0.9 amps Potential Transformer: Could Not Verity *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Incorrect Circuit Grounding: Instrument Wiring: Could Not Verify Current Circuit Wire Size: 12 Length: Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** loli VAN 128.2"BN 127.5°CR | izes c 4 Wire VAN Ven Von B CG 3 Wire VaB Vac Von *** PHASE ANGLE **+* N WYE Vania 2u9¥en'p —-266.0%cNIC 258.7 Delta Vacla Vac! Vonlc B A Neutral If Center Tap 1985-35 Meals Substation 25 KV Buss Page 2 ***COMMENTS*** This meter register is a 15 minute interval marked 30 minute. The lower bearing was improperly adjusted. This was corrected. Meter had been sealed with line pliers. This meter is improperly wired for KWH. The currents and potentials are not of the same phase causing the meter to want to drive in reverse at times. Current transformers are not 0.3 accuracy. ***RECOMMENDATIONS*** Rewire meter. Verify CT ratio and accuracy class. Change meter register name plate to read correctly. TEST CARD - FILE # 1985-36 *** CUSTOMER SERVICE INFORMATION *** 12-14-85 Test Date: Rate Schedule: Alaska Power Authority Customer: Station 12 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 ***METER INFORMATION *** 66-487-829 Meter # Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse wires 4 Rr: 55 5/9 M. Factor: 1 Type: nrewe Phase: 3 Gr: 100 Form: Demand Register Type: Mark: ti Interval: 15 Full Scale: 3.6 *«* METER TEST DATA ** As Found Full Load: ~7!2% Light Load: 916% EFF: -0-06% pF: -0.08% Bal: 0.36% As Left Full Load: ~°"!?% Light Load: 16% EFF; -0.06% pF; -0.08% Bal: 0.36% Demand Test: Correct Reset Motor Timez {5 Min Creep Test: No Creep Measured PF: 83% *** METER DATA *** Correct Meter Application: Yes Meter Condition: Gooq As Found Readings: KWH 1401 KW 0.08 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 7200 Socket Bypass Condition: Test Switch Good **#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: Power Transformer Multi Ratios CT 300 to 5 C.T. Burden Test: Could not perform - load @ 0.15 amps Potential Transformer: Electromagnetic Industries 120 to 1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 200' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 125.1 Yan 125.0 Yon 126.8 co 4 Wire Van Ven Yon 8 - 3 Wire VaB Vac Voa *** PHASE ANGLE *#* N WYE Vaqgia 33.09¥antn 32.9 Vente 34.7 Delta V,_-I V4 ali Vaal ACA BCB CNC B Neutral If Center ic 1985-36 Station 12 Page 12 ***COMMENTS*** CT ratio is too high for proper meter loading and good demand definition. Each division is 144 KWH. ***RECOMMENDATIONS*** Consideration should be taken to lower the CT ratio to 25:5. TEST CARD - FILE # 1985-37 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-14-85 Customer: Substation #11 - KWH Circuit #1 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV **#METER INFORMATION *** Rate Schedule: Alaska Power Authority Meter #66-487-827 Voltage: 120 Kh:1.8 Test Amps: 2+) Manuf: Westinghouse Wire: 4 Rr:55 5/9 M. Factor: ! Type: D4B-3FM Phase: 3 Gr: 100 Form: Demand Register Type: = Mark Ia Intervals > Full Scale: 3-6 *** METER TEST DATA *** As Found Full Load: 09-03% Light Load:-0-18% EFF; -0-01% pp, 0.0% Bal; 0:03% As Left Full Load: 01-03% Light Load: -0.18% EFF; -0-01% pp, 0.0% Bal: 29-03% Demand Test:Failed -3.6% Reset Motor Time:!> Min 2 Sec Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: P°°r As Found Readings: KWH 2868 Kw 0-81 KVAR 12 Month Peak KW: Meter Defects: Faulty Demand Register Meter Adjustments: None Multiplier: 2400 Socket Bypass Condition: Test Switch Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers; McGraw-Edison Type WAL59C 100 to 5 C.T. Burden Test: Fair No Drop @ | ohm and 1.4 amp Potential Transformer: 120 to | Not Verified *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct = Instrument Wiring: Correct Current Circuit Wire Size: 19 Length: 150! Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 125-4 Ven 125.2 Von 126.2 c 4 Wire Vv AN Van Von B ¢ 3 Wire Vv AB Vac Vo A *** PHASE ANGLE *#* “ WYE Vania 303.2Vanln 342.1 Vonlc 320.3 —_ Vacla Yac's Yenic B Neutral If Center fic 1985-37 Substation #11 - KWH Circuit #1 Page 2 ***COMMENTS*#** Demand rise test failed. Registration is 3.6% low. Current transformers are not class 0.3 metering accuracy. The circuit loading is badly unbalance. Meter was sealed with line pliers. ***RECOMMENDATIONS*** Replace demand register and recalibrate meter. Install 0.3 accuracy current transformers. TEST CARD - FILE # 1985-38 *#** CUSTOMER SERVICE INFORMATION *** Test Date: 12-14-85 Rate Schedule: Alaska Power Authority Customer: Substation #11 - KQH Circuit #1 Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***METER INFORMATION *** Meter # 66-491-284 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 55 5/9 M. Factor: 1 Type: D4B-3F Phase: 3 Gr: 100 Form: Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** As Found Full Load: 916% Light Load: 018% EFF: 0.16% PF: 0.14% Bal: 0.30% As Left Full Load: 9-!6% Light Load: 918% EFF: 0.16% PF; 0.14% Bal: 0.30% Demand Test: N/A Reset Motor Time: N/A = Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH KW KVAR KQH 1240 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 2400 Socket Bypass Condition: Test Switch *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw-Edison Type WA159C 100 to 5 C.T. Burden Test: Fair No Drop @ | ohm and 1.4 amps Potential Transformer: 120 to! Not Verified *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 150' Condition: good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 125.4 “BN 125.2 YON 126.2 c 4 Wire v AN Ven Von B Gc 3 Wire VaB Vac Voa *** PHASE ANGLE *** N WYE Vania 303-™Bn'B 342.1 YenIc 320.3 Delta Vacl, Yec'a Yoni 8 a Neutral If Center Tap 1985-38 Substation #11 - KQH Circuit #1 Page 2 ***COMMENTS*** Meter was sealed with line pliers. ***RECOMMENDATIONS*** None TEST CARD - FILE # 1985-39 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-14-85 Rate Schedule: Alaska Power Authority Customer: Substation #11 - 25 KV Bus Metering Service Type and Voltage: 3 Phase 4 Wire WYE 14.4/24.9 KV ***#METER INFORMATION *** Meter #66-487-328 Voltage: 120 Khs 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr: 55 5/9 M. Factor: 1 Type: D4B-3FM Phase: 3 Gr: 100 Form: Demand Register Type: = Mark la Intervals! 5 Full Scales 3.6 *** METER TEST DATA *** As Found Full Load: 09-44% Light Load: 2.48% EFF: 0.85% PF: 0.54% Balz 1.26% As Left Full Load: -9-25% Light Load: 09-28% EFF: -0.14% PF; -0.34% Bal: 0.27% Demand Test: Correct Reset Motor Time:15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Fair As Found Readings: KWH2261 Kw 0.08 KVAR 12 Month Peak KW: Meter Defects: Light Load Adjustments are closed limits Meter Adjustments: Full Load Multiplier: 7200 Socket Bypass Condition: Test Switch **#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: Power Transformer Multi-Ratio CT 300 to 5 C.T. Burden Test: Potential Transformer: 120 to | Not Verified *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Incorrect Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: !° Length: !7>' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 125-3 Vpn -:125.2 Von 126.4 c 4 Wire Van Ven Von B Cc 3.Wire Van Yec Yorn *** PHASE ANGLE *** N WYE Vania 110-0¥Vantg = 160-1 Youle 136.3 — Vacia “ects ‘onic BNeutral If Center Te 1985-39 Substation #11 - 25 KV Bus Metering Page 2 ***COMMENTS*** Meter had been sealed with line pliers. Once again the light load was quite fast. Had to make large adjustment in 1984 too. This meter is not properly wired for KWH. Current and potentials are not of the same phase. The test switch is wired on the load side of the meter. This was not corrected. Circuit loading is badly unbalanced. ***RECOMMENDATIONS*** Rewire meter. Lower CT ratio. TEST CARD - FILE # 1985-40 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-17-85 Rate Schedule: Alaska Power Authority Customers Tetfor Lake to Kodiak - Line KWH - Out Service Type and Voltage: 3 Phase 4 Wire WYE 138 KV Monee #TOTETSTL ann Meter Voltage: cee Kh: !-2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: !7 13/36 M. Factor: 5/24 Tye WRP-22 Pt - 3 Gr: 100 Form: Demand Register Type: Interval: Full Scale: #** METER TEST DATA *** : As Found Full Load: ~7"?™ Light Load: “024% Epp: ~-17% pp, -0:34% gay, 90-15% As Left Full Load: B® Tee toa OO pee, Demand Test: x * Reset Motor Time: N Creep Test: omreep Measured PF: *** METER DATA *** Correct Meter Application: Ba Meter Condition: an As Found Readings: KWH 6212 KW KVAR a 12 Month Peak KW: : Meter Defects: None Meter Adjustments: None Multiplier: 10000 — Socket Bypass Condition: No Bypass : *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: McGraw Edison 200:5 Not Varified C.T. Burden Test: Good No Drop 3 ohms @ 0.62 amps Potential Transformer: tench Elect TEV 138(200 VA) CCVT(0.6 accuracy) 1200:1 (WXYZ) #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: 9 Correct Circuit Grounding: Incorrect - Not Grounded Instrument Wiring: Could Not Verify Current Circuit Wire Size: 10 Length: 388! Condition: Good *#** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** We VAN VBN Yon co 4 Wire v AN Van Von B Cc 3Wire Van 113.1 %BC 9113.3 YCA 1131 *** PHASE ANGLE *** N Wre Van's Vania Yonlc Delta Vacl, 56.0%pclgp = 356 Ven! 8 a Neutral If Center Tut 1985-40 Terror Lake to Kodiak - Line KWH - Out Page 2 ***COMMENTS*** This meter package has no test switch. This makes it difficult and time consuming to test the meters. The mag tape recorder is not being used. Current return circuit is not grounded. Current transformers are on OCB bushings so we couldn't verify ratio and accuracy class. Should be 0.3 accuracy. Metering potentials are taken from the CCVT which are not metering accuracy class. Error on these instruments could amount to $2,000/month. See File 1985-62 for CCVT. File 1985-62 is a 4 Wire WYE circuit metered 3 Wire Delta. ***RECOMMENDATIONS*** Rebuild metering using 4 Wire WYE meters, form 9 and test switch. Ground current return circuit at the CT's. Verify CT ratio and accuracy class should be 0.3 accuracy for revenue metering. Install metering class potential transformers. TEST CARD - FILE # 1985-41 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-17-85 Rate Schedule: Alaska Power Authority Te Service Type and Voltage: 3 Phase 3 Wire WYE 138 KV ***METER INFO TION *** Meter Voltage: 120 Kh: 1.2 Test Amps: = 2.5 Manuf: Westinghouse Wire: 3 Rr: 17 13/36 M. Factor: 5/24 Type: WRP-22 Phase: 3 Gr: 100 Form: Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** - As Found Full Load: ~9-34% Light Load: -0-30% EFF; -0.33% PF: As Left Full Load: -9-98% Light Load: 09-28% EFF; 0.12% pF; Demand Test: N/A Reset Motor Time: N/A Creep Test: No Creep Measured PF: ae *** METER DATA *** f a Correct Meter Application: N° Meter Condition: Good a As Found Readings: KWH KW KVAR KQH 46420 °5> 12 Month Peak KW: Tos Meter Defects: None i Full Load Meter Adjustments: Multiplier: 10000 | Socket Bypass Condition: See File 1985-40 #*#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-40 C.T. Burden Test: See File 1985-40 Potential Transformer: See File 1985-40 #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-40 Circuit Grounding: See File 1985-40 _ Instrument Wiring: See File 1985-40 Current Circuit Wire Size: Length: Condition: *#** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE v Vv Vv = AN BN CN c 4 Wire v AN Ven Von B Cc 3Wire Van 2. we *** PHASE ANGLE *** N wre Vania Vania Yon! Delta Vacla ao Tok 6 a Neutral If Center Tut 1985-41 Terror Lake Powerhouse - Kodiak Line QH - Out Page 2 ***COMMENTS*** See File 1985-40. ***RECOMMENDATIONS*** See File 1985-40. TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-17-85 ***METER INFORMATION *** Meter (#30-983-543 Voltage: 120 Manuf: G-E. Wire: 3 Type: DSM-63 Phase: 3 Demand Register Type: M-30 *** METER TEST DATA *** As Found Full Load: 926% Light Load: 940% EFF: As Left Full Load: ~9-26% Light Load: -0-26% EFF: Khz 1.2 Gr: 50 Intervals 15 1985-42 Rate Schedule: Alaska Power Authority Customer: Terror Lake Powerhouse ~ Kodak Line KWH = In Service Type and Voltage: 3 Phase 4 Wire WYE 138 KV Test Amps: 2.5 Rr: 34 13/18 M. Factor: 5/24 Form: Full Scale: 9.6 0.29% pF; 0.0% — Bal: 0.75% -0.26% pR; -0.72%522 Bale 0.4% Demand Test: Correct Reset Motor Time: !5 Min ee Creep Test: No Creep Measured PF: *** METER DATA *** a Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 0007. —s KW 0.10 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Balance Full Load Multiplier: 10000, Socket Bypass Condition: *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-40 C.T. Burden Test: See File 1985-40 Potential Transformer: See File 1985-40 *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-40 Circuit Grounding: See File 1985-40 Instrument Wiring: See File 1985-40 Current Circuit Wire Size: Length: *#* REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE Vv AN Van Von 4 Wire VAN Van Von 3 Wire Vv AB Vac Vo A *#* PHASE ANGLE *** WYE Vania Vana Vonlc Delta Vacla Vaca Venice Test Plug Good Condition: a 8 Neutral If Center Tur 1985-42 Terror Lake Powerhouse - Kodiak Line KWH - In Page 2 ***COMMENTS*** See File 1985-40. ***RECOMMENDATIONS*** See File 1985-40. TEST CARD - FILE # 1985-43 *#* CUSTOMER SERVICE INFORMATION *** Test Date: 12-17-85 Rate Schedule: Alaska Power Authority Service Type and Voltage: 3 Phase 4 Wire WYE *+**METER INFORMATION *** Meter # 30-983-620 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: G-E. Wire: 3 Rr: 83 1/3 M. Factor: 75/144 Type: DSM-63 Phase: 3 Gr: 50 Form: Demand Register Type: M-30 Interval: 15 Full Scale: 4.00 *** METER TEST DATA *** : As Found Full Load: 0-13% Light Load: 0.43% EFF: 0.19% PF: 0.75% Bal 0.48% As Left Full Load: 9-12% Light Load: 0-3% EFF: 0.16% PF: Balz 0.48% Demand Test: Correct Reset Motor Time: 15 Min “ s Creep Test: No Creep Measured PF: : **+* METER DATA *** = Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 2978 Kw 1.09 KVAR a 12 Month Peak KW: mae a Meter Defects: None : Meter “ Light Load Multiplie Socket Bypass Condition: Test Plug Good **#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: 800:5 Not Verified C.T. Burden Test: Good No Drop 6 ohms @ 1.73 amps Potential Transformer: 14.4 KV - 120 Not Verified *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct ~ Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 60' Condition: Good *#** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE Vay, Ven Yon cu 4Wire Vay VBN Von 8 © 3Wire Van 115.2 Yeo 115.8 YCA 115.7 *** PHASE ANGLE *** N WYE Yaqly Vang Vente Delta Vacl, Yacla Vonic 8 Neutral If Genter ie 1985-43 Terror Lake Powerhouse Generator #1 Power Out Page 2 ***COMMENTS*** Instrument transformers are inaccessible and could not be verified. Being there is no revenue metering on this installation they are probably okay. This is a WYE system metered 3 Wire Delta. ***RECOMMENDATIONS*** Verify CT, PT ratio when units are shut down. Change metering to WYE. TEST CARD - FILE # 1985-44 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-17-85 Rate Schedule: Alaska Power Authority Customer: SMAI PoWethious Gaheratoe #a rowed Gut) Service Type and Voltage: 3 Phase 4 Wire WYE 13.8 KV 30-983-619 ***METER INFORMATION *** Meter # --—s—Ss=«V tage 120 Kh: 1.25 Test Amps: 2.5 Manuf: G-E- Wire: 3 Rr: 83 1/3 M. Factor: = 75/144 Type: DSM-63 Phase: 3 Gr: 50 Form: Demand Register Type: M-30 Interval: 15 Full Scale: 4.00 +++ METER TEST DATA *#** As Found Full Load: 9-54% Light Load: 9-03% EFF; 0.44% pp: As Left Full Load: 939% Light Load: ~9-19% EFF: 09-20% pR; Demand Test: Correct Reset Motor Time: !5 Min Creep Test: No Creep Measured PF: *** METER DATA *#** - Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 7922 Kw 2:00 KVAR 12 Month Peak KW: Meter Defects: Meter Adjustments: MultiptierSiaaaay Socket Bypass Condition: Test Plug Good *#* INSTRUMENT TRANSFORMER DATA *** 800:5 Not Verified 0.14% 0.14% None Full Load Current Transformers: C.T. Burden Test: Good No Drop 5 ohms @ 1.34 amps Potential Transformer: 14.4 KV - 120 Not Verified *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct 7 Instrument Wiring: Correct Current Circuit Wire Size: 10 Length: 100! Condition: Good #** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** ae VAN YBN Yon eT Wire Vay Van Ms B Cc 3 Wire VaB 114.1 Vac 114.7 Vou 114.6 *** PHASE ANGLE *** N wee | ee Yen's YonIc nT Vacia Yac's Yenc 8 Neutral If Center Te 1985-44 Terror Lake Powerhouse Generator #2 Power Out Page 2 ***COMMENTS*** See File 1985-43 ***RECOMMENDATIONS*** See File 1985-43 TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** 1985-45 Test Date: 12-17-85 Rate Schedule: Ajaska Power Authority Customer: Teor Lake Powerhouse Staton Service Transformer #1 Service Type and Voltage: 3 Phase 4 Wire WYE 277/480 Volt **+*METER INFORMATION *** Meter 130-982-804 Voltage: 120 Manuf: G.E. Wire: 3 Type: DSM-63 Phase: 3 Demand Register Type: M-30 Interval: 15 *** METER TEST DATA *** As Found Full Load: 0-03%] Light Load: -0.9% EFF: Khz 1.2 Rrz 13 1/48 Gr: 50 Test Amps: 2.5 M. Factor: 5/64 Form: Full Scale: 25.6 PF: 0. As Left Full Load: 0.16% Light Loads -0.3% EFF: 0.07% PFs Demand Test: Correct Reset Motor Time: 14 Min 59 Sec > Creep Test: No Creep Measured PF: #** METER DATA *** Correct Meter Application: No Meter Condition: Good As Found Readings: KWH09487 Kw 2.9 KVAR 12 Month Peak KW: ' Meter Defects: None Meter Adjustments: Light Load Multipliers 100 © Socket Bypass Condition: Test Socket Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 1600:5 Not Verified C.T. Burden Test: Good No Drop 6 ohms @ 0.51 amps Potential Transformer: Brown Boveri PT-6 4:1 #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 14 Length: *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN VBN Vv CN 4 Wire VAN Van Von 3 Wire v AB 120 Ypc 119.9 Yea 120.1 *** PHASE ANGLE *** WYE Yanla Yani Von! Delta Vacia 348.1%acla. iso Veni 38°% . Bals 0.0% Condition: Good ahr Cc N a B Neutral If Center Tur 1985-45 Terror Lake Powerhouse Station Service Transformer #1 Page 2 ***COMMENTS*** The station transformer secondary is 277/480 4 Wire WYE metered 3 Wire. The 1600:5 CT's are lo in the breaker and we couldn't verify. They are likely relay quality. Accuracy plus or minus This is not a revenue metering point and may be okay. ***RECOMMENDATIONS*** Change metering to 4 Wire 3 element WYE. Verify metering CT's ratio and accuracy class. TEST CARD - FILE # 1985-46 *#** CUSTOMER SERVICE INFORMATION *** Test Date: 12-18-85 Rate Schedule: Alaska Power Authority Customer: Teter Lake Powerhoie Statin Sevice Transformer #2 Service Type and Voltage: 3 Phase 4 Wire WYE 480 Volt ***METER INFORMATION *** Meter # 30-982-803 Voltage: 120 Kh: 1.2 Test Amps: = 2.5 Manuf: G-E- Wire: 3 Rr: 13 1/48 M. Factor: 5/64 Type: DSM-63 Phase: 3 Gr: 50 Form: Demand Register Type: M-30 Interval: 15 Full Scale: 25.6 #+# METER TEST DATA *** . As Found Full Load: 922% Light Load: 9-2% EFF: 0.22% PF: -0.12% Bal z 0.0% As Left Full Load: 9-22 Light Load: 9:2% EFF: 0.22% pF; 0.0% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** = Correct Meter Application: N° Meter Condition: Good As Found Readings: KWH 92076 kw KVAR aS 12 Month Peak KW: = Meter Defects: None Meter Adjustments: None Multiplier: Socket Bypass Condition: — Good Test Slide #*#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-45 C.T. Burden Test: Good No Drop 6 ohms @ 0.51 amps Potential Transformer: See File 1985-45 *#+* PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-45 Circuit Grounding: See File 1985-45 - Instrument Wiring: See File 1985-45 Current Circuit Wire Size: Length: Condition: #** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Tin Vong Von co 4Wire Van Meieg Yon B ¢ 3 Wire Van 119.5 %aco 119.2 Yoq 120.1 *** PHASE ANGLE *** N WYE Yaga Yen'a YonIc Delta Vacl, Yac's Yonic 6 a Neutral If Center Tap 1985-46 Terror Lake Powerhouse Station Serviec Transformer #2 Page 2 ***COMMENTS*** See File 1985-45 ***RECOMMENDATIONS*** See File 1985-45 TEST CARD - FILE # [985-47 *+** CUSTOMER SERVICE INFORMATION *** Test Date: 12-18-85 Rate Schedule: Alaska Power Authority Customer: [Testor Lake! Powerholse Por Lyons Line|Ih Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter # 71-381-605 _ Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 83 1/3 M.Factor: 1 Type: D4S-2M Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: 15 Full Scale: 2.4 *** METER TEST DATA *** - As Found Full Load: 09-16% Light Load: 09-53% EFF: 0.23% DPF: 0.2% As Left Full Load: = 9-06% Light Load: 9-28% EFF: 0.10% pF; 0.2% Demand Test: Correct Reset Motor Time: 14 Min 59 Sec = Creep Test: No Creep Measured PF: : *** METER DATA *** ae Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 9959 Kw 0 KVAR 12 Month Peak KW: eres Meter Defects: None se Meter Adjustments: Light Load Multiplier: 1200 Socket Bypass Condition: Good - Automatic *** INSTRUMENT TP (.SFORMER DATA *** Current Transformers: See File 1985-48 C.T. Burden Test: Patentisiitranstorner: See File 1985-48 *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-48 Circuit Grounding: See File 1985-48 I Instrument Wiring: See File 1985-48 Current Circuit Wire Size: Length: Condition: *#** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE Tas Ven Yon etl 4 Wire VAN Ven Von 8 ¢C 3Wire Van 116 Yao 116.1 %cA 116.2 *** PHASE ANGLE *** F wre T.8, Yen's Vente Delta Vacl, Vacla Venice 8 a Neutral If Center Tut 1985-47 Terror Lake Powerhouse Port Lyons Line In Page 2 *** COMMENTS*** See File 1985-48 except for detent. ***RECOMMENDATIONS*** See File 1985-48 except for detent. TEST CARD - FILE # 1985-48 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-18-85 Rate Schedule: Alaska Power Authority Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter # 71-386-355 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse wire: 3 Rr: 83 1/3 M. Factor: 1 Type: D4#S-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark la Interval: 15 Full Scale: 2.4 *«* METER TEST DATA *** As Found Full Load: 947% Light Load: 972% EFF: 0.52% PF: 0.2% Bal: 0.1% As Left Full Load: 9 !3% Light Load: 93% EFF: 0+16% pF: 3 0.1% Demand Test: Correct Reset Motor Time: !5 Min at Creep Test: No Creep Measured PF: a *** METER DATA *** - Correct Meter Application: N° Meter Condition: Good As Found Readings: KWH 920! Kw 0-15 KVAR F 12 Month Peak KW: , Meter Defects: Sone Meter Adj a Full Load Muitiptie d Socket Bypass Condition: G00d, Automatic *** INSTRUMENT TRANSFORMER DATA *** W si 3 Current Transformers: pea ar tale 30:5 Tap CT. Burden Tests Good No Drop 3 ohms @ 0.65 amps Potential Transformer: West 14400:120 #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect at Instrument Wiring: Correct Current Circuit Wire Size: Length: 15' Condition: Good +t aH Increase SE IOE Thos ae *** VOLTAGE MEASUREMENTS *** WYE v Vv Vv a AN BN CN . + Wire Vax Van Yon & . 3 Wire Van 116 Vac 116.1 Yea 116.2 *** PHASE ANGLE **+* c We. AA Yen's Vonlc Delta Vacla Vacla Vonic B Neutral If Center Tie 1985-48 Terror Lake Powerhouse Port Lyons Line Out Page 2 ***COMMENTS*** This is a 4 Wire WYE circuit metered 3 Wire Delta. Loads from the center phase to ground will not be metered. If the circuit loading is balanced the revenue loss would amount to $2,300/month. There is no detent on this meter which will allow for reverse rotation (subtractive registration) in the event Port Lyons delivers power to Terror Lake. ***R ECOMMENDATIONS*** Change metering to 3 element 4 Wire WYE. Use three 60:1 potential transformers and three 25:5 current transformers. Install detent. TEST CARD - FILE # 1985-49 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-19-85 Rate Schedule: Alaska Power Authority customer: (AiRB SRN? TEBE ake tine wwe Service Type and Voltage: 3 Phase 4 Wire WYE 138 KV ***METER INFORMATION *** Meter # 70-189-054 Voltage: 120 Khz 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 234/27. M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: = Mark Ia Interval: 15 Full Scale: 8.64 *** METER TEST DATA *** : As Found Full Load: -9-06% Light Load: -0-06% EFF: -0.06% PF: -0.4% Bal: 0.05% As Left Full Load: ~-9-96% Light Loads -0-06% EFF; -0.06% Demand Test: Correct Reset Motor Time: !5 Min Creep Test: No Creep Measured PF: ; *** METER DATA *** : 7 Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 6388 Kw 1-35 KVAR 12 Month Peak KW: - Meter Defects: None Meter Adjustments: None Multiplier: 10000 _ Socket Bypass Condition: — Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Siemens-Allis MCT-121/145 — 150/300:5 150 Tap A.C. 1.2 30.2 C.T. Burden Test: Good No Drop | ohm @ 1.77 amps Potential Transformer: G.E. CCVT CD310 138/175 accuracy class 1.2R MWXYZ *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect - Not Grounded ~ Instrument Wiring: Could Not Verify Current Circuit Wire Sizez14/10 Length: 150' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Vig a Tey = 4 Wire VAN Van Von B Cc 3 Wire Van 114.6 Yao 114.4 YoaA 114.7 *** PHASE ANGLE *** " WYE Vania Ven'a Venlc — Vacla anes ‘ac's — Vente B Neutral If Center se 1985-49 Airport Substation - Terror Lake Line In KWH Page 2 ***COMMENTS*** Meter cover is broken. Instrument transformers are not 0.3 accuracy class. This is a 4 Wire WYE circuit metered 3 Wire Delta. See file 1985-62 reguarding CCVT. ***RECOMMENDATIONS*** Repair meter cover. Install 0.3 accuracy current and potential transformers. Rebuild metering using 4 Wire form 9 meter. TEST CARD - FILE # 1985-50 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-19-85 Rate Schedule: Alaska Power Authority Customer: Airport Substation 138 KY Terror Lake KWH Out Service Type and Voltage: 3 Phase 4 Wire WYE 138 KV *#**METER INFORMATION *** Meter i 70-189-055 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 23 4/27 M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: = Mark Ia Interval: 15 Full Scale: 8.64/17.28 *** METER TEST DATA *** As Found Full Load: 942% Light Load: -0-34% EFF; -0.40% As Left Full Load: 916% Light Load: 0-28% EFF; 0.18% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** as Correct Meter Application: No Meter Condition: Good i. As Found Readings: KWH 0002 Kw 0-00 KVAR EE : 12 Month Peak KW: -. ze a Meter Defects: None : Meter Adjustments: Full Load - Light Load Multiplier: 10000 Socket Bypass Condition: Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-49 C.T. Burden Test: See File 1985-49 Potential Transformer: See File 1985-49 #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-49 Circuit Grounding: See File 1985-49 = Instrument Wiring: See File 1985-49 Current Circuit Wire Size: Length: Condition: *#** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** 4 Wire VAN Van Von & ¢ 3 Wire Vag 114.6 Yao 114.4 YoA 114.7 *** PHASE ANGLE *** N WYE -¥,.J, Van'p Vonle Delta Vv, —I 5 Vacl 6 Ven! fy ACA 74.5 “BCR 354.6 "CN'C B Neutral If Genter Tap 1985-50 Airport Substation 138 KV Terror Lake KWH Out Page 2 *** COMMENTS*** See File 1985-49 ***RECOMMENDATIONS*** See File 1985-49 TEST CARD - FILE # 1985-51 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-19-85 Rate Schedule: Alaska Power Authority Customer: Alport Substation 138 KV Swampy Acres KWH In Service Type and Voltage: 3 Phase 3 Wire Delta 138 KV ***METER INFORMATION *** Meter #70-189-053 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rrz 23 4/27 M. Factor: = 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark la Interval: 15 Full Scale: 8.64/17.28 #+* METER TEST DATA dated i As Found Full Load: 9-26% Light Load: -0-04% EFF: 0.2% pF: 0.02% Bal: 0.05% As Left Full Load: 9-26% Light Load: -0-04% EFF; 0.2% Demand Test: Correct Reset Motor Time: !5 Min Creep Test: No Creep Measured PF: ot eee *** METER DATA *** on Correct Meter Application: Ys Meter Condition: 8°°d As Found Readings: KWH 0125 Kw 0-35 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: Socket Bypass Condition: Test Switch - Good *#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: Siemens-Allis MCT-121/145 150/300:5 150 Tap ACC 1.2 BO.2 C.T. Burden Test: Good No Drop | ohm @ 1.25 amps Potential Transformer: G.E. CCVT CD31D 138 KV/115 ACC class 1.2R MWXYZ *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect Not Grounded = Instrument Wiring: Correct Current Circuit Wire Size: 14/12 Length: 150 Condition: Poor *#** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE v Vv Vv 7 AN BN CN c 4 Wire VAN VBN Von B Cc 3 Wire Vag 114.7 Yao 114.2 Yea 113.7 *** PHASE ANGLE #*+* is Wve . Vania Yen's Vonlc Delta Vacla 54.0 Vacs 353.6 Venlo a a Neutral If Center Tap 1985-51 Airport Substation 138 KV Swampy Acres KWH In Page 2 ***COMMENTS*** Current circuit is spliced in the breaker cabinet. Terminal blocks are miss-marked but correctly wired. Instrument transformers are not 0.3 accuracy class. See file 1985-62 reg. CCVT. ***RECOMMENDATIONS*** Correctly mark terminal blocks. Install 0.3 accuracy current and potential transformers. TEST CARD - FILE # 1935-52 ++* CUSTOMER SERVICE INFORMATION **+* Test Date: 12-19-85 Rate Schedule: Alaska Power Authority Customer: Airport Substation 138 KV Swampy Acres KWH Out Service Type and Voltage: 3 Phase 4 Wire WYE 138 KV ***METER INFORMATION *** Meter #70-189-056 Voltage: 120 Khs 1.2 Test Amps: 2:5 Manuf: Westinghouse Wire: 3 Rr: 23 4/27 M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval:!> Full Scale: 8-64/17.28 *** METER TEST DATA *** I As Found Full Load: -0-2% Light Load: -9-22% EFF: -0-2% pp; -0.4% — Bals 0.05% As Left Full Load: ~9-2% Light Load: -9-22% EFF: -0.2% Demand Test: Correct Reset Motor Timez! Min Creep Test: No Creep Measured PF: ##* METER DATA *** fae Correct Meter Application: No Meter Condition: Good As Found Readings: KWH*562 Kw 1.00 KVAR poe 12 Month Peak KW: Teast Meter Defects: None Meter Adjustments: None Multiplier: 10000 Socket Bypass Condition: Test Switch **#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-51 C.T. Burden Test: See File 1985-51 Potential Transformer: See File 1985-51 *##* PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See File 1985-51 Circuit Grounding: See File 1985-51 ~ Instrument Wiring: See File 1985-51 Current Circuit Wire Size: Length: Condition: #*#* REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE Vv Vv Vv i AN BN CN : 4 Wire VAN Ven Von 8 C 3 Wire Vag 114.7 Yao 114.2 Yea 113.7 *** PHASE ANGLE *** ii WYE Vanla Yan's Yonic Delta Vacl, 54.1 Yaclap 353.6 Vente B Neutral If Genter ‘.. 1985-52 Airport Substation 138 KV Swampy Acres KWH Out Page 2 ***COMMENTS*** See file 1985-51. The out circuit is 4 Wire WYE metered 3 Wire Delta. When Airport Substation is delivering power to Swampy Acres, the metering could be inaccurate as much as 5%. When Swampy Acres is delivering to Airport it is correct. The error on this metering caused by the CT's and PT's could be as much as $2,900/month. See file 1985-62 regarding CCVT. ***RECOMMENDATIONS*** See file 1985-51. Change metering to 4 Wire WYE. TEST CARD - FILE # 1985-53 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter #70-089-509 Voltage: 120 Kh: 1.8 Manuf: Westinghouse Wire: 4 Rr: 15 35/81 Type: D4B-3FM Phase: 3 Gr: 100 Demand Register Type: Mark la Interval: 15 *** METER TEST DATA *** Test Amps: 2.5 M. Factor: 5/18 Form: Full Scale: 12.96/25.92 As Found Full Load: 9:9% Light Load: -0-6% EFF: -0-12% PF: -0.18% | Balz 0.13% As Left Full Load: 90% Light Load: -0:6% EFF: -0:12% PF: -0.18%* Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: 91% *** METER DATA *** Correct Meter Application: Y€S Meter Condition: Good As Found Readings: KWH 3741 KW 3.6 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: Yes Socket Bypass Condition: Good **#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: 300/600:5 Not Verified as to the tap 300:5 C.T. Burden Test: Good No Drop 6 ohms @ 2.44 amps Potential Transformer: 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct ; Balz 0.13% ee Current Circuit Wire Size: 14/10 Length: 75' Condition: Good *** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** wre Van 130.5 Yan 131.0 YCN 131.0 4 Wire VAN Ven Von B 3 Wire Yap Vac Vou *** PHASE ANGLE *** N WYE Yanla 23.9 Yanlg 26.9 Yonto 24.7 Delta V acla Yecla Von! a 8 Neutral If Center Tut 1985-53 Airport Substation XFMR to 12.47 KV Bus KWH Page 2 ***COMMENTS*** Demand definition is poor. Each division is 100 KW. ***RECOMMENDATIONS*** Verify CT's as to ratio (tap setting) if demand billing is to be implemented in the future. Change register to provide 2 decimal definition. TEST CARD - FILE # 1935-54 **+* CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customer: Aitprt Substation 130 Buskin Feeder KWH Service Type and Voltage: 3 Phase 4 Wire WYE 12.47 KV ***METER INFORMATION *** Meter # 70-389-927 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse = Wires 4 Rr: 15 35/18 M. Factor: 5/18 Type: D4B-3FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: 15 Full Scale: ——-12.96/25.92 *** METER TEST DATA *** : As Found Full Load: 9-09% Light Load: 9-6% EFF: 0.19% PF: 0.26% As Left Full Load: 9-99% Light Load: 9-6% EFF: 0.19% DPF: 0.26% Demand Test: Correct Reset Motor Time: 15 Min , Creep Test: No Creep Measured PF: 84% *** METER DATA *** aie’ Correct Meter Application: Y&S Meter Condition: Good As Found Readings: KWH 2345 Kw 0-4 KVAR pee 12 Month Peak KW: “eee Meter Defects: None . Meter Adjustments: None Multiplier: 1000 Not VerifieBocket Bypass Condition: Test Switch - Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: Bushing CT's G.E. Class C 100 Not Verified C.T. Burden Test: Good No Drop 6 ohms @ 0.3 amps Potential Transformer: 60:1 Not Verified #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct = Instrument Wiring: Correct Current Circuit Wire Size: 14 Length: 90' Condition: Good *#** REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** — Van 130.5%BN 130.7 Yon 130.9 eo 4 Wire Vay Wg You B Cc 3Wire Van Vac he *** PHASE ANGLE **# = WYE Vantag 31-3 Ypnlg 35.5 Yonlc 32 Delta Vcl, Vicks Volo 6 a Neutral If Center Tap 1985-54 Airport Substation 130 Buskin Feeder KWH Page 2 ***COMMENTS*** PT's and CT's are unaccessible in the breaker to verify. Demand definition is poor each division is 100 KW. ***R ECOMMENDATIONS*** Verify ratio and accuracy class of instrument transformers if demand billing is to be implemented in the future. Change meter register to give 2 decimal definintion. TEST CARD - FILE # 1985-55 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customer: Airport Substation 130 USCG Feeder KWH Service Type and Voltage: 3 Phase 4 Wire WYE 12.47 KV ***METER INFORMATION *** Meter # 70-389-929 Voltage: 120 Kh: 1.8 Test Amps: 2.5 Manuf: Westinghouse Wire: 8 Rr: 15 35/81 M. Factor: 5/18 Type: D4B-3Fm Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: 15 Full Scale: 12.96 /25.92 *#** METER TEST DATA *** . As Found Full Load: ~9-35% Light Load: -0-32% EFF: -0.34% DPF: -0.62% Bal: 0.13% As Left Full Load: = 9-03% Light Load: -9-06% EFF: 0.01% pF; Bal: 0.13% Demand Test: Correct Reset Motor Time: !5 Min _ : Creep Test: No Creep Measured PF: 92.8% i *** METER DATA *** — . Correct Meter Application: Y&S Meter Condition: Good As Found Readings: KWH 9428 Kw 33 KVAR eae 12 Month Peak KW: Tt eel Meter Defects: None 7 Meter Adjustments: Full Load Multiplier: 10000 Socket Bypass Condition: Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: See File 1985-54 C.T. Burden Test: Good No Drop 6 ohms @ 2.3 amps Potential Transformer: See File 1985-54 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct = Instrument Wiring: Correct Current Circuit Wire Size: 14 Length: 90 Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 130.7 Yan —:130.8 Yon 130.8 co 4 Wire VAN Visn Von 8 ¢ 3 Wire Van Vac Voa *** PHASE ANGLE **+* i WYE Yanig 20.5 Venta = 23.0 Vout 22.0 Delta Vacls Yecls Yonlc B Neutral If Center “A. 1985-55 Airport Substation 13D USCG Feeder KWH Page 2 ***COMMENTS*** See file 1985-54 ***RECOMMENDATIONS*** See file 1985-54 TEST CARD - FILE # 1985-56 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customer: Aifport Substation 13A Feeder KWH Service Type and Voltage: 3 Phase 4 Wire WYE 12.47 KV Meter OSD II yon Meter Voltage: = Kh: !-8 Test Amps: 2.5 Manuf: Werte Wire: . Rr: 15 35/81 M. Factor: 5/18 Type: ee Phase: 3 Gr: 190 Form: Demand Register Type: Baer hs Mk Interval: !> Full Scale: 1 2-96/25.92 *** METER TEST DATA *** 0.19% As Found Full Load: Light Load: 92% ERR; 920% pp, -0.04% gay, 0.2% As Left Full Load: °°!9% Light Load: %2% EFF: 92% pp, -0.04% gay, 0.2% Demand Test: nmninai Reset Motor Time: 15 Min 1 Sec Creep Test: Re Crssp Measured PF: *** METER DATA *** Correct Meter Application: ii Meter Condition: €°°4 As Found Readings: kwu!!27 Kw °-0 KVAR 12 Month Peak KW: Meter Defects: are Meter Adj = Bone vattipuiec Socket Bypass Condition: Test Satcs Good **#* INSTRUMENT TRANSFORMER DATA *** See file 1985-54 Not Performed No Load See file 1985-54 Current Transformers: C.T. Burden Test: Potential Transformer: *** PROPERLY APPLIED METER CIRCUITS *** Ch Correct Socket Wiring: Circuit Grounding: Instrument Wiring: Correct Not Verified No Load Current Circuit Wire Size:!" Length: 7° Condition: ©°°4 *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *#** 130.4 ei e WYE VAN VBN 130. Von 130.8 Cc 4 Wire VAN Van Von B Cc 3 Wire VaB Vac Vou *** PHASE ANGLE *** N Fre awn Yen's Yonlc Delt Vent Voor Va a "ACA BCB CNC B Neutral If Center Ths 1985-56 Airport Substation 13A Feeder KWH Page 2 *** COMMENTS*** See file 1985-54. Breaker open; no load; unable to burden or phase angle. ***RECOMMENDATIONS*** See file 1985-54. Test CT's and phase angle under loads. TEST CARD - FILE # 1935-57 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customer: Airport Substation Station Service Service Type and Voltage: Single Phase 3 Wire 240 Volt *#**METER INFORMATION *** Meter #60-976-805 Voltage: 240 Khz 7.2 Test Amps: 30 Manuf: Sangamo Wire: 3 Rr: 27 7/9 M. Factor: | Type: J4S Phase: 1 Gr: 50 Form: Demand Register Type: N/A Interval: N/A Full Scale: N/A *** METER TEST DATA *** : As Found Full Load: 9-36% Light Load: 09-57% EFF: 0.40% PF: As Left Full Load: 9-08% Light Load: 90-28% EFF: 0.12% PF: 0.0%°:3: Demand Test: Reset Motor Time: i Creep Test: No Creep Measured PF: 2 **#* METER DATA *** 7? Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 044570 KW KVAR 12 Month Peak KW: i Meter Defects: None Meter Adjustments: Full Load Multipliers | Socket Bypass Condition: No Bypass *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: N/A C.T. Burden Test: N/A Potential Transformer: N/A *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Circuit Grounding: oe Instrument Wiring: Current Circuit Wire Size: Length: Condition: *#*#* REVENUE CHANGE *** *#** VOLTAGE MEASUREMENTS *** WYE v Vv Vv ia AN BN CN c 4Wire Van Ties Vis 8 Cc 3 Wire v AB Vac Yo A *** PHASE ANGLE *** N WYE Vana Vania Von! Delta Vacla Yac'p Von! 8 a Neutral If Center Tap 1985-57 Airport Substation Station Service Page 2 ***COMMENTS*** None ***RECOMMENDATIONS*#** None TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** Test Date: 17.99.85 1985-58 Rate Schedule: Alaska Power Authority Customer: Service Type and Voltage: single Phase 3 Wire 240 **+*METER INFORMATION *** Meter # 60-976-060 Voltage: 240 Kh: 7,2 Test Amps: 39 Manuf: sangamo Wire: 3 Rr: 27 7/9 M. Factor: 1 Type: jus Phase: rl Gr: 50 Form: 2S Demand Register Type: Interval: Full Scale: *#** METER TEST DATA *** ; As Found Full Load: -0.339% Light Load: -0.2% EFF: 0.30% PF: As Left Full Load: 0.05% Light Load: 0.3% EFF: 0.1% PFs — Demand Test: Reset Motor Time: ei Creep Test: No Creep Measured PF: **+* METER DATA *** gem Correct Meter Application: Yes Meter Condition: good As Found Readings: KWH 33523 KW KVAR ae) 12 Month Peak KW: a Meter Defects: None Meter Adjustments: Full Load Multiplier Socket Bypass Condition: No Bypass *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: C.T. Burden Test: Potential Transformer: #** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Circuit Grounding: iW Instrument Wiring: Current Circuit Wire Size: Length: Condition: *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE is Toon a Lr 4 Wire VAN Van Yon B Gc 3 Wire v AB Vac Vo A *** PHASE ANGLE “ WYE Vania Yen'a Von! Delta V,_I Vv, AI Viel A ACA BCB CNC BNeutral If Center Tuy 1985-58 Swampy Acres Sub Station Service Page 2 ***COMMENTS*** None ***RECOMMENDATIONS*** None TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** 1985-59 Test Date? 12-20-85 Rate Schedule: ajaska Power Authority Customer: swampy Acres Carlyn Feeder KWH Service Type and Voltage: 3 phase 4 Wire WYE 7200/12470 *+**METER INFORMATION *** Meter #70-089-503 Voltage: 120 Kh: |. Test Amps: 2,5 Manuf: Westinghouse Wire: 4 Rrz 23 4/27 M. Factor: 5/12 Type: D4B-3FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Intervals | 5 Full Scale: 8.64/17.28 *** METER TEST DATA *** As Found Full Load: -9.2% Light Load: -0.66% EFF: -0.29% PF: -0.38% Bal: 0.33% As Left Full Load: -0.15% Light Load: 0.02% EFF: -0.12% PF: -0.24% Balz 0.3% Demand Test: Correct Reset Motor Timez [5 Min PS eor Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWH 0008 KW 0.00 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 1500 Socket Bypass Condition: Good Test Switch *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: GE Bushing 300:5; 0.3 class; BO.5 unverified C.T. Burden Test: Not Performed No Load Potential Transformer: 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct _ Instrument Wiring: Correct Current Circuit Wire Size: 14 Length: 40' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** wre Van 120.3%BN 121.5 YCN 120.6 c 4 Wire v AN Ven Von B ‘Gc 3 Wire Vv AB Vac Vo A *** PHASE ANGLE *** WYE Vania Ven'p Vente Bete Vata Vacs Venice 8 Neutral If Genter Tug 1985-59 Swampy Acres Carolyn Feeder KWH Page 2 ***COMMENTS*#** No load on this circuit so couldn't perform burden and phase angle test. ***RECOMMENDATIONS*** Test for burden and phase angle under load. Verify CT ratio and accuracy class. TEST CARD - FILE # 1995 ¢0 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-35 Rate Schedule: 4j4ska Power Authority Customer swampy Acres 13D USCG Feeder KWH Service Type and Voltage: 3 phase 4 Wire WYE 7200/12470 *+**METER INFORMATION *** Meter #70-089-504 Voltage: 120 Kh: |. Test Amps: 2.5 Manuf: Westinghouse Wire: 4 Rr77 13/81 Me Factor: = 25/18 Type: D4B-3FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark la Interval:| 5 Full Scales = 2.592/5.184 *** METER TEST DATA *** As Found Full Load: -0.06% Light Loads -0.3% EFF: -0.11% PF:-0.12% Balz 0.33% As Left Full Load: -0.06% Light Load: -0.3% EFF: -0.11% PF: -0.12%, << Bals 0.33% Demand Test: Correct Reset Motor Time:z15 Creep Test: No Creep Measured PF: 88% *** METER DATA *** Correct Meter Application: Yes Meter Condition: Good As Found Readings: KWHO0362 KW 0.13 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier:5000 Socket Bypass Condition: Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 300:5 GE Unverified C.T. Burden Test: Good No Drop 6 ohms @ 0.48 amps Potential Transformer: 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct - Instrument Wiring: Correct Current Circuit Wire Size:!4 Length: 45' Condition: Good *#** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE Van 120-1 Yay 121-4 Von 120.5 cc 4 Wire VAN Van Von B Cc 3 Wire VaB Vac Voa *** PHASE ANGLE *** - WYE Yanty 30-5 Vand 37-0 Venti 18.5 — Vacia Yac's Yenic 8 Neutral If Center ty: 1985-60 Swampy Acres 13D USCG Feeder KWH Page 2 ***COMMENTS*** Demand definition is poor. Each division is 100 KW. ***RECOMMENDATIONS*** Change register to Rr 55 5/9 to provide better definition. Change CT ratio to 50:5. Verify CT ratio and accuracy class. TEST CARD - FILE # 1985-61 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customer: Swampy Acres XFMR to 12.47 Bus KWH Service Type and Voltage: 3 Phase 4 Wire WYE 7200/12470 ***METER INFORMATION *** Meter 970-089-519 Voltage: 120 Kh: !.8 Test Amps: 2:9 Manuf: Westinghouse Wire: 4 Rr: 46 8/27 M. Factor: 5/6 Type: D4B-3FM Phase: 3 Gr: 190 Form: Demand Register Type: Mark Ia Interval: !> Full Scale: _4+32/8.64 #** METER TEST DATA *** As Found Full Load: 992% Light Load: ~9-1% EFF; 90% pp, -0-06% gay, 026% As Left Full Load: 992% Light Load: ~9:!% EFF: 9:0% pp, -0:06% = gay, 0-26% Demand Test: Yes Reset Motor Time: /> Min Creep Test: No Creep Measured PF: 87% *** METER DATA *#** Correct Meter Application: Y&S Meter Condition: G°°d As Found Readings: KWH 9490 Kw 0-18 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 4000 Socket Bypass Condition: Test Switch Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: GE 400:5 C.T. Burden Test: Good No Drop 6 ohms @ 0.42 amps Potential Transformer: GE 60:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct 7 Instrument Wiring: Correct Current Circuit Wire Size: 14 Length: 95' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE v Vv Vv AN 120.3BN 121.5 “CN 120.9 c 4 Wire VAN Van Von B iC 3 Wire Vv AB Vac Vo A *** PHASE ANGLE *** N WYE Vania = 31.5”BN'B 38.6 Yonic 19.0 — VACIA “ac's Yenic B Neutral If Center ie 1985-61 Swampy Acres XFMR to 12.47 Bus KWH Page 2 ***COMMENTS*** Demand definition is poor. Each division is 200 KW. ***RECOMMENDATIONS*** If demand billing is to be implemented in the future change register to Rr 55 5/9 to provide better definition. Change CT ratio to 75:5. TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** Test Date: |2-20-85 Rate Schedule: Customers Syampy Acres 138 KV Airport Line Cut KWH Service Type and Voltage: 3 Phase 3 Wire Delta 138 KV ***METER INFORMATION *** Meter #70-281-703 Voltage: 120 Kh: 1.9 Test Amps: 2,5 1985-62 Alaska Power Authority Manuf: Westinghouse Wire: 3 Rr: 23 4/27 M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: | 5 Full Scalez—.64/17.28 *** METER TEST DATA *** As Found Full Load: -0,.13% Light Load: -9.349% EFF: -0.27% PF: -0.54% Bal: 9.1% As Left Full Load: -09.13% Light Load: -9.16% EFF: -0.14% PF: -0.44% Bal: 9.1% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: yes Meter Condition: Good As Found Readings: KWH 0125 KW 0.35 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 10,000 Socket Bypass Condition: Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 150:5 Not Verified C.T. Burden Test: Good No Drop @ 2 ohms and 1.34 amps Potential Transformer: CCVT GE 138 KV/115 Accuracy Class 1.2 R UWXYZ *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect Not Grounded Instrument Wiring: Could not verify Current Circuit Wire Size: 14 Length: 95' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** wre VAN YBN Von c 4 Wire Van V.! Von B C 3 Wire Van ji4.5%BC 114.2 YCA 114.5 *** PHASE ANGLE *** N WYE Vania Vania Venic Bette ("aca | oar *eele | 4572 “ene See) it Gemee ty 1985-62 Swampy Acres 138 KV Airport Line Out KWH Page 2 ***COMMENTS*** The instrument transformers do not meet 0.3 accuracy metering requirements. Demand definition is poor. Each division is 100 KW. (CCVT) Capacitive coupled voltage transformers are being used as metering potential transformers. These CCVT's are relay quality transformers at best and must be tuned for a given load. When the load varies so does the accuracy. Error is plus or minus 1.2%. ***RECOMMENDATIONS*** Change the capacitive couple voltage transformers and the current transformers to transformers that meet 0.3 accuracy class. Rebuild metering. TEST CARD - FILE # 1985-63 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Customers Swampy Acres ~ 18 KY Alport Line In KWH Service Type and Voltage: 3 phase 4 Wire WYE 138 KV ***METER INFORMATION *** Meter #79-281-704 Voltage: 120 Kh | .2 Test Amps: 2,5 Alaska Power Authority Manuf: Westinghouse Wire: 3 Rr: 23 4/27, -M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval:| 5 Full Scales = -8.64/17.28 *** METER TEST DATA *** As Found Full Load: 09.15% Light Load: -9,.4% EFF: 0.04% PF: 0.16% Bal: 0.5% As Left Full Load: 09.05% Light Load: -9.08% EFF: 0.02% PF: -0.02% Bal: 0.5% Demand Test: Failed Reset Motor Time: !> Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Y€s Meter Condition: Por As Found Readings: KWH 4605 Kw 1-00 KVAR 12 Month Peak KW: Meter Defects: Faulty Demand Register Meter i oe Light Load Multiplier: Socket Bypass Condition: Test Switch - Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 5€@ file 1985-62 C.T. Burden Test: See file 1985-62 Potential Transformer: See file 1985-62 *#** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See file 1985-62 Circuit Grounding: See file 1985-62 ~ Instrument Wiring: See file 1985-62 , Current Circuit Wire Size: 14 Length: 95' Condition: Good *##* REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN VBN Yon c 4 Wire Vay hee Teas B Cc 3 Wire Van iia.s BC 114.2 “CA 114.5 *** PHASE ANGLE *** N WYE Vania Van’ Vonic Delta Vacla — 55.7%acla 357.2 Yen'c pa Geee ic 1985-63 Swampy Acres - 138 KV Airport Line In KWH Page 2 ***COMMENTS*** Demand test failed. Registered 8% low. See file 1985-62. ***RECOMMENDATIONS*** Change demand register. See file 1985-62. TEST CARD - FILE # 1935-64 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Service Type and Voltage: 3 Phase 4 Wire WYE 69 KV ***METER INFORMATION *** Meter #70-281-715 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse Wire: 3 Rr: 23 4/27 M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: 15 Full Scale: 8.64/17.28 *##* METER TEST DATA *** As Found Full Load: -0.11% Light Load: -0.34% EFF: -0.16% PF: -0.4% Bal: 0.25% As Left Full Load: -0.09% Light Load: 0.16% EFF: -0.04% PF: -0.32% Bal: 0.25% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: **#* METER DATA *** Correct Meter Application: No Meter Condition: Good As Found Readings: KWH 0926 KW 0.40 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: 10000 Socket Bypass Condition: Test Switch Good #4 INSTRUMENT TRANSFORMER DATA *** Current Transformers: 600:5 Siemens Allis 0.6 BO5 Unverified C.T. Burden Test: Good No Drop 6 ohms @ 1.34 amps Potential Transformer: CCVT GE €00:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect Not Grounded Instrument Wiring: Correct Current Circuit Wire Size: !4 Length: 75' Condition: Good *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** WYE VAN VBN Von c 4 Wire Vay VeBN Von 8 a 3 Wire Vag 113.4 Bc 113.6 Yoq 112.8 *** PHASE ANGLE *** ' WYE Vanla Ven'B Vonlc Delta Vacla 56.1% acl 354 Vonle 8 Neutral If Center ‘Tee 1985-64 Swampy Acres - 69 KV Main Line | KWH In Page 2 #** COMMENTS *** See file 1985-65 ***RECOMMENDATIONS*** See file 1985-65 TEST CARD - FILE # 1985-65 *#** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: ‘laska Power Authority Customer: Swampy Acres 69 KV Main Line | KWH Out to Kodiak Service Type and Voltage: 3 Phase 4 Wire WYE 69 KV ***METER INFORMATION *** Meter Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: Westinghouse wire: 3 Rr: 234/27 M. Factor: 5/18 Type: DiB-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark la Interval: !> Full Scale: 8.64/17.28 *** METER TEST DATA *** As Found Full Load: 99% Light Load: ~0-04% Err; -0-1% pp, -0-72% aj; 0.349% As Left Full Load: 9-9 Light Load: “994% EFF; 91% pp, -0-72% aj, 0.34% Demand Test: Correct Reset Motor Time: !° Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: _ Meter Condition: — As Found Readings: KWH 3992 KW 0.90 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Multiplier: 10000 Socket Bypass Condition: Test Switch Good *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: 600:5 Siemens Allis 0.6 Accuracy BO5 Unverified C.T. Burden Test: Good No Drop 6 ohms @ 1.34 amps Potential Transformer: CCVT GE 1.2 accuracy class 600:1 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Incorrect Not Grounded Instrument Wiring: Could Not Verify Current Circuit Wire Size: 14 Length: 75' Condition: Good *** REVENUE CHANGE *** Increase $2,000/month *** VOLTAGE MEASUREMENTS *** WYE Vv Vv Vv AN BN CN c 4 Wire Van VBN Von 8 c 3 Wire VaB 113.4%Bc 113.6%CA 112.8 *** PHASE ANGLE *** N WYE V,,J, Ven'p Von!c Delta Vac, 56.Mpclh 354 Vente 8 Neutral If Center The 1985-65 Swampy Acres 69 KV Main Line 1 KWH Out to Kodiak Page 2 ***COMMENTS*** The CT's on this installation are labelled 600:5 although the utility tells us they are 300:5. They are not accessible to verify. Demand definition is poor. Each division is 500 KW. This is a 4 wire WYE system metered with a 3 wire Delta metering scheme which is inaccurate at least 5% due to the voltage unbalance amounting to $2,000/month. We couldn't verify all circuit wiring because the system was energized. If it is properly wired 3 wire Delta it could be in error as much as 5%. See file 1985-62 regarding CCVT to additional $4,900/month. CCVT are in error approximately 1.2% amounting to additional $4,900/month. ***RECOMMENDATIONS*** Verify metering current transformers as to ratio and accuracy class. Change if not 0.3 accuracy Change CCVT's to metering quality PT's (0.3 accuracy). Rebuild metering using 3 element form 9 meter. TEST CARD - FILE # 1985-66 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customers Swampy Acres 69 KY Main Line 2 KWH In Service Type and Voltage: 3 Phase 4 Wire WYE 69 KV ***METER INFORMATION *** Meter # 70-281-716 Voltage: 120 Kh: 1.2 Test Amps: 2.5 Manuf: | Westinghouse Wire: 3 Rr: 23 4/27 M. Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 100 Form: Demand Register Type: Mark Ia Interval: 15 Full Scale: 8.64/17.28 *** METER TEST DATA *** As Found Full Load: -0.26% Light Load: -0.56% EFF: -0.32% PF: -0.34% Bal: 0.05% As Left Full Load: 0.25% Light Load: 0.18% EFF: 0.24% PF: 0.04% Bal: 0.05% Demand Test: Correct Reset Motor Time: 15 Min 1 Sec Creep Test: No Creep Measured PF: *## METER DATA *** Correct Meter Application: Meter Condition: Good As Found Readings: KWH 0000 KW 0.00 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Full Load Multipliers Socket Bypass Condition: | Test Switch **#* INSTRUMENT TRANSFORMER DATA *** Current Transformers: GE Bushing 300:5 0.3 BO5 Unverified C.T. Burden Test: No Load Not Connected Potential Transformer: 60:1 Unverified *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Instrument Wiring: Current Circuit Wire Size: |4 Length: 140' Condition: Good *** REVENUE CHANGE *** **#* VOLTAGE MEASUREMENTS *** WxE VAN VBN Von c 4 Wire VAN VBN Von B Cc 3 Wire Vv AB Vac Vo A *** PHASE ANGLE *** = WYE Vanta Vania Von! Delta V ac! A Vac! Vv cnic B Neutral If Center Tap 1985-66 Swampy Acres 69 KV Main Line 2 KWH In Page 2 ***COMMENTS*** This circuit is not in use. Meter test only. ***R ECOMMENDATIONS*** When circuit is connected burden tests, phase angles and instrument wiring should be checked. TEST CARD - FILE # 1985-67 *** CUSTOMER SERVICE INFORMATION *** Test Date: 12-20-85 Rate Schedule: Alaska Power Authority Customer: Swampy Acres 69 KV Main Line 2 KWH Out Service Type and Voltage: 3 Phase 4 Wire WYE 67 KV ***METER INF! ION *** Meter Voltage: 120 Kh: 1.2 Test Amps: = 2.5 Manuf: Westinghouse Wire: 3 Rr: 23 4/27 — M, Factor: 5/18 Type: D4B-2FM Phase: 3 Gr: 10 Form: Demand Register Type: Mark la Interval: | Full Scale: 8.64/17.28 *** METER TEST DATA *** As Found Full Load: 9 !4% Light Load: 9:52% EFF; 0-22% pp; 0.1% Bal; 0.05% As Left Full Load: 9 !6% Light Load: ~9-1% EFF: 011% pp; -0.04% pal, 0.05% Demand Test: Correct Reset Motor Time: 15 Min Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Meter Condition: Good As Found Readings: KwuH 2000 Kw 0-00 KVAR 12 Month Peak KW: Meter Defects: None Meter Adjustments: Light Load Multiplier: (EEE socket Bypass Condition: Test Switch Good *#** INSTRUMENT TRANSFORMER DATA *** Current Transformers: See file 1985-66 C.T: Burden Test: No Load Not Connected Potential Transformer: 5€¢ file 1985-66 *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: See file 1985-66 Circuit Grounding: S¢® file 1989-66 = Instrument Wiring: See file 1985-66 Current Circuit Wire Size: Length: Condition: *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** wis VAN YBN Von c 4 Wire VAN Van Von B Cc 3Wire Van ho: ‘Gh *#* PHASE ANGLE *** N aoe Ven'B VYonlc _— Vacia ‘ac's Yenic B Neutral If Center he 1985-67 Swampy Acres 69 KV Main Line 2 KWH Out Page 2 ***COMMENTS*** See file 1985-66 ***RECOMMENDATIONS*** See file 1985-66 TEST CARD - FILE # *** CUSTOMER SERVICE INFORMATION *** Test Dates 12-20-85 Customer: Service Type and Voltage: 3 Phase 4 Wire ***METER INFORMATION *** Meter # 70-089-518 Voltage: 120 Manuf: Westinghouse Wire: 4 Type: D4B-3FM Phase: 3 Demand Register Type: Mark la Interval: *** METER TEST DATA *** As Found Full Load: 0.16% Light Load: -0.1% EFF: As Left Full Load: 0.16% Light Load: -0.1% EFF: Demand Test: Correct Reset Motor Time: Creep Test: No Creep Measured PF: *** METER DATA *** Correct Meter Application: Yes As Found Readings: KWH 2959 12 Month Peak KW: Meter Defects: None Meter Adjustments: None Meter Condition: KW 0.00 Rate Schedule: Multiplier: "3,000 Not Ver. Socket Bypass Condition: *** INSTRUMENT TRANSFORMER DATA *** Current Transformers: C.T. Burden Test: Potential Transformer: No Load 60:1 Unverified *** PROPERLY APPLIED METER CIRCUITS *** Socket Wiring: Correct Circuit Grounding: Correct Instrument Wiring: Correct Current Circuit Wire Size: 14 Length: 50! *** REVENUE CHANGE *** *** VOLTAGE MEASUREMENTS *** wre Yan 120.BN 121.6YCN 4 Wire Vv AN Van Von 3 Wire Vv AB Vac Vv CA *** PHASE ANGLE *** WYE Vania Ven' Ventc Delta V Ac! A Vac! Venice GE Bushing 300:5; 0.3 class BO5 unverified 120.6 1985-68 46 8/27 0.11% PF: 0.11% PF: 15 Min 1 Sec Good KVAR Test Switch WYE 12.47 KV Alaska Power Authority Test Amps: 25 M. Factor: 5/6 Condition: Form: Full Scale: 4.32/8.64 0.10% Bal: 0.07% 0.10% Bals 0.07% Good c Cc 6 Neutral If Center The 1985-68 Swampy Acres Local Feeder KWH Page 2 ***COMMENTS*** This circuit had no load so could not burden or phase angle test. See file 1985-66. ***RECOMMENDATIONS*** See file 1985-66. APPENDIX DAILY WORK LOG DAILY LOG FOR ALASKA POWER AUTHORITY METERING AUDIT 12/2 Monday 12/3 Tuesday 12/4 Wednesday 12/5 Thursday 12/6 Friday 12/7 Saturday 12/8 Sunday 12/9 Monday 12/10 Tuesday 12/11 Wednesday 12/12 Thursday 12/13 Friday 12/14 Saturday 12/15 Sunday 12/16 Monday 12/17 Tuesday 12/18 Wednesday 9:30 A.M. Arrive in Wrangell, tested Wrangell Substation. Tested Petersburg Substation. Inclement weather prevented travel to Tyee. Tested Wrangell Switchyard. Tested Tyee Powerhouse. Inclement weather prevented travel to Swan Lake. Tested Bailey Substation. Tested Swan Lake. Flew To Anchorage. Flew to Valdez, test equipment did not come. Plane couldn't get in with test equipment. Flew to Anchorage for test equipment. Tested Solomon Gulch. Tested Meals Substation and Fish Hatchery. Tested Pump Stations #11 and 12. Drove to Anchorage. Flew to Kodiak. Test equipment was bumped from flight. 8:30 A.M. contacted Bill Eberhart. He asked us to trace wires while waiting for test equipment. He will have Wes Hilliman call and go with us. Flew to Terror Lake and tested Terror Lake Substation. Finished Terror Lake testing. Weather prevented return travel. 12/19 Flew to Kodiak and tested Airport Substation. Thursday 12/20 Finished Airport Substation and Swampy Acres. Flew to Friday Anchorage. 12/21 Flew to Portland. Arrived at 11:30 P.M. Saturday